external services-road & drainage

Upload: atish-kumar

Post on 04-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 External Services-Road & Drainage

    1/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 1

    E2-E3: CIVIL

    CHAPTER-4

    EXTERNAL SERVICES ROAD

    &

    DRAINAGE

  • 7/30/2019 External Services-Road & Drainage

    2/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 2

    External Services Road & Drainage

    SSaannii ttaarryy IInnssttaa ll llaatt iioonnss Basic Philosophy

    It is a non pressure system, in a building is a non pressuresystem. This means that hydraulic pressure does not exist in the

    systems against water supply which is a pressure system. In case

    of water supply there is always full bore flow where it is

    essential that sanitary pipe should not have flow more than 1/4 to

    3/4 of its bore capacity if noise in the system and excessive air

    pressure fluctuation are to be avoided. The flow in the vertical

    stack finally becomes horizontal at bottom The self cleansing

    velocity concept therefore becomes important should serve the

    primary purpose of convenience and comfort to provide a

    system of conduits which are designed to be self cleansing while

    conveying soil, waste water to the sewer without risk of nuisance

    and Hazard to health. To carry waste and soil water without any

    leakages Water tight & air tight easy access for cleaning most of

    the horizontal branches will not have a continues flow but only a

    surge flow which is sufficient for cleaning However a cleansing

    velocity of 1 Mt/sec is recommended

    Design

    All fittings are not in constant use therefore if the system isdesigned assuming all fixtures being used continuously it would

    be uneconomical, would also make velocity of flow less making

    it less than self cleansing velocity leading to deposition of solids

    The probabilities of simultaneous discharge are:

    0 in 10 probability 1.000

    1 in 10 probability 0.1534

    2 in 10 probability 0.0124

    3 in 10 probability 0.00068

    4 in 10 probability 0.00002

  • 7/30/2019 External Services-Road & Drainage

    3/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 3

    For office buildings, size could be decided on following

    considerations

    Layout should be as simple as possible Make sure that WCs discharge directly in to the stack without

    unnecessary bends

    Pipes should be approachable Pipes when not embedded should run clear on t he wall Holes made in the wall for laying of pipes should be closed to

    stop entry of mosquitoes

    Any unused drain pipe should be demolished to keep it free fromrodents

    Gradient and pipe sizes

    The self cleansing velocity of 0.75 m/sec should be aimed Sometimes people tend to increase the Dai. of pipe where

    gradient is not available.

    Wherever not possible a flatter gradient can be used but min.velocity should not be less than 0.61 m/sec

    wherever unavoidable velocity should not be greater than 2.4m/sec- If so use Cast-iron pipes

    The approximate gradients which give this velocit y when flowinghalf full are as follows

    DIA mm GRADIENT DISCHARGE

    m3/min.

    100 1 IN 57 0.18

    150 1 IN100 0.42

    200 1 IN 145 0.73

    230 1 IN 175 0.93

    250 1 IN 195 1.1

    300 1 IN 250 1.7

    DIA. GRADIENT DISCHARGE

    100 1 IN 5.6 0.59

    150 1 IN 9.7 1.32

    200 1 IN 14 2.40

    230 1 IN 17 2.98

    250 1 IN 19 3.60

    300 1 IN 24.5 5.30

  • 7/30/2019 External Services-Road & Drainage

    4/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 4

    Fixture Unit Value

    Flow in the stack depends upon simultaneous probable use ofappliances. All appliances do not have similar discharge rate andcharacteristic Hence one way to approach the problem would be

    to assign some weight age to each appliances-

    Loading Unit

    Layout of Sewer System:

    Flowing layout for sewer system may be followed:-

    Separate System Combined System Partially Separate System

    sl.no Type of fixtures load factors

    1 kitchen sink(with drain board) 3

    2 Kitchen sink, 2

    3 Wash basin 1

    4 shower 2

    5 urinal,wall lip 4

    6 urinal stall 4

    7 water closet,tank operated 4

    8 water closet,valve operated 8

    * A shower head above bath tub does not increase the f ixture value

    ** Wash basin with 32mm and 40 mm trap hav e tha same load v alue

    FIXTURE UNITS FOR DIFFERENT SANITARY APPLIANCES

    SI.NO FIXTURE TRAP SIZE FIXTURE UNIT VALUE1 30 MM OR SMALLER 1

    2 40 MM 2

    3 50 MM 3

    4 65MM 4

    5 75MM 5

    6 100MM 6

    FIXTURE UNITS VALUE FOR FIXTURES BASED ON FIXTURE DRAIN OR TRAP SI

  • 7/30/2019 External Services-Road & Drainage

    5/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 5

    Comparison of Separate & Combined System

    Separate Combined

    1. Quantity to be treated isless

    2. More suitable for areahaving more intensity of

    rainfall

    3. It sewage pumping isrequired more suitable

    4. Cheaper; storm water inopen drains

    5. Less degree of sanitation.Storm water directly

    disposed

    6. Difficult to use in narrowstreets

    7. If less intensity through-outyear Not suitable

    Treatment cost is high

    More suitable for areas havingless rainfall

    Cost of pumping is high because

    load increases

    Overall construction cost is more

    than separate.

    High degree of sanitation is

    achieved

    Suitable for narrow streets.

    More suitable.

    Merits and demerits of partially separate system

    Merits:

    1. Economical with reference to a combined system. More efficientwith reference to a separate system.

    2. House plumping is reduced (bath & Kitchen sullage taken fromsame pipe).

    3. No flushing required.Demerits:

    1. Possibility of overflow.2. In dry weather. Self-cleaning velocity may not be obtained.

    Some Important Points

    Two type of pipes are available Sand cast iron pipes -conforming to 1759-available in

    1.8 m length-

    spun cast iron pipes conforming to 3989-available in1.74 m length

    There is a tendency on the part of contractor to use Rain watergrade pipes

    There is a tendency to use more of yarn and less of lead

  • 7/30/2019 External Services-Road & Drainage

    6/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 6

    Sanitary fittings are classified as First, Commercial& off grade,A the standard companies mark commercial fittings boldly. The

    commercial quality wall have defects which are not visible but

    the later performance is poor. off grade fittings should be

    avoided at all costs

    Check list

    Pipes-check for size and strength of materials Valves- check for conformity to specification for fitting pressure Check jointing Check that all installations are approachable for maintenance Check standard weights, Dimensions Check clamps check Quality of lead Water tanks, size, fittings, whether mosquito proof-whether lid

    fixes properly

    General lines and levels of installationsSome Common Usual Defects

    In laying Less slope No provision for clean out Incorrect &improper jointing Pipes not periodically cleaned pipes & joints not tested incorrect supervision

    In designing flat slope results Numerous pipe joints result Network clash with each other No provision for clean out

    Important Pipes less than 75 mm should not be used as waste pipes For self cleansing velocity use:

    use slope not less than 1 in 48 for 100 mm pipe 1 in 36 for 75 mm pipe

    General Guidelines for execution o f works.

    1. Plinth level is to be decided with reference to compound drainage

    scheme. Compound drainage should be finalized prior to giving the

    layout of the building.

  • 7/30/2019 External Services-Road & Drainage

    7/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 7

    2. Casting of RCC slab should be depressed to the following extent,

    W.C 600mm, Bath 300mm, Kitchen 300mm, Balcony 150mm.

    As soon as the structural / Architectural drawings for the slab and

    beams are received, the problem of taking out soil and waste pipes

    should be studied thoroughly. Due to carelessness on this account, theentire purpose of giving above depressions may be defeated.

    3. Before starting the work of flooring, Floor level plan should be

    finalized showing the final levels of rooms, bathroom, Kitchen,

    balcony and W.C. etc.

    4. Bathroom flooring should have a drop of 20mm from the outer face

    of the shutter with further slope of 1 in 72 towards trap.

    5. W.C. flooring should have a cut of 25mm. From the outer face of

    the shutter with further slop of 1 in 60 towards trap.

    6. Kitchen and balcony should have a fillet of 20mm with a further

    slope of 1 in 100.

    7. Separate plans for Bathroom, W.C. Toilet and Kitchen details

    should be drawn from the utility point of view. All the traps with

    levels should be marked in the plan. Layout of G.I pipes (inlet and

    outlet) is also to be shown along with layout of trap and soil / waste

    pipes in different colors. Numbers of urinals / wash basins are not to

    be provided blindly as shown in the Architectural drawings. In case 3

    urinals /2 wash basins have been shown but the space available can

    accommodate only 2 urinals / 1 wash basin, it will be advisable to go

    for 2 urinals / 1 wash basin ins tead of making it congested.

    8. Drops for rain water pipes, soil pipes, waste pipes, vent pipes, GI

    Inlet and outlet pipes should be drawn on plan and elevation in

    different colors immediately on award of work.

    9. The niche of 35cm. X 55cm. With a dividing self, should beprovided to serve as storing space for soap & surf etc. at the proper

    location after making proper study of bathroom plan.

    10. Instead of Glass shelf a Niche of size 150 x 110 mm equal to the

    width of wash basin should be provided in the brick wall above the

    wash Basin with a slope of 1 in 20.

    11. Only one tap should be provided in the wash basin where water

    supply is being fed from one source. No tap in wash basin should be

    provided where proper water suppl y system does not exist.

    12. Dado of at least 15cm. Should be done along with the flooring ofW.C., bath and kitchen and is to be rounded at the junction.

  • 7/30/2019 External Services-Road & Drainage

    8/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 8

    13. Black chips should not be added in Terrazzo flooring of W.C. bath

    and kitchen.

    14. Height (finished) of wash basin, cooking platform and urinalsshould be 800, 775 and 630 mm. r espectively.

    15. The plastering and white washing work in W.C. and bathroom is

    generally observed to be poor in finishing. White washing should not

    be allowed till the plastering has been done properly.

    16. The width of door in W.C. and Bathroom should not exceed 700

    mm and 750 mm respectively.

    17. Terrace drainage plan should be prepared showing slope and

    levels in advance before actual execution of Ter racing.

    18. Terracing should be allowed to start only after the work of khurra

    and rain water pipes have been completed.

    19. Khurra of size 600 x 600 instead of 450 x 450 should be

    provided.

    20. RCC tanks should be provided instead of M.S. / Sintex tanks

    specially where there is no provision of vertical extension. The clear

    space available between bottom of the tank and Terracing ( finished )

    should not be less than 600 mm.

    21. Schedule of doors, windows, ventilators ( fixed & open able )

    with drawing drawn to scale showing sizes with reference to grill

    details should be finalized immediately on award of work.

    22. While fixing steel windows, sagging of lintels / chajjas andthickness of the plaster below lintel and on jams is not considered

    with the result , opening of windows becomes difficult. The thickness

    of the plastering on lintel and jams should be kept in mind while

    leaving opening in brick work for windows or while preparing the

    schedule of door and windows.

    23. Geometry of jams of the door and windows and also that of niches

    and chajjas / fins should be in true plan.

  • 7/30/2019 External Services-Road & Drainage

    9/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 9

    24. Windows provided in the stair case partly above and partly below

    the landing are not desirable.

    25. All the windows must be operated by J.E / A.E. to confirm that

    the windows are opening and closing smoothly and properly.

    26. Finished thickness of RCC shelves should not exceed 40 mm.

    Finished thickness of RCC railing should not exceed 65 mm. The

    corner of plaster on brick work, RCC should be rounded.

    27. Details of cupboard and wardrobe should be drawn from utility

    point of view. Hanger height in wardrobe should not be less than

    1000mm and depth not less than 520 mm. Inside surface should be

    neatly finished.

    28. Stair case details with reference to Tread, Riser, angle iron nosing,

    Railing with hand rail should be studied properly before asking the

    contractor to start the work blindly. Inverted and projected Angle Iron

    nosing should be provided on the steps of stair case and open

    platform. Treads should have dead level.

    29. Parapet should have a slope of 1 in 3, 40 mm. CC 1:3:6 coping

    should be provided at the top of parapet with projection of 2 0mm on

    the inner face.

    30. Drip moulding is to be p rovided in chajjas & balconies etc.

    31. Junction of outer wall and chajjas should be rounded with

    sufficient slope towards spouts to check dampness.

    32. Water supply including water connection, sewerage scheme

    including sewer connection / septic tank and internal roads along with

    compound wall should be complete along with building from the users

    point of view. Effort for solving the difficulty such as U.G. tank,Pump house, O.H. tank, pumps, water / sewer connection should be

    taken much in advance, right from framing of Preliminar y Estimate to

    the award of work, if the provision did not exist in the sanctioned

    Preliminary estimate.

    33. Data required by the EE (E) for installing the pumps should be

    supplied as early as possible to minimize the chance of getting

    unnecessary blame for the delay of installation of pumps.

  • 7/30/2019 External Services-Road & Drainage

    10/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 10

    34. Copy of specifications, D.S.R., P.E, D.E (Schedule of Quantities )

    and plinth area rates should be available at the site at least for the

    major work.

    35. Registers such as cement and steel register, Drawing (Structuraland Architectural) register, Hindrance Register, site order book,

    Technical register in proper Performa should be available at site.

    Road Work

    Review of Geometric Design Standards for Rural Roads in

    Plains S.

    No.Item As per IRC:SP:20 (Rural Roads Manual)

    1. Classification (a) Other District Roads (b) Village Roads

    2. Carriageway width 3.75m but can be reduced to 3.00m where trafficless than 100 motorised vehicle per day.

    3. Roadway width minimum ODR and VR : 7.5 m for traffic more than100 motorised vehicles per day

    : 6.0 m for t raffic less than 100

    motorised vehicles per day

    4. Widening at Curves Widening of Pavement and Roadway Upto 20m radius 0.9 m

    21 60m radius 0.6 m More than 60 m radius Nil

    5. Width of Bridges 5.5 m

    4.25 m where traffic less than 100 motorised

    vehicles per day

    6. Roadway width of culverts andcauseways

    7.5 m

  • 7/30/2019 External Services-Road & Drainage

    11/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 11

    7. Minimum radius of horizontalcurves

    As per IRCSP:20

    Plain

    TerrainRolling

    Terrain

    (i) ODR

    Ruling 90 m 60 m

    Absolute

    Minimum 60 m 45 m

    ( i i) VR

    Ruling 90 m 60 m

    Absolute

    Minimum 60 m 45 m

    8. Longitudinal gradients

    Plain

    TerrainRolling

    TerrainRuling Gradient 3.3 % 3.3 % Limiting

    Gradient 5 % 5 %

    Exceptional

    Gradient 6 % 6 %

    Compaction Requirement for Embankment & Sub-Grade

    As PER IS: 2720 (PART 8)

    Sr.No.

    Type ofWork/Material

    Relative Compaction as percentage of Max.Laboratory Dry Density

    1. Sub-Grade &Earthen

    Shoulders

    Not More than 97

    2. Embankment Not More than 953. Expansive

    Clays:

    (i) Sub-Grade &

    500 mm Portion

    below Sub-Grade(ii) Remaining

    Portion of

    Embankment

    Not allowed

    Not more than 90

    General Guide to the Selection Of Compaction Plant for Different Types of

    Soil

    Type of compaction

    plant

    Suitability of compaction plant for

    different type of soil

    Remarks

    Cohesive

    soil

    Well-graded

    granular and dry

    Cohesive Soils

    Uniformly-

    graded

    materials1 2 3 4 5

  • 7/30/2019 External Services-Road & Drainage

    12/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 12

    1 Smooth-wheeled

    roller

    Suitable Suitable Suitable only

    if the roller

    is towed by

    tractors and

    the load per

    cm width of

    the roller is

    less than 55

    kg

    2 Pneumatic-tyred

    roller

    Suitable Suitable when

    load on each

    wheel is more

    than 2 tonnes

    (tons)

    Suitable only

    if the roller

    is towed by

    tractors and

    the load on

    each wheel is

    less than11/2 tonnes

    (tons)

    3 Vibratory roller Suitable

    only

    when the

    static

    load per

    cm width

    of the

    vibratory

    roller ismore

    than 7 kg

    Suitable Suitable; but

    when the

    static load

    per cm width

    of the

    vibratory

    roller is

    more than 12

    kg, the rollershould be

    towed by

    tractors.

    4 Sheeps foot roller Suitable Unsuitable Unsuitable

    5 Power rammer* Suitable Suitable Unsuitable

    Note:- For the purpose of this table, soils are grouped as follows:-

    1. Cohesive soil includes clays with upto 20 per cent of gravel andhaving a moisture content not less than the value of the plastic limit

    minus 4;

    2. Well-graded granular and dry cohesive soils include clays containingmore than 20 per cent of gravel and/or having a moisture content lessthan the value of the plastic limit minus 4; well graded sands and

    gravels with a uniformity coefficient exceeding 10 and all shales and

    clinker-ash.

    3. Uniformly-graded material includes sands and gravels with auniformity coefficient of 10 or less and all sits and pulversied fuel

    ashes. Any soil containing 80 per cent or more of material in the

    particle size range 0.06-0.002 mm will be regarded as sit for this

    purpose.

    Density Requirements of Embankment & Sub-Grade Material When TestedAS PER IS : 2720 (PART 8)

  • 7/30/2019 External Services-Road & Drainage

    13/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 13

    S.

    No.

    Type of Work Maximum Laboratory Dry

    Unit Weight

    1. Embankments up to 3 metres height, notsubjected to extensive flooding

    Not less than 15.2

    KN/Cum.

    2. Embankment exceeding 3 metres heightor embankments of any height subject to

    long period of inundation

    Not less than 16.0

    KN/Cum.

    3. Sub-grade & earthenshoulders/verges/backfill

    Not less than 17.5

    KN/Cum.

  • 7/30/2019 External Services-Road & Drainage

    14/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 14

    Possible Defects and Causes in Hot Laid Flexible PavementsDefect in

    Pavement

    Possible cause of defect

    Insu-

    ffici-

    en tBitu-

    me n

    Mi x

    ture

    to oco a

    rs e

    Ex c

    es s

    finesin

    mi x

    Ex c

    es s

    Bitume n

    Ex c

    es s

    Mo isture

    inmi x

    Mi x

    to o

    Ho tor

    Bu rne d

    Mi x

    to o

    cold

    Poor

    Spre

    ederOp e

    ra tio n

    In a

    de q

    uateroll

    in g

    Over

    Roll

    in g

    Ro l

    ling

    whenmi x

    to oho t

    Roll

    in g

    whenmi x

    to ocold

    Ro l

    lers

    standing

    onho t

    pave

    ment

    Ro l

    lers

    to ohe a

    vy

    Pa v

    e

    ropera t

    in gto o

    fast

    Tra

    ffic

    al lowed

    be for e

    cool

    Mi x

    laid

    into o

    thicka

    co u

    rs e

    Bleeding XBrown

    Dead

    Appreance

    X X X

    Rich Fa t

    SpotsX

    Poor

    Surface

    Texture

    X X X X X X X X X

    Rough

    Uneven

    Surface

    X X X X X X X X X

    Honeycomb

    or rave l ingX X X X X X

    Uneven

    Joint sX X X X X X

    Rol le r

    MarksX X X X X X X X

    Pushing orWaves

    X X X X X X X X

    Cracking

    (Fine

    Cracks)

    X X X X X

    Cracking

    (Large

    Crack)

    X X X

    Aggrega te

    Broken byX X X X X X

  • 7/30/2019 External Services-Road & Drainage

    15/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 15

    Rol le r

    Tearing of

    Surface on

    Laying

    X X X X X X

    Surface

    Sl ipping on

    Base

    X X X X X X X

    Note: Some of these can be corrected on si te, others at mixing plant . If there is any doubt the load, samples should be takenand sent to laboratory of test ing.

  • 7/30/2019 External Services-Road & Drainage

    16/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 16

    Clause 17.12.4.1

    ANNEXURE 17.23

    THICKNESS OF SLAB FOR CEMENT CONCRETE PAVEMENTS RECOMMENDED BY

    IRC

    Average Daily Number Commercial Vehicles (Wi th laden weight over 8 tonnes)

    both directions anticipated to develop the nest 20 years

    Thickness

    of slabNot Exceeding 200 Nos .. Exceeding 200 Nos. b ut up t o 350 Nos Exceeding 350 Nos.

    150 mm

    175 mm

    200 mm

    Description of sub-

    grade

    Thickness of

    base (mm)

    Thickness of slab based on Traffic Intensity (mm)

    Very

    Heavy

    Heavy Medium

    Heavy

    Medium

    Light

    Light Very

    Light

    Very stable Normal

    Unstable

    Reinforcements

    None 80

    Upto 150

    Kg/sqm.

    230

    250

    280

    7.5

    200

    230

    250

    5.4

    180

    200

    230

    5.4

    150

    180

    200

    3.8

    130

    150

    180

    3.8

    100

    130

    150

    2.7

    Recommended Spacing of Expansion and Contraction Joints(Clause 5.3.1.2)

    Sl.

    No.

    Type of Slab Thickness

    of Slab

    Mass of

    Reinforcement

    Spacing of

    Expansion

    Joints*

    Spacing of

    Contraction

    Joint

    (1) (2) (3) (4) (5) (6)

    m kg/m2

    m m

    (i) Reinforced concrete

    slabs with expansion

    joints only

    0.25

    0.20

    0.150.10

    7.6

    5.5

    3.82.7

    45

    36

    2512.5

    -

    -

    --

    (ii) Reinforced concrete

    slabs with expansion

    and dummy

    contraction joints

    0.25

    0.20

    0.15

    0.10

    5.5

    3.8

    2.7

    2.2

    51

    45

    36

    30

    17

    14

    13

    7.5

    (iii) Unreinforced

    concrete slabs

    0.210 and

    above

    0.15

    0.10

    -

    -

    -

    36

    27

    27

    4.5

    4.5

    4.5

    Note : In case of thicker airfield pavements, somewhat higher expansion joint spacing

    may be permitted particularly when construction is mainly carried out during summer

    months. Construction joint spacing could be increased to some extent in case a smooth

    under-layer of sand and polyethylene sheeting, etc., is provided below the pavement.

    Type of cement and its early strength development characteristics also have a bearing on

    contraction joint spacing. Whereas limited experience with higher spacing indicates the

    possibility of increasing the contraction joint spacing to 6-7.5 m and expansion joint

    spacing to abou 60 m, each case may need individual consideration in view of variety of

    factors involved.

  • 7/30/2019 External Services-Road & Drainage

    17/17

    E2-E3/Civil Rev date: 01-04-11

    BSNL India For Internal Circulation Only Page: 17

    Questions:-

    1. Describe the layout of sewerage systems.2. List the common defects in sanitary installations.3. What is the self cleansing velocity for SW Sewers?4. What is the maximum velocity for SW Sewers?5. What is minimum gradient for 100 mm dia sewer?6. What is maximum gradient for 150 mm sewer/7. Compare the combined and separate sewer s ystems.8. List the common defects of sewer in design.9. What is partially separate system of sewer10.List the advantage and disadvantage of partially separate system

    of sewer