final project reliability & process quality - lj (revi a. ; arfittariah ; arief b.)
TRANSCRIPT
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 1/21
FI NAL PROJECT
RELI ABI L I TY AND PROCESS QUALI TY
Evaluation of Reli abil ity, Maintainabili ty, and Safety In H igh Pressure Separator V-101
Area Hydrofini shing Unit PT. AGIP
RELI ABIL I TY ENGINEER :
Revi Adikhari sma NRP. 2412105021
Ar fi ttariah NRP. 2412105020
Ar ief Budhiyono NRP. 2412105018
DEPARTMENT OF ENGINEERING PHYSICS
FACULTY OF INDUSTRIAL TECHNOLOGY
SEPULUH NOPEMBER INSTI TUTE OF TECHNOLOGY
SURABAYA
2013
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 2/21
I . PIPING AND INSTRUMENTATION DIAGRAM
I I . HIGH PRESSURE SEPARATOR V-101
2.1 Process Description
High Pressure Separator is a unit that served as a separator two phase or three phase
such as oil, water, and gas. In the area of 100 - hydrofinishing unit in the recycle section,
high pressure separator separates the gas phase and liquid phase which will be passed to
the next process. Inputs that go into the high pressure separator comes from refining
reactor. Gas phase will be forwarded to the washing water receiver, while the liquid phaseis passed to the stripper.
At high pressure separator where the control loop there is a controlled flow and level. For there is a level loop LT1008 and an electrical signal is passed to LIC1008. Of LIC1008,
will be forwarded to FIC1002 where the system is a cascade system. For the inputs that go
into FIC1008 also obtained from FE1002 and FT1002 that sense of flow in the pipe. Signal
indicating that the controller has entered into will be continued to the I / P ie FY1002 in the
form of electrical signals and converted to pneumatic signal to command flow control valve.
Here is a flow control valve normally open or fail close.
In the unit there is also a protection system with sensors LSLL1010. Where the signal
of LSLL1010 which will be forwarded to an alarm LALL1010 from the system. Unsafe level
readings are also accepted by XY1010 solenoid valve to shut - off valve on XV1010 order
flow from high pressure liquid phase separator does not continue to flow and keep the level so it is not in a state of low - low.
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 3/21
2.2 I /O Equipment L ist
NO TAG SYMBOL DESCRIPTION
1 LG 1008 LEVEL GLASS
2 LT 1008 LEVEL TRANSMITTER
3 LIC 1008 LEVEL INDICATING CONTROLLER
4 FIC 1002 FLOW INDICATING CONTROLLER
5 FT 1002 FLOW TRANSMITTER
6 FE 1002 FLOW ELEMENT
7 FY 1002 I/P
8 FCV 1002 FLOW CONTROL VALVE
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 4/21
9 LSLL 1010 LEVEL SWITCH LOW LOW
10 LALL 1010 LEVEL ALARM LOW LOW
11 XY 1010 SOLENOID VALVE
12 XV 1010 ON-OFF VALVE
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 5/21
I I I . MAI NTENANCE DATA AND RELI ABIL I TY DISTRIBUTION
3.1 Maintenance Data of HP Separator V-101
LT – 1008
Occurence
Date
Occurence
Time
Completion
Date
Completion
Time
TTF
(Day) TTF (Hours)
TTR
(Hours)
3-Oct-06 7:00:00 3-Oct-06 7:00:00 0 0 0
5-Nov-06 3:00:00 9-Nov-06 11:00:00 33 792 104
7-Jan-07 16:00:00 11-Jan-07 15:00:00 59 1416 95
2-Mar-07 9:00 8-Mar-07 20:00 50 1200 155
17-May-07 15:00 20-May-07 16:00 70 1680 73
10-Jul-07 11:00:00 13-Jul-07 21:00:00 51 1224 82
20-Jul-07 21:00:00 25-Jul-07 15:00:00 7 168 114
9-Aug-07 16:00:00 10-Aug-07 14:00:00 15 360 22
13-Aug-07 20:00:00 16-Aug-07 21:00:00 3 72 73 12-Oct-07 9:00 16-Oct-07 15:00 57 1368 102
MTTF 828
Parameter Weibull : α = 1.4539 ; β = 1003.2 ; γ = 0
Probability Density Function
Histogram Weibull
x16001400120010008006004002000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 6/21
Parameter Normal : σ = 629.95 ; μ = 828
Probabil ity Density Function
f (1000) =
( ) = 0,00039
LIC – 1008
Occurence
Date
Occurence
Time
Completion
Date
Completion
Time
TTF
(Day)
TTF
(Hours)
TTR
(Hours)
4-Feb-06 13:00:00 4-Feb-06 13:00:00 0 0 0
18-May-06 2:00:00 21-May-06 16:00:00 103 2472 86
28-Oct-06 7:00:00 29-Oct-06 2:00:00 160 3840 19
10-Jan-07 17:00:00 12-Jan-07 17:00:00 73 1752 48
16-May-07 13:00 23-May-07 15:00 124 2976 170
5-Jun-07 8:00 12-Jun-07 6:00 13 312 166
13-Jul-07 14:00 18-Jul-07 19:00 31 744 125
13-Oct-07 18:00:00 16-Oct-07 16:00:00 87 2088 70
26-Feb-08 17:00:00 2-Mar-08 15:00:00 133 3192 142 19-Mar-08 17:00:00 22-Mar-08 8:00:00 17 408 63
MTTF 1778.4
Probability Density Function
Histogram Normal
x
16001400120010008006004002000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 7/21
Parameter Weibull : α = 1.5794 ; β = 2190.5 ; γ = 0
Parameter Normal : σ = 1354.9 ; μ = 1778.4
Probabil ity Density Function
Probability Density Function
Histogram Weibull
x
36003200280024002000160012008004000
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Probability Density Function
Histogram Normal
x
36003200280024002000160012008004000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 8/21
f (1000) =
( ) = 0,00017
FIC – 1002
Occurence
Date
Occurence
Time
Completion
Date
Completion
Time
TTF
(Day)
TTF
(Hours)
TTR
(Hours)
9-Sep-06 21:00:00 9-Sep-06 21:00:00 0 0 0
18-Dec-06 5:00:00 21-Dec-06 20:00:00 100 2400 87
24-Feb-07 4:00:00 26-Feb-07 8:00:00 65 1560 52
10-Apr-07 21:00:00 12-Apr-07 19:00:00 43 1032 46 16-Jul-07 13:00 23-Jul-07 15:00 95 2280 170
5-Sep-07 9:00 12-Sep-07 6:00 44 1056 165
13-Dec-07 14:00 18-Dec-07 16:00 92 2208 122
13-Feb-08 15:00:00 16-Feb-08 16:00:00 57 1368 73
26-Jul-08 17:00:00 28-Jul-08 19:00:00 161 3864 50
1-Sep-08 16:00:00 12-Sep-08 6:00:00 35 840 254
MTTF 1660.8
Parameter Weibull : α = 2.1984 ; β = 2094.8 ; γ = 0
Probability Density Function
Histogram Weibull
x
3500300025002000150010005000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 9/21
Parameter Normal : σ = 1073.5 ; μ = 1660.8
Probabil ity Density Function
f (1000) =
( ) = 0,00021
FT – 1002
Occurence
Date
Occurence
Time
Completion
Date
Completion
Time
TTF
(Day)
TTF
(Hours)
TTR
(Hours)
7-Nov-06 7:00:00 7-Nov-06 7:00:00 0 0 0
3-Dec-06 8:00:00 12-Dec-06 11:00:00 26 624 219
3-Feb-07 13:00:00 11-Feb-07 21:00:00 53 1272 200
4-Apr-07 5:00 6-Apr-07 14:00 52 1248 57
21-Jun-07 21:00 24-Jun-07 17:00 76 1824 68
8-Aug-07 1:00:00 13-Aug-07 14:00:00 45 1080 133
25-Aug-07 18:00:00 27-Aug-07 15:00:00 12 288 45
6-Sep-07 18:00:00 10-Sep-07 14:00:00 10 240 92
18-Sep-07 15:00:00 24-Sep-07 21:00:00 8 192 150
2-Nov-07 1:00 16-Nov-07 15:00 39 936 350
MTTF 770.4
Probability Density Function
Histogram Normal
x
3500300025002000150010005000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 10/21
Parameter Weibull : α = 1.6314 ; β = 956.71 ; γ = 0
Parameter Normal : σ = 594.1 ; μ = 770.4
Probabil ity Density Function
Probability Density Function
Histogram Weibull
x
150010005000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
Probability Density Function
Histogram Normal
x
150010005000
0.44
0.4
0.36
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 11/21
f (1000) =
( ) = 0,0004
FCV – 1002
Occurence
Date
Occurence
Time
Completion
Date
Completion
Time
TTF
(Day)
TTF
(Hours)
TTR
(Hours)
7-May-06 2:00:00 7-May-06 2:00:00 0 0 0
14-Sep-06 21:00:00 15-Sep-06 21:00:00 130 3120 24
30-Nov-06 20:00:00 30-Nov-06 16:00:00 76 1824 20
11-Jan-07 14:00:00 19-Jan-07 1:00:00 42 1008 179
7-Feb-07 20:00:00 9-Feb-07 5:00:00 19 456 33
8-Apr-07 16:00 13-Apr-07 15:00 58 1392 119
19-Apr-07 14:00 19-Apr-07 18:00 6 144 28 9-Jun-07 21:00 12-Jun-07 16:00 51 1224 67
11-Sep-07 20:00:00 13-Sep-07 10:00:00 91 2184 38
2-Dec-07 3:00 7-Dec-07 21:00 80 1920 138
MTTF 1327.2
Parameter Weibull : α = 1.6616 ; β = 1637.0 ; γ = 0
Probability Density Function
Histogram Weibull
x
300025002000150010005000
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 12/21
Parameter Normal : σ = 976.59 ; μ = 1327.2
Probabil ity Density Function
f (1000) =
( ) = 0,00025
3.2 System Reliabil ity of HP Separator V-101
In the picture above can be seen that the system is a serial (LT - LIC and FT - FIC)
which both can be considered parallel and then forwarded to the FCV to be serial. Weconclude if that system is serial systems.
Probability Density Function
Histogram Normal
x
300025002000150010005000
0.32
0.28
0.24
0.2
0.16
0.12
0.08
0.04
0
FCV
LIC
FIC
LT
FT
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 13/21
Cumulative Distribution Function
LT – 1008
F (1000) =
= 0,57
R(1000) = 1 – F(t)
= 1 - 0,57 = 0,43
LIC – 1008
F (1000) =
= 0,36
R(1000) = 1 – F(t)
= 1 - 0,36 = 0,64
FIC – 1002
F (1000) =
= 0,35
R(1000) = 1 – F(t)
= 1 - 0,35 = 0,65
FT – 1002
F (1000) =
= 0,59
R(1000) = 1 – F(t)
= 1 - 0,59 = 0,41
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 14/21
FCV – 1002
F (1000) = = 0,42
R(1000) = 1 – F(t)
= 1 - 0,42 = 0,58
Total System Reli abil ity for 1000 hours
R (t) = ( R (LT) . R (LIC)) + (R(FT) . R(FIC)) . R(FCV)
= (0,43 . 0,64) + (0,41 . 0,65) . 0,58 R(1000) = 0, 31
Reli abili ty for 720 Hours, 4320 Hours, and 8640 Hours
LT – 1008
F (720) =
= 0,46
R(720) = 1 – F(t)
= 1 - 0,46 = 0,54
F (4320) =
= 0,99
R(4320) = 1 – F(t)
= 1 - 0,99 = 0,01
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 15/21
F (8640) =
= 0,99
R(8640) = 1 – F(t)
= 1 - 0,99 = 0,01
LIC – 1008
F (720) =
= 0,31
R(720) = 1 – F(t)
= 1 - 0,31 = 0,69
F (4320) =
= 0,86
R(4320) = 1 – F(t)
= 1 - 0,86 = 0,14
F (8640) =
= 0,99
R(8640) = 1 – F(t)
= 1 - 0,99 = 0,0,01
FIC – 1002
F (720) = = 0,29
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 16/21
R(720) = 1 – F(t)
= 1 - 0,57 = 0,71
F (4320) =
= 0,92
R(4320) = 1 – F(t)
= 1 - 0,92 = 0,08
F (8640) =
= 0,99
R(8640) = 1 – F(t)
= 1 - 0,99 = 0,01
FT – 1002
F (720) =
= 0,48
R(720) = 1 – F(t)
= 1 - 0,48 = 0,52
F (4320) =
= 0,99
R(4320) = 1 – F(t)
= 1 - 0,99 = 0,01
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 17/21
F (8640) =
= 0,99
R(8640) = 1 – F(t)
= 1 - 0,99 = 0,01
FCV – 1002
F (720) = = 0,34
R(720) = 1 – F(t)
= 1 - 0,34 = 0,66
F (4320) = = 0,96
R(4320) = 1 – F(t)
= 1 - 0,96 = 0,04
F (8640) =
= 0,99
R(8640) = 1 – F(t)
= 1 - 0,99 = 0,01
From the simulation results by taking the example of 720 hours, 4320 hours and 8640 hours
can be seen that the reliability of each equipment will decrease. it can be seen from the value of
R at the time of 720 hours to 4320 hours to 8640 hours onwards decreased. so the longer it is
used, the level of reliability of the equipment will decrease and result in damage.
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 18/21
IV . FAI LURE MODE AND EFFECT ANALYSIS (FMEA)
No I tem
Potential
failure
mode
Potential
effect of the
failure Severity Probability
(occurence) Critical
rank Recommended
Action
1
LevelTransmitter LT-1008
Degradationof rangereading
Level tank
over highand allowexplosion II 2 / B 1
Check andcalibrationtransmitter
2
Level Indicating
Controller LIC-1008
Manufactingdefect
Cannottransmit
signal to
FICnormally III 4 / D 3
Check signalcable
3
Flow IndicatingController FIC-1002
Wrong signal
Cannot givecommand to
FCV II 3 / C 4 Check signal
cable
4
FlowTransmitter
FT-1002 Failed to
flow sensing
Cannottransmit processvariable present
value III 1 / A 4
Check andcalibration
transmitter
5
FlowControlValve
FCV-1002
Positioner stuck/ failed
open(premature
open)
Over pressureand allowexplosion I 5 / E 1
Check postioner ordiaphragma
valve
Notes :
High Risk
Medium Risk
Low Risk
Can be seen from the the above table that the level transmitter failed degradation of
range reading which will cause the tank level will be high and could explode. For the severity
level is II, occurence probability 2/B, critically rank 1. Recommended action is to check and
calibration transmitter. Level indicating controller failed manufacturing defect which will cause cannot transmit
signal to flow indicating controller. For the severity level is III, occurence probability 4/D,
critically rank 3. Recommended action is to check signal cable
Flow indicating controller failed wrong signal which will cause cannot give command to
flow control valve. For the severity level is II, occurence probability 3/C, critically rank 4.
Recommended action is to check signal cable.
Flow transmitter failed to flow sensing which will cause cannot transmit process variable
present value. For the severity level is III, occurence probability 1/A, critically rank 4.
Recommended action is to check and calibration transmitter.
Flow Control Valve failed positioned stuck or failed open which will cause over pressure
and allow explosion. For the severity level is I, occurence probability 5/E, critically rank 1. Recommended action is to check positioned or diaphragma valve.
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 19/21
V . FAULT TREE ANALYSIS (FTA)
In the picture above can be seen that the top event is the state failed to separated which is
caused by over-pressure, gas dehydrator trip, and flow turbulence. Three are the logical choice for the top event. After that is below the over-pressure basic events such as pump impeller was
broken and the control valve to fail closed with OR logic. For gas dehydrator is caused by over-
temperature, fluid viscosity, and safety devices not work with OR logic. Different with flow
turbulence events caused by three causes the friction on the pipe, shear induced structure, and
pipe leakage where the three cause have an AND logic.
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 20/21
VI . RELI ABIL ITY UNDER PREVENTIVE MAINTENANCE (MAI NTAINABIL ITY)
With T =30 days ; n = 1
FT 1002
No T R(t) R(t-nT) Rm(t)
β θ No PM PM Cumulative PM
1 0 hours 1 0 0, 991,63 957
2
720
hours 0,52 1384,6 0, 851,63 957
3
1000
hours 0,41 2439 0, 821,63 957
4
4320
hours 0,01 432000 0, 77
1,63 957
5
8640
hours 0,01 864000 0, 601,63 957
FCV 1002
No T R(t) R(t-nT) Rm(t)
β θ No PM PM Cumulative PM
1 0 hours 1 0 0, 991,66 1637
2
720
hours 0,66 1090,9 0, 921,66 1637
3
1000
hours 0,58 1724,1 0, 881,66 1637
4
4320
hours 0,04 108000 0, 861,66 1637
5
8640
hours 0,01 864000 0, 801,66 1637
8/13/2019 Final Project Reliability & Process Quality - LJ (Revi a. ; Arfittariah ; Arief B.)
http://slidepdf.com/reader/full/final-project-reliability-process-quality-lj-revi-a-arfittariah-arief 21/21
VII . ISHI KAWA DIAGRAM