    RICS SEMINAR

    FIDIC & QATAR LAW: WHAT YOU

    MUST KNOW

    SCOTTLAMBERT,RegionalHeadConstruction&

    Infrastructure

    31May2016

    HotelCityCenterRotana

    WestBay-Doha

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    2/18

    Introduction

    Freedomofcontract.

    Qatarlaws

    mandatoryprovisions;

    applyifconstructioncontractissilent;and

    nobindingprecedentbutjudgments/commentaryareimportant.

    Workscontracts(i.e.muqawalacontracts)(Articles682715).

    1

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    3/18

    FIDIC

    InternationalFederation of onsulting Engineers(commonlyknown

    asFIDI ).

    FIDICisthemostcommonlyusedstandardconditionsofcontractin

    Qatar.

    2

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    4/18

    Liquidated Damages

    Clause8.7-FIDICRedBook.

    TheContractorshallpaydelaydamagestotheEmployerifitfailsto

    completetheworks,bytheTimeforCompletion(subjecttoanyextensionsoftime).

    Suchdelaydamagesshallbetheonlydamagesduefromthe

    Contractorforsuchdefault.

    TherateofsuchdelaydamagesisquantifiedintheAppendixtoTender.

    3

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    5/18

    Liquidated Damages: Qatar Law

    IVIL ODE

    Thepartiesmayagreeafixedamountofdamagesinadvance.

    Acourtmaychangetheamountofdamagestoreflecttheactualloss

    suffered,andanycontractualagreementtothecontrarywillbetreatedasnullandvoid.

    Needtoprovethedifferencebetweenactuallossandpre-agreed

    loss.

    Ifthedamagecausedisduetoaforeignelementbeyondthepartyscontrol.

    4

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    6/18

    Time Bars

    Clause20.1RedBook.

    Thecontractormustgivenoticeofanyclaim,whetherfortimeor

    money,notlaterthan28daysafterhebecameaware,oroughtto

    havebecomeawareofthecausegivingrisetosuchaclaim.

    TheContractorrunstheriskoflosinghisentitlementtoadditional

    timeormoneyifhefailstonotify.

    NotoriouslyusedbyEmployerstorestricttimeperiodsforgiving

    notices.

    5

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    7/18

    Time Bars: Qatar Law

    Afailuretoadheretoacontractsnoticeprovisionwillnotnecessarily

    restrictclaim.

    CounterstoFIDIC: Theprinciplesofgoodfaith;

    Causingdisproportionateharm;and

    Unjustenrichment.

    Whenallthesefactorscombined,acourtmaytreadcautiously.

    6

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    8/18

    Limitation of Liability

    Clause17.6FIDIC.

    ThetotalliabilityoftheContractortotheEmployer,underorin

    connectionwiththeContractotherthanunder(sic)..shallnotexceedthesumstatedintheParticularConditions.

    Nottoapplyinanycaseoffraud,deliberatedefaultorreckless

    misconductbythedefaultingParty.

    Neitherpartytobeliabletotheotherforlossofuseofanyworks,lossofprofit,lossofanycontractorforanyindirectorconsequential

    lossordamagewhichmaybesufferedbytheotherpartyin

    connectionwiththecontract.

    7

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    9/18

    Limitation of Liability: Qatar Law(cont)

    Principleofdecennialliability.

    Contractorandengineer/supervisingarchitectjointlyliableto

    compensatetheEmployerforaperiodoftenyearsfromtheproject

    handoverdateifthe:

    buildingsufferstotalcollapse;

    buildingsufferspartialcollapse;or

    thestabilityofthebuildingisthreatened.

    Strictliability,cannotbewaived.

    Claimstobebroughtwithin3yearsfromdiscoveryofdefect.

    8

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    10/18

    Variations

    Clause13.1FIDICRedBook.

    VariationsmaybeinitiatedbytheEngineeratanytimepriortoissuingthe

    Taking-OverCertificatefortheWorks,eitherbyaninstructionorbyarequest

    fortheContractortosubmitaproposal.

    ContractortobeboundbyeveryVariationunlessitgivespromptnoticetothe

    EngineerthatitcannotreadilyobtainGoods.Uponreceivingsuchnotice,Engineertocancel,confirmorvarytheinstruction.

    Variationtoincludechangestothe:

    changestothequantities,qualityofanyitemorwork;

    changestothelevels,positionsand/ordimensionsofanypartoftheworks;

    sequenceortimingoftheexecutionoftheWorks;

    omissionofanyworkunlessitistobecarriedoutbyothers;and

    anyadditionalwork,Plant,Materialorservicesnecessaryforthe

    PermanentWorks. 9

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    11/18

    Variations Qatar Law (contd.)

    UnderQatarlaw,aVariationcanbeevidencedinmanywaysoral,by

    conductand/orinwriting.

    Maybeprovenbyexchangeofcorrespondence,engineersconsenttothe

    additionalworks,minutesofmeetings,expertdeterminationcasethroughthe

    court,etc.

    Re-measurementcontractsacontractormustimmediatelynotifythe

    employerofanysignificantincreaseinprice.

    CommonpracticeforEmployerstoinserttimebarrequirementsasapreconditiontoclaimingVariation.

    10

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    12/18

    Suspension

    Contractualrightsofsuspension

    clause8.8FIDIC99(Employersrightsofsuspension)

    TheEngineermayatanytimeinstructtheContractortosuspendprogressofpartoralloftheWorks.Duringsuchsuspension,theContractorshallprotect,storeandsecure

    suchpartortheWorksagainstanydeterioration,lossordamage.

    clause16.1FIDIC99(Contractorsrightsofsuspension)

    IftheEngineerfailstocertifyinaccordancewithSub-Clause14.6[IssueofInterim

    PaymentCertificates]ortheEmployerfailstocomplywithSub-Clause2.4[EmployersFinancialArrangements]orSub-Clause14.7[Payment],theContractormay,aftergiving

    notlessthan21daysnoticetotheEmployer,suspendwork(orreducetherateofwork)

    unlessanduntiltheContractorhasreceivedthePaymentCertificate,reasonable

    evidenceorpayment,asthecasemaybeandasdescribedinthenotice.

    11

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    13/18

    Suspension: Qatar Law (cont.)

    Righttosuspendatlaw

    formalities;

    proportionality/goodfaith;and

    risks.

    12

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    14/18

    Termination

    Clause16.2ofFIDIC1999-providesforterminationinaneventof

    defaultbytheemployer

    iftheengineerfailstoissueapaymentcertificatewithinaspecified

    period;

    ifthecontractordoesnotreceivetheamountdueunderapaymentcertificatewithinaspecifiedperiod;

    iftheemployerbecomesbankruptorinsolvent,orgoesintoliquidation;

    or

    iftheemployerfailstocomplyassignmentprovisions(clause1.7),orif

    thereisprolongedsuspension.

    Also,iftheEmployerfailsinadducingevidenceofsufficientfundsto

    paytheContractor.

    13

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    15/18

    Termination (contd.)

    Clause15.2FIDIC(Employersrighttoterminate).

    TheEmployershallbeentitledtoterminateiftheContractor:

    failstocomplywithrequirementsofperformancesecurityoranoticeto

    correct;

    abandonstheWorksordemonstratesnointentiontocontinueperformanceofhisobligationsundertheContract;

    withoutreasonableexcusefailstoproceedinaccordancewithclause8

    (commencement,delaysorsuspension)(sic).;

    subcontractsthewholeoftheWorksorassignstheContractwithoutthe

    requiredagreement; becomesbankrupt;or

    givesoroffersbribe.

    Clause15.5FIDIC(TerminationforConvenience).

    14

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    16/18

    Termination: Qatar Law (contd.)

    Issueofunilateralterminationofcontractsiscrucialfromboththe

    EmployerandtheContractorsperspective.

    Amuqawalacontractcanbeterminated

    uponcompletionoftheworks;

    withmutualconsent;and

    withcourtorder.

    Riskofwrongfulterminationlengthydisputes,legalcosts,project

    delays.

    Advisabletodraftclearandconciseterminationclausetoavoida

    disputeoverwrongfultermination.

    15

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    17/18

    Conclusion

    Balancingcommonlawcontractsundercivillawcanbetricky.

    DonotturnyourFIDICcontractintoaPandorasboxseekexpert

    advice.

    Knowyourproject-usethecorrectmodelFIDICstandardcontractasabase.

    Maintainarobustdocumentmanagementteamclear,cogent

    evidenceisworthitsweightingoldatthetimeofdisputes.

    16

  • 7/26/2019 FIDIC and Qatar Law 31 May 2016

    18/18

    17

    THE END

    Questions?

    ScottLambert

    RegionalHeadConstruction&Infrastructure

    Email:[email protected]

    Phone:+97143641641