external services-road & drainage
TRANSCRIPT
-
7/30/2019 External Services-Road & Drainage
1/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 1
E2-E3: CIVIL
CHAPTER-4
EXTERNAL SERVICES ROAD
&
DRAINAGE
-
7/30/2019 External Services-Road & Drainage
2/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 2
External Services Road & Drainage
SSaannii ttaarryy IInnssttaa ll llaatt iioonnss Basic Philosophy
It is a non pressure system, in a building is a non pressuresystem. This means that hydraulic pressure does not exist in the
systems against water supply which is a pressure system. In case
of water supply there is always full bore flow where it is
essential that sanitary pipe should not have flow more than 1/4 to
3/4 of its bore capacity if noise in the system and excessive air
pressure fluctuation are to be avoided. The flow in the vertical
stack finally becomes horizontal at bottom The self cleansing
velocity concept therefore becomes important should serve the
primary purpose of convenience and comfort to provide a
system of conduits which are designed to be self cleansing while
conveying soil, waste water to the sewer without risk of nuisance
and Hazard to health. To carry waste and soil water without any
leakages Water tight & air tight easy access for cleaning most of
the horizontal branches will not have a continues flow but only a
surge flow which is sufficient for cleaning However a cleansing
velocity of 1 Mt/sec is recommended
Design
All fittings are not in constant use therefore if the system isdesigned assuming all fixtures being used continuously it would
be uneconomical, would also make velocity of flow less making
it less than self cleansing velocity leading to deposition of solids
The probabilities of simultaneous discharge are:
0 in 10 probability 1.000
1 in 10 probability 0.1534
2 in 10 probability 0.0124
3 in 10 probability 0.00068
4 in 10 probability 0.00002
-
7/30/2019 External Services-Road & Drainage
3/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 3
For office buildings, size could be decided on following
considerations
Layout should be as simple as possible Make sure that WCs discharge directly in to the stack without
unnecessary bends
Pipes should be approachable Pipes when not embedded should run clear on t he wall Holes made in the wall for laying of pipes should be closed to
stop entry of mosquitoes
Any unused drain pipe should be demolished to keep it free fromrodents
Gradient and pipe sizes
The self cleansing velocity of 0.75 m/sec should be aimed Sometimes people tend to increase the Dai. of pipe where
gradient is not available.
Wherever not possible a flatter gradient can be used but min.velocity should not be less than 0.61 m/sec
wherever unavoidable velocity should not be greater than 2.4m/sec- If so use Cast-iron pipes
The approximate gradients which give this velocit y when flowinghalf full are as follows
DIA mm GRADIENT DISCHARGE
m3/min.
100 1 IN 57 0.18
150 1 IN100 0.42
200 1 IN 145 0.73
230 1 IN 175 0.93
250 1 IN 195 1.1
300 1 IN 250 1.7
DIA. GRADIENT DISCHARGE
100 1 IN 5.6 0.59
150 1 IN 9.7 1.32
200 1 IN 14 2.40
230 1 IN 17 2.98
250 1 IN 19 3.60
300 1 IN 24.5 5.30
-
7/30/2019 External Services-Road & Drainage
4/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 4
Fixture Unit Value
Flow in the stack depends upon simultaneous probable use ofappliances. All appliances do not have similar discharge rate andcharacteristic Hence one way to approach the problem would be
to assign some weight age to each appliances-
Loading Unit
Layout of Sewer System:
Flowing layout for sewer system may be followed:-
Separate System Combined System Partially Separate System
sl.no Type of fixtures load factors
1 kitchen sink(with drain board) 3
2 Kitchen sink, 2
3 Wash basin 1
4 shower 2
5 urinal,wall lip 4
6 urinal stall 4
7 water closet,tank operated 4
8 water closet,valve operated 8
* A shower head above bath tub does not increase the f ixture value
** Wash basin with 32mm and 40 mm trap hav e tha same load v alue
FIXTURE UNITS FOR DIFFERENT SANITARY APPLIANCES
SI.NO FIXTURE TRAP SIZE FIXTURE UNIT VALUE1 30 MM OR SMALLER 1
2 40 MM 2
3 50 MM 3
4 65MM 4
5 75MM 5
6 100MM 6
FIXTURE UNITS VALUE FOR FIXTURES BASED ON FIXTURE DRAIN OR TRAP SI
-
7/30/2019 External Services-Road & Drainage
5/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 5
Comparison of Separate & Combined System
Separate Combined
1. Quantity to be treated isless
2. More suitable for areahaving more intensity of
rainfall
3. It sewage pumping isrequired more suitable
4. Cheaper; storm water inopen drains
5. Less degree of sanitation.Storm water directly
disposed
6. Difficult to use in narrowstreets
7. If less intensity through-outyear Not suitable
Treatment cost is high
More suitable for areas havingless rainfall
Cost of pumping is high because
load increases
Overall construction cost is more
than separate.
High degree of sanitation is
achieved
Suitable for narrow streets.
More suitable.
Merits and demerits of partially separate system
Merits:
1. Economical with reference to a combined system. More efficientwith reference to a separate system.
2. House plumping is reduced (bath & Kitchen sullage taken fromsame pipe).
3. No flushing required.Demerits:
1. Possibility of overflow.2. In dry weather. Self-cleaning velocity may not be obtained.
Some Important Points
Two type of pipes are available Sand cast iron pipes -conforming to 1759-available in
1.8 m length-
spun cast iron pipes conforming to 3989-available in1.74 m length
There is a tendency on the part of contractor to use Rain watergrade pipes
There is a tendency to use more of yarn and less of lead
-
7/30/2019 External Services-Road & Drainage
6/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 6
Sanitary fittings are classified as First, Commercial& off grade,A the standard companies mark commercial fittings boldly. The
commercial quality wall have defects which are not visible but
the later performance is poor. off grade fittings should be
avoided at all costs
Check list
Pipes-check for size and strength of materials Valves- check for conformity to specification for fitting pressure Check jointing Check that all installations are approachable for maintenance Check standard weights, Dimensions Check clamps check Quality of lead Water tanks, size, fittings, whether mosquito proof-whether lid
fixes properly
General lines and levels of installationsSome Common Usual Defects
In laying Less slope No provision for clean out Incorrect &improper jointing Pipes not periodically cleaned pipes & joints not tested incorrect supervision
In designing flat slope results Numerous pipe joints result Network clash with each other No provision for clean out
Important Pipes less than 75 mm should not be used as waste pipes For self cleansing velocity use:
use slope not less than 1 in 48 for 100 mm pipe 1 in 36 for 75 mm pipe
General Guidelines for execution o f works.
1. Plinth level is to be decided with reference to compound drainage
scheme. Compound drainage should be finalized prior to giving the
layout of the building.
-
7/30/2019 External Services-Road & Drainage
7/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 7
2. Casting of RCC slab should be depressed to the following extent,
W.C 600mm, Bath 300mm, Kitchen 300mm, Balcony 150mm.
As soon as the structural / Architectural drawings for the slab and
beams are received, the problem of taking out soil and waste pipes
should be studied thoroughly. Due to carelessness on this account, theentire purpose of giving above depressions may be defeated.
3. Before starting the work of flooring, Floor level plan should be
finalized showing the final levels of rooms, bathroom, Kitchen,
balcony and W.C. etc.
4. Bathroom flooring should have a drop of 20mm from the outer face
of the shutter with further slope of 1 in 72 towards trap.
5. W.C. flooring should have a cut of 25mm. From the outer face of
the shutter with further slop of 1 in 60 towards trap.
6. Kitchen and balcony should have a fillet of 20mm with a further
slope of 1 in 100.
7. Separate plans for Bathroom, W.C. Toilet and Kitchen details
should be drawn from the utility point of view. All the traps with
levels should be marked in the plan. Layout of G.I pipes (inlet and
outlet) is also to be shown along with layout of trap and soil / waste
pipes in different colors. Numbers of urinals / wash basins are not to
be provided blindly as shown in the Architectural drawings. In case 3
urinals /2 wash basins have been shown but the space available can
accommodate only 2 urinals / 1 wash basin, it will be advisable to go
for 2 urinals / 1 wash basin ins tead of making it congested.
8. Drops for rain water pipes, soil pipes, waste pipes, vent pipes, GI
Inlet and outlet pipes should be drawn on plan and elevation in
different colors immediately on award of work.
9. The niche of 35cm. X 55cm. With a dividing self, should beprovided to serve as storing space for soap & surf etc. at the proper
location after making proper study of bathroom plan.
10. Instead of Glass shelf a Niche of size 150 x 110 mm equal to the
width of wash basin should be provided in the brick wall above the
wash Basin with a slope of 1 in 20.
11. Only one tap should be provided in the wash basin where water
supply is being fed from one source. No tap in wash basin should be
provided where proper water suppl y system does not exist.
12. Dado of at least 15cm. Should be done along with the flooring ofW.C., bath and kitchen and is to be rounded at the junction.
-
7/30/2019 External Services-Road & Drainage
8/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 8
13. Black chips should not be added in Terrazzo flooring of W.C. bath
and kitchen.
14. Height (finished) of wash basin, cooking platform and urinalsshould be 800, 775 and 630 mm. r espectively.
15. The plastering and white washing work in W.C. and bathroom is
generally observed to be poor in finishing. White washing should not
be allowed till the plastering has been done properly.
16. The width of door in W.C. and Bathroom should not exceed 700
mm and 750 mm respectively.
17. Terrace drainage plan should be prepared showing slope and
levels in advance before actual execution of Ter racing.
18. Terracing should be allowed to start only after the work of khurra
and rain water pipes have been completed.
19. Khurra of size 600 x 600 instead of 450 x 450 should be
provided.
20. RCC tanks should be provided instead of M.S. / Sintex tanks
specially where there is no provision of vertical extension. The clear
space available between bottom of the tank and Terracing ( finished )
should not be less than 600 mm.
21. Schedule of doors, windows, ventilators ( fixed & open able )
with drawing drawn to scale showing sizes with reference to grill
details should be finalized immediately on award of work.
22. While fixing steel windows, sagging of lintels / chajjas andthickness of the plaster below lintel and on jams is not considered
with the result , opening of windows becomes difficult. The thickness
of the plastering on lintel and jams should be kept in mind while
leaving opening in brick work for windows or while preparing the
schedule of door and windows.
23. Geometry of jams of the door and windows and also that of niches
and chajjas / fins should be in true plan.
-
7/30/2019 External Services-Road & Drainage
9/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 9
24. Windows provided in the stair case partly above and partly below
the landing are not desirable.
25. All the windows must be operated by J.E / A.E. to confirm that
the windows are opening and closing smoothly and properly.
26. Finished thickness of RCC shelves should not exceed 40 mm.
Finished thickness of RCC railing should not exceed 65 mm. The
corner of plaster on brick work, RCC should be rounded.
27. Details of cupboard and wardrobe should be drawn from utility
point of view. Hanger height in wardrobe should not be less than
1000mm and depth not less than 520 mm. Inside surface should be
neatly finished.
28. Stair case details with reference to Tread, Riser, angle iron nosing,
Railing with hand rail should be studied properly before asking the
contractor to start the work blindly. Inverted and projected Angle Iron
nosing should be provided on the steps of stair case and open
platform. Treads should have dead level.
29. Parapet should have a slope of 1 in 3, 40 mm. CC 1:3:6 coping
should be provided at the top of parapet with projection of 2 0mm on
the inner face.
30. Drip moulding is to be p rovided in chajjas & balconies etc.
31. Junction of outer wall and chajjas should be rounded with
sufficient slope towards spouts to check dampness.
32. Water supply including water connection, sewerage scheme
including sewer connection / septic tank and internal roads along with
compound wall should be complete along with building from the users
point of view. Effort for solving the difficulty such as U.G. tank,Pump house, O.H. tank, pumps, water / sewer connection should be
taken much in advance, right from framing of Preliminar y Estimate to
the award of work, if the provision did not exist in the sanctioned
Preliminary estimate.
33. Data required by the EE (E) for installing the pumps should be
supplied as early as possible to minimize the chance of getting
unnecessary blame for the delay of installation of pumps.
-
7/30/2019 External Services-Road & Drainage
10/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 10
34. Copy of specifications, D.S.R., P.E, D.E (Schedule of Quantities )
and plinth area rates should be available at the site at least for the
major work.
35. Registers such as cement and steel register, Drawing (Structuraland Architectural) register, Hindrance Register, site order book,
Technical register in proper Performa should be available at site.
Road Work
Review of Geometric Design Standards for Rural Roads in
Plains S.
No.Item As per IRC:SP:20 (Rural Roads Manual)
1. Classification (a) Other District Roads (b) Village Roads
2. Carriageway width 3.75m but can be reduced to 3.00m where trafficless than 100 motorised vehicle per day.
3. Roadway width minimum ODR and VR : 7.5 m for traffic more than100 motorised vehicles per day
: 6.0 m for t raffic less than 100
motorised vehicles per day
4. Widening at Curves Widening of Pavement and Roadway Upto 20m radius 0.9 m
21 60m radius 0.6 m More than 60 m radius Nil
5. Width of Bridges 5.5 m
4.25 m where traffic less than 100 motorised
vehicles per day
6. Roadway width of culverts andcauseways
7.5 m
-
7/30/2019 External Services-Road & Drainage
11/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 11
7. Minimum radius of horizontalcurves
As per IRCSP:20
Plain
TerrainRolling
Terrain
(i) ODR
Ruling 90 m 60 m
Absolute
Minimum 60 m 45 m
( i i) VR
Ruling 90 m 60 m
Absolute
Minimum 60 m 45 m
8. Longitudinal gradients
Plain
TerrainRolling
TerrainRuling Gradient 3.3 % 3.3 % Limiting
Gradient 5 % 5 %
Exceptional
Gradient 6 % 6 %
Compaction Requirement for Embankment & Sub-Grade
As PER IS: 2720 (PART 8)
Sr.No.
Type ofWork/Material
Relative Compaction as percentage of Max.Laboratory Dry Density
1. Sub-Grade &Earthen
Shoulders
Not More than 97
2. Embankment Not More than 953. Expansive
Clays:
(i) Sub-Grade &
500 mm Portion
below Sub-Grade(ii) Remaining
Portion of
Embankment
Not allowed
Not more than 90
General Guide to the Selection Of Compaction Plant for Different Types of
Soil
Type of compaction
plant
Suitability of compaction plant for
different type of soil
Remarks
Cohesive
soil
Well-graded
granular and dry
Cohesive Soils
Uniformly-
graded
materials1 2 3 4 5
-
7/30/2019 External Services-Road & Drainage
12/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 12
1 Smooth-wheeled
roller
Suitable Suitable Suitable only
if the roller
is towed by
tractors and
the load per
cm width of
the roller is
less than 55
kg
2 Pneumatic-tyred
roller
Suitable Suitable when
load on each
wheel is more
than 2 tonnes
(tons)
Suitable only
if the roller
is towed by
tractors and
the load on
each wheel is
less than11/2 tonnes
(tons)
3 Vibratory roller Suitable
only
when the
static
load per
cm width
of the
vibratory
roller ismore
than 7 kg
Suitable Suitable; but
when the
static load
per cm width
of the
vibratory
roller is
more than 12
kg, the rollershould be
towed by
tractors.
4 Sheeps foot roller Suitable Unsuitable Unsuitable
5 Power rammer* Suitable Suitable Unsuitable
Note:- For the purpose of this table, soils are grouped as follows:-
1. Cohesive soil includes clays with upto 20 per cent of gravel andhaving a moisture content not less than the value of the plastic limit
minus 4;
2. Well-graded granular and dry cohesive soils include clays containingmore than 20 per cent of gravel and/or having a moisture content lessthan the value of the plastic limit minus 4; well graded sands and
gravels with a uniformity coefficient exceeding 10 and all shales and
clinker-ash.
3. Uniformly-graded material includes sands and gravels with auniformity coefficient of 10 or less and all sits and pulversied fuel
ashes. Any soil containing 80 per cent or more of material in the
particle size range 0.06-0.002 mm will be regarded as sit for this
purpose.
Density Requirements of Embankment & Sub-Grade Material When TestedAS PER IS : 2720 (PART 8)
-
7/30/2019 External Services-Road & Drainage
13/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 13
S.
No.
Type of Work Maximum Laboratory Dry
Unit Weight
1. Embankments up to 3 metres height, notsubjected to extensive flooding
Not less than 15.2
KN/Cum.
2. Embankment exceeding 3 metres heightor embankments of any height subject to
long period of inundation
Not less than 16.0
KN/Cum.
3. Sub-grade & earthenshoulders/verges/backfill
Not less than 17.5
KN/Cum.
-
7/30/2019 External Services-Road & Drainage
14/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 14
Possible Defects and Causes in Hot Laid Flexible PavementsDefect in
Pavement
Possible cause of defect
Insu-
ffici-
en tBitu-
me n
Mi x
ture
to oco a
rs e
Ex c
es s
finesin
mi x
Ex c
es s
Bitume n
Ex c
es s
Mo isture
inmi x
Mi x
to o
Ho tor
Bu rne d
Mi x
to o
cold
Poor
Spre
ederOp e
ra tio n
In a
de q
uateroll
in g
Over
Roll
in g
Ro l
ling
whenmi x
to oho t
Roll
in g
whenmi x
to ocold
Ro l
lers
standing
onho t
pave
ment
Ro l
lers
to ohe a
vy
Pa v
e
ropera t
in gto o
fast
Tra
ffic
al lowed
be for e
cool
Mi x
laid
into o
thicka
co u
rs e
Bleeding XBrown
Dead
Appreance
X X X
Rich Fa t
SpotsX
Poor
Surface
Texture
X X X X X X X X X
Rough
Uneven
Surface
X X X X X X X X X
Honeycomb
or rave l ingX X X X X X
Uneven
Joint sX X X X X X
Rol le r
MarksX X X X X X X X
Pushing orWaves
X X X X X X X X
Cracking
(Fine
Cracks)
X X X X X
Cracking
(Large
Crack)
X X X
Aggrega te
Broken byX X X X X X
-
7/30/2019 External Services-Road & Drainage
15/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 15
Rol le r
Tearing of
Surface on
Laying
X X X X X X
Surface
Sl ipping on
Base
X X X X X X X
Note: Some of these can be corrected on si te, others at mixing plant . If there is any doubt the load, samples should be takenand sent to laboratory of test ing.
-
7/30/2019 External Services-Road & Drainage
16/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 16
Clause 17.12.4.1
ANNEXURE 17.23
THICKNESS OF SLAB FOR CEMENT CONCRETE PAVEMENTS RECOMMENDED BY
IRC
Average Daily Number Commercial Vehicles (Wi th laden weight over 8 tonnes)
both directions anticipated to develop the nest 20 years
Thickness
of slabNot Exceeding 200 Nos .. Exceeding 200 Nos. b ut up t o 350 Nos Exceeding 350 Nos.
150 mm
175 mm
200 mm
Description of sub-
grade
Thickness of
base (mm)
Thickness of slab based on Traffic Intensity (mm)
Very
Heavy
Heavy Medium
Heavy
Medium
Light
Light Very
Light
Very stable Normal
Unstable
Reinforcements
None 80
Upto 150
Kg/sqm.
230
250
280
7.5
200
230
250
5.4
180
200
230
5.4
150
180
200
3.8
130
150
180
3.8
100
130
150
2.7
Recommended Spacing of Expansion and Contraction Joints(Clause 5.3.1.2)
Sl.
No.
Type of Slab Thickness
of Slab
Mass of
Reinforcement
Spacing of
Expansion
Joints*
Spacing of
Contraction
Joint
(1) (2) (3) (4) (5) (6)
m kg/m2
m m
(i) Reinforced concrete
slabs with expansion
joints only
0.25
0.20
0.150.10
7.6
5.5
3.82.7
45
36
2512.5
-
-
--
(ii) Reinforced concrete
slabs with expansion
and dummy
contraction joints
0.25
0.20
0.15
0.10
5.5
3.8
2.7
2.2
51
45
36
30
17
14
13
7.5
(iii) Unreinforced
concrete slabs
0.210 and
above
0.15
0.10
-
-
-
36
27
27
4.5
4.5
4.5
Note : In case of thicker airfield pavements, somewhat higher expansion joint spacing
may be permitted particularly when construction is mainly carried out during summer
months. Construction joint spacing could be increased to some extent in case a smooth
under-layer of sand and polyethylene sheeting, etc., is provided below the pavement.
Type of cement and its early strength development characteristics also have a bearing on
contraction joint spacing. Whereas limited experience with higher spacing indicates the
possibility of increasing the contraction joint spacing to 6-7.5 m and expansion joint
spacing to abou 60 m, each case may need individual consideration in view of variety of
factors involved.
-
7/30/2019 External Services-Road & Drainage
17/17
E2-E3/Civil Rev date: 01-04-11
BSNL India For Internal Circulation Only Page: 17
Questions:-
1. Describe the layout of sewerage systems.2. List the common defects in sanitary installations.3. What is the self cleansing velocity for SW Sewers?4. What is the maximum velocity for SW Sewers?5. What is minimum gradient for 100 mm dia sewer?6. What is maximum gradient for 150 mm sewer/7. Compare the combined and separate sewer s ystems.8. List the common defects of sewer in design.9. What is partially separate system of sewer10.List the advantage and disadvantage of partially separate system
of sewer