fact sheet brac parcel 114 world war ii …fgacleanup.info/content/files/factsheets/brac114...
TRANSCRIPT
“Always on Guard Defending Freedom”
BRAC Site 114 Page 1 of 5 Revised May 19, 2017
FACT SHEET
BRAC PARCEL 114
WORLD WAR II TENT AREA
FORT GREELY, ALASKA
1.0 INTRODUCTION
This fact sheet describes the site generally known as the World War II Tent Area, located at Fort
Greely, Alaska (FGA). The site was investigated under the Base Realignment and Closure (BRAC)
program as Parcel 114. The following database identifications apply to this site:
• Army Environmental Database – Restoration – FGLY-005-R-01 and FGLY-0060
This site consists of a former bivouac training area located within approximately 40 acres of the
South Undeveloped Area (identified as former BRAC Parcel 1). The site consists of six clearings in
the forested area that was historically used as a bivouac training area during World War II (WWII).
In 2000, a fire went through this area. In 2008, during clearing and grubbing operations, site
personnel discovered a 4.5-inch rocket, still in its shipping canister, with explosive filler, lying on the
ground surface. All site clearing activities were stopped so that a Fort Richardson, Alaska Explosive
Ordnance Disposal (EOD) team could remove the Munitions and Explosives of Concern (MEC)
item. Afterwards, FGA elected to conduct a full unexploded ordnance (UXO) sweep of the area, to
provide MEC clearance, prior to allowing further clearing and grubbing operations to proceed.
Since the 2008 sweep, multiple investigations and clearance activities have been conducted at the
site. These investigations are described in greater detail below. Currently, the entire site area is
cleared of brush/trees, as vegetation removal was required to safely conduct MEC clearance
activities.
2.0 SITE LOCATION
The site is located approximately as follows:
Coordinates (Universal Transverse Mercator, Zone 6
North, North American Datum 1983):
Northing: 7093973 meters
Easting: 561768 meters
Physical Address:
The site is located south of Big Delta Avenue, near
the main gate of Fort Greely. To access the site,
head east on Big Delta Avenue. Turn right onto
Robin Road and head south. Pass through the
security gate and head west on a dirt road. Access to this area is restricted and must be
coordinated with the Sergeant of the Guard.
“Always on Guard Defending Freedom”
BRAC Site 114 Page 2 of 5 Revised May 19, 2017
3.0 DESCRIPTION AND FINDINGS OF SITE WORK
3.1 Listing of Documents with Site Information
The following documents contain information about this site:
• Final U.S. Army Base Realignment and Closure 95 Program, Environmental Baseline Survey
(EBS) Report, Fort Greely, Alaska. Woodward-Clyde Federal Services (WCFS), January
1997 (Table 5-1a). (WCFS, 1997).
• 1998 Remedial Investigation Report, Final, Fort Greely, Alaska. Jacobs Engineering Group,
Inc. (Jacobs), April 1999 (Table ES-1, page ES-7, Section 28.0, pages 28-1 and 28-2).
(Jacobs, 1999).
• Environmental Sites Decision Document, Final, Fort Greely, Alaska. Teledyne Solutions,
Inc. (TSI), June 2005. (TSI, 2005).
• Final Site Inspection Report for Fort Greely, Delta Junction, Alaska. TLI Solutions, Inc.
February 2007. (TLI, 2007).
• 2008 UXO Sweep Letter Report, Fort Greely, Alaska. Environmental Compliance
Consultants (ECC), May 11, 2008. (ECC, 2008).
• Geophysical Survey to Identify Potential Munitions and Explosives of Concern (MEC), Fort
Greely Military Installation, Fort Greely, Alaska. ASTS, July 2010. (ASTS, 2010).
• Draft After Action Report for Munitions and Explosives of Concern Removal Action, WWII
Tent Area and Jarvis Creek MMRP Burial Site, Fort Greely, Alaska. (WHPacific, June
2014).
• Final Supplemental Site Inspection Report for Munitions and Explosives of Concern at WWII
Tent Area and Jarvis Creek MMRP Burial Site, Fort Greely, Alaska. Tetra Tech, January
2015. (Tetra Tech, 2015).
• Final Streamlined Remedial Investigation Report, WWII Tent Area, Fort Greely, Alaska.
Bering-Kaya Support Services (BKSS), April 2017. (BKSS, 2017a).
• After Action Report, Munitions and Explosives of Concern Remedial Action, WWII Tent Area
and Jarvis Creek MMRP Burial Site, Fort Greely, Alaska. BKSS, May 2017. (BKSS, 2017b).
3.2 Description of Site Characterization and Remedial Actions
In 1996, pursuant to FGA being selected for BRAC, an EBS was conducted to ascertain the
environmental condition of property for all surplus parcels on the installation. The EBS listed
Parcel 114 as a Community Environmental Response Facilitation Act Category 7 parcel, defined as
follows:
• Areas that are not evaluated or require additional evaluation.
The WWII bivouac area has not been used for more than 50 years. Based on EBS Table 2-1, Table 2-
5, and Table 5-1a, WCFS conducted interviews/visual inspections and reviewed aerial photographs.
According to EBS Table 2-5, a visual survey was conducted by automobile. The EBS indicated
practices may have involved hazardous substances, ammunition, or other unknown activities. The
EBS recommended additional evaluation, including soil sampling (WCFS, 1997).
“Always on Guard Defending Freedom”
BRAC Site 114 Page 3 of 5 Revised May 19, 2017
In 1998, Parcel 114 was evaluated further during the remedial investigation performed under BRAC.
Additional aerial photograph reviews and interviews were conducted. These suggested that activities
in the subject area were limited to troop maneuvers and use of small arms munitions. The identified
clearings appeared to be former bivouac sites. The investigation did not reveal potential contaminant
sources at Parcel 114, and an intrusive field investigation was not conducted.
The 2005 Environmental Sites Decision Document lists BRAC 114 as having low-level
contamination that does not require further cleanup. The site was conditionally closed as a No
Further Remedial Action Planned (NFRAP) site (TSI, 2005).
In 2008, during clearing and grubbing activities, a 4.5-inch rocket round (still in its shipping canister)
was discovered. Following the find, clearing and grubbing operations were put on hold and EOD was
summoned to remove the rocket round. In order to provide clearance for clearing and grubbing
operations to proceed, Environmental Compliance Consultants (ECC) performed a subsurface UXO
clearance/sweep of approximately 21 acres located in the southern portion of the WWII bivouac area
(BRAC Site 114). The clearance/sweep covered the majority of the southern portion of the site, plus
some adjacent areas outside the site boundary. The clearance was performed using Schonstedt
GA-52Cx® magnetometers. Each target anomaly detected was excavated using a hand shovel and
visually identified. Of the numerous items unearthed and examined during the clearance activity, two
MEC items were identified. These items consisted of two point-detonating (PD) rocket fuzes,
containing high explosives, which were removed by US Army EOD personnel. Other inert metal
items were also unearthed and removed. These included metal banding, stakes, shipping container
caps, and other miscellaneous metal debris (ECC, 2008).
In 2010, ASTS and Zapata Incorporated, Blackhawk Division (ZAPATA/Blackhawk) performed
digital geophysical mapping (DGM) to identify the potential presence of MEC within a 10-acre area
proposed for construction activities in the southern portion of the WWII bivouac area (BRAC Site
114). This 10-acre area was included in the 2008 clearance/sweep. The survey area was divided into
15 subareas and surveyed in one-meter sampling swaths using a single-coil Geonics EM61-MK2®
time domain electromagnetic metal detector. The results of this DGM survey identified 156 metallic
targets that required further investigation to determine if the targets were MEC/material potentially
presenting an explosive hazard (MPPEH) (ASTS, 2010).
In June 2014, the 156 identified targets were intrusively investigated. No MEC/MPPEH was
recovered during the intrusive investigation. All targets consisted of scrap metal (nails, tent stakes,
rebar, and construction debris). Although no MEC/MPPEH was recovered, two MEC items were
identified outside of the investigation area. The first item was a PD fuze, which was observed on the
ground surface by a UXO Technician. The item, specifically identified as a M48 PD fuze, was found
within the WWII Tent Area site extent, just north of the investigation area. Eielson Air Force Base
EOD was notified and, after further investigation by the responding EOD team, a second PD fuze
was found beneath the fuze previously identified by the UXO Technician. EOD then performed
blow-in-place operations to destroy both MEC items (Tetra Tech, 2015).
Between May-August 2016, additional activities were conducted to address potential MEC
contamination in the northern portion of the site that was not previously cleared. These activities
included a magnetometer-assisted surface sweep, vegetation removal, DGM survey, and intrusive
investigation of metallic anomalies identified during DGM survey. UXO Technicians performed a
surface sweep of the northernmost ~26 acres of the site to remove any surface MEC/MPPEH items
and larger metallic items that would interfere with DGM survey. Subsequently, vegetation removal
was conducted to ready the site for DGM survey. DGM survey was conducted in July 2016, using a
3-coil EM61-MK2 towed-array platform. Based on the DGM results, 1,359 metallic targets were
“Always on Guard Defending Freedom”
BRAC Site 114 Page 4 of 5 Revised May 19, 2017
intrusively investigated, resulting in the discovery of three additional PD fuzes (one M51 fuze and
two M48 fuzes), which were destroyed by Eielson Air Force Base EOD.
A map showing the cumulative clearance efforts is included below.
“Always on Guard Defending Freedom”
BRAC Site 114 Page 5 of 5 Revised May 19, 2017
3.3 Summary of Remaining Contamination
The studies conducted between 1998 and 2005 resulted in a 2005 Environmental Sites Decision
Document that lists BRAC 114 as having low-level chemical contamination that does not require
further cleanup.
The MEC investigation and clearance activities conducted between 2008 and 2017 resulted in the
complete removal of MEC and munitions debris. There is no remaining munitions contamination at
the site.
4.0 SITE STATUS
Between cumulative survey and clearance efforts conducted in 2008, 2010, and 2016, the WWII Tent
Area has been surveyed and cleared for MEC. There is a small portion (0.6 acre) of the site at the
extreme southern boundary that has not been actively cleared. Although not surveyed and cleared in
the same fashion as the other portions of the site, this 0.6-acre area has had all surface vegetation
removed and was previously re-graded as part of security perimeter measures for the missile field.
Based on the extreme shallow nature of all other MEC findings in the WWII Tent Area, any
abandoned MEC in this area would have been revealed during the re-grading/grubbing activities.
Prior to MEC clearance, the site was assigned Administrative Controls, which incorporated it into the
FGA Geographic Information System and dig permit process, to notify contractors, workers, and
base personnel of potential MEC hazards in this area during excavation activities.
The site is considered to be free of any residual MEC contamination caused by previous usage as a
bivouac training area and was recommended for closure to the Alaska Department of Environmental
Conservation in December 2016. ADEC granted site closure for the WWII Tent Area on
6 April 2017.