facilities construction · project scope – addition/renovation interior framing, mep work, fire...

31
Facilities Construction N N O O R R T T H H S S I I D D E E I I N N D D E E P P E E N N D D E E N N T T S S C C H H O O O O L L D D I I S S T T R R I I C C T T Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION January 2018 1

Upload: others

Post on 04-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Facilities Construction

NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT

Leroy San Miguel

ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS

Henry Acosta

EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING

Jim Berg AIA

DIRECTOR OF FACILITIES CONSTRUCTION

January 2018

1

e006288
Rectangle
Page 2: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

PROJECTS IN

CONSTRUCTION

2

Page 3: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Architect – Noonan Rittiman

Project Architect – John Rittiman

NISD Project Manager – Chris Parker

Contractor – DL Bandy Constructors, Inc.

Contract Amount - $24,465,000

Construction Period – March 2017 – May 2018

Construction Status – 47%

Project Scope – New 800 Student Elementary School

(Prototype of Boldt ES and Cole ES)

CMU walls/roofing/steel structure in progress.

MEP rough-in in progress.

DR. LINDA G. MORA ELEMENTARY SCHOOL

Classroom Wing Front Entrance

3

Page 4: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

DR. LINDA G. MORA ELEMENTARY SCHOOL

4

Page 5: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

NORTHSIDE ACTIVITY CENTER RENOVATIONS

Architect – Richard Sanchez Architects, Inc.

Project Architect – Richard Sanchez

NISD Project Manager – Thomas Curiel

Contractor – O’Haver Contractors Co.

Contract Amount - $5,319,485

Construction Period – February 2017 – April 2018

Construction Status – 68%

Project Scope – Addition/Renovation

Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to

boiler being tested. Waterproofing exterior. Masonry in progress.

Roof top units being installed. Ductwork installed, electrical rough-in

underway. Track & motors for partitions at new building installed.

5

Page 6: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Building Exterior Exterior Windows Building Interior

NORTHSIDE ACTIVITY CENTER RENOVATIONS

6

Page 7: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Front Windows

COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work

Architect – Huckabee Architects

Project Architect – Jeff Rodriquez

NISD Project Manager – Chris Parker

Contractor – Central Builders

Contract Amount - $2,022,000

Construction Period – June 2017 – January 2018

Construction Status – 92%

Project Scope – Window Upgrades and ADA Work

Interior work complete.

Masonry in progress.

7

Page 8: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Story Telling Area Kitchen Loading Dock Kitchen Interior Walls

KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition

Architect – Pfluger

Project Architect – Carr Hornbuckle

NISD Project Manager – Chris Parker

Contractor – O’Haver Contractors Co.

Contract Amount – $2,335,100

Construction Period – June 2017 – March 2018

Construction Status – 70%

Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library

Kitchen interior walls and MEP rough-in in progress.

Phase 1 – Library is complete.

8

Page 9: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Architect – LPA

Project Architect – Mark Oppelt / Lowell Tacker

NISD Project Manager – Marilyn Sevedge

Contractor – Suburban Construction

Contract Amount - $6,850,000

Construction Period – June 2017 – August 2018

Construction Status – 27%

Project Scope – Replacement of Administration/Classroom Building

80% Floor Slab poured, 70% Columns complete.

Backfilling slab, electrical switchgear replaced.

Steel on Site.

Rendering of Building Replacement

Column Construction

Column Construction

GLENN ELEMENTARY School Building Replacements / Security Lobby

9

Page 10: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Cafeteria Entrance Kitchen Area Reading Area

TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition

Architect – Shawn Kaarlsen & Associates

Project Architect – Shawn Kaarlsen

NISD Project Manager – Chris Parker

Contractor – Workman Commercial Construction

Contract Amount – $2,231,800

Construction Period – June 2017 – March 2018

Construction Status – 70%

Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library

Kitchen interior walls and interior finishes, MEP rough-in in progress.

Phase 1 – Library is complete.

10

Page 11: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Architect – Alamo Architects

Project Architect – Jerry Lammers

NISD Project Manager – Thomas Curiel

Contractor – Bartlett Cocke

Contract Amount - $27,000,000

Construction Period – June 2017 – December 2018

Construction Status – 20% Package 2 (Building)

Project Scope – Fine Arts Building Replacement

Building piers being drilled. Underground Utilities underway.

Lower level concrete foundation poured.

Rendering of New Auditorium

HOLMES HS FINE ARTS Auditorium

11

Page 12: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

HOLMES HS FINE ARTS - AUDITORIUM

12

Page 13: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

Architect – Garza Architects

Project Architect – Jesse Garza

NISD Project Manager – James Evans

Contractor – Central Builders, Inc.

Contract Amount - $4,900,000

Construction Period – June 2017 – July 2018

Construction Status – 60%

Project Scope – New Administration Area and New Bus/Student Walkway Canopy

Phase 3 Library scheduled to start in December.

Admin. moved in, demo of new library space.

Installation new CMU walls for Library.

Rendering of New Administration Entrance Library Demolition Administration Front Entrance

BOONE ELEMENTARY SCHOOL

13

Page 14: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

PROJECTS IN

DESIGN/PLANNING

14

Page 15: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

RAYBURN MIDDLE SCHOOL Building Replacment

Architect – Marmon Mok

Project Architect – Monty Howard

NISD Project Manager – James Evans

Contractor – Turner Construction

Budget Amount- $6,400,000

Construction Period – June 2018 – August 2019

In Design

Project Scope – Building Replacement

15

Page 16: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

SCOBEE ELEMENTARY SCHOOL Additional Canopy

Architect – CMP

Project Architect – Richard Morales

NISD Project Manager – James Evans

Contractor – TBD

Budget Amount - $400,000

Construction Period – June 2018 – August 2018

In Design

Project Scope – Additional Canopy

16

Page 17: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

MARY HULL ELEMENTARY SCHOOL Bus Canopy

Architect – Garza Architects

Project Architect – Jesse Garza

NISD Project Manager – Thomas Curiel

Contractor – TBD

Budget Amount - $300,000

Construction Period – March 2018 – August 2018

In Design

Project Scope – Bus Canopy

17

Page 18: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

LINTON ELEMENTARY SCHOOL Additional Student Canopy

Architect – Munoz & Company Architects

Project Architect – Randy Hohlaus

NISD Project Manager – Chris Parker

Contractor – TBD

Budget Amount - $400,000

Construction Period – June 2018 – August 2018

In Design

Project Scope – Student Canopy

18

Page 19: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades

Architect – Nextgen Architects

Project Architect – Joel Hernandez

NISD Project Manager – Thomas Curiel

Contractor – TBD

Budget Amount - $2,820,000

Construction Period – April 2018 – November 2018

In Design

Project Scope – Cafeteria/Kitchen Renovations and Window Upgrades

19

Page 20: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

PEASE MIDDLE SCHOOL Fine Arts Addition & Bus Canopy

Architect – Garza Architects

Project Architect – Jesse Garza

NISD Project Manager – Thomas Curiel

Contractor – TBD

Budget Amount - $2,500,000

Construction Period – June 2018 – December 2018

In Design

Project Scope – Fine Arts Addition & Bus Canopy

20

Page 21: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

STINSON MIDDLE SCHOOL Science Classroom/Library Addition & Renovation

Architect – Pfluger Architects

Project Architect – Carr Hornbuckle

NISD Project Manager – Marilyn Sevedge

Contractor – TBD

Budget Amount - $5,200,000

Construction Period – June 2018 – August 2019

In Design

Project Scope – Science Classroom / Library Addition & Renovation

21

Page 22: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

EVERS ELEMENTARY SCHOOL Flooring Project

Architect – CWS

Project Architect – Robert Watts

NISD Project Manager – Chris Parker

Contractor – TBD

Budget Amount - $100,000

Construction Period – June 2018 – August 2018

In Design

Project Scope – Flooring

22

Page 23: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation

Architect – Garza Architects

Project Architect – Jesse Garza

NISD Project Manager – Chris Parker

Contractor – TBD

Budget Amount - $4,000,000

Construction Period – May 2018 – February 2019

In Design

Project Scope – Cafeteria/Kitchen Renovation

23

Page 24: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

KALLISON RANCH AREA MIDDLE SCHOOL

Architect – Alamo Architects

Project Architect – Jerry Lammers

NISD Project Manager – Thomas Curiel

Contractor – TBD

Budget Amount - $39,000,000

Construction Period – February 2019 – February 2021

In Design

Project Scope – New Middle School

24

Page 25: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work

Architect – Shawn Kaarlsen & Associates

Project Architect – Shawn Kaarlsen

NISD Project Manager – Marilyn Sevedge

Contractor – TBD

Budget Amount - $600,000

Construction Period – June 2018 – September 2018

In Design

Project Scope – Window Upgrades and ADA Work

25

Page 26: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

COLBY GLASS ELEMENTARY Window Upgrades / ADA Work

Architect – Marmon Mok

Project Architect – Monty Howard

NISD Project Manager – Chris Parker

Contractor – TBD

Budget Amount - $1,500,000

Construction Period – June 2018 – August 2018

In Design

Project Scope – Window Upgrades and ADA Work

26

Page 27: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation

Architect – Garza Bomberger

Project Architect – Roy Lewis

NISD Project Manager – Thomas Curiel

Contractor – TBD

Budget Amount - $3,000,000

Construction Period – June 2018 – December 2018

In Design

Project Scope – Cafeteria/Kitchen Renovation

27

Page 28: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

2017 GROWTH & IMPROVEMENT

28

Page 29: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

2017 GROWTH IMPROVEMENT

1. Athletic Storage Building – Taft HS – Complete and John Jay HS - 98% Complete

29

Page 30: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

2016 HAIL DAMAGE

ROOFING PROJECTS

PHASE I & II

30

Page 31: Facilities Construction · Project Scope – Addition/Renovation Interior framing, MEP work, fire sprinkler. Hydronic piping from chiller yard to boiler being tested. Waterproofing

LIST OF SCHOOLS

Hail Damage Roofing Projects

Phase I

Beard Elementary School

Carnahan Elementary School

Clark High School

South Transportation

Stevenson Middle School

Carlos Coon Elementary School

Elrod Elementary School

Fernandez Elementary School

Phase II

Esparza Elementary School

Nichols Elementary School

Connally Middle School

Howsman Elementary School

Leon Valley Elementary School

Scarborough Elementary School

Alternative ES & MS - North

Burke Elementary School

Brauchle Elementary School

Leon Springs Elementary School

Raba Elementary School

31