final report - surrey...surrey county council southern rail access to heathrow final report final |...
TRANSCRIPT
Surrey County Council
Southern Rail Access to Heathrow
Final Report
Final | 21 December 2016
This report takes into account the particular
instructions and requirements of our client. It is not intended for and should not be relied
upon by any third party and no responsibility is
undertaken to any third party.
Job number 227787-60
Ove Arup & Partners Ltd 13 Fitzroy
Street London W1T 4BQ United
Kingdom
www.arup.com
Document Verification
Job title Southern Rail Access to Heathrow Job number
227787-60
Document title Final Report File reference
4-05 Arup Reports
Document ref
Revision Date Filename Draft Report.docx
Draft 1 16 Sep Description Initial draft for discussion
2016
Prepared by Checked by Approved by Farnaz Jahanshahi
Name Emma Forde Ian Hood Stephen Bennett
Toby Hetherington
Signature
Draft 2 18 Nov Filename Surrey SRAtH - Draft Report.docx
2016 Description First formal draft
Prepared by Checked by Approved by
Farnaz Jahanshahi
Name
Emma Forde Stefan Sanders Stephen Bennett
Toby Hetherington
Edward Dawes
Signature
Final 21 Dec Filename Surrey SRAtH – Final Report.docx
2016 Description Final report
Prepared by Checked by Approved by
Name Edward Dawes Toby Hetherington Stephen Bennett
Signature
Final Filename Description
Prepared by Checked by Approved by
Name
Signature
Issue Document Verification with Document
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY
SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Contents
Page
Executive Summary 4
1 Background and Context 7
1.1 Scope of Study 7
1.2 Study Approach 8
1.3 Stakeholder Engagement 9
2 Existing Situation 10
2.1 Connections 10
2.2 Accessibility 10
2.3 Mode Share 13
2.4 Issues for Surrey 15
3 Strategic Vision for Surrey 16
3.1 Development objectives 16
3.2 Opportunities 16
3.3 Strategic Vision for Heathrow Surface Access 18
4 Infrastructure Options and Costs 19
4.1 Option 1 – Western Alignment and Staines Chord 19
4.2 Option 1c – Western Alignment and Staines Chord with LX Removal 22
4.3 Option 2 – Egham Tunnel 23
4.4 Option 3 – Chertsey Link 24
4.5 Option 4 – Eastern Alignment 25
4.6 Other SRAtH Studies 25
4.7 Summary of Rail Infrastructure Options 29
4.8 Additional Infrastructure Option 31
4.9 Supporting Infrastructure Scheme Requirements 33
5 Capacity and Service Options 35
5.1 Current Situation 35
5.2 SRAtH Train Service Options 40
5.3 Alternative Service Options 44
5.4 Cross Heathrow Connections 49
6 Demand Assessment 51
6.1 Network Rail Demand Forecasts 51
6.2 Demand from Surrey 51
6.3 Future Growth 53
6.4 Demand beyond Heathrow from Surrey 56
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
6.5 Validation of Network Rail Forecasts 60
7 Option Assessment 62
7.1 Value for Money 64
7.2 Summary of Options 65
7.3 Scheme Funding 67
8 Conclusions and Recommendations 68
8.1 Conclusions 68
8.2 Recommendations 70
Tables
Table 1: Other SRAtH Studies Summary Table .................................................... 28
Table 2: Infrastructure Options Summary ............................................................. 29
Table 3: Arup Cost Estimates ................................................................................ 31
Table 4: Comparison of Cost Estimates between Arup's cost point estimate and the Network Rail study range estimate. ................................................................. 31 Table 5: Comparison of current outer Windsor Line services to that in the ITT for the next South Western franchise. ......................................................................... 37
Table 6: Plain Line Planning Capacity Utilisation of Existing Infrastructure ....... 37
Table 7: Infrastructure and Train Service Combinations ....................................... 40
Table 8: Intermediate Station Stopping Pattern by Option .................................... 44
Table 9: Population Growth in Surrey. Source: TEMPRO data based on ONS 2008-based population projections ....................................................................... 54
Table 10: Heathrow Passenger Forecasts (mppa) – 2014-2050 ............................ 54 Table 11: Passenger and Employee Forecasts for Heathrow Northwest Runway . 55 Table 12: Annual Passenger and Employee Forecasts from Surrey ...................... 56 Table 13: Surrey Residents Commuting to London. Source: 2011 Census Data . 57
Table 14: Journey Time Comparison to Central London via London Waterloo vs
via London Paddington (Morning Peak Hour) ...................................................... 59
Table 15: Commentary on Network Rail forecasts ............................................... 60
Table 16: Option Assessment Summary Table...................................................... 63
Table 17: Option Scoring Summary Source: Arup analysis .................................. 64
Table 18: London/Surrey Benefit Cost Ratio Comparison .................................... 65
Figures
Figure 1: Study Approach ........................................................................................ 8
Figure 2: Surrey Rail Map. Source www.surreycc.gov.uk ..................................... 10
Figure 3: Heathrow Journey Time Mode Comparison. Source: DfT Connectivity Data ................................................................................................................... .... 11
Figure 4: Journey time to Heathrow by Car (AM PEAK) Source: DfT Connectivity Data ..................................................................................... ............. 12
| Final | 21 December 2016 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Figure 5: Journey time to Heathrow by Public Transport (AM PEAK) Source: DfT Connectivity Data ..................................................................................................12 Figure 6: Modal composition of trips to Heathrow from Surrey ...........................13 Figure 7: Variations in airport trips mode share by locality ..................................14 Figure 8: Opportunities for Strategic Connections with SRAtH. Source: http://www.projectmapping.co.uk/Resources/London%20Rail%20v30.pdf ..........17 Figure 9: Option 1a and Option 1b: Staines Chord................................................20 Figure 10: Egham Level Crossings ........................................................................21 Figure 11: Option 2 Egham Tunnel .......................................................................23 Figure 12: Option 3 Chertsey Link ........................................................................24 Figure 13: Option 4 Eastern Alignment .................................................................25 Figure 14: Indicative London Borough of Hounslow alignment ...........................27 Figure 15: All NR Options .....................................................................................30 Figure 16: Option 2b/3b Weybridge Chord ...........................................................32 Figure 17: Schematic Weybridge station track layout diagram. Adapted from
source www.networkrail.co.uk ...............................................................................33 Figure 18: Current Outer Windsor Lines Train Service Map for high peak hour arrivals to London Waterloo, excluding inner Windsor Line services. .................36 Figure 19: Weybridge Chord option indicative schematic train service map. .......45 Figure 20: Surrey Service Enhancement (with Option 3) indicative schematic train service map. ...........................................................................................................46 Figure 21: Total Passengers per year from Surrey districts using Heathrow Airport. Source: CAA Survey Data, 2012 ..............................................................52 Figure 22: Heathrow Airport Employee Mode Share. Source: Heathrow Airport
Employee Survey Data, 2011 .................................................................................53 Figure 23: Heathrow Northwest Runway Proposal. Source: Taking Britain Further – Summary, May 2014 ..............................................................................55 Figure 24: Commuter Destinations from Surrey to London Boroughs. Source: 2011 Census Data ..................................................................................................58 Figure 25: Annual Heathrow Demand vs London Commuting Demand from
Surrey .....................................................................................................................61
Appendices
Appendix A
Arup Cost Estimates
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Executive Summary
The key issues for surface access to Heathrow Airport from Surrey are that:
Car is the quickest mode of access to Heathrow from all towns in Surrey, with journey times on average ~40% faster than the equivalent journey by public transport. However, car journey times are unreliable due to high-levels of congestions especially during peak hours.
Rail journey times to Heathrow are often over double that of the
equivalent car journey and in many districts in Surrey there is no viable rail alternative to the car/taxi;
As a result, car and taxi remain the dominant modes for passenger and employee trips to Heathrow airport from Surrey, contributing to congestion on the local and strategic road networks. This congestion creates pollution from road transport that affects air quality as well as creates implications for road safety.
The scope of this study is to use existing empirical evidence in order to robustly
assess options for the provision of a rail connection between the South West rail network and London Heathrow Airport, as outlined in Network Rail’s “Southern
Rail Access to Heathrow Feasibility Study” report published in December 2015.
It reviews the core options assessed in the Network Rail report alongside other southern rail access proposals and comments on whether the key statements and claims are reasonable.
The outputs are advice and recommendations to Surrey County Council (SCC) on the preferred infrastructure and service pattern combinations that should be
considered for further development. The conclusions of our review, informed by engagement with key stakeholders, are provided below.
The Southern Rail Access scheme supports Surrey’s rail
development objectives
Overall, SRAtH supports Surrey’s rail development objectives by enabling:
A fast and direct rail link to the airport from Surrey that increases its attractiveness as a prime location for global and national businesses;
Connectivity between the county and the 70,000 jobs that exist in and around
the airport, helping to further drive economic growth; An alternative to road-based modes for travel to the airport, helping to
reduce the number of vehicles using the road network which would significantly improve localised air quality; and
An improved public transport linkage and increases in county rail capacity
that helps to accommodate sustainable population growth.
| Final | 21 December 2016 Page 4 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
However in developing and supporting the SRAtH scheme, it is important to ensure that it can be demonstrated to provide good value for money, be affordable to public and private stakeholders, and have acceptable impacts in Surrey.
Specific outputs are required from the Southern Rail
Access scheme
Our review of previous studies indicates that the following outputs should be achieved in order to fully meet Surrey’s rail development objectives:
New rail infrastructure between the South Western rail network and Heathrow Airport that provides for direct rail services between Surrey and Heathrow Airport;
Fast and frequent rail services between Surrey and Heathrow Airport, with fast
defined as reliable journey times between Woking and Heathrow of 30 minutes or less, and frequent defined as four trains per hour;
Potential to run directly beyond Heathrow to Old Oak Common (for
interchange to HS2 in future) and to London Paddington (for connectivity to central London); and
Sufficient stopping points in Surrey to provide convenient access for
travellers to Heathrow from all parts of the county.
There are options that have the potential to deliver these outputs
for Surrey
Based on the available information from the different studies, there are infrastructure / service option combinations that appear to have the potential achieve the outputs identified above.
The option that appears to have the best overall business case and benefits for Surrey is Option 1c Western Alignment plus Staines Chord with the Egham level crossings removed or replaced. This is because it has:
The lowest cost infrastructure solution; The potential to be delivered incrementally (i.e. the link to Heathrow and
Staines Chord can be delivered first, providing 2tph to Surrey in the peak period and 4tph off peak, and this can be increased to 4tph in the peak when the level crossings are removed or replaced;
The potential to operate a range of service options that best serve key areas
of Surrey/Hampshire and unlocking further potential for growth; A mix of fast and semi-fast services (exact stopping points to be determined);
and A potential new connection to London Paddington with competitive journey
times to existing London Waterloo services.
An alternative option is the Heathrow Southern Rail scheme which has a higher cost but potential to also have a good business case and provide similar benefits to
| Final | 21 December 2016 Page 5 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Surrey. This option uses the same infrastructure as Network Rail option 3, but the
service pattern has faster services to Heathrow (non-stop from Woking) and runs
beyond Heathrow to Old Oak Common and London Paddington. This scheme:
Avoids level crossing issues completely; Provides fast service patterns to Heathrow and beyond; and Has higher costs due to the viaduct route, but could potentially offer good
value for money if journey time improvements are substantial over the long.
This option does have limited connectivity to stations within Surrey, due to the
reliance on the operation of limited-stop service patterns. This could can be
resolved by assessing the potential for additional station stops and to more
precisely ascertain what effect these would have on overall scheme value for
money and service journey times. A review should also be undertaken into
whether a viaduct or tunnel would be the best type of infrastructure for this
option, taking into account land impacts and mitigation costs.
There is a need for further testing of these options on a consistent
basis
One of the issues from our review is that the infrastructure options have been
tested with different service pattern options. For example, Network Rail generally
tested infrastructure options with stopping services to Heathrow whereas
Heathrow Southern Rail tested infrastructure options with fast services to
Heathrow and beyond. Both parties used different assessment tools and this is
reflected in the range of benefit cost ratios reported in the option assessment.
The infrastructure/service options identified above need to be tested on a
consistent basis so that infrastructure options can be consistently compared using similar service patterns, and service patterns can be optimised using
consistent infrastructure options. This means using the same demand forecasting tool and the same service patterns for different infrastructure options.
Given the above, our recommendations for Surrey County Council are as follows:
Engage with stakeholders to build support for the SRAtH scheme – this includes Surrey County Council political leadership, Surrey boroughs and districts as well as neighbouring authorities (e.g. Hampshire) and relevant LEPs);
Promote supporting schemes needed to enable SRAtH – the schemes
identified in this report required to enable SRAtH, such as Woking flyover and station improvements, as these also have a benefit for main line services to Waterloo;
Engage with scheme promoters to undertake further development of
SRAtH options – this would include testing and assessment of the options
identified in our conclusions on a consistent basis to determine the optimum infrastructure and service combination for Surrey. This may require Surrey and its stakeholders to commission this work themselves.
| Final | 21 December 2016 Page 6 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
1 Background and Context
The Surrey Rail Strategy was completed and published in September 2013. The
Rail Strategy enables Surrey County Council (SCC) to understand how best to
influence key decision makers in the rail industry, to develop its thinking on
credible investments in rail infrastructure, and to make the best case for
investment in local rail infrastructure. The ultimate objective is to secure the
required investment in the county’s rail network aligned with the overarching
development objectives for Surrey. The priority options identified in the Surrey
Rail Strategy include promoting a future direct rail access solution to Heathrow
Airport from Surrey.
In October 2013, Arup completed a study into Surface Access to Airports for SCC. The objective of the study was to identify proposals for strategic investment that the County Council, working with partners, could plan and deliver.
The study recommended short-medium term actions which focused on reducing
car and taxi trips to the airports, developing express bus services to both Heathrow
and Gatwick airports, and optimising existing rail services to Gatwick airport on the North Downs Line.
In the long term, recommended actions included further enhancement of the
express bus network, engaging with stakeholders to develop southern rail access to Heathrow Airport, developing an upgrade of the North Downs Line, and
supporting these measures with marketing and awareness campaigns.
In the Airport Commission’s Interim Report (December 2013), it recommended
that the Government should work with Network Rail to undertake a detailed study
to find the best option for enhancing rail access into Heathrow from the south to
encourage modal shift towards more environmentally sustainable forms of
transport at Heathrow as well as to optimise the airport’s operations within its
current capacity constraints.
Network Rail completed a feasibility study in December 2015 to identify potential
market, train service and infrastructure options for a connection to Heathrow Airport from the south to enable potential funders to decide as to whether further
development work should be undertaken on the scheme.
1.1 Scope of Study
SCC commissioned Arup to review the Network Rail proposals for a southern rail connection to Heathrow Airport and advise on the preferred option(s) that should be supported.
The outcome of this study will be used by SCC to engage with key stakeholders such as the Department for Transport (DfT), Network Rail, Heathrow Airport
Limited, and local stakeholders such as businesses and borough and district
councils to secure the best outcome for Surrey in terms of connectivity to Heathrow Airport.
| Final | 21 December 2016 Page 7 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
This study also considers the context of previous work completed as part of
the Airtrack and Airtrack-Lite projects as well as the work that Heathrow Southern Rail has been promoting and proposals developed by the London
Borough of Hounslow in relation to southern rail access to Heathrow.
The scope of this study is to use available data and reports to robustly assess the southern rail access to Heathrow Airport options undertaken by Network Rail and comment on whether their key statements and claims are reasonable.
The study also considers alternative options for southern rail access from Surrey to Heathrow and provides a high level assessment of their feasibility.
It should be noted that this study was largely completed before the Government’s announcement on a third runway at Heathrow in October 2016, so the impact of this announcement is not considered in detail in the assessment.
1.2 Study Approach
We have developed a high-level strategic approach, proportionate to the scale of the study, which identifies and assesses the preferred options (s) for southern rail access to Heathrow Airport. The study approach is illustrated in Figure 1.
Figure 1: Study Approach
Chapter 1: Background and Context
Scope of Study Study Approach Stakeholder Engagement
Chapter 2: Existing Situation
Connections Accessibility Mode Share Issues for Surrey
Chapter 3: Strategic Vision for Surrey
Development Objectives Opportunities Strategic Vision
Chapter 4: Infrastructure Options and Costs
Options 1- 4 Other Studies Options Summary Additional Options
Chapter 5: Capacity and Service Options
Current Situation Service Options Alternative Options Cross-Heathrow
Chapter 6: Demand Assessment
Demand Forecasts Demand from Surrey Future Growth Beyond Heathrow Validation
Chapter 7: Option Assessment
Value for Money Summary of Options Scheme Funding
Chapter 8: Conclusions and Recommendations Conclusions Recommendations
| Final | 21 December 2016 Page 8 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
1.3 Stakeholder Engagement
Local stakeholder engagement is an important part of this study to gain views on what access to Heathrow they would like to see. This includes assessing stakeholder views on the following issues:
Train service options;
Journey time vs station stops;
Options for dealing with level crossings; and
Alternatives to southern rail access (e.g. new park and ride facilities at M25 Junction 11 or Cobham services, Heathrow Hub proposals).
One-to-one consultation was carried out with Network Rail and Heathrow Southern Rail to fully understand their options and assessment.
Further consultation was undertaken through a half-day workshop, held on 8 November 2016. The stakeholder views expressed in the engagement are taken account of in our final recommendations.
The following stakeholders were consulted as part of this study:
SCC members;
SCC officers;
Surrey boroughs and districts;
Hampshire County Council;
Heathrow Airport Limited;
Heathrow Southern Rail;
London Boroughs: Hounslow, Wandsworth, Kingston, Richmond;
LEPs: Enterprise M3, Coast-to-Capital, Thames Valley;
Network Rail;
Stagecoach Rail; and
Transport for London.
| Final | 21 December 2016 Page 9 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
2 Existing Situation
2.1 Connections
Figure 2 shows the existing Surrey Rail network, with the South Western Network
(red) operating out of London Waterloo, to destinations in South West London via
Hounslow, Richmond and Wimbledon and onward suburban/regional services to
destinations in Surrey including Staines, Guildford, Woking, Dorking and
Haslemere. The majority of services operate onwards to destinations in Hampshire
and Dorset such as Basingstoke, Reading, Southampton, Portsmouth and
Salisbury.
Heathrow Airport is located to the north of the existing Waterloo – Reading and Waterloo – Windsor Lines between Feltham and Staines.
The airport is currently served by London Underground services on the Piccadilly Line, as well as Heathrow Express (fast) and Heathrow Connect (stopping) services using the Great Western Main Line from London Paddington.
There is currently no rail connection between the South Western rail network
and Heathrow. The map shows the route of the existing airport connection bus and coach services that operate from Woking and Feltham stations.
Figure 2: Surrey Rail Map. Source www.surreycc.gov.uk
2.2 Accessibility
Analysis was undertaken on the existing level of accessibility to Heathrow airport from Surrey by car and public transport (including bus/coach). Connectivity data
| Final | 21 December 2016 Page 10 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
from the Department for Transport (DfT) was used to identify the morning (AM)
peak journey times from each major rail station to the airport. The difference in journey times between each mode option were then calculated in order to identify
the extent of the existing constraints on access to Heathrow.
Connectivity data from the DfT was also compared against typical travel time ranges obtained from Google Traffic data.
The results showed that the fastest journey times were achieved by private car
from all of the destinations analysed. The car provided journey times to Heathrow
on average ~40% faster than the equivalent public transport journey. However,
due to severe congestion issues that exist on the local and strategic road network
surrounding the airport, the reliability of journey times by car remains poor, with
variations of nearly double the journey time in some cases.
Most of the public transport trips originating from stations within Surrey require
between 1-3 interchanges in order to reach Heathrow, which is likely to have a significant impact on overall journey times and deter people from using these
modes. The majority of rail-only trips to the airport require users to travel into and out of central London in order to pick up one of the existing airport services.
Figure 3: Heathrow Journey Time Mode Comparison. Source: DfT Connectivity Data
AM PEAK Highway Public Transport (08:00 – 09:00)
Journey time Journey time Journey time Interchanges
(mins) range
(mins)
required
Guildford 34 30-50 82 1
Woking 25 22-35 63 0
Epsom 44 40-80 98 3
Redhill 51 40-80 88 3
Staines 8 9-14 21 0
Farnham 42 35-60 120 1
Mapping the connectivity data by census output area is shown in Figure 4 and
Figure 5 and highlights the geographical coverage of differing accessibility
constraints for each mode choice. Most areas of the county can connect to
Heathrow within a 60 minute drive time, whereas by public transport most of the
county has a journey time of 120 minutes or greater. Journey times are improved
for areas within the major rail corridors, but are still significantly higher than that
of the equivalent car journey time from the same origin point.
| Final | 21 December 2016 Page 11 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Figure 4: Journey time to Heathrow by Car (AM PEAK) Source: DfT Connectivity Data
Figure 5: Journey time to Heathrow by Public Transport (AM PEAK) Source: DfT Connectivity Data
| Final | 21 December 2016 Page 12 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
2.3 Mode Share
As a result of the relatively poor public transport accessibility from Surrey to
Heathrow, car and taxi currently account for almost 89% of total mode share
for trips to the airport from the county. The remaining 11% percent is made up
by bus/coach services and rail. The higher percentage of bus and coach trips 7%
compared to rail trips 4%, highlights the lack of a suitable rail connection and
competitive journey times to the airport by rail. These proportions are shown in
Figure 6 below.
Figure 6: Modal composition of trips to Heathrow from Surrey
Bus & Coach
Rail 7%
4%
Car
51%
Taxi
38%
These modal shares however differ spatially across Surrey, reflecting differing
levels of access and choice to certain modes and direct airport connections. Car
(51%) is the dominant mode for trips to Heathrow from Surrey, followed by taxi
(38%). Surrey Heath (69%) and Waverley (59%) have the highest private car
mode share to Heathrow Airport. 53% of airport passengers who live in
Runnymede and 45% who live in Spelthorne districts use taxi to get to the
Airport. Rail use is significant in Reigate and Banstead (25%) and Tandridge
(19%) reflecting relatively good access via the Brighton Main Line to Victoria
and the Underground to Heathrow. Bus/coach use is significant in Woking (21%),
Waverley (14%) and Guildford (9%) districts where access to the Woking RailAir
service is convenient.
| Final | 21 December 2016 Page 13 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Figure 7: Variations in airport trips mode share by locality
| Final | 21 December 2016 Page 14 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
2.4 Issues for Surrey
Following the assessment of the existing situation, the key issues for surface access to Heathrow Airport from Surrey are considered to be:
Car is the quickest mode of access to Heathrow from all towns in Surrey, with journey times on average ~40% faster than the equivalent journey by public transport. However, car journey times are unreliable due to high-levels of congestions especially during peak hours.
Rail journey times to Heathrow are often over double that of the
equivalent car journey and in many districts in Surrey there is no viable rail alternative to the car/taxi.
As a result, car and taxi remain the dominant mode for passenger and
employee trips to Heathrow airport from Surrey, contributing to congestion on the local and strategic road networks. This congestion creates pollution from road transport that affects air quality as well as creates implications for road safety.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 15
Surrey County Council Southern Rail Access to Heathrow Final Report
3 Strategic Vision for Surrey
3.1 Development objectives
To ensure that the best solution for improving rail access to Heathrow from
Surrey is promoted by SCC it is important to consider the overall context of
Surrey’s long term vision for travel.
In the Surrey Rail Strategy, the four rail development objectives for Surrey were identified as:
1. Maintaining global competitiveness
2. Driving economic growth
3. Reducing impacts on the environment
4. Accommodating sustainable population growth
In the Surface Access to Airports Study, access to Heathrow Airport was assessed against the above objectives.
3.2 Opportunities
In addition to addressing existing and future issues and gaps, southern rail access
to Heathrow (SRAtH) opens up a number of opportunities for the county to improve connectivity and integration with other current and proposed public
transport services within London and its surrounds.
For example, SRAtH could provide the following strategic connection opportunities for Surrey:
Heathrow Express services to and from London Paddington.
Piccadilly Line services to Hammersmith, Earls Court and other destinations within the west end and north of London.
Elizabeth Line (Crossrail) services (from December 2019) providing
frequent and direct journeys into and across Central London while also allowing for better interchange with national rail services from London terminals.
High Speed 2 services to the Midlands and the North through a new
interchange hub at Old Oak Common, reducing the requirement to travel into central London to interchange between rail terminals.
Western Rail Access to Heathrow services could start operating between
Heathrow and Reading via the proposed western rail access link currently being developed by Network Rail providing travel opportunities to Slough, Maidenhead and Reading.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 16
Surrey County Council Southern Rail Access to Heathrow Final Report
Figure 8 shows how the SRAtH scheme could provide a strategic link between the existing South Western and Great Western networks as well as the Heathrow Express, Piccadilly Line and Elizabeth Line services into London.
Figure 8: Opportunities for Strategic Connections with SRAtH. Source: http://www.projectmapping.co.uk/Resources/London%20Rail%20v30.pdf
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 17
Surrey County Council Southern Rail Access to Heathrow Final Report
3.3 Strategic Vision for Heathrow Surface Access
Heathrow Airport is critically important to the Surrey economy in terms of both
passengers and employees. There were over 2 million passengers travelling to Heathrow Airport from Surrey in 2015, and it is estimated that over 10,000 Surrey
residents currently work at the airport.
It is clear that a strong market exists for surface access to the airport and should
therefore be a requirement to ensure that convenient and efficient access to the
airport is established in order to maintain and improve the county’s global
competitiveness for business and to sustain strong levels of economic growth.
The high levels of congestion on the existing local and strategic road networks
impact on road-based access to the airport (car, taxi, and bus/coach). In particular, the unreliability of journey times leads to lost time for individuals and businesses
who have to leave a greater time contingency for trips made in the peak.
There is therefore a significant case for a fast, direct and reliable public transport
link to the airport from Surrey. Both the Surrey Rail Strategy and the Surface Access to Airports Study concluded that Surrey County Council should support
the development of SRAtH in order to enable it to better meet its development
objectives outlined in section 3.1.
The strategic vision should therefore be to:
Support the provision of southern rail access to Heathrow airport from
Surrey to deliver a fast, direct and reliable public transport connection that
supports Surrey’s rail development objectives to maintain global
competitiveness, drive economic growth, reducing impacts on the
environment and accommodate sustainable population growth.
The SRAtH supports the county’s development objectives because it provides:
A fast and direct rail link to the airport from Surrey that increases its attractiveness as a prime location for global and national businesses.
Connectivity between the county and the 70,000 jobs that exist in and
around the airport, helping to further drive economic growth.
An alternative to road-based modes for travel to the airport, helping to reduce the number of vehicles using the road network which would significantly improve localised air quality.
An improved public transport linkage and increases in county rail capacity
that helps to accommodate sustainable population growth.
However in developing and supporting the SRAtH scheme, it is important to ensure that it can be demonstrated to provide good value for money, and be affordable to public and private stakeholders.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 18
Surrey County Council Southern Rail Access to Heathrow Final Report
4 Infrastructure Options and Costs
The following section reviews the infrastructure requirements for each option set
out in the Network Rail report1 and the proposals from Airtrack, Airtrack-Lite,
Heathrow Southern Rail and the London Borough of Hounslow. A summary is provided at the end of this section.
For each Network Rail option proposed (which offers direct access from the
airport to the south) Arup has developed an initial permanent way concept design
in order to develop high-level cost estimates for comparison with those in the
Network Rail report. It has not been possible to obtain detailed information from
Network Rail regarding their cost estimates and assumptions other than what has
been included the report.
The cost estimates developed are indicative and include a number of assumptions and clarifications. They do not consider the feasibility of construction for each
alignment and should be considered relative to each other in order to provide an indicative cost for each scheme. Details regarding each cost estimate and the
assumptions are outlined in Appendix A.
4.1 Option 1 – Western Alignment and
Staines Chord
Option 1a and Option 1b provides the minimum infrastructure required to establish a southern rail link to Heathrow T5 station. Option 1a only provides a
link towards London Waterloo whilst Option 1b provides a link towards the south, as shown in Figure 9.
1 Southern Rail Access to Heathrow Feasibility Study (Network Rail, December 2015).
| Final | 21 December 2016 Page 19 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Figure 9: Option 1a and Option 1b: Staines Chord
Option 1a comprises a new link between Heathrow T5 station and the Staines to
Windsor Line. From Heathrow T5 station box a double track alignment starting
in a tunnel and rising to surface level south of the M25 Junction 14 for
approximately 2300m has been assumed. The surface route follows the M25
alignment until diverging along the previous route of the Staines & West Drayton
Line towards the Wraysbury River, where the alignment joins the Staines to
Windsor Line. The junction to the existing network has been designed with an at-
grade double junction. Option 1a excludes the Staines chord towards the south.
In Option 1b, a new double track chord is included linking the Staines to Windsor
Line with the Waterloo to Reading Line south of Staines station in order to
provide rail access towards the south,. The new chord would require the
realignment of the A308, replacement of the entrance to Elmsleigh Shopping
Centre Car Park (replaced with a spiral type structure), redesign of the existing
bus station access, as well as realignment of the existing track in order to provide
an at-grade junction. The chord has been designed to miss A308 South Street as
much as possible.
The Network Rail cost estimate for Option 1a and 1b is between £800m and £950m, Arup’s cost estimate is £726m, slightly below the range presented in the Network Rail report. Although as noted in above we have not been provided with assumptions and cost details used in the Network Rail estimate.
4.1.1 Level Crossings
The level crossings within the Egham area are noted in the Network Rail report as being a significant constraint on rail capacity due to the impact of barrier down
| Final | 21 December 2016 Page 20 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
times when there is an increase in service levels. One of the major concerns raised
with the original Airtrack scheme was the impact on local road traffic with the increase level of rail services operating through the route. Option 1b could result
in increased barrier down times during off-peak hours whilst also offering a limited service during the peak hours as to avoid impact on road traffic.
Currently within the Egham area there is a total of six highway crossings of the
rail line west of the River Thames. The only unrestricted grade separated crossing
is provided by the M25 motorway. A further grade separated crossing is provided
by the A320 Chertsey Lane immediately to the west of the river although this has
a low bridge with 13’3” headroom restriction. Alternative routes for higher
vehicles are signposted via level crossings. Figure 10 shows the locations of the 4
level crossings in the Egham area.
Figure 10: Egham Level Crossings
Given the currently limited number of crossing points, there would likely be
substantial severance impacts should one or all of the level crossings be closed. This would result in significant trip diversion to alternative routes that are
potentially unsuitable for the purpose.
The Network Rail report does not explore the opportunities for replacement
and/or removal of the level crossings in the Egham area, although Network
Rail’s level crossing policy is to replace or close level crossings where possible.
Option 2 and 3 proposed in the Network Rail report instead look to avoiding the
Egham area, partially in order to avoid routing additional services over the level
crossings.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 21
Surrey County Council Southern Rail Access to Heathrow Final Report
4.2 Option 1c – Western Alignment and
Staines Chord with LX Removal
Due to the significant increase in costs for Option 2 and Option 3 compared to
Option 1 (~£500m difference) Arup has developed high-level cost estimates for
removal and/or replacement of the four level crossings in order to understand the
costs in comparison to Options 2 and 3. Removal of level crossings is presented
as Option 1c, and assumes Option 1a and Option 1b are included in order to
provide the link between Heathrow T5 and Surrey. The removal/replacement of
the level crossings could allow for enhancements to the level of service offered in
Option 1b and also offer performance improvements to the existing services as
well as aligning with Network Rail’s long term aspirations to close level crossings
on a long term national basis.
In order to develop a cost estimate for Option 1c the following additional
assumptions apply for each of the four level crossings in the Egham area (detailed feasibility and traffic surveys have not been carried out as part of this assessment):
Rusham level crossing is closed and replaced with new road bridge to the south of the existing crossing - requires realignment of highway.
Egham level crossing is closed and replaced with footbridge only. Traffic
to be diverted via outer routes. Any costs associated with diversions are excluded.
Pooley Green level crossing track lowered beneath highway to make it a
grade separate junction.
Thorpe Lane level crossing is closed and traffic diverted via outer routes. Any costs associated with diversions are excluded.
Based on the assumptions above the cost estimate for the closure/replacement of
the four level crossings is approximately £42m. Although this cost estimate has
been provided for the purposes of comparison, the cost estimate does not include
any compensation costs and or costs associated with the mitigation of traffic
impacts associated with closing/replacing the crossings. The replacement or
removal of level crossings in the Egham area, in terms of SRAtH is incremental to
the cost of Option 1a and 1b, however removal of the level crossings could be
staged with the delivery of Option 1a and Option 1b initially followed later by the
removal and replacement of the crossings.
Although there are some potentially significant assumptions which could affect the
cost estimate above, there is also a significant difference between the estimate and
the cost of the alternative infrastructure alignment presented in the Network Rail
report. Including Options 1a and 1b, Option 1c with the level crossing closure
estimate is £768m, this compares to the lowest cost estimate of Option 2 of £1.45bn.
Additional costs (including mitigation) that may be identified as part of a more
detailed crossing closure assessment would have to be in the order of around £700m
in order to impact on the comparable feasibility of Option 1c.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 22
Surrey County Council Southern Rail Access to Heathrow Final Report
4.3 Option 2 – Egham Tunnel
Network Rail’s Option 2 provides additional infrastructure with the objective of
avoiding the section of line between Staines and Egham where the four level
crossings exist. Figure 11 outlines the indicative alignment for Option 2 and how it
connects with the existing rail network towards Staines and Virginia Water.
Figure 11: Option 2 Egham Tunnel
From Heathrow T5 station the tunnel alignment is the same as for Option 1
including the at-grade connection onto the existing network near the Wraysbury
River. Option 2 provides an additional alignment to the south via a second tunnel
section with a tunnel portal to the north of the Staines to Windsor line. The tunnel
proceeds under Staines, Egham and the M25, re-surfacing to the east of the
existing rail network near Stroude Road, and connecting to the existing network
north of Virginia Water station.
The Network Rail cost estimate for Option 2 is between £1.4bn and £1.8bn, Arup’s cost estimate is £1.45bn, towards the lower end of the range presented in the Network Rail report.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 23
Surrey County Council Southern Rail Access to Heathrow Final Report
4.4 Option 3 – Chertsey Link
Option 3 provides additional infrastructure to that provided in Option 1 and 2 with
the objective of avoiding the section of line between Staines and Egham and improving journey times to services from the south. Figure 12 outlines the
indicative alignment for Option 3 and how it connects with the existing rail network towards Staines and Chertsey.
Figure 12: Option 3 Chertsey Link
From Heathrow T5 station the tunnel alignment is the same as for Option 1
including the at-grade connection onto the existing network near the Wraysbury
River. Option 3 provides an additional alignment towards the south on a viaduct
starting to the north of the Staines to Windsor Line for approximately 6.7km. The
viaduct crosses the Wraysbury River, existing rail network and the A30 then
proceeds alongside the M25 south of Wraysbury Road. Where the viaduct
approaches the M25 Junction 12 with the M3, realignment of the B388 Thorpe
bypass is required and the viaduct is designed to be around 20m above the
ground level over the road junction to clear existing structures. Where the
existing Chertsey line crosses over the M25 the new viaduct joins with an at-
grade junction.
There are a number of additional assumptions that apply to the cost estimates for
Option 3. The estimate costs for the viaduct infrastructure are based on historical
cost data taking into consideration the complexity of the chosen location and the
solution required. The estimates also assume that no work or improvements to the
M25 motorway will be made during the same period and that the requirement for
the demolition of buildings will extend 20m to the east of the viaduct. The cost
estimates also exclude work that may be required to any existing structures.
| Final | 21 December 2016 Page 24 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
The Network Rail cost estimate for Option 3 is between £1.4bn and £1.8bn, Arup’s cost estimate is £1.6bn, within the range of the Network Rail estimate.
4.5 Option 4 – Eastern Alignment
Option 4 provides a rail link from Heathrow Central (T1, 2, 3) station to the
existing Staines to Windsor line joining to the West of Feltham station via an easterly tunnelled approach. Figure 13 shows the indicative alignment for Option
4 and how it connects with the existing rail network towards Feltham.
Figure 13: Option 4 Eastern Alignment
The option proposed would not provide services from Surrey to Heathrow, only from London Waterloo, and the Network Rail report has only considered this option in relation to services to London Waterloo.
As this option does not offer service opportunities towards Surrey, we have not
developed a cost estimate, however the Network Rail estimate is £1.0 to £1.4bn.
4.6 Other SRAtH Studies
The following section reviews the infrastructure options of other proposals for SRAtH:
Airtrack and Airtrack-Lite; Heathrow Southern Rail; and London Borough of Hounslow.
| Final | 21 December 2016 Page 25 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
4.6.1 Airtrack & Airtrack-Lite
Airtrack was a proposal to provide direct rail services from Heathrow airport to
London Waterloo, Reading and Guildford. The proposal involved reinstating a 4km stretch of the former Staines and West Drayton railway between the
airport and the existing Staines – Windsor line, running parallel with the M25 across Staines Moor.
The Airtrack proposals included infrastructure options similar to Options 1a and
1b presented in the Network Rail study and included tunnelling from Heathrow to
Stanwell Moor, a new rail link across the moor as well as the construction of
additional track in Staines town centre as well as the remodelling of Staines
station. The Staines Chord to the west of the existing station would also have been
reinstated.
The economic case for the scheme was established upon these minimal
requirements for infrastructure, which totalled approximately £680 million. The
proposal would have facilitated a 2tph London Waterloo – Heathrow service, a
2tph peak and 1tph off-peak Guildford – Heathrow service and a 2tph Reading –
Heathrow service. There was also discussion of extending the existing Heathrow
Express services to terminate at Staines-upon-Thames, providing an additional
2tph on the new link section.
As noted in the Network Rail report, one significant issue raised against the
Airtrack scheme was the impact of additional services on level crossing barrier
down times, particularly between Staines and Virginia Water where an additional
four trains per hour (4tph) were proposed in each direction. Longer barrier down
times would negatively impact on traffic congestion, particularly in Egham and
Wokingham.
Airtrack-Lite proposals looked to resolve some of the issues surrounding level crossings by making use of splitting and joining of trains at Staines, the infrastructure proposals remained the same as that proposed for Airtrack.
4.6.2 Heathrow Southern Rail
Heathrow Hub Ltd proposes a scheme called Heathrow Southern Rail (HSR) for
providing rail access to Heathrow from the south. The infrastructure proposals
developed for this scheme are very similar to Option 3 proposed in the Network
Rail report, whereby the Waterloo to Reading Line is entirely avoided for services
towards the south joining the existing rail network between Virginia Water and
Chertsey. The infrastructure costs developed by Heathrow Southern Rail are
estimated at £1.1bn.
4.6.3 London Borough of Hounslow
The London Borough of Hounslow submitted a pre-feasibility study for southern rail
access to Heathrow T5 in August 2015. The infrastructure proposal includes a new
grade separated junction to the south-west of Feltham station providing a link
towards Feltham and a second grade separated junction proving a link towards
Staines (forming a triangle junction). The alignment towards Heathrow continues
| Final | 21 December 2016 Page 26 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
on a viaduct from the grade separated junctions and includes a proposed new
station at Bedfont to serve the Bedfont Lakes Office Park and current/future
proposed residential and commercial developments. From Bedfont, the alignment
continues to the south of the airport and to the north of the Staines Reservoirs
onto Stanwell Moor where it turns back towards the airport and joins into the
station box at Heathrow T5 station. The alignment is similar to that found in a
report for Wandsworth Borough Council published September 2013.
Figure 14 below illustrates a high-level interpretation of the alignment. The indicative costs were valued in the range of £900m - £1bn.
Figure 14: Indicative London Borough of Hounslow alignment
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 27
Surrey County Council Southern Rail Access to Heathrow Final Report
4.6.4 Summary of Other SRAtH Studies
Table 1 provides an overview of the other proposals considered above.
Table 1: Other SRAtH Studies Summary Table
Airtrack Airtrack-Lite Heathrow London
Southern Rail Borough of
Hounslow
Scheme BAA Wandsworth Heathrow Hub Hounslow
Promoter Council Ltd Council
Infrastructure Tunnel Tunnel Chertsey Link Tunnel
required alignment alignment Tunnel alignment Re-modelling of Re-modelling of alignment New Bedfont Staines station Staines station Station
Staines Chord Staines Chord Elevated Track
Ashford Chord
Approximate £679m Not available £1.1bn £900m
Costs
The infrastructure scheme developed previously for Airtrack and Airtrack-Lite, is
similar to that for Option 1a and 1b in the Network Rail report. Both
infrastructure schemes will impact on level crossing barrier down time
subsequently affecting road traffic. Given the objections to the previous Airtrack
scheme in regards to the impact on level crossings it is also foreseeable that
Option 1b would succumb to similar scrutiny. The addition of a platform at
Staines could provide additional connectivity options potentially, for example,
allowing services from the Great Western Route to terminate at Staines, although
it is likely a third independent line to the additional platform at Staines would be
required to mitigate any performance risks.
The infrastructure proposals outlined in the Heathrow Hub HSR are similar to that
set out in the Network Rail report for Option 3, however with the objective of
providing faster journey times between Surrey/Hampshire and Heathrow. The cost
estimate for HSR infrastructure is £1.1bn compared to Network Rail’s estimate of
£1.4bn to £1.8bn, and Arup’s cost estimate of £1.6bn. It is understood the
difference in costs in the HSR scheme are around reducing the requirement of
viaduct sections compared to the Network Rail scheme. The impact on costs
associated with compensation are not included in the Arup cost estimate, however
with a viaduct alignment option these costs could be significantly greater than that
of Option 2 via a tunnel alignment.
The scheme proposed by the London Borough of Hounslow, offers limited
advantages to services towards Surrey and the south compared to the Network
Rail options. As with Option 1b, these proposals would not avoid impacting on
level crossings through the Egham area, limiting service levels especially during
peak hours. This option would also mean Staines is served via services from the
south rather than from London Waterloo. There is also an impact to journey times;
whilst this scheme could improve journey times for services from London
Waterloo, it will increase journey times for services from Surrey and the south.
The inclusion of a new station at Bedfont potentially adds to the increased journey
| Final | 21 December 2016 Page 28 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
times, however the development at Bedfont may support funding a SRAtH scheme.
4.7 Summary of Rail Infrastructure Options
The following table (Table 2) summarises the proposed infrastructure options identified above.
Table 2: Infrastructure Options Summary
Core Variants
Option 1 Option 1a – Option 1b – Option 1c – Staines Chord
Western Alignment Staines Chord (with level crossings removal)
Option 2 Option 2 – Egham
Tunnel
Option 3 –
Option 3
Chertsey Link
Option 4 – Eastern
Option 4
Alignment
Airtrack
Airtrack (Lite)
Airtrack
HSR
Heathrow
Southern Rail
Hounslow Eastern
Hounslow
Alignment
Option 1a is the core minimum infrastructure required to provide a southern rail link
to Heathrow, and offer only opportunities for services between London Waterloo
and Heathrow. Option 1a presents the minimum cost estimate which is required for
all options in the Network Rail study with the exception of Option 4.
Option 1b provides a new chord providing rail access from Egham direction,
however it could potentially result in significant local disruption requiring significant alterations to the access of the local car park and bus station as well as
highway realignments.
Option 2 provides opportunities for additional services above that in Option 1b
between Heathrow and Surrey/Hampshire as it bypasses the four level crossings
in the Egham area. It is also potentially a less intrusive option to the local area,
depending on how the tunnel design is completed. Option 2 re-joins the Waterloo
to Reading line allowing for interchange at Virginia Water station with Airport
services, whilst this would not be possible with Option 3, interchange could only
happen at Staines with Heathrow – London Waterloo services (of which only
2tph could stop at Staines).
Option 3 however provides the potential opportunity for additional services
between Heathrow and Surrey/Hampshire. Option 3 is potentially the most
intrusive option on the local area. Arup’s cost estimate has excluded any
compensation costs, as it is believed this is also excluded in the Network Rail
study estimates. The impact of implementing a viaduct structure through the
| Final | 21 December 2016 Page 29 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Egham area, alongside the M25 could have significant ramifications in respect of
compensation costs which will increase the cost difference between Option 2
and Option 3. To potentially minimise these impacts, an alternative option to the
development of a viaduct structure for Option 3 has been considered. This option
proposes tunnelling along the alignment for Option 3. For the purposes of
comparison Arup has produced cost estimates for a tunnel option which would
increase the costs of Option 3 by circa £120m.
Figure 15: All NR Options
Arup has developed its own costs estimates for each of the options outlined in the
Network Rail report which could offer SRAtH to Surrey rail stations. The cost
estimates for the options outlined in the Network Rail report range between
£0.68bn and £1.61bn, these point estimates are broadly aligned with the estimate
range quoted in the Network Rail report, although slightly lower. Options 1a and
1b lowest cost option allowing for services towards London Waterloo and
Surrey/Hampshire. Option 2 and 3 are significantly more expensive however both
are similar in cost. However the cost estimates amongst other assumptions do not
include costs associated with compensation which has the potential to
significantly increase the estimate cost for Option 3 due to the impact of the
viaduct structure. The same alignment for Option 3 developed as a tunnel rather
than a viaduct would increase the cost by approximately £120m, but could reduce
the risks regarding compensations costs and visual impact. Table 3 summarises
the cost estimates for each option.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 30
Surrey County Council Southern Rail Access to Heathrow Final Report
Table 3: Arup Cost Estimates
Option 1a Option 1b Option 1c Option 2 Option 3 Option 3
(Western (Staines (+ LX (Egham (Chertsey (Tunnel
Alignment) Chord) removal) Tunnel) Link) alternative)
Arup £679.9m £725.5m £725.5m £1,448.9m £1,605.8m +£120m
Estimate
(+£42m)
Table 4 compares Arup’s estimates with the Network Rail estimates. Comparison of Arup’s point estimates with the range estimate outlined in the Network Rail
study suggests the cost estimates outlined in the Network Rail report are representative of the infrastructure requirements, although detailed information
regarding the Network Rail estimates were not made available upon request.
The Network Rail Study has assumed capacity enhancements on the South West
Main Line are delivered as a requirement to increase capacity to London Waterloo
from Surrey and Hampshire. As noted previously it is not made clear the extent to
which the capacity available will be prioritised for trains to Heathrow, and
whether any capital costs would be associated with delivery of SRAtH, the costs
of these required schemes could have a significant impact.
Table 4: Comparison of Cost Estimates between Arup's cost point estimate and the Network Rail study range estimate.
Option 1a Option 1b Option 2 (Egham Option 3
(Western (Staines Chord) Tunnel) (Chertsey Link)
Alignment)
Arup £679,860,000 £725,530,000 £1,448,910,000 £1,605,830,000
Estimate
Network £700,000,000- £800,000,000- £1,400,000,000- £1,400,000,000-
Rail £900,000,000 £950,000,000 £1,800,000,000 £1,800,000,000
Estimate
The cost estimates developed by Arup are indicative and include a number of
assumptions and clarifications that are outlined in Appendix A1. The cost
estimates do not consider the feasibility of construction for each alignment and
should be considered relative to each other to provide an indicative cost for each
scheme. Details of Network Rail’s cost assumptions and exclusions were not
made available, however their study does report that “cost does not include future
inflation, asset resilience, power supply upgrades or potential depot and stabling
requirements”.
4.8 Additional Infrastructure Option
Arup has developed an additional infrastructure option to improve Surrey service connectivity with SRAtH from that proposed within the Network Rail report. The
Arup option is complementary to the Network Rail options and involves improving connectivity at Weybridge, where services are proposed to be removed
in the Network Rail report.
| Final | 21 December 2016 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 31
Surrey County Council Southern Rail Access to Heathrow Final Report
4.8.1 Weybridge Chord Option
The Network Rail options (1b, 2, 3) provide capacity for up to 4tph between Heathrow and any pair of the following destinations; Basingstoke, Guildford and Weybridge.
We have developed an additional enhancement to the Network Rail options which
predominantly seeks to improve connectivity. In addition to the options proposed
in the Network Rail report a chord between Weybridge Platform 1 and Byfleet
Junction could potentially provide half hourly (2tph) connectivity to all three
destinations. The proposed chord allows trains from the bay platform to access the
Down Slow Line without conflicting with services on the other lines. Figure 16
shows the proposed alignment for the junction and how this would connect to the
existing infrastructure, whilst Figure 17 on the following page, provides a
schematic track layout of how the new chord (dashed red line) would make use of
the existing grade separated Byfleet Junction.
Figure 16: Option 2b/3b Weybridge Chord
It is proposed that 1-2tph from Heathrow to Surrey/Hampshire could be routed via
a reversing move to serve Weybridge station. Stopping airport services at
Weybridge provides additional connectivity options, and could off-set some loss
in connectivity on the Chertsey Line by proving a station interchange at
Weybridge. An increase in though journey time of approximately 10 minutes
would be incurred to services which call at Weybridge as part of a reversal move.
The cost estimate for the Weybridge chord is between £23m and £49m depending on alignment. Details regarding the cost estimate are included in Appendix A.
This option could be developed alongside Option 1b, Option 2 and Option 3,
| Final | 21 December 2016 Page 32 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
although with a reduced level of service during peak hours to 2tph with Option 1b.
Figure 17: Schematic Weybridge station track layout diagram. Adapted from source www.networkrail.co.uk
4.9 Supporting Infrastructure Scheme Requirements
In addition to the specific SRAtH proposals, the Network Rail report also outlines several significant schemes required to be in place in order to accommodate SRAtH services. These enhancements are outlined in the Network Rail Wessex
Route Study report2, as key infrastructure schemes to support future demand on
the South West Main Line. The schemes relevant to SRAtH are:
Woking Junction grade separation;
Woking station additional Down through platform;
Freight regulation point/solution (potentially requiring a new loop);
Basingstoke (down) direction grade separation (if SRAtH is planned to Basingstoke); and
2 Wessex Route Study (Network Rail, August 2015).
| Final | 21 December 2016 Page 33 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Guildford station capacity enhancements (if SRAtH is planned to Guildford).
The enhancement schemes outlined in the Wessex Route Study are unfunded
proposed schemes for CP63 and beyond, which would be required regardless of
SRAtH, in order to improve capacity on the South West Main Line. As such the Network Rail study has excluded the scheme costs from their appraisal, although there is a possibility that funding may be required for these schemes as part of any SRAtH scheme, depending on timescales.
3 Control Period 6 – the Network Rail 5-year financial planning period running from April 2019
to March 2024.
| Final | 21 December 2016 Page 34 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
5 Capacity and Service Options
The following section presents the current train service provision and that planned as part of the next South Western Franchise, and capacity constraints in relation to SRAtH.
5.1 Current Situation
The existing rail network connecting London Waterloo and Surrey / Hampshire is
already very busy and adding trains to/from Heathrow is complicated. The
Heathrow trains will introduce new conflicting moves which will constrain the
timetable and potentially have a significant impact on performance. This
performance risk is mentioned in Network Rail’s report and this chapter
summarises the constraints and reviews the Network Rail proposals on future
capacity.
5.1.1 Current Capacity
Currently services typically operating from London Waterloo towards Reading, Weybridge, Windsor & Eton Riverside, Shepperton (via Twickenham),
Farnham (via Ascot) and on the Hounslow loop are considered as the Windsor Line services.
Today in the high peak hour (arrivals at London Waterloo between 0800h and 0859h) there are 15tph from the Windsor Line. This is expected to increase to
18tph by the end of CP54 with an additional Reading service and additional
Windsor & Eton Riverside services. Excluding the inner Windsor services, Figure 18 below outlines the current train service provision. Each line in the figure represents one train per hour, whilst the white dots indicate stops at stations.
4 Control Period 5 – the current Network Rail 5-year financial planning period running from
April 2014 to March 2019.
| Final | 21 December 2016 Page 35 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
Figure 18: Current Outer Windsor Lines Train Service Map for high peak hour arrivals to London Waterloo, excluding inner Windsor Line services.
5.1.2 South Western Franchise
The current South Western franchise is due for renewal in 2017. The next South
Western franchise Invitation to Tender (ITT) documentation is planned around
making use of the infrastructure enhancements delivered during CP5 and into CP6.
The infrastructure enhancements are due to be delivered with the end goal of
providing capacity for up to 20tph into London Waterloo from the Windsor Lines.
The main enhancement scheme required for this is the re-opening of Platforms 20-
24 and associated signalling and station track layout changes at London Waterloo.
It is envisaged that up to 18 trains per hour will operate from the Windsor Lines
during the start of CP6 (2019) as outlined in the ITT for the next franchise. The
following Table 5 compares current service provision to that in the ITT for the
next South Western franchise.
| Final | 21 December 2016
\\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Page 36
Surrey County Council Southern Rail Access to Heathrow Final Report
Table 5: Comparison of current outer Windsor Line services to that in the ITT for the next South Western franchise.
Current Peak
New SW Franchise ITT
Service Peak Service (indicative)
Reading – Waterloo 3tph 4tph
Windsor – Waterloo 2tph 4tph
Weybridge/Farnham – Waterloo 2tph 2tph*
Kingston Loop 2tph 2tph
Shepperton (via Twickenham) 2tph 2tph *Service provision to Weybridge/Farnham is dependent on franchise bidder choices, remaining services
are required to be delivered.
20tph is considered the maximum capacity of the Windsor Lines due to several
significant constraints on the route. In regards to SRAtH services to London Waterloo a key constraint for services between Heathrow and London Waterloo is
the section of track between Staines and Feltham which is limited to a maximum of 14tph with 12tph stopping.
For SRAtH services between Heathrow and Surrey/Hampshire, the key constraints are the level crossings in the Egham area, and capacity on the South
West Main Line. Table 6 compares the plain line planning capacity utilisation5
for today compared to the expected 2019 service levels (Department for Transport, South Western franchise ITT, 2016).
Table 6: Plain Line Planning Capacity Utilisation of Existing Infrastructure5
Line link Timetable Stopping Stopping Non- Total
Year trains dwell
trains
stopping
Utilisation
time
headway
trains
headway
Feltham – 2016 15% 53% 0% 68%
Staines
2019
20%
70%
0%
90%
Staines – 2016 12% 41% 0% 53%
Virginia Water
2019
13%
47%
0%
60%
Weybridge - 2016 3% 15% 0% 18%
Chertsey
2019
3%
15%
0%
18%
This indicates that there is potential spare capacity to introduce new services between Heathrow and Surrey via the Weybridge to Chertsey and Virginia Water
5 Plain line planning capacity is a measure of utilisation using the planning headways, which is
calculated as a function of the number of trains, stopping patterns and journey time though the section of line. It does not include the utilisation of planning margins at junctions, however provides an indication of the capacity available/utilised in the route section. Planning headways are the stated minimum margin between trains, and are usually in excess of the minimum technical signalling headway.
| Final | 21 December 2016 Page 37 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX
Surrey County Council Southern Rail Access to Heathrow Final Report
to Staines links. However, as reported in the Network Rail study the level
crossings in the Egham area act as a significant constraint on increasing the
number of services. The Network Rail report states that “The Office of the Rail
and Road (ORR) has advised that no additional services can be pathed via Egham
in the peak whilst these level crossings are in operation.” Therefore options
developed will need to avoid increasing the number of services on this section of
line in order not impact on level crossing barrier down time.
5.1.3 Heathrow – London Waterloo Constraints
All infrastructure options proposed in the Network Rail study seek to
accommodate four trains per hour all day, including the peak hours between
Heathrow and London Waterloo. Due to the maximum capacity of the route
between Staines and Feltham being 14 trains per hour (with 12tph stopping), this
therefore means there is not sufficient capacity to support an additional 4tph
Heathrow – London Waterloo services on top of the 12tph planned for CP6. Table
6 illustrates that between Feltham and Staines the assumed service increase in
CP6 of 3tph in the peak hours brings the planning capacity utilisation to 90%. The
high utilisation of this section of line presents a performance risk to services.
Our analysis indicates that even if capacity is increased between Staines and Feltham there are further capacity issues towards London Waterloo including
Barnes Junction and capacity approaching and at London Waterloo that would preclude any additional increase in capacity.
To accommodate the services from Heathrow to London Waterloo the Network
Rail study proposes to curtail the 2tph Weybridge – London Waterloo services at Virginia Water. This has the following implications;
1. The 4tph between Heathrow and London Waterloo will increase the line utilisation to 100% between Staines and Feltham during peak hours, presenting a significant performance risk to Windsor Line services.
2. Due to the capacity constraints it also suggests that 2tph of the Heathrow –
London Waterloo services will need to be timed as “semi-fast” or non-stop
services between Staines and Feltham (potentially resulting in only 2tph of the airport services calling at Staines and Feltham).
3. Although the Network Rail report has suggest curtailing the 2tph Weybridge –
London Waterloo services, it is feasible that other services operating through Staines and the Hounslow loop could be curtailed or removed instead. For
example 2tph services from Reading or Farnham (via Ascot).
5.1.4 Heathrow – Surrey/Hampshire Constraints
Not all the infrastructure options in the Network Rail report provide connectivity
between Surrey/Hampshire and Heathrow Airport (Option 1a and Option 4). Of the
options that do, Option 1b can only support 2tph in the peak without increasing level
crossing barrier closure times beyond that planned in 2019. This therefore requires
that any services routed though Egham from Heathrow will have to replace existing
services; the Network Rail report suggests it should be the
| Final | 21 December 2016 Page 38 \\GLOBAL.ARUP.COM\LONDON\PTG\ICL-JOBS\227000\227787 SURREY RAIL STRATEGY\227787-60 HEATHROW SOUTHERN RAIL ACCESS\4 INTERNAL PROJECT DATA\4-
05 ARUP REPORTS\REPORT\SURREY SRATH - FINAL REPORT - DEC 2016.DOCX