Facilities Update governing Board meeting. San marcos unified school district February 10, 2014. F acilities Update: In Construction. Woodland Park MS Modernization Project: Mar 2014* Modernize two (2) classrooms Remodel Administration Building - PowerPoint PPT PresentationTRANSCRIPT
S A N M A R C O S U N I F I E D S C H O O L D I S T R I C T
F E B R U A R Y 1 0 , 2 0 1 4
FACILITIES UPDATEGOVERNING BOARD MEETING
2
Facilities Update: In Construction
• Woodland Park MS Modernization Project: Mar 2014*• Modernize two (2) classrooms• Remodel Administration Building
• Twin Oaks HS Modernization Project: Completed• Remodel Administration Building
• Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Feb 2014*• Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – July 2014*
• NCREC – South: August 2014*• Professional Development and Centralized Kitchen
• Carrillo ES: Modernization Project: Apr 2014*• Modernize two (2) classrooms to add restrooms
*Note: Scheduled Completion Dates2/10/2014
3
Facilities Update: Woodland Park MS
Classroom Modernization and
Expansion
2/10/2014
4
Facilities Update: Woodland Park MSNew Restrooms
2/10/2014
5
Facilities Update: Woodland Park MS
Student Support Services2/10/2014
6
Facilities Update: Woodland Park MS
Conference Room and Student Support Services2/10/2014
7
Facilities Update: Woodland Park MS
Student Support Services2/10/2014
8
Facilities Update: Twin Oaks HS
Administrative and Student Support Services
Before
AFTER
2/10/2014
9
Facilities Update: Twin Oaks HS
Administrative and Student Support Services2/10/2014
10
Facilities Update: Twin Oaks HS
Administrative and Student Support Services2/10/2014
11
Facilities Update: District-wide
I.T. Infrastructure Project• Phase 1: 4 campuses
• MHHS, DO, LCM, PAL • Feb. 2014 completion
• Phase 2: 4 campuses• Design complete• Bid February 2014• Complete July 2014• KH, RL, SEMS, TOES
• Working on E-rate projects (additional Federal funding)
2/10/2014
12
Facilities Update: NCREC - South
Professional Development and Centralized Kitchen Project
• 3 Classrooms for Professional Development
• 1 Portable Kitchen (from San Marcos High School Temporary Campus)
2/10/2014
13
Facilities Update: NCREC - South
2/10/2014
14
Facilities Update: Carrillo ES Mod.
Existing
Remodel
2/10/2014
15
Facilities Update: Carrillo ES Mod.
2/10/2014
G O V E R N I N G B O A R D M E E T I N G
F E B R U A R Y 1 0 , 2 0 1 4
FACILITIES UPDATE:THANK YOU!