facilities construction - northside independent school ... · contractor – central builders, inc....
TRANSCRIPT
![Page 1: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/1.jpg)
Facilities Construction
NORTHSIDE INDEPENDENT SCHOOL DISTRICT
Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION
September 2018
1
![Page 2: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/2.jpg)
NEW SCHOOLS
2
![Page 3: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/3.jpg)
DR. LINDA G. MORA ELEMENTARY SCHOOL
Front Rendering
Architect – Noonan Rittimann Architects, LLC Project Architect – John Rittimann
NISD Project Manager – Chris Parker
Contract Amount - $22,465,000 Construction Period – March 2017 – August 2018 Construction Status – 100% Project Scope – New 800 Student Elementary School
(Prototype of Boldt ES and Cole ES)
Contractor – DL Bandy Constructors, Inc.
3
![Page 4: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/4.jpg)
DR. LINDA G. MORA ELEMENTARY SCHOOL
4
![Page 5: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/5.jpg)
DR. LINDA G. MORA ELEMENTARY SCHOOL
Front Entrance
Story Telling Mural Library Area
5
![Page 6: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/6.jpg)
DR. LINDA G. MORA ELEMENTARY SCHOOL
Front Entry
Serving Line Cafeteria Area
6
![Page 7: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/7.jpg)
ADDITIONS AND RENOVATION
PROJECTS IN CONSTRUCTION
7
![Page 8: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/8.jpg)
NORTHSIDE ACTIVITY CENTER RENOVATIONS
Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – O’Haver Contractors Co. Contract Amount - $5,319,485 Construction Period – February 2017 – August 2018 Construction Status – 100% Project Scope – Addition of the New Building is complete and in use.
New Addition Main Entrance
8
![Page 9: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/9.jpg)
NORTHSIDE ACTIVITY CENTER RENOVATIONS
NAC Renovated Meeting Room
NAC Addition Corridor
NAC New Meeting Room 9
![Page 10: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/10.jpg)
JOHN GLENN ELEMENTARY School Building Replacements / Security Lobby
Architect – LPA, Inc. Project Architect – Mark Oppelt / Lowell Tacker NISD Project Manager – Thomas Curiel Contractor – Suburban Construction Contract Amount - $7,034,840 Construction Period – June 2017 – August 2018 Construction Status – 100% Project Scope – Replacement of Administration/Classroom Building
Building is in Final Punch.
Rendering of Building Replacement 10
![Page 11: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/11.jpg)
JOHN GLENN ELEMENTARY School Building Replacements / Security Lobby
Front Entrance Front Entrance
11
![Page 12: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/12.jpg)
JOHN GLENN ELEMENTARY School Building Replacements / Security Lobby
Lobby Entrance Front Entrance
12
![Page 13: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/13.jpg)
OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke Contract Amount - $32,014,460 Construction Period – June 2017 – December 2018 Construction Status – 74% Package 2 (Building) Project Scope – Fine Arts Building Replacement
Outdoor stairs and canopies underway. Flooring on lower level ongoing. Face brick area A West, Tile & Ceiling grid in B/A West cloud framing and sheetrock in Auditorium. Mezzanine piping, ductwork, roofing on flyloft, gutters and sheet metal.
Rendering of New Auditorium 13
![Page 14: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/14.jpg)
OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM
14
![Page 15: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/15.jpg)
OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM
Exterior Construction
Exterior Construction
15
![Page 16: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/16.jpg)
OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM
Interior Construction
Exterior Construction
16
![Page 17: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/17.jpg)
MURRAY E. BOONE ELEMENTARY SCHOOL
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – James Evans Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018 Construction Status – 95% Project Scope – New Administration Area, New Bus/Student Walkway Canopy,
Landscaping in progress.
Rendering of New Administration Entrance 17
![Page 18: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/18.jpg)
Exterior Construction
Exterior Construction Bike Rack near Entry
MURRAY E. BOONE ELEMENTARY SCHOOL
Student Canopy
18
![Page 19: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/19.jpg)
DOLORES B. LINTON ELEMENTARY SCHOOL Additional Student Canopy
Architect – Munoz & Company Architects Project Architect – Randy Hohlaus NISD Project Manager – Chris Parker Contractor – Pronto Sandblasting Contract Amount - $375,900 Tentative Construction Period – March 2018 – August 2018 Construction Status – 100% Project Scope – Additional Student Canopy
19
![Page 20: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/20.jpg)
DOLORES B. LINTON ELEMENTARY SCHOOL Additional Student Canopy
Rendering of Additional Student Canopy
20
![Page 21: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/21.jpg)
DOLORES B. LINTON ELEMENTARY SCHOOL Additional Student Canopy
Student Canopy Student Canopy
Student Canopy
21
![Page 22: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/22.jpg)
SAM RAYBURN MIDDLE SCHOOL Building Replacement
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Contract Budget - $12,500,000 GMP Amount – Phase I - $3,051,018 GMP Amount - Phase II
Tentative Construction Period - June 2018 - August 2019 Construction Status - 25%
Site utilities in progress.ALE - Building renovation in progress, demolition is complete. Phase I in progress - Foundation Piers site Phase II in progress - Structural frame
Project Scope - Building Replacement (D & F)
GMP Amount - Phase III - Currently being Bid
22
![Page 23: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/23.jpg)
SAM RAYBURN MIDDLE SCHOOL Building Replacement
Existing Campus Aerial View
23
![Page 24: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/24.jpg)
SAM RAYBURN MIDDLE SCHOOL Building Replacement
Canopy between Building “F” & "A" Excavation - Foundation
Building “J” - ALE
24
![Page 25: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/25.jpg)
SAM RAYBURN MIDDLE SCHOOL Building Replacement
New Library Location
New Gym and Boys Lockers LocationBand Hall Addition Former Location of Gym, Boys Locker Room and Band Hall
25
![Page 26: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/26.jpg)
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy
Architect – Chesney Morales Partners, Inc. Project Architect – Richard Morales NISD Project Manager – James Evans Contractor – Breda Construction, Inc. Contract Amount - $468,095 Construction Period – June 2018 – October 2018 Construction Status – 65% Project Scope – Additional Student Canopy
Foundation work and site utilities in progress.Weather delays ongoing.
26
![Page 27: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/27.jpg)
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy
27
![Page 28: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/28.jpg)
F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy
Existing Canopy
Excavation - Sidewalk
Entrance
28
![Page 29: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/29.jpg)
MARY HULL ELEMENTARY SCHOOL Bus Canopy Renovation
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – Henock Construction Contract Amount - $400,000 Construction Period – June 2018 – September 2018 Construction Status – 99% Project Scope – Bus Canopy Renovation
Canopy roof completion in progress.
Front Entrance 29
![Page 30: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/30.jpg)
MARY HULL ELEMENTARY SCHOOL Bus Canopy Renovation
Proposed Bus Canopy
30
![Page 31: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/31.jpg)
MARY HULL ELEMENTARY SCHOOL Bus Canopy Renovation
Canopy Structure
Canopy Structure
31
![Page 32: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/32.jpg)
BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Thomas Curiel Contractor – WR Griggs Construction Co. Contract Amount - $2,671,000 Construction Period – June 2018 – December 2018 Construction Status – 60% Project Scope – Cafeteria/Kitchen Renovations and Window Upgrades
Concrete, caulking windows, electrical rough-ins, HVAC ductwork at Kitchen in progress. Temporary serving lines are complete.
Braun Station ES Braun Station ES 32
![Page 33: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/33.jpg)
BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades
Cafeteria Interior Restroom Upgrade Kitchen Interior
33
![Page 34: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/34.jpg)
BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades
Cafeteria Interior Temporary Serving Lines
34
![Page 35: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/35.jpg)
CHRISTIAN EVERS ES & JOHN JAY HIGH SCHOOL Flooring Project
Architect – CWS Architects Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – San Antonio Floor Finishers, Inc. Contract Amount - $178,645 Construction Period – June 2018 – August 2018 Construction Status – 100% Project Scope – VCT and Carpet Flooring Replacement
35
![Page 36: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/36.jpg)
CHRISTIAN EVERS ES & JOHN JAY HIGH SCHOOL Flooring Project
Evers Elementary John Jay High School John Jay High School
36
![Page 37: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/37.jpg)
JOHN MARSHALL HIGH SCHOOL Courtyard Renovations
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – RCO Construction Contract Amount - $336,525 Construction Period – June 2018 – August 2018 Construction Status – 100% Project Scope – Courtyard Renovations
37
![Page 38: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/38.jpg)
JOHN MARSHALL HIGH SCHOOL Courtyard Renovations
Exterior Courtyard
Exterior Courtyard 38
![Page 39: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/39.jpg)
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – CGC General Contractors, Inc. Contract Amount - $4,249,000 Construction Period – June 2018 – August 2019 Construction Status – 25% Project Scope – Cafeteria / Kitchen Renovation
Temporary serving lines are complete. Kitchen renovation work in progress.
39
![Page 40: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/40.jpg)
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen / Courtyard Renovations
Aerial of Site
NEW KITCHEN ADDITION
RENOVATED
CAFETERIA
40
![Page 41: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/41.jpg)
Kitchen Demolition
JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Cafeteria Work Kitchen Demolition
41
![Page 42: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/42.jpg)
E. M. PEASE MIDDLE SCHOOL Fine Arts & Canopy Addition
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – Webber Commercial Construction Co. Contract Amount - $2,784,000 Construction Period – June 2018 – December 2018 Construction Status – 29% Project Scope – Fine Arts Addition, Bus Canopy & Drainage Upgrades
Canopy foundations complete.Fine Arts Classrooms renovation and addition in progress.
42
![Page 43: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/43.jpg)
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Aerial Vi ew of Campus 43
![Page 44: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/44.jpg)
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Existing Front Entrance and Fine Arts Classrooms
Rendering of Band Room Addition at Fine Arts Classrooms
44
![Page 45: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/45.jpg)
E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades
Fine Arts Addition
Fine Arts Addition
Fine Arts Addition
Fine Arts Addition
45
![Page 46: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/46.jpg)
TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – Central Builders, Inc. Contract Amount - $3,892,000 Construction Period – June 2018 – February 2019 Construction Status – 40% Project Scope – Cafeteria / Kitchen Renovation
Kitchen renovation framing/MEP rough-in in progress.Temporary serving lines are complete.
Renovated Cafeteria 46
![Page 47: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/47.jpg)
TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation
Existing Exterior of Cafeteria
Exterior of Cafeteria Addition
47
![Page 48: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/48.jpg)
HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work
Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – James Evans Contractor – Central Builders Contract Amount - $2,977,000 Construction Period – June 2018 – September 2018 Construction Status – 100% Project Scope – Window Upgrades, ADA Work
48
![Page 49: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/49.jpg)
HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work
POWELL ELEMENTARY SCHOOL 49
![Page 50: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/50.jpg)
HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work
HELOTES ELEMENTARY SCHOOL
50
![Page 51: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/51.jpg)
HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work
Helotes ES - Classroom Window Before Helotes ES - Classroom Window After
Powell ES - Window Upgrades After 51
![Page 52: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/52.jpg)
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – WR Griggs Construction Contract Amount - $6,141,000 Tentative Construction Period – May 2018 – August 2019 Construction Status – 40% Project Scope – Science Classroom, Library Renovation and Classroom Addition
Demolition complete. Wall framing in progress. Plumbing, HVAC and Electrical rough-in in progress.
52
![Page 53: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/53.jpg)
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
53Site Plan
![Page 54: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/54.jpg)
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
Rendering of New Library
54
![Page 55: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/55.jpg)
Library - Interior Science Classroom - Renovation
KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation
Science Classroom - Addition55
![Page 56: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/56.jpg)
COLBY GLASS ELEMENTARY Window Upgrades / ADA Work
Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Chris Parker Contractor – CGC General Contractors, Inc. Contract Amount - $874,900 Construction Period – June 2018 – September 2018 Construction Status – 90% Project Scope – Window Upgrades and ADA Work
Punch list in progress.
56
![Page 57: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/57.jpg)
COLBY GLASS ELEMENTARY Window Upgrades / ADA Work
Existi ng Site Plan
57
![Page 58: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/58.jpg)
COLBY GLASS ELEMENTARY Window Upgrades / ADA Work
Window Replacement
58
![Page 59: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/59.jpg)
COLBY GLASS ELEMENTARY Window Upgrades / ADA Work
Before - Window Upgrades After - Window Upgrades
59
![Page 60: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/60.jpg)
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2018
60
![Page 61: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/61.jpg)
KALLISON RANCH AREA MIDDLE SCHOOL New Middle School
Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – TBD Construction Amount - $39,000,000 Construction Period – July 2019 – May 2021 Status - In Design Project Scope – New Middle School
Schematic Design is scheduled.
61
![Page 62: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/62.jpg)
RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School
Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $23,000,000 Construction Period – March 2019 – May 2020 Status - In Design Project Scope – New Elementary School
Construction drawings 30%.
62
![Page 63: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/63.jpg)
RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School
Rendering of Rancho Del Lago Elementary School
63
![Page 64: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/64.jpg)
NORTHSIDE NATATORIUM Pool Replacement
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – James Evans Contractor – TBD Construction Budget - $1,200,000 Construction Period – March 2019 – August 2019 Status – In Design Project Scope – Pool Replacement
Construction drawings 95%.
64
![Page 65: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/65.jpg)
NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS
Architect – Marmon MokProject Architect – Monty HowardNISD Project Manager – Thomas CurielContractor – TBDConstruction Budget – $350,000Construction Period – February 2019 – April 2019Project Scope – Plaza Pylons
Schematic Design in progress.
Flanking Steel Pylons 65
![Page 66: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/66.jpg)
NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS
Plaza of Influence Commemoration Marker
66
![Page 67: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/67.jpg)
2014 BOND PROJECTS
IN
BID/DESIGN PHASE
SUMMER 2019
67
![Page 68: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/68.jpg)
JOHN MARSHALL HIGH SCHOOL Library Upgrades
Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – TBD Construction Budget - $3,000,000 Construction Period – April 2019 – February 2020 Project Scope – Library Addition & Renovation
Schematic Design in progress.
68
![Page 69: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/69.jpg)
2018 BOND PROJECTS
ADDITIONS/RENOVATIONS
IN DESIGN
69
![Page 70: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/70.jpg)
GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building
Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Contract Amount - $4,000,000 Construction Period – June 2019 – July 2020 Project Scope – Library and Classroom Building
Schematic Design in progress.
70
![Page 71: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/71.jpg)
PROJECT LISTING - 2018 BOND PROJECTS
Galm Road Area High School
2019 Security Lobbies for 21 CampusesNorthwest Crossing Elementary School Cafeteria/Kitchen RenovationsPat Neff Middle School Cafeteria UpgradesMeadow Village Elementary School Special Education ALE UpgradesWilliam P. Hobby Middle School Bus/Student Covered WalkwayO'Connor High School Flooring ReplacementPaint Booth Replacement at Oliver Wendell Holmes High School and John Jay High School 2019 Door Hardware Project at Various CampusesIntegrated Security Management System Upgrades at Various Campuses - Phase 1O'Connor High School Agriculture Facility Upgrade
Additions and Renovations Projects in Design & Scheduled
New Construction Projects in Design
71
![Page 72: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/72.jpg)
ROOFING PROJECTS
72
![Page 73: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/73.jpg)
2016 Hail Damage Roofing Projects
Phase IV - Bidding
Phase I - Complete
Beard Elementary School
Carnahan Elementary School
Clark High School
Stevenson Middle School
Carlos Coon Elementary School
Elrod Elementary School
Phase II – In Construction
Esparza Elementary School
Nichols Elementary School Connally Middle School
Howsman Elementary School (2014 Bond) Leon Valley Elementary School
Scarborough Elementary School
Alternative ES & MS - North
Burke Elementary School
Brauchle Elementary School
Leon Springs Elementary School
Raba Elementary School
Phase III – In Construction
Burke Elementary School
Clark High School
Helotes Elementary School
O’Connor High School Rhodes Elementary School
Sul Ross Middle School
Steubing Elementary School
Portable Roofs – Phase II (102)
Vale Middle School
Zachry Middle School
Driggers Elementary School
Briscoe Middle School
Colonies North Elementary School Hoffmann Elementary School Scobee Elementary School Alternative MS - South
Northwest Crossing Elementary
Henderson Elementary School Knowlton Elementary School
Maintenance Building (2014 Bond)
LIST OF SC HOOLS
73
Portable Roofs - Phase I (40)
![Page 74: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018](https://reader034.vdocuments.net/reader034/viewer/2022042712/5fa3f92f147bb33cc82422a6/html5/thumbnails/74.jpg)
2016 Hail Damage Roofing Projects
Phase V - Design
O'Connor High School
Brandeis High School
Stinson Middle School
Kuentz Elementary School
John Jay High School
Hobby Middle School
Phase VI – Future
Support Services Center
Oak Hills Terrace Elementary School Kelly Smith Technology Center
Taft High School Northside Activity Center
North Transportation Station
Pease Middle School
Health Careers High School
Northside Tennis Center
Jefferson Middle School
John Glenn Elementary School
Mireles Elementary
Brennan High School Holmes High School
Rhodes Transportation Center Ward Elementary School
McDermott Elementary School
Mead Elementary School
Myers Elementary School
74