Fanning Outdoor Recreation Facility. Conceptual Plan Final report (draft) Presented by Stan Kochanoff & Tracey Tomlik. Stakeholders The Strait Regional School Board The NS Department of Health & Protection The Municipality of Guysborough Preliminary ‘shopping list’ 8km trail loop - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Fanning Outdoor Recreation Facility

Fanning Outdoor Recreation Facility

Conceptual PlanFinal report (draft)

Presented byStan Kochanoff & Tracey Tomlik

Page 2: Fanning Outdoor Recreation Facility

• Stakeholders– The Strait Regional School Board– The NS Department of Health & Protection– The Municipality of Guysborough

• Preliminary ‘shopping list’– 8km trail loop– Campsites – Outdoor classroom & shelter– Low ropes initiative course– Bird Blind– Interpretive signage– Access route to Lake & Canoe launch area

Page 3: Fanning Outdoor Recreation Facility

• Final Report– Conceptual Plan

• Showing in plan view where design elements are located

– Three Phased developmental approach• Organizing design elements into four separate projects

– Cost Estimates• Presenting expected cost associated with each design

element

Page 4: Fanning Outdoor Recreation Facility

• Bird Observation• 8km Trail• Group Campsites• Tree-Go• Outdoor Classroom• Teaching Garden• Soccer Field• Walking Track• Green Gym• Access Road• Canoe Launch

Page 5: Fanning Outdoor Recreation Facility

• Phase One– Establishing a Trail system– Two group campsites– Interpretive signage – Regulation Soccer Field– Access Road/ Turning circle

& parking– Canoe launch site

• Total Cost– $82,374 - 95,824

Page 6: Fanning Outdoor Recreation Facility

• Establishing a Trail System– 8kms of trail

• Yellow route (1km)• Blue route (2km)• Red route (5km)

• 8kms of trail – $2,500/km

• Total– $20,000

Page 7: Fanning Outdoor Recreation Facility

• Group Campsites (2)– (1) family camping

• Trail ($625)

• Picnic tables (2@$150)

• Fire pit (2@$100)

• Waste bins (2@$125)

– (2) Wilderness camping• Trail ($750)

• Fire pit ($100)

• Total– $ 2,225

11

2

Page 8: Fanning Outdoor Recreation Facility

• Interpretive Signage– Wooden signs– Describing local ecology– Showing direction

• Cost Estimate– 3 Large ($1,500)– 15 Small ($50 - 100)

• Total– $5,250 - 6,000

Page 9: Fanning Outdoor Recreation Facility

• Soccer Field (300 x 180ft)

– Extension • $15 - 20,000

– Bleachers ($4,800)– Benches ($600)– Nets ($5,300)– Fencing (behind nets)

• $14,400

• Total– $32,900 - 45,100

• Annual Maintenance– Lime (20lb/1000sqft)

• $135

– Fertilizer (10lbs/1000sqft)• $259

– Aeration • $480

• Total– $874

Page 10: Fanning Outdoor Recreation Facility

• Lake Access Road– Expanding the current

path to 11ft wide

• Cost Estimate– Excavating

• $810

– Class A Gravel• $6,480

– Ditching• $4,500

• Total– $11,790

Page 11: Fanning Outdoor Recreation Facility

• Turning point & temporary parking– 35ft Radius– 2@20x10 parking spots

• Cost Estimate– Fill

• $1,180

– Excavating• $295

– Class A Gravel• $2,360

• Total– $3,835

Page 12: Fanning Outdoor Recreation Facility

• Canoe Launch Site– Clearing rocks to create

a launching site– Constructing a dry dock

• Cost Estimate– Lake dragging ($3,000)– Dock ($2,500-3,000)

• Total– $ 5,500 - 6,000

Page 13: Fanning Outdoor Recreation Facility

• Phase Two– Bird Observation– Outdoor classroom

shelter– Teaching garden– Tree Plantings

• Total Cost– $40,524 - $45,524

Page 14: Fanning Outdoor Recreation Facility

• Bird Observation Tower– An offshoot of the

yellow hiking trail• 0.3km ($750)

– Observation platform• 256sqft footprint

– $12 - 15,000

• Total– $ 12,750 - 15,750

Page 15: Fanning Outdoor Recreation Facility

• Outdoor classroom– Shelter with no walls

• 1,600sqft

– Long table with benches– Location is flexible right

now

• Cost Estimate– Excavating ($90)– Class A gravel ($720)– Materials

• $8 - 10,000

• Total– $8,810 - 10,810

Page 16: Fanning Outdoor Recreation Facility

• Two possible locations

Page 17: Fanning Outdoor Recreation Facility

• Teaching garden (900sqft)

– Food production– Wildlife habitat

• Cost Estimate– Excavating ($50) – Soil ($200)– Compost ($250)– Gravel ($120)– Fence ($9,100)

• Total– $9,720

* Excluding the cost of plant material

Page 18: Fanning Outdoor Recreation Facility

• Tree Plantings– Soccer Field (10)– Playground (3)– Grassed slope (9)

• Cost Estimate– 5ft Evergreen

• $368 (8)

– 60mm Deciduous• $450 (14)

• Total– $9,244

Page 19: Fanning Outdoor Recreation Facility
Page 20: Fanning Outdoor Recreation Facility

• Phase Three– Walking Track– Green Gym Outdoor

Fitness Centre– Aerial Adventure

Course (Tree-Go)

• Total Cost– $74,235 - $84,235

Page 21: Fanning Outdoor Recreation Facility

• Walking Track– Located on the perimeter

of the soccer field– Walking & jogging for all

ages

• Cost Estimate– Excavation

• $335

– Track base (67cuyd)• Crusher dust ($3,900)

• Total– $4,235

Page 22: Fanning Outdoor Recreation Facility

• Outdoor Gym system– Green Gym (5units)– Stations placed

along walking track– One designated area

• Total– $20,000

Page 23: Fanning Outdoor Recreation Facility

• Aerial adventure course– Tree-Go unit

• Demo Area• Kids Area• Main Course

– >10” Trees or use poles

• Total– $50,000 - 60,000

Page 24: Fanning Outdoor Recreation Facility

• Phase 1– $82,374 - 95,824

• Phase 2– $40,524 - 45,524

• Phase 3– $74,325 - 84,325

• Total Cost Estimate– $197,223 - 225,583

• Summary– Presentation

• Final Plan (draft)• Cost Estimate

– Public Feedback• Questions or

concerns• Discussions

Page 25: Fanning Outdoor Recreation Facility

We Thank You for yourFeedback