final reportfinal report main report-2main report-2 … · 2005. 4. 24. · -i - report composition...

86
MINISTRY OF TRANSPORT & COMMUNICATIONS SULTANATE OF OMAN MARCH 2005 MARCH 2005 JAPAN INTERNATIONAL COOPERATION AGENCY FINAL REPORT FINAL REPORT MAIN REPORT-2 MAIN REPORT-2 PRE-FEASIBILITY STUDY PRE-FEASIBILITY STUDY

Upload: others

Post on 26-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

MINISTRY OF TRANSPORT &COMMUNICATIONS SULTANATE OF OMAN

MARCH 2005MARCH 2005

JAPAN INTERNATIONALCOOPERATION AGENCY

FINAL REPORTFINAL REPORT

MAIN REPORT-2MAIN REPORT-2

PRE-FEASIBILITY STUDYPRE-FEASIBILITY STUDY

Page 2: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,
Page 3: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

PREFACE

In response to a request from the Sultanate State of Oman, the Government of Japan decided to conduct the Study on Road Network Development and entrusted the project to Japan International Cooperation Agency (JICA).

JICA selected and dispatched a study team headed by Dr. Hani

Abdel-Halim at Katahira & Engineers International from January 2004 to February 2005.

The team held discussions with the engineers at Directorate General

of Roads, Ministry of Transport and Communications, as well as other officials concerned, and conducted field surveys, data analysis, Master Plan formulation and Feasibility Study. Upon returning to Japan, the team prepared this final report to summarize the result of the study.

I hope that this report will contribute to the enhancement of friendly

relationship between our two countries. Finally, I wish to express my sincere appreciation to the officials

concerned of the Sultanate State of Oman for their close cooperation extended to the study. March 2005

Kazuhisa MATSUOKA, Vice President Japan International Cooperation Agency

Page 4: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

Mr. Kazuhisa MATSUOKA Vice President Japan International Cooperation Agency

March 2005

Letter of Transmittal Dear Sir, We are pleased to submit herewith the Final Report of “The Study on Road Network Development in the Sultanate of Oman”. The report includes the advices and suggestions of the authorities concerned of the Government of Japan and your agency as well as the comments made by the Ministry of Transport & Communications and other authorities concerned in the Sultanate of Oman. The report analyses the present and future conditions and demand of transport in the Sultanate. It comprehensively covers the road transport sector as well as the issues of institution, financing and environment. The report presents the established road network development plan to the year 2030, and pre-feasibility study on high priority projects. The output of the Study concludes that the plan is technically, environmentally, economically and socially viable, and will contribute to the national and regional development in the Sultanate. In view of the urgency of developing the road network in the Sultanate, we recommend that the Government of the Sultanate of Oman implement the projects with high priority. We wish to take this opportunity to express our sincere gratitude to your agency, the Ministry of Foreign Affairs and the Ministry of Land, Infrastructure and Transport. We also wish to express our deep gratitude to the Ministry of Transport & Communications, Directorate General of Roads as well as other Governmental Agencies concerned in the Sultanate of Oman for the close cooperation and kind assistance extended to us during the Study. We hope this report will contribute significantly to the development of the Sultanate of Oman. Very truly yours, Dr. Hani Abdel-Halim Team Leader, The Study on Road Network Development in the Sultanate of Oman

Page 5: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

Location Map

Page 6: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- i -

Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups, either for experts in-charge of planning or technical feasibility studies. It contains the following five volumes: EXECUTIVE SUMMARY: is designed to address the decision-makers who do not extensive information in technical and engineering aspects. It contains brief information on all the major aspects of the Study, and concentrates on input and output of each aspect. It contains also a more concentrated summary for the main conclusions. MAIN REPORT – 1 “Road Network Development Plan”: is designed for planners, engineers and directors of DGR and concerned ministries and authorities, who need more technical information on the Master Plan formulation. It contained comprehensive information on the present conditions in sectors related to the Study, planning objectives and strategies, development and evaluation of alternatives, components of planned projects, prioritization in the planning process, evaluation results of the Master Plan and overall implementation plan. This report contains the Chapters from 1 to 16. MAIN REPORT – 2 “Pre-Feasibility Study”: is designed to include technical and detailed studies carried out on significant projects selected in line with the policies and concept of the Master Plan. The report gives the objectives, preliminary design, cost estimate and project evaluation on the technical, environmental and economic viability of four road projects. In addition, it contains other detailed studies conducted on three projects on specific fields of environment, hydrology and management. This report contains the Chapters from 17 to 26. APPENDIX: to contain necessary data, calculations and other information produced during the course of the Study. DRAWINGS: to contain preliminary design drawings produced for the Pre-Feasibility Study projects.

Page 7: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- ii -

MAIN REPORT – 2: PRE-FEASIBILITY STUDY TABLE OF CONTENTS

Page Preface Letter of Transmittal Location Map Abbreviations .......................................................................................................................... xvi CHAPTER 17 SELECTED PROJECTS FOR PRE-FEASIBILITY STUDY

17.1 Selection Procedure ...................................................................................... 17-1 17.2 Status of 7th 5-Year Plan Projects ................................................................. 17-2 17.3 Selected Projects ........................................................................................... 17-3 17.4 Study Procedure.............................................................................................. 17-6

CHAPTER 18 AL HAMRA – RUSTAQ ROAD (PHASE 4) 18.1 Objective of the Project ................................................................................ 18-1 18.2 Alignment and Preliminary Design .............................................................. 18-2

18.2.1 Physical Features of Project Site ....................................................... 18-2 18.2.2 Existing Road Condition ................................................................... 18-2 18.2.3 Proposed Road Alignment ................................................................. 18-5 18.2.4 Preliminary Design ............................................................................ 18-6 18.2.5 Pavement Design ............................................................................... 18-8 18.2.6 Structure Design ................................................................................ 18-8 18.2.7 Drainage and Cross Drainage Facilities............................................. 18-8

18.3 Preliminary Cost Estimation ......................................................................... 18-10 18.3.1 Procedure of Project Cost Estimate ................................................... 18-10 18.3.2 Unit Price and Cost of Major Construction Items ............................. 18-11 18.3.3 Construction Cost .............................................................................. 18-15 18.3.4 Engineering Service and Construction Supervision Cost .................. 18-15 18.3.5 Summary of Project Costs ................................................................. 18-16

18.4 Environmental Considerations and TOR for EIA ......................................... 18-17 18.4.1 Environmental Considerations........................................................... 18-17 18.4.2 Terms of Reference for the Project .................................................... 18-22

18.5 Project Evaluation ........................................................................................ 18-23 18.5.1 General ............................................................................................. 18-23 18.5.2 Traffic Demand Forecast ................................................................. 18-23 18.5.3 Preliminary Economic Evaluation ..................................................... 18-25

Page 8: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- iii -

18.5.4 Technical Evaluation ......................................................................... 18-32 18.5.5 Evaluation Form Other Aspects......................................................... 18-32 18.5.6 Overall Evaluation ............................................................................. 18-33

Annex 18-1 Detailed Cost Estimate of Hamra – Rustaq Road with Bridge ... A18-1-1 Annex 18-2 Detailed Cost Estimate of Hamra – Rustaq Road without Bridge ......................................................................................... A18-2-1 Annex 18-3 Environmental Checklist (Hamra to Rustaq Road) ...................... A18-3-1 Annex 18-4 Terms of Reference on the Environmental Impact Assessment of the Hamra – Rustaq Road, Sultanate of Oman......................... A18-4-1

CHAPTER 19 MADHA – DAFTA ROAD 19.1 Objective of the Project ................................................................................ 19-1 19.2 Alignment and Preliminary Design .............................................................. 19-2

19.2.1 Physical Features of the Project Site ................................................. 19-2 19.2.2 Existing Road Condition ................................................................... 19-2 19.2.3 Proposed Road Alignment ................................................................. 19-5 19.2.4 Preliminary Design ............................................................................ 19-6 19.2.5 Pavement Design ............................................................................... 19-7 19.2.6 Structure Design ................................................................................ 19-8 19.2.7 Drainage and Cross Drainage Facilities............................................. 19-8

19.3 Preliminary Cost Estimation ......................................................................... 19-10 19.3.1 Procedure of Project Cost Estimate ................................................... 19-10 19.3.2 Unit Price and Cost of Major Construction Items ............................. 19-11 19.3.3 Construction Cost .............................................................................. 19-14 19.3.4 Engineering Service and Construction Supervision Cost .................. 19-14 19.3.5 Summary of Project Costs ................................................................. 19-14

19.4 Environmental Considerations and TOR for EIA ......................................... 19-15 19.4.1 Environmental Considerations........................................................... 19-15 19.4.2 Terms of Reference for the Project .................................................... 19-18

19.5 Project Evaluation ........................................................................................ 19-19 19.5.1 General ............................................................................................. 19-19 19.5.2 Traffic Demand Forecast ................................................................. 19-19 19.5.3 Preliminary Economic Evaluation ..................................................... 19-23 19.5.4 Technical Evaluation ......................................................................... 19-28 19.5.5 Other Impacts..................................................................................... 19-28 19.5.6 Overall Evaluation ............................................................................. 19-29

Annex 19-1 Detailed Cost Estimate of Madha – Dafta Road........................... A19-1-1 Annex 19-2 Environmental Checklist (Madha to Dafta Road) ........................ A19-2-1 Annex 19-3 Terms of Reference on the Environmental Impact Assessment of the Madha – Dafta Road, Sultanate of Oman........................... A19-3-1

Page 9: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- iv -

CHAPTER 20 AL HIJ – FLIM ROAD

20.1 Objective of the Project ................................................................................ 20-1 20.2 Alignment and Preliminary Design .............................................................. 20-2

20.2.1 Physical Feature of the Project Site ................................................... 20-2 20.2.2 Existing Road Condition ................................................................... 20-2 20.2.3 Proposed Road Alignment ................................................................. 20-4 20.2.4 Preliminary Design ............................................................................ 20-5 20.2.5 Pavement Design ............................................................................... 20-6 20.2.6 Structure Design ................................................................................ 20-6 20.2.7 Drainage and Cross Drainage Facilities............................................. 20-6

20.3 Preliminary Cost Estimation ......................................................................... 20-8 20.3.1 Procedure of Project Cost Estimate ................................................... 20-8 20.3.2 Unit Price and Cost of Major Construction Items ............................. 20-9 20.3.3 Construction Cost .............................................................................. 20-12 20.3.4 Engineering Service and Construction Supervision Cost .................. 20-12 20.3.5 Summary of Project Costs ................................................................. 20-12

20.4 Environmental Considerations and TOR for EIA ......................................... 20-13 20.4.1 Environmental Considerations........................................................... 20-13 20.4.2 Terms of Reference for the Project .................................................... 20-16

20.5 Project Evaluation ........................................................................................ 20-17 20.5.1 General ............................................................................................. 20-17 20.5.2 Traffic Demand Forecast ................................................................. 20-17 20.5.3 Preliminary Economic Evaluation ..................................................... 20-21 20.5.4 Technical Evaluation ......................................................................... 20-26 20.5.5 Other Impacts..................................................................................... 20-26 20.5.6 Overall Evaluation ............................................................................. 20-27

Annex 20-1 Detailed Cost Estimate of Al Hij – Flim Road ............................. A20-1-1 Annex 20-2 Environmental Checklist (Al Hij to Flim Road)........................... A20-2-1 Annex 20-3 Terms of Reference on the Environmental Impact Assessment of the Al Hij – Flim Road, Sultanate of Oman ............................. A20-3-1

CHAPTER 21 MAHLAH – ISMAIYAH ROAD

21.1 Objective of the Project ................................................................................ 21-1 21.2 Alignment and Preliminary Design .............................................................. 21-2

21.2.1 Physical Feature of the Project Site ................................................... 21-2 21.2.2 Existing Road Condition ................................................................... 21-2 21.2.3 Proposed Road Alignment ................................................................. 21-5 21.2.4 Preliminary Design ............................................................................ 21-7 21.2.5 Pavement Design ............................................................................... 21-7

Page 10: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- v -

21.2.6 Structure Design ................................................................................ 21-8 21.2.7 Drainage and Cross Drainage Facilities............................................. 21-8

21.3 Preliminary Cost Estimation ......................................................................... 21-10 21.3.1 Procedure of Project Cost Estimate ................................................... 21-10 21.3.2 Unit Price and Cost of Major Construction Items ............................. 21-11 21.3.3 Construction Cost .............................................................................. 21-14 21.3.4 Engineering Service and Construction Supervision Cost .................. 21-14 21.3.5 Summary of Project Costs ................................................................. 21-14

21.4 Environmental Considerations and TOR for EIA ......................................... 21-15 21.4.1 Environmental Considerations........................................................... 21-15 21.4.2 Terms of Reference for the Project .................................................... 21-19

21.5 Project Evaluation ........................................................................................ 21-20 21.5.1 General ............................................................................................. 21-20 21.5.2 Traffic Demand Forecast ................................................................. 21-20 21.5.3 Preliminary Economic Evaluation ..................................................... 21-25 21.5.4 Technical Evaluation ......................................................................... 21-30 21.5.5 Other Impacts..................................................................................... 21-30 21.5.6 Overall Evaluation ............................................................................. 21-31

Annex 21-1 Detailed Cost Estimate of Mahlah – Ismaiyah Road .................. A21-1-1 Annex 21-2 Environmental Checklist (Mahlah to Ismaiyah Road) ................. A21-2-1 Annex 21-3 Terms of Reference on the Environmental Impact Assessment of the Mahlah – Ismaiyah Road, Sultanate of Oman.................. A21-3-1

CHAPTER 22 ENVIRONMENTAL STUDY ON HASIK – SHUWAYMIYAH ROAD

22.1 Objective of the Project ................................................................................ 22-1 22.2 Alignment ..................................................................................................... 22-2

22.2.1 Physical Feature of the Project Site ................................................... 22-2 22.2.2 Existing Road Condition ................................................................... 22-4 22.2.3 Assumed Road Alignment ................................................................. 22-4

22.3 Preliminary Cost Estimation ......................................................................... 22-11 22.4 Engineering Evaluation ................................................................................ 22-13 22.5 Environmental Considerations and TOR for EIA........................................... 22-14

22.5.1 Environmental Considerations ......................................................... 22-14 22.5.2 Terms of Reference for the Project .................................................. 22-20

Annex 22-1 Environmental Checklist (Hasik to Shuwaymiyah Road) ............ A22-1-1 Annex 22-2 Terms of Reference on the Environmental Impact Assessment of the Hasik – Shuwaymiyah Road, Sultanate of Oman............. A22-2-1

Page 11: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- vi -

CHAPTER 23 WADI STUDY ON BATINAH HIGHWAY 23.1 Introduction .................................................................................................. 23-1 23.1.1 Al Batinah Region ........................................................................... 23-2 23.1.2 Al Batinah Wadi Gauging Stations ................................................. 23-3 23.2 Flood Frequencies .......................................................................................... 23-8 23.2.1 Regional Flood Frequency Curves.................................................... 23-8 23.2.2 Determination of Peak Discharges in Al Batinah Highway .............. 23-10 23.2.3 Preparation of Flood Peaks Frequency Calibration Maps of Al Batinah Region......................................................................... 23-10 23.2.4 Hydraulic Calculations (Design) of Al Batinah Highway ............... 23-13 23.2.5 Evaluation of Flood Peaks Frequency of Existing Al Batinah’s Bridges ......................................................................... 23-14 23.3 Present Drainage Conditions ........................................................................ 23-16 23.3.1 Structures Condition Survey ............................................................. 23-16 23.3.2 Dams and Hydrological Conditions .................................................. 23-19 23.4 Estimated Annual Closing Days..................................................................... 23-26 23.4.1 Rainfall Intensities for Durations up to 24 Hours ........................... 23-27 23.4.2 Daily Rainfall Frequencies................................................................ 23-28 23.4.3 Calculation of Rating Curves .......................................................... 23-32 23.5 Multi-Function Culverts ............................................................................... 23-37 23.5.1 Concept of Multi-Function Culverts ............................................... 23-37 23.5.2 Existing Irish Crossings .................................................................. 23-38 23.5.3 Preliminary Cost Estimates ............................................................. 23-38 23.5.4 Provision of Underpass for Large Vehicles between Roundabouts... 23-45

Annex 23-1 Drainage Studies........................................................................... A23-1-1

CHAPTER 24 MANAGEMENT STUDY ON NEW BATINAH EXPRESSWAY 24.1 Introduction .................................................................................................. 24-1 24.1.1 Study Perspective ............................................................................ 24-1 24.1.2 Physical Outline of New Batinah Expressway ................................ 24-4 24.1.3 Cost Features ................................................................................... 24-6 24.1.4 Demand Forecast ............................................................................. 24-8 24.1.5 Vehicle Operating Cost and Travel Time Cost ................................ 24-8 24.1.6 Regulatory Preparation for Privatization ........................................ 24-8 24.1.7 Equity and Loans ............................................................................ 24-10 24.1.8 Other Cost Assumptions .................................................................. 24-10 24.1.9 Inflation ........................................................................................... 24-11 24.1.10 Financial Statements of Construction Stage .................................... 24-11 24.2 Toll System Study ........................................................................................ 24-11 24.2.1 Toll of Previous Studies .................................................................. 24-11

Page 12: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- vii -

24.2.2 Toll induced from User’s Economic Benefit ................................... 24-13 24.2.3 Toll from Field Interview ................................................................ 24-14 24.2.4 Tolls induced from User’s Logical Behaviors ................................. 24-16 24.2.5 Shadow Toll .................................................................................... 24-17 24.2.6 Summing up of Toll Systems .......................................................... 24-18 24.3 Preliminary Financial Study ......................................................................... 24-19 24.3.1 Initial Assumptions ......................................................................... 24-19 24.3.2 Financial Statements of each Five Years ......................................... 24-19 24.3.3 Reconsideration of Revenue ........................................................... 24-21 24.3.4 Reconsideration of Project Start ...................................................... 24-23 24.3.5 Reconsideration of Construction Period ......................................... 24-23 24.3.6 Reconsideration of Depreciation Costs ........................................... 24-23 24.3.7 Reconsideration of Loan Condition ................................................ 24-25 24.3.8 Reconsideration of Paid-up Capital ................................................ 24-25 24.4 Financial Study under Revised Conditions .................................................. 24-25 24.4.1 Assumptions .................................................................................... 24-25 24.4.2 Financial Reports ............................................................................ 24-26 24.5 Financial Feasibility Study with Government Support ................................ 24-26 24.5.1 Considerable Type of Support ......................................................... 24-26 24.5.2 Shadow Toll .................................................................................... 24-28 24.5.3 Government Participation to Capital ............................................... 24-29 24.5.4 Selective Toll ................................................................................... 24-30 24.6 Discussion and Recommendation ................................................................ 24-33 24.6.1 Technical Issues .............................................................................. 24-33 24.6.2 Comparison of Two Government Supporting Systems ................... 24-34 24.6.3 Recommendations ........................................................................... 24-36

CHAPTER 25 IMPLEMENTATION PLAN FOR PRE-F/S PROJECTS

25.1 Project Implementation Program ................................................................... 25-1 25.1.1 Introduction....................................................................................... 25-1 25.1.2 Feasibility Study ............................................................................... 25-2 25.1.3 Environmental Impact Assessment ................................................... 25-2 25.1.4 Detail Design, Tendering, Bidding and Mobilization ....................... 25-3 25.1.5 Land Acquisition ............................................................................... 25-3 25.1.6 Construction ...................................................................................... 25-3 25.2 Budget and Fund Allocation .......................................................................... 25-4 25.3 Implementation Plans..................................................................................... 25-4 25.3.1 Al Hamra – Rustaq Road (N27)........................................................ 25-4 25.3.2 Madaha – Dafta Road (N30) ............................................................. 25-5 25.3.3 Al Hij – Film Road (N47) ................................................................. 25-5

Page 13: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- viii -

25.3.4 Mahla – Ishmayia Road (N36).......................................................... 25-5 25.3.5 Hasik – Shuwaymia Road (N7)......................................................... 25-5 25.3.6 Batinah Highway Upgrading (U1) .................................................... 25-6 25.3.7 New Batinah Expressway (N1)......................................................... 25-7 25.4 Overall Implementation Schedule.................................................................. 25-7

CHAPTER 26 CONCLUSIONS AND RECOMMENDATIONS

26.1 Pre-F/S Projects under 7th Plan ...................................................................... 26-1 26.2 Pre-F/S Projects under 8th Plan ...................................................................... 26-3 26.3 Recommendations .......................................................................................... 26-4

Page 14: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- ix -

List of Tables Table 17.2-1 Status of 7th Plan Projects ....................................................................................... 17-2 Table 17.3-1 Pre-F/S Projects ...................................................................................................... 17-3 Table 18.2-1 List of the Drainage Facilities (1/2)........................................................................ 18-8 Table 18-2-1 List of the Drainage Facilities (2/2)........................................................................ 18-9 Table 18.3-1 Average Prices of Major Construction Materials ................................................. 18-11 Table 18.3-2 Labor Cost ............................................................................................................ 18-11 Table 18.3-3 Hourly Cost of Major Construction Equipments .................................................. 18-12 Table 18.3-4 Unit Cost of Major Construction Items of the Road with the Proposed Bridge.......... 18-13 Table 18.3-5 Unit Cost of Major Construction Items of the Road without the Proposed Bridge ..... 18-14 Table 18.3-6 Construction Cost of the Road with the Proposed Bridge...................................... 18-15 Table 18.3-7 Construction Cost of the Road without the Proposed Bridge................................. 18-15 Table 18.3-8 Engineering Services and Construction Supervision Cost of the Road with the Proposed Bridge.................................................................... 18-15 Table 18.3-9 Engineering Services and Construction Supervision Cost of the Road without the Proposed Bridge............................................................... 18-16 Table 18.3-10 Summary of Project Cost of the Road with the Proposed Bridge ......................... 18-16 Table 18.3-11 Summary of Project Cost of the Road without the Proposed Bridge ..................... 18-16 Table 18.4-1 Results of IEE on the Hamra – Rustaq Road.......................................................... 18-22 Table 18.5-1 Traffic Volume on Hamra – Rustaq Road............................................................... 18-23 Table 18.5-2 Total Vehicle Kilometers on Hamra – Rustaq Road ............................................... 18-25 Table 18.5-3 Total Vehicle Hours on Hamra – Rustaq Road ....................................................... 18-25 Table 18.5-4(1) Unit Running Cost by Vehicle Speed and Surface Type...................................... 18-26 Table 18.5-4(2) Unit Fixed Cost by Vehicle Types........................................................................ 18-26 Table 18.5-4(3) Unit Travel Time Cost by Vehicle Types ............................................................. 18-27 Table 18.5-5 Estimation of Benefits ............................................................................................ 18-27 Table 18.5-6(1) Economic Cost Estimation (Without Bridge Plan) .............................................. 18-28 Table 18.5-6(2) Economic Cost Estimation (With Bridge Plan) ................................................... 18-28 Table 18.5-7 Economic Indicators of Benefit Cost Analysis ....................................................... 18-29 Table 18.5-8(1) Benefit – Cost Stream of Al Hamra – Rutaq Road Construction Project (Without Bridge Plan).......................................................................................... 18-30 Table 18.5-8(2) Benefit – Cost Stream of Al Hamra – Rutaq Road Construction Project (With Bridge Plan) ............................................................................................... 18-31 Table 18.5-9 Sensitivity Analysis of Hamra – Rutaq Road Construction Project regarding to Benefit and Cost ................................................................................. 18-29 Table 18.5-10 Population, Employed Population and School Children in the Influence Area of Hamra – Rutaq Road .......................................................................................... 18-33

Page 15: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- x -

Table 19.2-1 List of the Drainage Facilities (1/2)........................................................................ 19-8 Table 19.2-1 List of the Drainage Facilities (2/2)........................................................................ 19-9 Table 19.3-1 Average Prices of Major Construction Materials ................................................... 19-11 Table 19.3-2 Labor Cost .............................................................................................................. 19-11 Table 19.3-3 Hourly Cost of Major Construction Equipments .................................................. 19-12 Table 19.3-4 Unit Cost of Major Construction Items..................................................................... 19-13 Table 19.3-5 Construction Cost ................................................................................................... 19-14 Table 19.3-6 Engineering Services and Construction Supervision Cost ..................................... 19-14 Table 19.3-7 Summary of Project Cost ...................................................................................... 19-14 Table 19.4-1 Results of IEE on the Madha – Dafta Road............................................................ 19-18 Table 19.5-1(1) Population of Direct and Indirect Influence Areas by Years................................ 19-21 Table 19.5-1(2) No of Secondary and Tertiary Workers in Direct and Indirect Influence Areas by Years ..................................................................................................... 19-21 Table 19.5-1(3) Private Vehicle Ownership of Direct and Indirect Influence Areas ..................... 19-21 Table 19.5-2 Number of Trips in Wilayah Madha ....................................................................... 19-22 Table 19.5-3 Traffic Volume on Madha – Dafta Road................................................................. 19-22 Table 19.5-4 Total Vehicle Kilometers on Madha – Dafta Road ................................................. 19-23 Table 19.5-5 Total Vehicle Hours on Madha – Dafta Road......................................................... 19-23 Table 19.5-6(1) Unit Running Cost by Vehicle Speed and Surface Type...................................... 19-24 Table 19.5-6(2) Unit Fixed Cost by Vehicle Types........................................................................ 19-24 Table 19.5-6(3) Unit Fixed Cost by Vehicle Types........................................................................ 19-25 Table 19.5-7 Estimation of Benefits ............................................................................................ 19-25 Table 19.5-8 Economic Cost Estimation ..................................................................................... 19-25 Table 19.5-9 Economic Indicators of Benefit – Cost Analysis .................................................... 19-26 Table 19.5-10 Benefit – Cost Stream of Madha – Dafta Road Construction Project .................... 19-27 Table 19.5-11 Sensitivity Analysis regarding Benefit and Cost of Madha – Dafta Road Construction Project ............................................................................................... 19-28 Table 19.5-12 Number of Population, Employed Population and School Children in the Influence Area of Madha – Dafta Road ............................................................ 19-29 Table 20.2-1 List of the Drainage Facilities ................................................................................ 20-7 Table 20.3-1 Average Prices of Major Construction Materials ................................................... 20-9 Table 20.3-2 Labor Cost .............................................................................................................. 20-9 Table 20.3-3 Hourly Cost of Major Construction Equipments .................................................. 20-10 Table 20.3-4 Unit Cost of Major Construction Items..................................................................... 20-11 Table 20.3-5 Construction Cost ................................................................................................... 20-12 Table 20.3-6 Engineering Services and Construction Supervision Cost ..................................... 20-12 Table 20.3-7 Summary of Project Cost ...................................................................................... 20-12 Table 20.4-1 Results of IEE on the Al Hij - Flim Road............................................................... 20-16

Page 16: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xi -

Table 20.5-1(1) Population of Direct and Indirect Influence Areas by Years................................ 20-19 Table 20.5-1(2) No of Secondary and Tertiary Workers in Direct and Indirect Influence Areas by Years ..................................................................................................... 20-19 Table 20.5-1(3) Private Vehicle Ownership of Direct and Indirect Influence Areas ..................... 20-19 Table 20.5-2 Number of Trips in Willayah Muhut ...................................................................... 20-20 Table 20.5-3 Traffic Volume on Al Hij – Flim Road ................................................................... 20-21 Table 20.5-4 Total Vehicle Kilometers on Al Hij - Flim Road .................................................... 20-21 Table 20.5-5 Total Vehicle Hours on Al Hij - Flim Road ............................................................ 20-21 Table 20.5-6(1) Unit Running Cost by Vehicle Speed and Surface Type...................................... 20-22 Table 20.5-6(2) Unit Fixed Cost by Vehicle Types........................................................................ 20-23 Table 20.5-6(3) Unit Fixed Cost by Vehicle Types........................................................................ 20-23 Table 20.5-7 Estimation of Benefit.............................................................................................. 20-23 Table 20.5-8 Economic Cost Estimate......................................................................................... 20-24 Table 20.5-9 Economic Indicators of Benefit Cost Analysis ....................................................... 20-24 Table 20.5-10 Benefit – Cost Stream of Al Hij - Flim Road Construction Project ....................... 20-25 Table 20.5-11 Sensitivity Analysis regarding Cost and Benefit of Al Hij - Flim Road Construction Project ............................................................................................... 20-26 Table 20.5-12 Number of Population, Employed Population and School Children in the Influence Area of Al Hij - Flim Road ............................................................... 20-27 Table 21.2-1 List of the Drainage Facilities (1/2)........................................................................ 21-8 Table 21.2-1 List of the Drainage Facilities (2/2)........................................................................ 21-9 Table 21.3-1 Average Prices of Major Construction Materials ................................................... 21-11 Table 21.3-2 Labor Cost .............................................................................................................. 21-11 Table 21.3-3 Hourly Cost of Major Construction Equipments .................................................. 21-12 Table 21.3-4 Unit Cost of Major Construction Items..................................................................... 21-13 Table 21.3-5 Construction Cost ................................................................................................... 21-14 Table 21.3-6 Engineering Services and Construction Supervision Cost ..................................... 21-14 Table 21.3-7 Summary of Project Cost ...................................................................................... 21-14 Table 21.4-1 Results of IEE on the Hamra – Ismaiya Road ........................................................ 21-19 Table 21.5-1(1) Population of Direct and Indirect Influence Areas by Years................................ 21-22 Table 21.5-1(2) No of Secondary and Tertiary Workers in Direct and Indirect Influence Areas by Years ..................................................................................................... 21-22 Table 21.5-1(3) Private Vehicle Ownership of Direct and Indirect Influence Areas by Years ...... 21-23 Table 21.5-2 Number of Trips in Wilayah Dima Wa At Taiyyin ................................................. 21-23 Table 21.5-3 Traffic Volume on Mahlah - Ismaiyah Road........................................................... 21-24 Table 21.5-4 Total Vehicle Kilometers on Mahlah - Ismaiyah Road........................................... 21-24 Table 21.5-5 Total Vehicle Hours on Mahlah - Ismaiyah Road................................................... 21-24 Table 21.5-6(1) Unit Running Cost by Vehicle Speed and Surface Type...................................... 21-26 Table 21.5-6(2) Unit Fixed Cost by Vehicle Types........................................................................ 21-26

Page 17: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xii -

Table 21.5-6(3) Unit Fixed Cost by Vehicle Types........................................................................ 21-26 Table 21.5-7 Estimation of Benefit.............................................................................................. 21-26 Table 21.5-8 Economic Cost Estimation ..................................................................................... 21-27 Table 21.5-9 Economic Indicators of Benefit Cost Analysis ....................................................... 21-28 Table 21.5-10 Benefit – Cost Stream of Mahlah - Ismaiyah Road Construction Project .............. 21-29 Table 21.5-11 Sensitivity Analysis regarding to Costs and Benefit............................................... 21-28 Table 21.5-12 Number of Population, Employed Population and School Children in the Influence Area of Mahlah - Ismaiyah Road...................................................... 21-30 Table 22.2-1 Summary Table of Alternative 1 ............................................................................. 22-9 Table 22.2-2 Summary Table of Alternative 2 ............................................................................. 22-10 Table 22.2-2 Summary Table of Alternative 3 ............................................................................. 22-11 Table 22.3-1 Unit Cost by Type of Structure ............................................................................... 22-11 Table 22.3-2 Total Cost of Alternatives ....................................................................................... 22-12 Table 22.4-1 Summary of Features of Alternatives ..................................................................... 22-13 Table 22.5-1 Results of IEE on the Hasik - Shuwaymiyah Road ................................................ 22-20 Table 23.2-1 Frequency of Flooding for Design of Highway Drainage Structures ..................... 23-10 Table 23.2-2 Mean Annual Floods (MAF) of Wadis in Al Batinah Region.............................. 23-11 Table 23.2-3 Typical Values of Manning Coefficient’s ............................................................... 23-13 Table 23.2-4 Calculated Flood Peaks Frequency of Existing Bridges......................................... 23-14 Table 23.3-1 Location and Characteristics of Surveyed 32 Irish Crossings along Al Batinah Highway.......................................................................................... 23-18 Table 23.3-2 Existing Recharge Dams of Al Batinah Region.................................................. 23-20 Table 23.3-3 Locations of Proposed Dams .................................................................................. 23-23 Table 23.4-1 Maximum Recorded 1-Day Rainfalls (>100 mm) in Al Batinah Region ............. 23-30 Table 23.4-2 Frequency Analysis for Rain Gauge Stations: Wadi Jizzi....................................... 23-31 Table 23.4-3 Estimated Duration of Flood Peaks along Al Batinah Highway.......................... 23-32 Table 23.5-1 List of Irish Crossing on Batinah Highway ............................................................ 23-40 Table 23.5-2 Total Costs for Three Cases .................................................................................... 23-42 Table 23.5-4 Summary of Total Cost ........................................................................................... 23-43 Table 23.5-5 List of Proposed Culvert Type ................................................................................ 23-47 Table 24.1-1 Cost of New Batinah Expressway .......................................................................... 24-7 Table 24.1-2 Implementation Plan of New Batinah Expressway ................................................ 24-9 Table 24.1-3 Cost Estimate per Package...................................................................................... 24-9 Table 24.1-4 Financial Statement of Expressway Company – Construction Stage ..................... 24-12 Table 24.2-1 Tolls of Former Studies........................................................................................... 24-13 Table 24.2-2 Price Index between 1997 and 2003....................................................................... 24-13 Table 24.2-3 Toll Statement System by Country ......................................................................... 24-13

Page 18: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xiii -

Table 24.2-4 Economic Benefit per Car of New Batinah Expressway – 2025............................ 24-14 Table 24.2-5 Interviewee Attributes............................................................................................. 24-14 Table 24.2-6A Summary of Interviews........................................................................................... 24-15 Table 24.2-6B Summary of Interviews........................................................................................... 24-15 Table 24.2-7 Expected Toll Sales induced from Interview Survey.............................................. 24-16 Table 24.2-8 Time Value -2005.................................................................................................... 24-16 Table 24.2-9 Expected Sales assumed Time Value Reasonable Behavior ................................... 24-17 Table 24.2-10 Economic Benefit of New Batinah Expressway..................................................... 24-18 Table 24.2-11 Summary of Tolls.................................................................................................... 24-18 Table 24.3-1 Initial Assumptions for Preliminary Feasibility Study............................................ 24-19 Table 24.3-2 Financial Statements of each Fie Years .................................................................. 24-20 Table 24.3-3 PFI Application Field.............................................................................................. 24-24 Table 24.3-4 Financing Scheme of Severn Bridge ...................................................................... 24-25 Table 24.4-1 Assumption Revised ............................................................................................... 24-25 Table 24.4-2 Financial Reports of Revised Assumption Case ..................................................... 24-27 Table 24.5-1 Shadow Toll and Retained Earning ........................................................................ 24-28 Table 24.5-2 Growth Rate from 2005 till 2030............................................................................ 24-28 Table 24.5-3 Economic Analysis of Shadow Toll........................................................................ 24-29 Table 24.5-4 Government Investment and Retained Earning ...................................................... 24-30 Table 24.5-5 Economic Analysis of Government Investment ..................................................... 24-30 Table 24.5-6 Company Financial Analysis .................................................................................. 24-31 Table 24.5-7 Economic Analysis for Company Participation Case ............................................. 24-32 Table 24.5-8 Government Investment and Retained Earning ...................................................... 24-32 Table 24.6-1 Summary of Shadow Toll and Capital Support Cases ............................................ 24-37 Table 24.6-2 Financial Statement of RO 9,500 Shadow Toll in Selected Years .......................... 24-38 Table 25.1-1 Major Characteristics of Pre-F/S Projects .............................................................. 25-1 Table 25.1-2 Length and Required Fund of Pre-F/S Projects ...................................................... 25-2 Table 25.2-1 Ratio of Pre F/S Projects Fund to Estimated Future Road Investments ................. 25-4 Table 25.3-1 Implementation Plan of Al Hamra – Rustaq Road (N27) ....................................... 25-4 Table 25.3-2 Implementation Plan of Madaha – Dafta Road (N30)............................................ 25-5 Table 25.3-3 Implementation Plan of Al Hij – Film Road (N47) ................................................ 25-5 Table 25.3-4 Implementation Plan of Mahla – Ismayia Road (N36)........................................... 25-6 Table 25.3-5 Implementation Plan of Hasik – Shuwaymia Road (N7)........................................ 25-6 Table 25.3-6 Implementation Plan of Batinah Highway (U1) ..................................................... 25-7 Table 25.4-1 Overall Implementation Schedule of Pre F/S Projects ........................................... 25-8

Page 19: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xiv -

List of Figures Figure 17.3-1 Location Map of Pre-F/S Projects .................................................................. 17-4 Figure 18.1-1 Location of Project Site .................................................................................. 18-1 Figure 18.2-1 Existing Road Condition ................................................................................ 18-4 Figure 18.2-2 Proposed Bridge ............................................................................................. 18-5 Figure 18.2-3 Proposed Alignment ....................................................................................... 18-6 Figure 18.2-4 Typical Cross Sections.................................................................................... 18-7 Figure 18.3-1 Procedure of Project Cost Estimate ................................................................ 18-10 Figure 18.5-1 Procedure for Project Evaluation.................................................................... 18-24 Figure 19.1-1 Location of the Project Site ............................................................................ 19-1 Figure 19.2-1 Existing Road Condition ................................................................................ 19-4 Figure 19.2-2 Proposed Alignment ....................................................................................... 19-6 Figure 19.2-3 Typical Cross Sections.................................................................................... 19-7 Figure 19.3-1 Procedure of Project Cost Estimate ................................................................ 19-10 Figure 19.5-1 Procedure for Project Evaluation.................................................................... 19-20 Figure 20.1-1 Location of the Project Site ............................................................................ 20-1 Figure 20.2-1 Existing Road Condition ................................................................................ 20-3 Figure 20.2-2 Proposed Alignment ....................................................................................... 20-5 Figure 20.2-3 Typical Cross Section ..................................................................................... 20-6 Figure 20.3-1 Procedure of Project Cost Estimate ................................................................ 20-8 Figure 20.5-1 Procedure for Project Evaluation.................................................................... 20-18 Figure 21.1-1 Location of the Project Site ............................................................................ 21-1 Figure 21.2-1 Existing Road Condition ................................................................................ 21-4 Figure 21.2-2 Proposed Alignment ....................................................................................... 21-6 Figure 21.2-3 Typical Cross Sections.................................................................................... 21-7 Figure 21.3-1 Procedure of Project Cost Estimate ................................................................ 21-10 Figure 21.5-1 Procedure for Project Evaluation.................................................................... 21-21 Figure 22.1-1 Location of the Project Site ............................................................................ 22-2 Figure 22.2-1 Topography of the Coast between Hasik and Shuwaymiyah (Photos)........... 22-3 Figure 22.2-2 Assumed Alignments of Alternatives ............................................................. 22-5 Figure 22.2-3 Assumed Routs of Sub-Alternatives of Alternative 1..................................... 22-7 Figure 22.2-4 Conceptual Cross Section of Alternative 1-1 ................................................. 22-6 Figure 22.2-5 Example of Road Constructed on Large Rock Blocks Placed in Sea............. 22-8

Page 20: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xv -

Figure 23.1-1 Locations of Walayat and Hydrometric Stations ............................................ 23-4 Figure 23.1-2 Location of Wadis and Drainage Pattern ........................................................ 23-5 Figure 23.1-3 Average Rainfall Runoff for Northern Oman Gauged Catchments of 1996... 23-7 Figure 23.1-4 Wadis and Location of Flood Stations of Al Batinah Region......................... 23-7 Figure 23.2-1 Regional Flood Frequencies Analysis (Growth Curves for Northern Oman)........ 23-8 Figure 23.2-2 Frequency of Rainfall Intensities for Plains, Hills and Mountains................. 23-9 Figure 23.2-3 Flood Peaks Frequency (m3/sec) for Areas Greater than 10 km2 Al Batinah (50 Years Return Period) .............................................................. 23-12 Figure 23.2-4 Locations of Bridges along Al Batinah Highway........................................... 23-15 Figure 23.3-1 Location of Surveyed Irish Crossings along Al Batinah Highway................. 23-17 Figure 23.3-3 Locations of Existing Dams in Al Batinah Region ........................................ 23-21 Figure 23.3-4 Locations of Proposed Dams in Al Batinah Region....................................... 23-22 Figure 23.3-5 Fulaji, Al Ma’awil, and Jizzi Dams at Al Batinah Region.............................. 23-24 Figure 23.4-1 Rainfall Intensity Frequencies of 12 Hours for Plain, Hills and Mountains .. 23-27 Figure 23.4-2 Rainfall Intensity Frequencies of 24 Hours for Plain, Hills and Mountain .... 23-28 Figure 23.4-3 Maximum Rainfall Frequency Plots for Plain Areas of Northern Oman ....... 23-29 Figure 23.4-4 Results of Rating Curves of the Proposed Rehabilitative Irish Crossings of Al Batinah Region...................................................................................... 23-36 Figure 23.5-1 Schematic Drawing of Multi-Function Culvert.............................................. 23-37 Figure 23.5-2 Location Map of Irish Crossing on Batinah Highway.................................... 23-39 Figure 23.5-3 Conceptual Illustration of Three Cases........................................................... 23-41 Figure 23.5-4 Condition of Site Where Vehicle Type Culvert is Proposed........................... 23-44 Figure 23.5-5 Conceptual Sketch of Multi-Function Culverts Usable During Light Flood . 23-45 Figure 23.5-6 Conceptual Drawing of Underpass for Large Vehicles .................................. 23-46 Figure 24.1-1 Study Flow...................................................................................................... 24-2 Figure 24.1-2 Proposed Alignment of New Batinah Expressway......................................... 24-5 Figure 24.6-1 Final Profit by Type and Volume of Subsidies ............................................... 24-34 Figure 24.6-2 Cash Position .................................................................................................. 24-35 Figure 24.6-3 Economic Benefit ........................................................................................... 24-36

Page 21: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xvi -

ABBREVIATIONS

4WD : Four Wheel Drive 5YDP : Five-Year Development Plan AADT : Annual Average Daily Traffic AAGR : Annual Average Growth Rate AASHTO : American Association of State Highway and Transport Officials AC : Asphalt Concrete ADT : Average Daily Traffic amsl : above mean sea level AP : Aden Port ASFR : Age-Specific Fertility Rate BAR Bowshar – Al Armarat Road B/C : Benefit/Cost Ratio BC : Box Culvert BOOT : Build, Operate, Own and Transfer BOT : Build, Operate and Transfer bpd : Barrel per Day BS : British Standard CC : Cement Concrete DBST : Double-Layer Bituminous Surface Treatment DD : Detail Design DGC : Directorate General of Communications (in Dhofar) DG : Director General DGR : Directorate General of Roads DGWRA : Directorate General of Water Resources Assessment DNC : Do Nothing Case DOT : UK Department of Transport DST : Double Surface Treatment EBH : Existing Batinah Highway EIA : Environmental Impact Assessment ESCWA : Economic and Social Committee for Western Asia EIRR : Economic Internal Rate of Return FFCO : Flood Frequency Curve of Oman F/S : Feasibility Study FIRR : Financial Internal Rate of Return FPF : Flood Peak Frequency FTZ : Free Trade Zone FYDP : Five-Year Development Plan GCCS : Gulf Co-operation Council Standard GDP : Gross Domestic Products GR : Grouted Riprap GRDP : Gross Regional Domestic Products GVA : Gross Value Added ha : hectare HCM : Highway Capacity Manual HDM : Highway Design Manual

Page 22: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xvii -

HUC : Highway User Cost IB : Irish Bridge ICC : Industrial Clarification Code IEE : Initial Environmental Examination IMF : International Monetary Fund IR : Internal Regulation ISIC : International Standard Industrial Classification JICA : Japan International Cooperation Agency LFPR : Labor Force Participation Rate LNG : Liquefied Natural Gas LOS : Level of Service MAF : Mean Annual Flood M/P : Master Plan MCI : Ministry of Commerce and Industry Mcm : Million cubic meters MD : Ministerial Decision MOAF : Ministry of Agriculture and Fisheries MOC : Ministry of Communications MOCI : Ministry of Commerce and Industry MOD : Ministry of Defense MOE&W : Ministry of Electricity and Water MOF : Ministry of Finance MOG : Ministry of Oil and Gas MOH : Ministry of Health MOHC : Ministry of Heritage and Culture MONE : Ministry of National Economy MOT&C : Ministry of Transport and Communications MRMEWR : Ministry of Regional Municipalities, Environment and Water Resources MWR : Ministry of Water Resources N.A., N/A : Not Available NBE : New Batinah Expressway NPV : Net Present Value NR : National Road NSA : National Survey Authority OD : Origin-Destination PC : Precast Concrete PC : Pipe Culvert P/C table : Production and Consumption Table PCE : Passenger Car Equivalent PCSG : Pre-stress Concrete Steel Girder PCU : Passenger Car Unit PDO : Petroleum Development of Oman PFI : Private Finance Initiative POT : Peak Over Threshold PSS : Passing Sight Distance R/A : Roundabout RC : Reinforced Concrete

Page 23: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

- xviii -

RCSG : Reinforced Concrete Steel Girder RD : Royal Decree RD/DGC : Road Department of DGC RDI : Road Density Index RO : Riyal Omani ROP : Royal Oman Police ROW : Right of Way SCTP : Supreme Committee for Town Planning SGRF : State General Reserve Fund SPT : Standard Penetration Test QSR : Quriyat - Sur Road SSD : Stopping Sight Distance ST : Surface Treatment TEU : Twenty Feet Equivalent Unit TFR : Total Fertility Rate TOR : Terms of Reference TRB : Transportation Research Board (USA) TRL : Transport Research Laboratory TTC : Travel Time Cost UAE : United Arab Emirates UK : United Kingdom VCR : Volume/Capacity Ratio veh : Vehicle VOC : Vehicle Operating Cost vpd : Vehicle per day ph : Vehicle per hour

Page 24: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

PART III

PRE-FEASIBILITY STUDY

Page 25: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

CHAPTER 17

SELECTED PROJECTS FOR PRE-FEASIBILITY STUDY

Page 26: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 1

CHAPTER 17

SELECTED PROJECTS FOR PRE-F/S STUDY 17.1 SELECTION PROCEDURE

This Study on the Road Network Development in the Sultanate of Oman is composed of two main phases. The first phase is to formulate the development plan for primary and secondary road networks to the target year of 2030. The main task of the second phase is to carry out preliminary feasibility studies (Pre-F/S) on selected projects with high priority for implementation, basically from the coming 7th Plan. The 7th Plan includes 19 road projects, either as dualization or new construction, with a total length of more than 1,000 kilometers. In general, the main links or skeleton of the road network in Oman is well developed and connects regions, wilayats and major development centers as well as major transport facilities as airports and ports. In addition, it can meet the present transport demand requirements and basic functions of a road network in a satisfactory level. In the short-term development of the road network, the Master Plan generally shows that small-scale projects for improvements are required to improve the overall functions of the road network, while major and large-scale projects are required in the medium and long terms due to the considerable increase in the transport demand in future. In the selection of the high priority projects for the Pre-F/S, basically significant road projects in line with the policy and concept of the Nationwide Master Plan are selected, providing that such projects require Pre-F/S before future implementation. In the mean time the following criteria are considered: Urgency: Projects that are in urgent need for implementation, and intended to solve urgent transport problems and greatly improve the network function. Integration: Projects that promote and provide integration with other socioeconomic development projects. Regional Balance: Projects that are distributed in different regions to promote regional development and knowledge for regional offices. Technical Issues: Projects that require technical depth in important issues such as environmental assessment, hydrological analysis at Wadi locations and privatization schemes through the systems of built-operate-transfer (BOT) and public-private- participation (PPP).

Page 27: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 2

17.2 STATUS OF 7TH 5-YEAR PLAN PROJECTS The projects included under the 7th Plan are the most urgent and required projects that will provide quick impact on the efficiency of the road network and meet the objectives and policy of the Master Plan. The status of all projects included in the 7th 5-Year Plan is investigated through information from both DGR and DGC. As the 7th Plan will start by the year 2006 with only short period before implementation activities, most of its planned projects are already in the design or tendering stages after carrying out required feasibility studies as shown in Table 17.2-1. Table 17.2-1 Status of 7th Plan Projects Project

No. Project Region

LengthKm

Project Status

D3-1 Nizwa - Bahla A’Dakhliyah 40 FS+PD June 04 - UDD3-2 Bahla - Ibri Adh Dhahira 85 FS+PD June 04 - UDD5-1 Majis (Sohar) - Az Zarub Batina/A’Dhahi 81 FS April 04 - TD D7 Ma'mura - Taqah Dhofar 20 TD 1993 D8 Muladdah - Hazm Batinah 24 TD 1998 D-9 Quriyat - Sur Phase III Ash Sharqiya 18 TD 2004 N4 Diba - Khasab Musandam 95 FS June 04 - UD N5 Lima Link - Khasab Musandam 25 FS - UD N6 Al Ashkharah - Shanna Ash Sharqiya 164 FS March 04 – UD N9 Marmul - Sawqrah Dhofar 140 FS March 04

N10 Shelim-Shuaymiyah Dhofar 48 FS April 04 + TD N12 Madinat AL Haq-Nashib Dhofar 28 PD May 04 - UD N14 Teetam-Qaftat Dhofar 12 PD June 04 - UD N26 Thumrait - Marmul Dhofar 86 FS + TD N27 Hamra-Rustaq, PhaseIV Bat/Ad Dhakh. 28 - N28 Yanqul-Fida-Dank Adh Dhahira 41 TD N30 Madha - Dafta Musandam 15 - N36 Mahlah - Ismaiyah Ash Sharqiya 38 - N47 Al Hij - Flim Al Wusta 19 -

Notes: FS: Feasibility Study (by consultant; economic analysis based on rough design) PD: Preliminary Design DD: Detailed Design TD: Tender Documents (by consultant) UD: Under Design (by consultant for complicated projects or by contractor for simple

projects; to include P/D, D/D and TD)

Page 28: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 3

17.3 SELECTED PROJECTS Due to the limited number of projects selected from the 7th Plan that meet the criteria and require Pre-F/S, and that some of the projects in the 8th Plan are important, but delayed due to financial constraints, it was agreed with DGR to include some of these projects in the Pre-F/S stage. The selected projects from the 8th Plan are considered as complicated projects that have technical importance and require special considerations and specific viability before implementation.

The selected road projects for Pre-F/S, that are in line with the policy and concept of the Nationwide Master Plan and confirm with the established criteria are as presented in Table 17.3-1. Figure 17.3-1 shows a location map for the selected projects.

Table 17.3-1 Pre-F/S Projects

Major Task

Road Project

No. Length(km)

Region Plan Justification

Hamra – Rustaq N27 28 Bat/A’Dakh 7th

To improve network efficiency and high transport demand

Madha – Dafta N30 15 Musandam 7th To strengthen integration and social welfare

Al Hij – Flim N47 19 Al Wusta 7th To promote regional and tourism development

Technical Study

Mahlah – Ismaiyah

38 A’Sharqiya 7th

To improve network efficiency in populated mountainous areas

Environ-mental Study

Hasik – Shuwaymiyah

120 Dhofar 8th

To assess the road impact as it passes through environmentally protected areas in both mountain and sea sides

Wadi Study

Batinah Highway

U1 270 Batinah 8th

To carry out hydrological analysis at wadis to replace Irish crossings to culverts and to provide underpasses at at-grade junctions

Manage-ment Study

New Batinah Expressway

N1 246 Batinah 8th

To study financing and management systems for private sector participation

Page 29: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 4

Figure 17.3-1 Location Map of Pre-F/S Projects

Page 30: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 5

The four projects selected from the 7th Plan, as listed above, will be subject to all Pre-Feasibility Study tasks. As for the three projects selected from the 8th Plan, the study will concentrate only on the major task for each project. The following sections provide an explanation on the nature of each of the selected projects.

1) Hamra – Rustaq Road Project (Phase 4): A 2-lane paved road connecting Ar

Rustaq in Batinah Region and Al Hamra in Ad Dakhliyah Region is currently being constructed across Al Hajar Al Ghabri Mountain Range. This road project is divided into 4 phases. Phase 1 (L = 15.0 km) is already completed. Phase 2 (L = 13.7 km) is under construction. Phase 3 (L = 9.5 km) is being designed. Phase 4 is the final section of this road and connects this road with NR No. 13. Upon completion, Al Hamra-Rustaq Road is expected to contribute to strengthen the communication between Barka/Rustaq area and Al Hamra/Bahla/Nizwa area. It is also expected to function as a detour route for NR 15 (Rusayl-Nizwa Road).

2) Madha – Dafta Road Project: Madha is the central town of Oman territory in UAE

territory, isolated from the main Oman territory of Musandam. (See Chapter 19.) There is a road connecting Qidfa in UAE (in the east of Madha) and Dafta in UAE (in the west of Madha), traversing the territory of Oman in east-west direction. This road passes an isolated UAE territory existing in Oman territory around Madha. The local residents desire to go to Dafta without passing the isolated UAE territory in Madha area. Therefore, they requested DGR to alter the route of the existing road so that they can go to Dafta without passing the isolated UAE territory.

3) Al Hij – Flim Road Project: Flim is small fishing village. There is a small island

called Mahawt Island about 5 km offshore from Flim. This island is currently used as the base for fishing. The sea between Mahawt Island and Flim is very shallow and the bottom of the sea is visible during ebb tide. Substantial part of the island and shore is covered by mangrove. The sea water is clear. There is plan to develop this area as a tourist spot. The Project is to support the tourism development, as well as to improve the access of the local residents to the market (to sell fish).

4) Mahlah – Ismaiyah Road Project: The central valley of Al Hajar Ash Sharqi

Mountain Range has rich underground and surface water. Accordingly, this area has high potential of agriculture and tourism. The Project Road longitudinally traverses the central valley. The section of NR 25 from Sabikah on NR 23 to Mahlah is already paved. Therefore, Mahlah – Ismaiyah Road is an extension of

Page 31: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 6

this NR 25. Also, Project N33 (Tiwi-Ismaiyah) and N38 (Al Mazari-Ghubrat At Tam) are to be connected to Mahlah – Ismaiyah Road and N37 (Qaran-Maqal- Sayq-Sabt-NR 23) Road. Accordingly, this road, together with N37 Road, is expected to function as the axis of the local network. They are also expected to function as the local detour route for NR 23(Bid Bid - Sur Road).

5) Hasik – Shuwaymiyah Road: This proposed road is the missing link in the coastal

road south of the country in Dhofar. While this road is expected to enhance the function of road network in the area and contribute to socioeconomic acitivities of the area, the area is environmentally critical that require great care in identifying its alignment and design. The road is considered as an important link in the road network; however, implementation of the road will be based on the results of its EIA.

6) Upgrading of Batinah Highway: This project is to provide culverts at

Irish-crossing sections along this most important highway in the country in order to upgrade it as an all-weather highway. In addition, the viability of providing grade-separation structures at at-grade junctions and intersections in order to provide safety facilities at such black-spots is investigated.

7) New Batinah Expressway: This project is to construct a divided, 4-lane, full

access-controlled expressway. The Project Road is to run parallel to the existing Batinah Highway. The location of the route is currently being studied by the Supreme Committee for Town Planning (SCTP). According to SCTP, the most probable location of the route is approximately 10 km from the existing Batinah Highway to south (to the mountain). At the Muscat-side end (near Filaiji R/A or Halban R/A), this expressway is to be connected to the Southern Expressway which traverses As Seeb and reach Al Qurm. Construction of the Southern Expressway is expected to be started in near future. (Tender documents have been prepared.) The Government intends to introduce “private participation” for financing the cost of the New Batinah Expressway. But private participation in the area of road is still new to Oman. Therefore, possibilities of private participation under a few scenarios are examined.

17.4 STUDY PROCEDURE

For the four projects categorized as “Technical Study” in Table 17.3-1, (Hamra – Rustaq, Madha – Dafta, Al Hij – Flim, and Mahlah – Ismaiyah ), studies are conducted in the following procedures. 1) Identification of study section: This is done on 1:100,000 topographical map.

Page 32: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

17 - 7

General alignment and starting and end point are confirmed. Discussion is held between DGR and the Study Team as Necessary.

2) Field survey: The Study Team members and DGR officials (mainly the Counterparts), and relevant consultant or contractor, visit the site of the project and confirm the possible alignment, start point and end point of the study road. Then, the Study Team members conduct simplified survey on the topography along the proposed alignment. Locations of necessary drainage facilities are marked and recorded. The GPS data of the proposed alignment is recorded to be used in presenting the proposed alignment on 1:100,000 topographical map.

3) Preliminary design: The Study Team member draws cross sections and estimate quantity of earth works. Quantities of other items such as slope protection, drainage, pavement, etc are estimated. The drawings of alignment, cross sections, drainage facilities, etc. are complied in a separate volume (“Drawings”).

4) Cost estimate: Based on the quantities estimated in the above, construction cost is estimated.

5) Economic evaluation: Using the construction cost as described above and estimated economic benefits calculated from the estimated traffic volume, three economic indicators (Net Present Value (NPV), Benefit/Cost Ratio (BCR) and Internal Rate of Return (IRR)) are calculated.

For the “Environmental Study” of Hasik-Shuwaymiyah Road, almost same procedure was followed except economic evaluation. In case of this road, the main focus was consideration on environmental impact. Therefore, economic evaluation was not carried out. For the “Wadi Study” of Batinah Highway which involves construction box culverts, types of culverts are selected based on the survey on the conditions of Irish crossings. The costs are estimated based on the design of culverts. Economic evaluation is made by comparing the cost and economic benefit accruing from the elimination of disturbance to the traffic. For the “Management Study” of New Batinah Expressway, some variations of toll rate system and resulting toll revenues are estimated and examined. Possible tolling system is proposed.

Page 33: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

CHAPTER 18

HAMRA - RUSTAQ ROAD

Page 34: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 1

CHAPTER 18

AL HAMRA - RUSTAQ ROAD (PHASE 4) 18.1 OBJECTIVE OF THE PROJECT

The existing Al Hamra - Rustaq road (Project No. N27, Batinah Region) which connects between National Road (NR) 13 in Rustaq side and NR 21 in Al Hamra side is unpaved stony and rough road. The road is passable only by four (4) wheel drive (4WD) vehicle. In Master Plan Study, this road becomes important road link between NR 13 and NR 21 across Al Hajar Al Ghabri Mountain Range connecting A’Dakhliyah Region with the coastal area. Taking into account the importance of this road, the Government intends to improve this Al Hamra - Rustaq road. The improvement project of this road divided into four (4) stages as described below: Phase 1: Length 15.000 kilometers Phase 2: Length 13.660 kilometers Phase 3: Length 9.500 kilometers Phase 4: Length 28.300 kilometers

Location map is shown in Figure 18.1-1.

Figure 18.1-1 Location of Project Site

Project Site

Page 35: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 2

The construction of Phase 1 project was already completed in January 2003 and opened to traffic, and the construction of Phase 2 project is now on-going and is expected to be completed in 2005. Phase 3 project has already been tendered-out and designing is now being conducted by the contractor. However, due to some difficulties of the severe terrain conditions, preliminary design of Phase 3 is haltered at present, and design of Phase 4 has not been started yet. Therefore, DGR requested the Study Team to carry out the pre-feasibility study of this project. The objectives of the project are: a) To complete road linkage between NR 13 and NR 21 across Al Hajar Al Ghabri

Mountain Range, b) To provide proper access road for people who are living along the project road, and c) To provide a diversion road of NR 15 between Muscat and Nizwa if necessary.

18.2 ALIGNMENT AND PRELIMINARY DESIGN 18.2.1 Physical Features of Project Site

The topography of the area where Al Hamra - Rustaq road traverses is roughly divided into northern side and southern side according to its topographic features. The southern side is comparatively moderate rolling terrain, but climbs up approximately 1,400 meters of the elevation before reaching the peak of the mountain. The northern side has the cliff at the top of the mountain and climbs down approximately 1,000 meters of the elevation to the foot of the cliff, where the village of Hatt is located in Wadi al Hat. From Hatt to the Rustaq side, the road is passing through mountainous terrain and sometimes is required to pass the small ridges where the road alignment transfer from one wadi to the other. Therefore, the road traverses almost inside the wadis, and gets down the altitude moderately to 400 meters above sea level.

18.2.2 Existing Road Condition

The road stretch is divided into four sections by the construction phases. Phase 1 & 2 are located in the southern side while Phase 3 & 4 are in the northern side. This Study focuses only on Section 4 between the village of Hatt and the end of the road joint with NR 13. The project road (Section 4) starts at the village of Hatt, then, climbs down the mountain along Wadi al Hat for about 2 kilometers. The road grazes the wadi bed in short distance at the village of Bilad Sayt then climbs up the ridge again. The road alignment is interrupted by the deep valley and it is forced to detour. The road goes upstream to cross the wadi at Chainage 4.8 kilometer then comes back the

Page 36: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 3

opposite of the valley. At this section, between Chainage 3.7 kilometer and 6.1 kilometer, the road faces very critical terrain condition with vertically standing cliff and steeply cut deep valley, named Wadi Bimah, such as that the mountain side slopes are overhanging, the road width is quite narrow, the shoulder is barely fixed by loose masonry and horizontal alignment just traces the topography without any relation to geometric requirements of road. Wadi Bimah and Wadi al Hat meet and become one stream at downstream beyond just few hundreds meters. From Chainage 8.4 kilometer, the road passes inside, or side bank of, the wadi up to Chainage 12.9 kilometer. At the point of 12.9 kilometer the wadi flows down to the narrow chasm of the mountain. The road goes away from wadi and traverse the ridge to another wadi, named Wadi Bani Awf. From Chainage 13.8 kilometer to the end point of Phase 4, the road just follows and passes inside Wadi Bani Awf. The wadi is passing through the valley and is narrow and go zigzag at the most of the stretch, but occasionally becomes relatively wider. The existing condition of the project road is shown in Figure 18.2-1.

Page 37: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 4

Figure 18.2-1 Existing Road Condition

End Point 28.3km

Wadi Bani Awf at 27km

Wadi al Hat & Bimah meet

Beginning Point 0km

Proposed Bridge Location

Wadi Bani Awf at 14km

Wadi Bani Awf at 9km

NR

13A

lA

wabi

Rustaq

Page 38: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 5

18.2.3 Proposed Road Alignment

The existing road passes through the limited space surrounded by cliffs and steep slopes of mountains. The peaks of the mountains adjacent to the road are over 1,000 meters high and many streams have carved the mountain slope. As the result of the investigation, it is assumed that the route of the planned road follow the existing road because preferable alternative route could not be found from the topographic map. However, alteration of alignment is proposed at the critical road section between chainage 3.7 kilometer and 6.1 kilometer to avoid the risks of the stability of the road. As the alternative, this Study suggests crossing the deep valley with a bridge, span length of which becomes approximately 120 meters and bridge length is approximately 190 meters. In this Study, the arch bridge made by the pre-stressed concrete shall be adopted with the consideration on the appropriateness for that span length, suitability on the site condition and availability of the materials. This alternative is also short-cuts the road length by about 2 kilometers. Figure 18.2-2 shows the rough sketch of the proposed bridge.

Figure 18.2-2 Proposed Bridge The road section inside the wadi shall be closed to bank basically to secure sufficient cross-sectional area for the flood stream. The elevation of the road shall be raised by 1.0 meter on average from the river bed to keep the road surface above the water level during the flood usually experienced. Figure 18.2-3 shows the proposed alignment of the project road.

Page 39: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 6

STA. 10+000

STA. 20+000

BEGINNINGSTA. 0+000

ENDSTA. 28+300

ProposedBridge Site

Section 3

Figure 18.2-3 Proposed Alignment 18.2.4 Preliminary Design

The proposed cross sections follow the Highway Design Manual of Oman (HDM). As mentioned in HDM, the carriageway of secondary road shall be 7.0 meters and paved shoulder of 1.5 meters in width shall be provided on both sides in this project. Basically the verge of 2.0 meters in width shall be adopted on both sides as stated in HDM. But the verge will be omitted or narrowed in the mountainous terrain and rolling terrain,

Page 40: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 7

where its vertical grade is steeper than 4 %, to avoid the erosion of unpaved verge surface and to install the side ditch on that space. The side ditches shall be lined by the grouted riprap on those sections to protect the pavement structure from the erosion. Where the slope of the mountain is very steep, the retaining wall shall be adopted to secure the necessary road width. The retaining wall will be either gravity type or reverse T-shape type depending on the site condition, and guardrail or concrete barrier shall be installed. Inside the wadi, road embankment shall be protected from the flood stream by the grouted riprap. As the result of the above consideration, the typical cross sections are proposed as shown in Figure 18.2-4.

Figure 18.2-4 Typical Cross Sections

shoulder shoulderside ditch vergecarriageway

AC Cource 50mm

Granular Base Course 150mm

Granular Subbase Course 150mm

2.0% 2.0% 5.0%

Mountainous & Cliff Terrain

41

Retaining Wall

Guardrail

verio

us

shoulder shoulderverge vergecarriageway

1.51

AC Cource 50mm

Granular Base Course 150mm

Granular Subbase Course 150mm

2.0% 2.0%5.0% 5.0%

Inside Wadi

River Bed River Bed

Grouted Riprap

Ave

rage

1000

shoulder shouldercarriageway

2.0% 2.0%

on Bridge

sidewalk sidewalk

Page 41: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 8

18.2.5 Pavement Design

The detail study for the pavement is not carried out in this Study because the traffic is forecasted to be small and bearing capacity of the subgrade seems to be high. Accordingly, the pavement structure similar to other secondary road may be adopted. In this Study, the same pavement structure of Section 3 of the same road, which is designed recently, is adopted.

18.2.6 Structure Design

HDM shows the standard drawings for the several types of structures, including retaining wall, cross drainage and slope protection, and they are used commonly in the projects whether they are under designing, construction or completed. In this Study, the structures are designed in accordance with HDM and the standard drawings of HDM are adopted in this Study for most of the cases.

18.2.7 Drainage and Cross Drainage Facilities

Through the site survey of the project road, necessary drainage facilities were studied and listed as shown in Table 18.2-1.

Table 18.2-1 List of the Drainage Facilities (1/2)

Chainage Drainage Chainage Drainage1 0km+300 Pipe 1-900 21 5km+100 Box 3-3.0*3.02 0km+500 Pipe 1-1500 22 5km+400 Box 1-3.0*3.03 0km+800 Pipe 2-1500 23 5km+500 Pipe 1-9004 0km+900 Pipe 1-1500 24 5km+900 Pipe 1-9005 1km+200 Pipe 1-1500 25 6km+100 Bridge(Short Cut)6 1km+300 Pipe 1-1500 26 6km+200 Pipe 1-9007 1km+600 Pipe 1-1500 27 6km+500 Pipe 1-15008 1km+700 Pipe 1-1500 28 7km+000 Pipe 1-15009 2km+025 Irish Bridge (50m) 29 7km+200 Box 1-3.0*3.0

10 2km+225 Irish Bridge (50m) 30 7km+300 Pipe 2-150011 2km+400 Box 1-3.0*3.0 31 7km+500 Pipe 1-60012 2km+700 Box 1-3.0*3.0 32 8km+120 Irish Bridge (40m)13 3km+000 Pipe 1-1500 33 8km+740 Irish Crossing (80m)14 3km+300 Pipe 1-1500 34 9km+130 Irish Crossing (60m)15 3km+500 Pipe 1-900 35 9km+225 Irish Crossing (50m)16 3km+700 Bridge(Short Cut) 36 9km+715 Irish Crossing (30m)17 3km+900 Pipe 1-900 37 10km+700 Box 2-3.0*3.018 4km+100 Pipe 1-900 38 10km+930 Irish Crossing (60m)19 4km+400 Pipe 1-900 39 11km+300 Box 3-3.0*3.020 4km+820 Irish Bridge (40m) 40 11km+735 Irish Crossing (70m)

Page 42: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 9

Table 18.2-1 List of the Drainage Facilities (2/2)

Chainage Drainage Chainage Drainage41 12km+130 Irish Crossing (60m) 56 18km+618 Irish Crossing (35m)42 12km+335 Irish Crossing (70m) 57 19km+125 Irish Crossing (50m)43 12km+913 Irish Bridge (25m) 58 19km+950 Irish Crossing (100m)44 13km+400 Pipe 2-1500 59 20km+750 Irish Crossing (100m)45 14km+115 Irish Crossing (30m) 60 21km+215 Irish Crossing (30m)46 14km+600 Pipe 1-1500 61 21km+445 Irish Crossing (90m)47 15km+100 Pipe 1-1500 62 21km+845 Irish Crossing (90m)48 15km+340 Irish Crossing (80m) 63 22km+530 Irish Crossing (60m)49 15km+530 Irish Crossing (60m) 64 24km+535 Irish Crossing (70m)50 15km+845 Irish Crossing (90m) 65 24km+830 Irish Crossing (60m)51 17km+140 Irish Crossing (80m) 66 25km+740 Irish Crossing (80m)52 17km+730 Irish Crossing (60m) 67 27km+035 Irish Crossing (70m)53 18km+120 Irish Crossing (40m) 68 27km+150 Irish Crossing (100m)54 18km+200 Box 1-3.0*3.0 69 27km+800 Box 3-3.0*3.055 18km+430 Irish Crossing (60m)

Page 43: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 10

18.3 Preliminary Cost Estimation 18.3.1 Procedure of Project Cost Estimate

The procedure of project cost estimation is shown in Figure 18.3-1. The estimate is made based on the unit prices of construction material, labor costs and equipment costs which are obtained from the survey of the current market prices. The unit costs of major construction items are decided after comparing the estimated unit cost with latest bid prices. The prices of items needed in the project, but not listed in the table are quoted from those available in Japan and converted to RO using the exchange rate of ; US$ 1.0 = RO 0.385 = JPY 108. Engineering services cost is estimated as the percentage of the construction cost. ROW acquisition cost for new roads and widening are not estimated because there is no necessity of new land acquisition for roads.

Figure 18.3-1 Procedure of Project Cost Estimate

Unit Cost of Major

Construction Items

Latest Bid Prices Unit Price of

- Construction Materials

- Labor Cost

- Equipment Cost

ROW Acquisition Cost

- New Roads

- Widening

Engineering Service

Cost

(% of Construction Cost) Construction

Cost Estimate

Project Cost

Quantity

Estimate

Market

Prices

Page 44: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 11

18.3.2 Unit Price and Cost of Major Construction Items

Unit prices of major construction materials, labor cost and equipment cost, which are determined based on the investigation of the latest market prices, are shown in Tables 18.3-1, 18.3-2 and 18.3-3, respectively. The major construction items are defined from “The Sultanate of Oman, General Specification for Roads, April 1994” and their unit costs of the road with and without the proposed bridge are presented in Table 18.3-4 and Table 18.3-5, respectively.

Table 18.3-1 Average Prices of Major Construction Materials (2004 Prices)

No. Material Description Unit Unit Price (RO) 1 2 3 4 5 6 7 8 9

10 11 12

13

14 15 16 17 18 19 20 21 22 23

Aggregates for granular sub-base course Aggregate for aggregate base course Aggregates for bituminous base course Fine aggregate for concrete Coarse aggregate for concrete Stone for drainage, masonry and slope protection Asphalt cement, grade 60-70 on site Asphalt cement, grade 50-60 on site Emulsified asphalt, grade RS-1 on site Cutback asphalt, MC and RC type on site Portland cement on site Deformed billet steel bars, AASHTO M31 grade 60 (High Yield) of any diameter Deformed billet steel bars, AASHTO M31 grade 40 (High Yield) of any diameter Highway signs Highway sign support Timber plank, on site Timber props, on site Wire mesh gabion, on site Explosive, on site Gas oil, on site Gasoline, Premium Gasoline, Regular Diesel

Cu.m. Cu.m. Cu.m. Cu.m. Cu.m. Cu.m. Ton Ton Ton Ton Ton Ton

Ton

Sq.m.

Nr. Cu.m Cu.m. Ton Kg

Liter Liter Liter Liter

3.0003.0003.0004.0003.5003.000

90.00080.000

100.000100.00025.000

250.000

225.000

50.00025.000

150.000150.000225.00050.0000.5000.1200.1140.102

Source: Study Team Survey

Table 18.3-2 Labor Cost (2004 Prices) No. Labor Category Unit Unit Rate (RO) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Supervisor Site Surveyor Foreman 1st Class Operator 2nd Class Operator Mechanic Driver Skilled Labor Semi-skilled Labor Mason Painter Carpenter Steel Fixer Electrician

Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

3.0003.0002.0002.0001.8001.7001.8001.2001.0001.2001.2001.2001.2001.200

Source: Study Team Survey

Page 45: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 12

Table 18.3-3 Hourly Cost of Major Construction Equipments (2004 Prices) No. Construction Equipment Hourly Cost (RO) 1 2 3 4 5 6 7 8 9

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57

Motor grader from 100 HP to 120 HP Motor grader from 120 HP to 150 HP Tractor from 60 HP to 100 HP Bulldozer with ripper from 100 HP to 150 HP Bulldozer with ripper from 150 HP to 200 HP Bulldozer with ripper from 200 HP to 250 HP Bulldozer with ripper from 250 HP to 300 HP Wheel Tractor up to 50 HP Wheel Tractor over 50 HP Motor scraper capacity up to 18 cu.m. Motor scraper capacity 18 to 24 cu.m. Sheeps foot roller from 5 to 10 ton Vibratory compactor with prime mover up to 5 ton Pneumatic compactor with prime mover from 30 to 50 ton Pneumatic self-propelled roller from 15 to 20 ton Tandem roller up to 8 ton Tandem roller from 8 to 12 ton Triaxle roller from 10 to 15 ton Light frog-rammer 0.1 ton Heavy frog-rammer 0.5 ton Wheel loader 1.2 to 1.6 cu.m. Wheel loader 1.6 to 2.5 cu.m. Excavator up to 0.8 cu.m. Excavator from 0.8 to 1.2 cu.m. Bituminous mixing plant with batching apparatus up to 80 ton/hr Bituminous mixing plant with batching apparatus 80 to 150 ton/hr Finisher up to 80 ton/hr Finisher from 80 to 120 ton/hr Bitumen sprayer up to t ton Tanker truck up to 6 cu.m. Dump truck up to 10 ton Dump truck from 10 ton to 15 ton Screening plant from 80 to 100 ton/hr Crushing plant up to 40 ton/hr Crushing plant from 40 to 60 ton/hr Air compressor up to 6000 l/m Air compressor over 6000 l/m Mechanical broom Power water pump Steel cutting machine Steel bending machine Belt conveyor Concrete mixer up to 0.5 cu.m. Concrete mixer over 0.5 cu.m. Automatic concrete batch plant without mixing Transmixer up to 5 cu.m. Concrete vibrators Crane up to 5 ton Crane with boom and jib from 5 to 10 ton Crane with boom and jib over 10 ton Generator 60 ~ 75 Kw Generator 100 Kw Generator 150 ~ 200 Kw Drilling Equipment Gravel strewer Asphalt cutter Vehicle for foreman and surveyor

12.00015.00012.00012.00016.00018.00020.000

8.0009.000

18.00022.000

7.0005.0005.0006.0005.0007.0008.0001.0001.5006.0008.0006.0009.000

20.00030.00010.00012.000

7.5005.5005.0006.000

18.00013.00015.000

2.5004.0004.0001.5001.0001.0002.0002.5004.000

16.00015.000

1.0005.000

10.00015.000

2.5005.0009.000

10.0005.0002.0005.000

Source: Study Team Survey

Page 46: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 13

Table 18.3-4 Unit Cost of Major Construction Items of the Road with the Proposed Bridge No. Description Unit Unit Cost (RO)

200 EARTHWORKS203 Earthworks Excavation

Suitable excavation to embankment Cu. m. 1.944 1.034 53% 0.859 44% 0.052 3%Suitable excavation to waste Cu. m. 1.733 0.920 53% 0.767 44% 0.046 3%Borrow excavation to embankment Cu. m. 3.660 1.300 36% 2.295 63% 0.065 2%

206 Excavation and Backfilling for StructuresStructural excavation in soils to a depth of 2m. Cu. m. 1.475 0.758 51% 0.679 46% 0.038 3%Structural excavation in rock to a depth of 2m. Cu. m. 2.625 1.392 53% 1.164 44% 0.070 3%Structural excavation in rock to a depth more than 2m. Cu. m. 4.043 1.855 46% 2.095 52% 0.093 2%

300 GRANULAR AND STABILIZED SUBBASE, BASECOURSE AND STABILIZED SUBGRADE302 Granular Subbase

Class A Subbase Cu. m. 5.000 2.094 42% 2.801 56% 0.105 2%Class B Subbase Cu. m. 4.000 1.675 42% 2.241 56% 0.084 2%

303 Aggregate BasecourseClass A Basecourse Cu. m. 5.000 2.112 42% 2.783 56% 0.106 2%Class B Basecourse Cu. m. 4.000 1.689 42% 2.226 56% 0.084 2%

400 BITUMINOUS PAVEMENT401 Bituminous Prime Coat and Tack Coat

Prime Coat such as MC70 Kg 0.120 0.078 65% 0.039 32% 0.004 3%Tack Coat such as RC250 Kg 0.150 0.097 65% 0.048 32% 0.005 3%

402 Bituminous BasecourseBituminous Basecourse Cu. m. 17.000 10.893 64% 5.563 33% 0.545 3%

405 Bituminous Wearing CourseBituminous Wearing Course Cu. m. 17.000 10.893 64% 5.563 33% 0.545 3%

500 CONCRETE AND CONCRETE STRUCTURES504 Concrete for Structures

Concrete Class 28/20 Cu. m. 40.000 13.954 35% 25.348 63% 0.698 2%509 Reinforcing Steel

High yield steel bars ton 250.000 153.428 61% 88.901 36% 7.671 3%Mild steel bars ton 250.000 152.690 61% 89.676 36% 7.634 3%

800 DRAINAGE AND SERVICE DUCTS801 Pipe Culverts

Reinforced Concrete Pipe Culvert 600 mm Lin. m. 35.000 18.270 52% 15.817 45% 0.914 3%Reinforced Concrete Pipe Culvert 900 mm Lin. m. 75.000 39.150 52% 33.893 45% 1.958 3%Reinforced Concrete Pipe Culvert 1500 mm Lin. m. 155.000 80.910 52% 70.045 45% 4.046 3%

900 SLOPE PROTECTION AND STABILIZATION901 Rip Rap

Loose stone riprap Class A Cu. m. 6.000 2.477 41% 3.399 57% 0.124 2%Loose stone riprap Class B Cu. m. 6.000 2.477 41% 3.399 57% 0.124 2%Mortared stone riprap Cu. m. 15.000 4.438 30% 10.340 69% 0.222 1%

902 GabionsGabions Cu. m. 13.000 4.977 38% 7.774 60% 0.249 2%

906 Ditch liningDitch lining (150mm thick) Sq. m. 2.000 0.573 29% 1.399 70% 0.029 1%

1200 SIDEWALKS, PAVED AREAS AND CURBS1202 Curbs

Precast concrete curb, Class 28/20 non-mountable type Lin. m. 5.000 1.744 35% 3.169 63% 0.087 2%Precast concrete curb, Class 28/20 mountable type Lin. m. 5.000 1.744 35% 3.169 63% 0.087 2%Precast concrete curb, Class 28/20 lip type Lin. m. 5.000 1.744 35% 3.169 63% 0.087 2%

1300 SAFETY BARRIERS, DELINEATORS AND FENCES1301 Corrugated Steel Beam Safety Barrier

Safety barrier beam (Class B, W-section) Lin. m. 5.000 3.610 72% 1.210 24% 0.180 4%Safety barrier post (Type C) including foundation Nr. 12.000 8.664 72% 2.903 24% 0.433 4%End anchorage (ramp down), including post (Type C) and foundation Nr. 25.000 18.050 72% 6.048 24% 0.902 4%W-beam terminal sectionRe-fixing of safety barrier beam Nr. 15.000 10.830 72% 3.629 24% 0.541 4%Re-fixing of safety barrier post including foundation Lin. m. 0.500 0.361 72% 0.121 24% 0.018 4%Re-fixing of end anchorage (ramp down) including posts Nr. 3.000 2.166 72% 0.726 24% 0.108 4%Re-fixing of W-beam terminal section Nr. 16.000 11.552 72% 3.870 24% 0.578 4%

1302 Concrete safety barrierConcrete safety barrier (Type A) Lin. m. 55.000 19.186 35% 34.854 63% 0.959 2%Concrete safety barrier (Type B) Lin. m. 30.000 10.465 35% 19.011 63% 0.523 2%

1303 Reflectorized Markers for safety barriersReflectorized markers (red) attached to Guardrail Nr. 4.000 2.888 72% 0.968 24% 0.144 4%Reflectorized markers (red) attached to concrete barrier Nr. 3.000 2.166 72% 0.726 24% 0.108 4%

1304 DelineatorsFlexible delineators Nr. 12.000 8.664 72% 2.903 24% 0.433 4%Irish crossing markers Nr. 35.000 25.270 72% 8.467 24% 1.263 4%Irish crossing water depth gauges Nr. 42.000 30.324 72% 10.160 24% 1.516 4%

1400 HIGHWAY SIGNS AND ROAD MARKINGS1401 Highway Signs

Triangular, side 900mm Nr. 25.000 18.050 72% 6.048 24% 0.902 4%Triangular, side 1100mm Nr. 30.000 21.660 72% 7.257 24% 1.083 4%Triangular, side 1200mm Nr. 40.000 28.880 72% 9.676 24% 1.444 4%Circular, diameter 900mm Nr. 30.000 21.660 72% 7.257 24% 1.083 4%Circular, diameter 1200mm Nr. 85.000 61.370 72% 20.562 24% 3.068 4%Rectangular sign Sq.m. 50.000 36.100 72% 12.095 24% 1.805 4%Kilometer post (sign No. 323) Nr. 25.000 18.050 72% 6.048 24% 0.902 4%Sign post support assembly, (Type 1A) Nr. 25.000 18.050 72% 6.048 24% 0.902 4%Sign post support assembly, (Type 1B) Nr. 54.000 38.988 72% 13.063 24% 1.949 4%Sign post support assembly, (Type II) Nr. 68.000 49.096 72% 16.450 24% 2.455 4%Sign post support assembly, (Type IIIA) Nr. 150.000 108.299 72% 36.286 24% 5.415 4%Sign post support assembly, (Type IIIB) Nr. 155.000 111.909 72% 37.495 24% 5.595 4%Re-fixing of removed highway sign (any size with single post) Nr. 20.000 14.440 72% 4.838 24% 0.722 4%Re-fixing of removed highway sign (any size with multiple post) Nr. 25.000 18.050 72% 6.048 24% 0.902 4%

1402 Road MarkingsTraffic lines (mechanically sprayed) Sq. m. 1.600 1.155 72% 0.387 24% 0.058 4%Curb painting (black and yellow) Sq. m. 1.000 0.722 72% 0.242 24% 0.036 4%Reflecting road studs (double face) Nr. 3.500 2.527 72% 0.847 24% 0.126 4%

Foreigncomponent

LocalComponent Taxes

Page 47: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 14

Table 18.3-5 Unit Cost of Major Construction Items of the Road without the Proposed Bridge

No. Description Unit Unit Cost(RO)

200 EARTHWORKS203 Earthworks Excavation

Suitable excavation to embankment Cu. m. 2.109 1.122 53% 0.931 44% 0.056 3%Suitable excavation to waste Cu. m. 1.731 0.919 53% 0.766 44% 0.046 3%Borrow excavation to embankment Cu. m. 3.660 1.300 36% 2.295 63% 0.065 2%

206 Excavation and Backfilling for StructuresStructural excavation in soils to a depth of 2m. Cu. m. 1.475 0.758 51% 0.679 46% 0.038 3%Structural excavation in rock to a depth of 2m. Cu. m. 2.625 1.392 53% 1.164 44% 0.070 3%Structural excavation in rock to a depth more than 2m. Cu. m. 4.043 1.855 46% 2.095 52% 0.093 2%

300 GRANULAR AND STABILIZED SUBBASE, BASECOURSE AND STABILIZED SUBGRADE302 Granular Subbase

Class A Subbase Cu. m. 5.000 2.094 42% 2.801 56% 0.105 2%Class B Subbase Cu. m. 4.000 1.675 42% 2.241 56% 0.084 2%

303 Aggregate BasecourseClass A Basecourse Cu. m. 5.000 2.112 42% 2.783 56% 0.106 2%Class B Basecourse Cu. m. 4.000 1.689 42% 2.226 56% 0.084 2%

400 BITUMINOUS PAVEMENT401 Bituminous Prime Coat and Tack Coat

Prime Coat such as MC70 Kg 0.120 0.078 65% 0.039 32% 0.004 3%Tack Coat such as RC250 Kg 0.150 0.097 65% 0.048 32% 0.005 3%

402 Bituminous BasecourseBituminous Basecourse Cu. m. 17.000 10.893 64% 5.563 33% 0.545 3%

405 Bituminous Wearing CourseBituminous Wearing Course Cu. m. 17.000 10.893 64% 5.563 33% 0.545 3%

500 CONCRETE AND CONCRETE STRUCTURES504 Concrete for Structures

Concrete Class 28/20 Cu. m. 40.000 13.954 35% 25.348 63% 0.698 2%509 Reinforcing Steel

High yield steel bars ton 250.000 153.428 61% 88.901 36% 7.671 3%Mild steel bars ton 250.000 152.690 61% 89.676 36% 7.634 3%

800 DRAINAGE AND SERVICE DUCTS801 Pipe Culverts

Reinforced Concrete Pipe Culvert 600 mm Lin. m. 35.000 18.270 52% 15.817 45% 0.914 3%Reinforced Concrete Pipe Culvert 900 mm Lin. m. 75.000 39.150 52% 33.893 45% 1.958 3%Reinforced Concrete Pipe Culvert 1500 mm Lin. m. 155.000 80.910 52% 70.045 45% 4.046 3%

900 SLOPE PROTECTION AND STABILIZATION901 Rip Rap

Loose stone riprap Class A Cu. m. 6.000 2.477 41% 3.399 57% 0.124 2%Loose stone riprap Class B Cu. m. 6.000 2.477 41% 3.399 57% 0.124 2%Mortared stone riprap Cu. m. 15.000 4.438 30% 10.340 69% 0.222 1%

902 GabionsGabions Cu. m. 13.000 4.977 38% 7.774 60% 0.249 2%

906 Ditch liningDitch lining (150mm thick) Sq. m. 2.000 0.573 29% 1.399 70% 0.029 1%

1200 SIDEWALKS, PAVED AREAS AND CURBS1202 Curbs

Precast concrete curb, Class 28/20 non-mountable type Lin. m. 5.000 1.744 35% 3.169 63% 0.087 2%Precast concrete curb, Class 28/20 mountable type Lin. m. 5.000 1.744 35% 3.169 63% 0.087 2%Precast concrete curb, Class 28/20 lip type Lin. m. 5.000 1.744 35% 3.169 63% 0.087 2%

1300 SAFETY BARRIERS, DELINEATORS AND FENCES1301 Corrugated Steel Beam Safety Barrier

Safety barrier beam (Class B, W-section) Lin. m. 5.000 3.610 72% 1.210 24% 0.180 4%Safety barrier post (Type C) including foundation Nr. 12.000 8.664 72% 2.903 24% 0.433 4%End anchorage (ramp down), including post (Type C) and foundation Nr. 25.000 18.050 72% 6.048 24% 0.902 4%W-beam terminal sectionRe-fixing of safety barrier beam Nr. 15.000 10.830 72% 3.629 24% 0.541 4%Re-fixing of safety barrier post including foundation Lin. m. 0.500 0.361 72% 0.121 24% 0.018 4%Re-fixing of end anchorage (ramp down) including posts Nr. 3.000 2.166 72% 0.726 24% 0.108 4%Re-fixing of W-beam terminal section Nr. 16.000 11.552 72% 3.870 24% 0.578 4%

1302 Concrete safety barrierConcrete safety barrier (Type A) Lin. m. 55.000 19.186 35% 34.854 63% 0.959 2%Concrete safety barrier (Type B) Lin. m. 30.000 10.465 35% 19.011 63% 0.523 2%

1303 Reflectorized Markers for safety barriersReflectorized markers (red) attached to Guardrail Nr. 4.000 2.888 72% 0.968 24% 0.144 4%Reflectorized markers (red) attached to concrete barrier Nr. 3.000 2.166 72% 0.726 24% 0.108 4%

1304 DelineatorsFlexible delineators Nr. 12.000 8.664 72% 2.903 24% 0.433 4%Irish crossing markers Nr. 35.000 25.270 72% 8.467 24% 1.263 4%Irish crossing water depth gauges Nr. 42.000 30.324 72% 10.160 24% 1.516 4%

1400 HIGHWAY SIGNS AND ROAD MARKINGS1401 Highway Signs

Triangular, side 900mm Nr. 25.000 18.050 72% 6.048 24% 0.902 4%Triangular, side 1100mm Nr. 30.000 21.660 72% 7.257 24% 1.083 4%Triangular, side 1200mm Nr. 40.000 28.880 72% 9.676 24% 1.444 4%Circular, diameter 900mm Nr. 30.000 21.660 72% 7.257 24% 1.083 4%Circular, diameter 1200mm Nr. 85.000 61.370 72% 20.562 24% 3.068 4%Rectangular sign Sq.m. 50.000 36.100 72% 12.095 24% 1.805 4%Kilometer post (sign No. 323) Nr. 25.000 18.050 72% 6.048 24% 0.902 4%Sign post support assembly, (Type 1A) Nr. 25.000 18.050 72% 6.048 24% 0.902 4%Sign post support assembly, (Type 1B) Nr. 54.000 38.988 72% 13.063 24% 1.949 4%Sign post support assembly, (Type II) Nr. 68.000 49.096 72% 16.450 24% 2.455 4%Sign post support assembly, (Type IIIA) Nr. 150.000 108.299 72% 36.286 24% 5.415 4%Sign post support assembly, (Type IIIB) Nr. 155.000 111.909 72% 37.495 24% 5.595 4%Re-fixing of removed highway sign (any size with single post) Nr. 20.000 14.440 72% 4.838 24% 0.722 4%Re-fixing of removed highway sign (any size with multiple post) Nr. 25.000 18.050 72% 6.048 24% 0.902 4%

1402 Road MarkingsTraffic lines (mechanically sprayed) Sq. m. 1.600 1.155 72% 0.387 24% 0.058 4%Curb painting (black and yellow) Sq. m. 1.000 0.722 72% 0.242 24% 0.036 4%Reflecting road studs (double face) Nr. 3.500 2.527 72% 0.847 24% 0.126 4%

Foreigncomponent

LocalComponent Taxes

Page 48: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 15

18.3.3 Construction Cost

Estimated construction cost of the road with and without the proposed bridge are presented in Table 18.3-6 and Table 18.3-7, respectively. Detailed cost estimate of them are shown in Annex 18-1 and Annex 18-2, respectively. The construction cost of the road with the bridge was estimated at RO 10,743,000, composed of 58.0% of a foreign currency component (or RO 6,231,000), 39.1% of a local currency component (or RO 4,201,000) and 2.9% of a tax component (or RO311,000). And the construction cost of the road without the bridge was estimated at RO 7,866,000, composed of 52.2% of a foreign currency component (or RO 4,106,000), 45.2% of a local currency component (or RO 3,555,000) and 2.6% of a tax component (or RO205,000). Indirect costs (contingency) was assumed at 10% of direct cost, referring to the latest bid prices.

Table 18.3-6 Construction Cost (RO 1,000) of the Road with the Proposed Bridge Foreign Local Tax Total

6,231 4,201 311 10,743 Amount (58.0%) (39.1%) (2.9%) (100%)

Table 18.3-7 Construction Cost (RO 1,000) of the Road without the Proposed Bridge

Foreign Local Tax Total 4,106 3,555 205 7,866 Amount

(52.2%) (45.2%) (2.6%) (100%)

18.3.4 Engineering Service and Construction Supervision Cost

The engineering services cost covering detailed design (D/D) and construction supervision cost (C/S) is estimated as a certain percent of the project construction cost. The investigation of the recent projects in the Sultanate of Oman shows that the current percents for D/D and C/S are about 3% and 4%, respectively. Estimated engineering services and construction cost of the road with and without the bridge are presented in Table 18.3-8 and Table 18.3-9, respectively.

Table 18.3-8 Engineering Services and Construction Supervision Cost (RO 1,000) of the Road with the Proposed Bridge

Foreign Local Tax Total 258 32 32 322 Detailed

Design (80.0%) (10.0%) (10.0%) (100%) 344 43 43 430 Construction

Supervision (80.0%) (10.0%) (10.0%) (100%) 602 75 75 752 Total

(80.0%) (10.0%) (10.0%) (100%)

Page 49: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 16

Table 18.3-9 Engineering Services and Construction Supervision Cost (RO 1,000) of the Road without the Proposed Bridge

Foreign Local Tax Total 188 24 24 236 Detailed

Design (80.0%) (10.0%) (10.0%) (100%) 251 32 32 315 Construction

Supervision (80.0%) (10.0%) (10.0%) (100%) 439 56 56 551 Total

(80.0%) (10.0%) (10.0%) (100%)

18.3.5 Summary of Project Costs

Summary of Project Cost of the road with and without the bridge are shown in Table 18.3-10 and Table 18.3-11, respectively.

Table 18.3-10 Summary of Project Cost (RO 1,000) of the Road with the Proposed Bridge Foreign Local Tax Total

258 32 32 322 Detailed Design (80.0%) (10.0%) (10.0%) (100%)

6,231 4,201 311 10,743 Construction (58.0%) (39.1%) (2.9%) (100%)

344 43 43 430 Construction Supervision (80.0%) (10.0%) (10.0%) (100%)

6,833 4,276 386 11,495 Total (59.4%) (37.2%) (3.4%) (100%)

Table 18.3-11 Summary of Project Cost (RO 1,000) of the Road without the Proposed Bridge

Foreign Local Tax Total 188 24 24 236 Detailed

Design (80.0%) (10.0%) (10.0%) (100%) 4,106 3,555 205 7,866 Construction

(52.2%) (45.2%) (2.6%) (100%) 251 32 32 315 Construction

Supervision (80.0%) (10.0%) (10.0%) (100%) 4,545 3,611 261 8,417 Total

(54.0%) (42.9%) (3.1%) (100%)

Page 50: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 17

18.4 ENVIRONMENTAL CONSIDERATIONS AND TOR FOR EIA 18.4.1 Environmental Considerations 1) General

The objectives of environmental considerations at the stage of the “Pre-Feasibility Study (Pre-F/S)” are: - To confirm the results of the “Initial Environmental Examination (IEE)”; - To clarify present conditions in the project site and specific environmental impacts

due to proposed road construction; - To re-evaluate comprehensively proposed project road; and - To provide the “Terms of Reference (TOR)” for EIA in the next “Feasibility

Study”.

The examined environmental considerations are:

1. Review of result of the IEE with data and information concerning the project, 2. Environmental investigation at the project site using “Environmental Checklist”

(refer to Table 12.1-1), 3. Analysis of environmental conditions and impacts, 4. Comprehensive evaluation, and 5. Provision of TOR for EIA.

The content of the site investigation consists of the following environmental items:

(1) Air pollution (2) Effluent (3) Noise and vibration (4) Land subsidence (5) Topography and geology (6) Soil and soil erosion (7) Hydrology and groundwater (8) Ecosystem, flora and fauna (9) Landscape (including coastal zone) (10) Regional development on the natural environment (11) Hazards (12) Other impacts on the natural environment (13) Wastes (14) Cultural heritage

Page 51: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 18

(15) Regional development on the social environment (16) Other impacts on the social environment

2) Environmental checklist for the project “HAMRA - RUSTAQ ROAD”

More detailed environmental investigation, analysis and comprehensive evaluation for the road section IV between Hatt and Ar Rustaq, a part of project road of Hamra - Rustaq road, were carried out using the environmental checklist. The results of investigation and evaluation are shown in Annex 18-3. Consequently, environmental impacts due to the proposed road are likely to occur on the environmental items of Air Pollution, Noise, Topography and Geology, Soil, Eco-system, Flora and Fauna, Cultural heritage, and Other Impacts on Social Environment. a. Air pollution - Present condition:

Air pollution at present in the site is not significant, because very low traffic volume and no other existing exhaust source. Several villages and small settlements are located on the Lowermost Terrace along the Wadi Hatt and Wadi Bani Awf. Topography around the villages and settlements is featured very narrow wadi channel, particularly around Zammah and Far villages.

- Impacts with project:

The traffic volume of project road is anticipated to increase to approximately 10,000 veh/day. Most of the road sections will not be affected; however around villages and settlements located along narrow wadi channel, air quality is likely to deteriorate as a result of increased exhaust pollutants due to longer retention time, where topographical feature shows closed space.

- Evaluation: 1~2:

Slight to moderate impact on air quality due to increased traffic volume is evaluated.

b. Noise pollution - Present condition:

Noise pollution at present in the site is not significant, because very low traffic volume and no other noise source. Several villages and small settlements are located on the Lowermost Terrace along Wadi Hatt and Wadi Bani Awf.

Page 52: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 19

Topography at the villages and settlements is featured with very narrow wadi channel, particularly around Zammah and Far villages.

- Prediction with project:

The traffic volume of project road is anticipated to be increased approximately 10,000 veh/day. Most of theroad sections will not be affected because of open space; however around villages and settlements located along narrow wadi channel, noise is likely to increase because of short distance away from project road and topographically closed space, which has cliff in both sides. The sound will echo again by cliff.

- Evaluation: 1~2:

Slight to moderate impact to noise due to increased traffic volume. c. Topography and Geology - Present condition:

Topography: The project area is located in the central part of Al Hajar Al Gharbi Mountains. Mountain Jabal Shams, being the highest peak in Oman, 3,009m above sea level, is located 10km west of the area and mountain ridge from Jabal Shams is connected to the project area.

Southern slope of the Al Jabal Al Akdar mountain ridge is characterized by large scale of cuesta topography showing gentle slope. On the contrary, northern slope of Al Jabal Al Akhdar mountain ridge is characterized by steep slope to vertical cliff as the cuesta topography. The project road section belongs to the northern steep slope terrain.

1. From 0 km (Start point: Hat village) to 15.3 km (Junction to Fashah):

The road section, marked by rugged and steep slope topography, belongs to high to moderate relief of mountain and passes along Wadi al Hatt and Wadi Bani Awf. V-shape deeply incised valleys and likely oddly shape rock outcroppings show in many places.

2. From 15.3 km to 28.3 km (End point): This road section is also marked by rugged mountainous terrain and belongs to the moderate and low relief of mountain. The section passes along wadi channel of Wadi Bani Awf. Around end point of the road, topography changes to lower hilly and flat terrain.

Page 53: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 20

Geology: The project area crossing Al Jabal Al Akdar Mountains are continuously cropped out the Autochthonous Units, consisting of the Huqf Group of End-Protoezoic to Cambrian age and Akhdar Group, Sahtan Group, Kahmah Group and Wasia Group ranging in age from Late Permian to Middle Cretaceous. The Huqf Group is intensely metamorphosed and shows fine schistose. The geological structure clearly shows anticline deformation (dome structure) in large scale. Igneous rocks originated from ancient ocean floor, so-called Samail Ophiolite, are locally found near the end point of project road.

- Impacts with project:

The project will require massive excavation and embankment for paved 2-lane road construction, even if the road alignment mostly follows along the existing alignment. Hence, large to small scale alteration of topography will occur in many places. In addition, much cuttings caused in the slope will be generally dumped to the slope side, so that topographically larger area more than right-of-way (ROW) is likely to be irreversible altered.

- Evaluation: 1~2:

Slight to moderate impact due to road construction. d. Soil - Present condition:

Soil is poorly developed, but alluvial soil is locally found in the wadi and terraces. Farmlands in villages and settlements use these surface soils.

- Impacts with project:

The existing project road mostly passes along the wadi channels, so that the area of ROW and working site will be altered of surface soil. In addition, much cuttings caused in the slope will be generally dumped to the slope side, so that topographically larger area more than ROW is likely to be irreversible altered.

- Evaluation: 1~2:

Slight to moderate impact to surface soil due to road construction. e. Eco-system, Flora and Fauna - Present condition:

Page 54: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 21

Flora: Vegetation is found along the entire stretch of the project area. The lower lying hills have less vegetative cover than the higher areas, except for depressions and wadi flow channels. The vegetation can be classified as an open xenomorphic Euphorbia community type. Much of this area represents a good example of undisturbed habitat in northern Oman.

Fauna: Wildlife known to the area may include the Arabian Leopard, Gazelle, Arabian Tahr and other fauna such as the red fox, etc. The IUCN red list of threatened animals (IUCN 1990) describes the mountain gazelle as vulnerable. Leopard and the Tahr are considered endangered.

- Impacts with project:

Any development in the area will be considered as having a significant impact as a result of the valuable nature of the habitat, because of rapidly increase of traffic volume in future. Whilst the area does not have official reserve status, permits are required to enter some areas. This area could be one of the protection areas proclaimed as Nature Reserve in near future.

- Evaluation: 2:

Moderate impact to eco-system, flora and fauna due to road construction. It is necessary to carry out detailed investigation concerning eco-system, flora and fauna in the area, particularly relationship between Al Jabal Al Akdar area and project area before construction or during EIA.

f. Other Impacts on Social Environment

- Present condition:

There are several villages and small settlements with farmlands and a number of domestic animals along the route shown as below.

0 km point: Junction to Hat village. 1.5 km point: 6 houses and Date farms. 5.1km point: Bimah settlement. 5.1km point: Zammah village. 13.4km point: 3 houses settlement with small farm. 18.3km: Teekah village, farm and Medical office. 20.4km point: Al Wasit settlement with small date farm. 23.9 km point: 2 houses settlement with small date farm. 25.6~26.1km point: Far village. 28.3km point: Junction of NR No.13, Substation.

Page 55: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 22

- Impacts with project: The existing and proposed road passes nearby the villages and farmland. As high traffic volume is predicted, zone around villages and settlements as well as domestic animals may face the chance of traffic accidents.

- Evaluation: 1~2:

Slight to moderate impact as increase of chance of traffic accidents to social environment due to road construction.

h. Other environmental items: Not significant impact.

3) Results of IEE

The comprehensive evaluation for the Hamra - Rustaq Road is concluded to be 2 as impact rating; summarized in Table 18.4-1. Hence, the implementation of comprehensive EIA before road construction is recommended. Table 18.4-1 Results of IEE on the Hamra - Rustaq Road - Air Pollution 1~2 - Increased traffic volume - Noise 1~2 - Increased traffic volume - Topography and Geology 1~2 - Alteration of topography - Soil 1~2 - Alteration of topography - Eco-system, Flora and Fauna 2

- High potential of various species of flora and fauna

- Increase of wastes due to increase of visitors

- Increased traffic volume - Other Impacts on Social Environment 1~2 - Increase of chance of traffic accidents

due to increased traffic volume - Other items 1

Comprehensive Evaluation 2

Recommendations *1 Recommended to carry out EIA Note *1 : Comprehensive Evaluation 1 : None to slight impacts : No need to carry out EIA or need to carry out partial EIA after scoping 1~2 : Small impacts : Recommended to carry out partial EIA on assigned items after

scoping 2 : Moderate impacts : Recommended to carry out EIA 2~3 : Relatively significant impacts: Recommended to carry out EIA 3 : Significant impacts : Recommended to carry out EIA

18.4.2 Terms of Reference for the Project Terms of reference (TOR) on the Environmental Impact Assessment of the Hamra -

Rustaq Road, Sultanate of Oman, are shown in Annex 18-4.

Page 56: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 23

18.5 PROJECT EVALUATION 18.5.1 General

The objective of this section is to examine viability of the improvement plan of Al Hamra - Rustaq Road from viewpoint of national economy of Oman. In order to achieve the objective, the following steps are carried out; Step 1: Traffic demand forecast on the Project Step 2: Estimation of economic benefit based on traffic demand on the Project Road

and unit vehicle operating cost Step 3: Estimation of economic cost based on the estimated financial cost mentioned in

Section 18.3. Step 4: Calculation of economic indicators using the economic benefit and economic cost. Step 5: Economic Evaluation of the Project Road. Step 6: Sensitivity analysis to be made by varying factors of influenced to economic

indicators such as the economic benefit and economic cost Step 7: Future socio-economic framework in the influence area of the Project Road Step 8: Evaluation from technical and socio-economic view points Step 9: Overall evaluation Figure 18.5-1 shows the procedure for project evaluation.

18.5.2 Traffic Demand Forecast

Future traffic demands forecasted in a form of OD matrix in the years 2010, 2020 and 2030 are assigned on the road network to estimate traffic volume on the Al Hamra - Rustaq Road. The estimated traffic volumes on the Road for the case of ‘with’ the project are summarized in Table 18.5-1.

Table 18.5-1 Traffic Volume on Hamra-Rustaq Road ( PCU / Day) AAGR (%) 2010 2020 2030

’10-‘20 ’20-‘30 Hamra – Wilayah Boarder 2,974 5,978 11,044 7.2 6.3Wilayah Border – Rustaq 2,878 6,122 11,058 7.8 6.1

Tables 18.5-2 and 18.5-3 show the estimated total vehicle kilometers and total vehicle hours of the Road, respectively.

Page 57: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 24

Future OD Traffic

Road Network w/ and w/o Project

Financial Cost ofProject

Unit Vehicle Operating Cost

Running Cost Saving

Fixed Cost Saving

Travel Time Cost Saving

Elimination of Transfer Cost

Economic Cost of Project

Economic Benefit of Project

Economic Indicators - NPV, -B/C Ratio - EIRR

Sensitivity Analysis

Evaluation of Project fromOther Viewpoints - Technical Aspect - Socio-economic Aspect - Other Aspect

Socio-Economic Framework

Overall Evaluation

Figure 18.5-1 Procedure for Project Evaluation

Traffic Demand Forecast on Project

Economic Evaluation of Project

Page 58: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 25

Table 18.5-2 Total Vehicle Kilometers on Hamra-Rustaq Road ( ‘000 PCU-km / Day) W/O Project W/ Project W/O-W/

W/O Bridge Plan 17.967.1 201.32010 W/ Bridge Plan

18,168.517,959.8 208.7

W/O Bridge Plan 31,377.6 341.72020 W/ Bridge Plan

31,719.331,363.1 356.2

W/O Bridge Plan 54,797.5 579.52030 W/ Bridge Plan

55,377.054,769.2 607.8

Table 18.5-3 Total Vehicle Hours on Hamra-Rustaq Road ( PCU-Hour / Day ) W/O Project W/ Project W/O-W/

W/O Bridge Plan 240,049 1,8902010 W/ Bridge Plan

241,939239,803 2,136

W/O Bridge Plan 439,198 2,9222020 W/ Bridge Plan

442,603439,198 3,406

W/O Bridge Plan 805,331 2,9222030 W/ Bridge Plan

809,697804,389 5,308

18.5.3 Preliminary Economic Evaluation

1) Evaluation Period

The evaluation period is assumed to be 30 years from 2010 to 2039 taking into account the service life of the Al Hamura - Rustaq Road.

2) Implementation Schedule

Following the recommended implementation schedule of the Master Plan, the implementation schedule of the Project is assumed as follows: ・ 2006 Detailed design, tendering and bidding ・ 2007 – ’09 Construction of Al Hamura- Rustaq Road (Phase 4)

3) Plans to be evaluated

There are two (2) plans of construction of Hamra - Rustaq Road to be evaluated as follows: ・ Without Bridge Plan: Constrction of Hamra – Rustaq Road without new Arch Bridge ・ With Bridge Plan: Construction of Hamra – Rustaq Road with new Arch Bridge

Page 59: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 26

4) Economic Indicators

The economic indicators used in this study are as follows: − Net Present Value (NPV) − Benefit Cost Ratio, (BCR), and − Economic Internal Rate of Return (EIRR)

5) Estimation of Benefit

By implementing Hamra-Rustaq Road project, a variety of benefits is expected such as improvement of comfort and safety, promotion of international and inter-regional trade and promotion of regional development in long term basis. Among these benefits, limited benefits to the three (3) items of vehicle operating cost: saving in running cost (VRC) (distance related vehicle operating cost), saving in fixed cost (VFC) (time related vehicle operating cost) and travel saving in time cost (TTC).

a. Unit Vehicle Operating Cost (VOC) Detailed unit VOC is described in Appendix A9-2. Tables 18.5-4 (1) to (3) summarizes the unit VOC on paved and unpaved surface type, VFC and TTC for vehicle groups. Table 18.5-4 (1) Unit Running Cost by Vehicle Speed and Surface Type (RO/’000 km)

Paved Surface Unpaved Surface Speed (km/h)

Passenger Car

Bus Truck Passenger Car

Bus Truck

5 km/h 66 109 116 104 177 14330 34 43 49 53 69 6150 33 41 47 53 66 5870 36 44 50 57 70 6290 41 49 55 64 79 69110 47 57 63 73 92 78130 54 67 73 85 108 91150 63 79 85 99 127 105

Note: All unit costs are presented in 2005 prices

Table 18.5-4 (2) Unit Fixed Cost by Vehicle Types (RO/Hr) Vehicle Type Fixed Cost Passenger Car 1.088

Bus 1.835 Truck 2.661

Note: All unit costs are presented in 2005 prices

Page 60: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 27

Table 18.5-4 (3) Unit Travel Time Cost by Vehicle Types (RO/Hr) Vehicle Type TTC (Person Base) TTC (Vehicle Base) Passenger Car 0.58 1.27 Bus 0.47 5.75 Truck 0 0

Notes: 1) All unit costs are presented in 2005 prices 2) TTC means travel time cost b. Estimation of Benefits

The saving in vehicle operating costs and travel time cost are estimated as presented shown in Table 18.5-5.

Table 18.5-5 Estimation of Benefits (RO ‘000 /Year)

Year

Saving in VRC

Saving in VFC

Saving in VOC

Saving in TTC

Total Saving

W/O Bridge Plan 1,104.8 1,072.8 2,087.5 654.2 4,829.3

2010 W/ Bridge

Plan 1,120.2 1,212.4 2,332.6 739.4 5,404.6

W/O Bridge Plan 1,274.4 1,657.3 2,931.7 1,010.7 6,874.1

2020 W/ Bridge

Plan 1,413.7 1,936.6 3,350.3 1,181.0 7,881.5

W/O Bridge Plan 1,630.8 2,478.1 4,108.9 1,511.3 9,729.0

2030 W/ Bridge

Plan 1,839.4 3,012.9 4,852.3 1,837.4 11,542.0

Note: VRC: Vehicle running cost, VFC: Vehicle fixed cost, VOC: Vehicle operating cost (VRC+VFC), TTC: travel time cost

6) Economic Cost

a. Construction Cost

The project cost calculated in the previous section is expressed as the financial cost. The economic cost is estimated by deducting government taxes and import duty of imported materials from financial cost as shown in Table 18.5-6/1 and 18.5-6/2 without and with bridge plan, respectively.

Page 61: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 28

Table 18.5-6 (1) Economic Cost Estimation (Without Bridge Plan) (RO ‘000)

Description Economic Cost Financial Cost

1 Construction Cost 7,722.8 8,011.9 1.1 Labor Cost 292.7 292.7 1.2 Material Cost 3,683.1 3.777.5 1.3 Equipment 3,470.1 3,652.7

2 Consultancy 532.8 560.9 2.1 Detailed Design 228.3 240.4

2.2 Construction Supervision 304.5 320.5

Total 8,255.6 8,572.8 Table 18.5-6 (2) Economic Cost Estimation (With Bridge Plan) (RO ‘000)

Description Economic Cost Financial Cost

1 Construction Cost 10,431.9 10,743.2 1.1 Labor Cost 341.5 351.6 1.2 Material Cost 5,164.3 5,318.4 1.3 Equipment 4,926.1 5,073.1

2 Consultancy 432.8 560.9 2.1 Detailed Design 306.2 322.3

2.2 Construction Supervision 408.2 429.7

Total 11,146.0 11,495.0

b. Maintenance Cost

The maintenance cost of the Hamra Rustaq Road is estimated on the basis of maintenance costs per kilometer applied on other national roads, which is RO 361 per km.

7) Benefit Cost Analysis

The economic analysis of the Project is carried out based on the above mentioned economic benefit and cost estimations. Table 18.5-7 shows the benefit – cost analysis of the Hamra Rustaq Road Construction Project during a project life period of 30 years and Tables 18.5-8 (1) and (2) shows the benefit - cost stream. Economic indicators show that both plans are economically feasible. However, construction of the proposed bridge gives lower indication from view points of B/C ratio and EIRR.

Page 62: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 29

Table 18.5-7 Economic Indicators of Benefit Cost Analysis Without Bridge Plan With Bridge Plan Net Present Value (NPV) RO 34.1 million RO 37.8 million

BCR 4.95 4.24 EIRR 27.3% 23.9%

Note: 1) Project life is assumed to be 30 years 2) Discount rate is assumed to be 6%.

8) Sensitivity Analysis

The sensitivity analysis is conducted under a worse case scenario incorporating increase and/or decrease of the estimation of economic cost and benefit. Table 18.5-9 shows the results of the sensitivity analysis regarding to benefit and cost.

Table 18.5-9 Sensitivity Analysis of Hamra - Rutaq Road Construction Project regarding to Benefit and Cost

Benefit

20% down Base Case 20% up NPV (RO Million) 27.7 33.8 41.8

B/C Ratio 4.95 6.19 7.42 20% down

EIRR (%) 27.2 32.0 36.4 NPV (RO Million) 24.1 32.1 40.2

B/C Ratio 3.96 4.95 5.94 Base Case EIRR (%) 23.0 27.2 31.1

NPV (RO Million) 22.4 30.5 38.5 B/C Ratio 3.30 4.12 4.95

Cost

20% up EIRR (%) 20.0 23.7 27.2

Note: Project life of the project is assumed to be 30 years

9) Summary of Economic Analysis

The implementation of both Hamra - Rustaq Road construction plans can be justified from view of national economic point of view since the economic indicators of all cases are higher than the opportunity rate of the capital investment in Oman which is designated at 6 % per annum. Regarding to the two plans, without Bridge plan is superior to with Bridge Plan. However, the second plan is expected to generate more NPV than the first plan.

Page 63: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

Und

isco

unte

d B

enef

it C

ost S

trea

m

Dis

coun

ted

Ben

efit

Cos

t Str

eam

R

O '000

RO

'000

Sq

Year

Const

ruction C

ost

O &

M C

ost

Cost

Tota

lB

enefit

Cost

-B

enefit

Sq

Year

Dis

counte

d C

onst

ruction C

ost

O &

M C

ost

Cost

Tota

lB

enefit

Cost

-B

enefit

12005

0.0

0.0

0.0

0.0

0.0

12005

1.0

00

0.0

0.0

0.0

0.0

0.0

22006

228.3

0.0

228.3

0.0

-228.3

22006

1.0

60

215.4

0.0

215.4

0.0

-215.4

32007

2,8

09.6

0.0

2,8

09.6

0.0

-2,8

09.6

32007

1.1

24

2,5

00.5

0.0

2,5

00.5

0.0

-2,5

00.5

42008

2,8

09.6

0.0

2,8

09.6

0.0

-2,8

09.6

42008

1.1

91

2,3

59.0

0.0

2,3

59.0

0.0

-2,3

59.0

52009

2,4

08.2

0.0

2,4

08.2

0.0

-2,4

08.2

52009

1.2

62

1,9

07.5

0.0

1,9

07.5

0.0

-1,9

07.5

62010

0.0

154.5

154.5

2,7

41.8

2,5

87.3

62010

1.3

38

0.0

115.4

115.4

2,0

48.8

1,9

33.4

72011

0.0

154.5

154.5

2,8

42.0

2,6

87.5

72011

1.4

19

0.0

108.9

108.9

2,0

03.5

1,8

94.6

82012

0.0

154.5

154.5

2,9

46.1

2,7

91.6

82012

1.5

04

0.0

102.7

102.7

1,9

59.3

1,8

56.6

92013

0.0

154.5

154.5

3,0

54.5

2,9

00.0

92013

1.5

94

0.0

96.9

96.9

1,9

16.4

1,8

19.5

10

2014

0.0

154.5

154.5

3,1

67.1

3,0

12.6

10

2014

1.6

89

0.0

91.4

91.4

1,8

74.6

1,7

83.2

11

2015

0.0

154.5

154.5

3,2

84.2

3,1

29.7

11

2015

1.7

91

0.0

86.2

86.2

1,8

33.9

1,7

47.7

12

2016

0.0

154.5

154.5

3,4

05.9

3,2

51.4

12

2016

1.8

98

0.0

81.4

81.4

1,7

94.2

1,7

12.8

13

2017

0.0

154.5

154.5

3,5

32.5

3,3

78.0

13

2017

2.0

12

0.0

76.8

76.8

1,7

55.5

1,6

78.7

14

2018

0.0

154.5

154.5

3,6

64.2

3,5

09.7

14

2018

2.1

33

0.0

72.4

72.4

1,7

17.9

1,6

45.5

15

2019

0.0

154.5

154.5

3,8

01.2

3,6

46.7

15

2019

2.2

61

0.0

68.3

68.3

1,6

81.3

1,6

13.0

16

2020

0.0

154.5

154.5

3,9

42.4

3,7

87.9

16

2020

2.3

97

0.0

64.4

64.4

1,6

45.0

1,5

80.6

17

2021

0.0

154.5

154.5

4,0

91.7

3,9

37.2

17

2021

2.5

40

0.0

60.8

60.8

1,6

10.7

1,5

49.9

18

2022

0.0

154.5

154.5

4,2

45.8

4,0

91.3

18

2022

2.6

93

0.0

57.4

57.4

1,5

76.7

1,5

19.3

19

2023

0.0

154.5

154.5

4,4

06.1

4,2

51.6

19

2023

2.8

54

0.0

54.1

54.1

1,5

43.6

1,4

89.5

20

2024

0.0

154.5

154.5

4,5

72.9

4,4

18.4

20

2024

3.0

26

0.0

51.0

51.0

1,5

11.4

1,4

60.4

21

2025

0.0

154.5

154.5

4,7

46.5

4,5

92.0

21

2025

3.2

07

0.0

48.2

48.2

1,4

80.0

1,4

31.8

22

2026

0.0

154.5

154.5

4,9

27.0

4,7

72.5

22

2026

3.4

00

0.0

45.4

45.4

1,4

49.3

1,4

03.9

23

2027

0.0

154.5

154.5

5,1

14.9

4,9

60.4

23

2027

3.6

04

0.0

42.9

42.9

1,4

19.4

1,3

76.5

24

2028

0.0

154.5

154.5

5,3

10.4

5,1

55.9

24

2028

3.8

20

0.0

40.4

40.4

1,3

90.2

1,3

49.8

25

2029

0.0

154.5

154.5

5,5

13.9

5,3

59.4

25

2029

4.0

49

0.0

38.1

38.1

1,3

61.8

1,3

23.7

26

2030

0.0

154.5

154.5

5,6

20.2

5,4

65.7

26

2030

4.2

92

0.0

36.0

36.0

1,3

09.5

1,2

73.5

27

2031

0.0

154.5

154.5

5,7

22.3

5,5

67.8

27

2031

4.5

49

0.0

34.0

34.0

1,2

57.8

1,2

23.8

28

2032

0.0

154.5

154.5

5,8

26.4

5,6

71.9

28

2032

4.8

22

0.0

32.0

32.0

1,2

08.2

1,1

76.2

29

2033

0.0

154.5

154.5

5,9

32.4

5,7

77.9

29

2033

5.1

12

0.0

30.2

30.2

1,1

60.6

1,1

30.4

30

2034

0.0

154.5

154.5

6,0

40.4

5,8

85.9

30

2034

5.4

18

0.0

28.5

28.5

1,1

14.8

1,0

86.3

31

2035

0.0

154.5

154.5

6,1

50.5

5,9

96.0

31

2035

5.7

43

0.0

26.9

26.9

1,0

70.9

1,0

44.0

32

2036

0.0

154.5

154.5

6,2

62.7

6,1

08.2

32

2036

6.0

88

0.0

25.4

25.4

1,0

28.7

1,0

03.3

33

2037

0.0

154.5

154.5

6,3

77.0

6,2

22.5

33

2037

6.4

53

0.0

23.9

23.9

988.2

964.3

Tota

l8,2

55.6

4,3

24.8

12,5

80.4

127,2

43.0

114,6

62.6

Tota

l6,9

82.4

1,6

40.0

8,6

22.4

42,7

12.2

34,0

89.8

Dis

count

Rat

e6.0

%N

PV

(R

O M

illio

n)

34.1

B/C

Rat

io

4.9

5

EIR

R27.3

Cost

1B

enefit

1

Tab

le 1

8.5.

8 (1

) B

enef

it - C

ost S

trea

m o

f Al H

amra

- R

usta

q R

oad

Con

stru

ctio

n Pr

ojec

t (W

ithou

t Bri

dge

Plan

)

18 - 30

Page 64: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

Und

isco

unte

d B

enef

it C

ost S

trea

m

Dis

coun

ted

Ben

efit

Cos

t Str

eam

R

O '000

RO

'000

Sq

Year

Const

ruction C

ost

O &

M C

ost

Cost

Tota

lB

enefit

Cost

-B

enefit

Sq

Year

Dis

counte

d C

onst

ruction C

ost

O &

M C

ost

Cost

Tota

lB

enefit

Cost

-B

enefit

12005

0.0

0.0

0.0

0.0

0.0

12005

1.0

00

0.0

0.0

0.0

0.0

0.0

22006

306.2

0.0

306.2

0.0

-306.2

22006

1.0

60

288.9

0.0

288.9

0.0

-288.9

32007

3,7

94.0

0.0

3,7

94.0

0.0

-3,7

94.0

32007

1.1

24

3,3

76.7

0.0

3,3

76.7

0.0

-3,3

76.7

42008

3,7

94.0

0.0

3,7

94.0

0.0

-3,7

94.0

42008

1.1

91

3,1

85.6

0.0

3,1

85.6

0.0

-3,1

85.6

52009

3,2

52.0

0.0

3,2

52.0

0.0

-3,2

52.0

52009

1.2

62

2,5

75.9

0.0

2,5

75.9

0.0

-2,5

75.9

62010

0.0

208.6

208.6

3,0

72.0

2,8

63.4

62010

1.3

38

0.0

155.9

155.9

2,2

95.6

2,1

39.7

72011

0.0

208.6

208.6

3,1

91.9

2,9

83.2

72011

1.4

19

0.0

147.1

147.1

2,2

50.1

2,1

03.0

82012

0.0

208.6

208.6

3,3

16.8

3,1

08.2

82012

1.5

04

0.0

138.8

138.8

2,2

05.9

2,0

67.1

92013

0.0

208.6

208.6

3,4

47.1

3,2

38.5

92013

1.5

94

0.0

130.9

130.9

2,1

62.8

2,0

31.9

10

2014

0.0

208.6

208.6

3,5

83.0

3,3

74.4

10

2014

1.6

89

0.0

123.5

123.5

2,1

20.8

1,9

97.3

11

2015

0.0

208.6

208.6

3,7

24.7

3,5

16.1

11

2015

1.7

91

0.0

116.5

116.5

2,0

79.9

1,9

63.4

12

2016

0.0

208.6

208.6

3,8

72.4

3,6

63.8

12

2016

1.8

98

0.0

109.9

109.9

2,0

39.9

1,9

30.0

13

2017

0.0

208.6

208.6

4,0

26.5

3,8

17.9

13

2017

2.0

12

0.0

103.7

103.7

2,0

01.0

1,8

97.3

14

2018

0.0

208.6

208.6

4,1

87.3

3,9

78.7

14

2018

2.1

33

0.0

97.8

97.8

1,9

63.2

1,8

65.4

15

2019

0.0

208.6

208.6

4,3

55.0

4,1

46.4

15

2019

2.2

61

0.0

92.3

92.3

1,9

26.2

1,8

33.9

16

2020

0.0

208.6

208.6

4,5

31.3

4,3

22.7

16

2020

2.3

97

0.0

87.1

87.1

1,8

90.8

1,8

03.7

17

2021

0.0

208.6

208.6

4,7

12.5

4,5

03.9

17

2021

2.5

40

0.0

82.1

82.1

1,8

55.1

1,7

73.0

18

2022

0.0

208.6

208.6

4,9

03.0

4,6

94.4

18

2022

2.6

93

0.0

77.5

77.5

1,8

20.8

1,7

43.3

19

2023

0.0

208.6

208.6

5,1

01.8

4,8

93.2

19

2023

2.8

54

0.0

73.1

73.1

1,7

87.4

1,7

14.3

20

2024

0.0

208.6

208.6

5,3

09.3

5,1

00.7

20

2024

3.0

26

0.0

69.0

69.0

1,7

54.8

1,6

85.8

21

2025

0.0

208.6

208.6

5,5

25.7

5,3

17.1

21

2025

3.2

07

0.0

65.1

65.1

1,7

22.9

1,6

57.8

22

2026

0.0

208.6

208.6

5,7

51.8

5,5

43.2

22

2026

3.4

00

0.0

61.4

61.4

1,6

91.9

1,6

30.5

23

2027

0.0

208.6

208.6

5,9

87.7

5,7

79.1

23

2027

3.6

04

0.0

57.9

57.9

1,6

61.6

1,6

03.7

24

2028

0.0

208.6

208.6

6,2

33.9

6,0

25.3

24

2028

3.8

20

0.0

54.6

54.6

1,6

32.0

1,5

77.4

25

2029

0.0

208.6

208.6

6,4

91.0

6,2

82.4

25

2029

4.0

49

0.0

51.5

51.5

1,6

03.1

1,5

51.6

26

2030

0.0

208.6

208.6

6,6

89.7

6,4

81.1

26

2030

4.2

92

0.0

48.6

48.6

1,5

58.7

1,5

10.1

27

2031

0.0

208.6

208.6

6,8

23.8

6,6

15.2

27

2031

4.5

49

0.0

45.9

45.9

1,4

99.9

1,4

54.0

28

2032

0.0

208.6

208.6

6,9

60.8

6,7

52.2

28

2032

4.8

22

0.0

43.3

43.3

1,4

43.4

1,4

00.1

29

2033

0.0

208.6

208.6

7,1

00.6

6,8

92.0

29

2033

5.1

12

0.0

40.8

40.8

1,3

89.1

1,3

48.3

30

2034

0.0

208.6

208.6

7,2

43.3

7,0

34.7

30

2034

5.4

18

0.0

38.5

38.5

1,3

36.8

1,2

98.3

31

2035

0.0

208.6

208.6

7,3

89.1

7,1

80.5

31

2035

5.7

43

0.0

36.3

36.3

1,2

86.5

1,2

50.2

32

2036

0.0

208.6

208.6

7,5

37.8

7,3

29.2

32

2036

6.0

88

0.0

34.3

34.3

1,2

38.1

1,2

03.8

33

2037

0.0

208.6

208.6

7,6

89.7

7,4

81.1

33

2037

6.4

53

0.0

32.3

32.3

1,1

91.6

1,1

59.3

Tota

l11,1

46.3

5,8

41.9

16,9

88.2

148,7

59.5

131,7

71.3

Tota

l9,4

27.1

2,2

15.7

11,6

42.8

49,4

09.9

37,7

67.1

Dis

count

Rat

e6.0

%N

PV

(R

O M

illio

n)

37.8

B/C

Rat

io

4.2

4

EIR

R23.9

Cost

1B

enefit

1

Tab

le 1

8.5.

8 (2

) Ben

efit

- Cos

t Str

eam

of A

l Ham

ra -

Rus

taq

Roa

d C

onst

ruct

ion

Proj

ect (

With

Bri

dge

Plan

)

18 - 31

Page 65: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 32

18.5.4 Technical Evaluation

The results of the technical analysis of the Hamra - Rustaq Road show that the Hamra - Rustaq Road construction project is technically feasible. However, the following technical notes shall be considered in the detailed design stage. ・ According to the preliminary engineering design, it is inevitable to avoid the steep

gradient of 12.33 % between station 0.000 and station 2.400 and of 13.53 % between station 6.500 and station 8.300. Taking into account the environmental considerations and function of this road, the preliminary design made in this study shall be accepted at this stage.

・ The area that the Hamra - Rustaq Road are sometimes influenced by heavy rain. In order to minimize damage of the road, proper Irish crossing and slope protection are proposed in this Study.

18.5.5 Evaluation Form Other Aspects 1) Improvement of Standard Living of Peoples

Construction of the Project Road is expected to contribute to the improvement of standard living of peoples. At present, it is estimated that 2,464 peoples in Rustaq side and 1,467 peoples in Hamra side are living at present within the influence areas of the Project Road as shown in Table 18.5-10, which can not be accessible without four (4) wheel drive vehicles. Daily travel such as ‘to work’ trip for workers, ‘to school’ trips for school children, ‘business’ trip for business men, and ‘ private’ trip for people can not be made without four (4) wheel drive vehicles. After completion of the Project Road, the Project will contribute to

・ More opportunities to access various basic facilities, such as religious facilities, hospitals, markets,

・ Achievement of easier daily travel to offices for employed people, and schools for school children,

・ More chances of developing unutilized potential lands, ・ Contribution to effective land use and the unity of nation

Page 66: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

18 - 33

Table 18.5-10 Population, Employed Population and School Children in the Influence Area of Hamra – Rustaq Road 2005 2010 2020 2030 Rustaq Side Population 2,464 2,585 2,636 2,614No. of Employed Population 674 726 809 886No. of School Children (below 15 ys old) 527 472 461 400Hamra Side Population 1,467 1,528 1,555 1,562No. of Employed Population 367 393 439 484No. of School Children (below 15 ys old) 314 287 272 239

2) Regional Development

Improved road system in the project area would greatly contribute to regional development. Travel time reduction, transport cost reduction, accessibility improvement and safe, comfort and reliable means of transportation would be directly and indirectly provide positive impact on the following; a. Agricultural industry

・ Higher farm gate prices → higher income for farmers → Upgrading the living standards → Incentive for farmers to produce → Regional economic growth

b. Tourism industry

・ Cheaper transport cost / Easy accessibility to Hotels / Sightseeing spots →

More tourists to visit → Regional economic growth

3) Traffic Safety The existing road is a track road and poorly equipped with traffic safety facilities such as guard rail, etc. with the completion of the Project, the traffic safety facilities will be installed and traffic safety will be greatly improved. Also, travel by non-4WD vehicles will become possible.

18.5.6 Overall Evaluation

As mentioned above, the implementation of the Hamra – Rustaq road construction project can be justified as feasible from view of economic, technical, and social impact points.

Page 67: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-1-1

Annex 18-1 Detailed cost estimate of Hamra – Rustaq Road with the Bridge

Lab. Mat. Equip. For. Local TaxEarthworks

203 Earthworks Excavation203.1 Suitable excavation to embankment Cu. m. 1.944 216,739 421,338 7,101 19,556 394,680 224,058 186,077 11,203203.2 Suitable excavation to waste Cu. m. 1.733 153,446 265,966 4,624 10,661 250,681 141,220 117,684 7,061203.4 Borrow excavation to embankment Cu. m. 3.660 39,033 142,859 611 48,851 93,397 50,735 89,588 2,537

206 Excavation and Backfilling for Structures

206.1 Structural excavation in soils to a depth of 2m. Cu. m. 1.459 26,431 38,551 1,049 2,177 35,326 19,878 17,679 994

206.3 Structural excavation in rock to a depth of 2m. Cu. m. 2.625 27,743 72,834 1,335 2,923 68,575 38,622 32,281 1,931

206.4 Structural excavation in rock to a depth more than 2m. Cu. m. 3.990 21,270 84,867 2,545 16,659 65,663 39,298 43,605 1,965Subbase and Base course

302 Granular Subbase302.1 Class A Subbase Cu. m. 5.000 0 0 0 0 0 0 0 0302.2 Class B Subbase Cu. m. 4.000 55,177 220,707 4,534 48,991 167,183 92,426 123,661 4,621302.3 Class C Subbase Cu. m. 3.000 0 0 0 0 0 0 0 0303 Aggregate Basecourse 0303.1 Class A Basecourse Cu. m. 5.000 0 0 0 0 0 0 0 0303.2 Class B Basecourse Cu. m. 4.000 41,566 166,265 3,476 35,920 126,869 70,221 92,533 3,511303.3 Class C Basecourse Cu. m. 3.000 0 0 0 0 0 0 0 0

Bituminous Pavement401 Bituminous Prime Coat and Tack Coat401.1 Prime Coat such as MC70 Kg 0.120 257,500 30,900 90 30,535 275 19,981 9,920 999401.2 Tack Coat such as RC250 Kg 0.150 0 0 0 0 0 0 0 0405 Bituminous Wearing Course405.1 Bituminous Wearing Course Cu. m. 17.000 28,178 479,019 1,186 447,892 29,941 306,932 156,740 15,347

Concrete and Concrete Structures504 Concrete for Structures504.1 Concrete Class 28/20 Cu. m. 40.000 24,629 985,175 77,443 494,830 412,901 343,674 624,317 17,184504.2 Concrete Class 32/20 Cu. m. 45.000 0 0 0 0 0 0 0 0504.3 Concrete Class 36/20 Cu. m. 50.000 0 0 0 0 0 0 0 0509 Reinforcing Steel509.1 High yield steel bars ton 250.000 1,199 299,787 11,786 261,858 26,142 183,983 106,605 9,199509.2 Mild steel bars ton 250.000 33 8,285 359 7,179 746 5,060 2,972 253

Drainage801 Pipe Culverts801.1 Reinforced Concrete Pipe Culvert 600 mm Lin. m. 35.000 14 490 18 113 359 256 221 13801.2 Reinforced Concrete Pipe Culvert 750 mm Lin. m. 50.000 0 0 0 0 0 0 0 0801.3 Reinforced Concrete Pipe Culvert 900 mm Lin. m. 75.000 14 1,050 38 243 770 548 474 27801.4 Reinforced Concrete Pipe Culvert 1050 mm Lin. m. 100.000 0 0 0 0 0 0 0 0801.5 Reinforced Concrete Pipe Culvert 1500 mm Lin. m. 155.000 252 39,060 1,406 9,023 28,631 20,389 17,651 1,019

Slope Protection901 Rip Rap901.1 Loose stone riprap Class A Cu. m. 6.000 10,652 63,911 1,770 15,360 46,781 26,381 36,210 1,319901.2 Loose stone riprap Class B Cu. m. 6.000 0 0 0 0 0 0 0 0901.3 Mortared stone riprap Cu. m. 15.000 37,317 559,750 34,301 306,569 218,881 165,619 385,850 8,281902 Gabions 0902.1 Gabions Cu. m. 13.000 0 0 0 0 0 0 0 0906 Ditch lining 0906.1 Ditch lining (150mm thick) Sq. m. 2.000 26,819 53,638 6,479 25,875 21,285 15,360 37,511 768

Bridge (Arch Bridge L=190m, W=14m) 3,300,000 118,800 1,689,600 1,491,600 2,006,400 1,193,280 100,320

MSCELLANEOUS STRUCTURES(1300 SAFETYBARRIERS, DELINEATORS AND FENCES, 1400HIGHWAY SIGNS AND ROAD MARKINGS, ANDOTHER ITEMS, 10% of SECTION 200 to SECTION

723,445 30,205 555,519 137,720 522,323 175,005 26,116

MEASURED WORKS TOTAL(SECTION 200 to 1900) 7,957,897 309,155 4,030,334 3,618,408 4,293,362 3,449,866 214,668

SECTION 100 PRELIMINARIES (25% of SECTION200 to SECTION 1800) ------ 1,989,474 16,439 894,088 1,078,947 1,471,594 444,300 73,580

SUB TOTAL 9,947,371 325,593 4,924,422 4,697,355 5,764,956 3,894,166 288,248

CONTINGENCY (10% of SECTION 200 to SECTION 1800) ------ 795,790

Total 10,743,160

ItemNo. Description Unit

Cost ComponentUnit Price(RO) Quantity Cost

(RO)

Page 68: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-2-1

Annex 18-2 Detailed cost estimate of Hamra – Rustaq Road without the Bridge

Lab. Mat. Equip. For. Local TaxEarthworks

203 Earthworks Excavation203.1 Suitable excavation to embankment Cu. m. 2.109 267,489 564,189 9,715 26,329 528,145 300,204 248,975 15,010203.2 Suitable excavation to waste Cu. m. 1.731 160,743 278,299 4,827 11,130 262,342 147,759 123,152 7,388203.4 Borrow excavation to embankment Cu. m. 3.660 71,379 261,246 1,117 89,333 170,795 92,778 163,829 4,639

206 Excavation and Backfilling for Structures

206.1 Structural excavation in soils to a depth of 2m. Cu. m. 1.475 27,523 40,597 1,121 2,418 37,058 20,860 18,694 1,043

206.3 Structural excavation in rock to a depth of 2m. Cu. m. 2.625 27,743 72,834 1,335 2,923 68,575 38,622 32,281 1,931

206.4 Structural excavation in rock to a depth more than 2m. Cu. m. 4.043 30,963 125,192 3,626 26,174 95,393 57,441 64,879 2,872Subbase and Base course

302 Granular Subbase302.1 Class A Subbase Cu. m. 5.000 0 0 0 0 0 0 0 0302.2 Class B Subbase Cu. m. 4.000 60,639 242,558 4,982 53,841 183,734 101,576 135,903 5,079302.3 Class C Subbase Cu. m. 3.000 0 0 0 0 0 0 0 0303 Aggregate Basecourse 0303.1 Class A Basecourse Cu. m. 5.000 0 0 0 0 0 0 0 0303.2 Class B Basecourse Cu. m. 4.000 45,461 181,843 3,801 39,285 138,756 76,800 101,203 3,840303.3 Class C Basecourse Cu. m. 3.000 0 0 0 0 0 0 0 0

Bituminous Pavement401 Bituminous Prime Coat and Tack Coat401.1 Prime Coat such as MC70 Kg 0.120 283,000 33,960 98 33,559 303 21,960 10,902 1,098401.2 Tack Coat such as RC250 Kg 0.150 0 0 0 0 0 0 0 0405 Bituminous Wearing Course405.1 Bituminous Wearing Course Cu. m. 17.000 30,754 522,811 1,295 488,839 32,678 334,992 171,070 16,750

Concrete and Concrete Structures504 Concrete for Structures504.1 Concrete Class 28/20 Cu. m. 40.000 40,943 1,637,731 128,740 822,594 686,398 571,315 1,037,851 28,566504.2 Concrete Class 32/20 Cu. m. 45.000 0 0 0 0 0 0 0 0504.3 Concrete Class 36/20 Cu. m. 50.000 0 0 0 0 0 0 0 0509 Reinforcing Steel509.1 High yield steel bars ton 250.000 2,077 519,281 20,416 453,582 45,283 318,688 184,658 15,934509.2 Mild steel bars ton 250.000 33 8,285 359 7,179 746 5,060 2,972 253

Drainage801 Pipe Culverts801.1 Reinforced Concrete Pipe Culvert 600 mm Lin. m. 35.000 14 490 18 113 359 256 221 13801.2 Reinforced Concrete Pipe Culvert 750 mm Lin. m. 50.000 0 0 0 0 0 0 0 0801.3 Reinforced Concrete Pipe Culvert 900 mm Lin. m. 75.000 98 7,350 265 1,698 5,388 3,837 3,321 192801.4 Reinforced Concrete Pipe Culvert 1050 mm Lin. m. 100.000 0 0 0 0 0 0 0 0801.5 Reinforced Concrete Pipe Culvert 1500 mm Lin. m. 155.000 252 39,060 1,406 9,023 28,631 20,389 17,651 1,019

Slope Protection901 Rip Rap901.1 Loose stone riprap Class A Cu. m. 6.000 10,652 63,911 1,770 15,360 46,781 26,381 36,210 1,319901.2 Loose stone riprap Class B Cu. m. 6.000 0 0 0 0 0 0 0 0901.3 Mortared stone riprap Cu. m. 15.000 41,701 625,516 38,331 342,588 244,597 185,078 431,184 9,254902 Gabions902.1 Gabions Cu. m. 13.000 0 0 0 0 0 0 0 0906 Ditch lining906.1 Ditch lining (150mm thick) Sq. m. 2.000 35,999 71,998 8,697 34,731 28,570 20,617 50,350 1,031

MSCELLANEOUS STRUCTURES(1300 SAFETYBARRIERS, DELINEATORS AND FENCES, 1400HIGHWAY SIGNS AND ROAD MARKINGS, ANDOTHER ITEMS, 10% of SECTION 200 to SECTION

529,715 22,116 406,758 100,841 382,451 128,141 19,123

MEASURED WORKS TOTAL(SECTION 200 to 1900) 5,826,866 254,035 2,867,457 2,705,374 2,727,066 2,963,447 136,353

SECTION 100 PRELIMINARIES (25% of SECTION200 to SECTION 1800) ------ 1,456,717 12,037 654,662 790,018 1,077,519 325,322 53,876

SUB TOTAL 7,283,583 266,071 3,522,119 3,495,392 3,804,584 3,288,769 190,229

CONTINGENCY (10% of SECTION 200 to SECTION 1800) ------ 582,687

Total 7,866,270

ItemNo. Description Unit Unit Price

(RO)Quantity Cost

(RO)Cost Component

Page 69: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-1

Ann

ex 1

8-3

E

NV

IRO

NM

EN

TAL

CH

EC

KL

IST

(H

AM

RA

TO

RU

STA

Q R

OA

D)

Roa

d Se

ctio

n: F

rom

Ham

ra to

Rus

taq,

Exi

stin

g ro

ad c

ondi

tion:

Gra

vel r

oad

Proj

ect R

oad

No.

: N27

, Pla

nnin

g ro

ad: M

etal

led

2-la

ne r

oad,

Dis

tanc

e: 2

8.3k

m

Env

iron

men

tal I

tem

s

Pres

ent e

nvir

onm

enta

l con

ditio

n

Impa

ct R

atin

g 1

= Sl

ight

2

= M

oder

ate

3= S

igni

fican

t

Rem

arks

Pred

icte

d tra

ffic

volu

me

in 2

030:

10

,000

veh

/day

Air

Pol

lutio

n -

Not

sig

nific

ant

so f

ar,

beca

use

very

low

tra

ffic

volu

me.

1~

2 -

Alth

ough

the

pro

ject

are

a at

pre

sent

is

low

po

pula

tion,

slig

ht t

o m

oder

ate

impa

ct t

o ai

r

qual

ity is

ant

icip

ated

due

to in

crea

se o

f fu

ture

tra

ffic

volu

me,

app

roxi

mat

ely

10,0

00 v

eh/d

ay,

and

narr

ow w

adi c

hann

els a

roun

d Za

mm

ah a

nd

Far v

illag

es.

Eff

luen

t and

Wat

er c

onta

min

atio

n - N

ot si

gnifi

cant

so fa

r. 1

- A

dditi

onal

impa

ct to

effl

uent

and

wat

er q

ualit

y du

e to

new

road

con

stru

ctio

n is

not

ant

icip

ated

in th

e ar

ea.

Noi

se a

nd V

ibra

tion

- Not

sign

ifica

nt so

far.

1~2

- A

lthou

gh

the

proj

ect

area

in

ve

ry

low

popu

latio

n, s

light

to m

oder

ate

impa

ct to

noi

se

pollu

tion

is

antic

ipat

ed

due

to

incr

ease

of

fu

ture

tra

ffic

volu

me,

app

roxi

mat

ely

10,0

00

veh/

day,

and

nar

row

wad

i ch

anne

ls a

roun

d Za

mm

ah a

nd F

ar v

illag

es.

Page 70: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-2

Lan

d Su

bsid

ence

- N

o ex

istin

g in

the

area

. 1

- Not

exi

stin

g.

Topo

grap

hy a

nd G

eolo

gy

Phot

o: G

entle

slop

e in

sout

h pa

rt of

Al J

abal

Al A

kdar

Mou

ntai

ns

Pho

to: S

teep

slop

e in

nor

th p

art o

f

Al J

abal

Al A

kdar

Mou

ntai

ns

Topo

grap

hy:

- P

roje

ct a

rea

is lo

cate

d in

the

cent

ral p

art o

f the

Al

Haj

ar A

l Gha

rbi M

ount

ains

. Al J

abal

Al A

kdar

(J

abal

Sh

ams)

M

ount

ains

, be

ing

the

high

est

peak

, 3,

009m

abo

ve s

ea l

evel

, in

Om

an,

is

loca

ted

10km

wes

t of

the

are

a an

d m

ount

ain

ridge

fro

m J

abal

Sha

ms

is c

onne

cted

to

the

proj

ect a

rea.

- Sou

ther

n sl

ope

of th

e A

l Jab

al A

l Akd

ar m

ount

ain

ridge

is

char

acte

rized

by

larg

e sc

ale

of c

uest

a to

pogr

aphy

sh

owin

g ge

ntle

sl

ope.

O

n th

e

cont

rary

, nor

ther

n sl

ope

of th

e A

l Jab

al A

l Akd

ar

mou

ntai

n rid

ge is

cha

ract

eriz

ed b

y st

eep

slop

e to

ve

rtica

l cl

iff

as

the

cues

ta

topo

grap

hy.

The

proj

ect

road

sec

tion

belo

ngs

to t

he n

orth

ern

stee

p sl

ope

area

. (1

) 0 (S

tart

poin

t: H

at v

illag

e)~1

5.3k

m (J

unct

ion

to

Fash

ah):

-

The

road

se

ctio

n be

twee

n th

em,

mar

ked

by

rugg

ed a

nd s

teep

slo

pe t

opog

raph

y, b

elon

gs t

o

the

high

to

mod

erat

e re

lief

of m

ount

ain

and

pass

es a

long

Wad

i al H

att a

nd W

adi B

ani A

wf.

V-sh

ape

deep

ly in

cise

d va

lleys

and

like

ly o

ddly

shap

e ro

ck o

utcr

oppi

ngs s

how

in m

any

plac

es.

1~2

- Sl

ight

to

m

oder

ate

impa

ct

due

to

road

co

nstru

ctio

n in

the

cen

tral

part

of A

l H

ajar

Mou

ntai

ns

with

re

lativ

ely

thic

k w

adi

vege

tatio

n.

It is

ne

cess

ary

to

follo

w

the

exis

ting

road

al

ignm

ent

for

min

imiz

ing

of

cutti

ng.

Phot

o: D

eepl

y in

cise

d va

lley

Pho

to: V

-sha

pe d

eep

valle

y at

Zam

mm

ah

Page 71: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-3

(2

) 15

.3~2

8.3k

m (

End

poin

t): T

his

road

sec

tion

is

also

mar

ked

by r

ugge

d m

ount

aino

us te

rrai

n an

d be

long

s to

th

e m

oder

ate

and

low

re

lief

of

mou

ntai

n.

The

sect

ion

pass

es

alon

g w

adi

chan

nel o

f Wad

i Ban

i Aw

f. N

ear e

nd p

oint

of t

he

road

cha

nges

low

er h

ills a

nd to

flat

ter t

erra

in.

Geo

logy

:

- Th

e pr

ojec

t are

a cr

ossi

ng th

e A

l Jab

al A

l Akd

ar

Mou

ntai

ns

are

cont

inuo

usly

cr

oppe

d ou

t th

e A

utoc

htho

nous

Uni

ts,

cons

istin

g of

the

Huq

f

Gro

up o

f En

d-Pr

otoe

zoic

to

Cam

bria

n ag

e an

d A

khda

r G

roup

, Sa

htan

Gro

up,

Kah

mah

Gro

up

and

Was

ia G

roup

ran

ging

in

age

from

Lat

e

Perm

ian

to M

iddl

e C

reta

ceou

s. Th

e H

uqf G

roup

is

in

tens

ely

met

amor

phos

ed

and

show

s fin

e sc

hist

ose.

- Th

e ge

olog

ical

stru

ctur

e cl

early

sho

ws

antic

line

defo

rmat

ion

(dom

e st

ruct

ure)

in la

rge

scal

e.

- Ig

neou

s ro

cks

orig

inat

ed f

rom

anc

ient

oce

an

floor

, so

-cal

led

Sam

ail

Oph

iolit

e, a

re l

ocal

ly

foun

d ne

ar e

nd p

oint

of t

he p

roje

ct ro

ad.

Ph

oto:

Cut

ting

of E

xist

ing

road

Ph

oto:

Lim

esto

ne o

f Def

orm

ed H

uqf G

roup

Soil

- S

oil

is p

oorly

dev

elop

ed,

mos

tly s

uffe

red

by

win

d er

osio

n. A

lluvi

al s

oil i

s fo

und

in th

e w

adi

and

terr

aces

, but

mos

tly th

in.

1~2

- Slig

ht to

mod

erat

e im

pact

to s

urfa

ce s

oil d

ue to

ro

ad c

onst

ruct

ion.

It i

s ne

cess

ary

to f

ollo

w th

e ex

istin

g ro

ad

alig

nmen

t fo

r m

inim

izin

g of

cu

tting

.

Page 72: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-4

Hyd

rolo

gy, g

roun

dwat

er

Ph

oto:

Fal

aj a

t dow

nstre

am o

f Al B

ir

Ph

oto:

Wad

i sed

imen

ts in

Aad

i Ban

i Aw

f

Hyd

rolo

gy:

- Pre

cipi

tatio

n in

the

proj

ect a

rea

is re

lativ

ely

high

, 20

0 to

300

mm

by

year

. The

se e

vent

s can

pr

oduc

e ra

pid

runo

ff a

nd m

ajor

wad

i und

erflo

w.

- Alth

ough

the

road

sect

ion

from

0 k

m to

7.8

km

pass

es th

e st

eep

slop

e, re

st o

f roa

d se

ctio

n fr

om

7.8

km to

28.

3 km

(End

poi

nt) m

ostly

pas

ses i

n

the

wad

i cha

nnel

s of W

adi B

ani A

wf,

whi

ch a

re

likel

y to

exp

erie

nce

flood

ing.

G

roun

dwat

er:

- The

re a

re e

ight

settl

emen

ts in

the

proj

ect a

rea.

M

ost o

f set

tlem

ents

get

wat

er b

y fa

laj s

yste

m. A

t pr

esen

t, no

fala

j sys

tem

cro

sses

exi

stin

g ro

ad.

1 - N

ot si

gnifi

cant

impa

ct w

ith p

roje

ct. H

owev

er, a

s th

e pr

ojec

t ar

ea

has

rela

tivel

y m

uch

prec

ipita

tion,

it

is n

eces

sary

to

inst

all

enou

gh

drai

nage

sy

stem

an

d pr

otec

tion

agai

nst

flood

ing

flow

s.

Ph

oto:

Wat

er g

age

in W

adi B

ani A

wf

Page 73: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-5

Eco

-sys

tem

, Flo

ra a

nd F

auna

Ph

oto:

Wad

i veg

etat

ion

in W

adi a

l Hat

Phot

o: W

adi v

eget

atio

n in

Wad

i Ban

i Aw

f

Flor

a:

- Veg

etat

ion

is fo

und

alon

g th

e en

tire

stre

tch

of th

e pr

ojec

t ar

ea.

The

low

er l

ying

hill

s ha

ve l

ess

vege

tativ

e co

ver t

han

the

high

er a

reas

, exc

ept f

or

depr

essi

ons

and

wad

i flo

w

chan

nels

. Th

e ve

geta

tion

can

be

clas

sifie

d as

an

op

en

xeno

mor

phic

Eup

horb

ia c

omm

unity

type

. Muc

h

of

this

ar

ea

repr

esen

ts

a go

od

exam

ple

of

undi

stur

bed

habi

tat i

n no

rther

n O

man

. Fa

una:

- W

ildlif

e kn

own

to th

e ar

ea in

clud

es th

e A

rabi

an

Leop

ard,

Gaz

elle

, Ara

bian

tah

r an

d ot

her

faun

a su

ch a

s th

e re

d fo

x, e

tc.

The

IUC

N r

ed l

ist

of

thre

aten

ed a

nim

als

(IU

CN

199

0) d

escr

ibes

the

m

ount

ain

gaze

lle a

s vu

lner

able

. Leo

pard

and

the

tahr

are

con

side

red

enda

nger

ed.

2 -

Whi

lst

the

area

doe

s no

t ha

ve o

ffici

al r

eser

ve

stat

us, p

erm

its a

re re

quire

d to

ent

er so

me

area

s. -

This

are

a co

uld

be o

ne o

f th

e pr

otec

tion

area

s pr

ocla

imed

as N

atur

e R

eser

ve in

nea

r fut

ure.

- Any

dev

elop

men

t in

the

area

will

be

cons

ider

ed

as h

avin

g a

sign

ifica

nt im

pact

as

a re

sult

of th

e va

luab

le

natu

re

of

the

habi

tat,

beca

use

of

rapi

dly

incr

ease

of

traffi

c vo

lum

e in

fut

ure.

Th

e fu

ture

traf

fic v

olum

e in

203

0 is

pre

dict

ed

to b

e 10

,000

veh

/day

in th

e pr

ojec

t are

a.

- It

is

nece

ssar

y to

in

vest

igat

e co

ncer

ning

ec

o-sy

stem

, flo

ra

and

faun

a in

th

e ar

ea,

parti

cula

rly r

elat

ions

hip

betw

een

the

Al

Jaba

l

Al

Akd

ar

area

an

d pr

ojec

t ar

ea

befo

re

cons

truct

ion

or d

urin

g EI

A.

Lan

dsca

pe

- The

are

a is

the

mos

t typ

ical

land

scap

e of

hig

hlan

d in

Om

an.

1 - M

inim

um c

ut a

nd e

mba

nkm

ent w

ill b

e re

quire

d fo

r the

road

con

stru

ctio

n.

Haz

ards

- N

ot e

xist

ing

so fa

r. B

ut s

mal

l ero

sion

of r

oad

due

to fl

oodi

ng is

foun

d in

som

e pl

aces

. 1

- Not

exi

stin

g im

pact

by

road

impr

ovem

ent.

Reg

iona

l Dev

elop

men

t on

Nat

ural

E

nvir

onm

ent

- Not

exi

stin

g so

far.

1 - U

nkno

wn.

Oth

er Im

pact

s on

Nat

ural

E

nvir

onm

enta

1

- Not

exi

stin

g so

far.

1 - U

nkno

wn.

Cul

tura

l Her

itage

- N

ot e

xist

ing

so fa

r. 1~

2 -

The

inve

stig

atio

n of

the

cultu

ral h

erita

ge in

the

Page 74: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-6

site

mig

ht b

e re

quire

d be

fore

road

con

stru

ctio

n.

Was

tes

- Not

sign

ifica

nt so

far.

1 -

As

high

fu

ture

tra

ffic

volu

me

in

2030

is

pr

edic

ted,

was

tes

alon

g th

e ro

ad a

nd p

arki

ng

area

s co

uld

be

incr

ease

d.

And

in

crea

se

of

unco

ntro

lled

was

tes

mig

ht b

e af

fect

ed t

o th

e ec

o-sy

stem

.

Reg

iona

l Dev

elop

men

t on

Soci

al

Env

iron

men

t

- Not

exi

stin

g so

far.

1 - U

nkno

wn.

Page 75: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-7

Oth

er Im

pact

s on

Soci

al E

nvir

onm

ent

Ph

oto:

Hat

vill

age

Phot

o: S

mal

l set

tlem

ent i

n W

adi H

at

Ph

oto:

Nar

row

wad

i cha

nnel

- 0

km:

Junc

tion

to H

at v

illag

e. T

he d

ista

nce

betw

een

junc

tion

and

Hat

vill

age

is a

bout

1km

. -

1.5

km: 6

hou

ses

and

Dat

e fa

rm w

ith fa

laj s

yste

m.

Unk

now

n na

me

of

this

smal

l se

ttlem

ent.

The

settl

emen

t is l

ocat

ed 4

0m fr

om e

xisti

ng ro

ad. T

here

is

wat

er fl

ow in

Wad

i Hat

. Ele

ctric

ity is

supp

lied.

3.

7km

: Dee

p an

d na

rrow

val

ley,

brid

ge is

pla

nned

to

bui

ld, 1

2o lo

ng, a

s a a

ltern

ativ

e.

- 5.

1km

: B

imah

set

tlem

ent.

2 ho

uses

and

dat

e fa

rms

with

fa

laj

syst

em.

The

settl

emen

t is

lo

cate

d 40

0m fr

om e

xist

ing

road

.

- 5.

1km

: Za

mm

ah v

illag

e. 1

2 ho

uses

and

dat

e fa

rms w

ith fa

laj s

yste

m. T

he v

illag

e is

loca

ted

on

the

low

erm

ost t

erra

ce a

nd e

xist

ing

road

pas

ses i

n th

e w

adi.

No

scho

ol in

vill

age.

- 1

3.4k

m: 3

hou

ses

and

smal

l far

m. T

he s

ettle

men

t is

loca

ted

in n

arro

w w

adi c

hann

el a

nd 5

0m a

way

fr

om e

xist

ing

road

. Ele

ctric

ity is

supp

lied.

-

15.3

km:

Junc

tion

to F

asha

h. R

oad

pass

es i

n th

e w

ider

wad

i, ra

ngin

g in

wid

th fr

om 4

0m to

200

m.

-

18.3

km:

Teek

ah:

10

hous

es,

date

fa

rm

and

Med

ical

offi

ce.

- 20.

0 km

: Wat

er fl

ow g

age

and

fala

j. - 2

0.4k

m: A

l Was

it, 1

hou

se a

nd sm

all d

ate

farm

. an

d lo

ng d

ate

farm

s. R

ich

vege

tatio

n.

- 26.

8km

: Wat

er g

age

of M

RM

EWR

. - 2

8.3k

m: J

unct

ion

of N

R N

o.13

to A

r Rus

taq.

S

ubst

atio

n.

1~2

- So

me

sect

ions

of

the

road

pas

s th

roug

h an

d ne

arby

or

insi

de o

f th

e vi

llage

s an

d ar

eas

of

farm

land

, whi

ch m

ay b

e im

pact

ed b

y th

e ro

ad

deve

lopm

ent.

Bec

ause

hi

gh

traffi

c vo

lum

e,

appr

oxim

atel

y 10

,000

ve

h/da

y in

20

30,

is

pred

icte

d. P

artic

ular

ly,

narr

ow w

adi

chan

nels

ar

ound

Zam

mah

and

Far

vill

ages

.

- In

crea

sed

chan

ce o

f tra

ffic

acci

dent

as

wel

l as

do

mes

tic

anim

als

due

to

incr

ease

d tra

ffic

volu

me.

Phot

o: N

arro

w w

adi c

hann

el n

ear F

ar v

illag

e

Page 76: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A

18-3

-8

- 2

3.9

km: 2

hou

ses a

nd sm

all d

ate

farm

. - 2

5.6~

26.1

km: F

ar v

illag

e. M

ore

than

50

hous

es

- A

ir q

ualit

y

1~2

Incr

ease

d tr

affic

vol

ume

- Noi

se

1~2

Incr

ease

d tr

affic

vol

ume

- Top

ogra

phy

and

Geo

logy

1~

2 A

ltera

tion

of to

pogr

aphy

- Soi

l 1~

2 A

ltera

tion

of to

pogr

aphy

- Eco

-sys

tem

, Flo

ra a

nd F

auna

2

Hig

h po

tent

ial

of v

ario

us s

peci

es o

f flo

ra a

nd

faun

a In

crea

se o

f was

tes d

ue to

incr

ease

of v

isito

rs

Incr

ease

d tr

affic

vol

ume

- Cul

tura

l her

itage

1~

2 In

fluen

ce to

cul

tura

l her

itage

- Oth

er Im

pact

s on

Soci

al E

nvir

onm

ent

1~2

Incr

ease

of

chan

ce o

f tr

affic

acc

iden

ts d

ue t

o

incr

ease

d tr

affic

vol

ume

Eva

luat

ion

- Oth

er it

ems

1

Com

preh

ensi

ve E

valu

atio

n 2

Rec

omm

enda

tions

*1

Rec

omm

ende

d to

car

ry o

ut E

IA

* 1 :

Com

preh

ensi

ve E

valu

atio

n

1

: Non

e to

slig

ht im

pact

s.

: No

need

to c

arry

out

EIA

1~2

: Sm

all i

mpa

cts.

: Rec

omm

ende

d to

car

ry o

ut E

IA o

n as

sign

ed it

ems

2

: M

oder

ate

impa

cts.

: R

ecom

men

ded

to c

arry

out

EIA

2~3

: Rel

ativ

ely

sign

ifica

nt im

pact

s. : R

ecom

men

ded

to c

arry

out

EIA

3

: Sig

nific

ant i

mpa

cts.

: R

ecom

men

ded

to c

arry

out

EIA

Page 77: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-1

Annex 18-4

TERMS OF REFERENCE ON

THE ENVIRONMENTAL IMPCT ASSESSMENT OF

THE HAMRA - RUSTAQ RORD,

SULTANATE OF OMAN 1. Project Title

"Environmental Impact Assessment of the Hamrat – Rustaq Road, Sultanate of Oman" (hereinafter referred to as “Study”)

2. Executive Agency

Directorate General of Road, (hereinafter referred to as “DGR”), Ministry of Transport and Communications, Sultanate of Oman.

3. Location of Project Area

Project area is located in the central part of the Al Hajar Al Gharbi Mountains. Jabal Shams Mountain, being the highest peak in Oman, 3,009m above sea level, is located 10km west of start point of the project road, and mountain ridge from Jabal Shams is connected to the project area, as shown in Attachment-1.

4. Background of the project

The Hamrat – Rustaq Road is designated as one of the 6th (2000-2005) and 7th Plan (2006-2010) proposed projects. This road has an important role of directly connecting between Al Batinah Region and A’Dakhuliyah Region crossing the Al Hajar Al Gharbi Mountains. The road construction between Hamrat and Rustaq, which distance of the road is 76 km, is scheduled as four sections, i.e. Road Section I, II, III, and IV. The project road is the Road Section IV.

Page 78: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-2

The Road Section I was completed. Road Section II is under construction. Road Section III will be commenced to construct in this year. The road planning and design for the Road Section IV is going on.

5. Objectives of the Study The Study should carry out to accord the Royal Decree No. 10/82 and its amendments entitled “Law on Conservation of the Environment and Prevention of Pollution” as well as other relevant regulations, decisions and guidelines. The principles of the Study are as follows: - EIA is a process to help decision makers to protect, conserve and manage Oman’s

environment, according to the principles of sustainable development, maintaining human well-being, healthy environment and a sound economy;

- The EIA process should ensure that the individual, company or government agency, proposing a project considers its effect on health, economy and culture of surrounding community as well as its impact on air, land and water;

- The EIA should be applied as early as possible in project’s planning stage and before irrevocable decisions are made; and

- Public information is an important component of an open and balanced EIA process.

And, the specified objectives of the Study are shown as below: i) To identify, predict, and assess environmental impacts due to proposed activities

on the physical, biological and social environment; ii) To propose mitigation measures for avoiding and reducing the impacts and

evaluating associated risk; and iii) To submit the Environmental Impact Assessment report and relevant documents.

6. Project Description: The project description of the Hamrat - Rustaq Road is shown hereafter:

- The project road is located in the southeastern part of the Al Batinah Region and adjoined to the A’Dakhuliyah Region. The project road area is topographically characterized by steep northern slope of cuesta topography developed at Jabal Shams Mountain,

- The project road has important role of directly connecting between Al Batinah

Page 79: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-3

Region and A’Dakhuliyah Region, - The project road is the final road section (Section IV) of the Hamrat – Rustaq Road. - The length of the project road is 28.3 km, - At 3.7 km from start point it is planned to build bridge, 120 m long, as an alternative

crossing deep valley, - The road hierarchy of the project road is designated secondary road that its

right-of-way is 50 m, and - The project road traverses mostly mountainous terrains and along the wadis, as

shown in Atachment-2. 7. Scope of the Study:

This project is classified as Roads of the Group five (Service projects) in accordance of the “Guidelines for Obtaining Environmental Permits” (Directorate General of Environmental Affaires). In addition, as results of the environmental consideration of the project is recommended that the project EIA should be carried out before project implementation, comprehensive EIA should be required. In order to achieve the objectives mentioned above, the scope of the Study consist of the following items: 1) Collect and review the existing data and information relevant to the project - Legislative information, - Topographical, geological and pedological data, - Aero photographs and/or satellite images covered in and around the project area, - Meteorological data around the project, - Hydrological and hydro-geological data relevant to the project, - Biological and ecological data and information, - Information of land use and its history, - Natural scenic spots, national park, etc., - Information of open-air recreation, - Information of natural hazards, - Sociological data and information, - Administrative data and information, - Socio-economic data, - Cultural and historical heritages, - Traffic volume data, and - Other data and information relevant to the traffic, etc.

Page 80: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-4

2) Project description

- Location, - Road design and design criteria,

- Road capacity, - Road section for construction, - Pre-construction activities,

- Construction plans and scheduling, - Staffing and support,

- Associating facilities and services, - Operating procedures and maintenances, - Future traffic volume,

- Land use requirement, and - Alternative alignments, etc.

3) Site description and its environment (Baseline survey) The content of the baseline study consists of the following environmental items:

(1) Air quality: Measuring points consist of each villages and settlements as well as start and end points, and number of measuring times is two, i.e. summer and winter seasons, and measuring parameters consist of SO2, TSP, PM10 and fallen-dust,

(2) Water quality: measuring points consist of each surface water flows, wells, water spring, and aflaj water, and number of measuring times is two, i.e. summer and winter seasons, and analysis parameters consist of pH, Electric conductivity (EC), Water temperature, Ca, Mg, Fe, Mn, K, Na, CO3, Hg, Pb, As, Cr, Cd, Se, SO4 and Cl,

(3) Noise and vibration: measuring points consists of each villages and settlements, and number of measuring times is two, i.e. summer and winter seasons, and measuring parameter is dB(A) on the boundary of ROW,

(4) Topography and geology: Topographical and geological investigation, and drilling survey at bridge building site, 2 holes x 10m in depth,

(5) Soil: Pedological investigation consists of soil sections at the point of every 2 km interval and each villages and farmlands,

(6) Surface water and groundwater: Hydrological and hydro-geological investigation consist of outflow and measurement in the sites, comprising of pH, EC and Water temperature,

(7) Ecosystem, flora and fauna: Number of investigating times is two, i.e. summer and winter seasons,

(8) Landscape,

Page 81: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-5

(9) Hazards, (10) Communities, (11) Wastes, (12) Cultural heritage, (13) Resettlement, and (14) Traffic volume and traffic accidents: Traffic census and interviews.

While baseline survey, the proponent should be found stakeholders, related to the project, e.g. residents of local communities in the site, indigenous people, experts from government organizations, local government officer, NGO, etc., and should be collected their opinions in order to get an appropriate agreement and to reflect to the decision-making of the project.

4) Evaluation of project’s impacts

The content of the evaluation of impacts with the project consists of the following items:

- Cumulative and indirect environmental impacts, likely to result from the project in

combination with existing or planned projects or activities, - Impact on socio-economic conditions, - Impact on physical and cultural heritage, and

- Proposal and evaluation of reasonable alternatives to the project and their impacts.

The evaluation should be carried out to use the environmental standards or guidelines to establish significant of the harmful impacts. A risk assessment can be used when there are no applicable threshold standards or guidelines. The following criteria should be applied to determine significant or adverse impacts:

(1) Magnitude, (2) Frequency and duration, (3) Location and sensitivity of environment, and (4) Irreversibility.

5) Mitigating measures and evaluating associated risks

The following approaches can be used to mitigate likely significant harmful impacts:

- Direct prevention by avoiding sensitive areas, - Reduction by adjusting work schedules, pollution control devices, changes in

design, etc.,

Page 82: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-6

- Restoration and remediation measures, and - Compensation.

6) Final assessment

The final assessment should be done to evaluate through a net effect analysis. 7) Documentation

Documentation I composed of reference and working documents. The former will contain a detailed record of the work done on the EIA. The latter is the document, which contain the information for action, e.g. the Environmental Impact Statement as well as Summary.

The content of the Environmental Impact Statement should be contained the following items:

- Information describing the EIA, - Information describing the project, - Information describing the site and its environment, shown as below:

(1) Physical features (2) Legislative framework (3) Assessment of impacts, shown as below:

a. Impacts on human beings, buildings and man made features, b. Impacts on flora, fauna and geology, c. Impacts on land, d. Impacts on water, e. Impacts on air and climate, f. Other direct and secondary effects associated with the project, g. Environmental management plan – Mitigating measures and risk

assessment, and h. Conclusions and additional information.

8. Study Timetable Tentative study timetable of the project shows in Attachment-3.

Page 83: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-7

Attachment: Attachment-1 Location Map of the Project Road Attachment-2 Topographic Map of the Project Road Attachment-3 Tentative Study Timetable of the Project

Page 84: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-8

0 50 100km25

Sur

Muscat

Saudi Arabia

United Arab Emirates

Yemen

Arabian Sea

Salalah

Persian Gulf

Shinas

Dank

IbriNizwa

Hayma

Ad Duqm

Shalim

Al Kahil

SadahTaqah

Thumrayt

Khasab

SahamAl Khaburah

Barka

Ibra

Adam

Al Ghabah

Dawkah

LEGEND

Major road Network

Project site

Attachment-1 Location Map of the Project Road

Page 85: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-9

0 5 km

Attachment-2 Topographic Map of the Project Area

End point

Start point

N

Page 86: FINAL REPORTFINAL REPORT MAIN REPORT-2MAIN REPORT-2 … · 2005. 4. 24. · -i - Report Composition The Final Report of the Study is structured to meet the requirements of two user-groups,

A18-4-10

Attachment-3 Tentative Study Timetable of the Project

Year 200 - Remarks

Number of month

1 2 3 4 5 6 7 8 9 10 11 12 13 14 -

1. Data collection

2. 1st. Field investigation

Summer/winter

season

3. 2nd. Field investigation

Winter/summer

season

4. Data analysis

5. Reporting 1

2

3

△ 1 : Inception report : Work in the site

2 : Draft Final report : Chemical analysis 3 : Final report

○ : Monthly report