Facilities Report. Zionsville Community Schools. Facilities & Grounds Overview by the Numbers. Acres—558 Farm Lease--200 Buildings—11 School Buildings—8 3 Secondary, 5 Elementary 5 have been constructed since 2001 - PowerPoint PPT PresentationTRANSCRIPT
Facilities Report
Zionsville Community Schools
Facilities & Grounds Overviewby the Numbers
Acres—558• Farm Lease--200
Buildings—11• School Buildings—8
o 3 Secondary, 5 Elementaryo 5 have been constructed since 2001o Each of the remaining 3 have had significant refurbishing since no later
than1998• Support Buildings—3• SF Under Roof--1,654,012
Maintenance and Grounds Employees—11 Custodians—43
• Ratio of SF to Custodian o Industry Average—26,000-28,000o ZCS—40,347
Peer District
•20 maintenance
•60 custodians
Facilities & Grounds Overviewby the Numbers
17
K-4 1955 1999 76,670 13
100,265K-4 2007 N/A
Site Area (in Acres)Facility Name and Location Grades
HousedInitial Year of Construction
K-4 1983 1998 189,347 14
Bldg. Sq. Footage
Latest Major Addition or Renovation
15
PK 2003 N/A 97,450 15
K-4 2005 N/A 97,450
775-8 2007 N/A 290,418
1970 2005 457,892 68
51283,811N/A2001
1998
1938
N/A
1977
N/A20,51520011978
10,868
29,726
2
20
Pleasant View Elementary
Eagle Elementary School
Union Elementary School
Stonegate Elementary School
Boone Meadow Elementary School
N/A
N/A
Zionsville West Middle School
Zionsville Middle School
Zionsville Community High School
Educational Services Center
ZCS Transportation Center
N/A
9-12
5-8
ZCS Maintenance Center
ZCS Facilities
Essential Questions
1. How do we pay for the upkeep of our facilities?
2. What are our needs?
3. What are our plans to pay for these needs?
4. Are we adequately accommodating student enrollment?
31.5%
9.3%
10.4%
5.6%
22.2%
21.0%
2013 Capital Projects Fund - Estimated Expenditures
Salaries & Benefits
Energy Savings Contracts
Other Purchased Services
Equip. Supplies & Materials
Building Capital Maint.
Building Utilities & Property Ins
2008 2009 2010 2011 2012 2013 $-
$500,000.00
$1,000,000.00
$1,500,000.00
$2,000,000.00
$2,500,000.00
$3,000,000.00
$3,500,000.00
$4,000,000.00
$4,500,000.00
$5,000,000.00
$5,500,000.00
$6,000,000.00
$6,500,000.00
CPF ExpendituresHistorical Data 2008-2011Estimated 2012 and 2013
Utilities & Property InsCapital Maint.Supplies & MaterialsPurchased ServicesSavings ContractsSalaries & Benefits
2008 2009 2010 2011 2012 2013 $-
$250,000.00
$500,000.00
$750,000.00
$1,000,000.00
$1,250,000.00
$1,500,000.00
$1,750,000.00
$2,000,000.00
$2,250,000.00
Building Capital Maintenance Expenditures
2010 2011 2012 2013 2014 $-
$500,000.00
$1,000,000.00
$1,500,000.00
$2,000,000.00
$2,500,000.00
$3,000,000.00
$3,500,000.00
$4,000,000.00
Circuit Breaker CreditsActual 2010 - 2012
with Est. Per Umbaugh Study 2013-2014
Actual 2010 -2012
2010 2011 2012 2013 2014 $-
$500,000.00
$1,000,000.00
$1,500,000.00
$2,000,000.00
$2,500,000.00
$3,000,000.00
$3,500,000.00
$4,000,000.00
Circuit Breaker CreditsActual 2010 - 2012
and Estimated (Per Umbaugh Study)2013-2014 with Net Loss after Debt Restructuring
Actual 2010 -2012
Net Loss after Debt Restruc-turing
Umbaugh Study's Projec-tion
2008 2009 2010 2011 2012 2013 $-
$250,000.00
$500,000.00
$750,000.00
$1,000,000.00
$1,250,000.00
$1,500,000.00
$1,750,000.00
$2,000,000.00
$2,250,000.00
Building Capital Maintenance Expenditures
Prioritizing Needs
Criteria• Safety and Security• Regulatory Compliance• Structural Integrity
Stratified Approach to Timing Preventative Maintenance and Safety Immediacy Long term
Stratified Approach to Needs
1. Preventative Maintenance & Safety Items• Maintenance Agreements (Boilers, Chillers, Etc.)• Bleacher and Playground Inspections & Maintenance• Parking Lots• High Voltage Inspections & Maintenance• Emergency Shutdown Systems• Gym Floors• Painting• Mandated Upgrade of Radio Communication System
2. Immediate Needs• Roof (ZCHS) • Carpet• Technology--Backup for MDF (ZCHS)• Technology– Cooling System for MDF• Foundation Repairs at Eagle• Athletic Facilities Repairs• Fire Alarm Upgrades• Repair/Maintain Sewage Lift Station (BME)
3. Long Term Needs• Upgrades to Water Heaters• Installation of UV Units for HVAC• Software and Hardware Upgrades for HVAC Controls• Boiler Upgrade/Replacement (PVE)• Upgrade Fire Suppression System (PVE)• Foundation Remediation (EE)• Security Access System (Trans)• Equipment and Vehicle Upgrades or Purchases (Maintenance)
Stratified Approach to NeedsStratified Approach to Needs
Focus on ZCHS Roof
Approach—Avoid Incurring Debt Through Phased Process• 3 Priority Based Phases
o Phase 1—2012-13 40% of Project Bid Process Fall 2012 Implementation Spring/Summer 2013
o Phases 2—2013-14 40%
o Phase 3—2014-15 20%
Building Capacity—Potential Concerns
2009-2010 2010-2011 2011-2012 2012-2013 2013-2014 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019
Grades PK-4 PK-4 PK-4 PK-4 PK-4 PK-4 PK-4 PK-4 PK-4 PK-4Capacity 3,167 3,167 3,167 3,167 3,167 3,167 3,167 3,167 3,167 3,167
Enrollment 2,102 2,215 2,306 2,433 2,476 2,498 2,562 2,629 2,704 2,784% Capacity 66% 70% 73% 77% 78% 79% 81% 83% 85% 88%
Grades 5-8 5-8 5-8 5-8 5-8 5-8 5-8 5-8 5-8 5-8Capacity 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000
ZMS ZMS ZMS ZMS ZMS ZMS ZMS ZMS ZMS ZMS
Enrollment 1,767 1,770 1,846 1,927 2,006 2,042 2,088 2,135 2,195 2,332% Capacity 59% 59% 62% 64% 67% 68% 70% 71% 73% 78%
Grades 9-12 9-12 9-12 9-12 9-12 9-12 9-12 9-12 9-12 9-12Capacity 2,025 2,025 2,025 2,025 2,025 2,025 2,025 2,025 2,025 2,025
Enrollment 1,725 1,752 1,795 1,813 1,820 1,866 1,933 2,029 2,124 2,155% Capacity 85% 87% 89% 90% 90% 92% 95% 100% 105% 106%
8,192 8,192 8,192 8,192 8,192 8,192 8,192 8,192 8,192 8,1925,594 5,737 5,947 6,173 6,302 6,406 6,583 6,793 7,023 7,27168% 70% 73% 75% 77% 78% 80% 83% 86% 89%
Zionsville Community Schools2009 IBRC Enrollment Projection and Current Capacities
Updated with Actual 2009-2010, 2010-2011, and 2011-2012 Enrollments
Actual Projected
Elem
enta
ryM
iddl
eHi
gh S
choo
l
Total CapacityResident Enrollment% Capacity
ZCHS at 1,839as of 8/1/2012
This EXCEEDS 2013 projection
Capacity Pinch Points:ZCHS and
Stonegate Elementary
2006 2007 2008 2009 2010 2011 2012400
450
500
550
600
650
700
Stonegate Elementary School History of Enrollment
Since Last Population Balancing
Building Capacity Pinch Points
Stonegate Elementary School• 663 Students—110%• Space is maximized• Gained 34 students during last school year
o Present Class Size --metric/+3 across grades • Timeline for action
o December 2012/January 2013—Acquire/Review Demographic Studyo February-March 2013—Gather Optionso April—Recommend Action to School Board
Zionsville Community High School• 1,839 Students—91%• Possible Approaches—Leadership Imperative: No new debt!
• Possible alternatives (perhaps in combination)• Additional space at ESC (ESC moves to another location)• Additional space at Pleasant View Elementary• Creative scheduling/calendaring• Hybrid courses/online coursework• Three-year graduate initiative (Mitch Daniels Scholarship)
• Timeline—• Present—Internal discussions ongoing• December 2012-January 2013—Review Demographic Study• Fall 2013—Formalize Discussions• Target to Initiate Solutions—2014
Building Capacity Pinch Points
1. How do we pay for the upkeep of our facilities? • From the Building Capital Maintenance slice of the CPF
2. What are our needs?• Needs are prioritized based upon established criteria. Debt avoidance is
accomplished through this stratified approach and the phasing of large ticket items such as the HS roof.
3. What are our plans to pay for these needs?• Take advantage of the mitigation of circuit breaker loss made possible by the debt
restructuring in 2013-2015.
4. Are we adequately accommodating student enrollment?• Yes, but the over capacity at SGE and the nearing capacity at ZCHS must be
addressed, thus this foreshadowing of planning activities
Essential Questions
Facilities Report
Zionsville Community Schools
BUILDING ITEM EST. COST
ZCHS High voltage switch gear inspection, repairs, and maintenance 13,500.00$ (Includes Freshman Center) Repair/replace hallway automatic gate 7,000.00$
Bleacher inspection/maintenance 17,000.00$ Inspection/maintenance of lift station 1,000.00$ Roof replacements (40% of total area) 620,000.00$ Hallway Carpet Repairs and replacements 20,000.00$ Replace/repair duct work on roof 15,000.00$ Install A/C Back-up for the MDF 10,000.00$ Install emergency back-up power for the MDF 15,000.00$
Subtotal - Zionsville Community High School 718,500.00$
ZMS High voltage switch gear maintenance 7,000.00$ Indoor/Outdoor bleacher inspection/maintenance 5,000.00$ Track repairs/resurfacing 50,000.00$
Subtotal - Zionsville Middle School 62,000.00$
ZWMS High voltage switch gear maintenance 7,000.00$ Generator inspection/service 3,000.00$ Bleacher inspection/maintenance 5,000.00$ Playground inspection, repair, and mulch 5,000.00$
Subtotal - Zionsville West Middle School 20,000.00$
Stonegate High voltage switch gear inspection/maintenance 2,500.00$ Parking lot maintenance & striping 15,000.00$ Playground inspection, repair and mulch 2,000.00$ Bleacher inspection/maintenance 2,000.00$
Subtotal - Stonegate Elementary School 21,500.00$
Eagle High voltage switch gear inspection/maintenance 4,000.00$ Investigate water issue in basement 30,000.00$ Parking lot maintenance & striping 10,000.00$ Playground inspection & maintenance 2,000.00$
Subtotal - Eagle Elementary School 46,000.00$
Union High voltage inspections/maintenance 4,000.00$ Bleacher inspection/maintenance 2,000.00$ Parking lot maintenance & striping 20,000.00$ Playground inspection, maintenance and mulch 5,000.00$
Subtotal - Union Elementary School 31,000.00$
PVE High voltage switch gear maintenance 4,500.00$ Tuck pointing boiler stack PVEU 3,000.00$ Parking lot maintenance & striping 22,500.00$ Playground inspection, repair, and mulch 5,000.00$
Subtotal - Pleasant View Elementary School 35,000.00$
Boone Meadow High voltage switch gear inspection/maintenance 4,000.00$ Inspection/maintenance of two lift station pumps 8,000.00$ Playground inspection, repair, and mulch 2,000.00$ Bleacher inspection/maintenance 2,000.00$
Subtotal - Boone Meadow Elementary School 16,000.00$
Transportation Center High voltage inspection/maintenance 2,000.00$
Subtotal - Transportation Center 2,000.00$
TOTAL - ALL FACILITIES 952,000.00$
Zionsville Community Schools2013 Capital Projects Budget
Priority List for Facilities