federal democratic republic of nepal data … · wecs water and energy commission secretariat widmp...
TRANSCRIPT
FEDERAL DEMOCRATIC REPUBLIC OF NEPAL DEPARTMENT OF IRRIGATION MINISTRY OF IRRIGATION
FEDERAL DEMOCRATIC REPUBLIC OF NEPAL
DATA COLLECTION SURVEY ON PROMOTING OPERATION AND
MAINTENANCE OF IRRIGATION SCHEME IN TERAI
FINAL REPORT
October 2016
Japan International Cooperation Agency
RD JR
16-085
Survey Area: Terai region (the area highlighted with green color)
D.R.
D.R.
1997Western
ral D.R.
2035Eastern D.R. = Development Region
i
Table of Contents
Survey Area Table of Contents Acronyms & Abbreviations
Chapter 1 Background and Objectives of the Survey ............................................... 1-1
1-1 Background of the Survey .............................................................................. 1-1 1-2 Objectives of the Survey ................................................................................. 1-2 1-3 Target Region of the Survey ........................................................................... 1-2 1-4 Scope of the Survey ........................................................................................ 1-3 1-5 Methodology of the Survey ............................................................................ 1-5
Chapter 2 National Policy and Development Plan of the Irrigation and Agriculture Sectors ................................................. 2-1
2-1 Overview of the Country ................................................................................ 2-1 2-2 Positioning of the Irrigation and Irrigated Agriculture Sectors in the National Plan ......................................................................................... 2-8 2-3 Legal System of the Irrigation Sector ............................................................. 2-8 2-4 National Policy and Development Plan/Strategy of Irrigation Sector .......... 2-10 2-5 Ministry of Irrigation .................................................................................... 2-16 2-6 Department of Irrigation (DOI) .................................................................... 2-18 2-7 Other Related Institutions ............................................................................. 2-26
Chapter 3 Current State of Irrigation in Terai region .............................................. 3-1
3-1 Overview of Terai region ................................................................................ 3-1 3-2 Outline of Irrigation Systems .......................................................................... 3-8 3-3 Situation of Irrigation and Irrigated Agriculture ........................................... 3-17 3-4 Assistance in the Irrigation and Irrigated Agriculture Sectors
by Other Donors ............................................................................................ 3-26 3-5 JICA’s Cooperation in the Past ..................................................................... 3-31
Chapter 4 Problems/Challenges of Each Irrigation System ..................................... 4-1
4-1 Irrigation Systems which were the target of the Detailed Study..................... 4-1 4-2 JMIS ................................................................................................................ 4-2 4-3 FMIS ............................................................................................................. 4-17
ii
Chapter 5 Problems of Irrigation Development and Challenges Extracted through the Survey ............................................... 5-1
5-1 Challenges Identified in the Field ................................................................... 5-1 5-2 Problem and Objective Analyses in the Workshop ......................................... 5-1 5-3 Challenges and Countermeasures Based on Field Survey and Workshop ...... 5-2 5-4 Targets of Technical Cooperation and Possible Activities……………………5-7 5-5 Importance of System-wide Water Management……………………………5-19 5-6 Relevance of Contents Applied from GON………………………………….5-20
Chapter 6 Proposed Approach of JICA’s Cooperation ............................................. 6-1
6-1 Policies and Needs in the Irrigation Sector ..................................................... 6-1 6-2 Proposed Cooperation Approach for an Improvement on the Irrigation O&M in Terai Region ............................... 6-2 6-3 Suggestion to Introduce the Agricultural Component .................................... 6-8 6-4 JICA-TCP Pilot Projects and Dissemination .................................................. 6-9 6-5 Possibility for the Distribution of Roles and Collaboration among the JICA-TCP and Other Donors’ Projects ......................................... 6-9 6-6 Considerations for Future Surveys and Implementation of the JICA-TCP................................................................................................ 6-10
References
ANNEXES:
ANNEX 1 Organization Charts of IMD, GWID and IDD
ANNEX 2 Organization Chart of DOA
ANNEX 3 Summary Tables of Questionnaire Answers (JMIS)
ANNEX 4 Summary Tables of Questionnaire Answers (IDD/IDSD)
ANNEX 5 Summary Tables of Questionnaire Answers (GWID)
ANNEX 6 Training Materials of IMD
ANNEX 7 List of IWRMP Irrigation Sub-projects
ANNEX 8 IWRMP Irrigation Sub-projects' Salient Features
ANNEX 9 List of CMIASP Irrigation Sub-projects
ANNEX 10 Salient Features of CMIASP-AF (Batch 1) Irrigation Sub-projects in Terai region
ANNEX 11 Questionnaire Answers (JMIS) (Digital file)
ANNEX 12 Questionnaire Answers (IDD/IDSD) (Digital file)
ANNEX 13 Questionnaire Answers (GWID) (Digital file)
iii
Acronyms & Abbreviations
ADB Asian Development Bank
ADS Agriculture Development Strategy
AMIS Agency-managed Irrigation System
AO Association Organizer
APP Agriculture Perspective Plan
AVRSCS Armed Violence Reduction and Strengthening Community Security
CBS Central Bureau of Statistics, National Planning Commission Secretariat
CMIASP Community Managed Irrigated Agriculture Sector Project
CMIASP-AF Community Managed Irrigated Agriculture Sector Project - Additional Financing
DADO District Agricultural Development Office, DOA
DDC District Development Committee
DOA Department of Agriculture, Ministry of Agricultural Development
DOI Department of Irrigation, Ministry of Irrigation
DTW Deep Tube Well
DPTC Disaster Prevention Technical Center
DWIDM Department of Water Induced Disaster Management
ET Evapotranspiration
FAO Food and Agriculture Organization of the United Nations
FGWID Field Groundwater Irrigation Division
FIMD Field Irrigation Management Division
FMIS Farmer-managed Irrigation System
GDP Gross Domestic Product
GESI Gender Equality and Social Inclusion
GOJ Government of Japan
GON Government of Nepal
GWID Groundwater Irrigation Division, DOI
IDD Irrigation Development Division, DOI
IDSD Irrigation Development Sub-division, DOI
IMD Irrigation Management Division, DOI
IMT Irrigation Management Transfer
ISP Irrigation Sector Project
iv
ISF Irrigation Service Fee
IWRMP Integrated Water Resources Management Project
IWRMP-AF Integrated Water Resources Management Project -Additional Financing
JICA Japan International Cooperation Agency
JICA-TCP JICA’s Technical Cooperation Project
JMIS Jointly-managed Irrigation System
MOAD Ministry of Agricultural Development
MOFALD Ministry of Federal Affairs and Local Development
MOF Ministry of Finance
MOI Ministry of Irrigation
NISP Nepal Irrigation Sector Project
NWP National Water Plan
O&M Operation and Maintenance
PIM Participatory Irrigation Management
PNA Peacebuilding Needs and Impact Assessment
SDE Senior Divisional Engineer
SISP Second Irrigation Sector Project
STW Shallow Tube Well
UNDP United Nations Development Programme
USAID United States Agency for International Development
VDC Village Development Committee
WB World Bank
WECS Water and Energy Commission Secretariat
WIDMP Water Induced Disaster Management Program
WUA Water Users’ Association
WUG Water Users’ Group
Rs. Rupee Currency in Nepal (Rs.1=Yen 0.9604, as of Sept. 2016)
v
LIST OF TABLES
Table 1-3-1 Development Regions and Districts in the Survey Area, Terai region ........................ 1-2 Table 1-4-1 Outline of the Applications Related to this Survey Made by GON ............................. 1-3 Table 1-4-2 Summary and Comparison of the Third Applications and Antecedent Two Surveys in the Past ............... 1-4 Table 1-4-3 Items for This Time Survey and their Details ............................................................. 1-5 Table 2-1-1 Basic Statistic data of Nepal ........................................................................................ 2-5 Table 2-4-1 Targets for the irrigation sector set by the National Water Plan 2005 ....................... 2-11 Table 2-4-2 Decennial transition of the irrigated area (Unit: ha) .................................................. 2-15 Table 2-4-3 Percentages of the irrigated area to the total agricultural land area ........................... 2-15 Table 2-6-1 Main Irrigation Systems in Terai region .................................................................... 2-22 Table 2-6-2 Budget of IMD (Fiscal Year of 2016/17) .................................................................. 2-22 Table 2-6-3 Budgets of Field IMDs for Fiscal Year 2016/17........................................................ 2-23 Table 2-6-4 Budgets allocated to the Bagmati and Babai Irrigation Systems from Project at the Central Level ........... 2-24 Table 3-1-1 Districts in Terai region ............................................................................................... 3-2 Table 3-1-2 Population Density and Road Density in Terai region ................................................ 3-5 Table 3-1-3 Differences in the ceilings of the land area to be possessed before and after the fifth amendments to the Land Act ............ 3-6 Table 3-1-4 Land Ownership and Utilization in Terai region ......................................................... 3-6 Table 3-1-5 Land Ownership, Renting-in and Renting-out of Farmers in Terai region .................. 3-7 Table 3-2-1 Definition of Irrigation System Scale .......................................................................... 3-8 Table 3-2-2 Definitions of Canal .................................................................................................... 3-9 Table 3-2-3 Distribution of roles in JMIS ..................................................................................... 3-11 Table 3-2-4 Comparison of Features between FMISs and JMISs ................................................ 3-11 Table 3-2-2 Comparison of the FMIS and the JMIS ..................................................................... 3-15 Table 3-3-1 Cultivation Area of Main Crops in Terai Region ...................................................... 3-17 Table 3-3-2 Crop Production in Terai Region (tons) .................................................................... 3-18 Table 3-3-3 Number of Agricultural Cooperatives by District in Terai Region ............................ 3-18 Table 3-3-4 Farmland area and irrigated area by water source in Terai region............................. 3-19 Table 3-3-5 Irrigated Area of the 25 Main Irrigation Systems in the Monsoon Season ............... 3-21 Table 3-3-6 Status of IMT of Major Irrigation Systems in Terai Region...................................... 3-24 Table 3-4-1 Comparison of Contents between CMIASP-AF and IWRMP-AF ............................ 3-30 Table 4-1-1 Irrigation Systems Studied in the Survey (JMIS) ........................................................ 4-1 Table 4-1-2 Irrigation Systems Studied in the Survey (FMIS) ....................................................... 4-1 Table 4-2-1 Water Source and Irrigated Areas of the studied JMISs .............................................. 4-2 Table 4-2-2 O&M of JMISs and WUAs’ Participation into the Irrigation Projects ........................ 4-3 Table 4-2-3 Status of the WUAs ..................................................................................................... 4-4 Table 4-2-4 ISF: Collection Rates and Distribution between WUAs and the GON ....................... 4-6 Table 4-2-5 Condition of Irrigation Facilities in Each Irrigation System Reviewed by the Interview Survey ................ 4-7 Table 4-2-6 Condition of Irrigation Facilities ................................................................................. 4-8 Table 4-2-7 Summary of Malfunctioning of Irrigation Facilities ................................................... 4-9 Table 4-2-8 Frequency of Canal Cleaning and its Record ............................................................ 4-11 Table 4-2-9 Status of Canal Cleaning ........................................................................................... 4-12 Table 4-2-10 Examples of Subsidy Comparisons between Nepal and India ................................ 4-15 Table 4-3-1 ISF and Its Collection Rate ....................................................................................... 4-17 Table 4-3-2 Irrigation Facilities of FMISs Visited ........................................................................ 4-18 Table 4-3-3 Canal Cleaning .......................................................................................................... 4-19
vi
Table 5-3-1 Challenges Identified through Field Visits, Challenges Recognized in the Workshop and Possible Countermeasures ........ 5-5 Table 5-4-1 Specifications of Candidate Sites of Pilot Project ....................................................... 5-8 Table 5-4-2 Current States of Hardware and Software of Candidate Irrigation Systems ............... 5-9 Table 5-4-3 Outlines of Candidate Irrigation Systems.................................................................... 5-9 Table 5-4-4 Scoring to Select Irrigation Systems for JICA-TCP .................................................. 5-10 Table 5-4-5 Challenges and Possible Activities in Kankai Irrigation Systems ............................. 5-12 Table 5-4-6 Challenges and Possible Activities in Bagmati Irrigation Systems (Hearing from the GAR2 Tertiary-canal-level WUA) .. 5-13 Table 5-4-7 Reaches of the Kankai Irrigation System .................................................................. 5-16 Table 5-4-8 Actual irrigable areas and the targets of irrigated areas of the Kankai Irrigation System ......................... 5-16 Table 5-4-9 Distribution of Roles in the maintenance works for the Kankai JMIS ...................... 5-18 Table 5-6-1 Area Where WUA is Responsible after IMT ............................................................. 5-25 Table 5-6-2 Relevance of Contents that DOI Staff Applied for Cooperation ............................... 5-27 Table 6-2-1 Outline of JIC-TCP (Irrigation Part Only) .................................................................. 6-3 Table 6-6-1 Challenges around the land ownership and their possible impact and mitigation measures .................... 6-10 Table 6-6-2 (1) Possible items to be studied with JMISs to address ethnic issues ....................... 6-13 Table 6-6-2 (2) Possible items to be studied with FMISs to address ethnic issues ....................... 6-13
vii
LIST OF FIGURES
Figure 2-1-1 Ecological Zones and Geography of Nepal ............................................................... 2-1 Figure 2-1-2 Trend of the land use in Nepal ................................................................................... 2-2 Figure 2-1-3 Rivers and their Basins in Nepal................................................................................ 2-3 Figure 2-1-4 GDP ........................................................................................................................... 2-4 Figure 2-1-5 GDP per capita ........................................................................................................... 2-4 Figure 2-1-6 General Government Revenue and Total Expenditure .............................................. 2-4 Figure 2-1-7 Current Account Balance ........................................................................................... 2-4 Figure 2-1-8 General Government Gross Debt ............................................................................... 2-4 Figure 2-1-9 Inflation, Average Consumer Prices .......................................................................... 2-4 Figure 2-1-10 Population ................................................................................................................ 2-4 Figure 2-1-11 Poverty rates ............................................................................................................ 2-4 Figure 2-1-12 Food Surplus and Deficit Districts in Nepal ............................................................ 2-7 Figure 2-4-1 Relationships of Laws, Regulations, Policies and Strategy in Irrigation Sector ...... 2-14 Figure 2-6-1 Organization Structure of DOI ................................................................................ 2-19 Figure 2-6-2 Staff Allocation to the DOI Central Office .............................................................. 2-20 Figure 2-6-3 Organization of IDD, Rautahat District ................................................................... 2-25 Figure 2-7-1 Organization Chart of MOAD ................................................................................. 2-27 Figure 2-7-2 Possible Implementation Structure for an Irrigation Project to be Implemented in Collaboration with MOAD ........ 2-28 Figure 3-1-1 20 Districts of Terai region (highlighted with light blue) .......................................... 3-1 Figure 3-1-2 Human Development Index Values across District, 2011 .......................................... 3-4 Figure 3-1-3 Human Poverty Index Value across Districts, 2011 ................................................... 3-4 Figure 3-2-1 Flow Chart of Rehabilitation Process ...................................................................... 3-14 Figure 3-3-1 Crop Calendar in Terai Region ................................................................................ 3-17 Figure 3-3-2 Rate of Irrigated area by District ............................................................................. 3-20 Figure 3-3-3 Image of Vicious Cycle in O&M of Irrigation Systems .......................................... 3-24 Figure 3-3-4 Schematic Diagram of Irrigation Blocks ................................................................. 3-26 Figure 4-1-1 Locations of Studied Irrigation Systems .................................................................... 4-2 Figure 4-2-1 Sluice Gates of the Tertiary Canals in Kankai ......................................................... 4-14 Figure 5-2-1 Objective Analysis and Countermeasures & Activities for Irrigation Improvement . 5-4 Figure 5-4-1 Tertiary canal and PVC pipe to take water off to the watercourse (left) and watercourse (right) in Bagmati . 5-8 Figure 5-4-2 Layout of Kankai Irrigation System ........................................................................ 5-14 Figure 5-4-3 Layout of Bagmati Irrigation System ...................................................................... 5-15 Figure 5-4-4 ISF Revenue of Kankai WUA (2005/06-2015/16) .................................................. 5-17 Figure 5-5-1 Conceptual Diagram of Joint Management ............................................................. 5-19 Figure 5-6-1 Image of the water management area at the on-farm canal level ............................. 5-21 Figure 5-6-1 Change of Expense for O&M after IMT ................................................................. 5-24 Figure 5-6-2 Transition of the Average IMT Collection Rate (Mexico, 2006) ............................. 5-24 Figure 5-6-3 Changes of Timeliness and Equity of Water Distribution through IMT .................. 5-25 Figure 5-6-4 Changes of Irrigated Area, Crop Yield and Farm Income through IMT .................. 5-25 Figure 6-2-1 Procedures of the pilot project approach ................................................................... 6-3 Figure 6-2-2 Approach of the JICA-TCP: Incentive mechanism for farmers ................................. 6-5 Figure 6-2-3 Proposed Framework of JICA Technical Cooperation Project .................................. 6-7
Data Collection Survey
1-1 JICA
Chapter 1 Background and Objectives of the Survey
1-1 Background of the Survey
Agriculture is one of the major industries of the Federal Democratic Republic of Nepal (Nepal). The
percentage contribution of the Agriculture and Forestry Sector to the Gross Domestic Product (GDP) for
the year 2013/2014 was 32.6%1 and 65.62% of the domestic labor population, respectively (aged between
15 and 60 years old). The stability and development of the agricultural sector in which the majority of the
labor population has been involved is one of the priority issues that the Government of Nepal (GON) has
been addressing, and well-functioning irrigation facilities are indispensable for such sectoral development.
The GON has continuously constructed irrigation facilities for a long time, with support from donors. Not
only budget and technology provided by GON but also fund collected from water users as irrigation service
fee (ISF) has been required to maintain such facilities. Thus, the collection of ISF is critical for the
irrigation system management. In addition, it has been recognized the need for capacity development of
water users’ associations (WUAs) in the organizational development and in the technique for operation and
maintenance (O&M)3.
The view of GON on the irrigation development and management mentioned above is reflected in national
policies, including the Agricultural Development Strategy (ADS) 2015-2035, which was approved by GON
in September 2014. The ADS states the importance of the rehabilitation of the existing irrigation systems,
the capacity development of WUAs, the expansion of irrigated area in the existing irrigation systems and
the development of year-round irrigation systems. Such strategies are planned to be implemented,
particularly, in the plain of Terai region where irrigated areas spread all over.
Nepal is divided into three regions from the points of view of geography and climate features: Terai region
(60 - 300m above sea level), Hill region (300 - 4,000m above sea level) and Mountain region (4,000m and
higher above sea level). The agriculture is mainly practiced in Terai and Hill regions. The former is the
producing region of cereals, while the latter is that of vegetables, fruits and livestock products such as milk,
through effective uses of small and narrow farming areas. Terai region consists of the plain of grain belt
stretching from east to west in Nepal.
Very high percentages of major food crops to the national total production are produced in Terai region. The
production amounts of rice, wheat and vegetables in Terai region accounts for 78.6%, 64.1% and 58.1% to
the national total production, respectively4. Nepal has attained the self-sufficiency in crops in general since
2010/11: however, looking at rice, which is one of the staple foods for the Nepalese, it has not attained the
self-sufficiency because the amount of imported rice keeps increasing for the last five years5. So as to attain
the self-sufficiency of their staple foods, it is essential for Nepal to increase the rice production in Terai
region, and this is feasible only when the maintenance of the existing irrigation systems in the region is
1 Statistical Year Book of Nepalese Agriculture 2013/2014, Ministry of Agricultural Development (MOAD) 2 Statistical Year Book of Nepalese Agriculture 2013/2014, MOAD 3 The term of “O&M” is utilized in Nepal to stand for only the maintenance of facilities to keep them functional. Here and after, the term of
“operation” will be utilized to stand for specifically the operation of facilities such as gates to distribute and deliver irrigation water to farmlands. 4 Statistical Year Book of Nepalese Agriculture 2013/2014, MOAD 5 Preparatory Survey on JICA’s Cooperation Program for Agriculture and Rural Development in Nepal -Food Production and Agriculture
in Terai- (2013)
Irrigation Scheme in Terai
DOI, MOI 1-2
given appropriately.
GON planned increases of food crop production and of farm income as agricultural development strategy
for Terai region in the “Agricultural Perspective Plan (APP) -1995/96 2014/15”. APP adopted, as means to
implement such a strategy, the expansion of year-round irrigated area, the construction/rehabilitation of
rural roads, an improvement of agricultural technology and extension services, and the strengthening of
project implementation mechanism with the participation of beneficiaries and/or rural communities in
addition to government agencies. Thus, the promotion of year-round irrigation in Terai region has formed
an important part of national policies and may contribute to an increase in food crop production.
1-2 Objectives of the Survey
Based on the background mentioned in the previous section, GON has made requests to the Government of
Japan (GOJ) for a Technical Cooperation Project of the Japan International Cooperation Agency
(JICA-TCP) to develop capacity for O&M of irrigation systems in Terai region in 2011. After some
discussions between the two governments, the Data Collection Survey on Food Production and Agriculture
in Terai region (2012) and the Preparatory Survey on JICA’s Cooperation Program for Agriculture and
Rural Development in Nepal -Food Production and Agriculture in Terai- (2013) were conducted. Then, this
time, the Data Collection Survey on Promoting Operation and Maintenance (O&M) of Irrigation Scheme in
Terai (hereafter referred to as “the Survey”) has been carried out.
The objectives of the Survey are (a) to examine the current state of irrigation projects in Terai region and (b)
to examine Japan’s cooperation strategy and its framework for technical cooperation projects, putting
emphasis on the current state of O&M by both the Department of Irrigation (DOI) of the Ministry of
Irrigation (MOI) and WUAs.
1-3 Target Region of the Survey
The new constitution was promulgated in 2015 and it divides Nepal into seven provinces. However, the five
Development Regions, Eastern, Central, Western, Mid-Western and Far-Western, are still used as
administrative unit practically. Terai region is not a development region and is, as seen in the previous
section, one of the three regions established in Nepal based on geographical and climatic features: Terai
(plain): Hill and Mountain. The five development regions are arrayed from east to west, while the three
regions of Terai (plain), Hill and Mountain lie from south to north. In this report, Terai region refers to the
geographical and climatic one mentioned above and not an administrative unit, except for the case
particularly noted.
Terai region is composed of twenty districts as follows.
Table 1-3-1 Development Regions and Districts in the Survey Area, Terai region
Development Regions Districts NumberEastern Jhapa, Morang, Sunsari, Saptari and Siraha 5 Central Dhanusha, Mahottari, Sarlahi, Rautahat, Bara, Parsa and Chitwan 7 Western Nawalparasi, Rupandehi and Kapilbastu 3 Mid-Western Dang, Banke and Baldiya 3 Far-Western Kailali and Kanchanpur 2
Total 20 Source: Central Bureau of Statistics. 2014. Population Atlas of Nepal 2014
Data Collection Survey
1-3 JICA
According to DOI, there is no distinctive difference among the five Development Regions in terms of
irrigation and agriculture development plans.
1-4 Scope of the Survey
There are two antecedent surveys to this time Survey, regarding the requested JICA-TCP:
Data Collection Survey on Food Production and Agriculture in Terai region (2012); and
Preparatory Survey on JICA’s Cooperation Program for Agriculture and Rural Development in Nepal
-Food Production and Agriculture in Terai- (from January to August, 2013).
GON submitted the application for a JICA-TCP for the irrigation sector three times to GOJ, in 2011, 2012
and 2015. The following table shows outlines of the application and the antecedent surveys in
chronological order.
Table 1-4-1 Outline of the Applications Related to this Survey Made by GON
Year/Topic Application in 2011 Application in 2012 Application in 2015 Project Title
Enhancing Food Productivity by Farmer’s Managed Small Irrigation Project (FMSIP) in Terai region
Irrigated Agriculture Strengthening Project
Project for Promoting O&M of Irrigation Systems in Terai Plain
Year 2012-2017 2013-2018
2016-2021
Target Area
3 Districts each from the 5 Development Regions (15 Districts)
Districts of Jhapa, Morang, Dhanusha and Mahottari (4 Districts)
20 Districts in Terai region
Overall Goal
Stable food production by the promotion of small scale irrigation
Promotion of irrigation and an increase in farmers’ income
The O&M system that the project applied is adopted in other areas out of the targeted areas.
Project Purpose
Organizational development of WUAs and capacity development of government officers at the field level who are working for the agriculture sector.
Development of model irrigation schemes to be operated and maintained by WUA
The Irrigation systems are well managed and maintained in the target areas.
Activities Construction of 65 small irrigation schemes, organizational development of WUAs, training to field engineers/officers (no mention of the water management within the command areas at the tertiary and lower level canals under the WUA’s management)
Organizational development of WUAs, training to farmers on agricultural technology (assistance to the development of inventory and manuals on the water management within the command areas at the tertiary and lower level canals under the WUA’s management
Organizational Development of WUAs and capacity development of DOI/IDD in O&M, establishment of model O&M systems, Strengthening the coordination and cooperation among stakeholders (assistance to the development of inventory and manuals on the water management within the command areas at the tertiary and lower level canals under the WUA’s management)
Input Dispatch of Experts, project operation costs, training costs (Costs for the construction of model irrigation facilities are counted as input from Japan)
Dispatch of Experts, project operation cost (no description on costs for the construction of model irrigation facilities)
Dispatch of Experts, project operation cost (no description on costs for the construction of model irrigation facilities)
Irrigation Scheme in Terai
DOI, MOI 1-4
Year/Topic Application in 2011 Application in 2012 Application in 2015 Related Survey
Data Collection Survey on Food Production and Agriculture in Terai region (2012)
Preparatory Survey on JICA’s Cooperation Program for Agriculture and Rural Development in Nepal -Food Production and Agriculture in Terai- (2013)
Data Collection Survey on Promoting Operation and Maintenance of Irrigation Scheme in Terai (2016)
Note: DOI: Department of Irrigation, IDD: Irrigation Development Division, WUA: Water Users’ Association
Relationship between the Survey and the above two antecedent surveys are summarized as follows:
Table 1-4-2 Summary and Comparison of the Third Applications and Antecedent Two Surveys in the Past
TOPIC 2012 Survey 2013 Survey This time Survey
Remarks of this time Survey
Target area
Not specified Districts of Jhapa, Morang, Dhanusha and Mahottari (4 Districts)
Entire Terai Plain (20 Districts)
Field visits: 14 irrigation systems in 13 out of the 20 districts in total were visited. Number of Invited irrigation systems to the Workshop: 6 Targets for the Questionnaire survey6: FIMD:13 offices IDD/IDSD:20 offices FGWID:11 offices
Contents of TCP (overall)
Farm mechanization, seed improvement, extension services, marketing, irrigation policies, micro-finance (credit)
Extension services, micro-finance, farm mechanization, income analysis, agronomy
O&M of irrigation systems
Possibility of the inclusion of Farming components shall be further discussed
Contents of TCP (irrigation)
The construction of new facilities shall be considered for western area (due to the low coverage of irrigation), Rehabilitation of existing facilities (such as FMIS) shall be considered for eastern and central areas
Expansion of year-round irrigated area
Construction/ rehabilitation of facilities shall be undertaken by GON
Note: FIMD: Field Irrigation Management Division, IDD: Irrigation Development Division, IDSD: Irrigation Development Sub-division, FGWID: Field Groundwater Irrigation Division, FMIS: Farmer-Managed Irrigation System. Source: Survey team
On the basis of results of the two antecedent surveys, the issues to be investigated through this time Survey
were defined as follows, with the major focus of the Survey on revealing the current situation of the existing
irrigation facilities in Terai region.
6 Questionnaires were sent to FIMD offices for JMIS, and IDD/IDSD offices for FMIS.
Data Collection Survey
1-5 JICA
Table 1-4-3 Items for This Time Survey and their Details Items Details
Present condition of the existing irrigation facilities
Information collection of individual systems which were not fully covered by the antecedent surveys ((1) sources of irrigation water, (2) conditions (good, rehabilitated, requiring a rehabilitation, with signals for the need for future rehabilitation, partially no functioning, etc.) and problems of the headworks as well as the main, secondary and tertiary canals
Implementation set-up (Distribution of roles)
- Progress in the IMT process (agreement of the distribution of roles b/w GON and WUA in JMISs) - Demarcation of roles in the maintenance/development/rehabilitation of the irrigation facilities between the GON and WUAs (The 2013 survey mentions that the 2013 Irrigation Policy defines the cost sharing between the GON and WUAs in the construction, rehabilitation and repair of the irrigation facilities. This time survey reveals actual practices on the ground of the cost sharing.
Ability and willingness of farmers to pay costs of O&M
- Interviews and questionnaire survey with representatives from WUAs (Number of WUAs, ISF collection status, WUA participation in the irrigation projects and O&M activities) (There is no detailed description on the actual situation of WUAs in the reports of the antecedent surveys.)
Notes: IMT: Irrigation Management Transfer, JMIS: Joint-management Irrigation System, IMD: Irrigation Management Division, IDD: Irrigation Development Division, WUA: Water Users’ Association
Source: Survey team
1-5 Methodology of the Survey
1-5-1 Survey Period
The field survey was conducted for 90 days from 19th of June to 16th of September, 2016 in Nepal.
1-5-2 Survey Methodology
(1) Data and information on irrigation and irrigated agriculture in Terai region were mainly collected
through questionnaires to the following 44 offices:
13 Field Irrigation Management Divisions (FIMDs)
20 Irrigation Development Divisions/Sub-divisions (IDDs/IDSDs)
11 Field Groundwater Irrigation Divisions (FGWIDs)
(Refer to Chapter 3 and Annexes for details of the questionnaires and their results.)
(2) The field survey of respective irrigation systems was carried out by visiting and interviewing DOI staff
and WUA members (Refer to Chapter 4 for details of the field survey).
(3) Problem Analysis was carried out in the workshop held on 14th of August, 2016 at the DOI central
office in Kathmandu (Refer to Chapter 5 for details of the workshop).
Data Collection Survey
2-1 JICA
Chapter 2 National Policy and Development Plan of the Irrigation and Agriculture Sectors
2-1 Overview of the Country
2-1-1 Geography
Nepal is a landlocked country which lies thinly from west to east along the main part of the Himalayan
Mountains. It faces the Tibet Autonomous Region of the People’s Republic of China (China) in north, and
the Republic of India (India) in south, east and west. The land area of the country is almost 14,720,000 ha
(147,181 km2. Approximately 885 km long from west to east and 193 km long from south to north), which
is less than two fifth of Japan, and one point eight times large of Hokkaido.
83% of its land area belongs to Mountain and Hill regions, while the remaining 17% is Terai region which is
the plain stretches along the international border with India in the southern Nepal (Figure 2-1-1). The
majority of farmers in Mountain and Hill regions live on subsistence agriculture, but the production has
been reducing recently due to land degrading and/or farm retirement. Meanwhile, owing to the sub-tropical
climate and fertile soil, Terai region is the most productive granary in the country.
Figure 2-1-1 Ecological Zones and Geography of Nepal Source: ADS published by MOAD
Looking at the land use of Nepal from 1991 to 2012, it is obvious that population increase has been
affecting it (Figure 2-1-2). In this period, as the total population increased, other land uses than agriculture
Irrigation Scheme in Terai
DOI, MOI 2-2
and forest also increased. Meanwhile, the forest area has inversely decreased by approximately 1 million
hectare and the agricultural land area seems to have remained as almost the same during these12 years. This
fact indicates that the forest area has been converted into the agricultural land area and areas for other land
uses, such as housing and commercial uses, however, the decline of forest area has not resulted in an
increase of agricultural land area, and it would be difficult to increase agricultural land area from now
onwards. Consequently, it is necessary to improve the land productivity of the existing agricultural lands in
order to increase agricultural production. The expansion of the irrigated area and the promotion of
year-round irrigation in the existing agricultural lands can be one of the possible measures to improve the
land productivity.
Figure 2-1-2 Trend of the land use in Nepal Source: Total population from World Bank, the others from FAOSTAT
2-1-2 Climate
The land area of Nepal lies between 27°and 30°N in latitude, and in Japan the Ogasawara Islands and the
Amami-oshima Island are located at almost the same °N in latitude. Although the entire country belongs to
the sub-tropical climate zone, a variety of climate features can be seen within the country because of a wide
range of elevation: from less than 100m in Terai region to the highest peak in the world, Mount Everest
(8,848 meters above sea level). Such different climate conditions and elevations can divide Nepal into the
following 3 regions:
(a) Terai region (from 60 to 300m high) under the subtropical climate;
(b) Hill region (from 300 to 4,000m high) under the temperate climate; and
(c) Mountain region (more than 4,000m high) under the alpine and cold climate.
The above three regions form continuous geographical features from south to north, and are located on
the Himalayan mountain-building belt which lies on from the Indian Ocean to the northern Tibet high
land. Himalayan oogenesis uplifted the geological formations of these regions made of sedimentary rocks.
The mountain region, which has steep slopes called the Himalayan geological group, has extremely cold
and arid climate. The Hill region is formulated with rocks of the Cretaceous-to-Tertiary Periods, and the
Himalayan oogenesis left lots of cracks inside of the foundations. Therefore, landslides in mountain
Data Collection Survey
2-3 JICA
slopes frequently happen and a huge amount of soils and stones are conveyed to downstream areas7.
The skirts of Hill region are called Siwalik, which is composed of sedimentary rocks from the Tertiary
period to the Pleistocene times. The foundation of the skirts is vulnerable to rainfall and causes
slope/land slide every year. The Terai region is composed of alluvial soils conveyed from the Hill region8.
As mentioned above, the geological features of Mountain and Hill regions (upper streams of Terai) are
that they easily cause land slide and soil erosion. Accordingly, rain causes a lot of sediments in river water
which flows down to Terai region during the monsoon season. Thus, irrigation systems in Terai regions
are required to remove sediments as part of the important maintenance activities; the sediments are
conveyed from Mountain and Hill regions by flood.
Figure 2-1-3 Rivers and their Basins in Nepal Source: Website: RAOnline Nepal, http://www.raonline.ch/pages/np/npmaps01i.html, accessed in October 2016
There are 3 large river basins: Karnali (② in Figure 2-1-3), Gandaki (⑤) and Koshi (⑧), and also other
small and medium river basins. Not to mention, the larger river basins have larger geologically vulnerable
area against rainfall than smaller ones, because the larger river basins have larger Siwalik geological area.
Therefore, large river stream includes more sediments than small and medium river streams. This implies
that surface water irrigation systems in small river basins have less sediment in canals than those in large
river basins.
7 T. Yamamoto, et al. 1998. “The Movement of Sediments and River Improvement in Nepal” Journal of Japan Society of Civil Engineering,
pp.309-314 8 T. Yamamoto, et al. 1998. “The Movement of Sediments and River Improvement in Nepal” Journal of Japan Society of Civil Engineering,
pp.309-314
Irrigation Scheme in Terai
DOI, MOI 2-4
2-1-3 Society and Economy
The International Monetary Fund (IMF) shows Nepalese economy, current national finance and their
projection as follows (from Figure 2-1-4 to Figure 2-1-11).
Figure 2-1-4 GDP Figure 2-1-5 GDP per capita
Figure 2-1-6 General Government Revenue and Total Expenditure
Figure 2-1-7 Current Account Balance
Figure 2-1-8 General Government Gross Debt Figure 2-1-9 Inflation, Average Consumer Prices
Figure 2-1-10 Population Figure 2-1-11 Poverty rates
Source of all the figures on this page: IMF. 2016. World Economic Outlook Databases April, 2016
Data Collection Survey
2-5 JICA
The population is projected to keep increasing by 1.35% per year. GDP and GDP per capita also keep
increasing. The inflation rate goes up once, but it will come down. However, it is predicted that the GON’s
current-account balance gets worse, causing the increased national debt. As for the poverty, it had showed
the downward trend as a whole, but it is important to keep an eye on the trend continuously because the
poverty rate in urban areas turned to the upward trend in 2010/11.
Table 2-1-1 shows basic statistics of Nepal.
Table 2-1-1 Basic Statistic data of Nepal
Item Data / Value Source GDP(2015) 20,880,546 Thousand US
Dollars The World Bank (WB)
GDP per capita(2015) 732.3 US Dollars Exports of Goods and Services: Percentage of GDP (2015) 11.7% Imports of Goods and Services: Percentage of GDP (2015) 41.6% External Debt Stocks (% of Gross National Income) (2014) 20.0% Poverty Headcount Ratio at $1.90 a Day (2011 PPP) (% of population) (2010)
15%
Poverty Headcount Ratio at $3.10 a Day (2011 PPP) (% of population) (2010)
48.4%
Average precipitation in depth (mm per year) (2014) 1,500mm Life Expectancy at Birth (2014) Total 69,6 years
Male 68.2 years Female 71.1 years
Population 26,494,504 National Population and Housing Census 2011
Sex Ratio (Number of males per 100 females) 91.6/100 Population Density 180/km2 Working Age Population (Population between 15 and 59 years old)
57% (15,091,848)
Annual Average Growth Rate of the Population 1.35 Population Distribution Terai region 50.27% (13,318,705)
Hill region 43% (11,394,007) Mountain region 6.73% (1,781,792)
Urban and Rural Populations Urban Area (Population of the 58 Municipalities)
17%
Rural Area 83% Number of Individual Households 5,423,297 households Average Household Size 4.88 persons Female-headed Households 25.73% Source of Drinking Water Tap / Piped Water 47.78%
Tube Well / Hand Pump 35% Spout 5.74% Uncovered Well 4.71% Covered Well 2.45%
Source of Lighting Electricity 67.26% Kerosene 18.28% Solar 7.44% Biogas 0.28%
Caste / Ethnicity 125 Castes / Ethnicity Mother Tongue 123 Languages Literacy Rate Total 65.9%
Male 75.1% Female 57.4%
Irrigation Scheme in Terai
DOI, MOI 2-6
Item Data / Value Source Religion Hindu 81.3%
Buddhism 9.0% Islam 4.4% Kirat 3.1% Christianity 1.4% Prakriti 0.5% Others 0.3%
Availability of the access to the Internet at the Household Level
Total 3.33% Urban Area 12.11% Rural Area 1.24%
Availability of Mobile Phones at the Household Level
Total 64.63% Urban Area 84.07% Rural Area 59.98%
Availability of Landline Telephone at the Household Level
Total 7.37% Urban Area 22.66% Rural Area 3.72%
It should be noted that the population of Terai region accounts for 50% of the national population.
Accordingly, the region is the key area for the development of the Nepal. Meanwhile, the male-female ratio
of the region is approximately 90 to 100 (men is less than women), and the ratio of female householders is
25.7%, which seems very high. This is probably due to men’s migrant working abroad. Therefore, the
women’s participation in irrigated agriculture is important.
The literacy rate has large difference between men and women. The literacy rate of males is 75%, while
that of females is as low as 57%. The average rate of 66% covers the low rate of females, and it seems that
the cause for the difference in the literacy rates between males and females attributes to gender
discrimination. That is, sons are prioritized to be educated in the poor household rather than daughters. In
the strong patriarchal system culture of Nepal, parents tend to think that educating daughters is wasting
money since the daughter marries into another family. The number one reason that boys cannot go to
school is “There is no school.” that is approximately 25%, while that of girls is “their parents do not want
to make them educated.” that is approximately 40%9.
As for information and telecommunication, the dissemination rate of fixed-line phone at the national level
is only 7%, but that of cellphone is 65%. The dissemination of cellphone rate is 60% even in rural areas.
Meanwhile, the national rate of access to the internet is as low as 3%. Thus, the cellphone will be very
useful for information sharing and communication in the irrigated areas.
2-1-4 Food Balance
The proportion of the household suffering from food shortage to all the households in Nepal was 51% in
1995/96, and it drastically decreased to 16% in 2010/11. However, food deficit was seen in 32 districts
out of the 75 in total, according to the agricultural production data from 2011/12 to 2013/14 (MOAD,
2016): Nepal: Zero Hunger Challenge National Action Plan (2016-2025)). Areas where the most serious
food shortage occurred were the Hill and Mountain regions in Far- and Mid-Western Development
Regions (ADS. p.32). The climate of these regions is relatively dry. Besides, the traffic system has not
been well developed and farmers’ access to the market is limited. Therefore, subsistence agriculture is
9 Journal of Gender Studies, Ochanomizu Univ. Vol.11 (2008) “Gender Equality in Education: Experiences of Nepal to Achieve EFA Goal 5”
Data Collection Survey
2-7 JICA
prevailing and farmers do not produce surplus foods. This is the background of the cause for the delay in
agricultural infrastructure development in these development regions.
Meanwhile, in seven districts in Terai region from Eastern to Central Development Regions, food deficit
due to unbalance between cereal production and demand within those districts has been reported. The
unbalance may be attributed to a yield reduction due to river flooding over agricultural lands during the
monsoon season, although it is not confirmed. Otherwise, it may be attributed to higher population
densities in Eastern and Central Development Regions than in other development regions in the western
part of Terai, although it is not confirmed, neither.
Figure 2-10-12 Food Surplus and Deficit Districts in Nepal Source: MOAD, 2016: Nepal: Zero Hunger Challenge National Action Plan (2016-2025)
MOAD analyzed major causes for the above food deficit as: (a) expensive food prices; (b) food
production which cannot catch up with the population increase, and (c) aftermath of the earthquakes. As
for food production, it is pointed out that the segmentation of agricultural lands among the poor has
resulted in a reduction of the productivity and efficiency of farming.
GON aims at eradicating famine in the next 10 years, and has adopted the following 10 policies with
priority to cope with food deficit comprehensively.
As for rural infrastructure development amongst the 10 policies, particularly, MOAD shall accelerate the
implementation of the rural infrastructure development stated in ADS10 in order to eradicate famine
(MOAD, 2016: Nepal: Zero Hunger Challenge National Action Plan:
(i) Enhanced food production and productivity;
(ii) Increased investment in agriculture;
(iii) Rural infrastructure development;
10 ADS spells out that rural roads, storage facilities, irrigation facilities (construction, rehabilitation, and expansion), improvement of water
management capacity of government agencies and farmers are the priority issues in the rural infrastructure sector.
Irrigation Scheme in Terai
DOI, MOI 2-8
(iv) Local consumption of local agricultural products;
(v) Agri-business promotion;
(vi) Creation of employment opportunities;
(vii) Promotion for youth to start farming;
(viii) Providing smallholders and landless farmers with agricultural inputs;
(ix) Safety net support for the socially vulnerable; and
(x) Food governance strengthening.
2-1-5 Basic Infrastructure
Infrastructure damaged by the earthquakes in 2015 is still under reconstruction with priority.
The total length of the strategic network of roads11 to date in the country is 12,500km, and that of rural
roads12 is 53,000km. The road density of the country is 0.44km/km2. As part of efforts to attain the
Sustainable Development Goals (SDGs), GON is to be engaged in the social infrastructure development,
aiming at attaining 5km/km2 of road density, 100% access to telephones, and 10-fold electric-power
generation by 203013.
2-2 Positioning of the Irrigation and Irrigated Agriculture Sectors in the National Plan
The National Planning Commission (NPC), which is led by the Prime Minister as the head of the Executive
branch of GON, is in charge of planning and coordinating national development. Nepal intends to get out of
the category of least developed countries by 2022 and join the middle income countries, by attaining more
than US$2,500 of GNI (Gross National Income) per capita by 2030. Currently, the NPC is leading the
formulation of Vision 2030, which is the long-term national development plan to realize the above intent. It
is supposed that irrigation development and irrigated agriculture are addressed as a principal measure for
the rural poor to increase income in Vision 2030.
ADS which was approved in 2014, is the long-term development strategy for the agriculture sector and is
currently under implementation. This strategy addresses not only agriculture but also irrigation, by
integrating related policies such as the 2010 draft doctrine of Integrated Water Resources Management and
the 2013 Irrigation Policy.
2-3 Legal System of the Irrigation Sector
2-3-1 National Code: Muluki Ain
Muluki Ain was promulgated in 1854. It ensures riparian rights and prior use rights of water. However, it
does not specify “ownership of water”.
The above old version of Muluki Ain 1854 was replaced by the new Muluki Ain in 1963. The new version
contains both substantive and procedural laws covering criminal and civil matters. Chapter 8 of Section 3,
“Land Cultivation (Jagga Abad Garneko)” sets out the priority use of water in irrigation, and also regulates
traditional farmer managed irrigation systems.
11 Main and branch roads administrated by the Department of Road 12 Rural and farm roads administrated by the Department of Local Infrastructure Development and Agriculture Roads 13 National Planning Commission. 2014. "Sustainable Development Goals 2016-2030 National (Preliminary) Report”
Data Collection Survey
2-9 JICA
2-3-2 Water Resource Act 1992
It is an umbrella act governing water resource management and declares the order of priority in water use.
The water use for drinking and domestic purposes has the first priority, followed by the water use for
irrigation.
It stipulates the formation of “Water User Association”, and requires water users obtain licenses. However,
no license is required in case of: (a) drinking and any other domestic use on individual or collective basis;
(b) irrigation of one’s own land on individual or collective basis; (c) operation of running water-mill or
water-grinder as cottage industry; (d) personal use of boat as local transportation; and (e) the personal use of
water resources available within specific land by the land owner.
2-3-3 Water Resource Regulation 1993
This regulation was made in accordance with Article 24 of the aforementioned Water Resource Act 1992. It
stipulates the establishment of the District Water Resource Committees as authority to issue licenses for the
water use in general. The submission of an Environmental Impact Assessment is the pre-requisite to apply
for the license for water resource utilization and survey. This regulation also regulates dispute settlement
mechanisms in relation to water charges.
2-3-4 Irrigation Regulation
(1) Irrigation Regulation 1989
This regulation was institutionalized through the accumulation of studies and experiences of the
participatory water management pilot projects, such as the Irrigation Water Management Project
(United States Agency for International Development: USAID, 1985), the Irrigation Line of Credit
(World Bank: WB, 1988), the Irrigation Sector Project (Asian Development bank: ADB, 1988), and
the Irrigation Sector Support Project (United Nations Development Programme: UNDP/WB/ADB,
1989). This regulation provides the legal framework to water user organizations, and was referred to in
the development of the Water Resources Act 1992.
(2) Irrigation Regulation 2000
The regulation was developed based on Section 24 of the Water Resources Act 1992 as amendment of
the Irrigation Regulation 1989. The WUA for irrigation is recognized under this regulation and the
WUA shall be registered to an irrigation office of respective districts in order to utilize the irrigation
system developed/rehabilitated by GON. Due to this regulation, the traditional water users’ groups
(WUGs) had to convert into the water users’ association (WUAs) with legal personality, and are
required to register to GON.
The WUAs have responsibility to utilize, distribute, maintain, operate and manage the irrigation
system handed over by GON. GON may fully or partially transfer an entire irrigation system to a
registered WUA.
Those irrigation systems, which are too large for a WUA to provide O&M, can be jointly-managed by
GON and WUA based on a written agreement. In case of the Joint Management Irrigation System,
each WUA can individually make an agreement with GON and begin the joint management.
(3) Irrigation Regulation 2004
Irrigation Scheme in Terai
DOI, MOI 2-10
This regulation is the amendment to the Irrigation Regulation 2000. The items newly added are: (a) the
establishment of exclusive fund for O&M, which can be disbursed for manual desilting, canal
reshaping at small scale, greasing, wage for gate operators, etc., and (b) the deposit of at least 10% of
the total ISF collected by WUAs to such an exclusive fund. In addition, the WUA has to pay 10% of
the total amount of ISF to GON as their income tax. Costs for the O&M are much larger than the total
revenue from the ISF collection for most of the WUAs. Therefore, WUAs have no other choice but to
postpone maintenance works, and they often rely on government assistance.
2-4 National Policy and Development Plan/Strategy of Irrigation Sector
2-4-1 Irrigation Policy
(1) Irrigation Policy 1992
This policy supports the Irrigation Management Transfer (IMT) from GON to WUAs, ISF collection
by WUAs, and the demand-based rehabilitation of the Farmer-Managed Irrigation Systems (FMISs).
All irrigation policies after the issuance of this policy consistently require the implementation of the
IMT.
(2) Irrigation Policy 1997
The aforementioned Irrigation Policy 1992 was amended in 1997 by reviewing the sections on the
irrigation sector development, resources mobilization, and economic analysis of the former policy.
The new policy intends to promote new technology and to maximize the participation of private and
non-governmental sectors. The new policy also reiterates the importance of demand-driven irrigation
development.
(3) Irrigation Policy 2003
The aforementioned Irrigation Policy 1997 was amended again in 2003. The new version put an
emphasis on decentralization and WUAs’ autonomous management of irrigation systems in order to
enhance the implementation of the Agricultural Perspective Plan 1995/96-2014/15. The primary focus
remained in the extension of irrigation services to all types of irrigation systems.
(4) Irrigation Policy 2013
The aforementioned Irrigation Policy 2003 was again amended in 2013. The new policy provides a
vision to provide sustainable and reliable year-round irrigation services, so as to increase agricultural
production and productivity. In addition, the new policy puts an emphasis on the sustainable
development of the irrigation sector, by maximizing the utilization of available water resources,
effective water management and institutional reform through empowerment of human resources.
2-4-2 Development Plan/ Strategy
(1) Agriculture Perspective Plan (APP) 1995/96-2014/15
It was a long-term plan for 20 years and the most comprehensive plan for agricultural and rural
development with the objectives of poverty alleviation and food security through accelerating
agricultural growth. It targeted to increase the agricultural gross domestic product to 4.9% per annum
and to reduce the incidence of poverty to 14% in rural areas by 2015. Six strategies adopted by this
Data Collection Survey
2-11 JICA
plan are as follows:
(i) Accelerated economic growth through technology guided agricultural development;
(ii) Agricultural growth creating production demand with multiplier effects on all sectors of the
national economy;
(iii) Higher employment growth as mechanism of attaining social objectives;
(iv) Public policy and investment focusing on a small number of priorities building on past
investment in human capital, and physical infrastructure and institutions;
(v) A package approach to development, specific to Terai, Hills and Mountain regions, that
would recognize the powerful complementarities of public and private investments in order
to ensure their coordination; and
(vi) Broader participation of key stakeholders that ensures regional balance and involvement of
women.
The first priority in the irrigation sector was the expansion of year-round irrigated area, followed by
the enhancement of women’s participation in WUAs and training in O&M of irrigation systems. APP
1995/96-2014/15 showed Terai region as promising candidate area for the “green revolution” in Nepal,
and stated the following 3 strategies for the region to increase food crop production:
(i) Rural infrastructure development, including irrigation facilities
(ii) Promotion of agricultural technology and of investment
(iii) Organizational development of related government institutions
(2) National Water Plan 2005
Water and Energy Commission Secretariat (WECS) prepared National Water Plan (NWP) in 2005 so
that the activities identified by the Water Resources Strategy 2002 can be implemented14. NWP 2005
aims to contribute to the overall national goals of economic development, poverty alleviation, food
security, public health and safety, decent standards of living for the people, and protection of the
natural environment in a balanced manner. NWP 2005 also has targets regarding the irrigation sector.
Table 2-4-1 indicates the targets of the irrigation sector set in the National Water Plan 2005. The plan
defines the target irrigated areas at 2007, 2017 and 2027, respectively. The current situation as of 2016
confirmed through interviews with relevant officers and literature reviews is also shown in the same
table as progress. The percentage of the year-round irrigated area to the total irrigated area as of 2016
(18%) was estimated based on the past achievement in 2010. According to DOI, the target value set in
the National Water Plan 2005 for this proportion is relatively high and it assumes that the actual
proportion still remains as only around 18%.
Table 2-4-1 Targets for the irrigation sector set by the National Water Plan 2005 Indicators 2007 Progress as of 2016 2017 2027
Percentage of year-round irrigated area to the 49% 18% 64% 67%
14 Water Resources Strategy 2002 focused on the following areas: (i) Integration of irrigation planning and management in agricultural
development; (ii) Improved management of existing irrigation systems, and improved planning and implementation of new irrigation systems; (iii)
Development of year-round irrigation in order to support the intensification and diversification of agriculture; (iv) Strengthening of capacity in
planning, implementation and management of irrigation; (v) Redistribution of arable land in order to improve irrigation efficiency and agricultural
productivity; and (vi) Improved groundwater development and management.
Irrigation Scheme in Terai
DOI, MOI 2-12
Indicators 2007 Progress as of 2016 2017 2027 total irrigated area (Source: ADS) Percentage of the irrigated area to the total land area with potential for irrigation
71% 79%
(Source: DOI) 81% 97%
Irrigation efficiency 35%
less than 40% (at least 170,000ha)
(Source: ADS) 45% 50%
Source: National Water Plan 2005
(3) Agriculture Development Strategy (ADS) 2015 - 2035
This Strategy15 is a long term agricultural development strategy for 20 years, developed as succeeding
strategy upon the completion of APP. It has been implemented since November 20, 2015 by GON
(DOI. Irrigation Newsletter No. 98, Mid November 2015 – Mid March 2016). The Ministry of
Agricultural Development (MOAD) was in charge of the development of the strategy in consultation
with the related government agencies and concerned donors. The ADS 2015 – 2035 is a
comprehensive strategy aiming at the reinvigoration of entire rural economies based on agriculture,
instead of focusing narrowly on agriculture.
Based on the existing administrative systems, MOAD takes the lead in the implementation of the same
strategy and coordinates other government agencies at different levels as well as donors and private
organizations. In addition to the consolidated funds of GON, financing from donors and private
organizations are also expected as resources for implementing activities of ADS. In particular, the
establishment and utilization of the ADS Implementation Trust Fund (ATF) with contributions from
donors are planned.
Projects and activities for the Irrigation Sector are planned to form a comprehensive package of
infrastructure and capacity development for irrigation development, which is prepared for one of the
13 outputs required to produce one of the four Outcomes of the ADS: Higher Productivity16. The
followings are the 8 strategies in the irrigation sector for the selected output 2.5 “Irrigated Area
expanded equitably and viably, and improved Irrigation Efficiency and Management”.
1) Expand irrigated area by most feasible means
a. Completing surface water irrigation systems under construction at present,
b. Pilot construction of medium scale ponds / groundwater-recharge basins,
c. Repairing damaged surface water irrigation facilities,
d. Repairing damaged shallow tube wells (STWs),
e. Construction of new STWs, and
f. Developing non-conventional irrigation systems.
2) Increase effective area of existing schemes
a. Irrigation efficiency improvement,
15 ADS replaces APP and it is consistent with other present related laws and policies. Although necessary legal backing for the implementation of
the proposed JICA-TCP is already available, the ADS recognizes the need for new legislative documents for the implementation of itself (For
instance, to establish funding sources for O&M activities, a legislation to enhance the ISF payment is proposed in the strategy paper as seen on the
next page, 2-4-2 (3), 6) b.). 16 ADS consists of the 4 expected outcomes: Output 1: Improved Governance, Output 2: Higher Productivity, Output 3; Profitable
Commercialization, and Output 4: Increased Competitiveness.
Data Collection Survey
2-13 JICA
b. Command area expansion,
c. Improvement of water allocation and cropping plan: provision of agriculture extension
services,
d. Construction of permanent headworks and improvement of main canals managed by farmers,
and
e. Construction of STWs in areas irrigated by minor canals where water shortage occurs.
3) Increase irrigation intensity
a. Improve catchment management.
b. Construct inter-basin transfer schemes.
4) Improve irrigation facilities and the water management within the command areas (the tertiary
and lower level canals) under the WUA’s management
a. Reform and strengthen the existing Irrigation Management Division (IMD).
b. Provide adequate levels of budget, either from national resources or the collection of
adequate ISF.
c. Build capacity of WUAs and provide advice and possibly funding to farmers.
5) Implement Irrigation Management Transfer (IMT) of the management of the 32 government
irrigation systems to WUAs
a. Joint management (government agency / WUA) for large systems with greater
responsibility progressively transferred to the WUA.
b. Full responsibility and ownership transferred to WUAs or federations of WUAs for the
medium scale irrigation systems, whose irrigated area is ranging from 5,000 to 10,000ha.
c. Prepare and implement an IMT pilot project17 for two medium to large irrigation systems,
including the formation of farmer-owned Irrigation Management Company or Cooperative
and studies on international experience of IMT as components.
d. Harmonizing and streamlining legal structures required for ownership transfer to WUAs.
6) Establish funding for O&M
a. Introduce incentives into the system (e.g. government budget support proportional to ISF
collection).
b. Introduce legislation to require a receipt for ISF payment to be attached land tax payment.
c. Enforce the existing requirement that ISF payments be brought up to date, before a land sale
can be registered.
d. Define and charge ISFs per crop in short-term and per volume of water in the long term.
7) Implement integrated water resource management.
a. Finalize the Integrated Water Resources Management (IWRM) policy drafted in 2010.
b. Introduce the IWRM through the country, with management based on hydraulic boundary,
starting in areas where there is inter-sectoral competition or conflict over water.
8) Build capacity of Women Farmers in Irrigated Agriculture and Water Resources Management as
one of measures to enhance Gender Equality and Social Inclusion (GESI).
17 This means a “pilot project” for the implementation of the ADS, and not a pilot project of any specific actual project.
Irrigation Scheme in Terai
DOI, MOI 2-14
As mentioned above, the irrigation regulations 2004 has been brought to effect based on the Water Resources Act promulgated in 1992. In addition, the foundation of national policies lies in the Irrigation Policy 2013, and to implement this policy, a comprehensive strategy, ADS, which addresses different sectors related to agriculture and rural development, such as agriculture, water resources, as irrigation sectors, was developed and put into practices. Figure 2-4-1 shows mutual relationships of these acts, regulations, policies and strategies.
Figure 2-4-1 Relationships of Laws, Regulations, Policies and Strategy in Irrigation Sector Source: Survey team
Agriculture Perspective
Plan (APP)
(1995/96-2014/15)Cent
Agriculture
Development Strategy
(ADS) 2015 -
Irrigation Policy 2003
Irrigation Policy
2013Far Western
Irrigation Policy
1992Mid Western
Irrigation Policy
Irrigation Regulation
2004
Water Resource
Regulation 1993
Irrigation Regulation
2000
Irrigation Regulation
1989
Muluki Ain 1963
Water Resource Act
1992
Laws Regulations Strategy Policy
Water Resource Strategy 2002
National Irrigation Plan 2005
Data Collection Survey
2-15 JICA
2-4-3 Progress of Irrigation Development
The following tables show the progress of irrigation development of Nepal and Terai region. The irrigated area of Terai region has accounted for 76%, 67%, 69% and 73% to the total irrigated area of the country in 1981/82, 1991/92, 2001/02 and 2011/12, respectively. Thus, 70% of the irrigated area of Nepal is intensively spread over Terai region and this implies that the region meets those conditions important for successful irrigation.
Table 2-4-2 Decennial transition of the irrigated area (Unit: ha) Year 1981/82 1991/92 2001/02 2011/12 Nepal 583,900 882,400 1,168,300 1,313,406 Terai (Percentage of the area in Terai to the total area of Nepal)
444,900 (76.2%)
595,100 (67.4%)
801,300 (68.6%)
953,740 (72.6%)
Table 2-4-3 Percentages of the irrigated area to the total agricultural land area
Year 1981/82 1991/92 2001/02 2011/12
Nepal 23.7% 34.0% 44.0% 52.0%
Terai 31.7% 43.3% 57.4% 74.2% Sources for Table 2-4-2 and Table 2-4-3 above: Agriculture Monograph and CBS. National Sample Census of Agriculture
(District) 2011/12 and National Sample Census of Agriculture 2011/2012
As seen earlier, there is little possibility of the expansion of the agriculture land in Nepal, and therefore, to
strengthen the cropping intensity on the existing agricultural land together with the provision of appropriate
irrigation facilities is necessary in order to increase agricultural production and to improve productivity.
Tables above show that the irrigated area has been expanded continuously. However, the year-round
irrigated area has not been expanded.
ADS discusses that the total year-round irrigated areas of Nepal in 2010 was 234,000ha and they accounted
for 18% of the irrigable areas of the country. According to the Nepal National Committee for the
International Commission on Irrigation and Drainage (ICID), the percentage of year-round irrigated area to
the total irrigated area in Terai region in 1997 was 36.6% (288,000ha). DOI admitted that such percentages
still remain as almost the same today, though the irrigated area is slightly increased in both Terai region and
in the country as a whole.
As an outcome of the policy implementation, irrigated area has consistently increased. However, the
year-round irrigated area has not increased. This fact implies that the sluggishness of the expansion of
year-round irrigated area could become a bottleneck to achieve increased agricultural production and
improved productivity. In other words, the expansion of the year-round irrigated area is the challenge to be
actively addressed by GON from now on.
2-4-4 Improvement of Irrigation Efficiency
The irrigation efficiency is classified into two categories: conveyance efficiency and application efficiency.
The former is determined by the proportion of water loss occurred while water travels from a headwork to
farming plots. The loss is caused not only due to seepage and evaporation but also due to malfunctioning
canal structures and inadequate gate operations. The latter is determined by the proportion of water loss
occurred when farmers apply water onto crops in their plots. The loss is caused mainly due to
over-irrigation, which may result in deep percolation below the effective root level of crops. Such water
Irrigation Scheme in Terai
DOI, MOI 2-16
loss by deep percolation can be reduced if farming plots are leveled, since water can pervade uniformly
over the plots without concentrating on the lowest areas.
ADS aims at improving the irrigation efficiency. To improve the conveyance efficiency, canal lining, proper
allocation of irrigation facilities to secure their functions as well as proper operation of facilities for water
management are needed. Lining reduces the seepage loss and water is distributed properly by well allocated
irrigation facilities. Controlling water flow by properly operating water management facilities makes
accurate water distribution possible. On the other hand, ADS pursues the improvement of the application
efficiency by the establishment of water distribution network through capacity development of WUA
members, leveling of farming plots, on-farm water management, and so forth.
2-5 Ministry of Irrigation
2-5-1 Mandates
Abundant water resource in Nepal is utilized not only for irrigation but also for hydraulic power generation,
urban and rural water supply, and industrial uses, and therefore, it is invaluable natural resource for Nepal’s
economic development. The authority for the water use and management in the irrigation sector is MOI.
MOI is in charge of the preparation of policies and plans and their implementation in the irrigation sector,
and at the same time, is responsible for the attainment of targets of the irrigation sector among the national
targets.
As per the Work Division (Second Amendment) Rules, 2009 of GON, this ministry has the following
duties:
(1) Development and implementation of policies/plans for conservation, regulation and utilization of
water resource for irrigation;
(2) Conducting and Promotion of surveys, researches and feasibility studies of irrigation
development;
(3) Construction, operation and maintenance of irrigation facilities;
(4) Human resource development and capacity building;
(5) Activities related to Flood and Flood Control;
(6) Study, research, feasibility study, construction, operation and maintenance of each irrigation
facility;
(7) Promotion of the participation of private sector in the irrigation development;
(8) Conducting survey and research on water resource development and undertaking of such
development;
(9) Groundwater Resources;
(10) Construction, conservation, integrated operation of irrigation facilities in rural areas as part of
Irrigation Development of the country;
(11) National and international seminars and workshops;
(12) Facilitation of bilateral and multilateral dialogues, agreements and mutual understandings
regarding irrigation;
(13) Cooperation among institutions related to irrigation development;
(14) Matters related to tax imposed on the use of irrigation;
(15) Prevention of natural disasters related to water;
Data Collection Survey
2-17 JICA
(16) Surveys and researches on disasters related to water;
(17) Coordination with International institutions and organizations on disasters related to water;
(18) Development and Implementation of policies and plans on disasters related to water;
(19) Qualification setting for the recruitment, transfer and promotion of technical service officers who
work for the following groups
- Meteorology Group
- Irrigation Sub-group
The Secretary is the administrative head of the Ministry and there are established three Divisions and two
Departments which are directly answerable to the Secretary. The Administration Division, Planning &
Program Division and Policy & Foreign Coordination Division are the three Divisions which assume the
roles of the ministry’s secretaries and most of their activities are carried out at the central level. On the
other hand, the two Departments, DOI and the Department of Water Induced Disaster Management
(DWIDM), have their activities at the local level. The outline of these Divisions and Departments are
described in 2-5-2 and 2-5-3 below.
2-5-2 Divisions
(1) Administration Division
This Division consists of the following three Sections.
(2) Planning & Program Division
The Division consists of the following three Sections.
(3) Policy & Foreign Coordination Division
The Division consists of the following four Sections.
Planning & Program Division
Budget & Program Section Monitoring & Evaluation Section
Information & Public Relations Section
Policy & Foreign Coordination Division
Environment Section Research & Development Section
Foreign Coordination Section Policy Section
Administration Division
Human Resource Management Section Fiscal Administration Section Legal Section
Irrigation Scheme in Terai
DOI, MOI 2-18
2-5-3 Departments
(1) DOI
DOI is a governmental agency, with the mandate to plan, develop, maintain, operate, and manage
socially adoptable and environmentally sustainable irrigation and drainage systems. The agency works
for surface water irrigation systems irrespective of their scales ranging from small to large scale, as well
as groundwater irrigation systems irrespective of their ownership ranging from individually owned to
community owned. The primary goal of DOI is to increase the irrigated area in the country as large as
possible, through the provision of year-round irrigation facilities. The overall goal is to contribute to an
increase of GDP and an improvement of the living standards of beneficiary farmers, by meeting basic
conditions to improve the farming land productivity through the expansion of the irrigated area.
(2) DWIDM
Nepal has a high potential that various types of water-induced disasters such as flood, soil erosion,
landslides, debris flow, bank erosion, etc. are induced easily due to its rugged topography and weak
geological formation with active fault. The expansion of such disasters may turn into serious threat to
sustainable development of the country by doing harms on roads, houses, hydraulic power generation
facilities, irrigation facilities and water purifying plants.
In order to prevent such water induced disasters in Nepal, the Disaster Prevention Technical Centre
(DPTC) was established based on an agreement between GON and GOJ signed in October 1991. The
support from JICA to DPTC was provided for seven and half years and GON has been implementing the
Water Induced Disaster Management Program (WIDMP) since July 2000, so as to institutionalize the
achievements of DPTC with support from JICA. DWIDP has been implementing WIDMP through its
seven divisions and five sub-divisions.
2-6 Department of Irrigation (DOI)
DOI belongs to MOI and is the governmental department responsible for irrigation development. Figure
2-6-1 shows its organization structure. The Director General is the head of Department and under the
Director General, there are 5 divisions headed by Deputy Director Generals. In addition, 5 Regional
Irrigation Directorates, Groundwater Irrigation Directorate and Irrigation Management Directorate are set
as branch offices directly answerable to the Director General. Directors of central level projects and
programs are appointed by the Director General.
The Irrigation Management Division (IMD) is in charge of O&M, on-farm water management and IMT at
the DOI central office. The Irrigation Management Directorate and the 13 Field-level Irrigation
Management Divisions (FIMDs) as well as the Irrigation Development Divisions/Sub-divisions
(IDDs/IDSDs) under each of the five Regional Irrigation Directorates are in charge of such duties at the
local level. In addition, the Groundwater Irrigation Directorate and the 11 Field-level Groundwater
Irrigation divisions (FGWID) construct tube wells and give maintenance to them.
D
ata Collection S
urvey
2-19
JICA
Irrigation Schem
e in Terai
DO
I, MO
I 2-20
Senior Divisional Engineer(Gazetted (II) Civil)
1
Engineer (Gazetted (III) Civil) 1Computer Operator(Nongazetted (I) Misc.)
1
Clerk (Nongazetted (I) /Gen.Admin.)
1
Office Assistant 2
Sub-total 6
Computer and documentation Computer and documentationComputer Officer (Gazetted (III)) 1 Computer Officer (Gazetted (III)) 1 Computer Officer (Gazetted (III)) 1 Computer Officer (Gazetted (III)) 1 Computer Officer (Gazetted (III)) 1 Under Secretary (Chief Admin.
Officer)1
Clerk (Nongazetted (I) / Gen.Admin.) 1 Clerk (Nongazetted (I) / Gen.Admin.) 1 Clerk (Nongazetted (I) / Gen.Admin.) 1 Clerk (Nongazetted (I) / Gen.Admin.) 1 Clerk (Nongazetted (I) / Gen.Admin.) 1 Section Officer 3Office Assistant 2 Office Assistant 2 Office Assistant 2 Office Assistant 2 Office Assistant 2 Clerk (Nongazetted (I) /
Gen.Admin.)4
Sub-total 4 Sub-total 4 Sub-total 4 Sub-total 4 Sub-total 4 Computer Operator(Nongazetted (I) Misc.)
4
Electrician 1Plumber 1
Senior Divisional Engineer (Gazetted (II)Civil)
1 Senior Divisional Engineer (Gazetted (II)Civil)
1 Senior Divisional Engineer (Gazetted(II) Civil)
1 Senior Divisional Hydrogeologist(Gazetted (II) Hydrogeology)
1 Senior Divisional Engineer(Gazetted (II) Agri)
1 Store Keeper 4
Engineer (Gazetted (III) Civil) 2 Engineer (Gazetted (III) Civil) 4 Engineer (Gazetted (III) Civil) 1 Hydrogeologist (Gazetted (III)Hydrogeology)
1 Engineer (Gazetted (III) Agri) 1 Office Assistant / SecurityGuards / Gardener / Sweepers
13
Computer Engineer (Various) 1 Sub-total 5 Sub-total 2 Sub-total 2 Engineer (Gazetted (III) Civil) 1 Sub-total 31
Sub-total 4 Sociologist (Gazetted (III) Various) 1 Account Section
Sub-total 4 Chief Treasury Controller 1
Monitering and Evaluation Section Senior Divisional Engineer (Gazetted (II)Civil)
1 Senior Divisional Engineer (Gazetted(II) Civil)
1 Account Officer 2
Senior Statistical Officer (Gazetted (II)Financial Planning & Statistics)
1 Sociologist (Gazetted (III) Misc.) 1 Engineer (Gazetted (III) Civil) 1 Senior Divisional Hydrogeologist(Gazetted (II) Hydrogeology)
1 Accountant 4
Sociologist (Gazetted (III) Various) 1 Engineer (Gazetted (III) Civil) 2 Sub-total 2 Hydrogeologist (Gazetted (III)Hydrogeology)
1 Senior Sociologist (Gazetted (II)Various)
1 Computer Operator(Nongazetted (I) Misc.)
1
Engineer (Gazetted (III) Civil) 1 Agri. Economist (Gazetted (III) Agri. Eco.Marketting)
1 Engineer (Gazetted (III) Civil) 1 Engineer (Gazetted (III) Civil) 1 Assistant Accountant 1
Agri. Economist (Gazetted (III) Agri.Eco. Marketting)
1 Hydrogeologist (Gazetted (III)Hydrogeology)
1 Sub-total 3 Engineer (Gazetted (III) Agri) 1 Office Assistant 2
Hydrogeologist (Gazetted (III)Hydrogeology)
1 Engineering Geologist (Gazetted (III)Engineering Geology)
1 Senior Divisional Engineer (Gazetted(II) Civil)
1 Sub-total 3 Sub-total 11
Engineer (Gazetted (III) Agri) 1 Engineer (Gazetted (III) Agri) 1 Engineer (Gazetted (III) Civil) 2 Law Section
Statistical Officer (Gazetted (III)Financial Planning & Statistics)
1 Sub-total 8 Sub-total 3 Senior Divisional Hydrogeologist(Gazetted (II) Hydrogeology)
1 Senior Legal Officer 1
Sub-total 7 Hydrogeologist (Gazetted (III)Hydrogeology)
1 Senior Divisional Engineer(Gazetted (II) Agri)
1 Legal Officer 1
Senior Divisional Engineer (Gazetted (II)Civil)
1 Senior Divisional Mechanical Engineer(Gazetted (II) Mech.)
1 Chemist (Gazetted (III) Chem) 1 Engineer (Gazetted (III) Civil) 1 Computer Operator(Nongazetted (I) Misc.)
1
Senior Divisional Engineer (Gazetted (II)Civil)
1 Engineer (Gazetted (III) Civil) 1 Mechanical Engineer (Gazetted (III)Mech.)
2 Sub-total 3 Engineer (Gazetted (III) Agri) 1 Sub-total 3
Engineer (Gazetted (III) Civil) 1 Sub-total 2 Mechanical Sub-Engineer(Nongazetted (I) Mech.)
1 Sub-total 3 Library
Sociologist (Gazetted (III) Misc.) 1 Senior Mechanist (Nongazetted (I)Mech.)
2 Senior Divisional Hydrogeologist(Gazetted (II) Hydrogeology)
1 Librarian 1
Environment Inspector 1 Senior Sociologist (Gazetted (II) Misc.) 1 Vehicle Driver 17 Hydrogeologist (Gazetted (III)Hydrogeology)
1 Senior Divisional Engineer(Gazetted (II) Agri)
1 Library Assistant 1
Sub-total 4 Sociologist (Gazetted (III) Misc.) 2 Sub-total 23 Engineer (Gazetted (III) Civil) 1 Engineer (Gazetted (III) Civil) 1 Office Assistant 1
Sub-total 3 Sub-total 3 Engineer (Gazetted (III) Agri) 1 Sub-total 3Senior Divisional Engineer (Gazetted (II)Civil)
1 Sub-total 3
Engineer (Gazetted (III) Civil) 2
Sub-total 3
Total 23 Total 23 Total 35 Total 16 Total 18 55
Total Number of Posts 170
Organization Chart of Department of Irrigation
Program Monitering and Evaluation Division Planning Division Surface Irrigation, Environment andMechanical Division
Groundwater Irrigation Division Irrigation Management Division
Deputy Director General Deputy Director General Deputy Director General Deputy Director General Deputy Director General Gazetted (I) / Civil - 1 Gazetted (I) / Civil - 1 Gazetted (I) / Civil - 1 Gazetted (I) / Hydrogeology - 1 Gazetted (I) / Agri- 1
Computer and documentation Computer and documentation Computer and documentation Administration Section
Geomatics Section Planning and Design Section Small and Medium Irrigation Section Shallow Tubewell Section System Management Section
Large Irrigation Section
Feasibility Study Section DeepTubewell Section
Water User's AssociationStrengthening Section
Procurement and Agreement ManagementSection
Water Quality Evaluation and UseSection
Water Management Section
Foreign Coordination Section Mechanical Management Section
Environment and climate change section
Ground Water Investigation Section
Gender Equality and Social Inclusion Section Irrigation Management TransferSection
Total (incl. Director General)
(Source: DOI)
Program and Budget Section
Director GeneralGazetted (I)
Figure 2-6-2 Staff Allocation to the DOI Central Office
Data Collection Survey
2-21 JICA
DOI officers affirmed in the interviews that DOI has accumulated skills in the irrigation facility
construction, since the main duties of the Department have been planning, designing, and constructing
of irrigation facilities for a long time. Accordingly, it is assumed that the DOI engineers have enough
capacity to plan and design small scale irrigation systems, and for the construction of large-scale
facilities, they have rich experience in the supervision, as DOI, usually, outsources the construction of
large scale facilities.
DOI is aware of the importance of O&M of the irrigation facilities, and has been developing the
capacity of their engineers in O&M. All the existing positions within DOI are shown in Figure 2-6-2
and the training materials to the DOI officers are listed in Annex-6.
With regard to the human resource capacity, currently 87 persons are assigned to the 27 positions for
civil engineer shown in the establishment for FIMDs, according to the obtained information.
Meanwhile, there are currently 20 persons are assigned to the 24 positions for agricultural engineers
defined in the establishment.
2-6-1 Irrigation Management Division (IMD)
The IMD is the division responsible for the management of Jointly-Managed Irrigation Systems
(JMISs), which are large and major scale irrigation systems developed by DOI. Separately, there are
IDD and IDSD as responsible offices for the management of medium and small scale irrigation systems.
IMD supports IDD and IDSD in O&M of medium and small scale irrigation systems under specific
projects such as the Integrated Water Resources Management Project – Additional Financing –
(IWRMP-AF) and the Community Managed Irrigated Agriculture Sector Project – Additional
Financing – (CMIASP-AF).
The large scale irrigation systems under the management of IMD are called “Main Irrigation Systems”,
which DOI has selected because of their scale (irrigated area) and difficulties in O&M. There are 25
Main Systems in Terai region, which are jointly managed by WUAs and 13 FIMDs and the IDD of
Rupandehi. The following table shows the general information on the 25 Main Irrigation Systems and
the irrigated areas vary from system to system. The smallest irrigated area is 1,800ha while the largest is
68,000ha: more than 37 times as large as the smallest one. The average irrigated area of the 25 systems is
12,800ha.
Irrigation Scheme in Terai
DOI, MOI 2-22
Table 2-6-1 Main Irrigation Systems in Terai region S/N IMD Name District S/N Irrigation System Command
Area (ha) 1 Kankai Jhapa (1) Kankai 8,000 2 Sunsari Morang Sunsari (2) Sunsari Morang 68,000
(3) Chanda Mohana 1,800 3 Koshi Pump Chandra
Nahar Saptari (4) Chandra Nahar 10,000
(5) Koshi West Canal (Distribution System) 10,500 (6) Koshi Pump Canal 13,180
4 Kamala Dhanusha (7) Kamala 25,000 (8) Hardinath 2,000
5 Bagmati Sarlahi (9) Mansumara 5,200 (10) Bagmati 37,600 (11) Jhanj 2,000
6 Narayani Parsa (12) Narayani 28,700 (13) Narayani Tube Well 2,800
7 Narayani Lift-Khageri Chitwan (14) Narayani Lift 4,750 (15) Khageri 3,900
8 Gandak Nawalparasi (16) Nepal Gandak Western Canal 10,300 9 Bhairawa Lumbini
Groundwater Rupandehi (17) Bhairahawa Lumbini Bhumigath Jalshorat 20,309
10 Banganga Kapilbastu (18) Banganga 6,350 11 Praganna Dang (19) Praganna Kulo 6,684 12 Babai Rajapur Bardiya (20) Babai 27,000
(21) Rajapur 14,870 13 Mahakali Mahakali (22) Pathraiya 2,000
(23) Mohana 2,000 (24) Mahakali 11,600
IDDO Rupandehi Rupandehi (25) Machawar Lift 5,600 13 Field IMDs & 1 IDDO 25 Irrigation Systems 330,143
Source: IMD and FIMD
The total budget of IMD for the fiscal year of 2016/17 is shown in Table below. The amount includes not
only the budget for O&M but also that for construction (rehabilitation).
Table 2-6-2 Budget of IMD (Fiscal Year of 2016/17) Item Amount (Unit: Nepal Rs.) *1 Remark
Irrigation System Management and Training Programs
8,927,000(8,605,628)
O&M*2 852,232,000(821,648,048)
The amount for all the O&M activities to be undertaken by IMD.
Rehabilitation of Large Scale Irrigation Systems and IMT Projects*3
646,094,000(622,834,616)
TOTAL 1,507,353,000(1,453,088,292)
*1 The amounts in Japanese Yen (Rs. 1 = Yen 0.9604) are shown in the parenthesis. The information on the budget adequacy for duties as well as on the availability of financial support from donors was not obtained. *2 This item includes the budget of the 13 FIMDs for O&M activities such as cleaning of canals and repairs of small scale canals, which is amounting to Rs. 263,331,000. *3 This item includes the budget of the 13 FIMDs for the repair and rehabilitation of facilities (LISP), which is amounting to Rs. 634,585,000.
Source: Ministry of Finance. Estimate of expenditures, Budget Details - Red Book
Data Collection Survey
2-23 JICA
Table below shows the annual budget for the FIMDs. As the Kankai irrigation system has a schedule of
large scale rehabilitation (re-plastering weir) in this coming spring, the costs for such rehabilitation is
budgeted under the item of construction. The budget for the Bagmati and Babai Irrigation Systems is zero,
since the budget required for these two irrigation systems is going to be allocated as part of the budget of the
project at the central level, as shown in Table 2-6-3. Therefore, such budget cannot be incorporated into the
budget of FIMDs.
Table 2-6-3 Budgets of Field IMDs for Fiscal Year 2016/17
Unit: Nepal Rupees, and the figure in parenthesis is the amount converted into Japanese Yen (Rs. 1 = Yen 0.9604)
No. FIMD in charge District Name of Irrigation
System O&M
(AMIS) Construction TOTAL
1 Kankai Jhapa Kankai 19,600,000 52,446,000 72,046,000 (18,894,400) (50,557,944) (69,452,344)
2
Sunsari Morang
Sunsari
Sunsari Morang 2,734,000 0 2,734,000 (2,635,576) (0) (2,635,576)
Chanda Mohana 8,055,000 0 8,055,000 (7,765,020) (0) (7,765,020)
Total of FIMD 10,789,000 0 10,789,000
(10,400,596) (0) (10,400,596) 3
Koshi Pump Chandra Nahar
Saptari
Chandra Nahar
8,042,000 90,000,000 98,042,000 (7,752,488) (0) (94,512,488)
Koshi West Canal (Distribution System)
4,255,000 47,500,000 51,755,000 (4,101,820) (0) (49,891,820)
Koshi Pump Canal
25,968,000 47,700,000 73,668,000 (25,033,152) (0) (71,015,952)
Total of FIMD 38,265,000 185,200,000 223,465,000
(36,887,460) (0) (215,420,260)
4
Kamala
Dhanusha
Kamala
18,545,000 0 18,545,000 (17,877,380) (0) (17,877,380)
Hardinath
4,240,000 185,456,000 189,696,000 (4,087,360) (178,779,584) (182,866,944)
Total of FIMD 22,785,000 185,456,000 208,241,000
(21,964,740) (178,779,584) (200,744,324) 5
Bagmati
Sarlahi
Mansumara
3,900,000 0 3,900,000 (3,759,600) (0) (3,759,600)
Bagmati
0 0 0 (0) (0) (0)
Jhanj
5,236,000 0 5,236,000 (5,047,504) (0) (5,047,504)
Total of FIMD 9,136,000 0 9,136,000
(8,807,104) (0) (8,807,104) 6 Narayani
Parsa
Narayani
2,050,000 0 2,050,000 (1,976,200) (0) (1,976,200) Narayani Tube Well 8,582,000 68,742,000 77,324,000 (8,273,048) (66,267,288) (74,540,336)
Total of FIMD 10,632,000 68,742,000 79,374,000
(10,249,248) (66,267,288) (76,516,536)
Irrigation Scheme in Terai
DOI, MOI 2-24
No. FIMD in charge District Name of Irrigation
System O&M
(AMIS) Construction TOTAL
7 Narayani Lift-Khageri
Chitwan
Narayani Lift
6,857,000 70,447,000 77,304,000 (6,610,148) (67,910,908) (74,521,056) Khageri
37,491,000 0 37,491,000
(36,141,324) (0) (36,141,324)
Total of FIMD 44,348,000 70,447,000 114,795,000
(42,751,472) (67,910,908) (110,662,380) 8
Gandak
Nawalparasi
Nepal Gandak Western Canal
10,768,000 41,147,000 51,915,000 (10,380,352) (39,665,708) (50,046,060)
9 Bhairawa Lumbini Groundwater
Rupandehi Bhairahawa Lumbini Bhumigath Jalshorat
9,955,000 0 9,955,000 (9,596,620) (0) (9,596,620)
10 Banganga Kapilbastu Banganga 17,715,000 31,147,000 48,862,000 (17,077,260) (30,025,708) (47,102,968)
11 Praganna Dang Praganna Kulo 20,540,000 0 20,540,000 (19,800,560) (0) (19,800,560)
12 Babai Rajapur
Bardiya
Babai
0 0 0 (0) (0) (0) Rajapur
21,715,000 0 21,715,000
(20,933,260) (0) (20,933,260)
Total of FIMD 21,715,000 0 21,715,000
(20,933,260) (0) (20,933,260)
13
Mahakali
Mahakali
Pathraiya
6,671,000 0 6,671,000 (6,430,844) (0) (6,430,844)
Mohana
1,717,000 0 1,717,000 (1,655,188) (0) (1,655,188)
Mahakali
18,695,000 0 18,695,000 (18,021,980) (0) (18,021,980)
Total of FIMD 27,083,000 0 27,083,000
(26,108,012) (0) (26,108,012) TOTAL 13 FIMDs
24 Irrigation
Systems 263,331,000 634,585,000 897,916,000
(253,851,084) (611,739,940) (865,591,024) *AMIS: Agency Managed Irrigation System
Source: Ministry of Finance. Estimate of expenditures, Budget Details - Red Book
Table 2-6-4 Budgets allocated to the Bagmati and Babai Irrigation Systems from Project at the Central Level
Unit: Nepal Rupees, and the figure in parenthesis is the amount converted into Japanese Yen (Rs. 1 = Yen 0.9604)
Irrigation System
O&M Construction TOTAL
Bagmati 101,655,000 296,718,000 398,373,000 (97,995,420) (286,036,152) (384,031,572)
Babai 8,000,000 658,300,000 666,300,000 (7,712,000) (634,601,200) (642,313,200)
TOTAL 109,655,000 955,018,000 1,064,673,000 (105,707,420) (920,637,352) (1,026,344,772)
Source: DOI
2-6-2 Field Level Irrigation Management Division (FIMD)
In July 2015, DOI newly established the Irrigation Management Directorate and the 13 FIMDs in Terai
region. The Irrigation Management Directorate guides, monitors and evaluates the FIMDs. Twenty-four out
Data Collection Survey
2-25 JICA
of the 25 Main Systems are managed by the 13 FIMDs, and the remaining one (Machawar Lift Irrigation
System) is under the IDD of Rupandehi District (Table 2-6-1). Each FIMD manages 1 to 3 Main Systems in
cooperation with WUAs. All these Main Systems are the targets of IMT and GON is bringing forward the
transfer process in accordance with the ADS as well as the Irrigation Policy 2013.
FIMD chiefs are the skilled Senior Divisional Engineers (SDEs), which is the second highest rank of the
DOI engineers. In addition, undergraduate engineers (civil engineers and/or agricultural engineers);
engineers with diploma (sub-engineers) and association organizers who are undergraduates, are assigned to
the FIMDs. The actual number of staff assigned to each FIMD is listed in Annex 3, while the proposed
establishment numbers and organizational structure are shown in Annex 1.
2-6-3 Irrigation Development Division / Sub-division (IDD/IDSD)
IDDs and IDSDs are placed under the Regional Irrigation Directorates located in each of the five
Development Regions of Nepal: Far-Western, Mid-Western, Western, Central and Eastern. Currently, either
IDD or IDSD is established in each District of the country, and there are 20 IDDs or IDSDs placed in Terai
region. IDDs and IDSDs are in charge of the development and O&M of small and medium scale surface
water irrigation systems, namely, FMISs. The figure below shows the organization of the IDD in Rautahat
District. Though the organization structure varies from district to district, the positions (SDE, Engineers,
and Sub-Engineers) and the number of staff assigned to IDD are similar. IDSD has the same functions as
IDD does, but its scale (the number of staffing) is smaller than IDD. Association Organizers (AOs) are
sociologists, who are engaged in the establishment and development of WUAs. The organizational
structure and budget of each of the IDDs are attached in Annex 1.
Figure 2-6-3 Organization of IDD, Rautahat District Source: IDD in Rautahat district
2-6-4 Groundwater Irrigation Divisions
There are 11 Groundwater Irrigation Divisions (GWIDs) established in Terai region and they are manned
with hydrogeologists, engineers and sociologists, although the total number of staff is limited (See Annex-1,
Proposed establishment, for details of the staff allocation). GWIDs build deep and shallow tube wells for
groundwater irrigation systems. In case of the irrigation system with the conjunctive use of surface and
ground water, GWID takes care of the part of groundwater within such systems.
Technical Section Administrative Section Finance Section
Engineer: -2 Sub Engineer:-2 Association Organizer:-1
Administrative Assistant (Nayab Subba):-1 Typist (Computer Operator):-1 Office Assistant (Kaa.Sa.):-4 Light Vehicle Driver:-1
Finance / Account Officer:-1 Accountant:-1
Chief Divisional Engineer (C.D.E.)
Irrigation Scheme in Terai
DOI, MOI 2-26
2-7 Other Related Institutions
2-7-1 Ministry of Agricultural Development
MOAD, when participating in an irrigation project, takes care of the agricultural component (Figure
2-7-1). More concretely, MOAD may be in charge of practices of crop water management, water-saving
rice-growing techniques, cropping patterns, production of improved seeds, agricultural mechanization, soil
management, support for marketing, improvement on access to markets, cropping plan, soil fertility
analysis and management, and the utilization of small agricultural machines and equipment, among others
within the command areas (the tertiary and lower level canals) under the WUA’s management.
Meanwhile, DOI is in charge of supporting water management in the command areas under the
management of WUAs, such as calculation of irrigation requirement for the distribution of water and the
training of on-farm irrigation method. After the completion of the IMT, WUAs remain responsible for the
water management of the command areas under their management, while beneficiary farmers assume the
responsibility for irrigation water use and crop production on their individual farming plots.
IMD of DOI is playing a pivotal role in projects for the irrigation sector, which are under the
implementation with support from WB and ADB and the participation of MOAD. As part of the
implementation structure, a Project Appraisal Committee chaired by the Director General of DOI is to be
set above IMD, and likewise, a Project Steering Committee chaired by the Secretary of MOI, above the
Project Appraisal Committee (Figure 2-7-2).
The Secretary of MOI chairs the Project Steering Committee, while the Director Generals of DOI and
DOA should be assigned to the same committee as members. Representatives from other related
government agencies, such as the Ministry of Federal Affairs and Local Development and the Ministry of
Finance, are usually assigned as members as well. The Project Steering Committee meets twice a year to
monitor progress of the project, to provide necessary instruction to the project, and to coordinate among
different government agencies for the implementation of the project.
The Director General of DOI chairs the Project Appraisal Committee, while all the Deputy Director
Generals of Division of DOI and the head of the Directorate of Agricultural Extension (DAE) compose
the Committee as members. The DAE is a program directorate of DOA and in charge of the agricultural
extension. The Project Director and Project Leaders also attend the meetings of the Project Appraisal
Committee. The appraisal meeting of the Committee is held usually twice a year, prior to the meeting of
the Project Steering Committee, in order to confirm progress, outputs and problems of the project, and to
examine challenges and possible countermeasures based on such a confirmation.
In order to implement the agricultural component, a Project Implementation Unit is established inside
DAE at the central level as PIU/DAE, and the Regional Agricultural Directorates (RADs) and the District
Agricultural Development Offices (DADOs) of the project are also involved in the implementation at
their respective levels. With the purpose of the coordination between DOI and DOA/DAE at the central,
between IMD and RAD, or between RID and RAD at the regional level and between FIMD and DADO,
or between IDD/IDSD and DADO at the district level, a coordination committee (CC) is set up at the
respective levels. The coordination meeting is usually held on a quarterly basis, with the participation of
representatives from the District Development Committees (DDCs) so as to share the information. In case
Data Collection Survey
2-27 JICA
where two districts are involved in the irrigation project or system such as JMIS (e.g. Bagmati Irrigation
System), the CC should be established in each district.
Figure 2-7-1 Organization Chart of MOAD Source: MOAD
Honorable Minister
State Minister
Secretary
Administration Division
Monitoring & Evaluation Division
Food Security, Agribusiness Promotion &
Environment Division
Planning Division
Policy & International Cooperation Coordination
Division
Agriculture Information and Communication Center (AICC)
Seed Quality Control Center (SQCC)
National Agriculture Research and Development Fund (NARDF)
Department of Agriculture (DOA)
Department of Food Technology and Quality Control (DFTQC)
Janakpur Agriculture Development Project
(JADP)
Agriculture Service Centers
District Agriculture Development Offices
Regional Labs Program
Directorates Regional
Directorates
Board Nepal Tea Coffee Development Board (NTCDB)
Council Nepal Agriculture Research Council (NARC)
Committees
1. Kalimati Fruit and Vegetable Market Development Committee (KFVMDC)
2. Cotton Development Committee (CDC)
3. Chandradangi Seeds and Milk Production Development Committee (CSMPDC)
4. Nepal Sugarcane and Sugar Development
Companies/Industries
1. Agriculture Inputs Company (AIC)
2. National Seeds Company (NSC)
Direct Control/command Coordination/ Facilitation
Irrigation Scheme in Terai
DOI, MOI 2-28
CPMO = Central Project Management Office PIU = Project Implementation Unit MOI = Ministry of Irrigation MOAD = Ministry of Agricultural Development DOI = Department of Irrigation IMD-= Irrigation Management Division DOA = Department of Agriculture DAE = Directorate of Agricultural Extension
RID = Regional Irrigation Directorate IMDe = Irrigation Management Directorate RAD = Regional Agricultural Directorate IDD/IDSD = Irrigation Development Division/Sub-division FIMD = Field Irrigation Management Division DADO = District Agricultural Development Office CC = Coordination Committee
Figure 2-7-2 Possible Implementation Structure for an Irrigation Project to be Implemented in Collaboration with MOAD
Source: Drawn by the Survey team based on the cases of other projects supported by WB and ADB
Agriculture Component
DOI (IMD) CPMO
DOA (DAE)
PIU
FIMDs DADOs (20)
MOA
FMISs JMISs
WUAs
IIDDOs
/IDSDOs (20)
Project Steering Committee
(PSC)
Project Appraisal Committee
(PAC)
RADs
Doner
Organization
IMDeRIDs
CC
CC
CC
Central Level Regional Level District Level
Local Offices in Terai, which manage large-Scale Irrigation Systems.
Data Collection Survey
2-29 JICA
2-7-2 District Development Committee and Village Development Committee
It is known that the District Development Committees (DDCs) and the Village Development Committees
(VDCs) are taking part in the irrigation development. These local government institutions are established in
each District and Village under the Ministry of Federal Affairs and Local Development. They are supposed
to have updated information on the irrigation development projects and their progress.
It is possible for WUAs to request financial assistance to DDCs or VDCs: however, in a hearing survey
conducted on the matter, the respondents admitted that there had been few cases that the local government
had provided assistance in response to such requests. In wake of special cases, such as natural disasters,
DDCs and VDCs may provide emergency support. Based on this background, WUAs usually request for
both technical and financial supports to IDDs, IDSDs or FIMDs. Nevertheless, the information on those
projects to be implemented in response to the requests from WUAs shall be shared with DDCs and VDCs
through the implementation periods.
Data Collection Survey
3-1 JICA
Chapter 3 Current State of Irrigation in Terai region
3-1 Overview of Terai region
3-1-1 Climate and Geology
The Terai region spreads in the southern part of Nepal covering from the west boarder to the east boarder
and lies in north of the Gangetic Plain of India. It has 17% of the total land area of the country, including the
area with the lowest elevate in the country: 70 meters above sea level. It enjoys the abundant amount of the
sun light and rain fall of the sub-tropical climate with fertile soil, and there are a large number of irrigation
systems with surface and ground water. The majority of the food crops for national consumption are
produced in this region.
Figure 3-1-1 20 Districts of Terai region (highlighted with light blue)
Source: Drawn by the Survey team based on the Research Gate Website
(https://www.researchgate.net/figure/227417012_fig1_Fig-1-Political-map-of-Nepal-showing-study-district-and-other-districts-by-ecological
[Accessed on 15/08/2016])
Terraced paddy field is one of the typical scenery of Nepal, however, it has become more and more difficult
to maintain those fields, due to decreased labor force and reduced collaborative agriculture works in the
hilly area of Nepal. The area has recently experienced a rapid population decrease due to a drastic increase
of emigrants from rural areas to urban areas or foreign countries. This tendency has caused an increase in
the abandoned farmland area, a decrease in the soil productivity and an increase in the frequency of soil
erosion and landslide in Hill and Mountain regions of Nepal. In addition, long-lasted conflicts, in
conjunction with a widening gap between the rich and the poor, made people tired and lose their identity of
community.
The tendency of an increase of emigration is also seen in Terai region. More people have abandoned
agriculture to work for manufacturing in near-by factories or to work in other countries, although the degree
of depopulation is not significant. Unlike those terraced paddy fields whose water retention function has
Irrigation Scheme in Terai
DOI, MOI 3-2
reduced, paddy fields in the plain area tend to have little damage caused by soil erosion. This implies that
Terai region has demonstrated its potential for the further development of irrigated agriculture, since the
region meets the required geographical conditions; however, sediments brought by river stream from
upstream should be removed incessantly.
As seen earlier, there are 20 Districts within Terai region, and each District is composed of villages and
municipalities, which are the minimum administrative unit of Nepal. The VDCs are supposed to have
general information on the irrigation facilities which exist within their village, and the DDCs are
supposed to have such information at the district level.
Table 3-1-1 Districts in Terai region No. District Population
(National Population
and Housing Census 2011)
No. of the
VDCs
No. of the Municipalities
Administrative Zone
Development Region
State
1 Kanchanpur 451,248 4 8 Mahakali Far-Western State 7 2 Kailali 775,709 28 8 Seti 3 Bardiya 426,576 18 5 Bheri Mid-Western State 5 4 Banke 491,313 33 25 Dang 552,583 31 4 Rapti 6 Kapilbastu 571,936 53 6 Lumbini Western 7 Rupandehi 880,196 48 68 Nawalparasi18 643,508 56 79 Chitwan 579,984 8 8 Narayani Central State 3 10 Parsa 601,017 66 2 State 2 11 Bara 687,708 68 612 Rautahat 686,722 84 313 Sarlahi 769,729 84 5 Janakpur 14 Mahottari 627,580 66 315 Dhanusha 754,777 71 616 Siraha 637,328 63 6 Sagarmatha Eastern 17 Saptari 639,284 91 518 Sunsari 763,487 39 5 Kosi State 1 19 Morang 965,370 50 820 Jhapa 812,650 33 8TOTAL 13,318,705 994 111 9 (out of 14) 5 (out of 5) 5 (out of 7)
Note; VDC stands for the Village Development Committee.
Sources: Local Governance and Community Development Programme – II, Ministry of Federal Affairs and Local Government
(http://lgcdp.gov.np/GIS_national [Accessed on 16/08/2016]), and Wikipedia
(https://ja.wikipedia.org/wiki/%E3%83%8D%E3%83%91%E3%83%BC%E3%83%AB%E3%81%AE%E8%A1%8C%E6%94%BF%E5%8C%
BA%E7%94%BB [Accessed on 15/08/2016])
DOI manages the medium and small scale irrigation systems by district and development region, and it
could not be confirmed through this Survey if DOI also manages the systems by administrative zone. DOI
remains functioning with their local offices at the district and development region levels, and any near
future restructuring of the Department has not yet been confirmed in accordance with the creation of
provinces in 2015. It should be noted that there is the possibility of restructuring of irrigation works by
province at some point. The following table illustrates the administrative system in Terai region. There are
18 As results of the establishment of 7 States by the new Constitution, Nawalparasi District is spread over both the States 4 and 5.
Data Collection Survey
3-3 JICA
25 irrigation systems at a large scale, which are called Main Irrigation Systems and are JMISs between
DOI and the WUAs, in Terai region. Out of these 25, 24 systems are managed by the 13 FIMDs, while the
remaining 1 is managed by IDD of Rupandehi District of Western Development Region.
3-1-2 Socio-economic Development
The “Nepal Human Development Report 2014” published by the NDP together with the United Nations
Development Programme (UNDP) Nepal Office reveals gaps in the Human Development Index Value
between Regions and Districts within the country as of 2011. The value of Terai region cannot be compete
with that of the national capital, Kathmandu, or that of the western Hill region, but still it remains almost as
same as the national average value: 0.490. However, looking at more closely the value per district, there are
gaps among Districts in Terai region. Chitwan District marked the highest value, 0.551, while Rautahat
District marked the lowest value, 0.386 (see Figure 3-1-2). Likely, regarding the Human Poverty Index
Value of 2011, there are significant gaps among Districts in Terai region. Chitwan District marked the
lowest value, 24.8, while Rautahat District marked the highest value, 46.4 (see Figure 3-1-3). As seen in
Section 2-1-4 of Food Balance, Chitwan District of Central Development Region is one of the districts
which have not met the self-sufficiency of food, reasons for which are considered as a rapid urbanization
and population growth.
The degree of social bond or solidarity within administrative units or villages in Terai region is not strong,
compared to that in Hill region. It is believed that this can be attributed to the background of the society of
the region. People in Terai region originally came from different places after measures against Malaria
mosquitos were taken by GON in the 1950s. On the other hand, the people in Terai region have formed
communities based on the year of immigration, ethnicity or caste, and they have a strong identity of such
social communities (Subedi, Das and Messerschmidt. “Tree and Land Tenure in the Eastern Terai, Nepal”).
Although the caste system was officially abolished by the 1963 Constitution, the system is still subtly alive
within the social structure of Nepal, significant gaps in the living standard remain between higher and
lower castes. The opportunities for women and lower castes in education and jobs are still limited, and they
are not granted equal access to public service delivery, compared to others.
Table 3-1-2 is a summary of the population and road network in Terai region as of 2011/2012. In the last
rows of the table, the proportion of value of Terai region to that of the entire country is shown. 50% of the
national population lives in Terai region, and the population density of the region is twice as high as the
national average. This indicates that the total production of this region, including the agriculture
production, is enough to sustain such a large population. In addition, the road density of Terai region
(km/100km2) is one point five times as high as the national average. This can be attributed to lower costs
required for the construction compared to those in Hill and Mountain regions, high population density,
and the strategic importance of the region for transit to India.
In order to look at the situation inside of Terai region, all the districts in the region are listed in Table
3-1-2 below in the geographical order from west to east. The population density of the districts in Eastern
and Central Development Regions, except Chitwan District, is higher (ranging from 445 persons/km2 to
652 persons/km2) than that of the districts in Far-Western, Mid-Western and Western Development
Regions, except Rupandehi District (ranging from 189 persons/km2 to 328 persons/km2). The road density
shows a similar tendency, namely, the density in Eastern and Central Development Regions is higher than
Irrigation Scheme in Terai
DOI, MOI 3-4
that in Far-Western, Mid-Western and Western Development Regions. These facts indicate that the eastern
part of Terai region is more developed than the western part.
Figure 3-1-2 Human Development Index Values across District, 2011 Source: National Planning Commission & UNDP Nepal. 2014
Figure 3-1-3 Human Poverty Index Value across Districts, 2011 Source: National Planning Commission & UNDP Nepal. 2014
Data Collection Survey
3-5 JICA
Table 3-1-2 Population Density and Road Density in Terai region No.
District Population (National Population and
Housing Census 2011)
Land Area (km2)
Population Density
(persons/ km2)
Road Length
(km)
Population per 1km of
road
Road Density
(km/ 100km2)
1 Kanchanpur 444,315 1,610 275.97 155 2,859 9.652 Kailali 770,279 3,235 238.11 310 2,488 9.573 Bardiya 426,946 2,025 210.84 211 2,019 10.444 Banke 493,017 2,337 210.96 226 2,178 9.695 Dang 557,852 2,955 188.78 366 1,523 12.396 Kapilbastu 570,612 1,738 328.32 223 2,559 12.837 Rupandehi 886,706 1,360 651.99 164 5,417 12.048 Nawalparasi 635,793 2,162 294.08 204 3,119 9.439 Chitwan 566,661 2,218 255.48 233 2,429 10.5210 Parsa 601,701 1,353 444.72 53 11,392 3.9011 Bara 701,037 1,190 589.11 167 4,189 14.0612 Rautahat 696,221 1,126 618.31 88 7,927 7.8013 Sarlahi 768,649 1,259 610.52 181 4,237 14.4114 Mahottari 646,405 1,002 645.11 185 3,489 18.4915 Dhanusha 768,404 1,180 651.19 195 3,938 16.5416 Siraha 643,136 1,188 541.36 145 4,438 12.2017 Saptari 646,250 1,363 474.14 247 2,622 18.0918 Sunsari 751,125 1,257 597.55 191 3,932 15.2019 Morang 964,709 1,855 520.06 216 4,462 11.6620 Jhapa 810,636 1,606 504.75 197 4,123 12.24Total or Average of Terai region (A) 13,350,454 34,019 392.44 3,958 3,373 11.63
Total or Average of Nepal (B) 26,494,504 147,181 180.01 11,636 2,277 7.91
(A) / (B) 50% 23% 218% 34% 148% 147%Source: Department of Roads. Road Network Data (2011/2012)
3-1-3 Land Ownership
The problems around the land ownership in Terai region stem from the malfunction of clear rules around
the issue, including the land registration system.
It is said that the land was traditionally distributed among the neighbors through discussion and verbal
agreements, and even today, not many Nepali people are aware of the land registration system. There is a
study which states that a half of the land owners in Nepal do not legally have the property right (Wily. L.A.
2008. "Land Reform in Nepal: Where is it Coming From and Where is it Going?” p.72), and there have
been cases where the claimed landowners could not submit any official document which proves their
property right on the land inherited from generation to generation, when they are involved in land conflicts.
Land conflicts can be caused when the owners of neighboring plots have different understandings of the
plot border, or when one of them intentionally tries to expand his/her plots beyond the plot border. In
addition, the case where an owner bribed the surveyor to manipulate the measurements, the case where a
person registered unregistered plots of somebody else in his/her name, and the case that a former owner of
the land did not take the necessary procedure to change the ownerships after selling his/her land, and finally
Irrigation Scheme in Terai
DOI, MOI 3-6
he/she pushed out the new owner from the land have been also reported19. Moreover, there were cases
where those people who do not have land but have been contracted by owners for actual cultivation on the
ground, start to claim the ownership of the entire or part of the land as remuneration for their long-time
works.
In Nepal, the farmland reform took place in the 1950s, and the Land Act, which is the principal legislation
for the reform, was enacted in 1964. The concerned act has been amended several times since then, and the
fifth amendment was given to the act in 2002. The act with the fifth amendments is still valid today,
although it has not been fully complied for various reasons20, including the amendment to reduce
drastically the ceiling of the agriculture land area (See Table 3-1-3).
Table 3-1-3 Differences in the ceilings of the land area to be possessed before and after the fifth amendments
to the Land Act Region Before the fifth amendment (ha) After the fifth amendment (ha)
Farmland Residence Total Farmland Residence Total Terai 16.40 2.00 18.40 6.77 0.68 7.45 Kathmandu Valley 2.70 0.40 3.10 1.27 0.25 1.52 Others 4.10 0.80 4.90 3.56 0.25 3.81
Source: Saito; Saito and Paudel. 2015
The Nepal Living Standards Survey 2010/2011 revealed the situation of the land ownership and utilization
as follows. Table 3-1-4 illustrates the land ownership and utilization by all the population of each region.
As the left column of the table, “Proportion to all the land utilized”, indicates, 24.9% of the total land
utilized by the population in Terai region is rented-in land. Meanwhile, the right hand of the same table
explains the situation of the land which is rented out to others. As average in Terai region, 6.8% of the
total land is rented out. The renting in and out of land is more actively undertaken in urban area than rural
area in this region.
Table 3-1-4 Land Ownership and Utilization in Terai region
Percentage to total operated land (%)
Percentage to total owned land (%)
Owned and operated land
Rented-in land
Total Owned and operated land
Rented-in land
Total
Nepal 81.60 18.40 100.00 94.30 5.70 100.00 Mountain region 87.80 12.20 100.00 94.90 5.10 100.00 Hill region 86.20 13.80 100.00 95.00 5.00 100.00 Terai region
Total 75.10 24.90 100.00 93.20 6.80 100.00 Urban Area 68.20 31.80 100.00 85.20 14.80 100.00 Rural Area
Eastern Development Region
71.20 28.80 100.00 95.20 4.80 100.00
Central Development Region
75.40 24.60 100.00 95.80 4.20 100.00
Western Development Region
80.60 19.40 100.00 95.10 4.90 100.00
Mid & Far Western Development Region
80.50 19.50 100.00 88.40 11.60 100.00
Source: Central Bureau of Statistics. National Living Standard Survey 2010/2011
19 The Asia Foundation. 2014. LAND DISPUTES AND SETTLEMENT MECHANISMS IN NEPAL’S TERAI, JSRP Paper 20 Saito et al. 2015. A Simulation Analysis on Land Reform in Nepal
Data Collection Survey
3-7 JICA
Unlike the previous table, the following table 3-1-5 illustrates the land ownership and utilization by only
farmers. The proportion of farmers whose farming land is all rented-in, in other words, the proportion of
farmers without land in Terai region is 9.1%, which is relatively higher than that in other regions, since the
proportion of national average is 5.4%, that in Mountain region is 1.5%, and that in Hill region is 2.7%.
Within Terai region, the proportion of the farmers without land in Eastern and Central Development
Regions is 9.1% and 11%, respectively. These proportions are higher than those in Western (3.2%), Mid-
and Far-Western (3.7%) Development Regions. There are more population in Eastern and Central
Development Regions, and therefore, the number of farmers without land is arguably also large in these
development regions.
Based on the situation of land ownership in Terai region mentioned above, those points to be considered
to bring forward the cooperation in the irrigation sector in Terai region are put together in “6-6
Considerations for Future Surveys and Implementation of the JICA-TCP”.
Table 3-1-5 Land Ownership, Renting-in and Renting-out of Farmers in Terai region Percentage of
households with owned agriculture
land (%)
Percentage of
households renting-out
land (%)
Percentage of
households renting-in land (%)
Percentage of
households renting-in
land only (%)Nepal 94.60 10.20 31.60 5.40Mountain region 98.50 10.60 28.10 1.50Hill region 97.30 9.70 28.00 2.70Terai region
Total 90.90 10.60 36.20 9.10Urban Area 80.50 17.50 38.60 19.50Rural Area
Eastern Development Region 90.90 8.80 41.10 9.10Central Development Region 89.00 8.10 35.90 11.00Western Development Region 96.80 8.30 31.80 3.20Mid & Far Western Development Region
96.30 15.90 31.20 3.70
Source: Central Bureau of Statistics. National Living Standard Survey 2010/2011
In the existing irrigation system, there have been reported disputes on the water distribution. Most of the
canals are equipped with several intake and drainage points, and this allows those farmers in upper streams
to induce more volume of water than they are supposed to do. Disputes may occur when an inequity of
water distribution is seen (Stein. D and Suykens. B. 2014. “Land Disputes and Settlement Mechanisms in
Nepal’s Terai”).
3-1-4 Ethnic issues
There are different ethnic and social groups in Terai region which are dedicated in agriculture. One of
such groups is Madhesi people, for instance, and irrigation systems are important common assets for them.
Madhesi established hundreds kilometers of canals in today’s Jhapa and Morang Districts hundreds of
years ago. Every year, Madhesi people live in areas between mid-west and far-east elects their village
leaders (badghar) between January and February (One vote per household). Badghar has the authority to
order village residents to repair canals within the village. For a canal runs through several villages,
badghars of the concerned villages select a Chaundhary who is responsible for O&M of such a canal.
Irrigation Scheme in Terai
DOI, MOI 3-8
Chaundhary can give an instruction to badghar to send villagers for the construction and/or rehabilitation
of such a canal. The equity among the villages is an important factor for the distribution of water from
such a canal21.
The promulgation of the new Constitution in 2015 has brought about a new social, economic and political
tension in the country especially in Terai region. There has been seen protest activities over the country
around the Constitution promulgated in September 2015. In Southern Nepal, the protest groups organized
general strikes called bandas. Vehicles of those people who did not participate in the strikes, office
buildings of the government agencies and facilities belonging to the police were attacked by the protest
groups, and frequent conflicts between the protest groups and the security units have left more than fifty
casualties from both sides.
This situation adds one more reason for DOI to develop guidelines for the Gender Equality and Social
Inclusion (GESI) in order to promote the GESI in irrigation policies and projects. In line with this, DOI is
making efforts to enhance the participation of different ethnic and social groups of Terai region in the
irrigation related projects and activities.
3-2 Outline of Irrigation Systems
3-2-1 Definition of the Scale of Irrigation Systems
The acreage for small, medium, large and major scales of irrigation system are different between Hill and
Terai region, because of topography. The table below shows the definition of scales of irrigation system in
these two regions.
Table 3-2-1 Definition of Irrigation System Scale Scale Hill Area Terai region
Major > 1,000ha > 5,000ha Large 500 to 1,000ha 2,000 to 5,000ha Medium 25 to 500ha 200 to 2000ha Small < 25ha < 200ha Source: Irrigation Policy 2013
The different scales of irrigation systems in Terai region can be classified into the following four
categories: small (less than 200 ha), middle (from 200 to less than 2,000 ha)22, large (from 2,000 to less
than 5,000 ha), and major (more than 5,000 ha). Based on this categorization, DOI divides the irrigation
systems into two categories for their own management purpose: the small and medium scale irrigation
systems and the large and major scale irrigation systems.
3-2-2 Definition of Canals
The main and lower level canals are defined by stream order. Meanwhile, those secondary and lower level
canals are classified by their irrigable areas. The table below summarizes the definitions of irrigation canals
in Nepal. For example, a canal which can irrigate an area ranging from 30 to 100 ha is classified as tertiary
canal, even if it is directly offtaking from the main canal.
21 Cederroth, Sven (1995), 'Managing the Irrigation: Tharu Farmers and the Image of Common Good', Nordic Institute of Asian Studies, Denmark. 22 This definition is different from the definition by ADS of the governmental middle-scale irrigation systems. According to ADS, the irrigated
area of the governmental middle-scale irrigation systems ranges from 5,000 to 10,0000ha.
Data Collection Survey
3-9 JICA
Table 3-2-2 Definitions of Canal Terms utilized in
this report Terms Definition
Main Canal Main Canal The canal off taking directly from the intake or headwork Secondary Canals Branch or Secondary
Canal The canal off taking from the main canal.
Distributaries or Sub-Secondary Canals
The canal offtaking from main and other canals, , which irrigates the area from 100 to 500 hectares
Tertiary Canals Minor or Tertiary Canals The canal off taking from main or secondary canals, which irrigates the area from 30 to 100 hectares.
On-farm Canals Watercourses The canal off taking from main, secondary or tertiary canals, which irrigates the area from 4 to 30 hectares.
Field Channels The canal off taking from main, secondary or tertiary canals, which irrigates the area up to 4 hectares.
Source: Irrigation Policy 2013
3-2-3 Management Type of Irrigation Systems
These small and medium scale irrigation systems in Terai region, whose irrigated area is less than 2,000 ha,
are originally traditional FMISs. They had been developed, operated and managed by the beneficiary
farmers for years. For such FMISs to have government supports for the rehabilitation or upgrade of
facilities, water user groups (WUGs) of those FMISs, which are composed of beneficiaries, are required to
organize WUAs with the registration to IDD or another irrigation office in charge, prior to the submission
of the application for government supports.
With the registration to the government agencies, the traditional WUGs are turned into the FMIS WUAs
registered to the government, and they become eligible for the government support.
Such WUAs tend to have few problems and challenges in the collective management of irrigation
facilities. They are organized on the basis of small scale community-based traditional groups for the
irrigation, and they can develop their regulations based on the existing traditional organizational structure
and regulations, although they can also refer to the organizational structure and regulations developed by
the government, with the guidance of Association Organizer. Moreover, their members’ experience in the
management of the irrigation systems and the group of users will help the WUAs to manage their
organizations.
The government intervention to FMISs is mainly on the organization and the registration of WUAs besides
on the rehabilitation of facilities. The traditional organization structure and regulations applied on the
ground are respected in the process of the registration to convert their irrigation system into an FMIS
registered to the government. When the construction work is completed, and the training in O&M of the
system and agriculture is implemented, the management of the irrigation system is transferred back to the
concerned WUA of FMIS. After the transfer of management, the government provides a minimum
intervention for O&M. The office of IDD/IDSD is normally situated far away from the WUAs, and this
geographical distance likely contributes to less support from IDD/IDSD to the WUAs after the transfer
and the initial training. Since such a FMIS is originally a property of beneficiary farmers, it cannot be the
target of IMT, even if the government manages the system temporarily during the construction period.
For the medium scale irrigation systems among FMISs, GON through DOI has been implementing the
Irrigation Scheme in Terai
DOI, MOI 3-10
Medium Irrigation Project (MIP) with its own budget since 2004/05. The targets of this project are the
medium scale irrigation systems over the country and its objectives are expansion of the irrigated area and
improvement on the agricultural productivity. According to DOI, MIP has already completed works by
August 2016 for 36,711 ha of the 288 irrigation systems, and is currently working for 95,433 ha of the
679 irrigation systems. DOI has the intension to continue the current support to the medium scale FMISs
for the time being. The targets of those projects supported by donors, CMIASP-AF and IWRMP-AF are
also medium scale FMISs (refer to 3-4-2 The Contents and Challenges of the On-going Projects).
In Terai region, there are a large number of FMISs registered to the government and the traditional FMISs
which have never received the government support as well. According to the GWID, there are numerous
groundwater irrigation systems in Terai region. IDD or IDSD of each district does not have the
information on the actual number of FMISs within the jurisdiction. Consequently, DOI neither has the data
of the actual number and name of FMISs.
On the other hand, there are large or major scale irrigation systems which are developed by DOI. They are
called “Main Systems” and there are a total of 25 Main Systems in Terai region. Out of the 25 systems, 24
systems are directly administrated by IMD. These Main Systems are classified into 3 types by the water
management conditions in the area prior to the establishment of Main System: Type 1) Systems which
were established by GON to benefit rain-fed farming plots. Type 2) Systems which were established by
GON to integrate several small-scale FMISs into one large-scale Main System, and Type 3) Systems
which were established by GON to integrate the rain-fed farming plots and neighboring FMISs under a
large-scale Main System.
They are JMISs, which are managed jointly by DOI (13 FIMDs and 1 IDD) and the WUAs. The number of
the WUA members of JMIS may be over 1,000, and if it is the case, to manage such a big group, there
should be put in place a systematic organizational structure and clear regulations on which the members
can agree. Accordingly, the WUAs of JMIS are required higher organizational management capacity than
those WUAs of FMIS. The operation of Main Systems requires experiences as well as engineering
knowledge. Moreover, due to the scale of Main Systems, the total canal length tends to be long, and
WUA’s burden for O&M is heavy in both the terms of work load and costs.
The columns of canal and maintenance of the following table show the distribution of roles on
maintenance between GON and WUA, although details of such a distribution are determined by a written
agreement as result of negotiation (Irrigation Regulation 2000, Irrigation Policy 2013). Depending on the
specific conditions of each system, such as the scale, the status quo of facilities, and the WUA’s current
level of capacity, the actual distribution of roles between GON and WUA can be adjusted. In JMISs, the
problems of a delay and/or a lack in the development of the major irrigation facilities are often
experienced. In order to make a required amount of water reach to tertiary and lower level canals, there
are cases where WUAs take necessary measures including those tasks which are not original the WUAs’
tasks such as the cleaning of the main canals. Even when the major irrigation facilities are well developed,
there are cases where the management of the entire irrigation system does not work fully and the water is
not distributed in an equitable manner. Appropriate technical assistance to address such managerial
problems is required.
Data Collection Survey
3-11 JICA
Table 3-2-3 Distribution of roles in JMIS Canal Construction Maintenance
Main Canals DOI DOI (IMD) Secondary Canals DOI DOI (IMD) in the participation of WUA
Tertiary Canals DOI or WUA (construction by outsourced contractors or by WUA members) WUA
On-farm canals Note: The Irrigation Regulation 2000 and the Irrigation Policy 2013 describe the distribution of roles in the maintenance works, but not that in the construction.
Source: Irrigation Policy 2013 and DOI especially for the distribution of roles in the construction
The management of the large and major scale irrigation systems mentioned above is transferred from DOI
to the WUAs of JMIS, which are organized with support from the FIMD. DOI provides the WUAs with
the training in the organizational development, O&M, etc. The FIMD office is normally situated near
from the WUAs and the FIMD and the WUAs can maintain a good level of mutual communication.
Because of such a geographical proximity, the WUAs seem to have a better access to the government
agencies to seek supports from them. FIMD provides the WUAs with technical assistance to develop the
irrigation schedule and to increase the knowledge required for the irrigation management such as
Evapotranspiration (ET) and irrigation efficiency, among others. However, the decision-making power is
always left to the WUAs.
The following table is a summary of the comparison of features between FMISs and JMISs.
Table 3-2-4 Comparison of Features between FMISs and JMISs Items FMISs JMISs partly handed over
by IMT Project Legislative Background (Law, Regulations)
Muluki Ain 1963 Water Resources Act 1992 Water Resource Regulation 1993 Irrigation Policy 2013
Water Resources Act 1992 Water Resource Regulations 1993 Irrigation Policy 2013
Strategic Background (Strategy, Plan)
Water Resource Strategy 2002 National Water Plan 2005 ADS 2015 - 2035
Water Resource Strategy 2002 National Water Plan 2005 ADS 2015 - 2035
Supervisory Office Irrigation Development Division (IDD) Irrigation Development Sub-division (IDSD)
Irrigation Management Division Project Office (IMDPO)
Number of Irrigation Systems in Terai (surface water and groundwater systems)
3,500 – 7,000 ha (a total irrigated area is estimated as approximately 709,831 ha) #1
25 systems (total command area is 330,143 ha)
Command area in Terai region
Small systems (less than 200 ha) Medium systems (200 – 2,000 ha)
Large systems (2,000ha – 5,000ha) Major systems (more than 5,000ha)
Financial sources for the development / rehabilitation
Multi and bilateral donors Own funds of GON
Multi and bilateral donors Own funds of GON
Irrigation Scheme in Terai
DOI, MOI 3-12
Items FMISs JMISs partly handed over by IMT Project
O&M Implementation institutions / agencies
WUAs
Headworks & main canals: DOI Secondary canals: DOI with
participation of WUAs Tertiary canals & Distribution
Networks: WUAs Policy: the regular management
responsibility of large systems is gradually transferred from IMDPOs to WUAs.
Implementation institutions / agencies for the development and rehabilitations
Water users in principle Water users with the support from the
IDD/IDSD staff, in case that water users cannot technically and financially bear with burdens.
Portions for DOI: DOI Portions for WUAs:
Water users in principle Water users with the support
from the IMDPO staff, in case that water users cannot technically and financially bear with burdens.
Issues for further development / rehabilitations
Increased irrigation efficiency (ADS#2) Improvement on headwork, main canal
and distribution networks (ADS) Improvement on water management
(ADS) Capacity development of WUAs (ADS)
Promotion of IMT (Irrigation Policy 2013, ADS) Capacity development of IMD (ADS) Capacity development of WUAs
(ADS) Improvement on water management
(ADS) Rehabilitation / Improvement of
facilities (ADS) Technical assistance needed in order to optimize water use for reliable year-round irrigation (2016.8.14 workshop results)
Newly installation of tube-well as water source.
Maintenance of existing DTWs & STWs Maintenance (dredging) of the existing
reservoirs as water source. Enhancement of improvement on ISF
collection mechanism, including periodical auditing system.
Establishment/update of asset management of irrigation facilities.
Construction and/or improvement of on-farm irrigation system
Introduction of new technology to increase irrigation efficiency
Construction/maintenance of water-regulating structures
Establishment/improvement of drainage systems for the medium/large scale projects in plain area.
Enhancement of construction of on-farm irrigation and drainage system
Newly installation of tube-well as water source.
Maintenance of existing DTWs & STWs
Maintenance (dredging) of the existing reservoirs as water source.
Enhancement of improvement on ISF collection mechanism, including periodical auditing system.
Establishment/update of asset management of irrigation facilities.
Construction and/or improvement of on-farm irrigation system
Introduction of new technology to increase irrigation efficiency
Construction/maintenance of water-regulating structures
Establishment/improvement of drainage systems for the medium/large scale projects in plain area.
Enhancement of construction of on-farm irrigation and drainage system
Data Collection Survey
3-13 JICA
Items FMISs JMISs partly handed over by IMT Project
Relative importance on the above technical assistance weighted by participants of the workshop held in the DOI central office
30% 70%
#1 Irrigated area in Terai region (2011/12) = 953,740ha Command area of the 25 Main Systems in Terai region = 330,143ha Irrigated area (estimation) by FMISs in Terai region = 953,740 – 330,143 = 623,597ha With the assumption of: the average size of FMIS command area = 100ha, No. of FMISs = 6,235 With the assumption of: the average size of FMIS command area = 200ha, No. of FMISs = 3,118 #2 ADS
Source: Survey team
3-2-4 The Process of Facility Improvement and Farmer’s Participation
(1) FMIS
The farmers (WUG/WUA members) participate in the irrigation infrastructure rehabilitation/upgrading
from the beginning. First of all, farmers have to make contact with IDD and to apply for improvement of
facilities by submitting the filled “Demand Form” and depositing the amount of 50Rs./ha in accordance
with the size of the command area. The process from the survey to designing is carried out by DOI staff
discussing with the applicant WUG/WUA members, by utilizing the opportunities such as monthly
meetings with the WUG/WUAs. It takes 2 to 3 months to go through this process. The following flow
chart shows the process of infrastructure rehabilitation / upgrading of a FMIS. It involves the screening and
examination at the IDD, the Regional Directorate and the DOI central office, respectively. It takes 2 to 3
years until the budget is allocated to the applied works, after the final approval by the DOI central office is
given on the application.
(2) JMIS
The WUA’s main executive committee submits the filled-up “Demand Form” to the FIMD office in charge.
The FIMD staff and the concerned WUA members discuss the contents of government support, its priority,
etc. to reach an agreement. Since the irrigation system was developed by GON, a feasibility study is not
required for the rehabilitation / upgrading of the system, but the cost estimation is essential. Once a
detailed plan of government support is developed, the FIMD makes a written proposal report and submits it
to IMD. Once it is approved and the necessary budget is allocated, the government support will be
provided.
Irrigation Scheme in Terai
DOI, MOI 3-14
Figure 3-2-1 Flow Chart of Rehabilitation Process Source: Survey team
8. The proposal report is sent to the DOI central office and screened.
If it passes the screening
If it passes the screening and it is approved.
1. Water Users Group (WUG) submits the Demand Form to IDD in charge.
2. WUG deposits the amount of money of 50Rs./ha multiplied by the command area to the above IDD.
3. The above IDD screens demands (applications) from WUGs based on the Demand Forms submitted.
4. DOI engineers visit the site and conduct the identification survey (location, water source, topography, etc.) and screen demands (application) from WUGs.
5. Feasibility (land survey, planning, designing, cost estimation) is conducted by IDD. IDD implements this process consulting with WUG, and usually it takes a few months.
If it passes the screening
If it passes the screening
6. IDD submits the proposal report, which contains the demand form and its feasibility results to the Regional Irrigation Directorates (RID).
7. RID screens WUGs’ demands based on the proposal reports submitted by IDDs under the directorate.
If it is concluded feasible
9. Tendering for construction is held (2 -3 years later after the approval).
11. WUA deposits the money of 0.5% of the contract amount to IDD.
12. WUA bears 3 to 15 % of the contract amount and contributes by cash or in kind. A written agreement is made between IDD and WUA.
13. When construction is completed, the money deposited at the above 2 and 11 is refunded to WUA.
10. Association Organizer (AO) of IDD organizes WUG to Water Users’ Association (WUA).
Data Collection Survey
3-15 JICA
Table 3-2-2 Comparison of the FMIS and the JMIS Item FMIS JMIS
WUA Water users organize the WUAs at each level of the main, secondary and tertiary canals. In this regard, there is only the main committee established for a small scale system. The structure of the committees varies from the system to system.
The WUA is registered to IDD or IDSD. A constitution is made by the WUA with
support from IDD or IDSD. It can be made based on traditional rules.
The committee members are selected by methods stipulated by the constitution, which is usually an election.
The General Assembly Meeting is usually held once a year, and as needed for emergency case. It is stipulated in the constitution.
The treasurer of the main committee manages finance. The financial status is reported to the members at the General Assembly Meeting.
An audit report is submitted to IDD or IDSD annually in order to re-new the registration.
Information is distributed from the main committee to the members through verbal messages, cell phone, notice to the public, FM radio, etc.
Water users organize the WUA s at each level of the main, secondary and tertiary canals. The number and the structure of WUAs vary from the system to system. For those canals at a lower level than the tertiary canal and for the canals at the field level, water users organize Water Users Groups (WUGs).
The WUA main committees are registered to FIMD. The WUAs at the secondary canal level are registered to the WUA main committees. The WUAs at the tertiary canal level are registered to the WUAs at the secondary canal level.
A constitution is made by the WUA with support from FIMD. It is usually made based on traditional rules.
The committee members are selected as stipulated in the constitution. They are usually selected by election.
The General Assembly Meeting is usually held once a year, and as needed for emergency case. The General and Special Assembly Meetings are stipulated in the constitution. In case that there are too many WUA members to meet at the same time, the representative system can be adopted.
The treasurer of the main committee of the WUA manages finance. The financial status is reported at the General Assembly Meetings. And then, the participants inform all other members.
An audit report is submitted to FIMD annually in order to re-new the registration.
Information is distributed from the main committee to members through verbal messages, cell phone, notice to the public, FM radio, etc.
Participation of Farmers
Refer to “3-2-4. The Process of Facility Improvement and Farmer’s Participation (1) FMIS”
Refer to “3-2-4. The Process of Facility Improvement and Farmer’s Participation (2) JMIS”
Irrigation Scheme in Terai
DOI, MOI 3-16
Item FMIS JMIS Canal Cleaning
The WUA is responsible for the entire irrigation system.
No written records, except for expenditures.
No written plans. The canals are cleaned twice a year before the commencement of the crop seasons, at least.
The WUA can apply for technical or financial support from IDD for anything the WUA alone cannot handle.
Responsibilities of FIMD and of the WUA are stipulated in the agreement (Table 3-2-3)
FIMD’s maintenance works are planned and reported since the budget is allocated from the consolidated fund.
The WUA has no written records, except for expenditures.
No written plans. The canals are cleaned twice a year before the commencement of the crop seasons, at least. FIMD may support the WUA to plan, if requested.
The WUA can apply for technical or financial support from FIMD for anything the WUA alone cannot handle.
Repair works
The WUA is responsible for the entire irrigation system.
No written records, except for expenditures.
The WUA can apply for technical or financial support to IDD in the rehabilitation, or for anything the WUA alone cannot handle. (Refer to “3-2-4. The Process of Facility Improvement and Farmer’s Participation (1) FMIS”)
Responsibilities of FIMD and of the WUA are stipulated in the agreement (Table 3-2-3)
The FIMD works are planned and reported since the budget is allocated from the consolidated fund.
The WUA has no written records, except for expenditures.
The WUA can apply for technical or financial support to FIMD in the rehabilitation or for anything that the WUA alone cannot handle (Refer to “3-2-4. The Process of Facility Improvement and Farmer’s Participation (1) FMIS”).
Water Allocation
The WUA makes the irrigation schedule by going through the procedure written in the constitution.
The schedule needs to be informed to and approved by all the WUA members.
The WUA members can express objections to the schedule, if any.
The WUA makes the irrigation schedule with support from FIMD. All the related decisions are made by the WUA.
The schedule needs to be informed to the lower-level committees and to be approved by all the WUA members.
The WUA members can express objections to the schedule, if any.
Water Delivery
The WUA members operate the canal system and deliver water.
No record is taken, except for the pumping irrigation systems.
In accordance with the schedule, FIMD and the WUA operate the canal system in charge and deliver water.
The Flow rate is confirmed by gauges or Parshall flumes if they are furnished.
Farming Paddy is cultivated in the monsoon season. Wheat, vegetables, pulses, maize are
cultivated in the winter season. Vegetables, pulses are cultivated in the
spring season where water is available. The farmers understand the importance of
irrigation facilities. Increased benefits by improved yields
and/or marketing becomes as incentive.
Paddy is cultivated in the monsoon season. Wheat, vegetables, pulses, and maize are
cultivated in the winter season. Vegetables, pulses are cultivated in the
spring season, where water is available. Reliable water delivery down to the tail end
becomes an incentive; reliable water delivery results in an expansion of irrigated area, and increased yields.
Source: DOI, WUA
Data Collection Survey
3-17 JICA
3-3 Situation of Irrigation and Irrigated Agriculture
3-3-1 Crop Production in Terai Region
There are three crop seasons in Terai region: monsoon (summer) from July to October, winter from
December to March and spring from March to July. While rice is cultivated in monsoon, wheat is a winter
crop. The following figure is a crop calendar in Terai region.
Crop Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecRice (Main) Rice (Spring) Maize (Winter) Wheat Maize (Spring) Rapeseed and Mustard Jute Pluses and Vegetables
Figure 3-3-1 Crop Calendar in Terai Region Source:DOA
The table below shows the cultivation areas of main crops in Terai region. Maize, pluses and vegetables
are produced in the winter and spring seasons. The cultivation areas of rice in the region account for
68.3% of the national total areas, likewise, the areas of wheat, pulses and vegetable account for 57.2%,
75.3% and 55.6%, respectively. The cultivation areas of the Eastern and Central Development Regions in
Terai region are significantly larger than those of other three Development Regions. The production of the
Eastern and Central Development Regions in Terai region seems to contribute significantly to the national
total production, and to play an important role in the irrigation development. Meanwhile, the Cultivation
area of maize in Terai region accounts for only 17.4% and it is mainly produced in Hill region.
Table 3-3-1 Cultivation Area of Main Crops in Terai Region
Source: MOAD. Agricultural Statistics in 2013/2014 in Nepal
3-3-2 Crop Production in Terai Region
The production of rice and pulses, among major crops, in Terai region accounts for 80% of the national
total production of the same crops. These crops are produced more in the Eastern and Central
Development Regions. The following table shows the production share of major crops among different
Development Regions.
Region Eastern Central Western Mid western Far western Total (Terai) Nepal Percent (%)Paddy 297,363 280,744 190,850 126,730 120,246 1,015,933 1,486,951 68.3%Maize 65,150 37,162 14,770 35,000 9,140 161,222 928,761 17.4%Wheat 70,935 165,500 79,140 50,177 65,933 431,685 754,468 57.2%Pulses 49,890 72,929 27,985 66,100 30,542 247,446 328,738 75.3%
Vegetables 42,742 57,775 12,740 13,812 14,630 141,699 254,932 55.6%
Irrigation Scheme in Terai
DOI, MOI 3-18
Table 3-3-2 Crop Production in Terai Region (tons) Development Region Rice (%) Wheat (%) Pluses (%) Vegetables (%)
Eastern 1,066,353 21.1 183,900 9.8 50,240 14.3 584,880 17.1Central 1,298,442 25.7 483,241 25.7 80,834 22.9 794,695 23.2Western 761,711 15.1 245,458 13.0 32,529 9.2 208,073 6.1Mid-Western 484,567 9.6 154,367 8.2 74,877 21.2 189,281 5.5Far-Western 353,461 7.0 141,000 7.5 31,340 8.9 209,918 6.1
A total of Terai region 3,964,534 78.6 1,207,966 64.1 269,820 76.6 1,986,847 58.1A total of Nepal 5,047,047 1,883,133 352,473 3,421,035
Terai region/ Nepal (%) 78.6 64.1 76.6 58.1 Source: MOAD. Agricultural Statistics in 2013/2014 in Nepal
3-3-3 Agricultural Cooperatives
The tables below show the number of agricultural cooperative in each district. There are a number of
small scale cooperatives, and several cooperatives belong to one large scale or main irrigation system.
Members of the cooperatives are different from those of WUAs. Water users of WUAs are not necessarily
the member of the cooperatives.
Table 3-3-3 Number of Agricultural Cooperatives by District in Terai Region
Eastern Development Region (1,697 agricultural cooperatives in total)
District Jhapa Morang Sunsari Saptari Siraha Dhanusha Mahottari Agricultural
Cooperatives 317 192 197 211 236 291 253
Central Development Region (1,390 agricultural cooperatives in total)
District Sarlahi Rautahat Bara Parsa Chitwan Agricultural
Cooperatives 275 409 432 163 111
Western Development Region (516 agricultural cooperatives in total)
District Nawalparasi Rupandehi Kapilbastu Agricultural
Cooperatives 73 132 311
Mid-Western Development Region (603 agricultural cooperatives in total)
District Dang Banke Bardiya Agricultural
Cooperatives 253 188 162
Far-Western Development Region (393 agricultural cooperatives in total)
District Kailali Kanchanpur Agricultural
Cooperatives 205 188
Source: DOA
Data C
ollection Survey
3-19
JICA
Jhapa Morang Sunsari Saptari Siraha Dhanusa Mahottari Sarlahi Rautahat Bara Parsa ChitawanNo. of total holdings 120,538 126,891 86,650 89,241 88,527 96,006 80,844 98,288 79,233 81,292 59,496 n.a.Area (ha) of total holdings 102,443 109,943 75,141 73,908 78,798 72,307 64,977 80,678 64,835 56,867 48,899 n.a.No. of irrigated holdings reporting 70,518 92,912 69,063 61,062 62,404 72,564 59,177 69,597 74,042 75,103 52,012 n.a.Area (ha) of irrigated holdings reporting 54,774 83,577 68,331 46,620 52,119 52,560 47,137 61,918 59,330 52,048 42,489 n.a.River/lake/pond by gravity No. of holdings 30,072 35,628 35,094 21,679 13,393 20,474 20,730 15,084 14,460 13,443 4,559 n.a.
Area (ha) 22,470 23,320 38,227 16,144 9,777 11,274 10,225 11,773 9,871 8,751 3,446 n.a.pumping No. of holdings 2,506 6,187 2,128 9,024 6,303 24,001 8,919 13,780 9,862 10,748 16,085 n.a.
Area (ha) 1,544 5,857 1,414 4,661 3,348 14,185 4,431 12,129 4,659 4,298 9,835 n.a.Dam/reservoir No. of holdings 4,461 16,706 1,365 11,088 4,851 6,194 13,359 17,910 14,794 11,147 20,272 n.a.
Area (ha) 4,373 20,398 807 8,620 3,954 3,603 6,714 12,980 9,732 6,166 14,533 n.a.Tube well/boring No. of holdings 30,122 44,703 39,310 30,971 44,492 24,948 29,405 28,039 48,645 51,644 25,892 n.a.
Area (ha) 22,050 31,714 27,162 16,761 33,689 14,237 18,516 21,984 32,524 30,760 12,525 n.a.Others No. of holdings 4,511 2,733 402 994 2,820 8,646 2,647 1,608 1,965 4,426 1,720 n.a.
Area (ha) 2,400 1,395 104 309 701 5,272 1,323 396 364 485 1,273 n.a.Mixed No. of holdings 2,656 1,289 1,084 229 954 6,796 6,720 3,434 5,154 2,562 1,892 n.a.
Area (ha) 1,938 893 617 126 650 3,990 5,929 2,657 2,180 1,587 876 n.a.Percentage of Irrigated Land Area 53.5 76.0 90.9 63.1 66.1 72.7 72.5 76.7 91.5 91.5 86.9 76.3Poverty Head Count Ratio 10.6 16.5 12.0 39.5 34.6 23.1 16.2 17.7 33.4 29.9 29.2 8.9
DistrictDevelopment Region Eastern Central
Nawalparasi Rupandehi Kapilbastu Dang Banke Bardiya Kailali Kanchanpur
No. of total holdings 101,337 104,174 74,770 86,623 61,433 68,063 111,662 70,573 1,685,641Area (ha) of total holdings 56,125 71,188 64,578 61,952 44,120 47,234 66,659 44,353 1,285,003No. of irrigated holdings reporting 82,269 92,334 41,778 65,388 40,648 52,957 101,559 65,640 1,301,027Area (ha) of irrigated holdings reporting 42,584 58,925 28,068 43,151 22,405 37,940 60,079 39,685 953,740River/lake/pond by gravity No. of holdings 25,950 13,371 12,040 8,173 3,997 9,200 23,988 47,518 368,853
Area (ha) 10,571 6,403 5,869 4,198 2,013 6,979 12,418 29,628 243,354pumping No. of holdings 13,115 23,275 16,559 1,482 9,532 2,139 11,660 1,678 188,983
Area (ha) 6,722 11,135 10,115 490 4,757 893 4,873 988 106,334Dam/reservoir No. of holdings 10,789 7,338 6,384 50,003 1,015 24,102 4,628 15,638 242,044
Area (ha) 5,301 4,172 4,516 34,797 361 18,717 3,295 8,775 171,816Tube well/boring No. of holdings 32,043 59,740 12,578 7,573 28,441 19,282 66,089 0 623,917
Area (ha) 16,361 34,880 6,076 3,407 14,243 9,423 35,598 0 381,908Others No. of holdings 10,743 4,727 2,023 2,204 2,368 5,364 13,707 3,121 76,729
Area (ha) 2,211 769 718 171 832 1,640 2,410 295 23,069Mixed No. of holdings 4,465 3,421 1,707 561 277 611 3,293 0 47,105
Area (ha) 1,418 1,566 773 90 199 288 1,485 0 27,260Percentage of Irrigated Land Area 75.9 82.8 43.5 69.7 50.8 80.3 90.1 89.5 74.2Poverty Head Count Ratio 17.0 17.3 35.5 25.1 26.4 28.7 33.6 31
DistrictDevelopment Region
TotalWestern Mid-Western Far-Western
Table 3-3-4 Farmland area and irrigated area by water source in Terai region
Source: Central Bureau of Statistics. 2015. National Sample Census of Agriculture 2011-2012
Irrigation Schem
e in Terai
DO
I, MO
I 3-20
Figure 3-3-2 Rate of Irrigated area by District Source: Central Bureau of Statistics. 2014. Population Atlas of Nepal, 2014
Data Collection Survey
3-21 JICA
3-3-4 Irrigated Area in Terai Region
Terai Region is an advanced irrigated area and irrigated areas account for 74.2% of a total farm land.
Surface water constitute 54.6% of water resources for irrigation and 36.6% out of the surface water are
supplied by rivers, lakes and ponds (gravity irrigation system: 25.5% and pump irrigation system: 11.1%),
and 18% by dams and reservoirs. Meanwhile, groundwater irrigation (shallow and deep wells) accounts
40.0%. This implies the importance of groundwater development and utilization in Terai plain,
particularly for the areas where is neither perennial rivers nor storage of water in dams or reservoirs.
Table 3-3-4 indicates source of irrigation by region, and Figure 3-3-2 irrigation rate by district. The
groundwater irrigation is necessary for year-round irrigation, and its irrigated area is expanded including
conjunctive use with surface water. Table 3-3-5 shows areas under irrigation by main systems during
monsoon season.
Table 3-3-5 Irrigated Area of the 25 Main Irrigation Systems in the Monsoon Season S/N Irrigation Area Command
Area (ha) Irrigable Area
(ha) Beneficial
Households1 Kankai 8,000 7,000 11,000 2 Sunsari Morang 68,000 60,550 n.a.3 Chanda Mohana 1,800 1,800 n.a.4 Chandra Nahar 10,000 10,000 30,000 5 Koshi West Canal (Distribution System) 10,500 10,500 n.a.6 Koshi Pump Canal 13,180 13,180 n.a.7 Kamala 25,000 25,000 36,000 8 Hardinath 2,000 2,000 5,600 9 Mansumara 5,200 5,200 n.a.
10 Bagmati 37,600 n.a. 27,00011 Jhanj 2,000 2,000 n.a.12 Narayani 28,700 n.a. n.a.13 Narayani Tube Well 2,800 2,800 n.a.14 Narayani Lift 4,750 4,700 n.a.15 Khageri 3,900 3,900 10,00016 Nepal Gandak Western Canal 10,300 9,000 n.a.17 Bhairahawa Lumbini Bhumigath Jalshorat 20,309 10,443 7,00018 Banganga 6,350 6,000 5,000 19 Praganna Kulo 6,684 5,800 3,900.20 Babai 27,000 27,000 n.a.21 Rajapur 14,870 13,200 n.a.22 Pathraiya 2,000 2,000 n.a.23 Mohana 2,000 2,000 n.a.24 Mahakali 11,600 11,600 n.a.25 Machawar Lift 5,600 3,500 n.a. A total of 25 Irrigation Systems 330,143 n.a. n.a.
Source: Interview with DOI and WUA and their reply to questionnaires
3-3-5 Organizations Related to Irrigation Systems Management
Because of the government policy, irrigation management and O&M are decentralized to WUAs. In
principle, small and medium scale irrigation systems are fully transferred to WUAs. Meanwhile, large and
major scale irrigation systems are partly transferred to WUAs based on a written agreement between the
GON and WUAs, in consideration of technical difficulties in O&M.
Irrigation Scheme in Terai
DOI, MOI 3-22
(1) Irrigation Management Division (IMD)
IMD has thirteen FIMDs in Terai region. Those thirteen IMDs and IDD of Rupandehi District jointly
manages the large scale irrigation systems with the WUAs. In accordance with agreement with the WUAs,
they implement (a) operation of irrigation facilities in charge, (b) maintenance and repair of irrigation
facilities, (c) formulation of an irrigation plan with WUAs, (d) technical and/or financial support, on a
demand basis, for repair works that WUA cannot handle, and (e) organizational development of WUA
(Refer to “2-6 Department of Irrigation (DOI)”).
(2) Irrigation Development Division (IDD)/ Irrigation Development Sub-Division (IDSD)
IDDs/IDSDs are in charge of rehabilitation and upgrade of irrigation facilities based on demand from
WUAs and other farmer groups such as a non-registered water user group (WUG) of farmers. Since those
irrigation systems are FMIS, IDDs/IDSDs are not involved in O&M. Once the construction works are
completed, they hand over the facilities to respective WUAs (Refer to “2-6 Department of Irrigation
(DOI)”).
(3) WUA
WUAs are the managing bodies of irrigation systems, not only for FMISs but also for JMISs (Irrigation
Regulation 2000). The WUAs of JMIS make decisions on those issues arising from the area under their
management within the JMIS. GON supports the WUAs through consultations. In order to receive
government assistance, beneficiaries have to establish WUAs following the GON policy, and the WUA
main committees must have their written constitutions and be registered to an irrigation office in charge:
FIMD, IDD or IDSD. It is necessary to turn in the audit report annually to the office to renew the
registration.
The members of WUA main committee cannot exceed eleven, and at least 67% of the members shall be
representatives from the areas irrigated with the secondary, tertiary and lower level canals. Water users at
each level of the canals, from the main to the tertiary canals, should set up a WUA (Irrigation Policy
2013). The WUA at the tertiary canal composes of the WUA at the secondary canal and therefore is
registered as water user to the WUA at the secondary canal. Likewise, a WUA at the secondary canal is
registered as water user to the WUA at the main canal. The WUA at the main canal is registered to the
government, such as FIMD. For those canals lower than the tertiary canal, a WUA is established at each
canal. Those small scale irrigation systems consisting of only a main canal have a WUA at main canal
only and does not have a hierarchy of WUAs with WUAs at main, secondary and tertiary canal levels
WUAs.
The WUA committee at the main canal addresses issues related to the management of the entire irrigation
system under the main canal, while the WUA committee at the secondary canal addresses the issues
related to the management of the secondary canal, and the WUA committee at the tertiary canal addresses
the issues related to the management of the tertiary canal. The WUA at the main canal can delegate their
power and responsibilities to the lower level canal WUAs, and as a result, for example, WUAs at the
tertiary canal may have the delegated power and responsibility to carry out the cleaning of their own
canals. According to the irrigation policy in 2013, WUA shall have female representatives at a rate of
33% as well as proper representation of Dalit, Downtrodden and Backward ethnic communities.
Data Collection Survey
3-23 JICA
WUA contributes to construction works by 3 to 15% of the contract amount and this contribution is cash
or in kind (Irrigation policy in 2000). The word “in kind” means labor service. WUA members supervise
contractors’ construction works after being trained by IDD technical staffs, since IDD engineers cannot
come to the site for supervision every day. Meanwhile, WUAs manage, operate and maintain FMISs and
on-farm facilities of JMIS. Workload of WUAs to implement O&M of main and secondary canals
depends on agreement between the GON and WUA main committees. Activities at lower-level canal
WUAs are based on the regulations written by individual WUAs.
3-3-6 Status of IMT
Whereas IMT is one of the important polities in the irrigation sector in recent years, the progress is lagged
behind, because the development of irrigation facilities seems to be prioritized to the management of
existing irrigation systems in budget allocation. Those projects with support from donor were often
implemented as pilot, and within the framework of such projects, only those facilities managed by the
target WUAs were improved. The extension of similar investment to other irrigation systems is still
on-going. As seen earlier, the requirement of a great deal of budget and labor load for O&M of the intake
facilities due to a large volume of sediments is one of the factors which contribute to such a delay in the
promotion of IMT.
The progress of IMT in the 25 main systems in Terai region is not significant. In most of the WUAs, their
members understand that they have to assume the responsibilities for O&M of the on-farm irrigation
systems and for the provision of support to GON in O&M of the main and secondary canals, to benefit
from the irrigation water. However there are the preconditions for the WUA members to perform such
responsibilities. Namely, enough volume of water is delivered to their plots and they are satisfied with the
yields of their crops. Nevertheless, such preconditions have not been met, since the water delivery is not
reliable and the users cannot use irrigation water efficiently in many of the irrigation blocks.
The major problems can be summarized as follows:
(a) The tertiary and lower level canals within the irrigation system are not developed, or the functions of
the irrigation system have been reduced because of aging (For example, the irrigation systems in
Narayani, Kamala, Hardinath, Banganga, and Machawar).
(b) The irrigation water is not delivered as required due to the dilapidation of the main irrigation facilities
for aging (For example, the irrigation systems in Hardinath, Machawar, Narayani, Banganga, and
Chandra Nahar)
(c) The volume of water flow has been reduced due to changes of canal cross-section by scouring and/or
sediments (The Banganga irrigation system)
(d) The amount of sediments accumulated in canals is too large to be removed manually (For example,
the irrigation systems in Kamala, Hardinath, and Banganga)
The above cases show that the challenge identified by the WUAs is the fact that water is not reaching to
every corner due to problems in somewhere within the irrigation system. Such malfunction of system may
promote failures in the water management, and failures in the water management may lower the farmer’s
willingness to undertake agricultural works as well as to participate in the WUA’s activities. This may
lead to a reduction in the ISF collection rate and subsequently, a reduction of the WUA’s O&M activities.
Then, the irrigation facilities may not be kept in good condition and degraded. The irrigation system falls
Irrigation Scheme in Terai
DOI, MOI 3-24
in a vicious cycle in this way.
Figure 3-3-3 Image of Vicious Cycle in O&M of Irrigation Systems Source: Survey team
When both hardware (infrastructure) and software (organizational and institution development, O&M,
etc.) aspects are maintained well, IMT can be done in a successful manner. The following table shows
IMT status of the main systems in Terai region. Software improvement is necessary for all of the systems,
and most of them need rehabilitation of infrastructure. In case of irrigation taking surface water, problems
with sedimentation would be serious due to large scale rivers.
IMT pilot projects do not target the entire large or medium scale irrigation systems, but a part of them (for
instance, an irrigation block. Reference to Figure 3-3-4). WUA members and FIMD staffs learn the
know-how of the pilot projects and are expected to disseminate it to the remaining irrigation blocks
within the same systems. Currently, IWRMP-AF is implementing IMT pilot projects in the Narayani I
(Block 2), Sunsari-Morang (Ramgunj Branch) and Mahakali Irrigation Systems.
Table 3-3-6 Status of IMT of Major Irrigation Systems in Terai region
S/N Name of the Project District IMT Status Conditions before the
Project No
Assistance necessary
Hardware improve-
ment needed
Software improve-
ment needed
1 Kankai IS Jhapa Type 3 2 Sunsari Morang IS Sunsari & Morang Type2 3 Chanda Mohana IS Morang Type 2 4 Chandra Nahar IS Saptari Type 2 5 Koshi West Canal
(Distribution System) IS Saptari on-going Type 1
6 Koshi Pump Canal IS Saptari on-going Type 1 7 Kamala IS Siraha & Dhanusha on-going Type2 8 Hardinath IS Dhanusha Type 9 Mansumara IS Sarlahi Type 3
10 Bagmati IS Sarlahi & Rautahat Type 2 11 Jhanj IS Rautahat Type 3
Lack of irrigation water
Malfunction of irrigation facilities Shortage of
budget for facility
maintenance
Decrease in ISF collection
Decrease in theirrigated area, Reduction in the
production
Deterioration of Facilities
Stagnation on maintenance activities
Farmers’ loss of motivation
Increase of cost for facility
maintenance
Inadequate water management
Data Collection Survey
3-25 JICA
S/N Name of the Project District IMT Status Conditions before the
Project No
Assistance necessary
Hardware improve-
ment needed
Software improve-
ment needed
12 Narayani IS Parsa, Bara & Rautahat Type 1 13 Narayani Tube Well IS Bara & Parsa Type 1 14 Narayani Lift IS Chitwan Type 1 15 Khageri IS Chitwan Type 3 16 Nepal Gandak Western
Canal IS Nawalparasi Type 1
17 Bhairahawa Lumbini Bhumigath Jalshorat IS
Rupandehi Type 1
18 Banganga IS Kapilbastu Type 3 19 Praganna Kulo IS Dang Type 3 20 Babai IS Bardiya Type 3 21 Rajapur IS Bardiya Type 3 22 Pathraiya IS Kailali Type 3 23 Mohana IS Kailali Type 3 24 Mahakali IS Kanchanpur Type 3 25 Machawar IS Rupandehi Type 3
TOTAL Note: Conditions before the Project: 1: There had been no traditional irrigation system at all. Farmers had practiced rain-fed agriculture. 2. There had been traditional FMISs and those FMISs were developed and integrated to a large system. 3. There had been both rain-fed area and traditional FMISs. Those areas were developed and integrated to a large system,
Source: IMD, DOI
The rightmost column of the table above shows the classification of each Main Irrigation System by the
conditions of farming practices before the establishment. Out of the 25 systems, 7 systems categorized as
Type 1 were established to benefit the rain-fed farming plots. 5 systems categorized as Type 2 were
established to benefit several FMISs, and 13 systems categorized as Type 3 were established to benefit
both rain-fed farming plots and their neighboring FMISs. As each system has different and specific
background before its establishment, lessons from an IMT pilot project targeting a part of a system may
not be relevant to other parts even within the same System.
Since the aforementioned IMT pilot projects tend to target only a part of the system, their approach may
not contribute to an improvement on the performance of the entire system. Indeed, what would be
required in order to break the vicious cycle and bring the positive cycle is that each stakeholder enhances
his/her capacity to improve water management as a whole. In line with this, IMT should be promoted
further.
The schematic diagram of irrigation blocks of Figure 3-3-4 illustrates a block rotation irrigation
mechanism instead of the water distribution to the entire system at once. It is recommended to implement
such block rotation irrigation on a pilot project basis.
Irrigation blocks are basically formed at the tertiary canal level. Representatives from the WUAs of the
tertiary canals are the members of the WUAs of the secondary canals, and subsequently, representatives
from the WUAs of the secondary canals are the member of the WUA of the main canal. Since the WUA at
a higher level should coordinate all the WUAs under the same, all the WUAs should be involved in the
Irrigation Scheme in Terai
DOI, MOI 3-26
implementation of block rotation irrigation.
Figure 3-3-4 Schematic Diagram of Irrigation Blocks
Source: Survey team
3-4 Assistance in the Irrigation and Irrigated Agriculture Sectors by Other Donors
3-4-1 Content of Past Projects
(1) Nepal Irrigation Sector Program (NISP from November 1999 to June 2004 funded by WB)
The NISP project was launched by the DOI with financial assistance from WB in the Far-Western,
Mid-Western, Western and Eastern development regions, covering an irrigable area of 68,735 ha. The
project is aimed at introducing reforms in the water resource sector on a national scale, contributing to the
National Water Resource Development Plan23. It also aims to increase productivity of the irrigation
schemes through large scale adoption of proven technical intervention. Additionally, it supports the
government with institutional and technical capability in water planning, management and orienting
public agencies by handing over their O&M responsibility to user organizations.
(2) Irrigation and Water Resource Management Project (IWRMP, from 2007 to 2013 funded by WB)
Main objectives of the project were improvement of agricultural productivity in selected irrigation
schemes and enhancement of institutional capacity for integrated water resource management. Primary
23 National Water Resource Development Plan is made by WECS in 2003, which is mentioned in “WB Report No 31484: IMPLEMENTATION
COMPLETION REPORT (IDA-30090) ON A CREDIT IN THE AMOUNT OF SDR 58.70 MILLION (US$ 79.77 MILLION EQUIVALENT) TO
THE KINGDOM OF NEPAL FOR AN IRRIGATION SECTOR PROJECT (February 11, 2005)”. However, its contents are unclear. Neither the
Plan itself nor relevant materials are found in DOI.
Data Collection Survey
3-27 JICA
target beneficiary groups of the project were water users and WUAs. The IWRMP was comprised of the
following four components:
Component A: Rehabilitation and Modernization of Irrigation Infrastructure
Component B: Irrigation Management Transfer Reform
Component C: Institutional and Policy Support for Improved Water Management
Component D: Integrated Crop Water Management (ICWM)
(i) Component A: Rehabilitation and Modernization of Irrigation Infrastructure
Objective of this component were to improve irrigation water delivery service in the selected
schemes: Mountain (1,024ha), Hills (10,680ha) and Terai Plain (1,624ha). Under this component,
rehabilitation and improvement of 168 FMISs spreading over 40 districts in Nepal were conducted
for the improvement of the irrigation water delivery to 26,392ha of land in total. With regard to
groundwater, the project directly supported DTW groundwater schemes covering an estimated
area of 2,100ha.
(ii) Component B: Irrigation Management Transfer Reform
The component was designed for the implementation of IMT to address problems on large scale
irrigation system projects (JMIS projects) such as low capacity performance, poor O&M, low cost
recovery, and inadequate maintenance funds. The component B worked with four legally
empowered WUAs and implemented four subprojects located in Kankai, Sunsari Morang,
Narayani, and Mahakali. Irrigated area of the four projects in total was about 23,100ha.
All the activities requiring civil construction have been completed. Activities of the WUA capacity
development program in Kankai was also been finished. Meanwhile, development activities at a
considerable number of WUAs still remain in the Sunsari, Morang, Narayani and Mahakali
irrigation subprojects, and they were handed over to IWRMP-AF.
(iii) Component C: Institutional and Policy Support for Improved Water Management
Objective of the component C was to provide more effective and streamlined water resources
management services at the national level within selected basins through institutional
strengthening of relevant institutions, namely the Water and Energy Commission Secretariat
(WECS) and the DOI. The activities included river basin plans, establishment of telemetry
systems and initiation of rules and policy.
(iv) Component D: Integrated Crop Water Management (ICWM)
Primary objective of this component was to increase crop production and improve productivity
and profitability of agriculture by means of integration between agriculture and water management.
Sub-objectives of the Component D are as follows:
Integration of crop and water management;
Improvement of on-farm water distribution structure; and
Investment support for communities and productive assets.
The activities included improvement support for field level channels and water distribution
structures, community support for small scale investment such as unconventional irrigation
Irrigation Scheme in Terai
DOI, MOI 3-28
technologies, seed banks, storage facilities, market collection place and farm-to-market access
facilities were provided.
(v) Issues and Problems
The following issues and problems were observed during the project implementation period. As
the second issue explains, because the project focused only on the implementation of trainings, it
did not cover overall capacity development of WUAs. Future project formulation should take
account of this point.
The Kankai, Mahakali and Sunsari Morang projects encountered frequent flood attacks.
Especially edges of the command area nearby rivers exposed to the serious damage.
The WUA capacity development programs focused on training only, thus did not meet the
requirements for overall development of WUAs
The budget allocated by the government for WUA capacity development works were not
timely and adequate
Participation of officers in workshops and field training programs was limited due to
insufficient availability of qualified officers and engineers
(3) Irrigation Sector Project (ISP, from 1989 to 1996 funded by ADB)
The DOI implemented the ISP in thirty-five districts at the eastern and central development regions with
assistance from ADB. The Irrigation policy (1988) stressed strategic approach on participation of farmers’
groups and cost-sharing mechanism for irrigation development and O&M works of canals.
As pilot tests of the approach, the DOI implemented community development projects focusing on
agriculture communities which had already managed traditional irrigation systems. The DOI also
conducted programs to enhance WUAs’ capacities in order to improve livelihood of small scale farmers,
reduce poverty rate and generate employment opportunities in rural areas. The cropping intensity
increased by 14% compared to the beginning of the projects which was 149%.
(4) Second Irrigation Sector Support project (SISP from 1997 to 2003 funded by ADB)
The SISP has been implemented as a follow up project of the ISP. The SISP was launched with the
implementation of provisions for the Irrigation Policy (1992), which stresses the importance of
participatory approaches of farmers in irrigation construction. The project targeted farming communities
which already managed traditional irrigation systems and strengthened WUAs in thirty-five districts of
the central and eastern development region of Nepal. The project scope was limited to enhancement of
WUAs, improvement of FMIS, capacity development of irrigation offices and provision of agricultural
extension services. The project accomplished 278 sub-projects (FMIS) covering 39,757ha out of the
planned 283 projects which covers 41,147ha. About 278 WUAs were registered while 178 were planned.
The cropping intensity increased by 40% compared to the beginning of the projects which was 170%.
Yields of paddy, wheat and maize also increased thanks to improvement in water availability.
(5) Irrigation Management Transfer Project (IMTP from 1995 to 2004 funded by ADB and the USAID)
The DOI implemented the IMTP financed by ADB and United States Agency for International
Development (USAID) which aimed to achieve the Irrigation Policy 1992. This project included
Data Collection Survey
3-29 JICA
achievement of the Development Plan formulated in 1985 and irrigation management transfer to WUAs.
The IMTP emphasized the need to improve O&M of the existing government operated projects through
beneficiary participation and transferring O&M responsibilities. The total area transferred from the eight
districts of Saptari, Dhanusha, Sarlahi, Chitwan, Nawalparasi, Kapilbastu, Kailali and Kanchanpur was
45,563 ha.
The project performance increased considerably when irrigation system rehabilitation (main, branch,
tertiary) was completed. The participation of WUAs also increased and intensive water distribution
schedule was implemented. Capacity of fourteen WUAs was developed to manage all the branch canals
of the jointly managed irrigation project, except for Panchakanya, which was fully turned over to the
farmers. The average irrigation intensity increased by 27% and productivity of irrigated paddy, maize and
early paddy increased remarkably in three projects where farmers operated and maintained the branch
canals.
(6) Community Managed Irrigated Agriculture Sector Project (CMIASP from 2006 to 2013 funded by
ADB)
This ADB-assisted project is a follow-up program of the Irrigation Sector Project (ISP) and the Second
Irrigation Sector Project (SISP) covering thirty-five districts in the Eastern and Central development
regions. The objective is to improve agriculture productivity and sustainability of existing small and
medium sized FMISs suffering from low productivity and high poverty incidence.
Under CMIASP, 111 irrigation subprojects (ISP) were implemented with a total target area of 16,105 ha.
The subprojects are comprised of irrigation infrastructure development that involves rehabilitation of
existing irrigation infrastructure and/or expansion of irrigation networks, social development,
strengthening of WUAs, agricultural development and livelihood enhancement. A report on the evaluation
is not obtained.
3-4-2 The Contents and Challenges of the On-going Projects
Currently, Community Managed Irrigated Agriculture Sector Project – Additional Financing
(CMIASP-AF) supported by ADB and Integrated Water Resources Management Project – Additional
Financing (IWRMP-AF) supported by WB are under implementation. The target area of CMIASP-AF is
the Eastern and Central Development Regions, while that of IWRMP-AF is the Western, Mid-Western
and Far-Western Development Regions. These two programs cover the whole country, dividing it into two
zones. While the major target of these two programs is small and medium scale irrigation systems, which
are FMIS, the IWRMP-AF is also implementing the IMT at the 3 main irrigation systems out of the 25
JMISs in Terai region.
Table 3-4-1 explains comparison of the CMIASP-AF and the IWRMP-AF. The contents of those
programs are basically composed of rehabilitation of irrigation facilities, institutional development, water
management and agriculture. Due to a lawsuit brought by consulting companies employed by the DOI,
the water management of the IWRMP-AF component has been suspended. These contents are
implemented for not only FMISs but also for three main irrigation systems under IMT. The DOI is in
charge of rehabilitation of irrigation facilities, institutional development and water management, while the
DOA implements agriculture component.
Irrigation Scheme in Terai
DOI, MOI 3-30
While field level officers of the DOI are in charge of the both programs of FMIS and employed
consultants are supporting these officers, consultants (engineers, experts of social development, etc.)
hired by WB implement IMTs of the three main irrigation systems. Those consultants and officers of the
IMD listen to WUA members and address the issues related to agriculture, maintenance and improvement
of facilities, institutional development, collaboration of water management and agriculture.
The project period is about five years, but rehabilitation of the facilities takes three years. Therefore, the
capacity development of WUA members and the trainings in agriculture and water management have to
be conducted simultaneously. Water is not yet distributed, as the rehabilitation of irrigation facilities has
been still on-going, and the implementation of the soft components is not fully bringing about expected
outputs. It is expected to find and apply solutions to those challenges posed by the tight schedule.
Table 3-4-1 Comparison of Contents between CMIASP-AF and IWRMP-AF
CMIASP-AF (ADB) IWRMP-AF (WB)
Period 2014 - 2020 2014 - 2018
Target area Eastern and central development regions Western, mid-western and far-western development
regions
Irrigation
Sub-projects
150 FMISs
Out of which, 145 FMISs are traditional
ones while the remaining 5 are newly
developed.
83 FMISs
IMT None 3 main systems1 in Terai (large or major system)
Infrastructure Rehabilitation and improvement of
Irrigation Systems
Irrigation infrastructure improvement/rehabilitation
Institutional
Development
Trainings of Organizational operation and
accounting, Planning for O&M and water
management Irrigation service fee (ISF) collection. Gender Equity and Social Inclusion
(GESI) WUA strengthening
Trainings of Organizational operation and accounting, Planning for O&M and water management Irrigation service fee (ISF) collection. Gender Equity and Social Inclusion (GESI) WUA strengthening
Water
Resources
Management
None Integrated water resources management plan for hydropower and irrigation at river basins
Policy support for productivity increase (Note) it is suspended.
Agriculture Leader farmer training Farmers Field School and
demonstration: - On-farm Water Management
Training - Water-saving Rice Technologies - Cropping Pattern - Improved Seed Production - Farm mechanization
Soil management Market Support and Accessibility
Leader farmer training Farmers Field School and demonstration:
- On-farm Water Management Training - Water-saving Rice Technologies - Cropping Pattern - Improved Seed Production - Farm mechanization
Soil management Market Support and Accessibility Trainings to 60 social mobilizers (28 females) in
cropping pattern design, soil fertility management, and use of small farm machinery
1 Narayani Block ; 2 Sunsari-Morang Ramgunj Branch and Mahakali
Source: CMIASP-AF and IWRMP-AF
Data Collection Survey
3-31 JICA
3-4-3 Problems with Implementation of Sub-projects by Donors
As for FMIS, DOI field staffs (IDD/IDSD staff) and local consultants hired by DOI mainly implement the
sub-project components. Meanwhile, as for the IMT of the three main systems, WB consultants
(engineers and sociologists) play core roles in facilitating IMT between FIMD and WUAs. They listen to
WUA members to identify problems and solve them with FIMD staff so that farmers are willing to accept
hand-over of the irrigation system. Such problems are usually infrastructure rehabilitation/upgrade,
institutional development and O&M and farming. There is a common problem in implementation of
CMIASP-AF and IWRMP-AF.
The irrigation sub-project implementation period of CMIASP-AF and IWRMP-AF is usually 5 years.
And, the irrigation sub-project most likely includes the rehabilitation of headworks and/or main canal. In
order to fund rehabilitation of such facilities, the procedure explained in Section 3-2-4 has to be taken.
Therefore, it takes at least 3 years to finish the rehabilitation works. Meanwhile, O&M and agricultural
components need at least 2 to 3 years respectively. That is, it takes 7 to 9 years to finish the irrigation
sub-project because rehabilitation, O&M and agriculture should be implemented in series. Accordingly,
the 5-year sub-project brings confusion on the implementation. In practice, it is not possible to provide
O&M training to farmers using facilities under construction. Likewise, it is difficult to give farmers
trainings related to farming without proper water delivery.
Coordination committees are established between DOI and DOA. They are not only at the central level,
but also development regional and district level, too. The coordination committees are held as needed. At
the beginning of the program, such as at the stage of the planning and sub-project selection, they may
have meetings frequently, for instance, monthly. After that, they are held every 3 months during the
implementation phase. They usually discuss planning and implementation schedule of the components in
the coordination committees. Discussion at district-level committee is crucial because implementation of
the program becomes usually behind schedule.
Since the main component of CMIASP-AF and IWRMP-AF is the rehabilitation of headworks and/or
main canals, the sub-project requires an extension of the project period for a couple of years. However, in
case of a program/project whose main component is O&M such as JICA-TCP, it seems feasible to achieve
expected outputs and objectives of a pilot program/project within 5 years as far as well-functioning
irrigation systems which do not require large scale rehabilitation works are selected as program/project
site.
3-5 JICA’s Cooperation in the Past
3-5-1 Janakpur Zone Agriculture Development Project (1980 - 1983)
A Model Farm Project of Irrigated Agriculture had been implemented from 1980 to 1983 as a part of the
Janakpur Zone Agriculture Development Project. The model farm is the model of groundwater irrigation
in rain-fed agricultural areas. Three district, namely Sarlahi, Mahottari and Dhanusha, are selected in
Terai because it was confirmed that there were abundant groundwater in those 3 districts. There are 3
model farms with STW (4.1 to 5.6 ha) and 1 model farm with DTW (45.6 ha). Those model farms were
served as not only hubs of extension activities but also models of groundwater irrigation.
Irrigation Scheme in Terai
DOI, MOI 3-32
3-5-2 Rajkudwa Irrigation Proejct
The “Integrated Rural Development Project in the Lumbini Zone”, which was conducted from 1988 to
1989 with support from JICA, marked the Rajkudwa Irrigation Project as one of the projects to be
prioritized in the implementation. The project aimed at an expansion of irrigated area in the paddy fields
located between the Gudrung and the Kondre rivers in Kapilvastu District.
Having the DOI of the Ministry of Water Resources as the responsible agency from GON, the
pre-feasibility study was conducted in 1992. Likewise, the feasibility study from 1992 to 1993, and the
basic designing mission in 1994, respectively. The population of the project site was 33,260 with 5,150
households at that time, and the project aimed to increase the irrigated area from 890ha to 1,800ha. The
overall project cost was 681.8 million Nepal Rupees.
Nonetheless, the project has made no progress since the completion of basic designs in January 1995. In
accordance with the report of the JICA’s Project Status Survey 2014, the project was cancelled no later
than year 2000. The report says the reason of the cancellation is high cost.
3-5-3 Master Plan Study on Terai Groundwater Resources Evaluation and Development Project
(1991 - 1995)
Irrigation by STWs is prioritized where surface water is not easily available and STW development is
more advantageous technically and economically than surface water irrigation development. However,
the irrigable area of DTWs is generally larger than that of STWs and it is supposed that DTW
development is more advantageous technically and economically than STW development. Thus, the
preliminary survey of the master plan survey mentioned above was conducted in March 1991. As a result,
Jhapa, Mahottari and Banke districts selected as study areas for groundwater development by DTWs.
The master plan survey was implemented from October 1991 to March 1995. Potential areas of DTW
irrigation were selected and a master plan was formulated regarding DTW irrigation. The target areas of
the master plan, that is, potential areas of DTW irrigation were 17,000ha, 7,000ha and 8,000ha in Jhapa,
Mahottari and Banke districts respectively. The entire project costs and periods were US$357.8 million
(US$3,400/ha) and 10 years for Jhapa district, US$31.7 million (US$4,500/ha) and 9 years for Mahottari
district and US$30.2 million (US$3,800/ha) and 8 years for Banke district. Also, it was concluded that the
irrigable area of a DTW should be 30ha or more (pumping discharge is at least 30L/s) so that the
irrigation system is economically feasible.
3-5-4 Feasibility Study on the Sunsari River Irrigation (2001 - 2002)
Based on the Scope of Work for the above mentioned study signed off on 29 November 2000, the study
was conducted from April 2001 to December 2002. The objectives of the survey were formulation of an
irrigation plan and its feasibility study as well as technical transfer to Nepali engineers through the survey.
The target area of the survey was 168.2km2, beneficiary population was 97,700 (13 VDC, 16,200
households). A rough irrigation plan was formulated in the first year of the survey. In the second year, a
development plan and an implementation schedule were formulated followed by the feasibility study.
The target area for irrigation development was 10,544ha, of which 397ha was STW irrigation. The overall
project cost was US$18.1 million. Also, the project evaluation concluded that it should be implemented
early, because it exceeds 12% that is the Nepali opportunity cost and it is anticipated that spillover effect
Data Collection Survey
3-33 JICA
to the landless poverty group. The JICA’s Project Status Survey 2014 has reported that it was in
preparation for implementation as of year 2003.
Data Collection Survey
4-1 JICA
Chapter 4 Problems/Challenges of Each Irrigation System
4-1 Irrigation Systems which were the target of the Detailed Study
Through an interview with IMD, those target irrigation systems for the study were selected. To select
JMISs, it was considered to select: 1) both good and poor JMISs in the operation and management, 2)
both the JMISs with good and poor potential in the water resources availability, 3) both the JMISs with
and without supports from other donors and 4) the JMISs recommended by IMD or in the workshops
(Table 4-1-1). The FMIS’s selection criterion for the study was either being good in the operation and
management, having supports from other donors, or having groundwater as water resource in order to
include different types of FMISs in the study targets (Table 4-1-2). Figure 4-1-1 indicates the JMISs and
FMISs visited and studied by the Survey team.
Table 4-1-1 Irrigation Systems Studied in the Survey (JMIS) Irrigation System
District Command Area
Reason for the Selection as a Target Survey Area
Kankai Jhapa 8,000ha Well-managed JMIS and recommended by IMD as a pilot project site
Kamala Siraha & Dhanusha
25,000ha A poorly managed JMIS
Hardinath Dhanusha 2,000ha A JMIS having insufficient water and poor management Narayani Parsa, Bara
& Rautahat 28,700ha A JMIS having insufficient water and with supports from
the other donors (WB) Banganga Kapilbastu 6,350ha A JMIS having sufficient water resources and reservoir Machawar Rupandehi 5,600ha A JMIS using pump and water resources are in short
supply in spring Praganna Kulo Dang 5,800ha Nominated as a pilot project candidate by the workshop
participants Bagmati Sarlahi &
Rautahat 37,600ha Nominated as a pilot project candidate by the workshop
participants Chandra Nahar Saptari 10,000ha Nominated as a pilot project candidate by the workshop
participants Source: Survey Team
Table 4-1-2 Irrigation Systems Studied in the Survey (FMIS) Irrigation System District Reason for the Selection as a Target Survey Area Buwa Gramin (115ha, 172HH)
Morang A well-managed FMIS
Kalikoshi (187ha, 2,000HH)
Morang A well-managed FMIS
Dudhmati (230ha, 600HH)
Mahottari A subproject site of the other donors’ project (CMIASP-AF funded by ADB)
Itiyakulo (2,500ha, 8,450HH)
Rupandehi A well-managed FMIS and a subproject site of the other donors’ project (CMIASP-AF funded by ADB)
Jhimjhime (200ha. 800HH)
Rupandehi A subproject site of the other donors’ project (IWRMP-AF funded by WB)
Tamsariya (240ha, 540HH)
Rupandehi A FMIS combining ground water and surface water
( ) Irrigated area and beneficiary households identified in the field survey
Source: Survey Team
Irrigation Scheme in Terai
DOI, MOI 4-2
Figure 4-1-1 Locations of Studied Irrigation Systems
JMIS FMIS Source: Survey Team
4-2 JMIS
4-2-1 Conditions of Irrigation
Following Table 4-2-1 indicates condition of irrigation systems studied by the Survey.
Table 4-2-1 Water Source and Irrigated Areas of the studied JMISs
Note) The figures in parentheses of Kankai are actual irrigated areas at present.
Source:Responses to the Questionnaire applied to the JMISs
The information on the irrigable area in Table 4-2-1 was obtained by applying the questionnaire to the
concerned JMISs. The values of the irrigable areas in the rainy season of the table above seem reliable,
while the figures of the irrigable areas in winter and spring seem overestimated. All of the irrigation
systems take water from perennial rivers except the Banganga irrigation system. The irrigation systems
Irrigation System
Water Source Means of Water
Intake
Area (ha)
CommandArea
Irrigable Area Rainy
Season Winter Spring
Kankai Perennial River Diversion Dam 8,000 7,000
(5,500) 4,000
(3,000) 3,600
(2,500) Kamala Perennial River Barrage 25,000 25,000 25,000 10,000 Hardinath Perennial River Diversion Dam 2,000 2,000 2,000 1,000 Narayani Perennial River Barrage in India 28,700 - - -
Banganga Perennial/Seasonal Rivers Diversion Dam & Reservoir
6,350 6,000 4,000 2,000
Machawar Perennial River Diversion Dam 5,600 3,500 3,000 50Praganna Kulo Perennial River - 6,684 5,800 3,500 3,500 Bagmati Perennial River Diversion Dam 37,600 - - -Chandra Nahar Perennial River Diversion Dam 10,000 10,000 10,000 8,000
Kankai
Bagmati
Chandra Nahar
Hardinath
KamalaMarchawar
Banganga
DudhmatiBuwa Gramin
Kalikoshi
Itiyakulo
Jhimjhime
Tamsariya
Praganna Kulo
Narayani
Data Collection Survey
4-3 JICA
take water from the headworks by diverting flow of rivers. The irrigated areas in the rainy season are the
same as those in the winter season, or may be the former is little less than the latter. Nevertheless, the
irrigated areas in the spring season decreases significantly. This can be attributed to little discharge of
rivers before the rainy season, and annual water discharge of those rivers shall be confirmed.
4-2-2 WUA
(1) Organization
The responsibility of government for O&M of the irrigation facilities of JMISs varies depending on the
irrigation systems. The JMISs which were studied in this survey were listed in the following table, and
they are categorized in two types: Type-A and Type-B. In the Type-A JMIS, the GON controls the main
canal only and in the Type-B JMIS, the GON controls both main and secondary canals. The GON usually
controls up to the secondary canals in the large scale irrigation systems whose command area is more
than 10,000ha (The irrigated areas highlighted in bold font and underlined in Table 4-2-2).
Table 4-2-2 O&M of JMISs and WUAs’ Participation into the Irrigation Projects
JMIS O&M
Responsibility Distribution*1
Command Area (ha)
Beneficiary Households
*2
WUAs’ Participation into Projects Planning Designing Construction
Kankai A (GON: Main) 8,000 11,000 Yes No Yes Kamala B (GON: Secondary) 25,000 36,000 - - Yes Hardinath A (GON: Main) 2,000 5,600 - - Yes Narayani A (GON: Main) 28,700 - Yes No No Banganga A (GON: Main) 6,350 5,000 Yes No No Machawar A (GON: Main) 5,600 n.a. Yes Yes Yes Praganna Kulo A (GON: Main) 6,684 3,900 Yes No Yes Bagmati B (GON: Secondary) 37,600 27,000 Yes No Yes Chandra Nahar B (GON: Secondary) 10,000 30,000 Yes No Yes
*1: A: the GON controls up to the main canal、B: the government controls both the main and the secondary canals. *2: The Number is estimated based on the response to the questionnaire and data shared by individual households. Source:Responses to the Questionnaire applied to the JMISs
The number of beneficiary households of each JMIS is obtained from the responses to the questionnaire
applied to the JMISs or estimated based on the average farmland area per household, so that it should be
considered just as a reference. Regarding the WUAs participation into the establishment of the JMISs,
many of them seems to have participated into the planning phase, but not in the designing and actual
construction works. How the WUAs have participated in the establishment process, and what of the
distribution of roles in the management of JMISs, the WUAs have understood may be confirmed at a later
stage.
A WUA committee is set up at each level of canals: main, secondary and tertiary. WUAs usually have a
discussion with FIMD in charge about irrigation schedule. Each committee is composed of president,
vice-president, secretary, treasurer, and representatives from lower-level canal WUA committees. At least,
33% women participation are required as well as proper representation from Dalit, Downtrodden,
Backward ethnic communities. Committee members are elected every two years; their term is stipulated
in the constitutions of the committee. The upper-level canal WUAs inform the committees’ decisions and
reports to the lower-level canal WUAs.
Irrigation Scheme in Terai
DOI, MOI 4-4
Table 4-2-3 Status of the WUAs Irrigation System
Status Problems
Kankai There is a main canal committee, secondary canal committees and tertiary canal committees.
n.a.
Kamala There is a main committee, secondary canal level committees and tertiary canal level committees for each of east and west main canals.
There are inactive WUAs due to no development of the command area (the tertiary and lower level canals) under the WUA’s management.
Hardinath There is a main committee, secondary canal level committees and tertiary canal level committees for each of east and west main canals.
n.a.
Narayani The main committee has been not functioning for last 10 years. The IMD is now re-organizing the main committee. Secondary committees at Blocks 2 and 8 are acting at present.
There are inactive WUAs due to no development of command areas (the tertiary and lower level canals) under the WUA’s management.
Banganga There is a main committee, secondary canal level committees and tertiary canal level committees.
WUA has been refusing the IMT due to deteriorated/ malfunctioning/ disabled infrastructure in the command area (the tertiary and lower level canals) under the WUA’s management.
Machawar There is a main committee and secondary canal level committees.
The ISF is high because of pumping irrigation system, and its collection rate is low.
Praganna Kulo
There are 3 main canals and 3 WUA main committees on the right bank of the river. There is a coordination committee for these 3 WUA main committees.
Since DOI developed the area where conventional FMISs were concentrated in order to establish the JMIS, the WUGs of original FMISs were transformed into the WUA. The WUA has adopted the WUGs’ traditional rules to manage the JMIS.
Bagmati (GAR2WUA)#1
Tertiary canal level committees are established and secondary canal level committees are under the formation at present for where the tertiary canals were established in the command areas under the WUA’s management.
The WUA main committee has not yet organized.
Chandra Nahar
There is a main committee, secondary canal level committees and tertiary (village channel) level committees. The WUA is well-functioning.
The entire irrigation system is deteriorated, but the deterioration within the command area under the WUA’s management is worse and not working. Due to the situation, the WUA has not agreed with the IMT.
#1 IMT has been implemented and the WUA at the main canal level has not been yet organized. So far, tertiary canal level committees have been established for the developed command area, and the preparation for the establishment of secondary canal level committees is underway. The GAR2WUA, one of the tertiary canal level committees was studied in particular (GAR2 stands for the second tertiary canal in the right bank of the Gadhaiya secondary canal which is a branch canal of the east main canal.). Since each WUA in the Bagmati irrigation system is independently operated, the current situation and challenges of the WUAs within the same irrigation system may vary from WUA to WUA. To understand the situation and challenges faced by other WUAs, further studies will be required. Source: WUA and FIMD
The irrigation facilities of the Bnganga system are extensively destroyed. The Chandra Nahar system
becomes malfunctioning due to aging. Under such circumstances, any transfer of the management to the
WUAs has not taken place in these two irrigation systems. In the Chandra Nahar system, actually, the
Data Collection Survey
4-5 JICA
WUAs are well-organized and active at the secondary and tertiary canals, although these WUAs have not
agreed with the implementation of IMT. These WUAs are not able to afford the costs for the rehabilitation
of their irrigation facilities, and a prompt rehabilitation by GON of the irrigation facilities is awaited. .
The WUAs of Kankai, Praganna Kulo, Bagmati (GAR2) and Chandra Nahar are evaluated as well
organized by DOI, since the WUAs of these irrigation systems have followed the instructions provided by
DOI. Meanwhile, the WUAs of the Banganga and Kamala Irrigation Systems are evaluated as not well
organized. The WUAs of these irrigation systems do not seem to trust DOI, since the water is not
distributed to the WUA members. Their irrigation systems have not yet had the tertiary canals and are not
functioning due to severe deterioration.
Those highly evaluated WUAs are the ones which have a long history (e.g. Chandra Nahar), whose
on-farm facilities are either functioning well or under development (e.g. Kankai and Bagmati), or which
are closely united as organization (e.g. Praganna Kulo). In any case, whether water is distributed or not
affect the results of evaluation and actual conditions of each of the WUAs.
(2) Registration
All the WUA main committees are registered by application to the irrigation office in charge: FIMD or
IDD. The secondary canal level committees are registered to the main committee, and the tertiary canal
level committees are registered to the respective secondary canal level committees. The WUA main
committee has to submit the audit report to the irrigation office so as to renew the registration. The WUAs
of all the surveyed irrigation systems have already completed their registration.
(3) Constitution
All the registered WUAs, including the secondary and tertiary level ones, have the written constitutions
since it is a prerequisite for the registration. Thus, prior to the registration, a WUA has to make a
constitution by its own members under the guidance of FIMD or IDD. The association organizer (AO) is
in charge of such activities. The contents of the Constitution vary from WUA to WUA, as it is tailored for
each of the WUAs considering the respective circumstances.
(4) Board Members
WUA board members are selected through election. The election may be carried out indirectly by
representatives from the systems when there are a number of WUA members.
(5) General Assembly
General assembly is held once a year. It can be also held when necessary, such as an emergency case.
(6) Financial
The treasurer is in charge of finance. The collected ISF is first shared between the WUA and the GON.
Then, the WUA portion is further shared between the WUA main committee and the lower level WUA
committees. The WUA main committee has to prepare an audit report and submit it to the irrigation office
(FIMD or IDD) for the registration renewal. The financial status shall be also reported to the WUA
members at the annual general assembly meeting.
Regarding the ISF, beneficiaries sometimes do not pay the charged fines or do not follow the constitution,
Irrigation Scheme in Terai
DOI, MOI 4-6
and the management around ISF should be improved. Deteriorated and malfunctioning irrigation facilities
in the Banganga System discourage some beneficiaries to pay ISF, and the collection rate of ISF remained
to 30%. In the Chandra Nahar System, the WUA has not collected the ISF for the last three years. This is
because farmers are still struggling to recover from the damages and losses caused by the flood which
occurred three years ago.
The Machawar Irrigation System is a pumping irrigation system, and it is a heavy burden for the WUA to
pay the expensive electric bills. The amount of ISF has to be high, and as a consequence, the ISF
collection rate declines. Only four pumps out of the ten in the irrigation system are currently working for
only 12 hours per day due to blackouts. The pumping capacity has been reduced since those pumps have
already 35 years and are deteriorated. All these conditions have affected negatively the ISF collection rate
of the Machawar System. Meanwhile, in the Banganga Irrigation system, the irrigation facilities except
headworks had been impaired and the WUA refused the IMT, and the ISF collection rate remains low.
In contrast, the ISF collection rate of the Kankai, Hardinath and Bagmati WUAs is 70%. Despite water
shortage together with inadequate water management, the ISF collection rate remains high in the
Hardinath Irrigation System. This may be attributed to the fact that the irrigated area of the Irrigation
System is relatively small and farmers can practice three cropping seasons per year. 2,000ha of paddy in
the rainy, winter and spring seasons, respectively. The WUA members desilt sediments from the irrigation
facilities with a help from FIMD and this contributes to avoid malfunctioning of the irrigation system, and
hence: a high collection rate of ISF.
Table 4-2-4 ISF: Collection Rates and Distribution between WUAs and the GON
Irrigation System
Amount Collection Period
Collection Rate
Penalty Share WUA GON
Kankai 300 Rs./0.66ha/crop Jun – Jul 70% No water delivery 90% 10%Kamala 150 Rs./ha/crop Dec – Jun 40% double payment 80% 20%Hardinath 150 Rs./ha/crop Dec – Jun 60 - 70% double payment 80% 20%Narayani (Block 2)
300 Rs./ha/crop Aug – Oct 60% No penalty 80% 20%
Banganga 150 Rs./ha/crop After
winter/summer crop harvest
30% Ban on participation in elections
90% 10%
Machawar 750 Rs./ha/yr - 10 - 20% 25% increased payment 90% 10%Praganna Kulo
600 Rs./ha/yr Crop season
end 50%
- 100% 0%
Bagmati (GAR2)
600 Rs./ha/yr - 60 - 70% - 100%#1 0%
Chandra Nahar
60 Rs./ha/crop (until 3 years ago)
None for the last 3 years - n.a.
No penalty n.a. n.a.
#1: The information source was the GAR2 WUA. Meanwhile, according to the FIMD in charge of the Bagmati Irrigation System, the share rates of the collected ISF between the WUA and GON are 70% and 30%, respectively.
Source:WUAs
(7) Means of information transfer from the WUA main committee to its members
The means below are used for information transfer from the WUA main committee to its members.
Verbal message from main committee members to lower level canal WUAs, including cell phone
Data Collection Survey
4-7 JICA
in Kamala, Narayani and Banganga
Announcing with microphones and speakers in Kamala and Hardinath
FM radio (local announcement in FMISs and JMISs in Kankai and Bagmati)
Putting an article on newspaper in Chandra Nahar
Posting on a WUA notice board in Machawar
Announcing with speakers on a bicycle in Bagmati
4-2-3 Irrigation Facilities
(1) Condition of Irrigation Facilities
All the irrigation systems have hardware problems. Causes of the deterioration are mostly aging and
budget shortage for the rehabilitation. The GON cannot afford the rehabilitation of all the JMISs and
therefore, multi-/bi-lateral assistance, such as the Saudi Fund for Development, is indispensable.
The following table summarizes the current condition of irrigation facilities of the respective irrigation
systems, including canals and the other hydraulic structures. The headworks and the main canals, which
are maintained by the GON, are functioning in most of the irrigation systems. The repair of the headwork
of the Kankai Irrigation System is scheduled for the spring season of 2017, the rehabilitation of the entire
system will be completed at the same time.
Compared to the headwork and the main canal, the secondary and tertiary canals are not maintained well.
WUAs are in charge of the maintenance of these canals, however, they are not able to keep them in a
good condition, due to inadequate budget and technology for the maintenance. It seems that there are a
few irrigation systems, which require a major rehabilitation to their principal structures, although a
functional diagnosis of the irrigation structures has not been carried out to each of the structures.
Table 4-2-5 Condition of Irrigation Facilities in Each Irrigation System Reviewed by the Interview Survey
Irrigation System Condition of Irrigation Facilities
Headwork/Water Source Main Canal Secondary Canal Tertiary Canal
Kankai C B C C Kamala - B C D Hardinath - B C - Narayani - C C - Banganga B C C C Machawar - C D D Praganna Kulo - B B B Bagmati A B B C Chandra Nahar B C C D
A = Maintenance and repair are done and functioning properly B = Warning signs are found but functioning during the next crop season C = Partly malfunctioning D = Dilapidated and malfunctioning in whole E = Partly disabled
Source:Interview with JMIS based on questionnaires
Irrigation Scheme in Terai
DOI, MOI 4-8
Table 4-2-6 Condition of Irrigation Facilities Irrigation System
Condition Problem
Kankai The facilities are rehabilitated by IWRMP and the headwork, main, secondary and tertiary canals are in good condition.
Embankment portions of the secondary and tertiary canals are preferentially lined. The headwork is to be rehabilitated in the spring of 2017
Kamala The system has aged as a whole though the headwork is maintained in a good condition. The main and secondary canals have significant sediments. Unlined portion of the canals are soured and needs reshaping. The command area at the tertiary and lower level canals under the WUA’s management has not been developed.
The FIMD in charge is not able to desilt the extensive sediments due to budget shortage.
The FIMD in charge does not have enough capacity to develop the irrigation system within the command area (the tertiary and lower level canals) under the management of WUA.
The FIMD has not been able to develop the command area.
The WUAs cannot manage water in the command area at the tertiary and lower level canals under the management of WUAs due to non-existence of water control facilities.
Hardinath The system has dilapidated as a whole though the headwork is maintained in a good condition. Main and secondary canals have significant sediments. Unlined portion of canals are soured and needs reshaping. Tertiary and field canals are underdeveloped.
Seepage loss from unlined canals is significant.
Some sluice gates are broken. Canal reshaping is needed. The FIMD is not able to solve the above
problems due to budget shortage. Narayani The system has dilapidated as a whole, and
canal capacity has decreased due to sediments. There are no tertiary systems developed.
Desilting and reshaping are needed to recover the canal capacity,
The WUAs cannot manage water in the command area (the tertiary and lower level canals) due to non-existence of tertiary systems.
The FIMD is not able to solve the above problems due to budget shortage.
Banganga The system has dilapidated as a whole though the headwork is maintained in a good condition. The unlined portion of the main canal is scoured significantly. There are 2 reservoirs for the dry season irrigation in the system, but both of them are filled with sediments. The tertiary systems are malfunctioning and some structures are disabled.
Desilting and reshaping are needed to recover the canal and the reservoir capacities,
The WUAs cannot manage water in the command area (the tertiary and lower level canals) due to non-existence of water control facilities.
The FIMD is not able to solve the above problems due to budget shortage.
Data Collection Survey
4-9 JICA
Irrigation System
Condition Problem
Machawar Only 4 pumps out of 10 are workable due to aging. In addition, those 4 pumps are aging (35 years old) and the pumping capacity has decreased. Moreover, the brick-lined canals are partly broken due to the insufficient compaction of backfilled soils.
Irrigation is not feasible during approximately 12-hours blackouts per day.
ISF is not sufficiently collected for brick-lining repair; ISF mainly used for pump operators’ salary.
Governmental financial support (3,000,000Rs/yr) is not enough: electricity costs 2,200,000Rs/yr; grease costs 800,000Rs/yr; and the remaining is used for the canal maintenance.
IDD Rupandehi does not have budget to replace the pumps and/or rehabilitate the canals.
Praganna Kulo
Since the system has started its operation in 2005 and is still new, it is maintained in a good condition. The system does not have headwork because it will be buried with sediments within one year. There are 3 side intakes and temporary canals channeled in the riverbed by the DOI guiding water from a river to the intake.
The DOI should always be prepared for excavation of temporary canals
Because of uncontrollable intake, water supply is unstable.
Bagmati The barrage is in good condition, and there is a generator in case of blackout. The sluice gates are rehabilitated and well-functioning. These rehabilitations are owing to the Saudi Fund for Development.
The command area (the tertiary and lower level canals) has been partially developed with tertiary systems. But there still remain areas where not yet developed.
Chandra Nahar
The system was established in 1927, almost 90 years ago. The facilities are malfunctioning. The tertiary systems (village channels) are also malfunctioning.
The whole systems need rehabilitation since it has never had major rehabilitation for nearly 90 years.
Source:WUAs and FIMDs
The following table summarizes above identified problems:
Table 4-2-7 Summary of Malfunctioning of Irrigation Facilities Problems Keyword Example of the systems
Problems caused by natural conditions
Sediments, insufficient cross section, desilting, command area (the tertiary and lower level canals) (irrigated farmland)
Kamala、Narayani, Banganga
Problems caused by water shielding of structures
Water leakage Hardinath
Problems caused by control accuracy of the facilities
Water control facilities, sluice gate Kamala, Hardinath, Banganga
Problems caused by aging of the facilities
Deterioration, aging Kamala, Hardinath, Narayani, Banganga, Machawar, Chandra Nahar
Problems caused by the operation of the facilities
Pump Machawar
Problems caused by efficient water use and equity
Rotation at the main and tertiary canals
Kamala, Hardinath, Narayani, Banganga, Chandra Nahar
Source:WUAs and FIMDs
Since IWRMP funded by the WB (refer to 3-4-1) has just rehabilitated the irrigation system in Kankai,
(Figure 4-2-1) further large scale rehabilitation is unnecessary except for the planned repair works of the
Irrigation Scheme in Terai
DOI, MOI 4-10
headwork next spring. FIMD gate operator keeps a record of the operation including cross-regulator,
opening of head-regulator, flow rate and water depth. A main committee, secondary canal level
committees and tertiary level committees are also organized by IWRMP and they are actively involved in
the activities. Meanwhile, sufficient water is not supplied to the downstream of the command area due to
excess water use at the upper stream. Additionally, plot to plot irrigation is common in the Kankai system
and therefore water use efficiency should be improved by enhancing on-farm distribution systems.
The problem caused by the natural conditions is inevitable. The river flow brings soils derived from weak
stratum in the upper stream of Terai region. The Kankai irrigation system has a settling basin which
facilitates removal of suspended soils before such soils enter into the canals, and this helps to reduce the
sediment load in the irrigation system. Such a facility is necessary for other irrigation systems and the
GON is expected to support them in the installation of such a facility.
Soil derived from the areas vulnerable to rainfall is likely to enter large scale irrigation systems, which
taking water from large rivers with the high volume of water flow. Such a large scale irrigation system is
assumed to have more sediment load to be removed than small scale irrigation systems. Large scale
irrigation facilities require not only advanced operation but also intensive desilting works and therefore
the GON and donors supports would be necessary.
A problem with water tightness of structures is mainly attributed to defective lining of canals in the
irrigation systems. Lining is particularly necessary for canals constructed in the foundation mainly
consisting of sand and gravel. Once lining is damaged and irrigation water seeps underground, shortage of
water in an irrigation system would be caused. Besides sluice gates would be collapsed, if water leakage
is caused around the gate and the leaked water washes out surrounding foundation.
Inaccurate operation of the facilities causes problems on the water allocation; especially on the equity of
water delivery in the command area (the tertiary and lower level canals). Other problems are usually
prioritized to be solved to ensure the water is reaching to facilities.
In order to address properly those problems arising from the aging of the irrigation facilities, the decisions
on the rehabilitation or updating should be made based on adequate technical knowledge and experiences.
Given that the facilities are still functioning despite aging, other more urgent issues can be prioritized to
the rehabilitation of such facilities.
The Machawar irrigation system is the only system which has difficulties in its operation of the facilities.
In case of pump irrigation, feasibility of projects should be examined in advance. Providing that the
situation has significantly changed since the pump irrigation is constructed, alternative plans should be
assessed for the irrigation system and/or selection of crops to be irrigated should be reviewed.
Problems on efficient water use can be divided into two major issues. One is that the downstream blocks
where water supply is often trouble are to be prioritized for water supply at the main canal level; the
upstream blocks should be received water later. This arrangement can secure equity of water allocation
within the irrigation system. Though the system in Chandra Nahar adopts this measure and distributes
water at the main canal level and each irrigation block, it does not fully implement due to malfunctioning
of irrigation facilities. The other irrigation systems are not implementing the above measure; thus, it
should be prioritized in such irrigation systems immediately. Another problem is inefficient use of
Data Collection Survey
4-11 JICA
supplied water which relates to the accurate operation of the facilities aiming at equity of water
distribution among the beneficiaries in the irrigation blocks. This issue will remain behind because there
would be other issues to be prioritized.
As mentioned above, an issue of irrigation systems in Terai region is how to improve function of overall
irrigation facilities but their bottlenecks differ individually. Thus, an operation and management plan for
the whole irrigation system should be developed firstly. The plan is expected to design with experts
having substantial experiences and sufficient knowledge and this enables the plan to assure its feasibility
and efficiency.
4-2-4 Maintenance
(1) Inspection and Maintenance
Periodical inspection is a basic requirement for the maintenance work for irrigation systems followed by
cleaning and repair. It is confirmed that inspection on headworks and pumps in the JMISs is usually
conducted after finishing irrigation period in spring, implementation of inspection on other facilities is not
recognized. This is mainly because cleaning is considered to be the most effective avoiding
malfunctioning of irrigation facilities due to circumstances of heavy sediments. Besides, other case shows
that maintenance works of aging irrigation pumps require much budget and workloads and therefore
would be bottlenecks of irrigation in such system.
Effective and equal water supply requires proper operation and control of irrigation facilities including
sluice gates. In fact, sediments in the canals are the biggest challenge for each irrigation system and the
cleaning of the canals would be fundamental for the operation and management as explained below:
(2) Cleaning
The major maintenance works undertaken by WUAs is the cleaning of canals. As part of their
responsibility, WUAs clean the canals whose management was handed over by the GON. In principle,
FIMD cleans the main canal and FIMD and WUAs jointly clean the secondary canals. Table below
illustrates the current status of cleaning of canals, which are carried out as part of the maintenance works,
in the JMISs
Table 4-2-8 Frequency of Canal Cleaning and its Record
Irrigation System
Main Canal Secondary Canal Tertiary CanalOrganization
in charge Frequency Record Organization in charge Frequency Record Organization
in charge Frequency Record
Kankai GON 1/year Yes GON 1/year Yes WUA 1-2/year Yes Kamala GON 1/year Yes GON 1/year Yes WUA 2/year Yes Hardinath GON 1/year Yes GON 1/year Yes WUA 2/year - Narayani GON 1/year Yes GON - - WUA - - Banganga GON - Yes GON - Yes WUA 2/year Yes Machawar WUA 1/year No WUA 1/year Yes WUA 1/year - Praganna Kulo
GON & WUA 2/year No WUA 2/year No WUA - No
Bagmati GON - Yes GON - Yes WUA - Yes Chandra Nahar
GON 1/year Yes GON 1/year Yes WUA - No
Source:Interview with JMIS based on questionnaire
The GON controls main and secondary canal level water use facilities and canals in Kamala, Bagmati and
Chandra Nahar and is also in charge of cleaning of those canals. While only the main canal is managed by
Irrigation Scheme in Terai
DOI, MOI 4-12
the GON in Kankai, Hardinath, Narayani and Banganga, it implements the cleaning of both the main and
secondary canals.
On the other hand, the WUAs in Machawar and Praganna Kulo implements cleaning of the main canals
which the GON is responsible for. Although details of responsibilities for management of the facilities
and cleaning of the canals are not studied, they should be clarified in advance for the smooth joint
operation. Actual responsibilities of the GON and WUAs should be identified for the further development
of JMIS. The following table summarizes a situation of the canal cleaning and its related problems.
Table 4-2-9 Status of Canal Cleaning Irrigation System
Current Status Problems
Kankai The main canal is cleaned (desilted and mowed) by the FIMD once a year but not in all the parts in accordance with a schedule. Work record is also taken. The secondary canals are cleaned by the FIMD once a year. The tertiary canals are cleaned by the respective WUAs (tertiary canal level WUAs) once or twice a year.
The WUAs do not have annual plan of cleaning. No record of cleaning has been taken, but it could be confirmed through the revision of the expenditure record.
Kamala Main works are desilting for the main, secondary and tertiary canals. The FIMD cleans the main and secondary canals timely once a year based on its observation. The WUAs contribute to the FIMD maintenance works of the secondary canals in kind. There are work records.
Extent of sedimentation is significant, and the amount of sediments is beyond the capacity of manual desilting, that is mechanical dredging is necessary. Various sizes of excavators are necessary in accordance with size of the canals.
Hardinath Main works are desilting. The FIMD implements desilting of the main canals once a year. The FIMD also clean the secondary canals once a year and the WUAs contribute to it in kind. Meanwhile, the WUAs implements desilting of the tertiary canals twice a year. Since the desilting by the FIMD is once a year, the WUAs have to desilt the main and secondary canals by themselves when the amount of sediments is large.
The desilting budget of the FIMD is not sufficient since extent of sedimentation is significant.
The WUAs need excavators due to large volume of sediments.
Narayani Main canal is not cleaned by the FIMD. Secondary canals are also not cleaned by WUAs.
Maintenance budget of the FIMD is not sufficient.
WUAs are inactive except for Blocks 2 and 8. Thus, the amount of ISF collected is little except for Blocks 2 and 8.
Banganga Main works are desilting. The cleaning is under the responsibility of the FIMD because no facilities are handed over to the WUAs. The main and secondary canals are cleaned by the FIMD. Some records are kept. However, the FIMD is not able to dredge 2 reservoirs filled with sediments. The tertiary canals are cleaned by the WUAs where the WUAs are active twice a year.
The FIMD does not have enough budget to clean up the tertiary canals.
Amount of collected ISF is not enough for cleaning the tertiary canals.
Machawar The pumps are maintained frequently by 4 operators, who were subject to trainings for pump maintenance: greasing, simple replacement of parts and fuses, etc. The pump operators get paid 50% from IDD and the other 50% from the WUA main committee. The main and secondary canals are cleaned by the WUA once a year before the monsoon season, and the tertiary canals twice a year before the monsoon and winter crop seasons
Maintenance costs of the pumps are high due to costs of grease and spare parts.
It is difficult to clean the brick-lined canal, which is not so strong and the surface is not smooth due to joints; excavators cannot be used unlike concrete-lining.
Data Collection Survey
4-13 JICA
Irrigation System
Current Status Problems
Praganna Kulo
The main canals are cleaned by the FIMD and the WUA twice a year before the monsoon season and winter crop seasons. The secondary canals are cleaned by the WUA twice a year before the monsoon and winter crop season. The WUA sometimes cleans the tertiary canals.
The system was developed by integrating various FMISs and the rain-fed farmlands which had existed in the area. The JMIS has been managed by adopting the traditional rules which the FMISs had established and applied. Under such rules, regular cleaning of canals is undertaken. When flooding, the FIMD closes intakes and prevents soil intrusion into the facilities, and this practice makes the cleaning easier.
Bagmati The main and secondary canals are cleaned by the FIMD once a year before the monsoon season. Tertiary canals are cleaned by the WUA where the WUAs are established twice a year in the case of GAR2.
The system is on the way of IMT process. The WUA main committee is not yet established. The secondary and tertiary level WUA committees are still under capacity building by the FIMD.
Chandra Nahar
The main and secondary canals are cleaned by the FIMD once a year. There are records. The tertiary canals (village channel) are cleaned by the WUAs.
The irrigation facilities need repair/rehabilitation rather than maintenance.
Source:WUA and FIMD
Due to heavy sediments, the desilting is beyond capacity of the WUAs in Kamala and Hardinath. As
aforementioned, the systems require facilities such as settling basin that removes suspended soil particles
before entering into the canals or introduction of excavators as the WUAs expect. Regarding the use of
excavators, the case in Machawar pointed out a difficulty in mechanical dredging due to the difference of
lining materials.
The Narayani case indicates a difficulty in collecting ISF from the areas where WUAs are inactive.
Though the facilities are deteriorated and their rehabilitation and maintenance are necessary, the WUA in
Banganga is well-functioning and implement the cleaning of the tertiary canals twice a year. This implies
that capacity development of WUAs is important to improve the performance of irrigation systems.
(3) Repair
According to JMIS, heavy desilting/dredging by excavators is often regarded as repair in Nepal, but there
is no clear definition. Repair works that WUAs can conduct by themselves are limited to DIY level. Such
repair works are small canal reshaping (small amount of earthwork). At the Machawar Lift Irrigation
System, there are pump operators who were trained for pump maintenance, but they are not able to repair
or replace the pumps. The WUA members are able to carry out repair works, but it must be done under
the instructions of the DOI technical staffs.
There are two funding sources to endure the rehabilitation costs. First, WUAs can outsource the
rehabilitation works with the disbursement from the collected ISF. Secondly, WUAs can request financial
support to DOI, especially when the rehabilitation works are too costly for them. However, it takes
usually a long time to go through the required procedure to receive the requested support, the use of the
ISF is more common on the ground.
4-2-5 Water Allocation
(1) Water Distribution Plan
Water distribution planning, irrigation schedule with rotation plans, are made by WUAs. However, WUAs
Irrigation Scheme in Terai
DOI, MOI 4-14
have expertise neither on crop water requirement nor water use efficiency although they are the decision
maker. Accordingly, FIMD supports WUAs to make irrigation schedules through advises and discussions
with them from technical point of view. In Chandra Nahar, the FIMD advises the WUA to preferentially
allocate water to downstream beneficiaries as aforementioned. Due to the dilapidated facilities, an overall
irrigation distribution system is not functional.
On the other hand, the irrigation schedule of the Machawar Lift Irrigation System is solely decided by the
WUA based on the discussion by respective representatives from 9 branches canals, because they know
discharge rates and conditions of the pumps. However, the schedule is only designed for equal water
distribution plan among the branches canals and the plans of individual branch canals within each WUA
are undeveloped.
Equitable water distribution results in increased collection of ISF and expansion of irrigated areas. Thus,
the DOI expects technical support for the preparation of an irrigation plan.
(2) Water Delivery
In JMIS, the government gate operators deliver water in accordance with the schedule by operating canal
structures in the portion under the FIMD’s responsibility, while WUA members operates the systems in
the portion under WUA’s responsibility. The government operators adjust the gate opening by calibrations
or counting the thread ridge of the spindle of sluice gate or by observing the water level gauge for the
rating curve or the depth of water flowing through the Partial flumes.
Figure 4-2-1 Sluice Gates of the Tertiary Canals in Kankai Source: Survey Team
On the other hand, there are usually no proper flow control structures, i.e. on-farm systems, in the
command area and WUA members are not able to manage water. Further, they operate sluice gates
without measuring the water discharge even if there are flow control structures. That is, water is not
delivered efficiently in the command area.
Figure 4-2-1 shows water intakes of the tertiary canals of the Kankai irrigation system. Thanks to
sedimentation basin at the beginning of the main canal, sand entering the irrigation facilities is limited and
therefore water is smoothly delivered to the main canal. Meanwhile, plans for operation of sluice gates at
the secondary and the tertiary canals are undeveloped and the water discharge is also not controlled.
4-2-6 Farming
The key for farmers to have motivation in agriculture is profitability. The farmers in Terai region is not
able to compete against Indian farmers who get subsidized plentifully by the government (Table 4-2-10).
Data Collection Survey
4-15 JICA
Fertilizer costs 1,000NPR/50kg in Nepal, while 384NPR/50kg in India. Diammonium phosphate (DAP)
costs 2,350NPR/50kg in Nepal, while 1,280 NPR/50kg in India. Tractor-plowing costs 1,600NPR/ha in
Nepal, while 1,000NPR/ha in India. Moreover, there is crop insurance in India but not in Nepal.
Table 4-2-10 Examples of Subsidy Comparisons between Nepal and India Item Nepal India
Fertilizer 1,000 NRs/50kg 384 NRs/50kg DAP 2,350 NRs/50kg 1,280 NRs/50kg Tractor-plowing 1,600 NRs/ha 1,000 NRs/ha Crop Insurance No Yes
Source:WUAs and DADO
Since the rice farming is not so profitable, most of households cultivate vegetables, maize, wheat, pulses,
sugarcane, oil seeds, aquaculture, etc. in winter and/or in spring. Rice is mainly for self-consumption in
such households. Most of households also have non-farm income by retail business, self-employment
(carpenter, plasterer, etc.), manual labor (construction, agriculture), working abroad (Middle East, India,
etc.).
Therefore, it is necessary to improve profitability of agriculture so that farmers are motivated to do
farming. In order to increase farm income, what is necessary are improvements of yield, cropping
intensity, product quality, marketing to sell higher price and/or cost reduction in farming. Two cropping is
very common in Terai region: monsoon rice and winter upland crops. But three cropping is not so
practiced, that is, the extension of year-round irrigation will enable three cropping so that farmers earn
more farm income.
Expansion of cultivated areas in winter and spring, particularly cultivation of cash crops, would directly
increase farmers’ income and generate a positive impact. Provided WUAs’ activities and proper water
distribution, irrigation water for the farming are available, capacity development of WUAs would
motivate farmers.
As Chapter 3 described, technical support for farming is also implemented by irrigation projects such as
IWRMP-AF (2013 to 2014) funded by WB and CMIASP-AF (2013 to 2018) funded by ADB and should
further approached in the context of water management and agriculture. MOAD and DOA administrate
agriculture projects. A trouble between officers of the DOI and the DOA is not reported in the project
areas of WB and ADB.
4-2-7 Identified Challenges
DOI engineers tend to focus more on main and secondary canals so as to improve irrigation efficiency.
This is because they recognize the main and secondary canals as fundamental facilities for O&M. The
larger irrigation systems are, the more important the canals are because more sediment from upper stream
of a river is entering into the facilities. In addition to operation of whole irrigation facilities, a problem
with desilting of heavy sediments makes the IMT difficult. This would be a main factor that JMIS as large
scale irrigation system is less successful while operation of the FMIS as small scale one goes smoothly
(Identified Challenge: Measures for Sediments).
The collection rate of ISF largely depends on the condition of facilities in the irrigation systems. There are
two most commonly observed cases as follows: 1) The maintenance of irrigation facilities is lagged
Irrigation Scheme in Terai
DOI, MOI 4-16
behind in the schedule, so that farmers cannot irrigate their farmland, when necessary. This results in
non-payment of ISF by farmers, and then the work again delays due to a shortage in the maintenance
budget. Thus, the irrigation system management falls into the vicious cycle; and 2) The preset ISF rate
may not be enough to cover the necessary maintenance costs, although the irrigation facilities are
well-maintained and the ISF collection rate remains high (Table 5-4-1). Regarding the former case, only
those farmers who have benefitted from enough irrigation water tend to pay ISF, but the overall ISF
collection in the JMIS is not working well. As for the latter case, the amount of ISF should be reviewed
by the WUAs for the sustainable irrigation management (Identified Challenge: ISF Collection).
Capacity development of the WUA members in the planning of O&M is necessary. There are too many
problems to be solved, and no one is able to prioritize all of them to address. Even the problems are
prioritized, they are not addressed in the priority order. For example, though WUA members should
appreciate the importance of the cleaning, it may be difficult for them to do so, due to the fact that
irrigation facilities are disabled and not functioning. Therefore, the rehabilitation of facilities by the GON
is necessary in order to promote members’ better understanding of O&M. In this regard, technical support
may be more feasible in the Kankai Irrigation System than any other irrigation systems, because their
facilities are functioning (Identified Challenge: O&M Planning).
The water management system which can improve on efficiency in water use and equity in water
distribution among the beneficiaries within the command areas (the tertiary and lower level canals) of
WUAs has not been established in many of the JMISs. In some JMISs where such a water management
system has been developed and applied, the system often does not work properly. Although farmers
understand the importance of on-farm irrigation systems in the command areas (the tertiary and lower
level canals), they often lack know-how of the water distribution based on the measurement of water
volume. Technical supports by DOI engineers are necessary for the establishment of irrigation system in
the command areas (the tertiary and lower level canals), although such supports are not available at
present (Identified Challenge: Equitable water distribution within the command areas of WUA).
Not all the DOI engineers acknowledge properly the importance of irrigation system within the command
area (the tertiary and lower level canals), although such terminal facilities are equally important as the
main and secondary canals are. They tend to focus only on the main and secondary canals. This implies
that an interface, connecting the main and secondary canals with on-farm irrigation systems, or with the
irrigation systems within the command areas (the tertiary and lower level canals) under the WUA’s
management is likely to have problems which disturb the efficient use of overall irrigation systems
(Identified Challenge: Technical assistance in the water management within the command areas of
WUA).
What improves farmers’ motivation on agriculture is an improvement on the profitability of farming, and
an improvement on productivity, cropping intensity and crop quality is part of the challenges identified to
this end. Besides, the collection of market information is necessary since it enables farmers to buy
agricultural inputs at lower prices and sell their produces at higher prices. The availability of year-round
irrigation may also work as one of the incentives for farmers to produce more. Thus, those interventions
for the irrigation sector shall ideally go in tandem with interventions for the agriculture sector (Identified
Challenge: Agricultural Development).
Data Collection Survey
4-17 JICA
An improvement on the efficiency of the entire irrigation systems may keep the current water delivery
systems efficient. If the systems are further developed and year-round irrigation becomes feasible, the
conditions for agricultural in Terai region would be improved significantly. The introduction of cash crops
could increase farmers’ household income, while the profitability of rice in the region is not high, because
of the low competency in the prices compared to the same commodity of the neighboring country, India.
Furthermore, the year-round irrigation would contribute to the DOI’s promotion of IMT (Identified
Challenge: Year-round irrigation).
4-3 FMIS
4-3-1 WUA
(1) Organization
In case of the FMIS, there is a WUA main committee but no lower level committees, because the system
is small. The WUA main committee is composed of representatives from areas instead of representatives
from lower level canals.
(2) Registration
All the WUA main committees are registered by application to the IDD. The WUA main committee has to
submit an audit report to an irrigation office so as to renew the registration.
(3) Constitution
All the registered WUAs have a written constitution. Since the FMISs are small community-based
irrigation system which have been managed by water users since before the government intervention. The
governing rules are still based on the traditional rules.
(4) Board Members
The board members (president, vice president, secretary and treasurer) are selected through election once
every two years but it is often vote of confidence.
(5) General Assembly
A general assembly is held once a year. In this regard, it will be held when needed, such as for emergency.
(6) Finance
Table 4-3-1 ISF and Its Collection Rate Irrigation System Amount Collection Rate
Buwa Gramin#1 3,000 Rs./ha/crop 90% Kalikoshi Collected only when necessary n.a.
Dudhmati Not yet collected. To be collected once the headwork upgrading is finished
n.a.
Jhimjhime #2 Not collected (Penalty charges only) n.a. Tamsariya (DTW conjunctive use) 200Rs./hour (No Pay, No Water) 100% #1 When a member attends a WUA activity such as canal cleaning, she or he gets paid 500 Rs. as daily pay. This is one of the
refund systems of ISF. #2 If a member does not attend to WUA activities such as canal cleaning, the person pay a fine of 6,000 Rs./ha. Some members
with small holdings do not attend to WUA activities intentionally and pay fine, which is small amount. Source: Interview to WUAs
The treasurer is in charge of finance. Collected ISF is kept by the WUAs because the system is fully
Irrigation Scheme in Terai
DOI, MOI 4-18
transferred to it. The WUA main committee has to prepare an audit report and submit it to the irrigation
office (FIMD or IDD) for the registration renewal. Financial status is also reported to its members at the
general assembly.
Table 4-3-1 above shows the amounts of ISF and the ISF collection rates of the studied FMISs. In some
systems the ISF collected at a fixed amount and the collection rates are as high as 90 or 100%, while in
other systems, the ISF is collected only when necessary. Thus, the collection rates of FMISs significantly
differ from the ones of JMISs.
(7) Information transfer from the WUA main committee to its members
The following means are used for information transfer from the WUA main committee to its members:
Verbal messages, including the conversation on cell phones, from the main committee members to the lower level canal WUAs; and
FM radio.
4-3-2 Irrigation Facilities
(1) Conditions of the Irrigation Facilities
Conditions of the irrigation facilities are summarized in the table below. The construction firstly targets
on headwork, followed by a main canal (Table 4-3-2). On-farm irrigation systems are not targeted for
infrastructure improvement.
Table 4-3-2 Irrigation Facilities of FMISs Visited Irrigation System Status
Buwa Gramin Main canal is kept in good condition. There is neither headwork nor secondary canals. Kalikoshi The WUA is building facilities by little and little, getting technical assistance from the IDD.Dudhmati The headwork is under construction by CMIASP-AF. The earthen weir is upgraded to
concrete one. The main canal is not upgraded because the benefit-cost ratio is lower than other candidate systems.
Itiyakulo The headwork is relocated to upstream by 150m because the riverbed is eroded and river water level lowered.
Jhimjhime The headwork is under upgrading. The main canal in the upstream portion is flume. Tamsariya (DTW conjunctive use)
There are 4 DTWs in 6 areas. The systems are handed over to the WUA just 3 months ago. It is a conjunctive use system where groundwater is used supplementary, except for Area 6. The surface water irrigation systems mainly used is a traditional one.
Source:WUA
4-3-3 Maintenance
(1) Cleaning
The WUAs of FMISs traditionally know the importance of facilities and share a common understanding
of operation and management in the systems. In this regard, the WUAs in the JMIS should start from the
planning and is behind in the irrigation management (Table 4-3-3).
Data Collection Survey
4-19 JICA
Table 4-3-3 Canal Cleaning Irrigation System Status
Buwa Gramin The WUA assigns cleaning works of the main canal to groups (villages) in the system. No record is taken.
Kalikoshi The WUA cleans canals twice a year before monsoon and winter crop seasons. No record is taken.
Dudhmati The WUA has not yet started activities. After completion of the headwork construction, it will join IDD’s trainings and then begin activities.
Jhimjhime The WUA cleans three times a year before monsoon, winter and spring crop seasons. The cleaning takes 2 to 3 days by 3 groups of the WUA members.
Tamsariya (DTW conjunctive use)
Since water is clean and it flows in the pipelines from DTWs, no cleaning is needed.
Source:WUA
(2) Repair
As for repair works that need cement, unlike routine maintenance, the WUAs implement them under
technical and financial supports of IDD/IDSD. General cleaning of the canals is done by the WUAs.
4-3-4 Water Allocation
(1) Water Distribution Plan
1) Surface Water Irrigation System
The WUA main committee makes an allocation plan and an irrigation schedule. The committee
members take the plan and the schedule back to her/his area and report to the members.
2) Groundwater Irrigation System in Tamsariya
The users make a phone call to the pump operator in charge and order the timing and the duration of
water delivery. The ISF is not collected on a basis of area but on a basis of time. The WUA members
strictly follow the no-payment-no-water rule.
(2) Water Delivery
The WUA members operate the irrigation facilities by themselves. Even the DTWs are operated by the
farmers trained by GWID staffs in Tamsariya.
4-3-5 Identified Challenges
Compared to the WUAs of JMIS, the WUAs of FMIS are working smoothly with less strict rules. They
collect ISF by following their traditional rules, and they do not need more strict rules. The FMISs have
been managed by their water users before the GON started the management of irrigation systems, and
therefore, the GON does not see the necessity to strengthen the management of FMISs although it
provides FMISs with the initial training and the government portion of the rehabilitation costs. DOI does
not recognize so far any challenge of the management of FMISs to be addressed.
Data Collection Survey
5-1 JICA
Chapter 5 Problems of Irrigation Development and Challenges Extracted through the Survey
This chapter presents considerations regarding problems, challenges and orientation of improvement of
irrigation development by GON, on the basis of results of the workshop on 14 August 2016, in which DOI
staff participated, and results of existing irrigation facilities and other donors’ assistance programs
considered in the antecedent chapters. Then, it considers relevance of the GON’s application for JICA-TCP,
in terms of its objectives, contents and inputs, from the viewpoint how the JICA-TCP contributes to solving
problems and challenges on irrigation development of Nepal.
5-1 Challenges Identified in the Field
As mentioned in Chapter 4, challenges identified through field visits of JMISs are as follows:
Challenge #1: Countermeasures against sediments;
Challenge #2: ISF collection;
Challenge #3: Formulation of maintenance plan;
Challenge #4: Equitable water distribution within the on-farm area;
Challenge #5: Technical assistance for on-farm water management;
Challenge #6: Improvement of farming; and
Challenge #7: Year-round irrigation.
5-2 Problem and Objective Analyses in the Workshop
As the preparatory works for the workshop on 14 August, the Survey team narrowed challenges identified
through the report of “Preparatory Survey on JICA’s Cooperation Program for Agriculture and Rural
Development in Nepal -Food Production and Agriculture in Terai- (2013)” down to those related to O&M
of irrigation facilities, water management and capacity strengthening of DOI staff and WUA members. In
the workshop, DOI staff analyzed causes of irrigation development problems (Problem Analysis). In
addition, the Survey team pointed out problems of irrigation in the on-farm area where WUA is responsible
for water management, as well as problems regarding major facilities. The summary is as follows.
1) Water is not available enough for winter and spring cultivation from seasonal rivers. In addition,
Narayani Irrigation System does not receive water from the perennial river, which is its water source,
because India does not have to give water to Nepal based on the international treaty24 between Nepal
and India.
2) There are irrigation systems that are not able to convey designed discharge due to
disabled/malfunctioning canal structures (e.g. cross- and head-regulators), or canal cross-section
reduced by erosion/scouring/collapse of side slope or sediments.
3) Seepage loss of water from unlined canals is larger in the dry season (winter and spring) than in the
rainy season (monsoon) because soils are drier.
4) Water is not distributed equitably among water users in the on-farm area. Allocated water is limited
and water users in the upstream zone over-irrigate. Consequently, water shortage occurs in the
downstream zone.
24 Water rights of India and Nepal are 90% and 10% respectively, in accordance with the international treaty.
Irrigation Scheme in Terai
DOI, MOI 5-2
5) Water is not efficiently delivered and/or utilized even if water is available. Since the plot-to-plot
irrigation is widely practiced in the on-farm area, the application efficiency is low.
6) There are no drainage systems in the on-farm area, or they are malfunctioning even if they exist.
The workshop participants arranged the narrowed-down challenges and the above causes in a problem
diagram. Then, they re-arranged the problem diagram to an objective diagram which shows possible
countermeasures to solve the problems. The proposed core objective of the objective diagram was
“Maximize irrigated area through the optimization of irrigation water distribution based on agreement and
mutual understanding among stakeholders”, but the workshop participants changed the core objective to
“Optimize water use for reliable year-round irrigation”. That is to say, the orientation to improve the
current irrigation state in Terai region has been changed from “expansion of irrigated area” to “reliable
year-round irrigation”.
Figure 5-2-1 is the objective diagram formulated through discussion by the participants. The figure shows
the overall goal on the leftmost side, and means to attain it are developed to the right-hand side. In
addition, it shows the applicability to FMIS and JMIS as well as possibility of implementation/assistance
by GON, WUAs, donors and NGOs as a matrix: the code “Y” indicates “applicable”.
In order to optimize water use for reliable year-round irrigation, the participants pointed out the necessity
of capacity building of DOI staff and beneficiary farmers, improvement of O&M and construction
including rehabilitation of existing facilities. Since the construction most likely becomes out of scope of
the JICA-TCP, the following explains the other two necessities.
Capacity Building: it is necessary to strengthen the functions and roles of IMD, inclusive of its
review, so that IMD is able to give technical assistance and advices to DOI field staff and farmers
and also to make stronger cooperative relationship with them25.
O&M26: possible activities are the calculation of crop water requirements as well as irrigation
requirements based on such crop water requirements, the formulation of water allocation plan
based on available water volume and an improvement of water management by both GON and
WUAs27.
5-3 Challenges and Countermeasures Based on Field Survey and Workshop
Challenges recognized through field surveys and pointed out in the workshop are tabulated in Table 5-3-1
item by item. There are 9 items and they are: (a) Implementation of O&M; (b) Diversification of water
sources; (c) Construction of irrigation facilities; (d) ISF Collection; (e) Maintenance Plan; (f)
Organizational management; (g) Technical assistance in water management; (h) Agriculture; and (i)
25 Trainings that IMD conducts for WUA members are demand-basis, that is, DOI gives them trainings that they request. Training that they
request are supposed to be on-farm water distribution, water distribution in the farm plot including crop water management, ISF collection
method, etc. 26 The O&M here means not only the operation and maintenance of irrigation facilities but also the water management in the Irrigation
Systems. 27 In a JMIS, FIMD (DOI) estimates the crop water requirement and the demand of irrigation water and explains them to the WUAs, so that the
WUAs and FIMD can reach an agreement through discussion. In accordance with the agreement, FIMD should deliver the water to the WUAs. In
the areas managed by the WUAs, the water is distributed in accordance with the estimate made by FIMD, due to the technical constraints of the
WUAs. For the Kankai Irrigation System, the IWRMP consultants employed by WB developed a computer program to calculate water
requirement for each crop and the demand of irrigation water. FIMD in charge of the Irrigation System calculates the water requirement by
utilizing the computer program.
Data Collection Survey
5-3 JICA
Expansion of irrigation services. As for the first 3 items ((a), (b) and (c)), it is assumed that GON will take
care of them, while for the remaining 6 items ((d), (e), (f), (g), (h) and (i)), there is a possibility to be
addressed through the implementation of the JICA-TCP.
The primordial precondition for the target areas for the JICA-TCP is that the irrigate facilities are
functioning and to make this precondition meets, whether the amount of ISF is appropriate or not would
be a possible challenge. It is confirmed that in those irrigation systems where the facilities are constructed
and maintained, the ISF collection rates are high, yet the amount of ISF is still lower (0.2 to 0.6%. Refer
to 5-4-2 Pilot Project Site of JICA-TCP) than the cases in other countries as a fact (3 to 4% in the
Philippines and Myanmar). It is recommended to set an appropriate amount so as to put a sustainable
maintenance mechanism of the irrigation system in place.
The development of a maintenance plan is necessary to take stock of all the facilities, including those at
the plot level, within the command areas of WUAs, and may be in a high priority for WUAs, although its
priority cannot be high for individual water users. On the other hand, those individual water users put a
high priority in the technical assistance in the water management, since techniques to make water reach
each beneficiary will be acquired by addressing this item. The organizational management and agriculture
are the items prioritized following to the technical assistance in the water management.
Irrigation Scheme in Terai
DOI, MOI 5-4
Figure 5-2-1 Objective Analysis and Countermeasures & Activities for Irrigation Improvement Source: Survey team
(5) Capacity enhancement of
IMD staff and other DOI staff
through workshops and field
training.
Y N
(12) Construction of drainage
facilities
(33) Establishment/improvement of drainage
systems for the medium/large scale projects in
plain area.
Y Y Y Y Y Y
N
N
N
(27) Introduction of new technology for
increasing irrigation efficiencyY Y Y Y Y Y N
(10) Enhancement of technical
support to DOI field staff and
WUAs for water management
(26) Improvement of on-farm irrigation system
(34) Enhancement of construction of on-farm
irrigation and drainage systemY Y Y Y Y Y Y
Y Y Y Y
N
Y Y N
STW: Shallow Tube Well
IMD:Irrigation management Division
ISF:: Irrigation Service Fee
DTW: Deep Tube Well
Y
(32) Construction of water-regulating structures Y Y Y Y Y
YY
Y N
(31) Introduction of new technology for
increasing irrigation efficiencyY Y Y Y Y Y
(30) Construction of on-farm irrigation system
Construction (4) Construction of irrigation and
drainage infrastructure
(11) Construction of irrigation
facilities
(29) Newly installation of tube-well as water
source.Y Y Y Y
(28) Maintenance of water-regulating structures Y Y Y Y
Y Y Y Y Y Y
(25) Change the mind set of farmers regarding
irrigation water as economic commodityY Y N Y N
(24) Establishment/update of asset management
of irrigation facilities.Y Y Y Y Y Y N
N N
N N Y
(23) Enhancement of improvement of ISF
collection mechanism, including periodical
auditing system.
Y Y Y Y Y Y Y
(17), (18) & (20): Utilization of
groundwater will be out of scope, if
surface water is sufficiently available. (9) Improvement of concept on
tariff management for ISF.
(22) Improvement of concept on application of
fine clauses to violators of WUA member.Y Y Y Y
[ NOTE ] (21) Maintenance (dredging) of existing
reservoirs as water sourceN Y Y Y
(20) Maintenance of existing DTWs & STWs Y Y Y Y Y Y N
Y Y N
Y Y Y N N
(1)Optimize water use for
reliable year-round irrigation. (19) Use of reservoirs Y Y Y Y Y N N
Operation and
Maintenance(3) Improvement/ preparation of
water management plan based
on crop water requirement,
irrigation demand and water
availability
(8) Enhancement of conjunctive
use with groundwater and
existing reservoirs/ponds.
(17) Use of dug wells & ponds Y N
Y Y
(16) Capacity enhancement of IMD and other
DOI field staff on technical support to WUAs for
on-farm irrigation water management through
workshops and field training.
Y Y Y N Y Y N
Y Y Y N N
(18) Use of STWs & DTWs Y Y
Y N Y N
Y Y Y
(7) Enhancement of on-farm
irrigation managemnet capability
(15) Enhancement of technical support for on-
farm irrigation water management to WUAs
through workshops and field training.
Y Y Y Y Y
(14) Capacity enhancement of water users for
organizational operation of WUA through
workshops and field training.
Y Y Y Y
Causes that year -round irrigation does not expand are:[1] Surface water is not available enough for cultivation in winter and spring → Possible solutions: (18) (29)[2] Inequity on water distribution amomg WUA members → Possible solutions: (12) (14)[3] Farmers make lands fallow → Possible solutions: n.a.[4] Water is available but its delivery and/or utilization are not efficient → Possible solutions: (13) (14) (15) (16) (17) (19) (22) (23) (25)[5] Lack of water control facilities at the on-farm level → Possible solutions: (29) (30) (31) (32) (27)[6] Malfunctioning and/or disabled irrigation facilities → Possible solutions: (20) (21) (26) (27) (28) (31) (32)[7] Seepage loss from unlined canals → Possible solutions: canal lining
(6) Capacity building of
organizational operation for
WUAs
Construction/ rehabilitation to beout of scope of JICA'scooperation
NGO
Capacity Building (2) Improvement of roles and
functions of IMD to provide
technical support /advices and
strengthening of linkage among
all stakeholders
(12) Providing countermeasures through
identifying the reasons why the farmers do not
follow rules for regular monitoring plan on
irrigation system.
Y Y Y Y Y
FMIS JMISGON/DOI
WUADonor(Fin)
Donor(Tech)
N N
(13) Development/updating of Canal
Maintenance Plan & Canal Operation PlanY Y Y
Data Collection Survey
5-5 JICA
Table 5-3-1 Challenges Identified through Field Visits, Challenges Recognized in the Workshop and Possible Countermeasures
Item Challenges identified through field visits
Challenges recognized in the workshop Possible countermeasures
(a) Implementation of O&M
1) Countermeasures against sediments
20) Maintenance of existing DTWs & STWs 21) Maintenance (dredging) of existing reservoirs as water source 28) Maintenance of water-regulating structures
Profound upgrading of water intake facilities of JMIS, including construction of settling basin, except for Kankai Irrigation System
(b) Diversification of water sources
17) Use of dug wells & ponds 18) Use of STWs & DTWs 19) Use of reservoirs 29) Newly installation of tube-well as water source.
Construction after investigating possibilities of new water sources
(c) Construction of irrigation facilities
30) Construction of on-farm irrigation system 31) Introduction of new technology for increasing irrigation efficiency 32) Construction of water-regulating structures 33) Establishment/improvement of drainage systems for the medium/large
scale projects 34) Enhancement of construction of on-farm irrigation and drainage system
Construction by GON and construction of some on-farm irrigation facilities by JICA-TCP
(d) ISF Collection
2) ISF Collection 22) Improvement of concept on application of fine clauses to violators of WUA member.
23) Enhancement of improvement of ISF collection mechanism, including periodical auditing system
25) Change the mind set of farmers regarding irrigation water as economic commodity
The implementation is possible within the framework of JICA-TCP. However, it may be difficult to get an agreement from those farmers who have never benefitted from the irrigation water. The proportion of ISF to the gross income per unit area is lower than that in similar cases in other countries.
(e) Maintenance Plan
3) Formulation of maintenance plan
12) Providing countermeasures through identifying the reasons why the farmers do not follow rules for regular monitoring plan on irrigation system.
13) Development/updating of Canal Maintenance Plan & Canal Operation Plan24) Establishment/update of asset management of irrigation facilities.
Implementation of Technical Cooperation
(f) Organizational management
14) Capacity enhancement of water users for organizational operation of WUA through workshops and field training.
Implementation of Technical Cooperation
Irrigation Scheme in Terai
DOI, MOI 5-6
Item Challenges identified through field visits
Challenges recognized in the workshop Possible countermeasures
(g) Technical assistance in water management
4) Equitable water distribution within the on-farm area, which is the area where WUA manages water
5) Technical assistance for water management within the on-farm area (on-farm water management)
15) Enhancement of technical support for on-farm irrigation water management to WUAs through workshops and field training.
16) Capacity enhancement of IMD and other DOI field staff on technical support to WUAs for on-farm irrigation water management through workshops and field training.
26) Improvement of on-farm irrigation system (facilities and water management)
27) Introduction of new technology for increasing irrigation efficiency
Implementation of Technical Cooperation
(h) Agriculture 6) Improvement of Farming Implementation of Technical Cooperation (i) Expansion of
the Irrigation Service
7) Year-round irrigation 1) Optimize water use for reliable year-round irrigation. This is the goal when all of the above countermeasures are completed.
Note: The numbers of item listed in the column of “Challenges identified through field visits” are consistent with those put to the challenges listed in Section 5-1 “Challenges Identified in the Field”. The numbers of item shown in the column of “Challenges recognized in the workshop” are consistent with those put to the countermeasures proposed in Figure 5-2-1 to each of the challenges identified in the workshop. Source: Survey team
Data Collection Survey
5-7 JICA
5-4 Targets of Technical Cooperation and Possible Activities
As summarized in Table 5-3-1, the 5 items, which are ISF collection, maintenance plan, organizational
operation and technical assistance of maintenance, can be possible activities of JICA-TCP. Then, the
prerequisite to be candidate sites of the JICA-TCP is existence of irrigation systems where fundamental
canal structures and irrigation facilities are functioning. The examination and concrete challenges of
JICA-TCP candidate JMISs are presented below.
5-4-1 Candidate Irrigation Systems (JMISs)
The workshop participants have nominated the following 5 irrigation systems for the JICA-TCP pilot
project: Chandra Nahar, Bagmati, Bhairahawa Lumbini Groundwater, Praganna Kulo and Patharaiya.
Meanwhile, the irrigation system that IMD recommends is Kankai irrigation system.
Table 5-4-2 tabulates the current states of those 6 irrigation systems, including Kankai, in terms of
hardware and software. In addition, Table 5-4-3 summarizes history and challenges of each irrigation
system. Here, it is reasonable to remove Bhairahawa Lumbini Groundwater and Patharaiya from the
JICA-TCP candidate sites because of the following reasons.
1) Bhairahawa Lumbini Groundwater Irrigation System
This is the pumping irrigation system whose water source is DTWs. Some pumps are needed to be
replaced. JICA-TCP should target surface water irrigation systems that DOI puts higher priority than
groundwater ones.
2) Patharaiya Irrigation System
This requires a major rehabilitation/upgrade of the entire system, that is, irrigation facilities from the
headworks, through the main, secondary and tertiary canals to on-farm irrigation systems at the tail. It
would require a significant amount of finance and 3 -5 years for the construction works.
Now, there are 4 candidate sites remaining: Kankai, Chandra Nahar, Bagmati and Praganna Kulo. The
water sources of these 4 systems are perennial rivers. Namely, water is available even in the dry season. It
is reasonable to select the pilot project site from these 4 systems. As for these 4 systems, the Survey team
gave scores to those 4 systems in terms of necessity of rehabilitation, water source, possibility of
irrigation during the dry season, number of canals and ISF collection rate. As a result, Kankai and
Bagmati have got high scores followed by Chandra Nahar and Praganna Kulo (Table 5-4-4).
5-4-2 Pilot Project Site of JICA-TCP
Irrigation systems that JICA-TCP should target were identified to be Kankai, Chandra Nahar, Bagmati
and Praganna Kulo. In accordance with scoring shown in Table 5-4-4, Kankai and Bagmati have higher
priority than the other two systems. The table below shows outlines of these 4 systems. The command
areas of Kankai and Bagmati are 8,000ha and 45,600ha respectively, and the beneficiary households of
Kankai and Bagmati are approximately 11,000 and 32,600. In addition, the average farm-holding sizes of
Kankai and Bagmati are very different. Whereas the former is 0.73ha, the latter is 1.40ha.
Irrigation Scheme in Terai
DOI, MOI 5-8
Table 5-4-1 Specifications of Candidate Sites of Pilot Project
Item Irrigation System Kankai Chandra Nahar Bagmati Praganna Kulo
Main Canal Nos. 1 1 2 5#1 Length (km) 36 31 48.2 56
Secondary Canal Nos. 22 12 6 - Length (km) 74 43 112 150
Tertiary Canal Nos. 287 237 21 - Length (km) 110 31 122.4 71
Irrigation Area (ha) 7,000 Irrigable area (rainy season)
10,000 Irrigable area (rainy season)
37,600 Command
Area
5,800 Irrigable area (rainy season)
Beneficiary Households 11,000 30,000 27,000 3,900 Avg. Holding Size (ha) 0.64 0.33 1.40 1.50 ISF (a) Rs/ha/crop 300Rs/0.66ha n.a. n.a. n.a. Rs/ha/year (a) n.a. n.a. 600 600 Monsoon Paddy (MS)
Yield(t/ha) 3.8 3.6 4.5 3.4
Farm gate price (Rs/kg)
25 22 Self- consumption
20
Income (Rs) (b) 95,000 79,200 99,000 68,000 (a)/(b) for the MS % 0.3 0.2#2 0.6 0.49
#1 Including canals from seasonal rivers #2 Assuming 60 Rs./ha/crop (ISF of 3 years ago) Source: IMD and DOI
5-4-3 Current State of Candidate Irrigation Systems
Tables 5-4-5 and 5-4-6 show challenges and countermeasures of Kankai and Bagmati Irrigation Systems,
which are prioritized candidate sites. The targets of technical cooperation are 1) DOI engineers, including
FIMD staff and 2) WUA members. Meanwhile, the following are recognized as contents that should be
implemented in technical cooperation: efficient water management plan and implementation of on-farm
water management. Most farm plots are delivered water by plot-to-plot irrigation, but a watercourse was
found in Bagmati, where a pipe is installed between the tertiary canal and the watercourse so that water
flows into the watercourse (Figure 5-4-3). Since the watercourse enables water users to irrigate farm plots
respectively, the irrigation efficiency is improved. It is recommended that FIMD staff disseminates this
practice. In addition, it is confirmed that WUA members are willing to pay ISF.
Figure 5-4-1 Tertiary canal and PVC pipe to take water off to the watercourse (left) and watercourse (right) in Bagmati
Source: Survey team
PVC pipeTertiary canal
Watercourse
Data Collection Survey
5-9 JICA
Table 5-4-2 Current States of Hardware and Software of Candidate Irrigation Systems
Candidate Irrigation System
Hardware (Y: Necessary, N: Not necessary) Necessity of Improvement
Software (Y: Necessary, N: Not necessary) Necessity of Improvement
Remarks Headworks &
Main Canals
Branch/ Secondary
Canals
Tertiary canals & On-farm Systems
Headworks &
Main Canals
Branch/ Secondary
Canals
Tertiary canals & On-farm Systems
Kankai N#1 N Y#2 Y Y Y #1: The Maintenance of weir has been already scheduled. #2: Field ditches are necessary to be made
Chandra Nahar N N Y Y Y Y GON shoulders the maintenance costs of main canals, branch canals and other hardware.
Bagmati N N Y Y Y Y GON shoulders the maintenance costs of main canals, branch canals and other hardware.
Praganna Kulo N N Y Y Y Y GON implements the maintenance of main canals, branch canals and other hardware.
Bhairahawa Lumbini Groundwater Y N N Y Y Y Some pumps need to be replaced.
Patharaiya Y Y Y Y Y Y GON shoulders the maintenance costs of main canals, branch canals and other hardware.
Source: IMD and field visit survey
Table 5-4-3 Outlines of Candidate Irrigation Systems Candidate
Irrigation System Outline
Kankai
It was designed by a Japanese consulting company in 1970s, and rehabilitated by IWRMP. There is a settling basin built between the diversion on Kankai river and the intake of the main canal. The length of the main canal is 36km, of which 11.5km is concrete-lined. The WUA has been reorganized by IWRMP. The crop water requirement is estimated by the Penman-Monteith method so as to decide the irrigation requirement. It is an irrigation system for spring rice cultivation. Therefore, Kankai-system farmers are not as active in vegetable cultivation as farmers of other irrigation systems.
Chandra Nahar
It was constructed nearly 100 years ago. Since then, no major rehabilitation was implemented. Some facilities are disabled and DOI is carrying on rehabilitation. WUAs have been established from the main-canal level to the tertiary-canal level. The WUA main committee has cadasters and design drawings. No irrigation facilities are handed over to WUA at present because the facilities are dilapidated and needs rehabilitation and WUA does not agree.
Bagmati
It is possible to operate the barrage during the blackout because there is a generator in case of emergency. Canal structures such as cross-regulators are under rehabilitation, supported by Saudi Funds for Development (SFD). FIMD is currently carrying on IMT while rehabilitating canal structures as well as developing its command areas. Tertiary-canal-level WUAs are established where the command area has been developed, and the establishment of secondary-canal-level WUAs is in progress.
Irrigation Scheme in Terai
DOI, MOI 5-10
Candidate Irrigation System Outline
Praganna Kulo
It is located on the right-bank side of Rapti river at the foot of the Hill area of Nepal. There are significant sediments on the river bed. The river is perennial and 300m wide at the location. Neither diversion dam nor barrage is built. There are 3 side intakes on the right riverbank, and each side intake has a main canal. The irrigable area is 5,800ha. The 1st, 2nd and 3rd intakes irrigate 500ha, 4,400ha and 900ha, respectively. In addition, there are 2 more main canals which take water at 2 weirs on 2 seasonal rivers in the command area. Each main canal of the aforementioned 3 main canals has WUA main committee, and there is a WUA joint committee in order to coordinate those 3 WUAs. DOI/FIMD is responsible for O&M of side intakes and main canals as well as channeling the riverbed by excavator so that river water flows to the side intakes. The system used to be 3 FMISs that are more than 100 years old, and DOI developed them to the larger irrigation systems. The joint management has begun since 2005. In this regard, the WUAs are still operated by their traditional rules. Actually, it is an aggregation of 3 different irrigation sub-systems. Therefore, JICA-TCP will have to pay attention to all of the 3 sub-systems so that economic disparity of farm households among the 3 sub-systems does not enlarge, if JICA-TCP targets Praganna Kulo Irrigation System. The WUA joint committee does not mean unification of the 3 WUAs.
Bhairahawa Lumbini Groundwater
It is a groundwater irrigation system in Rupandehi district. The 22-year construction works ends in 1999, and 181 DTWs are built. However, 12 DTWs out of 181 are now inactive. The remaining 169 DTWs irrigate 20,309ha, but some of them are necessary to be replaced. The groundwater-pumping irrigation is significant affected by electric supply: pumps do not work during blackout. Not only Rupandehi district but also nationwide districts are suffering from blackout of nearly 12 hours per day. Even if electricity is supplied, the voltage is lower than standard because demand is high and exceeds supply. Consequently, the operation efficiency of pumps is not good.
Patharaiya It is necessary to rehabilitate headworks, main canals, secondary canals, tertiary canals and lower level canals. Rehabilitation of these facilities must be finished till the soft component focusing on on-farm water management begins
Source: IMD and field visit surveys
Table 5-4-4 Scoring to Select Irrigation Systems for JICA-TCP
Irrigation System (See the figure below)
a. Necessity of rehabilitation b. Water source
c. Water intake during the dry
season
d. Number of main canals and WUAs
e. ISF collection state TOTAL
Kankai 5 5 5 5 5 25 Chandra Nahar 3 5 5 5 1 19 Bagmati 5 5 5 3 5 23 Praganna Kulo#2 5 5 3 2 3 18 Bhairahawa Lumbini Groundwater #1
0 0 5 0 5 10
Patharaiya#3 0 5 5 n.a. n.a. 10 Source: Survey team
Data Collection Survey
5-11 JICA
Scoring a. Necessity of rehabilitation: Less (5 pts.) ↔More (0 pts.) b. Surface water (5 pts.), Groundwater (0 pts.) c. Groundwater (5 pts.), Perennial river (4 pts.), Reservoir (3
pts.), Seasonal river (0 pts.) d. 1 main canal & 1 WUA (5 pts.), 2 main canals and 2 WUAs,
each on the right and left bank sides (3 pts.), 3 main canals and 3 WUAs (2 pts.)
e. Collection rate: Higher (5 pts.) ↔Lower (0 pts.)
#1 There are 64 main canals. ISF collection rate is assumed very high because it is a pumping irrigation system.
#2 ISF collection rate is supposed around 50% based on interview to Chief Divisional Engineer of the system.
#3 Detailed information was not available.
Irrigation Scheme in Terai
DOI, MOI 5-12
Table 5-4-5 Challenges and Possible Activities in Kankai Irrigation Systems # Current Challenges Possible Activities in JICA-TCP Targets Expected Outcomes1 A There is no maintenance plan of
headworks, main canal and secondary canals
Support that FIMD formulates maintenance plan, rehabilitation plans (incl. periodic inspection) of water intake and conveyance facilities as well as budget plan to implement them.
FIMD staff Other DOI staff
It is able to know facilities to be managed, and Maintenance is carried out timely and properly, and it
is possible to avoid becoming malfunctioning due to lack of budget.
2 A There is no maintenance plan of
tertiary canals Support that WUAs formulate maintenance
plan, rehabilitation plans of on-farm irrigation facilities as well as budget plan to implement them
WUA members FIMD and other
DOI staff (Training of Trainers: ToT)
It is able to know facilities to be managed, and WUA becomes able to maintain on-farm facilities
timely and properly, without relying on GON.
3 A Tail-end farmers in the on-farm area
do not receive water because upstream farmers take water more than allocated volume.
Support irrigation practice by rotation such as irrigating from the tail-end plot towards upstream and cropping, and
Give guidance on reviewing proper irrigation requirement.
WUA members FIMD and other
DOI staff (ToT)
Equitable irrigation is practiced in the on-farm area, The amount of ISF collected increases, and Irrigated area in the spring crop season increases.
4 B Since the farm plot surface is uneven.
Such plot needs extra water. Implement leveling of farm plots (implement
in demonstration plot.) WUA members DADO and DOA
staff (ToT)
Water use efficiency in the on-farm area is improved, and then irrigated area increases particularly in the spring crop season.
5 B Since the plot-to-plot irrigation is the
dominant practice, extra irrigation water is needed and, at the same time, drainage problems take place.
Develop watercourses and farm ditches in the on-farm area so that each plot receives water from watercourses/farm ditches.
WUA members FIMD and other
DOI staff (ToT)
Water use efficiency in the on-farm area is improved, and then irrigated area increases particularly in the spring crop season, and
Farm plots with drainage problems decease. 6 C WUA members hope for technical
trainings of rice cultivation, but DOA has not yet tackled it.
Demonstrate paddy cultivation, Give training of fertilizer application level and
methods, and Give training of seed production.
WUA members DADO and DOA
staffs(ToT)
Water use for low-land paddy cultivation is improved, Since fertilizer is costly, farmers can reduce the
production costs by learning how to use fertilizer properly, and
It is expected that quality seeds make yields increase.
7 C The ISF collection rate is 70% at
present, and the WUA seek to raise the collection rate and the fee. However, the decrease of the collection rate is feared due to raise in fee.
Give guidance on proper ISF (money amount), how to calculate it and how to charge it, and
Support formulation of a reporting system of maintenance plan, the amount of ISF collected and expense to WUA members.
WUA members FIMD and other
DOI staff (ToT)
WUAs stop relying on GON for costs of WUA activities (operation, maintenance and management) and,
The revenue of WUA becomes stable because the feeling of unfairness on charging ISF decreases within WUA.
#) A: Most Important, B: Important, C: As necessary
Source: Survey team
Data Collection Survey
5-13 JICA
Table 5-4-6 Challenges and Possible Activities in Bagmati Irrigation Systems (Hearing from the GAR2 Tertiary-canal-level WUA) # Current Challenges Possible Activities in JICA-TCP Targets Expected Outcomes1 A There is neither maintenance plan nor
rehabilitation plan of on-farm irrigation facilities.
Support that WUAs formulate maintenance plan, rehabilitation plans of on-farm irrigation facilities,
Support financial resource planning to implement the above plans, and
Support formulation of recording system of implementation and reporting system.
WUA members DOI officers
including the FIMD officers (TOT)
WUA becomes able to maintain on-farm facilities timely and properly, without relying on GON, and
The reliability of irrigation becomes better.
2 A Peon (employee of WUA), who distribute
water in the on-farm area, measures nothing on water delivery, and also takes no record of water delivery.
Give guidance to Peon so that he is able to give proper amount of water to each plot, and
Support that farmers gain knowledge about proper amount of irrigation water so that they do not instruct Peon to over-irrigate.
WUA members FIMD and other
DOI staff (ToT)
Water use efficiency in the on-farm area is improved and,
Thereby, system-wide water use efficiency is improved.
3 B Irrigation facilities are not developed in
the on-farm area. (Water distribution is not efficient because water is controlled by embanking and cutting soil banks, which needs excessive works.)
Give technical guidance of how to build division boxes by a participatory way; division boxes are placed in the on-farm area.
WUA members FIMD and other
DOI staff (ToT)
The accuracy of water diversion is improved. Thereby water use efficiency in the on-farm area is improved.
The workload of Peon is reduced. Subsequently the efficiency of water distribution is improved.
4 B Since the farm plot surface is uneven.
Such plot needs extra water. Implement leveling of farm plots (implement in
demonstration plot.) WUA members DADO and DOA
staff (ToT)
Water use efficiency in the on-farm area is improved, and then irrigated area increases particularly in the spring crop season.
5 C Since the plot-to-plot irrigation is the
dominant practice, extra irrigation water is needed.
Develop watercourses and farm ditches in the on-farm area so that each plot receives water from watercourses/farm ditches directly.
WUA members FIMD and other
DOI staff (ToT)
The loss of water due to deep percolation decreases during water distribution. Thereby, water use efficiency in the on-farm area is improved, and then irrigated area increases particularly in the spring crop season.
6 C There is no repair record of the tertiary
canals. (FIMD has a record if it supported WUA to repair the tertiary canal.)
Give guidance to WUAs so that they make records of repair.
WUA members FIMD and other
DOI staff (ToT)
It becomes possible to identify spots where repair works implemented frequently from the repair records and to select spots where radical countermeasures (upgrade) should be implemented.
7 C The ISF collection rate is 60-70% at
present, and the WUA seek to raise the collection rate and the fee. However, the decrease of the collection rate is feared due to raise in fee.
Give guidance on proper ISF (money amount) , how to calculate it and how to charge it, and
Support formulation of a reporting system of maintenance plan, the amount of ISF collected and expense to WUA members.
WUA members FIMD and other
DOI staff (ToT)
WUAs stop relying on GON for costs of WUA activities (operation, maintenance and management) and,
The revenue of WUA becomes stable because the feeling of unfairness on charging ISF decreases within WUA.
8 C FIMD is working on WUA establishment
at the secondary-canal and tertiary-canal levels in Bagmati Irrigation System, but it is not getting along.
Support farmers so as to establish WUAs together with Bagmati IMD staff.
FIMD and other DOI staff (ToT)
Establishment of WUAs makes the management of Bagmati Irrigation System smoother.
#) A: Most Important, B: Important, C: As necessary
Source: Survey team
Irrigation Scheme in Terai
DOI, MOI 5-14
Figure 5-4-2 Layout of Kankai Irrigation System Source: Survey team
Canals with red color are secondary canals;
to be controlled by WUAs, to be cleaned by
GON with participation of WUAs’
The intakes connecting to the secondary canals are operated and maintained by WUAs.
The tertiary canals are
: Irrigation Rotation Boundary for Every Other Year
Data Collection Survey
5-15 JICA
Figure 5-4-3 Layout of Bagmati Irrigation System Source: Survey team
WUAs for the secondary and tertiary canals have not yet been set up; under the process of establishment as of August 2016. The Main and secondary canals are operated, maintained, and cleaned by GON.
Irrigation Scheme in Terai
DOI, MOI 5-16
The outline of the Kankai Irrigation System can be summarized as follows:
Table 5-4-7 Reaches of the Kankai Irrigation System Construction Year Reach Secondary Canal Remarks
1971 – 1981 (Phase I)
I S0 – S1 A = 4,000 ha Main Canal L = 22.5km (All are Lining Canal)
II S3 – S5 III S6 – S8 IV S9 – S12
1980 – 1990 (Phase II)
V S13 – S21 A = 3,000 ha Main Canal L = 13.6 km
(Lining length: 700m) Source: KIMD and the WUA of the Kankai Irrigation System
There are 190 WUAs at the tertiary canal level, 22 at the secondary canal level and 5 block WUAs
established in the Kankai Irrigation System. Each block WUA consists of two representatives (one female
and one male) and therefore there are 10 representatives in total. At the top of the hierarchy of WUAs, a
main canal WUA is established with a total of 15 members, consisting of a president, a vice-president, a
secretary, a treasurer and the former president in addition to the 10 representatives from the block WUAs.
The president, the vice-president, the secretary and the treasurer are elected from the members of 190
tertiary canal level WUAs. Concerning the relation between the blocks and the reaches, the block 1 has
the reach I, the block 2 has the reaches II and III, the block 3 has the reach IV, and the block 4 plus the
block 5 constitute the command area of the reach V.
It is said that the total command area of the Kankai Irrigation System is 8,000ha. However, the irrigable
area is up to 7,000ha, and the current irrigated area is 5,500ha. The main crop to be irrigated during the
rainy season is paddy rice, and usually there is sufficient volume of water available. The maximum
discharge of the river in the rainy season is considered as 5,200m3/s., based on the record marked in 2011.
The delivery capacity of the main canal is 10.15m3/s, and all the command area of 7,000ha can be
irrigated in the rainy season. For the winter and spring seasons, the annual rotation method is applied
between the Reaches I, II, III, IV and the Reach V. The minimum discharge of the river in winter is
7.74m3/s, and it is seen as technically feasible that 50% of such a minimum discharge, namely 3.87m3/s of
water can be off-taken by the Kankai Irrigation System to irrigate up to 4,000ha.
Table 5-4-8 Actual irrigable areas and the targets of irrigated areas of the Kankai Irrigation System
Source: KIMD and WUA in the Kankai Irrigation System
According to the hearing from 14 out of the 15 representatives to the WUA at the main canal, the farmers
are used to produce paddy rice in the rainy and spring seasons, and leave the plots fallow in the winter
season. However, in recent years, DADO has been promoting the wheat production in the winter season
through the provision of a 50% of subsidy to seeds and fertilizers (including limes) to individual farmers.
Irrigation system Water source Means of water intake
Area (ha)
Command Area
Irrigable Area Rainy
season Winter Spring
Kankai Perennial River Diversion Weir 8,000 (1) Actual Irrigated Area 5,500 3,000 2,500
(2) Irrigable Area 7,000 4,000 4,000(3) Target Increased Area (= (2) - (1))
1,500
(+27%)1,000
(+33%) 1,100
(+44%)(4) Target Crop Rice Wheat Rice, Vegetables
Data Collection Survey
5-17 JICA
This has contributed to an increase of the number of farmers who are engaged to the wheat production.
This DADO’s wheat promotion program has paid 5,000Rs./ha in cash to the farmers of model farm as an
incentive measure28. The model farm system was started with 50ha in 2015 and the area will be expanded
to 100 ha in the winter season of 2016/2017. Moreover, marketing support to match the farmers with
traders is planned to be commenced. The WUA is willing to expand the wheat production areas up to
1,000 -1,500ha with the understanding that the volume of irrigation water of their Irrigation System is
enough to do so.
The Constitution of the WUAs in the Kankai Irrigation System was developed for the first time 23 years
ago, and it has been revised six times so far. The latest amendment was given in September 2016 and
through which, it is stipulated that 40% of the representatives and especially the Treasurer of the WUA at
the main canal should be female. It was also added to the Constitution that 33% of the representatives and
members to the WUAs at the secondary and tertiary canals should be also female. Besides, to improve the
transparency in the accounting, the number of signers to deposit to and to withdraw from the bank
accounts is increased to two, so
that either the Secretary or the
Treasurer should also sign
checks or slips together with the
President. The amendment also
requires the disclosure of all
cash transactions and the
establishment of the audit
mechanisms. The consultation
and approval on the amendment
is carried out by 225
representatives, which are
consisting of the 181 existing
representatives and 2 more
ad-hoc representatives from
each of the WUAs at the
secondary canal.
Meanwhile, the Kankai Irrigation Management Division
(KIMD), an office of DOI, which is in charge of the
Kankai Irrigation System, has a total of eleven (11) staffs,
consisting of: two civil engineers (full-time and part-time),
two agriculture engineers (full- and part-time), one
assistant engineer (full-time), two administrative officers
and others three staffs.
In 2015, 1.4 million Rs. is collected annually as ISF in the
Kankai Irrigation System. The members should pay
28 According to the interviews with farmers, 5,000 Rs. per ha worked effectively as incentive and they were motivated to produce wheat.
Backhoe owned by the WUAs of the Kankai Irrigation System
251,000
386,201291,200
656,543
169,999
436,663373,500
675,000724,000
1,152,000
1,342,687
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
Irrigation ServiceFee (Rps)
Figure 5-4-4 ISF Revenue of Kankai WUA (2005/06-2015/16) Source: Kankai WUA
Irrigation Scheme in Terai
DOI, MOI 5-18
200Rs. per 0.66ha twice a year after each harvest. In other words, the ISF rate of this Irrigation System
was 400Rs./0.66ha/year. Since 2016, the rate was raised to cover the costs of O&M, and the members
now should pay 300/0.66ha/six months. ISF revenue has been increasing in recent years shown in Figure
5-4-4; it is reported that percentage of collected amount is 64% for whole WUA and that of irrigated area
reaches 90% or more. The share rates of the collected ISF between the WUAs and the GON are 90% and
10%, respectively. The share for the WUAs is again distributed among the WUAs at the different levels:
40% to the main canal level WUA, 20% to the secondary canal level WUAs, and the remaining 40% to
the tertiary canal level WUAs. When the collected ISF is insufficient for the implementation of activities,
the WUA can ask for support from KIMD. In 2015, KIMD disbursed 0.6 million Rs. for the maintenance
of the main canal of the Kankai Irrigation System.
Table 5-4-9 shows the distribution of roles between GON (DOI/IMD) and the WUAs in O&M and the
management of the Kankai Irrigation System. While Table 3-2-3 describes that DOI is responsible for
O&M of branch or secondary canals with the participation of WUAs as general rules, this rule does not fit
to the reality of the Kankai Irrigation System, where the O&M of the secondary canals are left to the
WUAs, while DOI takes care of O&M of only the main canal.
Table 5-4-9 Distribution of Roles in the maintenance works for the Kankai JMIS Canal Operated, Maintained and Managed by
Main Canals DOI (IMD) Secondary Canals
WUA Distributaries or Sub-Secondary Canals Tertiary Canals
WUA On-farm canals
GON provided one tractor, one backhoe and one threshing machine to the WUAs of the Kankai Irrigation
System in 2015 and the WUAs are responsible for the O&M of those machineries. The WUAs construct
the tertiary canals by using the backhoe and the construction budget disbursed by KIMD from the budget
allocated to the implementation of IWRMP, in order to cover the costs of earth work, fuel, labor,
transportation and wage for backhoe operators (500Rs./day) and watchmen. Regarding the establishment
of the tertiary canals from S17 to S21 of the Reach V, only 10% of the construction works has been
completed so far, which comprises the connections with the secondary canal and the water diversion gates.
The works of the Reach V shall be finished by 2018 and therefore, all the planned construction works for
the Kankai Irrigation System would be completed, though some of the tertiary canals from S0 to S16 may
remain incomplete. A comprehensive IMT of the Kankai Irrigation System is planned to be also
undertaken, once physical works are completed. Meanwhile, GON continues taking care of the water
management and cleaning of the main canal. The average height of sediment through the year is about
30cm.
Although most of the construction works of the tertiary canals from S0 to S16 have been finished, some
works still remain. KIMD has no plan to construct new tertiary canals, and has budgeted 0.6 million Rs.
for 2016 only to undertake maintenance works. KIMD will support the WUA in the maintenance works
by clarifying the priority among the secondary and tertiary canals. The structure of the tertiary canals is
simple enough so that they can be established manually.
Data Collection Survey
5-19 JICA
KIMD employs gate keepers for operating the gates of
the secondary canals and measuring water discharge at
S0 – S16 and she/he measures the discharge three
times a day. A total of sixteen gate keepers engage the
works in the canals between S0 and S16 and earn 500
Rs. per day per person. One of the sixteen keepers
operates 2 gates. While the hired gate keepers operate
the gates which divert water to the secondary canals
from the main, the WUA members operates the lower
level canals by themselves.
The WUA affirmed that the canal S1 is always
recommended for a pilot project of any technical
cooperation. However, the canal S1 is already well maintained. Therefore, the WUA proposes other
canals which are not yet well maintained, such as S8, S17 and S18, whose maintenance is smoothly
managed, yet it would be better option that secondary, tertiary and on-farm canals are constructed in
poorly managed areas such as S8, S17 and S18, and then such models are disseminated to the other areas.
This needs further investigation.
5-5 Importance of System-wide Water Management
A series of activities aforementioned will contribute to “Optimize water use for reliable year-round
irrigation”. However, the perspective of the system-wide improvement of water management seems to be
a little bit missing in accordance with participants’ statements during the workshop. That may be because
that it was a workshop that targeted DOI staff, that is, they paid particular attention to capacity
strengthening on water management, organizational operation and crop water management by WUA.
However, it is essential to improve the system-wide irrigation efficiency so as to optimize water use.
The ADS aims at transferring the responsibility for O&M of principal facilities such as headworks and
main canals to WUAs in future. Of course, it depends on the size of irrigation systems, but it is obviously
infeasible in near future when
one thinks about the capability
of WUAs. As a result, the joint
management is the basic and
dominant management form,
which GON (DOI) takes
responsibility for O&M of
headworks, main canals and
large secondary canals (red
parts in the figure below) and
WUA manages smaller canals,
usually the tertiary and lower
level canals , down to the
farmland (blue parts in the
A tertiary canal in the Kankai Irrigation System
Figure 5-5-1 Conceptual Diagram of Joint Management Source: Survey team
Irrigation Scheme in Terai
DOI, MOI 5-20
figure below).
The joint management requires clear hydraulic borders between the government-managing area and the
WUA-managing area in the same irrigation system. Usually, the borders are drawn at the starting points
of tertiary canals. It is easy to make the hydraulic borders, because the head-regulators are installed in
the gates at the starting points of the tertiary canals. Accordingly, the GON’s role is to deliver the amount
of water agreed with WUA to the management interface, and WUA pays some money to GON in
exchange for the delivery service from ISF collected from the WUA members. Then, it is the WUA or/and
WUG that are in charge of water distribution amongst lower-level canals and on-farm water management
below the interface.
GON (DOI) has to distribute water to all the tertiary canals which are offtaking from the main canal, since
the WUAs are basically established at such level. The water should be distributed in accordance with the
areas to be irrigated and the cropping plans in an equitable manner. During the dry season when water is
not available enough, DOI has to distribute water in a volume reduced by a certain rate to all the canals
(to all the WUAs), in conformity with areas to be irrigated with the available volume of water.
In some cases, it may be necessary to impose a water distribution method that enhances the system-wide
irrigation efficiency. For example, first, water shall be delivered to the areas (the WUAs) at the tail of the
canal systems where tend to be suffered from water shortage. Once the ploughing and seeding are done,
water should be delivered to the next areas along with the tertiary canals. Thus the water is distributed
gradually by zoning starting from the farthest areas in the canal systems until all the areas are irrigated.
Based on the premise that irrigation facilities are in a condition to perform their minimum functions as
hardware, in order to improve the system-wise efficiency, it is necessary to support both GON and WUA
in their capacity development. It is indispensable for DOI to enhance the capability to manage water at
the headworks and main canals, because DOI has to deliver water equitably to every WUA, and it forms
the base for WUAs to develop their capacity to manage the command areas (the tertiary and lower level
canals) under their management. Thus, it is expected that the JICA-TCP implements activities concerning
the importance and improvement of the system-wide water management by GON, referring to the priority
activities identified in the workshop in which DOI staff participated.
5-6 Relevance of Contents Applied from GON
5-6-1 Background of the Application
GON has been implementing large scale irrigation development and irrigation system management for the
last several decades. At present, GON is trying to transfer the 25 main irrigation systems in Terai region to
WUA in accordance with the IMT policy. Once the IMT is completed, WUA takes responsibility for the
on-farm area below a branch canal in the irrigation system. Meanwhile, GON takes responsibility for
delivering irrigation water equitably to the most upstream point of the on-farm area that each WUA
manages.
However, such joint management is not functioning well so far. Accordingly, water is not necessarily
utilized efficiently. Even if water sources of some irrigation systems are perennial rivers and water is
available through the year, their irrigated area in the dry season (winter and spring) is limited to less than
half of the command area, or it is very little.
Data Collection Survey
5-21 JICA
Under such circumstances, GON is intensively carrying on rehabilitation/upgrade of headworks and
conveyance systems (main canals, large branch canals) of the main irrigation systems, so as to improve
irrigation efficiency and expand the year-round irrigated area of the existing irrigation systems. Moreover,
GON (DOI) has acknowledged the importance of facility rehabilitation and water management in the
on-farm area, in order to improve water utilization within the existing irrigation system. Whereat, DOI
has applied for JICA-TCP, which contributes to the expansion of year-round irrigated area, focusing on
improvement of improvement of O&M and water management in the on-farm area.
5-6-2 Relevance of Objectives of the GON’s Application
The irrigation efficiency of the irrigation system consists of two efficiencies: conveyance efficiency and
application efficiency. The former is the efficiency of water conveyance from the water intake facilities to
the point where WUA starts water management with responsibility, and the latter is the efficiency of
applying water to farm plots. The former can be improved greatly by structural rehabilitation of canals
and/or by building water-control structures. On the other hand, what is important to improve the latter is
to supply the right amount of water to the effective root zone29 of crops in the right manner, taking crop
water requirement and loss of water into consideration. In other words, farmers need to learn so-called
“on-farm water management30”, which is the water management technologies in the on-farm area.
From the above viewpoints, the improvement of on-farm water management is a reasonable approach so
as to improve the application efficiency and expand the year-round irrigated area. However, the on-farm
water management has a limitation, which is that it does not necessarily improve the system-wide water
management or water use although it improves the irrigation efficiency within respective farm plots. It is
essential to involve water management including the water-conveyance process in order to enhance the
system-wide irrigation efficiency and increase year-round irrigated area.
Therefore, the improvement of on-farm water management is just the prerequisite to increase the
year-round irrigated area, but it cannot be the sufficient condition. The increase of the year-round irrigated
area requires the system-wide optimization of water management. That is, the optimization needs not only
WUA’s improving on-farm water management but also DOI’s improving water management on the
water-conveyance facilities and delivering water to WUAs equitably and timely.
29 This is a range of depth of soil where the plant roots can uptake soil moisture most effectively. 30 This means the distribution and utilization of water on crops within each of the farming plots in an effective and efficient way.
Figure 5-6-1 Image of the water management area at the on-farm canal level Source: Survey team
2ndary Canal
Tertiary Canal
On-farm Canals: appropriate management for proper irrigation water distribution is required.
Main Canal
The Management Area for Tertiary Canal Level WUA
Irrigation Scheme in Terai
DOI, MOI 5-22
5-6-3 Target Area
The irrigated farmlands in Terai region occupy 72.6% of the nationwide irrigated area. The production
amounts of paddy, wheat, pulses and vegetables in Terai region account for 78.6%, 64.1%, 76.6% and
58.1% of the nationwide production amounts, respectively. There are numerous FMISs (small and
medium scale irrigation systems) and 25 JMISs (large scale irrigation systems). Irrigated agriculture in
those FMISs and JMISs in Terai region is important from the viewpoint of the food security, and GON
has proposed Terai region as the target are of JICA-TCP. Thus, it is concluded that the JICA-TCP targets
irrigation systems scattered in Terai region.
Data Collection Survey
5-23 JICA
5-6-4 Joint Management in the IMT Process
ADS aims at implementing the full IMT of less-than-10000ha JMISs (13 out of the 25 main systems in
Terai region). However, large facilities of those systems such as headworks, main canals and large branch
canals are currently under management of DOI. Accordingly, they are now jointly-managed by DOI and
WUA.
Irrigation systems under JMIS are large scale ones with large catchment area. Hence, it is difficult for
WUA to operate and maintain large facilities alone by WUA’s own funds and technologies. Then, it is
recommended that the joint management go on as a superior way of managing large scale irrigation
systems from now on, and that JICA-TCP does not implement the full IMT but the partial IMT for joint
management. As for more-than-10000ha irrigation systems, in addition, ADS intends to transfer more
reasonability to WUA than the present reasonability, in terms of facilities to be handed over. However,
what is of paramount importance is to establish a sustainable joint management at each system
corresponding to the capability of WUA, taking the sediment state into account.
Joint management firstly enables DOI to reduce the maintenance costs of irrigation systems, because
WUA takes responsibility of O&M in the on-farm area, including financial responsibility. As a result,
DOI becomes able to allocate budgets for O&M of principal facilities, rehabilitation necessary or new
projects. Moreover, it will be possible to improve the management system of the government responsible
portion of the JMIS, since FIMDs become able to employ more gate operators and/or other staff for the
O&M of main canals.
On the other hand, IMT imposes WUA to take heavier reasonability and more burdens of O&M.
Therefore, there must be benefits for WUA more than the burdens, or it is necessary that the feeling of
fairness, if any, must dissolve, so that WUA to agree to IMT. In fact, famers had not been satisfied with
irrigation services and the government had not been able to provide better irrigation services to farmers,
in many instances such as Mexico where IMT was implemented relatively smoothly.
As a result, IMT is likely to go successfully in many cases where WUAs are organized in an evolutional
manner by phasing, starting from the management at the farmland level, through that at the turn-out level
(by water users’ groups), and that at the tertiary canal. Such IMT is established based on the farmers’
initiative of doing by themselves because the government cannot do it. Besides, the organization of
WUAs can give peer pressure to upstream farmers’ groups, which take more water than they need, so as
to attain more equitable distribution of water within an irrigation system. .
There are many case studies of IMT, and the following is an example of such studies. The basic is to
make a win-win relationship between the government and farmers. At the first sight, it seems that the
government gains more profits than farmers do, e.g. maintenance cost reduction. But the WUA officially
established as an organization becomes able to demand water on an equal footing. The WUA becomes
able to duly complain to other WUAs in the same system, which takes excessive water, through the
government as mediator. Meanwhile, the government becomes able to concentrate on equitable water
distribution among all the WUAs (among all the tertiary canals) through enhanced gate operation on the
main canal.
Irrigation Scheme in Terai
DOI, MOI 5-24
Case study of IMT: FAO Water Reports No.32 Irrigation Management Transfer - Worldwide efforts and results (2007)
1) The table on the right-hand
side (Table 5-6-1) is a
series of IMT cases
investigated. The table
shows that IMT was
implemented at the field
canal level in 25 cases and
that it was implemented at
the distributary canal level
in 23 cases. That is, principal facilities such as headworks and main canals are under management
of the government in all of 48 cases. In other words, all cases are joint management. In accordance
with the case study, it is concluded that “WUAs have the potential to perform their basic functions
but that they need sustained training, consultation, support services and a proper legal basis in
order to enable them to function effectively”. It is also concluded from Figure 5-6-1 that “Right
IMT makes a reduction in the government O&M cost, but the farmers’ financial burden for O&M
does not necessarily increase after IMT.”
2) It was only 4 cases out of
the 43 cases that the
quality of maintenance has
deteriorated after IMT. All
of those 4 cases are
African countries, and the
government reduced the
financial contribution to
O&M drastically while
farmers could not
compensate the amount
reduced for O&M by the
self-pay burden. Thus, IMT was
not successful in those 4
countries.
3) The ISF collection rate went up
after IMT at 75% of irrigation
systems studied. This fact
implies that IMT has improved
the quality of irrigation water
delivery service. Figure 5-6-2
shows the transition of the ISF
Table 5-6-1 Area Where WUA is Responsible after IMT
Figure 5-6-1 Change of Expense for O&M after IMT
76%
43%
20%
37%
15% 11%
Figure 5-6-2 Transition of the Average IMT Collection Rate (Mexico, 2006)
Data Collection Survey
5-25 JICA
collection rate of a successful case in Mexico, which is often cited as a successful one. The ISF
collection rate had kept declining before IMT, but it turned to go up after IMT.
4) The timeliness of irrigation
was obviously improved at 30
out of 39 cases studied (Figure
5-6-3). Farmers receive water
more timely after IMT, that is,
at the time closer to when they
want to irrigate before IMT.
Further, the equity of water
distribution was obviously
improved, too. In other words,
over-irrigation by upstream
farmers has decreased and tail-end farmers receive more water than before IMT.
5) The improvement of irrigation
water distribution normally
results in increased cropping
intensity and/or extended
irrigated area. The extension
of irrigated area has been
reported at 25 out of 39 cases
studied (Figure 5-6-4). In this
regard, it is very difficult to
identify causes of increased
crop yield because there are
many elements that have
influences on crop yield other
than water use improvement. For instance, sudden changes of crop yields can be caused by
elements related to neither cultivation technologies nor water use: e.g. political decisions. However,
crop yield increases after IMT have been reported at 21 out of 33 cases studied (Figure 5-6-4).
This result indicates the possibility that irrigation water delivery of the right amount at the right
time enhances crop yields. Then, enhanced crop yields have potential to increase farm income per
unit area and subsequently to improve the ISF collection rate.
5-6-5 Involvement of JICA-TCP in Future IMT Implementation by GON
Many IMT cases studied in the above have proved the possibility that IMT has effects on making water
distribution more proper, crop yield increase, farm income increase and enabling the government to
reduce the maintenance cost. In this regard, it should be noted that all of the cases were so-called “Partial
IMT” which transfers on-farm facilities only (e.g. tertiary canals, watercourses) to WUA, that is,
irrigation systems are under joint management after IMT.
Irrigation management is being transferred from DOI to WUA in accordance with the IMT policy that
Figure 5-6-4 Changes of Irrigated Area, Crop Yield and Farm Income through IMT
Figure 5-6-3 Changes of Timeliness and Equity of Water Distribution through IMT
Irrigation Scheme in Terai
DOI, MOI 5-26
GON has adopted as an irrigation management policy. In JMISs, watercourses and farm ditches have been
transferred to WUAs. The tertiary canals, sub-secondary canals and/or secondary canals have been also
transferred to WUA, although the situation varies from system to system.
In order to implement irrigation with a high system-wide efficiency while improving on-farm water
management requested by IMD of DOI, it is necessary to implement joint management at a high level,
which is established through partial IMT tailored to the size of the irrigation system. Consequently,
JICA-TCP needs to work on both DOI and WUA in order to implement joint management at a high level.
5-6-6 Target Irrigation Systems for the IMT Approach
The IMT policy was formulated in 1992, and it has been consistently a major policy of DOI since then
(Irrigation Policy 1992, 1997, 2003, 2013). Further, ADS intends to attain more efficient use of water in
both FMISs and JMISs, including the 25 main systems in Terai region, by 2035.
The total command area of 25 main irrigation systems accounts for 34.8% (331,644ha) of the total
irrigated area in Terai region. The average command area of the 25 main systems is 13,000ha, and the
remaining 65.2% (622,096ha) is the area irrigated by numerous FMISs scattered in Terai region. The
exact number of FMISs is unknown, but it is supposed that there are 3,000-6,000 FMISs, assuming the
average command area of FMISs is 100-200ha.
Partial IMT is in progress at the 25 JMISs. On the other hand, many FMISs have been originally
constructed by Farmers themselves. Accordingly, it is farmers who have the ownership of the irrigation
system and its O&M responsibility from the beginning. Thus, FMISs cannot be the target of IMT, and it is
reasonable that irrigation systems for the pilot project of JICA-TCP are selected from the 25 JMISs.
However, FMISs are supposed to have something to study in terms of cohesion, rules and organizational
operation of WUA.
According to DOI, the O&M of FMIS is good in many cases, compared to JMIS. That is probably
because (a) the irrigation facilities and WUA are much smaller scale compared to JMIS, (b) beneficiaries
live in the same village or in some nearby villages, that is, peer-pressure functions under such
circumstances, and it is easier to manage the irrigation system and operate WUA owing to the above (a)
and (b). Therefore, the O&M of FMISs are implemented more smoothly than those of JMISs.
However, assuming one of WUAs in a JMIS is equivalent to the WUA of a FMIS, the same
organizational rules as those of FMIS is applicable to WUAs in JMIS. Then, from this aspect, the idea of
study tour as a part of training occurs. Which to say, WUA members of the JMIS that JICA-TCP targets
visit a FMIS and learn organizational operation, etc. from the WUA of the FMIS. There are a number of
WUAs in a single JMIS. Coordination among WUAs should be eventually the responsibility of DOI,
which manages the main canal delivering water to those WUAs in the downstream31.
31 The tertiary-canal-level WUA registers to the secondary-canal-level WUA of the secondary canal that supplies water to the tertiary canal.
Likewise, the secondary-canal-level WUA registers to the main-canal-level WUA of the main canal that supplies water to the secondary canal.
Then, the main-canal-level WUA registers to GON (FIMD). The coordination among WUAs should be under the responsibility of the upper-level
WUA to which they register, and eventually it should be the responsibility of GON to which the main-canal-level WUA registers.
Data Collection Survey
5-27 JICA
5-6-7 Contents of Technical Transfer that IMD-DOI Expects
The “Y” in the column of the “Donor (Tech)” column in Figure 5-2-1 indicates the necessity of technical
assistance by donor organizations, which DOI expects. JICA-TCP is able to cooperate in these technical
fields: (13), (14), (15), (16), (20), (21), (23), (24), (26) and (27) (highlighted in yellow). These technical
contents will contribute to the improvement of the system-wide O&M as well as on-farm water
management.
It is the prerequisite that GON implements rehabilitation/upgrade of facilities by its own funds if
necessary for JICA-TCP. Therefore, the JICA-TCP does not include the component of facility
rehabilitation/upgrade. JICA-TCP aims to increase the year-round irrigated area by capacity strengthening
of both DOI staff and WUAs and improvement of water management from the conveyance system to the
on-farm level.
5-6-8 Relevance of Applied Contents for JICA-TCP from GON
The table below summarizes what discussed in the workshop and contents of high priority found out
through interviews to IMD. Then, the relevance was examined, based on the above discussion, in terms of
objectives, approach, contents of technical transfer, etc. As a result, each of applied contents from GON is
necessary to increase year-round irrigated area through the improvement of the system-wide irrigation
efficiency. However, in addition to improvement of on-farm water management, it is desired to target the
entire system and strengthen the capability of FIMD/DOI staff working for irrigation system
management.
Table 5-6-2 Relevance of Contents that DOI Staff Applied for Cooperation Item Proposed Contents Relevance
Objective/ Challenge
Improvement of on-farm water management Improvement of the system-wide water management is necessary, too.
Yes, but not enough
Target Area Terai Region Yes Approach IMT
Improvement of a resultant joint management after IMT. Yes, but not enough
Target of IMT Primarily 25 JMISs followed by FMISs The target is the 25 JMISs, and FMISs are candidates of study tour as
a part of training.
Be modified
Method Pilot project and its dissemination Yes
Contents of Technical Transfer
On-farm water management improvement through capacity building and O&M improvement Improvement of the system-wide water management is necessary, too.
Yes, but not enough
Source: Survey team
Data Collection Survey
6-1 JICA
Chapter 6 Proposed Approach of JICA’s Cooperation
6-1 Policies and Needs in the Irrigation Sector
The Irrigation Policy 2013, which forms the base for development policies for the irrigation sector of
Nepal, provides a vision for the implementation of year-round irrigation services and also highlights the
sustainable development of irrigation sector through effective water management and empowerment of
human resources. Meanwhile, ADS, the base for development policies for the agriculture sector,
illustrates the strategies for irrigation development with a comprehensive package of infrastructure and
capacity development for “Irrigation Area expanded equitably and viably, and improved Irrigation
Efficiency and Management”. One of such strategies aims at implementing IMT from GON to the WUAs
of the 32 government irrigation systems, including the JMISs in Terai region.
The Survey confirmed six measures to be taken to improve the functions of the JMISs in Terai region, as
follows: 1) an improvement on the ISF collection; 2) the formulation of an O&M plan of irrigation
facilities; 3) the equitable water distribution; 4) an enhancement of water management skills; 5) an
improvement of agriculture components; and 6) an expansion of year-round irrigated areas. Besides, a
core problem/objective of irrigation development in Terai region, which was identified in the workshop
held at the central-level, is stable year-round irrigation. It was also proposed in the same workshop to
achieve this through an improvement on the ISF collection, the formulation and implementation of an
O&M plan, the institutional development of WUAs, an enhancement of water management skills, etc.
These issues are acknowledged as needs of local communities and national policy.
Though both the Irrigation Policy 2013 and ADS aim at improving agricultural productivity and
production, the potential for an expansion of farmland in Nepal is low. Therefore, an increase of crop
productivity in the existing land areas would be necessary. To achieve it, an expansion of the irrigated
areas is considered as effective approach. According to ADS, the beneficiary areas of year-round
irrigation are estimated to occupy about 18% of the total irrigated area in Nepal as of 2016, while the
irrigated areas in Terai region cover 73% of the total irrigated areas of the county in 2011/2012. Thus, it is
obvious that a promotion of year-round irrigation in Terai region would lead to an improvement of the
productivity of farmlands at the national level. Thus, the need
for such a project is high.
On the other hand, the “Country Assistance Policy for Nepal”
formulated by GOJ in April 2012 targets “Poverty alleviation
in rural areas” as one of the priority areas of its assistance to
Nepal, and states that “Japan intends to increase the
agricultural productivity and farmers’ income by disseminating
agricultural technology and fostering farmers’ organizations”.
The Promotion of irrigated agriculture would contribute to an
increase of agricultural productivity and hence, farmers’
income. Thus, a JICA-TCP for the irrigation sector would be in
line with the aforementioned priority area of Japan’s assistance
policy.
Structure of the main irrigation systems in Nepal
The structure of irrigation systems in Terai region, Nepal, is similar to that in other countries. There are secondary and tertiary canals under the main canal, and the water is delivered to each farmland through turn-outs established on the tertiary canals. Usually, therefore, a WUA is established for each turn-out. In some cases, the secondary canals are not established and turn-outs are established directly on the main canal.
Irrigation Scheme in Terai
DOI, MOI 6-2
Under the above circumstances, DOI has applied for a technical assistance to Japan in May 2016, so as to
improve O&M of irrigation systems. The Survey team has confirmed with IMD through an interview that
the application prioritizes O&M, including the water management, at the on-farm32 level. In addition, in
the workshop held on 14 August 2016 at the DOI central office, the participating DOI staffs have also
prioritized the capacity development of WUAs, including the capacity development in the water
management at the on-farm level, so that beneficiary areas of year-round irrigation could be expanded.
DOI has been implementing IMT of 25 main irrigation systems in Terai region for years and applied for a
technical cooperation in form of JICA-TCP under such circumstances. As mentioned above, the priority is
put on the on-farm water management in accordance with the contents of the application and confirmation
through interviews. However, the system-wide approach is essential in order to improve water
management of the irrigation system as a whole and expand the year-round irrigated area. Therefore, the
technical cooperation through JICA-TCP has a large significance.
6-2 Proposed Cooperation Approach for an Improvement on the Irrigation O&M in Terai Region
It is proposed that the JICA-TCP which will be developed in response to the request from GON will adopt
the pilot approach which is illustrated in the aforementioned section “5-4 Targets of Technical
Cooperation and Possible Activities“. Relevant knowledge and technologies will be transferred to
stakeholders of the irrigation systems previously selected, and utilize such selected systems as models of
future dissemination. Based on lessons learnt drawn from the process and results of the technical transfer,
the knowledge and technology will be widely disseminated to stakeholders of other irrigation systems.
Through the workshop DOI gave a higher priority to the 25 main irrigation systems (JMISs) than to small
and medium scale irrigation systems (FMISs): the weighing given by the participants was JMIS : FMIS =
70% : 30%. Such a prioritization is actually reasonable because the FMISs are not the target of IMT, since
they are originally farmers’ property. Besides, the IMT of JMISs is more difficult due to the larger scale
of their facilities.
The IMT of Irrigation systems in Nepal is in progress, and that the existing JMISs are currently
jointly-managed by GON and WUAs. In order to “increase the year-round irrigated areas”, it is
indispensable to address the entire irrigation systems, by targeting both the GON staff who manage the
major facilities, such as the main canal, and the WUAs that manage the command areas (the tertiary and
lower level canals) by and large (See Table 3-2-3 Distribution of roles in JMIS and Table 5-4-9
Distribution of Roles in the Maintenance works in the Kankai JMIS)..
Based on all mentioned above, it can be proposed that the JICA-TCP will select JMISs and subsequently,
pilot areas from the selected JMISs, taking into account the criteria proposed in section “5-4 Targets of
Technical Cooperation and Possible Activities” and other factors, so that outputs of the JICA-TCP can be
disseminated to other irrigation blocks within the same selected JMISs.
32 The word “on-farm” means the area where WUA members manage irrigation water by themselves, including the inside of
respective farm plots where they grow crops,
Data Collection Survey
6-3 JICA
The pilot areas of the JICA-TCP will be
visited by representatives from other
irrigation blocks and concerned
government officers at a later
dissemination phase. The WUAs and the
DOI officers (especially, community
organizers) whose capacity is developed
through the implementation of the
JICA-TCP are supposed to be in charge
of dissemination of the JICA-TCP
outputs to other blocks, by utilizing the
products of the same JICA-TCP: the
Joint Management Guidelines/Manual
for JMISs and the methodology to
replicate the joint-management system
in other places.
Table below shows possible contents of the JICA-TCP: objectives, outcomes, activities, external
conditions, etc. The project objective is proposed as that the year-round irrigated area of the targeted
irrigation system increases, which was indicated as the priority challenge by the workshop participants.
Under this objective, the project outcomes are classified into three categories: (a) outputs that GON staff
should accomplish; (b) outputs that WUAs should accomplish; and (c) outputs that both GON staff and
WUAs should accomplish, respectively, as table below shows.
Table below also shows the draft activities required to produce the outputs. . The activities are mainly
trainings. In this regard, it is not the JICA-TCP but GON staffs who give trainings to WUAs. The
JICA-TCP gives TOT (Training of Trainers) to GON staff so that they are able to give trainings to WUAs.
Namely, GON staff of the JICA-TCP pilot areas has to participate in the TOT for WUAs, in addition to
the trainings to improve on the water management at the principal facilities which should be under the
GON management.
Table 6-2-1 Outline of JIC-TCP (Irrigation Part Only)
Overall
Goal
Agricultural production increases in the target area.
Project
Goal
The year-round irrigated area of the targeted irrigation system increases
Outcomes GON (Managing entity of principal facilities) 1. DOI staff capacity on water management and facility maintenance are improved in the
GON-responsible portion where are principal irrigation facilities. 1.1 Facilities are sufficiently maintained in the GON-responsible portion where are principal irrigation
facilities, 1.2 Water is properly and equitably delivered to the command areas (the tertiary and lower level
canals) under the WUA’s management , and 1.3 The amount of money and its percentage that the WUA pays to GON out of ISF collected
increase.
Figure 6-2-1 Procedures of the pilot project approach Source: Survey team
JICA-TCP(Pilot
Project)
To select pilot areas (WUAs) from the JMISs selected from Terai region
Disseminationof outputs of the JICA-TCP
Dissemination by phasing to other areas within the same JMISs selected for the JICA-TCP
WUAs and DOI officers who have acquired therelevant knowledge and experience on the Joint Management of JMISs
Joint Managemnet Guidelines/Manual for JMISs
Methodology of dissemination ofoutputs of the JICA-TCP to other areas
Irrigation Scheme in Terai
DOI, MOI 6-4
WUA (Managing entity of the on-farm area) 2. WUA’s capacity on water management and facility maintenance are improved in the
on-farm area where WUAs manage water. 2.1 Facilities are sufficiently maintained in the on-farm area where WUAs manage water, 2.2 Water is properly and equitably distributed to lower-level WUGs within the command areas under
the WUA’s management (equitable distribution through main canal → secondary canals → tertiary canals →turn-outs),
2.3 The ISF is properly collected in accordance with the O&M plan, 2.4 On-farm canals including tertiary canals are developed, and 2.5 The application efficiency of the on-farm irrigation is improved. GON and WUA 3. A model site of joint-management is established 3.1 The Cooperation between GON and the WUAs is strengthened, 3.2 Irrigation water is delivered to the entire irrigation system as planned, and 3.3 A methodology to replicate the joint-management system in other places is established.
Activities FOR GON Staffs Who Manage Principal Facilities 1.1 Training on O&M of principal facilities, e.g. headworks and main canal, (lectures and practices), 1.2 Technical training on calculation of irrigation water requirement based on annual cropping plan#1,1.3 Technical training on water allocation planning at the main canal level in consideration of annual
water demand and available water amount at the water source#2, 1.4 Lectures and practices on rotational irrigation during drought period and for low-volume
irrigation#3, and 1.5 Lectures on the budgeting based on the facility maintenance plan #4. #1 It is important to calculate the irrigation water requirement based on the water requirement in depth when one calculates the irrigation water requirement of paddies. The Penman method (Penman-Monteith method) is not as accurate as the water-requirement-in-depth method, in order to calculate the irrigation water requirement of paddies, because the Penman method was originally established to calculate crop water requirement of upland crops.
#2 Prospective contents are technical trainings and practices of the gate operation to deliver required volume of water by season.
#3 In case where an irrigation system is operated with less volume of water than that originally designed at an early stage of crop growth, it is necessary to raise the canal water level by operating the cross-regulator and to provide the training on the application of rotational irrigation by grouping tertiary canals. On the other hand, in case of water shortage, such as drought, the prioritization in water delivery to seeding and planting in downstream areas shall be examined.
#4 Trainings are regarding estimation of annual costs necessary for maintenance, formulation of a realistic facility maintenance plan based on the amount of ISF collected in past years, considering possibility to raise ISF to compensate deficit, introduction of government subsidies, and so forth.
For WUA Members Who Manage the Command Area at the Tertiary and Lower level Canals 2.1 Training on the O&M Planning of part of the irrigation systems under the management of WUAs
(lectures and practices) 2.2 Workshops, lectures and practices to calculate a proper amount of ISF based on the O&M plan 2.3 Training to farmers on the planning of tertiary and on-farm canals (lectures and practices) 2.4 Training to farmers on the construction of tertiary and on-farm canals (lectures and practices) 2.5 Training in the water management for rice paddy fields through equitable water distribution
(rotation) within the areas under the management of WUAs (lectures and practices) #1. #1 Mutual agreement among the members of the WUAs should be supported on rotation of water for rice paddy so that the water can be first supplied to downstream areas where water shortage frequently occurs. NOTE: The JICA-TCP team does not directly give the above trainings, etc. to WUA members, but GON staff gives them to WUA members. Accordingly, GON staff needs to gain TOT trainings for WUA strengthening in addition to trainings and lectures concerning principal facilities.
Data Collection Survey
6-5 JICA
For GON and WUA 3.1 GON and the WUAs together develop and share the O&M plan and the financing for the
implementation of the same plan 3.2 GON and the WUAs together develop the irrigation plan of the entire irrigation system including the
tertiary and on-farm canals 3.3 GON and the WUAs together develop guidelines and manuals for the joint management by IMT
through the implementation of pilot projects.
External Conditions
N/A
Source: Survey team
The farmers who are members of the WUAs for the selected pilot areas are required to contribute to the
JICA-TCP in forms of the payment of ISF, labor and time. The farmers’ contributions are actually
indispensable for O&M and the water management of the concerned JMISs, and are required even after
the termination of the JICA-TCP. It is, therefore, important that an incentive mechanism for farmers to
continuously make contributions in forms of the payment of ISF, labor and time, is institutionalized into
the JICA-TCP framework. The figure below shows the incentive mechanism which the JICA-TCP may
aim at.
The knowledge and skills on the water management and O&M which will be transferred to the WUA
members through the implementation of the JICA-TCP will surely work as incentive for farmers.
However, in order to ensure continuous contributions from farmers, improved and stable agricultural
income should be sought. The objective of the JICA-TCP, expanded year-round irrigated areas would
directly lead to an increase of agricultural income, first of all, it is important to attain the project objective
through the implementation of the JICA-TCP.
Project objective
Incentive for farmers
Increase in the year-round irrigated areas
Improved and stable agricultural income/ Increased number of farmers whose agricultural income has been improved
Acquitance of relevant knowledge and skilss on cultivation and agricultural business
Optimization of the collection and management of ISF
Improvement on themaintenance of facilities and the water management
Contents of the capacity development for WUAs ● knowledge and skills required for the water managment and the maintenance of facilities wihtin the command areas under the WUA's management● knowledge and skilss to improve the organizational managment of the WUAs● knowledge and skills to enhance the coordination and cooperation among related organizations and institutions
Contents of the capacity development for government officers● knowledge and skills required for the water managment and the maintenance of facilities wihtin the command areas under the GON's management● knowledge and skilss to improve the organizational managment of the WUAs● knowledge and skills to enhance the coordination and cooperation among related organizations and institutions
factors which work as incentive for farmers
Figure 6-2-2 Approach of the JICA-TCP: Incentive mechanism for farmers Source: Survey team
Irrigation Scheme in Terai
DOI, MOI 6-6
The implementation of the agricultural component to be described later, has not been included into Table
6-2-1, since it is understood that further discussion will be required to determine whether such a
component should be included into the JICA-TCP framework. Nonetheless, if the knowledge and skills of
cultivation and agricultural business can be disseminated to farmers simultaneously with the
implementation of the JICA-TCP, the possibility to attain improved and stable agricultural income will be
elevated, and the number of farmers who can benefit from both the components. Therefore, positive
results of the feasibility analysis of the agricultural component are expected.
Figure 6-2-3 shows the possible JICA-TCP framework developed based on the request from GON. An
improvement on O&M, especially, an improvement on the water management in the command area under
the WUA’s management, in addition to the measures against the central problems identified in the
workshop: the year-round irrigated areas have not been expanded. The figure shows the principal
challenges, solutions to the identified challenges, possible technical assistance to be provided and possible
outputs through the implementation of the JICA-TCP.
Data Collection Survey
6-7 JICA
Agricultural Development Strategy 2015-2035: O&M Activities in the Irrigation Sub-sector IMT promotion of main irrigation systems, Improvement of irrigation efficiency, Capacity strengthening of IMD, Expansion of year-round irrigated
areas of the existing irrigation systems, Capacity development of WUA on on-farm water management, Improvement of ISF collection for O&M
Year-round irrigated area does not increase. (Irrigation water is not available enough for winter and spring cultivation.)
Possible
Solutions
Possible
Technical
Cooperation
Software
Problems
Background
Infrastructure GON implements
improvements/ rehabilitations of irrigation
systems.
Hardware
Challenges Irrigation facilities are malfunctioning, disabled or non-existent
between water intake facilities and the tail-end plot
Mutual Influence Water is available, but its distribution
JICA&
IMD Staff
IMD Field Office
& DOI Staff
WUA of
JMIS
JICA-TCP
Outcomes Increased year-round irrigated area of existing irrigation systems
The system-wide irrigation efficiency is improved.
A model site of joint- management is established.
Increased ISF and Improved O&M
1) Training on O&M of irrigation facilities in on-farm area 2) Technical training on equitable water distribution in the on-farm area 3) Technical training to improve irrigation in the farm plot 4) Workshops and lectures to improve ISF collection system 5) Workshops and lectures for financial management of WUA 6) Workshops, lectures and study tours on organizational operation
1) Training on O&M of principal facilities (lectures & practices) 2) Technical training on calculation of irrigation water requirement based on
annual cropping plan 3) Technical training on water allocation planning at the main canal level, which
includes annual water demand and available water amount at the water source 4) Trainings on rotational irrigation for drought period and low-volume irrigation 5) Formulation of maintenance plan premised on ISF to be financial source
IMD Staff IMD Field Office
& DOI Staff
WUA of JMIS &
FMIS
Dissemination (GON)
Improvement of O&M of Principal Facilities Equitable and timely distribution of proper amount of water
to branch canals, and capacity enhancement of IMD for such distribution
Improvement of O&M in the On-farm Area
Equitable water distribution within the on-farm area, improvement of irrigation in the farm plot and capacity
enhancement of WUA for such improvements
WUA Side GON Side
Figure 6-2-3 Proposed Framework of JICA Technical Cooperation Project Source: Survey team
Irrigation Scheme in Terai
DOI, MOI 6-8
6-3 Suggestion to Introduce the Agricultural Component
The application from GON does not mention about agricultural component at all. The government
officers who attended the workshop did not indicate the necessity for assistance to the agricultural
component, either. However, the IMT process usually involves assistance in agricultural component33, in
order to achieve not only an increase in agricultural income through year-round irrigation, but also the
proper collection of ISF. Moreover, assistance in agricultural components may work as incentive for
farmers to take the increased burden due to IMT, including the maintenance of the irrigation facilities in
the command areas of WUAs, the ISF collection from the WUA members, etc.
In order to assure the self-sustainability of the transferred irrigation systems, it is important for WUAs to
collect ISF after seeing an improvement on agricultural profit of the members, and to save part of the
collected ISF for periodical and future large scale rehabilitations as well as for emergency rehabilitations,
and for other WUA activities. In other words, it is important that each of the WUA members improves
his/her own economic situation by increasing the production of current crops or by cultivating and
marketing more cash crops, and as a result, he or she can remain capable to pay proper ISF. In
consideration of all this above mentioned, the Survey
team proposes the incorporation of the agricultural
component into the prospective JICA-TCP, although it
has not been included in the requests from GON so far.
For instance, the need for technical support in the rice
cultivation would be increased in the Kankai Irrigation
System, shortly after the construction of on-farm
canals by farmers, as the rice production is popular
among them. Farmers grow different varieties of
paddy rice by season: a variety called Sanamonsuli
which takes 100 to 120 days to grow in the rainy
season, and another variety which takes 90 days to
grow in spring. The yield of those varieties are about
4.8ton/ha. Since it is said that farmers show less interest
in the production of spring rice, technical support for the
cultivation of spring rice as incentive for farmers may be
considered.
The introduction of young seedlings in rice cultivation
(to be implemented as a pilot project): Rice seedlings of
more than 30 days old are transplanted to paddy fields in
in Terai region. Such old seedlings have a reduced
potential for tillering, which may bring about a reduced
yield. In order to increase the yield per unit area, the
33 Agricultural component includes cultivation technology including water-saving cultivation, soil diagnosis & management, cropping,
introduction of quality seeds, mechanization, post-harvest processing and marketing, etc.
Seedling transplanted is 30-45 days old.
Source: Survey team
Example of farm ditches built by farmers (Terai region) Source: Survey team
Data Collection Survey
6-9 JICA
introduction of younger seedlings (seedlings of 21 to 24 days old) together with paddy-field leveling,
and the introduction of the technique to transplant a fewer seedlings per planting spot may work. In this
regard, the System of Rice Intensification (SRI), which promotes the transplantation of only one seedling
per spot, is not recommendable in those paddies where the surface is not leveled and drainage capacity is
not high.
6-4 JICA-TCP Pilot Projects and Dissemination
The JICA-TCP implements pilot projects in a few irrigation blocks under the WUA’s management in
selected JMIS(s) (Actually, most of them are on the tertiary canals). Since the entire JMIS is too big to be
a pilot project site, it is reasonable that the JICA-TCP implements the pilot project at an irrigation block
which is the area irrigated by a branch canal in a JMIS. It is desired that three WUAs are selected in the
upstream, mid-stream and downstream zones respectively in a single JMIS.
The upstream WUA tends to over-irrigate by taking water more than requisite amount. The downstream
WUA has water shortage frequently compared to the up- and mid-stream WUAs. The mid-stream WUA is
located between them. Accordingly, selecting theses 3 WUAs gives GON the opportunity to enhance its
coordination capability. Respective WUAs distribute water within their own responsible areas after
receiving water from DOI at the most upstream point, which is the management interface between WUA
and DOI. However, what is very important to improve the system-wide irrigation efficiency is that the
JICA-TCP targets WUAs from the upstream to the downstream.
The JICA-TCP conducts workshops and trainings at its project sites. Then, DOI field staff in other
irrigation systems/districts visits the pilot project sites, and learns how to manage principal facilities so as
to make equitable water distribution as well as know-how of on-farm water management that is equitable
water distribution amongst WUGs in a WUA. After that, they go back to irrigation systems/districts and
disseminate what they learned.
6-5 Possibility for the Distribution of Roles and Collaboration among the JICA-TCP and Other
Donors’ Projects
6-5-1 Sharing Roles
As mentioned in the Chapter 3, CMIASP-AF and IWRMP-AF has divided Nepal into 2 zones and been
implementing sub-projects targeting FMIS. The IWRMP-AF is conducting IMT at three main irrigation
systems in Terai region: Sunsari-Morang, Narayani and Mahakali. The JICA-TCP targets Terai region,
which is the major food-producing area of Nepal, because GON has requested the area through the
application to Japan. Consequently, it is possible to avoid overlapping if JICA-TCP targets irrigation
systems that are neither CMIASP-AF sub-projects nor IWRMP-AF sub-projects.
6-5-2 Collaboration Possibility
The Survey team discussed the possibility of collaboration between JICA-TCP and CMIASP-AF and also
between JICA-TCP and IWRMP-AF with concerned parties during the Survey period. As a result, the
following items are listed as possible collaboration.
Irrigation Scheme in Terai
DOI, MOI 6-10
Sharing training contents for strengthening capacity of WUA and DOI staff,
Sharing training contents regarding on-farm water management for WUA and DOI staff,
Sharing information on the ISF collection,
Sharing methodologies for improving the ISF collection rate, and
Sharing information collected regarding irrigation facilities and WUAs in Terai.
6-6 Considerations for Future Surveys and Implementation of the JICA-TCP
6-6-1 Recommendations on Land Ownership issues
As seen in Section 3-1-3, there are by and large three challenges for farmers of Terai region regarding the
land ownership as follows:
1. Continuous and frequent amendment to the Land Related Act and weak enforcement of the same act
2. Inadequate diffusion of the information on the land registration and the land ownership (a low level
of recognition and understanding of the land registration system)
3. A significant proportion of the rented land area to the cultivated land area (approximately 25%); that
of the farmers farming by renting land in Terai region to all the farmers of the country
(approximately 36%); and, that of the farmers who do not have their own land to cultivate to all the
farmers in Eastern and Central Development Regions (approximately 10%).
A summary of possible impact of these challenges on the prospective JICA-TCP, together with possible
measures to be taken in future surveys and in the implementation of the JICA-TCP project in order to cope
with or mitigate such an impact are compiled in the following table.
Table 6-6-1 Challenges around the land ownership and their possible impact and mitigation measures No. Challenge Possible impact on the
prospective JICA-TCP Possible measures to be taken
In future surveys In the implementation of the prospective
JICA-TCP 1. Frequent
amendment to the Land Related Act and weak enforcement of the current act
If the current act is actually enforced on the ground, the farming land will be fragmented. This could cause confusion among the WUA members and could result in changes of the membership of WUAs.
To confirm progress and perspective of the land reform
To conduct a sample survey on the current situation of land registration in the selected irrigation blocks to understand the situation
To keep following the land reform process and direction and when necessary, to share the information with the WUA members
To facilitate the WUAs to include rules of member change into their constitutions or regulations through discussion and agreement among the members
Data Collection Survey
6-11 JICA
No. Challenge Possible impact on the prospective JICA-TCP
Possible measures to be taken In future surveys In the implementation of
the prospective JICA-TCP
2. Inadequate diffusion of the information on the land registration and the land ownership (a low level of recognition and understanding of the land registration system)
(1) In some cases of land dispute, farmers who actually cultivate such land should leave from the land as results of the mediation process. If there is land which is not registered properly within the targeted irrigation systems, there remains a risk of changes of the WUA members during or after the implementation of the JICA-TCP.
(2) When the irrigated area is expanded due to improved O&M and on-farm water management, new land dispute could arise on the area to be newly irrigated.
To conduct a sample survey on the current situation of land registration in the selected irrigation blocks to understand the situation
To understand the customary and legal process of mediation of land dispute cases.
To provide the counterpart officials and WUA members with access to the information on the land registration system and merits of the registration.
Irrigation Scheme in Terai
DOI, MOI 6-12
No. Challenge Possible impact on the prospective JICA-TCP
Possible measures to be taken In future surveys In the implementation of
the prospective JICA-TCP
3. A significant proportion of the rented land area to the cultivated land area
(1) When there is no agreement between the landowner and tenants on the cost sharing and decision-making for the O&M activities, it may cause a delay in the O&M activities.
(2) If all the landowners are not involved in the WUAs, necessary decision-making by the landowners on the O&M activities cannot be made timely.
To conduct a sample survey on the current situation of rented land in the selected irrigation blocks to understand the situation.
To understand the distribution of roles between a landowner and a tenant on a rehabilitation/improvement of facilities on the rented land, stipulated by laws and customary laws.
To confirm what tells the existing WUA constitutions or regulations on the distribution of power and responsibilities between landowners and tenants for a rehabilitation and/or improvement of the facilities on the rented land.
To facilitate the WUA members to reach an agreement with their landowners regarding the cost sharing and decision-making responsibility on the O&M activities.
To facilitate the WUA members in the establishment of communication channels with landowners regarding the O&M activities
Source: Survey team
6-6-2 Recommendations on Ethnic issues
1) Recommendations for future surveys
In future surveys, it would be important to confirm whether different ethnic and social groups, such as
Madhesi and Tharu, among others, can have an equal access to benefits from the prospective JICA-TCP
or not, as well as whether there is an enabling environment for different ethnic and social groups to work
together and to share necessary costs and burdens, including the payment of ISF. For this purpose, it is
recommended to include the following issues in surveys.
(1) WUAs
There are 25 JMISs in Terai region and the information on the location and irrigated area for each of
them is available. However, there is no information on the total number of the FMISs with their
respective locations. Therefore, as part of the coming survey, a sample study on the FMISs would be
conducted in conjunction with IDD officers in charge. The WUA or representatives from the
beneficiary farmers of each of the FMISs, whose existence is registered to the IDD, would be
interviewed to collect relevant information on FMISs. It is important to bear in mind that there are
two types of the FMISs: some FMISs managed by the officially registered WUAs and others
Data Collection Survey
6-13 JICA
managed by the beneficiary groups which have not been registered.
Table 6-6-2 (1) Possible items to be studied with JMISs to address ethnic issues
No. Possible Items to be studied Possible information Source
1 The proportion of the ethnicities/castes of the WUA members of the 25 JMISs in Terai region
Officials of the FIMD / IDD
2 A comparison of the proportion of the ethnicities/castes in the WUA executive committee with that in the entire WUA members
Officials of the FIMD / IDD
3 Relationship between each ethnic and social group and the FIMD/IDD Officials of the FIMD / IDD
Representatives from each of the WUAs
4 Positive or negative impact of having different ethnic and social groups within the same WUA , and possible measures to be taken to mitigate or reduce negative impact, if any
Representatives from each of the WUAs
5 The existence and application of the constitution/regulations of WUA, and conditions for the membership stipulated in the WUA constitution/regulations
Representatives from each of the WUAs
6 Relationship among the WUAs of other FMISs/JMIS which share the same main canal or water source
Representatives from each of the WUAs
7 Challenges of the management of the WUA and needs for capacity development
Representatives from each of the WUAs
Source: Survey team
Table 6-6-2 (2) Possible items to be studied with FMISs to address ethnic issues No. Possible Items to be studied Possible
information Source
1 Details of the FMIS(Canal network, Irrigated area, Cropping practices, Availability of delivered water through the year, Existence of rules for water distribution and irrigation system maintenance, etc.)
Representatives from each WUA or alternative organization with similar functions
2 Roles played by the WUA or alternative organizations, Existence of the constitution and/or regulations, organizational structure, the number of the WUA members (beneficiary farmers), conditions for the membership, the proportions of ethnicities /castes in the members
3 A comparison of the proportion of the ethnicities / castes in the WUA executive committee with that in the entire WUA members
4 Reasons for not having registered officially as WUA, if it is the case, and whether they are interested in the registration
5 Relationship with the FIMD/IDD in charge or any other public entities (including local governments)
6 Relationship among the WUAs of other FMISs/JMIS which share the same main canal or water source
7 Challenges in the management by the WUA or alternative organizations and needs for capacity development
Source: Survey team
(2) Lessons from previous projects
The Ministry of Internal Affairs of the GON and the United Nations Development Programme
(UNDP) have been jointly implementing a project to strengthen security at the community level,
called“Armed Violence Reduction and Strengthening Community Security (AVRSCS)” from 2014
to 2016 in the nine districts of Terai region: Kanchanpur, Kailali, Bardiya, Banke, Parsa, Bara,
Irrigation Scheme in Terai
DOI, MOI 6-14
Dhanusha, Saptari, and Morang. The major activity of the project is to strengthen the functions to
maintain security of the National Police, and the emergence of trust between community people and
the police through the implementation of the project has been confirmed.
If there is a case where trust has been built between the protest groups and the police, as part of
results of this project, it would be worthy to analyze the case in order to identify contributing factors
for such a result. Moreover, it would be possible to draw lessons for the prospective JICA-TCP to
enhance the participation of different ethnic and social groups in the project. In the forthcoming
survey, the AVRSCS’s results and approach could be confirmed with officials of the Ministry of
Internal Affairs and UNDP, as well as community people and the police at the project sites, in order
to draw lessons.
(3) Relationship among residents
The information on the relationship, conflict and power balance among different ethnic and social
groups in Terai region should be also collected. If there is an imbalance of powers among residents,
it would be important to take necessary measures on the ground to prevent decision-makings only by
powerful people for the implementation of the prospective JICA-TCP.
2) Recommendations for the implementation of Prospective JICA-TCP
It would be important to assure that there is equity among beneficiary farmers from different ethnic
groups with regard to the benefits and costs (burden) of the O&M of irrigation facilities.
2.1) Selection of the project sites
In order to assure equity in benefits and burden among different ethnic and social groups, the
proportion of ethnic groups in possible project sites should be confirmed prior to the selection of
project sites (irrigation systems). The concentration of benefits only on one specific group should be
avoided. If the situation allows, the project will consider the selection of a location (irrigation
system) where different ethnic and social groups would work in collaboration to achieve common
goals.
If there is an irrigation system in those places where the emergence of trust between communities
and the police is confirmed through the implementation of the aforementioned AVRSCS, it can be
considered to include such a system in the project sites.
On the other hand, those locations where conflicts are on-going or most likely conflicts will occur
near future, the timing of the commencement of project activities needs to be examined. It is
necessary to analyze the updated information on security which is collected from the implementing
agencies, local governments of possible project sites, police, JICA Nepal Office, Japanese Embassy
in Nepal, etc. to select the project sites.
2.2) Selection of beneficiaries
It is important to make a balance in the distribution of benefits among different ethnic and social
groups and avoiding a concentration of benefits only on a specific group, as proposed earlier. When
there are seen internal separations and conflicts within a group, it is also important to take it into
account to select beneficiaries in order not to exacerbate the situation.
Data Collection Survey
6-15 JICA
2.3) Reduction of negative impact
A delay in the implementation of a project or any changes in the contents of project activities could
deepen mistrust of people in Terai region against the GON. Such mistrust could cause a delay or
suspension of a part or the entire project activities.
It is important for both the implementing agencies and JICA to make the project operation plan
realistic, and take necessary measures to assure the allocation of budget and human resources for the
implementation of the project, so that the project can be implemented smoothly as planned.
2.4) Observations for the implementation of the prospective project
Taking into account that Nepal is one of the conflict affected countries, a PNA for the targeted area
or a PNA for the project should be conducted at the project formulation, so that the project can be
designed not to worsen instability factors and to utilize or enhance stability factors. During the
implementation period, the PNA should be updated periodically, and the project should be allowed to
be flexible to modify its contents, including the re-location of the project sites, when necessary. It is
also important for all the institutions involved in the project implementation to agree that the security
of beneficiaries and of people who are engaged in the project implementation should be prioritized at
any time, as well as measures to be taken in case of emergency.
DOI is the government agency in charge of the development and O&M of irrigation systems, and the
majority of its officers are engineers. However, they are also socially sensitive by facilitating the
participation of oppressed people in the decision-making process of WUAs in accordance with a
statement in the Irrigation Policy 2013: “there shall be proper representation of Dalit, Downtrodden,
and Backward ethnic communities is such association”. DOI is working with all farmers in an
equitable manner, since they should be equal, having the same rights as WUA member. In addition,
DOI is promoting the democratic management of WUAs.
In the existing JMISs in Terai region, the WUA members are beneficiary farmers, although WUAs
are under the establishment process in some JMISs. Both those farmers who have the ownership of
agricultural land and practice agriculture, and others who are renting the agricultural land in a legally
or customarily effective manner and practice agriculture can be members of a WUA. Those irrigation
systems with WUAs composed only of large scale farmers cannot be selected as project sites, but the
proportion of socially oppressed people of the target WUAs may not be fully controlled by the
project, since it depends on the situation of land ownership, and the scales of farmers who are renting
the farming land within the project sites.
References: Category Author Year Title Source
General European Parliament 2014 "At a glance: Nepal's political parties and the difficult road towards a new Constitution "November 2014
http://www.europarl.europa.eu/RegData/etudes/ATAG/2014/542165/EPRS_ATA(2014)542165_REV1_EN.pdf
General Informal Sector Service Center
2015 Human Rights Year Book 2015 http://www.insec.org.np/pics/publication/1429808399.pdf
General KARKI, Budhi & EDRISHINHA, Rohan
2014 The FEDERALISM debate in Nepal: Post Peace Agreement, Constitution Making in Nepal Volume II
http://www.np.undp.org/content/dam/nepal/docs/projects/UNDP_NP_SPCBN_the-federalism-debate-in-nepal.pdf
General Ministry of Environment 2010 Climate Change Vulnerability Mapping for Nepal
http://www.nccsp.gov.np/publication/2010ClimateChangeVulnerabilityMappingforNepal.pdf
General JICA Nepal Office 2011 Nepal NGO Handbook (Japanese) https://www.jica.go.jp/nepal/office/about/ngodesk/materials/ku57pq00000qgi4x-att/NGO_Handbook01.pdf
Administrative System
Asia Foundation 2012 A Guide to Government in Nepal: Structures, Functions, and Practices
http://asiafoundation.org/resources/pdfs/AGuidetoGovernmentinNepal.pdf
Administrative System
DEVKOTA, K. L. (International Center for Public Policy)
2014 "Impact of Fiscal Decentralization on Economic Growth in the Districts of Nepal"
http://scholarworks.gsu.edu/cgi/viewcontent.cgi?article=1011&context=icepp
Administrative System
Food and Agriculture Organization of the United Nations (FAO)
2010 Agricultural Extension Services Delivery System in Nepal
ftp://ftp.fao.org/OSD/CPF/Country%20NMTPF/Nepal/AgExtServDelSysNepal.pdf
Administrative System
PANDEY, ReshmiRaj (Ministry of Federal Affairs and Local Development of Nepal)
N/A Decentralization, Devolution and Local Governance in Nepal (Presentation)
http://dms.nasc.org.np/sites/default/files/documents/Decentralization,%20Devolution%20and%20Local%20Governance%20in%20Nepal.pdf
Administrative System
PAUDEL, Laxmi Kant 2011 "Governance of Agriculture Service Delivery in Nepal: Status, Issues, and Challenges"
http://sjpg.pactu.edu.np/system/files/journal/articles/6__laxmi_kant_paudel__governance_of_agriculture_service_delivery_in_nepal__status_issues_and_challenges.pdf
Administrative System
SIJAPATI, Suman and PRASAD, Krishna Chandra
N/A "IMPROVING GOVERNANCE IN NEPAL’S WATER RESOURCES SECTOR THROUGH INSTITUTIONAL CHANGES"
file:///C:/Users/hiro-yashiki/Downloads/IMPROVING_GOVERNANCE_IN_NEPAL'S_WATER_RESOURCES_SE.pdf
Administrative System
Rie Yasuda 2004 Assistance for Democratic Governance and Decentralization by UNDP : A Case of Decentralization in Nepal
http://ci.nii.ac.jp/naid/110004628078
Administrative System
Rie Yasuda 2005 Local Governance Structure in Nepal : Where is Local Self-Governance Act (1999) going?
http://ci.nii.ac.jp/naid/110004628081
Administrative System
作増良介 2010 ”ネパールの地方行政システムの現状
と課題 ―シャンジャ郡自治体の予
算執行分析を通して―”
http://www.idcj.or.jp/pdf/idcjr200901.pdf
Finance Financial Comptroller General Office
2015 Consolidated Financial Statement Fiscal Year 2013/14
http://www.fcgo.gov.np/wp-content/uploads/book-mater-1.pdf
Finance Ministry of Finance N/A Red Book FY 2014/15 http://www.mof.gov.np/uploads/document/file/Red%20Book%20FY%202014-15_20140917050612.pdf
Policies/ Plans
Council of Ministers N/A Irrigation Policy, 2060 http://doi.gov.np/wp-content/uploads/2015/10/IrrigationPolicy2060-EnglishFinal.pdf
Policies/ Plans
Ministry of Agriculture Development
2015 Agriculture Development Strategy (ADS) 2015-2035
http://www.moad.gov.np/downloadfile/final%20ADS%20report_1440476970.pdf
Policies/ Plans
Ministry of Agriculture Development
2016 Nepal: Zero Hunger Challenge National Action Plan (2016 - 2025)
http://www.npc.gov.np/images/download/ZHC_NAP_(2016_-_2025).pdf
Policies/ Plans
National Planning Commission
1995 Nepal Agriculture Perspective Plan 1995/96-2014/15 A.D. (Final Report) Summary Document
http://lib.icimod.org/record/4168/files/APROSC%20Nepalagricultureperspectiveplan630AGN.pdf
Policies/ Plans
National Planning Commission
2013 AN APPROACH PAPER TO THE THIRTEENTH PLAN (FY 2013/14 – 2015/16)
http://faolex.fao.org/docs/pdf/nep150783.pdf
Policies/ Plans
National Planning Commission
2015 Sustainable Development Goals 2016-2030 National (Preliminary) Report
http://www.np.undp.org/content/dam/nepal/docs/reports/SDG%20final%20report-nepal.pdf
Category Author Year Title Source Policies/ Plans
National Planning Commission & Asia Development Bank
2015 Envisioning Nepal 2030 - Proceedings of the International Seminar -
https://www.adb.org/sites/default/files/publication/185557/envisioning-nepal-2030.pdf
Policies/ Plans
National Planning Commission
2010 The Food Security Atlas of Nepal http://documents.wfp.org/stellent/groups/public/documents/ena/wfp223377.pdf?_ga=1.128096972.1357272805.1475940085
Policies/ Plans
Office of the Prime Minister and Council of Ministers
2015 Policies and Programmes of the Government of Nepal for Fiscal Year 2072-73 (2015-16)
http://www.nra.gov.np/uploads/brochure/uR3txdcPfC160114062655.pdf
Policies/ Plans
Water and Energy Commission Secretariat
2002 "Executive Summary: Water Resources Strategy - Nepal -"
http://www.wecs.gov.np/uploaded/water-resources-strategy.pdf
Policies/ Plans
Water and Energy Commission Secretariat
2005 National Water Plan http://www.moen.gov.np/pdf_files/national_water_plan.pdf
Statistics Central Bureau of Statistics
2011 NEPAL LIVING STANDARDS SURVEY 2010/11: STATISTICAL REPORT VOLUME ONE
http://siteresources.worldbank.org/INTLSMS/Resources/3358986-1181743055198/3877319-1329489437402/Statistical_Report_Vol1.pdf
Statistics Central Bureau of Statistics
2011 NEPAL LIVING STANDARDS SURVEY 2010/11: STATISTICAL REPORT VOLUME TWO
http://siteresources.worldbank.org/INTLSMS/Resources/3358986-1181743055198/3877319-1329489437402/Statistical_Report_Vol2.pdf
Statistics Central Bureau of Statistics
2012 National Population and Housing Census 2011 (National Report) Volume 01
http://unstats.un.org/unsd/demographic/sources/census/wphc/Nepal/Nepal-Census-2011-Vol1.pdf
Statistics Central Bureau of Statistics
2013 STATISTICAL YEAR BOOK OF NEPAL 2013
http://cbs.gov.np/image/data/Publication/Statistical%20Year%20book%202013_SS/Statistical-Year-book-2013_SS.pdf
Statistics Central Bureau of Statistics
2014 POPULATION ATLAS OF NEPAL 2014
http://cbs.gov.np/atlas/
Statistics Central Bureau of Statistics
2014 STATISTICAL POCKET BOOK OF NEPAL 2014
http://cbs.gov.np/image/data/Publication/Statistical%20Pocket%20Book%202014.pdf
Statistics Central Bureau of Statistics
2015 Nepal - National Sample Census of Agriculture 2011-2012
file:///C:/Users/hiro-yashiki/Downloads/ddi-documentation-english-53.pdf
Statistics Department of Roads N/A ROAD NETWORK DATA http://www.dor.gov.np/documents/5.%20Road%20Network%20Data.pdf
Statistics International Centre for Integrated Mountain Development and Central Bureau of Statistics
2003 Mapping Nepal Census Indicators 2001 and Trends
http://lib.icimod.org/record/21217/files/MappingNepalCensus2001.pdf
Statistics National Planning Commission & United Nations Development Programme Nepal Office
2014 Nepal Human Development Report 2014: Beyond Geography: Unlocking Human Potential
http://hdr.undp.org/sites/default/files/nepal_nhdr_2014-final.pdf
Statistics United Nations Development Programme
2015 Human Development Report 2015: Work for Human Development
http://hdr.undp.org/sites/default/files/2015_human_development_report.pdf
Statistics World Bank 2016 Global Economic Prospects: Divergences and Risks
http://pubdocs.worldbank.org/en/842861463605615468/Global-Economic-Prospects-June-2016-Divergences-and-risks.pdf
Land Ownership
Community Self Reliance Centre (CSRC), Land Watch Asia, Asian NGO Collation for Agrarian Reform and Rural Development (ANGOC)
2009 Land and Land Tenure Security in Nepal (Country Study: Nepal)
http://csrcnepal.org/uploads/publication/y6nhKRaVwrhsbVf2AeClUdDUkcd-M7F8.pdf
Land Ownership
STEIN, Danielle and SUYKENS, Bert
2014 LAND DISPUTES AND SETTLEMENT MECHANISMS IN NEPAL’S TERAI
http://eprints.lse.ac.uk/56348/1/JSRP_Paper12a_Land_disputes_and_settlement_mechanisms_Suykens_and_Stein_2014.pdf
Land Ownership
SUBEDI, Bhishma P., DAS, Chintamani L. and MESSERSCHMIDT, Donald A.
N/A Tree and Land Tenure in the Eastern Terai, Nepal: A Case Study from the Siraha and Saptari Districts, Nepal
http://www.fao.org/docrep/v2670e/v2670e02.htm
Land Ownership
United States Agency for International Development
N/A USAID COUNTRY PROFILE: PROPERTY RIGHTS AND RESOURCE GOVERNANCE - NEPAL -
http://www.usaidlandtenure.net/sites/default/files/country-profiles/full-reports/USAID_Land_Tenure_Nepal_Profile.pdf
Category Author Year Title Source Land Ownership
WILY, Liz Alden with CHAPAGAIN, Devendra & SHARMA, Shiva
2008 Land Reform in Nepal: Where is it coming from and where is it going?
https://www.researchgate.net/publication/270956263_Land_Reform_in_Nepal_Where_is_it_Coming_from_and_Where_is_it_Going
Land Ownership
Konomi SAITO,Katsuhiro SAITO and Damaru Ballabha Paudel
2015 A Simulation Analysis on Land Reform in Nepal
http://libir.soka.ac.jp/dspace/bitstream/10911/4473/1/%E9%BD%8B%E8%97%A4%E4%B9%8B%E7%BE%8E%E3%83%BB%E9%BD%8B%E8%97%A4%E5%8B%9D%E5%AE%8F%E3%83%BB%E3%83%91%E3%82%A6%E3%83%87%E3%83%AB%20%E3%83%80%E3%83%9E%E3%83%AB_%E5%89%B5%E4%BE%A1%E7%B5%8C%E6%B8%88%E8%AB%96%E9%9B%8644%E5%B7%BB.pdf
Japanese Government’s Policy
株式会社国際開発センター 2013 ネパール国別評価(第三者評価)報
告書 http://www.mofa.go.jp/mofaj/gaiko/oda/shiryo/hyouka/kunibetu/gai/nepal/kn12_01_index.html
Japanese Government’s Policy
外務省 2012 対ネパール連邦民主共和国 国別援
助方針 http://www.np.emb-japan.go.jp/jp/pdf/odapolicy.pdf
Agriculture/ Irrigation
Asia Development Bank N/A "SECTOR ASSESSMENT (SUMMARY): AGRICULTURE AND NATURAL RESOURCES"
https://www.adb.org/sites/default/files/linked-documents/cps-nep-2013-2017-ssa-04.pdf
Agriculture/ Irrigation
Asia Development Bank N/A "SECTOR ASSESSMENT (SUMMARY): IRRIGATION - Nepal: Community Irrigation Project-"
https://www.adb.org/sites/default/files/linked-documents/38417-02-nep-ssa.pdf
Agriculture/ Irrigation
DARBAS, Toni; SULAIMAN, Rasheed; MITTAL, Nimisha; DAVKOTA, Kamal and BROWN, Peter R.
2015 Institutional Analysis for Agricultural Innovation: Synthesis
http://www.sias-southasia.org/new/wp-content/uploads/2015/12/Darbas-et-al_Institutional-Analysis-Synthesis_Technical-Report.pdf
Agriculture/ Irrigation
Jalsrot Vikas Sanstha (JVS)
2015 Integrity Mapping in Irrigation Projects Final Report (JVS)/GWP Nepal November
http://www.gwp.org/Global/ToolBox/Case%20Studies/Asia%20and%20Caucasus/CS_480_Nepal_WIN%20mapping%20report%202015.pdf
Laws/ Regulations
ARYAL, Ravi Sharma 2011 THE LAW ON OWNERSHIP AND RIGHT TO WATER IN NEPAL
http://www.jvs-nwp.org.np/sites/default/files/Water%20Right%20and%20Ownership%20in%20Nepal.pdf
Laws/ Regulations
International Foundation for Electoral Systems
2016 Factsheet on Electoral Provisions in Nepal’s New Constitution
https://www.ifes.org/sites/default/files/2016_ifes_nepal_electoral_provisions_constitution_factsheet_final.pdf
Laws/ Regulations
KANSAKAR, Dibya Ratna 2011 REGULATING COMMON POOL GROUNDWATER UNDER FUGITIVE SURFACE WATER LAW: LIMITATIONS IN LAWS AND REGULATIONS IN NEPAL
http://www.jvs-nwp.org.np/sites/default/files/Water%20Laws%20and%20Regulations%20in%20Nepal.pdf
Laws/ Regulations
WaterAid Nepal 2005 Water Laws in Nepal: Laws Relating to Drinking Water, Sanitation, Irrigation, Hydropower and Water Pollution
file:///C:/Users/hiro-yashiki/Downloads/water%20laws%20in%20nepal%20(1).pdf
Laws/ Regulations
1964 The Lands Act, 2021(1964) http://faolex.fao.org/docs/pdf/nep6239.pdf
Laws/ Regulations
1992 WATER RESOURES ACT, 2049 (1992)
http://www.wecs.gov.np/uploaded/Water-Resources-Act-2049-english.pdf
Laws/ Regulations
1999 Local Self Governance Regulation, 2056 (1999)
http://www.mofald.gov.np/sites/default/files/Resources/docs_25.pdf
Laws/ Regulations
1999 LOCAL SELF-GOVERNANCE ACT, 2055 (1999): AN ACT MADE TO RPOVIDE FOR LOCAL SELF-GOVERNANCE
http://www.undp.org/content/dam/nepal/docs/reports/governance/UNDP_NP_Local%20Self-Governance%20Act%201999,%20MoLJ,HMG.pdf
Laws/ Regulations
2000 Irrigation Rules, 2056 (2000) http://faolex.fao.org/docs/pdf/nep27488.pdf
Laws/ Regulations
2008 Good Governance (Management and Operation) Act, 2064 (2008)
http://faolex.fao.org/docs/pdf/nep137755.pdf
Laws/ Regulations
2015 The Constitution of Nepal http://www.nepalembassy-germany.com/pdfs/Constitution_full_english.pdf
*The date of the last access to all the references was October 9, 2016.