    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    2

    SECTION B - SUPPLIES OR SERVICE AND PRICE/COST

    B.1 This is an Open Market Solicitation with a 40% CBE Set Aside requirement.

    B.2 The District of Columbia Public Library Office of Procurement is seeking one contractor,to provide Design/Build Services to complete the construction of a modular unit forFrancis Gregory Interim Library in the District of Columbia, in accordance with the termsand conditions herein.

    B.3 Preferences for Local Businesses, Disadvantaged Businesses, Resident-ownedBusinesses, Small Businesses, Longtime Resident Businesses, or Local Businesses withPrincipal Offices Located in an Enterprise Zone

    Under the provisions of the Small, Local, and Disadvantaged Business EnterpriseDevelopment and Assistance Act of 2005 (the Act), Title II, Subtitle N, of the Fiscal

    Year 2006 Budget Support Act of 2005, D.C. Law 16-33, effective October 20, 2005,the District shall apply preferences in evaluating proposals from businesses that aresmall, local, disadvantaged, resident-owned, longtime resident, or local with a principaloffice located in an enterprise zone of the District of Columbia.

    B.4 The District contemplates award of a Firm Fixed Price Contract. The estimated pricerange for this requirement is between $650,000.00 and $850,000.00.

    B.5 PRICE

    The Offeror shall submit its price proposal as indicated in the space below. In general the

    price shall be broken down into the following segments:

    Overall Modular Builders Fee (Overhead and Profit) $________Pre-Construction Services (design and permits) $________Modular Builders General Conditions $________18-month lease cost $________Site Preparation and Build Out $________Delivery Charge $________Close-out, Removal and Restoration $________

    Total Project Cost $________

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    2/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    3

    SECTION C: DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

    C.1 BACKGROUND

    C.1.1 This solicitation is to engage one General Contractor/Modular-Builder to completethe design, construction, delivery, set-up and interior fit-out construction for theFrancis Gregory Interim Library in the District of Columbia (the Project). TheGeneral Contractor/Modular-Builder will be responsible for the design, construction,deliver, set-up and the interior fit-out of Interim Library if awarded this contract. TheInterim library is located at the Anne Beers Elementary School located along 36thStreet in Southeast Washington DC. See attached Attachment J.1 Aerial LocationMap.

    C.1.2 The Interim neighborhood library is intended to maintain and expand the level ofexcellence for District libraries and shall provide library users with easy access to

    desired material and technology. The modular unit should be of the highest qualityand functionality. DCPL hopes that this Interim library will symbolically celebratethe important values of knowledge, learning, community, diversity, and sustainability.The library will be approximately 3, 600 square feet in size. A basis of design thatgenerally describes the Interim library is Attachment J.2 and should be used by theGeneral Contractor/Modular-Builder as the basis for design.

    C.1.3 The Interim library location will be located along 36th Street SE in Washington DC inthe northwest corner of the multi-purpose field of the existing Anne Beers ElementarySchool. The General Contractor/Modular Builder shall plan accordingly in order todeal with construction activity taking place adjacent to an elementary school. The

    General Contractor/Modular Builder will required to coordinate their constructionphasing, delivery and traffic control with DC Office of Public Education FacilitiesManagement, and the principal of Anne Beers Elementary School.

    C.1.4 The Library acknowledges the importance of a sustainable design. The Library isNOT seeking official LEED certification on this project; however the Library wouldlike to implement as many green and sustainable features as possible.

    C.2 SCOPE:

    C.2.1 The General Contractor/Modular-Builder shall provide all of the necessary labor,

    equipment, supplies, and other resources necessary to complete the design andconstruction of the Francis Gregory Interim Library according to the terms andconditions of this solicitation and the subsequent negotiated contract. The Interimlibrary shall be completed no later than January 31, 2010. The Library definessubstantial completion as having received a Certificate of Occupancy from theDistrict Department of Consumer and Regulatory Affairs (DCRA). DCPL envisionsthat construction should be able to begin on or about December 1, 2009. Earlycompletion is strongly encouraged. The DCPL contemplates that after the design and

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    3/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    4

    fit-out of the Interim space, the Francis Gregory Interim library will have the samefunctional capabilities as Anacostia, Benning or Watha T. Daniel/Shaw InterimLibraries and that it will include finishes, furnishings and fixtures appropriate for afirst class, state of the art library. Basis of Design Drawings of the Anacostia,Benning and Watha T. Daniel/Shaw libraries is attached as Attachment J.2. The

    General Modular Library Minimum Building Specifications that must be achieved areattached as Attachment J.3.

    C.2.2 The General Contractor/Modular-Builder shall be responsible for all required utilityconnections including but not limited to: public water, public sanitary sewer,electricty and telephone service. The General Contractor/Modular Builder shall carryan allowance in its Site Preparation and Build Out line item to cover all feesassociated with utility connections.

    C.3 Requirements

    C.3.1 Phase 1 (Design Phase)

    C.3.1.1 Schematic: The General Contractor/Modular-Builder shall cause itsOwner/engineer (the A/E) to conduct a thorough review of the Basis ofDesign Drawings AttachmentJ.2 of the new Anacostia, Benning and ShawModular Library drawings (such documents, the Minimum DesignRequirements) which will provide the basis for the design of the FrancisGregory Interim Library. The General Contractor/Modular-Builder shall causeits A/E to review the General Modular Library Minimum BuildingSpecifications Attachment J.3. After this review of both documents iscomplete, the General Contractor/Modular-Builder and its A/E shall meet withDCPL and its representatives to discuss the essential elements of the designand the best way for moving forward. Based on the results of the review andthe following meeting with DCPL, the General Contractor/Modular-Buildershall then cause the A/E to prepare a full set of buildable and permitabledocuments for the new Francis Gregory Interim Library that are consistentwith the Minimum Design Requirements and consistent with the DistrictOffice of the Chief Technology Officer (OCTO) general scope of workattached as Attachment J.4. and that all are acceptable to DCPL.

    C.3.1.2 Design Development/Construction Documents. Based on the approvedschematic design documents, the General Contractor/Modular-Builder shallcause its A/E to prepare a set of buildable and permitable ConstructionDocuments. The General Contractor/Modular-Builder and its A/E shall meetas often as required with DCPL and its representatives to ensure that thedesign is evolving in a mutually acceptable manner. The specific servicesrequired during this phase are:

    a. Select and draft outline specifications for materials, systems, equipmentincluding FF&E.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    4/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    5

    b. Develop detailed and dimensioned plans, wall sections, building section,and schedules.

    c. Early release plans i.e. Foundation to Grade Plans, site and utility plansd. Complete code compliance analysis and drawing.e. Meet with review agencies as required (DCRA, HPO, HMP, DDOT,

    DDOE, WASA, PEPCO, CFA, NCPC, etc).

    C.3.1.3 Deliverables. The following deliverables are required during the designphase.

    a. A reconciliation report that addresses issues raised by DCPL and theGeneral Contractor/Modular-Builder as a result of the 50% DD/CDprogress printing.

    b. Project Budget and Schedule and any revisions or modifications as aresult of changes or directives from DCPL.

    c. A permitable and buildable set of Construction Documents to include

    Civil, Ownerural, Structural and MEP plans and specificationsd. Building permit, applicable trade permits, Certificate of Occupancy andany other District required license or permit to complete the scope ofwork.

    C.3.2 Construction Phase Once DCPL and the General Contractor/Modular-Builderhave agreed that the scope of work can be completed for the agreed Lump Sum Price,the Construction Phase of the project shall commence. During the ConstructionPhase, the General Contractor/Modular-Builder will be required to fully complete theProject in accordance with the plans and specifications as well as the agreed uponLump Sum Price. The work is to be conducted as quickly as possible and must becompleted no later than January 31, 2010. In addition to the above, the followingsections shall be provided during this phase.

    C.3.2.1 Construction Management. The selected General Contractor/Modular-Builder will be required to construct a first-class Interim library in accordancewith the approved Construction Documents. At a minimum it is envisionedthat the General Contractor/Modular-Builder will be required to undertake thefollowing tasks:

    a. Construction and deliver a turn-key, fully functioning Francis GregoryModular Library.

    b. Participate and assist in Project/Planning meetingsc. Maintain full-time on-site construction supervision and provide daily

    inspections, quality control, monitoring, coordination of various trades,record drawings, and daily work log

    d. Conduct weekly progress meetings following a GeneralContractor/Modular-Builder generated agenda with the ProgramManager and all trades.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    5/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    6

    e. Provide general safety and signage and posting for the project and seethat each subcontractor prepares and submits adequate safety programand monitoring throughout the project

    f. Provide DCPL with a written monthly report that includes (i) an updatedschedule analysis, (ii) an updated cost report, (iii) tracking of any project

    issues including the responsible party that are generated at the weeklyprogress meetings and (iv) a monthly review of cash flowg. Manage the change order process with the trade subcontractors to verify

    validity, purpose, and costh. Prepare payment requests including required lien waivers, verify

    accuracy and forward to DCPL for approval and paymenti. Assemble close-out documents requiredj. Provide assistance to DCPL through any applicable warranty periodsk. Provide Principal at Beers Elementary with a weekly schedule of

    activities that can be expected so the school staff can be prepared.

    C.3.2.2 Site Security. The General Contractor/Modular-Builder shall be required toprovide the necessary security personnel to protect the space. The GeneralContractor/Modular-Building shall take the necessary steps to secure theconstruction site from the adjacent Elementary School playing field.

    C.3.2.3 Project Cleanliness. The General Contractor/Modular-Builder shall berequired to manage the work in such a manner so as to minimize the pollutionand debris in or around the construction site. The GeneralContractor/Modular-Builder shall be required to police the school grounds atthe end of each day to ensure no debris is making its way onto their site. TheGeneral Contractor/Modular-Builder shall be required to police the woodedarea to the north of the site that is owned by the National Park Service (NPS)to ensure that no debris is making its way into this area. Any fines issued byNPS shall be the sole responsibility of the General Contractor/Modular-Builder.

    C.3.2.4 Maintenance of Traffic. The General Contractor/Modular-Builder shall beresponsible for providing the necessary flagman and traffic control devices asare required to maintain traffic. The General Contractor/Modular-Buildershall be required to obtain the necessary lane closure and other permitsrequired for its work from the District Department of Transportation, ifneeded.

    C.3.2.5 Permitting, Third Party Review and Inspections. The GeneralContractor/Modular-Builder shall pay for and engage the services of a thirdparty review firm and a permit expediting firm for the permitting process anda third party inspection firm for inspections during the construction phase. TheGeneral Contractor/Modular-Builder shall be responsible for obtaining allrequired permits. The General Contractor/Modular-Builder shall be requiredto cooperate with DCPL and the third party reviewers and inspectors to assist

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    6/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    7

    in completion of the scope of work. The General Contractor/Modular-Builderand/or its consultants shall be responsible for preparing applications and otherdocuments necessary to obtain building permits and certificates of occupancy.DCPL shall execute such instruments as required and the GeneralContractor/Modular-Builder and/or its consultants shall be responsible for

    walking such documents through any and all District agencies to gainnecessary approvals for the duration of the project.

    C.3.2.6 Utility Connections. The General Contractor/Modular-Builder shall beresponsible for design, review, permitting and installation for all electricalpower, water and sanitary sewer service for the Interim library. The GeneralContractor/Modular-Builder is responsible for all installation costs for theservices listed above. The General Contractor/Modular Builder shall beresponsible to pay the respective connection/tap fees. The GeneralContractor/Modular-Builder shall coordinate with the respective agencies forconnections, meters, and sizing of service lines.

    C.3.2.7 Landlord Approvals. The General Contractor/Modular-Builder shall beresponsible for coordinating with the DCPS Office of Educational FacilitiesModernizations (OPEFM) for all aspects of this project. The Libraryanticipates that OPEFM will seek approval on utility connections, tie-ins toexisting building services, work hours, parking restrictions and other relatedactivities. OPEFM contact information will be provided upon award.

    C.4. FF&E and Move-in

    C.4.1 DCPL shall be responsible for the selection, purchase and installation of FF&E. Thisincludes but is not limited to: (i) free standing tables, chairs, and desks, (ii) libraryshelving, and (iii) signage.

    C.4.2 The General Contractor/Modular-Builder shall be responsible for the transport ofDCPL provided IT equipment, books and other library material from 901 G StreetNW, A-Level to the new Interim location. The General Contractor/Modular-Builderis only responsible for transport, loading and unloading. The shelving of books and ITset up will be handled by DCPL personnel.

    C.4.3 The General Contractor/Modular-Builder shall be responsible for the fabrication andinstallation of the circulation desk and staff area millwork as detailed on theconstruction documents.

    C.5 Key Personnel

    C.5.1 In its proposal, each Offeror will be required to identify its key personnel. Keypersonnel shall include, at a minimum, the following individuals: (i) the ProjectExecutive; (ii) the Field Superintendent; and (iii) key Project Managers (i.e. theProject Managers responsible for structural, mechanical, electrical and special

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    7/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    8

    systems). The General Contractor/Modular-Builder will not be permitted to reassignany of the key personnel unless DCPL approves the proposed reassignment and/or theproposed replacement.

    C.6 Licensing, Accreditation and Registration

    C.6.1 The General Contractor/Modular-Builder and all of its subcontractors and subconsultants (regardless of tier) shall comply with all applicable District of Columbia,state, and federal licensing, accreditation, and registration requirements and standardsnecessary for the performance of the contract.

    C.7 Conformance with Laws

    C.7.1 It shall be the responsibility of the General Contractor/Modular-Builder to performunder the contract in conformance with the DCPLs Procurement Regulations and allstatutes, laws, codes, ordinances, regulations, rules, requirements, orders, and policies

    of governmental bodies.

    C.8 Davis-Bacon Act

    C.8.1 The Davis-Bacon Act is applicable to this Project. As such, the GeneralContractor/Modular-Builder and its trade subcontractors shall comply with the wageand reporting requirements imposed by that Act.

    C.9 Apprenticeship Act

    C.9.1 The Apprenticeship Act shall apply to this contract and the GeneralContractor/Modular-Builder and all of its trade subcontractors shall be required tocomply with that act.

    C.10 Time is of the Essence

    C.10.1 Time is of the essence with respect to the contract. The Project must be substantiallycomplete by January 31, 2010. Substantially complete shall mean the Certificate ofOccupancy for the project has been issued. As such, the General Contractor/Modular-Builder must dedicate such personnel and other resources as are necessary to ensurethat the Project is completed on-time and in a diligent, skilled, and professionalmanner.

    C.11 DCPL Responsibilities.

    C.11.1 In general, the General Contractor/Modular-Builder shall be responsible for allpreconstruction and construction phase activities. DCPL shall be responsible for thefollowing activities.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    8/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    9

    C.11.1.1 Zoning. DCPL shall be responsible for obtaining the necessary zoningapprovals for the Project. Any easements which are required for the Projectshall be the responsibility of DCPL.

    C.11.1.2 FF&E, Materials and IT. DCPL shall be responsible for providing IT

    equipment and library materials for the Interim location. DCPL shall also beresponsible for a majority of the FF&E as listed under sections C.4.1 andC.4.2. The General Contractor/Modular-Builder shall be responsible for thescope of work as listed under section C.4.3.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    9/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    10

    PART I

    SECTION D: PACKAGING AND MARKING

    D.1 MATERIAL DELIVERY, HANDLING AND STORAGE:

    A. The Contractor shall deliver materials and equipment in the original, properlylabeled, unbroken packages, containers, cartridges or bundles and in suchquantities and such ample time that progress of work will not be delayed.

    B. The Contractor shall protect materials and products against any damage ordeterioration during transit to the site, unloading, delivering and storing at site,installation or erection and during period between installation or erection and finalacceptance by the District, that shall include, but not limited to:

    1. Minimum exposure to weather during delivery.

    2. Storage off ground in dry, well-ventilated spaces.

    3. Covering, as necessary, for adequate protection from soiling and wetting.

    C. The Contractor shall provide storage methods that will facilitate inspection andtesting before and during the use as follows:

    1. Space for storage of materials and equipment will be approved by theDCPLs Inspector (see Paragraph H.23).

    2. The Contractor shall not occupy more space at the site than is absolutelynecessary for proper execution of the work.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    10/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    11

    PART I

    SECTION E: INSPECTION AND ACCEPTANCE

    E.1 INSPECTION:

    The inspection and acceptance requirements for the resultant contract will begoverned by Article 11 of the Standard Contract Provisions For Use WithSpecifications for District of Columbia Government Construction Projects, dated1973, as amended and incorporated herein by reference. A copy of this booklet isavailable free of charge to the bidders at the Bid Issuance Office located at 901 GStreet, N.W. Washington, DC 20001.

    In addition, the acceptance criteria for different parts of the work, described in othersections of the RFP and Specifications (Section C.3) shall apply.

    E.2 PARTIAL ACCEPTANCE:

    A. The Contracting Officers Technical Representative (COTR) may, at his/heroption, accept part of the work under this contract in writing prior to the COTRsfinal acceptance of all the work under the contract, when the COTR considers itbeneficial to the District of Columbia.

    B. Liquidated damages are not required for this project. SEETIME FORCOMPLETION in Section F.1.

    E.3 FINAL INSPECTION:

    The Contractor shall give the COTR written notice at least fourteen (14) days in advanceof date on which project will be 100% complete and ready for final inspection. Prior tofinal inspection date, the Contractor shall verify in writing that in the Contractors bestjudgment no deficiencies exist.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    11/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    12

    SECTION F - DELIVERIES OR PERFORMANCE

    F.1 CONTRACT TYPE

    The District contemplates award of a Firm Fixed Price Contract.

    F.2 TIME FOR COMPLETION:

    The Contractor shall complete all the work 30 Days after issuance of Notice To Proceed.

    F.3 TERM OF CONTRACT

    F.2.1 Project Schedule. DCPL requires that the Interim library be completed no laterthan January 31, 2010. DCPL envisions that construction should be able to beginin December 1, 2009. Early completion is strongly encouraged.

    F.2.2 Project Delivery Method. DCPL intends to implement the Project through aDesign / Build method.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    12/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    13

    SECTION G - CONTRACT ADMINISTRATION DATA

    G.1 INVOICE PAYMENT

    G.1.1 The District will make payments to the Design-Builder, upon the submission ofproper invoices or vouchers, at the prices stipulated in this contract, for suppliesdelivered and accepted and/or services performed and accepted, less anydiscounts, allowances or adjustments provided for in this contract.

    G.1.2 The District will pay the Design-Builder on or before the 30th day after receivinga proper invoice from the Design-Builder.

    G.2 INVOICE SUBMITTAL

    G.2.1 The Design-Builder shall submit proper invoices on a monthly basis or asotherwise specified in this contract. Invoices shall be prepared in triplicate andsubmitted to the agency Chief Financial Officer (CFO) with concurrent copies tothe Contracting Officer (CO) the Contracting Officer's Technical Representative(COTR) specified in G.7 below. The address of the CFO is:

    Name: Chief Financial OfficerDC Public Library Martin Luther King Jr.

    Address: 901 G Street Northwest, Suite 441Washington, D.C. 20001

    Telephone: 202-727-1198

    G.2.2 To constitute a proper invoice, the Design-Builder shall submit the followinginformation on the invoice:

    G.2.2.1 Design-Builders name, Federal tax ID, DUNS number and invoicedate (Design-Builders are encouraged to date invoices as close to thedate of mailing or transmittal as possible.);

    G.2.2.2 Contract number, block number two (2) and encumbrance number,block number twenty-one (21) of the Solicitation CoverSheet.Assignment of an invoice number by the Design-Builder is also

    recommended, the assigned DCPL Purchase Order Number is required

    G.2.2.3 Description, price, quantity and the date(s) that the supplies/serviceswere actually delivered and/or performed. Contractor shall provide thisinformation with a schedule of values or approved equal.

    G.2.2.4 All sub-contractor and sub-consultant invoices requested under subjectpayment application.;

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    13/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    14

    G.2.2.5 Name, title, telephone number and complete mailing address of theresponsible official to whom payment is to be sent;

    G.2.2.6 Name, title, phone number of person preparing the invoice;

    G.2.2.7 Name, title, phone number and mailing address of person (if differentfrom the person identified in (G.2.2.6) above to be notified in theevent of a defective invoice); and

    G.2.2.8 Authorized signature

    G.3 METHOD OF PAYMENT

    G.3.1 The District will pay the amount due the Design-Builder under this contract inaccordance with the terms of the contract and upon presentation of a

    properly executed invoice.

    G.3.2 The Form of Contract provides that ten percent (10%) of the Design-Build Feewill be withheld as retention. This amount will only be earned by the Design-Builder if the project is delivered before the January 31, 2010 deadline and on theagreed upon budget.

    G.4 ASSIGNMENTS

    G.4.1 In accordance with Title 19 Chapter 43, unless otherwise prohibited by thiscontract, the Design-Builder may assign funds due or to become due as a result ofthe performance of this contract to a bank, trust company, or other financinginstitution

    G.4.2 Any assignment shall cover all unpaid amounts payable under this contract, andshall not be made to more than one party.

    G.4.3 Notwithstanding an assignment of money claims pursuant to authority containedin the contract, the Design-Builder, not the assignee, is required to prepareinvoices. Where such an assignment has been made, the original copy of theinvoice must refer to the assignment and must show that payment of the invoice isto be made directly to the assignee as follows:

    Pursuant to the instrument of assignment dated ___________,make payment of this invoice to _______________________(name and address of assignee).

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    14/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    15

    G.5 CONTRACTING OFFICER (CO)

    G.5.1 Contracts may be entered into and signed on behalf of the District Governmentonly by contracting officers. The address and telephone number of theContracting Officer is:

    Wayne R. MinorChief Procurement OfficerDC Public LibraryOffice of Procurement901 G Street, Northwest, Suite 401Washington, DC 20001

    G.6 AUTHORIZED CHANGES BY THE CONTRACTING OFFICER

    G.6.1 The Contracting Officer is the only person authorized to approve changes in anyof the requirements of this contract.

    G.6.2 The Design-Builder shall not comply with any order, directive or request thatchanges or modifies the requirements of this contract, unless issued in writing andsigned by the Contracting Officer.

    G.6.3 In the event the Design-Builder effects any change at the instruction or request ofany person other than the Contracting Officer, the change will be considered tohave been made without authority and no adjustment will be made in the contractprice to cover any cost increase incurred as a result thereof.

    G.7 CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE (COTR)

    G.7.1 The COTR is responsible for general administration of the contract and advisingthe Contracting Officer as to the Design-Builders compliance or noncompliancewith the contract. In addition, the COTR is responsible for the day-to-daymonitoring and supervision of the contract, of ensuring that the work conforms tothe requirements of this contract and such other responsibilities and authorities asmay be specified in the contract. The COTR for this contract is:

    Lisa DeanesProject Manager for 21

    stCentury Capital Projects

    DC Public Library MLK Jr.901 G Street, Northwest, Suite 443Washington, DC 20001

    G.7.2 It is understood and agreed that the COTR shall not have authority to make anychanges in the specifications/scope of work or terms and conditions of thecontract.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    15/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    16

    G.8 UNAUTHORIZED CHANGES

    G.8.1 Design-Builder may be held fully responsible for any changes not authorized inadvance, in writing, by the Chief Contracting Officer, may be denied

    compensation or other relief for any additional work performed that is not soauthorized, and may also be required, at no additional cost to the District, to takeall corrective action necessitated by reason of the unauthorized changes.

    G.9 LIMITATION OF AUTHORITY

    G.9.1 Only a person with prior written authority from the CCO shall have the express,implied, or apparent authority to alter, amend, modify, or waive any clauses orconditions of the contract. Furthermore, any alteration, amendment, modification,or waiver of any clause or condition of this RFP is not effective or binding unlessmade in writing and signed by the CCO or its authorized representative.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    16/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    17

    PART I

    SECTION H - SPECIAL CONTRACT REQUIREMENTS

    H.1 LIQUIDATED DAMAGES:

    A. Not Applicable.

    H.2 DISTRICT AND DCPL RIGHTS AND RESPONSIBILITIES:

    A. DISTRICT OF COLUMBIA PUBLIC LIBRARY (DCPL)

    1. DCPL serves as the authorized contracting agent for public library improvementProjects for the District of Columbia (District)

    2. The COTR is responsible for the technical administration of the contract and

    advising the Contracting Officer as to the Contractors compliance ornoncompliance with the contract. In addition, the COTR is responsible for theday-to-day monitoring and supervision of the contract, of ensuring that the workconforms to the requirements of this contract and such other responsibilities andauthorities as specified in writing by the Contracting Officer.

    3. DCPL will designate a Project Manager for the Project to consult with the Ownerand the COTR, who shall be authorized to act on behalf of DCPL to performspecific responsibilities of the District under the Contract.

    4. Information and services required of DCPL shall be furnished in good faith and ina timely manner to avoid delay in the progress of the Project.

    5. DCPL shall provide to the Contractor all necessary passes for Contractorsemployees required to enter into the facility.

    6. DCPL officers, agents, employees and consultants shall at all times have access tothe Work whenever the Project is in preparation or progress

    7. DCPL may send directions to the Contractor through the Owner or the COTR.

    8. The foregoing are in addition to other rights and responsibilities of DCPLenumerated herein and especially those in respect to DCPLs right to prosecutethe Work, approve payments and accept the Project.

    9. Upon the issuance of the Notice to Proceed or at a reasonable time thereafter,DCPL shall provide the Contractor the Project site in such condition to permit theContractor to perform the Work.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    17/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    18

    B. DCPLs RIGHT TO PROSECUTE WORK AND BACKCHARGE CONTRACTOR

    1. If the Contractor fails or neglects to prosecute the Work with the necessary

    diligence so as to complete the Work within the time specified in the Drawingsand Specifications or any portion of the Work by the applicable milestone date asset forth in the Construction Schedule, the COTR shall notify the Contractor inwriting of such failure or neglect.

    2. If the Contractor fails to correct any Defective Work within the time fixed in thewritten notice, DCPL may correct such Work and seek recovery of all costs,including any consequential damages, from the Contractor or the Contractor'sSurety.

    3. In such case, a Change Order shall be issued deducting from payments then or

    thereafter due the Contractor the costs of correcting such deficiency.

    4. If the payments then or thereafter due the Contractor are not sufficient to coversuch costs, the Contractor and the Contractor's Surety shall pay the amount of theinsufficiency to DCPL.

    5. The decision of DCPL to back-charge the Contractor shall be final.

    C. DCPLS RIGHT TO PARTIAL OCCUPANCY

    1. If the Owner finds it necessary to occupy or use a portion of the Project prior toContract Completion, such occupancy or use may be accomplished if the COTRinforms DCPL that the area in question has been approved for temporaryoccupancy by the regulatory authorities.

    2. If such Partial Occupancy or use is approved by DCPL, the Owner, through theCOTR, may process either a Change Order or a Contract Completion certificatelisting the deficient Work under the Contract for approval by DCPL, provided thatno such occupancy or use shall commence before any insurers providing propertyinsurance have acknowledged notice thereof and in writing effected any changesin coverage necessitated thereby.

    3. From the date of execution of the Change Order or Contract Completioncertificate by DCPL, the Contractor shall be relieved of obligation to maintain theaccepted portion of the Work, but shall remain obligated to correct any Punch Listitems then uncorrected. The Contractor shall continue to carry the appropriateinsurance during performance of any Punch List Work.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    18/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    19

    4. Partial Occupancy or use of the premises by the Owner shall not constituteacceptance of any Work not in conformity with the Plans and Specifications.Partial occupancy shall not relieve the Contractor of liability for any express orimplied warranties or responsibility for Defective Work.

    H.3 PERMITS, LICENSES AND CERTIFICATES:

    A. The District will be responsible for obtaining the building permit issued by theDepartment of Consumer and Regulatory Affairs (DCRA), Building and LandRegulation Administration, located at 941 North Capitol Street, N.E.,Washington, D.C. The Contractor shall apply for and obtain all other permitsrequired for this project including Raze Permit, certificates and licenses from theOffice of Licenses and Permits, Permit Processing Division, Department ofConsumer and Regulatory Affairs.

    1. The Contractor shall apply and pay for all required permits well inadvance of the time that they are needed.

    2. If the Contractor experiences any difficulty in obtaining a permit, theContractor shall request assistance immediately from the COTR.

    3. The Contractor shall schedule the intermediate and final inspectionsrequired for any permit certification. The Contractor shall give theOwner, the COTR Manager and the Owner reasonable notice of the datearranged for any inspection.

    B. It is the responsibility of the Contractor to ascertain, obtain, maintain and pay for

    the required permits, licenses, fees, tap fees and certificates required by localauthorities for this project. Permits, Licenses and Certificates may include, butare not limited to:

    Permits and Certificates Licenses

    1. Plumbing 1. Master Plumbers2. Electrical 2. Electrical3. Refrigeration 3. Refrigeration4. Elevator 4. Boiler5. Boiler and Pressure Tank 5. Pressure Tank

    6. Public Space - To work in, excavate 6. Elevatorin or occupy

    7. Signs and Temporary Fences8. Work on Sunday and after 6:00 p.m. weekdays.9. Razing

    C. The District will not allow work requiring permits and licenses to proceed untilthe Contractor produces evidence showing that such permits and licenses have

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    19/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    20

    been procured from the DCRA. Permits will be issued only to persons dulylicensed for work in the District of Columbia, except as follows:

    1. Where electrical, plumbing and refrigeration Contractors and their craftpersons perform work under contract with the District of Columbia and

    the work is physically located in areas outside the District of Columbia, itshall be sufficient if any such Contractor and the Contractors craftpersons are licensed either by the District of Columbia or by anygovernmental agency having jurisdiction over the area adjoining the siteon which the work is performed.

    D. The Contractor shall prominently display all permits within the confines of theconstruction site.

    H.4 TEMPORARY FACILITIES, UTILITY CONNECTIONS AND SERVICES:

    The Contractor is responsible for locating all existing utilities and performing therequired modifications to all utilities for the completion of construction. All utility costs,costs to modify and connection fees shall be incorporated into the fixed price bid.

    A. TEMPORARY FACILITIES AND UTILITIES BY OTHERSB. TEMPORARY WATER: For construction purposes, temporary connection to the

    existing water mains is permitted, at the Contractors expense, contingent uponthe Contractor performing the following:

    1. That no connections to water mains be made without first acquiring approvalfrom the District of Columbia Water and Sewer Authority (WASA).

    2. That the Contractor shall furnish all necessary temporary lines, fittings,valves, and make all temporary connections to bring the water to the jobsite.

    3. That all pipe, fittings, and hose used shall be leak proof and that hook-upsand connections be made in a manner comparable to new work to preventunnecessary waste of water.

    4. That all branches from temporary main feed be equipped with tight cut-off valves.

    5. That upon completion of the work, temporary lines, fittings, valves andother accessories are removed; disconnections made and services restoredto an approved condition.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    20/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    21

    C. PERMANENT CONNECTIONS TO MAINS:

    The Contractor shall make and pay for all the required permanent connections forwater, sewer, gas, electrical, telephone and fire alarm systems at its own expense.

    The Contractor shall pay fees and associated costs and make all arrangementswith utility companies and appropriate agencies as may be required for proper andexpeditious completion of the project.

    H.5 SHOP DRAWINGS AND CATALOGUE CUTS:

    A. Within fifteen (15) calendar days from the date of the Notice to Proceed, theContractor shall prepare a complete list of all samples, catalogue cuts and shopdrawings required to be submitted as follows:

    1. The Contractor shall submit the list to the COTR or his designee, the COTR,

    in quadruplicate for approval. The COTR will return one (1) copy of theapproved list to the Contractor.

    2. The District will not make progress payments until the required list has beensubmitted by the Contractor. The District will not make payments for anymaterials installed by the Contractor without approval by the COTR wheresubmittal of the same is required.

    B. The Contractor shall not install or use materials in the work until the COTR hasgiven written approval of required samples, shop drawings or catalogue cuts, to besubmitted as stated above.

    1. Normally, 14 calendar days will be required for checking submittedmaterials. However, more time will be required for more complexsubmittals. The Contractor is advised that submittals that are kept simple(i.e. related to one section of the specifications or to one system) will beprocessed more expeditiously than more complex submittals. Approval ofmaterials, shop drawings, catalogue cuts shall be only for thecharacteristics or uses named in the submission and shall not be construedas:

    a. Permitting any departure from contract requirements except asspecifically stated in the approval.

    b. Relieving the Contractor of the responsibility of complying withthe contract requirements because of errors which may exist.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    21/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    22

    c. Constituting a complete check, but will indicate only that thegeneral method of construction and detailing is satisfactory and theContractor shall be responsible for the dimensions and design ofadequate connections, details and satisfactory construction of all

    work.

    C. The Contractor shall submit all the shop drawings, samples and catalogue cuts inaccordance with the following requirements:

    1. Letter of transmittal, for each transmittal, submitted in triplicate andcontaining the following information:

    a. Project name and contract number;

    b. Work for which material is intended;

    c. Identification of material in accordance with Federal Specificationor A.S.T.M. number, manufacture, model, type, class, brand name,specifications reference, and local distributor;

    d. General Contractors stamp of approval as evidence that drawings,samples, and catalogue cuts included in the submittal have beenchecked for conformity with contract requirements includingdimensions, quality, grade, type, quantity coordination with otherwork and that the Contractor assumes all responsibility for errorsor discrepancies.

    D. SHOP DRAWINGS:

    The Contractor shall submit shop drawings as described below:

    1. Submit six sets of each drawing.

    2. Identified as to project name and number, Contractor, fabricator,manufacturer, model, type, class, brand name, specifications reference,local distributor, and date drawn to which drawing applies.

    3. Drawings shall be complete in every respect and assembled into sets.

    a. Each submission shall show complete system to which it appliesand shall include catalog cuts, samples and other applicable datapertinent to the system.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    22/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    23

    b. The COTR will review and approve the shop drawing submittals,and if approved, will return three (3) sets of the same to theContractor.

    c.

    When corrections to shop drawing prints are necessary, two (2)prints of each shop drawing will be returned to the Contractor forcorrections and resubmission in six sets.

    4. The Contractor shall submit one (1) reproducible print of each approvedshop drawing after final approval of submitted shop drawings has beenmade.

    5. If drawings show variations from contract requirements because ofstandard shop practices or for any other reasons, the Contractor shall makespecific mention of such variation and the cause therefore, in the letter of

    transmittal.

    a. If the variations in the drawings are acceptable to the COTR, he/shemay initiate any changes to the contract under Article 3, Changes,of the Standard Contract Provisions which will be subject to theContracting Officers approval.

    b. If drawings submitted indicate a departure from the contractrequirements which the Contracting Officer finds to be in the bestinterest of the District of Columbia and to be so minor as not toinvolve a change in contract price or time for completion, he mayapprove the drawings.

    E. COMPOSITE SHOP DRAWINGS:

    In addition to shop drawings specified in the various sections of thespecifications, the Contractor shall submit composite shop drawing details ofconstricted spaces, pipe and duct spaces, mechanical, equipment rooms andceiling spaces where pipes, ducts, conduit, crossover and where items such aslight fixture housing project into the space, to ensure that equipment approved foruse or proposed for use fits into the space provided.

    1. In the event of a conflict, the Contractor may offer his suggestions forsolution of the problem on the shop drawing submittal or by lettersubmitted therewith;

    2. Submittal of composite shop drawings shall be provided in 15 days afterNotice to Proceed to prevent a delay in construction.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    23/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    24

    F. The Contractor shall submit, with a letter of transmittal, samples, catalogue cuts,test reports, and certifications, as required. The Contractor shall not submit anysamples and catalogues with bids. The Contractor must refer to the specificationsections for samples, catalogue cuts, test reports and certifications required underthe contract.

    1. The Contractor shall submit the required samples prepaid in duplicate,unless otherwise specified in the applicable specification section.

    2. The Contractor shall submit the required catalogue cuts in six sets.

    3. The Contractor shall submit each item and label it with the followinginformation:

    a. Project name and contract number;b. Work for which material is intended;c.

    Contractor, manufacturer and fabricator;d. Applicable Federal Specification, A.S.T.M. specification or other

    standard;e. Contract specification reference; andf. Manufacturer's brand name, class or grade and type.NOTE: The COTR shall hold for thirty (30) days and then destroysamples submitted without the above labels.

    4. The Contractor shall submit samples of materials that are required tomatch work in place and shall also submit representative samples ofpresent materials which they are to match. The Contractor may take asample of present materials from the work in place, but if this is notpossible, the Contractor will take a sample to the site of the work forinspection and verification.

    5. The COTR will approve a sample submitted only for the characteristics orfor the uses named in such approval and no other purpose.

    a. No approval of a sample shall be taken in itself to change or modifyany contract requirement unless specifically stated in the approval.

    b. The Contractor shall send the approved samples not destroyed intesting back to the COTR.

    c. The Contractor shall mark for identification and use in the work theapproved samples of hardware, miscellaneous accessories and signs ingood condition.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    24/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    25

    d. The COTR may retain for thirty (30) days any samples not destroyedin testing and that are not approved, and then dispose of them or returnthem to the Contractor at his expense if requested within thirty (30)days from the date of rejection.

    6. The COTR will request the Contractor to deliver test samples as specifiedin the various specification sections and other test samples deemednecessary, or the COTR will take the same from various material orequipment delivered by the Contractor for use in the work. The COTRhas the right to request any additional tests from an accredited testingfacility on any materials delivered to the site of the work, at the Districtsexpense.

    7. If any of these test samples fail to meet the specification requirements, anyprevious approvals will be withdrawn and such materials or equipment

    shall be subject to removal and replacement by the Contractor withmaterials or equipment meeting the specification requirements at noadditional cost to the District.

    8. The District may refuse to consider under this contract any further samplesof the same brand or make of material that fails to pass specified tests.

    9. The COTR reserves the right to disapprove any material, which ispresently, or which previously has been, unsatisfactory in service.

    10. The Contractor shall submit material lists, schedules and diagrams formaterial, equipment, fixtures, fittings, hardware required underspecification sections in six sets and labeled as set forth for catalogue cuts.

    11. The Contractor shall identify individual items included in brochures andcatalogs that are submitted for approval in the transmittal letter and in itssubmittal material.

    H.6 PROPRIETARY RESTRICTIONS:

    A. Proprietary names or brands are mentioned for descriptive, not restrictive,purposes and are intended to establish minimum standards of quality formaterials, fabrication and finishes.

    1. Such references shall not be construed as limiting competition orcontrolling selection of manufacturers, and the Contractor in such casesmay submit for approval any item or type of construction which, in thejudgment of the Contracting Officer, expressed in writing, is equal to thatspecified.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    25/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    26

    2. The COTR will judge the submissions on the basis of durability, strength,appearance, serviceability of parts, output, coordination with related workand the ability to fulfill the requirements of the specified item.

    H.7 DEBRIS AND CLEANING:

    A. During the progress of the Work, the Contractor shall be responsible for theremoval of all waste materials and rubbish attributable to the Work to anappropriate disposal site designated by the COTR. The Contractor shall performdaily broom cleaning in the area of the Contractor's Work.

    B. The Contractor shall, at the end of each working day or as directed by the COTR,remove all waste materials and rubbish from the Project.

    C. Upon completion of the work, the Contractor shall remove all equipment,salvaged materials provided for the work (except any materials that are to remain

    the property of the Government of the District of Columbia as provided in thespecifications) and leave the premises in a neat and clean condition satisfactory tothe COTR at the site.

    D. The Contractor shall, as required for the Project or as directed by the COTR,remove any waste materials or rubbish from areas adjacent to the Project.

    E. If the Contractor fails to clean up during the progress of the Work, the provisionof paragraph H.2.B shall be invoked.

    F. If the Contractor fails to maintain the areas adjacent to the Project clean and freeof waste materials and rubbish, upon written notification by the COTR, DCPLshall direct the local jurisdiction having responsibility for the area to clean thearea.

    G. The cost of cleaning the area adjacent to the Project shall be deducted from theresponsible Contractor as the COTR recommend and the Department determinesto be just.

    H. The decision of DCPL shall be final.

    I. FINAL CLEANING

    1. At the completion of the Work, the Contractor shall restore all propertynot designated for alteration by the Plans and Specifications to as near itsoriginal condition as practicable and clean the site of all waste materialsand rubbish attributable to the Work, including without limitation:

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    26/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    27

    2. Clean transparent materials, including mirrors and glass in doors andwindows, leaving both sides of the glass in a polished condition;

    3. Replace chipped, scratched or broken glass or other damaged transparentmaterials;

    4. Remove excess glazing or caulking compound, and other substances thatare noticeable vision-obscuring materials;

    5. Remove labels that are not permanent, remove marks, stains and soiledspots from finished surfaces;

    6. Remove dust, dirt, marks, stains, paint droppings and other blemishes andleave in polished condition all equipment and material with exposedfinished surfaces, including, without limitation, ceilings, walls, doors,counter tops, piping, ductwork, air inlet and outlet devices, hangers and

    supports, unit ventilators, aluminum or stainless steel trim and finishhardware;

    7. Clean exposed exterior and interior hard-surfaced finishes to a dust-freecondition, free of stains, films and similar foreign substances;

    8. Vacuum carpeted surfaces, damp mop all hard floors, sweep paved areasbroom clean, rake grounds that are neither paved nor planted to a smootheven-textured surface, and broom clean and damp mop concrete floors;

    9. Clean washable air filters or replace all air filters at the Project;10. Remove all waste materials and rubbish from any roof surface and clean

    any roof drains;

    11. Remove any temporary controls required pursuant to the storm waterpollution prevention plan and permit.

    12. At the completion of the Project, the electrical Contractor shall clean alllight fixtures, which includes, without limitation, removing bugs, debris,stains, rust and dirt, and replacing any burned out or substantiallydiminished light bulbs.

    13. Unless otherwise specified in the Plans and Specifications, the Contractorshall strip, apply one (1) seal coat, two (2) finish coats of wax and shallpolish all resilient flooring, except waxless floors.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    27/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    28

    14. Should any Work be performed after a final cleaning by the Contractor,the Contractor responsible for such Work shall clean any affected areaagain as provided above so that upon Contract Completion, the premisesshall be left ready for occupancy by the Owner.

    15.

    Final cleaning shall be done to the reasonable satisfaction of the Owner,the COTR and the Owner.

    16. If the Contractor fails to clean up at completion of the Work, the provisionof paragraph GC 5.3 shall be invoked.

    17. If a dispute arises among Contractors as to responsibility for finalcleaning, the COTR or the Owner may authorize another Contractor, orengage a qualified cleaning company, to perform the clean up, and deductthe cost from amounts due to those Contractors responsible as the COTRor the Owner recommend and DCPL determines to be appropriate. The

    decision of DCPL on the responsibility for such cost shall be final.

    H.8 MATERIALS AND WORKMANSHIP:

    A. Unless otherwise specified, all materials and equipments incorporated in the workunder the contract shall be new. All workmanship shall be first class and bypersons qualified in the respective areas.

    B. In the absence of specific requirements for installation of a material or product,the Contractor will be held responsible for installation of said material or productin strict accordance with the manufacturer's printed instructions andrecommendations.

    C. UNCOVERING THE WORK

    1. If any Work is covered contrary to the requirements of the Plans andSpecifications or to the written request of the Owner or the COTR, such Workmust, if required by the Owner or the COTR in writing, be uncovered forobservation and replaced, if not in conformity with the Plans andSpecifications, and recovered at the Contractor's expense.

    2. If any Work has been covered in accordance with the Plans and Specificationsand is Work which the Owner or the COTR had not requested the opportunityto observe prior to covering, the Owner or the COTR may request that suchWork be uncovered by the Contractor.

    3. If such Work is found not to be in conformity with the Plans andSpecifications, the Contractor shall pay all costs of uncovering, replacing andrecovering the Work, unless it is found by DCPL that such condition wascaused by another Contractor.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    28/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    29

    4. If such Work is found to be in conformity with the Plans and Specifications,the cost of uncovering and replacing and recovering the Work shall, byappropriate Change Order, be paid to the Contractor.

    D.

    CORRECTION OF THE WORK

    1. The Owner, through the COTR, shall notify the Contractor in writing if anyWork is found by the Owner to be Defective, whether observed before or afterContract Completion. The Owner or the COTR shall specify in the writtennotice the time within which the Contractor shall correct the Defective Work.

    2. The Contractor shall bear all costs of correcting such Defective Work,including the cost of any consequential damages.

    3. If the Contractor fails to correct any Defective Work within the time fixed inthe written notice, DCPL may correct such Work and seek recovery of allcosts, including any consequential damages, from the Contractor or theContractor's Surety.

    E. SUBSTITUTIONS1. Substitutes for Standards or Approved Equals shall not be considered after

    the bid opening unless the Contractor can conclusively demonstrate to theOwner one of the following conditions:

    2. Unavailability of all Standards or Approved Equals through no fault of theContractor or the Contractor's Subcontractors and Material Suppliers;

    3. All Standards or Approved Equals are no longer produced;4. All Standards or Approved Equals will not perform as designed.

    F. LABOR1. The Contractor shall maintain a sufficient workforce and enforce good

    discipline and order among the Contractor's employees the employees ofthe Contractor's Subcontractors and Material Suppliers. The Contractorshall not permit employment of unfit persons or persons not skilled intasks assigned to them.

    2. The Contractor shall dismiss from the Project any person employed by theContractor or the Contractor's Subcontractors and Material Suppliers whois found by DCPL, pursuant to a recommendation from the COTR or theOwner, to be incompetent, guilty of misconduct, or detrimental to theconstruction of the Project.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    29/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    30

    3. The Contractor shall employ all legal efforts to minimize the likelihood oreffect of any strike, work stoppage or other labor disturbance.Informational pickets shall not justify any work stoppage.

    H.9 STANDARDS:

    A. Any material specified by reference to the number, symbol or title of a specificstandard such as a Commercial Standard, a Federal Specification, ASTMcertification or other similar standard, shall comply with the requirements in thelatest revision hereof.

    B. The District will not furnish any copies of the applicable Federal Specifications,Commercial Standards and other standard specifications to the bidders. However,the Contracting Officer will furnish upon request, information as to how copies ofthe standards referred to may be obtained, and it will be responsibility of the

    requestor to obtain the necessary documents from respective sources.

    C. Where a standard is referred to in the various sections of these specifications, itshall include the installation requirements specified therein unless specificallymodified in the contract specifications.

    H.10 EQUIPMENT COORDINATION:

    It shall be the responsibility of the Contractor to ascertain that the make and model of allshop or factory fabricated equipment furnished not only meets all requirements of thecontract document, but it shall be of the proper physical size and dimension to fit the space orarea, ductwork, conduit, panel boxes, disconnect switches and related accessory equipment.Where the physical size of any equipment is dependent upon other equipment, coordinationshall be done by the Contractor to assure that they are compatible and will fit within thelimitations of the space where they are to be located, including coordinating of utilityconnections and coordination of space for servicing the equipment, changing filters, cleaningtubes and similar operations.

    H.11 STOPPAGE OF WORK AND CONTRACT TERMINATION:

    If the Contractor fails to abide by any, or all, of the provisions of the contract, theContracting Officer reserves the right to stop all the work, or any portion thereof, affectedby the Contractors failure to comply with the contract requirements. This stoppage willremain in effect until the Contractor has taken action to meet the contract requirements,or any separable part thereof. After written notification and work stoppage, the Districtmay terminate the right of the Contractor to proceed as allowed in the followingprovisions.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    30/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    31

    SUSPENSION OF THE WORK

    1. If, in the judgment of DCPL, the Contractor is causing undue risk of damage toany part of the Project or adjacent area, DCPL may suspend the Worktemporarily, either wholly or in part, for such period until, in the judgment of the

    Department, the safe and proper prosecution of the Work may be resumed. TheDepartment shall provide notice to the Contractor's Surety of any suspensionordered pursuant to this Article.

    2. Work Stoppage Due to Hazardous MaterialsA. In the event the Contractor encounters materials reasonably believed to be

    containing asbestos, polychlorinated biphenyl (PCB) or other hazardouswaste or material, which has not been rendered harmless, the Contractorshall immediately stop Work in the area affected and report the conditionto DCPL, through the COTR, in writing.

    B.

    The Work in the affected area shall be resumed upon written notice fromthe COTR that the material has been removed or rendered harmless.C. The term "rendered harmless" shall mean that the level of exposure is less

    than any applicable exposure standards set forth in OSHA or otherapplicable regulations.

    3. In case of such suspension, an extension of time, if appropriate, will be allowed asprovided in the Plans and Specifications but no payment will be made to theContractor for any expense or damages resulting there from.

    4. Any failure of DCPL to suspend the Work shall not relieve the Contractor of theContractor's responsibility to perform the Work safely and in accordance with thePlans and Specifications.

    5. The Contractor shall, upon receipt of notice of suspension, cease Work on thesuspended activities and take all necessary or appropriate steps to limitdisbursements and minimize costs with respect thereto. The Contractor shallfurnish a report to DCPL, within five (5) days of receipt of the notice ofsuspension, describing the status of the Work, including without limitation, resultsaccomplished, conclusions resulting there from, and such other information asDCPL may require.

    6. In the event of suspension under this Article, the Contractor shall be entitled topayment of compensation due under the Drawings and Specifications, uponsubmission of a proper invoice, for the Work performed prior to receipt of noticeof suspension, which shall be payable based upon the Contract Cost Breakdown.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    31/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    32

    TERMINATION FOR CONVENIENCE

    1. DCPL may, at any time upon 20 days written notice to the Contractor, terminatethe Contract in whole or in part for the Owner's convenience and without cause.

    2. Upon receipt of the notice of termination for convenience, the Contractor shallimmediately, in accordance with instructions from DCPL, proceed withperformance of the following duties.A. Cease operation as specified in the notice;B. Place no further orders and enter into no further subcontracts for materials,

    labor, services or facilities except as necessary to complete continuedportions of the Project;

    C. Terminate all subcontracts and orders to the extent they relate to the WorkD. terminated;E. Proceed to complete the performance of any Work not terminated;F.

    Take actions that may be necessary, or that DCPL may direct, for theprotection and preservation of the terminated Work.

    3. Upon such termination, the Contractor shall be paid in accordance with theContract Cost Breakdown for Work completed, including any amount retained,and the value of materials ordered and delivered, less any salvage credit theContractor may receive for them.

    4. All materials, equipment, facilities and supplies at the Project site, or stored offsite, for which the Contractor has been compensated, shall become property of theOwner.

    5. The Contractor shall be entitled to a fair and reasonable profit for all Workperformed and all expenses directly attributable to the termination of the contract.In no event shall the Contractor's compensation exceed the total Contract price.

    6. Any dispute as to the sum then payable to the Contractor shall be resolved inaccordance with the Government of the District of Columbia Standard ContractProvisions for Use With Specifications for District of Columbia ConstructionProjects dated 1973, and amendments thereto in Article 8, of the GeneralProvisions.

    TERMINATION FOR CAUSE

    1. If DCPL determines that the Contractor has failed to prosecute the Work with thenecessary force, or has refused to remedy any Defective Work, DCPL shall notifythe Contractor and the Contractor's Surety of such failure or refusal. TheContractor shall begin to cure such failure or refusal within five ( 5 ) days ofreceipt of the notice.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    32/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    33

    2. If the Contractor fails to cure such failure or refusal within 20 days of receipt ofthe notice, DCPL may terminate the Contract and employ upon the Work theadditional force, or supply the materials or such part of either as is appropriate,and may remove Defective Work.

    3.

    If the Contractor is so terminated, the Contractor's Surety shall have the option toperform the Contract. If the Contractor's Surety does not commence performanceof the Contract within ten (10) days of the date on which the Contract wasterminated, DCPL may complete the Work by such means as DCPL deemsappropriate. DCPL may take possession of and use all materials, facilities andequipment at the Project site or stored off site for which the District has paid.

    4. If the Contractor is so terminated, the Contractor shall not be entitled to anyfurther payment. If DCPL completes the Work and if the cost of completing theWork exceeds the balance of the Contract price, including compensation for alldirect and consequential damages incurred by DCPL as a result of the

    termination, such excess shall be paid by the Contractor or the Contractor'sSurety.

    5. If the Contractor's Surety performs the Work, the provisions of the Plans andSpecifications shall govern such Surety's performance, with the Surety beingsubstituted for the Contractor in all such provisions including, without limitation,provisions for payment for the Work and provisions about the right of DCPL tocomplete the Work.

    CONTRACTOR BANKRUPTCY

    1. If the Contractor shall file a voluntary petition in bankruptcy or shall have aninvoluntary petition in bankruptcy filed against the Contractor, or if theContractor makes a general assignment for the benefit of creditors, or if a receiveris appointed for all or a substantial part of the Contractor's business or property,DCPL shall serve written notice on the Contractor and the Contractor's Suretystating that any failure of the Contractor to provide adequate assurances ofcontinued performance will be considered a rejection of the Contract, which shallresult in termination of the Contract for cause. Such termination of the Contractneed not he evidenced by an order of any court rejecting the Contract.

    2. Upon a final determination, either by a court or by arbitrators having jurisdiction,that the termination pursuant to paragraph GC 13.4.1 was improper, thetermination will be deemed to be a termination for convenience.

    3. The Contractor's sole remedy for a wrongful declaration of default by theDepartment shall be limited to recovery of profit on Work completed prior to suchdeclaration and reasonable expenses directly attributable to the termination of thecontract.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    33/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    34

    H.12 SUBCONTRACTORS AND MATERIAL SUPPLIERS:

    A. DCPLS APPROVAL1. Within Thirty (30) days of the Notice to Proceed, the Contractor shall list theContractor's proposed Subcontractors and Material Suppliers to the COTR,through the COTR, for DCPLS approval.

    2. The Department reserves the right to reject any Subcontractor or MaterialSupplier. Failure of the Department or their designee, the COTR, to notify theContractor of rejection within ten (10) days of receipt of such list forms shallconstitute notice that the Department has no objection.

    3. If DCPL rejects any Subcontractor or Material Supplier, the Contractor shallreplace the Subcontractor or Material Supplier at no additional cost to the District.

    B.

    REPLACEMENT

    1. The Contractor shall not replace any Subcontractor or Material Supplier afterexecution of the Contract without written approval of DCPL.

    2. The Contractor shall submit to the COTR, through the COTR, amended Forms 26or 27 and a written justification for the change of the Contractor's Subcontractorsor Material Suppliers.

    C. CONTRACTOR'S RESPONSIBILITY1. Nothing contained in the Plans and Specifications shall be construed as creating

    any contractual relationship between any subcontractor and the Government ofthe District of Columbia.

    2. The divisions or sections of the specifications are not intended to control theContractor in dividing the work among the subcontractors or to limit the workperformed by any trade.

    3. The Contractor shall be as fully responsible to the Government of the District ofColumbia for all acts and omissions of the Contractor's Subcontractors andMaterial Suppliers and of persons employed by them as he is for the acts andomissions of persons directly employed by him, and shall beresponsible forscheduling and coordinating the Work of the Contractor's Subcontractors andMaterial Suppliers with the COTR.

    4. The Contractor shall be responsible for the coordination of the trades,subcontractor and material persons engaged upon his work.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    34/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    35

    5. The Contractor shall, without additional expense to the Government of theDistrict of Columbia, utilize the services of specialty subcontractor of those partsof the work which are specified to be performed by specialty subcontractor.

    6. The Government of the District of Columbia will not undertake to settle any

    differences between the Contractor and his subcontractor or betweensubcontractors.7. Delays, interference, disruption, hindrance attributable to the Contractor's

    Subcontractors or Material Suppliers shall be deemed to be within the control ofthe Contractor.

    8. The Contractor shall require that each of the Contractor's Subcontractors have acompetent supervisor at the Project whenever Work is being performed by theSubcontractor.

    9. The Contractor agrees to bind the Contractor's Subcontractor and Material

    Supplier to the terms of the Plans and Specifications, so far as applicable to theWork of such Subcontractor or Material Supplier.

    D. No portion of the contract shall be subcontracted except with the prior writtenconsent of the Contracting Officer, or his authorized representatives, and suchconsent, when given, shall not be construed to relieve the Contractor of anyresponsibility for the fulfillment of the contract. Request(s) or permission tosubcontract any portion of the contract shall be in writing and accompanied by: (a)a showing that the organization which will perform the work is particularlyexperienced and equipped for such work, and (b) an assurance by the Contractorthat the Labor Standards Provisions set forth in this contract shall apply to laborperformed on all work encompassed by the request(s). The request(s) also shallprovide the following information:

    1. Subcontractors name, address, telephone number, and Federal SocialSecurity Number used on the Employers Quarterly Federal Tax Return,U.S. Treasury Department Form 941.

    2. Estimated dollar amount of the subcontract.

    3. Estimated starting and completion dates of the subcontract.

    4. The subcontractor approval request form included herein should be used torequest approval of subcontractor on this project. The form should becompleted for each subcontractor requested for approval and submitted tothe Contracting Officer. Copies of these forms are available upon requestfrom the COTR.

    E. Any work or service so subcontracted shall be performed pursuant to asubcontract agreement, which the District will have the right to review and

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    35/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    36

    approve prior to its execution by the Contractor. Any such subcontract shallspecify that the Contractor and the subcontractor shall be subject to everyprovision of this contract. Notwithstanding any such subcontract approved by theDistrict, the Contractor shall remain liable to the District for allContractors work and services required hereunder.

    F. WARRANTY AND GUARANTEE1. The Contractor shall require each Subcontractor and Material Supplier to fully

    warrant and guarantee, for the benefit of the Owner, the effectiveness, fitness forthe purpose intended, quality and merchantability of any Work performed or itemprovided or installed by such Subcontractor or Material Supplier.

    G. INDEMNIFICATION1. INDEMNIFICATION FOR INJURY OR DAMAGE

    A. To the fullest extent permitted by law, the Contractor shall indemnify andhold harmless DCPL, the Owner, the COTR and the Owner, their respectiveofficers, consultants, agents and employees, in both individual and officialcapacities, from and against all claims, damages, losses and expenses, direct,indirect or consequential arising out of or resulting from the Work.

    B. In the event of any such injury, including death, or loss or damage, or claimsthere for, the Contractor shall give prompt notice thereof to the Departmentand the Owner.

    C. The indemnification obligations of the Contractor under paragraph GC 16.1.1shall not extend to the liability of the Owner, the Owner's consultants, agentsor employees for negligent preparation or approval of Drawings,Specification, Change Orders, opinions, and any other responsibility of theOwner, except to the extent covered by the Contractor's insurance.

    2. INDEMNIFICATION FOR PATENT OR COPYRIGHT USEA. To the fullest extent permitted by law, the Contractor shall indemnify, hold

    harmless, and defend DCPL, the Owner, the Owner and the COTR, theirrespective members, officers, consultants, agents, representatives andemployees, in both individualand official capacities from and against all claims, damages, losses andexpenses arising out of the Contractor's infringement of patent rights orcopyrights.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    36/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    37

    H.13 USE OF PREMISES:

    A. If the Contractor considers it necessary to perform any work after the regularworking hours on Saturdays, Sundays or legal holidays, the Contractor shallperform this work without any additional expense to the Government of the

    District of Columbia.

    B. The Contractor shall use only such entrances to the work area as designated by theCOTR or is designee, the COTR.

    C. Once the installation work is started, the Contractor shall complete the work asrapidly as possible and without unnecessary delay.

    D. The Contractor shall occupy only such portions of the premises as required forproper execution of the contract.

    E. The Contractor shall perform all the work in such a manner as to cause minimumannoyance or noises and disturbances to occupants of adjacent premises andinterference with normal traffic.

    F. The Contractor shall keep gates locked to maintain security into work areadictated by the existing job conditions of such nature as to prevent:

    1. Entry of work areas by unauthorized persons;

    2. Removal of Government property and supplies.

    G. The Contractor shall not load or permit the loading of any part of any structure tosuch an extent as to endanger its safety.

    H. The Contractor shall comply with the regulations governing the operation ofpremises that are occupied and shall perform his contract in such a manner as notto interrupt or interfere with the conduct of Government of the District ofColumbia and/or Washington Metropolitan Area Transit Authority (WMATA)business.

    H.14 PATENTS:

    The Contractor shall hold and save the Government, its officers, agents, servants and

    employees, harmless for liability of, any nature or kind, including cost and expenses for,

    or on account of any patented or unpatented invention, article or appliance manufactured

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    37/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    38

    or used in the performance of this contract, including their use by the Government of the

    District of Columbia.

    H.15 SAFETY PRECAUTIONS:

    A. The Contractor shall perform all site, plant and construction work in strictaccordance with the Safety Standards of the District of Columbia and the U.S.Occupational Safety and Health Act of 1970 and the D.C. Occupational Safetyand Health Act of 1988, D.C. Official Code secs. 32-1101 et seq. and 1-620.01 etseq.

    1. The Contractor or his representative shall be thoroughly familiar withthese standards and have copies of same available at the project site at alltimes.

    B. Operators of explosive-actuated tools shall have a training certificate, as requiredby the Safety Code in their possession.

    C. The Contractor shall be responsible for providing and installing adequatetemporary shoring or bracing for all walls, slabs and like constructions until suchitems attain their design, strength, and stability.

    1. The Government, its officers, agents, servants, and employees shall not beheld liable for any property damages or physical harm resulting frominadequate protection.

    2. Prior to execution of shoring and/or bracing, the Contractor shall submitdetails and calculations for shoring and/or bracing designs for the COTRsreview and concurrence.

    D. The Contractor shall exercise special precautions to prevent use of or access to theContractors materials, equipment or tools and entry into the Contractors workareas by non-authorized personnel.

    1. A Contractors attendant shall be present at all times when bituminouskettles are in operation to prevent the public from coming in contact withthe kettles.

    2. The Contractor shall remove each kettle as soon as its use is complete.

    E. The Contractor shall chute or hoist to the ground any and all the materials beingremoved from the roof areas or any upper floor.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    38/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    39

    F. The Contractor shall not permit any live wires to be left exposed and unguarded,including open panel boards.

    G. The Contractor shall cover all open trenches during hours when work is not beingexecuted, as required for protection of the public.

    H.16 PROGRESS SCHEDULE:

    A. CONSTRUCTION SCHEDULE1. The Contractor shall submit, not later than seven (7) days after official Notice to

    Proceed (NTP) has been issued, one reproducible print plus three copies of an initialschedule diagram plus three copies of computer reports and the narrative for the first90 days of all the contract activities. When the total construction cost for the Projectis $500,000 or more, critical path scheduling methods shall be provided. TheContractor shall submit to DCPL, within 30 days of the date of the Notice to Proceed,

    a Construction Schedule signed by the COTR and the Contractors. For projects over$2 million construction cost total, an intermediate Bar Chart Schedule may besubmitted for the first 60 days followed by the complete CPM Schedule within 90days of the Notice to Proceed. The Contractor shall submit all the schedules andreports for approval by the COTR and COTR, and all schedules and reports mustconform to the following minimum requirements:

    A. Include activities for all Contractor submittals, including but not limited tocatalogue-cuts, samples, shop drawings and laboratory tests, approvals byCOTR and COTR, procurements by Contractor, and delivery of materialand equipment to the job site.

    B. Include in each schedule the following details and format:

    1. Time scaled in workdays, CPM Network (arrow) diagram with eachwork activity showing cost and man-loading on arrow system plus anarrative to facilitate monitoring and control of work progress and atool for measurement of progress payments.

    2. Each field work activity shall have a maximum duration of 20workdays. Provide identification of each phase of the Work includingany milestone dates required by the Construction Documents;

    3. Each activity shall show all the associated costs for the purpose ofprogress payment, as required by Section G.4., with no front loading.In addition, the sum total all the activity costs shall equal the totalamount of the contract award.

    4. All computer reports shall include I-J, J-I, and Total-Float sortsfor all the activities, without any masking or plugging of any dates

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    39/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    40

    (except NTP and contract milestone). The computer reports shall besubmitted in hard-copy plus soft form of read/write CDs giving all theactivity data and schedules.

    A. Monthly Progress Updates and Reports:1. The Contractor shall submit monthly update by the 25th of each

    month and the same shall include a narrative and three copies of I-J, J-I and Total-Float computer printouts plus read/write CDs ofall the activity data and schedules. These reports shall include theactual start; percent complete or finish dates for each activity, asmutually agreed with the COTR and COTR plus any approved logicchanges.

    2. In the case of any logic changes that result in any delay to the contractmilestone(s), the Contractor shall submit a revised schedule diagram

    and the computer reports for approval by the COTR by the nextupdate reporting date.

    3. The updated Construction Schedule shall be signed by the Contractorand the COTR which shall serve as an affirmation that the Contractorcan meet the requirements of the updated Construction Schedule.

    4. No payment will be made without an updated Construction Scheduleapproved by all the COTR, the Contractors, the Owner and DCPL.

    5. The Contractor shall revise the Contractor's plan for the Workaccording to the comments received from the COTR and COTR andsubmit four (4) copies of a revised Construction Schedule,to theCOTR within ten (10) days after receipt.

    6. Provide a graphic presentation of the sequence of the Work for theProject in the media and format required by the project;

    7. Provide activities and durations identified for all shop drawing reviewand approval, product review and procurement, fabrication, shopinspection and delivery, including lead time, coordination drawingdelivery, Punch List, Project close-out requirements, ContractCompletion and occupancy requirements;

    8. Identify disruptions and shutdowns due to other operations;

    9. Identify the critical path of the Work, for CPM Schedules;

    10. Identify the crew size and total resource hours for each activity in theschedule.

  • 8/14/2019 FGI-Modular RFP - Revision 1 10-19-10 _2

    40/102

    Solicitation No. DCPL-2010-R-0001, Design/Build Service for a Modular Unit forFrancis Gregory Interim Library

    41

    11. Provide a space for each Contractor's signature.

    12. The Owner through the COTR shall provide a complete specificationfor a Critical Path Method (CPM) Schedule. The Contractor shall

    develop the Construction Schedule data using commerciallyavailable, COTR recommended personal computer software. Finalcopy schedules shall be provided to the COTR in color in full sizeand 11"x17" size.All base line and monthly updated schedules shall be submitted inelectronic format to the COTR. The CPM Schedule Chart shall beused as a tool for scheduling and reporting sequenced progress of thework. Provide clear graphics legend and other data such asmilestones, constraints and items required by the project, Associateand Using Agency. On each submission show the state projectnumber and project name and provide a signature approval and date

    line for all parties to the schedule.Further, provide in each schedule: Activity identification anddescription for each activity broken down to a 15 day maximumduration, responsibility of each Contractor, Contractor's resources andcrew size for each activity, provide early start, early finish, late start,late finish. Show predecessor activities and successor activities foreach activity entry free float, total float and percentage of completionand identify the logic relationship between all activities.Also, show all submittal dates, coordination drawing input, reviewand approval durations. Unless otherwise specified, submit the CPMConstruction Schedule in graphic and tabular form. Provide a twoweek look-ahead schedule print out for each weekly progressmeeting. Provide with each monthly schedule update a list of allchanges to the previously approved base line schedule or monthlyupdated sched