  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    1/24

    Contents

    1 Precautions ..............................................................................................................................................2

    2 Tools for Installation .............................................................................................................................3

    3 Outline and Structure.............................................................................................................................4

    4 Installing the Lifting eyes.....................................................................................................................5

    5 Adjust the Position of the MDF (optional)........................................................................................6

    6 Installing the Cabinet on a Concrete Pedestal (reshell)..................................................................7

    6.1 Plan Space for the cabinet..............................................................................................................................................7

    6.2 Constructing the concrete pedestal................................................................................................................................8

    6.3 Installing the Cabinet Base Frame.................................................................................................................................9

    6.4 Installing the Passive Cabinet......................................................................................................................................106.5 Fixing the CCC rack(optional).....................................................................................................................................11

    6.6 Installing the Active Cabinet.......................................................................................................................................12

    6.7 Installing the Waterproof Module................................................................................................................................13

    7 Routing Cables .....................................................................................................................................14

    7.1 Connecting AC Power Cables and Ground Cable.......................................................................................................14

    7.2 Connecting Subscriber Cables.....................................................................................................................................15

    7.3 Connecting Optical Cable and Optical Fibers..............................................................................................................16

    8 Installing the accessories of the Passive Cabinet...........................................................................17

    8.1 Installing the Maintenance Socket...............................................................................................................................17

    8.2 Installing the Maintenance Illuminator........................................................................................................................18

    8.3 Installing the Door Status Sensor.................................................................................................................................19

    9 Installing Batteries................................................................................................................................20

    10 Checking the Cabinet Installation ..................................................................................................21

    11 PoweringOn the Device....................................................................................................................22

    12 Sealing the Cabinet.............................................................................................................................23

    13 MDF Label............................................................................................................................................24

    1

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    2/24

    Precautions

    NOTE

    This document aims to provide simple and distinctive guidelines for hardware installation.

    This document does not describe operations for the pre-delivery installation of the internal cables and so on. Instead, this document

    describers only the operations for on-site installation.

    Electrostatic Discharge

    Before touching the device, or holding the boards and IC chips, wear the ESD gloves or the ESD wrist strap to prevent the

    electrostatic discharge of the human body from damaging the sensitive components. Ensure that the other end of the ESD

    wrist strap is well grounded.

    Bundling cables

    The distance between cable ties or fiber binding straps inside the cabinet should be within 250 mm. (For subscriber

    cablethe distance is 200 mm. )

    Affixing labels / tags

    l After routing the cable, affix the label or fasten the tag to the cable, and 20 mm away from the connector.

    l After the label for the signal cable is affixed to the signal cable, the rectangular text area of the label should face

    rightwards or downwards.

    l After the identification plate for the power cable is affixed to the power cable, the text area of the plate should face

    rightwards or downwards. Ensure that the side affixed with the label faces outwards.

    Using the desiccant

    After removing the packing case of the cabinet on the site, take out the desiccant packages from the corresponding paperbag (Note: Do not tear the own packages of the desiccant). Then, put the desiccant packages at proper places of the cabinet.

    After powering on the cabinet, the desiccant packages must be removed and disposed of as an industrial waste.

    2 Copyright Huawei Technologies Co., Ltd. 2011. All rights reserved.

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    3/24

    Tools for Installation

    Before you begin, get the following tools ready.

    Tape measure Philips screwdriver Flathead screwdriver

    Adjustable wrench Socket wrench Percussion drill

    Claw hammer Diagonal pliers Hydraulic crimper

    Cable cutter Network cable crimping pliers Wire stripper

    ESD wrist strap Wire cutter Multimeter

    Rubber hammer

    3

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    4/24

    Outline and Structure

    4

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    5/24

    Installing the Lifting eyes

    5

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    6/24

    Adjust the Position of the MDF (optional)

    6

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    7/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.1 Plan Space for the cabinet

    7

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    8/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.2 Constructing the concrete pedestal

    8

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    9/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.3 Installing the Cabinet Base Frame

    9

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    10/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.4 Installing the Passive Cabinet

    10

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    11/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.5 Fixing the CCC rack(optional)

    11

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    12/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.6 Installing the Active Cabinet

    12

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    13/24

    Installing the Cabinet on a Concrete Pedestal (reshell)

    6.7 Installing the Waterproof Module

    13

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    14/24

    Routing Cables

    7.1 Connecting AC Power Cables and Ground Cable

    14

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    15/24

    Routing Cables

    7.2 Connecting Subscriber Cables

    15

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    16/24

    Routing Cables

    7.3 Connecting Optical Cable and Optical Fibers

    16

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    17/24

    Installing the accessories of the Passive Cabinet

    8.1 Installing the Maintenance Socket

    17

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    18/24

    Installing the accessories of the Passive Cabinet

    8.2 Installing the Maintenance Illuminator

    18

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    19/24

    Installing the accessories of the Passive Cabinet

    8.3 Installing the Door Status Sensor

    19

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    20/24

    Installing Batteries

    20

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    21/24

    Checking the Cabinet Installation

    No. Requirement Method

    1 The cabinet components are installed correctly. The cabinet door shall have no distortion.

    The boards can be plugged and unplugged without difficulty. Installation of self-made

    components shall comply with the requirements.

    Observe and try out

    2 The cabinet is installed correctly without flake-off or damage. Observe

    3 The cabinet is installed reliably, satisfying the quakeproof requirements in the project

    file.

    Observe

    4 The cabinet installation site complies with the project file. Observe the

    installation site

    5 All cable apertures are sealed well, including apertures for power cables, ground cable,

    optical cable, and external subscriber cables.

    Observe

    6 The external positive lead and positive lead of battery are correctly and reliably

    connected to the power system.

    Test with a

    multimeter

    7 The protective covers on the battery terminals are intact. Observe

    8 None of the cables has damage, fracture, or joint on the cable. Observe

    9 The power cable and ground cable adopt a whole segment of copper core. The cable has

    no joint in the middle or scratch on the skin.

    Observe

    10 The cross sectional area of the power cable and that of the ground cable comply with the

    project file, satisfying the power distribution requirements of the cabinet.

    Observe

    11 Optical fiber headers and board optical ports to be used are protected with protective

    caps. If necessary, clean them in compliance with Huawei regulations.

    Observe

    12 Cables outside the cabinet are buried underground if possible. If they are routed through

    the cabling rack, the lightning proof measures shall be adopted.

    Observe

    21

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    22/24

    Powering On the Device

    22

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    23/24

    Sealing the Cabinet

    23

  • 7/31/2019 F01H200A Installation Pocket Guide(02)

    24/24

    MDF Label