February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management Dennis J. Frailey

Upload: constance-lyons

Post on 13-Dec-2015

218 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

February 15, 2004

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

Simple Steps for Effective Software Risk Management

Dennis J. Frailey

Page 2: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

2 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

Objective

• To present some basic risk management techniques – Some of these are not widely used

• And some basic elements of a risk management plan

Page 3: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

3 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

Frequent Problems

• No consensus on what the real risks are

• Different perspectives on necessary level of risk decomposition

• Vague processes for risk management

• Poor risk assessment• Confusion between mitigation and

abatement (contingency actions)

Page 4: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

4 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

Recommended Solutions

• A clear risk management process– Defining risk properly– A consistent analysis/assessment procedure– Specific steps for identification, analysis,

mitigation, monitoring and abatement

• A good risk management plan– Defining who does what, when and how– Checklists to make sure the process is

followed– Decomposition to a level where specific

causes are identified

Page 5: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

February 15, 2004

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

The Risk Management Process

1) Risk Assessment • The things you do as you plan

your project

2) Risk Control• The things you do during the

project

Page 6: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

6 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

1) Risk Assessment

A) Risk Identification- Clearly stating the real risks

B) Risk Analysis- Causes, categories, impact

C) Risk Prioritization- Which risks should get the attention?

D) Risk Planning & Mitigation- Minimizing impact- Planning contingency actions

Page 7: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

7 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

Risk Management Plan Should Indicate …

• What process you have already followed to identify, analyze, prioritize, and mitigate risks– What risks you have identified• And the evidence that you base this on

– How you have analyzed these risks– How you have prioritized them– How you have mitigated them

Page 8: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

8 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

2) Risk Control

A) Risk Monitoring

- Watching to see if risks happen

B) Risk Abatement

- Counteracting risks

- Taking contingency actions as needed

C) Updating the Plans

Page 9: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

9 Software Risk Management

Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved

February 15, 2004

Risk Management Plan Should Indicate …

• What process you will follow during the project to control risks– How you will monitor them (this

usually ties strongly to your measurement plan)

– How you will abate risks (contingency plans, ongoing mitigation)

• And what process you will use to keep the plan up to date– Ongoing assessment, updating of

plans, priorities, etc.

Page 10: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

February 15, 2004

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

Details

Page 11: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

11

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

A) Risk Identification

• Risks are:– things that can go wrong – patterns of risk change over the

lifecycle• for example, cost estimating risks occur

early, whereas risks of staff burnout occur later

• If it has already happened, or is certain to happen, it is a problem, not a risk!– You should be discussing your action plan

for managing the problem

Page 12: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

12

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

How to State a Risk• Indicate the problem and the cause– “The project might be late”

This doesn’t say much. Why might it be late?

– “There might be employee turnover”So what? This states the cause but not the

problem

– “The project might be late due to employee turnover”Good. This states both the cause and the

problem

Page 13: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

13

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

B) Risk AnalysisPartition Into Categories

• Sample Categories:-- cost risks

-- schedule risks -- other management risks -- technical risks -- other risks specific to the situation,

such as safety or security risks• One Risk may have multiple categories– Estimating inaccuracies can lead to cost and

schedule risks

Page 14: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

14

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

B) Risk AnalysisIdentify Contributing Factors

• Many risks can occur in several ways (from several causes)

• If you aren’t careful, you will only be looking for one of the ways

• You need to get to the actual causes

Page 15: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

15

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

Example of Multiple Contributing Factors

Risk: Not enough memory to hold the softwarePossible Contributing Factors (causes): Size of computer memory is too small Expertise of programming staff too low Inefficiency of compiler Choice of algorithms – too large Operating system requires too much space

Page 16: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

16

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

Using a Hierarchy of Contributing

Factors• Each risk can be seen as a

contributing factor to a larger risk• The top level risk is that the

project will fail• Sometimes it helps to use a

hierarchy to organize risks and contributing factors

• (See next slide)

Page 17: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

17

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

A Sample Risk Hierarchy

Staffing Funding . . .

ProcessorToo Slow

. . .

Size ofMemory

ProgrammingExperience

CompilerEfficiency

Choice ofAlgorithms

MemoryToo Small

PerformanceFailure

ProjectFailure

Page 18: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

18

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

C) Risk PrioritizationRank the Risks

• Prioritize on the basis of probability (how likely) and impact

Risk Likelihood Cost

Weighted

CostLate Hardware 75% 100,000 75,000

Sub-Contractor Failure 20% 250,000 50,000

Memory Size 50% 50,000 25,000

Test Equipment Delay 30% 40,000 12,000

Requirements Changes 99% 5,000 4,950

Building hit by plane 0.0001% 50,000,000 50

You cannot prevent all risks - focus on the big ones

Page 19: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

19

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

D) Risk MitigationDoing Something About Risks

BEFORE they happen

Risk: memory size inadequateFactor: Compiler produces bloated codePotential mitigation:

•Choose a more efficient compiler•Negotiate improvements with vendor

Factor: Inexperienced programmersPotential mitigation:

•Training program •Use more experienced programming staff

Page 20: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

20

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

Identify Monitoring Procedures for Each Risk

• Determine how to tell if it is a problem; how frequently to monitor; etc.

• Example: monitor projected size vs. memory limits on a monthly basis

0

50

100

150

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Limit Threshold Estimate

Page 21: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

21

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

Develop a Contingency Plan• Identify what to do if the risk occurs

despite your mitigation efforts

Risk: memory size exceededContingency Plan:

• Switch to a slower but smaller algorithm• Use a more efficient compiler • Use a smaller operating system• Use larger memory size

Page 22: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

February 15, 2004

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

Risk Control

Things You Do During Project Execution

Page 23: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

23

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

Review Status and Take Action

• Review status of risks at periodic reviews (Monitor)– Measurements– Changes in impact analysis

• Take appropriate action when called for (Abatement)– Closer monitoring– Contingency activities

Page 24: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

24

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

Risk Monitoring• Establish thresholds so you know when to

act– Beware of the “frog in the water” problem

– Historical experience is a good basis to judge when things are getting out of hand

Page 25: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

25

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

“Do Your Homework”

• Track all actions to closure (Monitoring)– Don’t forget about them

• Update the plan (Planning)– Keep it consistent with current knowledge

and status– Risks and their priorities will change as you

progress through the project

Page 26: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

26

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

February 15, 2004

The Risk Thread Should be Visible in your Plan

• Risk • Evidence• Analysis• Risk Factors / Causes– There may be many

• Priority• Mitigation• Monitoring• Abatement/Contingency

Page 27: February 15, 2004 Software Risk Management Copyright © 1995-2004, Dennis J. Frailey, All Rights Reserved Simple Steps for Effective Software Risk Management

February 15, 2004

Software Risk ManagementCopyright © 1995-2004, Dennis J. Frailey,

All Rights Reserved

You Cannot Prevent All Risks

But you can Manage Them