 HONOLULU RAIL TRANSIT PROJECT 

 

 

February 2017 MONTHLY PROGRESS REPORT 

  

   

www.HonoluluTransit.org  

  

Page 2: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

2 | P a g e   

    

THIRD PARTY DISCLAIMER This report and all subsidiary reports are prepared for the Federal Transit Administration (FTA). This report should not be relied upon by any party, except the FTA or HART, in accordance with the purposes as described below.  For projects funded through the FTA Full Funding Grant Agreements (FFGAs) program, the FTA and its Project Management Oversight Contractor (PMOC) use a risk‐based assessment process to review and validate a project sponsor’s budget and schedule. This risk‐based assessment process is a tool for analyzing project development and management. Moreover, the assessment process is iterative in nature; any results of an FTA or PMOC risk‐based assessment represent a “snapshot in time” for a particular project under the conditions known at that same point in time. The status of any assessment may be altered at any time by new information, changes in circumstances, or further developments in the project, including any specific measures a sponsor may take to mitigate the risks to project costs, budget, and schedule, or the strategy a sponsor may develop for project execution. Therefore, the information in the monthly reports will change from month to month, based on relevant factors for the month and/or previous months.  

REPORT FORMAT AND FOCUS This report is submitted in compliance with the terms of FTA Contract No. DTFT60‐09‐D‐00012, Task Order No. 2. Its purpose is to provide information and data to assist the FTA as it continually monitors the grantee’s technical capability and capacity to execute a project efficiently and effectively, and hence, whether the grantee continues to be ready to receive federal funds for further project development.   This report covers the project and quality management activities on the Honolulu Rail Transit Project managed by the Honolulu Authority for Rapid Transportation (HART) with HART as the grantee and partially financed by the FTA FFGA.                            ON THE COVER: Left: Station construction at the Ho‘opili Station site. Upper right: West Loch Station construction. Lower right: Construction at the Pearlridge Station site.   

Page 3: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

3 | P a g e   

TABLE OF CONTENTS  

LIST OF ACRONYMS ......................................................................................................................................................... 4  

PROJECT MAP .................................................................................................................................................................. 7  

1     SUMMARY ................................................................................................................................................................ 8  

2     OVERALL PROJECT PROGRESS AND FINANCIALS .................................................................................................... 10 2.1 Project Progress ............................................................................................................................................... 10 2.2 Project Budget ................................................................................................................................................. 12 2.3 Project Contingency ......................................................................................................................................... 12 2.4 Project Funding  ............................................................................................................................................... 13 

 

3     SCHEDULE ............................................................................................................................................................... 14  

4     CONTRACT STATUS ................................................................................................................................................. 16 4.1 System‐Wide .................................................................................................................................................... 17 4.2 Section I – West O‘ahu/Farrington Highway: East Kapolei to Pearl Highlands ................................................ 24 4.3 Section II – Kamehameha Highway: Pearl Highlands to Aloha Stadium .......................................................... 32 4.4 Section III – Airport: Aloha Stadium to Middle Street Transit Center Station ................................................. 38 4.5 Section IV – City Center: Middle Street Transit Center Station to Ala Moana Center ..................................... 42 4.6 Contract Status ................................................................................................................................................ 45 

 

5     OVERALL PROJECT‐WIDE ACTIVITIES ...................................................................................................................... 50 5.1 Permits ............................................................................................................................................................. 50 5.2 Hawai‘i Department of Transportation (HDOT) Agreements .......................................................................... 50 5.3 Utility Agreements ........................................................................................................................................... 51 5.4 Right‐of‐Way .................................................................................................................................................... 53  

6     MANAGEMENT AND ADMINISTRATIVE UPDATES .................................................................................................. 58 6.1 Safety and Security .......................................................................................................................................... 58 6.2 Quality Management ....................................................................................................................................... 63 6.3 Buy America Compliance ................................................................................................................................. 64 6.4 Disadvantaged Business Enterprise (DBE) ....................................................................................................... 64 6.5 Planning and Environment ............................................................................................................................... 64 6.6 Risk Management ............................................................................................................................................ 65 6.7 Community Outreach....................................................................................................................................... 66 6.8 Staffing ............................................................................................................................................................. 67 6.9 Operations and Maintenance (O&M) .............................................................................................................. 68  

APPENDICES .................................................................................................................................................................. 69 A. Project Contingency Management ................................................................................................................. 70 B. Project Cost Reports ....................................................................................................................................... 75 C. Project Organization Chart .............................................................................................................................. 78 

 

TABLE OF FIGURES  

Figure 1. Overall Project Progress (% Complete) ...................................................................................................... 10 Figure 2. Construction Progress (% Complete) .......................................................................................................... 10 Figure 3. Design Progress (% Complete).................................................................................................................... 11 Figure 4. Utilities Progress (% Complete) .................................................................................................................. 11 Figure 5. Planned vs. Received Project Funding ........................................................................................................ 13 Figure 6. New Starts Drawdown by Federal Fiscal Year ............................................................................................ 13 Figure 7. HRTP Master Project Schedule Summary (MPSS) ...................................................................................... 15 Figure 8. Right‐of‐Way Status for the Parcels ........................................................................................................... 53 Figure 9. Relocation Status for the Occupants .......................................................................................................... 54 Figure 10. Inter‐Governmental Agreement Status .................................................................................................... 54 Figure 11. Staffing Activities ...................................................................................................................................... 67  

Page 4: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

4 | P a g e   

LIST OF ACRONYMS  

A&E  Architect/Engineer AB  AnsaldoBreda 

ACHP  Advisory Council on Historic Preservation ACS  Access Control System AFA  Air Force Association AFE  Authorized for Expenditure AGS  Airport Guideway and Stations AHJV  Ansaldo Honolulu Joint Venture AIS  Archaeological Inventory Survey 

APTA  American Public Transportation Association ARRA  American Recovery and Reinvestment Act ASG  Airport Station Group ASU  Airport Section Utilities ATC  Automatic Train Control ATO  Automated Train Operation AVA  Anil Verma Associates, Inc. BA  Buy America 

BAC  Buy America Compliance  BACM  Buy America Compliance Matrix BAFO  Best and Final Offer BART  Bay Area Rapid Transit BCS  Balanced Cantilever System BFS  Budget and Fiscal Services BLS  Bureau of Labor Statistics BMP  Best Management Practice BOD  Board of Directors BPS  Baseline Project Schedule BUE  Bottom‐Up Estimate 

BUEG  Back‐up Emergency Generator CAM  Construction Access Milestone CAR  Corrective Actions CCGS  City Center Guideway and Stations CCO  Contract Change Order CCTV  Closed Circuit Television CDC  Compendium of Design Criteria CDL  Commercial Driver License CDR  Conceptual Design Review CE&I  Construction Engineering and Inspection CEL  Certifiable Elements List CIC  Communication Interface Cabinet CIL  Certifiable Items List CIP  Cast‐in‐place CJA  Condon‐ Johnson & Associates CM  Construction Manager 

CMP    Corrugated Metal Pipe CMS  Contract Management System CMU  Concrete Masonry Unit 

CNMMP  Construction Noise Mitigation and Monitoring Plan CO  Certificate Occupancy COI  Conflict of Interest 

COMMs  Communications CONRAC  Consolidated Rental Car Facility 

COR  Corporation Counsel CP  Consulting Party 

CPM  Critical Path Method CPO  Chief Procurement Officer CPP  Contract Packaging Plan 

CRMS  Customer Relational Management System CROE  Construction Right‐of‐Entry CSC   Core Systems Contract  

CSCC  Construction Specification Conformance Checklists CSL  Cross Hole Sonic Logging 

CSOC  Core Systems Oversight Consultant CSSP  Construction Safety & Security Plan CTS  Communications Transmission System CWR  Continuous Welded Rail 

CWRM  Commission on Water Resource Management CZM  Coastal Zone Management DAGS  Department of Accounting & General Services 

DB   Design‐Build  DBB   Design‐Bid‐Build  

DBE Disadvantaged Business Enterprise DBEDT Department of Business, Economic Development and TourismDBOM  Design‐Build‐Operate‐Maintain  DCAB Disability and Communication Access BoardDCCC Design Criteria Conformance ChecklistsDCN Design Change Notice DDC Department of Design and ConstructionDES Department of Environmental Services DFF Direct Fixation Fastener 

DFIM Design Furnish Install Maintain DFM Department of Facility Maintenance DHHL  Department of Hawaiian Homelands  DHR Department of Human Resources DIT Department of Information Technology

DKSG Dillingham and Kaka‘ako Station GroupDLIR Hawai‘i Department of Labor and Industrial RelationsDLNR  Department of Land and Natural Resources DOE Department of Education DOH Department of Health DOL Department of Labor DPM Deputy Project Managers DPP Department of Planning and PermittingDPR Department of Parks and Recreation DPS Department of Public Safety DS DownstreamDTS Department of Transportation ServicesDTU Dillingham Temporary Utilities DVT Design Verification Test EAC Estimate at Completion ECP Environmental Compliance Plan E/E Elevator/EscalatorEK East Kapolei

EMC Electromagnetic Compatibility EMF Electromagnetic Forces EMI Electromagnetic Interference EMP Environmental Management Plan EOR Engineer of RecordEOS Electrically Operated Switch ESA Engineering Services Agreement FAA Federal Aviation Administration FAI First Article Inspection FAT Factory Acceptance Tests FCN Field Change Notice FD  Final Design 

FDAS Fire Detection Alarm System FDC Field Design Change FDR Final Design Review FEIS  Final Environmental Impact Statement FFC Fixed Facility Contractors 

FFGA  Full Funding Grant Agreement  FHSG Farrington Highway Station Group FHWA Federal Highway Administration FISC Fleet and  Industrial Supply Center 

FLSWG Fire Life Safety Working Group FOCN Fiber Optic Communication Network FPO Federal Preservation Officer FTA  Federal Transit Administration  FTE Full‐Time Equivalent FWS Fish and Wildlife Service GAT Great Aleutian Tsunami GBS Gap Breaker Station GDR Geotechnical Data Report GEC  General Engineering Consultant  GET  General Excise Tax GIS Geographic Information System GPR Ground Penetrating Radar GSA  General Services Administration  GT General TermsHA Hazard Analysis

HABS Historic American Buildings Survey HAER Historic American Engineering Record 

Page 5: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

5 | P a g e   

HALS  Historic American Landscape Survey HART   Honolulu Authority for Rapid Transportation  HCC  Honolulu Community College 

HCDA  Hawaii Community Development Authority HCSD  Hawai‘i Capital Special District HDCC  Hawaiian Dredging Construction Company HDOE  Hawai‘i Department of Education HDOH  Hawai‘i Department of Health HDOT   Hawai‘i Department of Transportation  

HDOT‐A    Hawai‘i Department of Transportation Airports DivisionHDPE  High‐density polyethylene HECO  Hawaiian Electric Company  HFD  Honolulu Fire Department HHF  Historic Hawai‘i Foundation 

HHFDC  Hawaii Housing Finance & Development CorporationHHPRB  Hawai‘i Historic Places Review Board 

HIE  Hawaii Independent Energy HILT  Hawaiian Islands Land Trust 

HIOSH  Hawaii Occupational Safety and Health Division HP  Historic Preservation 

HPC  Historic Preservation CommitteeHPCA  Historic Preservation Certification Application HPD  Honolulu Police Department HPF  Historic Preservation Fund 

HRHP  Hawai‘i Register of Historic Places HRI  Hitachi Rail Italy 

HRTP  Honolulu Rail Transit Project HRU  Hitachi Rail USA, Inc. HTI  Hawaiian Telcom HTL  Hazard Tracking Log HV  High Voltage  

HVAC    Heating, Ventilation and Air Conditioning I&T  Inspection & Testing 

IAMR  Interstate Access Modification Report IC  Interim Certification 

ICCS  Integrated Communications Control System ICD  Interface Control Documents ICE  Independent Cost Estimate ICM  Interface Control Manual 

ICWG  Interim Certification Working Group IDS  Intrusion Detection System IFB  Issued for Bid IFC  Issued for Construction IJ  Isolation Joint 

INMS  Integrated Network Management System IP  Implementing Procedures ITP  Inspection and Test Plan ITS  Intelligent Transportation Systems IVR  Interactive Voice Response 

JTMS  Joint Traffic Management System JU&O  Joint Use & Occupancy JUOA  Joint Use and Occupancy Agreement 

JV  Joint Venture  KCDD  Kaka‘ako Community Development District KCH  Kanehili Cultural Hui KHG   Kamehameha Highway Guideway KHSG  Kamehameha Highway Station Group KIWC  Kiewit Infrastructure West Company KKJV  Kiewit/Kobayashi Joint Venture LCC   Leeward Community College  

LEED   Leadership in Energy and Environmental Design   LPR  License Plate Reader LRV  Light Rail Vehicle MIM  Manufacture‐Install‐Maintain MITT  Multimodal Integration Technical Team MMIS  Maintenance Management Information System MMP  Mitigation Monitoring Program MOS  Minimum Operable Segment MOT   Maintenance of Traffic  MOU  Memorandum of Understanding MOW  Maintenance of Way MPS   Master Project Schedule  MPSS  Master Project Schedule Summary MPV  Multiple Purpose Vehicle 

MS4 Municipal Separate Storm Sewer SystemMSE Mechanically Stabilized Earth MSF  Maintenance and Storage Facility  MTM Modern Track Machineries NCE Non‐Conformance Evaluation NCR  Non‐Conformance Report  NDC Notice of Design Change  NEPA National Environmental Policy Act NHL National Historic Landmark NOI Notice of Intent

NPDES National Pollutant Discharge Elimination SystemNPS National Park Service NR National Register

NRHP National Register of Historic Places NSM Negotiation Strategy Memo NTP  Notice to Proceed NTS Network Time Server 

O&M Operations and Maintenance OCC Operations Control Center OCCL Office of Conservation and Coastal LandsOCIP  Owner‐Controlled Insurance Program  OIBC O‘ahu Island Burial Council OIL Open Items List

OMPO Oahu Metropolitan Planning OrganizationORCC Operational Readiness Conformance ChecklistsOSB Operations and Servicing Building 

OSHA Occupational Safety and Health AdministrationOTS O‘ahu Transit Services OTW Oceanic Time Warner 

OTWC Oceanic Time Warner Cable P3 Public‐private partnership PA  Programmatic Agreement  

PAIS Programmatic Agreement Implementation SchedulePARs Preventative Actions PB Parsons Brinckerhoff, Inc. PCI Payment Card Industry PDR Preliminary Design Review PE  Preliminary Engineering  

PGC Pacific Guardian Center PHA Preliminary Hazard Analysis PHPR Pearl Highlands Park and Ride PICM Project Interface Control Manual PIG Permitted Interaction Group PIM Project Interface Manager PLA Project Labor Agreement PLO Priority‐Listed Offerors PM Project Managers

PMC  Project Management Consultant  PMIM Project Management and Interface ManagementPMOC  Project Management Oversight Contractor PMP Project Management Plan PMSC Program Management Support ConsultantPPE Personal Protective Equipment 

PRTCC Pre‐revenue Testing Conform ChecklistPSG Platform Screen Gate PSGS Platform Screen Gate System PSIT Pre‐shipment Inspection Test PUC Public Utilities Commission PUP Property Utilization Plan PV Passenger VehicleQA Quality Assurance

QAM Quality Assurance Manager QAP Quality Assurance Plan QC Quality Control

QMP  Quality Management Plan  QMS Quality Management System QTF Quality Task ForceR&R Revise & Re‐submitRAC Rail Activation Committee   

RAMP Real Estate Acquisition and Relocation Management PlanRCMP  Risk and Contingency Management Plan RCP Reinforced Concrete Pipe RE Resident Engineer

READ Real Estate Acquisition Database 

Page 6: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

6 | P a g e   

RFC  Request for Change RFHB  Request for High Bids RFI  Request for Information 

RFID  Requests for Interface Data RFMP   Rail Fleet Management Plan  RFP   Request for Proposals  RFQ   Request for Qualifications  ROC  Rail Operations Center ROD  Record of Decision ROE  Right of Entry ROW  Right‐of‐Way RR  Risk Register 

RSD  Revenue Service Date RTM  Requirements Traceability Matrix RTSA  Regional Transit Stabilization Agreement S&S  Safety and Security S1  Segment 1 

SAIS  Supplemental Archaeological Inventory Survey SCADA  Supervisory Control and Data Acquisition SCAP  Stream Channel Alteration Permit SCC  Standard Cost Category 

SHPD  State Historic Preservation Division SHPO  State Historic Preservation Officer 

SIC  Sandwich Isle Communications SIT  System Integration Testing 

SLAN  Station Local Area Network SOG  Slab on Grade SOI  Secretary of the Interior 

SOW  Scope of Work SP  Special Provisions 

SQP  Supplemental Quality Plan SSC  Safety Security Certification 

SSCP  Safety and Security Certification Plan SSCWG  Safety and Security Certification Working Group 

SSI  Sensitive Security Information SSMP  Safety and Security Management Plan SSRC  Safety and Security Review Committee SSSP  Site Safety Security Plan STCC  Specification/Testing Conformance Checklists STG  Shimmick/Traylor/Granite, JV 

SWPPP  Storm Water Pollution Prevention Plan T&M  Time and Material TAP  Transportation Alternatives Program TC  Train Control 

TCCR  Train Control and Communications Room TCE  Temporary Construction Easement TCO  Temporary Certificate Occupancy TCP  Traffic Control Plan TCS  Train Control System TES  Traction Electrification System 

TIGER  Transportation Investment Generating Economic RecoveryTIP  Transportation Improvement Program TOC  The Outdoor Circle TOD  Transit‐Oriented Development TPO  Thermoplastic Olefin TPSS  Traction Power Sub‐Station TSA  Transportation Security Administration TSI  Transportation Safety Institute TVA  Threat & Vulnerability Assessments TVM  Ticket Vending Machine TWF  Train Wash Facility UCA  Utility Construction Agreement 

UFRCRA  Utility Facilities Relocation and Cost Reimbursement AgreementUH  University of Hawai‘i 

UHWO  University of Hawai‘i West O‘ahu  UL  Underwriters Laboratories 

UPS  Uninterrupted Power Supply USACE  U.S. Army Corps of Engineers USDOT  U.S. Department of Transportation 

USN  United States Navy VAR  Volt‐Ampere Reactive VE  Value Engineering 

VECP  Value Engineering Change Proposal VRC  Vertical Raceway Column 

VRCS Voice Radio Communication System VRF Variable Refrigerant Flow WA Work AreaWHS Waipahu High School WL West Loch

WLO West LochWOEDA West Oahu Economic Development AssociationWOFH West O‘ahu/Farrington Highway WOSG West O‘ahu Station Group WQC Water Quality Certification WSS West Side Stations

WSSG West Side Station Group WTB Wheel Truing Building WTC Waipahu Transit Center WYL West Yard LeadYCB Yard Control Bungalow YOE  Year of Expenditure 

 

Page 7: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017 

7 | P a g e   

Page 8: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

8 | P a g e   

   

1     SUMMARY  

KEY ACTIVITIES THIS MONTH Project Overview In February, Move Oahu Forward and the Honolulu Authority for Rapid Transportation (HART) held a second public viewing of HART’s Honolulu Train #1. Attendees were able to take a brief entry tour of HART’s state‐of‐the‐art Rail Operations Center as well as walked through the first high‐tech driverless train in the United States. The delivery of Train #2 to Honolulu is planned for April 2017.  

Kapālama Canal Community Workshop The Department of Planning and Permitting held a community workshop in February to discuss initial design plans for a linear park along Kapālama Canal, and how it will be integrated with future development in the area, including rail. The project will feature: 

A bicycle and pedestrian path along the canal 

Complete Streets treatments along Kohou and Kokea Streets 

Small park spaces for community gathering 

Water quality improvements 

New pedestrian bridges.  

Cost:  

Project Costs Summary Through January 27, 2017 

  Current FFGA Budget ($M)  Incurred To Date ($M) 

Project Budget  $4,497.7  $2,511.0 

Project Contingency  $450.9  $0.7 

Finance Charges*  $173.1  $1.0 

TOTAL  $5,121.7  $2,512.7 * $173.1 million represents the project debt financing costs that are federally eligible. The total estimated debt financing costs of the project is $215 million, per the FFGA Financial Plan. 

Schedule: 

Project Progress*Through January 27, 2017 

  Actual    Early FFGA Plan  Late FFGA Plan 

Overall Project Progress  55.7%    89.3%  86.2% 

Overall Construction Progress  49.3%    86.5%  82.7% 

Overall Design Progress  89.5%    100%  100% 

Overall Utilities Progress  56.9%    100%  100% * Reported percentages complete are based on the Full Funding Grant Agreement (FFGA) budget and Revenue Service Date (RSD). HART will revise its progress curves when the project budget and RSD are re‐baselined. 

 

BOARD MEETING Q&A  Listed below are questions raised by community members at the Feb. 16, 2017 HART Board meeting:  

Question: Will HART provide training on how to use the system’s Ticket Vending Machines?   Answer: Yes. The TVMs, as they are known, are designed to operate much like an ATM, or Automatic Teller Machine, at banks and other institutions. They will have screens directing people what to do in steps, and what to do next. There will be 8 languages available on the screen. Passengers can also use audio directions and braille. Printed material and videos will also be produced to provide instructions on how to use both the system’s smart cards and ticket vending machines.    

Question: Will TVMs sell fares in different languages?  Answer: Yes. English, plus Mandarin, Korean, Japanese, Tagalog, Ilocano, Hawaiian and Samoan. There is no existing text to speech for audio with the last four languages listed, so customers will be directed to call our customer service center which will connect them to the City’s simultaneous translation services.  

Question: Will elevators and rail cars contain signage encouraging the public to give priority to the disabled?   Answer: Yes. We will have signs and announcements in the rail cars encouraging the public to give priority to seniors and individuals with disabilities. Currently, we do not have plans for such signs for the elevators, however some can easily be added adjacent to all elevator hoist way doors. 

Page 9: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

9 | P a g e   

PROGRESS REPORT SUMMARY OF CHANGES The following is a brief summary of major changes that have occurred from the previous month’s report. For more information and detail, please refer to the respective pages in the report.  Project Contingency  

$1.1M contingency drawdown during January 2017. Please see page 12.  Project Funding  

The General Excise Tax (GET) Surcharge amount received in January 2017 is $57 million. Please see page 13. 

The total amount of cash received has increased due to the GET surcharge amount received. Please see page 13.   Contract Status  

Contracts in Procurement o The Issue NTP dates for On Call Appraisers “II” and Engineering Design and Design Review Services 

Contractor have been updated to say “As needed.” Please see page 16.  o Dates for the Owner Controlled Insurance Program (OCIP) Contract “II” have been updated. Please see 

page 16. o Legal Counsel for Public Utilities Commission (PUC) Matters has been included on the Active Procurements 

table. Please see page 16.  o A table has been included for upcoming procurements under evaluation. Please see page 16.  

 

Core Systems Contract (CSC) o The weighted value percent complete has been corrected. Please see page 17. 

 

Elevators and Escalators Manufacture‐Install‐Maintain (MIM) o The contract substantial completion date has been updated from June 2018 to July 2018. Please see page 

20. o The late plan percentage has been corrected. Please see page 20. 

 

 West O‘ahu/Farrington Highway (WOFH) o The current contract value amount has decreased due to change orders. Please see page 24.  

 

West O‘ahu Station Group (WOSG) o The NCR log numbers have been corrected to remove voided NCR’s. Please see page 27.  

 

Maintenance and Storage Facility (MSF) o The final acceptance date has changed from March 1, 2017 to May 1, 2017. Please see page 30. 

 

Kamehameha Highway Guideway (KHG) o The current contract value amount has increased due to change orders. Please see page 32. 

 

Airport Section Guideway and Stations (AGS)  o The schedule status has changed from “On time” to “Schedule Under Review.” Please see page 38.  

 

City Center Section Guideway and Utilities Final Design  o The percent complete based on expenditures has been adjusted due to a credit. Please see page 42. o The incurred‐to‐date amount has decreased due to a credit. Please see page 42. 

 Right‐of‐Way (ROW) 

The budget table has been removed as it is being updated and will be included in a future Monthly Progress Report. 

The Inter‐Governmental Agreements table has been updated to more clearly show which agreements have obtained a construction Right of Entry (ROE). Please see pages 54‐57. 

Page 10: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

10 | P a g e   

 

2     OVERALL PROJECT PROGRESS AND FINANCIALS  

2.1   Project Progress (data as of January 27, 2017) Reported percentages complete are based on the Full Funding Grant Agreement (FFGA) budget and Revenue Service Date (RSD). HART will revise its progress curves when the project budget and RSD are re‐baselined. Note: 

Actual = Actual cost of work performed, based on invoiced‐to‐date amount. 

Early Plan = Earliest dates activities can begin and finish, based on logic and durations used in the schedule. 

Late Plan = Latest dates activities can begin and finish and not have an impact on completion date, based on logic and durations used in the schedule. 

 

Figure 1. Overall Project Progress (% Complete) 

 

At present “overall” project progress is based on the weighted value progress of the individual construction and design contracts (Design‐Build [DB], Design‐Bid‐Build [DBB], Design‐Build‐Operate‐Maintain [DBOM], Elevator/Escalator Manufacture‐Install‐Test‐Maintain [MIM], Final Design [FD] and DB‐DBOM design levels of effort), not including City or non‐design consultant labor. Overall Project Progress reflects all project elements as budgeted. 

 

 Figure 2. Construction Progress (% Complete) 

 

Overall construction progress is based on the weighted average progress of the individual DBB and E/E MIM construction contracts and the DB‐DBOM construction levels of effort, not including consultant construction engineering and inspection (CE&I) services. 

Page 11: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

11 | P a g e   

   

Figure 3. Design Progress (% Complete) 

 

Overall design progress is based on the weighted average progress of the individual FD contracts and the design levels of effort of the DB and DBOM construction contracts, not including City or non‐design consultant labor. Note: Design responsibility will be transferred to DB, once DB packages are awarded. Deductive change orders will be issued to correct the total contract amount.  

  

Figure 4. Utilities Progress (% Complete) 

 

Overall utilities progress is based on the weighted average progress of the DB and DBB utilities levels of effort. 

    

Page 12: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

12 | P a g e   

      

2.2  Project Budget (data as of January 27, 2017)  

FFGA Project Budget = $5,121.7M  o Current Project Budget ‐ $4,497.7M o Current Project Contingency ‐ $450.9M o Project Finance Charges ‐ $173.1M  

Total Incurred Cost = $2,512.7M (55.9% of current project budget) o January 2017 Incurred Cost = $48.0M 

 

The FFGA budget was $5.122 billion, as presented in the section above. In 2016, the City and County of Honolulu passed an ordinance to extend the General Excise Tax (GET) to 2027, thereby increasing the current project budget up to $6.8 billion.   

The Project Budget is being updated to reflect current program expectations and will be finalized in collaboration with the Federal Transit Administration (FTA). The Project Management Oversight Contractor’s (PMOC’s) predicted Estimate at Completion (EAC) value, not including finance costs, was $7.623 billion, based on FTA’s Beta Range model. 

    

2.3   Project Contingency (data as of January 27, 2017) Note: A breakdown of Project contingency drawdowns is discussed in further detail in Appendix A.  

Current Project Contingency Balance = $450.9M o Contingency drawdown to date is $192.7M (30% of baseline project contingency budget) o $1.1M contingency drawdown during January 2017. Please see Appendix A for more details. 

 

The Draft Cost Contingency Drawdown Chart is being updated to reflect current program forecast needs, and will be included in a future Progress Report. 

 Note: Project Cost Reports can be found in Appendix B. 

                

Page 13: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

13 | P a g e   

2.4  Project Funding (data as of January 27, 2017) Figure 5. Planned vs. Received Project Funding 

Planned2

($YOE M)

[A] [B] [C] = A +B

Beginning Project Cash Balance3

0 298 298 n/a

Interest Income on Cash Balance 7 3 2 9

FTA Section 5309 New Starts  Revenue4

0 1,550 712 712

ARRA Funds 0 4 4 4

Net General  Excise Tax (GET) Surcharge revenues  FY2010‐FY2028 378 4,816 1,489 1,867

Total 385 6,671 2,505 2,592

1 GET and Interest Income  received during Pre‐Prel iminary Engineering (pre‐PE) phase  prior to entry into PE

2 Update  to FFGA Financia l  Plan, Table  A‑1 Capital Plan Cash Flows  submitted to the  FTA on Dece,ber 1. 2016.

4 New Starts  Funds  Obl igated Through Federal  Fisca l  Year 2014 Totals  $806.3 Mil l ion

Planned vs. Received Project Funding

Funding Source

Pre‐FFGA 

Project1  Project Funding Total Project

2007 ‐ 2009 

Actuals Received

2009 ‐ Present 

Actuals 

Received

2007 ‐ Present 

Actuals Received

3 Beginning Project Cash Balance  at Entry into Prel iminary Engineering (PE) on October 16, 2009 (the  FFGA Project start date) =  Pre‐PE GET, 

inves tment and miscel laneous  income  minus  pre‑PE expenditures .  The  $298 mil l ion i s  included in the  Pre‐FFGA actual  amounts  received 

between 2007‐2009 of $378 mil l ion.

   

General Excise Tax (GET) Surcharge  o $57M = GET surcharge received in January 2017. 

 

Full Funding Grant Agreement (FFGA) o $0 = New Starts drawdown received in January 2017.   

$9.5 million for January was processed after the data date and will be included in Figure 6 next month. 

 Figure 6. New Starts Drawdown by Federal Fiscal Year (data date as of January 27, 2017) 

Federal Fiscal Year (FFY) Allocation

FTA Obligated Amounts

Actual Drawdown Amounts to Date

Available Balance

FFGA Base Case Cash flow

2008 $15,190,000 $15,190,000 $02009 $19,800,000 $19,800,000 $02010 $30,000,000 $30,000,000 $02011 $55,000,000 $55,000,000 $0 $20,607,2422012 $200,000,000 $200,000,000 $0 $99,382,7582013 $236,277,358 $236,277,358 $0 $258,280,2772014 $250,000,000 $156,087,250 $93,912,750 $441,719,7242015* $250,000,000 $0 $250,000,000 $250,000,0002016* $250,000,000 $0 $250,000,000 $250,000,0002017** $243,732,642 $0 $243,732,642 $230,010,000

Total $1,550,000,000 $712,354,608 $837,645,392 $1,550,000,000

New Starts Grant Information by Federal Fiscal Year (Amounts in italics are pending)

* FTA is requiring HART to submit a Recovery Plan prior to awarding FFY 2015 & 2016 allocations to the project.** FFY 2017 allocation was included in the 2017 budget and is pending congressional approval.

  

   

Page 14: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

14 | P a g e   

         

3     SCHEDULE  (data as of Jan. 27, 2017) 

 OVERVIEW and KEY ISSUES 

HART’s Interim Revenue Service Date (RSD) is planned for December 2020.    

The current forecasted RSD is December 2025, inclusive of contingency. The two eastern guideway contracts are planned as follows:  

o Airport Guideway and Stations’ (AGS) construction Notice to Proceed (NTP) was issued on Dec. 1, 2016. o City Center Guideway and Stations (CCGS) construction NTP is forecasted for August 2018. 

 

CCGS contract duration and options are being evaluated by the project team to support Recovery Plan A (scope of existing FFGA to Ala Moana Center) and B (alignment to downtown Honolulu). 

o HART is assessing the completion of utility design prior to construction. o In this update, HART conducted a Risk Workshop to evaluate the amount of schedule contingency 

required and potential mitigation steps required to maintain the forecasted RSD.  

The overall critical path to full Revenue Service is the CCGS guideway and stations’ construction, core systems installation, systems testing and commissioning.  

Key schedule issues: o West O‘ahu Station Group’s (WOSG’s) baseline schedule approval is anticipated. HART is withholding 

payments until identified issues are resolved. Current progress is behind by six months. o Farrington Highway Station Groups (FHSG’s) rebaseline schedule is under review. HART is withholding 

payment until an acceptable schedule is provided and approved. Currently, negotiation of construction access milestone (CAM) dates consists of a nine month contract extension. 

o Kamehameha Highway Station Group’s (KHSG) baseline schedule has been accepted.   

Page 15: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

15 | P a g e   

Figure 7. HRTP Master Project Schedule Summary (MPSS)   The Master Program Summary Schedule reflects currently approved schedule end dates for contracts that have been awarded, and planned dates for future contracts. Active contracts’ end dates will not change, unless a change order is issued.  

 

Page 16: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

16 | P a g e   

 

4     CONTRACT STATUS  

Contracts in Procurement  OVERVIEW 

Awarded Contracts: o No updates to report this month. 

Active Procurements: o Art‐in‐Transit:  HART continues its negotiations with the highest‐ranked artists for each of the stations. To 

date, seven contracts have been awarded. o City Center Guideway and Stations (CCGS) Design‐Build RFP:  RFP Part 2 was issued on Feb. 2, 2016. The 

solicitation is on hold pending additional funding. o On Call Appraisers “II” RFP: The RFP was issued on Nov. 16, 2016. Proposals were due on Dec. 30, 2016. 

No proposals were received. Due to HART’s immediate need for appraisal services and prior solicitation attempts, HART is proceeding with alternative procurement.   

o Engineering Design and Design Review Services Contractor RFQ: The RFQ was issued on Dec. 22, 2016. Qualifications were received on Jan. 31, 2017, and are currently under review to be placed on a qualified list.  

o Owner Controlled Insurance Program (OCIP) Contract “II” RFP: The RFP was issued on Dec. 23, 2016. Proposals were due on Feb. 27, 2017. 

o Legal Counsel for Public Utilities Commission (PUC) Matters RFP: The RFP was issued on Feb. 1, 2017.  Proposals are due on March 15, 2017. 

 

  

  

Page 17: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

17 | P a g e   

Original Contract:                        $573,782,793  Incurred‐to‐Date:        $251,200,781 Current Contract Value1:           $600,573,187  Incurred in January:        $5,887,396 

 

1Current Contract Value = Original contract value (excluding $823.6M O&M budget) + executed Change Orders 

 

4.1   System‐wide  

A. Core Systems Contract (CSC) Contract No.: DBOM‐920   DBOM Contractor: Ansaldo Honolulu Joint Venture (AHJV) Contract Start Date: January 2012 Contract Substantial Completion: March 2019 Projected Substantial Completion: July 2025  Project Description: Providing rail passenger vehicles, automated train control system, traction electrification system (TES), communication systems, passenger platform screen gates (PSGs), and operation and maintenance of the project.    

% Complete  Schedule Status 

Based on Expenditures* 41.8% 

On time** Weighted Value 41.9% 

Early Plan* 67.8% 

Late Plan* 60.2% *Data as of Jan. 27, 2017. The progress chart reflects early program expectations. When the overall schedule is rebaselined and Construction Access Milestone dates are revised, the cost curve will be revised. **Based on draft Rebaseline Rev J. 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

COST INFORMATION:       

 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

 SCHEDULE: Upcoming Schedule Status per February 2017 

Installation of Communication equipment in MSF started and will continue in the coming months. 

Installations for Train Control and Communications Room (TCCR) at the stations will start in Q2 2017 at Ho‘opili and West Loch. 

Train #1 and #2 testing is ongoing. Delivery of Train #2 to Honolulu will be rescheduled to April 2017 in order to include production truck assemblies.   

Hitachi to continue inspection of aluminum extrusion profile defects in assembled cars and conduct associated fracture mechanics analysis.  

Train Dynamic Design Verification Tests are planned to start around April 2017. HART will need to complete a technical analysis of the structural defect found in one of the aluminum extrusion profiles before permitting dynamic train testing. 

Energize 3rd Rail Track for Dynamic Testing in March 2017, following completion of track shim replacement.      

Disadvantaged Business Enterprise (DBE) Participation 

 January Change Orders 

Actual DBE Participation:  $403,788    Change No.  Description  Amount ($) 

DBE % Attained:  0.067%    None  ‐‐‐ ‐‐‐ 

      Cumulative to Date $26,790,394 

Page 18: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

18 | P a g e   

WORK PROGRESS: 

                 

Activities this Month: Design:  Review of design submittals is ongoing. Manufacturing:  Conducted Interim Certification for Dynamic Testing Quality 

Assurance (QA)/Quality Control (QC) inspection with Hitachi Rail Italy (HRI) QA Engineer. 

Performed First Article Inspection of Passenger Vehicle (PV) Assembly at Hitachi Rail factory in Pittsburg, CA. 

Performed First Article Inspection of Truck Assembly at Hitachi Rail factory in Pittsburg, CA. 

Provided oversight of production truck assembly (Train #2) at Hitachi Rail factory in Pittsburg, CA. 

Continued with investigation oversight of car shell structural defect NCR.  

Pre‐shipment inspection and test of Supervisory Control and Data Acquisition (SCADA) continues. 

Qualification test on Platform Screen Gate System (PSGS) continues. Installation, Testing and Commissioning:  Low Voltage Functional Test on Train #1 is ongoing.  Automatic Train Control (ATC) installation in the MSF Yard is 

substantially completed.  SCADA installation in the MSF Yard Control Bungalow (YCB) is 

complete.  SCADA installation in the MSF Operations and Servicing Building 

(OSB) is 48% complete.  Communications (COMMS) installation in the MSF continues.  Continued coordination with HECO to energize Waipahu Traction 

Power Sub‐Station (TPSS).  AHJV completed terminating train control cabling for wayside 

equipment.  AHJV completed continuity and megger test on the ATC cables in 

the MSF.  AHJV performing local testing and commissioning of MSF Yard Train 

Control (TC) equipment.  Continued coordination with WOSG, FHSG and KHSG station 

contractors.  Installation and testing of TES cabling on Dynamic Section 

(Guideway from West Loch to West Yard Lead) is completed.  AHJV commenced installation of TES jumpers from East Kapolei to 

Ho‘opili.  Preparation to commence dynamic train testing on Dynamic Section 

is ongoing. 

Look Ahead: Design:   Continue Final Design of all subsystems. Manufacturing:  Passenger Vehicle Manufacturing – 

Monitor corrective action related to material defect with aluminum extrusion. Continue to work with Hitachi performing a technical review of fracture mechanics analysis and corrective action plan. 

PV Truck Fabrication – Continue truck frame and bolster fabrication activities in Italy. 

Continue manufacturing of automated train control, traction power, and other subsystems equipment. 

Installation, Testing and Commissioning:  Installation and testing of communications 

system cabling and devices in MSF.  Continue Routine and Design Verification 

testing on Train #1 in Honolulu.  Energization of Waipahu TPSS for Dynamic 

Section testing.  Continue testing of ATC wayside 

equipment in MSF.  Installation of Operations Control Center 

(OCC) technical room equipment.  Installation of CIC (Communication 

Interface Cabinet) cabinets in MSF.  Testing of Waipahu TPSS with HECO 

power.  Commence installation of Train Control 

devices on guideway (Ho‘opili to East Kapolei). 

Installation of West Loch TPSS.  Installation of West Loch TCCR equipment 

in the coming months.  Continue TES installation on guideway.  Commence installation of cable support 

system in guideway box girder. 

 

  Base DesignPercent Complete  

East Kapolei –Aloha Stadium Design 

Aloha Stadium –Middle Street Design 

Passenger Vehicles   94%

PSGS  100%

Communications   69%  64%  0% 

Fire Detection   100% 100%  0% 

ATC / SCADA   100%  100%  100% 

TES  100% 100% 100% 

Page 19: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

19 | P a g e   

 KEY ISSUES: 

Delays in the west side guideway and station contracts have affected the Core Systems Contract. HART issued revised Construction Access Dates in April 2016 with an anticipated shift in project completion from January 2020 to March 2023 (i.e., three years). The CSC submitted the revised Baseline Project Schedule (BPS Rev J) in October 2016 and formally claimed for delays.  

The deferred NTP for City Center Guideway and Stations will further delay the Core Systems Contract. Delays to the Revenue Service Date impact the Core Systems Contract. The current projected project completion date has shifted to December 2025.  

The CSC’s Communications System design completion is delayed. The Communications System delay is an internal AHJV delay and not affecting any critical path activities at this time. HART is monitoring this subsystem delay as it is a key component needed for future signaling system qualification testing and can affect system wide integrated testing if it is not adequately addressed. 

Hawaiian Electric provided HART with results of the power quality study which shows that HART will need to mitigate the voltage variations caused by the operation of the trains leaving the stations. Mitigation measures being reviewed by HART include the installation of Static Volt‐Ampere Reactive (VAR) Compensation equipment or other solutions including refining the operation of the trains. 

Energization of the Waipahu TPSS by Hawaiian Electric to conduct Dynamic Testing of the Vehicle is becoming critical. 

Quantification of extruded aluminum profile defects on the assembled car shell is in progress. Conclusive fracture mechanics analysis of defects must be completed by AHJV for HART to authorize dynamic train testing. Car shell production in Italy is on‐hold, pending resolution of car shell NCR. 

_______________________________________________________________________________________________________ 

 KEY MILESTONES: 

Dynamic testing without ATC in April 2017. Passenger vehicle static system level testing necessary to begin dynamic test activities (under manual control) on the guideway Dynamic Section. 

_______________________________________________________________________________________________________ 

 QUALITY MANAGEMENT: 

AHJV has identified an interim QA Manager for PV final assembly in Pittsburg, CA. Core Systems Oversight Consultant (CSOC) is coordinating with AHJV to ensure all outstanding QA issues are relayed to the interim manager to ensure timely resolution.  

CSOC has reviewed AHJV/HRI/METRA corrective actions to prevent future defects in the extruded aluminum parts that make up the underframe of the car shell. New subassemblies are being fabricated for production and retrofit. Car shell production in Italy is on‐hold, awaiting new subassemblies. 

HART is reviewing AHJV NCRs for Nexans cable in MSF.  

CSC NCR Log 

  TOTAL CLOSED OPEN

AHJV & Subs  35  35  0 

Hitachi Rail  815  702  113 

TOTAL  850  737  113 

      

    

Page 20: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

20 | P a g e   

Original Contract:              $50,982,714    Incurred‐to‐Date:        $7,135,528   Current Contract Value1:  $52,051,922    Incurred in January:       $140,825   

 

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 

   B. Elevators and Escalators Manufacture‐Install‐Maintain (MIM) 

Contract No.: MI‐930   Contractor: Schindler Elevator Corporation Contract Start Date: August 2013 Contract Substantial Completion: July 2018 Projected Substantial Completion: The July 2018 completion date will change to a later date predicated on the award of the DB contracts for the east portion of the guideway.   Project Description: Furnish / install / test / maintain all elevator and escalator equipment located at the 21 stations.   

% Complete  Schedule Status 

Based on Expenditures* 13.7% 

Pending** Weighted Value 13.7% 

Early Plan* 86.0% 

Late Plan* 76.4% *Data as of Jan. 27, 2017. The progress chart reflects early program expectations. When the overall schedule is rebaselined and Construction Access Milestone dates are revised, the cost curve will be revised. **The Elevators and Escalators schedule is dependent on other contractor’s schedules. Actual release for manufacturing will be coordinated for a ‘just in time’ delivery. 

____________________________________________________________________________________________________________  

COST INFORMATION: 

   

      

 

____________________________________________________________________________________________________________  

SCHEDULE: 

Elevators' schedule for the FHSG and WOSG has been established. On Dec. 1, 2016, HART sent a Notice to Proceed (NTP) letter for the release of the equipment for Kamehameha Highway Station Group. The Airport Guideway and Stations (AGS) Design‐Build (DB) contract has been awarded and the Notice to Proceed has been issued. The DB contractor is in the process of developing a schedule for acceptance. This contract contains four stations. Elevators' schedule for the remaining eight eastside stations will be established once the City Center Guideway and Stations DB contract is awarded and the DB schedule is accepted. 

      

DBE Participation    January Change Orders 

Actual DBE Participation:  $0    Change No.  Description  Amount ($)

DBE % Attained:  0%    None  ‐‐‐  ‐‐‐ 

      Cumulative to Date  $1,069,208 

Page 21: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

21 | P a g e   

         

WORK PROGRESS: Activities this Month:  The release for manufacturing of the required Elevator 

and Escalator for the Farrington Highway Station Group and West O‘ahu Station Group occurred in October 2016. 

The release for manufacturing for the Kamehameha Highway Station Group was released in December 2016. 

Final Design is approximately 41% complete, as 9 of the 21 stations have been released for manufacturing. All draft equipment drawings for the 21 stations have been submitted for review and have been accepted. 

Design is complete on the three FHSG stations, three WOSG stations, and the three KHSG stations. 

Permits for the installation of all elevators and escalators for the FHSG, KHSG and the WOSG have been issued. These permits are for installation only, not operation. 

Look Ahead:  Elevators' schedule for the four stations in the AGS 

DB contract will be established once the contractors schedule is accepted. The remaining eight eastside stations will be established once the DB contract is awarded for the CCGS and the DB schedule for this contract is accepted.  

  

____________________________________________________________________________________________________________  

KEY ISSUES: 

The release for manufacturing the E&E equipment will be coordinated for a ‘just in time’ delivery. Final completion of the equipment requirements for the four stations included in the DB contract for Airport Guideway and Stations will be subject to the final design of the DB. The eight stations included in the City Center Guideway and Stations contract is also on hold pending contract award of the DB contract for this work. Both of the DB solicitation packages contain the size and configuration of the elevators and escalators purchased for these twelve remaining stations. 

Coordination with station contractors on construction interface milestones. 

The re‐bidding of the Airport and City Center sections of guideway with stations as Design‐Build contracts will impact the completion of the Elevator Escalator contract. 

_______________________________________________________________________________________________________  

KEY MILESTONES: 

No significant milestones were completed this month. _______________________________________________________________________________________________________  QUALITY MANAGEMENT: 

Elevators and Escalators NCR Log Total NCRs Issued To Date CLOSED OPEN

0  0  0 

          

Page 22: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

22 | P a g e   

Original Contract:               $15,464,198    Incurred‐to‐Date:      $2,256,592   Current Contract Value1:  $15,464,198    Incurred in January:  $1,068,912   

 

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 

C. Fare Collection System Contract No.: MI‐900   Contractor: INIT, Innovations in Transportation Inc. Contract Start Date:  April 2016 Contract Substantial Completion: September 2021 Projected Substantial Completion: 60 days after full rail revenue service date  

Project Description: The fare collection system is a joint HART and City and County of Honolulu (DTS, DIT, BFS) project that will consist of a multi‐modal, closed loop, account based smart card system. The Fare System vendor, INIT Innovations in Transportation Inc., is responsible for design, manufacture, testing, installation and operation of the entire system inclusive of hardware and software.   

The rail portion of the project will consist of Ticket Vending Machines (TVMs) and fare gates at stations that accept smart cards which can also be used for payment on board TheBus and facilitate a seamless transfer between modes. Equipment and software to be used by both HART and the City and County will include transaction processing, fare equipment monitoring, and customer service systems, as well as a Data Warehouse. TheBus equipment will consist of stand‐alone smart card readers on board.    

% Complete  Schedule Status 

Based on Expenditures* 14.6% 

On time Weighted Value 20% 

Early Plan* 0.8% 

Late Plan* 0.8% *Data as of Jan. 27, 2017.

_______________________________________________________________________________________________________________________________________  

COST INFORMATION:        

      

_______________________________________________________________________________________________________________________________________  

SCHEDULE:   The baseline schedule for the fare systems project has the following milestones and is currently tracking to schedule: 

o Conceptual Design Review (CDR), Preliminary Design Review (PDR) and Final Design Review (FDR) completed by April 14, 2017. This date has slipped by two weeks.  

o Production Testing is anticipated to be completed by September 2017. Please note that previous reports should not have stated Field Integration Testing completed by June 30, 2017, but rather First Article Testing completed by June 30, 2017. 

_______________________________________________________________________________________________________________________________________  

WORK PROGRESS: Activities this Month:  Completed 10 Pre‐FDR workshops to help 

finalize design. Reviewed first package of FDR documents on hardware. 

Continued gap analysis of network design.   Completed Task 1 of the branding work.  Ongoing review of wiring requirements 

within stations for SCADA and network connections. 

Look Ahead: Review two additional FDR document packages.  Release remaining Contract Milestone Payment #3, once 

outstanding deliverables are complete.  Resolve gaps in network design inclusive of hardware, software 

and maintenance roles and responsibilities. Identify and resolve potential gaps in City networking infrastructure and INIT design. 

Review proposed Retail Network software and hardware with retail partners. 

Complete second task of smart card branding work. 

DBE Participation    January Change Orders 

Actual DBE Participation:  $0    Change No.  Description  Amount ($)

DBE % Attained:  0%    None  ‐‐‐  ‐‐‐ 

      Cumulative to Date $0 

Page 23: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

23 | P a g e   

          KEY ISSUES: 

Starting and completing three design reviews on time in order to maintain schedule with final design milestone acceptance by May 2017. 

_______________________________________________________________________________________________________  KEY MILESTONES: 

PDR was 90% complete by Jan. 13, 2017. 

FDR completion by April 14, 2017. _______________________________________________________________________________________________________  QUALITY MANAGEMENT: 

Fare Collection NCR Log Total NCRs Issued To Date CLOSED OPEN

0  0  0 

                             

Page 24: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

24 | P a g e   

Original Contract:                  $482,924,000  Incurred‐to‐Date:      $643,013,671   Current Contract Value1:      $661,691,103  Incurred in January:      $8,881,730   

 

1Current Contract Value = Original contract value + executed Change Orders 

  

4.2   Section I – West O‘ahu/Farrington Highway: East Kapolei to Pearl Highlands  

A. West O‘ahu/Farrington Highway Guideway (WOFH) Contract No.: DB‐120   DB Contractor: Kiewit Infrastructure West Company (KIWC)  Contract Start Date: December 2009 Contract Substantial Completion: March 2017   Projected Substantial Completion: March 2017  

Project Description: Design and construction of 6.8 miles of rail alignment, starting at the East Kapolei Station and ending at the Pearl Highlands Station.  

% Complete  Schedule Status 

Based on Expenditures* 97.2%  Anticipated and current contract completion dates align.  

Weighted Value 98.1% 

Early Plan* 100% 

Late Plan* 99.9% *Data as of Jan. 27, 2017.

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

COST INFORMATION:  

  

  

     

 _______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________  

SCHEDULE: 

As of the January 2017 progress update, the project is scheduled for substantial completion in March 2017.  _______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

WORK PROGRESS: 

      

DBE Participation    January Change Orders 

Actual DBE Participation:  $11,806,725    Change No.  Description  Amount ($) 

DBE % Attained:  1.82%    0140  Variance From Trench Restoration Detail  ($443,277) 

      0142  Asbestos Pipe at Utility Conflict 3‐673‐V1  $8,524 

      0143  Deletion of Site Restoration Work Pier 253 ($72,436) 

      Cumulative to Date $178,767,103

WOFH Construction Status as of 2/22/17 

Utility Status Qty  

to Date Final Qty 

% Complete 

 Structure Element 

***Total to Date 

Planned to Date Total Qty 

% Complete 

  Accepted Schedule* 

Revised Schedule** 

Water Line  9,348  9,348  100%    Shafts  309  309  309  309  100% 

Sewer Line  570  570  100%    Columns  283  283  283  283  100% 

Fuel Line  340  340  100%    Segment Casting  3,209  3,209  3,209  3,209  100% 

Gas line  1,591  1,591  100%    Spans Stressed  274  274  274  274  100% 

Drainage Line   5,090  5,166  98%    Track work  277  278  278  278  99.6% 

Elec/Telecom  20,950  21,374  98%    Third Rail  277  278  278  278  99.6% 

Street Lights  8,275  8,357  99%    Mill & Overlay   27,400  N/A  N/A  27,643  99.0% 

Traffic Sig/ITS Duct bank 

10,802  10,802  100%  

* Accepted Schedule was submitted in 2013. ** The planned values are based on KIWC’s pending July schedule revision dated August 24, 2015.  Revised schedule reflects a 6‐month delay in completion. *** Total quantity for the construction items has been revised to reflect the latest Issued for Construction number of shafts, columns, segments and spans. 

System Sites  7,046  7,046  100%   

ITS Systems Devices 

4,121  4,121  100%  

Page 25: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

25 | P a g e   

Activities this Month: Track Construction 

KIWC continues to construct concrete plinths, and install Continuous Welded Rail (CWR) for track on grade and third rail from Spans 249‐255.  

Civil Structures  KIWC is working to complete punch list activities.  

Station Contractor Interfaces   KIWC, FHSG, CSC and WOSG continue holding Interface 

closeout meetings to resolve current design and construction conflicts. 

Traffic Signals  KIWC has completed the construction of the traffic 

signals. KIWC is working on completing the punch list items in order for the Department of Transportation Services (DTS) to inspect and accept the traffic signals.  

LCC‐ Access Structure   LCC Access Structure: KIWC is working to complete 

punch list items for the handover to the station contractor. 

Look Ahead:Design Progress 

All design packages have been completed.  Column 

KIWC will continue work correcting punch list items. Guideway Segment Erection 

KIWC will continue work correcting punch list items. Balanced Cantilever Structure 

KIWC will continue work to complete concrete plinth construction and correcting punch list items. 

Track Construction  KIWC will continue work to complete the 

construction of concrete plinths and track on grade.  Continue to correct punch list items.  

Civil Structures  KIWC will continue working to complete punch list 

items.  Traffic Signals 

KIWC will work to complete punch list items. LCC Station Access Structure 

KIWC has completed the construction of the LCC structure and is working to complete the punch list items in preparation to turn over to the stations group. 

 

_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

 

KEY ISSUES: 

Closeout and Coordination – KIWC is continuing coordination with Nan, HDCC, and Ansaldo for shared access on and around the guideway. KIWC continues to submit all project closeout documents and as‐built drawings for HART review.   

Shared Access – Ansaldo has been given access to the entire top of the guideway and has started the traction power cabling installation. Hawaiian Dredging has access to West Loch Station from Piers 156‐161, and has been given access to Waipahu Depot Station at Piers 212‐216.  

Shims – KIWC will continue the shim replacement work starting from Span 250, working west towards East Kapolei.   

Tendons – KIWC has completed their investigation of the condition of all tendons using impulse‐response testing, as well as visual inspections. HART is waiting for an updated report to incorporate the last five spans from Ho‘opili and Pearl Highlands. 

_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

 

KEY MILESTONES: 

Punch List: 97% of KIWC’s list has been verified and closed by CE&I. The remaining items are scheduled to be closed by March 2017. 

_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

 

SUBSTANTIAL COMPLETION:  No progress to report this month. _________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

 

QUALITY MANAGEMENT: 

KIWC continues to follow their established quality processes through quality monitoring and audits. 

Closing Out NCRs – KIWC has been working to correct, validate, and close out NCR’s during this period. Totals are displayed in the table below. 

WOFH NCR LOG Total NCRs Issued To Date CLOSED OPEN

573  558  15 

    

Page 26: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

26 | P a g e   

Original Contract:               $56,088,470  Incurred‐to‐Date:      $8,073,367 Current Contract Value1:   $58,080,535  Incurred in January:                 $0 

 

1Current Contract Value = Original contract value + executed Change Orders 

B. West O‘ahu Station Group (WOSG) Contract No.: DBB‐171   Contractor: Nan, Inc. Contract Start Date: October 2015 Contract Substantial Completion: March 2018 Projected Substantial Completion: TBD  

Project Description: The West O‘ahu Station Group construction contract includes services to build three (3) transit stations along Kualaka‘i Parkway and Farrington Highway. The stations are East Kapolei (EK), UH West O‘ahu (UHWO) and Ho‘opili Stations. In addition to the transit stations, operational ancillary buildings, traction power substation and adjacent areas are included in this project. 

% Complete  Schedule Status 

Based on Expenditures* 13.9% 

6 months behind ** 

Weighted Value 13.9% 

Early Plan* 50.0% 

Late Plan* 50.0% *Data as of Jan. 27, 2017.**Further explanation is provided in the Schedule section. 

_____________________________________________________________________________________________________________________________________________________________________________________________________________________ 

COST INFORMATION:   

      

__________________________________________________________________________________________________________________________________________________________________________________________________________________________  

SCHEDULE: 

Baseline schedule was approved under the condition that the outstanding comment would be resolved before any further pay requests are processed by HART. Currently, the contractor has not resolved the issue and we are withholding payments. 

The schedule status reported above reflects the contractor’s progress schedule as of December 2016. HART is working with the contractor to mitigate any delays, if possible, and is evaluating the contract substantial completion date and warranted time extensions. 

_______________________________________________________________________________________________________  

WORK PROGRESS: Activities this Month:  The baseline schedule is conditionally approved, awaiting the 

contractor to address the remaining comment.   Progress schedule has been updated to the current month.  Poured East and West box girder walls and diaphragm at Ho‘opili.  Poured final UHWO west entry foundation stem walls.  Completed construction of UHWO TCCR structure (walls and 

roof).   Relocation of 46kV lines at UHWO.  Excavation for grade beams and utilities at East Kapolei.  Poured UHWO pier caps.  

Look Ahead:  Continue construction of the platform box 

girders at Ho‘opili.  Walls and columns at West Entrance 

Building at UHWO.  Install HECO 46kV Manholes #1 and #2 at 

UHWO.   Approval of baseline schedule. 

   

DBE Participation    January Change Orders/Amendments 

Actual DBE Participation:  $0    Change No./Amend  Description Amount ($) 

DBE % Attained:  0%    None  ‐‐‐  ‐‐‐ 

      Cumulative to Date  $1,992,065 

Page 27: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

27 | P a g e   

           

KEY ISSUES: 

Progress payments are being withheld from Nan, Inc. due to their inability to resolve baseline schedule submittal comments.  

_______________________________________________________________________________________________________  

KEY MILESTONES: 

No key milestones were completed during this reporting period. _______________________________________________________________________________________________________ 

 QUALITY MANAGEMENT: 

Conducted bi‐weekly Quality Task Force Meetings.  

WOSG NCR Log

Total NCRs Issued To Date CLOSED OPEN 

6  5  1                                                              

Page 28: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

28 | P a g e   

Original Contract:                 $78,999,000  Incurred‐to‐Date:  $3,473,290 Current Contract Value1:     $81,855,039  Incurred in January:             $0 

 

1Current Contract Value = Original contract value + executed Change Orders 

C. Farrington Highway Station Group (FHSG) Contract No.: DBB‐271   Contractor: Hawaiian Dredging Construction Company, Inc. Contract Start Date: August 2015 Contract Substantial Completion: January 2018 Projected Substantial Completion: October 2018      Project Description: The Farrington Highway Station Group construction contract includes services to build three (3) transit stations along Farrington Highway. The stations are West Loch (WLO), Waipahu Transit Center (WTC) and Leeward Community College (LCC) Station. The station work includes operational ancillary buildings, a traction power substation at WLO, kiss and ride lots, and parking lots.  

% Complete  Schedule Status 

Based on Expenditures* 4.2% 

9 months behind** 

Weighted Value 4.3% 

Early Plan* 72.6% 

Late Plan* 72.6% *Data as of Jan. 27, 2017.**Further explanation is provided in the Schedule section. 

_______________________________________________________________________________________________________ 

 COST INFORMATION: 

  

 

    

_______________________________________________________________________________________________________ 

 SCHEDULE: 

HART’s current assessment of the schedule: HDCC has submitted the re‐baselined Baseline Project Schedule (BPS). The revised Construction Access Milestone (CAM) dates are based on the addition of time to the contract CAM dates, contract substantial completion dates, and continued discussions with CSOC. Negotiations are ongoing and not yet finalized.

HDCC’s current assessment of the schedule: They will deliver the project 9 months late.   _______________________________________________________________________________________________________ 

 WORK PROGRESS: Activities this Month:  The Value Engineering Change Proposal (VECP) has been 

conditionally accepted. Design and pricing still need to be finalized. VECP is impacting the project progress.

WLO: Completed hollow core planks and topping slab at the Ancillary building.

WLO: Installed grounding grid at Makai station. WLO: Continued to install manholes/handholes and conduit for 

Communication and electrical.

Look Ahead:  WLO: Underground utility work continues. WLO: Vertical raceway column (VRC) 

ductbank installation will continue. WLO: Pour footings and walls for Makai 

station. WTC: Begin drilled shaft and/or Augercast 

piles. LCC: Begin work on the TCCR.  

DBE Participation    January Change Orders/Amendments 

Actual DBE Participation:  $32,700    Change No./Amend  Description  Amount ($) 

DBE % Attained:  0.04%    None  ‐‐‐  ‐‐‐ 

      Cumulative to Date $2,856,039 

Page 29: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

29 | P a g e   

Activities this Month (continued):  WLO: Poured Makai station entrance foundation and escalator 

footings. WLO: Began form work for platform box girders. WTC: Moved construction fence; mobilized equipment. WTC: Drilled for ground water monitoring. LCC: Completed construction fence installation and Best 

Management Practices (BMPs).  LCC: Mobilized equipment and job trailer.  LCC: Began mass excavation.  _______________________________________________________________________________________________________  KEY ISSUES: 

A Change Order is in process to settle time impacts to the project. HDCC delay in providing critical submittals is impacting the critical path.  Acceptance of the Rebaselined BPS and becoming current with monthly updates is critical. The VECP has been conditionally accepted. Design and pricing still need to be finalized. VECP is impacting the project 

progress. _______________________________________________________________________________________________________  KEY MILESTONES: 

West Loch – TCCR should be ready to be provided to CSC in April 2017. Waipahu station box girder construction is critical to program goals.  _______________________________________________________________________________________________________________________________________ 

 QUALITY MANAGEMENT: 

CE&I is working with HDCC to ensure required submittals are approved prior to related construction activities.  

FHSG NCR LogTotal NCRs Issued To Date CLOSED OPEN 

16  15  1                             

Page 30: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

30 | P a g e   

Original Contract:                $195,258,000    Incurred‐to‐Date:  $274,816,663   Current Contract Value1:   $274,675,032    Incurred in January:     $183,536   

 

1Current Contract Value = Original contract value + executed Change Orders 

D. Maintenance and Storage Facility (MSF) Contract No.: DB‐200  Contractor: Kiewit/Kobayashi Joint Venture (KKJV) Contract Start Date: July 2011 Actual Substantial Completion: July 2016    

Project Description: The MSF contract consists of the Operations and Servicing Building (OSB), Maintenance of Way (MOW), Train Wash Facility (TWF) and Wheel Truing Building (WTB). In addition to the four (4) facility buildings, MSF includes rail procurement, special trackwork, ties, third rail and other track material for the four guideway segments on the project. 

% Complete  Schedule Status 

Based on Expenditures* 100.1% Substantial Completion Obtained** 

Weighted Value 99.9% 

Early Plan* 100% 

Late Plan* 100% *Data as of Jan. 27, 2017. Percentage is based off of billings for pending change orders. **Further explanation is provided in the Schedule section. 

_______________________________________________________________________________________________________  

COST INFORMATION:  

            

 

_______________________________________________________________________  

 

SCHEDULE: 

The MSF project is currently in the close‐out stage. The new target date for final acceptance is May 1, 2017, for the following key reasons: 

o Pending punchlist items to be completed. o As‐Built Drawings to be submitted. o Isolation Pad/Shims delivery and installation by April 1, 2017. o Change Order development and completion of the disputed items. 

_______________________________________________________________________  

WORK PROGRESS: Activities this Month: Yard/Utilities 

Submitting final documents for training, O&M manuals, etc. for project close‐out continued. 

Civil As‐built drawings are under HART review. 

Track and Systems As‐built drawings resubmitted and under HART review. 

OSB  

Submitting final documents for training, O&M manuals, etc. for project close‐out continued. 

Punchlist item work continued. 

Look Ahead:Yard/Utilities 

Final documents for training, O&M manuals, etc. for project close‐out submitted. 

Civil As‐built drawings completed. 

Track and Systems As‐built drawings completed. 

OSB 

Final documents for training, O&M manuals, etc. for project close‐out submitted. 

DBE Participation    January Change Orders 

Actual DBE Participation:  $710,472    Change No.  Description  Amount ($) 

DBE % Attained:  0.26%    None  ‐‐‐ ‐‐‐ 

      Cumulative to Date  $79,417,032 

MSF Construction Status   99.9% Complete Overall 

as of 02/15/17

Element  % Complete* 

OSB  99.9% 

MOW Building  99.9% 

WTB  99.9% 

TWF  99.9% 

Rail  99.9% 

Paving  100% *Not including testing and commissioning.

Page 31: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

31 | P a g e   

Activities this Month (continued): 

Commissioning and Training of the In‐Ground Hydraulic Lifts, HVAC lifts, truck lifts, and portable lifts continued. 

OSB Foundation and Structural As‐built drawings are under HART review. 

OSB Building Finishes As‐built drawings under HART review. MOW  

Submitting final documents for training, O&M manuals, etc. for project close‐out continued. 

MOW Foundation and Structural As‐built drawings are under HART review. 

MOW Building Finishes As‐built drawings are under HART review. WTB 

Submitting final documents for training, O&M manuals, etc. for project close‐out continued. 

WTB As‐built drawings resubmitted and under HART review. TWF 

Submitting final documents for training, O&M manuals, etc. for project close‐out continued. 

TWF As‐built drawings resubmitted and under HART review. Rail Procurement and Installation  

Submitting final documents for training, O&M manuals, etc. for project close‐out continued. 

Punchlist item work continued. Administration 

Assisting with the completion of final documents for final acceptance of the MSF project. 

Look Ahead (continued): 

OSB Foundation and Structural As‐built drawings completed. 

OSB Building Finishes As‐built drawings completed. 

Commissioning of the In‐Ground Hydraulic Lifts completed. 

Punchlist completed. MOW 

Final documents for training, O&M manuals, etc. for project close‐out submitted. 

MOW Foundation and Structural As‐built drawings completed. 

MOW Building Finishes As‐built drawings completed. 

WTB 

Final documents for training, O&M manuals, etc. for project close‐out submitted. 

WTB As‐built drawings completed. 

Punchlist items completed. TWF 

Final documents for training, O&M manuals, etc. for project close‐out submitted. 

TWF As‐built drawings completed.  

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

KEY ISSUES: 

Final Acceptance – Coordination with KKJV has continued for equipment and building commissioning, final punchlist, submittals, training, O&M manuals, spare parts, and equipment turnover for final acceptance. Most of this work has been completed pending final documentation to be submitted.  

As‐Built Drawings – As‐built drawings for Mass Grading, OSB and MOW Building Finishes, Track and Systems, Train Wash Facility and Wheel Truing Building have been resubmitted, and the initial as‐built drawings for OSB and MOW Foundation and Structural, Civil are currently under review by HART. The Facility Specifications as‐built was submitted and is under review. 

3/16” Direct Fixation Isolation Pads – The isolation pads were procured and the first delivery for WOFH arrived. The installation of the isolation pads commenced on Feb. 10, 2017. KKJV provided approved isolation pad certifications for the isolation pads delivered. KKJV is working with LB Foster to procure the isolation pads for the East Side Project. Internal meetings are being held weekly with WOFH, MSF and KHG to discuss the Design‐Builders actions on the procurement, delivery and reinstallation of the isolation pads and shims.  

Dispute Mediation – Dispute mediation Change orders were signed by the Design‐Builder, pending execution by HART. _______________________________________________________________________________________________________  

KEY MILESTONES: 

Commissioning, Testing and Training of the In‐Ground Floor Lifts, Wheel Lathe, Wheelset Press, Portable Lifts, and Buffer Stop:  Commissioning and training for the portable lifts, truck lifts, and heating, ventilation and air conditioning hydraulic lifts were not completed in January and continued this month.  

_______________________________________________________________________________________________________  

QUALITY MANAGEMENT:  Overall quality of the contract is good. 

MSF NCR Log

Total NCRs Issued to Date CLOSED OPEN

34  32  2 

Page 32: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

32 | P a g e   

Original Contract:               $372,150,000    Incurred‐to‐Date:   $349,726,272   Current Contract Value1:   $398,526,421    Incurred in January:   $7,297,179   

 

1Current Contract Value = Original contract value + executed Change Orders 

4.3   Section II – Kamehameha Highway: Pearl Highlands to Aloha Stadium A. Kamehameha Highway Guideway (KHG) Contract No.: DB‐320  Contractor: Kiewit Infrastructure West Company (KIWC) Contract Start Date: June 2011 Contract Substantial Completion: May 2017   Projected Substantial Completion: May 2017  

Project Description: Kamehameha Highway Guideway DB Contract (KHG) consists of 3.9 miles and starts 400 feet east of the Pearl Highlands Station and terminates 1,400 feet beyond the Aloha Stadium Station. KHG work scope is made up of utility relocations, traffic signal improvements, highway widening, drilled shaft foundations, columns and aerial structure. 

% Complete  Schedule Status 

Based on Expenditures* 87.8% 

On time** Weighted Value 88% 

Early Plan* 100% 

Late Plan* 100% *Data as of Jan. 27, 2017.**Further explanation is provided in the Schedule section. 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

COST INFORMATION:           

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

SCHEDULE:  KIWC continues to have challenges meeting schedule due to various factors, including lower productivity and 

resource sharing between the KHG and WOFH projects, and self‐directed work stoppage for traffic signal and civil roadway work. HART’s position is that the projected substantial completion date will be May 2017, although the contractor’s progress schedule shows the guideway to be completed in May 2017 and overall project schedule to be completed in June 2018. 

 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

WORK PROGRESS: 

 

DBE Participation    January Change Orders 

Actual DBE Participation:  $322,296    Change No.  Description Amount ($) 

DBE % Attained:  0.08%    047  Unknown Abandoned MH at 12‐942‐E1  $7,200 

      048  Abatement of Asbestos Wrapped F10  $239,500 

      049  1‐773‐E1 HECO Impact on Shaft 270  $326,500 

      050  Hazardous Materials at Aiea Laundry  $65,000 

        Cumulative to Date  $26,376,421 

KHG Construction Status as of 2/22/17

Utility Status Qty  

to Date  Final Qty % 

Complete   Structure Element 

Total  to Date 

Planned to Date 

Total Qty 

% Complete 

Accepted Schedule* 

Revised Schedule** 

Water Line  4,362  4,362  100%    Shafts  186  186  186  186  100% 

Gas Line  12,641  12,641  100%    Columns  169  169  169  169  100% 

Sewer Line  492  492  100%    Segment Casting  2,029  2,029  2,029  2,029  100% 

Drainage Line  1,000  1,469  68%    Spans Stressed  163  166  163  163  100% 

Elec/Telecom  19,100  19,455  98%    Track work  158  166  117  166  95.2% 

System Sites  86%  N/A  86%    Third Rail  72  166  115  166  43.4% 

Signals/ITS/ Lights 

16,153  18,486  87%   Mill & Overlay 

Roadway 0  N/A  0  20,500  0% 

          * Accepted Schedule was submitted in 2013.   ** These quantities are based on KIWC’s pending August 2015 schedule revision dated Sept. 23, 2015. Revised schedule reflects a 12 month delay in completion. 

       

Page 33: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

33 | P a g e   

 

Activities this Month: Shaft/Column/Segments 

Punch list development.  

Dry finish of spans is ongoing in Phase 12.  Utility Relocation Progress 

The ongoing relocation of HECO electrical lines and Hawaiian Telcom, Oceanic Time Warner Cable and Intelligent Transportation Systems (ITS) ductbanks is occurring in various phases along the alignment. 

Systems Site #10 and #24 work is ongoing. 

Traction Power and communication ductbanks for System Site #12 are being installed in the roadway at Pearlridge Station area.  

Ongoing splicing of Oceanic Time Warner Cable underway. Median Restoration   

Center median restoration in Phases 4, 6, 7 and 11 continues with fence, curb install, paving and grading medians in progress.  

Traffic Signals 

Ongoing Traffic Signal Change Order work in progress at the following intersections: Acacia Rd; Waimano Home Rd; Puu Poni St; Kaahumanu St; Kekaha St.; Kanuku St; East & West Pali Momi.  

Trackwork 

Ongoing installation of mainline track and fasteners, special trackwork, and contact rail. 

Look Ahead: Design Progress 

KIWC is working to complete final design. To date, 46 of 49 drawing packages have been issued for construction. 

KIWC is working on As‐Builts.  Shaft/Column/Segments 

Dry finish of guideway spans is anticipated to continue in Phase 12.   

Punch list development.  Utility Relocation 

Acquisition of Right of Entry (ROE) for utility relocations is being pursued by HART and KIWC jointly, and meetings with property owners are ongoing. 

Median Restoration 

Center median restoration in Phases 9 and 12.  Traffic Signals 

Traffic Signal Change Order work to continue in several intersections. 

Trackwork 

Installation to continue through March. 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

KEY ISSUES: 

HECO/HDOT Utility Priorities – HECO Aerial “sway” Easement needed for conflict 9‐883‐E1. HART and the property owner are working to mitigate the delay. 

Access Coordination between Contracts – Coordination between contractors is ongoing and requires turnover of guideway work to follow‐on station contractors. 

Civil Roadway Work – KIWC has submitted a claim for extended overhead and management costs associated with completing the remaining civil roadway work (i.e. highway widening, retaining walls, mill and overlay, signage and striping) due to resequencing the schedule. This work could be accomplished at a later date if this option has merit in mitigating HART caused delays. HART is currently evaluating the merit of the claim and options. 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

KEY MILESTONES: 

The last guideway span was stressed on Dec. 29, 2016. 

A small number of utility conflicts/relocations (i.e. HTI, OTWC, HECO) were completed by the end of February 2017. 

Trackwork anticipated to be completed March 2017. ________________________________________________________________________________________________________________________________________________________________________________________________________________________  

QUALITY MANAGEMENT: 

Quality Process – KIWC continues to follow an established quality process.  

Longitudinal Tendons – Due to WOFH NCR 509, longitudinal tendons have been monitored for possible indications of rust. KIWC added two witness points to their Pre‐Grout Inspection Checklist for HART to visually inspect the tendon anchorages for corrosion, take photographs, and observe the removal of the deviator boots to ensure no water had accumulated at the low points of the duct.  

Shims – NCR #225 was issued to KIWC in October 2016, for non‐compliance with ASTM testing requirements. 

KHG NCR Log Total NCRs Issued to Date  CLOSED  OPEN 

238  230  8  

Page 34: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

34 | P a g e   

Original Contract:               $5,203,646    Incurred‐to‐Date:    $2,460,942   Current Contract Value1:  $5,246,168    Incurred in January:   $606,367   

 

1Current Contract Value = Original contract value + executed Change Orders 

B. Ramp H2R2 Contract No.: DBB‐385   Contractor: Royal Contracting Co. Ltd. Contract Start Date: May 2015 Contract Substantial Completion: October 2016 Projected Substantial Completion: June 2017  Project Description: Ramp H2R2 is an off‐ramp from the H2 Interstate which will connect the north bound H2 Interstate to east bound Kamehameha Highway. The off‐ramp terminates just west of the intersection of Kamehameha Highway and Waihona Street.  

% Complete  Schedule Status 

Based on Expenditures* 46.9% 

8 months behind 

Weighted Value 46.9% 

Early Plan* 100% 

Late Plan* 100% *Data as of Jan. 27, 2017. The progress chart reflects early program expectations. When the overall schedule is rebaselined, the cost curve will be revised. 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

COST INFORMATION:      

 ________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

 

SCHEDULE: 

Royal Contracting was awarded this project on May 4, 2015, and issued NTP on May 18, 2015. Start of construction was delayed due to unforeseen HDOT required soil remediation and submittal of required documentation. The contractor has projected a substantial completion of June 2017. Contract Change Order CCO‐0002 extended the original completion date by 124 days to Oct. 2, 2016.   

A change order is in process to approve additional delay time that is associated with the unforeseen HDOT required soil remediation that extends beyond Oct. 2, 2016. There are no delay claims associated with this time extension since the remediation delays were concurrent with contractor delays. 

_______________________________________________________________________________________________________  

WORK PROGRESS: Activities this Month:  Completed pouring of all the linear vertical retaining wall 

sections.   Waterproofing and backfilling of the retaining wall along the 

linear alignment.   Installed new 24” Reinforced Concrete Pipe (RCP) culvert, 

concrete pipe jacket, and outfalls.  Installed storm drain manholes and storm water treatment 

unit. 

Look Ahead:  Reinforcing and pouring of the vertical retaining 

wall sections along the radius alignment.  Continue to install storm drains and storm drain 

structures.    Continue waterproofing and backfilling behind 

retaining wall.  Installation of street lights.   

  

DBE Participation    January Change Orders/Amendments 

Actual DBE Participation:  $375,116    Change No./Amend  Description  Amount ($)

DBE % Attained:  7.15%    None  ‐‐‐  ‐‐‐ 

      Cumulative to Date $42,522 

Page 35: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

35 | P a g e   

           

KEY ISSUES: 

No key issues to report this month.  _______________________________________________________________________________________________________  

 KEY MILESTONES: 

No significant milestones were completed this month.  _______________________________________________________________________________________________________ 

  QUALITY MANAGEMENT: 

Conducted bi‐weekly Quality Task Force meetings.   

Ramp H2R2 NCR Log 

Total NCRs Issued To Date  CLOSED  OPEN 

6  6  0 

                         

Page 36: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

36 | P a g e   

Original Contract:              $115,805,845 Incurred‐to‐Date:           $7,740,145   Current Contract Value1:  $115,805,845 Incurred in January:       $7,093,190   

 

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 

C. Kamehameha Highway Stations Group (KHSG) Contract No.: DBB‐371   Contractor: Nan, Inc. Contract Start Date:  

Notice to Commence Administrative Work: April 2016  Notice to Commence Investigative/Pre‐Construction Work at Pearl Highlands:  July 2016 Full Notice to Proceed (NTP): October 2016 

Contract Substantial Completion: May 2019 Projected Substantial Completion: May 2019    

Project Description: The Kamehameha Highway Stations Group construction contract includes services to build three (3) transit stations along Kamehameha Highway. The stations are Pearl Highlands Station, Pearlridge Station, and Aloha Stadium Station. In addition to the transit stations, operational ancillary buildings, bus stops/transit centers, park‐and‐ride lots, kiss‐and‐rides, pedestrian crossing improvements, Train Control and Communications Rooms (TCCRs), and landscaping of the station sites are included. 

% Complete  Schedule Status 

Based on Expenditures* 6.7% 

On time Weighted Value 6.7% 

Early Plan* 8.1% 

Late Plan* 8.1% *Data as of Jan. 27, 2017.

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

COST INFORMATION:            

 ________________________________________________________________________________________________________________________________________________________________________________________________________________________ 

 

SCHEDULE:  The Baseline Project Schedule was finalized and accepted by HART on Jan. 20, 2017. 

________________________________________________________________________________________________________________________________________________________________________________________________________________________  

WORK PROGRESS: Activities this Month:  Pearl Highlands – Rock slope protection 

installation continues along Waiawa Stream. All sheet piles have been installed. Continue work on the sewer line on Kamehameha Highway. Load Shaft has been accepted and Load Tests are being conducted.  

Pearlridge Station – Construction fences continue to be installed along the northern and southern sites. The Method Shaft has been approved and the Load Test Shaft is awaiting approval. Clearing and demolition work began on both sites as well as ongoing environmental investigation activities.  

Aloha Stadium – Continuing coordination with the KHG contractor to get site access. 

Look Ahead: Finalize and award CO 00001.  Continue ongoing third party utility coordination with the 

KHG contractor, Hawaiian Telcom (HTI), Hawaiian Electric Company (HECO), and Oceanic Time Warner (OTW).  

Pearl Highlands – Continue rock slope protection work and begin work on a 36” stormdrain pipe concrete collar along Waiawa Stream. Continue work on the sewer line on Kamehameha Highway. Finish Load Shaft testing and proceed with production shafts. Mass excavation activities will continue.  

Pearlridge Station – Complete construction fencing, and clearing and demolition work. Obtain acceptance for Load Test Shaft and Load Test, and begin production shafts.  

Aloha Stadium – Continuing coordination with the KHG contractor to get site access. 

 

DBE Participation    January Change Orders/Amendments 

Actual DBE Participation:  $0   Change No./Amend Description  Amount ($)

DBE % Attained:  0%    None ‐‐‐ ‐‐‐

      Cumulative to Date $0

Page 37: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

37 | P a g e   

    

KEY ISSUES: 

Existing overhead utilities continue to be relocated underground at the Pearlridge Station site on Kamehameha Highway, as part of the KHG contract. KHSG continues to coordinate with the KHG contractor and third party utilities to monitor the installation of new utilities and the completion of utility relocations.  

Coordinating with HART ROW for a sway easement acquisition required for relocation of an existing overhead HECO 46kV line near the Pearlridge Station site (along southern site).  

HART is exploring the option for the KHSG contractor to construct a temporary third lane by the mauka side of the Pearlridge Station to allow for platform construction to begin. Negotiations are ongoing with the KHSG contractor.  

Executing a change order to incorporate Issued for Construction drawings and specifications (CO 00001) into the contract. 

The height and width of the water isolation barrier along Waiawa Stream has been addressed and HDOT has allowed work to proceed.  

Transite pipes with asbestos in soil stockpiles were discovered during mass excavation activities in the Pearl Highlands Station area. The transite pipes and soil stockpiles have been removed from the site and the KHSG contractor is proceeding with mass excavation activities. 

_______________________________________________________________________________________________________  KEY MILESTONES: 

Stadium Memorandum of Understanding (MOU) and Construction Right‐of‐Entry (CROE) approved. 

Partial Access for Systems Equipment Installation at Pearl Highlands Station – The TCCR and the Uninterruptible Power Supply (UPS) Building/Rooms are to be turned over from the KHSG contractor to the CSC contractor in November 2017.  

Station Site Turnover at Pearlridge Station – Both the northern and southern sites at the Pearlridge Station have been vacated by the KHG contractor. The contractor mobilized the crane on the southern parcel and the method shaft work was completed in January 2017.  

Station Site Access at Aloha Stadium – Projected in April 2017 or possibly sooner. _______________________________________________________________________________________________________ 

 QUALITY MANAGEMENT: 

KHSG NCR Log 

Total NCRs Issued To Date  CLOSED  OPEN 

4  4  0 

                

Page 38: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

38 | P a g e   

Original Contract:                 $874,750,000    Incurred‐to‐Date:      $17,425,173   Current Contract Value1:     $874,750,000    Incurred in January:    $7,001,288   

 

1Current Contract Value = Original contract value + executed Change Orders 

4.4   Section III – Airport: Aloha Stadium to Middle Street Transit Center Station A. Airport Section Guideway and Stations (AGS) Contract No.: DB‐450  Contractor: Shimmick/Traylor/Granite, JV (STG) Contract Start Date: December 2016 Contract Substantial Completion: May 2021 Projected Substantial Completion: May 2021  Project Description: The Airport Guideway and Stations Design‐Build contract consists of the design and construction of 5.2 miles of elevated guideway, four stations, and associated facilities between Aloha Stadium and the Middle Street Transit Center. The contractor will begin by interfacing with design disciplines, third‐party stakeholders, and construction contracts within the corridor of the project to coordinate and resolve utilities conflicts. Design field verification efforts (potholing and geotechnical exploration) will be followed by construction activities once design packages have been approved. 

 

% Complete  Schedule Status 

Based on Expenditures* 2.0% 

Schedule Under Review 

Weighted Value 1.99% 

Early Plan* 0% 

Late Plan* 0% *Data as of Jan. 27, 2017. The progress chart reflects information from initial contract mobilization payment and no baseline or 1st year schedule information. 

_______________________________________________________________________________________________________________________________________ 

 COST INFORMATION:       

 

_______________________________________________________________________________________________________________________________________ 

 SCHEDULE: 

First year schedule has been reviewed, and was returned to the contractor as “Revise and Resubmit” on Feb. 3, 2017. 

_______________________________________________________________________________________________________________________________________ 

 WORK PROGRESS: Activities this Month:  Mobilization / office setup activities are ongoing.  Ongoing Utility Design Coordination meetings.  Limited STG submittals for HART review.  Maintenance of Traffic (MOT) and Environmental 

meetings held, focusing on requirements for early start. 

Coordinate and implement reoccurring bi‐weekly Task Force Meetings, organized by discipline. 

Look Ahead:  Outstanding Submittals by STG are pending HART review.  One‐year (Initial) schedule review workshops.  Design workshops for submittals (by discipline/issues).  On‐going coordination meetings with HECO and other 

third‐parties (HDOT‐A, Navy, Keehi Park).  STG field activities for surveying, potholing and 

geotechnical boring investigations.  Resolution of design comments and Request for 

Information’s (RFIs) from Task Force Meetings.   

DBE Participation      January Change Orders 

Actual DBE Participation:  $0      Change No.  Description  Amount ($) 

DBE % Attained:  0%      None  ‐‐‐  ‐‐‐ 

        Cumulative to Date $0 

Page 39: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

39 | P a g e   

   

         KEY ISSUES:  Timeliness of submittals (all environmental, HDOT, survey permits and approval of Site Safety Security Plan), 

necessary to begin work.  STG to assume casting yard lease.  Interpretation of contractual requirements regarding invoice submittals.  Filling key roles (Quality Manager, etc.).  _______________________________________________________________________________________________________  KEY MILESTONES: 

NTP was issued on Dec. 1, 2016. 

Pre‐construction meeting was held on Jan. 12, 2017.  _______________________________________________________________________________________________________  QUALITY MANAGEMENT: 

“DRAFT” Quality Assurance Plan (QAP) has been submitted by STG. A workshop was held on Feb. 15 with HART Quality to expedite the resubmission of the final document. 

Design work has been initiated. 

No construction activities have started. 

STGJV Quality Manager was rejected on Jan. 6 based on lack of qualifications. STGJV has not resubmitted another candidate.  

AGS NCR Log 

Total NCRs Issued To Date  CLOSED  OPEN 

0  0  0 

                 

Page 40: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

40 | P a g e   

Original Contract:                 $27,993,290    Incurred‐to‐Date:   $26,649,470   Current Contract Value1:     $26,905,525    Incurred in January:                $0   

 

1Current Contract Value = Original contract value + executed Change Orders 

B. Airport Section Utilities Construction Contract No.: DBB‐505  Contractor: Nan, Inc. Contract Start Date: July 2014 

Contract Substantial Completion: July 2016 Actual Substantial Completion: October 2016  

Project Description: The Airport Utilities contract consisted of relocating utilities lines and facilities that have been determined to be impacted by the construction of the HART aerial guideway and associated facilities between Aloha Stadium and Middle Street Transit Center. The scope of utilities included underground communications lines, Navy electrical lines, fuel lines, gas lines, water lines, storm sewer lines, sanitary sewer lines and street light conduits and poles/fixtures. HECO work was excluded from this contract.  

% Complete  Schedule Status 

Based on Expenditures* 99.1% Substantial Completion Obtained 

Weighted Value** 99% 

Early Plan* 100% 

Late Plan* 100% *Data as of Jan. 27, 2017. **Based on a preliminary November/December 2016 invoice. 

_______________________________________________________________________________________________________________________________________  

COST INFORMATION:      

 

_______________________________________________________________________________________________________________________________________  

SCHEDULE: 

Nan, Inc. has completed the contract scope and punch list items. Roadways have been paved, striped and the landscaping has also been completed as of the substantial completion date of Oct. 7, 2016. Additional unforeseen utility items, not originally identified in this contract, and several contract work items have been removed from Nan’s scope, due to unresolved conflicts resulting in potential cost and schedule impacts, and were transferred to the On‐Call Construction contract. Airport Utility contract completion of outstanding submittals and other changes are in progress. 

 

On‐Call has completed the removal of the asbestos contaminated Chevron fuel lines and irrigation line along Aolele Street, and final paving was completed on Dec. 10, 2016. On‐Call has also completed the installation of a realigned 24” and 8” Navy waterline, along with any removal of redundant pipes. Work has begun on removing and filling the abandoned 8” Air Force Association (AFA) fuel line along Kamehameha Highway. 

         

DBE Participation      January Change Orders 

Actual DBE Participation:  $36,094      Change No.  Description  Amount ($) 

DBE % Attained:  0.13%      None  ‐‐‐  ‐‐‐ 

        Cumulative to Date ($1,087,813) 

Page 41: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

41 | P a g e   

        

WORK PROGRESS: Activities this Month: 

On‐Call has completed the removal of the old 24” waterline and has begun locating and removing the 8” AFA fuel line along Kamehameha Highway.  

Nan resubmitted As‐built drawings addressing AECOM’s initial review comments. 

Several contract change orders are being processed.   Certified Item List is pending final acceptance. 

Look Ahead:

CE&I‐II team continues to work on completing outstanding change orders, including a time delay claim of 3 months.   

AECOM to finalize the As‐builts by early March. Accept final As‐builts and Certifiable Items List (CIL’s). 

 

_______________________________________________________________________________________________________  KEY ISSUES:  Complete outstanding contract change claims.   Review and acceptance of final close out As‐builts and CIL’s.   _______________________________________________________________________________________________________  

KEY MILESTONES: 

Substantial completion occurred on Oct. 7, 2016. _______________________________________________________________________________________________________  

QUALITY MANAGEMENT: 

Overall quality of the contract is good.  

Airport Utilities NCR Log 

Total NCRs Issued To Date  CLOSED  OPEN 

19  19  0 

                     

Page 42: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

42 | P a g e   

Original Contract:               $43,948,220  Incurred‐to‐Date:      $44,399,339   Current Contract Value1:  $57,889,307  Incurred in January:     ($32,259)2   

 

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 2The incurred amount has decreased due to a credit.  

4.5   Section IV – City Center: Middle Street Transit Center Station to Ala Moana Center A. City Center Section Guideway and Utilities  Contract No.: FD‐530   Contractor: AECOM Technical Services, Inc., Final Design Consultant (Engineer of Record) Contract Start Date: July 2012 Projected Substantial Completion: January 2019  Project Description: The City Center Section Guideway and Utilities final design contract consists of 4.2 miles of elevated transit guideway serving eight (8) passenger stations, in addition to roadway widening, utility relocation, and other improvements to facilitate construction of the guideway. Design of the City Center Guideway has been suspended under this contract and will be completed by the City Center Guideway and Stations (CCGS) DB contract. However, designs for utilities and roadway are proceeding under this FD‐530 Final Design contract for use in the Dillingham Temporary Utilities (DTU) DBB construction contract, and the CCGS DB contract.  

% Complete  Schedule Status 

Based on Expenditures* 76.7% 

On time** Earned Value 77% 

Early Plan* 100% 

Late Plan* 100% *Data as of Jan. 27, 2017. The progress chart reflects early program expectations. When the overall schedule is rebaselined, the cost curve will be revised. ** Further explanation is provided in the Schedule section. 

__________________________________________________________________________________________________  

COST INFORMATION:        

 

__________________________________________________________________________________________________  

SCHEDULE: 

DTU utilities design is scheduled to conclude in mid‐2017.  

CCGS utilities and roadway design commenced on Dec. 29, 2016, and is scheduled to conclude on or before January 2019. 

__________________________________________________________________________________________________  

WORK PROGRESS: Activities this Month:  DTU pole loading calculations submitted to 

HECO.  Permanent utilities and roadway Design Kickoff 

meeting was held with reviewing authorities.    Consultants identified preliminary easements 

for 138kV undergrounding. 

Look Ahead:  An advance package for DTU at Mokauea Street is being 

prepared. A meeting with DPP to discuss the advance package will be set up. 

Anticipate HECO comments to finalize DTU pole locations. 

HART will begin acquiring the 138kV easements.    

DBE Participation      January Change Orders/Amendments 

Actual DBE Participation:  $191,227      Change No./Amend   Description  Amount ($) 

DBE % Attained:  0.41%      None  ‐‐‐  ‐‐‐ 

        Cumulative to Date  $13,941,087 

Page 43: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

43 | P a g e   

         KEY ISSUES: 

Completion of DTU design is critical to overall program schedule. Individual work packages are being separated and expedited to begin construction on schedule‐critical work.  

Property access is critical to verifying design and starting construction. DTU design is proceeding based on assumptions regarding existing utility information, which will be verified during construction. 

Utility construction agreements are required prior to initiating DTU work by utility owners. 

Recently advanced design for 138kV shows conflicts between proposed 138kV and proposed 12kV and 46kV lines, which dictates that these utilities must be constructed in series. The design team is investigating design solutions with the intent to enable concurrent construction of 12kV, 46kV and 138kV in parallel. 

Finalizing 138kV alignment is critical to delineating and commencing acquisition of utility easements. Right‐of‐way acquisition will be initiated in phases to prevent several challenging areas from delaying the start of right‐of‐way activities on other properties.  

__________________________________________________________________________________________________  KEY MILESTONES: 

DTU pole loading calculations submitted to HECO. 

Preliminary easements identified for 138kV undergrounding.  

                           

Page 44: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

44 | P a g e   

Original Contract:              $18,321,918    Incurred‐to‐Date:   $12,205,081   Current Contract Value1:  $19,631,717    Incurred in January:                $0         

 

1Current Contract Value = Original contract value with Design Allowance + executed Change Orders 

B. Dillingham and Kaka‘ako Station Group (DKSG) Contract No.: FD‐550   Contractor: Perkins+Will (P+W), Final Design Consultant (Engineer of Record) Contract Start Date: August 2013 Construction Docs Bid‐Ready:  N/A Actual Substantial Completion: Work concluded February 2016  

Project Description: Design of eight (8) stations for the fourth and final phase of the current project that will connect Dillingham Boulevard to Ala Moana Center. The DKSG stations have been combined with the City Center Guideway into a single City Center Guideway and Stations Design‐Build package. Due to the change from a DBB to a DB delivery method, the design for these stations has been suspended and will not be completed under this FD‐550 contract.  

% Complete  Schedule Status 

Based on Expenditures* 62.2% Substantial Completion  Obtained 

Earned Value 63% 

Early Plan* 100% 

Late Plan* 100% *Data as of Jan. 27, 2017. The progress chart reflects early program expectations. When the overall schedule is rebaselined, the cost curve will be revised. 

_______________________________________________________________________________________________________________________________________  

COST INFORMATION:       

 _______________________________________________________________________________________________________________________________________ 

 SCHEDULE: 

There is no work scheduled under this contract. 

This contract is scheduled to be closed out in early 2017.  

_______________________________________________________________________________________________________________________________________ 

 WORK PROGRESS: Activities this Month:  Administrative closeout activities are ongoing. 

Look Ahead: 

Future efforts will be administrative only. _______________________________________________________________________________________________________________________________________ 

 KEY ISSUES: 

N/A. _______________________________________________________________________________________________________  KEY MILESTONES: 

N/A.   

DBE Participation      January Change Orders 

Actual DBE Participation:  $0      Change No.  Description  Amount ($) 

DBE % Attained:  0%      None  ‐‐‐ ‐‐‐ 

        Cumulative to Date  $1,309,799 

Page 45: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

45 | P a g e   

4.6   Contract Status Cost reports are run from the HART Contract Management System (CMS) 

  

Page 46: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

46 | P a g e   

   

Page 47: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

47 | P a g e   

   

Page 48: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

48 | P a g e   

   

Page 49: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

49 | P a g e   

 

Page 50: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

50 | P a g e   

    

  

5     OVERALL PROJECT‐WIDE ACTIVITIES     

 

5.1   Permits   

Permits Submitted and In‐Progress o HART received amendments to the West O‘ahu Farrington Highway Community Noise Permit for standard 

construction activities from East Kapolei to Pearl Highlands until Nov. 22, 2019. o HART and Shimmick Traylor and Granite Joint Venture (STG) submitted a National Pollutant Discharge 

Elimination System (NPDES) application for construction.  o Nan, Inc. is continuing with constructing Phase 2 activities along Waiawa Stream, and daily monitoring is being 

conducted by the Construction Engineering & Inspection water quality monitors.  o HART and Nan, Inc. submitted an application for a Community Noise Variance for the Pearl Highlands Station.  

 

Look Ahead o Upcoming significant permit activity: 

HART is submitting an extension to the U.S. Army Corps of Engineers Nationwide Permits for work in Waters of the United States.   

   

5.2   Hawai‘i Department of Transportation (HDOT) Agreements  

Activities this Month o Grant application is being processed for the FY16 $3M associated with the Federal Highway Administration 

(FHWA) fund transfer to FTA for the HDOT requested highway improvements. o The WOFH Master Agreement and Joint Use and Occupancy Agreement (JUOA) Amendment 1 is being routed 

for signatures through HART, City and State. o The KHG, AGS, CCGS Master Agreement Amendment 1 is being routed for signatures through HART, City and 

State.  

Look Ahead o Execution of the City Center Joint Use and Occupancy Agreement. o Execution of the West O‘ahu Farrington Highway Master Agreement and Joint Use and Occupancy Agreement 

Amendment 1. o Execution of Amendment 1 to the Master Agreement for the sections to and from: Kamehameha Highway 

Guideway, Airport Guideway and City Center Guideway.               

Page 51: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

51 | P a g e   

  

5.3  Utility Agreements  

Utility Agreements Status Matrix 

Utility Owner  Status WOFH  KHG  Airport  City Center 

ESA  UCA  ESA  UCA  UCA  COMBINED ESA  UCA 

AT&T (Corporation) 

Executed  05/11/11  12/20/11 5/18/12 

Including with ESA  

Not Required 

12/26/13  Draft sent to AT&T NTP  05/12/11  12/21/11 

Amd 01  07/01/11  HRS Ch. 104  11/22/16         

AT&T (Government Solutions) 

Executed     12/26/13   

Not Required 

12/26/13 Combined with AT&T 

Corp NTP 

Chevron Executed  12/04/09 

 11/04/11 

   NTP  12/22/09  11/15/11

Amd 01  07/01/11   

Hawaiian Telcom 

Executed  05/20/10  11/17/14 05/10/12   12/31/14  05/28/15  09/27/13 

Draft sent to HTI for review NTP  06/14/10  11/18/14 

Amd 01  07/01/11    04/13/15   Pending Utility 

signature    

Amd 02  05/10/12             

Executed              Temp OH Pending Signature NTP             

HECO 

 Design Services 

Construction Services 

Design Services 

Construction Services 

Design Services 

Construction Services 

Design Services 

Construction Services 

Executed  11/20/13  11/29/13  11/20/13  11/29/13  11/20/13  Agreement under 

Executive review 

11/25/13  HECO revision to include 

Temp Poles NTP  11/20/13  11/29/13  11/20/13  11/29/13  11/20/13  11/25/13 

Amd 01   Draft sent to 

HECO            

Memorandums of 

Understanding 

08/07/14 – Construction Drawings05/01/15 ‐ Access

05/15/15 ‐ Derrick Truck

06/23/15 ‐Master Agreement

06/09/15 ‐MSF Advanced Construction 

09/16/15 ‐ Right of Entry

10/12/15 – Clearance (West) 11/10/15 ‐ Dillingham Blvd Materials

07/13/16 – KHG Vertical Clearance 

Power Quality ‐  Pending 

Oceanic Time Warner Cable 

Executed  12/08/09 12/21/11  01/09/12  06/02/14  12/19/14 

04/03/13  Draft sent to OTWC for review NTP  12/22/09  04/04/13 

Amd 01  07/01/11  02/27/14 HRS Ch 104 HRS Ch. 104Amd 02  10/07/13  HRS Ch. 104

Executed      9/22/16 NTP      9/30/16

Pacific Lightnet/ Wavecom  

Executed  04/28/10  03/12/12  02/15/12    

NTP  04/29/10  03/13/12 02/16/12Amd 01  07/01/11  HRS Ch. 104

Sandwich Isle Communications 

Executed  05/20/10   04/20/12         

NTP  06/08/10 Amd 01  07/01/11   

Hawai‘i GAS 

Executed  12/18/09  06/30/1106/01/12  04/14/14 

08/19/1409/27/13 

05/08/15NTP  12/22/09  07/12/11 08/20/14 05/11/15

Amd 01  07/01/11  10/17/14 08/28/14 HRS Ch. 104 HRS Ch. 104

Amd 02    05/09/16 10/23/15Amd 03      HRS Ch. 104

Page 52: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

52 | P a g e   

Utility Agreements Status Matrix 

Utility Owner  Status WOFH  KHG  Airport  City Center 

ESA  UCA  ESA  UCA  UCA  COMBINED ESA  UCA 

Level 3/TW Telecom 

Executed  12/02/09      

02/14/12  Oceanic  to relocate for TW Telecom 

  10/11/12 Draft sent to TW Telecom 

NTP  12/22/09  02/16/12 

Amd 01  07/01/11   Amd 02     

Tesoro 

Executed    

02/15/1209/12/13   

08/27/13  

NTP  02/16/12 09/03/13 Amd 01      09/12/14Amd 02      05/13/15Amd 03      HRS Ch. 104

Legend    = Action this month  COR = Corporation Counsel  UCA = Utility Construction Agreement 

    = Not applicable  ESA = Engineering Services Agreement UFRCRA = Combined Engineering and Construction Utility Agreement

  

Issues 

No major issues to report this month.    General 

Coordinating with Board of Water Supply to provide stray current information and maintenance plans.    HECO  

Davis‐Bacon requirements – HECO has a collective bargaining agreement that has different wage scales and allows payment to its labor  forces bi‐weekly, which does not satisfy Davis‐Bacon. Based on the State of Hawaii Department of Labor and Industrial Relations correspondence, HECO has begun the process to pay their employees weekly. HECO has submitted a rate conformance request that has so far been denied by the United States Department of Labor (DOL), although HECO has appealed. HECO and HART are still awaiting a final decision from the DOL for the applicable rates.     

HECO 46kV Substation near MSF area – HECO indicated a need in the 2019 timeframe for a new dedicated 46kV substation to feed the MSF area due to requirements in the HECO Rule 13 for line extensions and substations. HART is reviewing the various options with HECO.  

Additional Clearances – HECO requires the need for additional horizontal working clearances from overhead line conductors to the guideway for their 138kV and 46kV overhead lines along portions of all guideway segments. 

Horizontal Working Clearances Analysis – For City Center, HART and HECO have agreed to underground the overhead 138kV lines. HART’s designers are progressing to a preliminary engineering design with feedback from HECO. For AGS, a HECO‐HART combined solution of increased Navy easements and redesigned (shortened) pole arms may alleviate undergrounding the 9‐pole 138kV system fronting Pearl Harbor. Combined with specialized equipment from the west side, to maintain and replace the 46kV system, undergrounding of HECO transmission lines may not be necessary. For WOFH and KHG, HECO has successfully tested two new bucket trucks (not currently in their fleet) that can perform the 46kV work with less than their required working clearance. This will mitigate the need to relocate almost 90% of the 46kV poles/lines that do not meet their current required working clearances. For the 138kV lines at WOFH and KHG, HECO and HART traveled to Colorado to review the operational capabilities of the Phoenix and Skybird bucket trucks. HECO is evaluating their findings to better determine the extent of their power lines that can be addressed through the use of this new equipment. A final report from HECO is expected shortly.  

Alternative Equipment – For WOFH and KHG, HECO has proposed that HART purchase (9) new Altec bucket trucks to mitigate the 46kV clearance. HART is reviewing this. HECO and HART will continue to look for alternative equipment that could possibly mitigate the 138kV working clearance areas.  

     

Page 53: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

53 | P a g e   

   

5.4   Right‐of‐Way (data as of Feb. 1, 2017) KEY ISSUES 

o Request sent to FTA for Post‐ROD approval which will give HART the authority to negotiate parcels based on the alignment adjustments for the City Center Section. 

o In order to support the Airport Guideway and Stations Design‐Build contract and to maintain the project schedule, eminent domain proceedings were authorized by the HART Board and the Honolulu City Council for several parcels. However, negotiations are still continuing with all private property owners in the Airport section in an attempt to reach mutual agreement.  

o Negotiations are underway with HECO regarding clearances next to the HART system. HART may have approximately 100 new private easements that will be acquired  for HECO undergrounding. Another 146 small parcels will be located in public streets and HDOT property. They are primarily in the Airport and City Center sections for miscellaneous utility easements for HECO and other utilities. These parcels will eventually be turned over to HECO. This issue remains unresolved. 

o Support is continuing for the negotiations with UH Honolulu Community College to secure construction right of entry. 

o The main outstanding issue with the US Navy is how the national register nomination is handled for Big Makalapa and Little Makalapa. HART’s consultant is working directly with the United States Navy (USN)  Federal Preservation Officer (FPO) on the nomination. 

o There are currently no ROW actions impeding construction work and the objective is to secure site access via Rights of Entry (ROE) or other arrangements. ROW has moved forward with some condemnation and obtained legally enforceable possession of the property. However, these possession authorities will eventually require resolution of the valuation of the subject parcel. 

 ACQUISITIONS Figure 8. Right‐of‐Way Status for the Parcels [data provided by Real Estate Acquisition database (READ)] 

  

   

Page 54: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

54 | P a g e   

 RELOCATIONS Figure 9. Relocation Status for the Occupants (data provided by READ) 

  STATUS OF INTER‐GOVERNMENTAL AGREEMENTS  Figure 10. Inter‐Governmental Agreement Status – These are agreements between HART and other government entities, with the exception of D.R. Horton. Agreements to be executed are in white. Completed agreements are in grey at the end of the table. 

                                                                              Inter‐Governmental Agreements  

  

Agency 

Pending Agreements (Completed Agreements 

are shaded grey) 

  

Target 

  

Section 

Construction Right of Entry Obtained  

  

Notes/Remarks 

State  Agreements           

UH – University of Hawaii  Master Agreement is on indefinite hold. 

   

  WOFH, KHG, City Center 

Will be executed for each campus

Construction is not impacted as the ROE for right to access and construct will be executed for each campus. 

UH – Urban Gardens  Conveyance to HDOT(H) – Department of Transportation Highways 

May 2017  KHG     Yes   

In process.     

UH ‐ HCC  Construction Right of Entry for guideway & station 

May 2017  City Center   In review.  

DLNR – Dept of Land & Natural Resources 

Kapolei Easement Agreement for overhead guideway and for park and ride facility 

 May 2017 WOFH   

Yes  In process.  

DLNR  Keehi Lagoon Easement Agreement 

May 2017  Airport  Yes  In process. 

DLNR  City Center Construction Right of Entry  

May 2017 City Center 

  In process. 

DLNR  City Center Easement Agreement   May 2017 City Center    In process. 

DLNR/C&C Wastewater Div 

Easement Agreement  May 2017 City Center    In process. 

DLNR/C&C Wastewater Div  

Construction Right of Entry  

May 2017  City Center    In process. 

DOE – Department of Education Waipahu H.S. 

Permanent Easement (State portion)  

May 2017  WOFH   Yes Master/Construction Agreement in place.  Re‐set‐aside from DLNR to HART in process. 

DOE – Waipahu H.S.   Permanent Easement  (City portion)  

May 2017  WOFH  Yes  Master/Construction Agreement in place. Permanent easement from City in process. 

Page 55: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

55 | P a g e   

                                                                              Inter‐Governmental Agreements  

  

Agency 

Pending Agreements (Completed Agreements 

are shaded grey) 

  

Target 

  

Section 

Construction Right of Entry Obtained  

  

Notes/Remarks 

Aloha Stadium / Department of Accounting & General Services (DAGS) 

Easement Agreement for guideway 

Jan 2018  KHG  Yes  In process.  

Aloha Stadium/ DAGS 

Easement Agreement for station park and ride 

 Jan 2018  

KHG   Yes  Process Easement Agreement. 

HDOT(H) – Dept. of Transportation Highways   

Master Agreement Amendment  April 2017  WOFH   Yes  In process. 

HDOT(H) and (A) – Dept of Transportation Highways & Airports  

 Master Agreement for KHG, Airport and City Center Amendment 

April 2017  KHG, Airport, 

City Center 

Yes, except for City 

Center whose JU&O will be executed when the Notice to 

Proceed (NTP) is issued 

In process. 

HDOT(H)  Joint Use & Occupancy (JU&O) Sub‐agreement  Amendment 

 April 2017 WOFH  Yes  In process.  

HDOT(H)  Joint Use & Occupancy (JU&O) Sub‐agreement 

 Aug 2018  City Center    In process and will be executed when Notice to Proceed (NTP) is issued. 

HDOT(A)  Easement Agreement for Airport Division parcel (Main guideway easement) 

 May 2017 

Airport  Yes  Process Easement Agreement. 

OCCC ‐ Dept. of Public Safety, Oahu  Community Correctional Center 

MOU   May 2017 City Center    In process. 

OCCC/DLNR  Construction Right of Entry  

May 2017  City Center    Draft Construction Right of entry under review.  

DLNR/OCCC   Easement Agreement  March 2018 City Center   To be processed. 

HCDA ‐HI Community Development Authority 

Construction ROE, License Agreement, & Final Disposition

 May 2017 City Center    Coordination is ongoing. 

DAGS – Dept. of Accounting & General Services / Hi Housing Finance & Development Corp (HHFDC) 

Construction Right of Entry   May 2017 City Center    In process. 

DAGS/HHFDC  Easement Agreement  May 2017  City Center    To be processed. 

DAGS   Construction Right of Entry for City Center 

 May 2017 City Center    To be processed. 

DAGS  Easement Agreement for City Center 

May 2017  City Center   To be processed. 

Federal  Agreements            

U.S. Gov't/General Services Administration (GSA)/Federal Courthouse 

Master Agreement to include Security & Landscape Plan  

May 2017  City Center No, but construction is not impaired 

Under review.  

GSA Federal Courthouse  License (Right of Entry) & Temporary Construction Easement (TCE)  Agreements     

 May 2017 City Center  No, but construction is not impaired 

Under review. 

Page 56: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

56 | P a g e   

                                                                              Inter‐Governmental Agreements  

  

Agency 

Pending Agreements (Completed Agreements 

are shaded grey) 

  

Target 

  

Section 

Construction Right of Entry Obtained  

  

Notes/Remarks 

GSA Federal Courthouse  Quitclaim Easement Document    May 2017 City Center  No, but construction is not impaired 

Under review.  

Other  Agreements           

D.R. Horton  Final Easement Agreement    Jan 2018  

WOFH   Yes  In process and subject to owner’s development plans. 

  COMPLETED  AGREEMENTS 

       

City  Agreements            

DFM – Dept. of Facility & Maintenance (Kamehameha Hwy/Makalapa Manor) 

Jurisdictional transfer from DFM to HART. 

  Airport  Yes   

DPR ‐ Dept. of Parks & Recreation  (MSF drainage) 

Construction consent to construct   WOFH  Yes    

State  Agreements            

UH – University of Hawaii  Pre‐Construction Right of Entry and Amendment 

  WOFH, KHG, City Center 

Yes   

UH ‐ West O‘ahu  (UHWO) 

Construction Right of Entry for Station 

  WOFH  Yes   

UH ‐ Leeward Community College (LCC) 

Construction Right of Entry for Guideway  

  WOFH  Yes   

UH ‐ LCC  Construction Right of Entry for Station 

  WOFH  Yes   

UH ‐ Urban Gardens  Construction Right of Entry    KHG  Yes   

DLNR – Dept. of Land and Natural Resources 

Kapolei Construction Right of Entry for overhead guideway and for park and ride facility 

  WOFH  Yes   

DLNR  Keehi Lagoon Construction Right of Entry 

  Airport  Yes   

DOE – Dept. of Education Waipahu H.S. 

Master/Construction Agreement     WOFH  Yes   

DOE/DLNR for Waipahu H.S. 

Construction Right of Entry    WOFH  Yes  Executed by DLNR with DOE concurrence 

Aloha Stadium / Department of Accounting & General Services (DAGS) 

MOU for guideway & station     KHG  Yes   

Aloha Stadium/DAGS  Construction Right of Entry for guideway 

  KHG  Yes   

Aloha Stadium/DAGS  Construction Right of Entry for station park and ride 

  KHG  Yes   

HDOT(H) – Dept. of Transportation Highways 

Master Agreement for HDOT Highways for WOFH 

  WOFH   Yes   

Page 57: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

57 | P a g e   

                                                                              Inter‐Governmental Agreements  

  

Agency 

Pending Agreements (Completed Agreements 

are shaded grey) 

  

Target 

  

Section 

Construction Right of Entry Obtained  

  

Notes/Remarks 

HDOT(H) and (A) – Dept. of Transportation Highways & Airports 

Master Agreement for HDOT Highways and Airports, for KHG, Airport and City Center Sections 

  KHG, Airport, 

City Center

Yes, except for City 

Center whose JU&O will be executed 

when the NTP is issued  

 

HDOT(H)  Joint Use & Occupancy (JU&O) Sub‐agreement  

  WOFH  Yes   

HDOT(H)  Joint Use & Occupancy (JU&O) Sub‐agreement 

  KHG  Yes   

HDOT(H)  Joint Use & Occupancy (JU&O) Sub‐agreement 

  Airport   Yes   

HDOT(A)  Joint Use & Occupancy (JU&O) Sub‐agreement for Airport Division parcels 

  Airport  Yes   

DHHL ‐ Dept. of Hawaiian Home Lands 

Master Agreement    WOFH, MSF Yes   

DHHL  License/Construction Right of Entry 

  WOFH, MSF Yes   

HCDA ‐HI Community Development Authority  

Pre‐construction Right of  Entry    City Center Yes, effective upon request  

Verbal approval granted by the HCDA Board in 6/2016. 

Federal  Agreements            

U.S. Navy  Licenses/Construction Right of Entry 

  WOFH, KHG, Airport 

Yes   

U.S. Navy  Easement Agreements    WOFH, KHG, Airport 

Yes  Grant of Easement executed. 

U.S. Navy  Pearl Harbor Station Acquisition of Fee Transfer 

  Airport  Yes  Quitclaim deed executed. 

U.S. Post Office (USPS)  Honolulu Processing Center acquisition  

  Airport  Yes  Acquisition completed. 

Other   Agreements              

D.R. Horton  Agreement for Construction    WOFH  Yes   

                  

Page 58: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

58 | P a g e   

6     MANAGEMENT AND ADMINISTRATIVE UPDATES  

6.1   Safety and Security (S&S)  

Key Issues  The Core Systems Ansaldo/H‐JV Safety and Security Certification point of contact is on island part‐time. This 

individual is on island for approximately 10 days once every 6 weeks. This raises a concern of not providing onsite availability of certification expertise and experience at the Core Systems contractor level. HART Safety and Security Department certification efforts continue to progress while the status of the replacement manager is being addressed. An interim plan proposed by Ansaldo/H‐JV to address the gaps in coverage for meeting system safety requirements has been accepted. This issue will be ongoing and monitored by HART Safety and Security and Core Systems. 

Shims – KIWC will continue the shim replacement work starting from Span 250, working west towards East Kapolei.      Tendons – KIWC has completed their investigation of the condition of all tendons using impulse‐response testing, as 

well as visual inspections. HART is waiting for an updated report to incorporate the last five spans from Ho‘opili and Pearl Highlands.   

CSOC has reviewed AHJV/HRI/METRA corrective actions to prevent future defects in the extruded aluminum parts that make up the underframe of the car shell. New subassemblies are being fabricated for production and retrofit. Car shell production in Italy is on‐hold, awaiting new subassemblies. 

The specification and testing conformance checklist verification effort (% verified) lags behind construction completion percentage due to the fact that a significant percentage of the needed submittals are submitted at the end of the project; such as test reports, O&M manuals, training, and as‐built drawings. 

Safety and Security has one (1) unfilled OSHA Safety Specialist II position. 

 Two Month Look Ahead 

Safety and Security Management Plan (SSMP) Rev 6A ‐ SSRC approval. 

Safety and Security Certification Plan (SSCP) Rev 5A ‐ SSRC approval.  

DB‐120, WOFH Guideway Civil Certification. 

YCB DCCC and CSCC Civil Certification. 

PT‐002 Delivery IC, Bogies only. 

PT‐001, IC to enter Dynamic Testing.  Dynamic Section ‐ Test Track IC – Civil – TES ‐ SIT. 

  

6.1.1 S&S Twelve (12) Month Certification Projected Milestones and Work Priority: 

12 ‐ Month Certification Projected Milestones Contract and Interim Certificates (IC)    Next 30‐90 days Next 90‐180 days Next 180‐270 days  Next 270‐365 days

X – Projected Month      Feb2017 

Mar2017 

Apr2017

May2017 

Jun2017 

July2017 

Aug2017 

Sept 2017 

Oct 2017 

Nov2017 

Dec2017 

Jan2018

1. Safety & Security Management Plan (SSMP) Rev 6A X      

2. Safety & Security Certification Plan (SSCP) Rev 5A X      

3. DB‐200 MSF Civil Contract Final Certification  X      

4. DB‐120, WOFH Guideway Civil Certification  X      

5. YCB DCCC & CSCC Civil ‐ Certification (CSC)  X      

6. PT‐002 Delivery – IC – bogies only  X      

7. PT‐001, IC to enter Dynamic Testing  X      

8. Dynamic Section ‐ Test Track IC – Civil – TES ‐ SIT X      

9. Nine (9) MOW Vehicles Final Certification  X      

10. FD‐430 & DBB‐505, Airport Utilities Civil Certification X      

11. PT‐002, IC to enter Dynamic Testing  X      

12. DB‐320, KHG Guideway Civil Certification  X      

13. FD‐340 & DBB‐385 Ramp H2R2 Civil Certification X      

14. MSF TES Certification  X      

15. FD‐600, DBB‐602 UH W. Oahu. P&R ‐ Road B ‐ Cert       X

 

Page 59: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

59 | P a g e   

  6.1.2 S&S Certification Documents  

Key HART S&S Certification Documents ‐ Status S&S Project Plans, PHAs, Core Systems SSHA and & O&SHA, and TVA 

Documents  REV #  Date Approved

Comments 

Documents ApprovedHART SAFETY AND SECURITY 

1. Safety & Security Management Plan (SSMP)  Rev 5 10/16/2015 SSMP Rev 6A update under review  

2. Safety & Security Certification Plan (SSCP)  Rev 4. B 12/14/2015 SSCP Rev 5A update under review 

3. WOFH SSCP  Rev 0 10/22/2014 SSRC approved ‐ No future updates: HART SSCP is in affect

4. Construction Safety and Security Plan (CSSP)  Rev 3 10/06/2015 SSRC approved and signed

5. Security Sensitive Information (SSI) Plan  Rev 0 12/15/2015 SSRC approved and signed

6. Project Preliminary Hazard Analysis (PHAs)  Rev 2. A 9/3/2015 Rev 2A ‐ DRAFT annual update completed 9/3/2015 

a. MSF – Yard and Shop  Rev 2. A 2/24/2016 SSRC approved

b. Alignment  Rev 2. A 3/23/2016 SSRC approved

c. Tracks  Rev 2. A 2/24/2016 SSRC approved

d. Stations  Rev 2. A 3/23/2016 SSRC approved

7. TES Back‐Up Generator System HA  Rev A 5/25/2016 SSRC Approved

8. Threat & Vulnerability Assessments (TVAs)   Rev 1 1/16/2015 Update on hold ‐ pending East Alignments re‐design 

HART CORE SYSTEMS 9. Core Systems Contract (CSC) PHAs (DBOM)  Rev G 9/1/2016 SSRC Approved (CMS # 575) 

10. Central ATC O&SHA  Rev C 9/23/2015 SSRC approved (CMS # 874)

11. Wayside/ATC System HA  Rev C 6/22/2016 SSRC approved (CMS# 835)

12. Wayside ATC SSHA  Rev B 6/22/2016 SSRC approved (CMS# 836)

13. Wayside ATC O&SHA  Rev D 9/23/2015 SSRC approved (CMS # 850)

14. Passenger Train ATC SSHA  Rev E 2/24/2016 SSRC approved (CMS # 853)

15. Passenger Train ATC O&SHA  Rev F 2/24/2016 SSRC approved (CMS # 873)

16. UPS O&SHA  Rev C 2/24/2016 SSRC approved (CMS # 1092)

17. TES SSHA   Rev B 11/30/2016 SSRC approved (CMS # 884)

18. FDAS SSHA  Rev C 4/27/2016 SSRC approved (CMS # 1216)

19. FDAS O&SHA  Rev B 2/24/2016 SSRC approved (CMS # 1217)

20. SCADA SSHA  Rev C 6/22/2016 SSRC approved (CMS# 854)

21. SCADA O&SHA  Rev E 5/25/2016 SSRC Approved (CMS # 887)

22. Communications O&SHA  Rec C 1/25/2017 SSRC Approved (CMS # 1206) 

Documents Pending ApprovalHART SAFETY AND SECURITY 23. Project Preliminary Hazard Analysis (PHAs)  Rev 2. A Rev 2A ‐ DRAFT annual update completed 9/3/2015 

e. Traction Power  Rev 2. A Update on‐hold ‐ pending approval of TES SSHA and O&SHA

f. Train Control  Rev 2. A Update on‐hold ‐ pending approval of ATC SSHA & O&SHA

g. Vehicles  Rev 2. A Update on‐hold ‐ pending approval of PT SSHA & O&SHA

h. Communications  Rev 2. A Update on‐hold ‐ pending approval of Comms SSHA and O&SHA

24. Elevator/Escalators System HA  Rev A Under Development

25. Project OHAs  Rev A Under development

HART CORE SYSTEMS and Other Contracts 26. Technologies PHAs  Rev E 2/9/2017 – R&R (CMS # 545)

27. Passenger Train Fire Hazard Analysis (FHA)  Rev D 11/22/2016 – AAN Re‐submit (CMS# 749) 

28. Passenger Train SSHA  Rev B 10/25/2016 ‐ CSC R&R (CMS # 1273) 

29. Passenger Train O&SHA  Rev B 12/9/2016 ‐ CSC UTR (CMS # 1320) 

30. Passenger Train ATC System HA  Rev C 3/18/2016 Hart Accepted (CMS # 751) pending SSRC approval

31. TES O&SHA  Rev C 2/8/2017 – R&R (CMS # 1099)

32. PSGS SSHA  Rev D 1/26/2017 ‐ CSC UTR (CMS # 938) 

33. PSGS O&SHA  Rev D 1/11/2017 ‐ Accept, (CMS # 880) pending SSRC approval

34. Communications SSHA  Rev D 1/29/2017 ‐ CSC UTR, (CMS # 1205) 

35. MOW Support Vehicles O&SHA  Rev A 2/21/2017 – UTR (CMS # 1752)

      

Page 60: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

60 | P a g e   

   6.1.3 S&S Open Items List Status 

 

“Open Items List” “Open Items” ‐ Design/Construction and Verification Issues

Month 2016‐2017 

Total # 

Total # Open 

Total # Closed 

% ClosedOverall 

# Closed In Month 

% Closed In Month 

Oct  258  46 212 82% 0 N/A 

Nov  259  44 215 83% 3 1% 

Dec  259  44 215 83% 0 N/A 

Jan  262  40 222 85% 7 3% 

Feb  262  34 228 87% 6 2% 

  

6.1.4 S&S Construction Specification Conformance Checklists (CSCC) ‐ Civil Contracts 

 

Construction Specification Conformance Checklists (CSCC) 

Civil ‐ Contracts   ‐  CSCC Verification Status Construction ‐ Installation – Start‐up & Testing Phases

Contracts  % Verified 

+ / ‐  % Change 

Comments

WOFH / KHG Interim Revenue Service Date (2020)

Civil Contracts Under Construction DB‐200, MSF and Rail Yard   97% Verification underway – IC Certificate issued – Final Cert ‐ Pending

DB‐120, WOFH Guideway   83% +1% Verification underway 

DB‐320, KHG Guideway  65% +16% Verification underway

DBB‐385, H2R2 Ramps  58% Verification underway

DBB‐271, Farrington Hwy Station Group (FHSG)  18% Verification underway

DBB‐171, West O‘ahu Station Group (WOSG)  Pre‐verification activities

DBB‐371, Kamehameha Hwy Stations Grp (KHSG)  Pre‐verification activities

MI‐930, Elevators & Escalators, WOSG  Pre‐verification activities

MI‐930, Elevators & Escalators, FHSG Pre‐verification activities

MI‐930, Elevators & Escalators, KHSG Pre‐verification activities

Civil Contracts Under Design or in Pre‐bidding or Pre‐Award Phases MI‐900 Fare Collection System   Base CSCC SSRC approved 4/27/2016 

AP00 Art‐in‐Transit, 12 Artists/contracts  Base CSCC SSRC approved 10/28/2016 

DBB‐602, UH W. Oahu Temp P&R & Road B  Under development

DB‐275, Pearl Highlands PS/ Transit Center  TBD – waiting for 100% conformed specifications

Airport / City Center Final Revenue Service Date (2025)

Civil Contracts Under Construction DBB‐525, Airport Section, 7 ‐ Drilled Shafts  100% N/A 8/26/2015 SSRC approved –Certification Completed

DBB‐505, Airport Utilities ‐ Construction   90% 26% Verification underway – project close‐out underway 

Civil Contracts Under Design or in Pre‐bidding ‐ Pre‐Award Phases DBB‐511, Dillingham Utilities & Road Widening  TBD – waiting for 100% conformed specifications

DB‐450, Airport Guideway  TBD – waiting for 100% conformed specifications

DB‐450, Airport Stations  TBD – waiting for 100% conformed specifications

DB‐550, City Center Guideway  TBD – waiting for 100% conformed specifications

DB‐550, City Center Stations  TBD – waiting for 100% conformed specifications

MI‐930, Elevators & Escalators, Airport Stations  Base CSCC ‐ SSRC approved, 8/26/2015 

MI‐930, Elevators & Escalators, City Center Stations  Base CSCC ‐ SSRC approved, 8/26/2015 

AP00 Art‐in‐Transit, 11 Artists/contracts  Base CSCC SSRC approved, 10/28/2016 MI‐900 Fare Collection System   Base CSCC SSRC approved, 4/27/2016 

  

   

Page 61: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

61 | P a g e   

6.1.5 S&S Specification / Testing Conformance Checklists (STCC) ‐ Core Systems  

Specification / Testing Conformance Checklists (STCC) 

Core Systems – Contracts ‐ STCC Verification Status Procurement ‐ Production ‐Manufacture ‐ Installation ‐ Start‐up & Testing Phases 

Contracts  % Verified 

+ / ‐  % Change 

Comments

WOFH / KHG Interim Revenue Service Date (2020)

DBOM‐920 Core System Contracts under Design / Procurement ‐ Production ‐Manufacture ‐ Installation ‐ STCCYard Control Bungalow (YCB) CSC Civil ‐ Contract   59% Base STCC SSRC Approved 3/23/2016, verification underway

MOW Vehicles (8‐support vehicles) overall  75%

1) Rail car mover  43% Base STCC SSRC Approved 3/23/2016, verification underway

2) Multipurpose Vehicle  94% 22% Base STCC SSRC Approved 3/23/2016, verification underway

3) Enclosed trailer containing re‐railing equip  71% Base STCC SSRC Approved 3/23/2016, verification underway

4) Rail 15‐ton flatbed trailer  71% Base STCC SSRC Approved 3/23/2016, verification underway

5) Rail grinder  86% Base STCC SSRC Approved 3/23/2016, verification underway

6) Tamper  86% Base STCC SSRC Approved 3/23/2016, verification underway

7) Sperry (Geometry) car  86% Base STCC SSRC Approved 3/23/2016, verification underway

8) Hi‐reach lift truck  86% Base STCC SSRC Approved 3/23/2016, verification underway

Passenger Trains (PT)/Cars 

1) General Requirements ‐ Applies to all PTs   13% Base STCC SSRC Approved 12/9/2015, verification underway

2) PT‐001‐ Certification (E‐1, E‐2, M‐1, M‐2 Cars)  Base STCC under CS PM review 3) PT‐001‐ Interim Cert ‐ for Dynamic Testing  Base STCC SSRC Approved 12/9/2015, Pre‐verification activities

4) PT‐002 – Certification (E‐1, E‐2, M‐1, M‐2 Cars)  Base STCC under CS PM review 5) PT‐002‐ Interim Cert – for Dynamic Testing  Base STCC SSRC Approved 12/9/2015, Pre‐verification activities

6) PT Certification for Pre‐Revenue Service (STCC)  Base STCC under CS PM review 

Traction Electrification System (TES)  

1) General Requirements TES ‐ Project Wide  57% Base STCC SSRC Approved 9/28/2016, verification underway

2) MSF ‐ Rail Yard ‐ TES  50% Base STCC SSRC Approved 9/28/2016, verification underway

3) Dynamic Section Test Track ‐ WOFH Guideway  Base STCC SSRC Approved 9/28/2016 

4) Functional Section SIT Test Track  Base STCC SSRC Approved 9/28/2016 

5) WOFH and KHG Guideways  9% Base STCC SSRC Approved 9/28/2016, verification underway

Uninterrupted Power Supply (UPS) 

1) General Requirements UPS ‐ Project Wide  67% Base STCC SSRC Approved 9/28/2016, verification underway

2) MSF‐UPS  50% Base STCC SSRC Approved 9/28/2016, verification underway

3) Segment 1 ‐  UPS, WOFH & KHG  23% Base STCC SSRC Approved 9/28/2016, verification underway

Communication Systems 

1) General Requirements Comm‐ Project Wide  54% Base STCC SSRC approved 6/22/2016, verification underway

2) MSF and Rail Yard Communications  5% Base STCC SSRC approved 6/22/2016, verification underway

3) KHG and WOFH Communications   Base STCC SSRC approved 6/22/2016 Fire Detection Alarm System (FDAS) 

1) General Requirements FDAS ‐ Project Wide  61% Base STCC SSRC Approved 9/28/2016, verification underway

2) MSF ‐ FDAS  67% Base STCC SSRC Approved 9/28/2016, verification underway

3) Segment 1 – FDAS, WOFH & KHG  21% Base STCC SSRC Approved 9/28/2016, verification underway

Platform Screen Gate System (PSGS) 

1) General Requirements PSGS ‐ Project Wide  37% Base STCC SSRC Approved 9/28/2016, verification underway

2) Segment 1 – PSGS, WOFH & KHG  Base STCC SSRC Approved 9/28/2016 

Traction Power Generators Back‐up System  Base STCC SSRC approved 3/23/2016 

ATC / SCADA 

1) ATC / SCADA General Requirements ‐ Project Wide  68% Base STCC SSRC approved 11/30/2016, verification underway

2) MSF / ROC ‐ ATC / SCADA  33% Base STCC SSRC approved 11/30/2016, verification underway

3) Segment 1 WOFH & KHG Guideways & Stations  34% Base STCC SSRC approved 11/30/2016, verification underway

4) PT – ACT ‐ Initial Revenue Service Date (7‐PTs)  22% Base STCC SSRC approved 11/30/2016, verification underway

System Integration Testing (SIT) & Demonstration 

1) SIT General Requirements ‐ Project Wide SIT/DEM  32% Base SIT STCCs pending SSRC approval, verification underway

2)  MSF SIT/DEM  28% Base SIT STCCs pending SSRC approval, verification underway

3)  Functional Section ‐ SIT ‐ Test Track   Base SIT STCCs pending SSRC approval 4) Segment‐1 WOFH & KHG ‐ SIT / DEM  Base SIT STCCs pending SSRC approval Operational Requirements Ops Readiness Conform Checklists (ORCC)  31% ORCC REV‐0 ‐ SSRC approved 12/09/2015, verification underway

Pre‐revenue Testing Conform Checklist (PRTCC)  TBD

 

Page 62: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

62 | P a g e   

Specification / Testing Conformance Checklists (STCC) 

Core Systems – Contracts ‐ STCC Verification Status Procurement ‐ Production ‐Manufacture ‐ Installation ‐ Start‐up & Testing Phases 

Contracts  % Verified 

+ / ‐  % Change 

Comments

Airport & City Center Final Revenue Service Date (2025) Passenger Trains (PT)/Cars 

1) PT‐008‐20 Certification (E‐1, E‐2, M‐1, M‐2 Cars)  Base STCC under CS PM review 

2) PT‐008‐20‐ Interim Cert ‐ for Dynamic Testing  Base STCC SSRC Approved 12/9/2015 3) PT‐011‐20 Cert for Pre‐Revenue Service  Base STCC under CS PM review 

Traction Electrification System (TES)  

1)  Airport and City Center Guideways Base STCC SSRC Approved 9/28/2016 

Uninterrupted Power Supply (UPS) 

1) Segment 2 – UPS, Airport  47% Base STCC SSRC Approved 9/28/2016, verification underway

2) Segment 3 – UPS, City Center  48% Base STCC SSRC Approved 9/28/2016, verification underway

Communication Systems 

1) Airport Communications  Base STCC SSRC Approved 6/22/2016 

2) City Center Communications  Base STCC SSRC Approved 6/22/2016 

Fire Detection Alarm System (FDAS) 

1) Segment 2 – FDAS, Airport  Base STCC SSRC Approved 9/28/2016 

2) Segment 3 – FDAS, City Center  Base STCC SSRC Approved 9/28/2016 

Platform Screen Gate System (PSGS) 

1) Segment 2 – PSGS, Airport  Base STCC SSRC Approved 9/28/2016 

2) Segment 3 – PSGS, City Center  Base STCC SSRC Approved 9/28/2016 

ATC / SCADA 

1) Segment 2 Airport & Stations  2% Base STCC SSRC approved 11/30/2016, verification underway

2) Segment 3 City Center & Stations  Base STCC SSRC approved 11/30/2016 3) PT – ACT Final Revenue Service Date (13‐PTs)  Base STCC SSRC approved 11/30/2016 System Integration Testing (SIT) & Demonstration 

1) Segment – 2  Airport & C&C ‐ SIT / Dem  Base SIT STCCs under review pending final SIT Plan

Operational Requirements Ops Readiness Conform Checklists (ORCC)  SSRC approved 12/09/2015

Pre‐revenue Testing Conform Checklist (PRTCC)  Base PRTCC under development 

 6.1.6 S&S Certification Certificates Issued to Date 

S&S Certification Certificates Issued to Date Contracts / Interim Certification (IC) Certificates Issued Date  Signed  Comments1. FD‐430 / DBB‐525 Airport 7‐Piers Civil Cert Certificate  9/21/2015  SSRC approved 

2. Three (3) – MOW Vehicles Delivery & M‐7, M‐2, M‐1 MSF Tracks – IC Certificate   2/4/2016  SSRC approved 

3. MSF Yard M‐4 and M‐6 Tracks – IC Certificate  3/10/2016  SSRC approved 

4. PT‐001 Delivery, OSB, M‐5/M‐4 Tracks, ORCC, MOW MPV ‐  IC Certificate  3/29/2016  SSRC approved  

5. Five (5) – MOW Vehicles Delivery – IC Certificate (Vehicles Only)  5/20/2016  SSRC approved 

6. MOW Facility Early Occupancy – IC Certificate (Administrative Areas Only)  5/23/2016  SSRC approved 

7. MSF Civil IC Certificate ‐ Tracks and Facilities  7/6/2016  SSRC approved 

8. PT‐001 Truck (Bogies) Delivery #1 IC, 1 set of bogies ‐ wheel Sets 21 & 29  11/10/2016  SSRC Approved 

9. PT‐001 Truck (Bogies) Delivery #2 IC, 7‐sets of bogies ‐ wheel sets 6, 7, 8, 12, 18, 22, 24, 25, 26, 27, 30, 31, 33, 58 

12/01/2016  SSRC Approved 

 6.1.7 Construction Safety and Security Safety and Security Incidents  Incidents for Jan. 21, 2017‐Feb. 17, 2017: 

H2R2: A container was broken into and some caulking and motor oil was stolen. 

KHSG: Minor damage occurred when a skid steer bumped into an office trailer. 

KHG: Minor damage to a forklift that bumped into a sign board trailer. 

WOFH: Graffiti was found on the bottom of the guideway by Waipahu High School. 

WOFH: A person climbed around the security board on a ladder and accessed the inside of the guideway. 

MSF: A Lea + Elliott vehicle bumped a bollard as they were moving to provide space for construction equipment, causing minor damage. 

Page 63: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

63 | P a g e   

Ho

urs

wo

rke

d

No

. of R

eco

rda

ble

No

. of L

oss

Tim

e

Ho

urs

wo

rke

d

No

. of R

eco

rda

ble

No

. of L

oss

Tim

e

Ho

urs

wo

rke

d

No

. of R

eco

rda

ble

No

. of L

oss

Tim

e

January 145,806 1 0 172,799 0 0

February 126,526 1 0 172,950 1 0

March 139,422 3 1 183,147 0 0

April 71,856 1 0 230,808 2 0

May 167,204 0 0 181,979 1 0

June 123,391 2 1 165,737 0 0

July 130,954 0 0 167,039 0 0

August 52,834 1 0 154,381 1 1 129,067 1 1

September 108,337 1 1 102,224 1 0 113,137 0 0

October 126,351 0 0 172,845 0 0 130,238 0 0

November 116,929 3 3 45,913 0 0 94,003 1 0

December 102,942 1 0 154,215 0 0 106,913 1 0

Total 507,393 6 4 1,534,735 10 3 1,847,817 7 1

OSHA Annual Incident Rate

2014 2015 2016

Work Hours for WOFH, KHG, MSF, Airport, CORE System as reported to OCIP and certified. 1.3 0.76

  

 

6.2  Quality Management  Key Issues 

HART NCR Log 

Total NCRs Issued To Date  CLOSED  OPEN 

60 (Audits)  57  3 

1 (Construction)  1  0  

o Resolution of two (2) major WOFH NCRs that need to be addressed and corrected to prevent recurrence and to mitigate impact on the overall progress of the project. The major NCRs are described below: ‐ Tendons:  KIWC has completed their investigation of the condition of all tendons using impulse‐response 

testing, as well as visual inspections. HART is waiting for an updated report to incorporate the last five spans from Ho‘opili and Pearl Highlands.   

‐ Shims: KIWC will continue the shim replacement work starting from Span 250, working west towards East Kapolei.      

o Resolution of one (1) major KHG NCR that needs to be addressed and corrected to prevent recurrence and to mitigate impact to the overall progress of the project. The major NCR is described below:  ‐ Shims:  NCR #225 was issued to KIWC in October 2016, for non‐compliance with ASTM testing 

requirements.  o Resolution of one (1) major CSC NCR that needs to be addressed and corrected to prevent recurrence and to 

mitigate impact on the overall progress of the project. The major NCR is described below: ‐ CSOC has reviewed AHJV/HRI/METRA corrective actions to prevent future defects in the extruded 

aluminum parts that make up the underframe of the car shell. New subassemblies are being fabricated for production and retrofit. Car shell production in Italy is on‐hold, awaiting new subassemblies.      

Audit Look Ahead o Issued Audit 16‐003 HRU Joint HART/AHJV QA Audit Closeout Letter.   o Issued Audit No. 16‐017 CEI (West) QA Audit Closeout Letter.  o Issued Audit 16‐009 WOSG Combined QA, Buy America and Environmental Compliance Audit Closeout Letter.  o Issued Audit No. 16‐019 KHSG Combined QA, Buy America and Environmental Compliance Audit Closeout Letter.  o Prepared Project Combined Management System Audit Schedule for 2017. o Issued and met with ED‐CEO and Senior Management Team to discuss the 2016 Annual Assessment of the 

adequacy of the Quality Management Plan (QMP) and its implementation.   

Page 64: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

64 | P a g e   

Oversight and Monitoring  o Bi‐weekly Quality Task Force Meetings. o Pre‐activity Meetings. o Inspection and Testing: Performed Spot Inspection of the “WOFH, KHG and MSF Drainage Systems” after heavy 

rain and flooding occurred on the Island on Feb. 11‐12, 2017. o Prepared Project NCRs Trend Analysis from July 2016 to February 2017.   

6.3   Buy America Compliance (49 CFR 661 and 49 CFR 663)  Overview and Key Issues 

o HART conferred with FTA Region 9 by teleconference on Feb. 17, 2017 regarding request for Buy America waiver for variable refrigerant flow (VRF) system for east side of the corridor of the Project. Seeking a Buy America Waiver is a long and unpredictable process. While seeking a waiver is not ruled out, HART is exploring alternative ways to approaching this issue. FTA will also respond to HART’s query relating to method of calculations for rolling stock requirements for Buy America. 

 

6.4   Disadvantaged Business Enterprise (DBE)  Activities this Month 

o $49,112,374 = total dollar participation for all DBEs on all HART contracts from 9/24/07 to 2/28/17   

6.86% = DBE utilization on total disbursed FTA funds received to date ($49,112,374 divided by $716,354,608) 

2.78% = DBE utilization to date on total Project FTA funds ($49,112,374 divided by $1,763,903,901)  

6.5   Planning and Environment  Activities this Month 

o Programmatic Agreement Activities: ▪ HART submitted Big Makalapa and Little Makalapa National Register nominations to the Navy’s Federal 

Preservation Officer (FPO) on Sept. 23, 2016. Comments were received from the FPO on Nov. 3 and included minor non‐substantive revisions. The nominations were revised and transmitted back to the FPO on Nov. 8, 2016. The FPO transmitted the nominations to the State Historic Preservation Division (SHPD) for review and State Historic Preservation Officer (SHPO) signatures, and the top sheets were signed and sent back to the FPO on Dec. 9, 2016. The Department of Defense transmitted both Makalapa nominations to the Keeper of the National Register of Historic Places on Jan. 19, 2017.                  

▪ The required second design workshop for Pearl Harbor Station will be scheduled in 2017. ▪ The Annual FTA/Consulting Party meeting is scheduled for March 15. The handout packet to be provided 

prior to the meeting is in final review and edit.   ▪ The Quarterly Mitigation Monitoring Report 2016 Q4 has been finalized and submitted to FTA. ▪ The Semi‐Annual Programmatic Agreement report has been finalized and was submitted to the Kako‘o for 

distribution to the Consulting Parties.   ▪ The Annual Demolition Report is complete. ▪ All revised drawings and minor permit application reports for Historic Preservation (HP) Fund projects at 

1138 Maunakea Street, 158‐162 N. King Street, 1040 Richards Street, and 15‐19 N. Hotel Street were completed and submitted to the Department of Planning and Permitting (DPP). 

o Planning, Environmental, and Cultural Activities: ▪ Staff met with the AGS Environmental Consultant (EKNA Solutions) to review the pre‐submittal draft 

Environmental Compliance Plan for the AGS contract. ▪ Staff met with the Department of Parks and Recreation (DPR) and DPP for Dillingham Boulevard Street Tree 

consultation, including discussion on Kamani trees.  ▪ HART completed remediation activities at the Mauka Lagoon Station.    ▪ HART met with the property owner and the State of Hawaii Department of Health to coordinate an updated 

remediation schedule for the property near Pearl Highlands Station.  

Looking Ahead o Prepare and submit final Post‐ROD Documentation to FTA for approval: 

Airport Casting Yard, pending SHPD concurrence letter of no additional effect 

Page 65: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

65 | P a g e   

Conduct an Environmental Assessment at the Airport Casting Yard.    City Center Casting Yard, pending SHPD concurrence letter of no additional effect  Additional Right‐of‐Way, on hold awaiting potential project refinements  Hōlau Market/Ai‐Goto, 2nd quarter 2017  West O‘ahu Park & Ride Lots, on hold pending identification of potential Park & Ride sites  Incorporate SHPD Form for permit applications with DPP and the Office of Conservation and Coastal 

Lands (OCCL).  

6.6  Risk Management  The primary goal of risk management is to maintain a reserved contingency balance throughout the life of the Project that is acceptable to HART and the FTA. Effective management of project risks is necessary to significantly increase the likelihood of delivering a successful project. Risk management is the systematic process of identifying, analyzing, and responding to risk in a timely manner. Risk management is integral to all phases leading up to revenue service opening including: planning, design, construction, systems testing, system operation start up, safety and security certification, and ultimately to project construction closeout.   The HART program Risk Management System focuses on mitigation strategies to assist the project teams in project delivery. The bottoms up risk assessment for all projects in the program are updated monthly by the project teams. A network model is then updated to evaluate the cost and schedule contingencies of the program, including relationships between each of the individual projects and contracts. Risk assessment discussions with the project teams are held periodically to identify, assess, prioritize, manage and mitigate risk exposure, and develop prudent contingency plans. The Project Risk Register (RR) is the depository for all risks identified for the Project. Every month, risks contained in the RR are reviewed to confirm risks are appropriately identified, identify new risks, and close out risks that no longer pose an issue. The individual project register updates are now on path to be updated on a monthly basis and outputs will be compared to forecasting reports, eventually becoming an input to the forecast report.   The risk management system quantifies the risk as schedule impact or direct cost impact independently. The schedule impact is than monetized based in the model and based upon the contracts impacted. The top risks to the program are then evaluated on both schedule and cost.   As HART implements the risk management system focused on mitigation, monitoring, and control, the PMOC has requested to work with HART to possibly develop a new tracking mechanism or data reporting set to better assist in the oversight of the program. HART risk management plans to report risk updates by project on a monthly basis and perform a model update of the program on a quarterly basis. Currently, HART is in the process of updating the Risk and Contingency Management Plan (RCMP) with input from the PMOC. Current activities include the build‐up of the contingency curves and hold‐points as well as monthly reporting.  NOTES OF SIGNIFICANCE  

HART is currently going through an exercise in developing a recovery plan to manage the funding gap. 

Intensive focus continues to be placed on issues involving HECO coordination and clearance issue resolution; this includes alternative equipment studies.  

On‐Call contractor is verifying the existing as‐built data of the utilities in the City Center Section. 

Developing agreements with landowners and utilities for access during construction is mitigating potential construction schedule delays. 

Working to establish a schedule with the contractor for the AGS contract. 

Review and quantifying the impacts of the funding delay to the program, including financing cost.   

Identifying strategies to mitigate funding delay impacts to the MPS and the EAC.   

Revising the RCMP along with contingency curves.  

Performed a scenario workshop regarding the City Center delivery model. Looking at ways to improve the City Center construction duration and risk profile. 

HART’s Risk Manager position will be filled with the current senior risk advisor from the Program Management Support Consultant (PMSC). 

Performed risk assessment for Dillingham Temporary Utilities work scheduled to commence early summer 2017.   

Page 66: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

66 | P a g e   

AREAS OF FOCUS A) Market Conditions – The construction market in Hawai‘i continues to outpace other major metropolitan US cities. The years 2015 and 2016 set new records for construction in the state. This translates to increased escalation of about 1% per month from late 2014 through the end of 2016, according to the Rider Levett Bucknall, Quarterly Construction Cost Report. These conditions may impact the supply of experienced craft labor which will in turn affect contractor productivity rates and traffic mobility issues. Looking forward into 2017 and beyond, the construction market looks to slow down from its record pace, but remain above average. HART will monitor this situation as it develops in the coming months. 

Mitigation Progress:  

HART’s continuous improvement in estimating methodology has led to more confidence in the likely construction pricing, but continued pricing pressures in the market could still lead to higher than expected price proposals and bids.  

The combined guideway and station package on the City Center Guideway and Stations contract is still in active procurement.  

B) Utilities – Utilities continue to be an issue for the project, as they are for most Transit and Rail projects. 

Mitigation Progress: 

Resources to relocate HECO facilities are now keeping up with scheduled requests to resolve utility conflicts through improved coordination efforts between agencies at all levels from project management to executive levels. 

Identifying existing utilities along the City Center corridor. 

Resolve utility conflicts prior to construction contracts being issued.  

Sign construction agreements with utilities for the Dillingham Temporary Utility work as well as the City Center construction area. 

C) Right‐of‐Way – While construction access for nearly all west side acquisitions is complete, east side acquisitions are still in active negotiations for construction access and acquisition. The goal is to provide site access to the contractors for the entire project to avoid or mitigate against associated inefficiencies related to re‐sequencing the work plan which would have a negative impact to the revenue service date.    

Mitigation Progress:  

West side – Construction access for all property transactions have been accomplished, with the exception of a few ancillary utility relocation or road widening improvements.  

East side – Construction access for the Airport Section is nearly complete with the exception of 6 parcels, of which 4 are in or about to open escrow for closing; 1 is pending relocation of an antenna; and 3 require cost‐to‐cure mitigation. None are expected to adversely impact the anticipated construction schedule. Negotiations for construction access in the City Center Section are actively ongoing with access obtained for approximately 65% of the Dillingham Temporary Utility portion of the section, and 35% of the remaining portion of the section. Relocation and cost‐to‐cure activity is ongoing and are not impacting preconstruction work at this time. 

 

6.7   Community Outreach  Overview 

Since the inception of HART, the outreach team has participated in: o 1,055 Presentations and Events 

7 Events and Presentations in February 2017, including an open house public visitation of Honolulu’s rail cars, a presentation to the students at Hahaione Elementary School, and the UH College of Engineering Job Fair.  

o 603 Neighborhood Board Meetings  9 Neighborhood Board Meetings in February 2017. 

Page 67: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

67 | P a g e   

Community Input   HART’s public outreach team responded to more than 75 public inquiries and comments this month. Inquiries 

were related to filing claims, project construction timetable, operations and financial plans, and HART’s public visitation of its rail cars. 

 

6.8   Staffing  Overview 

Project Staffing: o Target: 139 Full‐Time Equivalent (FTE) City staff o Actual Total: 129 FTE (HART City and PMC staffs ‐ reflects all arrivals as well as departures this month) 

City Staff: 112  PMC Staff: 17 

The following personnel departed the project in February: Internal Control Analyst and Director of Special Projects. 

The following positions have been filled and the start date is reflected below: the Chief Financial Officer, Design and Construction Project Manager, the Operations and Maintenance Administrative Specialist , Accountant IV, and Deputy Director of Planning. 

 Figure 11. Staffing Activities 

Staffing Activities

Title  Group New/Existing HART position (City or PMC) 

Position Status  Start Month 

Design and Construction 

Director of Design & Construction  Design & Construction  Existing (City)  Recruiting   

Project Manager (WOSG)   Construction  Existing (City)   Filled  February 

Engineer (Electrical or Mechanical)  Core Systems  Existing (City)  Recruiting/Interviewing   

Budget and Finance 

Chief Financial Officer  Budget and Finance  Existing (City)  Filled  March 

Financial Analyst  Budget and Finance  Existing (City)  Recruiting   

Accountant IV  Budget and Finance  New (City)  Filled (Internal)  February 

Accountant III  Budget and Finance  New (City)  Recruiting/Interviewing   

Administrative Services 

Personnel Clerk  Administrative Services  Existing (City)  Temp fill, recruiting via Civil Service 

 

Public Information 

Information Specialist  Public Information  Existing (City)  Recruiting/Interviewing   

Project Controls 

Scheduler  Project Controls  Existing (City)  Recruiting/Interviewing   

Procurement & Contracts 

Procurement  & Specifications Specialist  Procurement  Existing (City)  Recruiting/Interviewing   

Agreements Arbiter and Manager/Insurance Risk Manager 

Procurement  New (City)  Recruiting/Interviewing   

Deputy Director of Procurement and Consultant Contracts 

Procurement, Contracts and Construction Claims 

New (City)  Recruiting/Interviewing   

Safety 

Safety Specialist  Safety  Existing (City)  Recruiting/Interviewing   

Operations & Maintenance 

Administrative Specialist   Operations & Maintenance  New (City)  Filled (Internal)  February 

Planning, Permitting & ROW  

Deputy Director of Planning  Planning  Existing (City)  Filled  March 

Planner VI (Land Use/Sustainability)  Planning  Existing (City)  Recruiting   

Secretary  Planning  Existing (City)  Recruiting   

Right‐of‐Way Agent IV   Right‐of‐Way  New (City)  Recruiting/Interviewing   

  For the latest project organization chart, see Appendix C.  

Page 68: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

68 | P a g e   

         

6.9  Operations and Maintenance (O&M)  Overview 

o Rail O&M continues to develop policies and procedures, and to oversee the Core System Contractor’s O&M mobilization and development. 

o Rail O&M is coordinating with the HART project teams, Department of Transportation Services, O‘ahu Transit Services (OTS), and other government agencies.    

Ongoing Activities  o Hired Operations / Administrative Specialist. o Submitted Transfer of Capital Assets process (stations) for baseline review. o Submitted Rail Activation Plan and Rail Activation Schedule for baseline review. o Developing Pre‐Revenue Operations and Start‐up Plan. o Developing Asset Management Plan. o Developing Operations and Maintenance Staffing Plan. o Developing Matrix of Responsibilities for Operations and Maintenance. o Ongoing Operations and Maintenance working groups. o Ongoing coordination with LCC Workforce Development Program. 

 

Look Ahead o Collaborating with the Bay Area Rapid Transit (BART) Asset Management Team in preparation for Maintenance 

Management Information System (MMIS) development.   

   

Page 69: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

HonoluluRailTransitProjectMonthlyProgressReport  February2017

69 | P a g e   

   

APPENDICES  

 

Page 70: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

70 | P a g e   

Appendix A. Project Contingency Management  

    

Page 71: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

71 | P a g e   

  

Page 72: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

72 | P a g e   

  

Page 73: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

73 | P a g e   

  

Page 74: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

74 | P a g e   

  

Page 75: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

75 | P a g e   

Appendix B. Project Cost Reports (data as of Jan. 27, 2017) Cost reports are run from the HART Contract Management System (CMS) Project Costs by SCC – Level 2 

  

Page 76: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

76 | P a g e   

   

Page 77: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

77 | P a g e   

  

 

Page 78: February 2017 MONTHLY PROGRESS REPORThartdocs.honolulu.gov/docushare/dsweb/Get/Document-20390/2017… · CRMS Customer Relational Management System CROE ... HA Hazard Analysis HABS

Honolulu Rail Transit Project Monthly Progress Report   February 2017 

78 | P a g e   

Appendix C. Project Organization Chart