NORWALK HIGH SCHOOL ATHLETIC FIELDS AND POSSIBLE STADIUM PROJECT (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING) Status: DSA Plan Check Review – Pending DSA Approval DSA No.: 03-117769 Anticipated Construction Start Date: Fall 2020 Department of Toxic Substances Control (DTSC) and California Environmental Quality Act (CEQA) study in process. On Friday, January 19, 2018, the Facilities performed a site walk at Norwalk HS with the environmental consultant Ninyo & Moore to mark-up the drilling locations for additional sampling required by DTSC. On Wednesday, January 24, 2018, Ninyo & Moore returned to the Norwalk HS to drill and obtain additional samplings. The samplings obtained are currently undergoing review by Ninyo & Moore. On Tuesday, January 23, 2018, the Draft Environmental Impact Report (EIR) has been published for 45-day public review from January 23, 2018 to March 8, 2018, as part of the CEQA analysis process. The scoping meeting is scheduled for March 1, 2018, 6:00 – 7:30pm at Norwalk High School Library, to receive public comments on the Draft EIR. F A C I L I T I E S P L A N N I N G & C O N S T R U C T I O N “Planning & Building Schools of Excellence”

Upload: others

Post on 30-Jan-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

NORWALK HIGH SCHOOL ATHLETIC FIELDS AND POSSIBLE STADIUM PROJECT (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING)

Status: DSA Plan Check Review – Pending DSA Approval DSA No.: 03-117769 Anticipated Construction Start Date: Fall 2020

Department of Toxic Substances Control (DTSC) and California Environmental Quality Act (CEQA) study in process. On Friday, January 19, 2018, the Facilities performed a site walk at Norwalk HS with the environmental consultant Ninyo & Moore to mark-up the drilling locations for additional sampling required by DTSC. On Wednesday, January 24, 2018, Ninyo & Moore returned to the Norwalk HS to drill and obtain additional samplings. The samplings obtained are currently undergoing review by Ninyo & Moore. On Tuesday, January 23, 2018, the Draft Environmental Impact Report (EIR) has been published for 45-day public review from January 23, 2018 to March 8, 2018, as part of the CEQA analysis process. The scoping meeting is scheduled for March 1, 2018, 6:00 – 7:30pm at Norwalk High School Library, to receive public comments on the Draft EIR.

F A C I L I T I E S P L A N N I N G & C O N S T R U C T I O N

“Planning & Building Schools of Excellence”

Page 2: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

GLENN HIGH SCHOOL ATHLETIC FIELDS AND STADIUM PROJECT

(ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BERNARDS PROGRAM MANAGEMENT: CUMMING, GENERAL CONTRACTOR: USS CAL BUILDERS, INC.)

Status: Construction Phase

DSA No.: 03-117757

Bid No.: 201718-3 (Formal)

Construction Start Date: January 2018

Construction trailers have been set. Mobilization, SWPPPs and abatement activities were completed. Demolition is approximately 80% complete, including clear and grub of top soil, removal of chain link fencing and footings, small structures, and asphalt paving. Removal of trees located on South end is scheduled in February, which will complete demolition activities. Excavation of buildings foundations will start early part of February.

.

DEMOLITION AND GRADING

OVER EXCAVATION FOR FIELDHOUSE BLDG.

OVER EXCAVATION FOR BASEBALL DUGOUT/STORAGE BLDG.

Page 3: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

LA MIRADA HIGH SCHOOL GYM EXPANSION & LOCKER ROOM

MODERNIZATION PROJECT (ARCHITECT: DLR GROUP, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING) Status: DSA Review

Submitted seismic analysis to DSA on January 29, 2018. Pending approval of the seismic analysis of the gymnasium by DSA.

LA MIRADA HIGH SCHOOL INTERIM PE LOCKER BUILDINGS PROJECT (ARCHITECT: WESTGROUP DESIGN, PROGRAM MANAGEMENT: CUMMING)

Status: DSA Approved

DSA No.: 03-118461

Anticipated Construction Start Date: Summer 2018

LA MIRADA HIGH SCHOOL CAMPUS-WIDE RENOVATION OF HARD/SOFT SCAPE PROJECT

(ARCHITECT: NAC ARCHTIECTURE, PROGRAM MANAGEMENT: CUMMING) Status: Schematic Design

[Site Plan of Interim PE Bldgs.]

[Floor Plan of Girls’ Locker Bldg.]

[Floor Plan of Boys’ Locker Bldg.]

Page 4: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

BENTON MIDDLE SCHOOL LANDSCAPE RENOVATION & ACCESSORY BUILDING

PROJECT (ARCHITECT: DLR GROUP, LANDSCAPE ARCHITECT: LYNN CAPOUYA INC, CONSTRUCTION MANAGER AND PROGRAM MANAGEMENT: CUMMING)

SITE OBSERVATION PHOTOS BY CUMMING CORPORATION CM AT BENTON MS

Status: Construction Phase

DSA No.: 03-117773

Bid No.: 201718-1 (Formal)

Construction Start Date: January 2018

Contractor is on site; construction is ongoing for Phase 1. Contractor is installing the Irrigation lines and storm drain lines as well as grading the track. Curbs for the track and concrete placement at the ADA parking area to follow.

Page 5: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

CORVALLIS MIDDLE SCHOOL LANDSCAPE RENOVATION & ACCESSORY

STRUCTURES PROJECT (ARCHITECT: DLR GROUP, LANDSCAPE ARCHITECT: LYNN CAPOUYA INC, CONSTRUCTION MANAGER

AND PROGRAM MANAGEMENT: CUMMING)

SITE OBSERVATION PHOTOS BY CUMMING CORPORATION CM AT CORVALLIS MS

MORRISON ES AND LOS ALISOS MS HVAC/MODERNIZATION OF ADMIN. & MPR

BUILDINGS PROJECTS (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BERNARDS, PROGRAM MANAGEMENT: CUMMING)

Status: DSA Approved – Bidding Phase

DSA No.: 03-117756(Morrison ES) & 03-117755 (Los Alisos MS)

Anticipated Construction Start Date: Summer 2018

Status: Construction Phase

DSA No.: 03-117774

Bid No.: 201718-2 (Formal)

Construction Start Date: January 2018

Contractor is on site; construction is ongoing for Phase 1. Contractor is installing the Irrigation lines and storm drain lines. Catch basins and the curb for the track to follow. Phase 1 is currently on track.

Page 6: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

Projects were advertised for bidding on Tuesday, February 6, 2018 and bids will be opened on March 22nd. Construction is anticipated to begin on June 7th, 2018.

GARDENHILL ES AND HUTCHINSON MS HVAC/MODERNIZATION OF ADMIN. & MPR BUILDINGS PROJECTS (ARCHITECT: DLR GROUP, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING)

Status: DSA Approved – Bidding Phase

DSA No.: 03-118109 (Gardenhill ES) & 03-118110 (Hutchinson MS)

Anticipated Construction Start Date: Summer 2018

Projects were advertised for bidding Tuesday, February 6, 2018 and bids will be opened on March 20th. Construction is anticipated to begin on June 7th, 2018.

HUTCHINSON MS GARDENHILL ES

Page 7: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

CHAVEZ ELEMENTARY SCHOOL PLAYGROUND PROJECT (ARCHITECT: TBD)

Status: Planning Last week Facilities Staff conducted site visits with various Architect Firms to obtain cost for the architectural services needed for the new playground. We anticipate taking an agreement to the Monday, February 26, 2018 Board Meeting to begin the design phase.

GLAZIER ELEMENTARY SCHOOL KINDERGARTEN PLAYGROUND REPLACEMENT PROJECT (ARCHITECT: TBD)

Status: Planning Last week Facilities Staff conducted site visits with various Architect Firms to obtain cost for the architectural services needed for the new playground. We anticipate taking an agreement to the Monday, February 26, 2018 Board Meeting to begin the design phase.

JOHN GLENN HIGH SCHOOL ELECTRONIC MARQUEE PROJECT

(ARCHITECT: DONALD KROTEE PARTNERSHIP)

Status: Construction DSA No.: 03-118126 The electronic marquee project is complete. Project closeout with the Division of the State Architect is in progress.

INSTALLATION OF THE NEW ELECTRONIC MARQUEE

Page 8: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

NORWALK ADULT SCHOOL ELECTRONIC MARQUEE PROJECT (ARCHITECT: DONALD KROTEE PARTNERSHIP) Status: Bidding

DSA No.: 03-117490

Anticipated Construction Start Date: February 2018 Staff has requested a purchase order to build and install the marquee. Staff has forwarded inspection services agreements to proposed firms. The project inspector and geotechnical/material testing and special inspection agreements are scheduled for Board of Education approval on February 26, 2018.

HUTCHINSON MIDDLE SCHOOL ELECTRONIC MARQUEE PROJECT (ARCHITECT: DONALD KROTEE PARTNERSHIP)

Status: DSA Approved DSA No.: 03-118556 Anticipated Construction Start Date: March 2018

DSA approved the project for construction. The bidding phase will commence after receipt of the approved plans and specifications.

NEW ELECTRONIC MARQUEE

Page 9: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

NORWALK HIGH SCHOOL ELECTRONIC MARQUEE PROJECT

(ARCHITECT: DONALD KROTEE PARTNERSHIP)

Status: DSA Approved DSA No.: 03-118554 Anticipated Construction Start Date: March 2018

DSA approved the project for construction. The bidding phase will commence after receipt of the approved plans and specifications.

ESCALONA ELEMENTARY SCHOOL PORTABLE CLASSROOM PROJECT (ARCHITECT: WESTGROUP DESIGNS)

Status: Design Development/Construction Documents

Converse Consultants identified/staked the boring locations at Escalona ES for soil sampling.

Page 10: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

MOFFITT ELEMENTARY SCHOOL HEAD START PORTABLE CLASSROOM PROJECT

(ARCHITECT: WESTGROUP DESIGNS)

LOS ALISOS MIDDLE SCHOOL PORTABLE REPLACEMENT PROJECT (ARCHITECT: WESTGROUP DESIGNS) Status: DSA Approved

DSA No.: 03-117927

The project was approved by the Division of the State Architect on January 29th. Upon receipt of the approved plans and specifications, staff will request a bid schedule from the Purchasing department. Staff is also scheduling a project review meeting with the site administrator.

HUTCHINSON MIDDLE SCHOOL PORTABLE LOCKER ROOM & CLASSROOM PROJECT (ARCHITECT: WESTGROUP DESIGNS)

Status: Design Development/Construction Documents

Converse Consultants sampling the soil at Moffitt ES for the Geotechnical Report. (Pictured)

Status: Design Development/Construction Documents Converse Consultant sampling the soil at Hutchinson MS for the geotechnical report.

Page 11: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

NORWALK HIGH SCHOOL PORTABLE WEIGHT ROOM & FIRE WATER SERVICE

LOOP PROJECT (ARCHITECT: RACHLIN PARTNERS)

Status: Design Development/Construction Documents

NORWALK HIGH SCHOOL CTE CULINARY ARTS CLASSROOM CONVERSION PROJECT

(ARCHITECT: RACHLIN PARTNERS) Status: DSA Plan Check Review DSA No.: 03-118429

On Monday, January 29, 2018, the Facilities performed the roof coring with the roofing contractor to examine the existing condition of the roof at Bldg. K.

MONDAY, 1/29/18 CORING OF EXISTING ROOFING AT NORWALK HS

On Tuesday, January 30, 2018, the Facilities performed the examination of the existing gas pipe conditions with the plumber, Abe’s Plumbing.

TUESDAY, 1/30/18 EXISTING GAS PIPE EXAMINATION AT NORWALK HS

Page 12: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

EXCELSIOR HIGH SCHOOL AUDITORIUM CNRA GRANT PROJECT (ARCHITECT: RUHNAU CLARKE)

Status: Scope Development Facilities staff along with Business Services, Technology Services and Maintenance & Operations met with the architect (Ruhnau Clarke) and the Theater Consultant (The Ruzika Group) on Monday, February 5th, to discuss the project scope. The team also toured the interior and exterior of the auditorium with the architect and Theater Consultant. The architect is scheduled to forward a potential/proposed scope for the District’s review within two weeks.

MONDAY, 2/5/18

EXCELSIOR AUDITORIUM SITE VISIT WITH RUHNAU CLARKE ARCHITECTS AND THE RUZIKA GROUP

Page 13: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

KITCHEN REMODEL PROJECTS LOCATED AT DISTRICT OFFICE, JOHN GLENN HS,

LA MIRADA HS, AND NORWALK HS (ARCHITECT: WEBB, CONSTRUCTION MANAGER: BERNARDS)

Status: Design

During the Monday, January 22, 2018 Board Meeting, the Board approved the agreements for WEBB to design the kitchens and Bernards for construction management services. Currently the District, Bernard, and WEBB are coordinating the design development. Considering the Monday, May 29, 2018 Board meeting, WEBB informed that they require 6 weeks for procurement time and 30 days for installation.

Page 14: F A C I L I T I E S P L A N N I N G & C O N S T R U ... - Edl€¦ · 201718-2 (Formal) Construction Start Date: January 2018 . Contractor is on site; construction is ongoing for

RAMONA HEAD START SHADE STRUCTURES PROJECT (ARCHITECT: DOUGHERTY)

Status: Pre-Bidding Anticipated Construction Start Date: Summer 2018 The project was approved by the Division of the State Architect (DSA) in 2017. Facilities Staff is currently working with Head Start to order the shade structures from Dave Bang Associates. Once the structures are fabricated they should arrive within 6-8 weeks. Project is currently on track for Summer 2018 Construction.

NORWALK ADULT SCHOOL RESTROOM REMODEL (ARCHITECT: TBD)

Status: Planning

A request was received from Norwalk Adult School to remodel a restroom in the 300 wing. On Tuesday, February 6, 2018, Facilities Staff met with Dougherty Architects for a site visit. Facilities Staff is currently working on a total construction and project budget.