fba, fbe, fbt e 531 731mt.schneider-electric.be/op_main/fba/fba_531731.pdf · areva sachsenwerk...
TRANSCRIPT
T&D
MEDIUM VOLTAGE SWITCHGEAR
Operating Instructions
FBA,FBE,FBTGas-Insulated Ring Main Units up to 36 kV
Operating InstructionsNo. 531 731Edition 01/05
>>
Manufacturer:
AREVA Sachsenwerk GmbH
Rathenaustraße 2D-93055 RegensburgPhone +49 (0)9 41/46 20-0Fax +49 (0)9 41/46 20-418
Service:
Should you have any queries as toour service, please do not hesitateto contact:
AREVA Sachsenwerk GmbH
Service-CenterD-93055 RegensburgPhone +49 (0)9 41/46 20-777Fax +49 (0)9 41/46 20-778
©-2004-AREVA Sachsenwerk GmbH
IMPORTANT NOTE
The Operating Instructions, which are exclusively valid are always supplied by AREVA Sachsenwerk GmbHtogether with the product in question. Our products may only be commissioned, operated, serviced, repaired or decommissioned together with Operating Instructions which have been directly enclosed to the product inquestion by the factory.
On the other hand, these operating instructions are provided to the customer at his/her request for informationonly. None of our products may be commissioned, operated, serviced, repaired or decommissioned on thebasis of these operating instructions.
Non-compliance with this instruction may entail serious damage to the product, the objects pertaining to it, as well as a health hazard or mortal danger. AREVA Sachsenwerk GmbH shall not be held liable for any suchdamage.
3
1 Type 4
2 Rules and Regulations 5
3 Transport 6
4 Installation 7
5 High voltage connection 10
6 Low voltage wiring 14
7 Final work before commissioning 19
8 Operation 20
9 Work on the switchgear 25
10 Insulating gas, container 31
11 Admissible number of operations for the switch disconnectors 32
12 Appendix 33
Contents>>
These operating instructions applyto ring main units: • Type FBA for 12, 17.5,
and 24 kV• Type FBE for 36 kV• Type FBT (transformer switch
block) for 12, 17.5, 24, 36 kV
Type designation
The type designation of the type-tested ring main unit and trans-former switch block indicates the variant, rated peak withstand current,rated voltage, rated lightning impulsewithstand voltage and additionalequipment.
FBA 4 / 24 - 2 / 3001
Components fitted CCT
Rated lightning impulse
withstand voltage125 kV
Rated voltage24 kV
Rated peak withstand current
40 kA
Ring main unit
1 Type>>
4
Fig. 1Gas-insulated ring main unit type FBA/FBE
Fig. 2Transformer switch block FBT
Jack ring
Operating panel
Fuse attachment
High voltage connector withmounted cableplugs (not in-cluded in thescope of delivery)
Instrument recess
5
The switchgear is:• metal-clad • SF6-insulated• type-tested• tested for internal arcs (IEC
60298)• especially suited as ring main
unit for use in power transformerstations
• in compliance with the require-ments of the IEC publication62271-200.
• suited for normal service conditions in accordance with the DIN EN 60694 or IEC pub-lication 60694;for admissible additional condi-tions consult the manufacturer.
Breaking capacity of the switch dis-connector-fuse combination accord-ing to IEC 62271-105.
The feeders with fuses - if equip-ped with all-pole tripping - are in accordance with IEC 62271-105.
All relevant regulations, norms, rules,VDE recommendations and codeshave to be adhered to for transport,erection, assembly, connection andoperation.
Special reference is made to following regulations valid in the Federal Republic of Germany:- DIN EN 62271-200 or
IEC publication 62271-200- VDE 0101 (HD 6371 S1)- DIN EN 50110-1- DIN EN 62271-102 or
IEC publication 62271-102- DIN EN 60265-1 or
IEC publication 60265-1- IEC-Publication 61243-5- VDEW requirements for the
operation of switch disconnectorsystems
- “SF6 systems code“ of the indus-trial injuries insurance institution oflight- and electrical engineering
- accident prevention rules BGV A 2 of the industrial injuries in-surance institution of light- and electrical engineering
- connection and operational condi-tions of the local power supplier.
Users other than from Germanyshould - take the above regulations as
basis;- be in compliance with the local
regulations.
Apart from the mentioned regula-tions take also the following docu-ments into account:- Operating Instructions for the devi-
ces type “IVIS“ integrated in the instrument recess (no. 531 751);
- engineering document “Selectionof HV HRC fuse links for distribu-tion transformers” (no. 531 401)
- Assembly Instruction issued by the manufacturer of cable fittingsconnected to the switchgear;
- current list or Operating Instruc-tion issued by the fuse manu-facturer;
- engineering notes “Gas-insulatedring main unit FB up to 36 kV“;
- Operating Instruction for those devices integrated in the switch-gear (short-circuit indicator etc.).
Erection, assembly and wiring of the switchgear
must only be done by electri-cians!Operational reliability and ser-vice life depend on the expertexecution of the assemblyworks and correct operating.The notes included in theseOperating Instructions must be adhered to. Otherwise war-ranty claims may become nulland void.
For further queries and repeat ordersspecify the type of switchgear, yearof manufacture and serial number.
2 Rules and Regulations>>!
6
Transport of theswitchgear
Packing of the switchgear:• For truck transport, the switchgear
comes on a pallet wrapped withprotective PE foil. Two plasticstraps are used to fix the switch-gear.
• For sea transport the switchgearis wrapped with sealed aluminiumfoil and desiccant within a closedbox with solid wooden bottom.
• For air freight the switchgearcomes within a wooden crate withsolid wood bottom and insulatingair cushion foil as dust protectionor within wooden boxes also withsolid wood bottom.
For transporting the switchgearensure that the transport unit doesnot get out of place or tip over (if re-quired fix the transport pallet on theloading area by nails). If possibleleave the transport units packed. Repack parts for further storage thathave been unpacked for inspections.Use the original packing material.
Transport to the erectionsite
Store the equipment under admis-sible operational conditions. Avoidcondensation.
For transport, make sure that theswitchgear cannot get out of placelaterally (if required by supports).
When transporting the switchgear tothe erection site note that the mainweight is located in the upper part ofthe switchgear. A label at the side ofthe switchgear indicates the centerof gravity.
Transport with forklift truck:Carry the switchgear on pallet only.
Transport without pallet: Hook the crane gear into the jackrings at the unit. Angle at the cranegear > 45°.
3 Transport>>
Variant Width[mm]
FBT
FBA
2011 690
3000990
Height Depth[mm] [mm]
Weight[kg]
1315 725(1045)1
220 to 235460
FBA
30013002
1010
40004001 1330
FBA
4002400350005001
1315(1045)1
725
1315 725
300 to 350
400 to 415400 to 415
(1045)1 425 to 465425 to 465480510
FBT
50025003
1650
50042011 990
FBE
FBE
300030014000
1460
1315(1045)1
725
1700 865
530555580460
(1400)1
1700 865510560600
FBE
40014002
1930
50005001 240050025003
1700(1045)1
865
1700 865
650700700750
(1045)1 800850
Weights
Fig. 3Transport of unit with pallet
>450
Fig. 4Transport of unit without pallet
1) optional
7
Fig. 5Removing and reattaching the cable compartment or fuse cover
4 Installation>>1. Earthingswitch “ON”
2. Unlock, pulloff the key
Lock*
Remove
* When attaching the cover make sure that all hooks are inserted completely that they can be locked.
Attach
3. Lift the coverand remove it.
Frontside L-bars can beremoved panel by panelfor erecting, installationand wiring.
Requirements for theswitchgear room
Before erecting the switchgearcheck the switchgear room accor-ding to the data for civil work:- openings for high voltage cables
and low voltage cables, cableconduit if specified (see Figure 7and 8);
- stability of the fixing points mustcorrespond to the weight of theswitchgear (for weight informationsee section Transport on page 6).
Erection
The ring main units FBA, FBE andFBT come with switch disconnectorin “OFF” position, energy store re-leased and earthing switch in “ON”position.
The energy store must not be charged during erec-
tion, assembly and wiring - riskof injury!
Before placing the switchgear on its location check the even surfaceof the fixing points on the floor. Unevenness should only be 1 mm as a maximum. In case of larger unevenness place shims under the fixing points. For fixing the switchgear to the floor use screw connections M10with tightening torque 40±4 Nm.Make sure not to distort the switch-gear by the fixing screws.
Switchgear earthing
The earthing terminal is located inthe bottom part of the switchgear atthe left side wall.Treat the contact surfaces accordingto section 12.Connect the earthing terminal withthe earthing facility of the switch-gear building. Select cross-sectionand material of the earthing line according to IEC 62271-200 or national dimensioning rule.Tighten the screw connection M12with a tightening torque 70±7 Nm.The connection line is not includedin the scope of delivery.
8
!
Fig. 6Earthing
9
35E
GF
35D
22
H40
0
75
60
D
Fig. 7Fixing and floor openings
L3 L2 L1
pq
n
Fig. 8Required wall opening for angle entry-plugs
Variant D E F G H12 -24kV
FBT 2011
[mm]
620
[mm]
300
[mm]
646
[mm]
590
[mm]
615
FBA 3000
FBA 3001
FBA 3002
FBA 4000
940
940
940
620
940
1260
320
1260
966
966
590
590
966
1286
590
590
615
615
615
615
FBA 4001
FBA 4002
FBA 4003
FBA 5000
1260
1260
940
620
1260
1580
320
1580
FBA 5001
FBA 5002
FBA 5003
FBA 5004
1580
1580
1260
940
1580
1580
620
320
1286
1286
590
590
1606
1606
590
590
615
615
615
615
1606
1606
590
590
1606
1606
590
590
615
615
615
615
Variant36 kV
FBT 2011
D E[mm]
920
[mm]
520
FBE 3000
FBE 3001
FBE 4000
FBE 4001
1390
1390
1390
955
1860
1860
1860
1425
F G[mm]
946
[mm]
745
H[mm]
745
1416
1416
745
745
1886
1886
745
745
770
770
770
770
FBE 4002
FBE 5000
FBE 5002
FBE 5003
1860
2330
955
2330
2330
2330
1425
955
1886
2365
745
745
2365
2365
745
745
770
770
770
770
FBA/T FBE/TU(kV)
Mass n
12/17.5/24
120
36
170
Mass p
Mass q
30
310
75
370
For angle entry-plugs in the transformer feeder
For straight entry-plugs in the transformer feeder
Rear sideAt option
Required screw con-nection:min. M10 ø 15
If crossbeam – max. width 80
10
The switchgear is equipped with outside cone connection bushingsas standard.Standard variants:• Transformer feeder for FBA/FBT
up to 24 kV:connection bushing DIN EN 50181 connection type A(Ir: 250 A; plug contact 7.9+0.02/-0.05 mm)
• Transformer feeder for FBE/FBT36 kV:connection bushingDIN EN 50181 connection type B (Ir: 400 A; plug contact 14 0/-0.04 mm)
• Mains cable feeder for FBA up to 24 kV:FBE 36 kV:FBT up to 36 kV:connection bushing DIN EN 50181 connection type C(Ir: 630 A; screw contact with internal screw thread M16).
Further variants available on request.
Before assembling the cable plugs the outside
cone connection bushing mustbe cleaned free from greaseand silicone using detergents(see section 12).
When connecting the power supply cables and
especially the transformercable, make sure that the cablebushings are not exposed toany mechanical strain duringassembly or in assembledcondition.
Such strain may also occur subsequently and
be due to fasteners and finalwork on the concrete station.
Check the switchgear after havingcompleted assembly work accordingto Chapter 7 “Final work beforecommissioning”.
5 High voltage connection>>
!
!
!
Fig. 9Outside cone connection bushing
Cable 1
11
Nearly all common cable connectionsystems in solid insulation, metal-clador partial insulation variant for plasticor compound-impregnated cablesmay be attached to the ring mainunit.For partial insulated cable connec-tion systems a cable compartmentcover is compulsory needed for eachpanel.Only plastic cables (solid insulation)are used for the connection of thetransformer feeder (see HD 629.1 S1).For distances/insulation level consultthe manufacturer of the cable plugs! T-plugs are recommended for con-nection of cable feeders.
Use angle or straight entry-plugs for connection of the transformerfeeder. For this purpose change the positionof the cable holder (see Figure 12).
Tools and hardware (cable clamps,screws, conical spring washers etc.)for assembly of the cable connectionsystems (cable fittings) are not inclu-ded in the scope of delivery.
The front of the switchgear is accessible for the assembly of thecable connection systems. For thispurpose remove the front-side cablecompartment and fuse compartmentcovers (see Figure 5).
Strictly adhere to the assembly instructions
issued by the cable fittingmanufacturers (including tighte-ning torques) when assemblingthe cable connection systems.
Tighten the cable connection to theouter cone connection bushing(thread M16) only with a tighteningtorque 40±5 Nm as a maximum. Fortightening torque of the holdingscrews take the load carrying capa-city of the cable fittings into account(max. 10 Nm). Tighten the screw connections at thefixing bolts ø 4.5 mm hand-tight.
!
Fig. 10Metal-clad cable fitting, screw contact
Fig. 11Plug contact
Retaining plate
Do not loosen the screw connections.
20 - 35 mmthread reach
Fixing holes M8 for possible fixing of the T-plug (max. 10 Nm,thread reach 10 mm)
Fixing linkø 4.5 mm
Retaining plate
Before starting the work at the cables and prior to their connectionto the switchgear make sure that thecables are earthed.• Position the adjustable cable
holders as desired and fix them(horizontally and vertically ad-justable, screw connection M10with tightening torque 72±7 Nm).
• Screw contact: Adhere to the instructions issuedby the manufacturer.Slightly grease the external sur-face of the copper insert at theconnection bushing and the screw contact (see section 12).
• Plug contact: Adhere to the instructions issuedby the manufacturer.Slightly grease the external sur-face of the copper insert at theconnection bushing.Do not grease the plug contact!
• Place and align the enclosure according to manufacturer’sinstructions. Pay attention to parallelism.
• Attach the entry-plugs to the re-taining plate of the switchgearpanel according to manufacturer’sinstructions. Place the terminatinginserts and tighten them.
• Fix the cables by cable clamps(cable clamps are not included in the scope of delivery).
• Treat the contact surface of theearthing connections (plug enclo-sure and copper shield) accord-ing to section 12. Fix the earthconnection at the cable holderby screws M10 with tighteningtorque 40±4 Nm.
• Check the correct assembly of thecable clamps.
Adjusting the position of the cable holder and
fixing the cable is to be madeso that no additional forces actupon the connection bushing!
Fig. 12Transformer feeder with angle entry-plug (position of cable holder can be changed)
Fig. 13Mains cable connection: fixing of earth connection to the cable holder
Position of cableholder with straightentry-plugs
Switch panel seen from below
Cable conduit
Earth connection
Copper shieldof cable
Earth connection
Bushing
Power supply
Bushing
!
12
13
Additional retaining plates with hard-ware for overvoltage arrester anddouble cable connection are avai-lable from AREVA Sachsenwerk.
Where overvoltage arresters are usedthe switchgear is to be equippedwith additional retaining plates towhich fixing parts for overvoltagearresters can be attached.• Treat the contact surfaces for
earth connections according tosection 12.
• When assembling adhere to theovervoltage arrester manufactu-rer’s instructions!
Also for double cable connection itis necessary to attach two additionalretaining plates to which the secondcable holder can be screwed on depending to its position. • Fixing by cable clamps and earth-
ing as for single connection.• Treat the contact surfaces of the
earth connections according tosection 12.
• When assembling the entry-plugfollow the instructions given bythe manufacturer!
Cover non-used outside coneconnection bushings with voltage-proof terminating caps (not includedin the scope of delivery). The ma-nufacturers of cable connectionsystems offer such voltage-proofterminating caps.
Fig. 14Overvoltage arrester with separate earthing bar
Retaining plate
Retaining plate
Cable holder
Fig. 15Example: Double cable connection
The units situated inside the enclo-sing line are fitted in the ring mainunit as ordered and wired as for asthe terminal strip. Units outside theenclosing line are not supplied withthe switchgear.
The free switching elements of theauxiliary switch (S11) are set in thefactory as shown in the circuit dia-gram. Irrespective of the factorysettings, each element of the auxilia-ry switch may be set as break, makeor wiper contact.
The following is not included in thescope of delivery: - K1A contactor “OFF”- K1E contactor “ON”- S1A push button “OFF”- S1E push button “ON”
6 Low voltage wiring>>
14
Earthing switch Switch disconnector Short-circuit indicatorAuxiliary switch Auxiliary switch
Motor drive control Drive Motor
Off On DC ACAuxiliarycontacts
Transducer
FunctionShort-circuit indicator
1st feeder-H11
2nd feeder-H12
3rd feeder-H13
4th feeder-H14
5th feeder-H15
(terminals 8-12; special variant)Motor at switch disconnectorSwitch disconnectorEarthing switch
-M11 -M12-Q11 -Q81
-Q12 -Q82
-M13 -M14-Q13-Q83
-Q14-Q84
-M15-Q15 -Q85
Auxiliary contact at theearthing switch actuatorAuxiliary switch at switch disconnectorAuxiliary switch at earthing switch
-Q81-S51/52 -G82-S51/52
-S11-S81
-S12-S82
-Q83-S51/52 -Q84-S51/52
-S13-S83
-S14-S84
-Q85S51/52
-S15-S85
Example: Switchgear with five cable feeders
Appliance identifiers for mains cable feeder
Wiring diagram for mains cable feeder (Example: 1st feeder)
453
454
451311
314304
313303
302 452312
301
-H11
L1
L2
L3
N
L1
-Q81- S51
-Q81-S52
8 9 10
M
12 11
M84
10383
72 9244
-M11
14 14
104645244322412
-S81-Q81
91 43
43
44
11 11
-S1A
L -
L+
-K1E -K1E
-K1A
-S1E
K1A
-S11
645244322412
2412
6351433123112311
716351433123
23
24
11
11
12
-Q11
(L+) (L-)
-K1A -K1E
-M11
Terminals 11, 12for make HORSTMANN only- Type GAMMA for
auxiliary voltage 230 V AC- Type ALPHA E for
remote reset by DC voltage
Last change: 05.11.1999
Modifications reserved.
15
The units situated inside the enclo-sing line are fitted in the ring mainunit as ordered and wired as for asthe terminal strip. Units outside theenclosing line are not supplied withthe switchgear.
The free switching elements of theauxiliary switch (S13) are set in thefactory as shown in the circuit dia-gram. Irrespective of the factorysettings, each element of the auxilia-ry switch may be set as break, makeor wiper contact.
The following is not included in thescope of delivery: - K1A contactor “OFF”- K1E contactor “ON”- S1A push button “OFF”- S1E push button “ON”
Earthing switch Switch disconnector FuseAuxiliary switch Auxiliary switch
Tripping device Drive controlDriveMotor Auxiliary contact
Off Off On DC AC tripping
FunctionShunt opening release
1st feeder 2nd feeder-F12
3rd feeder-F13
4th feeder-F14
5th feeder-F15
Motor at switch disconnectorSwitch disconnector with fuse attachmentPush switch at fuse attachmentEarthing switch
-M12-Q12-Q12-S31/32-Q82
-M13-Q13
-M14-Q14
-Q13-S31/32-Q83
-Q14-S31/32-Q84
-M15-Q15-Q15-S31/32-Q85
Auxiliary contact at theearthing switch actuatorAuxiliary switch at the switch disconnectorAuxiliary switch at the earthing switch
-Q82-S51/52
-S12-S82
-Q83-S51/52 -Q84-S51/52
-S13-S83
-S14-S84
-Q85-S51/52
-S15-S85
Example: Switchgear with one cable feeder and four transformer feeders
Appliance identifiers for transformer feeder with integrated fuse attachment
Wiring diagram for transformer feeder with integrated fuse attachment (example: 3rd feeder)
453
454
451311
314304
313303
302 452312
301
N
L1
-Q83 -S52
-Q83- S51
-M13 MM84
10383
-Q13-S32
72
12
92 44
-M13
1414
1042145244322412
-S83-Q82
332 334 344342
91 43
43
44
1111
-S1A
L–
L+
-K1E -K1E
-K1A
-S1E
-K1A
-S13
40252443224122412
341
1)
331
-Q13 -S32
11
12 1414
-Q13 -S31
40151433123112311
71
11 11
12
2135143312311
11 23
2412
-Q12
(L+)
(L-)
-K1A -K1E
C1
C2-F13
2)
1) Not for motor drive,see current path ON!
2) Diode for DC only
Last change: 05.11.1999
Modifications reserved.
16
The switchgear may be equippedwith the following control devices or actuators:
Auxiliary switches S11-S15(switch disconnector)are simultaneously and positivelyactuated with the mechanical postionindicator ON-OFF by the correspon-ding switch disconnector. The auxiliaryswitches are set according to thewiring diagram (other settings arepossible - see page 17).
Auxiliary switches S81-S85(earthing switch)are also simultaneously and posi-tively actuated with the mechanicalposition indicator ON-OFF by thecorresponding earthing switch. Theauxiliary switches are set accordingto the wiring diagram (other settingsare possible - see page 17).
Push switches S31-S32are actuated by the fuse trip linkageat the integrated fuse attachment.
Optional:Motors M11-M15for actuation of the switch discon-nectors.
Shunt opening releases F12-F15
Rated voltage [kV] 12 17.5 24 36
Closing time (for motor actuation)
Opening time(for motor actuation)
[s] ≤ 6
[s] ≤ 0.7
≤ 3
≤ 3
Opening time for tripping device 160 W
Minimum command time “OFF”for trip. device 160 W
[ms] ≤ 34
[ms] ≤ 20
Arcing time (max. value)
Opening time T0
Motor charging time “ON”
Motor charging time “OFF”
[ms]
[ms]
15
38
[s]
[s]
≤ 6
–
–
–
15
–
≤ 3
≤ 3
Motor (power consumption) [W] 150 150 170
Transformer feederStored-energy drive SF
Mains cable feederSnap-action drive SFU
12 17.5 24 36
45
170
Ratedsupply voltage
VDC24 48 60 110 125
Starting current
Operating current
[A]
[A]
13.3
5.5
12.1
2.8
8.4
2.2
4.7
1.2
4.1
1.1
220VAC
120 230
2.5
0.6
6.8
2.2
3.7
1.2
Motor power consumption for SF- and SFU drives
Ratedsupply voltage
VDC24 48 60 110 125
Coil current [A] 6.3 3.2 2.6 1.3 1.2
220VAC
120 230
0.7 0.9 0.5
Magnet coil (160 W) power consumption for the shunt opening release (SF drive)
Switching times
Note:The values given are typical and can be used to dimension the auxiliary power supply. Deviations towards higher and lower values may be possible.
17
Auxiliary switches
The switch function is set in the factory according to the wiring diagram.
Switch disconnector in “OFF” posi-tion - energy store released.
Other switch functions of the auxilia-ry switch can be set by means ofadjustable cams.
• Remove the operating panel (loosen the screws).
• Set the desired switch function.• Re-engage the cams in the
catches.• Check that the cam is inserted in
the changed position.
Fig. 16 Auxiliary switch cam setting
Fig. 17 Possible switch functions of the auxiliary switches (switching program)
Switching device“OFF” “ON”
Auxiliary switch “ON”
Earlybreak contact
Latemake contact
Earlymake contact
Latebreak contact
Wiping contact
Cam position for setting procedure,switching device “OFF”
Cam
View orientation for setting
Ratedsupply voltage
VDC24 48 60 110 220
Switching capacity
Rated short-time current
Time constant T=L/R
Rated continuous current
[A] 8
100 A for a duration of 30 ms
[ms]
[A]
≤ 20
10
4 3 2 1
VAC120 230
10 10
–
Auxiliary switches
Connection of externalcontrol wires
Procedure:• Switch disconnector in “OFF”
position (see section 8)!• Earthing switch in position “ON”
(see section 8)!• Remove operating panel (loosen
the screws).• Remove cable compartment cover
of the cable feeder (see Figure 5).• Connect external control wires to
the terminal strips of the controldevices and actuators accordingto wiring diagram for each feeder.When laying low voltage cablesmake sure that there is sufficientdistance to movable drive parts.
The following wires may be con-nected:
- stranded wires up to 1.5 mm2 withend sleeve
- solid wires up to 2.5 mm2.• Reassemble the operating panel.• Reattach the cable compartment
cover of the mains cable feeder(see Figure 5).
18
Fig. 18Cable laying (external control wires) in the substructure and drive recess
19
High voltage must not beapplied. All active parts mustbe earthed.
Check:• Data on the rating plate against
the required characteristic data.• Rated supply voltage of the con-
trol devices and actuators.• Watch the red-green manometer
indication value (rated filling pres-sure, see section 10).
Check that the operatingability is not affected bytransport or assembly on site
• Operate the switching devices according to section 8.
• Watch the switch position indicators.
Check the cleaning andassembly work
• Cleaning of the switchgear fromdirt due to assembly work.
• Removing of all attached signs,notes, brochures and documentswhich are not longer needed.
• Tightening torques of all screwedconnections made on the site:- cable fitting at outside cone
connection bushing - earthing line- low voltage wiring.
• Phase position(line identifiers of connection bushing and cable must corres-pond to each other).
• Reassembly of all parts whichhave been removed during thework on the site.
Check the control circuits
• Apply the rated supply voltageand check the function of all elec-trical drives of the switching devi-ces.
• Inspect the wiring laid on site.
Insert the fuses
For this, see section 9.
Check the fuse tripping
For this, see section 9.
7 Final work before commissioning >>
20
8 Operation>>
2
1
7 34
Cable 1 Cable 2
21 3
Transf.
5
6 7 3 4
8
34
5
6 7 3 4
8
Cable Transf.
21
Fig. 19Operating panel for type FBA/FBE
Fig. 20Operating panel for type FBT
1 Switch position indicatorswitch disconnector “ON” - “OFF”in mains cable feeder
2 Opening for plug-in lever switch disconnector in mains cable feeder
3 Switch position indicator earthing switch “ON” - “OFF”
4 Opening for plug-in leverearthing switch
5 Switch position indicatorswitch disconnector in transformer feeder
6 Opening for plug-in lever switch disconnector in transformer feeder
7 Slide for non-force interrogation inter-locking earthing switch/switch discon-nector
8 Rating plate
Position: Condition:Switch disconnector Earthing switch
Cable compartment or fuse cover
Switch disconnector
Earthing switch
ON
OFF
–
–
ON
OFF
Locked
Unlocked
Locked
Unlocked
Locked
Locked
–
–
Unlocked
Locked
Cable compartment or
fuse cover removed Locked Locked –
Interrogation interlock
In the ring main cable unit, the following interlocks are integrated as standard:
21
Mains cable feeder
The following describes the switching operations.
Complete the ON-OFF movements up to the end
(stop). Never let go the plug-in lever before completing theswitching operation (risk ofinjury).
Switching the switch dis-connector in the mainscable feeder
Switch disconnector “OFF”.
Earthing switch “OFF”.
• Insert the plug-in lever (black).• Operate in one impetus the
plug-in lever clockwise (approx.95°) until the closing is com-plete. For this, support the swit-ching operation with one hand inthe middle of the plug-in lever.
• Pull off the plug-in lever imme-diately after this operation.
Switch disconnector “ON”.
Earthing switch “OFF”.
The opening is performed in an ana-logous manner (see Figure 21).
Switching the earthingswitch in the mains cablefeeder
Switch disconnector “OFF”.
Earthing switch “OFF”.
• Open the slide for the plug opening.
• Insert the plug-in lever (red). • Operate in one impetus the
plug-in lever clockwise (approx.95°) until the closing is com-plete. For this, support the swit-ching operation with one hand inthe middle of the plug-in lever.
• Pull off the plug-in lever imme-diately after this operation.
Switch disconnector “OFF”.
Earthing switch “ON”.
The opening is performed in an ana-logous manner (see Figure 22).
!
2
ON OFF
Fig. 21Switching the switch disconnector in themains cable feeder
2 3
Fig. 22Switching the earthing switch in the mainscable feeder
ON OFF
Slide to the left
22
Transformer feeder withintegrated fuse attach-ment
The following describes the switching operations.
Complete the ON-OFF movements up to the end
(stop). Never let go the plug-in lever before completing theswitching operation (risk ofinjury).
Switching the switch dis-connector with stored-energy drive and all-polefuse tripping in the trans-former feeder
(Transformer feeder without all-polefuse tripping see page 28).
Switch disconnector “OFF”.
Earthing switch “OFF”.
• Insert the plug-in lever (black).• Operate in one impetus the
plug-in lever anticlockwise untilthe switch latch is locked(approx. 95°). When doing so,support the switching operationwith one hand at the middle of theplug-in lever (this charges thebreaking spring).
• Then, operate in one impetus the plug-type lever clockwise (approx. 115°) until closing iscomplete (this charges and re-leases the closing spring).
• Pull off the plug-in lever imme-diately after this operation.
Switch disconnector “ON”.
Earthing switch “OFF”.
Opening (see Figure 23):
• Insert the plug-in lever.• Operate it in one impetus
(approx. 20°) anticlockwise untilthe opening is complete.
Switching the earthingswitch in the transformerfeeder
Switch disconnector “OFF”.
Earthing switch “OFF”.
• Open the slide for the plug opening.
• Insert the plug-in lever (red). • Operate in one impetus the
plug-in lever clockwise (approx.95°) until the closing is com-plete. For this, support the swit-ching operation with one hand inthe middle of the plug-in lever.
• Pull off the plug-in lever imme-diately after this operation.
Switch disconnector “OFF”.
Earthing switch “ON”.
The opening is performed in an ana-logous manner (see Figure 24).
!3
OFF
ON
Charging
Fig. 23Switching the switch disconnector in thetransformer feeder
3
Fig. 24Switching the earthing switch in the transformer
ON OFF
Slide to the left
Switching on/off theswitch disconnector withthe auxiliary hand crank
If the ring main unit is equipped withmotor drive (optional) it is also possi-ble to locally operate the switch dis-connector using an auxiliary handcrank (if the rated supply voltagefails, for example).
Operate the auxiliary hand crankclockwise (approx. 31 revolutions)for closing and up to the stop(switch “OFF”) for opening.
Locking the openings forplug-in levers
It is possible to lock the openings forplug-in levers against unauthorizedoperation (optional).
23
Fig. 25Switching on/off the switch disconnector using the auxiliary hand crank
Fig. 26Locking of the openings for plug-in levers
Shackle diameter min. 6 mm
24
Short-circuit indicator
The switchgear may be equippedwith short-circuit indicators.
Principally, there are two ways ofusing short-circuit indicators:- Short-circuit indicators which are
directly mounted on the single corecables. In this case it is necessaryto provide inspection glasses inthe cable compartment cover (optional).
- Short-circuit indicators within theinstrument recess (see Figure 27).The phases L1, L2, L3 are separate-ly indicated.
On request, it is possible to providethe following for the short-circuit indicators:- manual reset facility- automatic reset facility- remote reset facility- remote signalling contact- earth fault indicator
Note the specifications given by theshort-circuit indicator manufacturer!
Checking the dead state
The electronic voltage information system IVIS with integrated displayunit (three lightning arrow symbols)indicates the dead state of a feeder.
The voltage information system IVISindicates faults by interrupted arrowsymbols (these symbols disappear incase of dead state).
In such a case the switchgear mayremain in operation, but correctiveactions have to be agreed with themanufacturer.
The response conditions for aphase comparator with LRM inter-face are met at the IVIS measure-ment sockets.
Note the Operating Instructions forIVIS (no. 531 751)!
Alternatively, you can also establishthe dead state of the feeder with acontinuous voltage indicator (see Figure 29). Plug sockets for the con-tinuous voltage indicator (HR system)are then located in the instrumentrecess.
The indication is within the range ofthe tolerances required by VDE 0682,Part 415 or IEC publication 61243-5.
Always check all three phases L1,L2 and L3. Note the manufacturer’sinformation for the continuous voltageindicator.
If you want to check the voltage indicator note the manufacturer’s information for the testing instru-ments.
Phase comparison withIVIS
It is possible to carry out a phasecomparison using a phase compara-tor type MS 100 (see Operating Instructions no. 531 753).
Fig. 27 Voltage information system IVIS and short-circuit indicator in the instrument recess
Fig. 28 Plug sockets for the continuous voltage indicator in the instrument recess
Fig. 29Example for a continuous voltage indicator
25
Before you attempt to remove covers from the
switchgear remove the voltagefrom and earth any parts whichmay be alive and becomeaccessible by opening!Adhere to the relevant safetyregulations for any work on theswitchgear!
Removing and reassemb-ling the cable compart-ment or fuse covers
Take into account the interlock con-ditions (see page 20) before you remove cable compartment or fusecovers!Removing and reassembling of thecable compartment or fuse covers isto be made as shown in Figure 30.
Fig. 30Removing and reattaching the cable compartment or fuse cover
9 Work on the switchgear>>1.Earthingswitch “ON”
2.Unlock andpull off thekey.
3.Lift the coverand remove it.
Frontside L-bars can be remo-ved panel by panel for erecting,installation and wiring.
* When attaching the cover make sure that all hooks are inserted completely so that they can be locked.
ReattachRemove
Unlock *
!
Replacing fuses (trans-former feeder with inte-grated fuse attachment)
Fuse links are not included in thescope of delivery. For informationsee the engineering document “Selection of HV HRC fuse links for distribution transformers“ (no. 531 401).
Because earthing switchesare arranged before and after thefuses it is possible to replace thefuses without the need of insulat-ing auxiliary means.IEC publication 60282-1 recom-mends to replace all three fuse linkseven if only one fuse link of the all-pole fuse tripping has been blown ina three-phase system.
Tripping of a fuse is mechanicallyindicated in the fuse symbol on thefuse cover (red mark).
• Open the switch disconnector.• Close the earthing switch.• Unlock the fuse cover.• Remove the fuse compartment
cover.• Pull off the fuse link at the grip
surfaces (see Fig. 33), do notturn.
• Remove the grip end with fuse linkusing both hands (see Fig. 35).
• Prepare the new fuse link for replacing:
- Loosen the machine screw in theannular spring of the grip end(see Fig. 36).
- Pull out the fuse link by slight turning.
- Treat the contact surfaces at thegrip end and at the brand-newfuse link according to section 12.
- Insert the brand-new fuse link withthe contact side having the strikerinto the contact of the grip end byslight turning (see Fig. 36).
- Lock the fuse link against pullingout by slight tightening of the machine screw.
• Insert the fuse link.• Push the fuse link in without
turning.• The cam at the right grip surface
must be catched from the stop ofthe insulating tube (see Fig. 37).
• Reassemble the fuse cover
26
Fig. 31Indication of fuse tripping (red mark)
Fig. 32 It is recommended to replace always all threefuse links.
Fig. 33Do not turn the grip surfaces.
Fig. 34 At first pull out the fuse with one hand
Fig. 35Removing the old and inserting the new fuse.
Replacing short fuse linksfor switchgear with fusegauge e=442 mm
Extension tubes are available as spe-cial accessories for the use of fuselinks with e=292 mm in switchgearhaving a rated voltage 24 kV, but isoperated with a rated voltage of10 kV. The fuse links are not included in the scope of delivery.For information see the engineeringdocument “Selection of HV HRCfuse links for distribution transfor-mers“ (no. 531 401).
Replacing of fuse links as describedabove.
• Treat the contact surfaces (brand-new fuse link, extension tube andgrip end) according to section 12.
• Insert the brand-new fuse link withthe contact side having the strikerinto the contact of the grip end byslight turning. Use a screwdriverto slightly turn the machine screw(fixing of the fuse link in the gripend). Turn the extension tube onthe opposite contact side havingno striker.
27
Fig. 36 Assembly of the fuse link to the grip end
Fig. 38 Assembly of short fuse links
Fig. 39Grip end connected to fuse end and extension tube
Fig. 37Cam at the right grip surface catched
Machine screw
Annular spring
Extension tube
Fuse link
Striker side
Grip end
Striker side
Checking the all-pole fusetripping
• With the switch disconnector in“ON” position, it is possible tocheck the all-pole tripping throughthe tripping linkage using a trip-ping pin ø ≤ 2,1 mm, L > 80 mm,which is inserted through the ope-ning in the fuse covering up to thestop. The tripping pin is not inclu-ded in the scope of delivery.
Transformer feeder withoutall-pole fuse tripping
If the transformer feeder has no all-pole fuse tripping a label indicatesthis condition.
The label is located close to the fusesymbol on the operating panel.
The response of one fusedoes not cause a tripping of aswitch disconnector.
In this case the switch disconnectoris equipped with a snap-action driveSFU and is operated as a switch dis-connector in a mains cable feeder:
Closing (approx. 95°) as described on page 21.
Opening (approx. 95°) as described on page 21.
28
Openingø 2,3Pin ≤ 2,1
Indicator red
Fig. 40Checking the all-pole fuse tripping
Cable testing (with livebusbar)
Procedure of cable testing describedfor T-plugs.Other cable fittings require an analo-gous procedure. • Adhere to the assembly instructi-
on for the cable fittings!• Switch off the mains cable feeder
in the ring main unit, that meansswitch disconnector in “OFF” posi-tion (see page 21).
• Switch the mains cable feeder inthe mate station dead, that meansswitch disconnector in the matestation in “OFF” position.
• Earth the mains cable feeder, thatmeans earthing switch in “ON”position (see page 21).
• Remove the cable compartmentcover (see Fig. 30).
• Connect the line from the testinginstrument to the test adapter(note manufacturer’s instructions).
• The distance of bare parts of thetest adapter to the earthed sub-structure of the switchgear mustbe 90 mm as a minimum.
• Eliminate the earth connection by simulation of an assembledcable compartment cover (see Fig. 41B).
• Bring the earthing switch in “OFF”position.
In this condition operationof the switch disconnec-
tor is not interlocked! Attachthe prohibition sign to DIN 4844,ISO 7010 “DO NOT OPERATE”to the operating panel close tothe opening for the switch dis-connector plug-in lever!
Additional lock for mainscable feeder (option) forcable testing
An extra interlock may be providedfor cable testing, which preventsthe switch disconnector from beingswitched on as long as the earthingswitch is opened.• Dielectric test of the cable. Test
duration 15 minutes as a maximum.
• After the dielectric test bring theearthing switch to the “ON” posi-tion (see page 21).
• Dismantle the test adapter.• Provide the cable fitting with the
terminating plug according to
manufacturer’s instructions.• Insert the double-bit key and turn
it anticlockwise.• Reattach the cable compartment
cover (see Fig. 30).
29
!
Fig. 41A: Cable testing at T-plugB: Simulation of assembled cable compartment cover
Only allowed for cabletesting
1 Dismantle the cap and the terminating insert
2 Attach the test adapter
3 Simulate the interlock, earthing switch “OFF”
1
2
3
A
B
Rated voltage Test DC voltageUr (kV) max. (kV)
First test Repeat test7.21217.524
2948
2034
6096
4267
36 108 76admissible limits for the switchgear
Cable sheath testing
If there are no documents availablewhether the cable connection systemis approved for cable sheath testingor not ask the manufacturer of thecable connection system before-hand.
When testing the cable sheath make sure that the
connector housing has no con-tact with earthed switchboardparts. The connectors must not havecontact to each other. If requireddisconnect the connectors.
• For cable sheath testing discon-nect the earth connections (cop-per shield) from the cable holder.
• For identification of damages atouter plastic coverings apply atest DC voltage of 5 kV as a maxi-mum between Cu shield of thecable and earth.
• After completed cable sheathtesting reassemble the earth con-nection (Cu shield) at the cableholder (see section 12).
30
Fig. 42Cable sheath testing principle
!
Switch-gear
31
p SF6
Grüne s(Betriebbereic h
Mano m
Füllvent
Mano manschlukupplun
-23 C0 C20 C40 C60 C
0
00
00
Fig. 43Attachment of pressure gauge in the instrument recess
Green area(operatingrange)
Filling valve
Pressuregaugecoupling
Pressuregauge
General information
Type of insulating gas:Sulphur hexafluoride SF6 accordingto DIN VDE 0373 or IEC 60376.
The switchgear comes ready-to-operate with operative gas filling whichis designed for the whole service life.The container for the switchgear isdesigned as “sealed pressuresystem” according to the definitiongiven in the IEC publication 62271-200. The sealed pressure systemconcept makes any maintenance ofthe in-sulating gas filling unnecessary.Under normal operating conditionsaccording to DIN EN 60694 orIEC publication 60694 a service lifeof 30 years of the hermetically sealedpressure system can be expected.
• Do not let out insulating gas fromthe pressure container of theswitchgear.
Do not bore holes into the pressure container!
• Do not open the pressure container.
• The container must be kept freefrom foreign metallic deposits.
• It is absolutely necessary to avoidany crevice corrosion.
• Repair work at the high voltagepart can only be done in the manu-facturer’s works.
Rated filling pressure(operating pressure)
The rated filling pressure is 0.030 MPaat 20 °C.
In principle, operation of the switch-gear is only allowed when the pres-sure is within the green area. If therated filling pressure has been drop-ped down to atmospheric pressureat ambient temperature operation ofthe switchgear is allowed in specialcircumstances. In these cases, how-ever, the rated insulation level of theswitchgear with rated voltage 24 kVis only 24 kV, rated impulse with-stand voltage 95 kV (for switchgearwith rated voltage 36 kV the ratedinsulation level is 36 kV, rated im-pulse withstand voltage 145 kV).For switchgear 12 kV, then the ratedinsulation level is 12 kV, rated im-pulse withstand voltage 75 kV.
The temperature value necessary forpressure indication is to be measuredclose to the switchgear.
The filling valve becomes accessibleby disconnecting the pressure gaugecoupling from the filling valve. Thefilling valve closes automatically whenthe pressure gauge coupling is dis-connected.
Never open other screwedconnections, otherwise
there is the risk of gas loss.
10 Insulating gas, container>>
!
!
32
Switchgear type FBA, FBE, FBTneed no maintenance over more than20 years of operation.
The admissible number of operationsare generous designed so that theywill not be reached at operatingtimes of more than 20 years undernormal conditions.
If nevertheless the admissible numberof operations should be exceeded inspecial circumstances, please con-tact the manufacturer.
Depending of operational stress andconditions we recommend to inspectthe switchgear visually every fouryears.
In case dirt depositions are foundthe switchgear must be cleaned byexpert staff.
In case of doubts or deviations fromthe correct condition of the switch-gear contact the manufacturer.
11 Admissible number of operationsfor the switch disconnectors >>
Mains cable feederRated normal current 400 A
Mains cable feederRated normal current 630 A
Bre
ak n
umbe
r n
Bre
ak n
umbe
r n
Breaking current Ia (A)Breaking current Ia (A)
1000
500
100
50
10
1000
500
100
50
10
10 50 100
400
500
1000
5000 10 50 10
0
500
630
1000
5000
Bre
ak n
umbe
r n
Bre
ak n
umbe
r n
Breaking current Ia (A) Breaking current Ia (A)
Transformer feederType FBA, FBT 12 kVTake-over current 3000 A
Transformer feederType FBA, FBT 24 kVTake-over current 800 A
1000
500
100
50
10
1000
500
100
50
20
10
10 50 100
500
800
1000
500010 50 10
0
500
1000
3000
5000
Fig. 44Charts on admissible number of operations
Maintenance sequencefor sliding contact sur-faces (e.g.: fuse link)
• Cleaning with non-fuzzy cloth, incase of heavy contamination usedetergents.
• Apply a thin and uniform film ofcontact lubricant KL.
Treating screw-fastenedcontact surfaces
Pre-treat the contact surfaces immediately before tightening.
Material of Pre-treatmentcontact surfaces
Copper silver-plated (1) or copper alloy (4)silver-plated
Copper or (1)copper alloy (2)
(4)
Steel or (1)zinc coated steel (3)
(4)
(1) Cleaning- with non-fuzzy cloth,- in case of heavy contamination
with detergent(2) Polish surface bright - with abrasive cloth (grain size 100
or less) or- with wire brush which is only
allowed to be used for copper.(3) Polish surface bright, remove
existing passivation film- with abrasive cloth (grain size
100 or less) or- with wire brush which is only
allowed to be used for steel.(4) Treat with contact lubricant KL- Apply lubricant to both contact
surfaces so that the space bet-ween the contact surfaces is filled after tightening.
Auxiliaries
You can purchase the auxiliaries fromAREVA Sachsenwerk.
Order no.
Contact lubricant KL S 0081570.5 kg can
Detergent S 0081521 l can
Detergent for outside cone connection bushing: HAKU 1025-700Chemische Werke KlutheGottlieb-Daimler-Str. 12D-69115 Heidelberg
The use of other auxiliaries is not allowed.
Facilities, devices andaccessories
Order no.
Plug-in lever for switch dis-connector AGS C01132-01
Plug-in lever for earthing switch AGS C01133-01
Double-bit key AGS 434101-01
Auxiliary hand crank for motor drive AGS 617831-01
Short-circuit indicator *(instrument recess) –
Short-circuit indicator(on XLPE cable) –
For IVIS equipment:phase comparator MS100 AGS C26320-01
* Transducers at the outside cone connectionbushing can not be retrofitted.
Disposal after theservice life
There is a disposal guide availablefor disposal of switchgear typesFBA, FBE and FBT. On request theService Center in the manufacturer’sworks will carry out the disposal. Address for return:
12 Appendix>>
33
34
Notes:
AREVA Sachsenwerk GmbH · Rathenaustraße 2 · D-93055 Regensburg · Postfach 10 01 55 · D-93001 RegensburgTelefon +49 (0)9 41/46 20-0 · Telefax +49 (0)9 41/46 20-4 18
Our policy is one of continuous development.Accordingly the design of our products may changeat any time. Whilst every effort is made to produceup to date literature, this brochure should only beregarded as a guide and is intended for informationpurposes only. Its contents do not constitute an offerfor sale or advice on the application of any productreferred to in it. We cannot be held responsible forany reliance on any decisions taken on its contentswithout specific advice.
AREVA T&D
T&D Worldwide Contact Centre
www.areva-td.com
AR
EV
AS
ach
sen
we
rk G
mb
H R
eg
en
sbu
rg-
© -
AR
EVA
- 2
005.
AR
EVA
, the
AR
EVA
logo
and
any
alte
rnat
ive
vers
ion
ther
eof a
re t
rade
mar
ks a
nd s
ervi
ce m
arks
of A
RE
VATh
e ot
her
nam
es m
entio
ned,
reg
iste
red
or n
ot, a
re t
he p
rope
rty
of t
heir
resp
ectiv
e co
mpa
nies
- 3
8919
1982
RC
S P
AR
IS -
Cre
atio
n: S
CH
RE
ML
Med
ia G
mbH
Reg
ensb
urg
- P
rinte
d in
Ger
man
y