final design report - calvin college | grand rapids, michigan€¦ ·  · 2014-05-15final design...

112
NATURAFILL © 2013, TEAM 13, CALVIN COLLEGE LAST UPDATED: 5/15/2014 FINAL DESIGN REPORT NATURAFILL: FUEL FOR THOUGHT Team 13 Karl Bratt Jonathan Haines Brandon Koster

Upload: dinhliem

Post on 17-May-2018

217 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

NATURAFILL © 2013, TEAM 13, CALVIN COLLEGE LAST UPDATED: 5/15/2014

FINAL DESIGN REPORT

NATURAFILL: FUEL FOR THOUGHT

Team 13 Karl Bratt Jonathan Haines Brandon Koster

Page 2: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

i

© 2014, Karl Bratt, Jonathan Haines, Brandon Koster, and Calvin College

Page 3: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

ii

DEDICATION

For Our Friend and Former Teammate

Eric DeGroot

1992-2013

However great our labors, this project will be forever incomplete.

Page 4: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

iii

Executive Summary

This report outlines the design, manufacture, and testing of a home refueling appliance capable of

compressing household natural gas to 3,600 psi, thereby producing compressed natural gas (CNG). The

team’s original goal was to design, build, and test a natural gas home refueling appliance that is lower

cost and more reliable than appliances currently on the market. In the course of nine months, team

NaturaFill developed a preliminary prototype of such system using a two-stage hydraulic cylinder

compression system. This design, composed of one double acting hydraulic cylinder, minimizes floor

space and overall cost. For reliability, the system’s manifolds and compression cylinders were

constructed from cold worked steel, guaranteeing strength and stability. For safety, the system is

controlled with input, output, and thermocouple modules affixed to monitoring software. All in all,

NaturaFill, has explored the many engineering and non-engineering aspects of this project and upon

completion of this report, NaturaFill believes that large-scale production of such a system would cost

approximately $3,500.

Page 5: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

iv

Table of Contents

1 Project Overview ............................................................................................................................... 1

1.1 Calvin College Senior Design ......................................................................................................... 1

1.2 Mission Statement ........................................................................................................................ 1

1.3 Problem Statement ....................................................................................................................... 1

1.4 Industry Overview ......................................................................................................................... 1

1.4.1 Compressed Natural Gas....................................................................................................... 1

1.4.2 Benefits of CNG ..................................................................................................................... 2

1.4.3 Growth Rate Expectations .................................................................................................... 3

1.4.4 Barriers to Entry .................................................................................................................... 4

1.5 Project Proposal ............................................................................................................................ 5

1.5.1 Objective ............................................................................................................................... 5

1.5.2 Target Customers .................................................................................................................. 5

1.5.3 Existing Competitors ............................................................................................................. 5

1.5.4 Competitive Strategy ............................................................................................................ 7

1.6 Team Organization: ....................................................................................................................... 7

1.6.1 Team Members ..................................................................................................................... 7

1.6.2 Team Member Strengths ...................................................................................................... 8

1.6.3 Team Leadership and Management ..................................................................................... 9

1.7 Design Norms .............................................................................................................................. 10

1.7.1 Stewardship: ....................................................................................................................... 10

1.7.2 Trust .................................................................................................................................... 11

1.7.3 Integrity ............................................................................................................................... 11

2 Requirements .................................................................................................................................. 12

2.1 Safety .......................................................................................................................................... 12

Page 6: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

v

2.2 Price ............................................................................................................................................ 12

2.3 Refueling Rate ............................................................................................................................. 12

2.4 Heat Loss ..................................................................................................................................... 12

2.5 Serviceability ............................................................................................................................... 12

2.6 Reliability ..................................................................................................................................... 12

2.7 Noise ........................................................................................................................................... 13

2.8 Size .............................................................................................................................................. 13

2.9 User Interface ............................................................................................................................. 13

3 Deliverables ..................................................................................................................................... 14

3.1 Project Proposal and Feasibility Study ........................................................................................ 14

3.2 Final Design Report ..................................................................................................................... 14

3.3 Working Prototype ...................................................................................................................... 14

3.4 Team Website ............................................................................................................................. 14

4 Design Considerations..................................................................................................................... 15

4.1 Compression System ................................................................................................................... 15

4.1.1 Motor Driven Reciprocating Compression .......................................................................... 15

4.1.2 Wobble Plate Compression ................................................................................................. 15

4.1.3 Pneumatic Cylinder Compression ....................................................................................... 16

4.1.4 Hydraulic Cylinder Compression ......................................................................................... 16

4.1.5 Decision ............................................................................................................................... 17

4.2 Lubricated vs. Oil-less ................................................................................................................. 17

4.3 Hydraulic System ......................................................................................................................... 18

4.3.1 Hydraulic Power Unit .......................................................................................................... 18

4.3.2 4-Way, 3 Position Solenoid Valve ....................................................................................... 19

4.4 Compression Cylinder System ..................................................................................................... 20

Page 7: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

vi

4.4.1 Material ............................................................................................................................... 20

4.4.2 Surface Finish ...................................................................................................................... 21

4.4.3 Sizing ................................................................................................................................... 21

4.4.4 Manifolds ............................................................................................................................ 21

4.4.5 General Layout .................................................................................................................... 22

4.4.6 Fittings and Taps ................................................................................................................. 23

4.4.7 Bolts & Threaded Rod ......................................................................................................... 23

4.4.8 Gaskets ................................................................................................................................ 24

4.4.9 Pistons ................................................................................................................................. 24

4.5 Natural Gas System ..................................................................................................................... 26

4.5.1 Heat Removal ...................................................................................................................... 26

4.5.2 Pressure Sensors ................................................................................................................. 27

4.6 Control System ............................................................................................................................ 28

4.6.1 Raspberry Pi ........................................................................................................................ 28

4.6.2 National Instruments LabVIEW & FieldPoint ...................................................................... 30

4.6.3 Decision ............................................................................................................................... 30

5 Calculations ..................................................................................................................................... 32

5.1 Summary ..................................................................................................................................... 32

5.2 Autodesk CFD .............................................................................................................................. 32

5.2.1 Overview ............................................................................................................................. 32

5.2.2 Goals.................................................................................................................................... 32

5.2.3 Status .................................................................................................................................. 32

5.2.4 Results ................................................................................................................................. 32

5.2.5 Conclusion ........................................................................................................................... 33

5.3 Engineering Equation Solver ....................................................................................................... 34

5.3.1 Overview ............................................................................................................................. 34

Page 8: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

vii

5.3.2 Procedure ............................................................................................................................ 34

5.3.3 Results ................................................................................................................................. 34

5.3.4 Conclusion ........................................................................................................................... 34

5.4 MathCAD ..................................................................................................................................... 34

5.4.1 Overview ............................................................................................................................. 34

5.4.2 Procedure ............................................................................................................................ 35

5.4.3 Results ................................................................................................................................. 35

5.4.4 Conclusion ........................................................................................................................... 35

6 Final Design ..................................................................................................................................... 36

6.1 Hydraulic System ......................................................................................................................... 36

6.1.1 Overview ............................................................................................................................. 36

6.2 Natural Gas System ..................................................................................................................... 37

6.2.1 Overview ............................................................................................................................. 37

6.2.2 Residential Natural Gas Supply ........................................................................................... 37

6.2.3 Piston Seals ......................................................................................................................... 37

6.2.4 Tubing.................................................................................................................................. 38

6.2.5 Check Valves ....................................................................................................................... 38

6.2.6 Relief Valve .......................................................................................................................... 38

6.2.7 Shut-off Valve ...................................................................................................................... 39

6.2.8 Manifolds ............................................................................................................................ 39

6.2.9 Pressure Gauges and Transducers ...................................................................................... 40

6.2.10 Heat Sinks ............................................................................................................................ 41

6.2.11 Blow-By Recovery System ................................................................................................... 42

6.2.12 Refueling Nozzle .................................................................................................................. 42

6.3 Control System ............................................................................................................................ 42

6.3.1 Enclosure Box ...................................................................................................................... 43

Page 9: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

viii

6.3.2 FieldPoint Modules ............................................................................................................. 43

6.3.3 Solid State Relays ................................................................................................................ 44

6.3.4 Thermocouples ................................................................................................................... 45

7 Prototype Development ................................................................................................................. 46

7.1 Machining ................................................................................................................................... 46

7.2 Fabrication & Assembly .............................................................................................................. 46

7.3 Modifying .................................................................................................................................... 47

7.4 Mounting ..................................................................................................................................... 48

8 Testing ............................................................................................................................................. 50

8.1 Test Planning ............................................................................................................................... 50

8.2 System Testing ............................................................................................................................ 50

8.2.1 Air Testing ........................................................................................................................... 50

8.2.2 Natural Gas Testing ............................................................................................................. 50

8.3 Results ......................................................................................................................................... 50

8.3.1 Compression Ratios............................................................................................................. 50

8.3.2 Pressure and Temperature ................................................................................................. 52

8.3.3 Friction ................................................................................................................................ 52

9 Obstacles ......................................................................................................................................... 52

9.1 Controls ....................................................................................................................................... 52

9.2 Piston Seals ................................................................................................................................. 53

9.3 Storage Tanks .............................................................................................................................. 53

9.4 Gaskets ........................................................................................................................................ 54

9.5 Top Dead Center Volume ............................................................................................................ 55

9.6 Piston O-Ring Seal ....................................................................................................................... 55

10 Future Improvements ..................................................................................................................... 56

Page 10: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

ix

10.1 Proper Component Sizing ........................................................................................................... 56

10.2 Noise Control .............................................................................................................................. 57

10.3 Imbedded Electronics ................................................................................................................. 57

10.4 Fabricating for Flexibility ............................................................................................................. 58

11 Financial Estimates .......................................................................................................................... 59

11.1 Cost of Development .................................................................................................................. 59

11.2 Cost of Production ...................................................................................................................... 60

12 Conclusion ....................................................................................................................................... 61

13 Acknowledgements ......................................................................................................................... 62

13.1 Professor Ned Nielsen ................................................................................................................. 62

13.2 Professor Steve VanderLeest ...................................................................................................... 62

13.3 Professor Matthew Heun ............................................................................................................ 62

13.4 Mr. Jimmy Moerdyk .................................................................................................................... 62

13.5 Mr. Lee Otto ................................................................................................................................ 62

13.6 Mr. Ross Pursifull ........................................................................................................................ 62

13.7 Mr. Phil Jasperse ......................................................................................................................... 62

13.8 Mr. Jerry LaBreck ........................................................................................................................ 62

13.9 Mr. Kevin Fern ............................................................................................................................. 63

13.10 Mr. Tim Wolfis ............................................................................................................................. 63

14 Appendix ......................................................................................................................................... 64

14.1 Appendix A. Work Breakdown Structure .................................................................................... 64

14.2 Appendix B. EES Calculations ...................................................................................................... 66

14.2.1 Two Stage Compression System Sizing Calculations ........................................................... 66

14.2.2 Heat Transfer Calculations .................................................................................................. 68

14.3 Appendix C. MathCAD Calculations ............................................................................................ 71

Page 11: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

x

14.3.1 Pump/Reservoir Horsepower Requirement ....................................................................... 71

14.3.2 Stress in Spacer Plate Bolts (First Stage) ............................................................................. 71

14.3.3 Stress in Threaded Rod (First Stage) ................................................................................... 74

14.3.4 Friction Calculations ............................................................................................................ 76

14.4 Appendix D. As-Built Part Drawings ............................................................................................ 77

14.5 Appendix E. Raw Testing Data .................................................................................................... 92

14.6 Appendix F. Manufacturer Component Specifications ............................................................... 97

14.6.1 O-ring Groove Dimension Instructions ............................................................................... 97

Page 12: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

xi

Table of Figures

Figure 1. Price Equivalent per Barrel of Oil and Natural Gas .................................................................... 2

Figure 2. Oil Price as a Multiple of Natural Gas Price ............................................................................... 3

Figure 3. Number of Natural Gas Vehicles by Region (1991-2001) .......................................................... 4

Figure 4. BRC FuelMaker Phill® ................................................................................................................. 6

Figure 5. CNG Pump II® ............................................................................................................................. 6

Figure 6. Ross Pursifill’s CNG Home Refueling Unit ................................................................................ 10

Figure 7. Motor Driven Reciprocating Compression System .................................................................. 15

Figure 8. Wobble Plate Compression System ......................................................................................... 16

Figure 9. Hydraulic Cylinder Compression System ................................................................................. 17

Figure 10: Custom Built Hydraulic Power Unit........................................................................................ 18

Figure 11: Off-The-Shelf Hydraulic Power Unit ....................................................................................... 19

Figure 12: Solenoid Valves ..................................................................................................................... 19

Figure 13: Tandem Centered 4-Way, 3-Position Solenoid Valve ............................................................ 20

Figure 14: Pre-honed Steel Tubing .......................................................................................................... 21

Figure 15: First & Second Stage FEA Stress Simulations ......................................................................... 22

Figure 16: Sandwich Stacking .................................................................................................................. 22

Figure 17: Pyramid Stacking .................................................................................................................... 23

Figure 18: O-Ring Seals on Manifold ....................................................................................................... 24

Figure 19: 5" Diameter Aluminum Piston ............................................................................................... 24

Figure 20: Layout of PTFE Seals & Rider Rings ........................................................................................ 25

Figure 21: Pressure Transmitter .............................................................................................................. 27

Figure 22: Pressure Gage ........................................................................................................................ 27

Figure 23: Raspberry Pi Computer .......................................................................................................... 29

Page 13: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

xii

Figure 24: Raspberry Pi Control Schematic ............................................................................................. 29

Figure 26: NI FieldPoint Modules ............................................................................................................ 30

Figure 26: LabVIEW Interface .................................................................................................................. 30

Figure 27: LabVIEW Block Diagram ......................................................................................................... 31

Figure 28. Pressure Results from Simulation .......................................................................................... 33

Figure 29. Plane of Simulation Pressure Results ..................................................................................... 33

Figure 30: Hydraulic System Schematic .................................................................................................. 36

Figure 31. Natural Gas System Schematic .............................................................................................. 37

Figure 32. High Pressure Natural Gas Check Valves ............................................................................... 38

Figure 33. Adjustable High Pressure Natural Gas Relief Valves .............................................................. 39

Figure 34. Example of CNG Ball Valve ..................................................................................................... 39

Figure 35. Example of Manifold and Connections at End of CNG Compression Chamber ..................... 40

Figure 36. Pressure Transmitter Example ............................................................................................... 41

Figure 37. Pressure Gage Example .......................................................................................................... 41

Figure 38. Example of Tubing Loops ....................................................................................................... 41

Figure 39. General Purpose CNG Refueling Nozzle for Time-Fill ............................................................ 42

Figure 40: Compiled Control & Monitoring System ................................................................................ 43

Figure 41: Sealed Electrical Control Box ................................................................................................. 43

Figure 42: FieldPoint Module Communication with Windows XP .......................................................... 44

Figure 43: Solid State Relays ................................................................................................................... 44

Figure 44: Machining............................................................................................................................... 46

Figure 45: Fabrication & Assembly ......................................................................................................... 47

Figure 46: Piston Spacing Diagram .......................................................................................................... 48

Figure 47: Mounting of Final Prototype .................................................................................................. 49

Figure 48: Pressure Reaching 3,600 psi.................................................................................................. 51

Page 14: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

xiii

Figure 49: Temperature Data from Testing ............................................................................................ 51

Figure 50: Blown Fuse in Ethernet Controller ......................................................................................... 53

Figure 51. Proposed Pressure Vessel ...................................................................................................... 54

Figure 52. Piston O-ring .......................................................................................................................... 55

Figure 53: Final NaturaFill Prototype ...................................................................................................... 61

Page 15: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

xiv

Table of Tables

Table 1. NGV Reductions in Exhaust Emissions ........................................................................................ 2

Table 2. Compression Technology Decision Matrix ................................................................................ 17

Table 3. Steel Tubing Sizing Chart ........................................................................................................... 20

Table 4: Bolt & Threaded Rod Safety Factors ......................................................................................... 24

Table 5. Comparison of Development Boards ........................................................................................ 28

Table 6. Work and Heat Removal Calculation Results ............................................................................ 34

Table 7: Operational Budget ................................................................................................................... 59

Table 8: Costs of Production ................................................................................................................... 60

Page 16: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

1

1 Project Overview

1.1 Calvin College Senior Design

Calvin College is a Christian liberal arts college located in Grand Rapids, Michigan. Calvin’s engineering

program is ABET accredited and has a reputation for producing well-rounded engineers by integrating

this liberal arts curriculum with engineering. Senior design is the capstone of the engineering program

in which students conceive, develop, and implement a project of their interest over the course of the

year, combining material learned both inside and outside the classroom.

1.2 Mission Statement

NaturaFill, a design team comprised of three mechanical engineering

seniors, exists to decrease American dependence on foreign oil by

increasing the availability of abundant, clean burning natural gas

transportation to the average American.

1.3 Problem Statement

Today, there is scarcity in the infrastructure for compressed natural gas (CNG) in the United States

transportation landscape. Currently, only 605 public CNG refueling stations exist, compared to the

168,000 gasoline stations.1 In response, a few small companies, such as BRC Fuelmaker, have

developed home refueling units that run on electricity and connect to existing natural gas lines.2

Unfortunately, these models begin at $5,000 before installation.3

1.4 Industry Overview

1.4.1 Compressed Natural Gas

Natural gas is a colorless, odorless, non-corrosive, and extremely flammable mixture of hydrocarbon

gases. Natural gas, a fossil fuel, originates from the chemically breakdown of organic matter over time

to produce methane, or CH4.4 When compressed to 3600psi, natural gas is termed, “compressed

natural gas” or “CNG.”

1 http://www.afdc.energy.gov/fuels/natural_gas_locations.html 2 http://www.cngnow.com/vehicles/refueling/Pages/refueling-at-home.aspx 3 Jimmy Moerdyk, Moerdyk Energy Inc. (MEI), 9/27/13, 9:00AM 4 http://www.naturalgas.org/overview/background.asp

Page 17: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

2

1.4.2 Benefits of CNG

CNG can easily be used as an alternative for gasoline in a dedicated vehicle engine or in conjunction

with gasoline in a “bi-fuel” application. In fact, the octane rating for CNG is higher than that of gasoline,

producing greater power, acceleration, and cruise speed for vehicles running on CNG. Though the

safety concerns are different, CNG’s narrow flammability range makes it inherently safer than gasoline.

In addition, emission comparisons of CNG and gasoline-fueled vehicles have revealed substantial

reductions in greenhouse gases (see Table 1. NGV Reductions in Exhaust Emissions).

Table 1. NGV Reductions in Exhaust Emissions

NGV Potential Reductions in Exhaust Emissions (%) Carbon

Monoxide (CO) Non-Methane Hydrocarbons

(NMHC) Nitrogen Oxides

(NOx) Carbon Dioxides

(CO2)

90% 75% 60% 25%

CNG not only provides a cleaner-burning fuel alternative to gasoline, it is also an economically feasible.

As a result of new shale gas discoveries and new drilling technology the supply of natural gas in the

United States has increased substantially. This increase in supply has forced the price of natural gas

down 70% over the last five years.5 The current pipeline natural gas of about $3.80 per million BTU6

has an energy equivalent price of $0.42 per gasoline gallon equivalent (GGE)7. Over the past twenty

years, this price drop has been reflected in a large price separation between gasoline and natural gas

(see Figure 1. Price Equivalent per Barrel of Oil and Natural Gas).

Figure 1. Price Equivalent per Barrel of Oil and Natural Gas8

5 http://www.infomine.com/investment/metal-prices/natural-gas/5-year/ 6 http://www.oil-price.net/ 7 http://www.energyalmanac.ca.gov/transportation/gge.html 8 http://pictorial-guide-to-energy.blogspot.com/2012/03/gaseous-emissions.html

Page 18: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

3

In fact, the price of oil is over eight times higher than that of natural gas, as shown in Figure. 2. Oil

Price as a Multiple of Natural Gas Price.

Figure 2. Oil Price as a Multiple of Natural Gas Price9

1.4.3 Growth Rate Expectations

The economic and environmental incentives associated with CNG have already encouraged transit,

garbage, and transportation fleets to convert from diesel and gasoline fuel to CNG.10 Unfortunately,

this has been primarily restricted to vehicles such as taxicabs, transit and school buses, garbage trucks,

and public works vehicles. Because these vehicles are typically maintained and fueled at a central

location, it is has been economical for them to convert to natural gas. In total, the number of CNG

powered vehicles on the road is growing at a staggering rate of 30 percent a year.11 Currently, there

are 135,000 natural gas vehicles in the United States and 15.2 million worldwide12 (see Figure 3.

Number of Natural Gas Vehicles by Region).13

9 http://www.infomine.com/investment/metal-prices/natural-gas/5-year/ 10 http://www.cngnow.com/vehicles/fleets/Pages/government.aspx 11 http://www.ngvamerica.org/media_ctr/fact_ngv.html 12 http://www.ngvc.org/about_ngv/index.html 13 http://www.iangv.org/current-ngv-stats/

Page 19: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

4

Figure 3. Number of Natural Gas Vehicles by Region (1991-2001)

In the coming years, it is also forecasted that the number of factory built bi-fuel vehicles will also be on

the rise. “Bi-fuel” indicates that a vehicle can run on both gasoline and natural gas fuel sources.

Presently, larger vehicles such as the 2013 Chevrolet Silverado and GMC Sierra 2500 HD are factory-

offered with bi-fuel capability. Ross Pursifull, a research specialist at Ford Motor Company, spoke with

the team14 and confirmed rumors that the 2015 Chevrolet Impala will also be built bi-fuel ready.15

Chevrolet’s decision results from increased market pressure for CNG vehicles in residential applications.

Increased demand for residential natural gas vehicles (NGVs) will correspondingly increase demand for

CNG fueling stations.

1.4.4 Barriers to Entry

The biggest hurdle to widespread consumer adoption of natural gas vehicles is availability to fueling

stations. There are over 270 publically accessible gasoline fuel stations for every one station supplying

CNG.16 The capability to fuel a CNG vehicle at home side-steps waiting for an adequate nationwide

network of fueling stations. Unfortunately, cost has been the major deterrent away from existing CNG

home refueling units.

14 Pursifull, Ross; Ford Motor Company; 11/9/13, 10:00AM 15 http://blog.caranddriver.com/antelope-in-the-gas-2015-chevrolet-impala-to-gain-bi-fuel-gasolinecng-capable-v-6-model/ 16 http://www.afdc.energy.gov/fuels/natural_gas_locations.html

Page 20: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

5

1.5 Project Proposal

1.5.1 Objective

The objective of NaturaFill is to design, build, and test a natural gas home refueling appliance with a

production cost of less than $2,000 and refueling rate of 0.35 gasoline gallons equivalent (GGE) per

hour. The system must be capable of compressing natural gas to the standard pressure of 3,600 psi in

a safe and controlled environment.

1.5.2 Target Customers

This increased use of CNG in transportation vehicles has made it seemingly more affordable and feasible

in light-duty, consumer applications. In total, 56 percent of American households are currently using

natural gas for residential heating.17 As a result, NaturaFill’s natural gas home refueling appliance aims

to target customers with existing natural gas lines and fossil fuel dependent vehicles. A potential

secondary market for CNG vehicles and the system would include customers desiring reduced emission

large vehicle options, such as trucks or sports utility vehicles (SUVs). The majority of electric or hybrid

powered vehicles on the market today are small with little hauling capacity. In the realm of trucks and

SVUs, natural gas vehicles are a suitable option for improved environmental impact.

1.5.3 Existing Competitors

BRC FuelMaker

FuelMaker is currently the largest producer of CNG home refueling units. Their most popular unit, the

Phill®, costs $5,000 before installation. The Phill® (see Figure 4) refuels at an average rate between

0.4-0.5 GGEs per hour but is unreliable due to its reciprocating compression system.

17 http://www.naturalgas.org/overview/uses_residential.asp

Page 21: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

6

Figure 4. BRC FuelMaker Phill®

CNGPump

CNGPump, maker of the CNG Pump®, uses hydraulic compression for conversion of natural gas into

CNG. Their cheapest model is the CNG Pump II®, which refuels at a rate of 2 GGEs per hour.

Unfortunately, their upfront cost is $7,000 before installation, an inhibitor for most customers.18

Figure 5. CNG Pump II®

18 http://www.cngpump.com/shoppingcart/products/CNGPUMP%252d2gge-%28Time-Fill%29-Hydraulic-Fueling-Station-for-cars%7B47%7Dtrucks-%282gge-per-hour%29.html

Page 22: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

7

General Electric

The biggest potential competitor is General Electric (GE). They have announced a partnership with

Chesapeake Energy to develop a natural gas home refueling unit with an upfront cost of $500.19 If

proposition becomes a reality, it would undercut NaturalFill’s suggested retail price and therefore,

undermine its value proposition. From conversations with Ross Persifill, Research Specialist at the Ford

Motor Company, and other industry insiders, the general consensus suggests high unlikeliness of GE’s

proposition becoming a reality. For this reason, the team forecasts the elapse of a substantial amount

of time before GE enters this market.

1.5.4 Competitive Strategy

Existing in-home refueling units are currently in the price range or $5000-$7000+ and fill at a rate of

around 1-2 GGEs per hour. Today, most systems are currently made in Europe and the United States,

however, it is rumored that a less expensive Asian variety will soon be hitting the market will be released

soon. NaturaFill plans to compete by ensuring quality and safety and competing at a lower price point

by reducing the compression rate of approximately 0.35 GGEs. In actuality, this compression rate would

be comparable to charging a 100% electric vehicle overnight for average daily usage. The team’s

strategy to compete on price and differentiation will make residential use of natural gas vehicles more

economically feasible in the American transportation landscape.

1.6 Team Organization:

1.6.1 Team Members

Karl Bratt

Bratt is a Mechanical concentration engineering student also in pursuit of

a business minor. Originally from Racine, Wisconsin, Bratt has diverse

interests in business finance, operations, and supply chain. Bratt has had

two summer internships working for General Electric as a manufacturing

engineer and continuous improvement specialist. He is passionate about

the potential business opportunities involved with the NaturaFill project.

In his free time, he enjoys playing piano, golf, and tennis, and is an avid

runner. Last year, he ran the Chicago marathon.

19 http://oilprice.com/Finance/investing-and-trading-reports/Chesapeake-GE-Get-in-on-Home-Refueling-Game.html

Page 23: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

8

Jonathan Haines

Haines is a Mechanical concentration engineering student also in pursuit

of a mathematics minor. Originally from East Brunswick, New Jersey,

Haines desires to work in the automotive industry in the design and

manufacture of fuel-efficient vehicles. His hands-on experience with

thermodynamics, CAD modeling, and manufacturing were valuable in the

design and construction of the final prototype. In his free time, Jon enjoys

playing guitar, traveling, and being outdoors during the summer months.

Brandon Koster

Koster is a Mechanical concentration engineering student and also

pursuing a business minor. Originally from Visalia, California, Koster has

been a natural gas transportation enthusiast for years, both from a

business and engineering perspective. Growing up as the son of a

contractor, Koster gained valuable fabricating, mechanical design, and

project execution skills at a young age. In his free time he enjoys rock

climbing, cheering the Los Angeles Dodgers, fixing his car, listening to

Texas Country music, and taking road trips.

1.6.2 Team Member Strengths

Karl Bratt

Bratt's background in project management was valuable in the organization and planning components

of the project. In addition, his experience in forecasting and cost analysis were helpful in evaluating

and marketing the value proposition of the product. Finally, Bratt’s willingness to learn was

instrumental in programing the electrical control and safety systems of NaturaFill.

Jonathan Haines

Haines’s experience with thermodynamics, Autodesk Inventor, and Autodesk CFD simulator were

valuable in the design and testing of various components. In addition, his experience in metal

fabrication was critical for the machining of metal manifolds, pistons, and spacer plates.

Brandon Koster

Koster’s industry knowledge served to connect the team to companies and individuals in the industry

that provided valuable guidance and support throughout the project. In addition, his background in

hydraulics has been instrumental in the design and modeling of the final prototype.

Page 24: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

9

1.6.3 Team Leadership and Management

Project Manager

Bratt functioned as the Project Manager for NaturaFill. Bratt was primarily responsible for the

organizational components of the project. This included, but was not limited to, the planning and

scheduling of team meetings, review and on-time delivery of project deliverables, and work breakdown

of tasks among the team member using Microsoft Project.

Budget Manager

Koster acted as the Budget Manager for NaturaFill. Koster was primarily responsible for managing the

team’s operational budget. This included, but was not limited to, turning in all reimbursement forms,

requesting parts purchases, and communicating with team sponsors.

Senior Design Faculty Advisor

Ned Nielsen, a Mechanical Engineering professor at Calvin College, functioned as the faculty advisor for

mechanically concentrated Senior Design projects. He was responsibility for providing constructive

feedback on the project throughout the course of the year. Nielsen’s extensive engineering background

was be helpful for finalizing the team’s CNG refueling unit design and keeping the team on schedule.

Mechanical Faculty Consultant

Matthew Heun, a Mechanical Engineering professor at Calvin College, agreed to meet with NaturaFill

to address the transfer of heat released by the compression system. Heun has also gave the team

advice with the use of Autodesk CFD and National Instruments LabVIEW 8.5.

CNG Industry Consultant

Lee Otto, the Founder and CEO of CNGPump, Inc. in Appleton, WI, offered the team advice on seal

technology, heat dissipation, and control systems. Unfortunately, he was unable to provide any further

technical information due to confidentiality.

Automotive Industry Consultant

Ross Pursifull, a CNG enthusiast and Research Specialist at Ford Motor Company in Dearborn, MI,

agreed to meet with NaturaFill and discuss the CNG industry from an automotive industry standpoint.

In addition, he demonstrated the use of a home refueling unit to fuel his own NGVs (see Figure 6. Ross

Pursifull CNG Home Refueling Unit.

Page 25: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

10

Figure 6. Ross Pursifill’s CNG Home Refueling Unit

Industry Mentor

Jimmy Moerdyk, the Vice President of Operations at Moerdyk Energy, Inc. in Grand Rapids, MI,

provided support and suggestions to the team based on his experience in CNG vehicle conversions and

installation of home refueling units. Moerdyk has been enthusiastic of NaturaFill’s $2,000 production

price target.

1.7 Design Norms

1.7.1 Stewardship:

As the concentration of CO2 in the atmosphere approaches the 400 ppm mark, the political, social, and

economic pressures for alternative energies has risen drastically.20 CNG, which burns cleaner than

coal or oil, could be a solution to this environmental and economic challenge.

Environmental Sustainability

It has been proven that natural gas vehicles produce less emissions than traditional gasoline powered

vehicles (see Table 1. NGV Reductions in Exhaust Emissions). As worries rise on the negative effects of

greenhouse gases on the environment, the team believes that transition from gasoline fueled

transportation to natural gas exemplifies good stewardship over the environment.

20 http://www.gasnaturally.eu/uploads/Modules/Publications/the-role-of-natural-gas-in-a-sustainable-energy-market-final.pdf

Page 26: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

11

Economic and Political Sustainability

Natural gas is widely available in the United States. In fact, 98% of the natural gas consumed in the

United States is produced in either the US or Canada.21 In addition, the price of natural gas has declined

tremendously in the past five years, especially in comparison to oil (see Figure 1). The economic

feasibility of this project promotes the design norm of stewardship over limited financial resources.

Transitioning transportation fuels toward natural gas would also render the United States more energy

independent and therefore offer the world a chance for more political stability.

1.7.2 Trust

The team’s goal of creating a fully-functional natural gas home refueling unit will only be accomplished

if the prototype is proven safe. Since a prototype malfunction could be highly dangerous, the team

conducted all preliminary testing of the devise with a non-combustible gaseous materials. In addition,

emergency stops were integrated into the electronic controls to ensure system shutdown should

dangerous conditions arise. By designing the system with safety first, the team hoped to protect and

earn the trust of their end user.

1.7.3 Integrity

The design norm of integrity is closely associated with aesthetic beauty and ease-of-use. By integrating

easy-to-use controls and graphic interface, the team sought to incorporate beauty into the final design.

In addition, each component on the machine was carefully constructed to achieve both functionality

and aestheticism. Finally, the team’s logo was crafted to warrant professionalism and visual appeal.

21 http://anga.us/why-natural-gas/clean#.UmCKfPmsgyo

Page 27: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

12

2 Requirements

2.1 Safety

Due to high pressures and the flammable nature of natural gas, the most important design requirement

for the home refueling appliance is safety. The system shall adhere to all safety standards and come

equipped with monitoring equipment and emergency stops (E-stops). The system will also have a

pressure relief valve to vent gas in the case of over-pressurization. In addition, a check valve and shut-

off valve will prevent backflow and pressurization of the household natural gas system.

2.2 Price

Since the majority of commercially available CNG home refueling units cost more than $5000, the unit

shall have a production cost under $2,500 and a 2014 selling price between $3,000 and $3,500.

2.3 Refueling Rate

Nearly all of the units on the market operate with a faster fueling rate, ranging from 1.2-2.0+ GGEs per

hour. The appliance team’s appliance shall be a slow filling unit with a refueling time comparable to

plugging in an electric car overnight. This design shall have a fueling rate of 0.35 GGEs per hour. At this

rate, 3.5 gallons of gasoline would be replace by 10 hours of CNG refueling. This will provide about 90

miles of range for an average sedan.

2.4 Heat Loss

During compression, the temperature of the natural gas increases due to work being done on the gas

and the conservation of energy. When compressing to 3,600 psi without external cooling, the

temperature of the gas will exceed 350°F. This will be too hot to safely pump into a natural gas vehicle.

The team’s appliance will deliver natural gas to the vehicle at below 100 °F.

2.5 Serviceability

The appliance shall have minimal complexity and promote ease-of-service by qualified technicians. The

appliance will also be designed in such a way that weight is minimized, making transportation to and

from a service center easier.

2.6 Reliability

To withstand daily use and cyclical fatigue, the unit shall be reliable for 5 years without repair. This shall

grant competitive advantage over less reliable motor driven reciprocating CNG compressors.

Page 28: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

13

2.7 Noise

Designed for location in one’s garage, the refueling appliance shall operate with minimal noise

pollution. To achieve this, the noise level shall remain under 50 dB from a distance of ten feet away.

2.8 Size

As mentioned previously, this unit shall be stored in one’s garage. For this reason, the refueling

appliance shall take up less than 10 sq. ft. of floor space.

2.9 User Interface The unit shall incorporate an easy-to-use interface for simple operation and troubleshooting. This

aligns with the team’s design norm of integrity, making it easy for the user to understand the problem

with the appliance quickly.

Page 29: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

14

3 Deliverables

3.1 Project Proposal and Feasibility Study

NaturaFill shall submit a complete project proposal and feasibility study detailing a background on the

project, a proposed solution, and the feasibility of this solution. This report will be submitted no later

than December 9, 2013 at 3:30pm E.S.T.

3.2 Final Design Report

NaturaFill shall submit a final report at the completion of the project to explain the project background,

research and data analysis, design alternatives and decisions, prototype design and testing, and final

design conclusions. This final design report will be submitted no later than May 14, 2014 at 3:30pm

E.S.T.

3.3 Working Prototype

The team will demonstrate a working prototype of the refueling unit at the Engineering Department

Senior Design Night on May 10, 2014. The team hopes to demonstrate, on-stage, the refueling of an

actual natural gas vehicle.

3.4 Team Website

The team shall maintain a website as a means of updating the college, sponsors, and the public on the

project status. These updates shall be executed by Andrew Hall and will occur at milestones throughout

the project lifespan. All final updates to the website, including published final versions of the PPFS and

Final Design Report, must be made by May 12, 2014 at 3:30pm E.S.T.

Page 30: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

15

4 Design Considerations

4.1 Compression System

Early on in the project, a pivotal decision needed to be made as to what form of compression system

to use. Four types were analyzed: motor driven, wobble plate, pneumatic, and hydraulic.

4.1.1 Motor Driven Reciprocating Compression

A motor driven reciprocating compressor is the industry standard for compressing natural gas. Early

on in the process, the team ruled out this option due to lack of complexity and reliability issues on

similar refueling appliances constructed from these compressors. An example of this type of

compression system can be seen below in Figure 7.

Figure 7. Motor Driven Reciprocating Compression System

4.1.2 Wobble Plate Compression

The team talked to industry professionals and conducted extensive research to understand the function

and complexity of wobble plate compressors (see Figure 8. Wobble Plate Compression System). Lee

Otto, Founder of CNGPump, and Kurt Skov, Engineering Manager at Best Metal Products, both

expressed interest in this technology, which is typically used in automotive air conditioning units.

Research revealed high levels of complexity and potentials for unbalance in the linkages. Due to this

complexity and the perceived inability to prototype, the team determined that construction of a wobble

plate compression system was beyond the scope of the project.

Page 31: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

16

Figure 8. Wobble Plate Compression System22

4.1.3 Pneumatic Cylinder Compression

A pneumatic, or air driven, compression system would require one or many double rod pneumatic

cylinders being used to compress the natural gas to the required pressure of 3,600psi. To the team’s

knowledge, this technology has never been used to compress natural gas. The team speculates that

this might be due to a low cycle rate, the energy lost to heat when gas is compressed, and the potential

safety risk of mixing oxygen with natural gas. One positive of this design would be that home users

would have the use of the air compressor for other applications as well, such as running pneumatic

tools.

4.1.4 Hydraulic Cylinder Compression

A hydraulic cylinder compression system (Figure 9. Hydraulic Cylinder Compression System) would

require one or many double rod hydraulic cylinders to compress gas at a low cycle rate, similar to the

operation of a pneumatic system. In commercial applications, this technology is slowly being

introduced as an alternative to the motor driven reciprocating compressors. Due to high reliability and

off-the-shelf componentry, many companies and individuals in the industry believe that hydraulic

compressors have the potential for becoming the industry standard in natural gas compression.

22 http://www.jaguar-swansea.co.uk/aircon/systems.htm

Page 32: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

17

Figure 9. Hydraulic Cylinder Compression System23

4.1.5 Decision

To make the decision about what compression technology to utilize, a decision matrix (see Table 2) was

created by weighting a list of desired criteria and rating each design alternative on a scale of one to ten.

After totally the scores of each alternative, hydraulic compression was chosen due to its reliability, ease-

of-prototyping, and potential cost savings.

Table 2. Compression Technology Decision Matrix

Criteria Score Weight Motor Driven Wobble Plate Hydraulic Pneumatic

Cost to Manufacture 10 14% 5 5 5 6

Reliability 9 12% 5 8 9 7

Safety 9 12% 8 8 8 8

Ease of Use 7 12% 5 5 5 5

Serviceability 7 10% 4 3 10 10

Efficiency 6 10% 7 8 5 4

Prototype Cost 5 7% 5 8 8 9

Innovation 5 7% 1 10 6 8

Marketability 5 7% 5 8 7 5

Ability to Prototype 4 5% 7 5 8 7

Noise Pollution 3 4% 3 8 7 6

5.3 6.8 7.0 6.7

4.2 Lubricated vs. Oil-less

The team was faced with the problem of how to reduce friction in their system. There are two

common approaches to this problem: lubricated and oil-less. In natural gas compressors, lubricated

units require extra equipment to remove all the oil from the natural gas before it gets into the

vehicle’s fuel system. Oil-less compressors use low-friction polymer seals and cylinder linings to

23 http://www.hydropac.com/GRAPHICS/hydrogen3b.jpg

Page 33: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

18

reduce friction. Most current large-scale natural gas compressors use lubrication, but there is an

increasing trend toward oil-less compressors for the sake of simplify, reduced maintenance costs, and

a lower risk of damaging the vehicle’s fuel system. The team choose to build an oil-less compressor

for the reasons listed above.

4.3 Hydraulic System

Having decided upon a hydraulic compression system, research was conducted to determine setup,

sizing, and structure of the compressor and necessary componentry. Initial calculations of pressure and

heat generation directed the team towards a four-stage compression system consisting of two double-

acting hydraulic cylinders. After further calculation (see Appendix B. EES Calculations), it was

discovered that a two-stage system consisting of one double acting cylinder was possible if each

compression stage had a 16:1 compression ratio. This would reduce cost and complexity, thereby

aligning with the team’s mission and design requirement of serviceability.

4.3.1 Hydraulic Power Unit

The team discussed their needs for a hydraulic power unit with Ryan Anderson, a hydraulic power unit

technician with Bond Fluidaire, during a visit. The team discuss many of their requirements with

Anderson and they discussed ballpark pricing for their budget. The low-noise and very high run time

(often >12 hours) makes the team’s hydraulic power unit specifications different than most units used

in the industry. This led the team to compare both custom and off-the-shelf options for the hydraulic

pump and reservoir.

Custom

These units (see Figure 10: Custom Built Hydraulic Power Unit)24 require each

component of the system to be purchased individually, thereby reducing overall

cost. Custom hydraulic pumps are generally designed with a specific application

of the unit in mind. Because they are customizable, the team would be able to

construct a unit to a size appropriate for the final appliance prototype. A

concern with customized systems is that they are not typically intended to

reliability run for long periods of time.

24 http://www.gshydraulics.com/images/products/large/HydraulicPowerUnit01_CustomCompact.jpg

Figure 10: Custom Built Hydraulic Power Unit

Page 34: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

19

Off-The-Shelf

These units are all-in-one packages, designed for multiple applications. They are

comprised of a reservoir, hydraulic pump, electric motor, manifold, valves, and

piping and sold as one unit. These units are less customizable in size and can be

more expensive than their customized counterparts. On the flip side, off-the-

shelf hydraulic power unit units have increased reliability and require less labor

to assemble. Based on calculations (see Appendix C), the system would run at

full capacity with a pump rated for 4 gallons per minute. The team found a 1.25

gallon per minute hydraulic power unit in the parts closet in the Calvin College

Engineering Building, however, these calculations show that the team would

need to purchase a new pump in order to run the final prototype at full

capacity.

Decision

The team chose to use an off-the-shelf hydraulic power unit do to cost and accessibility. The optimal

off-the-shelf power unit would have the capacity of pumping 4 gallons of hydraulic fluid per minute.

The team decided to use the 1.25 gallon per minute power unit for their prototype. This system is not

optimum for meeting the team’s compression rate goals, but it will allow the team to prove the

mechanical concept of their design and still stay near their budget for the project.

4.3.2 4-Way, 3 Position Solenoid Valve

The team compared three methods of controlling the hydraulic fluid flow into the cylinder: open,

closed, and tandem centered solenoid valves (see Figure 12).

Open Centered

In neutral, all lines are open, placing the pump in open flow mode.2

Closed Centered

In neutral, all lines are blocked, also placing the pump in a state of stall.

Tandem Centered

In neutral, hydraulic fluid is cycled from the pump back into the reservoir. This

allows the pump to remain running, promoting longer life of the pump.

Decision

The team decided to use a tandem centered 4-way, 3-position solenoid valve for controlling the flow of

hydraulic fluid into the double acting hydraulic cylinder (see Figure 13). In doing so, the team hoped to

promote longer life of the pump, especially when operating in neutral, or centered, position.

Figure 11: Off-The-Shelf Hydraulic Power Unit

Figure 12: Solenoid Valves

Page 35: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

20

Figure 13: Tandem Centered 4-Way, 3-Position Solenoid Valve

4.4 Compression Cylinder System

4.4.1 Material

Deciding upon material, thickness, and size of the compression cylinders were critical steps before

additional design of the system could be accomplished. Each compression cylinder, modeled as thick-

walled pressure vessels, required high strength materials to withstand the pressure and heat generated

by the pistons themselves. After calculations and conversations with Best Metal Products, a custom

hydraulic cylinder manufacturer, the team decided upon thick-walled steel tubing as the material of

choice. Thick-walled steel tubing is reliable, easy to purchase, and relatively inexpensive. However, it is

produced in a limited variety of diameters. Furthermore, some machining work might need to be done

to get the inside wall to the specified exact diameter and tolerance.

Table 3. Steel Tubing Sizing Chart25

25 http://www.swagelok.com/downloads/webcatalogs/EN/MS-01-107.PDF

Page 36: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

21

4.4.2 Surface Finish

Having selected steel, the next challenge was reducing the amount of

friction between the piston and the compression chamber walls. The ideal

way of accomplishing this in industry is by using honed tubing. Honed

tubing can be purchased or machined in-house. Due to limitations of the

Calvin machine shop in maintaining honing tolerances, the team chose to

purchase the pre-honed steel (see Figure 14). The team also discussed the

possibility of coating the inside of the cylinders with PTFE, or Teflon, to

further reduce friction. This was deemed to be outside the scope of the

project because of the complexity and cost that would be required to

maintain extremely tight tolerances inside the cylinder with the PTFE

coated interior.

4.4.3 Sizing

The smallest and least expensive interior diameter available for honed steel tubing was 1.25”. Using

this sized tubing for the second compression chamber necessitated a 5” interior diameter of the first

stage compression cylinder, in order to maintain two 16:1 compression ratios while still using the same

stroke length for each stage (see Figure 14). Although this size cylinder diameter would reduce the

projected refueling rate for the final system, the team believed this design provided the most value for

the least cost.

4.4.4 Manifolds

The manifolds at each end of the compression chambers have many important functions within the

appliance. Needing to withstand the high pressures generated by the piston strokes, these manifolds

must have a high yield strength. In addition, they must be thick enough so that holes may be drilled

into the sides to release the compressed gas. Finally, there must be room for cylindrical milling on the

front faces of the manifolds themselves to secure the honed tubing in place.

Material & Thickness

After extensive modeling in AutoDesk Inventor and Solidworks, it was determined that 1” thick cold-

rolled steel would be strong enough to withstand impact force and pressures of 3,600psi, while

maintaining rigidity with the presence of internal cavities (see Figure 15: First & Second Stage FEA Stress

Simulations). One advantage is that steel is also relatively inexpensive compared to other high strength

materials. The downside is increased weight due to a density of 0.284 lb/in³ at STP.2

Figure 14: Pre-honed Steel Tubing

Page 37: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

22

Sizing

Having decided upon a 6” outer

diameter of the first stage

compression cylinder, it was

calculated that the manifolds

would need to be at least 7”x7” in

size. All in all, at the most extreme

operating conditions, the

manifolds will still maintain a

safety factor of over 3, as

indicated in Figure 15: First &

Second Stage FEA Stress

Simulations.

4.4.5 General Layout

Using an iterative design approach, the team

transitioned from a sandwich to pyramidal stacking

system for the compression and hydraulic cylinders.

Sandwich Stacking

The team originally modeled the two-stage

compression system as a sandwich, with each

compression cylinder held together by tie rods (see

Figure 16). This model proved difficult to attach a

hydraulic cylinder to. In addition, this model

necessitated a large amount of unnecessary manifold

material on the second compression stage, thereby adding weight and cost.

Pyramid Stacking

To add reinforcement and reduce material waste, the team proposed a pyramidal stacking layout, in

which each compression cylinder would be sandwiched independent of one another (see Figure 17:

Pyramid Stacking). This necessitated the addition of spacer plates and bolts between the hydraulic and

compression cylinders. Although they added complexity to the overall design, these modifications

resulted in a lighter and more robust system.

Figure 15: First & Second Stage FEA Stress Simulations

Figure 16: Sandwich Stacking

Page 38: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

23

4.4.6 Fittings and Taps

To reduce unnecessary complexity, the team sought to standardize the

threads and fittings used throughout the system. A key decision that

needed to be made involved whether to use NPT or SAE straight thread

fittings and taps. NPT, or National Pipe Thread, is normally tapered and

used primarily for gas and water pipe fittings. On the other hand, SAE

straight threading is more common in high pressure natural gas

applications. After conversations with two industry experts, both

recommended the use of SAE straight thread connections with O-ring seals

instead of Teflon tape seals on NPT threads. This, combined with the added

difficulty in machining tapered taps, led the team to decide on SAE-4

straight thread fittings and taps to pipe the natural gas out of each manifold

and into the next area of the system. In order to accommodate the

common fitting size of 1/4” NPT for monitoring equipment such as

thermocouples and pressure gages, the team also created 1/4” NPT taps in

their manifolds in addition to the SAE-4 taps.

4.4.7 Bolts & Threaded Rod

To insure the safety of the system, MathCAD was used to calculate the various safety factors for the

threaded rod and bolts in both compression system stages. Using an iterative design approach, the bolt

and rod specifications were modified until a minimum safety factor of 3 was found for each

compression stage. Modeled as a thick walled pressure vessel, the primary stress equations used in

these calculations were:

𝜎 = 𝑃𝑖𝑟𝑖

2−𝑃𝑜𝑟𝑜2

𝑟𝑜2−𝑟𝑖

2 ± 𝑟𝑖2𝑟𝑜

2 𝑃𝑜−𝑃𝑖

𝑟𝑖2(𝑟𝑜

2−𝑟𝑖2)

(1)

𝜏 = 𝐹

𝐴𝑒𝑓𝑓 (2)

𝑆𝑎𝑓𝑒𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 = 𝜎𝑚𝑎𝑥

𝜎=

𝜏𝑚𝑎𝑥

𝜏 (3)

Using UNC bolts and threaded rod, a summary of the calculated safety factors has been tabulated (see

Table 4: Bolt & Threaded Rod Safety Factors).

Figure 17: Pyramid Stacking

Page 39: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

24

Table 4: Bolt & Threaded Rod Safety Factors

1st Stage 2nd Stage

Safety Factor Spacer Plate Bolts Threaded Rod Spacer Plate Bolts Threaded Rod

Thread Shear 14.12 6.57 6.24 23.94

Tension 6.36 3.27 7.42 12.00

Tearout 482.75 84.48 241.38 307.75

Nut Stripping 16.18 6.73 7.61 24.51

4.4.8 Gaskets

The team originally intended to use a rubber-like material to seal the honed

cylinder to the manifolds. Having difficulty finding inexpensive gasket

materials, capable of withstanding the high temperature and pressures

generated by the compression chambers, the team consulted with Ross

Pursifull, a CNG research specialist from Ford Motor Co. Mr. Pursifull

recommended the use of O-rings instead of gasket materials. After further

conversations with Zatkoff Seals and Packings Inc., the team decided upon a

fluorocarbon rubber O-ring material for satisfactory sealing functionality (see

Figure 18: O-Ring Seals). The team decided to sill utilize gasket materials to seal between the manifolds

and the spacer plates and between the spacer plates and the hydraulic cylinders. These seals are part

of the low-pressure blow-by recovery system, which captures gas that slips past the pistons and carries

it back to the low pressure gas supply side of the system.

4.4.9 Pistons

Material

The team researched three materials for constructing the pistons:

steel, aluminum and PTFE (Teflon). Steel is relatively inexpensive

for its strength. The heaviest material of the three, raised concerns

over unnecessary unbalance issues. Aluminum pistons are most

common in both compressors and internal combustion engines,

due to their relatively light weight and high thermal conductivity.

There was some thought in possibly making the pistons out of PTFE

(Teflon). This would have eliminated the need for seal rings

Figure 18: O-Ring Seals on Manifold

Figure 19: 5" Diameter Aluminum Piston

Page 40: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

25

because the entire piston would be made out of an extremely low-friction material. Disadvantages of

using PTFE include the very high cost of the raw material and fact that using PTFE as a piston material

is unproven. All this considered, the team eventually decided upon aluminum (see Figure 19).

Seals

The team researched three methods for sealing the pistons to the compression chamber walls: oil,

Teflon, and bronze sleeves. Oil sealing is the conventional method for sealing air and natural gas

compressors. Oil provides excellent wear protection and blow-by elimination. Disadvantages to oil

seals include the added complexity involved with preventing leaks and having to check oil levels on a

regular basis. Also, natural gas compressors equipped with oil seals require additional filters to ensure

that the oil does not contaminate the natural gas going into the vehicle.

Oil-less compressor technology uses low-friction cylinder wall coatings, such as PTFE (Teflon), and seal

rings made out of low friction polymers, such as PTFE or PEEK, to protect against wear and excessive

heat generation while still maintaining at tight seal. A disadvantage of this alternative is the high cost

of low-friction coatings and polymers.

In discussions with Lee Otto, founder of CNGPump, he recommended the use of a bronze sleeve inside

the cylinder wall and bronze bushing seals to provide a tight seal. This alternative would be simple and

inexpensive. A disadvantage of this alternative is the relatively high coefficient of friction of bronze

compared to oil seals and PTFE.

After weighting the pros and cons of each alternative, the team decided to use PTFE cylinder wall

coatings and PTFE rings. This decision was based on the team’s requirement for a very low friction seal,

as well as the need to avoid contaminating the natural gas with oil. In regards to layout, two PTFE

Figure 20: Layout of PTFE Seals & Rider Rings

Page 41: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

26

(Teflon) rider rings will be used to stabilize the piston as it moves up and down inside the cylinder walls

(see Figure 20: Layout of PTFE Seals & Rider Rings)26. Located inside these rider rings will be two PTFE

(Teflon) seals, providing the majority of the main protection against blow-by inside the compression

chamber. This design is far more common in the industry and the team hypothesizes that the gas being

allowed to pass through the rider rings freely will lead to better stabilization for the piston. If the sealing

from this layout proves insufficient the team will modify it by adding additional seal rings.

4.5 Natural Gas System

The natural gas system will move the gas from a residential natural gas line, through each of the two

compression cylinders, and ultimately into the tank of a natural gas vehicle. It is designed to dissipate

heat, prevent backflow, and monitor the thermodynamic states of the natural gas using thermocouples,

pressure gages, and a pressure transducer.

4.5.1 Heat Removal

The team researched three ways for dissipating heat from the natural gas: fins, tubing loops, and fans.

Fins

Finned tubing is a very common way to dissipate heat from a working fluid. The fins provide increased

surface area for heat transfer to the air to occur and therefore increase heat transfer rates. A

disadvantage to this alternative is the fact that most finned tubing is designed for low pressure

applications. Should fins be installed on high pressure tubing, separation between the tube and fins

may occur due to thermal expansion and contractions in the metal. There is another type of finned

tubing in which the fins and tubing have been bonded together in a heat welding process. These custom

finned tubing systems, specifically designed for high pressure applications, are unfortunately very

expensive.

Tubing Loops

Another common means of heat dissipation within working fluids is tubing loops. Since natural

convection relies on surface area, adding loops to metal tubing increases surface area and thus, heat

transfer. In reference to the CNG refueling appliance, this method would increase the volume of gas in

the heat sink and allow more time for the compressed natural gas to cool. Disadvantages to tubing

loops include the additional cost of buying extra tubing and the additional labor cost involved in bending

the tubing to create the heat sinks.

26 http://www.ihi.co.jp/compressor/en/products/process-gas/gas-recipro/images/fea_photo_01.jpg

Page 42: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

27

Fans

Fans are another very effective way to dissipate heat from a working fluid into the surrounding air.

Disadvantages to using fans include increased noise pollution and corrective maintenance due to the

additional moving parts. Fans also require routine maintenance and cleaning.

Decision

The team has decided to use tubing loops to cool the natural gas between each compression stage.

Due to this method’s added reliability and durability, the team sees this as the most ideal method for

heat removal. While it may cost more upfront, the team sees this as the better long-term option.

4.5.2 Pressure Sensors

Pressure Transmitter

Pressure transmitters (see Figure 21: Pressure Transmitter) measure pressure using

a strain gauge and output a low-voltage signal that corresponds to a certain

pressure. This low-voltage signal must be converted to a digital signal using a DC to

AC converter chip in conjunction with a computer-based control system. These

sensors would be used in combination with thermocouples to determine the

thermodynamic state of the compressed natural gas. This is critical for creating

accurate heat transfer and fluid flow models. In addition, these signals can be

interpreted by the computer control system to shut down the machine

should pressures get too high. The disadvantage of using pressure transmitters is their relatively high

cost compared to simple pressure gages.

Pressure Gages

Pressure gages (see Figure 22: Pressure Gage) provide a relatively inexpensive way of

measuring pressure. These gages are more robust and reliable than their digital

counterparts. In addition, their threaded mounts make them easily installable on

most tubes and fitting. The major disadvantage of pressure gages is that data

acquisition must be done manually by a human being. This not only reduces the

accuracy of the data, it greatly limits the number of pressure samples being

taken. Should corrective maintenance be necessary on the appliance, historic pressure data would be

unattainable. Furthermore, emergency safety stops cannot be computer programmed using pressure

gages.

Figure 22: Pressure Gage

Figure 21: Pressure Transmitter

Page 43: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

28

Decision

The team has decided to use a pressure transmitter for the final compression stage and pressure gages

for all the other stages. At minimum, the team needs this one digital pressure transmitter to ensure a

final stage pressure of 3,600 psi and indicate to the computer when the natural gas vehicle tank is full.

Furthermore, readings from this transmitter are necessary for the system’s programmable safety stops.

Multiple pressure transmitters throughout the system were deemed too costly and not value added.

4.6 Control System The team looked into two options for the electronic controls and display of the overall system: a

Raspberry Pi development board and LabVIEW/FieldPoint module assembly.

4.6.1 Raspberry Pi

In comparison to similar development boards (see Table 5), the Raspberry Pi (see Figure 23)

accomplishes all necessary mechanical, safety, and relay functionalities at approximately half the cost.

Table 5. Comparison of Development Boards27

Dev Board Raspberry Pi BeagleBone Black CubieBoard

Price $25-$30 $45-$55 $50-$60

CPU 700 MHz Low Power ARM1176JZ-F

AM335x 1GHz ARM Cortex-A8

Arm Cortex A8 1GHz

GPIO 8 GPIO pin I²C, SPI, UART

Two 46 Pin Configurable Bus

Two 48 Pin Configurable Bus

Power 5V, 1A 5V, 700mA 5V, 2A

Memory 512MB SDRAM (Model B)

2GB embedded MMC

NAND (max 64GB) SATA II, SD

Card 3.0

Dimensions 8.6x5.4x1.7(cm) 10×6 (cm) 90x40x13(mm)

Application Learning Embedded apps Robotics

Basic Learning Embedded apps Robotics

Advanced Learning Embedded apps Video Robotics

Ease of Use Easy Easy (but closed) I/O and peripherals are not so easy to manage

27 http://www.open-electronics.org/a-comprehensive-comparison-of-linux-development-boards/

Page 44: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

29

The only downside to the Raspberry Pi is the limited onboard input and

output (I/O) ports. In addition, the onboard I/O is limited in connection

pins and zero tolerance to anything above 0.0 or 3.3V. Furthermore, the

onboard general-purpose input/output (GPIO) pins are connected directly

to the connection pins of the processor, causing potential for the entire

board to fry. The Slice of PI/O is just one available option for protecting

the Raspberry Pi’s unguarded input and output pins. This Slice of PI/O ad-

on is inexpensive and provides the Raspberry Pi a buffer, conversion levels,

analog I/O, and protection devices to avoid the risk of damage. Overall,

there are many breakout boards that have been developed and can be

easily plugged into the Raspberry Pi’s GPIO pins. This development

board, an all-in-one package, would function well to control the final appliance and relay data to an

ascetically appealing user interface (see Figure 24: Raspberry Pi Control Schematic).

Figure 24: Raspberry Pi Control Schematic

Figure 23: Raspberry Pi Computer

Page 45: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

30

4.6.2 National Instruments LabVIEW & FieldPoint

The second option analyzed involved using lab monitoring equipment from National Instruments (NI).

Using NI FieldPoint input, output, thermocouple, power supply, and Ethernet modules (see Figure 26),

the team would record and display temperature and pressure data. In addition, feedback loops could

be created to shut the system down should the system reach an unsafe operating environment. All

data and programming would be managed using National Instruments LabVIEW 8.5 (see Figure 26).

4.6.3 Decision

Originally, the team decided on the Raspberry Pi because of its compact size, ease of use, and vast

online community presence for additional support. At the beginning of February 2014, the team was

notified that the only electrical engineer in the group, was dropping out of engineering. Having already

chosen and purchased a Raspberry Pi development board, the team of three mechanical engineers

began researching how to program it. It was soon realized that this was beyond their technical

knowledge. Therefore, the team has chosen to use NI LabVIEW & FieldPont to demonstrate the

mechanical feasibility of the final prototype (see Figure 27: LabVIEW Block Diagram). Should this

appliance go into production, a Raspberry Pi would be used instead.

Figure 26: NI FieldPoint Modules Figure 26: LabVIEW Interface

Page 46: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

31

Figure 27: LabVIEW Block Diagram

Page 47: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

32

5 Calculations

5.1 Summary

In order to determine the size requirements for the natural gas compression cylinders, the stressed

experienced by the system, and the heat transfer required in the tubing connecting the cylinders, the

team has decided to use a combination of Engineering Equation Solver (EES), MathCAD, and Autodesk

CFD simulator. EES was chosen for its ease of use, integration of thermodynamic properties, and

potential for optimization. Autodesk CFD simulator was chosen for its ability to simulate fluid flow,

compression, and heat transfer simultaneously. MathCAD was used in order to calculate the stresses

incurred by compression.

5.2 Autodesk CFD

5.2.1 Overview

Due to the complexity of this project and the difficulty and expense in implementing design changes

after production begins, the team will use Autodesk CFD to test initial designs. A variety of design

changes such as length of the cylinders, diameters of the cylinders, and wall thickness of the cylinders

will be altered and simulated in order to optimize our design.

5.2.2 Goals

The end goal of using Autodesk CFD is to have a full working model of the system that simulates and

shows the changes in pressure and temperature as the natural gas goes through it.

5.2.3 Status

Currently a simple model of compression has been successfully simulated. The purpose of creating this

model was to

5.2.4 Results

Figure 28. Pressure Results from Simulation shows the trend of the data obtained from the simulation

modified to account for calibration error.

Page 48: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

33

Figure 28. Pressure Results from Simulation

Figure 29. Plane of Simulation Pressure Results shows a plane from the simulation pressure results

showing the higher pressure after compression.

Figure 29. Plane of Simulation Pressure Results

5.2.5 Conclusion

After obtaining these results from Autodesk CFG, it was decided that additional testing would be time

consuming and would be a poor use of the limited time.

Page 49: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

34

5.3 Engineering Equation Solver

5.3.1 Overview

In conjunction with simulating the compressor, calculations are being done in EES in order to ensure

that the results obtained from the simulation are accurate as well as create the frame work for the

initial design.

5.3.2 Procedure

A model of compression was used to determine the bore of the two compression cylinders along with

the stroke. Once those values were obtained, a mass flow rate could be calculated to perform a heat

transfer analysis

5.3.3 Results

Table 5 shows the results for work required from the pistons and heat removal requirements assuming

that the temperature will be brought down to about room temperature in between compression

stages. Full results and calculations can be found in Appendix B. EES Calculations.

Table 6. Work and Heat Removal Calculation Results

First Stage Work Required 1,167 (BTU/hr)

First Stage Heat Removal Require 1,121 (BTU/hr)

Second Stage Work Required 1,137 (BTU/hr)

Second Heat Removal Require 1,137 (BTU/hr)

5.3.4 Conclusion

From these calculations it was determined that a two stage compression with two 16 to 1 compression

ratios would compress the gas to the required pressure. From there it was determined that at the

desired flow rate, with a low value of convective heat transfer rate, that 10 feet of tube would be

enough to cool the gas off to the required temperature.

5.4 MathCAD

5.4.1 Overview

In order to insure safety, stress calculations needed to be done on each mode of failure in the bolts that

will hold the compressor together. To perform these calculations MathCAD was used for its user

interface and capability to format equations neatly.

Page 50: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

35

5.4.2 Procedure

Stress calculations we performed on each mode of failure for each bolt. The axial stress that would pull

the manifolds apart were calculated using a thick walled pressure vessel calculation. The stresses in

shear for both the threads on the rod and the nut, along with axial tension, and tear-out stress were

calculated using the appropriate effective area. Once the stresses were found, the safety factors were

calculated using the minimum proof stress of the bolts in consideration.

5.4.3 Results

The results of the safety factor calculations have been tabulated in Table 4: Bolt & Threaded Rod Safety

Factors.

5.4.4 Conclusion

Given that the minimum safety factor calculated was 3.27, it was decided that the bolts specified would

adequately hold the compressor together even in the case of a malfunction causing an unexpected

pressure increase.

Page 51: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

36

6 Final Design

6.1 Hydraulic System

6.1.1 Overview A hydraulic system will be used to convert electrical energy into mechanical work that will drive the

pistons a therefore compress the gas. An overview schematic of the proposed hydraulic system is

shown below in Figure 30: Hydraulic System Schematic.

Parker 3L Series Double Rod

Hydraulic Cylinder

Ashcroft 5000 psi

Pressure Gauge(s)

Figure 30: Hydraulic System Schematic

D03 Solenoid-Operated

Hydraulic Control Valve

5000 psi Tubing

with SAE 6 Straight

Thread Fittings

1.25 Gallon Hydraulic Pump &

Reservoir Monarch Hydraulics Inc.

Page 52: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

37

6.2 Natural Gas System

6.2.1 Overview The natural gas system will move the gas from a residential natural gas line, through each of the four

compression cylinders, and ultimately into the tank of a natural gas vehicle. It also is designed to

prevent backflow at every possible point and monitor the thermodynamic state of the natural gas using

thermocouples, pressure gages, and a pressure transmitter. A schematic of the natural gas system is

shown below in Figure 31.

Figure 31. Natural Gas System Schematic

6.2.2 Residential Natural Gas Supply The team’s unit will be optimized to operate on a residential natural gas system with a pressure of 2

psi. This is the industry standard for larger homes, while 0.3 psi is standard for average homes. Natural

gas utility companies will usually install a 2 psi meter/regulator on a house if the customer has a special

reason to have one. Since the team’s system is an “intensifier” type of compressor, the initial pressure

into the first stage of the compressor is very important. To protect older appliances not design to used

2 psi natural gas, the team will recommend that customers who have to upgrade to a 2 psi

meter/regulator add an additional step down regulator to their residential natural gas system so that

their other appliances can continue to operate on 0.3 psi.

6.2.3 Piston Seals

After completing some initial research, the team realized that getting the piston seal to hold high

pressure gas and prevent it from blowing by the piston would be the most difficult part of the project.

The team had a conference call with Lee Otto of CNGPump, who makes hydraulic natural gas

compressors, and discussed the issue of piston seals. Mr. Otto stressed the importance of a “mirror-

Page 53: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

38

like” finish on inside of the chamber. The team achieved this by using honed tube. He also mentioned

starting with bronze bushings as seals for a crude prototype. He mentioned that PTFE (or Teflon) seals

would be a good next step. He mentioned that his compressors use a proprietary material that he

claims has ten times less friction than PTFE.

The team decided that they wanted to start with PTFE to increase their chances of having a successful

prototype. This led them to contact Zatkoff Seals and Packings, were they meet Mr. Jerry LaBreck. Mr.

LaBreck assisted the team in finding the seals that would best suit their needs. Mr. LaBreck contacted

engineers inside the seals division of the Parker Hannifin Corporation and they prescribed the FBS-C

Flexiseal product to best meet the team’s requirements. The seals are made of carbon reinforced PTFE

and contain a spring that “energizes” the seal to constantly maintain contact with the inside of the

cylinder wall.

6.2.4 Tubing The team will be using stainless steel tubing to pipe the natural gas between compressor stages. The

team has selected ¼ in. OD tubing, with a wall thickness of 0.049 in. According to Table 3, this will give

the team the capability to handle 3600 psi with a safety factor of 2.

6.2.5 Check Valves As displayed in Figure 32, the team’s design uses check valves at every point where backflow could

possibly occur.

Figure 32. High Pressure Natural Gas Check Valves28

6.2.6 Relief Valve The design utilizes an adjustable pressure relief valve after the final stage. Gas is always free to flow in

the forward direction, therefore if over-pressurization occurred anywhere in the system it will be

relieved through this relief valve. An examples of adjustable relief values made for high pressure

natural gas applications are shown below in Figure 33. As a cost saving measure, a relief valve was not

28 http://www.hylokusa.com/products/valves/check-relief-valves.aspx

Page 54: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

39

used in the prototype. The system was still adequate because it was to be attended by a team member

during testing to ensure over-pressurization did not occur.

Figure 33. Adjustable High Pressure Natural Gas Relief Valves29

6.2.7 Shut-off Valve A manual shut-off valve will be utilized between the residential natural gas system and the first stage

of the compressor. The will allow the compressor to be shut of manually during servicing. An example

of a ball valve made for compressed natural gas applications is shown below in Figure 34. This was not

implemented into the prototype because the team was only compressing atmospheric air during

testing.

Figure 34. Example of CNG Ball Valve30

6.2.8 Manifolds Manifolds will be used to distribute the compressed natural gas at the end of each compression

chamber. The piping system will be attached to the manifolds using SAE Straight Thread O-Ring and

NPT treaded adapters and Teflon tape to seal the connection. These manifolds will be constructed out

29 http://www.hylokusa.com/products/valves/check-relief-valves.aspx 30 http://www.hylokusa.com/compressed-natural-gas/cng-parts.aspx

Page 55: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

40

of steel. An example of a manifold used to distribute gas at the end of a hydraulic natural gas

compression system is shown below in Figure 35.

Figure 35. Example of Manifold and Connections at End of CNG Compression Chamber31

6.2.9 Pressure Gauges and Transducers The team knew that they would have to monitor pressure and temperature inside each stage to test

and optimize their design. Temperature and pressure will be known so that the thermodynamic state

can be determined. This will allow the team to perform accurate heat transfer and fluid flow analyses

on the system.

Pressure transducers are very costly, however the team needed at least one to monitor the pressure

after the final stage. An example of a pressure transmitter is shown below in Figure 36. This is

necessary in order to tell the control system when the vehicle tank is full (pressure has reached 3600

psi). Regular pressure gages will be used to monitor the pressure of all other stages, these an example

of one of these gages is shown below in Figure 37.

31 http://www.gonaturalcng.com/wp-content/uploads/2012/11/cng_compressors.png

Page 56: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

41

Figure 36. Pressure Transmitter Example

Figure 37. Pressure Gage Example

6.2.10 Heat Sinks The compressor design will utilize tubing loop heat sinks and a fan to being the compressed gas back to

room temperature following each compression stage. An example of utilizing tubing links as a heat sink

in conjunction with a fan is shown below in Figure 38. This will improve the overall isentropic efficiency

of the system and result in safer operation that is less prone to overheating.

Figure 38. Example of Tubing Loops32

32 http://www.lmcompressor.com/images/Web%20Page%20CNG_3021%20_.jpg

Page 57: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

42

6.2.11 Blow-By Recovery System

After discussions with consultant Leo Otto and Professor Nielsen, it became apparent that the team

would have to devise a system to recover the natural gas that slips past the piston during compression.

The team decided to feed this gas back into the low-pressure supply of the system. This will allow the

volume behind each piston to remain at supply pressure. Check values were used to prevent backflow.

6.2.12 Refueling Nozzle Fuel will be dispensed using a purchased compressed natural gas fueling nozzle. There is an accepted

industry standard for these nozzles. Any nozzle purchased will fuel any compressed natural gas vehicle.

More complex and expensive nozzles are available, but because they are design for fast-fill units.

Because the team’s compressor is a time-fill unit, the simplest nozzles will be sufficient. An example of

a general purpose compressed natural gas refueling nozzle is shown below in Figure 39. This was not

integrated into the team’s prototype because the team made a direct connection into the CNG tank

using stainless steel SAE straight thread O-ring tube fittings instead. This was done to save cost and

was feasible because the demonstration tank was permanently mounted to the top of the appliance.

Figure 39. General Purpose CNG Refueling Nozzle for Time-Fill33

6.3 Control System The final prototype combined the functionality of National Instruments FieldPoint modules and a

computer loaded with LabVIEW 8.5 to demonstrate the mechanical functionality of the overall system

(see Figure 27: LabVIEW Block Diagram). This system had many components, including, but not limited

to, a sealed enclosure box, input and output FieldPoint modules, three solid state relays, a power

distribution bus bar, two high temperature thermocouples, a pressure transducer, a power supply, and

multiple strain release gaskets to preserve the functionality of the wires (see Figure 40).

33 http://www.opwglobal.com/Product.aspx?pid=138

Page 58: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

43

6.3.1 Enclosure Box

A sealed enclosure box was used to ensure that any potential natural gas leaks would not ignite with

sparks generated by the electrical componentry (see Figure 41). Nylon glands were used to seal around

the cords entering the box and silicone sealant was used to seal around holes in the boxes that were

left over from previous users.

Figure 41: Sealed Electrical Control Box

6.3.2 FieldPoint Modules

Din rail mounted FieldPoint modules were used for all data collection and feedback. These

components, valued at over $2,000, were lent to the team by the college for testing purposes. Using

an FP-2000 Ethernet controller, data was channeled from the modules, through a router, and then into

a Windows XP computer capable of supporting legacy FieldPoint software (see Figure 42).

Figure 40: Compiled Control & Monitoring System

Page 59: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

44

Figure 42: FieldPoint Module Communication with Windows XP

6.3.3 Solid State Relays

Solid State relays used the extremely small current DC output of the FieldPoint IO device to switch 120V,

12A AC current for powering of the hydraulic pump and solenoid valve. These relays were used because

they could be switched with .005mA of input DC current, thus aligning with the FieldPoint unit’s output

capabilities (see Figure 43).

Figure 43: Solid State Relays

Page 60: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

45

6.3.4 Thermocouples As stated above, the team needed to monitor the pressure and temperature of the gas at each stage

for accurate heat transfer and fluid flow modeling. Monitoring the temperature at every stage was

more important than monitoring the pressure at each stage because it is impossible for over-

pressurization to occur during the first three stages because gas is always free to flow in the forward

direction. Over-heating, however, can theoretically occur at any stage in the system. Therefore, a

thermocouple was installed after each compression stage to monitor the temperature of the gas leaving

that stage. Using this temperature data, LabVIEW was programmed to shut down the pump and

solenoid valve should temperature exceed 250 degrees Fahrenheit. These thermocouples were pipe-

plug type that threaded into the manifolds using 1/4” NPT threads and provided a high pressure seal to

prevent gas from escaping through the thermocouple port.

Page 61: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

46

7 Prototype Development

7.1 Machining

In order to build a compressor, a variety of parts needed to be machined with some requiring tight

tolerances. The parts machined by the team include, four end-plate manifolds, two spacer plates, four

spacing collars, a coupling nut, honed tube for cylinder wall, and six total pieces required to form two

pistons. The technical drawings of these parts can be found in the appendix. A steel frame was also

constructed in order to hold all the components together.

Figure 44: Machining

7.2 Fabrication & Assembly

Once all the components of the compressor where machined, their dimensions were verified and

assembled to insure proper fit. The compressor was then assembled using the bolts and threaded rod

specified earlier.

Page 62: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

47

Figure 45: Fabrication & Assembly

7.3 Modifying

Once initial assembly was completed, the team tested the compression ratios of the first and second

stage compressors. Due to some uncertainty in calculating the top-dead-center volume, the team

planned to adjust the position of the piston on the extended tie-rod of the hydraulic cylinder, thereby

reducing the volume at the end of compression. An example of this is shown below (see Figure 46:

Piston Spacing Diagram). The team made a number of changes until the desired compression ratios

were achieved.

Page 63: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

48

Figure 46: Piston Spacing Diagram

7.4 Mounting

Once the system was tested, it was mounted in a steel case with the hydraulic pump. Once mounted,

steel tubing was used to connect all aspects of the hydraulic system and the natural gas system (see

Figure 47: Mounting of Final Prototype).

Page 64: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

49

Figure 47: Mounting of Final Prototype

Page 65: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

50

8 Testing

8.1 Test Planning

As previously mentioned, LabVIEW was chosen to test the feasibility of the system. Multiple

thermocouples and a pressure transducer were set to take data during testing. In addition to the

collection of data, the LabVIEW software was used to set up safe guards which would shut down the

system if an unsafe pressure or temperature was reached. Finally LabVIEW was used to control the

solenoid valve of the hydraulic cylinder, thereby controlling the system.

8.2 System Testing

8.2.1 Air Testing

To insure safety while still testing the feasibility of the system, initial testing of the system will be testing

using air. The goal of this test is to insure that the system can withstand the pressures associated with

compression.

8.2.2 Natural Gas Testing

Once testing with air proved that there is no potential for leaks in the system, the team was planning

on testing the system with natural gas. The results from this test were to show if the system meet the

required goals. The team was unable to test their prototype with natural gas due to safety concerns

and a lack of adequate time. However, the team is confident their system is capable of safely

compressing natural gas.

8.3 Results

8.3.1 Compression Ratios

The team started testing each cylinder individually using atmospheric air. The goal of these tests were

to verify that each stage was indeed result in a 16:1 compression of the air. This meant that the team

had to achieve a maximum pressure of about 225 psi from an input of atmospheric are. The team

adjusted the spacing between the piston and the rear of the threaded portion of the hydraulic rod in

order to adjust the total volume in the cylinder. After the team was confident that both stages were

near a 16:1 ratio, they plumbed the two stages together with a heat sink and check valves in between

the two chambers.

Page 66: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

51

The team then plugged the output of the second stage manifold in order to determine the maximum

pressure that the compressor could achieve. These tests went very well, and the team was able to

achieve their goal of the compressor generating the target pressure of 3600 psi, as seen in Figure 48.

Figure 48: Pressure Reaching 3,600 psi

Figure 49: Temperature Data from Testing

Page 67: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

52

8.3.2 Pressure and Temperature

The team set out to monitor pressure and temperature during these tests, however the team was

unable to gain good data from the pressure transducer. In the Figure 49, the pressure has been

approximated by manual observation due to the malfunction of the team’s pressure transducer. This

approximation was conducted by applying a linear fit to the beginning and final pressures achieved

through the test run.

8.3.3 Friction

The team saw a pressure in the hydraulic lines of approximately 400 psi when the piston was moving

without pressure. Calculations were done to find the force required to overcome the friction force in

the system, these calculations are shown in Appendix C. The results of these calculations showed a

force of 8.73 kN needed to overcome the friction in the system. This high number is to be expected

because of the extremely tight, interface fits between the seals and rider rings and the inside of the

cylinder.

9 Obstacles

9.1 Controls

As mentioned previously, the team unfortunately lost its only electrical engineering during the month

of February. This led to the decision of using National Instruments equipment to control the system.

Since all the remaining team members were mechanical engineers, there was a lack of experience in

wiring the control panel. This inexperience prompted the wiring of AC current to the DC input $1,500

Ethernet control module. The module failed to operate after several attempts of rewiring. Finally, it

was discovered that a fuse had been blown during the accident (see Figure 50).

Page 68: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

53

Figure 50: Blown Fuse in Ethernet Controller

By soldering a wire between the connectors of the fuse holder (see Figure 50), the module came back

to life and was able to operate flawlessly for the remainder of the project. The team member who

made this mistake has learned his lesson and will not make such mistake again.

9.2 Piston Seals

After the team had selected a carbon-reinforced PTFE Parker FBS-C Flexiseal with the help of Mr. Jerry

LaBreck from Zatkoff Seals and Packings and engineers from the Parker Hannifin Corporation, the team

was told that these seals were a custom product and that they would have a 6 – 8 week lead time. This

was discouraging to the team, because they had initially planned on building a small, single stage model

of their design before beginning to construct their final prototype. The long lead time associated with

the seals forced the team to reconsider this plan and eventually opted to move on to building their final

prototype without building a small scale model. Mr. LaBreck and the Parker engineers also assisted the

team by supplying basic build parameters for the pistons that the seals would mount to. The team was

satisfied with the performance of the seals and their decision to move directly to building their final

prototype.

9.3 Storage Tanks

For the sake of simplicity, cost savings, and reduced testing time, the team initially proposed using part

of the honed tube that was donated to create a miniature pressure vessel to hold the compressed gas.

Page 69: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

54

The team was informed by the company that donated the honed tube that it was against ASME

regulations to use the honed tube for this purpose. This led to the team needing to acquire a tank to

compress air and eventually natural gas into. The proposed design of the pressure vessel is shown below

in Figure 51.

Figure 51. Proposed Pressure Vessel

Because of this, the team was forced to find natural gas tanks which are costly. Luckily the team was

able to borrow the tanks from Crazy Diamond which helped the team substantially.

9.4 Gaskets

The team initially thought that they would use gaskets to seal between the honed tube and the

manifolds. The team contacted a few local gasket distributors, but found it difficult to find a gasket

material that would withstand the high temperatures and pressures that the design required. This lead

the team to address this issue in a conversation with their mentor, Ross Pursifull of Ford Motor

Company. Mr. Pursifull suggested that the team use O-rings instead of gaskets to achieve the seal

between the honed tube and the manifolds. We contacted Jerry LaBreck at Zatkoff Seals and Packings

Page 70: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

55

and he supplied us with the O-rings we needed as well as the specifications for the grooves that were

to be cut in the manifolds to hold the O-rings in place.

9.5 Top Dead Center Volume

The team calculated a top dead center volume knowing that there may be some inaccuracy with the

calculation due to the complexity of determining exactly where top dead center is due to the check

valves. Upon initial tests however the team found that the on the second stage, the volume in the veins

of the top manifold to too large, meaning that a 16:1 compression ratio could not be achieved. To solve

this problem the team had to redesign and remake the manifold with smaller holes for the gas to flow

through. This redesign eliminated the problem and allowed the team to achieve a 16:1 ratio in the

second stage and therefore achieve their target pressure of 3600 psi.

9.6 Piston O-Ring Seal

In order to seal the piston so that no gas could get through the center hole of the piston, O-rings were

placed on both the top side and bottom side of the piston with the bottom O-ring held in place by a

washer. The bottom of the piston with the O-ring is shown below in Figure 52.

Figure 52. Piston O-ring

The problem that the team faced with this O-ring was first of all that the inner diameter was too large.

This caused the washer to cut through the O-ring when used. The washer was replaced with a second

O-Ring

Page 71: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

56

washer, however after testing it was found that the O-ring has squeezed around the washer. A final

washer was used with a small enough inner diameter and a large enough outer diameter. After testing

with the third washer it appears that the O-ring is not sealing the way the team had hoped. To solve

this problem, the team recommends cutting a groove into the bottom of the piston for the O-ring to sit

in.

10 Future Improvements

10.1 Proper Component Sizing

As shown in the hydraulic power unit calculations in

Page 72: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

57

Appendix C. MathCAD Calculations, the hydraulic power unit used for the final prototype does not

provide enough power to move the system at a frequency of 4 cycles per second. The team was

achieving about 10 seconds per cycle with their 1.25 gallon per minute hydraulic pump.

In order to correct this disparity, the team thinks it would be best to reduce the size of the compressor

as opposed to increasing the size of the hydraulic power unit. This decision was made in light of the

fact that 1.25 gallon per minute hydraulic power units are readily available at a very economic cost

because they are used for common applications such as log splitters and pipe benders. The team think

that they would be able to create a unit that averages a compression rate of around 0.2 GGE per hour

with this change. This is under the goal that the team initially set out to achieve, but it is the only way

the team forces being able to build a compressor that is economical for home residential applications.

A large CNG tank could be added to a low-rate system like this in order to provide a buffer should the

customer need fuel quickly.

10.2 Noise Control

The team initially planned to implement a noise control system with their final prototype. When the

team was forced to prioritize with features were most important to include in their final prototype, the

noise control system was ruled out because it was non-essential to proving the mechanical viability of

the system and would have made accessing the system for modifications, testing, and demonstration

difficult.

If the team were to take their prototype to production, a noise control system would be an essential

part of the final product. The team believes that covering the outside of the frame with sheet metal

and spraying the inside of the sheet metal with a polyurethane foam would be the best initial design

for implementing noise control. One difficulty with this approach would be that heat would be trapped

inside the enclosure, along with the noise. Initial testing shows that heat generation for the prototype

is low due to its low compression rate. The team feels that the heat generation would be small enough

to not cause a problem with the noise control system, but there is no way to test this hypothesis at this

time.

10.3 Imbedded Electronics

As mentioned, a production model of this system will incorporate all the electronic functionality of the

current system using an imbedded development board. This board will communicate to an LED display

Page 73: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

58

and allow for ease-of-use and aesthetic appeal. In addition, this onboard computer will have all the

necessary safety systems and emergency stops.

10.4 Fabricating for Flexibility

When the team fabricated the frame for the equipment to mount in, they welded all of the cross-

member mounts that the equipment would sit on. This meant that the equipment could not be

removed from the bottom of the unit. This often meant that the team had to spend many hours

unbolting the entire compressor to adjust some the volume of the chambers. If the team would have

had the foresight to bolt the mounts to the frame, modifying and tuning the compressor would have

been much easier.

Page 74: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

59

11 Financial Estimates

11.1 Cost of Development

The estimated and actual budget for the development of the team’s home refueling unit prototype is

listed in Table 7: Operational Budget. Initial research into the component costs for the preliminary Bill

of Materials resulted in a total operational budget of $3,000.

Table 7: Operational Budget

Originally, the college granted the team $2,000 of this $3,000 proposed budget, assuming the rest

would be supplemented by donations. Although Wolverine Oil & Gas did grant the team an additional

$500, there remained a $500 budget gap.

Thanks to part donations by Harbor Steel, Best Metal Products, and Crazy Diamond Performance, the

team was able to complete the project only $177.14 over budget. After conversations with the team’s

faculty advisor midway through the year, it was promised that exceeding the budget by a few hundred

dollars would be covered by emergency funds provided by the college. NaturaFill is very grateful to the

Date Vendor DescriptionBudgeted

Amount

Actual

Cost Difference

12/6/2013 Amazon SainSmart 4-Channel Relay Module 20.00$ 13.50$ 6.50$

12/6/2013 Speedway Gas for 11/2/2013 Ross Pursifull Visit -$ 42.65$ (42.65)$

12/6/2013 Office Depot Paper for Sponsorship Letters 20.00$ 18.54$ 1.46$

12/6/2013 Printing Services Brochures and Envelopes 60.00$ 62.45$ (2.45)$

12/6/2013 Printing Services Postage for Sponsorship Letters 10.00$ 11.50$ (1.50)$

12/9/2013 NovaTech High Pressure Pipe-Plug Thermocouple 40.00$ 37.59$ 2.41$

2/6/2014 McMaster Carr Multipurpase Pressure Gauges (2) 30.00$ 19.68$ 10.32$

2/27/2014 Harbor Steel Supply 5' x 7" x 1" CR Steel Plate 150.00$ -$ 150.00$

3/1/2014 Bond Fluidaire Hydraulic Power Unit 550.00$ -$ 550.00$

3/1/2014 McMaster Carr Hydraulic Solenoid Valve 300.00$ 192.69$ 107.31$

3/1/2014 Best Metal Products Steel pipe for compression cylinders 150.00$ -$ 150.00$

3/1/2014 Bond Fluidaire Hydraulic Fittings and Teflon Tape -$ 10.49$ (10.49)$

3/1/2014 eBay Small Hydaulic Test Cylinder -$ 70.64$ (70.64)$

3/4/2014 Zatkoff Seals Seals 200.00$ 481.32$ (281.32)$

3/12/2014 Bond Fluidaire Hydraulic Fittings and Tubing 50.00$ 44.00$ 6.00$

3/13/2014 Great Lakes Fluid Power Hydraulic Fittings 10.00$ 9.34$ 0.66$

3/15/2014 Speedway Gas for 3/15/2014 Ross Pursifull Visit -$ 38.91$ (38.91)$

3/15/2014 Crazy Diamond Performance 2 CNG Tanks & Pressure Regulator -$ -$ -$

3/19/2014 Bond Fluidaire Hydraulic Cylinder 650.00$ 527.80$ 122.20$

4/6/2014 Northern Tool + Equipment Hydraulic Solenoid Valve 120.00$ 119.99$ 0.01$

4/6/2014 McMaster Carr Hardware and Piston Aluminum Stock 200.00$ 212.40$ (12.40)$

4/6/2014 NovaTech High Pressure Pipe-Plug Thermocouple 40.00$ 37.59$ 2.41$

4/17/2014 McMaster Carr Coupling Nuts, O-Rings -$ 25.11$ (25.11)$

4/22/2014 Omega Presure Transducer -$ 175.00$ (175.00)$

4/28/2014 Swagelok Check valves, Fittings, Tubing 400.00$ 396.00$ 4.00$

5/2/2014 Home Depot / Lowe's Paint & Primer -$ 24.47$ (24.47)$

5/3/2014 McMaster Carr Misc. Bolts -$ 20.00$ (20.00)$

5/5/2014 McMaster Carr Misc. Power Supply Components -$ 63.60$ (63.60)$

5/6/2014 Swagelok Pressure Regulator, Fittings, Adapters -$ 410.11$ (410.11)$

5/7/2014 McMaster Carr Washers, Hexnuts, and Cord Grip -$ 89.86$ (89.86)$

5/8/2014 McMaster Carr Additional Cord Grip -$ 21.91$ (21.91)$

Total 3,000.00$ 3,177.14$ (177.14)$

Page 75: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

60

college for providing these emergency funds, which enabled the completion of the team’s home

refueling unit prototype.

11.2 Cost of Production

Should a revised version of the prototype enter production, a detailed statement of cash flows has been

listed in Table 8: Costs of Production. Using component costs listed in the operational budget (see Table

7: Operational Budget), a preliminary production budget was calculated by assuming industry standards

in economics of scale. Based on these industry standards as well as suggested future changes to the

prototype, the cost to manufacture was estimated at $2,080 per unit. At an initial selling price of $3,500

and moderate annual growth in sales and price, the team believes that NaturaFill would be profitable

in its third year of existence as a Limited Liability Corporation (LLC).

Table 8: Costs of Production

Year 1 Year 2 Year 3

Estimated Sales 50 200 500

Selling Price ($/Unit) 3,500$ 3,750$ 4,000$

Fixed Variable

Employees ($/Unit) -$ 40$

Parts ($/Unit) -$ 2,000$

Distribution ($/Unit) -$ 40$

Building Rent & Utilities 120,000$ -$

Administrative Costs 300,000$ -$

Prototype Materials 3,000$ -$

Marketing 30,000$ -$

Machines & Tooling 100,000$ -$

Total Revenue 175,000$ 750,000$ 2,000,000$

Total Cost (657,000)$ (969,000)$ (1,593,000)$

Net Income (482,000)$ (219,000)$ 407,000$

Gross Profit Margin -275% -29% 20%

Page 76: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

61

12 Conclusion

The goal of the NaturaFill project was to design, build, and test a natural gas home refueling appliance

that is lower cost and more reliable than appliances currently on the market. While the current

prototype would have cost close to $7,000 without donations and educational pricing, the team still

believes that a production model could be sold for as low as $3,500, taking into account the changes

proposed in section 10 Future Improvements.

Lessons learned from doing this project included:

Creating a more accurate plan where tasks are accomplished in an orderly manner, without unnecessary rework.

The difficulty and value in being able to troubleshoot problems and come up with effective solutions.

The benefit for fabricating components with ease-of-disassembly in case of needed repair or cleaning.

The value in budgeting more conservatively, to account for additional shipping costs and requirements for ordering in bulk.

Overall, the team continues to believe that transitioning domestic energy consumption away from

imported oil, in favor of cleaner, American natural gas, is vital for long term economic, environmental,

and political stability. With an estimated market price of $3,500, the team desires that, in some small

way, NaturaFill has helped in carrying out that mission.

Figure 53: Final NaturaFill Prototype

Page 77: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

62

13 Acknowledgements

13.1 Professor Ned Nielsen

Professor Ned Nielsen is the faculty advisor for NaturaFill. The team is grateful to Professor Nielsen for

his insights and constructive criticism throughout the design process.

13.2 Professor Steve VanderLeest

Professor Steve VanderLeest is an adjunct advisor for NaturaFill. The team is grateful to Professor

Nielsen for his presentation feedback and advice on the project’s electronic control systems.

13.3 Professor Matthew Heun

Professor Matthew Heun is a Mechanical Engineering professor with a wide range of knowledge in

thermodynamics. The team is grateful to Professor Heun for providing feedback on the AutoCAD CFD

simulation and supporting the team’s efforts to model heat generation by the compression system.

13.4 Mr. Jimmy Moerdyk

Mr. Jimmy Moerdyk is the VP of Operations of Moerdyk Energy, Inc. The team is grateful to Mr.

Moerdyk for his mentorship and industry insights.

13.5 Mr. Lee Otto

Mr. Lee Otto is the CEO and founder of CNGPump, Inc. The team is grateful to Mr. Lee for his advice to

the team regarding hydraulic cylinder seal technology and safety controls.

13.6 Mr. Ross Pursifull

Mr. Ross Pursifull Otto is a Research Specialist at the Ford Motor Company. The team is grateful to Mr.

Lee for his industry insight on the future of CNG and willingness to demonstrate the use of his CNG

home refueling unit.

13.7 Mr. Phil Jasperse

Mr. Phil Jasperse is the Calvin College metal and wood shop supervisor. The team is grateful to Mr.

Jaspers for his training in metal cutting and fabrication. The team is also grateful to Mr. Jaspers for his

advice on the fabrication of components.

13.8 Mr. Jerry LaBreck

Mr. LaBreck is a sales manager at Zaktkoff Seals and Packing. He provided the team with valuable advice

and discounted or sample sealing products to help ensure that the sealing was done properly and within

Page 78: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

63

budget. He also was instrumental in communicating with Parker Hannifin engineers on behalf of team

to obtain the necessary integration instructions for the seals throughout the system.

13.9 Mr. Kevin Fern

Mr. Fern is the president of Crazy Diamond Performance, a CNG technology company in Shelby

Township, MI. He graciously allowed the team to borrow two small CNG tanks and provided the team

with much helpful advice on safely handling high pressure natural gas.

13.10 Mr. Tim Wolfis

Mr. Wolfis is a sales representative for Grand Rapids Valve and Fitting, a Swaglok distributor. He was

able to provide the team with valuable advice regarding high pressure system plumbing and was able

to arrange an agreement for the team to receive high pressure fittings and tubing at a discounted rate.

Page 79: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

64

14 Appendix

14.1 Appendix A. Work Breakdown Structure

Page 80: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

65

Page 81: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

66

14.2 Appendix B. EES Calculations

14.2.1 Two Stage Compression System Sizing Calculations

"Constants" MM_CH4 = MolarMass(CH4) T_cr = 190.7 [K] P_cr = 4640 [kPa] GGE = 2.567 [kg] P_atm = 100 [kPa] T[1] = 300 [K] "Inputs" P_g_service_psia = 0.5 [psi] "!High Pressure Residential Gas Meter" "Design Variables" CyclePeriod = 4 [s] "!Design Variable" "Capacity" "GGE_dot = 0.5" "!Specified Result" "Compression Ratios" r = 16 "Input Variable" "Hyrdaulic Cylinder" Bore_H = (2.5 [in]) * convert(in,m) "Input Variable" "Isentropic Efficiency"

Page 82: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

67

eta = 0.8 "!Stream 1" m_dot = m_cycle / CyclePeriod GGE_dot = (m_dot / GGE) * convert('hr', 's') P_g_service = P_g_service_psia * convert('psi', 'kPa') P[1] = P_atm + P_g_service s[1] = entropy(CH4, T = T[1], P = P[1]) v[1] = volume(CH4, T = T[1], P = P[1]) m_cycle = Vol[1] / v[1] h[1] = enthalpy(CH4, T=T[1]) Bore_1 = (5 [in]) * convert(in,m) "Input Variable" Bore_1_in = Bore_1*convert(m,in) Stroke_1_2 = (6 [in]) * convert(in,m) Stroke_1_2 = Vol[1] / ((Bore_1^2)*(1/4)*pi) Stroke_1_2_in = Stroke_1_2 * convert(m,in) HydroAdv_1 = (Bore_H^2) / (Bore_1^2) "!Stream 2" v[2] = v[1] / r Vol[2] = v[2] * m_cycle s_s[2] = s[1] h_s[2] = enthalpy(CH4, v = v[2], s = s_s[2]) eta = (h_s[2] - h[1]) / (h[2] - h[1]) T[2] = temperature(CH4, h = h[2]) T_F[2] = ConvertTemp(K,F,T[2]) P[2] = pressure(CH4, v = v[2] , h = h[2]) P_psia[2] = P[2] * convert(kPa, psia) s[2] = entropy(CH4, v = v[2] , h = h[2]) "Stage 1" W_avg_cycle[1] = (h[2] - h[1]) * m_dot "Stream 2 Cooling" T_cool[2] = 300 [K] h_cool[2] = enthalpy(CH4, T = T_cool[2]) s_cool[2] = entropy(CH4, T = T_cool[2], v = v[2]) Q_cool[2] = m_dot*(h[2]-h_cool[2]) P_cool_psia[2] = pressure(CH4, v = v[2] , h = h_cool[2]) * convert(kPa, psia) "!Stream 3"

Page 83: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

68

v[3] = v[2] / r Vol[3] = v[3] * m_cycle s_s[3] = s_cool[2] h_s[3] = enthalpy(CH4, v = v[3], s = s_s[3]) eta = (h_s[3] - h_cool[2]) / (h[3] - h_cool[2]) T[3] = temperature(CH4, h = h[3]) T_F[3] = ConvertTemp(K,F,T[3]) P[3] = pressure(CH4, v = v[3] , h = h[3]) P_psia[3] = P[3] * convert(kPa, psia) s[3] = entropy(CH4, v = v[3] , h = h[3]) ((Bore_2^2)*(1/4)*pi) = Vol[2] / Stroke_1_2 Bore_2_in = Bore_2*convert(m,in) HydroAdv_2 = (Bore_H^2) / (Bore_2^2) "Stage 2" W_avg_cycle[2] = (h[3] - h_cool[2]) * m_dot "Stream 3 Cooling" T_cool[3] = 300 [K] h_cool[3] = enthalpy(CH4, T = T_cool[3]) s_cool[3] = entropy(CH4, T = T_cool[3], v = v[3]) Q_cool[3] = m_dot*(h[3]-h_cool[3]) P_cool_psia[3] = pressure(CH4, v = v[3] , h = h_cool[3]) * convert(kPa, psia)

14.2.2 Heat Transfer Calculations

"Heat Transfer Calculations Senior Design Team 13: Naturafill" "!Givens" GGE = 2.567 [kg]*convert(kg,lbm) Cycle_Period = 6 [sec] GGE_dot = 0.5 [1/hr]"GGE" GGE_dot = m_dot/GGE *convert(1/sec,1/hr) eta =0.80 T_atm = 100[F] d_tube = 0.25[in]*convert(in,ft) h_conv_nat = 20 [W/m^2*K]*convert(W/m^2*K,BTU/hr*ft^2*F)

Page 84: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

69

"!Stage 1: inlet" P[1] = 16[psi] T[1] = 70[F] h[1] = enthalpy(CH4,T=T[1]) s[1] = entropy(CH4,T=T[1],P=P[1]) "!Stage2: First stage Compression" h_s[2] = enthalpy(CH4,s=s[1],v=v[2]) v[1] =volume(CH4,T=T[1],P=P[1]) eta = (h_s[2]-h[1])/(h[2]-h[1]) P[2] =Pressure(CH4,v=v[2],T=T[2]) T[2] = temperature(CH4, h=h[2]) v[2] = v[1]/16 W_first = m_dot*(h[2]-h[1])*convert(1/sec,1/hr) "!Stage3: First Stage Cooling" s[3] = entropy(ch4,T=T[3],P=P[3]) T[3] = 100 [F] "cooling temperature" h[3] = enthalpy(CH4,T=T[3]) P[3] = Pressure(CH4,T=T[3], v=v[2]) Q_conv_23 =m_dot*(h[2]-h[3])*convert(1/sec,1/hr) Q_conv_23 = pi*d_tube*Length_tube_1*h_conv_nat*(T[2]-T_atm) w_second = m_dot*(h[4]-h[3])*convert(1/sec,1/hr) "!Stage4: Second Stage Compression" v[4] = v[2]/14 h_s[4] = enthalpy(ch4,s=s[3], v=v[4]) eta = (h_s[4] - h[3])/(h[4]-h[3]) T[4] = temperature(ch4, h=h[4]) P[4] = Pressure(ch4,T=T[4], v=v[4]) "!Stage5: Second Stage Cooling" T[5] = 100 [F] "cooling final" P[5] = pressure(ch4,T=T[5],v=v[4]) h[5] = enthalpy(ch4,T=T[5]) Q_conv_45 =m_dot*(h[4]-h[5])*convert(1/sec,1/hr) Q_conv_45 = pi*d_tube*Length_tube_2*h_conv_nat*(T[4]-T_atm)

Page 85: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

70

Page 86: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

71

14.3 Appendix C. MathCAD Calculations

14.3.1 Pump/Reservoir Horsepower Requirement

14.3.2 Stress in Spacer Plate Bolts (First Stage)

Page 87: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

72

Page 88: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

73

Page 89: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

74

14.3.3 Stress in Threaded Rod (First Stage)

Page 90: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

75

Page 91: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

76

14.3.4 Friction Calculations

Page 92: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

77

14.4 Appendix D. As-Built Part Drawings

Page 93: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

78

Page 94: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

79

Page 95: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

80

Page 96: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

81

Page 97: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

82

Page 98: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

83

Page 99: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

84

Page 100: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

85

Page 101: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

86

Page 102: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

87

Page 103: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

88

Page 104: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

89

Page 105: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

90

Page 106: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

91

Page 107: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

92

14.5 Appendix E. Raw Testing Data

Testing w/ Air Compression - 5/14/14 Thermocouples (deg F)

Time (s)

*Time (min)

First Stage

Second Stage

**Pressure Approx. (psi)

0.00 0.0000 67.8739 67.8739 260.000

0.10 0.0017 67.8739 67.8179 260.003

0.20 0.0033 67.8739 67.8179 260.006

0.30 0.0050 67.8739 67.8179 260.009

0.40 0.0067 67.8739 67.8179 260.012

0.50 0.0083 67.8739 67.8179 260.015

0.60 0.0100 67.8739 67.8179 260.018

0.70 0.0117 67.8739 67.8179 260.021

0.80 0.0133 67.8739 67.8179 260.024

0.90 0.0150 67.8739 67.8179 260.027

1.00 0.0167 67.8739 67.8179 260.030

1.10 0.0183 67.8739 67.8179 260.033

1.20 0.0200 67.8739 67.8179 260.036

1.30 0.0217 67.8739 67.8179 260.039

1.40 0.0233 67.8739 67.8179 260.042

1.50 0.0250 67.8739 67.8179 260.045

1.60 0.0267 67.8739 67.8179 260.048

1.70 0.0283 67.8739 67.8179 260.051

1.80 0.0300 67.8739 67.8179 260.054

1.90 0.0317 67.8739 67.8179 260.057

2.00 0.0333 67.8739 67.8179 260.060

2.10 0.0350 67.8739 67.8179 260.063

2.20 0.0367 67.8739 67.8179 260.066

2.30 0.0383 67.8739 67.8179 260.069

2.40 0.0400 67.8739 67.8179 260.072

2.50 0.0417 67.8739 67.8179 260.075

2.60 0.0433 67.8739 67.8179 260.078

2.70 0.0450 67.8739 67.8179 260.081

2.80 0.0467 67.8739 67.8179 260.084

2.90 0.0483 67.8739 67.8179 260.087

3.00 0.0500 67.8739 67.8179 260.090

3.10 0.0517 67.8739 67.8179 260.093

3.20 0.0533 67.8739 67.8179 260.096

3.30 0.0550 67.8739 67.8179 260.099

3.40 0.0567 67.8739 67.8179 260.102

Page 108: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

93

3.50 0.0583 67.8739 67.8179 260.105

3.60 0.0600 67.8739 67.8179 260.108

3.70 0.0617 67.8739 67.8179 260.111

3.80 0.0633 67.8739 67.8179 260.114

3.90 0.0650 67.8739 67.8179 260.117

4.00 0.0667 67.8739 67.8179 260.120

4.10 0.0683 67.8739 67.8179 260.123

4.20 0.0700 67.8739 67.8179 260.126

4.30 0.0717 67.8739 67.8179 260.129

4.40 0.0733 67.8739 67.8179 260.132

4.50 0.0750 67.8739 67.8179 260.135

4.60 0.0767 67.8739 67.8179 260.138

4.70 0.0783 67.8739 67.8179 260.141

4.80 0.0800 67.8739 67.8179 260.144

4.90 0.0817 67.8739 67.8179 260.147

5.00 0.0833 67.8739 67.8179 260.150

5.10 0.0850 67.8739 67.8179 260.153

5.20 0.0867 67.8739 67.8179 260.156

5.30 0.0883 67.8739 67.8179 260.159

5.40 0.0900 67.8739 67.8179 260.162

5.50 0.0917 67.8739 67.8179 260.165

5.60 0.0933 67.8739 67.8179 260.168

5.70 0.0950 67.8739 67.8179 260.171

5.80 0.0967 67.8739 67.8179 260.174

5.90 0.0983 67.8739 67.8179 260.177

6.00 0.1000 67.8739 67.8179 260.180

6.10 0.1017 67.8739 67.8179 260.183

6.20 0.1033 67.8739 67.8179 260.186

6.30 0.1050 67.8739 67.8179 260.189

6.40 0.1067 67.8739 67.8179 260.192

6.50 0.1083 67.8739 67.8179 260.195

6.60 0.1100 67.8739 67.8179 260.198

6.70 0.1117 67.8739 67.8179 260.201

6.80 0.1133 67.8739 67.8179 260.204

6.90 0.1150 67.8739 67.8179 260.207

7.00 0.1167 67.8739 67.8179 260.210

7.10 0.1183 67.8739 67.8179 260.213

7.20 0.1200 67.8739 67.8179 260.216

7.30 0.1217 67.8739 67.8179 260.219

7.40 0.1233 67.8739 67.8179 260.222

7.50 0.1250 67.8739 67.8179 260.225

7.60 0.1267 67.8739 67.8179 260.228

7.70 0.1283 67.8739 67.8179 260.231

Page 109: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

94

7.80 0.1300 67.8739 67.8179 260.234

7.90 0.1317 67.8739 67.8179 260.237

8.00 0.1333 67.8739 67.8179 260.240

8.10 0.1350 67.8739 67.8179 260.243

8.20 0.1367 67.8179 67.8179 260.246

8.30 0.1383 67.8179 67.8179 260.249

8.40 0.1400 67.8179 67.8179 260.252

8.50 0.1417 67.8179 67.8179 260.255

8.60 0.1433 67.8179 67.8179 260.258

8.70 0.1450 67.8179 67.8179 260.261

8.80 0.1467 67.8179 67.8179 260.264

8.90 0.1483 67.8179 67.8179 260.267

9.00 0.1500 67.8179 67.8179 260.270

9.10 0.1517 67.8179 67.8179 260.273

9.20 0.1533 67.8179 67.8179 260.276

9.30 0.1550 67.8739 67.8179 260.279

9.40 0.1567 67.8739 67.8179 260.282

9.50 0.1583 67.8739 67.8179 260.285

9.60 0.1600 67.8739 67.8179 260.288

9.70 0.1617 67.8739 67.8179 260.291

9.80 0.1633 67.8739 67.8179 260.294

9.90 0.1650 67.8739 67.8179 260.297

10.00 0.1667 67.8739 67.8179 260.300

10.10 0.1683 67.8739 67.8179 260.303

10.20 0.1700 67.8739 67.8179 260.306

10.30 0.1717 67.8739 67.8179 260.309

10.40 0.1733 67.8739 67.8179 260.312

10.50 0.1750 67.8739 67.8179 260.315

10.60 0.1767 67.8739 67.8179 260.318

10.70 0.1783 67.8739 67.8179 260.321

10.80 0.1800 67.8739 67.8179 260.324

10.90 0.1817 67.8739 67.8179 260.327

11.00 0.1833 67.8739 67.8179 260.330

11.10 0.1850 67.8739 67.8179 260.333

11.20 0.1867 67.8739 67.8179 260.336

11.30 0.1883 67.8739 67.8179 260.339

11.40 0.1900 67.8739 67.8179 260.342

11.50 0.1917 67.8739 67.8179 260.345

11.60 0.1933 67.8739 67.8179 260.348

11.70 0.1950 67.8739 67.8739 260.351

11.80 0.1967 67.8739 67.8739 260.354

11.90 0.1983 67.8739 67.8739 260.357

12.00 0.2000 67.8739 67.8739 260.360

Page 110: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

95

12.10 0.2017 67.8739 67.8739 260.363

12.20 0.2033 67.8739 67.8739 260.366

12.30 0.2050 67.8739 67.8739 260.369

12.40 0.2067 67.8739 67.8739 260.372

12.50 0.2083 67.8739 67.8739 260.375

12.60 0.2100 67.8739 67.8739 260.378

12.70 0.2117 67.8739 67.8739 260.381

12.80 0.2133 67.8739 67.8179 260.384

12.90 0.2150 67.8739 67.8179 260.387

13.00 0.2167 67.8739 67.8179 260.390

13.10 0.2183 67.8739 67.8179 260.393

13.20 0.2200 67.8739 67.8179 260.396

13.30 0.2217 67.8739 67.8179 260.399

13.40 0.2233 67.8739 67.8179 260.402

13.50 0.2250 67.8739 67.8179 260.405

13.60 0.2267 67.8739 67.8179 260.408

13.70 0.2283 67.8739 67.8179 260.411

13.80 0.2300 67.8739 67.8179 260.414

13.90 0.2317 67.8739 67.8739 260.417

14.00 0.2333 67.8739 67.8739 260.420

14.10 0.2350 67.8739 67.8739 260.423

14.20 0.2367 67.8739 67.8739 260.426

14.30 0.2383 67.8739 67.8739 260.429

14.40 0.2400 67.8739 67.8739 260.432

14.50 0.2417 67.8739 67.8739 260.435

14.60 0.2433 67.8739 67.8739 260.438

14.70 0.2450 67.8739 67.8739 260.441

14.80 0.2467 67.8739 67.8739 260.444

14.90 0.2483 67.8739 67.8739 260.447

15.00 0.2500 67.8739 67.8739 260.450

15.10 0.2517 67.8739 67.8739 260.453

15.20 0.2533 67.8739 67.8739 260.456

15.30 0.2550 67.8739 67.8739 260.459

15.40 0.2567 67.8739 67.8739 260.462

15.50 0.2583 67.8739 67.8739 260.465

15.60 0.2600 67.8739 67.8739 260.468

15.70 0.2617 67.8739 67.8739 260.471

15.80 0.2633 67.8739 67.8739 260.474

15.90 0.2650 67.8739 67.8739 260.477

16.00 0.2667 67.8739 67.8739 260.480

16.10 0.2683 67.8739 67.8739 260.483

16.20 0.2700 67.8739 67.8739 260.486

16.30 0.2717 67.8739 67.8739 260.489

Page 111: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

96

16.40 0.2733 67.8739 67.8739 260.492

16.50 0.2750 67.8739 67.8739 260.495

16.60 0.2767 67.8739 67.8739 260.498

16.70 0.2783 67.8739 67.8739 260.501

16.80 0.2800 67.8739 67.8739 260.504

16.90 0.2817 67.8739 67.8739 260.507

17.00 0.2833 67.8739 67.8739 260.510

17.10 0.2850 67.8739 67.8739 260.513

17.20 0.2867 67.8739 67.8739 260.516

17.30 0.2883 67.8739 67.8739 260.519

17.40 0.2900 67.8739 67.8739 260.522

17.50 0.2917 67.8739 67.8739 260.525

17.60 0.2933 67.8739 67.8739 260.528

17.70 0.2950 67.8739 68.0981 260.531

17.80 0.2967 67.8739 68.0981 260.534

17.90 0.2983 67.8739 68.0981 260.537

18.00 0.3000 67.8739 68.0981 260.540

18.10 0.3017 67.8739 68.0981 260.543

18.20 0.3033 67.8739 68.0981 260.546

18.30 0.3050 67.8739 68.0981 260.549

18.40 0.3067 67.8739 68.0981 260.552

18.50 0.3083 67.8739 68.0981 260.555

18.60 0.3100 67.8739 68.2101 260.558

18.70 0.3117 67.8739 68.2101 260.561

18.80 0.3133 67.8739 68.2101 260.564

18.90 0.3150 67.8739 68.2101 260.567

19.00 0.3167 67.8739 68.2101 260.570

19.10 0.3183 67.8739 68.2101 260.573

19.20 0.3200 67.8739 68.2101 260.576

19.30 0.3217 67.8739 68.2101 260.579

19.40 0.3233 67.8739 68.2101 260.582

19.50 0.3250 67.8739 68.2101 260.585

19.60 0.3267 67.8739 68.2101 260.588

19.70 0.3283 67.8739 68.1541 260.591

19.80 0.3300 67.8739 68.1541 260.594

19.90 0.3317 67.8739 68.1541 260.597

20.00 0.3333 67.8739 68.1541 260.600

20.10 0.3350 67.8739 68.1541 260.603

20.20 0.3367 67.8739 68.1541 260.606

20.30 0.3383 67.8739 68.1541 260.609

*Data continues to Time = 22.8 minutes

**Pressure approximated due to malfunctioning pressure transducer.

Page 112: Final Design Report - Calvin College | Grand Rapids, Michigan€¦ ·  · 2014-05-15FINAL DESIGN REPORT LAST UPDATED: 5/15/2014 ii DEDICATION For Our Friend and Former Teammate Eric

FINAL DESIGN REPORT LAST UPDATED: 5/15/2014

97

14.6 Appendix F. Manufacturer Component Specifications

14.6.1 O-ring Groove Dimension Instructions