NORWALK HIGH SCHOOL ATHLETIC FIELDS AND POSSIBLE STADIUM PROJECT (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING)
Status: DSA Plan Check Review – Pending DSA Approval DSA No.: 03-117769 Anticipated Construction Start Date: Fall 2020
Department of Toxic Substances Control (DTSC) and California Environmental Quality Act (CEQA) study in process. On Friday, January 19, 2018, the Facilities performed a site walk at Norwalk HS with the environmental consultant Ninyo & Moore to mark-up the drilling locations for additional sampling required by DTSC. On Wednesday, January 24, 2018, Ninyo & Moore returned to the Norwalk HS to drill and obtain additional samplings. The samplings obtained are currently undergoing review by Ninyo & Moore. On Tuesday, January 23, 2018, the Draft Environmental Impact Report (EIR) has been published for 45-day public review from January 23, 2018 to March 8, 2018, as part of the CEQA analysis process. The scoping meeting is scheduled for March 1, 2018, 6:00 – 7:30pm at Norwalk High School Library, to receive public comments on the Draft EIR.
F A C I L I T I E S P L A N N I N G & C O N S T R U C T I O N
“Planning & Building Schools of Excellence”
GLENN HIGH SCHOOL ATHLETIC FIELDS AND STADIUM PROJECT
(ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BERNARDS PROGRAM MANAGEMENT: CUMMING, GENERAL CONTRACTOR: USS CAL BUILDERS, INC.)
Status: Construction Phase
DSA No.: 03-117757
Bid No.: 201718-3 (Formal)
Construction Start Date: January 2018
Construction trailers have been set. Mobilization, SWPPPs and abatement activities were completed. Demolition is approximately 80% complete, including clear and grub of top soil, removal of chain link fencing and footings, small structures, and asphalt paving. Removal of trees located on South end is scheduled in February, which will complete demolition activities. Excavation of buildings foundations will start early part of February.
.
DEMOLITION AND GRADING
OVER EXCAVATION FOR FIELDHOUSE BLDG.
OVER EXCAVATION FOR BASEBALL DUGOUT/STORAGE BLDG.
LA MIRADA HIGH SCHOOL GYM EXPANSION & LOCKER ROOM
MODERNIZATION PROJECT (ARCHITECT: DLR GROUP, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING) Status: DSA Review
Submitted seismic analysis to DSA on January 29, 2018. Pending approval of the seismic analysis of the gymnasium by DSA.
LA MIRADA HIGH SCHOOL INTERIM PE LOCKER BUILDINGS PROJECT (ARCHITECT: WESTGROUP DESIGN, PROGRAM MANAGEMENT: CUMMING)
Status: DSA Approved
DSA No.: 03-118461
Anticipated Construction Start Date: Summer 2018
LA MIRADA HIGH SCHOOL CAMPUS-WIDE RENOVATION OF HARD/SOFT SCAPE PROJECT
(ARCHITECT: NAC ARCHTIECTURE, PROGRAM MANAGEMENT: CUMMING) Status: Schematic Design
[Site Plan of Interim PE Bldgs.]
[Floor Plan of Girls’ Locker Bldg.]
[Floor Plan of Boys’ Locker Bldg.]
BENTON MIDDLE SCHOOL LANDSCAPE RENOVATION & ACCESSORY BUILDING
PROJECT (ARCHITECT: DLR GROUP, LANDSCAPE ARCHITECT: LYNN CAPOUYA INC, CONSTRUCTION MANAGER AND PROGRAM MANAGEMENT: CUMMING)
SITE OBSERVATION PHOTOS BY CUMMING CORPORATION CM AT BENTON MS
Status: Construction Phase
DSA No.: 03-117773
Bid No.: 201718-1 (Formal)
Construction Start Date: January 2018
Contractor is on site; construction is ongoing for Phase 1. Contractor is installing the Irrigation lines and storm drain lines as well as grading the track. Curbs for the track and concrete placement at the ADA parking area to follow.
CORVALLIS MIDDLE SCHOOL LANDSCAPE RENOVATION & ACCESSORY
STRUCTURES PROJECT (ARCHITECT: DLR GROUP, LANDSCAPE ARCHITECT: LYNN CAPOUYA INC, CONSTRUCTION MANAGER
AND PROGRAM MANAGEMENT: CUMMING)
SITE OBSERVATION PHOTOS BY CUMMING CORPORATION CM AT CORVALLIS MS
MORRISON ES AND LOS ALISOS MS HVAC/MODERNIZATION OF ADMIN. & MPR
BUILDINGS PROJECTS (ARCHITECT: RACHLIN PARTNERS, CONSTRUCTION MANAGER: BERNARDS, PROGRAM MANAGEMENT: CUMMING)
Status: DSA Approved – Bidding Phase
DSA No.: 03-117756(Morrison ES) & 03-117755 (Los Alisos MS)
Anticipated Construction Start Date: Summer 2018
Status: Construction Phase
DSA No.: 03-117774
Bid No.: 201718-2 (Formal)
Construction Start Date: January 2018
Contractor is on site; construction is ongoing for Phase 1. Contractor is installing the Irrigation lines and storm drain lines. Catch basins and the curb for the track to follow. Phase 1 is currently on track.
Projects were advertised for bidding on Tuesday, February 6, 2018 and bids will be opened on March 22nd. Construction is anticipated to begin on June 7th, 2018.
GARDENHILL ES AND HUTCHINSON MS HVAC/MODERNIZATION OF ADMIN. & MPR BUILDINGS PROJECTS (ARCHITECT: DLR GROUP, CONSTRUCTION MANAGER: BALFOUR BEATTY CONSTRUCTION, PROGRAM MANAGEMENT: CUMMING)
Status: DSA Approved – Bidding Phase
DSA No.: 03-118109 (Gardenhill ES) & 03-118110 (Hutchinson MS)
Anticipated Construction Start Date: Summer 2018
Projects were advertised for bidding Tuesday, February 6, 2018 and bids will be opened on March 20th. Construction is anticipated to begin on June 7th, 2018.
HUTCHINSON MS GARDENHILL ES
CHAVEZ ELEMENTARY SCHOOL PLAYGROUND PROJECT (ARCHITECT: TBD)
Status: Planning Last week Facilities Staff conducted site visits with various Architect Firms to obtain cost for the architectural services needed for the new playground. We anticipate taking an agreement to the Monday, February 26, 2018 Board Meeting to begin the design phase.
GLAZIER ELEMENTARY SCHOOL KINDERGARTEN PLAYGROUND REPLACEMENT PROJECT (ARCHITECT: TBD)
Status: Planning Last week Facilities Staff conducted site visits with various Architect Firms to obtain cost for the architectural services needed for the new playground. We anticipate taking an agreement to the Monday, February 26, 2018 Board Meeting to begin the design phase.
JOHN GLENN HIGH SCHOOL ELECTRONIC MARQUEE PROJECT
(ARCHITECT: DONALD KROTEE PARTNERSHIP)
Status: Construction DSA No.: 03-118126 The electronic marquee project is complete. Project closeout with the Division of the State Architect is in progress.
INSTALLATION OF THE NEW ELECTRONIC MARQUEE
NORWALK ADULT SCHOOL ELECTRONIC MARQUEE PROJECT (ARCHITECT: DONALD KROTEE PARTNERSHIP) Status: Bidding
DSA No.: 03-117490
Anticipated Construction Start Date: February 2018 Staff has requested a purchase order to build and install the marquee. Staff has forwarded inspection services agreements to proposed firms. The project inspector and geotechnical/material testing and special inspection agreements are scheduled for Board of Education approval on February 26, 2018.
HUTCHINSON MIDDLE SCHOOL ELECTRONIC MARQUEE PROJECT (ARCHITECT: DONALD KROTEE PARTNERSHIP)
Status: DSA Approved DSA No.: 03-118556 Anticipated Construction Start Date: March 2018
DSA approved the project for construction. The bidding phase will commence after receipt of the approved plans and specifications.
NEW ELECTRONIC MARQUEE
NORWALK HIGH SCHOOL ELECTRONIC MARQUEE PROJECT
(ARCHITECT: DONALD KROTEE PARTNERSHIP)
Status: DSA Approved DSA No.: 03-118554 Anticipated Construction Start Date: March 2018
DSA approved the project for construction. The bidding phase will commence after receipt of the approved plans and specifications.
ESCALONA ELEMENTARY SCHOOL PORTABLE CLASSROOM PROJECT (ARCHITECT: WESTGROUP DESIGNS)
Status: Design Development/Construction Documents
Converse Consultants identified/staked the boring locations at Escalona ES for soil sampling.
MOFFITT ELEMENTARY SCHOOL HEAD START PORTABLE CLASSROOM PROJECT
(ARCHITECT: WESTGROUP DESIGNS)
LOS ALISOS MIDDLE SCHOOL PORTABLE REPLACEMENT PROJECT (ARCHITECT: WESTGROUP DESIGNS) Status: DSA Approved
DSA No.: 03-117927
The project was approved by the Division of the State Architect on January 29th. Upon receipt of the approved plans and specifications, staff will request a bid schedule from the Purchasing department. Staff is also scheduling a project review meeting with the site administrator.
HUTCHINSON MIDDLE SCHOOL PORTABLE LOCKER ROOM & CLASSROOM PROJECT (ARCHITECT: WESTGROUP DESIGNS)
Status: Design Development/Construction Documents
Converse Consultants sampling the soil at Moffitt ES for the Geotechnical Report. (Pictured)
Status: Design Development/Construction Documents Converse Consultant sampling the soil at Hutchinson MS for the geotechnical report.
NORWALK HIGH SCHOOL PORTABLE WEIGHT ROOM & FIRE WATER SERVICE
LOOP PROJECT (ARCHITECT: RACHLIN PARTNERS)
Status: Design Development/Construction Documents
NORWALK HIGH SCHOOL CTE CULINARY ARTS CLASSROOM CONVERSION PROJECT
(ARCHITECT: RACHLIN PARTNERS) Status: DSA Plan Check Review DSA No.: 03-118429
On Monday, January 29, 2018, the Facilities performed the roof coring with the roofing contractor to examine the existing condition of the roof at Bldg. K.
MONDAY, 1/29/18 CORING OF EXISTING ROOFING AT NORWALK HS
On Tuesday, January 30, 2018, the Facilities performed the examination of the existing gas pipe conditions with the plumber, Abe’s Plumbing.
TUESDAY, 1/30/18 EXISTING GAS PIPE EXAMINATION AT NORWALK HS
EXCELSIOR HIGH SCHOOL AUDITORIUM CNRA GRANT PROJECT (ARCHITECT: RUHNAU CLARKE)
Status: Scope Development Facilities staff along with Business Services, Technology Services and Maintenance & Operations met with the architect (Ruhnau Clarke) and the Theater Consultant (The Ruzika Group) on Monday, February 5th, to discuss the project scope. The team also toured the interior and exterior of the auditorium with the architect and Theater Consultant. The architect is scheduled to forward a potential/proposed scope for the District’s review within two weeks.
MONDAY, 2/5/18
EXCELSIOR AUDITORIUM SITE VISIT WITH RUHNAU CLARKE ARCHITECTS AND THE RUZIKA GROUP
KITCHEN REMODEL PROJECTS LOCATED AT DISTRICT OFFICE, JOHN GLENN HS,
LA MIRADA HS, AND NORWALK HS (ARCHITECT: WEBB, CONSTRUCTION MANAGER: BERNARDS)
Status: Design
During the Monday, January 22, 2018 Board Meeting, the Board approved the agreements for WEBB to design the kitchens and Bernards for construction management services. Currently the District, Bernard, and WEBB are coordinating the design development. Considering the Monday, May 29, 2018 Board meeting, WEBB informed that they require 6 weeks for procurement time and 30 days for installation.
RAMONA HEAD START SHADE STRUCTURES PROJECT (ARCHITECT: DOUGHERTY)
Status: Pre-Bidding Anticipated Construction Start Date: Summer 2018 The project was approved by the Division of the State Architect (DSA) in 2017. Facilities Staff is currently working with Head Start to order the shade structures from Dave Bang Associates. Once the structures are fabricated they should arrive within 6-8 weeks. Project is currently on track for Summer 2018 Construction.
NORWALK ADULT SCHOOL RESTROOM REMODEL (ARCHITECT: TBD)
Status: Planning
A request was received from Norwalk Adult School to remodel a restroom in the 300 wing. On Tuesday, February 6, 2018, Facilities Staff met with Dougherty Architects for a site visit. Facilities Staff is currently working on a total construction and project budget.