Page 1: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION

LAVOCHKIN ASSOCIATION

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

IKI, 13 October 2010

M. MartynovDeputy General Designer

Moscow Solar System Symposium

Page 2: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

"PHOBOS-GROUNT" MAIN MISSION PARAMETERS

• Investigation of Phobos's substance delivered to the earth in laboratory conditions;

• Investigation of Phobos and Mars;• Realisation of joint researches with the

Chinese microsatellite

Launch site Baikonur

Launch date November 2011

Launch vehicle "Zenit-2"

Earth-Mars flight duration 10 – 11.5 months

Lift-off from Phobos February – March 2013

Mars-Earth flight duration 10.5 – 11.5 months

Date of arrival to the Earth August 2014

Total mission duration ~ 33-34 months

Mass of scientific equipment 50 kg

Mass of Phobos soil samples 0.2 kg

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Page 3: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

MISSION PROFILE

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Page 4: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

MAIN PARAMETERS OF THE "PHOBOS GROUNT" SC

Parameter Value

SC mass, including:– main propulsion (fuelled)– flight module (fuelled)– return vehicle (fuelled)– return capsule– Spacecraft YH-1

13 500 kg

11 375 kg

1 560 kg

285 kg

11 kg

115 kg

Frequency range of communication line:– flight module - Earth– return vehicle - Earth

Х -band

Х -band

Information rate at maximal distance:– flight module– return vehicle

4 bit/s, 16 Kbit/s

8 bit/s

Solar arrays area:– flight module– return vehicle

10 m2

1.64 m2

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Return capsuleReturn vehicle

Flight module

SC YH-1

Mainpropulsion

Jettisonable block of tanks

Truss

Page 5: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

RETURN CAPSULE

Basic state:• RC braking in atmosphere of the Earth performs only by aerobraking without

use of parachute system which as has shown world experience, can fail;• Applied form of the return capsule which aerodynamic characteristics are well

known;• RC landing performs on testing area "Sary-Shagan" which is equipped by

necessary measuring instruments for definition of a landing point of RC which do not have active instruments such as a radio beacon.

Page 6: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Page 7: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

2009

Page 8: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Soil type Manipulator of LA Manipulator of IKI

prehensile type penetration type collect type

Small dispersed (sand) + + +

Small Stone + + Only together with sand

Massive rock - + -

Page 9: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Page 10: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Testing model

Structure mockup Antenna mockup Landing deviceBurn test of propulsion subsystem

Page 11: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

Autonomous thermovacuum test

of return module

Integrated thermovacuum test

of return module

Autonomous thermovacuum test

of flight module

Integrated thermovacuum test

of flight module

Thermovacuum tests

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Page 12: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

Static testTransportation

loadsAircraft landing Centrifuge Vibration test

Vibrostatic tests

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Page 13: FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION "PHOBOS-GRUNT" PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT IKI, 13 October

""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT

Milestone

Soil sampling developmentJanuary 2010 - December

2010

Flight module electrical testsOctober – November

2010

Chinese microsatellite delivery 20 December 2010

Final assemblage of a space craft, electrical tests December 2010 – January

2011

Electrical tests in vacuum chamber February - march 2011

Final operations July – august 2011

Operations in Launch site September 2011

Launch November 2011