feasibility study for the road network for ......university of moratuwa road network for hambantota...
TRANSCRIPT
![Page 1: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/1.jpg)
FEASIBILITY STUDY FOR THE
ROAD NETWORK
FOR HAMBANTOTA DEVELOPMENTPLAN (RNHDP)
Volume I
Final Report
Department of Transport & Logistics Management,
University of Moratuwa
December 2010
![Page 2: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/2.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
![Page 3: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/3.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
i
Table of Contents
Volume I Final Report
Study Team ______________________________________________________xi
Executive Summary ____________________________________________________ xii
CHAPTER 1 Background ___________________________________________ 1-1
1.1 Objectives of the Study _________________________________________ 1-1
1.2 Study Area of the Proposed Project _______________________________ 1-2
1.3 Scope of Work ________________________________________________ 1-3
1.4 Reporting ____________________________________________________ 1-6
CHAPTER 2 Data Collection ________________________________________ 2-1
2.1 Maps _______________________________________________________ 2-1
2.2 Reports _____________________________________________________ 2-1
2.3 Traffic and Transport Data_______________________________________ 2-2
2.4 Social Assessment ____________________________________________ 2-3
2.5 Preliminary Field Observation ____________________________________ 2-4
CHAPTER 3 Project Impact Area_____________________________________ 3-1
3.1 Geography & Climate __________________________________________ 3-1
3.2 Population ___________________________________________________ 3-1
3.3 Land use Pattern in the area _____________________________________ 3-2
3.4 Economic Activities ____________________________________________ 3-3
3.5 Greater Hambantota Development Plan ____________________________ 3-6
3.6 Current Status of Development ___________________________________ 3-8
3.7 Industrial Zones ______________________________________________ 3-21
3.8 Urban Development Centres ____________________________________ 3-22
![Page 4: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/4.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
ii
CHAPTER 4 Stakeholder Meetings ___________________________________ 4-1
4.1 Hambantota Meeting ___________________________________________ 4-1
CHAPTER 5 Final Road Network_____________________________________ 5-1
5.1 Introduction __________________________________________________ 5-1
5.2 Definition of Transport Functionalities ______________________________ 5-3
5.3 Road Network Proposed by RDA _________________________________ 5-5
CHAPTER 6 Geometric Design ______________________________________ 6-1
6.1 Geometric Design Criteria _______________________________________ 6-1
6.2 Number of Lanes & Staged Construction ___________________________ 6-2
6.3 Lane Width___________________________________________________ 6-5
6.4 Shoulders and Centre Median____________________________________ 6-6
6.5 Service Corridor_______________________________________________ 6-6
6.6 Grade_______________________________________________________ 6-7
6.7 Design Speed ________________________________________________ 6-7
6.8 Operating Speed ______________________________________________ 6-7
6.9 Cross Sections_______________________________________________ 6-10
6.10 Intersections ________________________________________________ 6-12
6.11 Intersection Control ___________________________________________ 6-14
CHAPTER 7 Traffic Analysis ________________________________________ 7-1
7.1 Inter- Regional Connectivity______________________________________ 7-1
7.2 Design Parameters of Road Network ______________________________ 7-2
7.3 Traffic Forecasting_____________________________________________ 7-9
7.4 Scenarios for Benefit Cost Analysis_______________________________ 7-15
7.5 Generated Traffic_____________________________________________ 7-17
7.6 Port Based Traffic ____________________________________________ 7-26
![Page 5: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/5.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
iii
7.7 Network Performance _________________________________________ 7-28
7.8 Analysis of Scenarios _________________________________________ 7-30
7.9 Traffic Levels ________________________________________________ 7-33
7.10 Level of Service ______________________________________________ 7-33
CHAPTER 8 Public & Non-Motorised Transport _________________________ 8-1
8.1 Introduction __________________________________________________ 8-1
8.2 Field Observation______________________________________________ 8-2
8.3 Livable Compact City for Hambantota______________________________ 8-3
8.4 Population and Transit Demand __________________________________ 8-3
8.5 Public Transport_______________________________________________ 8-4
8.6 Public Transport Network _______________________________________ 8-5
8.7 Non-Motorised Transport_______________________________________ 8-10
8.8 Public Transport Stations_______________________________________ 8-13
CHAPTER 9 Social Analysis ________________________________________ 9-1
9.1 Background __________________________________________________ 9-1
9.2 Methodology of the Assessment of Potential Impacts__________________ 9-1
9.3 Populations Served along the Road Commands______________________ 9-2
9.4 Agricultural Land Use Pattern ____________________________________ 9-3
9.5 Real Estates Market of the Road Vicinity ___________________________ 9-4
9.6 Local Economic Centres Served by the Roads _______________________ 9-6
9.7 Nature of Built Up Area Affected and the Likelihood Negative Impacts on
Houses, Shops and Public Buildings ____________________________________ 9-7
9.8 Public Places Served by Proposed Candidate Roads__________________ 9-8
9.9 The Significant Religious and Other Public Centres Connected to Roads __ 9-9
9.10 Connectivity Impacts of the Proposed Roads _______________________ 9-10
![Page 6: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/6.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
iv
CHAPTER 10 Economic Benefits_____________________________________ 10-1
10.1 Vehicle Operating Cost Savings:_________________________________ 10-1
10.2 Travel Time Savings __________________________________________ 10-3
10.3 Socio-Economic (Regional) Development__________________________ 10-5
10.4 Summarised Benefits for all Scenarios ____________________________ 10-6
CHAPTER 11 Economic Costs ______________________________________ 11-1
11.1 Land Acquisition & Resettlement_________________________________ 11-1
11.2 Resettlement Costs ___________________________________________ 11-1
11.3 Earth works _________________________________________________ 11-2
11.4 Drainage ___________________________________________________ 11-3
11.5 Road Works_________________________________________________ 11-3
11.6 Structures (Bridges and Culverts) ________________________________ 11-4
11.7 Elephant Underpasses ________________________________________ 11-5
11.8 Roadway Facilities____________________________________________ 11-6
11.9 Lighting & Safety _____________________________________________ 11-7
11.10 Rehabilitation in 2021 (after 10 years) ___________________________ 11-7
11.11 Routine Maintenance ________________________________________ 11-8
11.12 Summary of the BOQ________________________________________ 11-8
CHAPTER 12 Economic Benefit Cost Analysis __________________________ 12-1
12.1 Assumptions in Analysis _______________________________________ 12-1
12.2 Benefit Analysis for Stage II Construction Over 3 Years _______________ 12-2
12.3 Sensitivity Analysis ___________________________________________ 12-3
12.4 Stepwise construction as Stage I and Stage II ______________________ 12-5
CHAPTER 13 Conclusions__________________________________________ 13-1
![Page 7: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/7.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
v
Annex 1: Preliminary Field Observations
Annex 2: List of Participants for the Stakeholder Consultation Program
Volume II Appendices to Final Report
Appendix 1 Road Network Proposed by RDA
Appendix 2 Final Road Network Proposed by Study Team
Appendix 3 Typical Cross Sections Used for Roads Proposed
Appendix 4 Estimated Traffic Levels (ADT) on Project Roads (2012, 2022 & 2032)
Appendix 5 Forecasted Level of Service (LOS) on Project Roads (2012, 2022 & 2032)
Appendix 6 Public Transport & Non-Motorized Corridors in Road Network
Appendix 7 Proposals for Reducing Accidents involving Elephants & Other Wild Life
![Page 8: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/8.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
vi
List of Tables
Table 1-1: List of Roads Proposed by RDA _________________________________ 1-3
Table 2-1: Traffic Survey Program________________________________________ 2-2
Table 2-2: Summary of Flow of Traffic Counts_______________________________ 2-3
Table 3-1: Population of Greater Hambantota Area (2001) _____________________ 3-2
Table 3-2: Projections for Population______________________________________ 3-2
Table 3-3: Land Use in the Area _________________________________________ 3-3
Table 3-4: Land Use for Development of Hambantota Port_____________________ 3-9
Table 3-5: Estimated Traffic at Port of Hambantota__________________________ 3-12
Table 3-6: GDP and Industrial Contribution in Sri Lanka 1970-2005_____________ 3-13
Table 3-7: Aviation Demand Forecast for the Proposed Weerawila Airport________ 3-17
Table 3-8: Floor Area Allocation of Proposed Administrative Complex ___________ 3-18
Table 3-9: Proposed Land Use Distribution under City Centre Development ______ 3-20
Table 5-1: RDA List of Road Links Identified in Hambantota Development Plan ____ 5-6
Table 5-2 : Details of the Traces for the 4 New Roads ________________________ 5-7
Table 5-3: HR19: Connection between A018 and Sooriyawewa-Mirijjawila Road (HR16)
___________________________________________________________________ 5-9
Table 5-4 : HR08: between Sooriyawewa-Mirijjawila Road (HR16) and Hambantota-
Gonnoruwa-Meegahajandura Road (HR02) _______________________________ 5-11
Table 5-5 : HR18: Road connecting Walawe Left Bank Road to Hambantota-Gonnoruwa-
Meegahajandura Road (HR02) _________________________________________ 5-13
Table 5-6: HR12: Airport Access Road ___________________________________ 5-15
Table 6-1: Stage Construction and Lane Capacities of Proposed Road Network ____ 6-2
Table 6-2 : Passenger Car Equivalence ___________________________________ 6-3
![Page 9: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/9.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
vii
Table 6-3: LOS under Different Development Scenarios for Stage I Improvements __ 6-4
Table 6-4: Existing Terrains and the Proposed Design Speeds of the Roads_______ 6-5
Table 6-5: Calculation of Average Operating Speed (km/hr) ____________________ 6-9
Table 6-6: Description of Types of Cross Sections defined ____________________ 6-10
Table 6-7: Proposed List of Road and the Cross Sectional Properties ___________ 6-11
Table 6-8: Intersection Types for Stage I and Stage II________________________ 6-12
Table 6-9: List of Potential Intersection Developments _______________________ 6-13
Table 7-1: Design Parameters of the Proposed Hambantota Road Network _______ 7-4
Table 7-2: Summary of Observed Traffic Flows (2007) ________________________ 7-9
Table 7-3: Daily One-Way Flow of Passenger Vehicles (Uva &Southern, 2007)____ 7-10
Table 7-4: Daily One-Way Flow of Goods Vehicles (Uva &Southern, 2007) _______ 7-10
Table 7-5: Employment Estimation ______________________________________ 7-12
Table 7-6: Population Estimates for Hambantota Development Area (2012-2032)__ 7-13
Table 7-7: Vehicle Growth Rates to be used for Analysis _____________________ 7-13
Table 7-8: Vehicle Growth Rates (2012-2032)______________________________ 7-14
Table 7-9: Vehicle Fleet and Vehicle Ownership Rate: 2006-2032 ______________ 7-15
Table 7-10: Description of Testing Scenarios ______________________________ 7-16
Table 7-11: Summary of Scenarios ______________________________________ 7-16
Table 7-12: TransPlan Estimates for Base Case Scenario (2012-2032) __________ 7-18
Table 7-13: TransPlan Estimates for Development Scenario (2012-2032) ________ 7-19
Table 7-14: TransPlan Estimates for Hypothetical Scenario I (2012-2032)________ 7-22
Table 7-15: TransPlan Estimates for Hypothetical Scenario II (2012-2032) _______ 7-24
Table 7-16: Average Daily Flows at Port of Colombo ________________________ 7-26
Table 7-17: Vehicle Entries per gate and vehicle movement rate at Port of Colombo 7-27
Table 7-18: Estimation of Vehicle Movements from Port of Hambantota (2010-2040) 7-28
![Page 10: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/10.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
viii
Table 7-19: Network Statistics from TransPlan output________________________ 7-29
Table 7-20: Analysis of Estimation Scenarios ______________________________ 7-31
Table 7-21: LOS for Links in HDP network (Development Scenario – 2032) ______ 7-34
Table 8-1: Projected Population and Predicted Transit Demand_________________ 8-4
Table 8-2: Mobility Alternatives for Motorisation _____________________________ 8-6
Table 8-3 : Public and Non-Motorised Transport Routes_______________________ 8-6
Table 8-4 : Transit User Origin and Destination (O-D) Estimation per day _________ 8-7
Table 8-5 : Transit Headway ____________________________________________ 8-7
Table 9-1 : Agricultural Land Use Pattern __________________________________ 9-3
Table 9-2: Percentages of Land in the Road Vicinity with Scrub Jungles __________ 9-4
Table 9-3: Perceived/ Current Market Values with Market Values of Land before 3 Years
___________________________________________________________________ 9-5
Table 9-4: List of Roads Serving Weekly Fairs ______________________________ 9-6
Table 9-5: Number of Buildings Likely to be Affected _________________________ 9-7
Table 9-6: Public Places Served by Proposed Candidate Roads ________________ 9-8
Table 9-7: Religious Places Served by Proposed Candidate Roads______________ 9-9
Table 9-8: Degree of Significance of the Roads Based on Different Aspects ______ 9-11
Table 10-1 : Economic Vehicle Operating Cost in Rs/km @ IRR =2 _____________ 10-2
Table 10-2 : Economic Vehicle Operating Cost in Rs/km @ IRR =4 _____________ 10-2
Table 10-3: Modal Share for Forecast period ______________________________ 10-2
Table 10-4: Summary of VOC Savings ___________________________________ 10-3
Table 10-5: Value of Time for Transport User Groups (in 2010 Rs/Hour) _________ 10-4
Table 10-6: Travel Time Savings ________________________________________ 10-4
Table 10-7: Freight Time Savings _______________________________________ 10-5
Table 10-8: Regional Benefits Rs mn ____________________________________ 10-6
Table 10-9: Summary of Benefits (Rs Mn in Current Year Prices) ______________ 10-7
![Page 11: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/11.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
ix
Table 11-1 : Percentage Land Use by Length along the Road _________________ 11-2
Table 11-2: Estimation of Cut and Fill volume ______________________________ 11-3
Table 11-3: Cost of Drainage___________________________________________ 11-3
Table 11-4: Cost of Base and the Pavement (Road Works) ___________________ 11-4
Table 11-5: Summary Table of Costs for Structures _________________________ 11-5
Table 11-6: Summary Table of Costs for Roadway Facilities __________________ 11-6
Table 11-7: Cost Estimates for Road Safety _______________________________ 11-7
Table 11-8 : Average Cost of Annual Maintenance __________________________ 11-8
Table 11-9: Summary of Stage II Construction Costs ________________________ 11-8
Table 12-1: Benefit –Cost Analysis for Stage II Construction over 3 Years________ 12-2
Table 12-2: Benefit –Cost Analysis for Stage II Construction Stretching over 6 Years 12-4
Table 12-3: Comparison of Cost of Construction for Stage I and Stage I &II_______ 12-5
Table 12-4: Benefit-Cost Analysis for Staged Construction____________________ 12-6
![Page 12: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/12.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
x
List of Figures
Figure 1-1 : Study Area of the Proposed Project _____________________________ 1-2
Figure 3-1: Location of Seaport and Proposed Administrative Area in Hambantota __ 3-8
Figure 3-2: Proposed Administrative Complex______________________________ 3-19
Figure 3-3 : Proposed Administrative Complex and Convention Centre __________ 3-21
Figure 3-4 : Existing Urban Hierarchy- Southern Province ____________________ 3-23
Figure 5-1 : Study Area with Zoning of UDA ________________________________ 5-2
Figure 8-1: Crutiba – A World Popular Median Bus Lane BRT Model_____________ 8-8
Figure 8-2: Sample operation routes for PT along Routes 1 and 2 ______________ 8-10
Figure 9-1 : Populations Served along the Roads in Each DS Division____________ 9-2
Figure 11-1 : Typical Pavement Section Used for Estimations _________________ 11-4
![Page 13: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/13.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
xi
Study Team
The members of the Study Team who participated in this project are as follows:
Prof. Amal S. KumarageTeam Leader/ Traffic Analysis/
Economic Analysis
Dr. Tissa LiyanageHighways Design/Engineering
Studies/Costing
Dr. T. Sivakumar Public Transport
Mr. SN Bentotage Transport Planning
Ms. Menike Somarathna Regional & Urban Development
Mr. Janaka Weerawardena Transport Demand Estimation
Mr. K. Jinapala Socio Analysis
Ms. Pradeepa Jayaratne GIS Mapping/TransPlan
Mr. Ranil Sugathadasa Project Manager
![Page 14: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/14.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
xii
EXECUTIVE SUMMARY
Feasibility Study for the Road Network for Hambantota development Plan (RNHDP) is
the project for the allied road network development of the Hambantota International Hub
Development that has been carried out by the Department of Transport and Logistics
Management of the University of Maoratuwa as invited by the Road Development
Authority (RDA).
Identification of the long term demand for transport, assessment of the requirements for
transport capacity development and the assessment of the socio-economic viability were
the main objectives while investigating the adequacy of the RDA proposed road network
development, making recommendations and carrying out the preliminary designs.
Study Area
Hambantota is located in the southern dry zone of Sri Lanka. It spreads over an area of
113,000 ha that lies between Walawe River and Kirindi Oya. The defined area for the
development plan covers DS Divisions of Sooriyawewa (21 GNDs), Hambantota (30
GNDs), Ambalantota (13 GNDs), Thanamalwila (5 GNDs), Sevanagala (14 GNDs),
Tissamaharama (15 GNDs) and Lunugamvehera (29 GNDs). This study strongly
considers that the hinterland of Hambantota has great potential to develop around the
port and Hambantota District in particular and as a result, the Southern Sri Lanka
(Ruhuna) in general will become an industrialised area.
Development Potential
The study area for the road network has been selected based on the provision of
accesses to the proposed international hub development sites such as the Airport,
Seaport, Cricket Stadium, Safari Park, BOI site etc. as well as the Convention Centre,
Administrative Complex and tourism related development and residential areas.
Providing access for these sites and inter-linking them to an appropriate level to the
national transport networks were the major concerns when designing the road network.
Based on the Feasibility Study estimates for the Port of Hambantota and discussions
with the Urban Development Authority it has been assumed as a precondition, that the
Port of Hambantota would by 2030 handle and the other development activities set out in
the Greater Hambantota Development Plan, would attract a total direct and indirect
![Page 15: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/15.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
xiii
employment of 94,000 which would require a net migratory population of 230,000 by the
year 2032. In keeping the objective of making Hambantota a 1st order city, the economic
development of Hambantota is considered to reach a status of being second only to
Colombo District and equal to the developed parts of Gampaha and Kalutara District.
Thus vehicle ownership over the 20 year period is assumed to increase from 9 vehicles
per 100 persons to 23 vehicles per 100 persons.
Connectivity to National Road Network
When defining the road network, additional measures have been taken to integrate
Eastern and Uva provinces nationally, as those provinces are considered to be the least
accessible provinces in Sri Lanka and ones that could be better served through a port
and airport compared to Western Province.
Functional Requirements for the Road Network
In addition to the provision of accesses for development sites, the study team has
purposefully introduced certain transport functionality aspects when defining road
network and their cross sections with the intention of increasing the performance of the
proposed network and specifically with respect to:
1. Definition of Outer Hambantota Development Area to ensure urban area and its
activities are impacted by through traffic
2. Provision of a high profile connection between the proposed Seaport and Airport
to facilitate air-sea connections
3. Provision of a viable public transport corridor to promote high density
development
4. Maximise Usage of Pedestrian and Cycle Access to encourage sustainable
transport and enhanced quality of life
Proposed Network
After considering the aforementioned functionality aspects, the RDA proposals which
contained 17 road links extending over 290.2 km, have been improved to a proposed
road network with 27 road links. It includes one omission, the Outer Circular Road II,
and the addition of 11 new links to the original proposal of the RDA. The total length of
![Page 16: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/16.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
xiv
the proposed network is 371.7 km of which new constructions would amount to around
38 km or around 10% of the network.
Traffic Estimation
As per the Terms of Reference the Traffic forecasts are made for the years 2012, 2022
and 2032. It is expected that full development potential of the Hambantota Development
Plan would have been achieved by the year 2032, while the year 2012 would see the
construction of the basic infrastructure such as the Stage I of the port, the air port, the
cricket stadium, administrative complex, safari park etc.
There will be an estimated 33,206 daily vehicle movements within the Hambantota
project area by the year 2032 due to the activity of the port which would include 7,994
container trucks,
In terms of traffic flow on the proposed road network, there would be only three road
secrions having a flow of more than 10,000 vehicles per day in 2012 mostly near
Siribopura Junction which by the year 2032, are expected to reach over 30,000. Of the
67 sections of road in the network, 31 are expected to carry more than 10,000 vehicles
per day by 2032. Around 10% of the network length only will have traffic levels of over
20,000.Hence the need for road capacity is low to moderate across the network.
Social Impact and Road Safety
The social assessment has focused on evaluating the most likely impacts of the
proposed road hub over the socio-economic environment in the local and regional
economies. The assigned field team had made observations by walkthrough surveys
along the candidate roads and by informal discussions with the community members
residing in the immediate vicinity of the roads. It is concluded that the proposed road
network would form a hub of interconnecting roads that are connected to other roads in
both local and regional levels. This network will create socially and economically
effective connectivity impacts in the area and thereby in the entire country. This would
offer direct and indirect benefit for people in these administrative units through multiple
roads.
Wild Life & Safety Issues
This report deals with the issues pertaining to the road safety arising from elephant
crossings of the proposed roads as well. This is considered as an important aspect as
![Page 17: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/17.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
xv
roads are to be widened as well as operating speeds increased. The combination of
both attributes is expected to pose a formidable challenge to avoid vehicles from
crashing to elephants.
At the request of wild life authorities underpasses have been located for crossing of
elephants and other wild life at four locations. Electric fences also have been suggested
in order to ensure that animals would not cross at random locations. However, since
these types of crossings have not been tested adequately in Sri Lanka, further studies
are recommended to determine suitability. Furthermore another underpass has been
provided for railway crossing on the Hambantota-Gonnoruwa road.
Benefit Cost Analysis
The Benefit-Cost Analysis indicates that the immediate full development of the proposed
road network (Stages I and II together) will cost Rs 71.1 billion and will have an
economic return on investment of around 13.5% p.a. with a NPV of Rs 9,301 million at a
Discounting Rate of 12%, while its Benefit Cost Ratio would be 1.14. Given that
economic cost of capital for this project may be significant; this is not considered a
favourable rate of return for a large scale highway project.
However, if it is constructed as a staged construction where only the roads identified in
Stage I (costing Rs 45.7 billion) are constructed to an interim standard in the first 3
years, and upgraded to full design standard at a cost of Rs 25.4 billion only after 10
years, then the economic performance improves significantly to a Benefit- Cost Ratio of
1.87 with a NPV of Rs 54,626 million as 12% Discount Rate. In this scenario, the design
life of the project is assumed to be 40 years with a major rehabilitation of Stage I roads
carried out after 20 years in addition to an intermediate improvement being carried out
after 10 years.
Thus construction of the proposed network can be recommended on the following
conditions:
That the construction is staggered in two Stages with the first Stage over the first
3 years and the others delayed till 2020 at least.
The land required for the Stage II design to be acquired under the Stage I and
where possible to covnert to Green Areas until required for capacity widening.
![Page 18: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/18.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
xvi
To re-examine the level of traffic by 2018 and examine which roads should be
improved to Stage II stage. This is to ensure that the assumed development
has taken place and there would be no loss in anticipated benefits.
Road Design
The cross sectional properties of the proposed roads have been considered for stage
developments, as Stage I and Stage II, for the purpose of effectiveness of the investment
plans. The cross sectional properties of each road have been identified for facilities such
as number of lanes, service roads, walkways, bicycle lanes, shoulders, public transport
lanes, parking bays, centre medians, bus bays, landscaping and utility corridors,
depending on the potential demand by the proposed land use developments.
When selecting the cross sections, a higher emphasis has been given for providing
facilities for the non-motorised access and public transport use in Greater Hambantota
Area. Moreover, there are forty one (41) intersections included in this project proposal.
They belong to three (3) categories of intersection types proposed for Stage I and nine
(9) categories for Stage II.
Public Transport
The study recommends that two routes be developed as a Superior Public Transport
Corridor mostly likely using Bus Rapid Transit Technology, a feasibility of which should
also be undertaken at a later stage. This will be the most important investment toe
ensure a high density development core in Hambantota for which the Siribopura-
Gonnoruwa Road section is the best candidate. Moroever, several transport terminals
have also been suggested to ensure good connectivity and balanced transport within the
region.
![Page 19: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/19.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
1-1
CHAPTER 1 BACKGROUND
The Road Development Authority (RDA) by agreement signed with the University of
Moratuwa dated 14th September 2010 has engaged the Department of Transport &
Logistics Management of the University of Moratuwa to report on the Feasibility Study for
the allied Road Network Development of the Hambantota International Hub
Development. For convenience of reporting, this project, the Feasibility Study for the
Road Network for Hambantota Development Plan, hereinafter referred to as RNHDP.
The Hambantota International Hub Development is a key initiative of the Government of
Sri Lanka. It comprises the construction of an international seaport, international airport,
extension of the Southern Highway and the extension of the Coastal Rail Line from
Matara. Additionally several other developments including industrial, commercial,
administrative, sports, tourism and residential developments are also being planned.
1.1 Objectives of the Study
The main objectives of this Study as per Terms of Reference issued by the Road
Development Authority are:-
a) To identify the long-term demand for transport for the developments proposed
for Hambantota.
b) To assess the requirements for transport capacity development to serve such
increase in demand and a strategic intervention.
c) To investigate the adequacy of the proposed road network development and
to make recommendations thereof.
d) To carry out a preliminary design of each recommended road link and provide
typical road sections and costs.
e) To carry out an assessment of socio economic viability of the network as a
whole.
![Page 20: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/20.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
1-2
1.2 Study Area of the Proposed Project
The Figure 1-1 of the area under the RNHDP shows the Study Area of the Proposed
Project. It also shows the proposed developments. The proposed developments in this
area include the:
Hambantota Port Development Project
Mattala International Airport Development
Sooriyawewa International Cricket Stadium
Railway Extension to Kataragama
Hambantota Administrative Complex
Ridiyagama Safari Park
Figure 1-1 : Study Area of the Proposed Project
![Page 21: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/21.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
1-3
1.3 Scope of Work
The National Road Network in this area is to be re-developed with a number of new road
links including a by-pass to Hambantota Town. The increased traffic from the
aforementioned developments is expected from many parts of the country. Thus the
road network in the region requires to be investigated for adequacy and where it is found
to be inadequate to be earmarked for development in a stage basis corresponding with
the expected traffic demands.
The road network also is to take in to account the overall transport efficiency and
accommodation of different modes of transport. This should include the consideration of
priority measures for public transport, non-motorised transport in city areas as well as rail
connectivity to the major transport generators. It should also consider the contribution of
the regional development within the on-going national road network development.
The Road Development Authority had identified seventeen (17) roads aggregating to a
length of 290.2 km and proposed either for construction as new links or for widening and
improvement. The list of roads, which has been proposed by the RDA is presented in
Table 1-1 below and illustrated in Appendix 1.
Table 1-1: List of Roads Proposed by RDA
No. Name of the RoadLength
(km)Proposed Intervention Work done up to June 2010
1Outer Circular
Highway I6.2
Construction of a new 4
lane road
Survey & Design completed,
Construction work
commenced
2
Hambantota-
Gonnoruwa-
Meegahajandura
32
Construction of a 4 lane
road with a reservation
for a 6 lane road
Part of Survey Completed
(10 km), Action has been
taken to commence the
construction work
3
Sooriyawewa-
Meegahajandura-
Kumaragama
18Widening to 4 lanes
(remaining section)
Construction of 0 - 9 km
completed for 4 lane, Survey
works for balance section will
be done through Survey
Department
![Page 22: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/22.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
1-4
No. Name of the RoadLength
(km)Proposed Intervention Work done up to June 2010
4
Andarawewa-
Udamattala-
Padawkema
13 Not decided
A new trace has been
identified to minimise the
damages to houses, Land
Survey work is in progress
5Udawalawa-
Thanamalwila40
Construction of a 2 lane
road with a reservation
for a 4 lane road
Feasibility study and Survey
works completed, Detail
design is in progress
6Moraketiya-
Sooriyawewa12
Initially a 2 lane road will
be constructedSurveys to be done
7Hambantota
Bypass Road7
Section of the road
already in use (2 lane), It
is expected to widen the
road to 4 lanes with land
reserved for 6 lanes.
Design for 2 lane completed
8Andarawewa-
Sooriyawewa7
Construction of a 2 lane
road with a reservation
for a 4 lane road
Surveys to be done
9Bopale Junction-
Kiriibbanara8.5
Construction of a 2 lane
road with a reservation
for a 4 lane road
Surveys to be done
10
Embilipitiya-
Moraketiya-
Kiriibbanara-
Udamadura
16
Construction of a 2 lane
road with a reservation
for a 4 lane road
Surveys to be done
11Outer Circular
Highway IINot decided
There are problems in
locating the road trace due to
elephant corridor
12Udamattala-
Thanamalwila18
Construction of a 2 lane
road with a reservation
for a 4 lane road
Surveys to be done
![Page 23: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/23.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
1-5
No. Name of the RoadLength
(km)Proposed Intervention Work done up to June 2010
13CGHW Road (243
km to 260 km)17 Widening to 4 lanes Surveys to be done
14 Lewaya Road 3.5 Widening to 4 lanes Surveys to be done
15Sooriyawewa-
Padalangala12 Widening to 4 lanes Surveys to be done
16Sooriyawewa-
Mirrijjawela24
Initially widening to 4
lanes, land will be
reserved for 6 lanes
Surveys completed
17
Southern
Expressway
Extension
74
Construction of a 4 lane
road with a reservation
for a 6 lane road
Expressway Standards
Economic feasibility is
completed, Preliminary
Environmental Assessment
is in progress, Arrangements
have been made to
commence the survey work
and detailed design
The Scope of work of the feasibility study for the proposed road links comprises of three
phases as follows.
Phase I: To assess the overall future transport requirements for the Hambantota
International Hub and the requirement of the road network and other land transport
facilities.
Phase II: To prepare a socio-economic feasibility study for the recommended road
network development. In this respect the Consultant shall assess the adequacy of the
road network to satisfy long-term development goals in terms of accessibility between
regions and town centres, traffic carrying capacity, mobility, and road safety aspects.
The traffic demand will be for years 2012, 2022 and 2032.
Phase III: To provide preliminary designs and typical cross sections and costs for the
recommended road network including requirements for public transport, non-motorised
modes of transport, parking and intersection controls.
![Page 24: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/24.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
1-6
1.4 Reporting
The following was agreed with RDA.
i. PROJECT INCEPTION REPORT
Within one (01) month of the commencement of, the Consulting Services, the
consultants will submit three (03) copies of Inception Reports with a soft copy to
RDA. The report shall give in brief the factual information on the work performed
and problems encountered during the reporting period and the proposed
methodology of study.
ii. PRESENTATION ON PHASE I
The DFR for Phase I shall be submitted in three (03) copies and a soft copy at the
end of the two (02) months from the date of commencement covering items in
Phase I of the Scope of Work.
iii. DRAFT FINAL REPORT PHASE II
The DFR for Phase II shall be submitted in three (03) copies and a soft copy at the
end of the three (03) months from the date of commencement covering items in
Phase II of the Scope of Work.
iv. DRAFT FINAL REPORT PHASE III
The DFR for Phase III shall be submitted in three (03) copies and a soft copy at the
end of the five (05) months from the date of commencement covering items in
Phase III of the Scope of Work.
v. DRAFT FINAL REPORT
Draft Final Report shall be submitted in 3 copies and soft copy at the end of the six
(06) months, summarising in detail all work performed, methodologies applied,
findings and recommendations of the Study and Preliminary Engineering Design as
well as highlighting the various aspects of the Study. This may have to be followed
by a presentation of the project.
The following submissions/presentations have been made to date:
Inception Report
Presentation on Phase I and Phase II
Working Paper on Phase III
Draft Final Report
![Page 25: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/25.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
2-1
CHAPTER 2 DATA COLLECTION
2.1 Maps
The identification of the road network for the improvement is done by investigating the
maps produced with GIS. However the digital Topographical Maps of the project area in
a scale of 1:50,000 were used for plotting the preliminary traces for new road sections
with the aid of geo-referenced co-ordinates which have been cross checked with GPS
readings on the field.
2.2 Reports
Urban Development Authority, Airport & Aviation Services (Sri Lanka), Sri Lanka Ports
Authority and Road Development Authority have conducted several studies on
respective components of the Greater Hambantota Development Plan. The substances
of such study reports were taken into consideration when finalising the road network and
the levels of capacity requirements. The summary of references is as follows:
1. Situational Report on Development Plan For Greater Urban Development Area
(Volume I) , Urban Development Authority, July 2009
2. Report on Proposed Hambantota Harbour Pre-Feasibility Study, Southern
Development Authority of Sri Lanka, February 1997
3. Development of Airport at Mattala, Sri Lanka, Environmental Impact
Assessment Report, The Airport and Aviation Services (Sri Lanka) Ltd.,
December 2008
4. Draft Report on Proposed International Cricket Stadium Cricket Academy at
Sooriyawewa, Urban Development Authority, 2008
5. Strategic Environmental Assessment for the Greater Hambantota Development
Plan , Phase I-Proposed Zoning Plan (Final Version), Central Environmental
Authority of Sri Lanka, January 2010
![Page 26: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/26.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
2-2
2.3 Traffic and Transport Data
No new traffic surveys have been conducted since the new developments in the
proposed Hambantota Development Plan were of a much larger magnitude than the
extrapolation of current traffic demand or its patterns would allow.
However, findings of the traffic surveys carried out in January 2007 for the Feasibility
Study of the Extension to the Southern Highway were adopted for preliminary analysis.
The adopted information included roadside origin destination (OD) surveys and manual
classified counts (MCC).
2.3.1 Roadside Traffic Survey
The roadside surveys for both OD and MCC counts in both directions of the road at each
location and the dates on which they were carried out are given in Table 2-1. The
duration of OD surveys is 12 hours from 7.00 a.m. to 7.00 p.m. The duration for MCC
surveys is also 12 hours and extended to 24 hours for a selected few locations for the
purpose of making some representative 24 hour counts.
Table 2-1: Traffic Survey Program
Date
(2007)Day Road and Survey Location
OD
MCC
Hambantota District 12 hr 24 hr
21st Jan SundayOn A2 Road at 235
thkm (between
Ambalantota and Hambantota)Yes Yes Yes
22nd Jan MondayOn A2 Road at 268
thkm (between
Thanamalwila and Lunugamvehera)Yes Yes
23rd Jan TuesdayOn Nonagama - Embilipitiya Road at
68th
kmYes Yes
24th Jan WednesdayOn A2 Road at 205
thkm (between
Tangalle and Ranna)Yes Yes
Matara District
25th Jan ThursdayOn Matara - Hakmana Road (between
Yatiyana and Kirinda)Yes Yes
26th Jan FridayOn A2 Road at 176
thkm (between
Kottegoda and Dickwella)Yes Yes Yes
![Page 27: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/27.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
2-3
The following Table gives the summary flow of these counts expanded to 24 hours.
Table 2-2: Summary of Flow of Traffic Counts
Road and Survey Location ADT
Hambantota District 12 hr 24 hr
On A2 Road at 235th
km (between Ambalantota and Hambantota) 4,354 5,391
On A2 Road at 268th
km (between Thanamalwila and Lunugamvehera) 1,794 2,379
On Nonagama - Embilipitiya Road at 68th
km 2,074 2,760
On A2 Road at 205th
km (between Tangalle and Ranna) 3,389 4,552
Matara District
On Matara - Hakmana Road (between Yatiyana and Kirinda) 3,190 4,207
On A2 Road at 176th
km (between Kottegoda and Dickwella) 4,868 6,999
2.4 Social Assessment
A Social Assessment Survey has been carried out by the Sociologist of the Study Team
to investigate the effects of the past, current and the future developments.
As the proposed road development programme hasn’t forged ahead to a stage that
requires a comprehensive Social Impact Assessment (SIA), the focus has been limited to
a Rapid Social Assessment (RSA). The RSA has been focused on identifying the
general socio-economic environment through the proposed road traces based on the
following factors:
1. Identification of demographic features (population) of the Divisional Secretariat
(DS) Divisions based on the roads under consideration.
2. Identification of the approximate number of existing buildings based on the usage
(housing, business premises, economic centres or public places) along each of
the roads under consideration.
3. Identification of the trends and community perceptions of the real estate property
market with respect to the ongoing and announced development programmes.
4. Identification of the land use information along the proposed road traces.
5. Identification of archaeological, cultural and religious locales along the proposed
road traces.
6. Evaluation of the impacts on connectivity through the proposed road
developments and the degrees of significance.
![Page 28: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/28.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
2-4
The understanding of the general socio-economic environment gathered through the
RSA will be useful for making policy decisions on the impact on the likelihood of affecting
houses, lands, economic and social infrastructure and physical and cultural properties of
the affected people, when the road development programme is implemented.
2.5 Preliminary Field Observation
The study team of the University of Moratuwa initially observed the road network that has
been proposed by RDA during their first field visit on 26th and 27th May 2010 with the
participation of regional officials from RDA and UDA. Also a meeting had been called
during the field visit with the regional officials from RDA and UDA to discuss their
development plans in related to the International Hub Development (IHD) for
Hambantota. With their assistance the study team was able to identify the different
development programmes together with their functionalities and capacities.
By analysing the information gathered during their first field visit, the study team was
able to establish a preliminary road network unreservedly incorporating the development
plans of RDA and UDA together with the wildlife concerns. However there was an
intention of consulting stakeholder agencies during the second field visit.
Subsequently, the study team of the University of Moratuwa made their second field visit
jointly with several RDA officers on 8th and 9th June 2010 and hold a stakeholder
consultation program at the District Secretariat, Hambantota under the patronage of the
District Secretary of Hambantota. The original proposals of RDA have been unfolded for
the stakeholders to examine, comment and air their concerns. The specific inputs from
UDA, Department of Wildlife Conservation, Ceylon Electricity Board and Mahaweli
Authority had been duly recorded.
At the end of the second field visit, the study team was able to propose a revised
network of roads to serve IHD of Hambantota by further strengthening the road network
with the aim of achieving regional and national integrity.
Observations recorded and images captured during first and second field visits are given
in Annex 1.
There were several additionalsite visits related to the proposed preliminary road network
and possible alternatives.
![Page 29: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/29.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-1
CHAPTER 3 PROJECT IMPACT AREA
The study team undertook four early reconnaissance trips across the project area to
determine the layout of the proposed roads, the land utilisation and constraints that exist
for the construction of the roads.
The Project Impact Area of this project is considered as the area referred to as the
Greater Hambantota Development Area which is wholly within the district of Hambantota
and includes the DS Divisions of Hambantota, Ambalantota, Sooriyawewa,
Lunugamvehera and Tissamaharama.
3.1 Geography & Climate
The expanse of the Greater Hambantota Development Area spreads over 113,000 ha,
located in the Southern Province of Sri Lanka. This region consists of mostly undulating
plains, isolated highlands with outcrops of eroded rocks, which are scattered in the area.
This area is located in the heart of south eastern dry zone. The annual average rainfall
varies from 800 mm along the southern coastal boundary to 1200 mm along the northern
boundary. A larger percentage of the average annual rainfall in this area receives during
north-east monsoon between October and December each year. Free water surface
evaporation exceeds precipitation in nine months over the year. Maximum rainfall
figures are quite usual during November, January and May every year, while the driest
period is typically during the month of August. Average annual temperature in this area
varies between 80oF – 81oF (26.6oC – 27.2oC)1.
3.2 Population
Greater Hambantota area consists of Seven (07) Divisional Secretariat (DS) Divisions;
five from Hambantota District plus selected Grama Niladhari (GN) Divisions of
1Source: Greater Hambantota Area, Development Plan, UDA, July 2009
![Page 30: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/30.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-2
Thanamalwila DS Division and Sevanagala DS Division. Population density of the area
ranges between 200-500 persons per sq. km.
Table 3-1: Population of Greater Hambantota Area (2001)2
D.S Division Total population Male Female
Sooriyawewa (21) 35,529 18,369 17,160
Hambantota (30) 46,757 23,830 22,927
Ambalantota (13) 17,526 9,059 8,467
Tissamaharama (15) 17,957 9,266 8,691
Lunugamvehera (29) 21,268 10,980 10,288
Thanamalwila (5) 7,989 4,224 3,765
Sevanagala (14) 36,820 19,217 17,603
Total Greater Hambantota Area 183,846 94,945 88,901
The population projections used by the Greater Hambantota Development Plan are
given in Table 3.2
Table 3-2: Projections for Population3
Name of the DS 2001 2010 2020 2030
Hambantota with Harbor Development 46,757 53,461 79,135 128,903
Lunugamvehera with Airport Development 21,268 24,318 35,996 58,634
Sooriyawewa 35,529 40,624 48,558 59,192
Ambalantota 17,526 20,039 26,931 39,864
Tissamaharama 17,957 20,532 23,828 27,653
Sevanagala (14) 36,820 42,099 48,858 56,702
Tanamalvila (5) 7,989 9,135 10,602 12,304
Total 183,846 210,208 273,908 383,252
3.3 Land use Pattern in the area
The land use pattern of the area is explained in the Table 3-3. It is found that 58% of the
land is scrub and vacant whilst 24% of the land is forest and sanctuaries. On the other
2Source: Census of Population and Housing 2001
3Source; Greater Hambantota Development Plan
![Page 31: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/31.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-3
hand, developed land amounts to only 6% out of 113000 ha. This includes homestead,
roads and other utilities and public and semi public zones.
Table 3-3: Land Use in the Area4
Land Use Extent (Ha) Percentage (%)
Paddy Land 5,656 05
Residential 3,960 04
Public & Semi Public 1,320 01
Roads & Other Utilities 1,210 01
Scrub & Vacant Land 64,880 58
Forest & Sanctuaries 27,500 24
Water Bodies 6,187 05
Salt pans 2,287 02
Total 113,000 100
3.4 Economic Activities
The major economic activities of the area have been identified as follows5:
Agriculture: The main livelihood activity of this area is agriculture, and paddy cultivation
is the main source of income. The geographical factors such as flat terrain, clear sun
light and alluvial soil has created a suitable background for paddy cultivation. 9.3% of
the national rice production is from Hambantota District. Highland cultivation occupies a
very important place in the agricultural pattern of Hambantota.
Many major and minor irrigation schemes are there to irrigate the paddy and crop
cultivation in the area, namely Lunugamvehera reservoir, Uda Walawe reservoir,
Rediyagama tank, Bandagiriya tank, Tissawewa, Debarawewa, Yodawewa, Weerawila
wewa, Pannegamuwa wewa, etc. Apparently there are many tanks in the area probably
due to the unavailability of sufficient rainfall throughout the year. However the farmers
have moved to subsidiary crops cultivation rather than traditional crops due to lack of
market opportunities. In areas where proper irrigation facilities are not available crops
such as Bran (Kurakkan), maize, corn etc. are cultivated.
4Urban Development Authority, 2001
5Greater Hambantota Area Development Plan, UDA
![Page 32: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/32.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-4
Animal Husbandry: Animal husbandry is another important economic activity in the
area. The geographical background, grasslands, scrubs and meadows has become a
major assistance for the success of this venture. Half of the produced milk is brought to
the milk collecting centres to process milk, yoghurt or milk powder while the balance is
kept to process curd since the curd of Southern Sri Lanka (Ruhuna) is famous all over
the island.
Fisheries Industry: Fisheries industry in this area could be categorised into 3 groups.
1. Sea Water Fisheries Industry
2. Fresh Water Fisheries Industry
3. Brackish Water Fisheries Industry
Fishery villages are distributed all over the Greater Hambantota coast and most of
theircatchis transported to the wholesale and institutional buyers in Colombo.
Salt Industry: Salterns in Greater Hambantota account for around 60% of the national
productionof salt.
Small Scale Industry: Small scale industries of the Greater Hambantota area consist
with following types of industries,
I. Production of Bricks
II. Lime Industry
III. Gem Mining
IV. Pottery Industry
V. Handicrafts and other Cottage Industry.
Tourism Industry: The Greater Hambantota area is emerging rapidly as a major tourist
destination in Sri Lanka. Among the visiting tourists, majority of them stay in coastal
resorts, some visiting wildlife and bird sanctuaries as well as archaeological and religious
sites.
Greater Hambantota has many tourist attractions. Sandy beaches, Bundala Bird
Sanctuary, Sithulpawwa temple, Kirinda rock, Ussangoda geological site, Kalametiya
Bird Sanctuary, Sooriayawewa Hot springs and Kataragama religious places are the
![Page 33: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/33.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-5
major tourist attractions in the area. These areas are equally famous among both local
and foreign tourists. Accordingly the tourism industry of the area can be categorised as
follows.
(a) Coastal Tourism
(b) Cultural Tourism
(c) Eco Tourism
The folloving locations can be highlighted under each category as locations that attract
either local or international tourists.
Coastal Tourism Cultural Tourism Eco Tourism
Palatupana
Hambantota
Ussangoda
Godawaga
Gotapappatha Vihara
Bandagiiya Temple
Ramba Vihara
Yahangala
Kahambagala
Madunagala Arannaya/ Nimalawa
Uda Walawa
Palatupana
Bundala
Bandagiriya
Meegahajandura
There are several places, available within the Greater Hambantota and surrounded area
for recreation activities. Listed below are some of the recreational places available in the
area.
- Yala National Park
- Nimalawa Forest
- Kalamatiya Sanctuary
- Bundala Sanctuary
- Weerawilla Bird Sanctuary
- Lunugamvehera Sanctuary
- Hambantota Beach
- Palatupana Beach etc…
![Page 34: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/34.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-6
3.5 Greater Hambantota Development Plan
The Government of Sri Lanka in 1994 adapted the strategy for accelerated economic
growth of southern region by introducing new concept based on an international harbour.
Accordingly this project was placed a high priority of government agenda. This city first
conceptualised by the Southern Development Authority with a view to provide more
employment opportunities within southern Sri Lanka and to offer enormous economic
opportunities for investors while accelerating the development of new enterprises in the
maritime field. It is now being planned by Urban Development Authority under powers
vested by the UDA Act No. 41 of 1978.
3.5.1 Greater Hambantota Development Area
The Greater Hambantota Area is being developed with an international seaport at
Hambantota as its main economic generator, located in the southern dry zone of Sri
Lanka. It spreads over an area of 113,000 ha that lies between Walawe River and
Kirindi Oya. The defined area for the development plan covers DS Divisions of
Sooriyawewa (21 GNDs), Hambantota (30 GNDs), Ambalantota (13 GNDs),
Thanamalwila (5 GNDs), Sevanagala (14 GNDs), Tissamaharama (15 GNDs) and
Lunugamvehera (29 GNDs). This area has been declared by UDA gazette no. 1090/5
under Section 3 of the aforesaid law on 26th July 1999. A zoning plan has been
prepared as a precursor to the city development plan under the provision of section 8 of
the said law.
3.5.2 Strategy for Development
One of the strategies adopted for developing Greater Hambantota is the active
development through the establishment of an international seaport. Naturally the vicinity
of a seaport can be effectively used to create a city which will grow in a planned manner.
This strategy is being implemented for Hambantota in a successful way.
The above strategy conforms to the Government policy of encouraging the emergence of
urban centres for achieving the goal of balanced regional development. Greater
Hambantota will be developed as a nature city. It will enhance to higher environment
standards. Furthermore, it will be an international business investment and industrial
centre. It will be the main transportation hub with an international seaport and an airport.
It will also be located in a very rich cultural area. Therefore, it can be developed as a
centre promoting international socio-cultural activities.
![Page 35: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/35.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-7
3.5.3 Potential for New Economic Activities
The available natural resources would provide sound economic base for new
development in Hambantota since large extent of underutilised land is available in
efficient urban structure that could certainly be designed conforming to an effective
development plan. This could clearly be seen in the new town centre development at
Siribopura.
In Greater Hambantota area, a number of large scale projects such as an oil refinery, a
road network, a botanical garden, and the town centre development are being
implemented in parallel to the seaport project development. This will enhance the
economic growth of the area as expected in the early stages and incorporate an
accelerated growth of transportation, communication, tourism facilities and urban
development.
The study team has visited and studied the proposed development sites under the
Greater Hambantota Development Plan that include several components such as:
Commercial Establishment
Convention Centre
Administrative Complex
Playgrounds and Recreational areas
Seaport Development
Airport Development
Extension of the Railway
Extension of the Southern Expressway
Oil Refinery
Tsunami Housing Scheme
![Page 36: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/36.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-8
3.6 Current Status of Development
The present state of these development efforts are as follows:
3.6.1 Hambantota Seaport Development
The primary industry that is to be the backbone of the development of the Hambantota
District is the construction of the proposed Seaport at Hambantota which was first
identified in the Shipping Policy of 1997.
Figure 3-1: Location of Seaport and Proposed Administrative Area in Hambantota6
The immediate purpose of the project is to establish an oil import/ bunkering terminal to
cater to the needs of ship bunkering at the route south of south of Sri Lanka and a range
of port traffic requirements of the local community, initially in a limited capacity, as well
as general cargo for other locations in Sri Lanka.
In the long run Hambantota is to be developed as a major industrial port in the southern
province of Sri Lanka. The port is expected to enhance the export earning of the country
6Source: Greater Hambantota Area Development Plan
![Page 37: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/37.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-9
via improvements of maritime transportation and the establishment of export companies
within a Free Economic Zone (FEZ).
The objective of the proposed port is to become one of the Sri Lanka's major
multipurpose ports and to be a gateway to India and surrounding countries.
According to the Feasibility Study that has been completed in June 2006 (Ramboll in
association with LHI and RDC and others), the proposed port has a growth potential for
50 to 100 years. The reasons for a successful harbour at Hambantota have been
identified as:
Location near the international shipping routes passing south of Sri Lanka,
Deep water near to the shoreline for ship access to the port.
Availability of abundant and inexpensive land for port related development
activities.
The development area of the port is confined to an area measuring 5 km east to west
(233 km to 238 km on the A2 Road) and 4 km in the north-south direction. This covers
an extent of 2,000 hectares. Based on the identified four stage development plan, a land
use plan has been developed as per the following land use requirements up to the year
2040 (Table 3-4). However, there is a prospect that the project will be accelerated to
complete within 30 years as per the ongoing accelerated program.
Table 3-4: Land Use for Development of Hambantota Port
Complete Port and
HarbourBasin AreaPort Area
Stage 1A (up to 2010) 236 hectares 146 hectares
Stage 1B (up to 2015) 330 hectares 200 hectares
Stage 2 (up to 2025) 650 hectares 320 hectares
Stage 3 (up to 2040) 1475 hectares 920 hectares
The Urban Development Authority has identified that Southern Sri Lanka (Ruhuna) as
one of the least urbanised areas in the country. However, with the Hambantota Port
development and the resulting potential for new industries, urbanisation can be as higher
as 40% over a 10 year period. Most influential increase would be through the rural
migration to urban areas especially from hinterland areas of Hambantota District.
![Page 38: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/38.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-10
The Port development area include the areas for cargo storage, internal roads,
communication systems, utilities, perimeter roads and the areas for the support services
including a new shipyard. It is expected that in the year 2015 only 330 hectares or
16.5% of the allocated land area for port development will be utilised. By the year 2040
the land utilisation is expected to increase up to 73%. The port development plan
envisages that the land presently developed under the Walawe left bank project has to
be utilised for port related development activities beyond the year 2040. Thus lands
lying to the north of the new east-west road to be constructed which has hitherto been
developed for agricultural activity may be required for port related activities beyond this
time.
The northern boundary of the Port will be the above mentioned east-west road that link
the existing Mirijjawila-Sooriyawewa Road and Hambantota-Gonnoruwa Road where the
new Ruhunupura Town Centre is to be constructed. The Western end of the port will be
the Mirijjawila-Sooriyawewa Road itself also known as the ‘100 foot road’.
The pollution free activities of the port such as Ro-Ro facilities for vehicle handling as
well as container and passenger terminals will be located to the eastern part of the port.
More sensitive activities such as handling of oil and coal, clinker and cement are to be
located towards the western end. The feasibility study has identified the potential for
several port-related activities such as shipyards, ship supplies and repair companies,
refineries, power plants etc. to come up in the long-term.
According to expectations set out in the feasibility study, the Hambantota Port will
function as an industrial seaport in the start up phase provided that individual cargo
generating industries can specifically be attracted to set up their businesses in or
adjacent to the port area. In the medium term, the port is expected to handle any
overflow cargo arising from reaching maximum utilisation in the existing ports of
Colombo, Galle and Trincomalee. Accordingly, it had been anticipated that7 the
expected economic growth rate to improve from the prevailing value of 6% p.a. to around
8% p.a. in year 2010 and thereafter. In the long-term horizon it is expected that
Hambantota would evolve to become the most important multi-purpose port that could
handle over 50% of Sri Lanka’s total cargo of all types.
7The Government policy paper Medium Term Budgetary Framework by the Ministry of Finance & Planning
assumes that the Sri Lankan economy will increase rapidly in the short term reacing 8.3% percent by 2009
from 6% in the year 2005.
![Page 39: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/39.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-11
This study strongly considers that the hinterland of Hambantota has great potential to
develop around the port and Hambantota District in particular and as a result, the
Southern Sri Lanka (Ruhuna) in general will become an industrialised area. Ruhuna is
considered as having the greatest potential due to the availability of land, the most
important factor of production in a densely populated country like Sri Lanka. Additionally,
the ever increasing congestion in Colombo area while decreasing the potential of its
expansion, justifies the need of developing Hambantota as a port-centred industrial
district.
It is also noted that previous development attempts such as those initiated through the
Southern Development Authority in the 1990s, and more recently under the Ruhuna
2000 program have really not taken off due to constraints in access to and within the
province and the absence of other infrastructure. Both the private sector entrepreneurs
as well as international donors are said to be waiting for a clear signal from the
government in terms of a properly formulated development plans for the region before
investing in the long-term.
The construction of the new port commenced on 15th of January 2008 and the filling up
of water commenced on 15th of August 2010. It has resulted in the opening of a sea inlet
to the new port near the 235 km post on the A2 Road. An alternate road has already
been constructed by the RDA northwards of the port in an east-west direction.
Within the initial years of operation of the port that has scheduled to open in November
2010, it is expected that the following cargo volumes and activities will be handled by
2013 onwards:
Dry and break bulk cargo -2.7 million MT (2013 onwards)
Vehicle imports – 110,000 units (2013 onwards)
Liquid cargo – 1.3 million MT (scheduled for2015 onwards)
Supply of bunker fuel and
Container movements from 2023 onwards
For bunkering services to be successful the cost of such services have to be comparable
with other competitive ports in the region such as Singapore, Fujairah, Tianjun Pelepas
and Dubai. Presently, bunker prices in Port of Colombo are said to be significantly
higher than that of the most of these competing ports. Thus the location of these
![Page 40: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/40.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-12
services is critical in order to minimise the cost of production of these goods and services
and to make the port flourish in Hambantota.
The estimated traffic for the Port of Hambantota is shown in Table 3-58. This has been
estimated on basis for the growth for Sri Lanka and the overflow over the existing ports
of Colombo, Galle and Trincomalee.
Table 3-5: Estimated Traffic at Port of Hambantota
2010 2013 2020 2030 2040
Dry and Break Bulk cargo (Tonnes million) 0 2,745 8,889 13,405 15,456
Vehicle Handling m(units 000) 53 110 213 224 203
Liquid Bulk (Tonnes million) 0 0 4.09 8.34 9.77
Containers (TEUs 000) 0 0 0 6,426 19,872
While, break bulk cargo, vehicles and liquid cargo would be used for domestic
consumption, a significant proportion of containers may be available for trans-shipment.
The yards for storage of these containers would also have to be provided within or
adjacent to the port which would further consolidate the competitive advantage of the
Hambantota Port over the Colombo Port.
In terms of cargo which characteristically have origins and destinations outside of the
port premises there is a certain disadvantage if the port is not connected through
distribution networks, to destinations which are primarily located in the Western Province
and other urban regions in the North Western, Central and Sabaragamuwa Provinces.
Therefore, a network of fast and efficient road and rail connections is a must for
Hambantota to consolidate its position as a primary port in the country.
However for Sri Lanka this will be an uphill battle, as the contribution from the industries
to its economy has never been a dominant factor. In fact it remains within a region of
24% to 30% during the last 4 decades.
At present, a significant contribution to industries is from the apparel sector.
Geographically, this is concentrated in the districts of Colombo, Gampaha and Kalutara,
which are the districts that are closest to the Port of Colombo. However, according to the
8Source: HambantotaPort Pre-feasibility Study, Ramboll et al. June 2006
![Page 41: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/41.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-13
Central Bank9 report, these areas are so congested that any further growth of the
industrial sector in these districts is highly unlikely.
Table 3-6: GDP and Industrial Contribution in Sri Lanka 1970-2005
YearGDP
Rs. billion
Contribution of
Industry to GDP
Rs. billion
% Contribution
1970 13.17 3.14 24%
1980 62.25 18.45 30%
1990 290.60 75.56 26%
2000 1,125.25 306.98 27%
2005 2,452.78 740.15 30%
2008 4,410.68 1,295.47 29%
Thus the opening of the Port of Hambantota will augur well for the potential development
of industries in Sri Lanka, where new lands that could be made available for new
industries are available quite freely in close proximity to the port.
The following individual industries appeared to be the most likely to be attracted to this
region when considering the potential of the long-term growth of Hambantota as an
industrial region.
Cement Industry: based on import of raw material and distribution to local markets.
Wheat Flour Processing: A potential site as an alternative location for the industry
that might complement Trincomalee as the only port to handle this operation at
present. This too would generate distribution activity by land to consumption
centres particularly in the Western, Southern, Uva, Sabaragamuwa and Central
Provinces.
Fertilizer: Being closer to agricultural areas for distribution and adequate space for
warehousing, Hambantota is likely to become a better location as warehousing
has been a problem now due to the congested roads leading to warehouses in
the north of Colombo. Thus the transport links to agricultural areas such as
Southern, Uva and Eastern Provinces are important.
9Central Bank Staff Reports Vol 33, 2003, Rupa Dheerasinghe
![Page 42: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/42.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-14
Car Imports: Adequate warehousing facilities would enhance imports to be handled
at the port so that distribution to different parts of the island takes place from
there.
Fuel Imports: This is currently handled only at Colombo, where the Ceylon
Petroleum Corporation has its refinery at Sapugaskanda. With the deregulation of
the industry to three players, it is quite possible that at least one of the private
players would want to develop their refining, storage and distribution facilities at
Hambantota as a counter magnet for Colombo. This too would result in heavy
freight movements to consumption areas identified earlier.
The trade opportunities have now opened up with India under the SAFTA (South Asian
Free Trade Agreement) enables companies of Indian origin to set up industrial plants in
these areas and export from these areas tax-free to other international markets. As
such, the potential for industrial development in the Hambantota district remains quite
favourable for the future.
3.6.2 Tsunami Housing Scheme
Since the tsunami in 2004, the land that was originally ear marked for Ruhunupura has
been developed for housing. Presently, over 1,600 houses have been constructed which
is considered to be in excess (around 1/3rd) which will then be available for new jobs and
families that would migrate due to new developments arising from the Hambantota
Development Plan. These houses have been built according to the guidelines defined
by the UDA and the project contains a number of community facilities such as schools
and health centres. Most of these houses are found along Hambantota-Gonnoruwa
Road in the area identified as Siribopura.
3.6.3 Mattala International Airport
The only document available with respect to the study of the Mattala International Airport
(UIA) is the updated Environmental Impact Assessment Report for the 2nd International
Airport at Udamattala in Hambantota District, prepared by the Airport and Aviation
Services Ltd (AASL) dated December 2008. Mattala is located 20 km north of
Hambantota and 10 km away from Gonnoruwa.
The decision to construct a second international airport in Sri Lanka has been long-
standing. Several locations have been examined previously, and the location in
Hambantota district was chosen in 2005. Previous locations in Kala Oya and Weerawila
![Page 43: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/43.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-15
were examined and later abandoned due to environmental reasons. The aviation
demand calculated for Weerawila Airport is shown in Table 3-7 and we can reasonably
assume that Mattala also will have the same demand.
Project Justification
1. Currently the only runaway available for international commercial carriers in Sri
Lanka is that of Bandaranaike International Airport (BIA), Katunayake.
2. In the case of bad weather, technical problems or even a staff strike at the BIA,
international carriers are forced to continue to Trivandrum, Chennai or Male as
alternative landing bases due to the lack of an “in-state” alternative landing strip.
These alternative aerodromes are 194, 350 and 439 nautical miles away
respectively from BIA while the proposed Mattala airport is only 100 miles away.
Thus all inbound flights need to carry considerable additional fuel reducing the
total potential payload they can carry.
3. With a closer airport, airlines will carry a reduced fuel load which will enable the
carrying of additional passengers or cargo which will result in considerable
increase in revenue. This increase allows for the imposition of a levy on all
airlines operating to BIA rationalised as a percentage of the saving or additional
earnings of the airlines due to the availability of a closer alternative airport.
4. Avoidance of the additional fuel from the inbound flights would require additional
refuelling for the departing flights (amounts vary between 400 kg for A320 and
4,800 kg for A340 as per Sri Lankan Airlines sources). Thus there will be an
increase of the sales of fuel.
Project Objectives
1. Enhance the viability of the enterprise, catering to business and commerce in the
whole of the Asia Pacific Region.
2. To be a catalyst in the development of the New Greater Hambantota Area.
3. To support the growth and give considerable economic benefits to Sri Lanka.
3.6.4 Extension of Southern Expressway
The continuous development of Colombo is a prime need concerning the future national
development as it has an already developed harbour, infrastructure and other external
economies. At present Colombo receives comparatively large amount of investment
![Page 44: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/44.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-16
both from the public sector and private sector. This project seeks to extend the Southern
Extressway presently under construction up to Godagama off Matara up to Hambantota.
This project seeks to:
To incorporate the proposed development that would otherwise be located in or
around Colombo city to industrial zones located at the identified interchanges.
To guide, facilitate and regulate development in an integrated manner to achieve
the planned development along the Southern Expressway Corridor.
To identify potential lands for future development in keeping with the demands
created by the Southern Expressway.
3.6.5 Extension of Southern Railways
A major rail link is planed from Matara to Kataragama passing through the Hambantota
town. Three alternative traces were investigated by the Sri Lanka Railways (SLR) and
the feasibility studies recommended a rail track with a length of 110 km at an estimated
cost of US$ 50 million.
The extended rail line will be located close to the coast and will provide for pilgrimage
traffic to Tissamaharama and Kataragama. The transport of freight from the seaport of
Hambantota to Galle, Colombo and to the hinterland will also be facilitated.
![Page 45: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/45.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-17
Table 3-7: Aviation Demand Forecast for the Proposed Weerawila Airport10
Traffic
Year
Total
Demand
000s
2010 Total
Demand
000s
2015 Total
Demand
000s
2020 Total
Demand
000s
2025
BIA WIA BIA WIA BIA WIA BIA WIA
% of National
Traffic 100% 99.0% 1% 100% 97.0% 3.0% 100% 95.0% 5.0% 100% 95.0% 5.0%
Paxs
(Nos.)
MG 6,494 6,494 64 9,185 8,909 275 12,829 12,187 646 17,924 17,027 896
HG 6,578 6,512 65 9,612 9,323 288 13,870 13,176 693 20,023 19,021 1,001
Cargo
(MT)
MG 282 279 2 460 446 13 738 701 36 1,183 1,123 59
HG 287 284 20 491 476 14 824 782 41 1,382 1,312 69
Aircraft
(Nos.)
MG 45.9 45 0.5 64.3 62 2 89 84 4 123 116 6
HG 46.5 46 0.5 67.4 65 2 96.5 91 5 138 131 7
10Forecasted figures extract form the feasibility report of BIA Development. Stage II of Phase II Prepared by Japan Airport Consultant Inc:
![Page 46: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/46.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-18
Also, there will be a rail route from the Hambantota seaport to the airport for possible
express services for freight and there will be connections to the city centre. The railway
will be established parallel to the access controlled highway. Sufficient space will be
provided between the road and railway to establish utility lines (power, water, fuel or
other services).
There will be road/rail terminals at the airport, the city centre and the seaport for
passenger interchange and goods transfers.
3.6.6 Proposed Administrative Complex
During the 2004 Tsunami, the town of Hambantota was completely destroyed. Hence
the need of building a new town centre to accommodate all residential commercial and
administrative activities along with a large housing scheme to house the affected families
of the Tsunami has been identified. A land has been identified about 3 km away from
the old town centre to locate the new developments.
An objective of the project is to improve the efficiency and convenience of administrative
services for the inhabitants thus promoting the development of the society by building an
administrative complex in Hambantota as a part of the tsunami rehabilitation. With this
project the Government institutions that have been squeezed in private buildings in a
scattered manner within the present town and across the region are to be brought under
one roof for the convenience of the general public.
Components of the Administrative Complex and the total floor area justification for the
proposed Administrative complex are summarised in Table 3-8.
Table 3-8: Floor Area Allocation of Proposed Administrative Complex
ComponentFloor Area (sqft)
Main Building 184,500
Municipal Council Building 7,800
Library Building 20,345
Accommodation Unit 39,000
Depots 22,750
![Page 47: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/47.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-19
3.6.7 Proposed International Convention Centre
The international convention centre project is scheduled to be designed and constructed
by the Government of Korea and is to be gifted to the Government of Sri Lanka.
Components of the convention centre
Main auditorium
Multi-functional area
Committee rooms
Restaurants
Accommodation
Public services
Offices
Maintenance & services
Figure 3-2: Proposed Administrative Complex11
11Source: Draft Development Plan, Greater Hambantota Area 2009, UDA
![Page 48: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/48.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-20
3.6.8 City Centre Development
The City Centre development spans towards the boundaries of the city bordering the
National Parks such as Udawalawa, Lunugamvehera and Yala in its East and
incorporates a vast area of state land in Hambantota to accommodate all needs of a truly
international city. The proposed development mainly focus on two objectives,
Providing an efficient transport system with accessibility to an international
airport, seaport, other regional centres, national highway network and railway
systems.
Providing investment opportunities to national, local and foreign investors.
The total area allocated for the development is 2,000 ha. It is 3% of total land use of
Greater Hambantota area Development Project. Proposed Land Use Distribution under
City Centre Development is given in Table 3-9. Furthermore, the proposed development
sites are summarised below and graphically shown in the Figure 3-3.
Port related commercial and trade activities.
Modern administrative and institutional centres.
Provisions for tourist accommodation and recreational activities.
Arising of opportunities and development of social infrastructure.
Economic development: heavy investment on economic infrastructure.
Investment for environmental infrastructure.
Table 3-9: Proposed Land Use Distribution under City Centre Development
Landuse Area (Ha.)
Trade and Commerce 360
Industries 180
Public and Semi-Public 160
Social and Cultural 100
Educational 200
Health 160
Open Spaces and Recreational 200
Religious 40
Residential/ Tourism 300
Roads and Other Utilities 260
Differed Area 40
Total Area 2,000
![Page 49: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/49.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-21
Proposed AdministrativeComplex
Proposed ConventionalCentre
Figure 3-3 : Proposed Administrative Complex and Convention Centre12
3.7 Industrial Zones
The following industrial zones are already operating within the Project Impact Area.
1. Koggala Export Processing Zone: Located southeast of Galle town, this EPZ
has presently 22 industries and is operating at 50% of its capacity. It still
depends on the Port of Colombo for most of its import and export cargo sources
and the lack of a fast connection to Colombo and other infrastructure problems
such as deficiencies in water and electricity and general support facilities in the
vicinity are the key issues that hinder the full exploitation of the facilities at this
EPZ over the last two decades in operation.
The annual freight movements from this EPZ are estimated as follows13:
12Source: Draft Development Plan, Greater Hambantota Area 2009, UDA
![Page 50: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/50.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-22
Exports:
25,000 tonnes or 2,500 TEUs. (of Full Container Loads) transported in
container carriers
6,500 tonnes of Less than Container Loads cargo transported in trucks
Imports:
10,000 tonnes or 1,000 TEUs and
3,000 tonnes of general cargo in trucks.
2. Mirijjawela Industrial Park: Located about 1 km from the Mirijjawela junction on
the Sooriyawewa Road. This is a newly established facility which presently has 5
garment related industries. Currently it is operating at about 50% capacity.
3. Bata Atha Industrial Park: Also located in the Hambantota District, it is placed
around 20 km towards Galle from Hambantota. This is yet to be developed even
though it was originally identified as a park for leather based industries.
3.8 Urban Development Centres
Hambantota DS is the Administrative Capital of the Hambantota District and it is to be
developed as a 1st order city. Therefore this city will have passenger attractions from
Embilipitiya, Tissamaharama, and Ambalantota towns which are 2nd order cities. Freight
transport to and from Colombo and its suburbs includes rice and paddy, forestry and
agricultural products and major industrial products as sugar, salt etc.14
Sooriyawewa and Thanamalwila are coming under third order category and with the
proposed road they will have a direct links to the Monaragala District. The existing urban
hierarchy of the area is shown in the Figure 3-4.
13Source: Hambantota Seaport Pre-Feasibility Study, Ramboll et al, June 2006.
14Source: Draft Development Plan, Greater Hambantota Area 2009, UDA
![Page 51: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/51.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3-23
Figure 3-4 : Existing Urban Hierarchy- Southern Province
![Page 52: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/52.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
4-1
CHAPTER 4 STAKEHOLDER MEETINGS
Representatives of key Governmental agencies were invited to Hambantota Divisional
Secretariat on 8th June 2010 to make them aware about the proposed road development
plans and to discuss their concerns and potential to partake in the said development in
Hambantota Area.
The stakeholder session included an initial presentation by the Study Team on the roads
proposed by the RDA. It also included a discussion time for each agency to examine or
clarify the programme and express their views or concerns. The list of participants at the
meeting is annexed in the Annex 2.
4.1 Hambantota Meeting
The stakeholder session was held at the meeting room of the District Secretariat in
Hambantota at 2.30 PM on 8th June 2010 and it was chaired by the District Secretary.
The following regional agencies, through their representatives, participated at the
meeting.
Road Development Authority (RDA)
Urban Development Authority (UDA)
Airport and Aviation Services (Ltd.) Sri Lanka (AASL)
Sri Lanka Port Authority (SLPA)
Department of Wildlife Conservation
Department of Forest
Ceylon Electricity Board (CEB)
Department of Irrigation
District Secretariat- Hambantota
Mahaweli Authority
The important observations and decisions made at the scoping session can be
summarised as follows:
Deputy Director, UDA Hambantota, raised the concerns on the absence of proper
databases to explicate the future attractions for the said developments. However it was
![Page 53: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/53.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
4-2
noted the limitations of the available information such as designed occupancy, floor
areas, parking area allocations with respect to the major developments. Accordingly,
UDA is not in the position to predict the total attractions to the development area without
a complete set of such development information. According to the UDA, there is a plan
to take over some of the lands of the current Tsunami housing scheme to use as a future
residential development.
Deputy Director, UDA, also mentioned that there are proposals for both Ambalantota and
Sooriyawewa to develop simultaneously as 2nd order cities. However, the employees
who are working in Hambantota Town would need to be provided through a well planned
transport services from and to their residences in the peripheral areas. It was
considered as one of the UDA’s main observations on the proposed developments. A
representative from the UDA also proposed a connecting road between Hambantota
Bypass road and the Hambantota Town through the proposed site for the Oil Tank
project of the Port. The UDA representative’s major concern of providing such
connection road was to re-establish the Sweet (Dodol) shops along the remaining
section of ex-Tangalle Road outskirts of the Hambantota Town. However the
representative of the SLPA highlighted that there is no possibility of having a public road
through this Industrial zone that has been proposed under the long-term development
plan of the Port.
UDA representatives also strongly supported for the inclusion of a second ring road in
the final road network on the basis of better utilisation of the land area defined as urban
by the UDA. However the representative of the Department of Wildlife Conservation
raised the concern over the possible disturbances to the wildlife inhabitants due to the
proposed ring road and specifically mentioned the possible disturbances to the
movement of elephants. Both the RDA and the Study Team pointed out the
ineffectiveness of having two ring roads close to each other from a transport point of
view.
The RDA has proposed to improve the existing road from Andarawewa to Padawkema
as the main access to the proposed Airport. This is already being developed as the
primary site access of the airport construction. However the AASL accepted that there is
a need for an alternative access to the Airport especially if required to handle emergency
situations where more than one access is required. The Study Team proposed a 2nd
access road connecting Gonnoruwa (Hambantota-Gonnoruwa-Meegahajandura Road)
and Udamattala (Andarawewa-Padawkema Road) parallel to the proposed airport
![Page 54: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/54.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
4-3
runway and via the airport’s main gate which would resolve the emergency access
concerns as well.
The representative of the Department of Wildlife Conservation pointed out that the
proposed road network intercepts three (3) major elephant corridors. Hambantota-
Gonnoruwa-Meegahajandura road intercepts the corridor twice near the proposed Outer
Circular Road II and at Gonnoruwa and also the CGHW Road close to the Bundala
Sanctuary. Hence it was requested to keep at least those three openings for elephant
movements when considering any fencing of roads. The Department of Wildlife
Conservation representative also highlighted that elephants are crossing the road at
grade on roads such as Hambantota-Gonnoruwa-Meegahajandura Road which are 6
lanes or greater would be dangerous for both the road users and the elephants.
Subsequently it was proposed that there would be a need for overpasses for roads at
some identified locations.
Representatives of the CEB requested for a 5m corridor along the Hambantota-
Gonnoruwa-Meegahajandura Road.
As revealed by the Project Engineer of the SLPA, the Ports Authority has not taken a
final decision on the proposed port’s entry/ exit gate locations. However SLPA is likely
to keep accesses to Mirijjawila-Sooriyawewa Road, Hambantota Bypass road as well as
CGHW Road.
Representative of the Mahaweli Authority has expressed their concerns on the planned
future developments northwards to the Hambantota Bypass Road and eastwards to the
Walawe Left Bank Road. It was revealed that there are no development plans for the
area chosen for the proposed Road connecting the Walawe Left Bank Road to
Hambantota-Gonnoruwa-Meegahajandura Road.
![Page 55: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/55.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-1
CHAPTER 5 FINAL ROAD NETWORK
5.1 Introduction
The study area for the road network has been selected based on the provision of accesses
to the proposed international hub development sites such as the Airport, Seaport, Cricket
Stadium, Safari Park, BOI site etc. as well as the Convention Centre, Administrative
Complex and tourism related development and residential areas. Providing access for these
sites and inter-linking them to an appropriate level were the major concerns when designing
the road network. Due concerns were given to Airport, Seaport, Safari Park, BOI and
Cricket Stadium sites when connecting them with the national road network. Thereby the
study area has been extended beyond the development area of Hambantota District
intercepting the borders of Uva Province, Sabaragamuwa Province and Matara District.
However, when defining the road network, additional measures have been taken to integrate
Eastern and Uva provinces nationally, as those provinces are considered to be the least
accessible provinces in Sri Lanka and ones that could be better served through a port and
airport compared to Western Province.
The layout plan for the proposed road network improvements is given in Appendix 2. The
final road network was decided after identifying the importance of the connectivity for land
use developments and the magnitude of such development for transport demand in future.
The capacities of the roads that have been considered for improvements are decided based
on the potential land use developments already proposed by UDA (Figure 5.1) and expected
travel demand in future where there are no specific demand data are available at present.
The cross sectional properties of the proposed roads have been considered for stage
developments, as Stage I and Stage II, for the purpose of effectiveness of the investment
plans. The cross sectional properties of each road are identified for facilities such as
number of lanes, service roads, walkways, bicycle lanes, shoulders, public transport lanes,
parking bays, centre medians, bus bays, landscaping and utility corridors, depending on the
potential demand by the proposed land use developments. Therefore, the cross sectional
properties are assigned based on the transport functionalities identified for each road link
discussed under this chapter.
![Page 56: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/56.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-2
Figure 5-1 : Study Area with Zoning of UDA
![Page 57: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/57.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-3
5.2 Definition of Transport Functionalities
In addition to the provision of accesses for development sites, the study team has
purposefully introduced certain transport functionality aspects when defining road
network and their cross sections with the intention of increasing the performance of the
proposed network. Following are some of transport functionality aspects attended to:
5.2.1 Definition of Outer Hambantota Development Area
The study proposes the provision of a road that would provide the definition for an Outer
Hambantota Development Area thus separating through traffic from local traffic. This
would provide the:
a) Creation of a road that will take East-West through traffic without interfering
with the activities of the Hambantota Development Area.
b) Through and uninterrupted travel from Southern Province to Uva and Eastern
Provinces.
c) Express access to the airport without roaming through the built-up areas of
Hambantota Development Area that should have local traffic flow conditions.
Such a road could be facilitated through the following modifications for the existing roads
and additions of new roads:
Minor modifications to the newly rehabilitated Ranna-Angunakolapelessa-Wetiya
Road
New road (HR19) from Wetiya (Node No HX31) via the proposed Safari park to
join the Sooriyawewa–Mirijjawila Road (Node No HX16)
Minor modifications to the Walawe Project Road up to the Node No HX32 and
thereafter a new trace up to the Andarawewa intersection (Node No HX12)
Proposed road from Andarawewa to Airport and through to Thanamalwila via
Udamattala or to Kataragama via Lunugamvehera.
![Page 58: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/58.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-4
5.2.2 Provision of a high profile connection between the proposed
Seaport and Airport
The study team recommends a high profile connection between the proposed seaport
and the airport that can move containers and industrial cargo between the transport hubs
as well as the industrial zones, which are ideally to be located between these two ports.
Such a road could be created by the provision of a separate access between the
proposed airport and seaport using the proposed Link HR18. This would take heavy
commercial vehicles by-passing the urban built-up areas and also avoiding the airport
access road (HR02). There should be no roadside development along this road and this
would also be an alternative express access to the airport.
5.2.3 Provision of a viable public transport corridor
As an urban development axis along Siribopura-Gonnoruwa Road stretch.
As a service road to provide necessary accesses to administrative and
commercial buildings.
To promote high density residential and employment centres along this corridor.
The proposed high quality public transport corridor will become viable initially to
serve with buses followed by BRT or LRT.
5.2.4 Maximise Usage of Pedestrian and Cycle Access
Provision of proper pedestrian and cycle accesses between Administrative
Centre and residential areas for those who are residing in close proximity and
walk or ride to work or any other purposes.
Concentration of quality residential development in tsunami housing area to allow
high income people to reside close to work areas, so that traffic congestions
can be minimised.
Provision for short distance travel access between work and residences for those
who would otherwise use cars to travel to work.
Provision of a set of travel paths as bicycles and walkways for tourism and short
distance commutes.
![Page 59: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/59.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-5
Tourism related developments would include cycle tracks within the town area
and extending along Lewaya Road as well as to Walawe Left Bank Project
areas to promote eco-tourism.
5.3 Road Network Proposed by RDA
After considering the aforementioned functionality aspects, the RDA proposals which
contained 17 road links, has been improved to a proposed road network with 27 links. It
includes one omission, the Outer Circular Road II, and the addition of 11 new links to the
original proposal of the RDA. The total length of the proposed network is 371.7 km of
which new constructions would amount to around 38 km or around 10% of the network.
The road network proposed by this study includes the reformation of 20 existing roads
and the construction of 5 new links and the down grading of the final section of the
Extension of the Southern Expressway and internal road network in City Area.
The roads identified for re-development generally follow their existing alignment with
modifications where necessary to enable safety and speed. The Southern Expressway
which was due to end at Gonnoruwa Road in its original proposal is proposed to be
stopped at the intersection of the Walawe Project Road. The list of the 27 road links
identified for the Hambantota Development Plan in this report is given in Table 5-1. The
locations of these roads are set out in Appendix 2.
![Page 60: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/60.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-6
Table 5-1: RDA List of Road Links Identified in Hambantota Development Plan
NoRoad Name
Road Length
(km)
Intervention
Type
HR01 Outer Circular Highway 6.2 New
HR02 Hambantota – Gonnoruwa – Megahajandura Road 29.4 Re-design
HR03 Sooriyawewa – Meegahajandura –Kumaragama Road 18.0 Re-design
HR04 Andarawewa – Udamattala – Padawkema Road 13.0 Re-design
HR05 Udawalawe – Thanamalwila Road 40.0 Re-design
HR06 Galwewa Junction -Moraketiya Road 12.0 Re-design
HR07 Hambantota Bypass Road 13.0 Re-design
HR08 Nabodagaswewa-Swodagama-Andarawewa Road 8.5 New
HR09 Bopale Junction - Kiribbanwewa Road 8.5 Re-design
HR10Embilipitiya – Moraketiya – Kiriibbanwewa - UdamaduraRoad
16.9 Re-design
HR11 Airport Central Access Road 1.5 Re-design
HR12 New Airport Access Road 8.1 New
HR13 CGHW Road (from Hambantota to Thanamalwila) 45.9 Re-design
HR14 Lewaya Road 3.5 Re-design
HR15 Sooriyawewa – Padalangala Road 12.0 Re-design
HR16 Sooriyawewa – Mirijjawila Road 24.0 Re-design
HR17 Extension of Southern Expressway New
HR18 Arabokka-Siyabalagaswewa-Gonnaruwa Road 11.0 New
HR19 Wetiya -Mahapalassa-Nabodagaswewa Road 12.0 New
HR20 Lunugamvehera - Kataragama Road 15.0 Re-design
HR21 Ranna - Angunakolapelessa - Wetiya Road 8.0 Re-design
HR22 Lunugamvehera -Weligatta Road 20.0 Re-design
HR23 7th Colony-Weerawila Road 9.7 Re-design
HR24 Udamattala – Thanamalwila Road 9.3 Re-design
HR25 Internal Road Grid in the City Area 12.0 New
HR26 Southern Expressway Access Road 3.3 New
HR27 Walawe Project Road 10.9 Re-design
Total 371.7
The Study Team conducted field observations on four (4) (HR8, HR12, HR18, HR19) out
of Five (5) new roads and the respective coordinates have been defined for their
centrelines. However, the remaining new road, the Outer Circular Highway (HR01), was
already under construction during this time and hence no further investigations were
considered.
The four new roads which are yet to be constructed have an aggregate length of 31.47
km as shown in Table 5-2. The table also shows the connectivity of new roads
associated with the existing road network.
![Page 61: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/61.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-7
Table 5-2 : Details of the Traces for the 4 New Roads
Road Start Node End Node
Length of
the Road
(km)
Road No. HR19
Connection between A018 Road
and Sooriyawewa- Mirijjawila
Road (100ft. road) identified as
No.HR16 on the list
Wetiya Junction on
A018 Road -Identified
as Intersection HX 31.
Walawe Road Junction
on Sooriyawewa-
Mirijjawila (100ft road) –
Identified as HX 16.
10.06
Road No. HR08
As a continuation of Road No.
HR19;this will connect the
Sooriyawewa-Mirijjawila Road
(HR16) and Hambantota-
Gonnoruwa-Meegahajandura
Road (HR02)
Walawe Road Junction
on Sooriyawewa-
Mirijjawila (100ft road) –
Identified as HX 16.
Andarawewa Junction -
Identified as HX12.
8.44
Road No. HR18
Road connecting the Walawe
Left Bank Road to Hambantota-
Gonnoruwa- Meegahajandura
Road (HR02)
New Junction created
on Walawe Left Bank
Road between 5th
and
6th
km –identified as
Intersection HX21.
New Junction created
on Hambantota-
Gonnaruwa –
Meegahajandura Road
between 8th
and 9th
km
-identified as
intersection HX07.
4.85
Road No. HR12
New Airport Access Road
New Junction created
on Hambantota-
Gonnoruwa-
Meegahajandura Road
between 8thand 9
thkm -
identified as
intersection HX03.
Udamattala Junction-
Identified as HX13 on
Andarawewa-
Udamattala-
Padawkema Road.
8.12
Total 31.47
![Page 62: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/62.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-8
Road No.HR19: Connection between A018 Road and Sooriyawewa-Mirijjawila
(100ft. road) Road (HR16)
Control Points/ Areas: Wetiya Junction (HX31), Ridiyagama Farm, Safari Park, Hot
Springs, Tank at Northern side of Safari Park, Walawe Road Junction on 100 ft. Road
(HX16).
Description: The new trace has a length of 10.06 km from the A018 Road to
Sooriyawewa-Mirijjawila Road (HR16) as shown in Appendix 2. Starting from the Wetiya
junction (HX31) on the A018, the new trace crosses the Walawe Right Bank Channel
within the first 200 m. The next 500 m of the trace stretches between the Walawe Right
Bank Channel and the Walawe River, where there are moderately dense settlements
and cultivations. However, around next 300 m of the trace between the Walawe River
and its Left Bank Channel runs through fewer settlements. The first 01 (one) km of the
trace between the Wetiya Junction on A018 and the Walawe Left Bank Channel can be
considered as the most socially sensitive area of the whole length of the trace, though
the construction would damage a fewer number of settlements.
The next 3 km of the road trace, from Walawe Left Bank Channel to the boundary of the
Safari Park, runs through the Government owned Ridiyagama Farmlands, which seems
to be under-utilised as an agricultural land. However the proposed trace will sever the
farmland. There is hardly any possibility of re-locating the new trace further southwards
as then it would be too close to the Ridiyagama Tank and the new Safari Park which is
already under construction.
Once the trace reaches the western edge of the boundary of the Safari Park, it traverses
through a land bounded by paddy fields and the northern boundary of the Safari Park for
a length of around 1.6 km. Since the Hot Springs are located in close proximity to the
eastern boundary of the Safari Park and northwards of the proposed trace, the exact
locations of the road trace for this section should be studied along with the environmental
aspects which would be more sensitive in this area. The final stretch of the trace will be
approximately 3.6 km long and mostly it runs through a conserved forest lands until it
connects the Sooriyawewa-Mirijjawila road (HR16).
Considerations in setting out/ Design: Special care should be taken in setting out the
section that runs parallel to the northern boundary of Safari Park due to the closeness to
the Hot Springs which is a natural resource and tourist attraction. The accuracy of GPS
![Page 63: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/63.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-9
co-ordinates of control points observed at the site may not be sufficient to address these
issues. Since the intersection design for both ends of the proposed trace is yet to be
finalised, provisions for this should be made when setting out the trace at the two ends.
Coordinates: Co-ordinates of the road trace from A018 Road to Sooriyawewa-Mirijjawila
Road (HR16) with a 100 m interval are shown in Table 5-3.
Table 5-3: HR19: Connection between A018 and Sooriyawewa-Mirijjawila Road
(HR16)
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
CoordinatesY- Coordinates
0/000 218847 113136 3/100 221087 115373
0/100 218925 113198 3/200 221151 115450
0/200 219004 113260 3/300 221215 115527
0/300 219082 113323 3/400 221278 115605
0/400 219159 113387 3/500 221341 115683
0/500 219235 113452 3/600 221404 115760
0/600 219309 113518 3/700 221468 115837
0/700 219380 113588 3/800 221532 115914
0/800 219447 113663 3/900 221598 115989
0/900 219509 113742 4/000 221663 116065
1/000 219562 113826 4/100 221730 116140
1/100 219609 113914 4/200 221796 116214
1/200 219655 114003 4/300 221864 116288
1/300 219702 114091 4/400 221935 116358
1/400 219817 114255 4/500 222012 116422
1/500 219885 114328 4/600 222093 116480
1/600 219959 114395 4/700 222176 116537
1/700 220037 114458 4/800 222256 116596
1/800 220117 114518 4/900 222335 116658
1/900 220199 114576 5/900 223117 117269
2/000 220281 114632 6/000 223209 117309
2/100 220364 114688 6/100 223301 117348
2/200 220446 114746 6/200 223394 117387
2/300 220526 114805 6/300 223486 117424
2/400 220604 114868 6/400 223580 117460
2/500 220679 114934 6/500 223673 117495
2/600 220752 115003 6/600 223767 117529
2/700 220822 115074 6/700 223861 117564
2/800 220891 115147 6/800 223954 117601
2/900 220957 115221 7/000 224047 117639
3/000 221023 115297 7/100 224138 117680
![Page 64: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/64.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-10
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
7/200 224227 117724 8/700 225450 118590
7/300 224315 117772 8/800 225533 118646
7/400 224401 117823 8/900 225617 118700
7/500 224485 117877 9/000 225701 118754
7/600 224568 117934 9/100 225786 118808
7/700 224649 117992 9/200 225871 118860
7/800 224730 118051 9/300 225957 118912
7/900 224809 118112 9/400 226043 118963
8/000 224888 118173 9/500 226129 119014
8/100 224967 118235 9/600 226215 119064
8/200 225046 118296 9/700 226302 119114
8/300 225125 118357 9/800 226389 119164
8/400 225206 118417 9/900 226476 119213
8/500 225286 118476 10/000 226563 119262
8/600 225368 118533 10/056 226611 119290
Road HR08: As an extension for Road HR19 to connect the Sooriyawewa-
Mirijjawila Road (HR16) and Hambantota-Gonnoruwa-Meegahajandura Road
(HR02)
Control Points/ Areas: The trace commences at the Walawe Road Junction on the
Sooriyawewa-Mirijjawila Road (HR16) and terminates at the Andarawewa Junction on
the Hambantota-Gonnoruwa-Meegahajandura Road (HR12). Attention has been paid to
avoid several tanks between Swodagama to Andarawewa Junction.
Description: The proposed road trace spans over a total length of 8.44 km and follows
through two distinctive sections in terms of the land use. The first 4.20 km of the trace
follows the existing Walawe Road up to Swodagama and a new trace has been
proposed for the remaining section of 4.44 km from Swodagama to Andarawewa
Junction as shown in Appendix 2. Considering the Walawe agricultural development
areas southwards and the forest area northwards, no major alignment corrections
(except in first 200 m to correct for curves) have been considered along the first 4.20 km
from the Intersection HX16. Therefore the proposed road trace roughly follows the
centreline of the existing road.
However, along the proposed 4.5 km section of new construction, there are a number of
concerns on wildlife especially on possible obstructions to the movements of elephants.
![Page 65: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/65.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-11
While a suitable crossing such as an underpass of the road has to be provided for the
elephants to ensure the safety of elephants and that of road users. An electric fence
may also have to be considered if required to ensure elephants use the underpass and
do not cross at-grade. There were considerations to avoid a number of water bodies and
irrigation structures in along the road trace.
Considerations in setting out/ Design: Since there are number of small tanks and
other hydrological structures located in the vicinity of the area of the new construction,
care should be taken when setting out. There might by minor deviations in the given co-
ordinates varying with the accuracy of the GPS used. The setting out should also keep
provision for the respective intersection designs which are still to be finalised.
Coordinates: Co-ordinates of the trace from the Sooriyawewa-Mirijjawila Road (HR16)
to the Hambantota-Gonnoruwa-Meegahajandura Road (HR02) at 100 m intervals are
shown in Table 5-4.
Table 5-4 : HR08: between Sooriyawewa-Mirijjawila Road (HR16) and Hambantota-
Gonnoruwa-Meegahajandura Road (HR02)
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
0/000 226611 119290 1/900 228215 120233
0/100 226685 119357 2/000 228308 120270
0/200 226758 119426 2/100 228401 120307
0/300 226824 119501 2/200 228494 120343
0/400 226889 119577 2/300 228587 120380
0/500 226955 119652 2/400 228679 120417
0/600 227021 119727 2/500 228772 120454
0/700 227101 119787 2/600 228866 120490
0/800 227192 119828 2/700 228963 120511
0/900 227285 119865 2/800 229063 120507
1/000 227378 119902 2/900 229162 120496
1/100 227471 119939 3/000 229261 120484
1/200 227564 119975 3/100 229361 120472
1/300 227657 120012 3/200 229460 120461
1/400 227750 120049 3/300 229559 120449
1/500 227843 120086 3/400 229659 120437
1/600 227936 120123 3/500 229757 120419
1/700 228029 120159 3/600 229853 120391
1/800 228122 120196 3/700 229951 120376
![Page 66: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/66.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-12
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
3/800 230051 120386 6/200 232230 121348
3/900 230147 120413 6/300 232322 121387
4/000 230243 120441 6/400 232412 121431
4/100 230339 120468 6/500 232498 121481
4/200 230436 120494 6/600 232581 121537
4/300 230532 120520 6/700 232660 121598
4/400 230628 120548 6/800 232736 121664
4/500 230724 120578 6/900 232808 121733
4/600 230818 120612 7/000 232878 121804
4/700 230910 120650 7/100 232947 121877
4/800 231000 120693 7/200 233016 121949
4/900 231088 120741 7/300 233086 122020
5/000 231173 120794 7/400 233157 122091
5/100 231257 120848 7/500 233231 122158
5/200 231339 120905 7/600 233308 122222
5/300 231422 120962 7/700 233387 122284
5/400 231505 121017 7/800 233467 122343
5/500 231589 121071 7/900 233550 122400
5/600 231675 121122 8/000 233633 122455
5/700 231764 121169 8/100 233717 122508
5/800 231855 121209 8/200 233803 122560
5/900 231948 121245 8/300 233889 122612
6/000 232042 121279 8/400 233975 122663
6/100 232137 121312 8/442 234011 122684
Road HR18: Road connecting the Hambantota by-pass Road (HR07) and
Hambantota-Gonnoruwa-Meegahajandura Road (HR02)
Control Points/ Areas: The starting point is on Hambantota by-pass Road (HR07) close
to Siyambalagaswewa and the terminating point is on Gonnaruwa Road (between 8th
and 9th km on Hambantota-Gonnaruwa-Meegahajandura Road (HR02). There are a
number of irrigation tanks in the path,
Description: The proposed road trace requires two distinct interventions according to
which it is divided to two sections. The first section follows the existing Walawe Road for
about 5 km up to Siyambalagaswewa and thereafter a new construction of the next 4.85
km up to Hambantota-Gonnoruwa-Meegahajandura Road (HR02).
![Page 67: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/67.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-13
The first section can be fitting to the centreline of the existing Walawe Road and it runs
through agricultural lands while the proposed section for new construction runs through
the reserved forests and wildlife zones. The section proposed as new construction
extends over a length of 4.85 km, from Siyabalagaswewa to Hambantota-Gonnoruwa–
Meegahajandura Road, as shown in the map given in Appendix 2.
Though there are no obstructing irrigation structures along either sides of the existing
Walawe Road, some structures may have to be relocated/ reconstructed due to the
proposed widening. This road will be the access for heavy vehicles plying between the
proposed industrial estate to be located close to the airport and the seaport. Hence the
typical slow moving vehicles such as tractor trailers would be obstructing such heavy
vehicle movements. Therefore, a parallel service road for slow moving vehicles will also
have to be provided. In the section proposed for new construction, there are a number
irrigational structures such as tanks and canals and the trace should avoid these as far
as possible. Additionally the elephant movements are also obstructed by this trace for
which a safe crossing facility has to be provided.
Considerations in setting out/Design: The western or northern entrance of the
proposed Hambantota Seaport is to be directly connected to the proposed Walawe Road
in order to provide a direct connection to the airport and the industrial areas adjacent to
the airport.
Special attention should be given to the design requirements at intersections at both
ends of new trace. Moreover special care should be taken in avoiding the small tanks
and other hydrological structures in this section.
Coordinates: Co-ordinates of the road trace that connects the Walawe Left Bank Road
to the Hambantota-Gonnoruwa-Meegahajandura Road (HR02) at 100 m intervals are
shown in Table 5-5.
Table 5-5 : HR18: Road connecting Walawe Left Bank Road to Hambantota-
Gonnoruwa-Meegahajandura Road (HR02)
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
0/000 236152 111566 0/400 236127 111965
0/100 236146 111666 0/500 236121 112065
0/200 236139 111765 0/600 236115 112165
0/300 236133 111865 0/700 236110 112265
![Page 68: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/68.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-14
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
0/800 236106 112364 2/900 236153 114463
0/900 236102 112464 3/000 236155 114563
1/000 236099 112564 3/100 236156 114663
1/100 236096 112664 3/200 236156 114763
1/200 236094 112764 3/300 236154 114863
1/300 236093 112864 3/400 236149 114963
1/400 236092 112964 3/500 236143 115062
1/500 236092 113064 3/600 236134 115162
1/600 236093 113164 3/700 236123 115261
1/700 236095 113264 3/800 236108 115360
1/800 236098 113364 3/900 236091 115459
1/900 236101 113464 4/000 236072 115557
2/000 236105 113564 4/100 236051 115655
2/100 236110 113664 4/200 236030 115752
2/200 236116 113764 4/300 236007 115850
2/300 236122 113864 4/400 235984 115947
2/400 236128 113963 4/500 235961 116044
2/500 236134 114063 4/600 235939 116142
2/600 236140 114163 4/700 235917 116239
2/700 236145 114263 4/800 235895 116337
2/800 236149 114363 4/851 235884 116387
Road HR12: Airport Access Road (HR11)
Control Points/ Areas: Udamattala Junction (HX15), Welipotha Tank and Main
entrance to the Airport (HX04)
Description: The new trace has a length of 8.12 km from Udamattala Junction (HX15) to
Hambantota-Gonnoruwa-Meegahajandura Road as shown in the map in Appendix 2.
The first 1.5 km of the trace starting from Udamattala Junction has been proposed to be
developed keeping its centre line on the same orientation of the existing gravel road
extending up to the Bandagiriya Tank. After this initial section of 1.5 km, it follows a new
trace at the north-western side of the Welipotha Tank, and runs parallel to the north/
western boundary of the proposed airport. Social influence of the trace is considered to
be negligible since the settlements are few in numbers even close to the Padawkema-
Andarawewa Road and the Hambantota-Gonnoruwa-Meegahajandura Road. However,
![Page 69: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/69.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-15
the environmental influence of the trace is considerably high since it obstructs the
elephant movements in the area.
Considerations in setting out/ Design: Setting out close to the end points of proposed
trace need to be coupled with the realignment process of Gonnoruwa Road and
Andarawewa-Padawkema Road at both ends. There might by minor deviations in given
co-ordinates depending on the accuracy of GPS co-ordinates of control points observed
at the site and the precision of the features given in the Topographical maps. Hence
appropriate minor adjustments would need to be introduced to the given coordinates
during the field setting out of the trace.
Coordinates: Co-ordinates of the trace from Udamattala Junction to Hambantota-
Gonnoruwa-Meegahajandura Road at 100 m intervals are shown in Table 5-6.
Table 5-6: HR12: Airport Access Road
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
0/000 234780 120704 2/300 236515 122215
0/100 234856 120770 2/400 236590 122281
0/200 234931 120835 2/500 236665 122346
0/300 235007 120901 2/600 236741 122412
0/400 235082 120967 2/700 236816 122478
0/500 235157 121033 2/800 236892 122543
0/600 235233 121098 2/900 236967 122609
0/700 235308 121164 3/000 237042 122675
0/800 235384 121230 3/100 237118 122740
0/900 235459 121295 3/200 237193 122806
1/000 235534 121361 3/300 237269 122872
1/100 235610 121427 3/400 237344 122937
1/200 235685 121492 3/500 237419 123003
1/300 235761 121558 3/600 237495 123069
1/400 235836 121624 3/700 237570 123134
1/500 235911 121689 3/800 237646 123200
1/600 235987 121755 3/900 237721 123266
1/700 236062 121821 4/000 237796 123331
1/800 236138 121886 4/100 237872 123397
1/900 236213 121952 4/200 237947 123463
2/000 236288 122018 4/300 238023 123529
2/100 236364 122083 4/400 238098 123594
2/200 236439 122149 4/500 238173 123660
![Page 70: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/70.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
5-16
Chainage
(m)
X-
Coordinates
Y-
Coordinates
Chainage
(m)
X-
Coordinates
Y-
Coordinates
4/600 238249 123726 6/500 239682 124974
4/700 238324 123791 6/600 239742 125047
4/800 238400 123857 6/700 239747 125146
4/900 238475 123923 6/800 239752 125246
5/000 238550 123988 6/900 239758 125346
5/100 238626 124054 7/000 239763 125446
5/200 238701 124120 7/100 239768 125546
5/300 238777 124185 7/200 239773 125646
5/400 238852 124251 7/300 239778 125746
5/500 238927 124317 7/400 239783 125846
5/600 239003 124382 7/500 239789 125945
5/700 239078 124448 7/600 239794 126045
5/800 239154 124514 7/700 239799 126145
5/900 239229 124580 7/800 239804 126245
6/000 239305 124645 7/900 239809 126345
6/100 239380 124711 8/000 239814 126445
6/200 239455 124777 8/100 239820 126545
6/300 239531 124842 8/126 239821 126571
6/400 239606 124908
![Page 71: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/71.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-1
CHAPTER 6 GEOMETRIC DESIGN
6.1 Geometric Design Criteria
Each road in the proposed road network possesses unique characteristic importance.
Also they belong to different localities within the Greater Hambantota Area. The
capacities of the road links are of different magnitude and vary from 2 lanes to 6 lanes
excluding the service lanes and the parking. Some of the roads belong to urban road
category while some are semi-urban and rural and depends on the land use
concentration at present and as per the proposed developments. The geometry
improvements of the individual roads in the proposed road network are to be selected by
considering the proposed future developments in Greater Hambantota Area to suit to
their future transport demand.
Design life of the road has been taken as 20 years. Additionally, the road reservation
should be take in to account and provision for future widening to higher number of lanes
and for adding service roads wherever considered appropriate within the proposed road
network.
Literature available on geometric design standards used for major high mobility roads
projects in Sri Lanka reflect that design standards used are not consistent and vary
significantly from project to project. Different standards of design speeds are adopted
due to the reasons such as varying topography and diverse roadside developments in
the similar categories of roads that belong to the different regions.
It is always important to maintain the consistency in standards among different projects,
especially when considering the different elements of a project and better if it complies
with widely used geometric design standards. Most of the proposed roads belong to the
Class A and B road categories of the RDA. Therefore, the RDA standards and the
manuals15 shall be used for designing both the horizontal and vertical geometric designs
of the roads in the proposed road network.
The topography along the trace has influence on the geometric design, especially for the
horizontal and vertical alignments of the road. Additionally, the terrain condition affects
15Geometric Design Standards of Roads, Road Development, 1998
![Page 72: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/72.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-2
the highway capacity. For this study it is observed that some road sections fall into the
category of rolling terrain condition where natural slopes rise and fall above or below the
roadway grade and most of the road sections can be categorised as level terrain
condition where highway sight distances are generally high. There are no roads in the
proposed network that should be categorised as mountainous. The proposed design
speeds with respect to the different vertical terrains are given in Table 6-4.
6.2 Number of Lanes & Staged Construction
The proposed roads in the network may be constructed by stages for better utilisation of
the infrastructure in the most economical manner. This can be emphasised as maximum
utilisation of the road infrastructure with adequate traffic levels to justify the benefits
against cost of the construction.
Initially, in the Stage I, the formation of the road cross section is defined to have lower
number of lanes as shown in Table 6-1. The lane capacities will be increased to higher
numbers (generally additional 2 lanes in most occasions) in Stage II after the traffic
levels are reached to their capacities [Generally construction will have to commence
once the Level of Service (LOS) has reached “D”.
However, it is proposed to acquire the required right of way for future widening during the
Stage I itself so that the total width proposed in Stage II is reserved. The lane capacities
in the proposed stage construction are shown in Table 6-1.
Table 6-1: Stage Construction and Lane Capacities of Proposed Road Network
Stage I Stage II Stage I Stage II
HR 01 4 n.a HR 13 2 n.a
HR 02 (H'tota- B'giriya) 4 10 HR 15 2 n.a
HR 02 (B'giriya- M'Jandura) 4 8 HR 16 4 n.a
HR 03 (S'Wewa-M'Jandura) 2 4 HR 17 4 6
HR 03 (M'Jandura-K'gama) 2 4 HR 18 4 6
HR 04 2 4 HR 19 2 6
HR 05 2 n.a HR 20 2 4
HR 06 2 4 HR 21 2 4
HR 07 4 6 HR 22 2 4
HR 08 2 4 HR 23 2 n.a
HR 09 2 4 HR 24 2 n.a
HR 10 2 4 HR 25 2 4
HR 11 4 8 HR 26 2 n.a
HR 12 4 8 HR 27 2 n.a
Number of LanesRoad No. Road No.
Number of Lanes
![Page 73: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/73.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-3
It can be seen that most of the road links provide LOS above “C” even after 20 years
from the base year (Table 6-3). Only few sections of the A2 Road having high flows are
saturated by this time. This shows that even at higher traffic growth levels (Development
Scenario), the Stage I capacity of almost all roads in the road network is adequate to
have an acceptable service level.
Provision of two lanes will not be adequate by the year 2022 for Road HR04, under the
development scenario. This is due to the principal function of the road that is the Airport
access from both east and west directions. Apart from above, it is observed that all the
other roads function at a very good LOS with the Stage I development lane capacities.
Passenger Car Units given in Table 6-2 have been used to estimate the design volumes
of each road in the road network. There is no significant design component that should
be considered as multi-lane highways in the Stage I design as most of the roads fall into
the category of 2 lane highways. However, more than 70% of the roads by lengths (275
km) are above 4 lane capacities under the Combined Stage I and II development.
Table 6-2 : Passenger Car Equivalence16
VehicleCategories
Two Lane Highway Multi-Lane Highway
Flat Terrain Rolling Terrain Flat Terrain Rolling Terrain
Motor Cycle 0.5 0.5 0.5 0.5
Cars & Vans 1.0 1.0 1.0 1.0
6W MGV 2.2 5.0 1.7 4.0
HGV 2.2 5.0 1.7 4.0
Buses 2.2 5.0 1.7 4.0
16Based on PCUs Factors used by University of Moratuwa
![Page 74: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/74.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-4
Table 6-3: LOS under Different Development Scenarios for Stage I Improvements
2012 2022 2032 2012 2022 2032 2012 2022 2032 2012 2022 2032
H001-010 A A B A A A
H001-020 C D E B B C
H002-010 A A B A A A
H002-020 A B C A A A
H002-030 B C D A B C
H002-040 A B C A A B
H002-050 B C D A B C
H002-060 A B C A A A
H002-070 A B C A A B
H003-010 A B C A A B
H003-020 B C D A B C
H003-030 B C D B B C
H003-040 A A A A A A
H004-010 B D E B C D
H004-020 B D E B C D
H004-030 B D E B C D
B427-010 A A A A A B A A A A A B
B427-020 A A A A A B A A A A A B
B427-025 A A B A B B A A B A B B
B427-030 A A B A B B A A B A B B
H006-010 A B C A A B
H007-010 A A A A A A
H007-020 A A B A A A
H007-030 A A B A A A
H007-040 A A A A A A
H007-050 A A A A A A
H008-010 A B C A A A
H008-020 B D E A B C
H009-010 A B B A A B
B549-010 A A B B C D A B B B C D
B549-015 A A B B C D A A B B B C
B549-020 A A A A A A A A B A A A
B549-025 A A A A A B A A A A A B
H011-010 A A A A A A
H012-010 A B C A B B
H012-020 A B C A B B
A002-830 A A A A A B A B C A A A
A002-840 A A A A B B A B C A A A
A002-845 A A A A A A A A B A A A
A002-847 C D E E E E D E E D E E
A002-850 C D E C D E D E E C D E
A002-860 C D E C D E D E E C D E
A002-870 B B C A A B B C D A A A
A002-880 B C C A B B B C D A A B
A002-890 B C C C D E B C D B C D
A002-895 B B C A B B B C C A B B
A002-900 B C C C D D B C D B C D
B251-010 A A A A A A A A A A A A
B563-010 A A A A A B A B C A A A
B563-020 A A A A A B A B C A A A
B562-010 A A A A A A A A A A A A
B562-015 A A A A A B A A A A A A
B562-020
B562-025 A A A A B C A B B A A A
H018-010 A A A A A A
H018-020 A A A A A A
H018-030 A A A A A A
H019-010 B C D A B B
H020-010 C D E B C E
B548-010 A A A B C D A B C A A B
B548-020 B B C C D E B D D B C D
B567-010 A A A A A A A A A A A A
B567-015 A A A A A A A A A A A A
H023-010 A A A A A A
H024-010 B C D B B C
H026-010 A B C A A B
H027-010 A A A A A A
Road - Link
No
Leve l Of Service (LOS) for 20% No Pa ssing Zones in Fla t T erra in
Base Case Scenario Development Scenario Hypothetical Scenario 1 Hypothetical Scenario 2
![Page 75: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/75.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-5
6.3 Lane Width
Lane widths between 3.5 m to 3.7 m have been used in RDA projects for two lanes, four
lanes and even for multi-lane highways. However, the desirable Lane width is 3.7 m, as
the width of the design vehicle varies from 2.1 m to 2.6 m. It is possible to maintain a
lane width of 3.25 m for two lane roads and 3.5 m for the multi-lane roads as the
minimum requirements since the property damage from land acquisition is not a very
significant issue in the area. The capacity of the lanes can be improved for the roads
with the congested lanes by converting part of the soft shoulders to the hard shoulder.
This can be introduced to two lane two-way roads in the road network with a very
marginal cost.
Table 6-4: Existing Terrains and the Proposed Design Speeds of the Roads17
HR01 Outer Circular Highway I 6.20 Flat 90 Urban
HR02 Hambantota – Gonnoruwa – Megahajandura Road 29.40 Rolling 90 Urban Connector
HR03 Sooriyawewa – Meegahajandura –Kumaragama Road 18.00 Flat 70 Semi-urban
HR04 Andarawewa – Udamattala – Padawkema Road 13.00 Flat 70 Rural connector
HR05 Udawalawe – Thanamalwila Road 40.00 Flat 70 Rural connector
HR06 Galwewa Junction -Moraketiya Road 12.00 Flat 70 Rural
HR07 Hambantota Bypass Road 13.00 Flat 90 Urban By Pass
HR08 Nabodagaswewa-Swodagama-Andarawewa Road 8.50 Flat 70 Rural connector
HR09 Bopale Junction - Kiribbanwewa Road 8.50 Flat 50 Rural
HR10 Embilipitiya – Moraketiya – Kiriibbanwewa - Udamadura Road 16.90 Flat 70 Rural
HR11 Airport Central Access Road 1.50 Flat 90 Urban
HR12 New Airport Access Road 8.10 Flat 90 Urban
HR13 CGHW Road (from Hambantota to Thanamalwila) 45.88 Flat 70 Rural
HR14 Lewaya Road 3.54 Flat 70 Rural
HR15 Sooriyawewa – Padalangala Road 12.00 Flat 50 Rural
HR16 Sooriyawewa – Mirijjawila Road 24.00 Rolling 90 Rural connector
HR17 Extension of Southern Expressway Flat Urban
HR18 Arabokka-Siyabalagaswewa-Gonnaruwa Road 11.00 Flat 90 Rural connector
HR19 Wetiya -Mahapalassa-Nabodagaswewa Road 12.00 Flat 70 Rural connector
HR20 Lunugamvehera - Kataragama Road 15.00 Flat 70 Rural
HR21 Ranna - Angunakolapelessa - Wetiya Road 8.00 Flat 70 Rural connector
HR22 Lunugamvehera -Weligatta Road 20.00 Rolling 50 Rural
HR23 7th Colony-Weerawila Road 9.66 Rolling 50 Rural
HR24 Udamattala – Thanamalwila Road 9.30 Flat 70 Rural
HR25 Internal Road Grid in the City Area 12.00 Flat 50 Residential
HR26 Southern Expressway Access Road 3.30 Flat 70 Urban
HR27 Walawe Left Bank Project Road 10.90 Flat 50 Rural
371.68
Proposed
Design
Speed
(km/h)
Type by Existing
Land Use
Total
Road
NumberRoad Name
Road
Lengt
h(km)
Terrain
17The prfile of roads in Rolling Terrain are actually very small vertical grades and thus 90 km/hr design
speed may be acceptable
![Page 76: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/76.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-6
6.4 Shoulders and Centre Median
The desirable and minimum desirable shoulder width is 3.0 m and 2.4 m for National
Highways in Sri Lanka. The shoulder width for recent developments that has been
introduced for national roads is much smaller than these figures (smaller as 1.2 m) due
to various reasons such as the acquisition and the capital costof the construction. The
same constraints are significantly applicable here too in which case the cost of the
capital is much important than the land acquisition. Therefore, the outer shoulder width
has been selected to vary between 2.0 m to 1.0 m for two lane two way roads. Minimum
of 0.5 m width of inner shoulder has been maintained in the design cross sections of
multi-lane highways of the proposed road network.
The above shoulder widths are adequate for moderate speed levels with low traffic and
low speed levels with moderate traffic levels. Therefore, adequate warning signs and the
visibility requirements shall be maintained for the improved safety of the road users
depending on the locality of each individual road. The important safety aspects shall be
considered at the detailed designs of each individual road.
A minimum width of 2.0 m has been maintained for centre median of divided multi-lane
highways in the proposed project roads. The UDA requirement is a minimum of 3.0 m
where they are to plant high grown trees in the centre median for promoting green area
concept in the dry zone. Typical cross sections are given in Appendix 3.
6.5 Service Corridor
The service corridors for utility installation such as water, electricity and
telecommunication lines are allocated on both sides of the road within the future
reservation of the right of way. Generally, the RDA has agreed to provide 5.0 m wide
service corridors on both sides of the main highways. These areas should be kept free
from any developments and should only be used as a landscaped area. Therefore, this
will be a very positive aspect for the free flow of the road traffic where there is a minimum
obstruction by the roadside developments.
![Page 77: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/77.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-7
6.6 Grade
The longitudinal grade of lower than 4% is desirable. However, it is observed that there
is no significant short length high gradient found in any of the road stretches in the road
network. Since most of the roads are in flat terrain, it is also necessary to maintain a
minimum grade to facilitate drainage. Minimum grade of 0.3-0.5% could be used for the
design.
6.7 Design Speed
The individual road links in the road network differ from others by its capacity, both the
horizontal and vertical geometry, and the type of expected use. The visibility constraints
of the roads are different from one to another due to the geometric conditions, lane
capacities and the land use of the roadside developments. Hence the important highway
design characteristics such as stopping, overtaking and continuation sight distances are
to be treated by taking the individual roads in the network into consideration. Since the
design speed is a function of above important design parameters, it is important to
consider different design speeds to individual or sub groups of the roads. However, it is
also important to note that the design speeds should not be varied drastically from one
road to the other in the same environment of proposed road improvements. Therefore,
the design speeds are selected in the range of 50 km/h to 90 km/h based on all the
above design criterions.
The most important road links with multi-lane capacities are expected to improve for the
design speed of 90 km/h. In keeping with the legal speed limit of 70 km/hr, the normal
design speed of 70 km/h is recommended for most of the roads. It is recommended to
follow the design speed of 50 km/h for the roads where it is not cost effective to improve
with expensive geometric improvements based on the existing terrain. The
recommended design speeds are given in Table 6-4 for each road link of the proposed
road network.
6.8 Operating Speed
The operating speeds for the proposed roadsare based on a number of parameters. In
the first instance it is based on the design speed, which has been considered as 50 km/h
![Page 78: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/78.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-8
to 90 km/h for different roads in the network. However, this cannot be maintained across
all sections due to variations in grade, type of intersection control method etc.
Additionally, the operating speed reduces with the traffic volume and percentage of
heavy vehicles in the traffic mix. As such the average operating speed for light
passenger vehicles as well as heavy vehicles that will be considered for each of the
traffic estimation years is given in Table 6-5. These figures have included the
adjustments for heavy vehicles taking reduction factor of 90% of the estimated operating
speeds.
![Page 79: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/79.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-9
Table 6-5: Calculation of Average Operating Speed (km/hr)
2012 2022 2032 2012 2022 2032 2012 2022 2032 2012 2022 2032
H001-010 72 72 69 72 72 72
H001-020 63 58 43 69 69 63
H002-010 72 72 69 72 72 72
H002-020 72 69 63 72 72 72
H002-030 69 63 58 72 69 63
H002-040 72 69 63 72 72 69
H002-050 69 63 58 72 69 63
H002-060 72 69 63 72 72 72
H002-070 72 69 63 72 72 69
H003-010 72 69 63 72 72 69
H003-020 69 63 58 72 69 63
H003-030 69 63 58 69 69 63
H003-040 72 72 72 72 72 72
H004-010 69 58 43 69 63 58
H004-020 69 58 43 69 63 58
H004-030 69 58 43 69 63 58
B427-010 72 72 72 72 72 69 72 72 72 72 72 69
B427-020 72 72 72 72 72 69 72 72 72 72 72 69
B427-025 72 72 69 72 69 69 72 72 69 72 69 69
B427-030 72 72 69 72 69 69 72 72 69 72 69 69
H006-010 72 69 63 72 72 69
H007-010 72 72 72 72 72 72
H007-020 72 72 69 72 72 72
H007-030 72 72 69 72 72 72
H007-040 72 72 72 72 72 72
H007-050 72 72 72 72 72 72
H008-010 72 69 63 72 72 72
H008-020 69 58 43 72 69 63
H009-010 72 69 69 72 72 69
B549-010 72 72 69 69 63 58 72 69 69 69 63 58
B549-015 72 72 69 69 63 58 72 72 69 69 69 63
B549-020 72 72 72 72 72 72 72 72 69 72 72 72
B549-025 72 72 72 72 72 69 72 72 72 72 72 69
H011-010 72 72 72 72 72 72
H012-010 72 69 63 72 69 69
H012-020 72 69 63 72 69 69
A002-830 72 72 72 72 72 69 72 69 63 72 72 72
A002-840 72 72 72 72 69 69 72 69 63 72 72 72
A002-845 72 72 72 72 72 72 72 72 69 72 72 72
A002-847 63 58 43 43 43 43 58 43 43 58 43 43
A002-850 63 58 43 63 58 43 58 43 43 63 58 43
A002-860 63 58 43 63 58 43 58 43 43 63 58 43
A002-870 69 69 63 72 72 69 69 63 58 72 72 72
A002-880 69 63 63 72 69 69 69 63 58 72 72 69
A002-890 69 63 63 63 58 43 69 63 58 69 63 58
A002-895 69 69 63 72 69 69 69 63 63 72 69 69
A002-900 69 63 63 63 58 58 69 63 58 69 63 58
B251-010 72 72 72 72 72 72 72 72 72 72 72 72
B563-010 72 72 72 72 72 69 72 69 63 72 72 72
B563-020 72 72 72 72 72 69 72 69 63 72 72 72
B562-010 72 72 72 72 72 72 72 72 72 72 72 72
B562-015 72 72 72 72 72 69 72 72 72 72 72 72
B562-020
B562-025 72 72 72 72 69 63 72 69 69 72 72 72
H018-010 72 72 72 72 72 72
H018-020 72 72 72 72 72 72
H018-030 72 72 72 72 72 72
H019-010 69 63 58 72 69 69
H020-010 63 58 43 69 63 43
B548-010 72 72 72 69 63 58 72 69 63 72 72 69
B548-020 69 69 63 63 58 43 69 58 58 69 63 58
B567-010 72 72 72 72 72 72 72 72 72 72 72 72
B567-015 72 72 72 72 72 72 72 72 72 72 72 72
H023-010 72 72 72 72 72 72
H024-010 69 63 58 69 69 63
H026-010 72 69 63 72 72 69
H027-010 72 72 72 72 72 72
Road - Link
No
Minimum Opera ting Service Speeds (km/h)
Base Case Scenario Development Scenario Hypothetical Scenario 1 Hypothetical Scenario 2
![Page 80: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/80.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-10
6.9 Cross Sections
Upon the conclusion of the road network, appropriate cross section types for the road
links have beenselected based on the functionality assigned for each road. When
selecting the cross sections, a higher emphasis has been given for providing facilities for
the non-motorised access and public transport (see Chapter 8) use in Greater
Hambantota Area. Table 6-6 summarises the recommended cross section types and
they are schematically illustrated to a greater detail in Appendix 3.
Table 6-6: Description of Types of Cross Sections defined
Code Description
4(Ex)/6 (Ex) 4 Lane Expressway with provision for 6 Lanes
4(S+NM)/10(S+PT+NM+SR)
Standard 4 Lanes with Non-Motorised(Bicycle/Pedestrian)
lane with provision for 2 Lane Public Transport corridor, Non-
Motorised lane and 2 Lane Service Road on either side
4(S+NM)/8(S+PT+NM)
Standard 4 Lanes with Non-Motorised(Bicycle/Pedestrian)
lane with provision for 2 Lane Public Transport corridor and
Non- Motorised lane on either side
4(S)/6(S) Standard 4 Lanes with provision to Standard 6 Lanes
4(S+NM)Standard 4 Lanes with Non-Motorised lane
(Bicycle/Pedestrian)
2(S)/4(S+PL)Standard 2 Lanes with provision for Standard 4 Lanes with
Passing Lanes where required
2(S+WS)/4(S+PL)Standard 2 Lanes with Wide Shoulder (2m) for SMT vehicles
with provision for Standard 4 Lanes with Passing Lanes
2(S+NM)Standard 2 Lanes with Non-Motorised (Bicycle/Pedestrian)
Lane
2(S+SW) Standard 2 Lanes with Side Walks
2(S) Standard 2 Lanes
2(S-Sub)/4 (S+PL)Sub-Standard 2 Lane with provision for Standard 4 Lanes
and Passing Lanes
Assignment of each cross section type for the links in the network indicates in the Table
6-7.
![Page 81: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/81.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-11
Table 6-7: Proposed List of Road and the Cross Sectional Properties
No Road Name Road Length (km)Proposed Cross Sectional Properties
Stage I Stage IIHR01 Outer Circular Highway 6.20 4(S+NM) N/A
HR02Hambantota – Gonnoruwa – Megahajandura Road (Hambantota – Badagiriya Jn) 29.40 4(S+NM) 10(S+PT+NM+SR)Hambantota – Gonnoruwa – Megahajandura Road (Bandagiriya - Meegahajandura) 4(S+NM) 8(S+PT+NM)
HR03Sooriyawewa – Meegahajandura –Kumaragama Road (Sooriyawewa - Meegahajandura) 18.00 2(S) 4(S+PL)Sooriyawewa – Meegahajandura – Kumaragama Road (Meegahajandura – Kumaragama) 2(S-Sub) 4(S+PL)
HR04 Andarawewa – Udamattala – Padawkema Road 13.00 2(S+WS) 4(S+PL)HR05 Udawalawe – Thanamalwila Road 40.00 2(S) N/AHR06 Galwewa Junction -Moraketiya Road 12.00 2(S) 4(S+PL)HR07 Hambantota Bypass Road 13.00 4(S) 6(S)HR08 Nabodagaswewa-Swodagama-Andarawewa Road 8.50 2(S+WS) 4(S+PL)HR09 Bopale Junction - Kiribbanwewa Road 8.50 2(S-Sub) 4(S+PL)HR10 Embilipitiya – Moraketiya – Kiriibbanwewa - Udamadura Road 16.90 2(S) 4(S+PL)HR11 Airport Central Access Road 1.50 4(S+NM) 8(S+PT+NM)HR12 New Airport Access Road 8.10 4(S+NM) 8(S+PT+NM)HR13 CGHW Road (from Hambantota to Thanamalwila) 45.88 2(S+NM) N/AHR14 Lewaya Road 3.54 2(S+NM) N/AHR15 Sooriyawewa – Padalangala Road 12.00 2S N/AHR16 Sooriyawewa – Mirijjawila Road 24.00 4(S) 6(S)HR17 Extension of Southern Expressway 4(Ex) 6(Ex)HR18 Arabokka-Siyabalagaswewa-Gonnaruwa Road 11.00 4(S) 6(S)HR19 Wetiya -Mahapalassa-Nabodagaswewa Road 12.00 2(S+WS) 4(S+PL)HR20 Lunugamvehera - Kataragama Road 15.00 2(S+WS) 4(S+PL)HR21 Ranna - Angunakolapelessa - Wetiya Road 8.00 2(S+WS) 4(S+PL)HR22 Lunugamvehera -Weligatta Road 20.00 2(S) N/AHR23 7th Colony-Weerawila Road 9.66 2(S) N/AHR24 Udamattala – Thanamalwila Road 9.30 2(S) 4(S+PL)HR25 Internal Road Grid in the City Area 12.00 2(S+SW) N/AHR26 Southern Expressway Access Road 3.30 2(S) N/AHR27 Walawe Project Road 10.90 2(S+NM) N/ATotal 371.68NOTE: S - Standard Lanes, NM - Non Motorized, WS - Wider Shoulders, PT - Public Transport Lane, SR - Service Road, N/A - Not Applicable
![Page 82: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/82.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-12
6.10 Intersections
The intersection types are defined by combined number of lanes of the main road(s) and
the minor road(s) involved. There are forty one (41) such intersections included in this
project proposal. They belong to three (3) categories of intersection types proposed for
Stage I and nine (9) categories for Stage II. A summary of the intersection types are
given in Table 6-8:
The intersection types, approach road links and the cross sectional properties of each
road link are given in Table 6-7. The identification number of each road intersection is
given in Table 6-9 and their locations referred to the map in Appendix 2. These
identification is assigned based on the size of the each intersection measure by how
many lanes are crossed by each road.
Table 6-8: Intersection Types for Stage I and Stage II
No. Intersection Type Stage I Stage II
1 8 x 6 Lane - 1
2 8 x 4 Lane - 1
3 8 x 2 Lane - 2
4 6 x 6 Lane - 6
5 6 x 4 Lane - 6
6 6 x 2 Lane - 4
7 4 x 4 Lane 9 5
8 4 x 2 Lane 12 8
9 2 x 2 Lane 20 8
Total Number of Intersections 41 41
The major intersections types such as 8 x 6 lanes, 8 x 4 lanes, 6 x 6 lanes and, 6 x 4
lanes are concentrated around and closer to Hambantota City and major development
areas. Also the largest intersection is only of 4 x 4 lanes proposed for Stage I. Around
fifty percent (50%) of the intersections in Stage I are of 2 x 2 lanes. But this is only
twenty percent (20%) for Stage II.
![Page 83: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/83.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-13
Table 6-9: List of Potential Intersection Developments
Stage I Stage IIStage I
Road 1 x Road 2
Stage II
Road I x Road 2
HX01 Hambantota - Gonnoruwa - Meegahajandura HR02 Hambantota By Pass Road HR07 4 x 4 Lane 8 x 6 Lane 4(S+NM)x4(S) 10(S+PT+NM+SR)x6(S)
HX02 Hambantota - Gonnoruwa - Meegahajandura HR02 Outer Circular Highway I HR01 4 x 4 Lane 8 x 4 Lane 4(S+NM)x4(S+NM) 4(S+NM)x10(S+PT+NM+SR)
HX03 Hambantota - Gonnoruwa - Meegahajandura HR02 Air Port Access Road HR12 4 x 4 Lane 6 x 6 Lane 4(S+NM)x4(S+NM) 8(S+PT+NM)x8(PT+NM)
HX04 Air Port Access Road HR12 Air Port Central Access Road HR11 4 x 4 Lane 6 x 6 Lane 4(S+NM)x4(S+NM) 8(S+PT+NM)x8(PT+NM)
HX05 Hambantota By Pass Road HR07 Sooriyawewa - Mirijjawila HR16 4 x 4 Lane 6 x 6 Lane 4(S)x4(S) 6(S)x6(S)
HX06 Arabokka - Siyabalagaswewa - Gonnaruwa Road HR18 Southern Expressway Access Road HR26 4 x 4 Lane 6 x 6 Lane 4(Ex)x4(S) 6(EX)x6(S)
HX07 Hambantota - Gonnoruwa - Meegahajandura HR02 Arabokka - Siyabalagaswewa - Gonnaruwa Road HR18 4 x 4 Lane 6 x 6 Lane 4(S)x4(S+NM) 6(S)X8(S+PT+NM)
HX08 Hambantota By Pass Road HR07 New Road through Walawe LB to Gonnoruwa Road HR18 4 x 4 Lane 6 x 6 Lane 4(S)x4(S) 6(S)x6(S)
HX09 Hambantota By Pass Road HR07 Outer Circular Highway I HR01 4 x 4 Lane 6 x 4 Lane 4(S+NM)x4(S) 4(S+NM)x6(S)
HX10 Hambantota - Gonnoruwa - Meegahajandura HR02 CGHW Road (243-km-260km) HR13 4 x 2 Lane 8 x 2 Lane 4(S+NM)X2(S+NM) 10(S+PT+NM+SR)x2(S+NM)
HX11 Hambantota - Gonnoruwa - Meegahajandura HR02 Southern Expressway Access Road HR26 4 x 2 Lane 8 x 2 Lane 2Sx4(S+NM) 2Sx10(S+PT+NM+SR)
HX12 Hambantota - Gonnoruwa - Meegahajandura HR02 Nabodagaswewa-Swodagama-Andarawewa Road HR08 4 x 2 Lane 6 x 4 Lane 4(S+NM)x2(S+WS) 8(S+PT+NM)x4(S+PL)
HX13 New Airport Access Road HR12 Andarawewa - udamattala - Padawkema HR04 4 x 2 Lane 6 x 4 Lane 4(S+NM)x2(S+WS) 8(S+PT+NM)x4(S+PL)
HX14 Sooriyawewa - Mirijjawila HR16 Sooriyawewa - Meegahajandura - Kumaragama HR03 4 x 2 Lane 6 x 4 Lane 2(S)x4(S) 4(S+PL)x6(S)
HX15 Airport Central Access Road HR11 Andarawewa - udamattala - Padawkema HR04 4 x 2 Lane 6 x 4 Lane 2(S+WS)x4(S+NM) 4(S+PL)x8(S+PT+NM)
HX16 Sooriyawewa - Mirijjawila HR16 Nabodagaswewa-Swodagama-Andarawewa Road HR08 4 x 2 Lane 6 x 4 Lane 2(S+WS)x4(S) 4(S+PL)x6(S)
HX17 Hambantota By Pass Road HR07 CGHW Road (243-km-260km) HR13 4 x 2 Lane 6 x 2 Lane 4(S)x2(S+NM) 6(S)x2(S+NM)
HX18 Hambantota By Pass Road HR07 CGHW Road (Ambalantota) 4 x 2 Lane 6 x 2 Lane 4(S)x2(S+WS) 6(S)x2(S+WS)
HX19 Sooriyawewa - Mirijjawila HR16 CGHW Road (Mirijjawila) 4 x 2 Lane 6 x 2 Lane 4(S)x2(S+WS) 6(S)x2(S+WS)
HX20 Outer Circular Highway I HR01 CGHW Road (243-km-260km) HR13 4 x 2 Lane 4 x 2 Lane 4(S+NM)x2(S+NM) 4(S+NM)x2(S+NM)
HX21 Arabokka - Siyabalagaswewa - Gonnaruwa Road HR18 Walawe Left Bank Project Road HR27 4 x 2 Lane 6 x 2 Lane 2(S)x4(S) 2(S)X6(S)
HX22 Hambantota - Gonnoruwa - Meegahajandura HR02 Sooriyawewa - Meegahajandura - Kumaragama HR03 2 x 2 Lane 4 x 4 Lane 2(S-Sub)x2(S) 4(S+PL)x4(S+PL)
HX23 Sooriyawewa - Meegahajandura - Kumaragama HR03 Galwewa Junction - Moraketiya Road HR06 2 x 2 Lane 4 x 4 Lane 2(S)x2(S) 4(S+PL)x4(S+PL)
HX24 Bopale Junction - Kiribbanwewa HR09 Sooriyawewa - Meegahajandura - Kumaragama HR03 2 x 2 Lane 4 x 4 Lane 2(S)x2(S-Sub) 4(S+PL)x4(S+PL)
HX25 Galnewa Junction - Moraketiya Road HR06 Embilipitiya - Moraketiya - Kiribbanwewa - Udamadura HR10 2 x 2 Lane 4 x 4 Lane 2(S)x2(S) 4(S+PL)x4(S+PL)
HX26 Bopale Junction - Kiribbanwewa HR09 Embilipitiya - Moraketiya - Kiribbanwewa - Udamadura HR10 2 x 2 Lane 4 x 4 Lane 2(S-Sub)x2(S) 4(S+PL)x4(S+PL)
HX27 Sooriyawewa - Meegahajandura - Kumaragama HR03 Udawalawe - Thanamalwila HR05 2 x 2 Lane 4 x 2 Lane 2(S)x2(S) 4(S+PL)x2(S)
HX28 Andarawewa - Udamattala - Padawkema HR04 CGHW Road (243-km-260km) HR13 2 x 2 Lane 4 x 2 Lane 2(S+WS)x2(S+NM) 4(S+PL)x2(S+NM)
HX29 Embilipitiya - Moraketiya - Kiribbanwewa HR10 Udawalawe - Thanamalwila HR05 2 x 2 Lane 4 x 2 Lane 2(S)x2(S) 2(S)x4(S+PL)
HX30 Udamattala - Thanamalwila HR24 CGHW Road (243-km-260km) HR13 2 x 2 Lane 4 x 2 Lane 2(S)x2(S+NM) 4(S+PL)x2(S+NM)
HX31 Wetiya - Mahapalassa - Nabodagaswewa Road HR19 Wetiya - Mahapalassa - Nabodagaswewa Road HR19 2 x 2 Lane 4 x 2 Lane 2(S)x2(S+WS) 2Sx4(S+PL)
HX32 Nabodagswewa - Swodagama - Andarawewa Road HR08 Walawe Left Bank Project Road HR27 2 x 2 Lane 4 x 2 Lane 2(S)x2(S+WS) 2Sx4(S+PL)
HX33 Embilipitiya - Moraketiya - Kiribbanwewa - Udamattala HR10 Embilipitiya Nonagama Rd (A 18) 2 x 2 Lane 4 x 2 Lane 2(S)x2(S) 2(A)x4(S+PL)
HX34 CGHW Road (243-km-260km) HR13 Udawalawe - Thanamalwila HR05 2 x 2 Lane 2 x 2 Lane 2(S)x2(S+NM) 2(S)x2(S+NM)
HX35 CGHW Road (243-km-260km) HR13 Lewaya Road HR14 2 x 2 Lane 2 x 2 Lane 2(S+NM)x2(S+NM) 2(S+NM)x2(S+NM)
HX36 CGHW Road (243-km-260km) HR13 Weligatta - Lunugamvehera Rd HR22 2 x 2 Lane 2 x 2 Lane 2(S+NM)x2(S) 2(S+NM)x2(S)
HX37 CGHW Road (243-km-260km) HR13 7th Colony - Weerawila HR23 2 x 2 Lane 2 x 2 Lane 2(S+NM)x2(S) 2(S+NM)x2(S)
HX38 CGHW Road (243-km-260km) HR13 Weligatta - Lunugamvehera Rd HR22 2 x 2 Lane 2 x 2 Lane 2(S+NM)x2(S) 2(S+NM)x2(S)
HX39 Weligatta - Lunugamvehera Rd HR22 7th Colony - Weerawila HR23 2 x 2 Lane 2 x 2 Lane 2(S)x2(S) 2(S)x2(S)
HX40 Padalangala - Sooriyawewa HR15 Embilipitiya Nonagama Rd (A 18) 2 x 2 Lane 2 x 2 Lane 2(S)x2(S) 2(S)x2(S)
HX41 Udawalawe - Thanamalwila HR05 Embilipitiya Nonagama Rd (A 18) 2 x 2 Lane 2 x 2 Lane 2(S)x2(S) 2(S)x2(S)
Intersection
NoName of Primary Road Road No
Road Properties of Approach RoadIntersection type
Road No
Name of Secondary Road
![Page 84: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/84.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6-14
6.11 Intersection Control
Initially, it is expected to control the traffic at the intersections and junctions by
introducing the lane marking and give way signs as much as possible with lower traffic
levels. Provisions for road safety with this lane marking and the sign controls are
allowed in the cost estimates. However, special attentions should be given for the
important and busy intersections such as HX01 to HX09 as the first priority intersections
with higher capacities. The second priority intersections are from HX10 to HX21 should
be treated next when the traffic levels are increased in future. It is adequate to control
the remaining 20 intersections with give way signs and the lane marking controls only,
until the traffic levels increase up to expected volumes in future with the development
activities are accelerated.
Attention should be given to individual intersections while designing the intersection
controls such as roundabouts, traffic islands and signal controls to suit for each such
locations and situations considering all the safety issues inherent to the locality. One of
the main concerns is the higher approach speeds into the intersections with low traffic
levels with high lane capacities during the initial stages. Therefore, additional traffic
control devices will be needed in some of the approach links of the main intersections. It
is also need to provide adequate illumination at these intersections during the night time
for improved safety of the road users.
![Page 85: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/85.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-1
CHAPTER 7 TRAFFIC ANALYSIS
Traffic levels in the Road Network for Hambantota Development will be influenced by the
following factors:
Diversion of existing traffic from other roads to A2 Road, in particular due to
reduction of travel distances, to destinations such as Uva and Eastern Provinces
as well as North Central Province from the south.
Diversion of traffic from other roads to the national network such as A4 due to
shorter distances and travel times from origins in the Western, North-Western,
Northern and Central Provinces to the south.
Traffic generated due to the development of the Port of Hambantota and its direct
results in terms of increased population.
Traffic generated by the industries to be set up as part of the Greater Hambantota
Development Plan as discussed in Chapter 3.
Increase in traffic due to development of a 2nd international airport in terms of
direct air passengers and cargo movements, as well as the support services.
Since the growth of traffic is largely dependent on the development of the port and port
related industries and to a lesser extent on the other developments, this growth is
expected to increase slowly over the design life of the project taken as 20 years.
7.1 Inter- Regional Connectivity
Inter-Regional connectivity is an important objective of this proposed road network. Only
by ensuring this, would the Greater Hambantota Area Development Plan achieve a
nationally significant status. This includes:
Connection to Colombo/Sri Jayewardenepura which will continue to be the
primate city agglomeration in the country for all administrative and commercial
activities into the foreseeable future and the whole of the Western Province which
will also continue to be an area of high economic activity.
The international airport at Katunayake.
![Page 86: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/86.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-2
Other provincial centres in the Central, Uva, Sabaragamuwa and Eastern
provinces which are geographically well located for Hambantota and the project
impact area to become the primary production and distribution point for goods
and services required in those provinces. Goods in this respect could be both
agricultural and industrial as was discussed earlier.
Connection between tourist accommodations in the project impact area (Matara
to Tissamaharama) to other places of tourist interest particularly those in the Uva,
Central and Eastern Provinces for daily or one night excursions.
This shows the need of connection to the following areas outside the Project
Impact Area:
o Matara Galle Kalutara Colombo Gampaha Katunayake
Puttalam.
o Embilipitiya Ratnapura Kegalle Kurunegala & Kandy Districts
Matale
o ThanamalwilaWellawaya Bandarawela Badulla & Nuwera Eliya
o Thanamalwila Wellawaya Buttala Passara Mahiyangana
Polonnaruwa, (& Batticaloa) Anuradhapura & Trincomalee.
o ThanamalwilaWellawaya Amparai & Pottuvil Batticaloa
7.2 Design Parameters of Road Network
The geometric design parameters used in the traffic analysis will have an effect on the
traffic levels on the network due to increase in speed and other features that contribute
towards the reduction of overall travel costs and this the generation of new traffic from
increased development activity that it will promote within the Hambantota Development
Area as well as the diversion of existing traffic from the national network.
7.2.1 Road Network
The national road network updated to 2010 as included in the TransPlan Database18 has
been used in the traffic analysis. This includes all existing roads and improvements
18University of Moratuwa
![Page 87: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/87.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-3
done up to January 2010. The road network data used in the analysis includes
information for each link of the entire national road network, the length, roughness, road
side development, curvature and gradient, traffic management and control features,
crossings, and free flow speed. Additionally, each node has been identified and
provided with a unique identification number.
Table 7.1 gives the attributes of each section of road included in the road network for the
Hambantota Area.
![Page 88: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/88.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-4
Table 7-1: Design Parameters of the Proposed Hambantota Road Network
No Road Name Short Term Feature (m) Long Term Features (m)
Sta
rtN
od
e
En
dN
od
e
Th
rou
gh
No
de
s
Lin
kL
en
gth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
eW
idth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
e
HR01 Outer Circular Highway HX09 HX20 6.2 16 2X2 N/A 2 2X2
HR02 Hambantota – Gonnoruwa– Megahajandura Road
HX01 B’griyaJc.
6 16 3.5X2
N/A 1 N/A 39 2.5X2 2X2+2.5X2
2X2
B’riya Jc. HX13 HX07HX04
12 16 3.5X2
N/A 1 N/A 23 2X2 2X2 2X2
HR03 S’wewa – M’jandura –K’ragama Rd
HX23 HX22 HX24 18 9.5 N/A 1.5X2 N/A N/A 16 2X2 N/A 2 2X2
HX24 HX27 5.5 N/A 1X2 N/A N/A 16 2X2 N/A 2 2X2
HR04 A’wewa –U’mattala –Padawkema Rd
HX12 HX28 13 11.5 N/A 2X1 N/A N/A 16 2X2 N/A 2 2X2
HR05 Udawalawe –Thanamalwila Road
HX41 HX34 HX29 40 7 N/A 2X2 N/A N/A
HR06 Galwewa Junction -Moraketiya Road
HX23 HX25 12 9.5 N/A 1.5X2 N/A N/A 16 2X2 N/A 2 2X2
![Page 89: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/89.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-5
No Road Name Short Term Feature (m) Long Term Features (m)
Sta
rtN
od
e
En
dN
od
e
Th
rou
gh
No
de
s
Lin
kL
en
gth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
eW
idth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
e
HR07 Hambantota BypassRoad
HX18 HX17 HX05 13 16 2X2 N/A 2 2X2 22 2X2 2 2X2
HR08 N’aswewa-Swodagama-A’wewa Rd
HX16 HX12 HX32 8.4 11.5 N/A 2X1 N/A N/A 16 2X2 N/A 2 2X2
HR09 Bopale Junction -Kiribbanwewa Rd
HX24 HX25 8.5 5.5 N/A 1X2 N/A N/A 16 2X2 N/A 2 2X2
HR10 Embilipitiya – Moraketiya– Kiriibbanwewa -Udamadura Road
HX33 HX29 HX25,HX26
16.9 9.5 N/A 1.5X2 N/A N/A 16 2X2 N/A 2 2X2
HR11 Airport Central AccessRoad
HX15 HX04 1.6 7 N/A 2X2 N/A N/A
HR12 New Airport Access Road HX03 HX22 HX12 20 16 3.5X2
N/A 1 N/A 23 2X2 2X2 2X2
HR13 CGHW Road toThanamalwila
HX19 HX34 17 7 2X2 N/A N/A 2X2
HR14 Lewaya Road HX19 HX17 HX35 3.54 7 2X2 N/A N/A 2X2
HR15 Sooriyawewa –Padalangala Road
HX14 HX40 12 7 N/A 2X2 N/A N/A
![Page 90: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/90.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-6
No Road Name Short Term Feature (m) Long Term Features (m)
Sta
rtN
od
e
En
dN
od
e
Th
rou
gh
No
de
s
Lin
kL
en
gth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
eW
idth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
e
HR16 Sooriyawewa – MirijjawilaRoad
HX14 HX19 24 16 2X2 N/A 2 2X2 22 2X2 2 2X2
HR17 Extension of SouthernExpressway
G’gama HX06 74 16 N/A 3.5 10 N/A 24 N/A 3.5 2
HR18 Arabokka-Siyabalagaswewa-Gonnaruwa Road
HX08 HX07 HX06,HX21
10.5 16 2X2 N/A 2 2X2 22 2X2 2 2X2
HR19 Wetiya -Mahapalassa-N’gaswewa Rd
HX31 HX16 10 11.5 N/A 2X1 N/A N/A 16 2X2 N/A 2 2X2
HR20 Lunugamvehera -Kataragama Road
HX28 K’ma 15 11.5 N/A 2X1 N/A N/A 16 2X2 N/A 2 2X2
HR21 Ranna – A’pelessa -Wetiya Road
Ranna HX31 16.1 11.5 N/A 2X1 N/A N/A 16 2X2 N/A 2 2X2
HR22 Lunugamvehera -Weligatta Road
HX38 HX36 HX39 23.6 7 N/A 2X2 N/A N/A
HR23 7th Colony-WeerawilaRoad
HX39 HX37 4 7 N/A 2X2 N/A N/A
HR24 Udamattala –Thanamalwila
HX13 HX30 18 9.5 N/A 1.5X2 N/A N/A 16 2X2 N/A 2 2X2
![Page 91: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/91.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-7
No Road Name Short Term Feature (m) Long Term Features (m)
Sta
rtN
od
e
En
dN
od
e
Th
rou
gh
No
de
s
Lin
kL
en
gth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
eW
idth
Ca
rria
ge
wa
y
wid
th
Sid
ew
alk
wid
th
Sh
ou
lde
rw
idth
Me
dia
nw
idth
Cy
cle
Lan
e
HR25 Internal Road Grid in theCity Area
10 7 2X2 N/A N/A N/A
HR26 Southern ExpresswayAccess Road
3 7 N/A 2X2 N/A N/A
HR27 Walawe Project Road HX21 HX32 10 7 2X2 N/A N/A 2X2
![Page 92: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/92.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-8
7.2.2 New Roads to be Included
A number of new expressways and road rehabilitation projects are being planned but the
dates of completion of which are not certain. However, since the proposed expressway
network will have a direct bearing on the project impact area and is expected to be in
place over the next 10 years, the following expressways have been included in the road
network for traffic analysis.
Outer Circular Road from Kerawalapitiya to Kottawa
Southern Highway from Kottawa to Godagama
Extension of Southern Highway from Godagama to Hambantota
CKAH from Kadawatha to Mirigama (Stage I)
Colombo-Katunayake Expressway
All above roads have been assumed to operate as toll roads.
7.2.3 Other Modes of Transport
Since the Sri Lanka Rail (SLR) is also planning an extension of the Coast Line as a
single track up to Beliatta and thereafter to Kataragama, the effect of this too would be
considered on the Hambantota Development Area. With single track operations, the
modal split would be similar to that of Galle-Colombo and Matara-Colombo sectors.
However the travel time and costs savings by nearly one half with the expressway, the
railway’s contribution would be moderate unless it is being upgraded to a high speed
service. However, if current operating practices were to continue it would not be
significant.
The other possibility is that of domestic air travel. However, the share of this is not
expected to be significant since the difference in overall travel time will be only marginal
when considering the fact that access to airports at Ratmalana or Katunayake as well as
to Udamattala will take also an additional one hour or more and thus total travel time
advantage would be just around 30 minutes or so. Therefore only a very small
percentage can be expected to opt for air travel in a scenario where the expressway is
also available.
![Page 93: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/93.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-9
However in the case of goods transport, the railway can play a critical role carrying as
much as 50% or more traffic to Colombo even though traffic destined for other parts will
not benefit as much from the railways.
7.3 Traffic Forecasting
7.3.1 Forecast Year
As per the Terms of Reference the Traffic forecasts are made for the years 2012, 2022
and 2032. It is expected that full development potential of the Hambantota Development
Plan would have been achieved by the year 2032, while the year 2012 would see the
construction of the basic infrastructure such as the Stage I of the port, the air port, the
cricket stadium, administrative complex, safari park etc. The year 2022 would be
considered as an interim stage between 2012 and 2032.
7.3.2 ObservedTraffic Patterns
The ADT at the following roadside surveys referred to in Section 2.3 are tabulated along
with the peak hour flow given in Table 7.2.
Table 7-2: Summary of Observed Traffic Flows (2007)
Road/ LocationAverage Daily
TrafficPeak Hour
Flow
A002 – CGHW Road (Dickwella) 6,643 650
A002 – CGHW Road (Ranna) 4,666 325
A002 – CGHWRoad (Ambalantota) 5,201 530
A002 – CGHWRoad (Lunugamvehera) 1,920 250
B275 – Matara-Kamburupitiya Road (Kirinde) 2,406 375
A018 – Nonagama-Embilipitiya Road (Siyambalangoda) 2,199 225
This shows that the traffic levels on the Colombo-Galle-Hambantota-Wellawaya (CGHW)
Road (A2) remain somewhat steady between Matara and Hambantota. Of this flow also
around 50% of traffic is made up of two and three wheeler vehicles. This signifies a high
proportion of local traffic around the town centres and a steady flow of the long distance
traffic.
![Page 94: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/94.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-10
7.3.3 Origin Destination of Flows
The origin-destination of passenger vehicles and freight vehicles from the surveys
carried out in 2007 are summarised in the following Tables. The volumes signify very
little traffic originating in Hambantota and traffic passing through Hambantota to be an
even less.
Table 7-3: Daily One-Way Flow of Passenger Vehicles (Uva &Southern, 2007)
Dis
tric
ts
Co
lom
bo
Mata
ra
Ham
ban
tota
Mo
nara
gala
Ratn
ap
ura
Bad
ull
a
Colombo 0 403 159 119 0 1
Matara 1,295 466 266 83 38
Hambantota 1,624 0 443 0
Monaragala 0 36 0
Ratnapura 0 0
Badulla 0
Table 7-4: Daily One-Way Flow of Goods Vehicles (Uva &Southern, 2007)
Dis
tric
ts
Co
lom
bo
Mata
ra
Ham
ban
tota
Mo
nara
gala
Ratn
ap
ura
Bad
ull
a
Colombo 0 51 83 13 0 2
Matara 272 223 86 87 40
Hambantota 465 0 184 0
Monaragala 0 12 0
Ratnapura 0 0
Badulla 0
7.3.4 Future Traffic Generators
In addition to the existing traffic that will use the proposed road network, the bulk of the
traffic using this infrastructure is expected from the activities relating to the Hambantota
![Page 95: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/95.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-11
Development Plan as discussed in Chapter 3 where a number of approved projects that
will become major traffic attractors and/or generators have been identified. This means
that a high degree of new traffic has to be estimated along with the diverted traffic and
generated traffic.
The major development projects that have been identified for the purpose of this study
are:
Hambantota Seaport and associated developments
Mattala International Airport
Administrative Complex
Proposed BOI Zone in Meegahajandura
International Cricket Stadium at Sooriyawewa
City Centre Development
Commercial Establishment
Convention Centre
The other development centres have been considered as secondary generators which
would developonly if the above primary developments take place.
In the case of the Hambantota Seaport, traffic estimates have been based on the amount
of cargo that is expected to be handled, the nature of cargo in terms of containers or
break bulk, vehicles, liquid etc as well as what percentage is expected to be the
transhipment. The highway traffic generation rates are estimated by comparing with
estimates of traffic from Port of Colombo for its associated cargo movements. The
forecast cargo volumes are as given in the Feasibility Study for the Hambantota Seaport.
These estimated are used for estimation of the corresponding road traffic volumes. Their
destinations are allocated on the expected destinations especially those in the provinces
of Uva, Eastern, Central and Southern.
As for the Mattala International Airport, the forecast will be based on the estimated
passenger traffic and its probable local destinations which would mostly be in the tourist
area stretching from Bentota to Tissamaharama along the south western coast, and
further along the east coast, particularly for Arugam Bay area.
![Page 96: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/96.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-12
7.3.5 New Employment & Migration
In a project impact area where the bulk of the new traffic is to arise from almost entirely
new activity, it is required to estimate the new in-migration that will take place. This is
the fundamental building block. Table 7-5 shows the consultants tabulation of the
estimation based on available figures and assumptions where such figures are not
available. It is estimated that the Greater Hambantota Area will not incur rapid migration
by 2012 as most construction oriented jobs and jobs in other activities can be assumed
to be filled up mostly by those living within the Hambantota District. However with more
specialised jobs starting off in later years, it is estimated that in-migration would be in the
ratio of 2 ½ times the number of such employees. This means an employee to migration
ratio of around 0.4.
Table 7-5: Employment Estimation19
Proposed Development 2012 2022 2032
Hambantota International Port 3,000 4,000 5,000
Hambantota Logistics Park 2,000 4,000 8,000
Mattala International Airport 2,580 4,400 6,220
Mattala Logistics Park 1,000 2,000 4,000
Sooriyawewa Cricket Stadium & IT Park 14,176 28,351 56,702
Administrative Complex 2,000 4,500 4,500
Others 5,000 10,000 10,000
TOTAL 29,756 57,251 94,422
Migratory Population Estimation 30,000 130,000 230,000
Employees Provided/Population 0.99 0.44 0.41
Accordingly, the study assumes an in-migration of the above numbers of 30,000,
130,000 and 230,000 at the three forecast years as shown above. As such the
population estimates for the forecast years for each of the Divisional Secretariat
Divisions (DSD)’s will be assumed as given in Table 7-6 for the purpose of making traffic
forecasts
19Sources; SLPA, AASL, UDA and Consultants estimates where published figures do not exist
![Page 97: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/97.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-13
Table 7-6: Population Estimates for Hambantota Development Area (2012-2032)
DS No DS NAME 2012 2022 2032
3303000 Ambalantota 83,244 124,360 155,770
3304000 Hambantota 72,932 108,953 143,985
3305000 Lunugamwehera 29,451 43,997 52,076
3309000 Tissamaharama 84,459 116,469 145,886
3310000 Sooriyawewa 57,593 119,131 158,805
HDP Area 327,680 512,909 656,523
Hambantota District 666,019 901,714 1,103,321
7.3.6 Vehicle Ownership
The assumptions concerning vehicle ownership is an important determinant of estimating
traffic demand. Table 7-7 shows the vehicle growth rates used that have been used by
the University of Moratuwa in similar studies20 for estimating the corresponding rates of
economic growth versus transport policy.
Table 7-7: Vehicle Growth Rates to be used for Analysis
Condition of Public Transport
Economic Growth Rate (% p.a. pc.)
High = 7.5 Medium = 6% Low = 5%
Translates to Vehicle Growth (% p.a.)
Improved from Present ConditionScenario 1
6.0% p.a.Scenario 2
5.0% p.a.Scenario 3
4.0% p.a.
Present Condition RemainsScenario 4
8.0% p.a.Scenario 5
6.0% p.a.Scenario 6
5.0% p.a.
Deteriorates from Present ConditionScenario 7
10.0 % p.a.Scenario 8
7.0% p.a.Scenario 9
6.0% p.a.
As there is no visible program for the improvement of public transport, it will be assumed
that current levels of service will continue. Moreover, for the purpose of this study the
economic growth rate would be assumed to start at the High Level and move to
Moderate and Low levels for areas within Sri Lanka such as in Colombo District that
already have a high level of vehicle ownership. Moreover, districts that have been
subject to conflict in the past are now experiencing rapid growth in vehicle ownership,
which is expected to continue for next few years before tapering off to national levels.
20University of Moratuwa, Feasibility Study for Extension to Southern Highway, 2007
![Page 98: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/98.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-14
As such the following ranges for growth rate in fleet has been used in the forecasting as
shown in Table 7-8 along with the corresponding vehicle ownership projections.
Table 7-8: Vehicle Growth Rates (2012-2032)
Growth Scenario Up to 2012 2012-2022 2022-2023
Exceptionally High
Growth Spurt
Areas recovering from
conflict, economically
backward areas
experiencing growth
(10-12% p.a.) and
12% p.a. in
Hambantota area due
to internal migration
Hambantota area due
to internal migration at
10%
Hambantota area due
to internal migration at
8%
High 8% 8% Maximum 7%
Moderate 6% 6% 6%
Low 5% 5% 5%
Stabilizing Districts which have
reached Vehicle
Ownership Rate of
over 15% (4%pa);
Add, districts which
have reached Vehicle
Ownership Rate of
over 20% (3%pa);
Add districts which
have reached Vehicle
Ownership Rate of
over 25% (2%pa);
Accordingly the following control fleet parameters for the HDA and Sri Lanka have been
used. Vehicle Ownership shown in Table 7-9 is computed on the basis of number of
operating vehicles per 100 persons. It can be seen that ownership over the 20 year
period is assumed to increase from 9 vehicles per 100 persons to 23 vehicles per 100
persons. The economic development of Hambantota is considered to reach a status of
being second only to Colombo District and equal to the developed parts of Gampaha and
Kalutara District.
![Page 99: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/99.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-15
Table 7-9: Vehicle Fleet and Vehicle Ownership Rate: 2006-2032
Growth
Scenario
2006 2012 2022 2023
Fleet VOR Fleet VOR Fleet VOR Fleet VOR
Hambantota
District
54,685 9 130,442 14 212,476 22 314,516 29
Colombo
District
452,759 19 529,665 21 711,826 27 867,711 31
Sri Lanka 1,898,198 9 2,492,447 12 3,862,151 17 5,437,302 23
7.4 Scenarios for Benefit Cost Analysis
The basic economic scenarios tested will be tested for with 3rd scenarios which for
computation purpose referred to as the Hypothetical Cases I and II:
Base Case (without Hambantota Development Plan): The Base Case Scenario
will estimate traffic without the proposed Hambantota Development Plan and
assuming vehicle growth rates as indicated in Table 7-8 will continue in all other
areas of the country except in Hambantota District. Moreover, only the road
network excluding that which is proposed for the Hambantota Development Plan
would be assumed to be in place.
Proposed Case (with Hambantota Development Plan): This will assume all
development activities in terms of what has been discussed in Chapter 3 will be
carried out and that the proposed road network would be in place. It will be
based on vehicle growth rates indicated in Table 7-8.
Hypothetical Case I (Hambantota Development Plan without the Road
Network): This is only for purpose of identifying the differences in traffic level if
there is a scenario where there would be socioeconomic development without the
required road network development. This would indicate when compared with
![Page 100: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/100.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-16
Base Case the traffic levels due to the socioeconomic development only and
when compared to the Development Case the loss if the network is not in place.
Hypothetical Case II (Road Network without Hambantota Development Plan):
This is only for purpose of identifying the differences in traffic levels between that
which is due to network development and the generation of new activities. As
such it will be based on Base Case Scenario socio economic development and
Proposed Case scenario for road network development.
Table 7-10: Description of Testing Scenarios
RoadNetwork
Population & VehicleGrowth
Population VGRHDP SEDev
S1 Base CaseExisting +Expressways
Normal W/o changes inpopulation of growth rateto HDP
Normal Normal No
S2DevelopmentCase
Existing +Expressways+ HDPNetwork
With migration populationand higher Vehicle GR toHDP
with migrationpop growth inHDP
High Vehgrowthrates
includingHDPs
S3HypotheticalCase I
Existing +Expressways
With migration populationand higher vehicle GR toHDP
with migrationpop growth inHDP
High Vehgrowthrates
includingHDPs
S4HypotheticalCase II
Existing +Expressways+ HDPNetwork
Normal W/o changes inpopulation of growth rateto HDP
Normal Normal no
Table 7-11: Summary of Scenarios
HDP Road
NetworkMigration
Growth
Rate for
VoR
New Socio
Economic
Dev
S1 Base Case: No Project No No Normal No
S2 Full Development Case Yes Yes High Yes
S3 Hypothetical Case I No Yes High Yes
S4 Hypothetical Case II Yes No Normal No
7.4.1 Estimation Using TransPlan Traffic Demand Forecasting
The TransPlan demand estimation model has been used to estimate the demand for the
proposed scenario given above, taking into account the impact that the Hambantota
Development Plan will have on the entire national road network. These estimates will be
compared with the Base Case Scenario for purposes of estimating the benefits due from
the development.
![Page 101: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/101.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-17
The TransPlan demand estimation program has been used with the design criterion
given in Table 7-12, to estimate the future traffic estimates under the four scenarios
discussed earlier. The results of the Base Case forecast are given in Table 7-12, the
Development Case in Table 7-13 and the Hypothetical CasesI and II are given in Tables
7-14 and 7-15 respectively.
.
7.5 Generated Traffic
The total traffic for future years would be composed of three main categories, namely (a)
the traffic already existing on the road network; (b) the generated traffic that would arise
from the proposed development activities of the port, airport and other developments and
(c) the traffic that would be generated due to the development of the road network.
![Page 102: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/102.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-18
Table 7-12: TransPlan Estimates for Base Case Scenario (2012-2032)
Le n gth W idt h
R o a d N o . L ink N o km s 2 0 1 2 20 2 2 2 03 2 2 0 1 2 20 2 2 2 0 32 2 0 1 2 20 2 2 2 0 32 2 0 1 2 2 02 2 2 0 32
H 00 1 H0 0 1- 0 10 3 .11 16 .0 0 - - - - - - - - - - - -
H 00 1 H0 0 1- 0 20 3 .14 16 .0 0 - - - - - - - - - - - -
H 00 2 H0 0 2- 0 10 0 .59 39 .0 0 - - - - - - - - - - - -
H 00 2 H0 0 2- 0 20 3 .55 39 .0 0 - - - - - - - - - - - -
H 00 2 H0 0 2- 0 30 1 .40 39 .0 0 - - - - - - - - - - - -
H 00 2 H0 0 2- 0 40 7 .97 39 .0 0 - - - - - - - - - - - -
H 00 2 H0 0 2- 0 50 - - - - - - - - - - - - - -
H 00 2 H0 0 2- 0 60 - - - - - - - - - - - - - -
H 00 2 H0 0 2- 0 70 - - - - - - - - - - - - - -
H 00 3 H0 0 3- 0 10 - - - - - - - - - - - - - -
H 00 3 H0 0 3- 0 20 - - - - - - - - - - - - - -
H 00 3 H0 0 3- 0 30 - - - - - - - - - - - - - -
H 00 3 H0 0 3- 0 40 - - - - - - - - - - - - - -
H 00 4 H0 0 4- 0 10 - - - - - - - - - - - - - -
H 00 4 H0 0 4- 0 20 - - - - - - - - - - - - - -
H 00 4 H0 0 4- 0 30 - - - - - - - - - - - - - -
H 00 5 B4 2 7- 0 10 4 .92 5 .9 0 1 ,46 3 2 ,1 86 3,0 2 2 7 ,19 8 10 ,7 5 7 1 4 ,8 6 9 20 9 3 1 6 4 4 4 3 4 .44 34 .0 2 3 3.5 2
H 00 5 B4 2 7- 0 20 1 5 .58 4 .8 6 1 ,46 3 2 ,1 86 3,0 2 2 2 2 ,79 4 34 ,0 6 3 4 7 ,0 8 1 74 1 1 ,1 2 6 1 ,5 8 9 3 0 .77 30 .2 5 2 9.6 3
H 00 5 B4 2 7- 0 25 7 .00 5 .9 7 1 ,91 2 2 ,8 61 3,9 5 8 1 3 ,38 6 20 ,0 3 1 2 7 ,7 1 4 35 9 5 4 5 7 6 7 3 7 .32 36 .7 7 3 6.1 1
H 00 5 B4 2 7- 0 30 7 .51 5 .9 7 1 ,93 2 2 ,8 92 4,0 1 4 1 4 ,50 5 21 ,7 0 7 3 0 ,1 2 9 39 7 6 0 3 8 5 2 3 6 .58 36 .0 2 3 5.3 5
H 00 6 H0 0 6- 0 10 - - - - - - - - - - - - - -
H 00 7 H0 0 7- 0 10 - - - - - - - - - - - - - -
H 00 7 H0 0 7- 0 20 - - - - - - - - - - - - - -
H 00 7 H0 0 7- 0 30 - - - - - - - - - - - - - -
H 00 7 H0 0 7- 0 40 - - - - - - - - - - - - - -
H 00 7 H0 0 7- 0 50 - - - - - - - - - - - - - -
H 00 8 H0 0 8- 0 10 - - - - - - - - - - - - - -
H 00 8 H0 0 8- 0 20 - - - - - - - - - - - - - -
H 00 9 H0 0 9- 0 10 - - - - - - - - - - - - - -
H 01 0 B5 4 9- 0 10 5 .61 5 .3 4 1 ,91 4 2 ,8 47 3,9 5 8 1 0 ,73 1 15 ,9 6 5 2 2 ,1 9 7 39 7 6 0 5 8 6 7 2 7 .00 26 .3 8 2 5.6 1
H 01 0 B5 4 9- 0 15 0 .51 5 .3 4 1 ,67 1 2 ,4 92 3,4 3 7 84 9 1 ,2 6 6 1 ,7 4 6 2 9 4 4 6 2 2 9 .16 28 .6 1 2 7.9 7
H 01 0 B5 4 9- 0 20 8 .19 5 .3 4 1 ,19 4 1 ,7 72 2,4 7 0 9 ,77 2 14 ,5 0 2 2 0 ,2 2 2 32 7 4 9 1 6 9 6 2 9 .91 29 .5 3 2 9.0 7
H 01 0 B5 4 9- 0 25 2 .52 5 .3 4 1 ,39 1 2 ,0 61 2,8 7 7 3 ,51 0 5 ,1 9 9 7 ,2 6 0 11 8 1 7 7 2 5 2 2 9 .78 29 .3 4 2 8.8 0
H 01 1 H0 1 1- 0 10 - - - - - - - - - - - - - -
H 01 2 H0 1 2- 0 10 - - - - - - - - - - - - - -
A DT V e h icle K m s V e hic le H rs S pe e d
![Page 103: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/103.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-19
Len gth W idth
Road N o. L ink No km s 2012 2022 2032 2012 2022 2032 2012 2022 2032 2012 2022 2032
H 001 H001-010 3.11 16 .00 - - - - - - - - - - - -
ADT Veh icle Km s Vehic le H rs Speed
H 012 H012-010 - - - - - - - - - - - - - -
H 012 H012-020 - - - - - - - - - - - - - -
H 013 A002-830 0.76 7.00 1,101 1,632 2,307 841 1,247 1,763 25 38 54 33.42 33.16 32.82
H 013 A002-840 1.77 7.00 931 1,380 1,946 1,646 2,438 3,439 28 42 60 57.90 57.68 57.41
H 013 A002-845 2.11 7.00 532 783 1,132 1,123 1,655 2,392 19 29 41 58.09 57.97 57.80
H 013 A002-847 0.38 7.00 10,559 16,058 22,493 3,981 6,054 8,480 75 120 182 53.02 50.27 46.68
H 013 A002-850 6.07 7.00 10,520 15,991 22,430 63,879 97,096 136,196 1,200 1,922 2,901 53.25 50.52 46.94
H 013 A002-860 7.51 7.00 10,016 15,252 21,385 75,259 114,605 160,686 1,432 2,295 3,450 52.54 49.95 46.57
H 013 A002-870 4.92 7.00 3,729 5,522 7,614 18,360 27,189 37,493 334 502 707 55.02 54.12 53.05
H 013 A002-880 7.43 7.00 4,518 6,756 9,341 33,580 50,207 69,421 615 939 1,331 54.63 53.50 52.15
H 013 A002-890 3.79 7.00 4,799 7,152 9,940 18,209 27,134 37,713 326 497 710 55.78 54.59 53.13
H 013 A002-895 9.28 7.00 4,091 6,097 8,409 37,971 56,587 78,045 676 1,026 1,447 56.14 55.13 53.94
H 013 A002-900 1.80 7.00 4,679 6,956 9,613 8,427 12,528 17,314 150 228 323 56.14 54.99 53.60
H 014 B251-010 3.59 6.00 316 463 679 1,135 1,664 2,439 30 44 64 38.15 38.06 37.94
H 015 B563-010 8.44 6.00 1,163 1,732 2,421 9,815 14,623 20,444 201 301 424 48.93 48.60 48.21
H 015 B563-020 3.60 6.00 945 1,413 1,954 3,401 5,086 7,033 72 108 150 47.35 47.09 46.78
H 016 B562-010 3.82 6.28 533 784 1,129 2,036 2,992 4,309 37 54 78 55.61 55.48 55.29
H 016 B562-015 4.84 6.28 574 848 1,208 2,778 4,104 5,849 50 74 106 55.59 55.44 55.25
H 016 B562-020 10.86 6.28 - - - - - - - - - 55.62 55.62 55.62
H 016 B562-025 3.81 6.28 1,223 1,830 2,532 4,663 6,979 9,657 89 134 187 52.26 51.93 51.54
H 018 H018-010 - - - - - - - - - - - - - -
H 018 H018-020 - - - - - - - - - - - - - -
H 018 H018-030 - - - - - - - - - - - - - -
H 019 H019-010 - - - - - - - - - - - - - -
H 020 H020-010 - - - - - - - - - - - - - -
H 021 B548-010 5.48 4.99 1,328 2,026 2,845 7,276 11,101 15,587 233 361 517 31.24 30.75 30.17
H 021 B548-020 10.67 4.99 4,457 6,663 9,276 47,582 71,128 99,024 1,642 2,595 3,910 28.97 27.41 25.32
H 022 B567-010 10.84 2.84 269 401 552 2,916 4,342 5,984 200 301 420 14.61 14.45 14.26
H 022 B567-015 12.77 2.84 110 162 232 1,410 2,064 2,957 95 140 202 14.80 14.73 14.65
H 023 H023-010 - - - - - - - - - - - - - -
H 024 H024-010 - - - - - - - - - - - - - -
H 026 H026-010 - - - - - - - - - - - - - -
H 027 H027-010 - - - - - - - - - - - - - -
T otal 196.17 429,031 644,312 897,442 10,106 15,657 22,794
![Page 104: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/104.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-20
Table 7-13: TransPlan Estimates for Development Scenario (2012-2032)
W idth
Ro a d N o . L ink No 2 0 1 2 20 2 2 2 03 2 2 01 2 2 02 2 2 0 32 2 0 1 2 20 2 2 2 0 32 2 0 1 2 2 02 2 2 0 32
H0 0 1 H 00 1 -0 1 0 3 .11 1 6 2 ,52 3 5 ,0 90 8,0 6 2 7,8 5 3 1 5,8 4 6 2 5,0 9 7 11 3 2 3 1 3 6 9 6 9 .21 68 .6 7 6 8.0 3
H0 0 1 H 00 1 -0 2 0 3 .14 1 6 1 3 ,82 0 26 ,6 77 4 0,9 6 0 4 3,3 9 4 8 3,7 6 6 1 2 8,6 1 4 65 0 1 ,3 1 1 2 ,1 1 5 6 6 .78 63 .8 8 6 0.8 0
H0 0 2 H 00 2 -0 1 0 0 .59 3 9 5 ,01 3 9 ,7 69 1 5,5 0 7 2,9 7 8 5,8 0 3 9,2 1 1 3 3 6 4 1 0 2 9 1 .16 90 .7 5 9 0.2 5
H0 0 2 H 00 2 -0 2 0 3 .55 3 9 7 ,69 6 14 ,9 68 2 3,7 0 3 2 7,3 5 2 5 3,1 9 6 8 4,2 4 1 30 1 5 8 9 9 4 1 9 0 .93 90 .3 0 8 9.5 4
H0 0 2 H 00 2 -0 3 0 1 .40 3 9 1 2 ,60 2 23 ,1 05 3 5,4 2 1 1 7,6 5 5 3 2,3 7 0 4 9,6 2 5 19 5 3 6 1 5 6 1 9 0 .51 89 .5 9 8 8.5 0
H0 0 2 H 00 2 -0 4 0 7 .97 3 9 8 ,46 8 14 ,9 91 2 2,5 3 3 6 7,4 9 1 1 1 9,4 7 8 1 7 9,5 8 8 74 3 1 ,3 2 3 2 ,0 0 3 9 0 .86 90 .3 0 8 9.6 4
H0 0 2 H 00 2 -0 5 0 5 .06 3 9 9 ,41 1 17 ,0 80 2 5,8 9 4 4 7,5 8 3 8 6,3 5 8 1 3 0,9 1 9 52 4 9 5 8 1 ,4 6 5 9 0 .78 90 .1 2 8 9.3 4
H0 0 2 H 00 2 -0 6 0 2 .17 3 9 4 ,48 7 9 ,1 41 1 4,6 3 5 9,7 1 3 1 9,7 9 0 3 1,6 8 5 10 6 2 1 8 3 5 1 9 1 .21 90 .8 1 9 0.3 3
H0 0 2 H 00 2 -0 7 0 8 .61 3 9 4 ,13 2 9 ,2 30 1 4,5 9 3 3 5,5 8 1 7 9,4 6 9 1 2 5,6 4 9 39 0 8 7 5 1 ,3 9 1 9 1 .24 90 .8 0 9 0.3 3
H0 0 3 H 00 3 -0 1 0 2 .03 1 6 2 ,34 2 5 ,1 94 8,1 7 2 4,7 6 1 1 0,5 6 0 1 6,6 1 4 6 4 1 4 3 2 2 8 7 4 .22 73 .6 2 7 2.9 9
H0 0 3 H 00 3 -0 2 0 1 .98 1 6 4 ,25 1 8 ,9 71 1 3,9 3 3 8,4 0 4 1 7,7 3 5 2 7,5 4 5 11 4 2 4 4 3 8 4 7 3 .82 72 .8 1 7 1.7 4
H0 0 3 H 00 3 -0 3 0 5 .05 1 6 4 ,76 6 10 ,1 28 1 5,8 5 5 2 4,0 5 2 5 1,1 1 5 8 0,0 2 3 32 6 7 0 4 1 ,1 2 2 7 3 .71 72 .5 7 7 1.3 2
H0 0 3 H 00 3 -0 4 0 8 .65 1 6 37 6 8 04 1,2 2 7 3,2 5 4 6,9 6 0 1 0,6 2 1 4 4 9 3 1 4 3 7 4 .63 74 .5 5 7 4.4 6
H0 0 4 H 00 4 -0 1 0 2 .91 1 6 6 ,22 3 13 ,2 07 2 0,5 6 8 1 8,0 8 9 3 8,3 9 3 5 9,7 9 1 24 6 5 3 4 8 5 1 7 3 .40 71 .9 0 7 0.2 7
H0 0 4 H 00 4 -0 2 0 4 .15 1 6 6 ,08 0 12 ,0 73 1 8,5 3 7 2 5,2 1 4 5 0,0 6 7 7 6,8 7 4 34 3 6 9 4 1 ,0 8 7 7 3 .43 72 .1 4 7 0.7 2
H0 0 4 H 00 4 -0 3 0 6 .05 1 6 6 ,68 1 13 ,2 86 2 0,4 4 6 4 0,3 9 5 8 0,3 2 5 1 2 3,6 1 8 55 1 1 ,1 1 7 1 ,7 5 9 7 3 .30 71 .8 8 7 0.2 9
H0 0 5 B 42 7 -0 1 0 4 .92 7 1 ,67 3 2 ,5 76 3,6 2 1 1 5,8 1 6 2 4,3 5 3 3 4,2 3 3 32 2 5 0 1 7 1 2 4 9 .06 48 .6 2 4 8.1 0
H0 0 5 B 42 7 -0 2 0 1 5 .58 7 1 ,67 3 2 ,5 76 3,6 2 1 2 6,0 6 3 4 0,1 3 1 5 6,4 1 2 49 4 7 6 7 1 ,0 8 9 5 2 .73 52 .2 9 5 1.7 8
H0 0 5 B 42 7 -0 2 5 7 .00 7 2 ,28 5 3 ,5 09 4,9 2 3 1 5,9 9 6 2 4,5 6 9 3 4,4 7 0 30 2 4 6 9 6 6 7 5 2 .99 52 .3 9 5 1.6 9
H0 0 5 B 42 7 -0 3 0 7 .51 7 2 ,55 1 4 ,1 07 5,8 5 8 1 9,1 4 9 3 0,8 2 7 4 3,9 6 9 36 7 6 0 0 8 7 1 5 2 .13 51 .3 7 5 0.4 8
H0 0 6 H 00 6 -0 1 0 1 2 .25 1 6 2 ,59 0 5 ,2 88 8,0 6 4 3 1,7 2 2 6 4,7 6 6 9 8,7 7 0 42 8 8 8 0 1 ,3 5 3 7 4 .17 73 .6 0 7 3.0 1
H0 0 7 H 00 7 -0 1 0 4 .15 2 2 1 ,75 9 3 ,6 85 5,9 3 0 7,2 9 6 1 5,2 8 9 2 4,6 0 3 9 6 2 0 3 3 2 8 7 5 .67 75 .3 7 7 5.0 3
H0 0 7 H 00 7 -0 2 0 3 .73 2 2 2 ,70 4 5 ,9 02 9,5 4 7 1 0,0 9 3 2 2,0 2 8 3 5,6 3 0 13 4 2 9 4 4 7 8 7 5 .52 75 .0 3 7 4.4 7
H0 0 7 H 00 7 -0 3 0 0 .70 2 2 3 ,10 5 6 ,5 99 1 0,6 0 1 2,1 7 7 4,6 2 6 7,4 3 2 2 9 6 2 1 0 0 7 5 .46 74 .9 2 7 4.3 0
H0 0 7 H 00 7 -0 4 0 1 .65 2 2 1 ,74 9 3 ,5 65 5,7 6 3 2,8 7 7 5,8 6 4 9,4 8 0 3 8 7 8 1 2 6 7 5 .67 75 .3 9 7 5.0 5
H0 0 7 H 00 7 -0 5 0 1 .92 2 2 1 ,94 5 3 ,7 96 6,0 4 1 3,7 3 0 7,2 8 1 1 1,5 8 6 4 9 9 7 1 5 4 7 5 .64 75 .3 5 7 5.0 1
H0 0 8 H 00 8 -0 1 0 4 .15 1 6 1 ,77 1 4 ,2 56 6,8 9 0 7,3 4 2 1 7,6 5 1 2 8,5 7 4 9 9 2 3 9 3 9 0 7 4 .34 73 .8 2 7 3.2 6
H0 0 8 H 00 8 -0 2 0 4 .16 1 6 5 ,07 6 11 ,6 46 1 8,6 0 9 2 1,1 0 0 4 8,4 1 1 7 7,3 5 7 28 7 6 7 0 1 ,0 9 4 7 3 .65 72 .2 4 7 0.7 0
H0 0 9 H 00 9 -0 1 0 8 .02 1 6 1 ,83 0 3 ,7 19 5,6 8 1 1 4,6 8 1 2 9,8 3 0 4 5,5 6 4 19 8 4 0 3 6 2 0 7 4 .33 73 .9 3 7 3.5 2
H0 1 0 B 54 9 -0 1 0 5 .61 1 6 5 ,15 5 8 ,8 50 1 2,9 7 4 2 8,9 0 8 4 9,6 2 9 7 2,7 5 6 37 9 6 5 7 9 7 4 7 6 .37 75 .5 8 7 4.6 9
H0 1 0 B 54 9 -0 1 5 0 .51 1 6 4 ,24 1 7 ,5 10 1 1,0 1 0 2,1 5 4 3,8 1 5 5,5 9 3 2 7 4 9 7 3 7 8 .55 77 .8 6 7 7.1 0
H0 1 0 B 54 9 -0 2 0 8 .19 1 6 1 ,19 9 1 ,7 88 2,5 0 2 9,8 1 6 1 4,6 3 8 2 0,4 8 4 12 4 1 8 5 2 6 0 7 9 .19 79 .0 7 7 8.9 2
H0 1 0 B 54 9 -0 2 5 2 .52 1 6 1 ,73 8 2 ,9 85 4,3 8 4 4,3 8 5 7,5 3 2 1 1,0 6 0 5 5 9 6 1 4 1 7 9 .08 78 .8 1 7 8.5 2
H0 1 1 H 01 1 -0 1 0 1 .50 1 6 2 ,07 0 4 ,0 09 6,2 2 5 3,1 0 5 6,0 1 3 9,3 3 7 4 2 8 1 1 2 7 7 4 .28 73 .8 7 7 3.4 0
Lin kL en gt h
ADT V e h ic le Km s V e hic le H rs S pe e d
![Page 105: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/105.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-21
W idth
Ro a d N o . L ink No 2 0 1 2 20 2 2 2 03 2 2 01 2 2 02 2 2 0 32 2 0 1 2 20 2 2 2 0 32 2 0 1 2 2 02 2 2 0 32
H0 0 1 H 00 1 -0 1 0 3 .11 1 6 2 ,52 3 5 ,0 90 8,0 6 2 7,8 5 3 1 5,8 4 6 2 5,0 9 7 11 3 2 3 1 3 6 9 6 9 .21 68 .6 7 6 8.0 3
Lin kL en gt h
ADT V e h ic le Km s V e hic le H rs S pe e d
H0 1 1 H 01 1-01 0 1 .50 1 6 2 ,07 0 4 ,0 09 6,22 5 3,10 5 6,0 13 9,33 7 42 81 1 27 7 4 .28 73 .8 7 7 3.4 0
H0 1 2 H 01 2-01 0 3 .42 1 6 6 ,37 2 11 ,2 57 16,70 4 21,78 6 3 8,4 86 57,11 1 297 5 32 8 03 7 3 .37 72 .3 2 7 1.1 3
H0 1 2 H 01 2-02 0 4 .16 1 6 6 ,41 4 11 ,0 12 16,23 7 26,70 3 4 5,8 46 67,60 0 364 6 33 9 49 7 3 .36 72 .3 7 7 1.2 3
H0 1 3 A 00 2-83 0 0 .76 7 1 ,32 7 2 ,6 94 4,26 2 1,01 4 2,0 58 3,25 6 30 63 1 02 3 3 .31 32 .6 3 3 1.8 4
H0 1 3 A 00 2-84 0 1 .77 7 1 ,69 4 3 ,4 96 5,53 5 2,99 4 6,1 77 9,78 1 52 1 09 1 76 5 7 .53 56 .6 5 5 5.6 3
H0 1 3 A 00 2-84 5 2 .11 7 30 7 5 62 89 2 64 8 1,1 87 1,88 4 11 20 33 5 8 .20 58 .0 8 5 7.9 2
H0 1 3 A 00 2-84 7 0 .38 7 21 ,81 6 40 ,2 44 60,66 2 8,22 5 1 5,1 72 22,87 0 175 4 52 1 ,4 16 4 7 .10 33 .5 9 1 6.1 5
H0 1 3 A 00 2-85 0 6 .07 7 9 ,61 8 17 ,0 54 25,38 7 58,39 8 1 0 3,5 53 1 54,15 2 1 ,087 2 ,0 75 3 ,4 22 5 3 .73 49 .9 2 4 5.0 5
H0 1 3 A 00 2-86 0 7 .51 7 9 ,03 6 15 ,9 19 23,61 8 67,90 0 1 1 9,6 17 1 77,46 3 1 ,280 2 ,4 13 3 ,9 29 5 3 .06 49 .5 7 4 5.1 7
H0 1 3 A 00 2-87 0 4 .92 7 1 ,24 8 2 ,3 51 3,56 6 6,14 3 1 1,5 75 17,55 7 109 2 08 3 19 5 6 .23 55 .7 0 5 5.1 0
H0 1 3 A 00 2-88 0 7 .43 7 1 ,83 8 3 ,6 05 5,47 0 13,66 2 2 6,7 91 40,65 1 244 4 86 7 51 5 5 .95 55 .0 8 5 4.1 5
H0 1 3 A 00 2-89 0 3 .79 7 8 ,87 0 16 ,8 27 25,49 0 33,65 4 6 3,8 40 96,70 9 627 1 ,2 87 2 ,1 72 5 3 .69 49 .6 1 4 4.5 2
H0 1 3 A 00 2-89 5 9 .28 7 2 ,30 5 3 ,7 40 5,37 1 21,39 3 3 4,7 09 49,84 7 375 6 16 8 98 5 7 .02 56 .3 1 5 5.5 0
H0 1 3 A 00 2-90 0 1 .80 7 7 ,10 8 11 ,5 39 16,53 7 12,80 1 2 0,7 81 29,78 3 233 3 93 5 95 5 4 .91 52 .8 3 5 0.0 8
H0 1 4 B 25 1-01 0 3 .59 7 28 1 5 14 81 6 1,00 9 1,8 47 2,93 2 20 36 57 5 1 .72 51 .6 1 5 1.4 7
H0 1 5 B 56 3-01 0 8 .44 7 1 ,34 1 2 ,9 54 4,59 4 11,32 5 2 4,9 43 38,79 1 213 4 77 7 54 5 3 .05 52 .2 7 5 1.4 5
H0 1 5 B 56 3-02 0 3 .60 7 1 ,19 2 2 ,6 38 4,08 8 4,29 2 9,4 96 14,71 8 81 1 81 2 85 5 3 .13 52 .4 2 5 1.7 1
H0 1 6 B 56 2-01 0 3 .82 2 2 1 ,66 6 3 ,4 31 5,50 2 6,35 8 1 3,0 96 21,00 3 74 1 52 2 45 8 6 .40 86 .1 3 8 5.8 1
H0 1 6 B 56 2-01 5 4 .84 2 2 2 ,81 2 6 ,4 00 10,44 4 13,60 8 3 0,9 76 50,54 7 158 3 62 5 94 8 6 .22 85 .6 7 8 5.0 5
H0 1 6 B 56 2-02 0 1 0 .86 2 2 - - - - - - - - - 8 6 .22 86 .2 2 8 6.2 2
H0 1 6 B 56 2-02 5 3 .81 2 2 4 ,44 5 10 ,5 99 17,23 3 16,95 4 4 0,4 24 65,72 7 204 4 93 8 11 8 2 .99 82 .0 4 8 1.0 0
H0 1 8 H 01 8-01 0 5 .10 2 2 1 ,00 5 1 ,9 04 3,01 4 5,12 8 9,7 10 15,37 6 64 1 20 1 91 8 0 .76 80 .6 2 8 0.4 5
H0 1 8 H 01 8-02 0 2 .19 2 2 1 ,66 0 3 ,3 75 5,38 8 3,63 5 7,3 92 11,80 0 45 92 1 47 8 0 .66 80 .3 9 8 0.0 9
H0 1 8 H 01 8-03 0 3 .11 2 2 1 ,49 8 3 ,0 14 4,80 4 4,66 3 9,3 84 14,95 4 58 1 17 1 87 8 0 .68 80 .4 5 8 0.1 8
H0 1 9 H 01 9-01 0 1 0 .35 1 6 3 ,70 9 8 ,2 51 13,01 3 38,39 9 8 5,4 27 1 34,73 5 519 1 ,1 71 1 ,8 73 7 3 .94 72 .9 7 7 1.9 4
H0 2 0 H 02 0-01 0 1 6 .62 1 6 8 ,87 7 16 ,6 49 25,13 5 1 47,52 2 2 7 6,6 80 4 17,69 5 2 ,025 3 ,8 89 6 ,0 33 7 2 .83 71 .1 4 6 9.2 3
H0 2 1 B 54 8-01 0 5 .48 1 6 3 ,41 2 7 ,2 87 11,49 7 18,69 2 3 9,9 26 62,99 3 239 5 16 8 23 7 8 .23 77 .4 1 7 6.5 0
H0 2 1 B 54 8-02 0 1 0 .67 1 6 7 ,47 3 13 ,4 46 19,99 1 79,77 4 1 4 3,5 29 2 13,39 9 1 ,031 1 ,8 87 2 ,8 59 7 7 .37 76 .0 8 7 4.6 3
H0 2 2 B 56 7-01 0 1 0 .84 7 24 5 4 72 71 4 2,65 9 5,1 13 7,74 3 49 94 1 42 5 4 .73 54 .6 2 5 4.5 0
H0 2 2 B 56 7-01 5 1 2 .77 7 28 0 5 09 76 8 3,57 0 6,4 96 9,80 4 65 1 19 1 80 5 4 .71 54 .6 0 5 4.4 7
H0 2 3 H 02 3-01 0 9 .50 7 6 1 1 31 20 4 58 2 1,2 44 1,93 5 12 25 39 4 9 .84 49 .8 0 4 9.7 7
H0 2 4 H 02 4-01 0 9 .49 1 6 4 ,70 1 7 ,7 10 11,05 2 44,62 8 7 3,1 95 1 04,93 2 605 1 ,0 02 1 ,4 50 7 3 .73 73 .0 9 7 2.3 7
H0 2 6 H 02 6-01 0 3 .28 2 4 2 ,66 6 5 ,4 69 8,73 6 8,74 6 1 7,9 45 28,66 2 112 2 31 3 71 7 8 .21 77 .8 2 7 7.3 6
H0 2 7 H 02 7-01 0 1 0 .90 7 2 6 83 14 5 28 7 9 06 1,57 8 5 17 29 5 4 .57 54 .8 2 5 4.7 9
T ot al 3 63 1 ,2 97,33 0 2 ,4 5 6,0 05 3,7 35,00 9 1 8 ,676 36 ,05 8 5 7 ,0 62
![Page 106: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/106.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-22
Table 7-14: TransPlan Estimates for Hypothetical Scenario I (2012-2032)
Le n gth W idt h
Ro a d N o . L ink No km s 2 0 1 2 20 2 2 2 03 2 2 0 1 2 20 2 2 2 03 2 2 0 12 20 2 2 2 03 2 2 0 1 2 2 02 2 2 0 3 2
H0 0 1 H 00 1 -0 1 0 - - - - - - - - - - - - - -
H0 0 1 H 00 1 -0 2 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 1 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 2 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 3 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 4 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 5 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 6 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 7 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 1 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 2 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 3 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 4 0 - - - - - - - - - - - - - -
H0 0 4 H 00 4 -0 1 0 - - - - - - - - - - - - - -
H0 0 4 H 00 4 -0 2 0 - - - - - - - - - - - - - -
H0 0 4 H 00 4 -0 3 0 - - - - - - - - - - - - - -
H0 0 5 B 42 7 -0 1 0 9 .45 5 .9 0 69 5 1 ,0 76 1,4 9 7 6 ,57 3 10 ,1 6 9 1 4,1 4 8 18 8 2 93 4 1 1 3 4.8 8 34 .6 7 3 4 .4 2
H0 0 5 B 42 7 -0 2 0 1 5 .58 4 .8 6 69 5 1 ,0 76 1,4 9 7 1 0 ,83 3 16 ,7 5 9 2 3,3 1 6 34 6 5 40 7 5 8 3 1.3 1 31 .0 4 3 0 .7 4
H0 0 5 B 42 7 -0 2 5 7 .00 5 .9 7 1 ,54 0 2 ,4 80 3,5 1 4 1 0 ,78 3 17 ,3 6 3 2 4,6 0 7 28 7 4 69 6 7 6 3 7.5 4 36 .9 9 3 6 .3 8
H0 0 5 B 42 7 -0 3 0 7 .51 5 .9 7 1 ,57 8 2 ,5 40 3,6 1 3 1 1 ,84 1 19 ,0 6 4 2 7,1 1 5 32 2 5 26 7 6 2 3 6.7 9 36 .2 3 3 5 .5 9
H0 0 6 H 00 6 -0 1 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 1 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 2 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 3 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 4 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 5 0 - - - - - - - - - - - - - -
H0 0 8 H 00 8 -0 1 0 - - - - - - - - - - - - - -
H0 0 8 H 00 8 -0 2 0 - - - - - - - - - - - - - -
H0 0 9 H 00 9 -0 1 0 - - - - - - - - - - - - - -
H0 1 0 B 54 9 -0 1 0 5 .61 5 .3 4 2 ,28 6 3 ,6 17 5,1 3 0 1 2 ,81 9 20 ,2 8 2 2 8,7 7 0 47 9 7 85 1,1 5 5 2 6.7 6 25 .8 5 2 4 .9 1
H0 1 0 B 54 9 -0 1 5 0 .51 5 .3 4 2 ,04 3 3 ,2 62 4,6 1 0 1 ,03 8 1 ,6 5 7 2,3 4 2 3 6 59 8 6 2 8.9 1 28 .0 9 2 7 .2 9
H0 1 0 B 54 9 -0 2 0 8 .19 5 .3 4 1 ,52 0 2 ,4 11 3,4 2 8 1 2 ,44 5 19 ,7 3 5 2 8,0 6 0 41 9 6 78 9 8 7 2 9.7 0 29 .1 1 2 8 .4 2
H0 1 0 B 54 9 -0 2 5 2 .52 5 .3 4 1 ,34 4 2 ,1 36 3,0 6 0 3 ,39 0 5 ,3 8 9 7,7 2 1 11 4 1 84 2 6 9 2 9.8 1 29 .2 9 2 8 .6 7
ADT V e h ic le Km s V e hic le H rs S pe e d
![Page 107: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/107.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-23
Le n gth W idt h
Ro ad N o . L ink No km s 2 01 2 20 2 2 2 032 2 0 12 202 2 2 03 2 20 12 20 22 2 03 2 2 01 2 2 022 20 3 2
H0 01 H 00 1 -0 1 0 - - - - - - - - - - - - - -
ADT V e h ic le Km s V e hic le H rs S pee d
H0 1 0 B 54 9 -0 2 5 2 .52 5 .3 4 1 ,34 4 2 ,1 36 3,0 6 0 3 ,39 0 5 ,3 8 9 7,7 2 1 11 4 1 84 2 6 9 2 9.8 1 29 .2 9 2 8 .6 7
H0 1 1 H 01 1 -0 1 0 - - - - - - - - - - - - - -
H0 1 2 H 01 2 -0 1 0 - - - - - - - - - - - - - -
H0 1 2 H 01 2 -0 2 0 - - - - - - - - - - - - - -
H0 1 3 A 00 2 -8 3 0 0 .76 7 .0 0 2 ,98 3 6 ,0 99 9,6 1 5 2 ,27 9 4 ,6 6 0 7,3 4 6 7 0 1 51 2 5 3 3 2.4 9 30 .8 7 2 9 .0 9
H0 1 3 A 00 2 -8 4 0 1 .77 7 .0 0 2 ,52 7 5 ,1 50 8,1 0 1 4 ,46 5 9 ,1 0 0 1 4,3 1 5 7 8 1 63 2 6 4 5 7.1 3 55 .8 3 5 4 .3 2
H0 1 3 A 00 2 -8 4 5 2 .11 7 .0 0 1 ,10 6 2 ,1 71 3,4 4 1 2 ,33 7 4 ,5 8 6 7,2 6 9 4 0 80 1 2 8 5 7.8 1 57 .3 0 5 6 .6 8
H0 1 3 A 00 2 -8 4 7 0 .38 7 .0 0 1 5 ,63 2 27 ,2 22 4 0,0 9 3 5 ,89 3 10 ,2 6 3 1 5,1 1 5 11 7 2 34 4 4 8 5 0.5 1 43 .8 1 3 3 .7 6
H0 1 3 A 00 2 -8 5 0 6 .07 7 .0 0 1 4 ,77 7 25 ,3 13 3 7,0 7 8 8 9 ,72 7 1 53 ,6 9 9 2 2 5,1 3 8 1 ,75 2 3 ,4 08 6,1 3 2 5 1.2 0 45 .1 0 3 6 .7 2
H0 1 3 A 00 2 -8 6 0 7 .51 7 .0 0 1 3 ,78 8 23 ,4 36 3 4,1 7 5 10 3 ,60 3 1 76 ,0 9 8 2 5 6,7 8 7 2 ,04 1 3 ,8 88 6,7 7 0 5 0.7 6 45 .2 9 3 7 .9 3
H0 1 3 A 00 2 -8 7 0 4 .92 7 .0 0 4 ,79 7 7 ,9 17 1 1,3 7 7 2 3 ,61 9 38 ,9 8 2 5 6,0 2 1 43 3 7 37 1,0 9 2 5 4.4 9 52 .9 0 5 1 .3 1
H0 1 3 A 00 2 -8 8 0 7 .43 7 .0 0 5 ,58 2 9 ,4 02 1 3,5 9 3 4 1 ,48 5 69 ,8 7 7 1 0 1,0 2 4 76 7 1 ,3 41 2,0 1 6 5 4.0 9 52 .1 1 5 0 .1 1
H0 1 3 A 00 2 -8 9 0 3 .79 7 .0 0 5 ,43 4 8 ,9 63 1 2,9 2 4 2 0 ,61 7 34 ,0 0 5 4 9,0 3 5 37 2 6 34 9 4 7 5 5.4 6 53 .6 5 5 1 .7 9
H0 1 3 A 00 2 -8 9 5 9 .28 7 .0 0 4 ,33 1 6 ,9 64 9,8 8 8 4 0 ,19 7 64 ,6 3 1 9 1,7 7 2 71 8 1 ,1 82 1,7 2 6 5 6.0 2 54 .6 8 5 3 .1 6
H0 1 3 A 00 2 -9 0 0 1 .80 7 .0 0 5 ,31 5 8 ,7 40 1 2,5 5 8 9 ,57 2 15 ,7 4 1 2 2,6 1 7 17 1 2 91 4 3 3 5 5.8 2 54 .0 6 5 2 .2 8
H0 1 4 B 25 1 -0 1 0 3 .59 6 .0 0 46 5 8 51 1,3 5 1 1 ,67 0 3 ,0 5 7 4,8 5 3 4 4 81 1 2 9 3 8.0 6 37 .8 5 3 7 .5 6
H0 1 5 B 56 3 -0 1 0 8 .44 6 .0 0 2 ,16 4 5 ,1 66 8,1 6 3 1 8 ,27 1 43 ,6 1 7 6 8,9 2 0 37 8 9 36 1,5 4 0 4 8.3 6 46 .6 0 4 4 .7 5
H0 1 5 B 56 3 -0 2 0 3 .60 6 .0 0 1 ,89 5 4 ,5 95 7,2 4 9 6 ,82 2 16 ,5 4 0 2 6,0 9 7 14 6 3 66 5 9 8 4 6.8 1 45 .2 4 4 3 .6 2
H0 1 6 B 56 2 -0 1 0 3 .82 6 .2 8 1 ,05 4 2 ,2 41 3,6 1 3 4 ,02 2 8 ,5 5 5 1 3,7 9 3 7 3 1 56 2 5 6 5 5.3 3 54 .6 9 5 3 .9 4
H0 1 6 B 56 2 -0 1 5 4 .84 6 .2 8 1 ,44 2 3 ,1 55 5,0 8 7 6 ,97 9 15 ,2 7 1 2 4,6 2 1 12 7 2 82 4 6 4 5 5.1 2 54 .1 9 5 3 .1 1
H0 1 6 B 56 2 -0 2 0 1 0 .86 6 .2 8 - - - - - - - - - 5 5.6 2 55 .6 2 5 5 .6 2
H0 1 6 B 56 2 -0 2 5 3 .81 6 .2 8 2 ,84 9 7 ,4 26 1 2,0 5 0 1 0 ,86 6 28 ,3 2 3 4 5,9 5 8 21 2 5 81 9 9 4 5 1.3 7 48 .7 7 4 6 .2 2
H0 1 8 H 01 8 -0 1 0 - - - - - - - - - - - - - -
H0 1 8 H 01 8 -0 2 0 - - - - - - - - - - - - - -
H0 1 8 H 01 8 -0 3 0 - - - - - - - - - - - - - -
H0 1 9 H 01 9 -0 1 0 - - - - - - - - - - - - - -
H0 2 0 H 02 0 -0 1 0 - - - - - - - - - - - - - -
H0 2 1 B 54 8 -0 1 0 5 .48 4 .9 9 3 ,35 8 6 ,6 50 1 0,1 7 3 1 8 ,39 8 36 ,4 3 7 5 5,7 3 7 61 8 1 ,3 29 2,2 7 5 2 9.7 9 27 .4 2 2 4 .5 0
H0 2 1 B 54 8 -0 2 0 1 0 .67 4 .9 9 6 ,33 2 11 ,0 83 1 6,2 4 4 6 7 ,59 2 1 18 ,3 1 2 1 7 3,4 0 6 2 ,44 2 4 ,9 81 9,7 5 0 2 7.6 7 23 .7 5 1 7 .7 9
H0 2 2 B 56 7 -0 1 0 1 0 .84 2 .8 4 67 2 1 ,2 79 1,9 2 7 7 ,28 0 13 ,8 5 8 2 0,8 8 7 51 6 1 ,0 35 1,6 7 3 1 4.1 1 13 .3 9 1 2 .4 9
H0 2 2 B 56 7 -0 1 5 1 2 .77 2 .8 4 15 5 2 71 4 0 8 1 ,97 4 3 ,4 6 4 5,2 0 6 13 4 2 37 3 6 1 1 4.7 4 14 .6 0 1 4 .4 4
H0 2 3 H 02 3 -0 1 0 - - - - - - - - - - - - - -
H0 2 4 H 02 4 -0 1 0 - - - - - - - - - - - - - -
H0 2 6 H 02 6 -0 1 0 - - - - - - - - - - - - - -
H0 2 7 H 02 7 -0 1 0 - - - - - - - - - - - - - -
T ot al 1 8 0 .93 1 0 8 ,35 8 1 92 ,6 89 2 8 5,4 5 6 55 7 ,38 8 9 79 ,4 9 2 1 ,4 4 1,9 9 6 1 3 ,43 9 2 5 ,6 27 4 3,3 5 1
![Page 108: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/108.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-24
Table 7-15: TransPlan Estimates for Hypothetical Scenario II (2012-2032)
Le n gth W idt h
Ro a d N o . L ink No km s 2 0 1 2 20 2 2 2 03 2 2 0 1 2 20 2 2 2 03 2 2 0 12 20 2 2 2 03 2 2 0 1 2 2 02 2 2 0 3 2
H0 0 1 H 00 1 -0 1 0 - - - - - - - - - - - - - -
H0 0 1 H 00 1 -0 2 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 1 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 2 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 3 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 4 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 5 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 6 0 - - - - - - - - - - - - - -
H0 0 2 H 00 2 -0 7 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 1 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 2 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 3 0 - - - - - - - - - - - - - -
H0 0 3 H 00 3 -0 4 0 - - - - - - - - - - - - - -
H0 0 4 H 00 4 -0 1 0 - - - - - - - - - - - - - -
H0 0 4 H 00 4 -0 2 0 - - - - - - - - - - - - - -
H0 0 4 H 00 4 -0 3 0 - - - - - - - - - - - - - -
H0 0 5 B 42 7 -0 1 0 9 .45 5 .9 0 69 5 1 ,0 76 1,4 9 7 6 ,57 3 10 ,1 6 9 1 4,1 4 8 18 8 2 93 4 1 1 3 4.8 8 34 .6 7 3 4 .4 2
H0 0 5 B 42 7 -0 2 0 1 5 .58 4 .8 6 69 5 1 ,0 76 1,4 9 7 1 0 ,83 3 16 ,7 5 9 2 3,3 1 6 34 6 5 40 7 5 8 3 1.3 1 31 .0 4 3 0 .7 4
H0 0 5 B 42 7 -0 2 5 7 .00 5 .9 7 1 ,54 0 2 ,4 80 3,5 1 4 1 0 ,78 3 17 ,3 6 3 2 4,6 0 7 28 7 4 69 6 7 6 3 7.5 4 36 .9 9 3 6 .3 8
H0 0 5 B 42 7 -0 3 0 7 .51 5 .9 7 1 ,57 8 2 ,5 40 3,6 1 3 1 1 ,84 1 19 ,0 6 4 2 7,1 1 5 32 2 5 26 7 6 2 3 6.7 9 36 .2 3 3 5 .5 9
H0 0 6 H 00 6 -0 1 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 1 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 2 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 3 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 4 0 - - - - - - - - - - - - - -
H0 0 7 H 00 7 -0 5 0 - - - - - - - - - - - - - -
H0 0 8 H 00 8 -0 1 0 - - - - - - - - - - - - - -
H0 0 8 H 00 8 -0 2 0 - - - - - - - - - - - - - -
H0 0 9 H 00 9 -0 1 0 - - - - - - - - - - - - - -
H0 1 0 B 54 9 -0 1 0 5 .61 5 .3 4 2 ,28 6 3 ,6 17 5,1 3 0 1 2 ,81 9 20 ,2 8 2 2 8,7 7 0 47 9 7 85 1,1 5 5 2 6.7 6 25 .8 5 2 4 .9 1
H0 1 0 B 54 9 -0 1 5 0 .51 5 .3 4 2 ,04 3 3 ,2 62 4,6 1 0 1 ,03 8 1 ,6 5 7 2,3 4 2 3 6 59 8 6 2 8.9 1 28 .0 9 2 7 .2 9
H0 1 0 B 54 9 -0 2 0 8 .19 5 .3 4 1 ,52 0 2 ,4 11 3,4 2 8 1 2 ,44 5 19 ,7 3 5 2 8,0 6 0 41 9 6 78 9 8 7 2 9.7 0 29 .1 1 2 8 .4 2
H0 1 0 B 54 9 -0 2 5 2 .52 5 .3 4 1 ,34 4 2 ,1 36 3,0 6 0 3 ,39 0 5 ,3 8 9 7,7 2 1 11 4 1 84 2 6 9 2 9.8 1 29 .2 9 2 8 .6 7
H0 1 1 H 01 1 -0 1 0 - - - - - - - - - - - - - -
ADT V e h ic le Km s V e hic le H rs S pe e d
![Page 109: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/109.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-25
Len gth W idth
Road N o. L ink No km s 2012 2022 2032 2012 2022 2032 2012 2022 2032 2012 2022 2032
ADT Veh ic le Km s Vehic le H rs Speed
H010 B 549-025 2.52 5.34 1,344 2,136 3,060 3,390 5,389 7,721 114 184 269 29.81 29.29 28.67
H011 H 011-010 - - - - - - - - - - - - - -
H012 H 012-010 - - - - - - - - - - - - - -
H012 H 012-020 - - - - - - - - - - - - - -
H013 A 002-830 0.76 7.00 2,983 6,099 9,615 2,279 4,660 7,346 70 151 253 32.49 30.87 29.09
H013 A 002-840 1.77 7.00 2,527 5,150 8,101 4,465 9,100 14,315 78 163 264 57.13 55.83 54.32
H013 A 002-845 2.11 7.00 1,106 2,171 3,441 2,337 4,586 7,269 40 80 128 57.81 57.30 56.68
H013 A 002-847 0.38 7.00 15,632 27,222 40,093 5,893 10,263 15,115 117 234 448 50.51 43.81 33.76
H013 A 002-850 6.07 7.00 14,777 25,313 37,078 89,727 153,699 225,138 1,752 3,408 6,132 51.20 45.10 36.72
H013 A 002-860 7.51 7.00 13,788 23,436 34,175 103,603 176,098 256,787 2,041 3,888 6,770 50.76 45.29 37.93
H013 A 002-870 4.92 7.00 4,797 7,917 11,377 23,619 38,982 56,021 433 737 1,092 54.49 52.90 51.31
H013 A 002-880 7.43 7.00 5,582 9,402 13,593 41,485 69,877 101,024 767 1,341 2,016 54.09 52.11 50.11
H013 A 002-890 3.79 7.00 5,434 8,963 12,924 20,617 34,005 49,035 372 634 947 55.46 53.65 51.79
H013 A 002-895 9.28 7.00 4,331 6,964 9,888 40,197 64,631 91,772 718 1,182 1,726 56.02 54.68 53.16
H013 A 002-900 1.80 7.00 5,315 8,740 12,558 9,572 15,741 22,617 171 291 433 55.82 54.06 52.28
H014 B 251-010 3.59 6.00 465 851 1,351 1,670 3,057 4,853 44 81 129 38.06 37.85 37.56
H015 B 563-010 8.44 6.00 2,164 5,166 8,163 18,271 43,617 68,920 378 936 1,540 48.36 46.60 44.75
H015 B 563-020 3.60 6.00 1,895 4,595 7,249 6,822 16,540 26,097 146 366 598 46.81 45.24 43.62
H016 B 562-010 3.82 6.28 1,054 2,241 3,613 4,022 8,555 13,793 73 156 256 55.33 54.69 53.94
H016 B 562-015 4.84 6.28 1,442 3,155 5,087 6,979 15,271 24,621 127 282 464 55.12 54.19 53.11
H016 B 562-020 10.86 6.28 - - - - - - - - - 55.62 55.62 55.62
H016 B 562-025 3.81 6.28 2,849 7,426 12,050 10,866 28,323 45,958 212 581 994 51.37 48.77 46.22
H018 H 018-010 - - - - - - - - - - - - - -
H018 H 018-020 - - - - - - - - - - - - - -
H018 H 018-030 - - - - - - - - - - - - - -
H019 H 019-010 - - - - - - - - - - - - - -
H020 H 020-010 - - - - - - - - - - - - - -
H021 B 548-010 5.48 4.99 3,358 6,650 10,173 18,398 36,437 55,737 618 1,329 2,275 29.79 27.42 24.50
H021 B 548-020 10.67 4.99 6,332 11,083 16,244 67,592 118,312 173,406 2,442 4,981 9,750 27.67 23.75 17.79
H022 B 567-010 10.84 2.84 672 1,279 1,927 7,280 13,858 20,887 516 1,035 1,673 14.11 13.39 12.49
H022 B 567-015 12.77 2.84 155 271 408 1,974 3,464 5,206 134 237 361 14.74 14.60 14.44
H023 H 023-010 - - - - - - - - - - - - - -
H024 H 024-010 - - - - - - - - - - - - - -
H026 H 026-010 - - - - - - - - - - - - - -
H027 H 027-010 - - - - - - - - - - - - - -
T otal 180.93 108,358 192,689 285,456 557,388 979,492 1,441,996 13,439 25,627 43,351
![Page 110: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/110.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-26
7.6 Port Based Traffic
Much of the above mentioned generated traffic will be associated with the activities of
the proposed port. An attempt has been made to estimate this specifically with a view of
determining an estimate of heavy vehicles using the port. For this purpose, estimates of
traffic movements in and out of the Port of Colombo have been used21. The total
average flows in and out of each gate as recorded in that study are given in Table 6-16
below. While weekend traffic is low, the week day traffic levels show around 13,000
vehicle movements including 4,800 freight vehicle movements.
Table 7-17 shows the breakdown of these vehicles by gate and Table 7-18 shows the
breakdown by vehicle type. It also yields a unit rate for traffic movements per cargo
movements. Accordingly, it has been estimated that there are 34.9 two and there
wheeled vehicles per 1000 MT of goods movements while for four wheel passenger
vehicles the estimate is 39.5 vehicles. In the case of goods vehicles there are 29.1
small goods vehicles and 67.6 medium goods vehicles per 1000 MT of cargo movement
handled by the port. Additionally there are 1.12 container truck movements per
container movement in or out of the port.
Table 7-16: Average Daily Flows at Port of Colombo
GateWeekday Weekend
All vehicles Freight Vehicles All vehicles Freight vehicles
De Saram In 1,505 840 699 347
Out 1,349 614 739 273
Port In 1,673 1,122 782 487
Access Out 1,935 1,096 685 325
Export In 2,011 55 358 18
Out 1,679 119 556 39
JCT In 1,024 15 437 7
Out 494 89 187 4
Main In 502 15 111 13
Out 446 15 111 8
LB In - - - -
Out 515 155 163 58
All gates In 6,714 2,386 2,046 872
Out 6,417 2,440 2,087 706
21Source: Analysis of Traffic to Port of Colombo, University of Moratuwa, 2005.
![Page 111: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/111.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-27
It was found that 95% of the freight vehicles that have one of the trip ends in the port
have their other trip end within the Western Province. Of this, around 40% of the trips
are within the Colombo Municipal Council area. Furthermore, only around 40% of the
trip ends are outside Colombo District.
Table 7-17: Vehicle Entries per gate and vehicle movement rate at Port of Colombo
Gate Bicycle Motor - Cycle3- WheelerLight vehiclesBus Tractor Lorry smallLorry LargeTankers ContainersMain Gate 2,291 19,274 5,796 227,381 1,348 539 5,863 6,807 135 -De Seram 9,585 106,099 4,012 184,337 42,574 9,808 80,243 190,132 95,846 169,180Port Access 12,270 155,145 6,271 170,141 10,361 1,091 14,451 102,248 15,269 602,856JCT 57,562 163,149 21,945 183,716 689 - 19,877 12,409 230 -LB Gate 9,805 53,703 2,263 34,545 - - 26,097 21,572 2,866 -Export Gate 43,233 532,149 23,901 372,574 8,084 1,054 15,465 56,238 1,054 -
Vehicles /yr 134,746 1,029,520 64,188 1,172,693 63,056 12,492 161,997 389,405 115,400 772,035
Freight/yr
Bulk Goods MT/Year (moved by road) 2,000,000TEUs/YR 690,000
Vehicles per 1000MT 28.1 67.6Container Moves/TEU 1.12
5759300
34.9 39.5
This information is useful in determining the possible travel patterns that could be
expected once the Port of Hambantota is operational. Accordingly, it is reasonable to
estimate that 40% of the trips will leave the project impact area after having travelled
within the project area, while 60% of movements will travel wholly within the project area.
This can be considered as a very conservative estimate, made assuming that the railway
will be a competitive mode of transport between Colombo and Hambantota for both
goods and passenger transport. As shown in Table 6-18, there will be an estimated
33,206 daily vehicle movements within the Hambantota project area by the year 2032
due to the activity of the port. A vehicle-wise breakdown of this is also shown in Table 6-
18, which indicates that 7,994 would be container trucks while 4,041 would be tanker
movements within the project area.
Of this 40% or 13,282 vehicles would be leaving the project area mostly through the
ESH, A2 and A18 roads, which would be new or generated traffic.
![Page 112: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/112.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-28
Table 7-18: Estimation of Vehicle Movements from Port of Hambantota (2010-2040)
Estimated Traffic at Port of Hambantota2013 2020 2030 2032 2040
Dry and Break Bulk cargo (000 million) 2,745 8,889 13,405 13,815 15,456Vehicle Handling m(units 000) 110 213 224 220 203Liquid Bulk (Tonnes 000) - 4,090 8,340 8,626 9,770Containers (TEUs 000) - - 6,426 9,115 19,872Total 2,745 10,730 36,202 44,711 78,746
vehicles per2 & 3 Wheeler Vehicles 34.9 1000 MT 95,921 374,930 1,265,049 1,562,376 2,751,685Light 4 wheel vehicles 39.5 1000 MT 108,378 423,623 1,429,343 1,765,285 3,109,052Medium Trucks 28.1 1000 MT 77,211 301,798 1,018,295 1,257,627 2,214,955Large Trucks 67.6 1000 MT 185,598 725,456 2,447,757 3,023,059 5,324,266Tankers 72.2 1000 MT 89,148 348,458 1,175,731 1,452,066 2,557,405Container Trucks 1.1 per TEU - - 2,156,999 3,059,676 6,670,385
Total Vehs/Year 556,257 2,174,266 9,493,175 12,120,090 22,627,748
per day within HAD 365 days/yr 1,524 5,957 26,009 33,206 61,994
Leaving HAD 0.4 of total 610 2,383 10,403 13,282 24,798
Estimated Port Related Traffic in Hambantota Development Area Road Network
2 & 3 wheelers 263 1,027 3,466 4,348 7,539Light 4 wheel vehicles 297 1,161 3,916 4,912 8,518Medium Trucks 212 827 2,790 3,500 6,068Large Trucks 508 1,988 6,706 8,412 14,587Tankers 244 955 3,221 4,041 7,007Container Trucks - - 5,910 7,994 18,275
Total Vehs/Year 1,524 5,957 26,009 33,206 61,994
Vehicle Composition of above
2 & 3 wheelers 17 17 13 13 12Light 4 wheel vehicles 19 19 15 15 14Medium Trucks 14 14 11 11 10Large Trucks 33 33 26 25 24Tankers 16 16 12 12 11Container Trucks - - 23 24 29
Total Vehs/Year 100 100 100 100 100
7.7 Network Performance
A summary of the outputs as affecting the entire national road network as well as the
Hambantota road network as shown in Table 7-19.
![Page 113: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/113.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-29
Table 7-19: Network Statistics from TransPlan output
2012 2022 2032 2,012 2022 2032 2,012 2022 2032
Base Scenario
Link Flow 79,334 119,196 166,200 34,129,157 51,829,536 73,352,710 34,049,824 51,710,340 73,186,510
Speed 42.80 42.08 41.17 24.90 22.03 19.27 24.83 21.97 19.21
Veh Kms 429,031 644,312 897,442 72,400,839 109,453,703 153,288,227 71,971,808 108,809,391 152,390,785
Veh Hrs 10,024 15,312 21,797 2,908,156 4,967,735 7,953,602 2,898,131 4,952,422 7,931,805
Development Scenario - - -
Link Flow 269,285 515,213 789,160 34,471,424 52,581,896 74,541,892 34,202,139 52,066,683 73,752,733
Speed 70.08 69.09 67.91 25.86 22.98 20.20 25.58 22.65 19.87
Veh Kms 1,297,330 2,456,005 3,735,009 74,278,051 113,601,166 159,830,193 72,980,721 111,145,162 156,095,184
Veh Hrs 18,512 35,548 54,999 2,871,849 4,943,057 7,910,769 2,853,337 4,907,509 7,855,770
- - -
Hypothetical Scenario 1 - - -
Link Flow 108,358 192,689 285,456 34,314,291 52,269,450 74,055,122 34,205,934 52,076,761 73,769,666
Speed 42.28 40.63 38.59 24.86 21.94 19.13 24.78 21.85 19.04
Veh Kms 557,388 979,492 1,441,996 73,562,174 112,204,403 157,673,203 73,004,786 111,224,911 156,231,208
Veh Hrs 13,182 24,106 37,370 2,959,233 5,113,529 8,243,744 2,946,050 5,089,423 8,206,374
- - -
Hypothetical Scenario 2 - - -
Link Flow 191,633 303,329 482,549 34,310,664 54,525,230 87,048,341 34,119,031 54,221,901 86,565,792
Speed 70.36 69.88 69.06 25.89 22.72 19.05 25.67 22.52 18.87
Veh Kms 967,681 1,541,377 2,466,750 73,404,727 116,648,050 186,379,664 72,437,046 115,106,672 183,912,914
Veh Hrs 13,754 22,056 35,719 2,835,378 5,133,596 9,783,005 2,821,624 5,111,540 9,747,286
HDP Network SL Network SL Network w/ o HAD Network
![Page 114: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/114.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-30
7.8 Analysis of Scenarios
The four scenarios that have been examined above can be used to determine the effect
of the proposed Hambantota road network on the local traffic conditions as well as traffic
on the national road network as a whole.
The four scenarios identified as Base Case (B); Development Case (D), Hypothetical
Case I (H1) and Hypothetical Case II (H2) have been used to determine the following
conditions as shown in Table 6-20.
Base Case Condition (B): The Table 6-20 gives the performance of the road
network under the Base Case in terms of vehicle kms, vehicle hrs and average
network speed. Development Impact (D-B): The net impact of traffic due to the
development and the road network by deducting the traffic levels under the
Development Scenario from the Base Case Scenario.
Loss without Hambantota Road Network (D-H1): The loss from total development
impact estimated above as D-B, if the road network was not in place.
Impact Due only to Roads (H2-B): This would estimate the benefits that would
arise if only the road network was in place without the socioeconomic
development or the traffic that such development would generate. This would
provide a more accurate estimate of diverted traffic and a worst case scenario of
not having generated traffic.
![Page 115: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/115.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-31
Table 7-20: Analysis of Estimation Scenarios
2012 2022 2032 2,012 2022 2032 2,012 2022 2032
Base Case B 429,031 644,312 897,442 72,400,839 109,453,703 153,288,227 71,971,808 108,809,391 152,390,785
Development Impact D-B 868,299 1,811,692 2,837,567 1,877,212 4,147,463 6,541,966 1,008,913 2,335,770 3,704,399
Loss W/O HDP Roads D-H1 739,942 1,476,513 2,293,013 715,877 1,396,763 2,156,989 (24,066) (79,750) (136,024)
Impact only due to Roads H2-B 538,650 897,065 1,569,308 1,003,888 7,194,346 33,091,437 465,238 6,297,281 31,522,129
2012 2022 2032 2,012 2022 2032 2,012 2022 2032
Base Case B 10,024 15,312 21,797 2,908,156 4,967,735 7,953,602 7,953,603 7,953,604 7,953,605
Development Impact D-B 8,487 20,236 33,202 (36,307) (24,677) (42,833) (44,794) (44,913) (76,034)
Loss W/O HDP Roads D-H1 5,329 11,442 17,628 (87,384) (170,472) (332,975) (92,713) (181,914) (350,604)
Impact only due to Roads H2-B 3,730 6,744 13,922 (72,778) 165,861 1,829,404 (76,507) 159,117 1,815,482
2012 2022 2032 2,012 2022 2032 2,012 2022 2032Base Case B 42.80 42.08 41.17 24.90 22.03 19.27 24.83 21.97 19.21
Development Impact D-B 27.28 27.01 26.74 0.97 0.95 0.93 0.74 0.68 0.66
Loss W/O HDP Roads D-H1 27.80 28.46 29.32 1.01 1.04 1.08 0.80 0.79 0.83
Impact only due to Roads H2-B 27.56 27.81 27.89 0.99 0.69 (0.22) 0.84 0.55 (0.34)
HDP Network SL Network w/o HAD NetworkSpeed (Km/hr)
Vehicle Hours
Vehicle Kms
HDP Network SL Network SL Network w/o HAD Network
SL Network
HDP Network SL Network SL Network w/o HAD Network
7.8.1 Total Development Benefits
By computing the difference in performance between the Base Case and the
Development Case, the following observations can be made:
1. There is an increase in vehicle km on the Hambantota Development Project
(HDP) network of between 202 to 316 percent when compared to estimates
made for Base Case. This impact of the HDP development on Sri Lanka’s overall
national road network will be in the range of 3 to 4 percent with the SL network
outside the HDP area being impacted by around 1 to 2 percent. In other words it
means that the envisaged development will add between 1 to 2 percent increases
in traffic across the entire national road network over the design period of the
project.
2. In terms of average speeds, there is an increase in speeds in the HDP network
by around 26 to 27 km per hour, whereas in the rest of the national network this
increase has been between 0.6 to 0.7 kms per hour.
3. Since increase in speeds due to a new or rehabilitated network has led to an
increase in vehicle hours of between 85 to 152 percent for the HDP roads, the
![Page 116: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/116.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-32
impact for the entire SL network has been between 0 and 1 percent. These are
less than the rates of increase observed for vehicle km.
7.8.2 Generation Benefits Due to Road Network
By computing the difference between the Development Scenario and Hypothetical
Scenario 1, we estimate the loss of benefits that would accrue if the socioeconomic
development was in place, but the proposed HDP road network was not in place. This
could be assumed as the total benefits due to traffic that would be ‘lost’ due to the
absence of the road network. This is therefore the generated traffic due entirely to the
road being available. In this case, the following observations can be made:
1. There is between 81 to 85 percent loss in vehicle-km generated for the full
development scenario. This means that 81 to 85 percent of the generated
vehicle km would not take place unless the road network was there to make it
happen. When taking the entire SL road network as a whole, the loss would be
between 33 to 38 percent of the full development benefit. For the network
outside the HDP there is an increase in vehicle km possibly because without the
HDP roads in place, other parts of the network would be used in serving the
needs of the HDP development.
2. The average network speed for the HDP network falls by 1 to 3 km/ hr below the
Base Case levels under this scenario.
3. This is also confirmed further by the reduction of vehicle hours saved by the HDP
road network falling by between 53 to 63 percent of the vehicle hrs when
compared to the full development scenario. In the case of the SL network, the
vehicle hrs increase steeply signifying that there is a high impact on the rest of
the network illustrated by average speeds falling by about 0.8 km/ hr below the
Base Case.
7.8.3 Diverted Traffic
The diverted traffic can be estimated after examining how much increase in traffic will
occur when the HDP road network is added without any corresponding socioeconomic
development. The following observations can be made:
1. The generated traffic in the HDP network due to the development will range
between 126 to 175 percent of the Base Case.
![Page 117: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/117.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-33
2. The travel time increase in the HDP network will range from 37 to 64 percent with
speeds increasing marginally, while on the rest of the network, there will initially
be a 1 percent reduction but that which will eventually increase to 23 percent
when average speeds reduce by a further 0.2 km/ hr.
7.9 Traffic Levels
The following observations can be made regarding the traffic levels for the Development
Scenario (Table 7-13):
1. There would be only three links having a flow of more than 10,000 ADT in 2012.
These are the H001-020 and H002-030 links which are both near Siribopura
Junction and also A002-847 link which is near the Lewaya. By the year 2032,
these flows are expected to reach over 30,000 ADT.
2. By 2032, there would be 31 links (from a total of 67 links in the HDP road
network) that would have more than 10,000 ADT.
3. The maximum flow of 62,000 ADT can be expected by year 2032 on the link
A002-847 which is a short link of 380 m length in the town area.
The traffic levels on each link for the years 2012, 2022 and 2032 are given in Appendix
4. It can be seen that even by 2032 several of the roads will have traffic levels less than
10,000 ADT. Around 10% of the network length only will have ADT over 20,000.
7.10 Level of Service
The level of service of the HDP network for the different years is illustrated in Table 7-21
and in Figure 7-2. It can be seen that in 2012, around 43 of the 67 links experience a
LOS A which indicates under utilization even under Stage I road construction, while in
2032 only 13 links have LOS A. On the other hand 17 of the links will have LOS D or
LOS E conditions indicating capacity constraints. These are also shown in Appendix 5.
![Page 118: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/118.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-34
Table 7-21: LOS for Links in HDP network (Development Scenario – 2032)
Road No. Link NoLength
(km)
Width
(m)
Development Scenario
2012 2022 2032
H001 H001-010 3.11 16.00 A A B
H001 H001-020 3.14 16.00 C D E
H002 H002-010 0.59 39.00 A A B
H002 H002-020 3.55 39.00 A B C
H002 H002-030 1.40 39.00 B C D
H002 H002-040 7.97 39.00 A B C
H002 H002-050 B C D
H002 H002-060 A B C
H002 H002-070 A B C
H003 H003-010 A B C
H003 H003-020 B C D
H003 H003-030 B C D
H003 H003-040 A A A
H004 H004-010 B D E
H004 H004-020 B D E
H004 H004-030 B D E
H005 B427-010 4.92 5.90 A A B
H005 B427-020 15.58 4.86 A A B
H005 B427-025 7.00 5.97 A B B
H005 B427-030 7.51 5.97 A B B
H006 H006-010 A B C
H007 H007-010 A A A
H007 H007-020 A A B
H007 H007-030 A A B
H007 H007-040 A A A
H007 H007-050 A A A
H008 H008-010 A B C
H008 H008-020 B D E
H009 H009-010 A B B
H010 B549-010 5.61 5.34 B C D
H010 B549-015 0.51 5.34 B C D
H010 B549-020 8.19 5.34 A A A
H010 B549-025 2.52 5.34 A A B
H011 H011-010 A A A
H012 H012-010 A B C
H012 H012-020 A B C
H013 A002-830 0.76 7.00 A A B
H013 A002-840 1.77 7.00 A B B
H013 A002-845 2.11 7.00 A A A
H013 A002-847 0.38 7.00 E E E
H013 A002-850 6.07 7.00 C D E
H013 A002-860 7.51 7.00 C D E
H013 A002-870 4.92 7.00 A A B
H013 A002-880 7.43 7.00 A B B
![Page 119: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/119.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
7-35
Road No. Link NoLength
(km)
Width
(m)
Development Scenario
2012 2022 2032
H013 A002-890 3.79 7.00 C D E
H013 A002-895 9.28 7.00 A B B
H014 B251-010 3.59 6.00 A A A
H015 B563-010 8.44 6.00 A A B
H015 B563-020 3.60 6.00 A A B
H016 B562-010 3.82 6.28 A A A
H016 B562-015 4.84 6.28 A A B
H016 B562-020 10.86 6.28 A A B
H016 B562-025 3.81 6.28 A B C
H018 H018-010 A A A
H018 H018-020 A A A
H018 H018-030 A A A
H019 H019-010 B C D
H020 H020-010 C D E
H021 B548-010 5.48 4.99 B C D
H021 B548-020 10.67 4.99 C D E
H022 B567-010 10.84 2.84 A A A
H022 B567-015 12.77 2.84 A A A
H023 H023-010 A A A
H024 H024-010 B C D
H026 H026-010 A B C
H027 H027-010 A A A
![Page 120: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/120.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-1
CHAPTER 8 PUBLIC & NON-MOTORISED
TRANSPORT
8.1 Introduction
As a part of this feasibility study, the Public Transport Network identification has been
carried out by the study team to investigate the potential links and nodes to connect
people and their interactions between activity zones in the project impact area as
identified in Chapter 3. In order to consider the contribution of the regional development
within the on-going national road network development and to ensure the overall
transport efficiency, it is obvious to accommodate different modes of transport, especially
public transport with priority measures, Non-Motorised Transport (NMT) in city areas as
well as rail connectivity to the major transport generators.
This investigation identifies the requirements for public transport, Non-Motorised modes
of transport and transfer terminals, whiles it focuses mainly on the followings:
Provision of a viable public transport (Transit) corridor
o Bus based transits
Ordinary buses
Superior Public Transports (BRT or LRT)
o Rail Based Transits (MRT)
o Domestic air travel
o Ferry Services
Maximum use of Non-Motorised transport
o Pedestrian and cycle access
Multimodal transfer terminals
World examples depict the fact that Public Transport has long had a role in improving
mobility of people and supporting urban and regional development. The current
developments taking place in Hambantota create high projections of population growth
and extended people movements in future. Such increasing roadway needs among
![Page 121: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/121.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-2
people increase their transport cost and make them think more about mobility
alternatives.
Developing country’s investment affordability, affordability of citizens to increase their
alternative mode choice and success story of public transport sustainability from other
cities would open up the option of accommodating Public Transport and NMT as mobility
alternative for RNHDP.
8.2 Field Observation
The study team of the University of Moratuwa has physically observed the impact area of
this study during their visits. The study team was able to observe the development
patterns and to establish a preliminary transit and NMT network along with transfer
terminals basically incorporating the development plans that have been considered over
the RDA proposals subsequent to the consultation of stakeholder agencies during the
second field visit.
The growing population of the region will consume more and more land over time and
the landscape within the development area will undergo a rapid transformation. The land
use pattern of the area is explained in the Table 3-3. It is found that 58 % of the land is
scrub and vacant whilst 24% of the land is covered by forest and sanctuaries. Though
the land space limitation appeared to be less at these base years, sooner it will be a key
issue with all the aforementioned developments geared to its ultimate operation.
In general, any growth plans, if implemented, will result in an increase in urbanised area.
While this phenomenon may not be different for this region, the observations made in
this area have brought the issue to the forefront of public awareness. During the process
of urbanisation, the disappearance of the rural land could be prevented by adopting
development standards intended to preserve rural character by requiring large lots and
low densities. However, the result will be a uniform blanket of suburban development,
rather than the preservation of genuine open space with historic, aesthetic and
environmental value.
Such low-density, dispersed development creates greater driving distances between the
places that people live, work, and shop. Additionally, as development will be spurred
further and further from core centre, commuters will spend more and more time in their
vehicles. Better road network decrease the time and cost of transportation within and
![Page 122: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/122.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-3
between developments areas, help families relocate from housing near their workplaces
to housing in the suburbs (job decentralisation followed), allow easy travel between
residential, commercial and industrial areas despite the considerable distances that often
separated them.
Based on few bad world examples like motorised oriented development in USA, a
proposal to make change to the pattern of development is appreciated by the study team
and, therefore, this study has identified that it is necessary to develop a transit network
plan and give provision of a viable public transport corridors and maximise the usage of
pedestrian and cycle access. A concept of livable city backed by a Transit Oriented
Development (TOD) is recommended.
8.3 Livable Compact City for Hambantota
Livability is defined as ‘quality of life’ as experienced by the residents within a city or
region and the quality of life is via better public transport provision and ‘walkable’ city
concept. This study has observed various residential and mix (residential plus other)
land-use, as shown in Figure 5-1 (Study Area with zoning of UDA) where few zones
have high potential to have a high population density in the future based on its spatial
location as well as induced land use demand will be created by the proposed public
transport network.
8.4 Population and Transit Demand
The major activity centres within the study area are observed concentrating in a triangle
made with three zones namely (1) Hambantota, (2) Mattala and (3) Meegahajandura.
The Hambantota zone consists of the Harbour Development, Administrative complex, etc
while the Mattala zone consists of the second international airport while the
Meegahajandura zone consists of the Cricket Stadium, Safari Park, etc. These three
identified zones are interconnected by two major transit routes (Route 1 and Route 2 as
shown below in Figure 8-2) formed in a “Y” shape.
Population estimates for Hambantota Development Area is given in Table 7-6 and the
information is reproduced below in Table 8-1 by considering the effective proportion of
trip interaction expected from estimated population by zones via major routes (interaction
![Page 123: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/123.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-4
insides the triangle). The Table 8-1 depicts the estimated population for base year 2012
and target year 2032, and the effective proportion of trip interaction among zones.
According to the observations made by the study team, the overall total population will
be 658,552 in year 2032 nearly double (97% increment) that of 2012.
The Table 8-1 is also estimates a Zonal Population (represents the effective population
that makes their trip between and within the three zones) and public transport demand
under the following assumptions:
a) Population generating trips within the triangle is varied (varied contributions are given
in the Table 8-1),
b) actual trip makers are only 50% of the effective population, and
c) modal share for public transport is 25%.
Table 8-1: Projected Population and Predicted Transit Demand
Zo
ne
AreasContribution
(%)2012* 2032*
Zonal
Population
Demand
for PT/day
1 Hambantota 100% 72,932 143,985 143,985 18,000
2Lunugamvehera 100% 29,451 52,076
66,665 8,333Tissamaharama 10% 8.446 14,589
3Meegahajandura 20% 11,519 31,761
47,338 5,917Ambalantota 10% 8,324 15,577
Total Effective Population 130,672 257,988
Percentile growth in population from baseyear
97%
8.5 Public Transport
The Public Transport Network development consists of four modes of transport. The first
is bus based public transport represented by ordinary buses, buses with priority
(Superior Public Transport) like Bus Rapid Transit (BRT) and Light Rail Transit (LRT) on
shared right of way. The second is rail based transit modes such as Mass Rapid Transit
(MRT). The other two modes would be domestic air services and ferry services.
![Page 124: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/124.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-5
8.5.1 Railway
Since SLR is planning for an extension to the existing coast line to Beliatta and thereafter
to Kataragama as a single track, the effect of this on the Hambantota Development Area
too should be considered. With single track operations, the modal split would be similar
to that of Galle-Colombo and Matara-Colombo. However, the expressway might be
cutting the travel time and costs down by nearly one half. As such, the proposed
contribution from railway would be moderate unless it is modernised to compete with the
expressways. However, if current operating practices were to continue it would not be
very much significant.
8.5.2 Domestic Air Travel
The other option available is the domestic air travel. However, the share of the domestic
air travel is not expected to be significant since the difference in overall travel time will be
only marginal when considering the access times to airports at Ratmalana or
Katunayake as well as to Mattala, that would be an hour or more and thus the total travel
time advantage would be just around 30 minutes or so. Therefore only a very small
percentage can be expected to opt for air travel in a scenario where the expressway is
also available.
8.5.3 Ferry Service
Ferry service is another option available and best suited for cruising and supporting the
leisure industry and tourist industry. As a general transit service it is not yet found to be
a formal mode of transport and it is not considered for this study. However, in the case
of goods transport, the railway and ferries can play a critical role.
8.5.4 Bus based public transport
The study has identified the bus based public transport as the system that carries the
major passenger demand associated with the region. It has been discussed in detail in
the rest of this chapter.
8.6 Public Transport Network
In order to accommodate the estimated public transport demand, as shown in Table 8-1,
and to eliminate any future deficiency in the system capacity, it is essential to eliminate
![Page 125: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/125.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-6
any imbalance in supply between motorised mobility and other more sustainable
mobility alternatives.
This study assesses the future needs and characteristics of the region, as discussed in
the above chapters, and identifies the areas where transit service appears to be feasible.
The following mobility alternatives as tabulated in Table 8-2 have been identified. There
are two different road networks, under public transport, identified for modes of BUS and
NMT, as depicted on a map given in Appendix-6. There are two major public transport
corridors (Route 1 and Route 2 as shown below in Figure 8-2) proposed and marked on
the map.
Table 8-2: Mobility Alternatives for Motorisation
System Network Distance/ (km)
Superior Public Transport (SPT) Priority bus ways/ BRT/LRT 37.5
Ordinary Buses (PT) Feeder bus/Loop bus 290.3
Non-Motorised Transport (NMT) Cycling/Walking 79.9
According to the urban development plan, as shown in Figure 5-2, and the total road
networks proposed herein this study, as shown in Appendix 2, the following routes are
identified as potential lines of passenger movements using those two different road
networks identified for PT and NMT in Table 8-2. The identified routes are shown in
Appendix-6 and the details are given in Table 8-3 which also shows the route numbers,
route name, and type.
Table 8-3 : Public and Non-Motorised Transport Routes
No. Route Route Name Alternatives *
1 HR02 Hambantota–Gonnoruwa–Megahajandura Road SPT / NMT
2 HR12 New Airport Access Road SPT
3 HR01 Outer Circular Highway NMT
4 HR07 Hambantota Bypass Road NMT
5 HR16 Sooriyawewa – Mirijjawila Road NMT
6 HR13 CGHW Road (from Hambantota to Weerawila) NMT
7 HR18 Arabokka- Siyabalagaswewa- Gonnoruwa Road NMT
8 HR25 Internal Road Grid in the City Area NMT
* Superior Public Transport (SPT), Non-Motorised transport (NMT)
8.6.1 Passenger Demand
As identified earlier, this study estimates its demand and necessary transit service
frequency based on the three zones, as mentioned in Table 8-1; (1) Hambantota, (2)
![Page 126: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/126.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-7
Mattala, and (3) Meegahajandura. As an approximation, the study has estimated the
transit passenger O-D demand (Origin and Destination demand: transit users interaction)
between zones by considering average demand generation and depicted in Table 8-4.
Table 8-4 : Transit User Origin and Destination (O-D) Estimation per day
O-DDestination
1 2 3
Origin 1 8,999 13,166 11,958
2 4,167 7,125
3 2,959
8.6.2 Transit Headway
Since the two major corridors connecting those three zones ((1) Hambantota, (2)
Weerawila and (3) Meegahajandura) is expected to operate under SPT (Superior Public
Transport) system, it is assumed to use high capacity buses like articulated buses and
assumed the comfortable carrying capacity of transit unit is 100 pax. Based on the
assumptions the transit headway averaged over day of operation is calculated and
tabulated in Table 8-5.
Table 8-5 : Transit Headway
Headway/(min)Destination
1 2 3
Origin 1 5 4 4
2 12 7
3 16
In this chapter, Superior Public Transport is exclusively identified for the two routes (1
and 2) that have a separate treatment under public transport provision. It is important to
note that there are other mixed-use (transit operations taking place along with all other
general vehicle) ordinary bus services in addition to the routes what is described in this
section. Therefore, the frequency especially from intra-zones will be served by mix-use
transit service as a feeder running along other routes.
8.6.3 Transit Modes
Bus Rapid Transit
One of the affordable and ideal alternative transit system best suiting for developing
countries transit is Bus Rapid Transit (BRT). BRT is a bus based rapid transit system
running on a separated bus lanes, possibly along the central median, enjoying its route
![Page 127: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/127.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-8
flexibility, and enhanced speed using lane separation and priority treatments. Figure 8-1
depicts a sample image from Crutiba – a World popular median bus lane BRT model.
BRT can operate in many different ways, from enhanced limited stop bus service or
express service to a service resembling LRT with an exclusive guide way and rail-type
stations. BRT is typically operated with buses that resemble light-rail vehicles that may
operate, at least partially, in their own right-of-way. BRT generally includes advanced
technologies that can improve the travel experience for riders, traffic signal priority,
station area amenities and real-time travel information. Well developed transit corridor
with high transit patronage can easily then converted to Light Rail Transit (LRT) which
can have comparably higher carrying capacity.
Figure 8-1: Crutiba – A World Popular Median Bus Lane BRT Model
Feeder Bus Service
Line-haul transits services like BRT operating along a separated bus lane would be
successful only if the system is fully integrated with efficient feeder systems. Feeder
systems can be provided typically by using existing bus services running along various
routes on mixed-use and feeding the passengers at BRT line by touching the line at
stations. Generally, the feeder system is not allowed to enter the line-haul bus lane.
The feeder service could be integrated in terms of its access also with NMT. Therefore,
the feeder system demands for easy and convenient transfer stations with aesthetic
design and user information.
![Page 128: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/128.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-9
8.6.4 Transit Routes
Two routes identified as Route 1 and Route 2 are the major transit corridors marked on
the map in Appendix 6. The details of each of these routes are described in the following
sections. The common portion of these two routes which is from Siribopura-Gonnoruwa
is the major development axis the functions of which are:
Service to provide access to administrative and commercial buildings
Promote high density residential and employment centres
Propose a superior public transport (SPT) corridor that later convertible to
BRT or LRT.
Route 1: Hambantota–Gonnoruwa–Meegahajandura Road (HR02)
Route 1 refers the line along road HR02 of Appendix 6 from junctions HX01 via HX02,
HX11 to Gonnoruwa where provision is given for expansion up to Meegahajandura
(HX22) via junctions HX07, HX03, and HX12. The detail information on its links and
nodes is given in Figure 8-2 below.
This route is one of the major accesses that would connect the regional administrative
centre to the rest of the region. It connects the heart of Hambantota with various other
activity centres, more specifically the Mattala International Airport, Sooriyawewa FTZ,
Cricket Stadium, etc. HR02 has been proposed as an urban development axis from
Siribopura to Gonnoruwa and a service road is provided to access the administrative and
commercial buildings. This corridor is intended to promote high density residential and
employment centres along it. The design provision is given to have a centre median
superior public transit corridor plus the service roads with NMT facilities. NMT facility
should be provided up to Gonnoruwa.
Route 2: New Airport Access Road (HR12)
Route 2 refers the line along road HR12 of the Hambantota Road Network as shown in
Appendix 6 which deviates from Route1 at Junction HX03 and is traced towards the
Mattala International Airport. As a new trace to provide access to the airport, it ends at
Lunugamwehera (HX13) via HX04. This corridor is also intended to promote high class
public transport corridor with centre median transit way.
Two high class line-haul public transport services could be operated along the major axis
HR02 up to Gonnoruwa (HX03) and then to split towards Meegahajandura and Mattala
![Page 129: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/129.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-10
International Airport. The Figure 8-2 depicts a sample route of operation that could be
offered with these two routes 1 & routes 2.
Figure 8-2: Sample operation routes for PT along Routes 1 and 2
8.7 Non-Motorised Transport
Hambantota region is historically identified as an area for tourist attraction due to its wild
life sanctuaries, beaches, etc. Along with the RNHDP development, the study team
intends to build on this tradition and to protect the regions’ identity by ensuring tourist
movements can be safely and effectively be accommodated within the road network.
Slow moving and environmental friendly modes of transport are required in and around
the areas which attracts tourists. Non-Motorised Transport (NMT) is recommended and
bicycling and walking are identified as the most demanding alternatives especially for
tourists. The NMT network is carefully developed by connecting land-use such as hotel
areas with the potential tourist attractions.
Cycling - The Hambantota development is taking place in a way that many activities are
concentrated around the new urban area so that it has the potential to become a
compact city with mix-land use. The team has identified this characteristic and proposes
a cycle path network to accommodate such short distance one or more cycle rental
service offered for the later group while the former one may use their own. Another
concern of cycling is the need to provide cycle lanes and locking systems to motivate
‘cycle-and-ride’ (park their cycle and ride on PT). A safe circulation path for cycling has
been developed and incorporated in the geometric designs of some selected routes.
Roads having cycle paths are shown in Appendix 6.
Walk way - Every transit rider is a pedestrian at some point during their travel
experience, whether it is walking to a bus stop, parking a bike near a transit station, or
walking from the bus/train to their final destination. If the pedestrian environment is
01 02 11 07 03
12 22
04 14
![Page 130: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/130.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-11
ignored, an area is not likely to see the development of a successful transit system.
While the study focused on ensuring a walk-able city, it is also focused on the potential
to increase the concentration of population and employment around the region as a
strategy to improve the region’s pedestrian activity. The study assumes that making the
region more pedestrian-oriented will be a key in developing a successful public transport
network in Hambantota region and thereby making it transport friendly and cost efficient.
8.7.1 Routes for Non-Motorised transport
As mentioned in the Table 8-3, there are six routes proposed for NMT, numbered as 3 to
8 excluding route 1 that has been designed for both SPT and NMT. They have been
identified based on their land use and the development plan. The NMT network is
recommended by the study team after taking in to account the following:
a) Provision of proper pedestrian and cycle accesses for those who reside in close
proximity to work such as between administrative centre and residential areas;
b) Concentration of residential development in tsunami housing areas to allow high
income people to reside close to work areas, so that traffic congestion can be
minimized;
c) Provision for short distance travel access between work and residences for those
who would otherwise use cars for travel to work;
d) Provision of a set of travel paths as bicycles and walkways for tourism; Tourism
related developments would include cycle tracks within the town area and
extending along Lewaya Road as well as to Walawe Left Bank Project areas to
promote eco-tourism.
Route 3: Outer Circular Highway (HR01)
Route 3 refers to the Ring Road HR01 shown in Appendix 6 from HX20 and including
junctions HX02 to HX09. It traces around the major activity centres and functions as a
ring road to bypass traffic from/to the following major connecting roads; CGHW Road,
Hambantota Bypass Road and Hambantota-Meegahajandura-Gonnoruwa Road. It also
acts as a collector for movements on the HR26 via residential and commercial zones
within the ring.
Public transport operates in mix-use manner along this route along with NMT facility.
![Page 131: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/131.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-12
Route 4: Hambantota Bypass Road (HR07)
Route 4 refers to the line along HR07 as shown in Appendix 6 (Proposed Roads Network
for Hambantota Development Plan) from junctions HX18 via HX05, HX08, HX09, and
HX01 to HX17. This route is the bypass road which earlier carried traffic on the A2
Road. This route connects the old A2 and the Hambantota city while providing access to
a rail-road inter-modal passenger transfer location at HX05.
The Extension of the Coastal Railway Line will provide for the large scale pilgrimage
traffic to Tissamaharama and Kataragama. The transport of freight from the seaport of
Hambantota to Galle, Colombo and the hinterland will be facilitated.
The major terminal at HX05 will act as major transfer for goods and people. The route
also pipes the traffic from A2 to airport via junction HX08. Along this route again at HX05
there is a botanical garden and a paddy field.
Route 5: Sooriyawewa – Mirijjawila Road (HR16)
Route 5 refers to the HR16 as shown in Appendix 6 (Proposed Road Network for
Hambantota Development Plan) starts from junctions HX05 and the above mentioned
transfer terminal. It will provide for farmers to access their paddy land as well as for eco-
tourists to tour around such areas using NMT facilities.
Route 6: CGHW Road (from Hambantota to Weerawila: HR13)
Route 6 refers to HR13 as shown in Appendix 6 (Public Transport & Non-Motorized
Transport Corridors) from Hambantota to Weligatta via junctions HX17, HX20 and HX36.
This route is established along historical locations and beside Hambantota old town and
beach. Therefore it has been proposed for development as a NMT facility corridor with a
mixed-use (transit operations taking place along with all other general vehicle; lanes are
shared by both buses and other vehicles) ordinary bus service (PT).
Route 7: Arabokka-Siyambalagaswewa-Gonnoruwa Road (HR18)
Route 7 refers to HR18 of the network given in Appendix 6 (Proposed Road Network for
Hambantota Development Plan) from junctions HX08 to HX07 via HX06 and HX21. This
route also traverses via paddy fields and touches the termination of the Southern
Highway. This route is also proposed to be facilitated with NMT. This route is proposed
as a part of a cycling loop composed of HR18, HR02, HR07, and/or HR26. This cycling
![Page 132: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/132.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-13
path is expected to attract tourists as it loops around different land use features including
areas where it may be possible to observe movements of wild elephants.
Route 8: Internal Road Grid in the City Area (HR25)
Route 8 refers to the road network formed within the high dense mix land use centre in a
grid form and it is referred to as HR25 in Appendix 6 (Proposed Roads Network for
Hambantota Development Plan). These routes functions as local access roads and
therefore are provided with NMT facilities to access the administrative centre, PT service
etc.
8.8 Public Transport Stations
The location of each of the potential transfer points along the total PT network has been
identified with respect to the following intersections; Bus - Bus and Rail - Bus. The study
has not considered the location of bus halts and confines itself to major transfer stations
and terminals.
8.8.1 Public Transport Terminals
The Figure 8-2 depicts the major two public transport corridors that have been identified
in which there are a few nodes. From Siribopura (HX01) to Gonnoruwa (HX03), the line
is a shared transit line. While Siribopura (HX01), Meegahajandura (HX22), and
Lunugamwehera (HX04) are terminals (end stations of SPT services), the junctions
HX11 and HX03 would become major transfer stations. Transfer stations could be one
or more of the following combination; Auto - PT (ordinary bus; Local or long-distance) -
SPT (superior buses; BRT) - Rail Service - Ports.
HX11 would function as a transfer terminal between private modes, SPT mode, and Rail
mode. HX03 would also function as a transfer station between Route 1 and Route 2
while HX04 would be considered as the access node to/from the airport. Table 8.6
summarises few identified stations (nodes) which serve for various purposes.
8.8.2 Cargo Terminals
There is another transfer station located at HX05 which connects the railway extension
with other activities like cargo movement from the sea port while HX04 serves as air
cargo terminal carrying out movement between Auto (Trucks) and Airlines.
![Page 133: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/133.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8-14
Table 8-6: Transit Stations
No Service Types Station Transit Node
Public Transport Terminals
1 SPT End Terminals HX01, HX22, HX04
2 SPT ~ SPT Transfer HX03
3Rail ~ SPT ~ Auto (Southern
expressway access)Park & Ride HX06
4 Rail ~ Auto ~ NMT Park & Ride HX05
5 NMT Bicycle hiring point HX17
Cargo Terminals
6 Rail ~ Auto Sea Cargo terminal HX05
7 Airways ~ Auto Air Cargo terminal HX04
As the proposed road development study does not require a detailed study of the public
transport services, the focus has been limited to identification of public transport
corridors and terminal locations along with non-Motorised transport provision.
![Page 134: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/134.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-1
CHAPTER 9 SOCIAL ANALYSIS
9.1 Background
As discussed previously, steps have already been taken to develop Hambantota District
with a variety of physical and related economic infrastructure facilities, especially within
the Greater Hambantota Area. A number of major economic infrastructure projects
including an International Airport at Mattala, a Commercial Harbour, an International
Convention Centre and an International Cricket Stadium as well as few peripheral
development activities have been initiated at the moment. The proposed road
infrastructure facilities to develop Hambantota as a hub would facilitate the economic
development endeavours in the district.
The social assessment has been focused on evaluating the most likely impacts of the
proposed road hub over the socio-economic environment in the local and regional
economies. The likelihood impacts of the road construction and the development of
housing and other built-up infrastructure have also been analysed.
Information gathering was through Grama Niladharies, Samurdhi Niyamakas, Agriculture
Extension Officers, Development Officers attached to the respective Divisional
Secretariats as well as through the Community Leaders. The assigned field team had
made observations by walkthrough surveys along the candidate roads and by informal
discussions with the community members residing in the immediate vicinity of the roads.
9.2 Methodology of the Assessment of Potential Impacts
Both positive and probable negative impacts identified under the social assessment have
been evaluated as per the following parameters.
(a) Geographical areas (local and regional) served and population to be served in
the road command areas
(b) Livelihood activities and land use of the road command areas
(c) Land values in the vicinity of the road
(d) Economic centres served by the roads
![Page 135: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/135.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-2
(e) Nature of built up area affected and the probable negative impacts on the
housing and other buildings
(f) The significant religious and other public places connected to the roads
(g) Connectivity impacts of the roads
9.3 Populations Served along the Road Commands
The proposed road network stretches over eleven (11) DS Divisions attached to
Hambantota, Monaragala and Ratnapura Districts. Numbers of people that can be
served along the above road commands based on each DS Divisions are shown in
Figure 9-1.
Figure 9-1 : Populations Served along the Roads in Each DS Division
![Page 136: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/136.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-3
9.4 Agricultural Land Use Pattern
A significant land use feature observed in the vicinity of most of the roads was scrub
jungles in government land. Despite of the scrub jungles there are small scale
agricultural activities adjacent to many roads under consideration as listed in Table 9-1.
Table 9-1 : Agricultural Land Use Pattern
Principle Land Use Pattern Related Road Commands
Chena cultivation
Hambantota-Gonnoruwa-Meegahajandura Road
Udamattala-Thanamalwila Road
Internal Road Grid in the City Area
Paddy under small tank + Chena
cultivation
Outer Circular Highway
Andarawewa-Udamattala-Padawkema Road
Galwewa-Moraketiya Road
Sooriyawewa- Meegahajandura-Kumaragama Road
Chena cultivation + SugarUdawalawa – Thanamalwila Road
Embilipitiya-Moraketiya-Keiriibanwewa-Udamadura Road
Chena, Paddy, Banana
Bo-pale Junction-Kiribbanwewa Road
Road connecting the Walawe Left Bank Road to
Hambantota-Gonnoruwa- Meegahajandura Road
Mixed crops + Chena and Paddy
Connection between A018 road and Sooriyawewa-
Mirrijjawela Road (100ft. road)
Ranna-Angunakolapelessa-Wetiya Road
Lunugamvehera-Weligatta Road
Paddy under major schemes
Sooriyawewa – Padalangala Road
Sooriyawewa-Mirrijjawela Road
Lunugamvehera to Kataragama Road
Weerawila-7th
Colony Road
Mainly non-agriculture & marginal
agriculture
Hambantota Bypass Road
CGHW Road (243-km – 260km)
Lewaya Road
Internal road grid in the city area
![Page 137: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/137.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-4
The information on approximate percentages of land in the road vicinity with scrub jungle
as observed are listed in Table 9-2.
Table 9-2: Percentages of Land in the Road Vicinity with Scrub Jungles
Related Roads Percentages of Area with Scrub Jungles
Galwewa- Moraketiya Road
Embilipitiya-Moraketiya-Weli Ara Road
Lewaya Road
Sooriyawewa-Padalangala Road
Southern Expressway extension
New road from Hambantota to Gonnoruwa
Ranna-Angunakolapelessa Road
less than 25 %
Hambantota–Gonnoruwa-Meegahajandura Road
Andarawewa ( A018 & Walawe Road) Junction
Bo-Pale junction -Kiribbanwewa Road
CGHW Road
Sooriyawewa- Mirrijjawela Road
Wetiya to 100 feet Road
Lunugamvehera-Weligatta Road
Weerawila-7th Colony Road
between 25 % to 50 %
Sooriyawewa- Meegahajandura-Kumaragama
Road
Andarawewa- Udamattala and Padawkema Road
Udawalawa-Thanamalwila Road
Lunugamvehera-Kataragama Road
between 51 % to 75 %
Outer Circular Road
Hambantota Bypass Road
Udamattala-Thanamalwila Road
Walawe New Road
More than 76%
9.5 Real Estates Market of the Road Vicinity
The current development programmes in Hambantota area have impacted much on the
real estate property market. The perceived property values have escalated by more
than 10 times in many areas within a period of 3 to 4 years in the Greater Hambantota
area while there is no significant change in areas covering Udawalawa–Thanamalwila
Road, Wetiya-Angunakolapelessa-Ranna Road, Lunugamvehera-Kataragama Road and
Embilipitiya–Samagipura Junction Road.
![Page 138: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/138.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-5
Some people have assigned superfluously perceived values to their land located in
places such as in the vicinity of the proposed Airport, cricket ground and commercial
port. There were groups of people who have expressed different views and argued that
the current boom in land prices might go in to burst during the post construction era of
the ongoing major development projects. The unit used to express the land value in the
past (about 4 – 5 years ago) was acres but there is a trend at present to express land
values based on perches.
Table 9-3: Perceived/ Current Market Values with Market Values of Land before 3
Years
Road
Previous Market
Value (3 years ago)
– SLR/ Hectare
Perceived Value/
Current Market
Value – SLR/ Hect.
Multiplier
Outer Circular Highway 40,000 240,000 6
Hambantota – Gonnoruwa –
Meegahajandura80,000 – 200,000 320,000 – 400,000 2 - 4
Sooriyawewa – Meegahajandura –
Kumaragama2,000 – 4,000 80,000 – 240,000 40 - 60
Andarawewa – Udamattala –
Padawkema80,000 – 120,000 400,000 – 600,000 5
Udawalawa – Thanamalwila 80,000 280,000 3.5
Galwewa -Moraketiya 140,000 – 160,000 240,000 – 280,000 1.75
Hambantota By Pass Road 40,000 – 80,000 480,000 6 - 12
Road connecting the Sooriyawewa-
Mirrijjawela Road and Hambantota-
Gonnoruwa-Meegahajandura Road
2,000 120,000 60
Bopale Junction - Kiribbanwewa 80,000 – 120,000 200,000 – 320,000 2.5 – 2.7
Embilipitiya – Moraketiya –
Kiribbanwewa - Udamadura2,000 480,000 180
Airport Access Road 40,000 480,000 12
Udamattala – Thanamalwila 160,000 – 200,000 320,000 – 480,000 2 – 2.2
CGHW Road (243-km – 260km) 40,000 – 80,000 400,000 – 480,000 6 – 10
Lewaya Road 80,000 520,000 6.5
Sooriyawewa – Padalangala 40,000 – 80,000 200,000 – 320,000 4 – 5
Sooriyawewa – Mirrijjawela 20,000- 40,000 160,000 – 320,000 8
Southern Expressway Extension 20,000 320,000 – 400,000 16 - 20
Road connecting the Walawe Left
Bank Road to Hambantota-
Gonnoruwa- Meegahajandura Road
120,000 – 160,000 200,000 – 240,000 1.5 – 1.6
Connection between A018 road and
Sooriyawewa- Mirrijjawela Road
(100ft. road)
40,000 – 80,000 120,000 – 160,000 2 – 3
![Page 139: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/139.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-6
Road
Previous Market
Value (3 years ago)
– SLR/ Hectare
Perceived Value/
Current Market
Value – SLR/ Hect.
Multiplier
Lunugamvehera to Kataragama 120,000 – 160,000 240,000 – 280,000 1.75 – 2
Ranna - Angunakolapelessa - Wetiya
Road80,000 – 120,000 200,000 – 600,000 2 – 2.5
Lunugamvehera -Weligatta 80,000 – 120,000 600,000 – 320,000 1.75 – 3
Weerawila-7th Colony 30,000 160,000 – 240,000 5.3 – 8
Internal Road Grid in The city Area 20,000 120,000 6
9.6 Local Economic Centres Served by the Roads
Except for new roads, all other roads are the existing roads with few established local
economic centres to support community with routine business activities. The most
benefited economic centre is the weekly fair (known as “Sathi Pola” in local language).
Some roads serve more than one weekly fairs as shown in Table 9-.4.
Table 9-4: List of Roads Serving Weekly Fairs
Road Weekly Fairs Served
Outer Circular Highway Hambantota
Hambantota-Gonnoruwa-Meegahajandura Hambantota + Sooriyawewa
Sooriyawewa-Meegahajandura-Kumaragama Sooriyawewa
Andarawewa-Udamattala-PadawkemaSooriyawewa + Lunugamvehera +
Pannegamuwe
Udawalawa-ThanamalwilaUdawalawa + Fair at Plot 141/2 +
Thanamalwila
Galwewa-Moraketiya Sooriyawewa
Hambantota By Pass road Hambantota
Road connecting the Sooriyawewa- Mirrijjawela Road
and Hambantota-Gonnoruwa-Meegahajandura RoadSooriyawewa
Bo-Pale Junction- Kiribbanwewa Kiribbanwewa
Embilipitiya – Moraketiya – Kiribbanwewa -
Udamadura
Embilipitiya + Daranduwe +
Kiriibbanwewa + Fair at Plot 11/4
Udamattala-Thanamalwila Thanamalwila
CGHW Road (243km-260km)Hambantota + Pannegamuwe +
Lunugamvehera
Lewaya Road Hambantota
Sooriyawewa-PadalangalaSooriyawewa + Padalangala + Alibata
Ara
Sooriyawewa-Mirrijjawela Sooriyawewa
Southern Expressway Extension Ambalantota + Hambantota
![Page 140: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/140.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-7
Road Weekly Fairs Served
Road connecting the Walawe Left Bank Road to
Hambantota-Gonnoruwa- Meegahajandura RoadHambantota + Sooriyawewa
Connection between A018 road and Sooriyawewa-
Mirrijjawela Road (100ft. road)Barwakumbuka + Sooriyawewa
Lunugamvehera to Kataragama Pannegamuwe + Kataragama
Ranna-Angunakolapelessa-Wetiya RoadBarawakumbuka + Angunokolapallssa
+ Ranna
Lunugamvehera-Weligatta Pannegamuwa
Weerawila-7th Colony Pannegamuwa
Internal Road Grid in the City Area Hambantota
9.7 Nature of Built Up Area Affected and the Likelihood
Negative Impacts on Houses, Shops and Public Buildings
It has been observed that most of the considered roads run through less populated and
lightly built up areas and therefore, likelihood of demolishing or evacuation of buildings
will be less significant. The observations of the social field survey team at the adjacent
environment of each road are summarised in Table 9-5.
Table 9-5: Number of Buildings Likely to be Affected
Related Roads
Number of
Buildings
Affected
Number of
Shops
Affected
Number of
Common
Buildings
Affected
Galwewa-Moraketiya < 10 < 10
Hambantota By Pass Road < 10 < 10
Bo-Pale Junction- Kiribbanwewa < 10 < 10
Udamattala - Thanamalwila < 10 < 10
Lunugamvehera to Kataragama < 10 < 10
Outer Circular Highway < 10 < 10 < 5
Weerawila-7th Colony < 10 < 10 < 5
Connection between A018 road and
Sooriyawewa- Mirrijjawela Road (100ft. road)< 10 < 5
Lunugamvehera-Waligatta < 10 < 5
Sooriyawewa-Padalangala < 10
Sooriyawewa-Mirrijjawela < 10
Sooriyawewa - Meegahajandura 11-25 < 10 < 5
Udawalawa-Thanamalwila 11-25 < 10
![Page 141: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/141.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-8
Related Roads
Number of
Buildings
Affected
Number of
Shops
Affected
Number of
Common
Buildings
Affected
Hambantota-Gonnoruwa-Meegahajandura 26-50 < 10
Andarawewa-Udamattala-Padawkema 26-50 < 10 < 5
Embilipitiya – Moraketiya – Kiribbanwewa -
Udamadura26-50 26 - 50 < 5
CGHW Road (243km-260km) 26-50 26 - 50 < 5
Ranna-Angunakolapelessa-Wetiya 26-50 < 10 < 5
Lewaya Road < 10
9.8 Public Places Served by Proposed Candidate Roads
All these roads are connected to various other public places where communities need to
visit. Some places get benefited from more than one road. Table 9-.6 includes number
of places and related candidate roads.
Table 9-6: Public Places Served by Proposed Candidate Roads
No. of Public Places Related Candidate Roads
Less than 5
Andarawewa-Udamattala-Padawkema
Connection between A018 road and Sooriyawewa- Mirrijjawela
Road (100ft. road)
Bo-Pale Junction- Kiribbanwewa
Udamattala - Thanamalwila
Lewaya Road
Sooriyawewa-Padalangala
Southern Expressway Extension
Road connecting the Walawe Left Bank Road to Hambantota-
Gonnoruwa- Meegahajandura Road
Lunugamvehera to Kataragama
Weerawila-7th Colony
Internal Road Grid in the City Area
6-10
Hambantota-Gonnoruwa-Meegahajandura
Sooriyawewa-Meegahajandura
Galwewa-Moraketiya
Embilipitiya-Moraketiya-Weliara
Sooriyawewa-Mirrijjawela
Connection between A018 road and Sooriyawewa- Mirrijjawela
Road (100ft. road)
![Page 142: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/142.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-9
No. of Public Places Related Candidate Roads
11-15Hambantota By Passs road
Ranna-Angunakolapelessa-Wetiya
15-20Udawalawa-Thanamalwila
CGHW Road (243km-260km)
9.9 The Significant Religious and Other Public Centres
Connected to Roads
Eleven (11) roads provide access to various religious places where local, regional,
sometimes national communities visit for religious activities. Some religious places have
access from several candidate roads in the proposed road list. Once these 11 roads
have been improved the religious places connecting them will have improved accesses.
The information on these religious places and connected candidate roads are shown in
Table 9-7.
Table 9-7: Religious Places Served by Proposed Candidate Roads
Road Religious Places
Hambantota-Gonnoruwa-Meegahajandura Gonnoruwa Temple
Bandagiriya Ancient Temple
Meegahajandura Temple
Andarawewa-Udamattala-Padawkema Katharagama Temple
Aluthgamara Temple
Udawalawa-Thanamalwila Katharagama Temple
Hambantota By Pass Road Katharagama Temple
Tissa Temple
Sithulpawwa Temple
Bo-Pale Junction- Kiribbanwewa Kiribbanwewa Temple
Embilipitiya – Moraketiya – Kiribbanwewa -
Udamadura
Embilipitiya Kawanthissa Temple
Kataragama Temple
Tissa Temple
CGHW Road (243km-260km) Kataragama Temple
Tissa Temple
Kirinda Temple
Sithulpawwa Temple
Southern Expressway Extension Kataragama Temple
Tissa Temple
Sithulpawwa Temple
Connection between A018 road and
Sooriyawewa- Mirrijjawela Road (100ft. road)
Madunagala Temple
Karandulena Temple
![Page 143: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/143.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-10
Road Religious Places
Lunugamvehera to Kataragama Kataragama Temple
Ranna-Angunakolapelessa-Wetiya Aluth Wewa Temple
Nimbamarama Kattakaduwa Temple
Ranna Temple
Mulkirigala Temple
Wewurukannala Temple
9.10 Connectivity Impacts of the Proposed Roads
The proposed road network would form a hub of interconnecting roads that are
connected to other roads in both local and regional levels. This network will create
socially and economically effective connectivity impacts in the area and thereby in the
country.
The local community/administrative units such as villages, GN Divisions and DS
Divisions are connected through several roads creating multiple connections to different
directions. For example, number of roads connected to DS Divisions ranging from 1-11.
This would offer direct and indirect benefit for people in these administrative units
through multiple roads.
The consultants have observed that many roads serve for more than one social or
economic centre such as weekly fairs called “Sathi Pola”, religious places or even public
institutions.
Considering the values of the parameters used for this rapid assessment and also based
on the views of the stakeholders as approached by the sociologist the roads can be
categorised in terms of their significance in certain aspects, such as their contribution to
the major development projects in the Greater Hambantota and its peripheral region,
contribution to the local community and also the degree of connectivity to the other part
of the country as whole. Depending on the understanding gained from the rapid survey,
a scoring system has been suggested ranging from1-6. The lower scores (figures)
represent higher degree of significance. The results of these simplified qualitative
analyses are shown in Table 9-8.
![Page 144: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/144.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-11
Table 9-8: Degree of Significance of the Roads Based on Different Aspects
Score More Important Nationally More important LocallyMore Important for Current and Future
Projects
1 Udawalawa -Thanamalwila Hambantota-Gonnoruwa-Meegahajandura Outer Circular Highway
Andara wewa –Udamaththala
Hambantota By Pass Road
CGHW Road (243km-260km)
Southern Expressway Extension
2 CGHW Road (243km-260km)
Lewaya Road
Sooriyawewa - Meegahajandura
Udawalawa –Thanamalwila
Galwewa –Moraketiya
Bo-Pale Junction- Kiribbanwewa
Lunugamvehera to Kataragama
Hambantota-Gonnoruwa-Meegahajandura
Sooriya wewa- Meegahajandura
Udawalawa –Thanamalwila
Udamattala- Thanamalwila
Lewaya Road
Road connecting the Walawe Left Bank Road to
Hambantota-Gonnoruwa- Meegahajandura Road
Connection between A018 road and
Sooriyawewa- Mirrijjawela Road (100ft. road)
Lunugamvehera to Kataragama
3 Outer Circular Highway
Hambantota By Pass Road
Southern Expressway Extension
Lunugamwehera to Kataragama
Andarawewa –Udamaththala
Hambantota By Pass Road
Udamattala-Thanamalwila
CGHW Road (243km-260km)
Sooriyawewa –Padalangala
Sooriyawewa- Mirrijjawela
Connection between A018 road and Sooriyawewa-
Mirrijjawela Road (100ft. road)
Lunugamvehera- Weligatta
Weerawila-7th Colony
Galwewa –Moraketiya
Bo-Pale Junction- Kiribbanwewa
Sooriyawewa- Padalangala
Sooriyawewa –Mirrijjawela
Ranna-Angunakolapelessa-Wetiya
Lunugamvehera- Weligatta
![Page 145: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/145.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
9-12
Score More Important Nationally More important LocallyMore Important for Current and Future
Projects
4 Hambantota-Gonnoruwa-
Meegahajandura
Sooriyawewa - Meegahajandura
Galwewa –Moraketiya
Sooriyawewa- Padalangala
Sooriyawewa- Mirrijjawela
Ranna-Angunakolapelessa-
Wetiya
Lewaya Road
Road connecting the Walawe Left Bank Road to
Hambantota-Gonnoruwa- Meegahajandura Road
Ranna-Angunakolapelessa-Wetiya
Internal Road Grid in the City Area
Weerawila-7th Colony
5 Lunugamvehera Weligatta
Weerawila-7th Colony
Outer Circular Highway
Southern Expressway Extension
Internal Road Grid in the City Area
6 Andarawewa –Udamaththala
Bopale Juntion- Kiribbanwewa,
Udamattala-Thanamalwila,
Road connecting the Walawe Left
Bank Road to Hambantota-
Gonnoruwa- Meegahajandura
Road
Connection between A018 road
and Sooriyawewa- Mirrijjawela
Road (100ft. road)
Internal Road Grid in the City Area
- -
![Page 146: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/146.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-1
CHAPTER 10 ECONOMIC BENEFITS
Benefits are categorised into quantifiable benefits as well as non-quantifiable benefits.
Non-quantifiable benefits may be items such as value of modernisation, reliability or for
social equity redress, all of which are very difficult to quantify. In order to arrive at a
conservative estimate for total economic benefits, such non-quantifiable benefits will be
ignored in favour of the quantifiable benefits.
Quantifiable benefits refer to those for which monetary values can be determined,
directly or by using reliable empirical models or other forecasting tools. Important
quantifiable benefits that are relevant to transport sector projects are described in more
detail below. In developed countries, most emphasis of improving transport facilities is
on saving time and, to a lesser extent, on reducing accidents, as infrastructure is largely
developed. In developing countries such as Sri Lanka, on the other hand, savings in
operating and maintenance cost, and provisions of basic access, are still important
objectives. Methods of calculating these benefits are discussed elsewhere22. A
summary of the discussions, are given below.
10.1 Vehicle Operating Cost Savings:
Savings in vehicle operating costs (VOC) are the most direct and one of the most
important benefits from transport improvements. These savings are mostly achieved by
upgrading technology; increasing speed; reducing congestion; reducing road roughness
and improving geometric design. The value of the savings is usually calculated as a
derivative of the vehicle specifications, road features, cost of operational inputs and
operating speed. VOC savings from a project are usually estimated by calculating the
differences before and after completion of the project concerned.23
22Assessing Public Investment in the Transport Sector, Kumarage et al, National Planning Department,
September 2001.23
Ibid
![Page 147: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/147.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-2
Table 10-1 : Economic Vehicle Operating Cost in Rs/km @ IRR =2
ModeOperating Speed (Km/hr)
30 40 50 60 70 80 90
Motor Cycles 2.59 2.5 2.49 2.51 2.54 2.57 2.6
Three Wheelers 6.09 5.67 5.48 5.4 5.35 5.33 5.33
Passenger Cars 35.66 28.16 24.53 24.65 24.79 24.97 25.20
Vans 25.37 23.19 22.00 21.33 20.99 20.87 20.96
Large Bus 56.98 50.22 46.55 44.55 43.64 43.57 44.17
2 Axle Truck 58.53 50.25 45.99 43.76 42.66 42.66 43.08
3 Axle Truck 76.89 70.43 66.99 65.22 64.61 64.95 66.16
Table 10-2 : Economic Vehicle Operating Cost in Rs/km @ IRR =4
ModeOperating Speed (Km/hr)
30 40 50 60 70 80 90
Motor Cycles 7.99 7.72 7.69 7.75 7.84 7.93 8.02
Three Wheelers 18.80 17.50 16.91 16.67 16.51 16.45 16.45
Passenger Cars 37.87 29.91 26.05 26.17 26.33 26.51 26.76
Vans 26.94 24.63 23.36 22.65 22.28 22.16 22.25
Large Bus 60.51 53.32 49.43 47.30 46.34 46.26 46.90
2 Axle Truck 62.15 53.36 48.83 46.46 45.30 45.30 45.74
3 Axle Truck 81.65 74.79 71.14 69.25 68.61 68.97 70.26
It can be seen that VOC savings range from 5 to 15% for most vehicle types across the
different ranges in operating speeds.
Vehicle operating cost are applicable only to diverted traffic since other traffic known as
generated traffic would be new traffic that does not exist on the road network at present.
As such the flows for each links for each of the forecast years of 2012, 2022 and 2032
are taken from the Diverted Traffic estimates provided in Table 7-16. The modal splits
for the forecasting period are assumed as follows and an average VOC calculated based
on this modal share.
Table 10-3: Modal Share for Forecast period
Mode Modal ShareMotor Cycles 10%Three Wheelers 10%Passenger Cars 35%Vans 15%Large Bus 10%2 Axle Truck 15%3 Axle Truck 5%
![Page 148: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/148.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-3
Vehicle Operating Costs are computed from two sources. The first is from the increase
in speeds enjoyed by the current Base Year Traffic on the current HDP road network.
The second is from the savings enjoyed by traffic diverted from the national network to
the proposed HDP network. A summary of this calculation is given in Table 9-5.
Table 10-4: Summary of VOC Savings
2012 2022 2032Pre DevelopmentTraffic on HDP by 2012 Vehicle kms/day 429,031 644,312 897,442
Speed (km/hr) 42.80 42.08 41.17Av VOC @ IRR4 (Rs/km) 32.07 32.18 32.33
Value/Day Rs mn 13.76 20.74 29.01
Traffic Diverting to HDP Vehicle kms/day 109,619 252,752 671,866Speed (km/hr) 24.83 21.97 19.21Av VOC @ IRR4 (Rs/km) 36.40 37.16 37.90
Value/Day Rs mn 3.99 9.39 25.46
Post DevelopmentTraffic on HDP by 2012 Vehicle kms/day 429,031 644,312 897,442
Speed (km/hr) 70.08 69.09 67.91
Av VOC @ IRR2 (Rs/km) 28.11 28.14 28.17Value/Day Rs mn 12.06 18.13 25.28
Traffic Diverting to HDP Vehicle kms/day 109,619 252,752 671,866Speed (km/hr) 70.08 69.09 67.91
Av VOC @ IRR2 (Rs/km) 28.11 28.14 28.17Value/Day Rs mn 3.08 7.11 18.93
TOTAL VOC Savings (Rs/mn) Traffic on HDP 1.70 2.61 3.73Traffic diverted to HDP 0.91 2.28 6.54
Total per day 2.61 4.89 10.26
Annual (Rs/Mn) 951.06 1,783.38 3,746.54
10.2 Travel Time Savings
Saving in travel time is a primary economic outcome sought in transport sector projects.
These savings are enjoyed by passengers as well as freight consignees. Savings
enjoyed by transport operators are usually included in the savings of vehicle operating
costs discussed in the next section. Time savings would be for travel savings of existing
trips.
10.2.1 Passenger Time Savings
The value of saving travel time of a passenger can vary with (a) hourly income; (b) the
purpose of the trip and (c) the quantum of travel time saved. The average Value of Time
![Page 149: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/149.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-4
(VOT) for passengers by mode of transport for 2010 prices have been calculated based
on VOT computation for passenger travel in Sri Lanka24.
Table 10-5: Value of Time for Transport User Groups (in 2010 Rs/Hour)25
User Group Rs/hr
Car 406.95
Van 153.27
Motor Cycle/Three Wheelers 42.82
Public Transport 37.19
Travel Time Savings are applicable only to diverted traffic since other traffic known as
generated traffic would be new traffic that does not exist on the road network at present.
As such the flows for each road and link for each of the forecast years of 2012, 2022,
and 2032 are taken from the traffic estimates provided in Table 6-19. The modal splits
are assumed to be as given in Table 10-3 for the design period. Vehicle Occupancy is
also assumed as cars 2.2; motor cycles/ three wheelers 1.2, vans 4 and buses 32
passengers per vehicle. These are based on observations at traffic counts and
published national Vehicle Occupancy Rates.26 The weighted average VOT per vehicle
hour is therefore calculated to be Rs 534.59 in 2010 prices.
Table 10-6: Travel Time Savings
2012 2022 2032
Vehicle Hrs saved/day 3,730 6,744 13,922
Annual Saving (Rs/mn) 728 1,316 2,717
10.2.2 Freight Time Savings
In this case, the time loss can lead to two different types of economic consequence; (a)
having to carry higher inventory levels and (b) losses sustained by perishable
commodities such as vegetables, milk, etc. The method of calculating values and
typical commodities in road freight transport in Sri Lanka may be referred.27 Accordingly,
an average consignment value of Rs. 120 per tonne-hour and an average truck load of 2
24Ibid
25Table will be duly filled in the Draft Final Report
26Ibid
27Ibid
![Page 150: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/150.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-5
tonnes have been used given that there are many light goods vehicles of capacity less
than 4 tonnes. .
Table 10-7: Freight Time Savings
2012 2022 2032
Vehicle Hrs saved/day 746 1,349 2,784
Annual Saving (Rs/mn) 65 118 244
10.3 Socio-Economic (Regional) Development
Transport infrastructure is a prerequisite for socio-economic development. This is also
referred to as regional development. This is illustrated by the new commercial,
industrial, residential and agricultural activity that often springs up after a project is
implemented. Transport projects, however, do not guarantee that such development will
occur. Availability of other factors of development, supporting infrastructure (e.g.,
electricity), and government policies also play a role. If development is dependent on
investment in non-transport infrastructure, net benefits should not all be credited to the
transport project, but must be apportioned in some way. Furthermore, transport projects
generally would have less effect on economic development where adequate services are
already available than where services are poor or non-available.
It is difficult to measure the contribution of transport projects on economic development.
It usually demonstrated in a transport project through an increase in travel volumes.
Either a consumer surplus or producer surplus or a combination of both causes this
phenomenon. This new (i.e. increase of) travel is referred to as generated or induced
traffic. However, the increase in traffic itself has no economic value. It is nevertheless,
an indication of increased economic activity in the region.
There are different approaches to estimating the contribution of a transport project to
such a development, although, the methods of valuing regional benefits are less straight
forward than in the case of other benefits. The general, approach is to estimate the
value of the producer or consumer surpluses, as the case may be, that has caused the
increased travel. Thereafter, to apportion a part of such surpluses as economic benefits
due to transport. This proportion could be equated to the proportion of the contribution of
![Page 151: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/151.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-6
transport sector (or road sector) to Gross Regional Development Product or any other
valid basis.
Productivity improvements arising from transport projects are also economic benefits.
For example, improved transport service may make it possible for industry to attract
skilled workers from greater distances, allowing production to be increased.
Alternatively, workers may be less tired and therefore more productive on the job and
less likely to make mistakes. On the other hand, business may be able to achieve
greater economies of scale because materials can be brought in at lower cost.
Table 10-8: Regional Benefits Rs mn28
2012 2022 2032
New Vehicle kms 739,942 1,476,513 2,293,013
New Vehicle Hrs 5,329 11,442 17,628
Regional Benefit (Rs/mn/yr) 1,092 1,934 3,035
The Regional Benefit arising from the Hambantota Road Network has been estimated
using the quantum of generated traffic. It is assumed that this traffic will be entirely due
to regional development. It may be assumed that the value of such inputs must be at
least equal to the cost of the new transport.
This includes the cost of vehicle operating costs and travel time costs. Based on the
premise that the contribution of transport activity will be valued at a total of Rs 3,035
million by the year 2032, based on the consideration that the contribution or the value
addition to GDP by the project would be worth at least 12% of the total regional growth.
10.4 Summarised Benefits for all Scenarios
The total benefits calculated for the years 2012, 2022 and 2032 for the Proposed
Development Scenario assuming that income levels will also be assumed to increase
also at 8% per annum is given in Table 10-9.
28Table will be duly filled in the Draft Final Report
![Page 152: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/152.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10-7
Table 10-9: Summary of Benefits (Rs Mn in Current Year Prices) 29
2012 2022 2032
Savings in Vehicle Operating Cost1,109 4,491 20,368
Passenger Travel Time Savings849 3,314 14,769
Freight Travel Time Savings76 297 1,325
Regional Benefits1,092 4,871 16,498
TOTAL3,127 12,973 52,960
29Table will be duly filled in the Draft Final Report
![Page 153: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/153.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-1
CHAPTER 11 ECONOMIC COSTS
The costs of construction for Stage II are discussed as follows:
11.1 Land Acquisition & Resettlement
The land acquisition and resettlement costs of the highway is estimated based on the
information gathered from following sources;
Topographic Maps of both 1:50000 and 1: 10000 (electronic files and hard
copies)
GIS data base available in Department of Transport and Logistics Management
UoM
RDA Land Division (Data collected in year 2007)
UDA unpublished reports
Field information collected from socio economic survey
The different land use within the proposed road corridors within their right of ways
(ROW) were obtained using GIS maps and 1:50,000 topographical maps. Then the
required land acquisition for the development was taken as the land area between the
proposed ROW and the existing ROW. The percentages of different land use by length
along each road are given in Table 11-1. There was no specific and authoritative source
to obtain land values for different areas. The land values were obtained as the market
prices for the current year from the rapid socio-economic surveys carried out at site for
all the selected roads for improvements. The total economic cost of land acquisition has
been estimated at Rs. 1,319,020,259
11.2 Resettlement Costs
The total number of houses affected by the improvements of the road network has been
computed as 259, those are within the ROW of the proposed road improvements.
Majority of the affected houses in the area are single storied houses. Therefore, a flat
rate for the resettlement has been applied in the estimates. The resettlement cost
includes the costs of the demolition of existing structures, reconstruction and the lands
for new construction of houses for the affected families. The cost of the new land extent
![Page 154: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/154.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-2
of 20 perches has been assumed for estimation of the resettlement cost within the
Greater Hambantota Development Area. The total value for resettlement cost is
estimated as Rs 547,918,750.
Table 11-1 : Percentage Land Use by Length along the Road
HR01 Outer Circular Highway 0 0 0 0 56 0 18 25HR02 Hambantota – Gonnoruwa – Megahajandura Road 12 6 4 5 56 0 11 7
HR03 Sooriyawewa – Meegahajandura –Kumaragama Road 13 14 8 0 30 0 33 2HR04 Andarawewa – Udamattala – Padawkema Road 6 0 7 15 56 0 10 7HR05 Udawalawe – Thanamalwila Road 19 3 0 6 56 0 10 6HR06 Galwewa Junction -Moraketiya Road 27 10 10 0 22 0 27 4HR07 Hambantota Bypass Road 14 2 30 10 27 0 18 0
HR08 Nabodagaswewa-Swodagama-Andarawewa Road 0 1 9 12 0 68 0 9HR09 Bopale Junction - Kiribbanwewa Road 17 0 17 0 5 0 61 0HR10 Embilipitiya – Moraketiya – Kiriibbanwewa - Udamadura Road 34 31 8 0 0 0 27 0HR11 Airport Central Access Road 0 0 0 0 100 0 0 0
HR12 New Airport Access Road 20 0 1 5 62 0 8 4
HR13 CGHW Road (from Hambantota to Thanamalwila) 38 26 9 3 7 1 16 1HR14 Lewaya Road 58 31 0 0 12 0 0 0HR15 Sooriyawewa – Padalangala Road 43 0 16 0 0 0 41 0HR16 Sooriyawewa – Mirijjawila Road 11 0 1 13 30 0 45 0
HR17 Extension of Southern Expressway - - - - - - - -
HR18 Arabokka-Siyabalagaswewa-Gonnaruwa Road 0 0 0 0 66 0 34 0
HR19 Wetiya -Mahapalassa-Nabodagaswewa Road 10 0 10 9 49 5 17 0HR20 Lunugamvehera - Kataragama Road 3 14 9 0 13 0 50 11HR21 Ranna - Angunakolapelessa - Wetiya Road 54 0 42 0 4 0 0 0HR22 Lunugamvehera -Weligatta Road 3 25 0 0 41 0 26 5HR23 7th Colony-Weerawila Road 31 0 34 0 5 0 31 0HR24 Udamattala – Thanamalwila Road 6 6 0 0 81 0 4 4HR25 Internal Road Grid in the City Area 0 0 0 0 92 0 8 0HR26 Southern Expressway Access Road - - - - 42 - 58 -
HR27 Walawe Project Road - - - - 83 - 17 -
18 9 8 4 32 3 22 4Total
Road NameNo
Sh
urb
s/B
are
Lan
d
Mars
hy
Ch
en
a
Fo
rest
Land Use (% by Total Length)
Ho
me
Gard
en
Co
mm
erc
ial
Pad
dy
Pla
nta
tio
n
11.3 Earth works
The earth works include, site clearing, excavating and removal of unsuitable materials,
embankment filling with cut materials and imported materials with CBR above 8 and sub
base construction with Type I materials with CBR above 20. The total volumes of earth
work required for excavation and removal, embankment fill together with the
excavatedmaterial and imported material and imported material for sub base are shown
in Table 11-2. The total estimated cost is Rs 8.207 billion.
![Page 155: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/155.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-3
Table 11-2: Estimation of Cut and Fill volume
No Item Unit QtyRate
(Rs)Amount (Rs)
1 Site Clearing m² 8,730,089 120 1,047,610,680
2 Cut and Removal of unsuitable materials m³ 2,619,027 353 923,570,271
3 Embankment Filling with Type II Material m³ 4,105,797 806 3,308,785,695
4Sub Base Construction with Type I
Materialm³ 2,514,297 1164 2,926,769,944
TOTAL 8,206,736,590
11.4 Drainage
The quantities for the drainage system with built-up drains with reinforced concrete and
earth drains for road drainage, lead away drainage are calculated based on linear meter
rate after identifying the cut and fill lengths based on the land use for each section of the
highway. The cost of the drainage system was estimated as Rs. 2.344 billion.
Table 11-3: Cost of Drainage
No Item Unit QtyRate
(Rs)Amount (Rs)
1 Construction of Earth Drains m 414,119 1664 689,094,349
2 Construction of Built up Concrete Drains m 202,952 8159 ,655,857,969
TOTAL 2,344,952,318
11.5 Road Works
The Road Works item is taken as the base, binder and the wearing course including
priming and tack coats appropriately where they are applicable depending on the new
road sections and the existing road sections. The items were separately quantified and
the rates were applied for each item for present year 2010. The average pavement
section used for the BOQ estimates is given in Figure 11-1.
![Page 156: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/156.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-4
Figure 11-1 : Typical Pavement Section Used for Estimations
The quantities and amounts are shown in Table 11-4. The total estimated cost is Rs
18.183 billion. This could be at design stage be selectively reduced by adopting a less
costly pavement section for roads having low traffic volumes.
Table 11-4: Cost of Base and the Pavement (Road Works)
No Item Unit QtyRate
(Rs)Amount (Rs)
1 Aggregate Base Course (ABC) m³ 877,080 3834 3,362,619,912
2 Bituminous Tack Coat m² 617,852 113 69,907,747
3 Bituminous Prime Coatm²
4,604,670148 680,045,220
4
Bituminous Binder Course
(60mm)m³ 313,351 25246 7,910,781,420
5
Asphalt Concrete Surfacing
(40mm)m³ 208,901 29486 6,159,696,991
TOTAL 18,183,051,290
11.6 Structures (Bridges and Culverts)
The bridges over rivers, main streams and irrigation channels as well as culverts across
main roads and by roads for cross drainage and for small waterways are included under
this item. The drainage structures such as Bridges have been identified as Multi-spans,
![Page 157: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/157.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-5
Two spans and Single span while the culverts have been identified as the type of Box
Culverts and the Hume Pipe (HP) Culverts. Also different rates have been applied on
the basis of widening and new construction for both cases. The bridges to overpass the
railway crossings are included under this item while the flyovers for Elephant Corridors
are separately listed for better understanding of their magnitude and the cost
proportions. The minimum size of the HP pipes are considered as diameter of 600mm
for the ease maintenance and the higher capacity of the cross drainage. The total
estimated cost is Rs 1.835 billion.
Table 11-5: Summary Table of Costs for Structures
No Item Unit QtyRate
(Rs)Amount (Rs)
1 Widening of Box Culverts m 14,116 15855 223,814,888
2Widening of Pipe Culverts (Dia
0.6m and above)m 7,058 12458 87,927,277
3 New construction of Box Culverts m 10,743 14723 158,160,413
4New construction of Pipe Culverts
(Dia 0.6m HP and above)m 6,446 11325 72,997,114
5 Bridge Construction (Single Span) m² 2,291 200000 458,240,000
6 Bridge Construction (Two Span) m² 2,312 225000 520,222,500
7 Bridge Construction (Multi-Span) m² 800 250000 200,000,000
8Bridge to Overpas Railway at
Mirijjawila Rdm² 456 250000 114,000,000
TOTAL 1,835,362,192
11.7 Elephant Underpasses
The elephant underpasses are provided at specifically selected places for providing safe
elephant crossings of the main roads. They are identified to ensure safe crossing for
elephantsand other wild life in areas considered on the basis of the present and future
elephant movements requested by the wildlife authorities. The underpasses have been
requested as a mitigatory measure by the Wild Life Authorities. However, the practicality
of wild life using such crossings has not been tested before hand in Sri Lanka on this
scale and further studies are recommended.
These underpasses for elephants and other wild life are provided across the pre-
identified locations of a few main roads. In these cases, electric fences are to be located
along both sides of the roads to divert the elephants towards the aforementioned
![Page 158: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/158.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-6
underpasses and for the safety of the road users and properties. Total of four (4)
underpasses have been proposed at two (2) identified locations on Hambantota-
Gonnoruwa Road and one (1) location across the Air Port Access Road (Road No 18)
and the final one (1) at the midway of the Road No 08. The total average length of an
underpass has been estimated as 450 meters where three spans (each approximately
50 meter span) are provided for elephant passes. An underpass for the railway crossing
at Hambantota-Gonnoruwa Road (Road No 02) is also included in addition to the
underpass for elephant crossings. The total cost of all the underpasse is estimated as
Rs 10.780 billion.
11.8 Roadway Facilities
The main items included for costing under roadway facilities are Walkways, Kerbs,
Bicycle lanes, Bus Bays, and landscaping. As observed, the major component will be
for landscaping where it is an obvious inclusion to make Hambantota as a green city to
stand with the nature of the inherent climatic situation. It has been insisted by UDA to
have these roads as green as possible to reduce the driver stress as well as for
pedestrians and non motorised users to have pleasant environment. The walkways
have been proposed for roads near the Hambantota City area together with separate
bicycle lanes. The kerbs are separately estimated as they are included in the centre-
medians and the islands for landscaping at different cross sections of the proposed road.
The total costs of the facilities are estimated as Rs 11.704 billion.
Table 11-6: Summary Table of Costs for Roadway Facilities
No Item Unit Qty Rate (Rs) Amount (Rs)
1 Walkways m² 1,383,904 1550 2,144,497,638
2 Kerbs-Type K1 m 1,523,540 1277 1,945,208,874
3 Bicycle Lanes m² 1,059,400 2476 2,622,915,490
4 Landscaping m² 2,311,830 2000 4,623,660,000
5 Bus Bays Nos 1,449 253944 367,852,779
TOTAL 11,704,134,781
![Page 159: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/159.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-7
11.9 Lighting & Safety
The estimate for this item includes, lighting at intersections and road links, all type of sign
boards, road markings, reflective road studs and eclectic fences to safeguard road users
and properties from potential elephant attacks. The current rates have been used and
applied considering two approaches. According to the first approach, the costs for the
item at intersection are taken as a separate item. As per the second approach, the rate
for facilities along the main highway is taken as linear meter basis. The summary is
given in Table 11-7. The total estimated cost is Rs 7.486 billion. This expenditure is
considered necessary to achieve the reduction in accident costs anticipated as benefits.
Table 11-7: Cost Estimates for Road Safety
No Item Unit Qty Rate (Rs) Amount (Rs)
1Traffic Sign Boards (All types) at
LinksNos 7,244 28000 202,832,000
2Traffic Signs Boards (All types) at
IntersectionsNos 42 100777 4,232,632
3 Lane Markings m 2,079,110 300 623,733,000
4 Reflecting Road Studs Nos 225,130 1050 236,386,500
5 Street lights on Main Highway km 362 16,428,557 5,949,437,532
6 Lighting at Intersections Nos 42 10,251,171 430,549,201
7 Electric Fencing km 78 500000 39,160,000
TOTAL 7,486,330,865
11.10 Rehabilitation in 2021 (after 10 years)
It is expected to rehabilitate the road network in year 2021 to ensure the project
outcomes are undisturbed during its life time. T his can be calculated as 10% of the total
capital cost of construction.
![Page 160: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/160.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-8
11.11 Routine Maintenance
Four major elements have been identified under routine maintenance expenditure for the
smooth operation of the highway. The associated annual costs for each of these items
are estimated as a percentage of the total construction cost of such items and given in
Table 11-8. The total annual cost for pavement, drainage, structures, roadway facilities,
lighting and safety will amount to around Rs 855 million per year. A breakdown of this is
given in Table 11-8. Howeve this will vary with the age of the road after construction.
Table 11-8 : Average Cost of Annual Maintenance
NoMaintenance Item
Description
Construction
Cost% % cost
1 Pavement 18,183,051,290 1 181,830,513
2 Drainage 2,344,952,318 2 46,899,046
3 Structures 1,835,362,192 1 18,353,622
4 Roadway Facilities 11,704,134,781 2 234,082,696
5 Lighting, Road Safety 18,183,051,290 1 181,830,513
TOTAL 855,482,420
11.12 Summary of the BOQ
The summary of the cost for the entire road network (Stage II) is given as in Table 11-9.
Table 11-9: Summary of Stage II Construction Costs
No Description Amount (Rs)
1 Land Acquisition and Resettlement 1,866,939,009
2 Preliminaries/General 2,603,671,482
3 Earthworks 8,206,736,590
4 Drainage 2,344,952,318
5 Base Course and Pavement 18,183,051,290
6 Bridges and Culverts Structures 1,835,362,192
7 Roadway Facilities 11,704,134,781
8 Road Safety & Lighting 7,486,330,865
9 Shifting of Services 724,280,000
10 Flyovers 12,740,000,000
![Page 161: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/161.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
11-9
No Description Amount (Rs)
11 Sub Total 67,695,458,527
12 Provisional Sum (Price Escalation as 5%) 3,384,772,926.35
Total 71,080,231,453.35
The total financial cost of construction of all roads to Stage II level between 2011 and
2013 is Rs 71 billion, including a provisional sum of Rs 3.385 billion provided for
price escalation.
![Page 162: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/162.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12-1
CHAPTER 12 ECONOMIC BENEFIT COST ANALYSIS
The economic cost benefit for the proposed project (Stage II level) has been considered
by taking all the project costs to be incurred during the design period of 20 years and the
corresponding benefits. For this purpose, the benefits of the project estimated in
Chapter10 are used. These costs are in economic terms. The costs are taken from the
computations in Section 8 where the estimates are made for financial costs.
In order to undertake an economic benefit-cost analysis, all costs also have to be
converted to economic costs. In this respect, the component of costs attributed to taxes
and other forms of transfer payments have to be deducted. Based on the Conversion
Rates published for Transport Sector Projects30, it is decided to consider 85% or 0.85 for
a project of this nature. As discussed earlier, land values since they are computed as
actual use or non-use values, they will not be converted as economic costs will be
assumed to be equal to financial costs.
Benefit-Cost Analysis is carried out for the selected development scenario that has been
considered in this project. The benefit component varies with the traffic level. The cost
component has been kept the same, since the scenarios were not based on different
geometric designs.
12.1 Assumptions in Analysis
The BCA for the proposed development project given in the following table are based on
the following assumptions:
A discounting rate of 12% per annum.
Inflation of financial costs for construction and for maintenance is assumed at 8%
per annum.
The economic value of the increase in benefits in terms of increasing income
levels will also be assumed to increase also at 8% per annum.
30Assessing Public Investment in the Transport Sector, National Planning Department, Kumarage et al,
2001
![Page 163: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/163.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12-2
Maintenance cost for the road will be 0.5% of the replacement value at year 0
and this rate will increase at 10% per annum in real terms.
Design life of road will be for 20 years and rehabilitation at cost of 10% of
replacement values will be necessary at 10 years and rehabilitation at 30% of
value after 20 years.
12.2 Benefit Analysis for Stage II Construction Over 3 Years
In the full development context assumed as Stage II level, it is assumed that the
construction will be completed in 3 years, the BCA for which is given in Table 12-1.
Table 12-1: Benefit –Cost Analysis for Stage II Construction over 3 Years
12 %
Year Cost Benefit Payback
2010 20,139 20,139 0 1.000 20139.4 - (20,139)
2011 21,751 20,139 0 0.893 17,982 - (38,121)
2012 23,491 352 22,103 1,109 849 76 1,092 3,127 0.797 17,620 2,492 (53,249)
2013 419 419 1,303 991 89 1,482 3,865 0.712 298 2,751 (50,796)
2014 497 497 1,520 1,150 103 1,715 4,489 0.636 316 2,853 (48,259)
2015 591 591 1,764 1,329 119 1,976 5,188 0.567 335 2,944 (45,651)
2016 702 702 2,038 1,528 137 2,268 5,971 0.507 356 3,025 (42,981)
2017 834 834 2,343 1,751 157 2,594 6,845 0.452 377 3,096 (40,262)
2018 991 991 2,685 2,000 179 2,957 7,821 0.404 400 3,159 (37,503)
2019 1,177 1,177 3,066 2,278 204 3,362 8,910 0.361 424 3,213 (34,715)
2020 1,398 1,398 3,491 2,587 232 3,813 10,122 0.322 450 3,259 (31,906)
2021 1,661 1,661 3,964 2,931 263 4,314 11,472 0.287 477 3,298 (29,085)
2022 7,047 1,973 9,020 4,491 3,314 297 4,871 12,973 0.257 2,315 3,330 (28,071)
2023 904 904 5,384 3,960 355 5,560 15,259 0.229 207 3,497 (24,781)
2024 1,074 1,074 6,391 4,688 420 6,328 17,828 0.205 220 3,648 (21,353)
2025 1,275 1,275 7,525 5,507 494 7,183 20,710 0.183 233 3,784 (17,802)
2026 1,515 1,515 8,800 6,428 576 8,135 23,939 0.163 247 3,905 (14,144)
2027 1,800 1,800 10,230 7,460 669 9,193 27,552 0.146 262 4,013 (10,394)
2028 2,139 2,139 11,833 8,617 773 10,368 31,591 0.130 278 4,108 (6,564)
2029 2,541 2,541 13,627 9,911 889 11,672 36,099 0.116 295 4,191 (2,667)
2030 3,018 3,018 15,632 11,356 1,018 13,119 41,126 0.104 313 4,263 1,283
2031 3,586 3,586 17,871 12,970 1,163 14,722 46,726 0.093 332 4,325 5,276
2032 4,260 4,260 20,368 14,769 1,325 16,498 52,960 0.083 352 4,377 9,301101,782 125,069 91,604 8,215 116,723 394,571 64,230 73,530
Benefit CostAnalysis
9,3011.14
13.50%
Co
ns
tru
cti
on
Co
st
Rec
urr
en
tC
ost
Ve
hic
leO
pera
tin
gC
os
tS
av
ing
s
Tra
ve
lT
ime
Sa
vin
gs
Go
od
sT
rav
elT
ime
Sa
vin
gs
Re
gio
na
lD
ev
elo
pm
en
tB
en
efit
s
Pre
se
nt
Va
lue
@D
isco
un
tR
ate
To
tal
Co
st
To
tal
Ben
efi
ts
Net Present Value(NPV)RsMillionBenefitCost Ratio(BCR)@12%
Internal RateofReturn(IRR)
![Page 164: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/164.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12-3
The BCA analysis indicates that the immediate full development of the proposed road
network (Stage I and II together) will have an economic return on investment of around
13.5% p.a. with a NPV of Rs 9,301 million at a Discounting Rate of 12%, while its Benefit
Cost Ratio would be 1.14. Given that economic cost of capital for this project may be
significant, this is not considered a favourable rate for a large scale highway project.
12.3 Sensitivity Analysis
In this context the Sensitivity Analysis will test for the conditions under which the BCA
can be improved at the 12% discount rate. This may be achieved by (a) reducing costs
or (b) by increasing benefits or (c) by delaying the incurrence of some costs or (d)
combinations of the above.
In this pursuit the following course of action is considered:
12.3.1 Construction Period of Combined Stages I and II
Accordingly we will examine the impact of having a period of combined Stages of
construction but, stretched over 6 years instead of 3. The results of this anaylis are
shown in Table 12-2.
![Page 165: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/165.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12-4
Table 12-2: Benefit –Cost Analysis for Stage II Construction Stretching over
6 Years
12%
Year Cost Benefit Payback
2010 10,070 10,070 0 1.000 10,070 - (10,070)
2011 10,875 10,070 0 0.893 8,991 - (19,061)
2012 11,745 10,875 1,109 849 76 1,092 3,127 0.797 8,670 2,492 (25,238)
2013 12,685 12,685 1,303 991 89 1,482 3,865 0.712 9,029 2,751 (31,516)
2014 13,700 13,700 1,520 1,150 103 1,715 4,489 0.636 8,706 2,853 (37,370)
2015 14,796 444 15,240 1,764 1,329 119 1,976 5,188 0.567 8,647 2,944 (43,073)
2016 527 527 2,038 1,528 137 2,268 5,971 0.507 267 3,025 (40,315)
2017 626 626 2,343 1,751 157 2,594 6,845 0.452 283 3,096 (37,502)
2018 744 744 2,685 2,000 179 2,957 7,821 0.404 301 3,159 (34,644)
2019 884 884 3,066 2,278 204 3,362 8,910 0.361 319 3,213 (31,750)
2020 1,050 1,050 3,491 2,587 232 3,813 10,122 0.322 338 3,259 (28,829)
2021 1,248 1,248 3,964 2,931 263 4,314 11,472 0.287 359 3,298 (25,890)
2022 1,482 1,482 4,491 3,314 297 4,871 12,973 0.257 381 3,330 (22,940)
2023 1,761 1,761 5,384 3,960 355 5,560 15,259 0.229 404 3,497 (19,847)
2024 2,092 2,092 6,391 4,688 420 6,328 17,828 0.205 428 3,648 (16,627)
2025 2,486 2,486 7,525 5,507 494 7,183 20,710 0.183 454 3,784 (13,298)
2026 9,588 2,953 12,540 8,800 6,428 576 8,135 23,939 0.163 2,046 3,905 (11,438)
2027 1,352 1,352 10,230 7,460 669 9,193 27,552 0.146 197 4,013 (7,623)
2028 1,607 1,607 11,833 8,617 773 10,368 31,591 0.130 209 4,108 (3,723)
2029 1,909 1,909 13,627 9,911 889 11,672 36,099 0.116 222 4,191 246
2030 2,268 2,268 15,632 11,356 1,018 13,119 41,126 0.104 235 4,263 4,275
2031 2,694 2,694 17,871 12,970 1,163 14,722 46,726 0.093 249 4,325 8,350
2032 3,200 3,200 20,368 14,769 1,325 16,498 52,960 0.083 264 4,377 12,462111,111 125,069 91,604 8,215 116,723 394,571 61,068 73,530
BenefitCostAnalysis
12,4621.20
14.40%
Pre
se
nt
Va
lue
@D
isco
un
tR
ate
To
tal
Co
st
To
tal
Ben
efi
ts
NetPresentValue(NPV)RsMillionBenefitCostRatio(BCR)@12%
InternalRateofReturn(IRR)
Co
ns
tru
cti
on
Co
st
Rec
urr
ent
Co
st
Ve
hic
leO
per
ati
ng
Co
st
Sav
ing
s
Tra
ve
lT
ime
Sa
vin
gs
Go
od
sT
rav
elT
ime
Sa
vin
gs
Re
gio
na
lD
ev
elo
pm
en
tB
en
efit
s
The stretching of construction over 6 years improves the BC Ratio to 1.20 and the
Economic Internal Rate of Return to 14.4% and where at a Discount Rate of 12% the
NPV is Rs 12,462 million. While this is an improvement to the scenario of constructing
the roads over 3 years, it does not improve the economic performance very much and
cannot be considered as adequately favourable.
![Page 166: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/166.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12-5
12.4 Stepwise construction as Stage I and Stage II
In this proposal it is envisaged that only Stage I will be constructed in the first 3 years
and the balance would be constructed lagged by 10 years.
The cost of the Stage I construction is set out against the cost of both Stage I and II in
Table 12-3.
Table 12-3: Comparison of Cost of Construction for Stage I and Stage I &II
No DescriptionAmount (Rs)
Stage I and II Stage I only
1Land Acquisition andResettlement
1,866,939,009 1,866,939,009
2 Preliminaries/General 2,603,671,482 1,656,274,696
3 Earthworks 8,206,736,590 5,282,524,369
4 Drainage 2,344,952,318 2,149,743,482
5Base Course andPavement
18,183,051,290 12,134,292,644
6Bridges and CulvertsStructures
1,835,362,192 1,184,202,634
7 Roadway Facilities 11,704,134,781 7,242,294,222
8Road Safety &Lighting
7,486,330,865 3,451,333,581
9 Shifting of Services 724,280,000 724,280,000
10 Flyovers 12,740,000,000 7,840,000,000
11 Sub Total 67,695,458,527 43,531,884,637
12Provisional Sum(Price Escalation as5%)
3,384,772,926.35 2,176,594,231.83
Total 71,080,231,453.35 45,708,478,868.35
The result of this analysis using an initial cost of Rs 45.8 billion for Stage I only in the first
3 years and the balance after 10 years is shown in Table 11.4 which indicates that the
Economic Internal Rate of Return increases to 18.5% while the BC Ratio also increases
to 1.87 and NPV at 12 percent Discount Rate also increases to Rs 54,626 million, thus
showing that the project could be made economically viable under these conditions.
![Page 167: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/167.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12-6
In this scenario, the design life of the project is assumed to be 40 years with a major
rehabilitation of Stage I roads carried out after 20 years in addition to an intermediate
improvement after 10 years. It is reasonable to assume an extended design life since
initial investments are made over 13 years and the accrual of benefits will also be
gradual as this is a long term project.
Table 12-4: Benefit-Cost Analysis for Staged Construction
12 %
Year Cost Benefit Payback
2010 12,951 12,951 0 1.000 12950.74 - (12,951)
2011 13,987 12,951 0 0.893 11,563 - (24,514)
2012 15,106 227 14,213 1,109 849 76 1,092 3,127 0.797 11,331 2,492 (33,352)
2013 269 269 1,303 991 89 1,482 3,865 0.712 192 2,751 (30,793)
2014 320 320 1,520 1,150 103 1,715 4,489 0.636 203 2,853 (28,144)
2015 380 380 1,764 1,329 119 1,976 5,188 0.567 216 2,944 (25,415)
2016 451 451 2,038 1,528 137 2,268 5,971 0.507 229 3,025 (22,619)
2017 536 536 2,343 1,751 157 2,594 6,845 0.452 243 3,096 (19,765)
2018 637 637 2,685 2,000 179 2,957 7,821 0.404 257 3,159 (16,864)
2019 757 757 3,066 2,278 204 3,362 8,910 0.361 273 3,213 (13,924)
2020 15,520 899 16,419 3,491 2,587 232 3,813 10,122 0.322 5,286 3,259 (15,951)
2021 16,761 1,068 17,829 3,964 2,931 263 4,314 11,472 0.287 5,126 3,298 (17,778)
2022 18,102 1,269 19,371 4,491 3,314 297 4,871 12,973 0.257 4,972 3,330 (19,421)
2023 4,532 581 5,113 5,384 3,960 355 5,560 15,259 0.229 1,172 3,497 (17,096)
2024 690 690 6,391 4,688 420 6,328 17,828 0.205 141 3,648 (13,589)
2025 820 820 7,525 5,507 494 7,183 20,710 0.183 150 3,784 (9,955)
2026 974 974 8,800 6,428 576 8,135 23,939 0.163 159 3,905 (6,209)
2027 1,158 1,158 10,230 7,460 669 9,193 27,552 0.146 169 4,013 (2,365)
2028 1,375 1,375 11,833 8,617 773 10,368 31,591 0.130 179 4,108 1,564
2029 1,634 1,634 13,627 9,911 889 11,672 36,099 0.116 190 4,191 5,566
2030 1,941 1,941 15,632 11,356 1,018 13,119 41,126 0.104 201 4,263 9,628
2031 2,306 2,306 17,871 12,970 1,222 14,722 46,785 0.093 213 4,330 13,745
2032 2,739 2,739 20,368 14,769 1,325 16,498 52,960 0.083 226 4,377 17,895
2033 51,074 3,254 54,328 22,878 16,509 1,435 18,709 59,530 0.074 4,009 4,393 18,279
2034 3,866 3,866 25,658 18,432 1,556 21,167 66,814 0.066 255 4,402 22,426
2035 4,593 4,593 28,737 20,558 1,686 23,900 74,881 0.059 270 4,405 26,561
2036 5,456 5,456 32,144 22,906 1,827 26,934 83,812 0.053 287 4,402 30,676
2037 6,482 6,482 35,913 25,498 1,980 30,301 93,692 0.047 304 4,394 34,766
2038 7,701 7,701 40,079 28,358 2,146 34,034 104,617 0.042 322 4,380 38,824
2039 9,149 9,149 44,682 31,513 2,326 38,171 116,690 0.037 342 4,362 42,844
2040 10,868 10,868 49,764 34,990 2,520 42,751 130,026 0.033 363 4,340 46,821
2041 12,912 12,912 55,374 38,823 2,731 47,820 144,748 0.030 385 4,314 50,750
2042 15,339 15,339 61,563 43,045 2,960 53,427 160,994 0.027 408 4,284 54,626246,528 542,230 387,004 30,766 470,435 1,430,434 62,585 117,211
Benefit Cost Analysis54,626
1.8718.50%
Pre
se
nt
Va
lue
@
Dis
cou
nt
Ra
te
To
tal
Co
st
To
tal
Ben
efi
ts
Net Present Value (NPV) Rs Million
Benefit Cost Ratio (BCR) @ 12%Internal Rate of Return (IRR)
Co
ns
tru
cti
on
Co
st
Rec
urr
ent
Co
st
Ve
hic
leO
per
ati
ng
Co
st
Sav
ing
s
Tra
ve
lT
ime
Sa
vin
gs
Go
od
sT
rav
elT
ime
Sa
vin
gs
Re
gio
na
l
De
vel
op
me
nt
Be
nef
its
Other forms of analysis such as a Multi-Criterion Analysis should be performed at
Feasibility Stage to ensure that the project can be further justified on other non-economic
criterion such as equity based improvements, social development, environmental
protection etc.
![Page 168: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/168.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-1
CHAPTER 13 CONCLUSIONS
The following objectives as set out in the Terms of Reference for the study have been
achieved in this report:
a) Identified the long-term demand for transport for the developments proposed
for Hambantota.
b) Assessed the requirements for transport capacity development to serve such
increase in demand and a strategic intervention.
c) Investigated the adequacy of the proposed road network development and to
make recommendations thereof.
d) Carried out a preliminary design of each recommended road link and provide
typical road sections and costs.
e) Carried out an assessment of socio economic viability of the network as a
whole.
The report notes that the Greater Hambantota Area is being developed with an
international seaport at Hambantota as its main economic generator, located in the
southern dry zone of Sri Lanka. It spreads over an area of 113,000 ha that lies between
Walawe River and Kirindi Oya. The defined area for the development plan covers DS
Divisions of Sooriyawewa (21 GNDs), Hambantota (30 GNDs), Ambalantota (13 GNDs),
Thanamalwila (5 GNDs), Sevanagala (14 GNDs), Tissamaharama (15 GNDs) and
Lunugamvehera (29 GNDs).
It also notes that the available natural resources is expected to provide sound economic
base for new development in Hambantota since large extent of underutilised land is
available in efficient urban structure that could certainly be designed conforming to an
effective development plan.
The study has also considered that in Greater Hambantota area, a number of large scale
projects have been proposed. The study team visited the proposed development sites
under the Greater Hambantota Development Plan that include several components
including a:
![Page 169: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/169.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-2
Commercial Establishment
Convention Centre
Administrative Complex
Playgrounds and Recreational areas
Seaport Development
Airport Development
Extension of the Railway
Extension of the Southern Expressway
Oil Refinery
Tsunami Housing Scheme
This study strongly considered that the hinterland of Hambantota has great potential to
develop around the port and Hambantota District in particular and as a result, the
Southern Sri Lanka (Ruhuna) in general will become an industrialised area. Ruhuna is
considered as having the greatest potential due to the availability of land, the most
important factor of production in a densely populated country like Sri Lanka. Additionally,
the ever increasing congestion in Colombo area while decreasing the potential of its
expansion, justifies the need of developing Hambantota as a port-centred industrial
district.
Representatives of key Governmental agencies were invited to Hambantota Divisional
Secretariat on 8th June 2010 to make them aware about the proposed road development
plans and to discuss their concerns and potential to partake in the said development in
Hambantota Area all of which were assessed and incorporated where possible.
The study area for the road network had been selected based on the provision of
accesses to the proposed international hub development sites such as the Airport,
Seaport, Cricket Stadium, Safari Park, BOI site etc. as well as the Convention Centre,
Administrative Complex and tourism related development and residential areas.
Providing access for these sites and inter-linking them to an appropriate level were the
major concerns when designing the road network.
When defining the road network, additional measures had been taken to integrate
Eastern and Uva provinces nationally, as those provinces are considered to be the least
![Page 170: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/170.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-3
accessible provinces in Sri Lanka and ones that could be better served through a port
and airport compared to Western Province.
In addition to the provision of accesses for development sites, the study team had
purposefully introduced certain transport functionality aspects when defining road
network and their cross sections with the intention of increasing the performance of the
proposed network and specifically with respect to:
1. Definition of an Outer Hambantota Development Area
2. Provision of a high profile connection between the proposed Seaport and Airport
3. Provision of a viable public transport corridor
4. Maximise Usage of Pedestrian and Cycle Access
After considering the aforementioned functionality aspects, the original RDA proposals
which contained 17 road links, has been improved to a proposed road network with 27
links. It includes one omission, the Outer Circular Road II, and the addition of 11 new
links to the original proposal of the RDA. The total length of the proposed network is
371.7 km of which new constructions would amount to around 38 km or around 10% of
the network.
The road network proposed by this study includes the reformation of 20 existing roads
and the construction of 5 new links and the down grading of the final section of the
proposed Extension of the Southern Expressway and up grading of the internal road
network in the City Area.
Future traffic levels in the Road Network for Hambantota Development project area will
be influenced by the following factors:
Diversion of existing traffic from other roads to A2 Road, in particular due to
reduction of travel distances and travel times, to destinations such as Uva and
Eastern Provinces as well as North Central Province from the south.
Diversion of traffic from other roads to the national network such as A4 due to
shorter distances and travel times from origins in the Western, North-Western,
Northern and Central Provinces to the south.
Traffic generated due to the development of the Port of Hambantota and its direct
results in terms of increased population.
![Page 171: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/171.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-4
Traffic generated by the industries to be set up as part of the Greater Hambantota
Development Plan.
Increase in traffic due to development of a 2nd international airport in terms of
direct air passengers and cargo movements, as well as the support services.
As per the Terms of Reference, the Traffic forecasts have been made for the years 2012,
2022 and 2032. It was expected that full development potential of the Hambantota
Development Plan would have been achieved by the year 2032, while the year 2012
would see the construction of the basic infrastructure such as the Stage I of the port, the
air port, the cricket stadium, administrative complex, safari park etc. The forecast year
2022 is considered as an interim stage between the years 2012 and 2032.
The highway traffic generation rates are estimated by comparing with estimates of traffic
from Port of Colombo for its associated cargo movements. The forecast cargo volumes
were as given in the Feasibility Study for the Hambantota Seaport. These estimated
were used for estimation of the corresponding road traffic volumes. Their destinations
were allocated on the expected destinations especially those in the provinces of Uva,
Eastern, Central and Southern.
As for the Mattala International Airport, the forecast are based on the estimated
passenger traffic and its probable local destinations which would mostly be in the tourist
area stretching from Bentota to Tissamaharama along the south western coast, and
further along the east coast, particularly for Arugam Bay area.
It was estimated that the Greater Hambantota Area will not incur rapid migration by 2012
as most construction oriented jobs and jobs in other activities can be assumed to be
filled up mostly by those living within the Hambantota District. However with more
specialised jobs starting off in later years, it was estimated that in-migration would be in
the ratio of 2 ½ times the number of such employe positions generated and filled.
Accordingly, the study assumed an in-migration of of 30,000, 130,000 and 230,000 at the
three forecast years as shown above.
Vehicle ownership over the 20 year period was assumed to increase from 9 vehicles per
100 persons to 23 vehicles per 100 persons. Due to the focus of attention of developing
Hambantota as a first order city, the economic development of Hambantota was
considered to reach a status of being second only to Colombo District and equal to the
developed parts of Gampaha and Kalutara District.
![Page 172: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/172.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-5
The diverted traffic has been estimated after examining how much increase in traffic will
occur when the proposed road network was added without any corresponding
socioeconomic development.
It was concluded that even for a stage wise development most of the road links show
LOS above “C” level even after 20 years. Thus a Stage-Construction was also
considered feasible without significant loss of benefits..
It was noted that at the provision of Stage 1 construction, there would be only three links
having more than 10,000 ADT in 2012. Those were the H001-020 and H002-030 links
which were both near Siribopura Junction and also A002-847 linkwhich was near the
Lewaya. By the year 2032, these flows were expected to reach over 30,000 ADT. By
2032, there would be 31 links (from a total of 67 links in the HDP road network) that
would have more than 10,000 ADT. The maximum flow of 62,000 AT can be expected
by year 2032 on the link A002-847 which was a short link of 380 m length.It was
observed that even by 2032 several of the roads will have traffic levels less than 10,000
ADT. Around 10% of the network length will have ADT over 20,000.
The BCA for the proposed development project had been carried out based on the
following assumptions:
A discounting rate of 12% per annum.
Inflation of financial costs for construction and for maintenance is assumed at 8%
per annum.
The economic value of the increase in benefits in terms of increasing income
levels will also be assumed to increase also at 8% per annum.
Maintenance cost for the road will be 0.5% of the replacement value at year 0
and this rate will increase at 10% per annum in real terms.
Design life of road will be for 20 years and rehabilitation at cost of 10% of
replacement values will be necessary at 10 years and rehabilitation at 30% of
value after 20 years.
The BCA analysis indicated that the immediate full development of the proposed road
network (Stage I and II together) will cost Rs 71.1 billion and will have an economic
return on investment of around 13.5% p.a. with a NPV of Rs 9,301 million at a
Discounting Rate of 12%, while its Benefit Cost Ratio would be1.14. Given that economic
![Page 173: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/173.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-6
cost of capital for this project might be significant this could not be considered a
favourable rate for a large scale highway project.
However, if it is constructed as a staged construction where only the roads identified in
Stage I costing Rs 45.7 billion are constructed in the first 3 years, and the others
constructed only after 10 years, then the economic performance improves significantly to
a Benefit-Cost Ratio of 1.87 with a NPV of Rs 54,626 million as 12% Discount Rate. In
this scenario, the design life of the project is assumed to be 40 years with a major
rehabilitation of Stage I roads carried out after 20 years in addition to an intermediate
improvement after 10 years.
Thus construction of the proposed network can be recommended on the following
conditions:
That the construction is staggered in two Stages with the first Stage being
completed over the next 3 years and the others delayed till 2020 at least.
The land required for the Stage II design to be acquired under the Stage I
and where possible to covnert to Green Areas until required for capacity
widening.
To re-examine the level of traffic by 2018 and examine which roads should
be improved to Stage II stage. This is to ensure that the assumed
development has taken place and there would be no loss in anticipated
benefits.
The cross sectional properties of the proposed roads have been considered for stage
developments, as Stage I and Stage II, for the purpose of cost effectiveness of the
investment plans.
The cross sectional properties of each road have been identified for facilities such as
number of lanes, service roads, walkways, bicycle lanes, shoulders, public transport
lanes, parking bays, centre medians, bus bays, landscaping and utility corridors,
depending on the potential demand by the proposed land use developments.
When selecting the cross sections, a higher emphasis had been given for providing
facilities for the non-motorised access and public transport use in Greater Hambantota
Area. Moreover, there are forty one (41) intersections included in this project proposal.
![Page 174: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/174.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-7
They belong to three (3) categories of intersection types proposed for Stage I and nine
(9) categories for Stage II.
There are two public transport routes identified as Route 1 and Route 2, the common
portion of these two routes which is from Siribopura-Gonnoruwa is the major
development axis the functions of which are:
To provide access to administrative and commercial buildings
To promote high density residential and employment centres and
To propose a high quality public transport corridor that later convertible to
BRT or LRT.
The study recommends that the above two routes be developed as a Superior Public
Transport Corridor mostly likely using Bus Rapid Transit Technology, a feasibility of
which should also be undertaken at a later stage. This will be the most important
investment toe ensure a high density development core in Hambantota for which the
Siribopura- Gonnoruwa Road section is the best candidate. Moroever, several transport
terminals have also been suggested to ensure good connectivity and balanced transport
within the region.
In addition six non-motorised routes mostly for pedestrian and bicycles have also been
identified. These are to promote people residing within short disctances of their working
places and school such as in the Adminsitrative Complex Areas to use non-motorised
transport.
The social assessment had been focused on evaluating the most likely impacts of the
proposed road hub over the socio-economic environment in the local and regional
economies. The likelihood impacts of the road construction and the development of
housing and other built-up infrastructure had also been analysed. The assigned field
team had made observations by walk-through surveys along the candidate roads and by
informal discussions with the community members residing in the immediate vicinity of
the roads.
This study dealt with the issues pertaining to the road safety arising from elephant
crossings of the proposed roads as well. This is considered as an important aspect since
roads are to be widened as well as operating speeds increased. The combination of
both attributes is expected to pose a formidable challenge to avoid vehicles from
crashing to elephants. At the request of wild life authorities underpasses have been
![Page 175: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/175.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
13-8
located for crossing of elephants and other wild life at four locations. Electric fences also
have been suggested in order to ensure that animals would not cross at random
locations. However, since these types of crossings have not been tested adequately in
Sri Lanka, further studies are recommended to determine suitability. Furthermore
another underpass has been provided for railway crossing on the Hambantota-
Gonnoruwa road.
It is concluded that the proposed road network would form a hub of interconnecting
roads that are connected to other roads in both local and regional levels. This network
will create socially and economically effective connectivity impacts in the area and
thereby in the entire country. This would offer direct and indirect benefit for people in
these administrative units through multiple roads.
![Page 176: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/176.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
ANNEX 1: PRELIMINARY FIELD OBSERVATIONS
![Page 177: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/177.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
Roads Observations
1. Outer Circular Highway This road is proposed as a new 4 lane road.
The selected trace follows a flat terrain of
bare lands connecting 3 major roads, ie.
CGHW Road, Hambantota Bypass Road and
Habantota-Meegahajandura-Gonnorouwa
Road. Also, the trace doesn’t interfere with
any natural barriers such as wildlife
reservations or irrigation structures/ tanks
etc.
2. Hambantota – Gonnoruwa –
Meegahajandura
The proposed Hambantota-Gonnoruwa-
Meegahajandura road is following the trace
of an existing road with disparate features.
The horizontal alignment of its first stretch up
to Bandagiriya Junction is more or less
straight and the RoW is 12m. However, the
vertical alignment has to be revised for
proper visibility. This stretch is located in a
fairly high ground with no water logging
areas and the surrounding area is mostly
uninhibited.
The stretch beyond Bandagiriya towards
Meegahajandura Junction follows a
meandering route and its RoW is 6.8m. This
stretch is located in a low-lying water logged
area and the surrounding area is mostly
inhibited.
Section between Hambantota – Gonnoruwa
View from the Hambantota Bypass Road
![Page 178: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/178.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
3. Sooriyawewa – Meegahajandura –
Kumaragama
The proposed road provides main accesses
for the Cricket Stadium, BOI and IT center
sites. It consists two physically diverse
stretches from Sooriyawewa to
Meegahajandura and Meegahajandura to
Kumaragama. The stretch from
Sooriyawewa to Meegahajandura has been
recently widened to 4 lanes but there are lots
of errors/ poor designs with regard to the
horizontal alignment.
The next stretch follows through a low-lying
agricultural area interfering with several
irrigation structures. The horizontal
alignment has to be improved in many areas
of this stretch. However, improvements might
be difficult due to the moderately denser
residential levels and the existing irrigation
structures.
4. Andarawewa – Udamattala –
Padawkema
The proposed trace for Andarawewa-
Udamattala-Padawkema Road deviates
intermittently from the existing road to have a
proper horizontal alignment. This will be the
major access road for the proposed Mattala
Airport that is under construction. The trace
is located through an inhibited agricultural
area where considerable amount of land
acquisition is necessary; for certain sections,
acquisitions would be for a new trace. Also
there are many existing irrigation
infrastructure along the trace.
5. Udawalawe – Thanamalwila The proposed Udawalawe – Thanamalwila
Road is the same road in use at present.
There are practical difficulties for major
improvements for some stretches as this
road follows the tank bund.
The bypass route via Udamadura and
Kiriibbanara would solve the above problem.
Section between Meegahajandura-
Kumaragama
Section between Udamattala- Padawkema
![Page 179: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/179.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
6. Moraketiya – Galwewa Junction The RoW of the existing Moraketiya –
Sooriyawewa road is around 6m over a
length of 12kms. This road spans through a
densely inhibited area when compare to the
other roads in the northern part of the
Hambantota District. More than half of its
length is located within the Uva Province.
Both horizontal and vertical alignments need
to be corrected at certain locations. Presently
a high frequency bus service is operating
along this road.
7. Hambantota By Pass Road The proposed road consists two distinct
sections; existing stretch for 7kms (up to the
Botanical Garden Junction) that requires
widening and construction of new stretch for
5km (from the Botanical Garden Junction to
Amabalantota). Existing road maintains a
RoW about 9m throughout its full stretch with
2 lane carriageway.
The proposed trace follows a flat terrain with
only a few residential areas. The stretch
between Botanical Garden Junction to
Siribopura Junction follows the Walawe
Development Lands. Presently inter-
provincial bus services are operating along
this road.
Existing Hambantota Bypass Road
Existing Moraketiya – Sooriyawewa Road
![Page 180: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/180.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
8. Road connecting the Sooriyawewa-
Mirrijjawela Road and Hambantota-
Gonnoruwa-Meegahajandura Road
The proposed road consist a stretch
requiring new construction for about 3 kms
and a stretch requiring widening for about
3.5 kms. New construction follows an
existing foot-path through the reserved
jungle while the widening is proposed for a
part of the Walawe Road connecting to 100ft
road. Walawe Road interferes with the
Walawe Development Area.
The relevant section of the Walawe Road
needs certain corrections for its horizontal
alignment. The proposed road trace follows a
flat terrain and there is no interfering with any
inhabitant areas. However the provisions for
wildlife movements need to be sets up
carefully during road design.
9. Bopale Junction - Kiribbanwewa The proposed road can be divided into 3
different sections based on existing surface
type. The first section has the RoW of just
5m over a length of 3 kms with a gravel
surface. Thereafter a 2km long concrete
section with its RoW of 5m and next to that is
a 4km long bituminous section with a RoW of
6.5 m. Considerable distance of this road is
located within the Uva province.
Full length of this road follows through
agricultural lands with some irrigational
structures on either side. A section of this
road is located on the Kiriibbanara Tank
bund. The surrounding of the last section is
moderately inhibited.
View of the Existing Foot-Path
Concrete Section of the Existing Road
![Page 181: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/181.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
10. Embilipitiya – Moraketiya –
Kiriibbanwewa – Udamadura
The proposed road is a renovation to an
existing road from Embilipitiya to Udamadura
via Moraketiya and Kiriibbanara. The road
has a RoW of 6.5m with a carriageway
varying between 4.5-5.0m through its total
length of about 17kms. It connects several
urban and suburban centers with moderately
dense residential areas. At present several
bus services are operating on this road.
The road is located on a fairly flat terrain.
However it requires correction of its
horizontal alignment at several locations.
Provisions for slow moving vehicles also
need to be set-up for better functionality of
this road.
11. Outer Circular Highway II This is a newly proposed trace that follows a
fairly flat terrain. The Western crescent of the
proposed road (or the stretch between
Hambantota By-pass road and Hambantota-
Gonnoruwa-Meegahajandura road)
interferes with a tank bund and low-lying
agricultural lands. Most of the lands had
been developed recently under Walawe Left
Bank project.
The Eastern crescent of the proposed road
follows a jungle area where many wild
animals including elephants are being
inhabited. As suggested by the wildlife
authorities, elephants are still crossing the
Hambantota-Gonnoruwa-Meegahajandura
road exactly on the proposed junction of
aforementioned two roads. Both sections
follow non-residential areas.
Starting Point of OCH II fromHambantota Bypass Road
Section between Moraketiya-Kiriibbanwewa
![Page 182: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/182.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
12. Udamattala – Thanamalwila The existing road is narrow and gravel
surfaced. At present it is not passable
through some stretches but it follows a flat
terrain for a length of 18kms approximately.
New construction has to be considered along
the existing gravel road.
This route is a part of old–famous cart-track
which transported salt from Hambantota to
Badulla. It follows an agriculturally developed
area and interfering with a number of
irrigation structures. The level of inhabitance
is moderately high and they are mostly
farmers.
13. CGHW Road (243-km – 260km)The existing CGHW road (between 243km-
260km) is a substandard two lane road with
approximately 10m RoW. Frequent short
and long distance bus services together with
other motor vehicles use this road.
This road follows a flat terrain and the road is
busy with roadside commercial activities
along certain stretches. Remaining plots
bedside the road are residential. Correction
of the horizontal alignment and
improvements of road safety are the current
requirements at certain stretches of the road.
14. Lewaya RoadLewaya Road has the same features of
CGHW road. Once it was the part of main
access towards Tissamaharama/
Weelawaya from Hambantotata.
Improvements for this road are also of the
same nature for CGHW road. However,
there are some areas where widening or
changes for alignment is difficult due to the
ponds of Lewaya.
Existing Gravel Road
![Page 183: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/183.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
15. Sooriyawewa – Padalangala RoadPresent 12km road from Padalangala to
Sooriyawewa has been developed as a
narrow two lane road with its RoW is about
11m. The road runs along a canal in its left
for almost 3/4th
of its total length leaving no
options for widening along that side.
Although its vertical alignment is satisfactory,
improvements are essential for its horizontal
alignment at several locations to ensure the
road safety. Passage for agricultural and
non-motorized vehicles need to be
considered during the design stage, as the
level of such is quite high. Road generally
follows an agricultural area with moderately
dense inhabitation.
16. Sooriyawewa – MirijjawilaThis road has substandard two lanes without
hard shoulders and comprises of a RoW of
100ft over a length of 24km approximately.
The existing horizontal and vertical
alignments are satisfactory with few
exceptions at certain locations.
The road mostly penetrates through
agricultural lands that have been developed
under Walawe Left Bank Project. Remaining
sections have moderately dense inhabitation.
17. Southern Expressway ExtensionConstruction not commenced yet
Existing Sooriyawewa – Mirijjawila Road
Existing Sooriyawewa – Padalangala Road
![Page 184: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/184.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
18. Road connecting the Walawe Left
Bank Road to Hambantota-
Gonnoruwa- Meegahajandura Road
The proposed development includes
widening of existing Walawe Road for 5km
and a new construction for the next 6km up
to Gonnaruwa Road. Existing Walawe road
follows Walwe Left Bank agricultural
developments while proposed new section to
follow the reserved forests and wildlife
zones.
The existing Walawe road requires
improvements for horizontal and vertical
alignment for the section under
consideration. However, there are no
obstructing irrigation structures along either
sides of the Proposed Walawe Road section.
Both sections generally follow flat terrains.
Western entrance of the Sea-Port can be
directly connected to the proposed Walawe
road through a properly designed
interchange close to the Hambanthota
bypass road. However, as the existing
Walawe road is heavily used by agricultural
and non-motorized vehicles, due attention is
required at the design stage for providing the
passage for freight vehicles along with the
agricultural and non-motorized vehicles.
19. Connection between A018 road and
Sooriyawewa- Mirrijjawela Road
(100ft. road)
This is a newly proposed trace over a length
of 10kms in the upstream of the Ridiyagama
Tank. It provides access to Safari Park that
is under construction now. The road trace
follows either agricultural lands or reserved
wildlife and forest areas but not through
many residential areas. Terrain is more or
less flat throughout the stretch.
Up-stream of Ridiyagma Tank
Existing Walawe Road
![Page 185: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/185.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
20. Lunugamvehera to KataragamaThe existing Lunugamwehera-Kataragama
road is an easy access for people from
Tanamalwila side to reach Kataragama.
With the development of roads such as
Andarawewa-Udamattala-Padawkema road
and Ranna-Wetiya-Andarawewa road, part
of the traffic can be diverted to that road if
there is a proper connection to Kataragama
from Padawkema. The proposed
improvement completes that route.
21. Internal Road Grid in The City AreaAt present, several hamlet roads that provide
access for the Tsunami housing schemes
connect the Gonnoruwa Road. However,
they are not properly established to form a
proper Grid Network. Most of these hamlet
roads are gravel surfaced except of the few
links that have been developed to operate
bus services via the housing scheme.
Proposed Grid Road Network will be
enveloped by the Outer Circular Road I.
Terrain condition is almost flat within the
area. Also UDA is planning to relocate the
housings and therefore acquisition of lands
for the road construction would be effortless.
There are no other archeological or structural
constraints within the area.
22. Ranna- Angunakolapelessa -Wetiya
Road
Ranna-Wetiya road via Angunakolapalassa
will be connected to the proposed Southern
Highway Extension between Ranna-
Angunakolapalassa. At present, this road
has been developed as a substandard two
lane road throughout its whole stretch.
The road follows an amalgam of sub-urban
and agricultural lands, which have
moderately dense hamlets. The terrain
condition is almost flat but it requires
improvements for horizontal alignment at
some stretches. Development of a bypass
road for Angunakolapalassa town area and
making provisions for slow moving vehicles
would enhance the performance of the link.
Existing Internal Road Connecting to
Gonnaruwa Road
Section of Wetiya- Angunakolapalassa
Road
![Page 186: FEASIBILITY STUDY FOR THE ROAD NETWORK FOR ......University of Moratuwa Road Network for Hambantota Development Plan i Table of Contents Volume I Final Report Study Team _____xi CHAPTER](https://reader034.vdocuments.net/reader034/viewer/2022042711/5f868df6deb5ab63e17ce2fc/html5/thumbnails/186.jpg)
University of Moratuwa Road Network for Hambantota Development Plan
ANNEX 2: LIST OF PARTICIPANTS FOR THE STAKEHOLDER
CONSULTATION PROGRAM
Date : 08th June 2010
Venue : District Secretariat Office-Hambantota
No Name Organization Designation
1 S. Kannamgodaarachchi Irrigation Department RDI
2 M.R Sudath RDA Senior Engineer
3 U.T Withana RDA Senior Engineer
4 H.U Dias Forest Department
5 Agil Hewageegana SLPA Chief Engineer
6 G. Withanage Airport & Aviation Chief Civil Engineer
7 W.P.K Chandrawansa UDA - Hambantota Dy. Director
8 R.M.D.B Meegasmulla District Secretariat District Secretary
9 I.Himali Rathnaweera District Secretariat Asst Dist. Secretary
10 G.G.C Samith Kumara C.E.B. Hambantota Area Electrical Engineer
11 A.Rajapaksha Director(Planning)
12 S. Bogahawatta C.E.B. PD(LSHD)
13 K.Paranawithana C.E.B Commercial Engineer
14 N.I.C Janaka Project Engineer
15 D.N. Siyamabalapitiya (Mrs.) RDA Deputy Planning Director
16 S.B Wijayakoon RDA Engineer
17 Dimuthu Fernando RDA Engineer
18 Prof. Amal S. Kumarage UoM Team Leader
19 S.N. Bentotage UOM/TLM Senior Lecturer
20 W.J Weerawardana UoM Project Co-ordinator
21 Dr. Tissa U.Liyanage UoM Highway Engineer
22 Dr. T. Sivakumar UoM Senior Lecturer
23 W. Sulani Madumini UDA Planning Assistant
24 P.G Mala Pathmakanthi UDA Planning Assistant
25 H.B.A Nayanananda RDA Chief Engineer
26 B. Kasturiarachchi RDA Engineer
27 P.M. Dharmathilaka
Dept Of Wildlife
Conservation Deputy Director
28 Wilson Ranawallige Forest Department
29 R.A Wanigatathna Perera MASL RPM
30 M.C Bandara SLPA ME
31 W.M.S Bandara U.D.A P/A
32 M.L.M Yehiya U.D.A P/O
33 S.A.S Dissanayake AASL Project Coordinator
34 S.H Udaya Kumara District Secretariat Assistant Director
35 J.K.P Rohini UDA Planning Assistant