union for the co-ordination of transmission of electricity UCTE, 15 Boulevard Saint-Michel, 1040 Brussels, Belgium, [email protected] Matthias Luther Union for the Co-ordination of Transmission of Electricity Feasibility of the synchronous interconnection of IPS/UPS with UCTE an overview about the study 2 nd joint Eurelectric-CIS EPC Seminar Electricity Market from Lisbon to Vladivostok ? Moscow, Russia, 24 November 2005

Upload: buicong

Post on 04-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

union for the co-ordination of transmission of electricity

UCTE, 15 Boulevard Saint-Michel, 1040 Brussels, Belgium, [email protected]

Matthias Luther

Union for the Co-ordination of Transmission of Electricity

Feasibility of the synchronous interconnection of IPS/UPS

with UCTE – an overview about the study

2nd joint Eurelectric-CIS EPC Seminar

Electricity Market from Lisbon to Vladivostok ?

Moscow, Russia, 24 November 2005

Page 2: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 2 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

1. UCTE – an introduction about the

association

2. State of play of the Feasibility Study

• Tasks and objectives

• Organisation and time frame

• Present status

• Next activities and conclusions

Presentation themes

Page 3: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 3 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

UCTE overview: Key figures 2005

Transmission System Operators 33

European Countries 23

Customers 450 mil.

Installed capacity 560 GW

Electricity consumption/year 2500 TWh

Electricity exchanges betw. countries/year 270 TWh

Length of high voltage lines 230.000 km

Page 4: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 4 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Main mission of UCTE

Providing pre-conditions for a functioning electricity market:

Technical and operational co-ordination in the

synchronous area

Controlling the short-term security of the system with

regard of load, frequency control and system stability

Monitoring the medium to long-term adequacy

between generation and load (3, 5, 10 years)

Responsibility for the development of the synchronous

area

Page 5: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 5 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Page 6: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 6 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Seite 2

Thema Datum Bereich

Key figures of IPS/UPS and UCTE

Inst. Capacity/[GW]

Consumption/[TWh]

Consumers/[mio]

300

1.200

280

Inst. Capacity/[GW]

Consumption/[TWh]

Consumers/[mio]

560

2.500

450

IPS/UPS: parallel operation

of 13 power systems

power systems of UCTE

power systems of IPS/UPS

other power systems

2nd joint EURELECTRIC-CIS EPC SEMINAR, 24 November 2005, Moscow, Russia

Page 7: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 7 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

UCTE-IPS/UPS Study – three major questions to answer

Is a full synchronous interconnection of IPS/UPS with UCTE

feasible?

What are the mandatory measures and requirements on both

sides?

What are the associated costs?

Considering technical, operational, organizational and legal

issues the study will answer the following questions:

Additionally, market aspects and environmental issues are

building the conditional framework

Initial priority: maintaining the present performance of the

systems with respect to system security and reliability

Page 8: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 8 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Consideration of non-synchronous link projects

• In October 2005 IPS/UPS has taken an initiative to consider non-

synchronous link projects in the investigation.

• Generally, the proposal is supported by the UCTE-Consortium if

projects can be identified with a certain degree of realisation capability

at time horizons to be analysed.

• Nevertheless, in order to identify a possible extension on the amount

of work, data provision and the time schedule, IPS/UPS companies are

requested to provide a description and specification of relevant

projects.

• Based on this information the parties will consult about the next

further steps and try to find a solution to the benefit of the project.

Page 9: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 9 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

The UCTE-Consortium

The UCTE Consortium consists of 11 Transmission System Operators:

other

TSOs

Page 10: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 10 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

The IPS/UPS Group of 8 Companies

Page 11: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 11 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

UCTE-IPS/UPS Study – common project organization

Project

Management

Project Representative

Board

Project Management

Board

Technical Aspects

WG 1:

Steady State

Analysis

WG 2:

System

Dynamics

WG 3:

Power System

Control

WG 4:

Operation and

Organization

WG 5:

Legal Aspects

Page 12: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 12 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

UCTE-IPS/UPS Study – time schedule

* target dates

pre-

phase

phase 2

Verification

and Simulation

phase 1

Model

Preparation

verification of

models

power system

simulations

sensitivity analyses

ToR

TEN-E

Application

Building

up of

consortia

Cooperation

Agreement

Project kick-off

survey of IPS/UPS

system

installation of

measurement

devices (WAMS)

power system

measurements

data collection

preparation of

models

further analyses

evaluation of results

identification of

measures and their

costs

presentation of

results

preparation of draft

of final report

phase 3

Assessment

and Results

final

phase

final report

final ac-

counting

end of

project

2005 2006 2007 2004

Page 13: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 13 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Achievements reached so far

pre-phase phase 1: Model Preparation

Preparation of the Terms of

Reference (ToR)

TEN-E application

Formation of the Consortium/

Group of Companies

Preparation of the

Cooperation Agreement

(signed on 19 April 2005)

Project kick-off, 20 April 2005

Preparation of project schedule

Issue of questionnaire on IPS/UPS system data,

15 June 2005

Data collection, preparation of individual models

Start of installation of measurement devices

within IPS/UPS

First joined workshops and IPS/UPS System

Survey Seminar, 4-6 October

First PMB meeting, 7 October

2005 2004 01.04.2005

Page 14: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 14 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Principles of data provision and model generation

ACCEPTANCE

BY THE PARTIES

April 2006 *

INDIVIDUAL

TSO MODELS

MERGING OF MODELS

QUALITY CHECK

/ VERIFICATION

go!

DATA PROVISION

BY QUESTIONNAIRE

DATA MODELLING

QUALITY CHECK

/ VERIFICATION

Support by

UCTE experts

Real system

measurements

Set up of common model

Real system

measurements

UCTE IPS/UPS

* target date

Page 15: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 15 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

The technical challenge: simulation of two synchronous

systems …

…with different

• geographical extensions

• generation and network structures

• operation philosophies

?

Page 16: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 16 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

• First common working activities confirm the dimension of the project

and its ambitious time schedule.

• IPS/UPS data provision and the installation of the Wide Area

Measurement System (WAMS) in the whole IPS/UPS synchronous area

have been recognized as pre-requisites for the preparation and

verification of well-qualified simulation models.

• The consideration of non-synchronous link projects will be analysed

after realistic projects are proposed and specified.

• System simulations will be carried out under the initial priority to

maintain system security and reliability on both sides.

Conclusions

Page 17: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 17 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Seite 2Thema Datum Bereich

Further available information

Visit us: www.ucte-ipsups.org

Page 18: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

union for the co-ordination of transmission of electricity

UCTE, 15 Boulevard Saint-Michel, 1040 Brussels, Belgium, [email protected]

Feasibility of the synchronous interconnection of

IPS/UPS with UCTE – an overview about the study

Back-up

Page 19: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 19 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

1 Cartelle

2 Montearenas

3 Aldeadavila

4 San Sebastian de las Reyes

5 Hernani

6 Arkale

7 Biescas

8 Vic

9 Rubi

10 Benejama

11 Puerto de la Cruz

12 Cedillo

13 Saucelle

14 Albertville

15 Tavel

16 Saucats

17 Tabarderie

18 Lonny

19 Uchtelfangen

20 Hagenwerder

21 Röhrsdorf

22 Krajnik

23 Wielopole

24 Rogowiec

25 Polaniec

26 Györ

27 Göd

28 Sajoszöged

29 Heviz

30 Paks

31 Portile de Fier

32 Tantareni

33 Blagoevgrad

34 Ag.Stefanos

35 Bassecourt

36 Mettlen

37 Lavorgo

38 Soazza

39 Rondissone

40 Redipuglia

41 Aurelia

42 Brindisi

43 Sorgente

44 Avelgem

measuring devices:

installed

planned

Wide Area Measuring System in UCTE

time synchronisation by GPS

1

2

3

4 5 6 7

14

19

20 22

24

25

26

29

31

32

33

34

36

37 38

40

35

44

45 49

53

46 47 48 51 52 50

15

16

17

18

21

39

41

42

43

3

13

11

10

9

12

23

27 28

30

8

45 Oujda

46 Ghazaouet

47 Tlemcen

48 Oued Sly

49 Jijel

50 Biskra

51 El Aouinet

52 Tajerouine

53 Tataouine

Page 20: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 20 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

Recording of inter-area-oscillations

49,810

49,850

49,890

49,930

49,970

50,010

13:00:15 13:00:20 13:00:25 13:00:30 13:00:35 13:00:40 13:00:45

f [Hz]

Uchtelfangen (D)

Cartelle (E)

Albertville (F)

Polaniec (PL)

Heviz (H)

Mettlen (CH)

Aouinet (DZ)

5 s

T ≈ 4,1s

f ≈ 0,24

Hz

Generation outage

980 MW in Spain

Page 21: Feasibility of the synchronous interconnection of … – an introduction about the association 2. State of play of the Feasibility Study •Tasks and objectives •Organisation and

Page 21 2nd joint Eurelectric-CIS EPC Seminar, 24 November 2005, Moscow, Russia Matthias Luther

A mechanical analogue of a two-area-system

v0 + Dv1 v0 + Dv2

Bibliography: Olle I. Elgerd, „Electric Energy Systems

Theory: An Introduction“. 1973

Analogue area 1 Analogue area 2 Relative soft

„tie-spring“

analogue of

weak tie-line