field electrical testing - … · initiate any claim forms perform an internal ... • using megger...

61
Regional Technical Seminar FIELD ELECTRICAL TESTING © SPX TRANSFORMER SOLUTIONS, INC. June 20, 2018

Upload: dangbao

Post on 13-Aug-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

Regional Technical Seminar

FIELD ELECTRICAL TESTING

© SPX TRANSFORMER SOLUTIONS, INC.

June 20, 2018

Field Electrical Testing Applications

2

Key Purposes of Field Electrical Testing:

Receiving inspection

Acceptance testing/commissioning of new equipment

Routine maintenance programs

Diagnostics/troubleshooting

June 20, 2018© SPX Transformer Solutions, Inc.

Receipt of Transformer

3June 20, 2018© SPX Transformer Solutions, Inc.

Receiving Inspection

4

Complete visual inspection

Review impact recorder

Impacts that warrant further

inspection

• 2 Gs – Lateral & Vertical

• 3 Gs - Longitudinal

Check tank pressure

Take dew point measurement

Perform core ground test

Inventory and inspect accessories

June 20, 2018© SPX Transformer Solutions, Inc.

Impact Recorders

Impacts that warrant further

inspection

• 2 Gs – Lateral & Vertical

• 3 Gs - Longitudinal

Mount recorder directly on

transformer

Assure there is adequate

battery life, recording paper

Redundant recorders are

recommended for critical

shipments

June 20, 2018© SPX Transformer Solutions, Inc. 5

External Inspection

June 20, 2018© SPX Transformer Solutions, Inc. 6

Receiving Inspection – As Found Conditions

7June 20, 2018© SPX Transformer Solutions, Inc.

Receiving Inspection – As Found Conditions

8June 20, 2018© SPX Transformer Solutions, Inc.

Receiving Inspection

If damage is evident from

visual inspection, impact

recorder reading, or testing:

Notify manufacturer

Notify carrier

Do not unload equipment

Initiate any claim forms

Perform an internal

inspection

June 20, 2018© SPX Transformer Solutions, Inc. 9

Receiving Inspection – Prevention Techniques

10June 20, 2018© SPX Transformer Solutions, Inc.

Insulation Moisture Content

11

Dew point measurement

• Introduce dry gas and stand idle for 12-

24 hours

• Measure dew point of gas

• Record tank pressure

• Record insulation temperature

• Utilize Pieper curve information to

calculate moisture present

• Acceptance range is less than 1.0%

June 20, 2018© SPX Transformer Solutions, Inc.

Dew point Measurement

12

Source: IEEE C57.93-2007

Dew point = -30°C

Tank Pressure = 3 PSI

Insulation Temp = 30°C

VC = 300 ( 14.7 + 3 )

14.7

VC = 361.2

VC = VP ( ATM + T P )

ATM

June 20, 2018© SPX Transformer Solutions, Inc.

Dew point Measurement

13

Moisture content is 0.9%.

Source: IEEE C57.93-2007

June 20, 2018© SPX Transformer Solutions, Inc.

Core Resistance (Megger)

14

Purpose

• Prove insulation integrity of core from ground potential and test for inadvertent core grounds.

Method

• Using megger instrument, 1000V is applied for one minute to core ground strap.

• Some transformers may have multiple core grounds and/or a separate clamp/endframe ground. Each should be tested independently

Preventative autotransformer

Series transformer

Clamp

• Some transformers may be constructed such that core ground strap is not accessible.

June 20, 2018© SPX Transformer Solutions, Inc.

Core Resistance (Megger)

15

Acceptance criteria

• Minimum standard acceptance limit is 100 megaohms when corrected to

20°C.

• Test is sensitive to temperature, moisture and contamination.

• Measured values will be different in air and oil.

June 20, 2018© SPX Transformer Solutions, Inc.

Field Acceptance Testing – Transformer Assembly

16

(Prior to assembly) Dew point (initial)

Core ground test (initial)

(After Assembly, Prior to filling) Transformer Turn Ratio (AC)

Current Transformer Testing (AC)

(Post vacuum oil processing/filling) Power Factor Testing (AC)

Excitation Testing (AC)

Frequency Response Analysis (AC)

Insulation Resistance (DC)

Winding Resistance Testing (DC)

• Core ground test (final)

• Controls and Alarm checks

Oil sample/DGA

June 20, 2018© SPX Transformer Solutions, Inc.

Transformer Turns Ratio

17

Purpose

Test is done to verify all internal connections and winding configurations are correct

Method

Tests are conducted using low voltage ratio bridge or three phase power supply and voltmeters.

Voltage is applied to the primary winding and the voltage is measured on a secondary winding.

Test is conducted at multiple tap positions.

Ratio is calculated in accordance with nameplate values.

June 20, 2018© SPX Transformer Solutions, Inc.

CT Ratio, Polarity & Excitation Current

18

Verify proper ratio and polarity of

current transformers

Ratio and excitation current can

be verified either by primary

current injection or secondary

voltage injection

Polarity is verified by battery

polarization or buck/boost circuits

Varied depending on relay

accuracy and burden rating of the CT. Generally ± 1% of calculated

ratio

June 20, 2018© SPX Transformer Solutions, Inc.

Field Acceptance Testing – Transformer Assembly

19

(Prior to assembly) Dew point (initial)

Core ground test (initial)

(After Assembly, Prior to filling) Transformer Turn Ratio (AC)

Current Transformer Testing (AC)

(Post vacuum oil processing/filling) Power Factor Testing (AC)

Excitation Testing (AC)

Frequency Response Analysis (AC)

Insulation Resistance (DC)

Winding Resistance Testing (DC)

Core ground test (final)

Controls and Alarm checks

Oil sample/DGA

June 20, 2018© SPX Transformer Solutions, Inc.

Oil Level Verification

20

N2 Blanketed Unit

June 20, 2018© SPX Transformer Solutions, Inc.

Oil Level Verification

21

N2 Final Level

June 20, 2018© SPX Transformer Solutions, Inc.

Oil Level Verification

22

Conservator Unit

Conservator Unit

June 20, 2018© SPX Transformer Solutions, Inc.

Oil Level Verification

23

Conservator Final Level

June 20, 2018© SPX Transformer Solutions, Inc.

Oil Level Verification

24

Determining Average Oil Temperature

Take oil temperature from liquid temperature gauge

Using infrared gun or tape on thermometer, record oil temperature at bottom of unit

Average the two readings

Determine correction factor measurement for each unit based on nameplate data as shown on previous slides

Note:

• On the N2 unit, measure from the PRD to the top of the oil as indicated

earlier

• On the Conservator unit, stick a dowel through the breather opening and

determine where it lands on top of the bag which indicates oil level. Put

a piece of tape on the dowel after calculating level.

June 20, 2018© SPX Transformer Solutions, Inc.

Power Factor Testing – Bushings

25

Purpose

Detection of moisture or foreign contamination in the insulation structure or damage or excessive contamination to external surfaces.

Method

Insulation power factor bridge is used to measure power factor and capacitance of bushings.

Test voltages are determined by bushing design and construction.

Power factor bridge shall be capable of a test voltage of 10 kV.

Readings are corrected to standard temperature.

Testing is highly susceptible to temperature, humidity and contamination.

June 20, 2018© SPX Transformer Solutions, Inc.

Power Factor Testing – Bushings

26

Detection of moisture or

foreign contamination in the

insulation structure or

damage or excessive

contamination to external

surfaces.

Sensitivity to temperature,

moisture, and

contamination

Applicable to condenser

bushings only

June 20, 2018© SPX Transformer Solutions, Inc.

Power Factor Testing – Bushings

27

C1 test checks main core

insulation

C2 test checks tap insulator

and core insulation between

capacitance tap and ground

flange.

Hot collar tests can be done

for solid bushing

June 20, 2018© SPX Transformer Solutions, Inc.

Power Factor Testing – Bushings

28

Acceptance criteria

Standard acceptance limit for bushings is 0.5% when corrected to

20°C.

Typical maintenance limits:

• Good - < 0.5%

• Deteriorated - .5% - 1.0%

• Investigate - > 1.0%

Recommended that the readings be compared to nameplate

values. Bushings should be replaced when the measured power

factor doubles the nameplate value or capacitance is in excess of

110% of the nameplate value.

June 20, 2018© SPX Transformer Solutions, Inc.

Power Factor Testing – Windings

29

Purpose

Detection of moisture or foreign contamination in the insulation structure.

Test can also detect changes in geometrical configuration of windings or damage to ground and static shields.

Method

Insulation power factor bridge is used to measure power factor and capacitance of windings.

Power factor bridge shall be capable of a test voltage of 10kV.

Tests typically completed at 10kV.

Testing his highly susceptible to temperature, humidity and contamination.

June 20, 2018© SPX Transformer Solutions, Inc.

Power Factor Testing – Windings

30

Less than 0.5% Good

> 0.5% but < 0.7% Deteriorated

> 0.5% but < 1.0% & Increasing Investigate

>1.0% Bad

Acceptance criteria

Standard acceptance limit for new transformer windings is 0.5% when

corrected to 20°C.

Natural ester fluid filled transformers will have a higher power factor

typically 2 to 4 times greater than measured in mineral oil.

For maintenance testing, the following limits are defined by Doble

Engineering

June 20, 2018© SPX Transformer Solutions, Inc.

Winding Excitation

31

Purpose

Maintenance test generally recognized to detect any changes in the magnetic circuit

Method

Voltage source is applied to winding and exciting current is measured.

Test is most often done with power factor bridge test set at 10 kV

Acceptable Criteria

This is a repeat test. All subsequent tests are compared to original baseline test for indications of variance

June 20, 2018© SPX Transformer Solutions, Inc.

Winding Excitation

June 20, 2018© SPX Transformer Solutions, Inc. 32

A B C

A B C

A B C

A Phase Excitation

C Phase Excitation

B Phase Excitation

A = C

B < A and C

Frequency Response Analysis

33

Test Methods

Impulse method (Framit)

Sweep Frequency Method (Doble)

Traces are not comparable between methods

Test for Winding Movement

Deformation

Winding Clamping

Short Circuit Damage

Comparison Test

Identical 1-Phase Units

Phases on 3-Phase Unit

Against Previous Test

June 20, 2018© SPX Transformer Solutions, Inc.

Doble SFRA Test

34June 20, 2018© SPX Transformer Solutions, Inc.

Doble SFRA Test

35

< 2kHz, core defamation,

shorted turns, residual

magnetism, open circuits

2kHz to 20kHz,

bulk winding

movement, core

clamping

20 kHz to 400kHz,

deformation within

windings

400 kHz to

2 MHz,

leads and

bushings

June 20, 2018© SPX Transformer Solutions, Inc.

Insulation Resistance (Megger)

36

Purpose

Prove insulation integrity between windings and between the winding and

ground potential.

Severe contaminants or insulation failure can be detected.

Polarization index can detect changes in insulation structure over time.

Method

Using megger instrument, 1000V to 5000V is applied for one minute

between windings and between windings and ground. If polarization index

(PI) measurement is required, test voltage must be applied for 10 minutes

in each test configuration.

Test is sensitive to moisture, temperature and contamination.

June 20, 2018© SPX Transformer Solutions, Inc.

Insulation Resistance (Megger)

37

Acceptance criteria

Minimum standard acceptance limit is 1000 Megaohms when

corrected to 20°C.

Test is sensitive to temperature, moisture and contamination.

Measured values will be different for different fluids. Natural ester

fluid filled transformers will have a reduced megger value up to 10

times less than measured in mineral oil.

June 20, 2018© SPX Transformer Solutions, Inc.

Winding Resistance

38

Purpose

Verify internal connections and detection of any open

or poor connections. This is often done as a

maintenance type test

Method

Using Wheatstone or Kelvin bridge, resistance of the

transformer winding is measured.

Test is very sensitive to temperature and must be

corrected to standard temperature for comparison.

The test is generally performed single phase of each

section of a winding.

June 20, 2018© SPX Transformer Solutions, Inc.

5

© SPX Transformer Solutions, Inc. 39June 20, 2018

6

© SPX Transformer Solutions, Inc. 40June 20, 2018

7

© SPX Transformer Solutions, Inc. 41June 20, 2018

8

© SPX Transformer Solutions, Inc. 42June 20, 2018

9

© SPX Transformer Solutions, Inc. 43June 20, 2018

Processed Oil in New Transformer

44

Test Standard Unit Voltage Value

< 69 kV 25

69 < 230 kV 30

230 < 345 kV 32

> 345 kV 35

< 69 kV 0.015

69 < 230 kV 0.015

230 < 345 kV 0.015

> 345 kV 0.015

< 69 kV 38

69 < 230 kV 38

230 < 345 kV 38

> 345 kV 38

< 69 kV 25

69 < 230 kV 10

230 < 345 kV 10

> 345 kV 10

< 69 kV 0.05

69 < 230 kV 0.05

230 < 345 kV 0.05

> 345 kV 0.05

Moisture

ContentASTM-D1533

max, PPM

@ 60°C

Avg. Oil

Temp.

Power Factor ASTM-D924max, % @

25°C

Neutralization

NumberASTM-D974

max, mg

KOH/g

Interfacial

TensionASTM-D971

min,

Dynes/cm

Dielectric

Breakdown

ASTM-D1816

w/ 1mm gap min, kV

Take baseline DGA prior to energization

Source: IEEE C57.106-2006

June 20, 2018© SPX Transformer Solutions, Inc.

Field Acceptance Testing

45

(Prior to assembly) Receiving Inspection

Dew point (initial)

Core ground test (initial)

(Prior to filling) Transformer Turn Ratio (AC)

Current Transformer Testing (AC)

(Post vacuum oil processing/filling) Power Factor Testing (AC)

Excitation Testing (AC)

Frequency Response Analysis (AC)

Insulation Resistance (DC)

Winding Resistance Testing (DC)

Core ground test (final)

Oil sample/DGA

June 20, 2018© SPX Transformer Solutions, Inc.

Energization Procedures

46

Source: C57.93-2007

Prior to energizing transformers, verify the following

• Electrical and oil tests have been complete and have met minimum standards

• Stand time after oil filling has been met

• Cooling controls have been set to automatic operation

• All temporary grounds and shorting wire have been removed

Energize the transformer with no load from either the high voltage or low voltage side. If possible, it is recommended that voltage be raised in increments.

June 20, 2018© SPX Transformer Solutions, Inc.

Energization Procedures

47

During the energization period without load,

it is recommended that close observation of

the transformer be made.

• Excessive audible noise

• Check of liquid temperatures, winding

temperatures, and ambient temperature

• Check of tank pressure

• Check of oil level indicators

• Check of gas detector relay.

Within the first month of operation, a DGA

sample should be taken for baseline analysis

June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – Routine/Preventative

48

Normal Maintenance Cycles

Unit Outages

PM programs

Validate against previous test data

Electrical testing and oil analysis

June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – Diagnostics/Troubleshooting

49

Post Incident Analysis

Abnormal test results

Known fault condition

Service bulletin

Result of oil analysis

June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – Initial Test Results – Doble Overall

50

Nameplate - Two-winding Transformer

Company Itasca Mantrap COOP Serial Number GT-01773

Location Shell Lake Sub, MN Special ID

Division

Circuit Designation

Manufacturer WAU Configuration D-Y

Year Manufactured 2013 Tank Type N2 BLANKETED

Mfr Location Goldsboro Coolant OIL

Phases 3 Class ONAN/ONAF

Oil Volume 2340 UG BIL 150 kV

Weight 54515 LB Winding Config. Delta-Wye

kV 34.5, 12.47 VA Rating 8.4, 10.5, , MVA

Note

Test Date 5/28/2014 Test Time 7:38:14 AM Weather SUNNY

Air Temperature 31 °C Tank Temperature 22 °C Rel. Humidity 0 %

Tested by

Work Order #

Last Test Date

Checked by

Test Set Type M4K Retest Date

Checked Date

Set Top S/N

Reason TROUBLE

Last Sheet #

Set Bottom S/N

Travel Time

P.O. #

Ins. Book #

Duration

Copies

Sheet #

Crew Size

Overall Tests

Meas. Test kV mA Watts %PF

corr

Corr

Fctr Cap(pF) IRauto IRman

CH + CHL 10.007 25.302 0.8530

0.99 6711.3

CH 10.005 8.174 0.3650 0.45 0.99 2168.1 G

CHL(UST) 10.008 17.118 0.5240 0.31 0.99 4540.7 G

CHL

17.128 0.488 0.28 0.99 4543.200 G

CL + CHL 10.008 47.299 1.441

0.99 12546.4

CL 10.008 30.157 0.8980 0.30 0.99 7999.3 G

CHL(UST) 10.008 17.118 0.5470 0.32 0.99 4540.7 G

CHL

17.142 0.543 0.32 0.99 4547.100 G

June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – Initial Test Results – Doble Excitation

51

Exciting Current Tests

Mfr Type Steps

Boost

%

Buck

%

Position

Found

Position

Left

Oil

Volume

De-Energized Tap

Changer

On-Load Tap Changer

H3 - H1 H1 - H2 H2 - H3

DETC LTC Test kV mA Watts X mA Watts X mA Watts X IRauto IRman

3 N/A 10.018

37.293 291.22 L 37.345 291.03 L Q

June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – Initial Test Results – Doble SFRA

52June 20, 2018© SPX Transformer Solutions, Inc.

Doble SFRA Test

53

< 2kHz, core defamation,

shorted turns, residual

magnetism, open circuits

2kHz to 20kHz,

bulk winding

movement, core

clamping

20 kHz to 400kHz,

deformation within

windings

400 kHz to

2 MHz,

leads and

bushings

June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – As Found Conditions

54June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – As Found Conditions

55June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – As Found Conditions

56June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – As Found Conditions

57June 20, 2018© SPX Transformer Solutions, Inc.

Field Testing – As Found Conditions

58June 20, 2018© SPX Transformer Solutions, Inc.

Test References

59

IEEE Guide for Installation of Liquid Immersed Power

Transformers (C57.93-2007)

IEEE Guide for Maintenance and Acceptance of Insulating Oil

in Equipment (C57.106-2006)

IEEE Guide for Interpretation of Gasses Generated in

Electrical Equipment (C57.104-2008)

NETA Acceptance Testing Specification 2010

IEEE Guide for Failure Investigation, Analysis, and

Documentation of Power Transformers and Shunt Reactors

(C57.125-1991 Appendix A)

IEEE C57.152 Field Diagnostics Guide (New)

June 20, 2018© SPX Transformer Solutions, Inc.

Common Issues Found With Test

June 20, 2018 60

1. Bushing Power factor

1. Power Factor in Crate

2. Hard to PF Bushings on Straps if Large Bushing

1. Supposed to have standing up for 24 hours

3. Resistance Readings not making since

1. Make sure that you have give enough time to let readings settle

2. If taking to long then check into different setups

4. SFRA or Excitation not correct

1. Check for magnetized core

5. Megger should show inductive kick

1. How often do you 20,000 Meg Ohms +

2. If no inductive kick then core ground might not be connected to the core ground.

© SPX Transformer Solutions, Inc.

Questions?Thank you!