feasibility study of gasification of biomass for … study of gasification of biomass for synthetic...

65
Feasibility study of gasification of biomass for synthetic natural gas (SNG) production Final report Presented to Energiforsk and Lund University, Faculty of Engineering, LTH May 29, 2015 Principal investigators Adam Eliasson, Johan Karstensson, Anders Kronander Tutors Hans T. Karlsson, Christian Hulteberg and Helena Svensson Disclaimer This project was carried out in the course “Feasibility Studies on Industrial Plants, (KET050)”, Department of Chemical Engineering, Faculty of Engineering, Lund University. This report was prepared in cooperation with Energiforsk. The report may not be reproduced without the written permission from the authors or Energiforsk.

Upload: dodien

Post on 17-Mar-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

Feasibility study of gasification of biomass for

synthetic natural gas (SNG) production

Final report

Presented to

Energiforsk and Lund University, Faculty of Engineering, LTH

May 29, 2015

Principal investigators

Adam Eliasson, Johan Karstensson, Anders Kronander

Tutors

Hans T. Karlsson, Christian Hulteberg and Helena Svensson

Disclaimer

This project was carried out in the course “Feasibility Studies on Industrial Plants, (KET050)”, Department of

Chemical Engineering, Faculty of Engineering, Lund University. This report was prepared in cooperation with

Energiforsk. The report may not be reproduced without the written permission from the authors or Energiforsk.

Page 2: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

Abstract

In this study, a production plant for Bio-Synthetic Natural Gas (Bio-SNG) from gasification of

biomass has been compiled. First, a literature review of possible utilities is presented followed

by a presentation of a process plant with necessary utilities. After the literature report, a brief

introduction regarding how the calculations were carried out is presented and followed by the

conclusions regarding process cost for the final product, SNG. The economy of a green field

erection was compared with an integrated SNG plant at an existing pulp and paper industry,

referred to as a brown field erection.

The calculations were partly carried out and integrated using Aspen Plus v8.2 as well as

MATLAB and Excel. The overall conclusion was that bark- SNG- and steam prices have a

significant influence on the economy evaluation. The brown field plant would benefit slightly

due to the knowledge of and the possibility to produce electricity from the high pressure steam

obtained from the exothermic reactions in the methanation step. However, with the base case

and today’s prices, the payback time is about 12 years based on the payback model, including

interest rate. This is a fairly good payback time for the investment. However, the calculations

are very sensitive to changes in prices, both in those of the products and in those of the biomass.

Thus it is still a risky investment considering a lifetime of 15-20 years.

Page 3: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

Contents

1. Introduction ........................................................................................................................... 1

2. Production of SNG from biomass ......................................................................................... 2

2.1. Pretreatment .................................................................................................................... 3

2.1.1. Hammer mill ............................................................................................................ 3

2.1.2. Drying of Biomass ................................................................................................... 4

2.2. Gasification .................................................................................................................... 6

2.3. Particle removal, purification and gas treatment ............................................................ 7

2.3.1. Particle removal ....................................................................................................... 7

2.3.2. Hydrogenation ......................................................................................................... 9

2.3.3. Water Gas Shift ....................................................................................................... 9

2.3.4. Hydrolysis ............................................................................................................. 10

2.3.5. Acid gas removal ................................................................................................... 10

2.3.6. Methanation ........................................................................................................... 12

2.3.7. Gas upgrade ........................................................................................................... 15

2.4. Desulfurization of flue gas leaving combustion chamber ............................................ 16

3. Overall process .................................................................................................................... 17

4. Discussion literature review ................................................................................................ 21

5. Method for cost estimates .................................................................................................... 22

5.1. Operating costs ............................................................................................................. 22

5.2. Capital costs ................................................................................................................. 22

6. Economical evaluation ........................................................................................................ 23

7. Discussion ........................................................................................................................... 27

8. Conclusions ......................................................................................................................... 29

9. References ........................................................................................................................... 30

Appendix A Calculations ..................................................................................................... 33

Appendix B Economy Summary ......................................................................................... 48

Appendix C Aspen flowsheet .............................................................................................. 58

Appendix D MATLAB SCRIPT .......................................................................................... 60

Page 4: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

1

1. Introduction

A high energy security with a continuously accessible supply of energy is vital for all countries.

With decreasing levels of fossil fuel reserves combined with military conflicts and increased

fuel prices, there is a strong ambition for many countries to replace the use of fossil fuels with

sustainable, renewable resources1. As Sweden has a net import of 100 % of its natural gas, the

energy demand is strongly dependent of our neighbors2. Biomass gasification would therefore

increase energy security and at the same time, decrease the risk of climate change.

The capacity of large-scale production of substitute natural gas, SNG, from biomass

gasification, could help increase the amount of renewable resources, especially in electricity

production. The processes are quite simple and there are several ways of converting biomass to

SNG. Also, there is a large pallet of available resources to be used. As natural gas is the world’s

third most important energy source, covering about 21 % of the world’s total primary energy

usage, the infrastructure is well developed and can be used for SNG3. Furthermore, the use of

natural gas is believed to increase, as can be seen in figure 1. In Europe, most natural gas is

used for heat and power generation plants. However, IEA estimates that about 30 % of the

transport fuel can be covered by biofuels in 20504.

Figure 1. Natural gas usage on a global level5.

In figure 2, the total Swedish transport energy demand is visualized. With a total energy demand

of about 122 TWh of which biogas from fermentation accounts for 0.6 TWh. In 2010 there is a

strong need to increase the amount of renewable resources in this sector to reach a more

sustainable transport sector. According to recent studies, the introduction of Bio-SNG together

with an increased amount of biogas from fermentation, up to 70 TWh could be achieved6. This

would account for about 57 % of the total energy usage in the transport sector, which thereby

could be covered by renewable resources6.

Page 5: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

2

Figure 2. Current- and potential methane production compared with the total energy consumption of the transport

sector in Sweden6.

This project compares a production plant for SNG which is integrated into an existing pulp mill

against a green field erection. An economic evaluation and comparison between the two is

performed and discussed to determine which one that would be the cheapest one to construct.

A broad investigation regarding potential synergies at integration with existing infrastructure

will be compared to a green field installation. The project will render a suggested process design

capable of receiving 200 MWth input of biomass.

The goal for this study is to design and evaluate economic aspects of a production plant for

Bio-SNG through gasification. A decision will be made whether the production plant should be

built as an integrated process, a green field erection or if it should be built at all. The integrated

process will be connected into an existing pulp mill located in Värö, outside Varberg, Sweden.

The feedstock for this case consists of residues from the pulp mill, most of which is bark.

Certain limitations have been set in this project. As mentioned before, there are several different

sorts of feedstock that could be used. However, in this project, only bark have been investigated.

This project was based on the considerable input of 200 MWth. Therefore, small size processes

and laboratory scale gasifiers have not been taken into account.

2. Production of SNG from biomass

A general process setup for the production of Bio-SNG is visualized in the box scheme seen in

figure 4. The biomass is transported to the process by train or heavy vehicles. Pretreatment

consists of drying the biomass as well as grinding it to the necessary size before it enters the

gasifier. The gasifier generates producer gas that has to be cleaned downstream in the process.

The total process releases a lot of excess heat which could be used to satisfy heat demands in

other utilities in the process or eventually even district heating. By cleaning the combustion

flue gas, gypsum will be obtained as a byproduct. In the best case, this gypsum could be sold

to increase the revenue. However, gypsum is very cheap and will be treated as a byproduct of

no value (might actually become a smaller cost).

Page 6: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

3

Figure 4. Box scheme over the bio-SNG production.

The gas that leaves the methane step of figure 4 consists of methane, carbon dioxide and water

and some trace elements of nitrogen, hydrogen and carbon monoxide. Before the gas can be

injected into the gas grid, it has to fulfill certain quality requirements which have been set by

the European Association for the Streamlining of Energy Exchange - gas (EASEE-gas). These

quality requirements are listed in table 1. Therefore, additional upgrading of the gas might be

necessary to increase pressure, increase energy density (adding propene) or to decrease the

amount of water or other components in the gas.

There are several gas quality requirements that the gas has to fulfill before it’s injected to the

gas grid. The requirements that have to be met can be seen in table 1.

Table 1. Gas quality requirements from European Association for the Streamlining of Energy Exchange – gas

[EASEE-gas, 2005].

Parameter Unit Min Max

Wobbeindedx (WI)a kWh/m3 13.60 15.81

Relative Density RDb m3 /m3 0.555 0.70

Total sulfur mg/m3 - 30

H2S + COS mg/m3 - 5

Mercaptans mg/m3 - 6

Oxygen mol-% - 0.001

Carbon Dioxide mol-% - 2.5

Water Dewpoint ˚C at 70 bar - -8

Hydrocarbon Dewpoint ˚C at 70 bar - -2 aThe Wobbe Index WI is defined as the higher heating value divided by the square root of the relative density RD b The relative density RD is defined as the gas density in relation to the density of air at standard conditions (0˚C,

1.01325 bar)

2.1. Pretreatment

Storage will be needed for quicklime, water, carbon dioxide and for gypsum. These storages

have an influence on the economy as they require investments and large areal. At Värö, there

are no unused silos or storages that could potentially be used. This would have been very

valuable as no investments had to be considered regarding the storage. The storage utilities

have not been presented in the process sheet above but will be taken into account in the

economy analysis for the process calculations.

2.1.1. Hammer mill

To reach the highest conversion of biomass to SNG, a uniform particle size of the bark is

necessary. This is due to that they will have the same residue time inside the gasifier. Therefore,

the bark has to be grinded before entering the gasifier as well as the drying utilities. There are

many different grinders that can produce the necessary size, and the economy aspect is

important. In this case, a hammer mill is installed to reach a particle size of about 30 mm.

Different sizes required for the different types of gasifiers are listed in table 2 below.

Page 7: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

4

Table 2. Different particle size required for different gasifiers [Bio-SNG from Thermal Gasification – Process

synthesis, Integration and Performance].

Fixed bed Fluidised bed Entrained Flow

Input particle size [mm] 10-300 <50 <0.1

2.1.2. Drying of Biomass

As the bark contains a lot of water (up to 50 wt-%7), it has to be dried in order to obtain a high

energy value. Considerable amounts of energy would otherwise be used to evaporate water

inside the gasifier and the temperature would not rise as high compared to dry biomass. The

efficiency of the gasifier is generally increased significantly with lower moisture content of the

biomass, but is rarely dried below 10 wt-% due to economic considerations7. The biological

degradation (microbial degradation) of the fuel is also lower after the water levels have been

decreased and therefore it can be stored for a longer period of time8. As much as 2.5-3 % of the

biomass dry matter can be degraded due to biological degradation if it is kept at 35 wt-%

moisture level9. The degradation of dry matter is strongly dependent on storage time and what

sort of biomass that’s being used. The drying process could be built with three different

techniques;

Low-temperature air drying

Drying using steam

Flue gas drying

Drying demands energy which is supplied as electricity (blowing the hot gases with turbines

and rotation of biomass thus exposing it to the warm air) and as heat. There are four different

specific factors that has to be taken into account:

Evaporation enthalpy (most important; about 2650 kJ/kg H2O)

Heating of the biomass and the air

Heating of the drying ware

Heat losses to the surroundings

The biggest energy demand is supplied to evaporate water, about 2650 kJ/kg H2O. Hot air has

a higher solubility of water compared to cold air. Therefore, a smaller volumetric amount of air

is needed if the air is preheated. This leads to lower electricity costs for the fans that draw air

from outside. There are patented solutions as Mabarex Dry-RexTM that are designed to fit drying

of bark. According to Mabarex the temperature of the air has to be about 30-90°C which is

considered as excess heat.

Problems associated with biomass drying is emission of volatile organic compounds (VOC).

High temperature in the dryer leads to higher emissions and flue gases might contain impurities

which have to be treated10. Lower temperatures lead to lower emissions and lower temperatures

could be achieved by using excess heat that can’t be used anywhere else. This makes it very

attractive from a design perspective so that as little as possible of the excess heat goes unused.

These low- temperature drying systems have an energy demand of just above 2700 kJ/kg H2O

with a heat source of 80°C11. Figure 5 shows a basic flow chart for bark drying.

Page 8: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

5

Figure 5. Basic flow chart of drying of bark.

In figure 6 below an example of a fluidized bed dryer is visualized.

Figure 6. Example of fluidized bed dryer12. Hot air is fed in the bottom and introduced to the biomass through small

holes in the bottom and removed as wet gas.

Air is first pre-heated in a heat exchanger with flue gases leaving the combustion chamber. The

air reaches a temperature of 30-90˚C after which the drying begins. As the drying begins, the

temperature of the air is decreased due to the evaporation of the moisture inside the biomass. If

the temperature of the air increases, the solubility of water in air increases. This will have an

impact on the amount of air that is necessary to reach a certain moisture level as visualized in

figure 7.

Page 9: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

6

Figure 7. Amount (kg) of dry air necessary to evaporate one kilogram water as a function of dry air temperature.

Higher temperatures give much lower amounts of air needed9.

2.2. Gasification

After drying, the biomass is fed to the gasifier which is the major conversion step in the process.

Inside the gasifier, the remaining water (moisture) is evaporated and the biomass is converted

by pyrolysis into a char as well as gas. The chemical reactions that occur in the gasification is

seen below.

→ 𝑐ℎ𝑎𝑟 + 𝑡𝑎𝑟𝑠 + 𝐶𝑂2 +𝐻2𝑂 + 𝐶𝐻4 + 𝐶𝑂 + 𝐻2 + NH3 + (𝐶2 − 𝐶3) + 𝑖𝑚𝑝𝑢𝑟𝑖𝑡𝑖𝑒𝑠 (R1)

𝐶 +1

2𝑂2 → 𝐶𝑂 Δ𝐻𝑟

298 𝐾 = −109 𝐾𝐽/𝑚𝑜𝑙 (partial oxidation) (R2)

𝐶 + 𝐶𝑂2 → 2𝐶𝑂 Δ𝐻𝑟298 𝐾 = +172 𝐾𝐽/𝑚𝑜𝑙 (reversed Boudouard) (R3)

𝐶 + 𝐻2𝑂 → 𝐶𝑂 + 𝐻2 Δ𝐻𝑟298 𝐾 = +131 𝐾𝐽/𝑚𝑜𝑙 (steam gasification) (R4)

𝐶𝐻4 +𝐻2𝑂 → 𝐶𝑂 + 3𝐻2 Δ𝐻𝑟298 𝐾 = +159 𝐾𝐽/𝑚𝑜𝑙 (steam reforming) (R5)

𝐶𝑂 + 𝐻2𝑂 → 𝐶𝑂2 +𝐻2 Δ𝐻𝑟298 𝐾 = −42 𝐾𝐽/𝑚𝑜𝑙 (water-gas shift) (R6)

R1 and R2 represent pyrolysis while R2-R6 are gasification reactions.

The overall function of the gasifier can be seen in figure 8. The technology represents an

indirect gasification and are based on indirect fluidized bed technology with <50 mm required

particle size (table 2). Biomass is fed into the riser (1) and steam (or air, if nitrogen dilution of

the producer gas is not a problem) is fed to the bottom. The gasifier consists of a fluidized bed

which is comprised of sand and/or olivine. The particle size of the bed medium is 0.2 mm to

0.3 mm. The particles of the bed medium heat the biomass to about 850°C and the biomass are

to some extent converted to gas which creates an updraft in the riser. In the riser, pyrolysis takes

place. Larger solids, such as bed material and biomass pieces and char, falls back down into the

down comers.

Page 10: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

7

In the combustion zone, particles such as char (which is carbon that have not been converted

into gas), tar and dust, burns at high temperature with air and heats the bed material to about

925°C.13 The combustor is typically operated at an air to fuel ratio of 1.2514. Flue gas leaves the

reactor and is further mixed with air and cooled. This technology’s name is Multipurpose

Integrated Lab-unit for Explorative and iNovative Achievements, called MILENA, and is

developed by Energy research Centre of the Netherlands, ECN.

Figure 8. Schematic overview of MILENA gasifier15.

Olivine as bed material show positive results regarding tar reduction in the producer gas and

also promotes the production of H2 in the CO shift reactions16.The loss of bed material is taken

care of by adding fresh bed material to the combustor continuously and therefore maintaining

the amounts necessary in the combustor. Low gasification temperatures gives a high yield of

methane but the lowest temperature limit (before the yield of methane is heavily decreased) is

about 750°C16. The producer gas consists mainly of carbon monoxide, hydrogen, carbon

dioxide, methane and water vapor. There are some trace components which have to be dealt

with prior to synthesizing methane. These components consist of particulate matter (ash and

bed particles), unsaturated hydrocarbons, tars and chars, sulfur, nitrogen compounds and alkali

metals. There are solutions to decrease the production of tars inside the gasifier by using

catalytic bed materials as mentioned before. However, post-gasification producer gas cleaning

technologies are mostly used16. Sulfur compounds that are present in the producer gas will

damage downstream catalysts and have to be reduced to well below 1 ppm.17

2.3. Particle removal, purification and gas treatment

2.3.1. Particle removal

The produced gas from the gasifier must be purified in several stages. This is due to that they

are corrosive for the system, harmful to the environment and their fouling in downstream heat

exchangers. Tars, both heavy and light tars, as well as cleaning of the gas from sulfur and

chloride is needed. Tars and heterocyclics are initially removed from a cleaning station of some

Page 11: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

8

kind consisting of several stages which could be based by oil, water or another media. The one

used in this project is called OLGA and can be seen in figure 9. These OLGA utilities are

followed by the removal of the remaining unwanted substances.

Tars can be explained as very complex heterogeneous aqueous mixtures of organic molecules

(aromatics, phenols, bases, asphaltenes, preasphaltenes, and particulate matter) in a broad range

of concentrations related to the formation conditions (temperature, residence time pressure,

feedstock, reactor design). It can be divided into four sections: primary products, secondary

products, alkyl tertiary products and condensed tertiary products18.

The producer gas leaving MILENA is cooled down to 400°C (which is above the dew point of

the tar in the gas19) with a heat exchanger. The OLGA system consists of three stages which are

collector, absorber and stripper, all using liquid oil as working media. The first stage is the

collector that condenses heavy tars from the producer gas and also removes most of the

remaining dust (dust that did not get caught in the cyclone) with scrubbing oil. The second stage

handles removal of fine dust and entrained oil aerosols using a wet electrostatic precipitator (w-

esp). To the first scrubber through a separator heavy tars are condensed by the cooled scrubbing

oil. Once the remains are separated from the scrubbing oil it’s led back into the MILENA as

recycled feedstock together with the remains from the stripper20. In the third stage the absorber

removes light tars with scrubbing oil which is operated above the dew point of water to avoid

mixing of tars and water. The temperature of the liquid scrubbing feed in the absorber controls

the outlet temperature of OLGA, which is about 60-80°C21. The stripper, operated with air at

180°C, is regenerating the scrubbing oil used in the absorber.

OLGA gas cleaning system is developed ECN, and compudised by Dahlman industrial group

and is chosen because it generates a product with least unwanted compounds. The product gas

will be totally clean from heavy tars and light tars but contains about 1 % of heterocyclics. Also,

the dew point is well below 20°C, which is a lot higher for other systems. With low dew point

there is no tar condensation and fouling so the gas is applicable without any risk further in the

process.22

Figure 9. Simplified process flow diagram for OLGA cleaning system22.

Page 12: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

9

The gas leaving the OLGA gas cleaning system is free of tars and dust. However, to guarantee

this a hot gas filter is installed downstream of the OLGA as seen in figure 10. Depending on

the size the filter contains different amounts of sintered metal fiber candles.

Figure 10. Hot gas filter21.

2.3.2. Hydrogenation

The gas stream out of OLGA contains small amounts of olefins, unsaturated hydrocarbons with

double c-c bonds, are created during the gasification. Without any removal of olefins it will

continue to be created and generate long chains of polyethylene and polypropylene etc. which

could be of major trouble inside the system. The olefins are removed by hydrogenation which

will saturate the double bonds of the hydrocarbons and form ethane and propane. This is done

with hydrogen in presence of a metal catalyst, often platinum or palladium, at about 150-200°C.

The reaction for ethylene to ethane is seen in reaction (1) below.23

𝐻2𝐶 = 𝐶𝐻2 +𝐻2𝑃𝑡, 𝑃𝑑→ 𝐻3𝐶 − 𝐶𝐻3 𝛥𝐻298

0 = −134 𝑘𝐽/𝑚𝑜𝑙 (1)

2.3.3. Water Gas Shift

To meet downstream process requirements, where the ratio of hydrogen to carbon monoxide

into the methanation step has to be as close as possible to 3. This is to receive a high conversion

of methane in the process. By using a reaction step called water gas shift (WGS), consisting of

one reactor with catalyst. In this reactor syngas will pass through a fixed-bed of catalyst where

CO and water is converted to H2 and CO2 according to the WGS reaction (2).

𝐶𝑂 +𝐻2𝑂 ↔ 𝐻2 + 𝐶𝑂2 𝛥𝐻2980 = −41 𝑘𝐽/𝑚𝑜𝑙 (2)

The reaction, depending on the catalysts, operates between 200°C and 500°C. The pressure

dependents for the reaction are small due to the stationary total mole. High moisture content

and low temperatures favor the right side of the reaction. The existing moisture from the

scrubber upstream is normally enough to drive the reaction to the decried ratio. To avoid

exceeding the H2-to-CO ratio a bypass stream of syngas may be needed.

Page 13: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

10

The WGS reactor can be placed both before (sour shift) and after the sulfur removal step (sweet

shift). In this case it is crucial to the downstream process that the carbon dioxide is held to a

minimum. Therefore the sour shift is preferable. Another benefit with this placement of the

reactor is that the reactor will hydrate carbonyl sulfate (COS) and other organic sulfur to

hydrogen sulfide (H2S). This will allow the reactor for hydrolysis of COS to be smaller because

it only has to take care of the bypass stream. Sour shift uses a cobalt-molybdenum catalyst. To

avoid getting liquid water in the shift reaction and damaging the catalyst the syngas is heated

to about 20°C above the saturation temperature. After the shift the gas flow is cooled by

generating low pressure steam before entering the acid gas removal system for removal of

H2S.24

2.3.4. Hydrolysis

Most of the sulfur in the biomass is converted to H2S in the gasifier. However, some of it, about

3 % to 10 %, forms a carbon-sulfide component (COS). In the sulfur removal step the COS will

not be efficiently separated, so to remove enough COS to reach the expectable concentration

for the product of SNG, a hydrolysis step will be needed. COS is converted to H2S by reaction

(3).

𝐶𝑂𝑆 + 𝐻2𝑂 ↔ 𝐻2𝑆 + 𝐶𝑂2 𝛥𝐻2980 = −34 𝑘𝐽/𝑚𝑜𝑙 (3)

𝐶𝑆2 + 2𝐻2𝑂 ↔ 2𝐻2𝑆 + 𝐶𝑂2 𝛥𝐻2980 = −20 𝑘𝐽/𝑚𝑜𝑙 (4)

2𝑅𝑆𝐻 + 2𝐻2𝑂 ↔ 2𝑅𝐻 + 2𝐻2𝑆 + 𝐶𝑂2 (5)

As mentioned earlier the sour WGS will work as a hydrolysis step for the COS and an additional

reactor will only be needed for the by-pass stream passing the WGS-reactor. To avoid getting

liquid water in the reaction and damaging the catalyst the syngas is heated to about 20°C above

the saturation temperature. An activated alumina-based catalyst is used in the COS hydrolysis

and usually operates at a temperature of 175-200°C. The pressure dependents for the reaction

are small due to the stationary total mole. Because of the reaction’s exothermic nature the

conversion of COS is favored at a low temperature. The temperature is however almost constant

throughout the reactor due to the large amount of non-reacting components in the stream.

After the hydrolysis, the gas stream is cooled by generating low pressure steam before entering

the acid gas removal.25 26

2.3.5. Acid gas removal

Within production of SNG in connection with gasification some CO2 will form. The biomass,

bark in this case, contains low amounts of sulfur and chloride but still needs purification from

the product gas out of OLGA. About 90 % of the sulfur content out of OLGA converts into H2S

and 10 % into COS. Low concentrations of HCl, below 5 ppm follows within the raw producer

gas. The chloride is removed from the gas together with the ash.

There are two widely used methods for sulfur removal. One is by adsorption of sulfur on zinc

oxide (ZnO) and the other is amine absorption. An equilibrium reaction for the ZnO absorption

technique removal is seen in reaction (6). ZnO can be used as sorbent for removal of both H2S

and COS. Volatile compounds from reacted zinc with halogens might occur and these need to

be removed by a secondary guard bed. The most common technique for this is using activated

Page 14: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

11

aluminum oxide, alumina27. 100 ppb as inlet concentration is acceptable according to

litterature29. An equilibrium reaction for the sulfur removal is seen in reaction (6).

𝑍𝑛𝑂 + 𝐻2𝑆 ↔ 𝑍𝑛𝑆 + 𝐻2𝑂 Δ𝐻2980 = −78 𝑘𝐽/𝑚𝑜𝑙 (6)

ZnO was used as sorbent, which can remove both H2S and COS, for the bulk removal of sulfur.

Remaining H2S is removed via a guard bed at 160°C and is also used for the removal of HCl.

Higher temperatures generate more volatile zinc compounds.27

The other widely used method for sulfur removal is the one implemented in this process. It

removes CO2 and H2S with amine absorption, which can be seen in figure 11. The absorption

system contains two large columns, one absorber and one stripper. The producer gas is fed into

the absorber via the bottom, while regenerated amine solution enters at the top. H2S and CO2

are absorbed into the amine solvent. When the absorption is done, the loaded amine solution is

preheated with the lean alkanolamine solution from the stripper and fed to the stripper. After

the acid gases has passed through the stripper, they are removed with steam generated in the

reboiler. This is fed to the condenser and later returns back into the regeneration column.

Figure 11. Flow scheme over removal of H2S by amine absorption28.

The amine absorption is performed with methyldiethanolamine with an additive of piperazine,

MDEA-PZ, because of the low energy demand for the regeneration compared to other amines

listed in table 3 below28. This is due to weaker bonds between CO2-amine for MDEA. It also

doesn’t form corrosive compounds so the additives, like piperazine, are mostly for

improvement of the mass transfer rate. Monoethanolamine, MEA, and diethanolamine, DEA,

have higher mass transfer rates but requires a lot more energy for the regeneration. A

comparison is seen in table 3. The reaction formula between CO2 and MDEA is seen below.

𝐻2𝑂(𝑙) + 𝐶𝑂2(𝑎𝑞) + 𝑀𝐷𝐸𝐴(𝑎𝑞) ↔ 𝐻𝑀𝐷𝐸𝐴+ +𝐻𝐶𝑂3−(𝑎𝑞)

Table 3. Concentrations over the solvents and energy requirements for removal of CO228.

Page 15: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

12

Removal system Amine concentration (wt-%) Energy requirement [GJ/mol CO2]

MEA 15-20 210

MDEA-PZ 40-55 40-60

2.3.6. Methanation

In order to obtain a composition of gas that reaches the standards for natural gas the content of

methane has to be increased. To reach the required composition, a methanation stage is

required. This catalytic synthetic production of methane from hydrogen and carbon monoxide

is described by the CO methanation reaction (7):

𝐶𝑂 + 3𝐻2 → 𝐶𝐻4 +𝐻2𝑂 Δ𝐻2980 = −206 𝑘𝐽/𝑚𝑜𝑙 (7)

It’s also possible to convert carbon dioxide to methane as in the following reaction (8):

𝐶𝑂2 + 4𝐻2 → 𝐶𝐻4 + 2𝐻2𝑂 Δ𝐻2980 = −165 𝑘𝐽/𝑚𝑜𝑙 (8)

To get the right ratio of the components in to the methanation stage the WGS reaction is used

upstream the process.

Both reactions (7) and (8) are very exothermic and it requires low temperatures and high

pressures to get a high yield of methane.29

Technologies for methanation can be classified into two main categories: fixed bed and

fluidized bed. There are several different types of technologies in both categories. One of the

fixed bed technologies is Topsoe’s Recycle Energy-efficient Methanation Process, called

TREMP™30. Through figure 12 the TREMPTM is visualized.

Page 16: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

13

700˚CR1

600˚CR2

400˚CR3

HE 13

HE 14

HE 16

HE 17

HE 18

HE 12

Compressor

Condensate

SNG to GRID

Compressor

250-300˚CR4

HE 20

HE 15

HE 19

Figure 12. Simplified process flow diagram for TREMP™ methanation.

The TREMP™ process is developed by Haldor Topsoe. This process converts CO and H2 with

a ratio of 3/1 into methane. The reaction that occurs is manly reaction 7. TREMP™ has a

chemical efficiency of about 80 % and produces a product with up to 98 % methane. The system

uses three or four adiabatic reactors with recycle and intermediate cooling. The temperature in

the first reactor is controlled by changing the reflux ratio. The concentration of reactants in the

stream entering the first reactor is controlled by recirculate parts of the stream leaving it. This

results in a lower temperature in the reactor. The catalyst is able to work in an interval between

250-700°C.

One of the advantages with this process is that, due to the MCR-2X methanation catalyst,

TREMP™ can run at fairly high temperatures, up to 700°C and therefore it’s possible to recover

a lot of the exothermic heat as high pressure steam, illustrated in figure 13. The high

temperature also makes it possible to lower the amount of methane that has to be recycled in

the process. Most catalysts used in methanation are ceramic based with nickel crystals as the

active part. The same goes for the MCR-2X.Any recycle involves a loss of energy but the MCR-

2X catalyst is a good choice to minimize the need for that, resulting in a more energy efficient

system and lower equipment costs. The high purity of methane in the product is compatible

with the specification for pipelines, ensuring easy distribution of the product.31

Page 17: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

14

Figure 13. Illustration of the use of the excess heat31.

Before the TREMP™ the process is designed so that the feed in to the TREMP™ provides a

1:3 ratio of carbon monoxide and hydrogen according to the methanation reaction (Eq1). Figure

14 show how the composition of the gas from the TREMP™ varies with the value of the module

(M) As can be seen in the figure 14 it is important to get the module as close to 3 as possible to

get a high yield of methane in the product.

𝑀 =𝑋𝐻2,𝑓𝑒𝑒𝑑−𝑋𝐶𝑂2,𝑓𝑒𝑒𝑑

𝑋𝐶𝑂,𝑓𝑒𝑒𝑑+𝑋𝐶𝑂2,𝑓𝑒𝑒𝑑 𝐸𝑞(1)

Figure 14. Illustration of how the how the gas composition varies with the module31.

To change the ratio between CO and H2 the WGS reaction is used upstream to the methanation

stage. The module of the inlet gas is adjusted by controlling the by-pass around the WGS stage.

The gas that leaves the first reactor is cooled in two stages, the first will heat a super-heated

steam stream and the second one will cool it to the temperature wanted at the inlet of reactor

two (200-250°C). As can be seen in figure 15, low temperatures favor a high yeild of methane.

To get a high yeild it’s reqiured to use a series of methanation steps.

Page 18: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

15

In TREMP™ the first reactor will operate close to the maximum allowed temperature for the

catalys (700°C). To operate at that temperature the stream into the first reactor should contain

about 20 % methane. The following steps the temperature will be decreased to get the yields

required. For 98 % methane for reactors will be needed. The last reactor will operate at 200-

300°C. Before the last reactor water will be separated from the gas stream to drive reaction 7

to the right.31

Figure 15. Illustrates the change in mol-% for methane over the reactors31.

The syngas composition will vary depending on what biomass that has been used in the process

and on the properties of the plants design parameters and conditions. In table 4 an example is

shown. In this case the amount of methane into the methanation was 15 mol-%.

The methanation was performed in four reactors at a product pressure of 2.4 MPa.31

Table 4. Example composition of the syngas leaving the TREMP™.

Substance Typical

composition

CH4 97.93 %

CO2 0.16 %

H2 1.36 %

N2 + Ar 0.53 %

CO 11 ppm

2.3.7. Gas upgrade

As the gas leaving the methanation step is a mixture of methane, carbon dioxide, water and

small amounts of trace elements such as nitrogen, hydrogen and carbon monoxide. It might

have to be upgraded before it enters the gas grid. However, the output concentration from the

methanation will be known first after the process has been fully simulated. If there is too much

carbon dioxide and moisture – an upgrading step will be installed and investigated to fit the

European Union standard requirements of natural gas (EASEE-gas, 2005). If the gas has to be

upgraded, the most important part is to remove carbon dioxide. This is a process which demands

a lot of energy and further investment costs.

Further upgrading of the gas consists of adding propane gas which will increase the energy

density necessary to reach the Wobbe Index (WI).

Page 19: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

16

2.4. Desulfurization of flue gas leaving combustion chamber

As SO2 emissions cause detrimental impacts on human health, it has to be removed from the

flue gas leaving the combustion chamber which is connected to the gasifier before it is released

to the atmosphere through a chimney. Flue gas desulfurization also decreases the problematic

acid rain which is part of the Acid Rain SO2 Reduction Program32. Another benefit from

cleaning SO2 is the decreased amount of aerosols in the atmosphere and there are also

regulations regarding SO2 emissions that has to be fulfilled.

Flue gas desulfurization (FGD) is usually based on an alkaline reagent such as calcium or

sodium. The alkaline reagent is injected to the flue gas using a spray tower. The SO2 binds to

the reagent and creates a solid compound, calcium or sodium sulfate. There are two separate

main processes called “once-through” or “regenerable”. Regenerable systems reuse the solids

generated from the process and once-through processes dispose the solids as waste. Available

technologies are wet-, semi-dry and dry systems.

In dry systems, dry sorbent is injected into the furnace. This requires very high flue gas

temperatures ranging between 950-1000°C which is higher than the obtained flue gas

temperature in the MILENA technology where a maximum of 850°C is reached33. Therefore

the dry system cannot be used in this case.

In wet systems the flue gas is put into contact with a solution containing the sorbent. The gas

becomes saturated with water due to the water content in the slurry. The SO2 in the flue gas

reacts with the alkaline reagents in the slurry, creating calcium sulfate solid particles. These

particles are collected at the bottom of the absorber and collected. If the slurry is then oxidized,

gypsum scale is formed.

Semi-Dry systems injects a higher concentration of the alkaline reagent into the flue gas by

using spray dryers. Most of the water in the slurry is evaporated creating a dry excess product

which can be removed from the flue gas using a particulate matter (PM) collection device such

as an ESP. About 10-15°C below saturation temperature is the optimum temperature for semi-

dry spray dryers33.

About 85 % of all flue gas desulfurization (FGD) systems are based on wet systems34. Different

technologies have efficiencies in the range from 50-90 %. 90 % efficiency is reached when

using wet scrubbers. Typical temperatures for wet scrubbers are 150-370°C35 and therefore, the

flue gas from the combustion chamber has to be cooled using a heat exchanger before the

scrubber. As there is a potential pressure drop across the absorber, an additional induced draft

(ID) fan may be required. The reactions that occurs in the absorber can be summarized by:

𝑆𝑂2 + 𝐶𝑎𝐶𝑂3 +1

2𝐻2𝑂 → 𝐶𝑎𝑆𝑂3 ∙

1

2𝐻2𝑂 + 𝐶𝑂2 (10)

𝑆𝑂2 +1

2𝑂2 + 𝐶𝑎𝐶𝑂3 + 2𝐻2𝑂 → 𝐶𝑎𝑆𝑂4 ∙ 2𝐻2𝑂 + 𝐶𝑂2 (11)

The required amount of limestone in wet FGD systems is about 1 mole of CaCO3 per mole

SO2.36 Process variables include flue gas flow rate, SO2 concentration, liquid-to-gas ratio (L/G),

pH and retention time. Retention time is about 12-16 hours.

Page 20: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

17

The chosen process used for flue gas desulfurization FGD is based on a wet system. Quicklime

is crushed using a Ball Mill into a fine powder with desired particle size. It is then mixed with

water in a feed tank. The flue gas is then mixed with the aqueous solution and the calcium

sulfate is collected at the bottom. In figure 16 the flue gas is inserted at the top of the spray

tower which is not the general case. In general, the flue gas flows upwards and the water is

sprayed downwards. An ESP device is used as particulate matter collector and the solid particles

is collected at the bottom and disposed of.

Figure 16. Typical process sheet of a wet FGD system using lime.

3. Overall process

Based on the above necessary utilities, a possible process scheme is presented below. The final

set up will have a high redundancy, meaning that some of the components (pumps, compressors

and heat exchangers) will have a double setup to ensure safety. In figure 17, a scheme over the

complete proposed process setup is presented. Table 5 below shows what every step of the

process changes. This is an overall simplified scheme that covers the idea of every unit

operation.

Page 21: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

18

Table 5. Composition through the process. 1 represents that the component is present and 0 that it has been removed.

0.5 is somewhere in between meaning that the utility will remove part of the component in the gas.

MILENA CYCLONE OLGA Hydrogenation Hydrolysis/WGS Acid

gas

removal

TREMP

Ash 1 0.5 0 0 0 0 0

CO 1 1 1 1 1 1 0

CO2 1 1 1 1 1 0 0

CH4 1 1 1 1 1 1 1

Tars 1 1 0 0 0 0 0

H2 1 1 1 1 1 1 0

H2S 1 1 1 1 1 0 0

COS 1 1 1 1 0 0 0

S 1 1 1 1 0 0 0

Ethene/propene 1 1 1 0 0 0 0

Benzene 1 1 1 0 0 0 0

Particles(sand,

dust)

1 0.5 0 0 0 0 0

Heterocyclics 1 1 0 0 0 0 0

Page 22: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

19

Fig

ure

17

. C

om

ple

te p

roce

ss s

chem

e fo

r p

rod

uct

ion

of

Bio

-SN

G f

rom

bio

mas

s.

Page 23: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

20

The production plant suggested in figure 17 begins with a hammer mill where the bark is

grinded to a maximum size of about 5 mm after which the drying begins. The dryer is based on

a rotary drum dryer with counter current flow of preheated air through the vessel. After drying,

the bark will be stored in a silo before transportation to the amount of gasifiers required to cover

the input of 200 MWth. The gasification is carried out using a Milena gasifier after which a

cyclone will recover most of the char, sand and particles. These particulates will be combusted

in the combustion chamber after which the flue gas will be cleaned using a FGD system based

on quicklime.

The primary gas that leaves the Milena has a temperature of 850˚C and has to be cooled prior

the absorber and collector (the OLGA) apparatus. A heat exchanger is installed which will

produce steam that can be used downstream in the process. The Collector will collect

particulates and, together with the W-ESP also large tars. The gas will be cleaned even further

using an absorber in which light tars are removed to the countercurrent flow of oil. The rich oil

solution is restored in a stripper and recovered to the system.

To satisfy purity requirements downstream, additional filters (HGF) is installed downstream of

the absorber. The gas now enters hydrogenation where unsaturated hydrocarbons (double c-c

bonds) becomes saturated and create mostly ethane and propene in the presence of platinum or

palladium catalyst.

The following step is hydrolysis which converts most of the sulfur from the biomass to H2S and

COS. This is installed closely to the WGS-reactors where CO and water is converted to H2 and

CO2 according to the WGS reaction (2). Heat exchanger #9 in figure 17 will cool the gas

intermediately. The following step consists of removing almost all of the sulfur components

which is obtained by absorption using MDEA-PZ amine. These components are recycled to the

combustion chamber, thus help drive the gasification process.

The final step is the methanation step which is based on fixed bed technology, called

TREMP™. Here, methane is produced to methane from hydrogen and carbon monoxide using

four reaction vessels and several heat exchangers. Before the gas can be inserted to the

TREMPTM process the pressure has to be increased to about 24 bar using compressors.

In table 6 all the compositions have been listed after each sub-process. The final gas

composition is not entirely qualified to be injected into the gas grid when compared to the gas

quality requirements from European Association for the Streamlining of Energy Exchange, in

table 1. This is because there is too much carbon monoxide present in the gas (maximum

allowed amount if 1 ppm).

Page 24: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

21

Table 6. Complete gas composition through the proposed process seen in figure 17. The simulations were carried

out using Aspen and MATLAB.

MILENA OLGA HYDG WGS/HYDR Acid gas

removal

TREMP

N2 0.06 % 0.06 % 0.061 % 0.06 % 0.16 % -

CO2 7.35 % 7.367 % 7.554 % 11.72 % 0.03 % 0.45 %

CO 10.34 % 10.377 % 10.640 % 6.47 % 17.39 % 19 ppm

H2 17.56 % 17.638 % 15.247 % 19.42 % 52.16 % 0.57 %

CH4 5.20 % 5.216 % 5.348 % 5.35 % 14.37 % 95.62 %

H2O 57.08 % 57.245 % 58.695 % 54.53 % 9.33 % 3.35 %

H2S 100 ppm 80 ppm 80 ppm 100 ppm 1 ppm 1 ppm

COS 9 ppm 10 ppm 10 ppm - - -

H3N 600 ppm 640 ppm 650 ppm 700 ppm 1 800 ppm 650 ppm

C2H2 0.10 % 0.105 % - - - -

C2H4 1.66 % 1.666 % - - - -

C2H6 0.10 % 0.105 % 2.38 % 2.38 % 6.39 % 50 ppm

C6H6 0.42 % 0.149 % - - - -

C7H8 50 ppm - - - - -

As can be seen in table 6 the gas does not meet the requirements. It could be altered by adding

a flash apparatus to the process flow sheet in order to remove a lot of water. The carbon

monoxide levels has to be decreased which should be taken care of in the bypass before the

WGS reactor. However, there have been some issues regarding the robustness of the

calculations in this case and the model have been problematic.

The total received composition out of TREMPTM nearly corresponds to the demands for

injecting it into the gas grid. Methane have a higher heating value (HHV) of 55.53 MJ/kg and

the after simulations in Aspen showed that the received flow rate was 1.7 kg/s. A value of 94.4

MWth from 200 MWth input of bark gives a chemical efficiency of 47.2 %.

Calculations for the energy output and the total chemical efficiency is seen below, Eq(14-15).

𝑄𝑜𝑢𝑡 = 1.7𝑘𝑔𝐶𝐻4𝑠∙55.53 𝑀𝐽

𝑘𝑔= 94.4 𝑀𝑊 𝐸𝑞(14)

𝜂𝑐ℎ𝑒𝑚 =𝑄𝑜𝑢𝑡

𝑄𝑖𝑛=94.4 𝑀𝑊

200 𝑀𝑊= 47.2 % Eq(15)

4. Discussion literature review

When different industrial gasification technologies were investigated and studied, no laboratory

scale gasifiers were included in the project. Only up to date, large scale gasifiers, gas cleaning

and upgrading utilities were compared. However, there are several different technologies which

have been proved promising in laboratory scale.

Due to time constraints there have not been any in depth studies in the matter of different

process utilities. As mentioned before, time was of essence and therefore process utilities were

Page 25: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

22

put together without optimization calculations for each utility. In further work, several in depth

studies have to be carried out at each and every utility to maximize revenue.

The combined process of MILENA, OLGA and TREMP™ has been chosen because of their

overall efficiency as well as lower investment and operating costs than their alternatives. The

production plant renders an input of 200 MWth which will demand an upscaling about ten times

of the gasifier. Not to mention along with all the production equipment such as vessels,

pipelines, pumps etc.

5. Method for cost estimates

To determine and investigate the feasibility of the SNG production plant an economical

evaluation was carried out. Capital and operating costs have been taken into consideration.

Detailed tables and calculations are found in appendix B.

5.1. Operating costs

Operating costs are divided into three sub groups, direct-, indirect- and fixed capital costs.

Direct costs include raw materials, catalysts, solvents, labor and utilities. Catalysts are lost due

to abrasion during usage. They also have a certain available lifetime including a number of

cycles before degeneration occur. This include purchase costs for the chemical company using

them. Solvents are lost due to leaks, incomplete recovery and degeneration. Utilities include

electricity, cooling/process water, compressed air, waste treatment and energy.

5.2. Capital costs

A capital cost estimation was carried out according to the Ulrich method37. The equipment’s

total contribution to both indirect and direct construction cost, CBM, is calculated using the

equation below, Eq(12).

𝐶𝐵𝑀 = 𝐶𝑃 · 𝐹𝐵𝑀 𝑎 𝐸𝑞(12)

CBM is the installed module cost, CP is the purchased equipment cost. FaBM is an addition factor

which takes both the material and different process parameters into consideration but also

installation costs, land improvements, transportation, piping, materials, labor for installation

and other costs associated to the apparatus. All costs are seen in appendix B.

To determine the necessary sizes for different process vessels the macroscopic behavior within

the unit is not considered. Instead, the relation between the inlet and the outlet streams are

compared using mass and energy balances for each vessel inside the process. Different process

vessels are calculated based on normal gas/liquid velocities and catalyst vessels including

reactors are based on necessary residence times.

Page 26: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

23

The module costs will sum up to the total capital cost of the plant according to the equation

below in which ffees represents contingency and contracting and fauxiliary takes auxiliary

equipment and buildings into consideration, seen in Eq(13).

𝐾2004 = (∑ 𝑐𝐵𝑀𝑖𝑛𝑖=1 ) · 𝑓𝑓𝑒𝑒𝑠 · 𝑓𝑎𝑢𝑥𝑖𝑙𝑖𝑎𝑟𝑦 𝐸𝑞(13)

As the process has fulfilled its requirements and cannot operate further, the process utilities

could be sold. In this case, as the project is based on worst case scenario, the final value of the

process equipment after expected lifespan is set to zero.

6. Economical evaluation

This part contains calculations and assumptions regarding all process utilities used for the

production of synthetic natural gas, SNG. All calculations are discussed separately after each

part and will provide the reader with a good overview. Each section contains a short

introduction and a brief discussion regarding the approach in which the problems have been

handled. Finally, the total cost for a green field erection is compared to an integration process

at Södra Cell Värö. This provides a total process cost for both processes.

The capital cost is calculated using Eq(13). Where ffees is about 1.15 and fauxiliary = 1.30 for green

field plants. As the brown field erection is considered an upgrade, the fauxiliary factor is set to

1.00 for this plant.

The total cost for the brown field was calculated to 860 Mkr and for green field installation the

cost was 1 118 Mkr. The annual net income was calculated to 130 Mkr.

The cost for the storage of bark was calculated using annuity method with a life span of 20

years and an interest rate of 10 %. With a storage time for the bark of three days gives an annual

cost of 225 000 kr/yr.

The payback time without interest date was calculated accordingly:

𝑇 =𝐺

𝑎

and with consideration of 10 % interest rate calculated as:

𝑛 = −(ln (1 − 𝐺 ∙

𝑋

𝑎)

ln(1 + 𝑋))

A payback time of 7 and 11 years, respectively, was obtained for the base case.

In table 7 a complete list of the base case items are gathered.

Page 27: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

24

Table 7. Compiled list for the base case scenario.

Investment G (kr) 860 000 000

Residual value 0

Yearly incomes and costs

Number of employees (st) 10

Salary/person (kr/yr) 750 000

Salary (kr/yr) 7 500 000

Maintenance (kr/yr) 43 000 000

Steam

Steam price (kr/GJ) 90

Steam production (GJ/yr) 560 000

Steam sales (kr/yr) 50 400 000

Bark

Bark price (kr/GJ) 37

Bark input (GJ/yr) 6 220 800

Bark purchase (kr/yr) 230 169 600

Restricted equity in bark (kr) 225 000

SNG

SNG price (kr/GJ) 124

SNG production (GJ/yr) 2 908 224

SNG sales (kr/yr) 360 619 776

Catalyst

Cost (kr/yr) 2 670 000

Annual net income

a (kr/yr) 130 000 000

Interest rate (10 %) 0.1

Payback T = G/a

T (yr) 6.7

Payback with interest rate (10 %)

n (yr) 11.8

The payback method based on an interest rate of 10 % was used to create figure 18-22. To

visualize the sensitivity and the influence of market prices, a sensitivity analysis was carried

out based on fluctuating bark prices, SNG-prices and steam prices. The total investment cost

and the number of shift workers at the process was changed to develop an understanding of

where the costs are located. In the base case, bark was assumed to be purchased at 37 kr/GJ,

SNG to be sold at 124 kr/GJ and steam to be sold for 90 kr/GJ.

Page 28: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

25

As can be seen in figure 18, a slight increase of the bark price would have large unfavorable

impact on the payback time. As much as a few percent would lead to significant changes in the

process economy.

Figure 18. Sensitivity analysis of fluctuating bark prices. A small change towards higher bark prices gives a

significant impact on the payback time.

In figure 19 an increase in SNG prices would lead to shorter payback times according to the

payback method. If the price of bark would decrease at the same time as the price of SNG

increased, there would be significant changes in the payback time. Furthermore, the steam

should be sold to increase revenue, and depending on the price the outcome fluctuates.

Figure 19. Sensitivity analysis of fluctuating SNG prices.

15 20 25 30 35 40 454

6

8

10

12

14

16

18

20

22

24Payback

Bark price kr/GJ

Payback t

ime in y

ears

110 120 130 140 150 160 1704

6

8

10

12

14

16

18

20Payback

SNG price kr/GJ

Payback t

ime in y

ears

Page 29: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

26

In figure 20, a sensitivity analysis was carried out at the steam price. This is to visualize the

importance of selling the steam to a high price. It is clear from the figure that the investment

will not be profitable if the steam can’t be sold for above 70 kr/GJ.

Figure 20. Sensitivity analysis of fluctuating steam prices. There is a high importance of selling the steam to a high

price to increase revenue.

Figure 21 shows the payback time for the current product and bark prices with a change in

investment cost of ± 30 %.

Figure 21. Sensitivity analysis of the investment cost ± 30 %.

20 30 40 50 60 70 80 90 10010

15

20

25

30

35

40Payback

Steam price kr/GJ

Payback t

ime in y

ears

6 7 8 9 10 11 12

x 108

5

10

15

20

25

30

35

40Payback

Investment cost kr

Payback t

ime in y

ears

Page 30: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

27

Figure 22 below shows a sensitivity analysis over number of employees.

Figure 22. Sensitivity analyses of the amount of employees needed at the plant.

7. Discussion

This project was based on commercial available gasification technologies and not promising

laboratory scale gasification techniques. However, these promising projects might help reduce

capital costs and increase efficiency in the future which will enhance SNG production in total.

The capital cost for the different apparatus in this process was calculated using the Ulrich’s

method which could lead to a slight different outcome.

As the process develops high pressure steam (100 bar at about 5 kg/s) this should be sold or

used somehow to increase revenue. If there is a strong need in the surrounding industries for

high pressure steam, the steam would reach high prices (at efficiencies of 80 % of turbines, the

price could correspond to the price of natural gas divided by 0.8). However, if there is not a

steam demand nearby, the price could also be set to zero as there would be nowhere to use it.

This gives a very varying economic situation which has to be taken into consideration. The

annual net income from steam in table 7 could therefore be very different from the base case.

Analyzing the composition in the steps downstream from the MILENA shows clearly that a big

part of the gas flow contains water. Some water is required in the WGS and the hydrolysis.

Throughout the simulation it’s clear that the amount of water is more than sufficient. Therefore

it could be possible to reduce the size of all vessels, pipes etc. if the water in the gas flow is

reduced to the amount needed for the downstream reactors.

In appendix C, the Aspen flow sheets of the combustion chamber can be seen to operate without

an inflow of the components removed from the acid gas removal. These will have impact on

10 12 14 16 18 20 22 24 26 28 3011.5

12

12.5

13

13.5

14

14.5

15

15.5Payback

Number of employee

Payback t

ime in y

ears

Page 31: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

28

the energy of the flue gas leaving the combustion chamber and will also increase the amount of

flue gases. However, these values were neglected. This might have a small impact on the heat

exchanger areas nearby. The energy in the recirculated chars, tars and sulfuric components are

assumed to have enough energy to supply the Milena gasifiers.

In this project, the site location have not been taken into consideration. However, as the price

of biomass and products could consist of about +40 % transportation costs, the site location

have a huge influence on the economy evaluation in total. Furthermore, if the product could be

sold nearby or injected straight away onto the gas grid, it would be very profitable. These

considerations have not been evaluated, as well as Väro’s potential electricity production which

is influenced by the electricity price. In a future study, these considerations should be interesting

to discuss further.

The familiarity at handling large amounts of biomass at Värö would decrease the number of

personnel necessary at each shift. According to a rule of thumb, about 1/3 of the total number

of personnel at a new plant would be needed at a plant like Värö. Furthermore, as annual salary

is just a fraction of the cost of the bark this would not have a great impact of the payback time,

which are illustrated in figure 18 and 21.

Page 32: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

29

8. Conclusions

Using the base case with today’s prices, the plant would have payback time of about 10 years.

However, as mentioned in the discussion, the payback time is strongly dependent on the price

of energy which fluctuate heavily from time to time. Further, as there might be a need for high

pressure steam nearby, the steam could be sold for about the same price as for the natural gas.

In this case, the price for bio-SNG is slightly higher compared to natural gas as there are both

tax incentives which promotes the bio-SNG.

See appendix B. With today’s prices, the payback time is pretty good but the income changes

rapidly with the prices of products and biomass which indicates an unreliable investment.

The literature review was developed to construct a solid fundament on which the process should

be designed. The objective was to determine whether or not this process should be built at all,

if it should be integrated to a pulp and paper industry or as a green field erection. However, as

the apparatus found on site at Värö will not have major influence on the handling of biomass

nor the handling of bark and gasification, one has to have a broader view of the problem. The

employees at Värö have valuable knowledge in this regard which could be of great value when

constructing a new plant. Though, this knowledge is hard to put a price tag on.

Värö do not have further, unused storage capacity of bark but they do have a steam network

and a steam generator which could make valuable electricity from the high pressure steam. If

there is a strong demand of high pressure steam at Värö, the steam produced could be of high

value and very useful, or the electricity could be sold and injected onto the grid. Also, tax

incentives could change the outcome of this newly developed technology. Nevertheless, as

there is a new government every 4th year, calculations regarding tax incentives should be treated

rather as a bonus than anything else.

If the bark could be purchased at a very low price, as would be the case if the company would

harvest bark from the company’s own forest, the economy analysis would be different.

Page 33: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

30

9. References

1 Asif M, Muneer T. Energy supply, its demand and security issues for development and emerging

Economies. 29 November 2005. School of Engineering, Napier University UK. Available from:

http://www.sciencedirect.com/science/article/pii/S1364032106000049

2 Energy, Transport and environment indicators, 2012 edition. Eurostat European Commission, ISS

1725-4566. p. 28 Table 2.2.1 Energy Dependency – all products (%). Available from:

http://ec.europa.eu/eurostat/documents/3930297/5968494/KS-DK-12-001-EN.PDF

3 BP Statistical Review of World Energy June 2014, 63rd edition. p.23 Table “Consumption*”.Available

from: http://www.bp.com/content/dam/bp/pdf/Energy-economics/statistical-review-2014/BP-statistical-

review-of-world-energy-2014-full-report.pdf

4 Scherrer P. Institute IBM Corporation, Global Transport Scenarios 2050. World Energy Council. p. 54,

Figure 18; Fuels in all transport “Demand between 2010 and 2050”. Available from:

http://www.worldenergy.org/wp-content/uploads/2012/09/wec_transport_scenarios_2050.pdf

5 BP World Energy Statistics 2012 (2012) and IEA World Energy Outlook 2011 (IEA, 2011a). Available

from: https://www.iea.org/publications/freepublications/publication/WEO2011_WEB.pdf,

http://www.bp.com/content/dam/bp/pdf/Statistical-Review-

2012/statistical_review_of_world_energy_2012.pdf

6 Dahlgren S, Liljeblad A. WSP - Energigas Sverige; Realiserbar biogaspotential i Sverige år 2030

genom rötning och förgasning. 2013-04-10. p.87. Available from:

http://www.energigas.se/Aktuellt/Kalendarium/Arr1310Gasdagarna/~/media/Files/www_energigas_se/

Aktuellt/VaraSeminarier/GasDagarna2013/PresentationerDag2/Anna_Stefan_%20WSP_Gasdagarna20

13.ashx

7 Holmberg A, Stenström S. Dewatering and Drying of Bark. Dept of Chemical Engineering Lund

university. International Journal of Energy Engineering 2014, 4(2A): 8-16 2014. Available from:

http://article.sapub.org/10.5923.j.ijee.201401.02.html

8 Johansson I, Larsson S, Wennberg O. Värmeforsk. Anläggningsteknik 881- Torkning av biobränslen

med spillvärme.Oktober 2004 ISSN 0282-3772.Available from:

http://www.varmeforsk.se/rapporter%3Faction%3Dsearch%26q%3D%26reportNumber%3D881%26pr

ojectNumber%3D%26title%3D%26author%3D%26year%3D%26year_start%3D%26year_end%3D?ac

tion=show&id=3129

9 Thörnqvist T, Gustavsson G.Kallufttorkningens betydelse för bränsleflisens lagringsbarhet. Sveriges

Lantbruksunivrsitet.Instutitionenförvirkeslära. Rapport nr 142. Uppsala 1983. ISBN 91-576-1665-5

10 Ishikawa A, TatsuroO, Kobayashi I. Effect on drying methods on volatile organic compound emission

from sugi wood. (Bulletin of FFPRI) Vol.8 No.4 (No.413) 215 - 222 december 2009 p. 220. Available

from: https://www.ffpri.affrc.go.jp/pubs/bulletin/413/documents/413-2.pdf

11 Holmberg H, Athila P. Evaluation of energy efficiency in biofuel drying by means of energy and

exergy analyses. AppliedThermalEngineering 25 (2005) p. 3115–3128. June 4, 2005.Available from:

http://www.sciencedirect.com/science/article/pii/S1359431105001055

12 Grén U, Theliander H. Grundläggande kemisk apparatteknik. Chalmers Tekniska Högskola. Göteborg

2001.

13 International Journal of Chemical Reactor Engineering. Volume 7. Issue 1. ISSN 1542-

6580. November 2009Bioenergy II: Scale-Up of the Milena Biomass Gasification Process. Available

from: http://www.degruyter.com/view/j/ijcre.2009.7.1/ijcre.2009.7.1.1898/ijcre.2009.7.1.1898.xml

Page 34: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

31

14 van der Meijden C.M, van der Drift B.J. Vreugdenhil. ECN - Experimental results from the allothermal

biomass gasifier MILENA. November 2008. Presented at the 15th European Biomass Conference 7-11.

May 2007. Berlin. Germany. Available from: http://www.ecn.nl/docs/library/report/2008/m08083.pdf

15 MILENA Biomass gasification process. Available from: http://www.milenatechnology.com/, 2015-

03-30.

16 Rauch R, Bosch K, Hofbauer H. Swierczynski D, Courson C, Kienneman A. Comparison of different

olivines from biomass steam gasification. Institute of Chemical Engineering, Vienna. Available from:

http://members.aon.at/biomasse/olivine.pdf

17 Forzatti P, Lietti L. Catalyst Deactivation. 1999 Dipartimento di ChimicaIndustriale e

IngegneriaChimicaG.Natta. Politecnico di Milano. Milan, Italy Catalysis Today 52 (1999) p. 165-181.

Fig. 1 p. 167. Available from:

http://www.quimica.ufpb.br/arymaia/Desativa%E7%E3o%20Catal%EDtica.pdf

18 C. Hulteberg,”Syngas Processes I,” unpublished.

19 van der Meijden C.M. ECN - Development of the MILENA gasification technology for the production

of Bio-SNG. 2010, pp. 1-187. ECN-B--10-016. Available from:

http://www.ecn.nl/docs/library/report/2010/b10016.pdf

20 Boerrigter H, CalisH.P, SlortD.J, Bodenstaff H,KaandorpA.J, den UilA.J and RabouL.P.L.M. Gas

cleaning for integrated biomass gasification (BG) and Fischer-Tropsch (FT) systems. December 2004,

p- 25-26. Available from: http://www.ecn.nl/docs/library/report/2010/b10016.pdf

21 Boerrigter H, van PaasenS.V.B, BergmanP.C.A,KönemannJ.W, EmmenR, WijnandsA. ECN -

“OLGA” TAR REMOVAL TECHNOLOGY. Proof-of-Concept (PoC) for application in integrated

biomass gasification combined heat and power (CHP) systems.ECN-C--05-009 Januray 2005, p. 29-31.

Available from: http://www.ecn.nl/docs/library/report/2005/c05009.pdf

22 Zwart R.W.R, Bos A, Kuipers J. Principle of OLGA tar removal system. ECN Biomass. Coal &

Environmental Research. Available from: https://www.ecn.nl/fileadmin/ecn/units/bio/Leaflets/b-08-

022_OLGA_principles.pdf

23 Rabou L.P.L.M, van der Drift A. Benzene and ethylene in Bio-SNG production.Proceedings of the

International Conference on Polygeneration Strategies 11, Vienna (2011), p. 157-162. Available from:

http://www.ecn.nl/docs/library/report/2011/m11092.pdf

24 Twigg M. Catalyst Handbook. Chapter 6: Water-gas-Shift Reaction 1996.

Second Edition, Manson Publishing; 1996.

25 US. Department of Energy. SYNGAS CONTAMINANT REMOVAL AND CONDITIONING .Available

from: http://www.netl.doe.gov/research/coal/energy-systems/gasification/gasifipedia/cos-hydrolysis

26 Anderson W, Bruno T. Kinetics, catalysis and reaction engineering. Physical and chemical properties

division. Kinetics of Carbonyl Sulfide Hydrolysis. Catalyzed and Uncatalyzed Reactions in Mixtures of

Water + Propane. National Institute of Standards and Technology Ind. Eng. Chem. Res. 2003, 42, p. 963-

970.Available from: http://pubs.acs.org/doi/pdf/10.1021/ie020772z

27 Tunå P. Substitute natural gas from biomass gasification. Svenskt Gastekniskt nätverk. Lund Institute

of Technology. Rapport SGC 187.mars 2008. SWEDISH. Available from:

http://www.sgc.se/ckfinder/userfiles/files/SGC187.pdf

28 Moulijn J, Makkee M, van Diepen E. Chemical Process Technology. Catalysis Engineering.

Department of Chemical Engineering. Delft University of Technology. The Netherlands. 2nded. Wiley.

2013.

Page 35: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

32

29 Rasmussen N. Technologies relevant for gasification and methanation in Denmark Project: Detailed

analysis of bio-SNG technologies and other RE-gases ForskNG 10689 Work Package 3: Environmental

aspects and analysis Milestone 3.1-1: Report on inventory of relevant bio-SNG technologies Danish Gas

Technology Centre Niels Bjarne Rasmussen September 2012. Available from:

http://www.dgc.eu/sites/default/files/filarkiv/documents/R1207_gasification_methanisation.pdf

30 Sudiro M, Bertucco A. Synthetic Natural Gas (SNG) from coal and biomass: a survey of existing

process technologies, open issues and perspectives. Department of Chemical Engineering (DIPIC).

University of Padova. Italy. Available from: http://cdn.intechopen.com/pdfs/11472/InTech-Synthetic-

natural-gas-sng-from-coal-and-biomass-a-survey-of-existing-process-technologies-open-issues-and-

perspectives.pdf

31 Jensen J.H, Poulsen J. M, Andersen N.U. From coal to clean energy. Haldor Topsoe. April 2011.

Available from:

http://www.topsoe.com/sites/default/files/topsoe_from_coal_to_clean_energy_nitrogen_syngas_march

_april_2011.pdf

32 National Air Quality Planning and Standards, Research Triangle Park, NC, March 2000; EPA-454/R-

00-003 (NTIS PB2000-104960).Quality and Emissions Trends Report, 1998, U.S. Environmental

Protection Agency, Office of Air.

33 Srivastava R.K, Josewicz W. Flue gas Desulfurization: The state of the art. Air and Waste management

Assoc. 51:1676-1688 2001. Available from:

http://www.cee.mtu.edu/~reh/papers/pubs/non_Honrath/srivastava01.pdf

34 United States Environmental Protection Agency. Air Pollution Control Technology Fact Sheet. EPA-

452/F-03-034. EPA-CICA Fact Sheet Flue gas Desulfurization p.3.

Available from: http://www.epa.gov/ttncatc1/dir1/ffdg.pdf

35 FETC 1996. Electric Utility Engineer’s FGD Manual, Volume 1: FGD Process Design. Department of

Energy. Federal Energy Technology Center. Morgantown, MW, 1996. Available from:

http://www.osti.gov/scitech/servlets/purl/629398

36 Sristava R. Controlling SO2 EMISSIONS. A Review of technologies. U.S. Environmental Protection

Agency. November, 2000. Available from:

http://plainsjustice.org/files/ElkRun/Elk_Run_References/EPA%20Publications/EPA_600_R-

00_093%20controlling%20so2%20emissions.pdf

37 Karlsson H. Short Notes on Cost Estimation Equations. Department of Chemical Engineering.

Page 36: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

33

APPENDIX A CALCULATIONS

In this Appendix A, “Calculations” some calculations are compiled to provide the reader

knowledge regarding the apparatus design and size.

HANDLING OF BARK

Calculate how many kg of bark that represents 200 MWth. Use this value to decide how many

kg of water that have to be evaporated from the bark (50 % wet in, and 10 % out) → necessary

energy for evaporation will be known and then we can calculate the volumetric amount of air

needed in the dryer. This amount of air will decide how many and how much energy that is

needed for the fans.

Table HB1. Summary of component balance in bark38

Dry Weight of constituents

Carbon (C) Oxygen (O) Hydrogen (H) Nitrogen (N) Ash

Bark Content

(%)

50.6 40.7 5.9 0 2.8

In Eq (17) A = Ash, Hcal higher heating value, hvap water 1bar, H hydrogen content F = moisture

content Higher heating value Norway spruce = 4.76 Kcal/kg39.

𝐻𝑏𝑖𝑜𝑓𝑢𝑒𝑙 = (1 − 𝐹) ∙ (1 − 𝐴)𝐻𝑐𝑎𝑙 − 𝛥ℎ𝑣𝑎𝑝((1 − 𝐹) ∙ 8.94 ∙ 𝐻 + 𝐹) = 14MJ

kg 𝐸𝑞(16)

Total amount of bark is calculated using Eq(17).

𝑚𝑏𝑎𝑟𝑘 = (1 − 𝐹) ·200 𝑀𝑊

𝐻𝑏𝑖𝑜𝑓𝑢𝑒𝑙= 11.5

𝑘𝑔

𝑠 𝐸𝑞(17)

Total net input of biomass to the dryer is twice as large due to its water content (22 kg/s). The

total amount of water driven of is:

𝑚ℎ2𝑂 = 𝑚𝑏𝑎𝑟𝑘 −𝑚𝑏𝑎𝑟𝑘 · 𝐹 = 9.2 𝑘𝑔

𝑠 𝐸𝑞(18)

The amount of air is calculated by using mollier diagram. Start temperature of air is set to 10-

20˚C with maximum of 0.02 kg water/kg air (this is corresponding to a relative humidity of 100

% which is worse than the worst case scenario). Final temperature of air (after preheating) is

80˚C with a maximum water content of 0.045 kg/kg.

FANS FOR DRYING OF BARK

The necessary amount of air is calculated using Eq(19).The total amount of energy required for

drying of biomass is about 2700 kJ/kg water evaporated. This value include heating of the

biomass as well as evaporation of water.

𝑚𝑎𝑖𝑟 =𝑚ℎ2𝑂

(𝑋𝑢𝑡 − 𝑋𝑖𝑛)= 306

𝑘𝑔𝑎𝑖𝑟𝑠

𝐸𝑞(19)

Page 37: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

34

With a density of 1kg/m3 this equals 306 m3/s of air required for the fans. The energy needed

for the dryer is:

𝐸𝑛𝑒𝑟𝑔𝑦𝑑𝑟𝑦𝑒𝑟 = 2700𝑘𝐽

𝑘𝑔· 12

𝑘𝑔

𝑠= 32 400

𝑘𝐽

𝑠

The fan installed for this purpose is a centrifugal backward-curved fan. One fan is used, with a

capacity of 500 standard m3 per second at 1 atm pressure and 273 K using Ulrich’s method

which was described before and according to graph figure 5.29 p 379.

𝐶𝐵𝑀 = 𝐶𝑝 · 𝐹𝐵𝑀 · 𝐹𝑝 Eq(20)

Eq(20) is used to determine the final purchase cost for the fans. Table TF1 shows received data

for the fan.

Table TF1. Parameter values for calculation of purchase cost of fan equipment.

Parameter Value

Cp 5·105

FBM (Carbon steel) 2.2

FP (1 kPa) 1

CBM ends up at a final price of:

𝐶𝐵𝑀 = 5 · 105 · 2,2 · 1 = 1.1 · 106 𝑈𝑆𝐷

STORAGE OF BARK

The storage of bark will need a capacity of 3 days of full SNG-production without any delivery

of biomass. The total mass will be, according to equation ES1 about 3000 ton of bark.

𝑀𝑠𝑡𝑜𝑟𝑎𝑔𝑒 = 11.5𝑘𝑔𝑓𝑢𝑒𝑙

𝑠· 3 600

𝑠

ℎ· 24

𝑑𝑎𝑦· 3 𝑑𝑎𝑦𝑠 ·

1

1 000

𝑡𝑜𝑛

𝑘𝑔= 3 000 𝑡𝑜𝑛 (𝐸𝑆1)

The bark density is about 105-135kg/m3 when dry which corresponds to a total volumetric

storage capacity of:

𝑉𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 = 3 000 𝑡𝑜𝑛 · 1 000 𝑘𝑔

𝑡𝑜𝑛· 1

105

𝑚3

𝑘𝑔= 29 000 𝑚3

The bark is stored in piles with an angle at the top of the cone of 50˚ and a height of 12 m. The

radius is calculated using equation ES2.

𝑟𝑏𝑜𝑡𝑡𝑜𝑚 = 𝐶𝑜𝑠(40˚)

𝑆𝑖𝑛(40˚)· 12 𝑚 = 14.30 𝑚 (𝐸𝑆2)

Page 38: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

35

The volume of 1 cone will be the following:

𝑉𝑐𝑜𝑛𝑒 = 𝜋 · 𝑟2 · ℎ

3= 2 569

𝑚3

𝑐𝑜𝑛𝑒

The amount of piles is calculated:

𝑛𝑐𝑜𝑛𝑒𝑠 = 29 000 𝑚3 ·

1

2 500

𝑐𝑜𝑛𝑒

𝑚3= 12 𝑠𝑡

The total amount of area necessary is:

𝐴𝑡𝑜𝑡 = 𝜋 · 𝑟2 · 𝑛𝑐𝑜𝑛𝑒𝑠 = 𝜋 · 14.3

2 · 14 = 9 000 𝑚2

The cones will not be placed right beside each other. They must be reachable and therefore, a

room in between the piles of 5 m is believed to be necessary. The piles are placed in 4∙3 with 5

m road in between each pile.

𝐴𝑊𝑖𝑡ℎ𝑟𝑜𝑎𝑑𝑠 = 𝑑𝑝𝑖𝑙𝑒 · 𝑛𝑝𝑖𝑙𝑒 + 5 · 𝑛𝑟𝑜𝑎𝑑𝑠 = (30𝑚 · 4 𝑝𝑖𝑙𝑒𝑠 + 3 · 5) · (30 · 3 + 2 · 5)

= 13 500 𝑚2

The construction cost this area will be added to the final process unit with different variables.

BARK DRYER

The dryer will be based on a rotary dryer. The cost is based on figure 5.33 p 381. The cost for

the dryer will be related to the necessary Volume. To calculate this, the bark density was set to

105-135 kg/m3 when dry.40

With a density of 135 kg/m3 dry substance give a total volumetric flow of biomass to about 0.1

m3/s as Eq(21).

1

135

𝑚3

𝑘𝑔· 12

𝑘𝑔

𝑠≈ 0.09

𝑚3

𝑠 𝐸𝑞(21)

The residence time is set to 2 minutes which gives a total volumetric flow of bark to 10.8 m3.

The bark is set to be 1/10 of the total volume of the rotary drum. This gives a necessary drum

of 100 m3. The following parameters are compiled in table TD1 for calculation of the purchase

cost of the dryer.

Table TD1. Compiled parameters for purchase cost of dryer.

Parameter Value

V 100 m3

Cp (Direct rotary dryer) 2 ·105

FBM (stainless steel) 4.5

Using the following equation for the total purchase cost is: 𝐶𝐵𝑀 = 𝐶𝑝 · 𝐹𝐵𝑀 = 2 · 105 · 4.5 =

9 · 105 𝑈𝑆𝐷. This cost is complete including drives.

Page 39: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

36

TRANSPORTATION OF BIOMASS (BARK)

The transportation of crushed, biomass to the dryer and from the dryer to the MILENA utilities

is carried out using conveyor belts. As there are 10 different MILENA’S, the conveyor belt will

transport the biomass to a silo in which the bottom is connected to pipes with valves that control

the amount of biomass to each MILENA utility.

For the conveyor, a closed belt conveyor is designed to carry out the work. From the dryer to

the silo a distance of 30 m is believed to be sufficient enough. The purchase cost parameters

are obtained from figure 5.14 p 372 and compiled in table C1.

Table T1. Compiled parameters for conveyor belt purchase costs.

Parameter Value

Cp 2.5·105

Conveyer distance (m) 30 m

Width (m) 1.5 m

FBM (closed belt) 2.4

These values are inserted to equation below. This cost is purchased equipment cost including

drives.

𝐶𝐵𝑀 = 𝐶𝑃 · 𝐹𝐵𝑀 = 2.5 · 105 · 2.4 = 6 · 105 𝑈𝑆𝐷

BARK CRUSHER (MILL)

As the bark has to be grinded to smaller pieces, a crusher is installed before the dryer. The dryer

is installed after the crusher to increase the drying efficiency. The calculations are made for a

hammer mill. The total mass of bark to the crusher is about 45 kg/h.

Table C1. These parameters represent the necessary values for calculations regarding the crusher cost.

Parameter Value

Cp 2.5·105

FBM (hammer mill) 2.8

Discussion

Recirculation of air could be implemented in the drying system which would increase the

efficiency. This has not been included in this project and in these calculations. A worst case

scenario of the inlet air has been chosen and the efficiency will be higher during most time of

the year.

MILENA

The MILENA gasifier consists of 10 different vertical vessels with 20 MWth each. The

maximum gas velocity inside them is set to 10 m/s and a residual time of 1.5 s. With a total

amount of gas produced (received from Aspen simulations) of 77 m3/s the total flow per

MILENA is about 8 m3/s.

𝐴𝑚𝑖𝑙𝑒𝑛𝑎 = 8𝑚3

𝑠·1

10

𝑠

𝑚= 0.8 𝑚2

𝐷 = √𝐴𝑚𝑖𝑙𝑒𝑛𝑎 · 4

𝜋 ≈ 1 𝑚

ℎ = 𝑣𝑔𝑎𝑠 · 𝑡𝑟𝑒𝑠𝑖𝑑𝑢𝑎𝑙 = 10𝑚

𝑠· 1.5 𝑠 = 15 𝑚

Page 40: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

37

TARS

The recycled tars from the OLGA purification step will be recycled to the combustion chambers

to drive the gasification process. Therefore, the lower- and higher heating value (LHV, HHV)

has to be calculated. The compositions of the tars is heavily influenced by reactor type,

temperature and used biomass. Therefore, it is very difficult to determine exact composition in

different cases. However, a general assumption carried out by Mason and Ghandi41 in which

XCtar is the mass percent of carbon, XHtar is the mass percent hydrogen and XOtar is the mass

percent oxygen.

𝐻𝐻𝑉 = 340.95 · 𝑋𝐶𝑡𝑎𝑟 + 1322.98 · 𝑋𝐻𝑡𝑎𝑟 − 119.86 · 𝑋𝑂𝑡𝑎𝑟

As the composition varies with temperature, an assumption that the tars can be represented by

lumped hydrocarbons was made42. These hydrocarbons have different heating value depending

on their gasification temperature. These temperatures and corresponding heating values are

listed in table T1.

Table T1. Different heating values for different temperatures. Corresponding to lumped hydrocarbons.

Temperature interval (K) Heating value (MJ/kg)

673-923 22-26

973-1273 40

To verify this heating value of 40 MJ/kg, this value have been double checked with

corresponding heating value for different components of the tars. As can be seen, the amount

of 40 MJ/kg seems reasonable.

Table T2. Compiled heating value for the different major components of the tars.

Component Lower heating value (MJ/kg)

Benzene 40.3

Toluene 40.6

Naphthalene 40.2

H2S 17.4

Phenol 31.9

The temperature of the MILENA is about 1100 K the heating value for further calculations is

set to 40 MJ/kg.

DISCUSSION CONCERNING TARS

The tar composition can vary in many ways depending on the residence time, gasification

temperature and the use of biomass. However, this will not have a major impact on the economy

calculations in this report and therefore, no further investigations regarding the tars have been

made. The heating value of tars is, according to literature42, between 27 MJ/kg to 40 MJ/kg

and stays in this interval even if the current biomass is swapped for another. The temperature

has the major influence in this energy density of the tar.

Page 41: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

38

OLGA

For removal of tars OLGA is used and it’s modelled as two process vessels in Aspen but

calculated as three vertical vessels. Also within the gas treatment station a w-esp, three pumps,

a cooler and a separator was the cost calculated for.

The OLGA process units consists of 3 vertical columns with 12 trays in each one. Between

each tray, there has to be enough space for a man to climb in and clean the utilities. This space

is set to 80 cm/tray. In the bottom as well as in the top additional 1.5 m is added in both the

bottom and the top. This gives a total height of 13m.

ℎ𝑂𝐿𝐺𝐴 = 0.8 · 12 + 2 · 1.5 ≈ 13 𝑚

The total gas flow to the OLGA utilities is 12 m3/s and a total maximum gas velocity inside an

absorber is about 3 m/s. This gives a total area of 4 m2, which gives a diameter of 1.13 m. The

material is Stainless Steel and the cost is calculated for vertical vessels by using the Ulrich’s

method.

The cost for the 3 different OLGA vessels is calculated to 3 600 000 USD.

W-ESP

With the total gas flow to the W-ESP the total cost can be calculated. The gas flow is about 70

m3/s and the total cost of the W-ESP becomes 4 510 000 USD according to the Ulrich method.

PUMP 2, 4, AND 5

Total flow to these pumps is 500 kmol/h of Dotriacontane (C32H66) and the density for the oil

solution is about 812 kg/m3 and the molar weight is 450 kg/kmol. The height difference is

approximately 15 m and the pump used are centrifugal pumps. A pump efficiency of 95 % was

used for cost calculations. However, friction is not considered a problem for these pumps.

Equation P1 was used for calculations where q is the flow capacity (m3/h), ρ is the density

(kg/m3), h is the height difference (m) and g is (9.82 kg/s2).

𝑚𝑝𝑢𝑚𝑝 = 500𝑘𝑚𝑜𝑙

ℎ· 450

𝑘𝑔

𝑘𝑚𝑜𝑙·

1

3 600

𝑠= 62

𝑘𝑔

𝑠

𝑝𝑝𝑢𝑚𝑝(𝑘𝑊) =𝑞 · ℎ · 𝑔 · 𝜌

3.6 · 106

The shaft work required for these pumps is about 10 kW. This gives a total cost using Ulrich’s

method to 42 500 USD / pump · 3 pumps = 127 500 USD.

CHAR

During pyrolysis and gasification of biomass the amount of char formed decrease with higher

surrounding temperatures4242. Using cyclones, the char will be recycled to the combustion

chamber, producing energy to help drive the gasification process.

The mass percent of char of the combustible part of the fuel created during pyrolysis can be

determined from the equations C1, C2, C3 below42 or from laboratory experiments. Where C1

represents biomass from pinewood and bark and the other represent biomass constituents.

Page 42: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

39

𝑌𝑐ℎ𝑎𝑟 = 180 · 𝑒(−0,0037·(𝑇−273)), 𝐶1

𝑌𝑐ℎ𝑎𝑟 = 90 · 𝑒(−0,0027·(𝑇−273)), 𝐶2

𝑌𝑐ℎ𝑎𝑟 =5

(1 − 1.25 · 𝑒(−5 · 0,0002·(𝑇−273)), 𝐶3

Models from the literature were chosen to model the combustion heating value of chars43. These

are compiled in equation C4, C5 below.

𝐻𝑐ℎ𝑎𝑟 = 16700 +2930

𝑌𝑐ℎ𝑎𝑟 , 𝑦𝑐ℎ𝑎𝑟 > 0.7, 𝐶4

𝐻𝑐ℎ𝑎𝑟 = 34000 , 𝑦𝑐ℎ𝑎𝑟 < 0.7, 𝐶5

Another way to determine the heating value of tar is to calculate the heating value by using the

molar percent of carbon, hydrogen and oxygen in the chars. The molar percent of carbon

increases with temperature and the molar percent of hydrogen and oxygen decrease with higher

temperatures. To determine these amounts, different empirical expressions can be used. To

determine the amount of carbon in the char equation C6 is used. Hydrogen, equation C7 and

oxygen equation C8.

𝑋𝐶𝑐ℎ𝑎𝑟 = 98

(1 + exp [−98 · 0.00035 · (T − 273)], 𝐶6

𝑋𝐻𝑐ℎ𝑎𝑟 = 53 · exp[−0.00177 · (𝑇 − 273)] , 𝐶7

𝑋𝑂𝑐ℎ𝑎𝑟 = 25 · exp[−0.0027 · (𝑇 − 273)] , 𝐶8

As soon as these percentages are known, the following expression found in literature44, equation

C9 can be used to determine the heating value of the char42.

𝐻𝐻𝑉 = 318.1 · 𝑋𝐶𝐶ℎ𝑎𝑟 + 142.3 · 𝑋𝐻𝐶ℎ𝑎𝑟 + 154 · 𝑋𝑂𝐶ℎ𝑎𝑟 , 𝐶9

Gasification occurs at 1123 K and at T = 1123 K the HHV was calculated using C9 to 33 MJ/kg

char. Using equation C1, the total mass percent of char is calculated to 7.75 wt-%. The total

amount of char produced with a mass flow of biomass of 11.5 kg/s becomes

𝑚𝑐ℎ𝑎𝑟 = 0.0775 · 11.5 = 0.89 𝑘𝑔𝑐ℎ𝑎𝑟𝑠

, 𝐶10

Using equation C9 together with the mass flow of char to the combustion chamber (equation

C10) the total energy released in the combustion chambers is calculated using equation C11.

𝑄𝑐ℎ𝑎𝑟 = 0.89 𝑘𝑔𝑐ℎ𝑎𝑟𝑠

· 33𝑀𝐽

𝑘𝑔𝑐ℎ𝑎𝑟= 29.6

𝑀𝐽

𝑠

These calculations show that the components are almost the same as tabulated work.

Page 43: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

40

DISCUSSION CONCERNING CHARS

To check the validity of 33 MJ/kg higher heating value of char, the value was compared and

verified with literature45 in which values ranging from 17.4 MJ/kg (at 573 K) to 32 MJ/kg (1073

K). As the temperature is even higher in the combustion chamber (1123 K) these values seems

reasonable. It also works well with equation C5 which indicates a heating value of about 34

MJ/kg.

HYDROGENATION, HYDROLYSIS, WGS AND METHANATION

The calculation in all these above apparatus were calculated using the same approach as the one

for hydrolysis as can be seen below. The total costs are stated in a separate table seen in

Appendix B economy summary.

Hydrolysis work flow. To calculate the volume of the vessel the total gas flow was divided by

the residence time for the vessel. Through the flow and the max velocity of the gas through the

reactor vessel, the area and diameter as well as the height was calculated.

𝑚𝑔𝑎𝑠3

𝑠∙ 3 600

𝑠

𝑚𝑘𝑎𝑡3 ∙ ℎ

= 𝑉

𝐴 =𝑚3

𝑠𝑚

𝑠

, the diameter was calculated through: 𝐴 =𝜋∙𝑑2

4.

The cost for these vessels are compiled in Appendix B, economy summary.

The cost for the catalyst was done by calculating the amount of needed catalyst, through

dividing the volume with the density and multiply it with the price.

𝐶𝑜𝑠𝑡𝑐𝑎𝑙𝑐𝑢𝑙𝑎𝑡𝑖𝑜𝑛𝑠 = 𝑚3 ∙

𝑘𝑔

𝑚3∙𝐸𝑈𝑅

𝑘𝑔∙𝑈𝑆𝐷

𝐸𝑈𝑅= 𝑈𝑆𝐷.

ACID GAS REMOVAL

The removal of H2S and CO2 is done with MDEA – PZ absorption through two columns, an

absorption tower and a stripper. Since there are ten MILENA gasifiers, the removal of these

components are done through ten absorption systems. The cost for the complete system with

installation costs, all utilities included, will have a cost of, 1.9 ∙ 106 ∙ 10 = 19 ∙ 106 𝑈𝑆𝐷

DESULFURIZATION

The desulfurization is dependent on the total flue gas flow rate (m3/s) leaving the combustion

chamber. To calculate the amount of flue gas that leaves the combustion chamber, the amount

of fuel entering the combustion chamber has to be known. During steady-state the combustion

chamber will operate based on char, Sulfur components and tars. During startup, oil will be

used to reach the appropriate temperature. However, oil cost has not been taken into

consideration in this project.

Page 44: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

41

As mentioned in the “Char” part, about 10 % of the total biomass will end up as char in the

combustion chamber delivering energy to the gasification process. The combustion chamber

will also receive a lot of energy from tars leaving the OLGA utilities. The total amount of tars

in the biofuel is approximately 10 % according to the literature study.

With a total amount of bark entering the gasification process of 11.5 kg/s, 20 % will end up in

the combustion chamber. Of these approximate 2.3 kg, 1.7 kg is believed to be char and 1.6 kg

is believed to be tars.

In this stage of the project, a very approximate calculation regarding the amount of flue gas is

necessary. Instead of using the exact amounts of different components in the charcoal,

tabulated46values are used instead. The table used is stated in table DS1 which shows values for

mineral coal used for the charcoal.

Table DS1. Combustion data for mineral coal in m3/kg at NTP (0˚C, 100 kPa)

Flue gas

Component O2 Air g0t g0 CO2 %dry

Mineral coal 1.857 8.85 8.59 9.21 18.65 %

As can be seen in figure DS1 the total gas flow from the combustion chamber is described by

“g”. This value is calculated by adding the excess air factor l-l0 to g0 seen in table DS1.

l = 1.25 · l0 = 11 m3/s

𝑔𝑐ℎ𝑎𝑟𝑠 ≈ 11 − 8.85 + 9.21 = 11.4𝑚3

𝑠

Flue gas

Air

Char Combustion

Tars

H2S

COS Figure DS1. Overview of the combustion chamber ingoing and outgoing processes for mass balance equations.

Page 45: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

42

There are also flue gas coming from the tars and the sulfuric flow rates. The amount of tars

entering the combustion chamber is about 1 kg/s. Even though the composition of tars are

different from benzene, benzene has been used to model the approximate amount of flue gas

created from tars. Benzene has a lower heating value of 40 MJ/kg, which is close to the lower

heating value of tars. Values are compiled in table DS2. The air to fuel ratio is set to 1.25, l =

1.25·10.5 = 13.25 m3/kg.

Table DS2. Combustion data for benzene in m3/kg at NTP (0˚C, 100 kPa)

Flue gas

Component O2 Air g0t g0 CO2 %dry

Benzene 2.18 10.5 10.05 10.92 17.38 %

gtars ≈ (13.25 − 10.5 + 10.92) · 1kg

s= 13.7

𝑚3

𝑠

Summary of the flue gas and necessary amount of air is compiled in table DS3. Additional flue

gas will come from H2S and COS. However, these are of less importance (additional 5 m3 was

added to the final flow). It is important to notice that these volumetric flows are evaluated at

NTP. The total gas flow becomes 13.7 m3/s + 11.4 m3/s which is about 25 m3/s evaluated at

NTP without the sulfur components. The total flue gas flow is about 30 m3/s NTP. These values

are actual (at the appropriate temperature) flows using aspen in calculations in HE1. The total

cost for the entire desulfurization step was verbally received from the supervisors to be 3.6 M

USD for this size.

Excess air

l-l0

Moisture

g gt g0 g0,t

Fuel

Figure DS2. Relation between stoichiometric and excess air amounts in the flue gas of a combustion chamber.

Page 46: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

43

HEAT EXCHANGER 1

The first heat exchanger will preheat the air prior combustion to reach a more efficient

combustion. As the temperature inside the combustion chamber is about 950˚C the air is set to

be preheated to about 500˚C using the hot flue gases which leaves the combustion chamber. To

calculate the flow of flue gas as well as to model the incoming carbon dioxide (4 kg/s from

MDEA-PZ stripper column) the following setup was constructed in aspen plus. In these

calculations, a k value of 150 W/(m2∙K) has been used for all heat exchangers.

Figure HE 1. Flow sheet of Aspen simulations of the combustion chamber and the heat exchanger preheating the

air to the combustion chamber using energy from the flue gas leaving the combustion chamber.

The CO2 input stream to the reactor comes from the CO2 removal system and should include

H2S and COS but these are neglected to zero. Instead, a total flow of 4 kg/s of CO2 is

simulated (because this will have impact on the total flow out of the reactor). The reactor will

model combustion reactions automatically as seen in figure HE 1.2.

Figure HE 1.2. Combustion reactions simulated automatically in Aspen.

To obtain an outlet flue gas temperature of 80˚C (which is necessary for the drying utilities) a

total heat exchanger area of about 5100 m2 is necessary according to the exchanger details in

Aspen. The heat exchanger will manage to increase the temperature of the air to approximately

500˚C which is sufficient for the combustion chamber.

Page 47: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

44

Figure HE 1.3. Summary of results for HE1 from Aspen plus. A K value of 150W/(m2∙K) have been used for

simulations.

The total flowrates and temperatures are listed in figure HE1.4 below.

The amount of flue gas leaving the combustion chamber is about 90 m3/s (figure HE1.4 flue

gas total flow) which includes all components entering the combustion chamber from the

process.

Cp = 500 000

FM = 3;

FaBM = FP ∙ FM = 6

CBM = CP ∙ FaBM = 500 000 ∙ 6 = 3 000 000 USD

Figure HE 1.4. Compiled flow rates and temperatures according to figure HE1 above.

Page 48: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

45

HEAT EXCHANGER 2 AND 4-9

Small temperature differences, therefore these exchangers are neglected. Heat exchanger 2 in

the flow sheet (figure 17) is inserted to Heat exchanger 1 in order to retrieve a hot temperature

of the necessary air into the combustion chamber.

HEAT EXCHANGER 10

Temperature leaving the WGS-reactors have a temperature of 200˚C and should be decreased

to 40˚C prior amine scrubbing. This heat exchanger was calculated using Aspen plus in the

same way as heat exchanger 1. Shell and tube.

The cost is 900 000 USD. See Appendix C Economy summary for Cp, CBM, Fa, and FaBM.

HEAT EXCHANGER 3

Heat exchanger number 3 in Figure 17 will decrease the gas temperature from 1123 K to 673

K prior OLGA apparatus. The hot gas will evaporate water which enters the heat exchanger at

about boiling temperature (100˚C). The heat of evaporation for water is 2650 kJ/kg. The setup

can be seen in figure HE3.

The ingoing mass flow of gas is compiled in table HE 3.1 it was achieved from Aspen modelling

with a starting biomass flow of 15.2 kg/s. The mass flow is constant through the system and to

develop an energy balance of the heat exchanger, the component’s specific heat capacity is

needed. These values change with temperature and therefore one value is stated for the inlet

temperature (1123 K) and one for the outlet required temperature (673 K).

Figure HE 3.1. Heat exchanger number 3 ingoing and outgoing streams and pressures.

Producer gas 1; T1 = 1123 K

Producer gas 2; T2 = 673 K

Water; Tw1 = 373 K; Liquid

Water; Tw2 = 373 K; Gas

Page 49: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

46

Table HE 3.1. Compiled mass flow components of gas stream.

Component Mass flow

(kg/h)

NAPHT-01 5

TOLUE-01 58

PHENO-01 5

N2 50

CO2 9 787

CO 8 761

H2 1 071

C2H2 41

CH4 2 523

C2H4 718

C2H6 48

H2S 7

COS 1.5

H3N 49

H2O 31 121

C6H6 470

The specific heat capacity is listed in table HE3.2 below.

Table HE 3.2. Components specific heat capacity for different temperatures.

Component T = 1123K

Cp (kJ/kg·K)

T = 673 K

Cp (kJ/kg·K)

CO2 0.84 1.10

CO 1.20 1.10

CH4 2.20 3.43

C2H4 1.53 2.65

H2 15.15 14.57

N2 1.19 1.81

C7H8 1.72 1.72

H2O 2.36 2.05

The total energy balance was stated as below where the specific heat capacity was multiplied

with the total mass flow of each component. The equation used is stated in Eq HE3.1 where

ΔTL is expressed in eq HE3.2.

𝑄𝑡𝑜𝑡 = 𝑄𝑝𝑟𝑜𝑑𝑢𝑐𝑒𝑟𝑔𝑎𝑠1 −𝑄𝑝𝑟𝑜𝑑𝑢𝑐𝑒𝑟𝑔𝑎𝑠2 = 𝑘 · 𝐴 · ∆𝑇𝐿̅̅ ̅̅ ̅ = 𝑚𝐻2𝑂 · ∆𝐻𝑉𝑎𝑝 Eq HE3.1

∆𝑇𝐿̅̅ ̅̅ ̅ = ∆𝑇1−∆𝑇2

ln∆𝑇1∆𝑇2

Eq HE3.2

Page 50: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

47

Figure HE3.2 is from Aspen simulations. Feed gas has a temperature of 850˚C with the

components in table HE3.1. The stream S1 has the same constituents but a temperature of

400˚C.

Figure HE3.2. Into

With a k value of 100 W/(m2·K) the area becomes 306 m2.

The compiled values from Aspen is seen in figure He 3.3 below. In which the heat duty is about

15 MWth.

Figure HE 3.3. Compiled values from the heat exchanger 3 in Aspen. The heating duty is -15 MWth.

With a heat duty of 15 MWth, the necessary area becomes about 310 m2 using equation HE3.1.

Cp = 30 000

FM = 3;

FaBM = FP ∙ FM = 7

CBM = CP ∙ FaBM = 30 000 ∙ 7 = 210 000 USD

Page 51: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

48

APPENDIX B ECONOMY SUMMARY

A summary of the compiled equipment costs are seen in table 7-11.

Table 7. Process cost for pretreatment and gasification.

Unit Op. Operating

Conditions

Material Cp (USD) FaBM CBM (USD)

Bark

storage

• 3 days cap.

• 3 000 ton

• No roof

• 9 000 m2

Asphalt

Fans • 400 m3/s 500 000 2.2 1 100 000

Bark Dryer • 0.1 m3/s

• V = 100 m3

Stainless steel 200 000 4.5 900 000

Conveyor

Belt

• Δh = 30 m

• width 1.5 m

250 000 2.4 600 000

Bark

Crusher

• 45 kg/s bark

• hammer mill

Stainless steel 250 000 2.8 700 000

MILENA Stainless steel 30 000 12 360 000∙10

Cyclone Stainless steel 80 000 5 400 000

TOTAL 7 300 000

Page 52: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

49

Table 8. Heat exchanger calculations in USD.

Heat exchanger

calculations

Operating

conditions

Material Cp (USD) FaBM CBM (USD)

Heat exchanger 1 • Type: Shell/tube

• Area: 5 000 m2

s.s 500 000 6 3 000 000

Heat exchanger 3 • Type: Shell/tube

• Area: 310 m2

s.s 30 000 7 210 000

Heat exchanger 10 • Type: Shell/tube

• Area: 2 200 m2

s.s 150 000 6 900 000

Heat exchanger 14-15 • Type: Shell/tube

• Area: 442 m2

• Pressure: 100 bar

s.s 30 000 4 120 000

Heat exchanger 16-17 • Type: Shell/tube

• Area: 300 m2

• Pressure: 100 bar

s.s 25 000 4 100 000

Heat exchanger 18-19 • Type: Shell/tube

• Area: 70 m2

• Pressure: 100 bar

s.s 10 000 4 40 000

Heat exchanger 20-21 • Type: Shell/tube

• Area: 85 m2

• Pressure: 100 bar

s.s 10 000 4 40 000

TOTAL 4 410 000

Page 53: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

50

Table 9. Process apparatus costs.

Unit op. Operating conditions Material Cp FaBM CBM (USD)

OLGA vessels • D = 1 m

• h = 13 m

• Number of trays = 12

• A = 4 m2

• vGmax = 3 m/s

• Oil: 500 l/h

s.s 300 000 12 3 600 000

W-Esp • vg = 46.5 m3/s s.s 1 100 000 4.1 4 510 000

Hydrogenation • 3 000 rh =

m3gas/(m3cat·h)

• h = 5.7 m

• D = 3.9 m

• vg = 35 m3/s

s.s 60 000 12 720 000

WGS reactor • 5 000 rh =

m3gas/(m3cat·h)

• h = 3.9 m

• D = 1.05 m

• vg = 12 m3/s

s.s 60 000 12 720 000

MDEA s.s 18 072 289

Compressor 1 • 24 MPa

s.s 4 000 000 6.3 25 200 000

Compressor 2 • 2 bar 15 000 6.3 100 000

Compressor 3 Maintain pressure in the

system. ΔP ~ 3 bar

s.s 1 500 000 6.3 9 450 000

Chimney - -

Desulfurization 3 614 457

TOTAL 65 986 746

Page 54: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

51

Table 10. All costs for hydrolysis and total TREMPTM with utilities steps.

Unit op. Operating

conditions

Material Cp FaBM CBM (USD)

Hydrolysis • 1 000 rh

• Gas flow rate =

20.3 m3/s

• Catalysts

Stainless steel 70 000 12 840 000

TREMP Reactor 1 • 5 000 rh

• Gas flow rate =

1.2 m3/s

• D = 1.2 m

• h = 1.9 m

Stainless steel 14 000 20 280 000

TREMP Reactor 2 • 3 000 rh

• Gas flow rate =

0.7 m3/s

• D = 0.9 m

• h = 2.6 m

Stainless steel 9 000 20 180 000

TREMP Reactor 3 • 3 000 rh

• Gas flow rate =

0.5 m3/s

• D = 0.8 m

• h = 2.6 m

Stainless steel 9 000 20 180 000

TREMP Reactor 4 • 3 000 rh

• Gas flow rate =

0.2 m3/s

• D = 0,5 m

• h = 2.6 m

Stainless steel 6 000 20 120 000

Pump 2

Pump 4

Pump 5

• 500 l/h

• rho = 800 kg/m3

• Δh = 15 m

• Centrifugal

Stainless steel 8500 5 127 500

Pump 8 • 5 l/s (Water)

• ΔP = 99 bar

• Fp = 2.75

• Fm = 1.9

Stainless steel 20 000 10 200 000

TOTAL 1 927 500

Page 55: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

52

TOTAL CAPITAL COST

(∑(𝐶𝐵𝑀)𝑖

𝑛

𝑖=1

) = 1 927 500 + 65 986 746 + 4 410 000 + 7 300 000 = 79 630 000 𝑈𝑆𝐷

As the brown field erection is considered an upgrade, the fauxiliary factor is set to 1.00 for this

plant.

𝐶𝑜𝑠𝑡$ 2004 = (∑(𝐶𝐵𝑀)𝑖

𝑛

𝑖=1

) · 𝑓𝑓𝑒𝑒𝑠 · 𝑓𝑎𝑢𝑥𝑖𝑙𝑖𝑎𝑟𝑦

Where ffees is about 1.15 and fauxiliary = 1.30 for green field plants.

𝐶𝑜𝑠𝑡𝑏𝑟𝑜𝑤𝑛 𝑓𝑖𝑒𝑙𝑑 = 79 630 000 · 1.15 · 1.00 ≈ 91 600 000 𝑈𝑆𝐷

𝐶𝑜𝑠𝑡𝑔𝑟𝑒𝑒𝑛 𝑓𝑖𝑒𝑙𝑑 = 79 630 000 · 1.15 · 1.30 ≈ 119 040 000 𝑈𝑆𝐷

The costs for the brown field and green field installations are converted from USD in 2004 to

Swedish crowns (kr) in 2012 which is seen below.

𝐶𝑜𝑠𝑡𝑘𝑟 2012 = 𝐶𝑜𝑠𝑡$ 2004 ∙ 𝑉𝐾𝐾 ∙𝐼𝐴𝐾 2012𝐼𝐴𝐾 2004

VKK is the exchange rate (7.3 kr/USD) from Ulrich database. IAK is equipment construction cost

index for Swedish currency. Where IAK 2012 is 148 and IAK 2004 is 115.

The cost for brown field was calculated to 860 Mkr and green field to 1 118 Mkr. The annual

net income was 130 Mkr/yr.

WASTE TREATMENT

Disposal cost for poisoned catalyst has been neglected.

CATALYST COST

In table 11, all the different costs for catalysts have been compiled. The lifetime of the catalysts

is about 3 years. The price for each catalyst was received from the course supervisors.

Table 11. Total cost for catalysts and the different catalyst based process utilities.

Hydrolysis WGS TREMP

I

TREMP

II

TREMP

III

TREMP

IV

Hydrogenation

Flow 20 11 1 1 0 0 35

Vmax 3 3 1 1 1 1 3

Rh 1 000 5 000 5 000 3 000 3 000 3 000 3 000

Volume 95 11 1 1 1 0 55

Area 7 4 1 1 0 0 12

Diameter 3 2 1 1 1 1 4

height 15 4 2 3 3 3 6

price 30 31 50 50 50 50 70

cost USD 3 155 083 366 176 62 169 56 125 38 856 17 269 4 230 954

TOTAL (USD) 7 926 632

Page 56: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

53

ANNUAL NET INCOME

The resulting costs for the “base case” process was calculated and compiled in table 12 below.

These values correspond to up to date prices. However, the price for SNG is set to

approximately 50 % higher than for natural gas. The steam price depend on the demands of the

surroundings. In the base case, bark was assumed to be purchased at 37 kr/GJ, SNG to be sold

at 124 kr/GJ and steam to be sold for 90 kr/GJ.

If Värö would invest in building a new SNG production, the annual extra income would be

approximately 154 Mkr/yr. Table 12 shows the results from made payback method using both

Eq(22) without interest rate, and Eq(23) with (X) as interest rate. The interest rate is set to be

10 % in these calculations.

Using Eq(22) the payback time was received, where G is the total investment cost and a is the

annual net income. The calculations were made with MATLAB, a script is shown in Appendix

D.

𝑇𝑃𝑎𝑦𝑏𝑎𝑐𝑘 = 𝐺

𝑎 𝐸𝑞(22)

In regards of the interest rate using the payback method the outcome differs.

𝑛 = −(ln(1 − 𝐺 ∙

𝑋

𝑎)

ln(1 + 𝑋)) 𝐸𝑞(23)

Page 57: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

54

Table 12. Compiled list for the base case scenario.

Investment G (kr) 860 000 000

Residual value 0

Yearly incomes and costs

Number of employees (st) 10

Salary/person (kr/yr) 750 000

Salary (kr/yr) 7 500 000

Maintenance (kr/yr) 43 000 000

Steam

Steam price (kr/GJ) 90

Steam production (GJ/yr) 560 000

Steam sales (kr/yr) 50 400 000

Bark

Bark price (kr/GJ) 37

Bark input (GJ/yr) 6 220 800

Bark purchase (kr/yr) 230 169 600

Restricted equity in bark (kr) 225 000

SNG

SNG price (kr/GJ) 124

SNG production (GJ/yr) 2 908 224

SNG sales (kr/yr) 360 619 776

Catalyst

Cost (kr/yr) 2 670 000

Annual net income

a (kr/yr) 130 000 000

Interest rate (10 %) 0.1

Payback T = G/a

T (yr) 6.7

Payback with interest rate (10 %)

n (yr) 11.8

To visualize the sensitivity and the influence of market prices, a sensitivity analysis was carried

out based on fluctuating bark prices, SNG-prices and steam prices. Also, the number employees

at the plant was changed to develop an understanding of where the costs are located.

As can be seen in figure AI.1 a slight increase of the bark price would have large unfavorable

impact on the payback time. As much as a few percent would lead to significant changes in the

process economy.

Page 58: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

55

Figure AI.1. Fluctuating bark prices and payback time. Higher bark prices would lead to a significant change in

payback time.

In figure AI.2 an increase in SNG prices would lead to shorter payback times. In figure AI.3

the payback time is visualized towards the price of which the steam could be sold.

Figure AI.2. Changes in SNG prices and its impact on payback time.

15 20 25 30 35 40 454

6

8

10

12

14

16

18

20

22

24Payback

Bark price kr/GJ

Payback t

ime in y

ears

110 120 130 140 150 160 1704

6

8

10

12

14

16

18

20Payback

SNG price kr/GJ

Payback t

ime in y

ears

Page 59: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

56

Figure AI.3. Payback time versus steam price. The importance of selling the steam to a high price to receive a good,

short payback time.

As can be seen in figure AI.4 the payback time is not as sensitive to change in number of

employees as in change of bark price, SNG-price and steam price.

Figure AI.4. Payback time versus number of employee. Cost dependence on how many employee’s working at the

site.

20 30 40 50 60 70 80 90 10010

15

20

25

30

35

40Payback

Steam price kr/GJ

Payback t

ime in y

ears

10 12 14 16 18 20 22 24 26 28 3011.5

12

12.5

13

13.5

14

14.5

15

15.5Payback

Number of employee

Payback t

ime in y

ears

Page 60: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

57

Figure AI5 shows a sensitivity analysis over the investment cost for the plant shifting ±30 %.

Figure AI.5. Payback time versus investment cost, shifting ±30 %.

6 7 8 9 10 11 12

x 108

5

10

15

20

25

30

35

40Payback

Investment cost kr

Payback t

ime in y

ears

Page 61: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

58

APPENDIX C ASPEN FLOWSHEET

Simulations using aspen is compiled below. These were modelled one by one instead of a total

flow sheet. Figure AB1 consists of the OLGA utility which was simulated using only two

vertical vessels instead of three.

Figure AB1. Simulation of the OLGA utilities. Two vertical vessels in which tars and particulates are removed

from the product gas.

Page 62: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

59

Figure AB2. This process sheet consists of the hydrogenation, hydrolysis and WGS apparatus followed by the

MDEA-PZ absorption column.

The TREMPTM was simulated using the flow sheet in Figure AB3. However, in stream S2, one

compressor should be installed to increase the pressure to about 24 bar. This simulation was

done outside the simulation below.

Figure AB3. Simulation of TREMPTM using Aspen. Two compressors are missing from this flow sheet because the

compressors were simulated outside the process sheet.

Page 63: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

60

APPENDIX D MATLAB SCRIPT

N=100; G=860e6; Personal=10; lon=750e3*Personal; p=0.1; %kalkylränta n=20; %livslängd Eout=linspace(1,1,N)*55*1.7/1000*3600*24*360; %GJ/år %Eout=transpose(Eout) Ein=linspace(1,1,N)*200/1000*3600*24*360; %GJ/år Esteam=linspace(1,1,N)*560000; %Ein=transpose(Ein) PriceOut=linspace(115,84*2,N); %PriceOut=transpose(PriceOut); PriceIn=linspace(42,37/2,N); %PriceIn=transpose(PriceIn) PriceSteam=linspace(20,100,N); A1=-G*p/(1-(1+p)^(-n))+(Eout.*PriceOut+90*Esteam(1,1)-Ein(1,1)*37-

G*0.05-lon-8e6/3); PB1=-log(1-(G./(Eout.*PriceOut+90*Esteam(1,1)-Ein(1,1)*37-G*0.05-lon-

8e6/3))*p)/(log(1+p)); %surf(PriceOut,PriceIn,Income) figure(1) plot(PriceOut,PB1,124,-log(1-G./(Eout(1,1)*124+90*Esteam(1,1)-

Ein(1,1)*37-G*0.05-lon-8e6/3)*p)/(log(1+p)),'*') title('Payback') xlabel('SNG price kr/GJ') ylabel('Payback time in years') grid

figure(2) A2=-G*p/(1-(1+p)^(-n))+(Eout(1,1)*124+90*Esteam(1,1)-Ein.*PriceIn-

G*0.05-lon-8e6/3); PB2=-log(1-G./(Eout(1,1)*124+90*Esteam(1,1)-Ein.*PriceIn-G*0.05-lon-

8e6/3)*p)/(log(1+p));

plot(PriceIn,PB2,37,-log(1-G./(Eout(1,1)*124+90*Esteam(1,1)-

Ein(1,1)*37-G*0.05-lon-8e6/3)*p)/(log(1+p)),'*') title('Payback') xlabel('Bark price kr/GJ') ylabel('Payback time in years') grid

figure (3) A3=-G*p/(1-(1+p)^(-n))+(Eout(1,1)*124+Esteam.*PriceSteam-Ein(1,1)*37-

G*0.05-lon-8e6/3); PB3=-log(1-G./(Eout(1,1)*124+Esteam.*PriceSteam-Ein(1,1)*37-G*0.05-

lon-8e6/3)*p)/(log(1+p)); plot(PriceSteam,PB3,90,-log(1-G./(Eout(1,1)*124+90*Esteam(1,1)-

Ein(1,1)*37-G*0.05-lon-8e6/3)*p)/(log(1+p)),'*') title('Payback') xlabel('Steam price kr/GJ') ylabel('Payback time in years') grid

Page 64: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

61

figure (4) dPersonal=linspace(10,30); dlon=750e3*dPersonal; plot(dPersonal,-log(1-G./(Eout(1,1)*124+90*Esteam(1,1)-Ein(1,1)*37-

G*0.05-dlon-8e6/3)*p)/(log(1+p))) title('Payback') xlabel('Number of employee') ylabel('Payback time in years') grid

figure (5) A3=-G*p/(1-(1+p)^(-n))+(Eout(1,1)*124+Esteam.*PriceSteam-Ein(1,1)*37-

G*0.05-lon-8e6/3); dG=linspace(0.7*G,1.3*G,N) PB3=-log(1-dG./(Eout(1,1)*124+90*Esteam(1,1)-Ein(1,1)*37-dG.*0.05-

lon-8e6/3)*p)/(log(1+p)); plot(dG,PB3,G,-log(1-G./(Eout(1,1)*124+90*Esteam(1,1)-Ein(1,1)*37-

G*0.05-lon-8e6/3)*p)/(log(1+p)),'*') title('Payback') xlabel('Investment cost kr') ylabel('Payback time in years') grid

Page 65: Feasibility study of gasification of biomass for … study of gasification of biomass for synthetic natural gas (SNG) production ... This project was carried out in the course

62

Calculation References

38 Forest Research Laboratory; Shool of forestry; Oregon April 1976 research Paper 31. “Properties and

uses of Bark as an Energy Source”; Stanley E. Corder; Table 4 ”A summary of Some published Ultimate

Analyses of bark.

39 Forest Research Laboratory; Shool of forestry; Oregon April 1976 research Paper 31. “Properties and

uses of Bark as an Energy Source”; Stanley E. Corder; Table 2 ” A Summary of Some Published Heating

Values and Ash Contents for Bark of Coniferous Species.”.

40 Forest Research Laboratory; Shool of forestry; Oregon April 1976 research Paper 31. “Properties and

uses of Bark as an Energy Source”; Stanley E. Corder; P.9 Bulk density

41 T. R. Nunn, J.B. Howard, J.P. Longwell, W. A. Peters; Product Compositions and Kinetics in the

Rapid Pyrolysis of Sweet Gum Hardwood, Ind. Eng. Chem. Process Des. Dev., 1985, 24, 3, 836-844

42 Richard. N, Thunman H; General equations for Biomass Properties, Chamers University, August 2002,

P. 10

43 H. Thunman, F. Niklasson, F. Johnsson, B. Leckner; Composition of Volatiles Gases and

Thermochemical Properties of Wood for Modelling of Fixed or Fluidized Beds, Energy & Fuels, 2001,

15, 1488-1497

44 A. Demirbas, Properties of charcoal derived from hazelnut shell and the production of briquettes using

pyrolytic oil, Energy, 1999, 24, 141-150 45 J.M. Encinar, J.F. Gonzàlez, J. Gonzàlez; Fixed-bed pyrolysis of Cynara cardunculus L. Products

yields and compositions, Fuel Processing Technology, 2000, 68, 209-222

46 Alveteg M. “Handbook”, Department of Chemical Engineering. Faculty of Engineering Lund

University of technology. P31 Table 3.5