    Design Proposal for the North Greenbush

    Hotel Development SiteNew York 43 & Best Road,

    North Greenbush, NY 12144

    Harpoon Engineering

    Charles Ohrin

    Paul StewartPatrick Lowe

    Mathew White

    Ian Marinaccio

    Ben Levitz

    Instructor

    Jack M. Reilly, Ph.D.

    Graduate Assistants

    Transportation: Felipe Aros Vera

    Structural: Xinwei Zhou

    Geotechnical: Mehrad Kamalzare

    May 9th, 2012

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    2/90

    2

    Table of Contents

    Design Outline .............................................................................................................................................. 4

    Final Design .................................................................................................................................................. 5

    Figure 1: The floor plan for the 1stfloor ............................................................................................... 5

    Figure 2: The floor plan for the 2nd, 3rd& 4thfloors.............................................................................. 6

    Figure 3: The Structural Plan ................................................................................................................ 6

    Figure 3: View of Dining Room .............................................................................................................. 8

    Figure 4: Alternate View of Dining Room ................................................................................................. 8

    Figure 5: View of Conference Room ..................................................................................................... 9

    Preliminary Structural Assessment ............................................................................................................... 9

    Interior Live Loads ................................................................................................................................... 9

    Snow Loads ............................................................................................................................................. 10Wind Loads ............................................................................................................................................. 11

    Rain-On-Snow Surcharge Load .............................................................................................................. 11

    Rain Loads .............................................................................................................................................. 11

    Seismic Loads ......................................................................................................................................... 12

    Load Combinations ................................................................................................................................. 12

    Summary of Loads .................................................................................................................................. 12

    Results ......................................................................................................................................................... 13

    Axial Forces ............................................................................................................................................ 13

    Moment & Shear Diagrams .................................................................................................................... 15

    Deflections .............................................................................................................................................. 21

    Figure 3: Deflected Shape ................................................................................................................... 21

    Material Takeoff ..................................................................................................................................... 21

    Connections................................................................................................................................................. 21

    Column Base Plate .................................................................................................................................. 23

    Connection Details .................................................................................................................................. 25

    Geotechnical Assessment ............................................................................................................................ 27

    Soil Profile .............................................................................................................................................. 27

    Soil Bearing Capacity ............................................................................................................................. 27

    Final Column Loadings ........................................................................................................................... 27

    Excavation and Compaction ................................................................................................................... 27

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    3/90

    3

    Settlement ............................................................................................................................................... 28

    Final Foundation Plan ................................................................................................................................. 29

    Special Conditions ...................................................................................................................................... 30

    Construction and Cost ............................................................................................................................. 31

    Soil Profile .................................................................................................................................................. 32

    CPM Schedule & Network Diagram: ......................................................................................................... 34

    Construction Cost Estimate ......................................................................................................................... 35

    AppendixALoading Calculations........................................................................................................ 39

    Snow LoadsFlat Roof & Drift ............................................................................................................. 39

    Rain Loads .............................................................................................................................................. 43

    Wind Loads ............................................................................................................................................. 44

    Seismic Loads ......................................................................................................................................... 47

    RISA 3DBasic Load Combinations .................................................................................................... 59

    Hand Calculations for Columns .............................................................................................................. 60

    AppendixBConnection Calculations .................................................................................................... 71

    AppendixCSettlement Calculations .................................................................................................... 82

    Initial Settlement Calculations ................................................................................................................ 82

    Final Settlement Calculations ................................................................................................................. 85

    AppendixDSquare Footing Calculations ............................................................................................ 86

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    4/90

    4

    Design OutlineThe design for this project will adhere to both The Town of Bethlehem and The New

    York State Building Codes for Mixed Economic Use. The City of Santa Ana, California has

    very clean requirements with regards to the design of hotels, and these requirements will also

    be used as a guide in order to provide the most practical hotel design possible. Since the

    structural design is not heavily dependent on the exact interior details of this project, things

    such as furniture and utility layouts will not be addressed in full detail. The major design

    requirements to be focused on will include,

    1. Setbacks:

    A landscaped setback not less than twenty-feet shall be provided to the extent it abuts a

    public or private street or freeway.

    2. Building Landscaping:

    A five foot minimum landscaped area shall be provided to separate ground floor units

    from pedestrian walkways.

    3. Drop-off Zones:

    Have a covered drop-off zone for guests to load and unload luggage from cars.

    4. Pedestrian Walkways:

    Must be minimum of eight feet wide

    5. Open Space:

    1,000 square feet of common space shall be provided at a 50 square feet per guest unit

    ratio up to a total of 7,500 square feet.

    6. Amenities:

    Outdoor and indoor amenities such as an outdoor/ indoor pool, exercise room, or business

    center

    7.

    Conference Rooms:

    Minimum of 2,500 square feet of interior floor area at 20 square feet per guest room ratio

    8. Lobby:

    Minimum of 1,000 square feet of interior shall be devoted to the lobby with a minimum

    ceiling height of twelve feet.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    5/90

    5

    9. Laundry Room:

    Shall include one washer and one dryer for every twenty guests

    10.Minimum Room Size:

    Each guest room shall have a minimum of 220 square feet.

    Final DesignAfter consideration of several different footprints, we chose a Y shaped floor plan (Figure

    1), with three wings, and one central core. Because the Bethlehem code defines a hotel as a

    building with no less than 41 dwelling units, our design has 48, 15 x 28 ft. rooms on floors 2, 3,

    and 4. These 3 floors will also contain 1 laundry room each having 3 washers and 3 dryers. The

    first floor will be reserved for amenities such as conference rooms, a gym, and a dining room.

    The first floor will also host the main lobby, staff offices, the hotel laundry room, storage rooms,

    and a kitchen to supply food for the dining room.

    Figure 1: The floor plan for the 1stfloor

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    6/90

    6

    Figure 2: The floor plan for the 2nd, 3rd& 4thfloors

    Figure 3: The Structural Plan

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    7/90

    7

    In order to keep mobility fluid and safe throughout the building, a staircase will be placed

    in each wing, paired with a means of egress. The central core of the building will feature its own

    staircase, as well as two elevators to provide handicapped access to the upper levels, with a

    machinery service room on the first floor to accommodate elevator repair and maintenance.

    In order to accommodate for HVAC, plumbing, and the depth of structural beams and

    girders, we are allocating 13 feet between each level, thus leaving 3 feet of overhead space for

    M.E.P. and structural systems in the rooms and corridors. However, because building code

    requires 11 feet of clearance in the lobby, the ceiling will only be dropped by 1.5 feet, which still

    provides adequate space for the structural elements, as well as the HVAC and plumbing.

    With regards to HVAC, every guest room will be equipped with an individual AC unitbuilt integral with the wall. This solution keeps costs down, while providing climate control to

    each individual room. However, all of the public rooms such as the lobby, hallways, gym, etc.

    will receive ventilation from centralized HVAC units on the roof.

    For the exterior of the building, we plan on using a brick veneer in order to provide a

    visually appealing and durable finish, which is easy to maintain. Another alternative to the

    exterior finish still incorporates the use of brick veneer, however, it would only be used for the

    first floor, leaving the rest of the faade to be compromised of EIFS, which is cheaper and easier

    to install.

    Finally, the roof will be designed to accommodate the 2 HVAC units which provide

    heating and cooling for the first floor and corridors and common areas for the 3 upper levels.

    The roof has also been designed to allow future incorporation of a green roof to help address

    sustainability issues.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    8/90

    8

    Figure 3: View of Dining Room

    Figure 4: Alternate View of Dining Room

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    9/90

    9

    Figure 5: View of Conference Room

    Preliminary Structural Assessment

    Interior Live Loads Concerning the live loads experienced by the structure, the base floor will be considered

    public rooms which entails of uniform live load of 100 psf which applies to the rooms

    themselves and any corridors that serve them (ASCE Table 4-1)

    The 100 psf live load will also be applied to the dining room and restaurant also located

    on the base floor (ASCE Table 4-1).

    Also located on the base floor will be a kitchen, which will have an estimated uniform

    live load of 150 psf (ASCE Table C4-1).

    For the hotel laundry room on the base floor, 3 Washers and 3 Dryers will be considered,

    whose weights are approximately 8500 lbs each, this value is increased by 20 percent to obtain a

    design value of 10,200 lbs as per ASCE 4.6-3.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    10/90

    10

    For the second, third, and fourth floor, a uniform live load of 46 psf for the private guest

    rooms (ASCE Table C4-2).

    The corridors serving these floors will be 40 psf uniform live load (ASCE Table 4-1).

    Rest rooms, which will be located throughout, will have a uniform live load of 60 psf

    (ASCE Table C4-1).

    Elevator machine room will be taken as a uniform load of 150 psf (ASCE Table C4-1).

    Also, reduction in live loads will be applied where applicable, dependent upon the

    location of the column and tributary area. The equation to apply live load reduction will be done

    in accordance to ASCE 4.7-1:

    L = Lo [ 0.25 + (15/ (square root (KLLAT))]

    L = reduced live load per ft2

    Lo= unreduced live load per ft2

    KLL= live load element factor (ASCE Table 4-2)

    AT= tributary area carried by column in ft2

    Snow LoadsWhen considering the loads placed upon the roof, a flat snow load, pf, was established to be

    27.72 psf. This value was derived from equation ASCE 7.3-1:

    Pf= 0.7*Ce*Ct*I*Pg

    Ce=Exposure Factor (ASCE Table 7-2)

    Ct=Thermal Factor (ASCE Table 7-3)

    I=Importance Factor (ASCE Table 1.5-2)

    Pg=ground snow load (ASCE Fig 7-1).

    The actual calculation and values for the aforementioned parameters can be found in the

    Appendix sections under Snow Loads heading. It is also important to find drift loads for the

    snow caused by the parapet walls and mechanical installations on the roof. For the parapet walls,

    the greatest uniform loads calculated was 22.46 psf. The drift loads appears in a triangular

    distribution, with 22.46 psf the height of the triangular distribution. This was done using ASCE

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    11/90

    11

    Fig 7.9 for drift snow loads. All pertinent drawings and calculations can be found in the

    Appendix section.

    Wind LoadsAs pertaining to the loads on the structure caused by wind, it is pertinent to understand how the

    values for wind pressures were developed. First, the hotel was classified as a Risk Category:

    III structure according to the table 1.5-1 found in ASCE/SEI 7 Minimum Design Loads for

    Buildings and Other Structures. This conclusion was reached due to the threat for substantial

    loss of human life in case of structural failure. The basic wind speed was established as being

    120 mph as per Figure 26.5-1B in ASCE and the remaining wind load parameters were

    determined using descriptions provided in chapter 26 ASCE (All wind parameters selected can

    be found in Appendix Wind Load Consideration).

    The windward wall is expected to experience a pressure of 12.7 psf.

    The leeward wall has a pressure of 6.2 psf.

    Side wall has a pressure of 10.5 psf.

    Roof has a pressure of 24 psf.

    Wind Load Consideration includes all pertinent calculations and drawings. The leeward, side

    and roof surfaces are expected to experience suction from the resulting wind force so the values

    are negative when seen in the calculation sheet.

    Rain-On-Snow Surcharge LoadAs per ASCE 77.10 Rain-On-Snow Surcharge Load, it was determined that this load may be

    neglected due to the fact that the ground snow load, pg= 40 psf, was greater than 20 psf.

    Rain LoadsIn determining the rain load to be applied to the roof, the ASCE 7 provisions given in Chapter 8

    and its accompanying commentary in Chapter C8 were used. It was determined that 2 primary 6

    diameter roof drains, and 2 secondary 12 wide channel scupper roof drains set 2 above the roof

    surface at the end of each of the three wings will provide adequate drainage for the structure.

    Based on this drainage system and the 2.5 per hour 100 year return period rain fall the

    maximum expected rain load (R) would be equal to 18.1 psf. See appendix for more detail

    regarding this calculation.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    12/90

    12

    Seismic LoadsIn determining the seismic loading to be applied to this structure ASCE 7 Chapters 11 and 12

    were used, as well as the USGS online DesignMaps site specific report generating application.

    First the site specific data was entered in to this online application in order to obtain the initial

    coefficients needed to generate the seismic loading condition to be applied for analysis. These

    coefficients were generated using the current provisions given in the 2010 ASCE 7 Standard, and

    are outline in further detail in the Summary Report and Detailed Reports which can both be

    found in the Appendix of this document. Next the Effective Seismic Weight (W) of the building

    was estimated using the provisions given in Section 12.7.2 of ASCE 7. Using this weight, the

    coefficients generated in the USGS report, and other provisions given in Chapter 12 values for

    the lateral forces to be applied the structure at each level and the shear force to be applied to the

    columns of the building were generated. See Appendix - A for more detail regarding these

    calculations and the USGS Site Specific Reports.

    Load Combinations

    1. 1.4D

    2. 1.2D + 1.6L + 0.5(Lr or S or R)

    3. 1.2D + 1.6(Lr or S or R) + (L or 0.5W)4. 1.2D + 1.0W + L + 0.5(Lr or S or R)

    5. 1.2D + 1.0E + L + 0.2S

    6. 0.9D + 1.0W7. 0.9D + 1.0E

    Summary of LoadsDead Loads:

    Floor Slab = 41 psf Brick Veneer = 40 psf

    Column = 96 plf Beam = 49 plf

    Girder = 96 plfLive Loads:

    1

    stFloor Rooms & Corridors = 100 psf

    Kitchen = 150 psf

    Restrooms = 60 psf

    Laundry Rooms = 150 psf Offices = 50 psf & 2000 lb P.L.

    Ceilings = 10 psf 2

    nd, 3

    rd, 4

    thFloor Corridors = 40 psf

    Guest Rooms = 46 psf

    Stairs & Exit Ways = 100 psf & 300 lb P.L.Green Roof = 100psf

    Snow Loads:

    Flat Snow Load, pf = 27. 72 psf

    Drift Loads, pd(max) = 22.46 psf

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    13/90

    13

    Wind Loads:

    Windward Wall = 12.7 psf Leeward Wall = 6.2 psf

    Side Pressure = 10.5 psf Roof Pressure = 24. 0 psf

    Rain-On-Snow Surcharge Load: pg = 40 psf > 20 psf => N/A

    Rain Loads:

    Max. Rain Load, R = 18.1 psf

    Seismic Loads:

    F1 = 33.07 kip F2 = 66.15 kip F3 = 99.22 kip

    F4 = 272.70 kip Vx = 471.14 kip

    Results

    Axial Forces

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    14/90

    14

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    15/90

    15

    Moment & Shear Diagrams

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    16/90

    16

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    17/90

    17

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    18/90

    18

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    19/90

    19

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    20/90

    20

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    21/90

    21

    Deflections

    Below is a graphical representation of the expected deflections in inches when all loads

    were applied. The rendering depicts one of three wings found in the hotel.

    Figure 3: Deflected Shape

    Material Takeoff

    Hot Rolled Steel Size Pieces Length (ft) Weight (k)A36 Gr.36 LL5X5X12X6 244 4491.2 212.4

    A992 W12X106 240 3120 331.2

    A992 W14X74 144 2623.5 194.6

    A992 W14X82 408 8844 725.3

    A992 W21X111 480 5172 575.5

    A992 W27X178 333 3466.3 616.9

    Total HR Steel 1849 27716.9 2655.9

    Connections

    Throughout the entire structure, there exists only as pin connections in order to reduce the

    amount of material that would be necessary if the joints transferred moments. Having solely pin

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    22/90

    22

    connections, lateral bracing is then installed to add stiffness to the structure for any lateral loads

    that are expected (wind, earthquake).

    The pin connections are comprised of gusset plates connected to the beams and girders by

    way of shear bolts. In consideration of bolted connections, there exists many modes of failure

    one must account for in order to ensure safety and serviceability of the structure. A possible

    mode of failure is the shear tear out at the end of the connected element due to the excessive

    bearing stress. This consideration results in the equation:

    Rn=1.2*Lc*t*Fu

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    23/90

    23

    excluded from the shear plane). The threads were included because of the conservative approach

    it provides.

    Also, it important to check the strength of elements in tension.

    Tensile yielding:

    Rn=Fy*Ag

    (ASCE J4-1)

    Fy=yielding stress of material

    Ag=Gross cross sectional area of material

    Tensile rupture:

    Rn=Fu*Ae(ASCE J4-2)

    Fu=ultimate stress of material

    Ae=Effective area

    It is important to note that effective area is the cross-sectional area accounting for the missing

    material due to the holes fabricated for the bolts.

    All of the strength values will be factored to a design strength as per LRFD steel design

    standards:

    Design Strength = 0.75*Rn

    The design factor is 0.9 for tensile yielding considerations*.

    Column Base PlateIn regards to the column connecting to the foundation footings, this will be achieved by

    means of a column base plate anchored to the underlying concrete. Columns that are connecting

    to the foundation are W12X106 with a peak compressive load of 705 kips. In designing the base

    plate dimensions, it is important to consider bearing capacity of the underlying concrete. This

    capacity is governed by the equation:

    Pp=0.85fcA(AISC J8-1)

    Pp=nominal strength of concrete

    fc=compressive strength of concrete (4 ksi)

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    24/90

    24

    A=bearing area (in2)

    When one subsitutes the load (705 kips) in for the nominal strength, one can then solve

    for the required area, which in this case was 346 in2. The column plate was then selected to have

    dimensions 19X 19 in order to have adequate bearing area (19

    2

    =361).The sides of the plate outside of the immediate beam area act as a cantilever and the

    greatest of those lengths will be taken in the calculation of the thickness of the plate (moment

    inceases as length increase for cantilever elements). The equation for plate thickness is:

    T=L*Square root ((2*Pu)/(.9*width of plate*length of plate*yielding stress of plate))

    (AISC 14-7a)T=thickness (in)

    Pu=705 kips

    Width of plate=length of plate=19 inYielding stress of plate=36 ksi (A36 steel used for plate)

    The resulting thickness for the plate is taken to be 1.75 inches. The column plate used for this

    projct will have the dimensions 1.75X 19X 19.

    The base plate will be anchored to the foundation using 4-12 anchor rods. This is derived from

    equation:

    L=(.02*Fy*Db)/(square root(fc)

    (ACI 12.3.2)

    L=length of anchor rodFy=yielding strength of rods (60 ksi)

    Db=diameter of rod

    Fc=compressive strength of concrete (4 ksi)

    All pertinent calculations and illustration can be seen in appendix titled Column Base Plate.

    All connection details are illustrated in the appendix sections under the title Connections.

    These connections were modeled using the computer program RISAConnection. The computer

    model checks all provisions established by ASCE and an example summary is also included with

    the first illustration. Also, there exists hand calculations checking the number of bolts necessary.

    The hand calculations are done in relation with Vertical braced Chevron computer model to

    ensure that 3 bolts were a satisfactory output for that connection.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    25/90

    25

    Connection Details

    W14 Beams to W12 x 106 Column

    W14x82 to W27x178:

    W27x178 to W27x178:

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    26/90

    26

    W27x178 to Column:

    Vertical Brace Chevron Connection

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    27/90

    27

    Geotechnical Assessment

    Soil Profile

    The general soil profile of the site consists of about three layers: a thin layer of top soil, a layer

    of a silt mix, and shale bedrock. The upper layers of this shale are heavily weathered and contain

    expansive pyrite. Our building was placed in the lower left corner of the site map, near the edge

    of the wetlands. For this location, borings B-29 to B-32 were used to investigate the soil beneath

    the foot print. The elevation across the foot print, from west to east, changes from 380 feet to 400

    feet, over a distance of about 300 feet. Water was found in B-32, 5 feet below the surface. See

    the attached site map and soil profile for further detail.

    Soil Bearing CapacityAccording to the geotechnical report developed by Dente Engineering, the maximum net

    allowable soil bearing pressure (qa) is 3000 psi for spread foundations. Using this qagreatly

    simplifies the design process. The alternative would be to develop an ultimate bearing capacity

    by taking the number of blows on each soil layer, factoring them to N60, find their cohesion and

    angle of internal friction and then use a variation of Terzaghis Bearing Capacity formula. Here

    the factors for N60 would have to be assumed, as well as the cohesion in the mixed silt layer. The

    end result will lead to a qa, which has already been established by Dente.

    Final Column Loadings

    To be cost effective and make the construction process easy, three column loads were chosen for

    footing designs. These select loads are shown below.

    # of columns Load range Selected Load

    19 < 300 kips 300 kips

    26 300 - 500 500 kips

    15 >500 705 kips

    The three ranges captured almost an equal amount of the 60 columns. The final loads are much

    higher than the estimated 150 kips from the preliminary report. With proper preparation of the

    site, reasonable footings can still be made.

    Excavation and CompactionThe elevation of the lot will be 400 feet, with the retaining wall along the border of the wetlands

    dropping to 380 feet. Extensive excavation will be required to meet this elevation and to remove

    unsuitable soil and broken shale. It has been determined that the site soil and shale are not

    suitable as fill under foundation areas. Shale below the floor subgrade must be replaced with 2 to

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    28/90

    28

    4 feet of structural fill to minimize the risk of expansion. Such a cushion will also reduce

    differential settlement. The increase in elevation will reduce the presence of groundwater, but the

    structure and the retaining wall still must have perimeter foundation drains. Dewatering will be

    required during construction and wet soils must be excavated and replaced. Since the building is

    on the low side of the elevation, on site soils will change the soil profile drastically. More

    important, since the site soil cannot be used under the foundation, a strong fill must be imported.

    This fill must be a well graded sand and gravel mix with less than 10 percent fines. Its soil

    modulus should be around 8000 ksf. This will provide the support needed for the structure.

    The structural fill also must be compacted to 95 percent of its maximum density and within 2

    percent of its optimum water content. Such work should be done during a dry season to make

    this more feasible. According to the report from Dente Engineering, the soil subgrades should be

    compacted by a vibratory drum of ten tons. Sufficient compaction will help to reduce the

    potential settlement and strengthen the surrounding soils.

    Settlement

    The theoretical settlement of a footing at each boring was calculated both elastically and rigidly,

    with equations Se = qo*(*B')* (1 - s^2/Es)*Is*If and Se rigid = .93 Se (Das). From the

    standard penetration tests conducted during the boring, the soil modulus was found for each

    layer, which was then used to find the average modulus under the foundation. Calculating the

    shape factor Is and depth factor If involve other factors A0, A1and A2, to calculate its factors F1

    and F2. A simplified method is to use tabulated values of F1and F2. Boring 29 had the highest

    rigid settlement of 4.6 inches at the center of the footing. Such high settlement will require

    excavation, compaction and fill of these weak, moist layers. Settlement calculations must then be

    repeated for the new soil conditions. The full calculations are shown in the appendix. Part of the

    excavation process will be to add structural fill under the footings and slabs and a new settlement

    calculation was done for the max column load by by the same method. By having a solid fill, the

    settlement was reduced to about an inch, with almost negligible differential settlement. The new

    settlement calculation follows the initial one in the appendix.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    29/90

    29

    Final Foundation PlanEach column will have its own square spread footing, which will be placed at a depth 4 feet

    below the surface. This depth will keep the footing stable and protect from frost penetration.

    From the three column loads, a footing was designed. The ACI code was used almost

    exclusively. The results of this analysis are shown in the table and diagram below.

    The width of the footing was found by the equation: B= col. load / 3ksf. Before the other

    dimensions could be found, the load was first factored to get the factored soil pressure, since the

    3 ksf already has a safety factor included. Spread footings are design first for shear and then for

    flexural resistance. No stirrups are added to the footings, so the concrete itself must be able to

    stand the shear. The one-way and two-way shears were calculated using an estimated depth to

    steel dimension d, Area/6. This is used to calculate the shear created by the load and the shear

    capacity of the footing. From there, the d can be altered to meet the required shear strength, but

    not overly excessive. The flexural resistance will have the same reinforcement in either direction

    300 kip 500 kip 705 kip

    B 10 ft 13 ft 16 ft

    d 18 inch 26 inch 32 inch

    h 22 inch 30 inch 36 inch

    Bar No. 5 No. 6 No. 6

    As / ft 0.49 in^2 / ft 0.59 in^2 / ft 0.71 in^2/ ft

    s 5 inch 9 inch 7.5 inch

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    30/90

    30

    since the footing is square. A one foot width is considered and treated as a beam. The maximum

    moment created by the net soil pressure can then be used to calculate the required amount of

    steel. This is often express in square inches per foot. The detailed formulas and calculations are

    provided in the appendix.

    Special ConditionsOur Environmental Engineering consulting group wanted us to put in a retaining wall next to our

    plot of land we were given. For the retaining wall, on the backside of the hotel, we decided to

    build a cantilever wall. A cantilever wall is the best option here because of how deep we are

    digging the foundation of the wall. From the data from the geotechnical report, we only have

    information about the soil five feet down. Thus, we can only plan our retaining wall to have a

    bottom base of five feet. However, with a cantilever wall, since the base expands backwards so

    far into the soil behind the wall, it will give us a more stable retaining wall. A picture of our

    design for the cantilever retaining wall can be seen below. This wall will also be the cheapest

    option among retaining wall designs.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    31/90

    31

    The elevation in front of the retaining wall is 380 feet. The elevation behind the retaining wall

    will be 400 feet. So the retaining wall will have a height of twenty feet. The base will be

    fourteen feet, with about four and two thirds feet being out in front of the wall. The thickness of

    the base will be two feet, and the thickness of the wall itself will be two feet. There will be about

    two feet of the wall underneath the ground. So, this puts the total height of the all at twenty two

    feet, but only twenty feet will be exposed. The length of this retaining wall will be about two

    hundred feet long until it intersects with the foundation of the hotel. Then it will run for about 30

    feet along the side of the foundation.

    Failure in a cantilever wall is mostly due to groundwater. The water table can have adverse

    affects on a cantilever wall. Here the water table is at about five feet. Since we will only be

    going down 2 feet for the base, we will not nut into the water table. So that will not have any

    affect here.

    Construction and Cost

    This retaining wall will be built around borings 29 and 31. The soil data for these two borings isbelow:B-29:The unit weight of the soil in this area was

    estimated 110 lb/ft3.The Phi angle of this soil is about 34.83o.The Cohesion of this soil is about 1.0.

    B-31:The unit weight of the soil in this area was

    estimated 110 lb/ft3.The Phi angle of this soil is about 27.75o.The Cohesion of this soil is about 0.5.

    Cantilever wall have an economic height maximum of twenty feet. Our wall just fits that

    specification. The cantilever wall frame has an area of seventy six feet. This is the combined

    areas of both rectangles that create the wall. This wall is then spanned along 230 feet total.

    Inside the wall, there will be a frame made of steel. This will give a mold to pour the concrete

    around. The most recent estimates for a cantilever wall online is 135 dollars per square foot.

    This would put the total of one foot section of wall at 10,260 dollars. Over 230 feet, this puts

    cost at 2,359,800 dollars. This cost includes all excavation, embankment, concrete and rebar

    cots.

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    32/90

    32

    Soil Profile

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    33/90

    33

    Site Map

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    34/90

    34

    CPM Schedule & Network Diagram:

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    35/90

    35

    Construction Cost EstimateEstimate Name: Capstone Hotel

    Building Type:

    Hotel, 4-7 Story with Face Brick with

    Concrete Block Back-up / Steel Frame

    Location: ALBANY, NY

    Story Count: 4

    Story Height (L.F.): 13

    Floor Area (S.F.): 135000

    Labor Type: Union

    Basement

    Included: No

    Data Release: Year 2012 Quarter 1 Costs are derived from a building model with basic components.

    Cost Per Square

    Foot: $186.87 Scope differences and market conditions can cause costs to vary significantly.

    Building Cost: $25,227,000

    % of

    Total

    Cost Per

    S.F. Cost

    A Substructure 2.60% $3.61 $488,000

    A1010 Standard Foundations $1.14 $154,000

    Strip footing, concrete, reinforced, load 11.1 KLF, soil bearing

    capacity 6 KSF, 12" deep x 24" wide

    Spread footings, 3000 PSI concrete, load 500K, soil bearing capacity

    6 KSF, 9' - 6" square x 30" deep

    A1030 Slab on Grade $1.20 $162,000

    Slab on grade, 4" thick, non industrial, reinforced

    A2010 Basement Excavation $0.05 $6,500

    Excavate and fill, 30,000 SF, 4' deep, sand, gravel, or common earth,

    on site storage

    A2020 Basement Walls $1.23 $165,500

    Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF,

    12" thick

    B Shell 24.70% $34.86 $4,705,500

    B1010 Floor Construction $15.61 $2,108,000

    Floor, concrete, slab form, open web bar joist @ 2' OC, on W beam

    and column, 30'x30' bay, 32" deep, 75 PSF superimposed load, 120

    PSF total load

    Floor, concrete, slab form, open web bar joist @ 2' OC, on W beam

    and column, 30'x30' bay, 32" deep, 75 PSF superimposed load, 120

    PSF total load, for columns add

    B1020 Roof Construction $2.58 $348,000

    Floor, steel joists, beams, 1.5" 22 ga metal deck, on columns, 30'x30'

    bay, 28" deep, 40 PSF superimposed load, 62 PSF total load

    Floor, steel joists, beams, 1.5" 22 ga metal deck, on columns, 30'x30'

    bay, 28" deep, 40 PSF superimposed load, 62 PSF total load, add for

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    36/90

    36

    column

    B2010 Exterior Walls $10.84 $1,463,000

    Brick wall, composite double wythe, standard face/CMU back-up, 8"

    thick, perlite core fill

    B2020 Exterior Windows $4.16 $562,000

    Aluminum flush tube frame, for insulating glass, 2" x 4-1/2", 5'x6'opening, no intermediate horizontals

    Glazing panel, insulating, 1/2" thick, 2 lites 1/8" float glass, clear

    B2030 Exterior Doors $0.27 $36,500

    Door, aluminum & glass, without transom, narrow stile, double

    door, hardware, 6'-0" x 7'-0" opening

    Door, steel 18 gauge, hollow metal, 1 door with frame, no label, 3'-

    0" x 7'-0" opening

    B3010 Roof Coverings $1.38 $186,500

    Roofing, asphalt flood coat, gravel, base sheet, 3 plies 15# asphalt

    felt, mopped

    Insulation, rigid, roof deck, composite with 2" EPS, 1" perlite

    Roof edges, aluminum, duranodic, .050" thick, 6" face

    Flashing, aluminum, no backing sides, .019"

    Gravel stop, aluminum, extruded, 4", mill finish, .050" thick

    B3020 Roof Openings $0.01 $1,500

    Roof hatch, with curb, 1" fiberglass insulation, 2'-6" x 3'-0",

    galvanized steel, 165 lbs

    C Interiors 23.70% $33.40 $4,508,500

    C1010 Partitions $6.17 $833,000

    Metal partition, 5/8"fire rated gypsum board face, 5/8"fire rated

    gypsum board base, 3-5/8" @ 24", 5/8"fire ratedopposite face, 3.5"

    fiberglas insulation5/8" gypsum board, taped & finished, painted on metal furring

    C1020 Interior Doors $13.12 $1,771,500

    Door, single leaf, kd steel frame, hollow metal, commercial quality,

    flush, 3'-0" x 7'-0" x 1-3/8"

    C2010 Stair Construction $1.41 $190,000

    Stairs, steel, cement filled metal pan & picket rail, 16 risers, with

    landing

    C3010 Wall Finishes $3.46 $466,500

    Painting, interior on plaster and drywall, walls & ceilings, roller work,

    primer & 2 coats

    Vinyl wall covering, fabric back, medium weightCeramic tile, thin set, 4-1/4" x 4-1/4"

    C3020 Floor Finishes $5.20 $702,000

    Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 35 oz

    Vinyl, composition tile, maximum

    Tile, ceramic natural clay

    C3030 Ceiling Finishes $4.04 $545,500

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    37/90

    37

    Acoustic ceilings, 5/8" plastic coated mineral fiber, 12" x 12" tile, 25

    ga channel grid, adhesive back support

    D Services 49.00% $69.16 $9,337,000

    D1010 Elevators and Lifts $6.73 $908,000

    Traction, geared passenger, 3500 lb, 6 floors, 10' story height, 2 car

    group, 200 FPM

    D2010 Plumbing Fixtures $24.42 $3,296,500

    Water closet, vitreous china, bowl only with flush valve, wall hung

    Urinal, vitreous china, wall hung

    Lavatory w/trim, vanity top, PE on CI, 20" x 18"

    Kitchen sink w/trim, countertop, stainless steel, 33" x 22" double

    bowl

    Service sink w/trim, PE on CI,wall hung w/rim guard, 22" x 18"

    Bathtub, recessed, PE on CI, mat bottom, 5' long

    Shower, stall, baked enamel, terrazzo receptor, 36" square

    Water cooler, electric, wall hung, wheelchair type, 7.5 GPH

    D2020 Domestic Water Distribution $0.60 $80,500

    Gas fired water heater, commercial, 100< F rise, 500 MBH input, 480

    GPH

    D2040 Rain Water Drainage $0.24 $32,500

    Roof drain, CI, soil,single hub, 5" diam, 10' high

    Roof drain, CI, soil,single hub, 5" diam, for each additional foot add

    D3010 Energy Supply $5.00 $675,500

    Commercial building heating system, fin tube radiation, forced hot

    water, 100,000 SF, 1mil CF, total 3 floors

    D3030 Cooling Generating Systems $14.10 $1,903,000

    Packaged chiller, water cooled, with fan coil unit, medical centers,

    60,000 SF, 140.00 ton

    D4010 Sprinklers $3.03 $408,500

    Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SF

    Wet pipe sprinkler systems, steel, light hazard, each additional floor,

    10,000 SF

    Standard High Rise Accessory Package 8 story

    D4020 Standpipes $0.37 $50,500

    Wet standpipe risers, class III, steel, black, sch 40, 4" diam pipe, 1

    floor

    Wet standpipe risers, class III, steel, black, sch 40, 4" diam pipe,

    additional floors

    Fire pump, electric, with controller, 5" pump, 100 HP, 1000 GPM

    Fire pump, electric, for jockey pump system, add

    D5010 Electrical Service/Distribution $1.40 $188,500

    Service installation, includes breakers, metering, 20' conduit & wire,

    3 phase, 4 wire, 120/208 V, 2000 A

    Feeder installation 600 V, including RGS conduit and XHHW wire, 60

    A

    Feeder installation 600 V, including RGS conduit and XHHW wire,

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    38/90

    38

    200 A

    Feeder installation 600 V, including RGS conduit and XHHW wire,

    2000 A

    Switchgear installation, incl switchboard, panels & circuit breaker,

    2000 A

    D5020 Lighting and Branch Wiring $8.60 $1,161,000

    Receptacles incl plate, box, conduit, wire, 10 per 1000 SF, 1.2 W per

    SF, with transformer

    Wall switches, 5.0 per 1000 SF

    Miscellaneous power, to .5 watts

    Central air conditioning power, 4 watts

    Motor installation, three phase, 460 V, 15 HP motor size

    Motor feeder systems, three phase, feed to 200 V 5 HP, 230 V 7.5

    HP, 460 V 15 HP, 575 V 20 HP

    Motor connections, three phase, 200/230/460/575 V, up to 5 HP

    Motor connections, three phase, 200/230/460/575 V, up to 100 HP

    Fluorescent fixtures recess mounted in ceiling, 0.8 watt per SF, 20FC, 5 fixtures @32 watt per 1000 SF

    D5030 Communications and Security $4.13 $557,500

    Communication and alarm systems, fire detection, addressable, 100

    detectors, includes outlets, boxes, conduit and wire

    Fire alarm command center, addressable with voice, excl. wire &

    conduit

    Communication and alarm systems, includes outlets, boxes, conduit

    and wire, intercom systems, 100 stations

    Communication and alarm systems, includes outlets, boxes, conduit

    and wire, master TV antenna systems, 30 outlets

    Internet wiring, 2 data/voice outlets per 1000 S.F.

    D5090 Other Electrical Systems $0.56 $75,000Generator sets, w/battery, charger, muffler and transfer switch,

    diesel engine with fuel tank, 250 kW

    E Equipment & Furnishings 0.00% $0.00 $0

    E1090 Other Equipment $0.00 $0

    F Special Construction 0.00% $0.00 $0

    G Building Sitework 0.00% $0.00 $0

    SubTotal 100% $141.03 $19,039,000

    Contractor Fees (General Conditions,Overhead,Profit) 25.00% $35.26 $4,760,000Architectural Fees 6.00% $10.58 $1,428,000

    User Fees 0.00% $0.00 $0

    Total Building Cost $186.87 $25,227,000

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    39/90

    39

    AppendixALoading Calculations

    Snow LoadsFlat Roof & Drift

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    40/90

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    41/90

    41

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    42/90

    42

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    43/90

    43

    Rain Loads

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    44/90

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    45/90

    45

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    46/90

    46

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    47/90

    47

    Seismic Loads

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    48/90

    48

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    49/90

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    50/90

    50

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    51/90

    51

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    52/90

    52

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    53/90

    53

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    54/90

    54

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    55/90

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    56/90

    56

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    57/90

    57

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    58/90

    58

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    59/90

    59

    RISA 3DBasic Load Combinations

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    60/90

    60

    Hand Calculations for Columns

    Remove constraint at a:

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    61/90

    61

    Solve For Moments About Node A

    Solve For Sum of Forces in Y Direction

    V(x) = Shear

    M(x) = Moment

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    62/90

    62

    (x) = Slope

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    63/90

    63

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    64/90

    64

    (x) = Deflections

    >

    (x) = Curvature

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    65/90

    65

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    66/90

    66

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    67/90

    67

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    68/90

    68

    E = Modulus of Elastisity (ksf)>

    i = Moment of Inertia ( )

    v(x) = Virtual Shear

    m(x) = Virtual Moment

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    69/90

    69

    (x) = Virtual Deflections

    >

    (x) = Virtual Curviture

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    70/90

    70

    >

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    71/90

    71

    Solving For Moments About Joint D>

    Solving For Sum of Forces in Y Axis

    Each Reaction is a column load per floor based on live load

    AppendixBConnection CalculationsConnection at Node 7 (Bottom of second floor, corner of end of wing)

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    72/90

    72

    Example summary from RISAConnection displaying code checks that each connection must pass

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    73/90

    73

    W14x82 to W27x178:

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    74/90

    74

    W27x178 to W27x178:

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    75/90

    75

    W27x178 to Column:

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    76/90

    76

    Vertical Brace Chevron Connection (This connection is checked by the following hand

    calculations to ensure 3 bolts is an adequate number)

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    77/90

    77

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    78/90

    78

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    79/90

    79

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    80/90

    80

    Column Base Plate

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    81/90

    81

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    82/90

    82

    AppendixCSettlement Calculations

    Initial Settlement CalculationsSe = qo*(*B')* (1 - s^2/Es)*Is*If

    Se rigid = .93 * Se

    Bearing Capacity 3 ksf

    qo net applied pressure on foundation 150 kips

    s Poisson's ratio = 0.3

    Es Avg soil modulus under foundation from 0 to 4B

    B' B/2 for center of foundation, B for corner

    Is Shape Factor

    Is = F1 + (1- 2 s/ 1-s) F2

    F1 = 1/pi (Ao +A1) F2 = n'/2pi * arctan A2

    Ao = m' ln [1 + (m'^2 + 1)^.5 * (m'^2 + n'^2)^.5 / m' (1 + (m'^2 + n'^2 + 1)^.5]

    A1 = ln [(m' + (m'^2 + 1)^.5) * (1+n'^2)^.5 / (m' + (m'^2+n' 2+1)^.5)]

    A2 = m' / n'*(m'^2 + n'^2 +1)^.5

    If Depth factor

    Where settlement is calculated

    Center Corner 4 1

    m' L/B L/B

    n' H/(B/2) H/B

    Soil Moduli N60 = N *H*B*S*R/ 60

    Es = Es(i) * z / H According to Das

    Factor JustificationEs(i) = 2000 psf* N60 * soil H 60 US Safety hammer,

    soil 5 Rope and pulley

    B 1 D = 2.25 inch

    S 1 Standard Sampler

    R 0.75 Rod Length < 12 ft

    Center

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    83/90

    83

    Parameters

    B 7.071068 Depth factor

    B' 3.535534 Df/B 0.565685

    L 7.071068 If 0.775 from Das 5.15

    4

    m' 1n' H/(B/2) F1,F2 and Is depend on n'

    Corner

    Parameters

    B 7.071068 Depth factor

    B' 7.071068 Df/B 0.565685

    L 7.071068 If 0.775 from Das 5.15

    1

    m' 1n' H/B F1,F2 and Is depend on n'

    B-31 B-30

    N N60 Es(i) (psf) z (ft) N N60 Es(i) (psf) z (ft)

    3 0.0225 225 2 2 0.015 150 3

    23 0.1725 1725 3 28 0.21 20160 2

    32 0.24 rock 16 0.12 rockH 5 H 5

    Es 1125 psf Es 8154 psf

    Settlement Settlement

    Center Center

    n' 1.414214 n' 1.414214

    F1 0.224 F1 0.224

    F2 0.075 F2 0.075

    Shape Factor Shape Factor

    Is 0.266857 Is 0.266857

    Se 0.354875 feet Se 0.048962

    Se rigid 0.330034 Se rigid 0.045534 feet

    Corner Corner

    n' 0.707107 n' 0.707107

    F1 0.257 F1 0.257

    F2 0.083 F2 0.083

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    84/90

    84

    Shape Factor Shape Factor

    Is 0.304429 Is 0.304429

    Se 0.202419 Se 0.027928

    Se rigid 0.18825 feet Se rigid 0.025973 feet

    B-32 B-29

    N N60 Es(i) (psf) z (ft) N N60 Es(i) (psf) z (ft)

    2 0.015 150 3 2 0.015 150 1

    38 0.285 2850 2 11 0.0825 rock

    35 0.2625 2625 2 H 1

    57 0.4275 rock Es 150 psf

    H 7

    Es 1628.571 psf

    Settlement SettlementCenter Center

    n' 1.979899 n' 0.282843

    F1 0.285 F1 0.014

    F2 0.064 F2 0.049

    Shape Factor Shape Factor

    Is 0.321571 Is 0.042

    Se 0.295406 Se 0.418897

    Se rigid 0.274728 feet Se rigid 0.389574 feet

    Corner Corner

    n' 0.989949 n' 0.141421

    F1 0.142 F1 0.009

    F2 0.083 F2 0.03

    Shape Factor Shape Factor

    Is 0.189429 Is 0.026143

    Se 0.087008 Se 0.130371

    Se rigid 0.080917 feet Se rigid 0.121245 feet

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    85/90

    85

    Final Settlement Calculations

    Final Settlement Calculations for 705 kip column on new fill

    Es = 8000 ksf

    Center

    Parameters

    B 16 Depth factor

    B' 8 Df/B 0.25

    L 16 If 0.88 from Das 5.15

    4

    m' 1

    n' H/(B/2) F1,F2 and Is depend on n'

    Corner

    Parameters

    B 16 Depth factor

    B' 16 Df/B 0.25

    L 16 If 0.88 from Das 5.15

    1 .8-.9

    m' 1

    n' H/B F1,F2 and Is depend on n'

    Settlement

    Center Corner

    n' 2.5 n' 5

    F1 0.376 F1 0.44

    F2 0.045 F2 0.03

    Shape Factor Shape Factor

    Is 0.401714 Is 0.457143

    Se 0.099789 feet Se 0.072264 feetSe

    rigid 0.092804 Se rigid 0.067206

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    86/90

    86

    AppendixDSquare Footing CalculationsFormulas and Nomenclature:

    Actual Soil Pressure < Soil Bearing Capacity

    D+L+Ws+Wf/B^2

    Ws weight of soil above footing

    Wf weight of footing *6% D+L)pfill 0.125 kcf

    Footing Thickness

    one-way and two-way shear

    1-way Vu

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    87/90

    87

    Calculations for each load:

    footing 1 = 705 kips

    Load 705 Kips

    B 16 ft

    Wsoil 85.33333 kipsQact 892.7333 kips

    Factored col Load

    D 133 kips

    L 572 kips

    Pfac 1074.8 kips

    Factored Soil Pressure p=P/B^2

    p = 4.198438 ksf

    Estimated depth to steel d=A/6

    d = 42.66667

    let d = 32 inch excess with estimate

    Beam Shear Flexural Reinforcement

    Vu = p*x*B consider 1 foot width

    264.9681 kips Steel in the NS and EW direction will be the sam

    Vc = 2*b*d sqrt(f'c) Depth to steel is to the higher bar

    777.1614 kips

    w p

    Vu

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    88/90

    88

    3. Vc = 4*sqrt(f'c)*bo*d As = rho*b*d

    1424.796 kips 0.676506 in^2 /ft

    Vc = 1424.796

    Vu

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    89/90

    89

    1. Vc = 6*[sqrt(f'c)]*bo*d

    1499.679 kips rho = [Mu/phi*b*d^2]*0.0033 /0.2

    2. Vc = ((as * d) / bo) +2)*sqrt(f'c)*bo*d 0.001798

    1782.513 kips

    3. Vc = 4*sqrt(f'c)*bo*d As = rho*b*d

    999.7857 kips 0.560865 in^2 /ftVc = 999.7857

    Vu

  • 7/23/2019 Final%252BReport-Harpoon%252BEngineering.pdf

    90/90

    bo = 4*x b 12 inch considered

    120 inch d 18 inch

    min of = 0.123495 ksi

    1. Vc = 6*[sqrt(f'c)]*bo*d

    819.6624 kips rho = [Mu/phi*b*d^2]*0.0033 /0.22. Vc = ((as * d) / bo) +2)*sqrt(f'c)*bo*d 0.002038

    683.052 kips

    3. Vc = 4*sqrt(f'c)*bo*d As = rho*b*d

    546.4416 kips 0.440138 in^2 /ft

    Vc = 546.4416