final geotechnical investigation report frt-18.5-k.99 ... · 1 day ago · final geotechnical...
TRANSCRIPT
FINAL
Geotechnical Investigation Report
FRT-18.5-K.99 Culvert Replacement Project
Mesa County, Colorado
Yeh Project No.: 219-061
July 19, 2019
Prepared for:
Collins Engineers, Inc.
Attn: Bryant E. Walters, P.E. 455 Sherman Street, Suite 160
Denver, CO 80203
Prepared by:
Yeh and Associates, Inc. 588 North Commercial Drive
Grand Junction, Colorado 81505 Phone: 970-242-5125 Fax: 970-255-8512
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
i
Table of Contents
1. PURPOSE AND SCOPE OF STUDY ........................................................................................ 1
2. PROPOSED CONSTRUCTION ............................................................................................... 1
3. SITE CONDITIONS AND GEOLOGICAL SETTING .................................................................... 1
3.1 SITE CONDITIONS .................................................................................................................................... 1
3.2 GEOLOGICAL SETTING .............................................................................................................................. 4
4. SUBSURFACE INVESTIGATION ............................................................................................ 4
4.1 SUBSURFACE CONDITIONS ........................................................................................................................ 5
4.1.1 FILL CLAY ........................................................................................................................................ 6
4.1.2 FILL SAND ....................................................................................................................................... 6
4.1.3 NATIVE CLAY ................................................................................................................................... 7
4.1.4 WEATHERED SHALE BEDROCK ............................................................................................................ 7
4.1.5 COMPETENT SHALE BEDROCK ............................................................................................................. 7
5. GROUNDWATER ................................................................................................................ 8
6. SEISMIC CONSIDERATIONS ................................................................................................. 8
7. SITE GRADING .................................................................................................................... 8
8. FOUNDATION RECOMMENDATIONS ................................................................................ 10
8.1 CONCRETE BOX CULVERT OPTION ............................................................................................................ 10
8.1.1 SHALLOW FOUNDATIONS................................................................................................................. 10
8.2 BRIDGE FOUNDATIONS ........................................................................................................................... 11
8.2.1 DRILLED SHAFT NOMINAL AXIAL RESISTANCE ...................................................................................... 12
8.2.2 DRILLED SHAFT AXIAL RESISTANCE FACTORS ....................................................................................... 13
8.2.3 DRILLED SHAFT LATERAL RESISTANCE ................................................................................................ 13
8.2.4 GENERAL DRILLED SHAFT RECOMMENDATIONS ................................................................................... 14
8.3 LATERAL EARTH PRESSURE ...................................................................................................................... 15
8.4 BRIDGE APPROACH EMBANKMENT ........................................................................................................... 15
9. PAVEMENT RECOMMENDATIONS .................................................................................... 16
9.1 SUBGRADE STRENGTH ............................................................................................................................ 16
9.2 TRAFFIC LOADING .................................................................................................................................. 16
9.3 DESIGN ASSUMPTIONS AND INPUTS ......................................................................................................... 16
9.4 PAVEMENT ........................................................................................................................................... 17
9.5 HOT MIX ASPHALT TYPE ......................................................................................................................... 17
9.6 PAVEMENT PREPARATION ....................................................................................................................... 18
10. WATER-SOLUBLE SULFATE AND CORROSION TESTING .................................................... 18
11. LIMITATIONS ................................................................................................................. 19
12. REFERENCES .................................................................................................................. 20
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
ii
List of Tables
TABLE 1 – BORING SUMMARY ............................................................................................................................. 6
TABLE 2 – SEISMIC DESIGN PARAMETERS FOR SITE CLASS B REFERENCE SITE .............................................................. 8
TABLE 3 – SEISMIC DESIGN PARAMETERS FOR SITE CLASS C ..................................................................................... 8
TABLE 4 – BRIDGE ABUTMENT BORING BEDROCK SUMMARY ................................................................................. 12
TABLE 5 – RECOMMENDED NOMINAL UNIT DRILLED SHAFT AXIAL RESISTANCE ......................................................... 13
TABLE 6 – LPILE PARAMETERS .......................................................................................................................... 14
TABLE 7 - FLEXIBLE PAVEMENT DESIGN PARAMETERS ............................................................................................ 16
TABLE 8 - RECOMMENDED HMA AND BASE THICKNESSES ...................................................................................... 17
List of Photos
PHOTO 1: TRANSVERSE AND ALLIGATOR CRACKING NEAR BORING P-1 ........................................................................ 2
PHOTO 2: PAVEMENT CRACKING AND POTHOLING IN 18.5 ROAD .............................................................................. 3
PHOTO 3: EAST INVERT OF THE EXISTING LITTLE SALT WASH PIPE CULVERT ................................................................. 3
List of Figures FIGURE 1 – SITE LOCATION MAP
FIGURE 2 – APPROXIMATE BORING LOCATION MAP
List of Appendices
APPENDIX A - BORING LOGS AND LEGEND
APPENDIX B - ENGINEERING GEOLOGY SHEET
APPENDIX C - LABORATORY TEST RESULTS AND CORE PHOTOGRAPHS
APPENDIX D - ESALS AND TRAFFIC LOADING CALCULATIONS
APPENDIX E - PAVEMENT DESIGN
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
1
1. PURPOSE AND SCOPE OF STUDY
This report presents the results of our geotechnical engineering investigation for construction of
either a box culvert or bridge to replace an existing culvert for the “Little Salt Wash” located at
approximately 18.5 and K.99 Roads at the northeastern edge of the City of Fruita in
unincorporated Mesa County, Colorado. The project site is located along 18.5 Road,
approximately 300 feet south of L Road, as shown in Figure 1 at the end of this report. The
purpose of this study was to evaluate geotechnical characteristics of the on-site soils and
provide geotechnical recommendations for the proposed bridge or box culvert that will replace
the existing culvert and pavement design recommendations for new roadway alignments at the
approaches.
The geotechnical investigation consisted of field reconnaissance and exploratory drilling to
investigate subsurface conditions. Drilling was observed by a representative of Yeh and
Associates (Yeh). Samples obtained during the field exploration were examined by the project
personnel and representative samples were selected for laboratory testing to evaluate the
engineering characteristics of materials encountered. This report summarizes our field
investigation, the results of our analyses, and our conclusions and recommendations for
foundations and pavement based on the proposed construction, site reconnaissance,
subsurface investigation, and results of the laboratory testing.
2. PROPOSED CONSTRUCTION
It is our understanding that either a concrete box culvert or a bridge with associated structures
along 18.5 Road has been proposed to replace the pipe culvert at Little Salt Wash. Plans for a
proposed box culvert or bridge structure and proposed road alignment were not made available
to Yeh at the time of this report. Based on the existing conditions at the site, a new bridge
structure would likely be single span with abutments founded on drilled shafts. A new road
alignment is also planned for the approaches along 18.5 Road.
3. SITE CONDITIONS AND GEOLOGICAL SETTING
3.1 Site Conditions
The project site extends from the L Road intersection south approximately 550 feet, and
includes the right-of-way of 18.5 Road and an existing culvert that conveys water from the Little
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
2
Salt Wash drainage under 18.5 Road. At the time of this investigation, the 18.5 Road surface
was asphalt pavement that appeared to be in poor to fair condition with transverse and alligator
cracking, and potholing, as shown in Photos 1 and 2. Based on a Colorado Department of
Transportation (CDOT) Structure Inspection Report done in February 2018, the existing culvert
is listed as an 18-foot diameter, 104-foot long aluminum corrugated plate pipe with corrosion
holes throughout the pipe and damage to the culvert apron, as shown in Photo 3. Water was
flowing through the culvert at the time of the investigation. The culvert headwalls are described
in the report as stacked concrete rubble, and/or boulders that are beginning to collapse. The
width of 18.5 Road in the area of the culvert is approximately 22 feet. The site is bordered by
residential properties to the northwest and southeast, and vacant lands to the northeast and
southwest. The Little Salt Wash is located through the middle of the project site, flowing
northeast to southwest. The ground surface of the roadway is nearly flat to gently sloping at a
grade of approximately two percent from north to south and at an approximate elevation of 4573
feet, based on City of Fruita GIS topography maps. No survey data was made available to Yeh
at the time of this report. Site drainage is from the northeast down to the southwest. The Main
Line Grand Valley Canal is located approximately 100 feet west of the project site, and the
Colorado River is approximately 2.5 miles to the southwest. Vegetation consisted of trees,
native grasses and shrubs.
Photo 1: Transverse and alligator cracking near boring P-1
18.5 Road looking east
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
3
Photo 2: Pavement cracking and potholing in 18.5 Road
looking south.
Photo 3: East invert of the existing Little Salt Wash pipe culvert
looking southwest.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
4
3.2 Geological Setting
The project site is located in the Grand Valley of the Colorado River, northeast of the
Uncompahgre Plateau and southwest of the Book Cliffs. The Quaternary age Redlands Fault
Complex is approximately four miles southwest of the project area at the northeast edge of the
Uncompahgre Plateau. Based on the 2009 geologic map of the Fruita quadrangle by Livaccari
and Hodge, the site is located on the Cretaceous age Smoky Hill Member of the Mancos Shale
bedrock that is dipping, or tilted, gently to the north-northeast. The shale bedrock, and soils
derived from the shale bedrock, may contain expansive clays, which can cause stability
problems for roads and buildings. Additionally, there is a possibility that evaporite mineral and
salt deposits, including sulfates such as gypsum, associated with the Mancos Shale may be
present in the soils that underlie the project site. As per the Colorado Geological Survey (CGS)
website for corrosive soils, these minerals may be corrosive to buried metal and concrete. Soil
corrosivity test results for soils sampled at the project site can be found in Section 9 of this
report. Additional surficial deposits include Quaternary age alluvium and artificial, or manmade,
fill and disturbed land.
Geologic hazards at the site include seasonal and flash flooding, and mud flows from Little Salt
Wash and from local washes and canals including Main Line Canal. Additional soil hazards
include swelling soils, collapsible and compressible soils in flooding areas, and corrosive soils
and swelling soils derived from the Mancos Shale. The potential for flooding and the resulting
scour should be anticipated within the project site and considered in the design of the culvert
replacement.
4. SUBSURFACE INVESTIGATION
Four borings were drilled March 25 and 27, 2019, by HRL Compliance Solutions, Grand
Junction, Colorado with a CME 55 rubber track rig. Drilling systems used were 6-inch solid-stem
auger, 10-inch hollow-stem auger, and HQ3 wire-line coring. Boring locations were identified in
the field by Yeh based on discussions with the client. Borings were auger drilled or cored to
depths ranging from 6 to 51.5 feet below the pavement surface on 18.5 Road.
Two borings were drilled to investigate foundation conditions for the culvert replacement and
two borings were drilled to evaluate subgrade conditions for pavement design. Boring A-1 was
located in the vicinity of a north abutment for a proposed bridge, approximately 40 feet north of
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
5
the culvert centerline in the center of the northbound lane of 18.5 Road. Boring A-2 was located
in the vicinity of a south abutment for a proposed bridge, approximately 40 feet south of the
culvert centerline in the center of the southbound lane of 18.5 Road. The two bridge abutment
borings were advanced using 10-inch hollow-stem auger to depths ranging from 15.8 to 20.0
feet, where HQ3 wire-line coring was performed through the hollow-stem auger. A minimum of
20 feet of penetration into competent bedrock was achieved at both bridge structure boring
locations, to total drilling depths of 50.3 feet and 51.5 feet below ground surface.
Two borings were drilled through the existing pavement of the southbound lane of 18.5 Road
approximately 190 feet south and 160 feet north of the center line of the culvert. The borings
drilled for pavement design were advanced to a depth of 6 feet using a 6-inch solid stem auger.
The approximate locations of the borings are presented on Figure 2 at the end of this report.
At selected intervals, a modified California sampler with a 2-inch interior diameter (ID) and 2.5-
inch outside diameter (OD), or a standard split spoon sampler with a 1⅜-inch ID and 2-inch OD
were driven into the subsurface to record blow counts and obtain samples. The sampler was
seated at the bottom of the boring, then advanced by a 140-pound hydraulic automatic, or
“auto,” hammer falling a distance of 30 inches. The number of blows required to drive the
sampler two 6-inch intervals or a fraction thereof, constitutes the N-value. The N-value, when
properly evaluated, is an index of the consistency or relative density of the material tested.
Samples obtained during the field explorations were examined by the project engineer and
representative samples were submitted for laboratory testing to evaluate the engineering
characteristics of materials encountered. Representative HQ3 size, 2-3/8-inch diameter core
samples from Borings A-1 and A-2 were retrieved for testing. In addition, bulk samples of auger
cuttings were obtained at appropriate depths from all borings. The boring logs and legend are
presented in Appendix A, and laboratory test results and core photographs can be found in
Appendix C. An engineering geology sheet is presented in Appendix B.
4.1 Subsurface Conditions
Subsurface conditions encountered above bedrock in the proposed abutment area borings
consisted of 5 inches of hot mix asphalt (HMA) over 1.1 to 1.6 feet of road base, over 8.0 feet of
sandy clay fill, over 3.0 to 6.3 feet of clay. The bedrock consisted of 14.0 to 14.5 feet of
weathered shale over more competent shale encountered to the maximum depths drilled.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
6
The pavement thickness encountered in the pavement borings consisted of 5 inches of asphalt
over 1.6 feet of road base. Boring P-1 had 3.5 feet of sand fill under the base course, over
native clay to the depth explored. Boring P-2 had 3.5 feet of native clay below the base course,
over weathered shale to depth explored. Table 1 summarizes boring depths, location, and
pavement and road base thicknesses.
Table 1 – Boring Summary
Boring Number
Boring Depth (feet)
Pavement Thickness (inches)
Road Base Thickness (inches)
Boring Location on 18.5 Road
A-1 51.5 5 13 40 feet north of culvert centerline, NB lane
A-2 50.3 5 19 40 feet south of culvert centerline, SB lane
P-1 6.0 5 19 160 feet north of culvert centerline, SB lane
P-2 6.0 5 19 190 feet south of culvert centerline, SB lane
4.1.1 Fill Clay
Four samples of the clay fill were tested in the laboratory. Two of the fill clay samples tested had
53 and 56 percent fines (material passing the No. 200 Sieve). Atterberg limits testing on these
samples indicated liquid limits of 24 and 25 percent and plasticity indices of 9 and 10 percent.
Swell/consolidation testing (ASTM D4546) was performed on three of the fill clay samples. One
sample from a depth of 2.0 feet exhibited no movement when wetted under an applied pressure
of 250 psf (pounds per square foot). A second fill clay sample from a depth of 6.5 feet exhibited
collapse of 0.1 percent when wetted under an applied pressure of 500 psf. A third fill clay
sample from a depth of 7.0 feet exhibited collapse of 0.4 percent when wetted under an applied
pressure of 1,000 psf. Proctor test results indicate the fill clay has a maximum dry density of 119
pounds per cubic foot (pcf) at an optimum moisture content of 12.5 percent when tested in
accordance with AASHTO T-99.
The fill clay samples classified as CL based on the Unified Soil Classification System (USCS)
and as A-4 (2) based on the American Association of State Highway and Transportation
Officials (AASHTO).
4.1.2 Fill Sand
Two samples of the sand fill (aggregate base course) tested had 20 and 44 percent fines, liquid
limits of no value and plasticity indices of non-plastic. The aggregate base course samples
classified as silty sand, SM (USCS), and as A-2-4 (0) and A-4 (0) (AASHTO).
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
7
4.1.3 Native Clay
Four native clay samples were tested in the laboratory. Three of the clay samples tested had 56
to 58 percent fines, liquid limits of 23 to 26 percent and plasticity indices of 6 to 9 percent.
Swell/consolidation testing (ASTM D4546) was performed on three of the clay samples. One
sample from a depth of 2.0 feet exhibited collapse of 0.1 percent when wetted under an applied
pressure of 250 psf. A second clay sample from a depth of 5.5 feet exhibited collapse of 0.1
percent when wetted under an applied pressure of 500 psf. The third clay sample from a depth
of 9.5 feet exhibited collapse of 0.1 percent when wetted under an applied pressure of 1,000
psf.
A bulk clay sample from boring P-2 taken at depths of 2 to 5 feet was subjected to Hveem R-
value testing (ASTM 2844) and had an R-value of 18 at an exudation pressure of 300 psi
(pounds per square inch). Proctor test results indicate the native clay has a maximum dry
density of 116 pounds per cubic foot (pcf) at an optimum moisture content of 14.3 percent when
tested in accordance with AASHTO T-99. The native clay samples classified as CL and CL-ML
(USCS), and as A-4 (1) and A-4 (2) (AASHTO).
4.1.4 Weathered Shale Bedrock
Five weathered shale samples were subjected to laboratory testing. Atterberg limits testing on
two weathered shale samples showed liquid limits of 26 and 27 percent and plasticity indices of
11 and 13 percent. Swell/consolidation testing (ASTM D4546) performed on one weathered
shale bedrock sample from a depth of 15.0 feet exhibited swell of 0.1 percent, when wetted
under an applied pressure of 1,000 psf.
Two core samples of weathered shale from borings A-1 and A-2 at depths of 20 feet and 24 feet
showed unconfined compressive strengths of 13,794 psf and 17,585 psf, respectively. Rock
Quality Designation (RQD) values in cored, weathered shale in borings A-1 and A-2 was zero
(0) percent.
4.1.5 Competent Shale Bedrock
Four core samples of apparently competent shale bedrock from borings A-1 and A-2 at depths
of 28.5 to 47.0 feet were tested and had unconfined compressive strengths of 552,453 psf to
751,248 psf. RQD values in cored, competent shale in borings A-1 and A-2 ranged from 47 to
100 percent.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
8
5. GROUNDWATER
Groundwater was not encountered in any of the borings during drilling. Water was flowing
through the culvert at the time of this investigation. Variations in groundwater conditions may
occur seasonally. The magnitude of the variation will be largely dependent upon the water
fluctuations in the Little Salt Wash, the Main Line Grand Valley Canal and other canals, and
nearby streams and washes, the amount of spring snowmelt, duration and intensity of
precipitation, flood irrigation, and the surface and subsurface drainage characteristics of the
surrounding area. Water flow in Little Salt Wash should be anticipated during construction.
6. SEISMIC CONSIDERATIONS
The proposed bridge or box culvert at FRT-18.5-K.99 is located at approximately latitude 39.178
degrees north and longitude -108.711 degrees west. The area of the proposed structure can be
classified as Site Class C, based on the recommendations in Table 3.10.3.1-1 of AASHTO
(2017). Based on the recommendations in Table 3.10.6-1 of AASHTO (2017), the area of the
proposed structure can be classified as a Seismic Zone 1.
The peak ground acceleration (PGA) and the short- and long-period spectral acceleration
coefficients (Ss and S1, respectively) for a reference Site Class B were determined using the
seismic design maps from the USGS website under the reference document AASHTO 2009.
The seismic design parameters for reference Site Class B and for Site Class C are shown in
Table 2 and Table 3 below.
Table 2 – Seismic Design Parameters for Site Class B Reference Site
PGA (0.0 sec) Ss (0.2 sec) S1 (1.0 sec)
0.077 g 0.160 g 0.039 g
Table 3 – Seismic Design Parameters for Site Class C
As (0.0 sec) SDS (0.2 sec) SD1 (1.0 sec)
0.092 g 0.192 g 0.067 g
7. SITE GRADING
All excavations and embankment grading should be performed in accordance with the Section
203 of the CDOT Standard Specifications for Road and Bridge Construction, 2017 (CDOT,
2017).
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
9
We recommend that all permanent un-retained cut and fill slopes be constructed no steeper
than 2 H: 1 V. Cut slopes should be protected from surface water runoff to prevent erosion and
slope failure. Surface drainage should be provided around all permanent cuts and fills to direct
surface runoff away from the slope faces. Fill slopes, cut slopes, and other stripped areas
should be protected against erosion by re-vegetation or other methods. Concentrated runoff
should be prevented in areas susceptible to erosion or slope instability.
Positive drainage should be provided during construction and maintained throughout the life of
the proposed structures. Surface features that could retain water in areas adjacent to the
structures should be sealed or eliminated.
Backfill against any structures and in utility trenches should be well compacted and free of all
construction debris, in order to reduce the possibility of moisture infiltration and migration. Flow
fill can be used to backfill confined areas and utility trenches.
Backfill placed on existing slopes that are steeper than 4H: 1V should be properly benched in
accordance with section 203.06 of the CDOT (2017). All compaction should be performed in
horizontal lifts that are 8-inches or less in loose thickness, using equipment and procedures that
will produce a uniform fill with the required moisture contents and densities throughout the lift.
The required percent of relative compaction and moisture content for the backfill materials are
presented in Section 203.07 of the CDOT (2017).
Imported backfill materials should have a Class 0 severity of sulfate exposure based on Table
601-2 of CDOT (2017). Backfill materials should be tested for severity of sulfate exposure prior
to placement. We recommend that the subgrade preparation process including soil excavation,
the placement and compaction of materials be observed and evaluated by the geotechnical
engineer of record or the engineer’s representative.
We anticipate that unshored, temporary excavation slopes may be used when the excavation
does not undermine existing structures, interfere with other construction, or extend beyond
construction limits. The Contractor is responsible for stability of temporary excavation slopes
and should observe the nature and conditions of the materials encountered during excavation,
including groundwater. If temporary excavations are made, they should be protected from
surface water runoff to prevent erosion and slope failure. All construction traffic should be set
back from the edge of temporary slopes a minimum of 5 feet, and excavated material, stockpiles
of construction materials, and construction equipment should not be placed closer to the edge of
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
10
any excavation than the depth of the excavation. We recommend that the contractor perform
periodic, daily monitoring of excavations and cut slopes to check for developing displacement,
deformations, bulges, and/or cracks in the soil.
8. FOUNDATION RECOMMENDATIONS
8.1 Concrete Box Culvert Option
Based on communications with the client, a concrete box culvert (CBC) with associated
retaining walls may be the selected alternative to replace the existing culvert. We recommend
the box culvert be designed in accordance with the CDOT M Standard Plans with the following
design and construction details.
8.1.1 Shallow Foundations
Shallow foundations should be constructed on properly placed structure backfill or native
weathered shale. Loose, disturbed soils encountered at foundation level should be removed and
replaced with Structure Backfill Class 1 per Section 206 of Colorado Department of
Transportation Standard Specifications for Road and Bridge Construction.
1. Using Load Resistance Factor Design criteria, from the AASHTO LRFD Bridge Design
Specifications, 8th Edition, (2017) (AASHTO LRFD); a nominal bearing resistance of qn =
34 ksf can be used for the shallow spread footing foundation below the CBC placed on
existing weathered shale or properly placed and compacted Structure Backfill Class 1.
This assumes a minimum effective width of 16 feet. A resistance factor of 0.45, per
Table 10.5.5.2.2-1 in AASHTO (2017) should be applied to the nominal bearing
resistance.
2. A minimum thickness of 6 inches of granular material should be placed below the bottom
of box culvert to increase resistance to sliding. An angle of internal friction of 34 degrees
should be used to calculate sliding resistance per AASHTO Section 10.6.3.4. Use a
resistance factor of 0.85 for friction to resist sliding.
3. Passive pressure to resist sliding can be estimated based on equivalent fluid densities
presented in Section 8.3. A resistance factor of 0.50 should be used for passive
resistance (per AASHTO 10.5.5.2.2-1).
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
11
4. Shallow spread footing foundations for the CBC wing walls should be protected from
frost action. Footings should be placed a minimum of 2.0 feet below final grade to
provide adequate frost protection.
5. All foundation and retaining structures should be designed for appropriate hydrostatic
and surcharge pressures resulting from flow in the Little Salt Wash, adjacent roadways,
construction materials, and equipment.
6. We anticipate that the CBC will be underlain by weathered shale bedrock. Foundation
movements could occur if water from any source infiltrates the foundation soils,
particularly if swelling soils are involved. Our laboratory test results indicate the soils and
weathered bedrock have low swell potential in accordance with AASHTO LRFD Section
10.4.6.3. However, proper drainage will further reduce the potential for movement due to
swelling soils and should be provided in the final design and during construction.
7. Associated walls up to 24 feet in height are anticipated with CBC construction. It is
imperative that the final wall configuration meets the minimum factor of safety
requirements of AASHTO under external stability conditions. Recommendations for
design to resist lateral loading can be found in Section 8.3 of this report.
8. All foundation excavations should be observed by a representative of the geotechnical
engineer prior to placement of structure backfill or concrete.
8.2 Bridge Foundations
If the existing culvert is to be replaced by a bridge, we recommend the proposed bridge
abutments be supported on a deep foundation system such as drilled shafts (referred to locally
as caissons) or driven piles. Laboratory tests show the on-site soils could be corrosive to buried
metal and driven piles may require steel protection/mitigation. A drilled shaft deep foundation
system with sulfate-resistant concrete is recommended. Drilled shaft recommendations are
provided below in Sections 8.2.1 through 8.2.4. Driven pile recommendations can be provided
on request.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
12
The soil and bedrock properties were estimated from drilling conditions, material descriptions,
and laboratory data. The design and construction of the foundation elements should comply with
all applicable requirements and guidelines listed in AASHTO LRFD.
Proposed bridge abutment boring estimated elevations, and approximate depths to weathered
and competent shale bedrock are presented in Table 4 below.
Table 4 – Bridge Abutment Boring Bedrock Summary
Boring Number and
Location
Estimated Elevation of Boring
(feet)
Estimated Elevation of Weathered
Bedrock (feet)
Estimated Elevation of Competent
Bedrock (feet)
A-1 North abutment
4573* 4558 4544
A-2 South abutment
4573* 4560 4545
*Based on City of Fruita GIS map
8.2.1 Drilled Shaft Nominal Axial Resistance
The bearing resistance of drilled shafts will be developed from side and tip resistance in the
underlying weathered and competent shale bedrock. The resistance from the overburden soil
above the weathered bedrock should be neglected when calculating drilled shaft capacity.
Drilled shafts should bear in the very hard (competent) shale that is slightly weathered to fresh.
Depth of penetration below the weathered shale should be at least 1.5 x D (where D is the
diameter of the shaft). Design should be in accordance with AASHTO 10.8.3.5.4b (2017). In
areas where rock coring produced suitable core recovery (RQD was greater than 50 percent),
axial resistance was calculated using design methods based on the unconfined compressive
strength of the rock using AASHTO 10.8.3.5 (2017). The expansive potential of the clay
overburden soils, and the weathered and competent bedrock are classified as low per Table
10.4.6.3-1 of the AASHTO LRFD specifications. Side resistance from shaft penetration through
the weathered shale and into the competent shale is expected to be sufficient to offset any uplift
due to swelling of clay overburden or adjacent weathered bedrock.
Table 5 contains the recommended values for the nominal side and tip resistance for drilled
shafts founded in the underlying weathered and competent shale bedrock. The upper three feet
of weathered bedrock penetration shall not be used for calculating drilled shaft resistance due to
the likelihood of construction disturbance and possible additional weathering. To account for
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
13
axial group effects, the minimum spacing requirements between drilled shafts should be three
(3) diameters from center-to-center.
8.2.2 Drilled Shaft Axial Resistance Factors
Based on Table 10.5.5.2.4-1 in AASHTO (2017), a resistance factor of 0.55 is recommended for
the side resistance while a factor of 0.50 can be used for the tip resistance. These factors
should be applied to the nominal resistance values in Table 5.
Table 5 – Recommended Nominal Unit Drilled Shaft Axial Resistance
“Hard” Weathered Shale (50<N<80 or 10ksf<UCCS<100ksf)
“Very Hard” Competent Shale (UCCS>100 ksf)
Drilled Shaft Nominal Unit Side Resistance (ksf)
Drilled Shaft Nominal Unit
Tip Resistance (ksf)
Drilled Shaft Nominal Unit
Side Resistance (ksf)
5 150 11
8.2.3 Drilled Shaft Lateral Resistance
The input parameters provided in Table 6 are recommended for use with the computer program
LPILE to develop the soil models used to evaluate the drilled shaft response to lateral loading.
Table 6 provides the estimated values associated with the soil types encountered in the borings.
The nature and type of loading should be considered carefully. The values in Table 6 may need
to be revised for foundation elements that are relatively close to a retaining wall.
Individual soil layers and their extent can be averaged or distinguished by referring to the boring
logs at the locations of the proposed foundations. The soils and/or bedrock materials prone to
future disturbance, such as from utility excavations or frost heave, should be neglected in the
lateral load analyses to the depth of disturbance, which may require more than but should not
be less than 3 feet.
Recommendations for p-y multiplier values (Pm values) to account for the reduction in lateral
capacity due to group effects are provided in Section 10.7.3.12 of AASHTO (2017). The Pm
value will depend on the direction of the applied load, center-to-center spacing, and location of
the foundation element within the group.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
14
Table 6 – LPILE Parameters
Soil Type LPILE Soil
Criteria
Effective Unit Weight (pcf)
Friction Angle
φ φ φ φ (deg.)
Cohesion c (psf)
Strain Factor ε50
p-y modulus kstatic (pci)
AGT 1 BGT AGT BGT
Native Clay
Stiff Clay w/o Free Water (Welch & Reese)
115 57.5 - 500 0.01 100 -
Weathered Bedrock
Stiff Clay w/o Free Water (Welch & Reese)
125 62.5 - 1,000 0.008 500 -
Competent Bedrock
Hard Clay w/o Free Water (Welch & Reese)
135 135 - 8,000 0.001 2000 -
Notes (1) AGT is an abbreviation for above groundwater table, BGT is an abbreviation for below
groundwater table.
8.2.4 General Drilled Shaft Recommendations
The following recommendations can be used in the design and construction of the drilled shafts.
1. Groundwater and potentially caving soils may be encountered during drilling depending
on the time of year and location. The Contractor shall construct the drilled shafts using
means and methods that maintain a stable hole. Drilled shafts should be installed in
accordance with Section 503 of CDOT (2017).
2. Bedrock may be very hard at depth. The contractor should mobilize equipment of
sufficient size and operating condition to achieve the required design bedrock
penetration.
3. Drilled shaft construction shall not disturb previously installed drilled shafts or buried
structures, if any. The drilled shaft concrete should have sufficient time to cure before
construction on a drilled shaft within three shaft diameters (center to center spacing) to
prevent interaction between shafts during excavation and concrete placement.
4. Based on the results of the field investigation and experience with similar properly
constructed drilled shaft foundations, it is estimated that foundation settlement will be
less than approximately ½ inches when designed according to the criteria presented in
this report.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
15
5. A representative of the geotechnical engineer should observe drilled shaft installation
operations on a full-time basis.
8.3 Lateral Earth Pressure
Bridge retaining/wing walls should be designed to resist lateral earth pressures. Based on the
existing geometry of the site there is a possibility of retaining walls and wing walls up to 24 feet
or more in height. Yeh recommends a global stability analysis be performed after a wall design
is completed. A global stability analysis was not included in our scope of work for this
investigation and can be provided upon request for an additional fee.
We recommend all retaining/wing walls be backfilled with properly compacted Class 1 Structure
Backfill meeting the requirements in the Colorado Department of Transportation, Standard
Specifications for Road and Bridge Construction (CDOT 2017). Walls can be designed using an
equivalent fluid density of 38 pcf for active pressures or 60 pcf for at rest conditions for Class 1
Structure Backfill. On-site materials should not be used for retaining/wing wall backfill because
the clayey material is not free draining and may build hydrostatic pressure. This equivalent fluid
density assumes a horizontal slope above the wall. This value also assumes that the backfill
materials are not saturated. Wall designs should consider the influence of surcharge loading
such as traffic, construction equipment and/or sloping backfill.
Retaining/wing walls should be constructed with a drainage system to prevent buildup of
hydrostatic pressure immediately behind the wall. Drainage systems such as free-draining
gravel, pipes, drain board and/or weep holes are commonly used for the wall drainage. Water
levels during irrigation season may make subsurface drains impractical. Walls should be
designed for the anticipated hydrostatic pressures where drains cannot be provided.
8.4 Bridge Approach Embankment
We recommend the upper 2 feet of embankment material consist of imported granular soil
having an R-value of at least 30 to support the pavement structure. The abutment backfill
should be designed and constructed in accordance with the CDOT Bridge Design Manual.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
16
9. PAVEMENT RECOMMENDATIONS
9.1 Subgrade Strength
An R-value of 18 was obtained from a representative bulk sample of native clay from a depth of
2 to 5 feet. The R-value of 18 was used to calculate a resilient modulus of 4,627 psi to model
subgrade strength for pavement design. The modulus value was used as one of the inputs for
the DARWin Pavement Design and Analysis computer program to determine recommended
pavement thickness. Other structural layer coefficients used in design were found in the
Colorado Department of Transportation 2014 Pavement Design Manual in accordance with the
1993 AASHTO Pavement Design Guide.
9.2 Traffic Loading
The design traffic loading was determined from an Average Daily Traffic (ADT) of 1,568 vehicles
per day based on a 1.24 growth factor computed from an estimated current ADT of 1,400. The
current ADT number was obtained from Mesa County through TH Engineering. Twenty-year
projected volumes were used as an input for the design of hot mix asphalt (HMA) pavement.
The resulting traffic ESAL (Equivalent Single Axle Load applications) value was estimated at
477,315 for HMA pavement. The data and calculations of the traffic loading ESAL value is
presented in Appendix D.
9.3 Design Assumptions and Inputs
Table 7 presents the input design parameters used for the design of all flexible pavement
sections.
Table 7 - Flexible Pavement Design Parameters
HMA Design Inputs
Initial Serviceability 4.5 Overall Deviation 0.44
Terminal Serviceability 2.0 HMA Str. Layer Coefficient 0.44
Reliability Level, % 95 Class 6 Aggregate Coefficient 0.12
Structural Numbers
Pavement ESALs Design Structural
Number (SN)
HMA Traffic Loading 477,315 3.61
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
17
9.4 Pavement
A pavement section is a layered structure designed to disperse dynamic traffic loads to the
subgrade. The performance of the pavement structure depends on the traffic loadings and
physical properties of the subgrade materials. The recommended pavement design thickness
sections are summarized below. Recommended HMA pavement thickness can be found in
Table 8.
HMA pavement design calculations were performed using the program DARWin Version 3.1.
The program follows the guidelines from the 1993 AASHTO Pavement Design Guide and the
2014 CDOT Pavement Design Manual. The program outputs for all pavement designs are
presented in Appendix E.
Table 8 - Recommended HMA and Base Thicknesses
Pavement Location Required
SN New HMA (inches)
Class 6 Aggregate Base Course
(inches)
Calculated SN
18.5 Road south of L Road in area of proposed replacement bridge
3.61 6 9 3.72
Based on the DARWin program Version 3.1 (1993 AASHTO) computer program, an HMA
pavement thickness of 6 inches overlying a minimum of 9 inches of Class 6 aggregate base
course would be acceptable for the proposed changes to 18.5 Road in the location of the bridge
replacement.
9.5 Hot Mix Asphalt Type
A printout from the LTPPBind program is presented following the pavement designs in Appendix
E. The data from the LTPPBind program, based on local weather data, recommends that
performance graded binder PG 64-28 be used in the project area. However, because of the
limited amount of asphalt mix that will be required for the structure approaches, we recommend
a nominal 1/2 inch mix conforming to CDOT Grading SX(75) containing the performance graded
binder; PG 64-22. This mix contains an unmodified asphalt binder, is a locally produced mix and
should be readily available from all local asphalt producers. Based on the LTPPBind output
attached in Appendix E the mix should provide 98% reliability against rutting and 91% reliability
to address low temperature thermal cracking.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
18
Aggregates for hot plant mix bituminous pavement should be of uniform quality, and composed
of clean, hard, durable particles of crushed stone, gravel, or slag. Excess of fine material should
be wasted before crushing.
9.6 Pavement Preparation
In order to prepare the subgrade for the placement of the new pavements, we recommend
removal of any topsoil material from the pavement areas. The upper 2 feet of existing fill
material should be removed and replaced compacted to at least 95 percent of the standard
Proctor density. Following removal of the existing fill soils and topsoil, the native subgrade or
existing fill should be reconditioned by scarifying and recompacting to a minimum depth of 8
inches. Stabilization, either mechanical or chemical, of the existing subgrade may be necessary
in order to achieve a stable paving subgrade. These recommendations can be provided during
construction if necessary. Subgrade deterioration in areas of frequent construction traffic should
be anticipated and stabilization methods such as imported layers of aggregate, or geogrid
stabilization, may be necessary. We recommend the installation of a non-woven separator
geotextile conforming to AASHTO M288 Class 1 on the compacted subgrade prior to placement
of the ABC.
10. WATER-SOLUBLE SULFATE AND CORROSION TESTING
Three samples acquired during drilling were tested for water-soluble sulfate and corrosion. One
fill clay sample from a depth of 2 feet had a concentration of water-soluble sulfates of 0.333
percent. Two weathered shale samples from depths of 5.5 and 13.0 feet had concentrations of
water-soluble sulfates of 1.417 percent and 0.918 percent, respectively. The concentration of
soluble sulfate in the soil samples for this project represent a susceptibility to sulfate attack to
concrete of Class 2 based on Table 601-2 of the 2017 CDOT Standard Specifications for Road
and Bridge Construction. Concrete mixes in contact with soils on this project should meet the
requirements for Class 2 in conformance with Section 601.04 of the CDOT Standard
Specifications.
When applicable, a layer of Structure Backfill (Class 1) or aggregate base course could be used
as a separator between concrete and native material. Structure Backfill and aggregate base
course are assumed to have Class 0 water-soluble sulfate exposure, or no effect on concrete.
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
19
The pH, electrical resistivity and water-soluble chloride concentration were also determined for
the three samples. Test results measured pH values of 7.6 to 8.0, resistivity values of 335 to
651 ohm-centimeters, and water-soluble chlorides concentrations of 0.0038 to 0.0193 percent.
The low resistivity values indicate the soils may be corrosive to buried metal. An increase in
moisture to surrounding soils typically increases corrosivity. Properly compacted non-corrosive
imported fill soils may be used as a barrier between corrosive soils and construction materials.
Options for corrosion mitigation could include sacrificial metal (heavier gauge construction
material) in design of structural elements and use of materials resistant to corrosion such as
galvanized or epoxy coatings; cathodic protection systems, and sulfate resistant concrete. A
qualified corrosion engineer should review this data to evaluate the appropriate level of
corrosion protection for subgrade utilities and buried metal and concrete structures proposed for
the area.
11. LIMITATIONS
This study was conducted in accordance with generally accepted geotechnical engineering
practices in this area for use by the client for design of the proposed culvert replacement.
Recommendations herein are intended to be used for design by a qualified structural engineer.
The preliminary analyses and recommendations presented in this report are based upon our
data obtained from limited field observations, widely spaced borings, laboratory testing, our
understanding of the proposed construction and other information as discussed in this report. It
is possible and likely that subsurface conditions may vary from those encountered in the
borings. We should also review the design for conformance to the recommendations in the
report when the scope of the proposed construction, including the proposed loads, finished
elevations or structure locations, become established.
The scope of services for this project did not include, specifically or by implication, any
environmental or biological (e.g., mold, fungi, and bacteria) assessment of the site or
identification or prevention of pollutants, hazardous materials or conditions or biological
conditions. If the owner is concerned about the potential for such contamination, conditions or
pollution, other studies should be undertaken.
The report was prepared in substantial accordance with the generally accepted standards of
practice for geotechnical engineering as exist in the site area at the time of our investigation. No
warranties, express or implied, are intended or made. The recommendations in this report are
Final Geotechnical Investigation Report Project No. 219-061 FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
20
based on the assumption that Yeh and Associates will conduct an adequate program of
construction testing and observation to evaluate compliance with our recommendations.
12. REFERENCES
AASHTO, (2017). AASHTO LRFD Bridge Design Specifications, 8th Edition, American
Association of State Highway and Transportation Officials, Washington, D.C.
American Association of State Highway and Transportation Officials. (1993). AASHTO guide for
design of pavement structures, 1993. Washington, D.C.: The Association
City of Fruita GIS maps accessed web site April 19, 2019 at: https://fruita-
gis.maps.arcgis.com/apps/webappviewer/index.html?id=e6ce33d199444f62b6bbd19849
f3ab60
Colorado Department of Transportation Pavement Design Manual, CDOT 2017.
Colorado Department of Transportation Standard Specifications for Road and Bridge
Construction, CDOT 2017.
Colorado Geological Survey, Corrosive Soils, accessed web site April 9, 2019 at:
http://coloradogeologicalsurvey.org/geologic-hazards/corrosive-soils/
Livaccari, R., and Hodge, J., 2009, Geologic map of the Fruita quadrangle, Mesa County,
Colorado, Open-File Report OF-09-04, scale 1:24,000.
U.S. Geological Survey Seismic Design Web Service Documentation,
https://earthquake.usgs.gov/ws/designmaps/, accessed April 11, 2019.
PROJECT NUMBER:
NOT TO SCALE
PROJECT:
FIGURE
DRAWN BY:
CHECKED BY:
DATE:
DATE:
DESIGNED FOR:
Consulting Engineers & ScientistsYeh and Associates, Inc. 1
JRM/SW
SWR
05-06-2019
05-06-2019
Collins Engineers, Inc.
219-061
N
Base maps acquired from maps.google.com and Google Earth
Site Location Map
FRT-18.5-K.99 Bridge Replacement
Fruita, Mesa County, Colorado
SITE
Fruita
FRT-18.5-K.99 Bridge
Replacement Area
18.5 R
oa
d
Figure 2
G
o
v
t
H
ig
h
lin
e
Canal
L Road
M
a
i
n
L
i
n
e
G
r
a
n
d
V
a
lle
y
C
a
n
a
l
L
i
t
t
l
e
S
a
l
t
W
a
s
h
Main Line G
rand V
alley C
anal
L
i
t
t
l
e
S
a
l
t
W
a
s
h
PROJECT NUMBER:
SCALE: 1"=30'
PROJECT:
FIGURE
DRAWN BY:
CHECKED BY:
DATE:
DATE:
DESIGNED FOR:
Consulting Engineers & ScientistsYeh and Associates, Inc. 2
JRM/SW
SWR
05-06-2019
05-06-2019
Collins Engineers, Inc.
219-061
0 15 30 60
Indicates proposed abutment area boring
Approximate Boring
Location Map
FRT-18.5-K.99 Bridge Replacement
Fruita, Mesa County, Colorado
NOTES: Base maps acquired from Google Earth.
Boring locations are placed according to
measurements taken by YA staff using basic
survey methods. Survey was not complete at time
of report.
Indicates pavement boring
P-1
A-1
LEGEND
(All locations are approximate)
18 1/2 Road
A-1
M
a
in
L
in
e
G
ra
n
d
V
a
lle
y
C
a
n
a
l
A-2P-2
40
40
P-1
Existing guardrail,
west side
North Bound Lane (NB) Mesa County
South Bound Lane (SB) City of Fruita
Approximate Centerline
of Existing Culvert
Approximate location of
proposed north abutment
Approximate location
of proposed south abutment
L
i
t
t
l
e
S
a
l
t
W
a
s
h
L
i
t
t
l
e
S
a
l
t
W
a
s
h
Indicates flow direction
Existing guardrail,
east side
APPENDICES
APPENDIX A - BORING LOGS AND LEGEND
APPENDIX B - ENGINEERING GEOLOGY SHEET
APPENDIX C - LABORATORY TEST RESULTS AND CORE PHOTOGRAPHS
APPENDIX D - ESALS AND TRAFFIC LOADING CALCULATIONS
APPENDIX E - PAVEMENT DESIGN
Appendix A
BORING LOGS AND LEGEND
Project Number: 219-061
Lithology Symbols(see Boring Logs for complete descriptions)
Asphalt
Lab Test Standards Other Lab Test Abbreviations
Notes
Moisture Content ASTM D2216Dry Density ASTM D7263Sand/Fines Content ASTM D421, ASTM C136,
ASTM D1140Atterberg Limits ASTM D4318AASHTO Class. AASHTO M145,
ASTM D3282USCS Class. ASTM D2487(Fines = % Passing #200 SieveSand = % Passing #4 Sieve, but not passing #200 Sieve)
Auger Cuttings Rock Core
Modified CaliforniaSampler(2.5 inch OD, 2.0inch ID)
StandardPenetration Test(ASTM D1586)
Sample Types
Legend for Symbols Used on Borehole Logs
Project:
Yeh and Associates, Inc.C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Aggregate Base Course (ABC)
SHALE BEDROCK
CLAY
FILL SAND
FILL CLAY
pH Soil pH (AASHTO T289-91)S Water-Soluble Sulfate Content (AASHTO T290-91,
ASTM D4327)Chl Water-Soluble Chloride Content (AASHTO T291-91,
ASTM D4327)S/C Swell/Consolidation (ASTM D4546)UCCS Unconfined Compressive Strength (ASTM D2166)R-Value Resistance R-Value (ASTM D2844)Re Electrical Resistivity (AASHTO T288-91)
1. "Penetration Resistance" on the Boring Logs refers to the uncorrected N value for SPT samples only, as perASTM D1586. For samples obtained with a Modified California sampler, drive depth is 12 inches, and "PenetrationResistance" refers to the sum of all blows. Where blow counts were > 50 for the 3rd increment (SPT) or 2ndincrement (MC), "Penetration Resistance" combines the last and 2nd-to-last blows and lengths; for other incrementswith > 50 blows, the blows for the last increment are reported.
WEATHERED SHALE BEDROCK
2. The Modified California sampler used to obtain samples is a 2.5-inch OD, 2.0-inch ID (1.95-inch ID with liners),split-barrel sampler with internal liners, as per ASTM D3550. Sampler is driven with a 140-pound hammer, dropped30 inches per blow.
FRT-18.5-K.99 Bridge Replacement
A-4 (2)CL
58 923
S/C=-0.1%
S/C=-0.1%
S/C=0.1%
20.0 ft - Switch toHQ CoreUCCS=13,794 psf
10.7
12.5
10.9
7.2
114.0
120.0
124.0
132.0
3-4
3-3
5-6
3-8
2-3
4-16
40-50/3"
7
6
11
11
5
20
50/3"
0.0 - 0.4 ft. 5 inches HMA.
0.4 - 1.5 ft. Aggregate Base Course;SAND, silty with gravel; brown; noplasticity; moist; medium dense, (fill).
1.5 - 9.5 ft. sandy CLAY with gravel,reddish brown, low plasticity, moist,medium stiff to stiff, (fill).
Reddish brown with dark brown, shalefragments.
9.5 - 15.0 ft. sandy CLAY, brown, lowplasticity, moist, medium stiff to stiff.
15.0 - 29.0 ft. WEATHERED SHALE,light brown with gray, predominantlydecomposed to moderately weathered,firm to very hard, lamination openfractures, some decomposed to clay;calcareous veins.
Color change to dark gray to black.
24.5 - 25.6 ft.Highly weathered zone.
89
95
0
0
Total Depth: 51.5 ft
Ground Elevation: Estimated 4573
Coordinates: N: E:
Location: In pavement 18.5 Rd, 40 ft north of culvert center
line, center of NB lane Groundwater Levels:
Logged By: J. Mulumba
Final By: J. Mulumba/S. White
Symbol
Depth
Date
Weather Notes: Sunny, 50°
Inclination from Horiz.: Vertical
Boring Began: 3/27/2019
Boring Completed: 3/27/2019
Drilling Method(s): Hollow-Stem Auger (10" OD) /
Coring
Driller: HRL Compliance Solutions
Drill Rig: CME 55 Rubber Track
Hammer Type: Automatic (hydraulic)-
-
-
-
-
-
Night Work:
ProjectName:
PAGE1 of 2
AASHTO& USCSClassifi-cations
Fin
es C
onte
nt
(%)
Pla
sticity
Index
Project Number: 219-061C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Liq
uid
Lim
it
Field Notesand
Other LabTests
FRT-18.5-K.99 Bridge Replacement
AtterbergLimits
Boring No.: A-1
Yeh and Associates, Inc.E
leva
tio
n(f
ee
t)
4570
4565
4560
4555
4550
De
pth
(fe
et)
5
10
15
20
25
Sam
ple
Type/
Advancem
ent M
eth
od
BO
RIN
G L
OG
20
15
2
19
-06
1 F
RT
-18
.5-K
99
GIN
T,M
W R
EV
EL
EV
.GP
J
20
15
YE
H A
SS
OC
IAT
ES
TE
MP
LA
TE
.GD
T
20
15
LIB
RA
RY
.GL
B
7/1
8/1
9
Mois
ture
Conte
nt
(%)
Dry
Density
(pcf)Blows
per6 in
Pe
ne
tra
tio
nR
esis
tan
ce
Lith
olo
gy
Soil Samples
Material Description
Re
co
ve
ry (
%)
Rock
RQ
D (
%)
32.0 ft - FastercoringUCCS=620,790 psf
46.5 ft -UCCS=552,453 psf
51.5 ft - End coring;backfill with cuttingsand native material.Gravel base andconcrete patch atsurface.
2.3
3.1
147.0
153.0
29.0 - 51.5 ft. SHALE, dark gray to black;slightly weathered to fresh; very hard; fewfractures.
32.6 - 32.9 ft. Iron-oxide staining.
Bottom of Hole at 51.5 ft.
93
98
100
100
100
0
73
99
100
83
ProjectName:
PAGE2 of 2
AASHTO& USCSClassifi-cations
Fin
es C
onte
nt
(%)
Pla
sticity
Index
Project Number: 219-061C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Liq
uid
Lim
it
Field Notesand
Other LabTests
FRT-18.5-K.99 Bridge Replacement
AtterbergLimits
Boring No.: A-1
Yeh and Associates, Inc.E
leva
tio
n(f
ee
t)
4545
4540
4535
4530
4525
4520
4515
De
pth
(fe
et)
30
35
40
45
50
Sam
ple
Type/
Advancem
ent M
eth
od
BO
RIN
G L
OG
20
15
2
19
-06
1 F
RT
-18
.5-K
99
GIN
T,M
W R
EV
EL
EV
.GP
J
20
15
YE
H A
SS
OC
IAT
ES
TE
MP
LA
TE
.GD
T
20
15
LIB
RA
RY
.GL
B
7/1
8/1
9
Mois
ture
Conte
nt
(%)
Dry
Density
(pcf)Blows
per6 in
Pe
ne
tra
tio
nR
esis
tan
ce
Lith
olo
gy
Soil Samples
Material DescriptionR
eco
ve
ry (
%)
Rock
RQ
D (
%)
A-4 (2)CL
A-4 (2)CL
53
56
10
9
11
25
24
26
pH=8S=0.333%Chl=0.0038%S/C=0%Re=393ohm·cm2.0 ft - Proctor:Optimum MoistureContent=12.5%;Maximum DryDensity=119 pcf
S/C=-0.4%
pH=7.6S=0.918%Chl=0.0193%Re=651ohm·cm
15.8 ft - Switch toHQ Core
24.0 ft -UCCS=17,585 psf
32
44
15
0
13.8
10.1
6.1
10.5
115.0
112.0
101.0
4-5
5-6
4-6
3-4
15-50/5"
30-50/3"
9
11
10
7
50/5"
50/3"
0.0 - 0.4 ft. 5 inches HMA.
0.4 - 2.0 ft. Aggregate BaseCourse; SAND, silty withgravel; brown; no plasticity;moist; medium dense, (fill).
2.0 - 10.0 ft. sandy CLAYwith gravel, reddish brown,low plasticity, moist, stiff, (fill).
10.0 - 13.0 ft. CLAY, brown,low plasticity, moist, mediumstiff.
13.0 - 27.5 ft. WEATHEREDSHALE, light gray to lightbrown, dark brown,moderately weathered, hardto very hard, lamination openfractures, some fractureshave clay infilling; friable.
Dark gray with bands of lightbrown.
56
100
95
0
0
0
Total Depth: 50.3 ft
Ground Elevation: Estimated 4573
Coordinates: N: E:
Location: In pavement 18.5 Rd, 40 ft south of culvert center
line, center of SB lane Groundwater Levels: Not Observed
Logged By: J. Mulumba
Final By: J. Mulumba/S. White
Symbol
Depth
Date
Weather Notes: Sunny, 50°
Inclination from Horiz.: Vertical
Boring Began: 3/25/2019
Boring Completed: 3/25/2019
Drilling Method(s): Hollow-Stem Auger (10" OD) /
Coring
Driller: HRL Compliance Solutions
Drill Rig: CME 55 Rubber Track
Hammer Type: Automatic (hydraulic)-
-
-
-
-
-
Night Work:
ProjectName:
PAGE1 of 2
AASHTO& USCSClassifi-cations
Fin
es C
onte
nt
(%)
Pla
sticity
Index
Project Number: 219-061C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Liq
uid
Lim
it
Field Notesand
Other LabTests
FRT-18.5-K.99 Bridge Replacement
AtterbergLimits
Boring No.: A-2
Yeh and Associates, Inc.E
leva
tio
n(f
ee
t)
4570
4565
4560
4555
4550
De
pth
(fe
et)
5
10
15
20
25
Sam
ple
Type/
Advancem
ent M
eth
od
BO
RIN
G L
OG
20
15
2
19
-06
1 F
RT
-18
.5-K
99
GIN
T,M
W R
EV
EL
EV
.GP
J
20
15
YE
H A
SS
OC
IAT
ES
TE
MP
LA
TE
.GD
T
20
15
LIB
RA
RY
.GL
B
7/1
8/1
9
Sand C
onte
nt
(%)
Gra
vel C
onte
nt
(%)
Mois
ture
Conte
nt
(%)
Dry
Density
(pcf)Blows
per6 in
Pe
ne
tra
tio
nR
esis
tan
ce
Lith
olo
gy
Soil Samples
Material Description
Re
co
ve
ry (
%)
Rock
RQ
D (
%)
28.5 ft -UCCS=603,923 psf
46.5 ft -UCCS=751,248 psf
50.3 ft - End coring;backfill with cuttingsand native material.Gravel base andconcrete patch atsurface.
3.6 155.0
27.5 - 50.3 ft. SHALE, darkgray to black; slightlyweathered to fresh; very hard;slightly fractured.Iron oxide staining.
Bottom of Hole at 50.3 ft.
100
100
100
100
100
47
93
100
100
100
ProjectName:
PAGE2 of 2
AASHTO& USCSClassifi-cations
Fin
es C
onte
nt
(%)
Pla
sticity
Index
Project Number: 219-061C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Liq
uid
Lim
it
Field Notesand
Other LabTests
FRT-18.5-K.99 Bridge Replacement
AtterbergLimits
Boring No.: A-2
Yeh and Associates, Inc.E
leva
tio
n(f
ee
t)
4545
4540
4535
4530
4525
4520
4515
De
pth
(fe
et)
30
35
40
45
50
Sam
ple
Type/
Advancem
ent M
eth
od
BO
RIN
G L
OG
20
15
2
19
-06
1 F
RT
-18
.5-K
99
GIN
T,M
W R
EV
EL
EV
.GP
J
20
15
YE
H A
SS
OC
IAT
ES
TE
MP
LA
TE
.GD
T
20
15
LIB
RA
RY
.GL
B
7/1
8/1
9
Sand C
onte
nt
(%)
Gra
vel C
onte
nt
(%)
Mois
ture
Conte
nt
(%)
Dry
Density
(pcf)Blows
per6 in
Pe
ne
tra
tio
nR
esis
tan
ce
Lith
olo
gy
Soil Samples
Material DescriptionR
eco
ve
ry (
%)
Rock
RQ
D (
%)
A-2-4 (0)SM
A-4 (0)SM
A-4 (2)CL
20
44
56
NP
NP
9
NV
NV
26 S/C=-0.1%6.0 ft - End drilling;backfill with cuttingsand native material,and asphalt patch atsurface.
45
39
34
35
17
10
6.1
12.2
10.1
105.0
108.0
9-8-5
12-18
6-7
13
30
13
0.0 - 0.4 ft. 5 inches HMA.
0.4 - 2.0 ft. Aggregate Base Course;SAND, silty with gravel; brown; noplasticity; moist; medium dense, (fill).
2.0 - 5.5 ft. silty SAND with gravel, brownwith red, no plasticity, moist, mediumdense, gravels up to 3-inch diameter, (fill).
5.5 - 6.0 ft. sandy CLAY, black, lowplasticity, moist, stiff, calcareous.
Bottom of Hole at 6.0 ft.
Total Depth: 6.0 ft
Ground Elevation: Estimated 4574
Coordinates: N: E:
Location: In pavement 18.5 Rd, 160 ft north of culvert center
line, SB lane Groundwater Levels: Not Observed
Logged By: J. Mulumba
Final By: J. Mulumba/S. White
Symbol
Depth
Date
Weather Notes: Sunny, 45°
Inclination from Horiz.: Vertical
Boring Began: 3/25/2019
Boring Completed: 3/25/2019
Drilling Method(s): Solid-Stem Auger (6" OD)
Driller: HRL Compliance Solutions
Drill Rig: CME 55 Rubber Track
Hammer Type: Automatic (hydraulic)-
-
-
-
-
-
Night Work:
ProjectName:
PAGE1 of 1
AASHTO& USCSClassifi-cations
Fin
es C
onte
nt
(%)
Pla
sticity
Index
Project Number: 219-061C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Liq
uid
Lim
it
Field Notesand
Other LabTests
FRT-18.5-K.99 Bridge Replacement
AtterbergLimits
Boring No.: P-1
Yeh and Associates, Inc.E
leva
tio
n(f
ee
t)
4570
4565
4560
4555
4550
De
pth
(fe
et)
5
Sam
ple
Type/
Advancem
ent M
eth
od
BO
RIN
G L
OG
20
15
2
19
-06
1 F
RT
-18
.5-K
99
GIN
T,M
W R
EV
EL
EV
.GP
J
20
15
YE
H A
SS
OC
IAT
ES
TE
MP
LA
TE
.GD
T
20
15
LIB
RA
RY
.GL
B
7/1
8/1
9
Sand C
onte
nt
(%)
Gra
vel C
onte
nt
(%)
Mois
ture
Conte
nt
(%)
Dry
Density
(pcf)Blows
per6 in
Pe
ne
tra
tio
nR
esis
tan
ce
Lith
olo
gy
Soil Samples
Material Description
A-4 (1)CL-ML
58 6
13
23
27
S/C=-0.1%2.0 ft - Proctor:Optimum MoistureContent=14.3%;Maximum DryDensity=116 pcfR-Value=18
pH=7.9S=1.417%Chl=0.0097%Re=335ohm·cm6.0 ft - End drilling;backfill with cuttingsand native material,and asphalt patch atsurface.
36610.6
7.0
113.0
123.0
4-6
12-20
10
32
0.0 - 0.4 ft. 5 inches HMA.
0.4 - 2.0 ft. Aggregate Base Course;SAND, silty with gravel; brown; noplasticity; moist; medium dense, (fill).
2.0 - 5.5 ft. silty CLAY sandy, brown, lowplasticity, moist, stiff, calcareous.
5.5 - 6.0 ft. WEATHERED SHALE,brown, decomposed as CLAY, with sand,low plasticity; medium hard; gypsumdeposits.
Bottom of Hole at 6.0 ft.
Total Depth: 6.0 ft
Ground Elevation: Estimated 4574
Coordinates: N: E:
Location: In pavement 18.5 Rd, 190 ft south of culvert center
line, SB lane Groundwater Levels: Not Observed
Logged By: J. Mulumba
Final By: J. Mulumba/S. White
Symbol
Depth
Date
Weather Notes: Sunny, 60°
Inclination from Horiz.: Vertical
Boring Began: 3/25/2019
Boring Completed: 3/25/2019
Drilling Method(s): Solid-Stem Auger (6" OD)
Driller: HRL Compliance Solutions
Drill Rig: CME 55 Rubber Track
Hammer Type: Automatic (hydraulic)-
-
-
-
-
-
Night Work:
ProjectName:
PAGE1 of 1
AASHTO& USCSClassifi-cations
Fin
es C
onte
nt
(%)
Pla
sticity
Index
Project Number: 219-061C o n s u l t i n g E n g i n e e r s & S c i e n t i s t s
Liq
uid
Lim
it
Field Notesand
Other LabTests
FRT-18.5-K.99 Bridge Replacement
AtterbergLimits
Boring No.: P-2
Yeh and Associates, Inc.E
leva
tio
n(f
ee
t)
4570
4565
4560
4555
4550
De
pth
(fe
et)
5
Sam
ple
Type/
Advancem
ent M
eth
od
BO
RIN
G L
OG
20
15
2
19
-06
1 F
RT
-18
.5-K
99
GIN
T,M
W R
EV
EL
EV
.GP
J
20
15
YE
H A
SS
OC
IAT
ES
TE
MP
LA
TE
.GD
T
20
15
LIB
RA
RY
.GL
B
7/1
8/1
9
Sand C
onte
nt
(%)
Gra
vel C
onte
nt
(%)
Mois
ture
Conte
nt
(%)
Dry
Density
(pcf)Blows
per6 in
Pe
ne
tra
tio
nR
esis
tan
ce
Lith
olo
gy
Soil Samples
Material Description
Appendix B
ENGINEERING GEOLOGY SHEET
Consulting Engineers & ScientistsYeh and Associates, Inc.
REUSE OF DOCUMENTThis document is the property of Yeh &Associates, Inc. The ideas incorporated on thisdocument are instruments of professionalservice and shall not be used for any otherproject without written authorization from Yeh& Associates, Inc.
N
Appendix C
LABORATORY TEST RESULTS AND CORE PHOTOGRAPHS
(ohm-cm)
250 500 1000 (psf)
A-1 6.5 MC 10.7 114 -0.1FILL CLAY, sandy with
gravel
9.5 MC 12.5 120 58 23 14 9 -0.1 A-4 (2) CL CLAY, sandy
15.0 MC 10.9 124 0.1WEATHERED SHALE
BEDROCK
20.0 to
20.3Core 7.2 132 13,794
WEATHERED SHALE
BEDROCK
32.0 to
32.5Core 2.3 147 620,790 SHALE BEDROCK
46.5 to
47.0Core 3.1 153 552,453 SHALE BEDROCK
A-2 2.0 MC 13.8 115 15 32 53 25 15 10 0.333 0.0038 393 8.0 0.0 A-4 (2) CLFILL CLAY, sandy with
gravel
2.0-5.0 Bulk 12.5* 119** 0 44 56 24 15 9 A-4 (2) CLFILL CLAY, sandy with
gravel
7.0 MC 10.1 112 -0.4FILL CLAY, sandy with
gravel
13.0 MC 6.1 26 15 11 0.918 0.0193 651 7.6WEATHERED SHALE
BEDROCK
24.0 to
24.3Core 10.5 101 17,585
WEATHERED SHALE
BEDROCK
28.5 to
28.9Core 3.6 155 603,923 SHALE BEDROCK
46.5 to
46.8Core
157.9
(wet)751,248 SHALE BEDROCK
Water
Soluble
Sulfate
(%)
Atterberg Limits
AASHTOResistivity
Unconfined
Compressive
Strength
219-061
Sample
Type
Dry
Density
(pcf)
Gravel
> #4
(%)
Swell /
Consolidation %
Applied Load (psf)Sand
(%)
Fines
< #200
(%)
LL
FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
PI
YEH & ASSOCIATES, INC
Summary of Laboratory Test Results
Project Name:
USCSR-
Value
Moisture
Content
(%)
Water
Soluble
Chloride
(%)PL
Sample Location
BoringMaterial Description
Project No:
Depth
(ft)
pH
Grain Size Analysis
MC - Indicates Modified California sampler
SPT - Indicates Split Spoon sampler
Bulk - Indicates auger cuttings
Core - Indicates HQ3 core samples 1 of 2* Optimum Moisture Content (%)
** Maximum Dry Density (pcf)
(ohm-cm)
250 500 1000 (psf)
Water
Soluble
Sulfate
(%)
Atterberg Limits
AASHTOResistivity
Unconfined
Compressive
Strength
219-061
Sample
Type
Dry
Density
(pcf)
Gravel
> #4
(%)
Swell /
Consolidation %
Applied Load (psf)Sand
(%)
Fines
< #200
(%)
LL
FRT-18.5-K.99 Bridge Replacement, Mesa County, Colorado
PI
YEH & ASSOCIATES, INC
Summary of Laboratory Test Results
Project Name:
USCSR-
Value
Moisture
Content
(%)
Water
Soluble
Chloride
(%)PL
Sample Location
BoringMaterial Description
Project No:
Depth
(ft)
pH
Grain Size Analysis
P-1 0.4 SPT 6.1 35 45 20 NV NP NP A-2-4 (0) SMFILL SAND, silty with
gravel
2.5 MC 12.2 105 17 39 44 NV NP NP A-4 (0) SMFILL SAND, silty with
gravel
5.5 MC 10.1 108 10 34 56 26 17 9 -0.1 A-4 (2) CL CLAY, sandy
P-2 2.0 MC 10.6 113 6 36 58 23 17 6 -0.1 A-4 (1)CL-
MLCLAY, silty, sandy
2.0-5.0 Bulk 14.3* 116** 18 CLAY, silty, sandy
5.5 MC 7.0 123 27 14 13 1.417 0.0097 335 7.9 WEATHERED SHALE
MC - Indicates Modified California sampler
SPT - Indicates Split Spoon sampler
Bulk - Indicates auger cuttings
Core - Indicates HQ3 core samples 2 of 2* Optimum Moisture Content (%)
** Maximum Dry Density (pcf)
Applied Normal Pressure, ksf
Applied Normal Pressure, ksf
1 6.5
2 9.5
Job No:
SWR
219-061 Project Name: FRT-18.5-K.99 Bridge ReplacementFigure C-1
YEH & ASSOCIATES, INC.
A-1 120 12.5 -0.1 CLAY, sandy (CL) Checked By:
Soil Description
SWELL /
CONSOLIDATION
GRAPH
A-1 114 10.7 -0.1FILL CLAY, sandy with
gravel (CL)Drawn By: JRM/SW
Swell(+) /
Consolidation(-)
(%)
Graph
Number
Boring
NumberDepth (ft)
Natural Dry
Density
(pcf)
Moisture
Content
(%)
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%
WATER ADDED
Graph 2
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%WATER ADDED
Graph 1
Applied Normal Pressure, ksf
Applied Normal Pressure, ksf
1 15.0
2 2.0
Job No:
SWR
219-061 Project Name: FRT-18.5-K.99 Bridge ReplacementFigure C-2
YEH & ASSOCIATES, INC.
A-2 115 13.8 0.0FILL CLAY, sandy with
gravel (CL)Checked By:
Soil Description
SWELL /
CONSOLIDATION
GRAPH
A-1 124 10.9 0.1WEATHERED SHALE
BEDROCKDrawn By: JRM/SW
Swell(+) /
Consolidation(-)
(%)
Graph
Number
Boring
NumberDepth (ft)
Natural Dry
Density
(pcf)
Moisture
Content
(%)
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%
WATER ADDED
Graph 2
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%
WATER ADDED
Graph 1
Applied Normal Pressure, ksf
Applied Normal Pressure, ksf
1 7.0
2
Job No:
SWR
219-061 Project Name: FRT-18.5-K.99 Bridge ReplacementFigure C-3
YEH & ASSOCIATES, INC.
Checked By:
Soil Description
SWELL /
CONSOLIDATION
GRAPH
A-2 112 10.1 -0.4 FILL CLAY, sandy Drawn By: JRM/SW
Swell(+) /
Consolidation(-)
(%)
Graph
Number
Boring
NumberDepth (ft)
Natural Dry
Density
(pcf)
Moisture
Content
(%)
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%
Graph 2
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%WATER ADDED
Graph 1
Applied Normal Pressure, ksf
Applied Normal Pressure, ksf
1 5.5
2 2.0
Job No:
Graph
Number
Boring
NumberDepth (ft)
Natural Dry
Density
(pcf)
Moisture
Content
(%)
Soil Description
SWELL /
CONSOLIDATION
GRAPH
P-1 108 10.1 -0.1 CLAY, sandy (CL) Drawn By: JRM/SW
Swell(+) /
Consolidation(-)
(%)
SWR
219-061 Project Name: FRT-18.5-K.99 Bridge ReplacementFigure C-4
YEH & ASSOCIATES, INC.
P-2 113 10.6 -0.1CLAY, silty, sandy
(CL-ML)Checked By:
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%
WATER ADDED
Graph 2
-2.0
-1.0
0.0
1.0
0.1 1 10
Co
nso
lid
ati
on
(-)/
Sw
ell
(+),
%WATER ADDED
Graph 1
Drawn By: JMPI 10
Sample ID: A-2
Project No.: 219-061 Sample
Description:FILL CLAY, sandy with gravel (CL)
Checked By: SWRFigure No.: C-5
Fines (%) 53SIEVE ANALYSIS
Sample
Depth (ft.):2.0
#200 53
Gravel (%) 15 LL 25 Project Name:FRT-18.5-K.99 Bridge
Replacement Yeh & Associates, Inc. Geotechnical Engineering Consultants
Sand (%) 32 PL 15
#4 85
#10 84
#40 81
¾ " 90
½" 87
⅜" 86
2" -
1 ½" -
1" 100
Sieve
Size
%
Passing
3" -
2 ½" -
0
10
20
30
40
50
60
70
80
90
100
0.010.11101001000
Perc
en
t P
assin
g
Particle Size (mm)
20040103/8" 41/2"3/4"3"12" 6" 1" 30 508 16
Sieve Analysis Hydrometer Analysis
Sieve Opening in Inches U.S. Standard Sieves Size of Particles in mm
1002"
Drawn By: SW
Sieve
Size
%
Passing
3" -
2 ½" -
2" -
1 ½" -
1" -
¾ " -
½" -
⅜" 100
#4 100
#10 97
#40 92
SIEVE ANALYSIS
#200 56
Gravel (%) 0 LL 24 Project Name:FRT-18.5-K.99 Bridge
Replacement Yeh & Associates, Inc. Geotechnical Engineering Consultants
Sand (%)
Sample
Depth (ft.):2.0 to 5.0
44 PL 15 Sample ID: A-2
Project No.: 219-061 Sample
Description:FILL CLAY, sandy with gravel (CL)
Checked By: SWRFigure No.: C-6
Fines (%) 56 PI 9
0
10
20
30
40
50
60
70
80
90
100
0.010.11101001000
Perc
en
t P
assin
g
Particle Size (mm)
20040103/8" 41/2"3/4"3"12" 6" 1" 30 508 16
Sieve Analysis Hydrometer Analysis
Sieve Opening in Inches U.S. Standard Sieves Size of Particles in mm
1002"
Drawn By: JMPI NP
Sample ID: P-1
Project No.: 219-061 Sample
Description:FILL SAND, silty with gravel (SM)
Checked By: SWRFigure No.: C-7
Fines (%) 20SIEVE ANALYSIS
Sample
Depth (ft.):0.4
#200 20
Gravel (%) 35 LL NV Project Name:FRT-18.5-K.99 Bridge
Replacement Yeh & Associates, Inc. Geotechnical Engineering Consultants
Sand (%) 45 PL NP
#4 65
#10 60
#40 51
¾ " 100
½" 94
⅜" 82
2" -
1 ½" -
1" -
Sieve
Size
%
Passing
3" -
2 ½" -
0
10
20
30
40
50
60
70
80
90
100
0.010.11101001000
Perc
en
t P
assin
g
Particle Size (mm)
20040103/8" 41/2"3/4"3"12" 6" 1" 30 508 16
Sieve Analysis Hydrometer Analysis
Sieve Opening in Inches U.S. Standard Sieves Size of Particles in mm
1002"
Drawn By: JMPI NP
Sample ID: P-1
Project No.: 219-061 Sample
Description:FILL SAND, silty with gravel (SM)
Checked By: SWRFigure No.: C-8
Fines (%) 44SIEVE ANALYSIS
Sample
Depth (ft.):2.5
#200 44
Gravel (%) 17 LL NV Project Name:FRT-18.5-K.99 Bridge
Replacement Yeh & Associates, Inc. Geotechnical Engineering Consultants
Sand (%) 39 PL NP
#4 83
#10 83
#40 81
¾ " 90
½" 86
⅜" 85
2" -
1 ½" -
1" 100
Sieve
Size
%
Passing
3" -
2 ½" -
0
10
20
30
40
50
60
70
80
90
100
0.010.11101001000
Perc
en
t P
assin
g
Particle Size (mm)
20040103/8" 41/2"3/4"3"12" 6" 1" 30 508 16
Sieve Analysis Hydrometer Analysis
Sieve Opening in Inches U.S. Standard Sieves Size of Particles in mm
1002"
Drawn By: JMPI 9
Sample ID: P-1
Project No.: 219-061 Sample
Description:CLAY, sandy (CL)
Checked By: SWRFigure No.: C-9
Fines (%) 56SIEVE ANALYSIS
Sample
Depth (ft.):5.5
#200 56
Gravel (%) 10 LL 26 Project Name:FRT-18.5-K.99 Bridge
Replacement Yeh & Associates, Inc. Geotechnical Engineering Consultants
Sand (%) 34 PL 17
#4 90
#10 80
#40 73
¾ " 100
½" 99
⅜" 97
2" -
1 ½" -
1" -
Sieve
Size
%
Passing
3" -
2 ½" -
0
10
20
30
40
50
60
70
80
90
100
0.010.11101001000
Perc
en
t P
assin
g
Particle Size (mm)
20040103/8" 41/2"3/4"3"12" 6" 1" 30 508 16
Sieve Analysis Hydrometer Analysis
Sieve Opening in Inches U.S. Standard Sieves Size of Particles in mm
1002"
Drawn By: JMPI 6
Sample ID: P-2
Project No.: 219-061 Sample
Description:CLAY, silty, sandy (CL-ML)
Checked By: SWRFigure No.: C-10
Fines (%) 58SIEVE ANALYSIS
Sample
Depth (ft.):2.0
#200 58
Gravel (%) 6 LL 23 Project Name:FRT-18.5-K.99 Bridge
Replacement Yeh & Associates, Inc. Geotechnical Engineering Consultants
Sand (%) 36 PL 17
#4 94
#10 89
#40 82
¾ " 100
½" 99
⅜" 99
2" -
1 ½" -
1" -
Sieve
Size
%
Passing
3" -
2 ½" -
0
10
20
30
40
50
60
70
80
90
100
0.010.11101001000
Perc
en
t P
assin
g
Particle Size (mm)
20040103/8" 41/2"3/4"3"12" 6" 1" 30 508 16
Sieve Analysis Hydrometer Analysis
Sieve Opening in Inches U.S. Standard Sieves Size of Particles in mm
1002"
FRT-18.5-K.99 Replacement Bridge Yeh Project No. 219-061 Boring A-1
Core Photos Page C-1 of C-8
20.0 feet to 30.0 feet, Box 1 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No. 219-061 Boring A-1
Core Photos Page C-2 of C-8
30.0 feet to 40.0 feet, Box 2 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No. 219-061 Boring A-1
Core Photos Page C-3 of C-8
40.0 feet to 490.0 feet, Box 3 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No. 219-061 Boring A-1
Core Photos Page C-4 of C-8
49.0 to 51.5 feet, Box 4 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No.219-061 Boring A-2
Core Photos Page C-5 of C-8
16.0 feet to 26.0 feet, Box 1 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No.219-061 Boring A-2
Core Photos Page C-6 of C-8
26.0 to 35.0 feet, Box 2 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No.219-061 Boring A-2
Core Photos Page C-7 of C-8
35.0 feet to 43.5 feet, Box 3 of 4
BORING
FRT-18.5-K.99 Replacement Bridge Yeh Project No.219-061 Boring A-2
Core Photos Page C-8 of C-8
43.5 feet to 51.5 feet, Box 4 of 4
END
50.3
BORING
Appendix D
ESALs and TRAFFIC LOADING CALCULATIONS
Traffic Loading Calculations
Traffic volume based on information received 04/25/2019 from TH Engineering/Mesa County
18.5 Road between L Road and M Road
1400
20-Year Factor = 1.24
from CDOT data for CR 13 (SH 139A)
1400 X 1.24 = 1736
Design Volume = (ADT + 20-Yr ADT)/2 =
(101+126)/2 = 1568
No vehicle type volumes were provided by client. Vehicle type volumes were assumed,
with trucks evenly split between single units and combination units (semi's).
Design
Vehicle Volume Percent ESAL 20-Year
Type ADT Volume Factor* days/yr years ESALs
Cars & PU 1568 0.90 0.003 365 20 = 30905
Single Units 1568 0.05 0.249 365 20 = 142508
Comb Units 1568 0.05 1.087 365 20 = 622112
Total 20-Year ESALs = 795525
*ESAL Factor from CDOT 2014 Pavement Design Manual
Design Lane Factor for 2-Lane Roads = 0.6
Total 20-Year Design ESALs = 477315
65
Estimated ADT:
Total 20-Year Design EDLA =
Proposed FRT-18.5-K.99 Bridge Replacement
Mesa County, Colorado Project No. 219-061
1 of 1
Appendix E
PAVEMENT DESIGN
Page 1
1993 AASHTO Pavement Design
DARWin Pavement Design and Analysis System
A Proprietary AASHTOWare
Computer Software ProductYeh & Associates, Inc.
Flexible Structural Design Module
FRT-18.5-K.99 Bridge Replacement
Fruita, Mesa County, Colorado
Yeh Project No. 219-061
Flexible Structural Design
18-kip ESALs Over Initial Performance Period 477,315
Initial Serviceability 4.5
Terminal Serviceability 2
Reliability Level 95 %
Overall Standard Deviation 0.44
Roadbed Soil Resilient Modulus 4,627 psi
Stage Construction 1
Calculated Design Structural Number 3.61 in
Specified Layer Design
Layer Material Description
Struct
Coef.
(Ai)
Drain
Coef.
(Mi)
Thickness
(Di)(in)
Width
(ft)
Calculated
SN (in)
1 HMA 0.44 1 6 12 2.64
2 ABC Class 6 0.12 1 9 12 1.08
Total - - - 15.00 - 3.72
FRT-18.5-K.99 Bridge Replacement Yeh Project 219-061
Fruita, Mesa County, CO
Appendix E
Asphalt Binder Selection Data
Five Closest Weather Stations
“Fruita 1 w” Weather Station