extra(latest)

Upload: ankit-rajput

Post on 13-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Extra(Latest)

    1/11

    Page | i

    Report on Vocational Training

    at

    National Thermal Power Corporation, Dadri

    Bachelor of Technology

    Mechanical Engineering

    By

    UJJAWAL PRATAP SINGH

    2012UME1368

    Under the supervision ofMr. Ashish Kumar Purwar

    Deputy Manager (AHP), NTPC Dadri

    Mr. Surya Pratap Singh

    Senior Engineer, NTPC Dadri

    Submitted to

    Dr. G.D. AgarwalDr. Gopal Agrawal

    Dr. Rakesh Jain

    DEPARTMENT OF MECHANICAL ENGINEERING MALAVIYA NATIONAL INSTITUTE OF TECHNOLOGY,

    JAIPUR

  • 7/26/2019 Extra(Latest)

    2/11

    Page | ii

  • 7/26/2019 Extra(Latest)

    3/11

    Page | iii

    ACKNOWLEDGEMENT

    An engineer with only theoretical knowledge is not a complete engineer.

    Practical knowledge is very important to develop and apply engineering

    skills.

    It gives me a great pleasure to have an opportunity to acknowledge and to

    express gratitude to those who were associated with me during my training at

    NTPC.

    I am very great-full to Mr. S.L. Soni for providing me with an opportunity to

    undergo training under his able guidance. Furthermore, special thanks to Mr.

    Atul Kumar Purti for his help and support at NTPC Dadri. Last, but not the

    least, I would also like to acknowledge the immense pleasure, brought about

    by my friends as they pursued their training along with me. We shared some

    unforgettable moments together. I express my sincere thanks and gratitude to

    NTPC authorities for allowing me to undergo the training in this prestigious

    organization. I will always remain indebted to them for their constant interest

    and excellent guidance in my training work, moreover for providing me with

    an opportunity to work and gain experience.

    THANK YOU

  • 7/26/2019 Extra(Latest)

    4/11

    Page | iv

    ABSTRACTThis Project Report has been prepared in fulfilment of Industrial Training to be

    carried out in third year of our four year B.TECH course. For preparing the Project

    Report, we have visited NTPC Dadri during the suggested duration for the period of

    45 days, to avail the necessary information. The blend of learning and knowledge

    acquired during our practical studies at the company is presented in this Project

    Report.

    The rationale behind visiting the power plant and preparing the Project Report is to

    study the mechanical overview, various cycles and processes (viz. Steam Generation,

    coal handling, turbine functioning) of power generation in thermal power plant.

    We have carried out this training under well experienced and highly qualified

    engineers of various departments at NTPC Dadri. We have tried our best to cover allthe aspects of the power plant and their brief detailing in this project report.

    The main aim to carry out this training is to familiarize ourselves with the real

    industrial scenario, so that we can relate with our engineering studies.

  • 7/26/2019 Extra(Latest)

    5/11

    Page | v

    CONTENTS

    Certificate.ii

    Acknowledgement...iii

    Abstract...iv

    Contents...v

    List of Figures..viii

    List of Tables..x

    Abbreviationsxi

    CHAPTER 1 INTRODUCTION.1

    1.1 About NTPC..1

    1.2 Strategies of NTPC...2

    1.3 Vision.3

    1.4 Mission.3

    1.5 Core Values3

    1.6 Installed Capacity.31.7 Working Principle.6

    1.8 About NTPC Dadri...7

    1.8.1 Installed Capacity...7

    1.8.2 Location.8

    1.8.3 Coal Source....8

    1.8.4 Water Source.8

    CHAPTER 2 COAL CYCLE..9

    2.1 Coal Supplied at NTPC Dadri..9

    2.2 Different Components of Coal Cycle.9

    2.2.1 Wagon Tippler.10

    2.2.2 Track Hopper10

    2.2.3 Paddle Feeder.11

  • 7/26/2019 Extra(Latest)

    6/11

    Page | vi

    2.2.4 Conveyer Belts..11

    2.2.5 Safety Switches in Conveyers.11

    2.2.6 Crusher House..12

    2.2.7 Stacker cum Reclaimer...12

    2.2.8 Coal Yard...13

    2.2.9 Coal Bunker.13

    2.2.10 Coal Feeder...14

    2.2.11 Coal Mill...14

    2.2.12 Furnace..15

    CHAPTER 3 WATER CYCLE17

    3.1 De-mineralized Water/Steam Cycle..17

    3.2 Condensate Cycle...17

    3.2.1 Hot Well...183.2.2 Condensate Extraction Pump...18

    3.2.3 Feed Water Heater...18

    3.2.4 Deaerator...19

    3.2.5 Feed Storage Tank.19

    3.3 Feed Water Cycle...20

    3.3.1 Boiler Feed Pump..20

    3.3.2 Feed Regulating Station...22

    3.3.3 Economiser.223.3.4 Boiler Drum...23

    3.3.5 Boiler..24

    3.4 Steam Cycle.25

    3.4.1 Superheater..25

    3.4.2 Reheater....26

    3.4.3 Steam Lines26

    3.4.4 Condenser.26

    3.5 Cooling Water Cycle...283.5.1 Raw Water Reservoir......28

    3.5.2 De-Mineralizing Plant...28

    3.5.3 Forebay...29

    3.5.4 Cooling Water Pump House....29

    3.5.5 Cooling Tower....29

  • 7/26/2019 Extra(Latest)

    7/11

    Page | vii

    CHAPTER 4 TURBINE AND GENERATOR..31

    4.1 Turbine....31

    4.1.1 High Pressure Turbine..31

    4.1.2 Intermediate Pressure Turbine..32

    4.1.3 Low Pressure Turbine...32

    4.2 Electricity Cycle..33

    4.3 Generator.....34

    4.4 Transformer....35

    4.5 Switchyard...36

    4.5.1 Circuit Breaker..37

    CHAPTER 5 AIR AND FLUE GAS CYCLE.38

    5.1 Air Cycles..38

    5.2 Fans..395.2.1 Primary Air Fan...39

    5.2.2 Forced Draft Fan.39

    5.2.3 Induced Draft Fan..40

    5.3 Flue Gas Cycles..41

    5.3.1 Air Preheater.41

    5.3.2 Electrostatic Precipitator..42

    5.3.3 Chimney...43

    5.4 Ash Handling Plant....45

    Conclusion47

    References48

  • 7/26/2019 Extra(Latest)

    8/11

    Page | viii

    LIST OF FIGURES

    S.No Figure No. Title Page No.1 Fig 1.1 PLF vs Year graph 2

    2 Fig 1.2 Strategies of NTPC 2

    3 Fig 1.3 Rankine Cycle (with reheat) 6

    4 Fig 2.1 Coal Cycle 10

    5 Fig 2.2 Wagon Tippler 11

    6 Fig 2.3 Track Hoppers 11

    7 Fig 2.4 Coal Sizes 12

    8 Fig 2.5 Stacker cum Reclaimer 139 Fig 2.6 Coal Bunkers (in Yellow) 14

    10 Fig 2.7 Coal Mills (Pulveriser) 15

    11 Fig 2.8 Rollers of Coal Mill 15

    12 Fig 3.1 Water Cycle 17

    13 Fig 3.2 Low Pressure Heater 19

    14 Fig 3.3 High Pressure Heater 19

    15 Fig 3.4 Deaerator (upper cylinder) and Feed Storage

    Tank (lower cylinder)

    20

    16 Fig 3.5 Boiler Feed Pump 22

    17 Fig 3.6 Boiler Drum 23

    18 Fig 3.7 Condenser 27

    19 Fig 3.8 Natural Draft Cooling Towers 30

    20 Fig 3.9 Cooling Tower from inside 30

    21 Fig 4.1 High Pressure Turbine 31

    22 Fig 4.2 Intermediate Pressure Turbine 3223 Fig 4.3 Low Pressure Turbine 32

    24 Fig 4.4 Generator (Red) and Turbine (Green) 34

    25 Fig 4.5 Station Transformer 36

    26 Fig 4.6 Switch Yard 36

    27 Fig 5.1 Flue Gas Cycle 38

  • 7/26/2019 Extra(Latest)

    9/11

    Page | ix

    28 Fig 5.2 Forced Draft Fan (bottom left) and Primary Air

    Fan (bottom right)

    40

    29 Fig 5.3 Induced Draft Fan 41

    30 Fig 5.4 Air Preheater 42

    31 Fig 5.5 Electrostatic Precipitator 43

    32 Fig 5.6 Chimney 4433 Fig 5.7 Hydrobins 46

    34 Fig 5.8 Dry Ash Silos 46

  • 7/26/2019 Extra(Latest)

    10/11

    Page | x

    LIST OF TABLESS.No Table No. Title Page No.

    1 Table 1.1 Installed Capacity of NTPC 32 Table 1.2 Coal Based Plants 4

    3 Table 1.3 Gas Based Plants 4

    4 Table 1.4 Projects Under Implementation 5

    5 Table 1.5 Power Plants with Joint Ventures 5

    6 Table 1.6 NTPC Dadri Coal Based 7

    7 Table 1.7 NTPC Dadri Gas Based 8

    8 Table 2.1 Crusher House 12

    9 Table 2.2 Coal Mill 1510 Table 2.3 Furnace specifications 16

    11 Table 3.1 Condensate Extraction Pump specifications 18

    12 Table 3.2 Boiler Feed Booster Pump specifications 21

    13 Table 3.3 Boiler Feed Pump specifications 21

    14 Table 3.4 Economiser Specifications 22

    15 Table 3.5 Boiler Drum specifications 23

    16 Table 3.6 Boiler Specifications 24

    17 Table 3.7 Superheater specifications 25

    18 Table 3.8 Reheater Specifications 26

    19 Table 3.9 Condenser Specifications 27

    20 Table 3.10 Cooling Tower Specifications 30

    21 Table 4.1 Turbine Specifications 33

    22 Table 4.2 Stage I (210MW) Generator specifications 35

    23 Table 5.1 PA Fan specifications 39

    24 Table 5.2 FD Fan specifications 3925 Table 5.3 ID Fan specifications 40

    26 Table 5.4 Electrostatic Precipitator specifications 42

    27 Table 5.5 Chimney Specifications 44

  • 7/26/2019 Extra(Latest)

    11/11

    Page | xi

    ABBREVIATIONSAHP ASH HANDLING PLANT

    APH AIR PRE HEATER

    BFP BOILER FEED PUMP

    CEP CONDENSATE EXTRACTION PUMP

    CHP COAL HANDLING PLANT

    CRH COLD REHEAT LINE

    DM DEMINERLISATION PLANT

    FD FAN FORCED DRAUGHT FAN

    HP TURBINE HIGH PRESSURE TURBINE

    HRH HOT REHEAT LINE

    ID FAN INDUCED DRAUHT FAN

    IP TURBINE INTERMEDIATE PRESSURE TURBINE

    LP TURBINE LOW PRESSURE TURBINE

    NRV NON RETURN VALVE

    PA FAN PRIMARY AIR FAN

    RH REHEATER

    SH SUPERHEATERSAC STRONG ACID CATION

    SBA STRONG BASE ANION

    TPH TONN PER HOUR

    T&G TURBINE AND GENRATOR

    WAC WEAK ACID CATION

    WBA WEAK BASE ANION