facilities modernization program funded by measure b project report april 16, 2012

5
Facilities Modernization Program Funded by Measure B Project Report April 16, 2012

Upload: amelia-cross

Post on 17-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Facilities Modernization ProgramFunded by Measure B

Project Report

April 16, 2012

PROJECT PROGRESS REPORTStudent Services & Central Administration

Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction

Project Update:• Storefront installation is complete. Glazing is 75% installed in the Storefronts• Curtainwall installation has started. Glazing to begin April 20• Interior framing continues on the first floor west side in the dining/kitchen area.• Data cable has started being pulled on the second floor east side• Sheetrock has started on one side of the walls.• Elevators are delivered and awaiting installation.• Mechanical units were delivered and installed on the roof.

Occupancy: Spring 2013

LAS POSITAS COLLEGEApril 16, 2012

PROJECT PROGRESS REPORTScience Building, Phase II

Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc

Project Update:• Interior Casework, Lighting and Fume hoods continue to be installed.• Ceiling Tiles being installed in all rooms, Power to building 95% complete, Elevator starts week of April

16, 2012 • Stair Treads and Guardrails are completed.• Greenhouse being installed.• Exterior and Interior Painting is complete. Restrooms completed.• 2nd floor classrooms are completed.• Storefront installation and Glazing Completed.

Occupancy: 09/2012

LAS POSITAS COLLEGEApril 16, 2012

PROJECT PROGRESS REPORTCampus Boulevard Phase I-III

Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: Suarez & Munoz Construction, Inc.

Project Update:• 100% Design review completed, final design was Approved by DSA February 2012. • Project was Bid on March 13, 2012 and Contractor will be Board Approved April 17, 2012.

Design Re-Start: 04/2011DSA Permit Approval: 02/2012Construction Start: 05/2012Occupancy: 10/2012

LAS POSITAS COLLEGEApril 16, 2012

PROJECT PROGRESS REPORTPhotovoltaic System Phase II

Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff

Project Update:• Fencing Completed.• Racking System and Array installation is completed.• Inverters and Transformer installed and completed. • New Switchgear tie in May 19, 2012.

Operational: February 2012

LAS POSITAS COLLEGEApril 16, 2012