Page 1: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Facilities Improvements Facilities Improvements and Bond Construction and Bond Construction UpdateUpdateFacilities Advisory Facilities Advisory CommitteeCommittee

Facilities Improvements Facilities Improvements and Bond Construction and Bond Construction UpdateUpdateFacilities Advisory Facilities Advisory CommitteeCommittee

Long Beach Community College District December 2, 2008

EDUCATE ENGAGE EMPOWER 1

Page 2: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Agenda Completed Construction Projects

PCC Learning Resource Center LAC Central Plant

Current & Upcoming Construction Projects LAC South Quad Complex LAC Learning Resource Center LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Infrastructure Improvements – Phase 3 PCC Central Plant PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building C Retrofit District Wide Building Needs Assessment Projects

Toilet Improvement Projects Quick-Start Projects ADA Projects Lighting Projects Classroom Improvement Projects

Recently Completed Facilities Improvements Important Ongoing Initiatives Planned Phasing of Future Projects

Q & A 2

Page 3: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Completed Construction Projects

Construction Complete Modern Facility with Computer Lab

and Multimedia Stand alone Data Center. Provides

District IT redundancy Bridge to building E Design elements move towards

energy efficiencies Ribbon cutting held 9/17/08

PCC Learning Resource Center – Measure E 2002PCC Learning Resource Center – Measure E 2002

3

Page 4: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Completed Construction Projects

Central Plant equipment, Public Safety, & Field House for Athletics

Final FF&E installation underway Plant ready for operation and

awaiting completion of LRC & SQC Construction Complete Anticipated startup 12/05/08

LAC Central Plant – Measure E 2002LAC Central Plant – Measure E 2002

4

Page 5: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Construction approx. 89% Complete

Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive office Multipurpose room State of the art Board Room

Substantial completion anticipated 1/09

South Quad Complex – Measure E 2002South Quad Complex – Measure E 2002

5

Page 6: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Construction 91% Complete Adds 10,000 ASF to existing

building Substantial Completion

Anticipated January 2009

LAC/Learning Resource Center – Measure E 2002LAC/Learning Resource Center – Measure E 2002

6

Page 7: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Design Development to be submitted this month Adds 4,000 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction 7/09

LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

7

Page 8: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Completed Schematic Design (June 2008) Currently in Design Development phase Will house Math and Culinary Arts instructional

program as well as Reprographics Estimated start of construction 2011

LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008

8

Page 9: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Planning initiated for approximately 900 Vehicles

To be procured under “Design Build Delivery” method

To be located Southeast corner of Lot J adjacent to the Verizon building

Photovoltaic Electrical Generation Array on top level of structure

Anticipated start of construction 2009

LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008

9

Proposed Parking Structure Loc.Proposed Parking Structure Loc.

Proposed Math Technology Bldg.

Proposed Math Technology Bldg.

Lot JLot J

Verizon Bldg.

Page 10: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

LAC Infrastructure Improvements – Phase 3LAC Infrastructure Improvements – Phase 3

Measure E 2008Measure E 2008

Planning underway with engineers Completes chilled water lines to

North side of campus Includes other major utility

upgrades; Reclaimed Water, Domestic Water, Data, etc.

Existing building HVAC systems to be upgraded in synch with infrastructure improvements

Coordinated with modernization and quick start projects

10

Page 11: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Houses Central Plant equipment and Maintenance and Operations facility

Construction Approximately 99% Complete

Currently provides chilled water to the PCC LRC

PCC Central Plant – Measure E 2002PCC Central Plant – Measure E 2002

11

Page 12: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Modern facility houses Welding Department and other trade programs

Construction is 45% complete

Replaces existing antiquated structures

New Northern face of the campus

Completion anticipated summer 2009

PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1

Measure E 2002Measure E 2002

12

Page 13: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

90% construction documents submitted Swing space planning completed 9/2008, construction of swing space starts

Spring 2009 Anticipated start of MDAB construction Summer 2009 To be completed in two phases

PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002(Multi-Disciplinary Academic Building) Measure E 2002

13

Page 14: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight

Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (TBD) To be completed concurrently with MDAB project Anticipated start of construction Spring 2010

PCC Building C Retrofit - Measure E 2008PCC Building C Retrofit - Measure E 2008

14

Page 15: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Toilet Improvement Projects

Quick-Start Projects ADA Projects

District Wide Building Needs Assessment ProjectDistrict Wide Building Needs Assessment ProjectMeasure E 2008Measure E 2008

15

Page 16: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Current and UpcomingConstruction Projects

Lighting Projects Classroom Improvement Projects

District Wide Building Needs Assessment ProjectsDistrict Wide Building Needs Assessment ProjectsMeasure E 2008Measure E 2008

16

Page 17: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Recently Completed Facilities Improvements

17

Replaced existing boilers, pumps, expansion tanks and common flue with new equipment via helicopter lift.

A newly upgraded design reflecting a mechanical engineered system was installed improving the efficiency of the boilers.

Completed 10/2008

Building “B” and “E” Boiler ReplacementBuilding “B” and “E” Boiler Replacement

Page 18: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Recently Completed Facilities Improvements

18

Additional Facilities ImprovementsAdditional Facilities Improvements LAC upgrades:

Veteran’s Stadium scoreboard and PA system upgrade Building K upgrades – Exterior door paint, room 111 floor

refinishing PCC upgrades:

Building AA – Built wall for information desk, installed carpet, and power upgrades

Building BB – Carpet and window blind installation Building CC – Installed fans in gym Building DD – Carpet and window blind installation Building EE – Window blind installation Building MM – Exterior paint, replaced doors and awnings, re-

glazed windows, and replaced fascia boards

Page 19: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Important Ongoing Initiatives

Master Landscape Project District Wide Energy Efficiency

Improvements Electronic Marquee Signage Wayfaring and Building Signage Campus Lighting Improvements

19

LBCCD Coming AdvancementsLBCCD Coming Advancements

Page 20: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Planned Phasing of Future Projects

20

Currently Planned ScheduleCurrently Planned Schedule 2008-09

Parking Structure – Design/Build concept Anticipate awarding bid Spring 2009

Moving Warehouse from PCC to Alteon Building at LAC – TBD Moving LAC Building A into Swing Space – Spring 2009 Install portables at PCC for Swing Space – Spring 2009 LAC/PCC Building Needs Assessment Projects

Bathroom Improvement Projects Quick-Start Projects Lighting Projects Classroom Improvement Projects Infrastructure Projects

Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC

Finalize Master Landscaping and Signage plans

Marquee signage anticipated to be installed March 2009

Page 21: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Planned Phasing of Future Projects

21

2009-10 Begin construction of Building A at LAC

Anticipating July 2009 start

Begin construction of Buildings CC, DD, and EE at PCC Anticipating July/August 2009 start

Begin Schematic Design for Buildings C and F at LAC Submit plans to DSA no later than March 2010

Begin Master Landscaping and Signage Initiatives

Continue District Wide Energy Efficiency Improvements Phase IIA

Lighting Upgrades, HVAC Upgrades, Control upgrades, Pool Cover, Roof replacement, etc

Phase IIB Upcoming advancements include connecting current buildings

to Central Plant infrastructure

Currently Planned ScheduleCurrently Planned Schedule

Page 22: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Planned Phasing of Future Projects

22

2010-11 Anticipated Construction completion of Building A

at LAC – January 2011 Submit plans to DSA for Math/Technology Building

at LAC Move Buildings C and F programs into Swing

Space (M/N Building) and begin construction – Spring 2011

Construction completion of Buildings CC, DD and EE at PCC

Begin construction of Buildings AA and BB at PCC Anticipating January/February 2011 start

Currently Planned ScheduleCurrently Planned Schedule

Page 23: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

Planned Phasing of Future Projects

23

2011-12 Begin construction of Math/Technology Building at LAC Submit plans to DSA for M/N Building at LAC

2012-13 Anticipated Construction completion of Buildings C and

F at LAC – December 2012

Anticipated Construction completion of Math/Technology Building at LAC – December 2012

Begin construction of Buildings M/N at LAC – January 2013

Anticipated Construction completion of Buildings AA and BB at PCC – June 2013

Currently Planned ScheduleCurrently Planned Schedule

Page 24: Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE

QUESTIONS & ANSWERS

EDUCATE ENGAGE EMPOWER 24