Facilities Plan Financial Update
November 27, 2018
Background Building Condition Survey completed by H2M
Architects & Engineers (Spring 2015)
Facilities Committee
$41.4M bond approved by voters on December 8, 2015 (73% support)
Park East, Construction Manager
Multi-Year Capital Plan
What is a Change Order? A change order is a change to the original planned/bid
work on a particular project.
Change orders typically result from unforeseen issues that are uncovered and/or opportunities to address specific unanticipated items in a cost effective way.
Examples from recent and past work: Cement pad under track/field bleachers at KPHS
Additional irrigation at KPHS
Additional parking and stairs at San Remo
Additional paving and cement island at WTR
Additional cement sidewalks at PV
Phase 1 Work Estimated Cost
Budget Contract Award/CO Variance
Asphalt/MS $490,500 $693,785 - $203,285
Flooring/MS $239,800 $109,737 +$130,062
Turf Field-Track-FI-GS/HS
$2,207,250 $2,574,380 -$367,130
Roof-Gym/HS $4,170,449 $3,140,762 +1,029,687
Asphalt/SR $610,400 $644,173 -$33,773
Flooring/SR $156,960 $86,381 +$70,579
Asphalt/FS $599,500 $330,870 +$268,630
Flooring/FS $408,750 $261,182 +$147,568
Fuel Pump/Transportation
$54,500 $240,390 -$185,890
Total $8,938,109 $8,216,078 +$722,031
Phase 2 Work
Estimated Cost
Budget
Contract Award/CO
Variance
Track Field Lighting/HS $545,000 $616,770 -$71,770
Media Center/HS $872,000 $1,532,052 -$660,052
HVAC/HS $828,400 $1,480,395 -$651,995
Auditorium/HS $129,710 $276,761 -$147,051
ED/Switchgear $436,000 $1,148,000 -$816,020
Asphalt/PV $790,250 $416,306 +$373,943
Flooring-Ceiling/PV $340,080 $474,483 -$134,403
ED-Switchgear/PV $190,750 $326,251 -$135,501
Bathroom Renovation/PV
$283,400 $354,534 -$71,134
Phase 2 (Continued) Work
Estimated Cost
Budget
Contract Award/CO
Variance
Asphalt/RJO $413,110 $440,727 -$27,617
Flooring/RJO $425,100 $175,758 +$249,341
Auditorium Upgrade/RJO
$136,250 $211,019 -$74,769
Ceilings/RJO $337,900 $525,675 -$187,775
ED-Switchgear/RJO $163,500 $288,123 -$124,623
Drainage/FS $78,018 -$78,018
Total $5,891,450 $8,448,898 -$2,557,448
Phase 3 Work
Estimated Cost
Budget
Contract Award/CO
Variance
Locker Room/MS $245,250 $206,622 +$38,628
Irrigation/MS $81,750 $83,610 -$1,860
*Roof/MS $5,177,500 1,000,000 +4,177,500
Comfort Station/HS $490,500 $430,653 +$59,847
Asphalt/HS $735,750 $570,800 +$164,950
HVAC/PV $635,470 $430,000 +$205,470
Total $2,188,720 $2,705,571 $4,660,648
* The WTRMS roof was only partially completed due to the discovery of asbestos on the upper roof area.
Phase Totals Work
Estimated Cost Budget
Contract Award/CO
Variance
Phase 1 $8,938,109 $8,216,078 +$722,031
Phase 2 $5,891,450 $8,448,898 -$2,557,448
Phase 3 $7,366,220 $2,705,571 +$4,660,648
*Total $22,195,779 $19,370,548 +$2,825,231
*Again, the WTRMS roof still needs to be completed next summer. To date, we have spent $1M on the lower portions of the roof, with the upper portions, where asbestos was found, still in need of completion.
Why Were the Construction Awards & Costs Higher Than Budgeted Amounts?
Delays in state approval resulted in aggressive and truncated timelines, which may have increased vendor bid amounts in Phase 2.
Initial H2M cost estimates on some projects missed the mark.
Increase in construction costs (increased demand). With school district construction at an all time high in this region, supply & demand has pushed prices up.
“This old house” – our facilities are old and in some cases we have uncovered items that need of a bit more attention than originally planned. This increased the scope of some projects.
The SED review process often requires changes and/or additional items that were not in the original plans/budget i.e. media center.
Additional work was needed at FS and HS to address drainage issues.
How do we Plan on Addressing These Cost Overages?
ALL remaining projects have already been approved at the NYS level. This should eliminate pricing issues related to timelines.
We are reviewing work that can be done in-house and reducing scope of some projects.
We may need to consider less change orders and project “adds” moving forward.
Continue to rebid or redesign projects certain projects to keep costs down i.e. Comfort Station
We may need to consider omitting some work at San Remo where we do not benefit from building aid.
If needed, the district has a Capital Reserve and remaining EXCEL money on the order of $1.2M. While we would only use this money as a last resort, it is there if we need it.
Current Work
Door & Lock Replacement – FS/PV
Bathroom Renovations – KPHS
Vestibules – KPHS/WTRMS (not funded through Bond Budget)
Preliminary Plans for Summer ‘19
Locker rooms/KPHS
Roof/WTRMS
Windows/WTRMS
Bathrooms/RJO-FS
Roof/FS (Not Bond)
Track/RJO (Not Bond)
KPCSD PRIDE
Athletics
Heritage
Museum
Transportation
Aides & Security
WTRMS
Teachers
Special Education
kpHS
Clericals
Fort Salonga
PTA
TA’s & Nurses