final report_sakthy selvakumaran

Upload: tsuak

Post on 13-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    1/57

    Low Cost Structures inMicro-Hydroelectric Power

    Generation

    by

    Sivasakthy Selvakumaran (SID)

    Fourth-year undergraduate project in Group D

    2009/2010

    " I hereby declare that, except where specif icall y indicated, the work submi tted herein i s

    my own ori ginal work."

    Signed:

    Date:

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    2/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    i

    Sivasakthy Selvakumaran Sidney Sussex

    Technical Abstract

    Motivations and fieldwork

    This report performs an analysis, evaluation and systemisation of techniques used in the

    construction of micro-hydroelectric systems by Practical Action in Cajamarca, Peru. The systems

    make use of the potential energy of water as it flows across the mountainside. Water is diverted

    by an intake structure, from a stream or river into a channel. The gravitational force of falling

    water drives a water turbine and generator. Practical Action work in some of the most

    mountainous regions of Peru. The geography of the area provides many challenges, including

    transportation, limited infrastructure and energy supply, and both drought and flooding events.

    My time in Cajamarca was split between desk-based research at the Practical Action offices in

    Peru, and field survey at micro-hydroelectric system sites. Project objectives and evidence of the

    problems that exist were discussed with engineers and local people. A sample of micro-

    hydroelectric power sites were analysed including systems of different sizes, and projects under

    construction as well as in operation. Work was undertaken in Spanish.

    Analysis and conclusions

    It was proposed to undertake an analysis of a micro-hydroelectric scheme with a focus on the

    intake structure and the channels. The proposed improvements to the civil works would increase

    some costs but these are offset through efficiencies in reduced material usage and reduced costs

    over the lifecycle of the schemes.

    Issues identified with the intake included lack of reinforcing steel combined with low strength

    concrete. A program was developed to provide an efficient design of the intake structure and to

    check suitability in terms of stability, sliding and other design considerations. The design

    program is simple and easy to understand; it allows design variations and provides estimated

    costs for the system components. Design options for the intake structure, other than a

    reinforced concrete, have been assessed, and developed into alternative solutions for

    consideration by Practical Action. These include low cost structures of gabion or masonry walls

    that are considered as appropriate technology. These walls have a dual function of acting as the

    intake structure and aiding with stability of the adjacent slopes.

    Issues identified with the channels included some cracking and the collapse or destruction of the

    channels due to slope failure. The channels conveying water to the turbines in micro-

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    3/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    ii

    Sivasakthy Selvakumaran Sidney Sussex

    hydroelectric systems are relatively small and do not pose any significant structural issues. For

    these types of systems, the primary purpose of the channel lining is to avoid losses of water by

    infiltration and to protect the base and the slopes of the channel against erosion caused by the

    flow velocity. In terms of the structural integrity, the thickness of the wall can be reduced to the

    minimum within the practical functionality and without running significant risks.

    As a direct result of the observations and analysis it was concluded that the slope stability was a

    major influence in the effectiveness of both the intake structure and the channels. It was

    therefore decided to investigate the behaviour of the surrounding slopes and their effect on the

    infrastructure of concern.

    Various means to improve slope stability were investigated and some design guidelines are

    suggested for appropriate solutions (such as gabion walls). A significant factor contributing to

    the slope instability is the build up of water pressures in the soil which exert significant forces on

    the structures as well as interrupting the water supply to the turbine. To address this risk, the

    provision of land drainage features was considered.

    Further work

    An important part of this research is the transfer of knowledge. This means that approved and

    improved technology can be developed and implemented, avoiding potential risks and improving

    reliability of the systems.

    A practical guide is being developed in order to clearly illustrate the issues identified through this

    research project and mitigation measures. This covers potential design options, early warnings

    and prevention of failures from the point of view of the local people who are responsible for the

    building and maintenance. A technical report is being produced, in Spanish, with the results of

    this research and suggestions for improvements to the micro-hydroelectric works.

    If any of the suggestions made prove to be appropriate or worthwhile to Practical Action to trial

    or implement, I would be interested in returning to Cajamarca, Peru to help with the

    development and assess how the effective they prove to be.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    4/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    iii

    Sivasakthy Selvakumaran Sidney Sussex

    Acknowledgements

    Firstly, I would like to thank ITDG: Soluciones Prcticas (Practical Action) in Peru for hosting

    me and providing me with the opportunity to carry out this research. I am especially thankful toGilberto Villanueva for guiding me whilst I was in Cajamarca and to Javier Coello for his

    support. I am grateful to all those who welcomed and accompanied me in the various villages

    and to the site visits in Cajamarca. I am most grateful for those who hosted and allowed me to

    attend their meetings and functions and provided their valuable input.

    I owe an enormous debt of gratitude to the staff at PREDES (Centro de Estudio y Prevencin

    de Desastres) who hosted me and provided assistance and advice during my entire stay in Peru.

    This research was financially supported by an Engineers Without Borders UK (EWB-UK)

    research bursary and later affiliated to the EWB-UK Research Programme.

    I would like to thank staff at Hyder, Mott MacDonald, Grontmij, and EWB-UK for their advice,

    suggestions and input. Also thanks are due to Maccaferri Ltd. (England), GVC and Oasys for

    allowing me free usage of their software as part of the analysis carried out under the study.

    At Cambridge University, I would like to thank my supervisor, Mr McRobie, for his support,

    encouragement and guidance throughout the project.

    To everyone who has supported me, in Peru and back home, and to those I met along the way

    that I have not specifically mentioned, I am also very thankful.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    5/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    iv

    Sivasakthy Selvakumaran Sidney Sussex

    Table of Contents

    Technical Abstract ........................................................................................................................................i

    Acknowledgements .................................................................................................................................... iii

    1. INTRODUCTION ................................................................................................................................ 1

    2. BACKGROUND ................................................................................................................................... 1

    2.1 The Work of Practical Action in Cajamarca ................................................................................ 1

    2.2 Objectives .......................................................................................................................................... 2

    3. FIELDWORK ........................................................................................................................................ 3

    3.1 Methodology ..................................................................................................................................... 3

    3.2 Design Issues .................................................................................................................................... 4

    4. DESIGN REVIEW AND CONSIDERATIONS ........................................................................... 5

    4.1 Total Energy Demand ..................................................................................................................... 6

    4.2 Hydraulic Energy Potential ............................................................................................................. 7

    4.3 Design of Civil Components to Meet Turbine Flow Requirements ........................................ 8

    4.3.1 Intake Structure ........................................................................................................................ 8

    4.3.2 Channels .................................................................................................................................... 9

    4.3.3 Settling Tank ........................................................................................................................... 11

    4.3.4 Pipeline..................................................................................................................................... 12

    5. INTAKE STRUCTURE ..................................................................................................................... 13

    5.1 Existing Intake Structure .............................................................................................................. 13

    5.1.1 Advantages over Complete Reinforced Concrete ............................................................. 15

    5.2 Field Observations ......................................................................................................................... 16

    5.3 Analysis ............................................................................................................................................ 17

    5.3.1 Existing Structures ................................................................................................................. 17

    5.3.2 Efficient Design ...................................................................................................................... 18

    5.3.2.1 Detailed Design of Larger Scale Intake Structure .......................................................... 18

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    6/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    v

    Sivasakthy Selvakumaran Sidney Sussex

    5.3.2.2 Development of Analysis Program .................................................................................. 19

    5.4Conclusions on Intake Structure .................................................................................................. 20

    6. CHANNELS ......................................................................................................................................... 22

    6.1 Existing Channel Types ................................................................................................................ 22

    6.1.1 Advantages over Traditional Design and Construction ................................................... 23

    6.2 Field Observations ......................................................................................................................... 24

    6.2.1 Problems Observed with Channels ..................................................................................... 24

    6.2.2 Risks ......................................................................................................................................... 24

    6.2.3 Infrastructure Vulnerability ................................................................................................... 24

    6. 3 Analysis ........................................................................................................................................... 26

    6.3.1 Larger Channels ...................................................................................................................... 26

    6.3.2 Optimisation of Size .............................................................................................................. 27

    6.3.3 Effect of Rapid Drawdown .................................................................................................. 28

    6.4 Conclusions on Channels ............................................................................................................. 29

    6.5 Recommendations ......................................................................................................................... 29

    7. SLOPE STABILITY............................................................................................................................ 30

    7.1 Typical Geological Conditions and Problems Encountered ................................................... 31

    7.2 Slope Analysis and Rapid Drawdown ......................................................................................... 33

    7.3 Potential Solutions to Slope Failure Issues ................................................................................ 34

    7.3.1 Reinforced Soil ....................................................................................................................... 34

    7.3.2 Soil Nailing .............................................................................................................................. 35

    7.3.3 Masonry walls .......................................................................................................................... 35

    7.3.4 Gabion walls............................................................................................................................ 36

    8. STRUCTURAL DESIGN SOLUTIONS ........................................................................................ 38

    8.1 Drainage Considerations ............................................................................................................... 38

    8.2 Potential Design Options. ............................................................................................................ 39

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    7/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    vi

    Sivasakthy Selvakumaran Sidney Sussex

    8.2.1 In-situ and Pre-Cast Reinforced Concrete Headwall ........................................................ 39

    8.2.2 Sheet Piled Headwall.............................................................................................................. 39

    8.2.3 Fabric Formwork ................................................................................................................... 40

    8.3 Use of Gabion Walls for an Intake Structure ............................................................................ 40

    8.4 Masonry Structures ........................................................................................................................ 41

    8.4.1 Mass Gravity Side Walls for Intake Structure .................................................................... 42

    8.5 Re-Design of an Intake System .................................................................................................... 44

    9. PRACTICAL GUIDE ......................................................................................................................... 46

    10. FURTHER WORK ........................................................................................................................... 47

    RISK ASSESSMENT RETROSPECTIVE ......................................................................................... 48

    BIBLIOGRAPHY .................................................................................................................................... 49

    Books ..................................................................................................................................................... 49

    Articles and Papers ............................................................................................................................... 49

    Internal Reports .................................................................................................................................... 49

    Standards ............................................................................................................................................... 50

    Images and Websites ............................................................................................................................ 50

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    8/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    1

    Sivasakthy Selvakumaran Sidney Sussex

    1. INTRODUCTION

    Practical Action (known as ITDG: Soluciones Prcticas in Peru) work in some of the most

    mountainous regions of Peru promoting micro-hydroelectric power schemes to provideelectricity to these remote populations. In their work Practical Action take the view that, for this

    scale of work, it is not necessary to use the same techniques or standards of safety for the civil

    engineering structures that are required on large hydroelectric stations. Some innovations have

    been permitted to reduce costs. Practical Action would like to better develop the engineering

    analysis for the solutions that they have been using so that any potential risks can be minimised.

    They are evaluating the themes of safety versus investment under a theme known as, obras

    civiles de bajo costo para microcentrales" (low cost civil works for micro-hydro schemes). This

    research project investigates civil infrastructure in micro-hydroelectric power schemes built by

    Practical Action in the region of Cajamarca.

    2. BACKGROUND

    The cities and villages of Peru have electricity but the communities that live in the mountains

    have few facilities and limited access to services. The geography of the area provides many

    challenges. These include difficulties in transportation as well as challenges in how to provide

    infrastructure and supply energy in a region prone to both drought and to flooding. Whilst

    rainfall in the region is favourable to a wide variety of agricultural production, the lack of access

    to electricity severely restricts economic development. A source of electricity could provide

    power for domestic lighting and cooking needs; for refrigeration for vaccine storage; for school

    classes; and for womens groupsto meet in the evening. It could be used directly for income-

    generating activities such as agricultural processes or light industry.

    2.1 The Work of Practical Action in Cajamarca

    Practical Action promotes small-scale hydroelectric power schemes that generate up to 500

    kilowatts of power. Their 'run-of-the-river' micro-hydro systems do not require a dam or storage

    facility to be constructed. Instead, water is diverted from the stream or river, channelled it in to a

    valley and 'dropped' in to a turbine via a pipeline, which converts the kinetic energy of flowing

    water into electricity. These schemes provide low-income communities in rural areas with an

    affordable, easy to maintain and long-term solution to their energy needs. This type of

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    9/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    2

    Sivasakthy Selvakumaran Sidney Sussex

    hydroelectric power generation avoids the adverse social and environmental impacts that larger

    hydroelectric schemes cause.

    Large projects use a dam and reservoir to smooth out the effects of water level fluctuations

    throughout the year. The major adverse impacts of hydroelectric power are social (forced

    displacement of people) and environmental (destruction of natural habitats). Large dams raise

    underground water levels near the reservoir, which has a significant effect on the surrounding

    flora and fauna. Millions of people have also lost their land and livelihoods, and have suffered

    because of downstream impacts and other indirect impacts of large dams. Large dams have been

    suggested as a major factor in the rapid decline of riverine biodiversity worldwide. This is why

    such larger hydroelectric schemes incorporating storage dams are not considered as a potential

    solution in this project.

    Practical Action require a technical analysis of specific aspects of their system for improved cost

    efficiency and reliability. They are interested in the analysis, evaluation and systemisation of the

    techniques and criteria that they have developed and adapted over the years.

    2.2 Objectives

    This research project is based on two civil components of the micro-hydro system, the intakestructure and the water channels. The objectives of this research project are:

    1. To better develop the analysis of the solutions implemented, analysing the safety and

    integrity of the structures and assessing current designs against technical standards.

    2. To analyse the design, materials, dimensions, etc., to determine whether the design being

    implemented uses the best available technology.

    3. To evaluate the safety and integrity of the designs against costs based on risk & value

    assessment.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    10/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    3

    Sivasakthy Selvakumaran Sidney Sussex

    3. FIELDWORK

    3.1 Methodology

    Before leaving the UK to conduct the site works, a health and safety risk assessment was

    conducted and an assessment on the nature of the work to be investigated were undertaken (as

    outlined in a proposal document I wrote prior to travel). All of the works carried out for this

    project have been conducted in Spanish and therefore I have translated all existing documents,

    technical information and drawings as required. The final findings produced will be translated to

    Spanish before being issued to Practical Action.

    Time in Cajamarca was split between desk-based research at the Practical Action offices in Limaand Cajamarca, and fieldwork at micro-hydroelectric system sites; working with local people and

    engineers. The sites included both those under construction and those already in operation. A

    summary of the sites investigated is provided in Table 1 below:

    Table 1: Information on hydro-electric systems investigated in Cajamarca.

    Name Location Power(kW)

    FamiliesBenefiting

    District Province Region

    MicrocentraleYanacancha

    La

    Encaada

    Cajamarca Cajamarca 40 110

    MicrocentraleChontabamba

    Paccha Chota Cajamarca 22 80

    Microcentrale ElRegalado

    Tumbadn San Pablo Cajamarca 12 40

    Central Hidroelctrica

    Chicce

    Baos del

    Inca

    Cajamarca Cajamarca Unknown Town of

    Cajamarca

    The sites were chosen in conjunction with the Practical Action engineer responsible for the

    projects. Transport and safety were limiting factors in the range of projects chosen for site visits.

    A sample was selected to show systems of different sizes, and to show projects ranging from

    those in operation for some years to projects still in the process of being constructed. In

    addition to visiting micro-hydro systems designed by Practical Action, a site visit was conductedto look at two intake structures which had been built by the Local Government for comparison

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    11/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    4

    Sivasakthy Selvakumaran Sidney Sussex

    purposes. These provided examples of larger structures, more expensive and more sophisticated

    technically than those designed by Practical Action.

    The visit to Peru was followed up in the UK by working with engineering consultancies to study

    water retaining structures and construction considerations in the UK.

    A few issues of concern in existing systems as well as those in the process of being constructed

    were observed. Some of the significant issues have been identified, investigated and suggested

    solutions developed throughout this project.

    3.2 Design Issues

    Following the fieldwork, the general design considerations were determined. Irrespective of the

    type of structure chosen for the application, calculations must demonstrate:

    Overall stability The whole structure should not sink, float, overturn, slide, or impose

    unacceptable loads on the ground.

    Element design The reinforced concrete walls/bases should have sufficient reinforcement

    and adequate thickness; timber/masonry/other materials should be of adequate strength.

    MaterialsConsiderations of whether materials are adequate and appropriate. For example,

    whether the concrete strength is adequate and whether materials are appropriate for the given

    environmental conditions.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    12/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    5

    Sivasakthy Selvakumaran Sidney Sussex

    4. DESIGN REVIEW AND CONSIDERATIONS

    It was decided that a complete analysis would be conducted for the civil works for a micro-

    hydroelectric scheme. This was done in order to develop a more efficient and appropriatetechnology for the remote regions of Cajamarca. The civil works which are a significant and

    critical component have the potential for design improvements and cost savings based on a risk

    and value approach (Owen 2009). In broad terms this looks at impacts and the probability of

    occurrence and assessing solutions, costs and residual risks.

    Figure 1 depicts the outline of a typical micro-hydroelectric scheme constructed by Practical

    Action in Cajamarca.The review would start at the intake structure where water is diverted from

    its natural course and carried along channels up to the settling tank (which helps to remove

    sediment that could harm the turbine). It then flows through a pipeline down the mountainside

    to drive a turbine. This in turn drives a generator to produce electricity.

    The purpose of this study is to have a better understanding of the current designs with a view to

    achieving cost efficiency and system security. The review of the parts of the micro-hydroelectric

    scheme would include the adequacy of the water conveyance system and improvements to the

    system design based on geotechnical, structural and hydraulic considerations.

    Figure 1: Diagram illustrating a typical micro-hydroelectric power scheme designed byPractical Action (image courtesy of Practical Action UK).

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    13/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    6

    Sivasakthy Selvakumaran Sidney Sussex

    The components of interest are the intake structure and channels. These were investigated and

    analysed for all of the sites visited in Peru. The analysis in this section of the report concentrates

    on two systems designed by Practical Action: one larger scheme and one smaller, the

    Chontabamba 22 kW Pelton Turbine and the Yanacancha 40 kW Pelton Turbine, respectively.

    The following outlines the process of checking the suitability of the system for Chontabamba

    Micro-Hydroelectric Power System. The system at Yanacancha was also analysed in a similar

    way (but not included in the body of this report as the methodology is the same).

    4.1 Total Energy Demand

    Before a system can be designed, the estimated energy requirement must be determined. All of

    the energy demands of these rural villages will not need to be satisfied simultaneously, for

    example the industrial consumption for a zone of little development will have a usage of nearly

    nil during the nights. Practical Action have developed calculation methods in order to make this

    estimation. The procedure is outlined in a Practical Action manual for the construction of

    micro-hydroelectric power schemes (Davila, C. et al. 2009).

    The following excerpt (Table 2) is taken from the technical profile produced for the

    Chontabamba Micro-Hydro System which is a document produced by Practical Action (ITDG2009) to calculate the size of the turbine, and hence size of the overall system, required to serve

    the Chontambamba population.

    Table 2: Determining the energy requirement of Chontabamba.

    TIPO DE DEMANDA(TYPE OF DEMAND)

    Demanda Diurna(Daily Demand)

    Demanda Nocturna(Nightly Demand)

    f.s. f.u. f.s. f.u.

    DOMSTICA (DOMESTIC) 16.00 kW 0.20 0.50 1.60 0.80 0.70 8.96ALUMBRADO PUBLICO

    (PUBLIC LIGHTING)1.28 kW 0.00 0.00 0.00 1.00 1.00 1.28

    INSTITUCIONAL(INSTITUTIONAL)

    6.00 kW 0.70 0.70 2.94 0.40 0.50 1.20

    INDUSTRIAL (INDUSTRIAL) 8.00 kW 0.80 0.80 5.12 0.40 0.40 1.28

    9.66 12.72

    f.s = factor de simultaneidad (simultaneity factor)

    f.u = factor de uso (usage factor)

    Mxima demanda diurna actual: 9.96 kW (Maximum actual nightly demand)Mxima demanda nocturna actual: 12.72 kW (Maximum actual daily demand)

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    14/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    7

    Sivasakthy Selvakumaran Sidney Sussex

    These figures were calculated by estimating the daily and nightly demand separately and

    comparing which of the two values is the maximum energy demand. Practical Action anticipate a

    10% loss in energy in the electrical transmission system, and a 40% increase in predicted usage

    requirements over the 15 year design life for this particular scheme. Hence, the demand

    becomes: 12.72 x1.10 x1.40 = 19.59 kW.

    4.2 Hydraulic Energy Potential

    At Chontabamba, the Ramosmayo stream passes through the right side of the town, at an

    approximate distance of 200 metres and the Suro stream passes through the left side at a greater

    distance. The Suro stream eventually joins the Ramosmayo stream. The streams originate in thewilderness at altitudes between 2600 and 3200 metres.

    The consistency of the flow of the streams throughout the year has been measured by Practical

    Action engineers by procedure as outlined in a Practical Action manual (Davila, C. et al. 2009).

    This ensures that the system is able to function throughout the year. Flow measurements made

    by Practical Action indicated that the flow rate during the months of lowest flow is between 0.06

    and 0.08 m3/s, with an average during the months of low flow of 0.07 m3/s.

    Electrical power is generated as the water falls from the settling tank down to the turbine house

    in the pipeline, converting the drop in potential energy into kinetic energy to drive the turbine.

    The approximate height of elevation through which the water needs to fall was found to be 58

    metres, using the inclinometer and measuring tape instrumental method; thus the electric power

    to be generated is 22.33 kW as estimated using Equation 1:

    = ....

    where = hydraulic efficiency of the turbine; = density of water (1000 kg/m3);

    g = acceleration due to gravity (9.81 m/s2); Q = volume flow rate passing through the turbine

    (m3/s); H = effective pressure head of water across the turbine (m).

    This generated power of 22 kW is assumed to be available at all times with a flow rate of

    0.07 m3/s passing through the turbine. Consequently the structures, pressure pipe and the

    mechanical and electrical components would be designed to achieve this design capacity. This isa suitable design value as it is above the power requirement of 19.59 kW with a factor of safety

    (Equ. 1)

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    15/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    8

    Sivasakthy Selvakumaran Sidney Sussex

    but not too far above so as to require enlarged structural, mechanical and electrical components,

    which would incur unnecessary additional costs. With the conditions of flow rate and elevations

    defined, the components of the micro-hydro system would have to be designed with

    characteristics of acceptable efficiency to achieve the required power of 22 kW. In this example,

    the components would be designed such that the minimum water flow rate is 0.07 m3/s.

    4.3 Design of Civil Components to Meet Turbine Flow Requirements

    4.3.1 Intake Structure

    The inlet structure should be located in the appropriate location of Ramosmayo River (just after

    the Suro River merges with it to access maximum available flow), and should consist of raising

    the necessary barrier height to permit the bypass of the design flow towards the transmission

    channel to the settling tank by constructing a barrier perpendicular to the direction of flow.

    Flow diverted into the channel would be controlled by a hand-wheel operated weir or sluice gate

    to regulate the required flow of water. The specified sluice gate size of 0.50m x 0.40m was

    determined to be appropriate.

    As part of this initial investigation the discharge over rectangular, trapezoidal and V-notch weirs

    were undertaken. Figure 2 below summarises these shapes used for which I calculated flow rate,

    Q, based on the value of water depth, h(as marked on Figure 2). Flow rates were estimated using

    data for the Practical Action systems.

    The size and dimensions of this intake structure are dependent on the width of the river bed and

    the slope conditions either side of the intake structure. These specific issues are investigated in

    greater depth in Section 5.3 of the report.

    Figure 2: Weir Shapes

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    16/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    9

    Sivasakthy Selvakumaran Sidney Sussex

    4.3.2 Channels

    The dimensions and hydraulic characteristics of the channels need to be such that the channels

    are able to conduct a specified minimum flow. This flow requirement at Chontabamba has been

    calculated as 0.70 m3/s. The calculation of the net elevation head is also required. This is the

    vertical distance between the discharge level at the settling tank and the micro-hydroelectric

    station at which point the diverted flow is returned to the stream/river.

    The normal water level in the channel (the water level at some distance downstream of the intake

    structure) will depend on the flow and the properties of the channel. The key properties of the

    channel will include slope, roughness coefficient and the geometric properties. The design of the

    intake structure will maintain a reservoir for continuous feed to the micro-hydroelectric powerstation via the channels.

    The water in the channel is being carried along the side of the mountain slopes, though flows at

    a gentler slope from the intake to reach the settling tank before it flows downhill to drive the

    turbine and rejoin the main flow. Power is derived from the kinetic energy as it flows downhill.

    Figure 3: Open channel parameters as specified on a trapezoidal channel.

    The Mannings equation for uniform flow in an open channel (Chow 1959) is written as:

    = 5

    3 .

    .2

    3 = 1

    where Q = design discharge of the channel (m3/s); A = cross sectional area of flow (m2); S0=bed

    slope of the channel; n = roughness coefficient of the channel section; P = wetted perimeter

    (m); = energy correction factor.

    Mannings Equation (Equation 2) is used to calculate the normal depth of flow in the inlet

    channel (where the water depth does not change in the direction of the flow) which would

    (Equ. 2)

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    17/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    10

    Sivasakthy Selvakumaran Sidney Sussex

    facilitate the determination of the sluice/weir gate level required at the intake structure and hence

    the overflow into the channel to the settling tank.

    In view of the channel bed material (sandy soil) any critical areas are required to be lined with

    concrete (or other impermeable material). This is to prevent loss of water by infiltration and to

    avoid the channel being undermined due to water washing away the sand. In some critical zones

    PVC pipe of 300 mm diameter would be utilised.

    Though there are regions of rectangular shaped channels and below ground pipelines, the

    majority of channel sections installed are trapezium in shape, lined or unlined earth channels.

    The parameters for rectangular, triangular and trapezoidal open channels (as defined in Figure 3

    for a trapezoidal channel) were substituted into Mannings equation, re-written in terms of flow,and the heights versus the flow rate plotted to gain an appreciation of the open channel

    behaviour and the suitability of existing designs.

    Figure 4: Graph to plot how the discharge rate is affected by water level depth in atrapezoidal channel.

    This is calculated based on Mannings equation. For this particular example, the channels weremodelled to be concrete lined

    (n=0.015), with a channel depth of 2.5 m and side slopes of 1 in 1. The slope of the channel was modelled with the average

    slope value at Chontabamba of 6 in 1000.

    Calculated and plotted by author.

    0.000

    10.000

    20.000

    30.000

    40.000

    50.000

    60.000

    0.00 0.50 1.00 1.50 2.00

    Flow

    Rate,Q(m3

    /s)

    Water Depth, h (m)

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    18/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    11

    Sivasakthy Selvakumaran Sidney Sussex

    4.3.3 Settling Tank

    Typical settlings tanks in these schemes (example pictured in Figure 5) are of concrete

    construction that would receive the water flow at the required rate and allow any sediment to

    settle at the bottom in order to avoid any damage to the mechanical equipment in the turbine

    house. The discharge pipe is set a level higher than the base slope to allow the sediment to be

    retained. Routine maintenance would be required to clean the settling tanks. The inlet and

    outlet would be designed to minimise turbulence and to avoid any air entrainment and sediment

    into the pipeline.

    Figures 5 and 6: System at Chontabamba

    Figure 5: Settling Tank Figure 6: Pipeline leading from settling tank intoturbine house, held in place by thrust block.

    Further to consultation with Practical Action staff, it was decided that this structure would notbe examined in detail during this research project. Engineering design guidance has already been

    produced on this structure by Practical Action. This allows for a focus in greater detail within

    this project on the two elements of greatest interest to Practical Action, the intake structures and

    the water channels.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    19/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    12

    Sivasakthy Selvakumaran Sidney Sussex

    4.3.4 Pipeline

    This pipe carries the water from the settling tank down to the turbine. The pipeline and the

    thrust block (used to prevent the movement of the pipe) can be seen adjacent to the building

    that houses the mechanical and electrical equipment in Figure 6.

    The following profile was developed from information collected for this project with the

    assistance of other Practical Action engineers. It models the slope from the settling tank to the

    turbine house and shows the pipeline along the longitudinal section.

    Figure 7: Slope and pipeline between settling tank and turbine house at Chontabamba.

    Profile drawn by author.

    Pipe calculations were also undertaken based on the existing tube profile to see that the flow at

    the bottom end of the pipe would be sufficient to drive the turbine. This included estimating

    friction losses and using hydraulic design charts. It was found that the pipeline currently in placeat Chontabamba was fit for purpose.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    20/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    13

    Sivasakthy Selvakumaran Sidney Sussex

    5. INTAKE STRUCTURE

    5.1 Existing Intake Structure

    The intake structure is used to divert water from the main river flow into channels that carry

    water along a different path to that of the natural flow. As the natural river course flows

    downhill, this diverted water can be maintained at a higher level, creating a height potential.

    The region experiences periods of both drought and heavy rain. In the case of drought, the

    construction of a barrier of appropriate height is necessary to secure the supply of water for

    power generation. However, a barrier that provides this requirement but can also support the

    passage of water in the river during rainy periods would result in a large infrastructure. This wasconfirmed by my calculations.

    Practical Action make use of an intake structure of concrete and wood mixed type barrier. This

    can be implemented at a low cost. The intake structure consists of two side walls either side of

    the stream. The required quantity of the water is diverted into a channel by means of a manually

    operated sluice/weir gate on one of these side walls and by a series of wooden stoplogs that can

    be placed perpendicular to the flow of the river to hold water back.

    The removable stoplogs are used to maintain water level upstream of the barrier in rivers with

    moderate slopes between 1 and 2%. For small streams, the stoplogs are slotted in rebates

    perpendicular to stream in concrete walls either side of the stream and base, forming the opening

    (see Figure 8 below). In large streams and rivers, structures are much wider with the opening

    formed by concrete columns and base.

    In the dry season, it functions with the interlocking stoplogs in place up to a height to allow

    sufficient build up of water level for draw-off, and during the rainy season the wooden stoplogs

    can be removed as necessary so that the flow can be regulated. This system also facilitates the

    removal of material accumulated at the barrier as the stop logs can be removed, and material

    transported down the river without the need to dredge upstream.

    This technology consists of designing channelling walls and base made of concrete of 140 to 175

    kg/cm2(approximately 1417.5 MPa) strength, which is made up of cement, sand and gravel,

    mixed with 25 - 30% large stone by volume.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    21/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    14

    Sivasakthy Selvakumaran Sidney Sussex

    Figure 8: Overhead schematic drawing by ITDG of Chontabamba

    intake structure with translations annotated.

    No stoplogs are in place in these intake structures.

    Figure 9: Photograph of Chontabamba

    intake structure (one of the smaller

    intake structures).

    Figure 10: Photograph of Yanacancha

    intake structure. Height of side wallseither side of intake is about 2m above

    ground.

    Figures 8, 9 and 10: Intake Structures

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    22/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    15

    Sivasakthy Selvakumaran Sidney Sussex

    5.1.1 Advantages over Complete Reinforced Concrete

    Reduces the cost by well over 35%, both in terms of materials and workmanship with

    reduced concrete, formwork and reinforcement.

    Facilitates cleaning of the accumulated sediments. The wooden stoplogs that make up

    the barrier are simply removed and the river flow is used to remove the sediments.

    It is a simple technology, easy to maintain and can be operated by the rural population.

    Reduces transport requirements, due to reduced use of cement and aggregates.

    In case of flooding, the wooden stoplogs serve as a fuse. When a flood occurs, it is possible that

    this action will break the wooden boards of the barrier allowing the river to move freely,

    preventing flooding or damage to the intake and other components of the micro-hydro system.Alternatively, the stoplogs can be removed as required during rainy season.

    Figure 11: Intake structure at Chontabamba

    Despite being only a couple of years old, there is quite significant concrete damage. The effects of scour are already visible at

    the bottom edges of the structure.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    23/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    16

    Sivasakthy Selvakumaran Sidney Sussex

    5.2 Field Observations

    A large number of cracks were observed in the intake concrete structures (as well as other

    structures and components such as channels, settling tanks, etc.). A number of factors could be

    contributing to this problem, including differential settlement, ground movements, thermal

    cracking due to inadequate reinforcement and the use of low strength concrete (14-17.5 MPa)

    for structures.

    Some of the issues with the current design

    have been identified from the site visits,

    and several others are evident from the

    detailed review of the design drawings.One noticeable feature is the distinct lack

    of reinforcement. There is more

    reinforcement present in the larger intake

    structures; however this is still insufficient

    by British Standards. Furthermore, the

    reinforcement used is not placed in the

    appropriate locations for the

    reinforcement to be effective. For

    example, by placing it at the bottom of the

    structure with little or no cover means that

    the reinforcement will be subjected to the

    effects of the environment and are likely to

    corrode. If this occurs, it will not serve

    any useful function as part of the structural

    member in providing adequate strength or

    preventing any thermal cracks.

    Based on the initial review, it was determined that the design of the intakes structure and

    channels would be carried out in accordance with the British Standards (primarily BS8110 for

    concrete, and BS8007 for water retaining structures and earth pressures acting on below ground

    structures in accordance with BS8002) to have an understanding of what considerations are vital

    in carrying out the design of such structures. Furthermore the regulations and standards of

    safety practised in the UK would be considered together with any specific requirements that

    Figure 12: Severe cracking in structures in

    Chontabamba.

    British Standard BS8007 states that water retaining structures

    should have a maximum crack width of 0.2mm. Cracks seen

    here were measured at around 1mm.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    24/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    17

    Sivasakthy Selvakumaran Sidney Sussex

    apply in Peru. There is no guidance available at present to aid in the design of such intermediate

    technology of small scale with alternative design and construction methods. The challenges and

    concerns present in designing larger scale structures are greater, making the design of intake

    structures and channels for larger scale hydroelectric power schemes worth examining closer in

    order to avoid any potential for catastrophic failures.

    5.3 Analysis

    5.3.1 Existing Structures

    Analysis of the structures in use in Peru has been undertaken based on guidance provided by

    British Standards, technical notes and design manuals currently used by practising engineers.

    The designs currently used by Practical Action have tried to use more innovative designs and

    construction methods and low cost technology. They had not, prior to this investigation, been

    designed or checked to ensure their safety and security. Having analysed the structures it can be

    seen that they have not been adequately designed to cope against certain failure mechanisms, for

    example, overturning, flotation and sliding.

    Hand calculations determined that the overturning stability was satisfactory and the risk of

    failure by sliding was very low in all cases. There were, however, several other concerns to

    address (as outlined in Section 5.2).

    Limitation of thermal and shrinkage crack widths (typically to 0.2mm as stated in BS8007) would

    need to be undertaken. This could be done by providing small bar reinforcement at small

    regular centres. In this country, meshes are considered good for this type of use (e.g. A252 or

    A393 meshes) though the availability and costs are likely to mean that this is not a suitable

    option for the micro-hydroelectric schemes built by Practical Action in

    Cajamarca. Reinforcement is generally needed in both faces for sections greater than 250mm

    thick. Minimum cover to reinforcement should typically be 40mm, subject to the environmental

    conditions.

    In the UK, virtually every reinforced concrete structure designed uses a cement mix of 50% each

    of Ordinary Portland Cement (OPC) and Ground Granulated Blast Furnace Slag (GGBFS). This

    is cheaper that 100% OPC, has better sulphate resisting properties and means that less

    reinforcement is needed to prevent thermal cracking, the only downside being that the concrete

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    25/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    18

    Sivasakthy Selvakumaran Sidney Sussex

    has to be cured for longer while it gains strength. This would be recommended if GGBFS is

    available at an economical cost in Peru.

    There should be a limit on water/cement (w/c) ratio of 0.55. A lower water-cement ratio leads

    to higher strength and durability but may make the mix more difficult to work with. Too much

    water will result in settling and segregation of the water, cement, sand and aggregate

    components. Also, mix with too much water will experience more shrinkage as the excess water

    leaves, resulting in internal cracks and visible fractures which will reduce the final strength.

    Problems are commonly caused by site workers ignoring this limit and putting more water in the

    mix to make the handling easier. Concrete should be mixed and cast on a low permeability

    surface, otherwise some water will leach out. In this case, more water will need be added to make

    the mix workable and control over the w/c ratio would be lost. This is another possible cause

    for the cracks mentioned in Section 5.2.

    5.3.2 Efficient Design

    The existing structural designs of concrete intake structures appear to be practical, although they

    could certainly be improved in order to achieve an acceptable standard based on a risk and value

    approach. This improvement is likely to increase the cost of the project by increasing the amount

    of reinforcement and increasing concrete quality. However this could potentially be offset by a

    more efficient design to reduce material costs and lessen maintenance requirements (lower life

    cycle costs). This includes, for example, making thinner walls so that a smaller volume of

    concrete is required. This would allow the costs saved to be used for other items such as more

    reinforcing steel.

    5.3.2.1 Detailed Design of Larger Scale Intake Structure

    The full detailed design was carried out for a potential intake structure. This design was in

    accordance with the British Standard design and resulted in a much greater amount of

    reinforcing steel than those used in the schemes designed by Practical Action in Peru. The

    structure was designed to be about 1.5m above the river bed and extending into the slope and

    below river bed level. This will then be the same scale as the Practical Action designed intake

    structures.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    26/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    19

    Sivasakthy Selvakumaran Sidney Sussex

    Figure 13: Drawings produced for the detailled design of a reinforced concrete intakestructure.

    These drawings are some examples and include the corner reinforcement detail, a plan view and a schematic explaining someof the reinforcement.

    Drawings by author.

    5.3.2.2 Development of Analysis Program

    Using the considerations highlighted in the detailed design, it was decided to develop a program

    that could very quickly design parts of the intake structure and check their suitability in terms of

    stability, sliding and other design considerations. Though there are software packages readily

    available on the market to design such features, the program that I developed has the Practical

    Action micro-hydro schemes in mind and focuses on creating side walls of the intake structure

    that also act as retaining walls to stabilise the slopes (parts of which can be seen in Figure 14

    below).

    The main advantage is that this program allows the user to input and vary the dimensions, and

    rather than simply presenting an output as to whether or not the input meets various structural

    safety criteria, it has the equations and calculations used to provide this output quite clearly

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    27/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    20

    Sivasakthy Selvakumaran Sidney Sussex

    displayed. Thereby the user is able to follow these calculations through and develop an

    understanding of how the design process works.

    The program then displays the rough estimated cost of components of the system. A key part of

    the focus of this program is to develop structures of low cost, and I created a section of the

    program to be used to see whether a structurally stable yet economic solution can be achieved

    when using reinforced concrete compared to the current designs.

    The initial idea was to use a general quantity surveyors guide to provide a cost estimate; however

    the costs of materials in the local area of the Province of Cajamarca will of course vary from the

    pricing and materials used here in the UK. Instead it was thought to be appropriate to pro rata

    the data for the Practical Action structures that have been reviewed. This feature has beenincluded in the program, but will need to be reviewed by Practical Action Engineers in

    Cajamarca to provide more accurate cost values based on what is available in the local region.

    5.4 Conclusions on Intake Structure

    Many of the problems identified in these structures were as a result of insufficient amount and

    poor usage of reinforcing steel combined with low strength concrete. The costs of the structure

    could be reduced by designing the structures to require less concrete.

    It was found that, in most cases, the resulting costs still ended up being higher than those of the

    intake structures actually constructed. It should be kept in mind that the cost values calculated

    are not confirmed. Despite the decrease in concrete required by a more efficient design, the

    increase in cost tends to come from the increase in reinforcement steel that these structures

    should have.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    28/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    21

    Sivasakthy Selvakumaran Sidney Sussex

    Figure 14: Example sections of intake design program developed by author.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    29/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    22

    Sivasakthy Selvakumaran Sidney Sussex

    6. CHANNELS

    6.1 Existing Channel Types

    The method of the trusses described below for the lining the channels with concrete permits an

    important reduction of costs. This is due to the decrease of the thickness of the lining down to

    between 5cm and 7.5cm, depending on the cross section of the channel. This permits an

    important saving in materials in that there is less concrete and no formwork. The method

    consists of placing trusses at required intervals, with straight runs at long intervals and curved

    zones at short intervals. The channels are then lined with concrete.

    These trusses are then removed and the gaps are filled with materials suitable to serve asexpansion joints, thereby avoiding formation of cracks in the channels. Currently, many

    governmental and private organizations are using these lined channels for other uses, mainly in

    small and medium irrigation works.

    This technique used to construct channels is simple and permits the employment of unskilled

    labour as compared to the more skilled labour required for using formwork.

    Figures 15 and 16: Channels

    Figure 15: Trusses being placed beforeconcrete is applied to earth channels.(Photograph courtesy of Practical Action).

    Figure 16: Complete concrete lined channels.(Photograph courtesy of Practical Action).

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    30/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    23

    Sivasakthy Selvakumaran Sidney Sussex

    6.1.1 Advantages over Traditional Design and Construction

    The advantages of the trusses over formwork (shuttering) for this scale of channel is summarised

    below:

    Allows more flexibility and facilitates the work in curved and straight sections with ease.

    Allows concrete thickness down to 50mm, thereby reducing the amount of concrete

    required. With the formwork method, a minimum thickness of 150mm is required to

    vibrate the concrete for adequate compaction. As there is no electricity available in these

    remote regions, a portable generator would be required which would incur further

    expenses, and so a process that does not involve electrical processes is ideal.

    Reduces the quantity of wood by approximately 80% as the need for formwork is

    eliminated.

    Reduces the use for materials for the placement of expansion joints (asphalt, sand) by

    50%.

    Eliminates the labour requirement for fixing and removal of formwork.

    Allows the finishing of the slopes and the floor (fair, rough or rip-rap finish) on the same

    day or almost immediately without having to remove the formwork.

    Good workmanship can be achieved with the local labour available with better efficiency.

    Allows reduction of raw materials (concrete, stone, sand, timber and other), resulting in

    lower cost of transportation of materials and reduces efforts for its attainment, especially

    in remote areas with difficult access.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    31/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    24

    Sivasakthy Selvakumaran Sidney Sussex

    6.2 Field Observations

    6.2.1 Problems Observed with Channels

    Based on observation, only the critical sections are lined with concrete due to a lack of availablefunding. Therefore, there is a potential for loss of water by infiltration into the ground due to

    channel cracking and channel erosion. The existing concrete channel sections have no provision

    for pressure relief to avoid issues with for flotation.

    Several large cracks were noticed in existing channels. Though this poses no risks to structures

    of such small size in terms of safety and structural integrity, these cracks lead to significant losses

    in water being transported towards the turbine.

    6.2.2 Risks

    It has been established that the structural integrity of the channels themselves is not a key

    concern for small works; however they are subjected to other risks.

    Landslides, soil creep and to a lesser extent the falling blocks of earth are the main risk factors

    that threaten the channel. These phenomena occur more frequently during the rainy season. It is

    also the case that the local population, intent on improving their pastures, have a tendency to

    over-irrigate the land. This exacerbates these risk factors as they further saturate the soil during

    the rainy season.

    6.2.3 Infrastructure Vulnerability

    The channel is the structural the most vulnerable structural component as channels often run up

    to a few kilometres through fields of various unstable conditions, susceptible to phenomena ofinstability such as landslides and soil creep, as well as erosion of slopes by river scour.

    The Yanacancha Micro-Hydro system can be used to highlight typical problems encountered

    with channels. In the first 50 metres from the intake, the channel does not present any major

    problems. Then, as it crosses a stream with a culvert the channel has accumulated sediment and,

    in combination with the falling earth from adjacent slopes, has a reduced channel capacity. In

    this same section the ground appears to be saturated with water, resulting in an increased lateral

    pressure of soils on the channel side. This causes sliding as well as a moment which may exceed

    the available moment resistance capacity, resulting in channel collapse. This prospect is even

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    32/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    25

    Sivasakthy Selvakumaran Sidney Sussex

    more likely to occur when these channels are not reinforced concrete, which would have a

    greater moment resistance capacity. The steel bars in the reinforced concrete would be able to

    carry some of the tensile forces which mass concrete is unable to carry, as well as some of the

    compressive and bending forces.

    In the next 150m of the channel, it is affected by landslides and soil creep. These phenomena

    generate a lateral thrust on the channel, the effect of which can be seen by the breaking and

    settling of the channel in several sections. Some of these breaks have been repaired very simply

    with a patch, however this is not a long-term solution as the soil sliding process continues and is

    likely to become acute in the following rainy season (Figure 17). Where then channel has

    developed cracks, a significant quantity of water is lost by seepage into the ground. These

    conditions are aggravated by an accelerated ground settlement process.

    The figures above illustrate some of these failure examples and critical conditions. For example,

    the yellow dotted lines in Figure 18 show the presence of faults in the slope due soil creep. This

    results in blockage and in some cases destruction of the channel.

    Figures 17 and 18: Slope Movement

    Figure 17: Indication of movement of slope

    into channel path A cover over the open

    channel has been added to prevent the flow in

    the channel from being cut off.

    Figure 18: The movement of sections of the

    slope material towards channel is visible here,

    as marked by the dotted lines.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    33/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    26

    Sivasakthy Selvakumaran Sidney Sussex

    Figures 19 and 20: Channels

    Figure 19: Slope collapse at Yanacancha. Thislead to the destruction of channels.

    Figure 20: Slope collapse at Yanacancha. Newchannels were dug into the earth and covered

    pipe put into place at critical sections. Pipecould not be installed along the entire length ofchannel due to lack of funding.

    6. 3 Analysis

    6.3.1 Larger Channels

    The full detailed design was carried out for a large channel section to have a good understanding

    of the design concept prior to looking at the relatively small channels that are part of the

    Practical Action micro-hydroelectric power schemes. The channel was designed to be five to ten

    times larger than those used in these micro-hydro schemes (about 3m in depth) with reinforced

    concrete and without any drainage features. It was noted that a large amount of concrete would

    be required to negate the flotation effects caused by ground water pressure. To overcome the

    flotation, a means to relieve these pressures must be considered in the channel design. However,

    the flotation was found not to be an issue with such small channels as those used in these micro-

    hydro schemes.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    34/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    27

    Sivasakthy Selvakumaran Sidney Sussex

    6.3.2 Optimisation of Size

    The size channels without any reinforcement or other structural considerations will be limited.

    For example, a large trapezoidal unreinforced channel with unstable side slopes can collapse,

    thereby resulting in the channel being destroyed and the system security will not be guaranteed.

    The graph below (Figure 21) shows the results of the examination of a general unreinforced

    concrete trapezoidal channel. It shows how large a concrete channel can be at given channel

    depths, varying the angle of the trapezoids side slopes and the thickness of channel wall. This is

    calculated irrespective of pressure relief, drainage, or other devices.

    It was assumed that the channel is built on top of a porous material (e.g. sand backfill) and that

    that the trapezium is hinged at the base corners. An analysis has been carried out to determine

    the maximum height that an empty channel can have such that the channel does not float away

    or have the sides collapse.

    Each line on the graph depicts a different depth, d, and the thickness of the channel is plotted

    against the angle, , of the side slopes to the horizontal.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    35/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    28

    Sivasakthy Selvakumaran Sidney Sussex

    Figure 21: The relationship of varying channel depth, side wall angle and thickness for anunreinforced concrete trapezoidal channel for different channel depths.

    Graphs produced by author using Matlab software.

    6.3.3 Effect of Rapid Drawdown

    A key concern with water-carrying structures is the build up of excess pore water pressure. This

    can cause an uplift pressure in channels resulting in failure during rapid drawdown of the

    channel water level.

    Embankments may become saturated by seepage during prolonged high water levels. If

    subsequently the reservoir pool is drawn down faster than the pore water can escape, excess pore

    water pressures and reduced stability will result. For the purposes of this analysis it is assumedthat drawdown is very fast, and no drainage occurs in materials with low permeability.

    Calculations were also undertaken to model the limits of a general trapezium channel with

    varying channel depth as affected by rapid drawdown.

    Channel depth

    increasing from 0.5m

    to 10m

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    36/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    29

    Sivasakthy Selvakumaran Sidney Sussex

    6.4 Conclusions on Channels

    In small works, as is the case of the micro-hydroelectric systems and especially in those where

    the flow rates will be relatively small, the channels do not bear significant ground forces or the

    forces imposed are negligible for the calculation of resistance. For these types of systems, the

    primary purpose of the channel lining is to avoid losses of water by infiltration and to protect the

    base and the slopes of the channel against erosion caused by the flow velocity. In terms of the

    structural integrity, the thickness of the wall can be reduced to the minimum within the practical

    functionality and without running significant risks.

    The channel is one of the most vulnerable parts of the system as it is at high risk of collapsing

    due to the effects of landslides, soil creep and lateral displacement by saturated and waterlogged

    terrain sliding downhill.

    6.5 Recommendations

    Based on the evaluation of the channels, my recommendations can be summarised as follows:

    1. Implement land drainage to reduce the build up of groundwater that appears to make the

    ground unstable. This is generally achieved by excavating selected regions of ground and

    filling it with drainage material such as gravel such that it leads to a pipe to carry the

    water away. As this may involve constructing drainage trenches and ditches on land

    owned by the local population, any implementation would require discussion with them

    and could only take place with their consent and understanding of the benefits.

    2. Adjust the irrigation system in pasture lands with appropriate technology such as drip

    irrigation or spraying, so that the moisture content of soils can be controlled.

    3. Evaluate the options for changing the channel liner or designing an alternative water

    conveyance system for the critical sections such as a flexible structures/ pipes that adapt

    to deformations of the soil. Use of PVC pipe for conveyance of water is an option. Thisis currently implemented in sections where slope failure has occurred, but the use of

    open section channels with design modifications could also be considered.

    4. Design the works to implement security and protection for the channel at critical

    locations. In order to prevent collapse, the slopes affected by erosion of the river could

    be stabilized. For lands affected by landslides, land drainage can be implemented.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    37/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    30

    Sivasakthy Selvakumaran Sidney Sussex

    7. SLOPE STABILITY

    The brief from Practical Action was to

    investigate the structural considerations ofthe intake structure and channels; however,

    from the work carried out it can be

    concluded that these factors could not be

    isolated form the effect of slope behaviour

    (examples of which can be seen in Figures 23

    and 24 below). It was therefore decided to

    investigate the behaviour of the surrounding

    slopes and their effect on the infrastructure

    of concern.

    Slope failure has the potential to destroy

    parts of the channel system following a

    period of heavy rainfall. There is evidence of slopes failure and the concrete lined channels

    being destroyed. Threats to existing structures exist in many regions due to the susceptibility of

    the landscape to erosion and landslide. For example, in Figure 22 of the intake structure, slope

    erosion and past slope failure can be seen. Similar slope failure in the future could potentially

    lead to damage to the intake structures.

    The channel and intake structures are some of the most vulnerable components of the micro-

    hydro system, due to exposure to various hazards that occur in this region such as landslides, soil

    creep, scour due to the river and erosion of slopes that support the channel and falling rocks.

    The risk of failure of the micro-hydroelectric system is high due to likely break-up, settlement

    and collapse of the channels and intake in such sections.

    These factors could result in collapse and total disruption of hydroelectric power for all users. In

    some cases it also affects farmlands that depend on these transmission channels to provide water

    for agricultural activities.

    Figure 22: Chontambamba intake

    Notice adjacent slope erosion.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    38/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    31

    Sivasakthy Selvakumaran Sidney Sussex

    Figures 23 and 24: Slope Failure

    Figure 23: Slope failure that affects the base of

    the channel. Earth is fractured in blocks.

    Figure 24: Channel path affected by slope

    failure.

    7.1 Typical Geological Conditions and Problems Encountered

    Similar issues with regards to slope stability are encountered throughout the Cajamarca region.

    Though the specific geological conditions are subject to some variation, they are quite similar in

    most cases and the study on Yanacancha Micro-Hydro system is provided here to illustrate a

    typical scenario where problems occur. This information was collected in the field, from

    speaking with local people and Practical Action engineers and from looking at previous studies

    (Rengifo, J. M. 2008).

    In terms of morphology, the area is located in the middle-lower part of the river basin which

    drains the Llaucano River. The valley presents mountainsides of moderate slope that are more

    rugged towards the lower regions and provided with good vegetation cover consisting primarily

    of grasses and some pine, eucalyptus and queuales.

    The area where the micro-hydro structures are located is predominantly land dedicated to

    livestock grazing and related agricultural production. Towards the downstream end of the system

    where the settling tank and the turbine house is located, the terrain becomes more rugged with

    steep slopes. There are no signs of increasing instability, except in the first few hundred metres

    of channel leading from the intake structure. This section of channel passes through pasture

    land that is oversaturated with water due to lack of proper drainage. This leads to the ground

    becoming unstable.

    Settling tank, turbine house,

    etc. further along

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    39/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    32

    Sivasakthy Selvakumaran Sidney Sussex

    Figure 25: Aerial view of part of the Yanacancha River Basin.

    Photograph courtesy of Google Maps. Annotations by author.

    The geological characteristics of the land are varied; the zone around the intake structure is

    composed primarily of sedimentary rock formation composed of limestone, marl and fine clays.

    The composition leads to fairly unstable soils that slide easily under the influence of excessive

    moisture from infiltration and uncontrolled flood irrigation applied to the grasslands.

    On the other hand, the predominant climate conditions in the area are divided into two marked

    stages. Between the months of November to April there is high humidity and intense rain, the

    rivers reach substantial levels and lands are prone to sliding. Between the months of May to

    October there are periods of drought, during which there is a reduction in the water supply

    available to drive the turbine to produce electricity.

    The geotechnical instability is associated with changing environmental conditions, above all the

    saturated ground conditions during the rainy season. Currently there is very little being

    implemented in order to address this issue of slope stability, apart from a few minor rock walls

    put in place after problems have arisen. This highlighted the need for further investigations of

    slope behaviour and design work to suggest alternative methods, in order to prevent such failure.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    40/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    33

    Sivasakthy Selvakumaran Sidney Sussex

    7.2 Slope Analysis and Rapid Drawdown

    While the development of deep-seated failure surfaces is possible, the more common sight

    viewed in site survey was in the form of relatively shallow slope failures. If left unattended these

    lead to the gradual deterioration of the slopes either side of the river channel, and eventually the

    collapse of the channel.

    The rapid drawdown scenario is one of the most severe loading conditions that earth slopes can

    experience. Flood events can leave water levels high in rivers and drainage channels for

    significant periods of time and then drop relatively rapidly once the floodwaters recede. The

    effect of this inundation on the soil in the slope, both prior to and subsequent to drawdown, is

    the idea of the rapid drawdown loading condition. To model this loading condition, the soil

    strength and pore pressure development in the slope must be considered.

    It was determined that the slopes for the systems being investigated would be analysed using the

    Simplified Bishop Method. Oasys Slope (produced by the software house of Arup) was used to

    analyse and understand some of the slope behaviour in the Cajamarca region (an example of

    such analysis using Oasys Slope can be seen in Figure 26). Oasys Slope performs two-

    dimensional slope stability analysis to study circular or non-circular slip surfaces. The program

    uses the method of slices and offers a variety of established methods for calculating interslice

    forces.

    The calculations used in this programme were backed up by carrying out a hand calculation of

    the Bishop Circle Method for failure, method of which is outlined in the U.S Army Corps of

    Engineers Engineering and Design Manual for the Structural Design of Concrete Lined Flood

    Control Channels (EM 1110-2-2007).

    The slopes input used in the example were generalised versions of the slopes that exist adjacent

    to intake structures in Cajamarca, and a geotechnical survey of much greater depth would need

    to be undertaken before a more accurate model could be produced. It was found that there were

    some variations between the hand calculations and the computer generated model. This was to

    be expected as the computer generated model goes through calculations with a greater degree of

    accuracy, though the outputs were within reasonable margins (19.7% difference between the

    factor of safety value generated) considering the factor of safety values are within 1.00 and 4.00.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    41/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    34

    Sivasakthy Selvakumaran Sidney Sussex

    Figure 26: Example of Oasys Slope analysis of slope failure using the Bishop Circle Methodfor failure.

    7.3 Potential Solutions to Slope Failure Issues

    Where the soil or ground is not inherently stable it will be prone to failure and so the

    performance of the existing soils needs to be improved. There are many ways to achieve

    reinforcement of the soils within embankments or slopes. Some of these potential methods are

    outlined in this section.

    7.3.1 Reinforced Soil

    Reinforced soil is the technique whereby fill material (frictional or cohesive) is compacted in

    successive layers onto horizontally placed sheets or strips of geosynthetic or metallic

    reinforcement. The considerations involved in designing this type of slope reinforcement have

    been developed into a programme called GCV Reactive.

    Some examples of soil reinforcement schemes for the sites investigated were produced. To verify

    the suitability of the output of the programme hand calculations were used, following those

    contained in HA 68/94: Design Methods for the Reinforcement of Highway Slopes by

    Reinforced Soil and Soil Nailing Techniques guide produced by the Highways Agency.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    42/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    35

    Sivasakthy Selvakumaran Sidney Sussex

    This method cannot be considered for protecting soil slopes and repairing soil slope failure

    throughout the entire system but the option may be considered in critical zones, such as those

    slopes which are adjacent to key pieces of infrastructure which are difficult or costly to replace.

    7.3.2 Soil Nailing

    HA 68/94 defines soil nailing as the technique whereby in situ ground (virgin soil or existing fill

    material) is reinforced by the insertion of tension-carrying soil nails. Soil nails may be of either

    metallic or polymeric material and either grouted into a predrilled hole or inserted using a

    displacement technique. They will normally be installed at a slight downward inclination to the

    horizontal.

    Soil nailing has the advantage over the reinforced soil method in that that slope would not have

    to be rebuilt and compacted; however the this technique requires specialised equipment and the

    costs incurred would be prohibitive. With such limited and difficult transport routes, it would be

    far too difficult to access the site with the required heavy machinery.

    7.3.3 Masonry walls

    Masonry walls have been used on a small scale to repair damaged zones that provide furtherthreat to the infrastructure. This idea is developed in further detail in Section 8.4, which

    provides potential solutions to the issue of infrastructure vulnerability due to slope failure.

    Figure 27: Section of channel which has been broken, rebuilt and protected by a masonrywall.

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    43/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    36

    Sivasakthy Selvakumaran Sidney Sussex

    7.3.4 Gabion walls

    Gabions are wire mesh baskets that are filled on site with stone or rock to form larger building

    modules. Usually, gabion baskets of different sizes are stacked in a stepped formation, with

    larger units at the base, to provide stability. Gabions have some advantages over loose stone

    material because of their modularity and ability to be stacked in various shapes; they are also

    resistant to being washed away by moving water. Gabions have advantages over more rigid

    structures because they can conform to ground movement, dissipate energy from flowing water,

    and drain freely.

    Maccaferri LTD. (England) granted a license to the gabion design programme GawacWin 2003.

    This enabled the possibility of investigating many different designs and design parameters in

    order to discover what characteristics would yield the optimum structure.

    Although flush faced walls can be used where space is limited, it is not recommended to

    construct vertical faced walls as gabions are a flexible structure and movement can occur during

    backfilling. This may cause instability and give the appearance of the wall leaning forward. To

    overcome this effect, and to improve stability, gabions are often designed at a slight inclination

    from the vertical.

    In determining the stepping arrangement it is not advisable to have a unit which overhangs the

    unit below at the rear of the wall. This is because the poor backfilling behind the wall will result

    in further soil movement later.

    Figure 28: Example of a gabion design input into GawacWin.

    This particular structure was used in the investigation to see the effect of flush-faced front walls. (Design 2 in Table 3).

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    44/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    37

    Sivasakthy Selvakumaran Sidney Sussex

    The validity of the results generated from running this software was checked by carrying out a

    hand calculation, which provided a result within reasonable agreement of the computer

    simulated run.

    There were a few conclusions reached as a result of the investigations carried out using this

    software package. An excerpt from one of these investigations can be seen in Table 3 below and

    the full set of results was used to conclude that flushed faced walls facing the river generally give

    higher toe bearing pressures. In Table 3 below, the same size gabion baskets are used in each

    level, but with their position relative to one another altered. Another conclusion was that it may

    be possible to reduce the bearing by spreading the load over a greater area using a gabion as a

    founding course.

    Table 3: Analysing the effect of flush-faced walls.

    Stability Checks 1(Flush Front

    Wall)

    2(SymmetricFigure 28)

    3(Stepped

    Front Wall)

    4(Stepped

    Front Wall)

    Sliding Safety Coefficient 2.72 3.22 2.86 2.47

    Overturning Safety Coefficient 3.78 4.96 4.35 3.62

    Overall Stability Safety Coefficient 1.57 1.60 1.58 1.53

    Base Normal Stress (left) kN/m2 84.66 48.66 67.25 67.65

    Base Normal Stress (right) kN/m2 29.90 49.34 40.11 34.27

    Max Allowable Stress kN/m2 183.69 187.85 184.72 179.14

  • 7/26/2019 FINAL REPORT_Sakthy Selvakumaran

    45/57

    Low Cost Structures in Micro-Hydroelectric Power Generation

    38

    Sivasakthy Selvakumaran Sidney Sussex

    8. STRUCTURAL DESIGN SOLUTIONS

    This report thus far has identified the problems that occur with some of the structures in the

    micro-hydroelectric power systems constructed by Practical Action, and investigated some of thecauses of these problems. This section of the report aims to address some of these problems

    with potential solutions.

    8.1 Drainage Considerations

    The back faces of the retaining walls that form either side of the intake structure are likely to be

    subjected to hydrostatic forces from groundwater. A means of providing a more structurally

    stable system, whilst only slightly modifying the existing design, would be to consider theprovision of drainage features.

    These hydrostatic forces could be reduced by the provision of a drainage path at the face of the

    wall. Such a drain could be provided by a layer of gravel, rubble or porous blocks with pipes to

    collect and remove the accumulated groundwater. This type of system is illustrated in Figure 29

    below which is based on a typical design currently in use but modified to make use of such

    features.

    Figure 29: Proposal to modify existing intake structures to include drainage features.

    Technical drawing produced by author. Drawing based on an original structure design by Practical Action. The

    proposed modifi