Facilities Construction
NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Leroy San Miguel
ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Henry Acosta
EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING
Jim Berg AIA
DIRECTOR OF FACILITIES CONSTRUCTION
January 2018
1
PROJECTS IN
CONSTRUCTION
2
Architect – Noonan Rittiman
Project Architect – John Rittiman
NISD Project Manager – Chris Parker
Contractor – DL Bandy Constructors, Inc.
Contract Amount - $24,465,000
Construction Period – March 2017 – May 2018
Construction Status – 47%
Project Scope – New 800 Student Elementary School
(Prototype of Boldt ES and Cole ES)
CMU walls/roofing/steel structure in progress.
MEP rough-in in progress.
DR. LINDA G. MORA ELEMENTARY SCHOOL
Classroom Wing Front Entrance
3
DR. LINDA G. MORA ELEMENTARY SCHOOL
4
NORTHSIDE ACTIVITY CENTER RENOVATIONS
Architect – Richard Sanchez Architects, Inc.
Project Architect – Richard Sanchez
NISD Project Manager – Thomas Curiel
Contractor – O’Haver Contractors Co.
Contract Amount - $5,319,485
Construction Period – February 2017 – April 2018
Construction Status – 68%
Project Scope – Addition/Renovation
Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to
boiler being tested. Waterproofing exterior. Masonry in progress.
Roof top units being installed. Ductwork installed, electrical rough-in
underway. Track & motors for partitions at new building installed.
5
Building Exterior Exterior Windows Building Interior
NORTHSIDE ACTIVITY CENTER RENOVATIONS
6
Front Windows
COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work
Architect – Huckabee Architects
Project Architect – Jeff Rodriquez
NISD Project Manager – Chris Parker
Contractor – Central Builders
Contract Amount - $2,022,000
Construction Period – June 2017 – January 2018
Construction Status – 92%
Project Scope – Window Upgrades and ADA Work
Interior work complete.
Masonry in progress.
7
Story Telling Area Kitchen Loading Dock Kitchen Interior Walls
KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition
Architect – Pfluger
Project Architect – Carr Hornbuckle
NISD Project Manager – Chris Parker
Contractor – O’Haver Contractors Co.
Contract Amount – $2,335,100
Construction Period – June 2017 – March 2018
Construction Status – 70%
Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library
Kitchen interior walls and MEP rough-in in progress.
Phase 1 – Library is complete.
8
Architect – LPA
Project Architect – Mark Oppelt / Lowell Tacker
NISD Project Manager – Marilyn Sevedge
Contractor – Suburban Construction
Contract Amount - $6,850,000
Construction Period – June 2017 – August 2018
Construction Status – 27%
Project Scope – Replacement of Administration/Classroom Building
80% Floor Slab poured, 70% Columns complete.
Backfilling slab, electrical switchgear replaced.
Steel on Site.
Rendering of Building Replacement
Column Construction
Column Construction
GLENN ELEMENTARY School Building Replacements / Security Lobby
9
Cafeteria Entrance Kitchen Area Reading Area
TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition
Architect – Shawn Kaarlsen & Associates
Project Architect – Shawn Kaarlsen
NISD Project Manager – Chris Parker
Contractor – Workman Commercial Construction
Contract Amount – $2,231,800
Construction Period – June 2017 – March 2018
Construction Status – 70%
Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library
Kitchen interior walls and interior finishes, MEP rough-in in progress.
Phase 1 – Library is complete.
10
Architect – Alamo Architects
Project Architect – Jerry Lammers
NISD Project Manager – Thomas Curiel
Contractor – Bartlett Cocke
Contract Amount - $27,000,000
Construction Period – June 2017 – December 2018
Construction Status – 20% Package 2 (Building)
Project Scope – Fine Arts Building Replacement
Building piers being drilled. Underground Utilities underway.
Lower level concrete foundation poured.
Rendering of New Auditorium
HOLMES HS FINE ARTS Auditorium
11
HOLMES HS FINE ARTS - AUDITORIUM
12
Architect – Garza Architects
Project Architect – Jesse Garza
NISD Project Manager – James Evans
Contractor – Central Builders, Inc.
Contract Amount - $4,900,000
Construction Period – June 2017 – July 2018
Construction Status – 60%
Project Scope – New Administration Area and New Bus/Student Walkway Canopy
Phase 3 Library scheduled to start in December.
Admin. moved in, demo of new library space.
Installation new CMU walls for Library.
Rendering of New Administration Entrance Library Demolition Administration Front Entrance
BOONE ELEMENTARY SCHOOL
13
PROJECTS IN
DESIGN/PLANNING
14
RAYBURN MIDDLE SCHOOL Building Replacment
Architect – Marmon Mok
Project Architect – Monty Howard
NISD Project Manager – James Evans
Contractor – Turner Construction
Budget Amount- $6,400,000
Construction Period – June 2018 – August 2019
In Design
Project Scope – Building Replacement
15
SCOBEE ELEMENTARY SCHOOL Additional Canopy
Architect – CMP
Project Architect – Richard Morales
NISD Project Manager – James Evans
Contractor – TBD
Budget Amount - $400,000
Construction Period – June 2018 – August 2018
In Design
Project Scope – Additional Canopy
16
MARY HULL ELEMENTARY SCHOOL Bus Canopy
Architect – Garza Architects
Project Architect – Jesse Garza
NISD Project Manager – Thomas Curiel
Contractor – TBD
Budget Amount - $300,000
Construction Period – March 2018 – August 2018
In Design
Project Scope – Bus Canopy
17
LINTON ELEMENTARY SCHOOL Additional Student Canopy
Architect – Munoz & Company Architects
Project Architect – Randy Hohlaus
NISD Project Manager – Chris Parker
Contractor – TBD
Budget Amount - $400,000
Construction Period – June 2018 – August 2018
In Design
Project Scope – Student Canopy
18
BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades
Architect – Nextgen Architects
Project Architect – Joel Hernandez
NISD Project Manager – Thomas Curiel
Contractor – TBD
Budget Amount - $2,820,000
Construction Period – April 2018 – November 2018
In Design
Project Scope – Cafeteria/Kitchen Renovations and Window Upgrades
19
PEASE MIDDLE SCHOOL Fine Arts Addition & Bus Canopy
Architect – Garza Architects
Project Architect – Jesse Garza
NISD Project Manager – Thomas Curiel
Contractor – TBD
Budget Amount - $2,500,000
Construction Period – June 2018 – December 2018
In Design
Project Scope – Fine Arts Addition & Bus Canopy
20
STINSON MIDDLE SCHOOL Science Classroom/Library Addition & Renovation
Architect – Pfluger Architects
Project Architect – Carr Hornbuckle
NISD Project Manager – Marilyn Sevedge
Contractor – TBD
Budget Amount - $5,200,000
Construction Period – June 2018 – August 2019
In Design
Project Scope – Science Classroom / Library Addition & Renovation
21
EVERS ELEMENTARY SCHOOL Flooring Project
Architect – CWS
Project Architect – Robert Watts
NISD Project Manager – Chris Parker
Contractor – TBD
Budget Amount - $100,000
Construction Period – June 2018 – August 2018
In Design
Project Scope – Flooring
22
CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Architects
Project Architect – Jesse Garza
NISD Project Manager – Chris Parker
Contractor – TBD
Budget Amount - $4,000,000
Construction Period – May 2018 – February 2019
In Design
Project Scope – Cafeteria/Kitchen Renovation
23
KALLISON RANCH AREA MIDDLE SCHOOL
Architect – Alamo Architects
Project Architect – Jerry Lammers
NISD Project Manager – Thomas Curiel
Contractor – TBD
Budget Amount - $39,000,000
Construction Period – February 2019 – February 2021
In Design
Project Scope – New Middle School
24
HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work
Architect – Shawn Kaarlsen & Associates
Project Architect – Shawn Kaarlsen
NISD Project Manager – Marilyn Sevedge
Contractor – TBD
Budget Amount - $600,000
Construction Period – June 2018 – September 2018
In Design
Project Scope – Window Upgrades and ADA Work
25
COLBY GLASS ELEMENTARY Window Upgrades / ADA Work
Architect – Marmon Mok
Project Architect – Monty Howard
NISD Project Manager – Chris Parker
Contractor – TBD
Budget Amount - $1,500,000
Construction Period – June 2018 – August 2018
In Design
Project Scope – Window Upgrades and ADA Work
26
MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation
Architect – Garza Bomberger
Project Architect – Roy Lewis
NISD Project Manager – Thomas Curiel
Contractor – TBD
Budget Amount - $3,000,000
Construction Period – June 2018 – December 2018
In Design
Project Scope – Cafeteria/Kitchen Renovation
27
2017 GROWTH & IMPROVEMENT
28
2017 GROWTH IMPROVEMENT
1. Athletic Storage Building – Taft HS – Complete and John Jay HS - 98% Complete
29
2016 HAIL DAMAGE
ROOFING PROJECTS
PHASE I & II
30
LIST OF SCHOOLS
Hail Damage Roofing Projects
Phase I
Beard Elementary School
Carnahan Elementary School
Clark High School
South Transportation
Stevenson Middle School
Carlos Coon Elementary School
Elrod Elementary School
Fernandez Elementary School
Phase II
Esparza Elementary School
Nichols Elementary School
Connally Middle School
Howsman Elementary School
Leon Valley Elementary School
Scarborough Elementary School
Alternative ES & MS - North
Burke Elementary School
Brauchle Elementary School
Leon Springs Elementary School
Raba Elementary School
31