Failure reporting form Gas-insulated Switchgear and Circuit Breaker Operating Mechanism
Basic information
Component data
Name of installation: Customer name:
Date of incident: Contact person:
Country of installation: Telephone (mobile):
Equipment type: GIS Other E-mail address:
Voltage level [kV]:
Component type: ELK EXK ENK Other: Year of manufacture:
Voltage [kV]: Total circuit breaker operations [CO]:
Phase designation: Spare parts available: No Yes (attached to report)
ABB bay designation: Customer bay designation:
Complete reporting form as detailed as possible. Return the document to your service center.
Before incident: In service Out of service
After incident: In service Out of service
Operating status
Delivery address spare parts
Attachments
Company name:
c / o: State:
Street: Country:
Postcode: Contact person:
City: Telephone:
Pictures Event log Layout scheme (with marked-up failure location)
Gas analysis Customer report Other
Supply additional documents as attachment to failure reporting form.
C
opyr
ight
ABB
Sw
itzer
land
Ltd
, 1H
C00
8887
4 E0
1 / A
D14
Failure type a) Dielectric failure b) Operating mechanism failure c) Gas leakage
d) Software / electronic part Pneumatic system (LTB / AIS only) Other (specify in event description)
Drive type: AHMA HMB HMC Other:
Serial number: Visible oil leakage: No Yes
Pump start frequency [starts / day]: Switch position: Open Closed
Total drive operations since commissioning [CO]: Drive operations since last maintainance [CO]:
Total pump starts since commissioning [CO]: Pump starts since last maintenance [CO]:
Gas compartment designation: Failed component:
Gas pressure [kPa]: absolut relative Date measured:
Failure location: LCC Operating mechanism Control room
c) Gas leakage
d) Software / electronic part failure
b) Operating mechanism failure
Event description
Short circuit current duration [ms]: Rupture disc activated: No Yes
Short circuit current [kA]: Gas analysis available: No Yes (attached to report)
Event log available: No Yes (attached to report)
a) Dielectric Failure
ABB Switzerland LtdService High Voltage ProductsBrown Boveri Strasse 58050 Zurich / Switzerland
24-hour Call and Support CenterPhone: +41 844 845 845E-mail: [email protected]
ABB AG GermanyService High Voltage ProductsKallstadterstrasse 168309 Mannheim / Germany
24-hour Call and Support CenterPhone: +49 180 6222 007E-mail: [email protected]
ABB China (Xiamen) LtdSite and After Sales Service 6# Chuangxin 3rd Road361006 Xiamen / P.R.China
24-hour Call and Support CenterPhone: +86 18150895781E-mail: [email protected]
Send form to responsible service center:
1: 2: 3: 4: 5: 6: 7: 8: 9: 10: 11: 12: 13: 14: 14b: 15: 16: 17: 18: 19: 20: 21: 22: 23: 24: 25: 26: 27: 28: 29: 30: 31: 32: 33: 34: 35: 36: 37: 38: 39: 40: 41: 42: 43: 44: 45: 46: 47: 48: 49: 50: 51: 52: 53: 54: 55: 56: 57: 58: 59: 60: 61: 62: 63: 64: 65: 66: 67: 68: 69: 70: 71: 72: 73: 74: 75: 76: 77: 78: 79: 80: 81: Submit to CH: Submit to DE: Submit to CN: Print: ?: Serial-No: