Project Management & Social Responsibility Assignment 5 - Organizing a Project
Matt Heywood Isaac Golumbia
Blake Elliott
Figure 1 - Spider Diagram
Figure 2 - Product Sketch 2a - Front View
A - Infrared Sensor B - Strain Gauge C - Bar D - Telescope E - Mounting system F - Grips G - Arduino
2b - Side View
A - Screws B - Infrared Sensor C - Wall Plate D - Bar Holder E - Hinge F - Locking Mechanism G - Lock H - Padded support I - Bar H - Arduino
Figure 3 - Worried Areas 3a - Assemble Chin-up Bar
3b - Software
3c - Manufacturing
Figure 4 – Packaging
Meng 293
Period Highlight: # Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
PERCENT
ACTIVITY COMPLETEPERIODS (Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
A - Pricing / Budget
B - Design
C - Order / Acquire Matericals
D - Produce Drawings
E - Produce Cirucit Schamatics
F - User Manual
G - Print Paperwork
H - Write Arduino Code
I - Make circuits (test)
J - Bar Manufacturing
K - Produce Mounting System
L - Final Assembaly
M - Product Testing
N - Assemble Packaging
O - Package Product
P - Shipping
Assignment 5 -
Gantt Chart 1, just
the tasks.
Meng 293
Period Highlight: # Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
ACTIVITY DURATIONCOMPLETEPERIODS (Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
A - Pricing/Budget
B - Design
C - Order / Acquire Matericals
D - Produce Drawings
E - Produce Cirucit Schamatics
F - User Manual
G - Print Paperwork
H - Write Arduino Code
I - Make circuits (test)
J - Bar Manufacturing
K - Produce Mounting System
L - Final Assembaly
M - Product Testing
N - Assemble Packaging
O - Package Product
P - Shipping
--- Either Team
Assignment 5 - Gantt
Chart 1.5, job
assignments.
Paperwork Team
Design / Manufactuing Team
Meng 293
Period Highlight: # Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
PERCENT
ACTIVITY COMPLETEPERIODS (Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42
A - Pricing/Budget
B - Design
C - Order / Acquire Matericals
D - Produce Drawings
E - Produce Cirucit Schamatics
F - User Manual
G - Print Paperwork
H - Write Arduino Code
I - Make circuits (test)
J - Bar Manufacturing
K - Produce Mounting System
L - Final Assembaly
M - Product Testing
N - Assemble Packaging
O - Package Product
P - Shipping
--- Either Team
Assignment 5 -
Gantt Chart 2, Real
Plan.
Paperwork Team
Design / Manufactuing Team
MENG 293 – Assignment 5 – Network Diagram
Start
N 38 39
1 38 39
O 39 40
1 39 40
END P 40 41
1 40 41
M 33 38
5 33 38
D 5 15
10 6 16 E 15 17
2 16 18
F 17 21
4 18 22
L 28 33
5 28 33
C 5 10
5 5 10
H 5 10
5 5 10
I 10 18
8 10 18
G 21 22
1 22 23
K 22 27
5 23 28
J 18 28
10 18 28
B 0 5
5 0 5
A 0 1
1 4 5
Slack: 1 Slack: 1
Slack: 1 Slack: 1
Slack: 1
Slack: 4
Task Price NOTESPurchase Bar 50 1" stainless tube (0.083" wall thickness, 6' length)Purchase Grips 5 Amazon.caPurchase Strain Gauge 100 Micro-Measurements MMF003129Purchase Motion Sensor 20 Parallax Inc. 910-28027
Purchase Mounting System Materials 208 fastners (wall to plate), sheet metal for fastning device, latch and hinge (with two small fastners)
Purchase Arduino Uno 40 Amazon.caPurchase Electronic Hardware 20 Wires, resistors, switches/relays, etc.Paperwork Printing 15 Monk OfficeShipping of Materials 65 -Purchase Packaging Materials 10 UPS Victoria
Total Price (Materials) 345
Task Time (hours) Price ($) NOTESPricing and Budgeting 8 320 One full day of work (2 people)Bar Design 50 2000 Five full days of analysis and design (2 people)Order and Acquire Materials 6 240 Pick up materials around town and order others from the internet (2 people)Produce Drawings 100 4000 Ten full days of work (2 people)Produce Circuit Schematics 16 640 Two days of work (2 people)Produce User Manual 38 1520 Four days of work (2 people)Print Paperwork 1 40 One hour for driving to print shop and back (2 people)Write/Test Arduino Code 50 2000 Five full days of work (2 people)Test/Build Circuits 70 2800 Seven full days of work (2 people)Manufacture Bar 100 4000 Ten full days of work (2 people)Manufacture Mounting System 55 2200 Six days of work (2 people)Final Assembly 48 3840 Five days of work (4 people)Test Product 46 3680 Five days of work (4 people)Package Product 5 400 One day of work (4 people)
Ship - - No work required. Price is dependant on location of shipment
Total Price (Labour) 27680
GRAND TOTAL ($) 28025
Appendix A - Rough Sketches
B - Cost estimate
C - Chipup Jobs