finalreport (autosaved)

Upload: karthik-vadlapatla

Post on 03-Jun-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 finalreport (Autosaved)

    1/23

    1 | P a g e

    INDE 7397

    Improving Productivity at Hardy Machines with Lean

    Report

    by

    Kartheek Vadlapatla1278272

    M.S., Industrial Engineering

    University of Houston - Systems

  • 8/11/2019 finalreport (Autosaved)

    2/23

    2 | P a g e

    Acknowledgement

    I wish to thank President Ankur Goel of Hardy Machine and Design and Dr. SharukhIrani for their tremendous contributions and support towards the completion of the

    project. I am also grateful to my project supervisor Dr. Suresh Khator who without

    his help and guidance this project would not have been completed. I also show my

    gratitude to my friends who contributed in one way or the other in the course of theproject.

  • 8/11/2019 finalreport (Autosaved)

    3/23

    3 | P a g e

    Table of Contents

    Title Page No:

    Acknowledgement 2

    Table of ContentsList of Tables

    List of Figures

    Introduction 4

    Problem Statement

    Goal and Objective 6

    1. Proposal 15S

    1.1Data collected at Hardy

    1.2

    Need for 5S

    1.3Steps in 5S implementation

    2. Proposal 2S.M.E.D

    2.1Data collected at Hardy

    2.2

    Need for S.M.E.D

    2.3Steps in implementation of S.M.E.D

    3. Conclusion

    References

  • 8/11/2019 finalreport (Autosaved)

    4/23

    4 | P a g e

    LIST OF TABLES

    Table 1- Time studies performed during the CNC Lathe setup

    Table 2 - Time studies are performed during the Milling machine setup

    Table 3 - Internal and External activities during CNC Lathe machine 406 setup

    Table 4 - Internal and External activities during CNC Lathe machine 408 setup

  • 8/11/2019 finalreport (Autosaved)

    5/23

    5 | P a g e

    LIST OF FIGURES

    Figure 1Time consumed to perform various operations during CNC Lathe setup

    Figure 2 - Time consumed to perform various operations during milling setup

    Figure 3 - Percentage of Value added and Non Value Added Work

    Figure 3Rack used for placing Milling Tools

    Figure 4Empty Micrometer Box

    Figure 5Milling tool Holder without screw

    Figure 7Grinding Dust

    Figure 8Machine is down for 3 Hours due to hydraulic pump failure caused by Oil Leak

    Figure 9 - Oil spilling

    Figure 10 - Scrap material on shop floor can cause trip hazard

    Figure 11 - Fork Lift blocking the path of crane used for moving job pieces

    Figure 12job Pieces damaged by the fork lift because the where not placed in the proper

    location on the Shop floor

    Figure 13 - Red Tag

    Figure 14 - 5S Audit for Hardy Machine and Design

    Figure 15

    Percentage of internal and external activities during Machine 406 Setup

    Figure 16Percentage of internal and external activities during Machine 406 Setup

  • 8/11/2019 finalreport (Autosaved)

    6/23

    6 | P a g e

    Introduction

    Hardy Machine & Design, Inc. is a modern job shop specialized in manufacturingcomponents for Oil and Gas, Aerospace and Health Industry. The company has over

    25 years of experience in its field and this experience is combined with current

    working methods and techniques. The company has reached a leading position in

    Precision Machining, Fabrication and Welding. The companys principles are toinvest into high class machines and the newest machining methods and to keep the

    working environment in an excellent shape.

    Hardy is a Make to Order (MTO) Job shop which manufactures a wide variety of

    products in low volumes. In a job shop environment the demand for customized

    products vary from day to day and Customers expectations are unpredictable. As aresult of customization, manufacturing environments gets complicated. Added to

    this, customers also expect the product to be delivered only a short period of timeafter placing their orders. This situation creates competition among Hardy and their

    competitors to manufacture and deliver products as fast as possible whileemphasizing the importance of minimizing lead times.

    Problem Statement

    Major problems at Hardy Machine and Design are their longer setup times and

    inventory/Tooling management. Firstly, longer lead times are causing customerdissatisfactory. Secondly, regarding the Tooling management, Hardy loosing

    machine spindle time due lack of point of use of tools and spending large amount ofmoney in purchasing misplaced and lost Tools.

    Goal and Objective

    The purpose of this project is to identify the root cause for Non value added activities

    that increases the setup time and inventory, and to propose LEAN methodologies toincrease the productivity without sacrificing Quality

  • 8/11/2019 finalreport (Autosaved)

    7/23

    7 | P a g e

    1.Proposal 1 - 5S

    The 5S-operation model is one part of the Lean model. It is just one of the manytools which the Lean-ideology includes.5S was originally developed by JIT expert

    Hiroyuki Hirano. The 5S frame work is an extension of Hiranos earlier work on

    Just in Time production Systems.5S represents a simple housekeeping approach to

    improve work environment. In general, 5S approach include the control over thework flow rather than workers behavior. It is relatively inexpensive to implement.

    It makes job safer and easier. It encourages preventive approach that preventsproblems before they occur. It provides a practical approach for dealing with real

    problems, faced by the workers. 5S consists of five (5) different phases. The names

    of the phases come from Japanese and all of them begin with the letter s. That is

    where the name 5S stems from. The phases are:

    - Seiri = Sort- Seiton = Stabilize/Set in order

    - Seiso = Shine/Sweep

    - Seiketsu = Standardize

    - Shitsuke = Sustain.

    The two most important elements are Sort and Set in Order. The success of

    improvement activities depends on them. The 5S system sounds so simple but it onimportant lean methodology, without implementing 5S other Lean concepts cannot

    be implemented [1]. Moreover, Cleanliness and order characterize significant issuesboth for customers and potential labor force. The starting point is that profitable and

    high-quality tasks can be conducted only in a clean environment. The basic idea is

    to increase productivity, to improve the level of quality and to raise work ethic.

    These factors are reached when the working environment is clean and in good order.5S is a practical tool for maintaining these. It helps to find and eliminate problems

    in time. The 5S-model is special because it can be applied in to an office as well asin the production of a company. Systematic and disciplined operations are developed

    with the 5S-model.

  • 8/11/2019 finalreport (Autosaved)

    8/23

    8 | P a g e

    1.1 Data Collected at Hardy

    Table 1- Time studies performed during the CNC Lathe setup

  • 8/11/2019 finalreport (Autosaved)

    9/23

    9 | P a g e

    Figure 6Time consumed to perform various operations during CNC Lathe setup

    Setup31%

    Search for Supervisor

    3%Discussion with

    Supervisor

    1%Search for Tools

    7%Search for Bolt

    6%

    Search for Handle

    17%

    Operator is out of office

    35%

    Setup Search for Supervisor Discussion with Supervisor

    Search for Tools Search for Bolt Search for Handle

    Operator is out of office

    Work Time

    31%

    Non value added

    Time

    69%

    Work Time Non value added Time

  • 8/11/2019 finalreport (Autosaved)

    10/23

    10 | P a g e

    Table 2 - Time studies are performed during the Milling machine setup

    Figure 7 - Time consumed to perform various operations during milling setup

    0

    5

    10

    15

    20

    25

    30

    DurationSetup Search for Holder Search for Drill

    Fixing Drill and Holder Search for two collets Fixing collet to Drill Holder

    Search for second tool Holder Fixing Tool holder and Tool

  • 8/11/2019 finalreport (Autosaved)

    11/23

    11 | P a g e

    Figure 8Percentage of Value added and Non Value Added Work

    Figure 9Rack used for placing Milling Tools

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%100%

    Value added Work Non Value Added work

    VA vs. NVA Work

  • 8/11/2019 finalreport (Autosaved)

    12/23

    12 | P a g e

    Figure 10Empty Micrometer Box Figure 11Milling tool Holder without

    screw

    Figure 8Machine is down for 3 Hours

    due to hydraulic pump failure caused by

    Oil Leak

    Figure 9 - Oil spilling Figure 10 - Scrap material on shop

    floor can cause trip hazard

    Figure 7Grinding Dust

  • 8/11/2019 finalreport (Autosaved)

    13/23

    13 | P a g e

    1.2 Need for 5S:

    During interaction with Operators and Management, and after performing Timestudies for Setup Operation, we had noticed that time for searching and picking up

    tools, equipment and other materials was significantly too long. Added to this rework

    due improper material Handling Techniques is also high. Useless time goes by and

    it harms the fluency of work. Hence by implementing 5S Philosophy, theproductivity and the quality can be increased, work in-processes and lead-times canbe reduced, better working circumstances can be created, searching times and costs

    can be decreased, Moreover, it also helps in rising company image.

    In fig-1, the activities marked yellow, performed by the Lathe operator can beeliminated by implementing 5S.This activities add up to 30% of setup time.

    Similarly, in fig-2, the non-value added time that adds up to 41% can be eliminated

    by 5S. It is found that the milling operators needs 10-15 mins to find the tools placed

    the rack (Fig4) and some of the tools are lost or misplaced due lack of dedicatedstorage place(Fig5,6). This can be eliminated by implementing First S and Second

    S (sort and set in order) in 5S Philosophy. Grinding dust (Fig -7) can lead to healthhazard and Oil spills (Fig 9) on shop floor can lead to slipping hazard. This can

    eliminated by implementing shine.

    Figure 11 - Fork Lift blocking the path of

    crane used for moving job pieces

    Figure 12 job Pieces damaged by the fork lift

    because the where not placed in the proper

    location on the Shop floor

  • 8/11/2019 finalreport (Autosaved)

    14/23

    14 | P a g e

    Added to this, other benefits of implementing 5S are:

    To gain control on equipment, material & inventory placement and position

    To eliminate the waste that result from uncontrolled processes.

    To ensure that improvements are sustained

    To Standardize critical processes such as Tool storage ,Machine clean up andMachine maintenance

    To improve consistency of shop supervision

    1.3 Steps in 5S implementation:

    Phase 1 - Sort

    The first phase is called Sort. Main point in this first phase is simply to sort

    everything. Every tool, object and instrument is looked through and every one ofthose will be recognized and the demands of those are evaluated. This phase also

    includes a task where criterions are created. Removable products will be sorted and

    after that, disposed of. Also useful products will be sorted and new places are createdafter sorting.

    Mostly used method in sorting-phase is Red-tag program. The removable or

    somewhere else storable products are marked with a red tag. That tag tells, for

    example, as shown in Fig 1, the name of the inspector, date, demand, reason of the

    tag, storage place and disposition date. Jigs, molds, junk and work-in process are

    often accumulated all over the stations and the purpose is to get rid of all these. First,all the tagged products are moved into the red tag area and after that, eitherpositioned again or removed for good.

  • 8/11/2019 finalreport (Autosaved)

    15/23

    15 | P a g e

    Figure 13 - Red Tag

    Removing useless items clarifies working environment and gives more space to act.Sorting helps everybody to keep places clean and in good order. Moving and safety

    at work gets better, it saves and increases space, clarifies processes and gives achance to save up in cleaning.

    Phase 2

    Set in Order

    The main purpose of stabilization is to find practical depository for every requisiteinstrument and those depositories should be marked properly. Every single item,

    which is necessary in working, will be organized in a way that those can be foundeasily when needed. Setting in order assures that it is a snap for everyone to find,

    take in use and put away the needed item. Target of all these actions is to eliminatepointless searching, improve safety at work and make working environment better.

    Places of the equipment are not the only things which are marked. It is advisable tomark tools itself for example with colored cable ties. Marking off the floor and

    dividing it into stations is a wise thing to do. That creates passages and clarifiesmovements in the production areas. When pulling the lines, it is useful to mark

    places for pallets, pallet jacks and garbage cans at the same time. Color-codes and

    signs are used to prevent the equipment getting mixed-up.

  • 8/11/2019 finalreport (Autosaved)

    16/23

    16 | P a g e

    Phase 3 - Shine

    It is not enough if phases one and two alone are implemented. First two phases

    remove problems in relation to space but one problem is hiding around the corner.

    Dirt wear down machines and makes quality worse. Third phase, Shine, is createdfor these problems. Everything will be cleaned up when operation model reaches

    this point, Floors, tools, tool racks, devices and especially machines. Engine lifeincreases and everything will be ready for instant use when those are cleaned. This

    leads automatically into situation where everything is kept in top condition.

    Phase 4 - Standardize

    Carrying out a 5S-campaign once in a cell or work station is a pushover. Withoutdaily discipline and clear follow-up and operation routines it is too easy to return

    into old habits. That is why the management level should set annual 5S-goals for

    every station and employee. Fourth phase is Standardization. This stage is destinedto create procedures and routines. Those should be guiding three (3) earlier phasesinto continuous and developing course of actions. Purpose of this phase is to take in

    use and maintain all that, which is created earlier in sorting, stabilizing and shining.

    Target is to change constant methods into standards which employees are expectedto obey. Mundane tasks are established and those are followed precisely. Instructions

    should be so crystal clear that almost everyone could check the station with the help

    of those standard methods. Actions are being supervised and followed by persons.Everyone should know what to do. Check lists are created in standardization phase

    and on by a way of those the level of operation model is monitored.

    Phase 5 - Sustain

    Last phase is sustaining the level which is reached with four earlier phases. Standardsmethods and balanced workplace are maintained and followed all the time. Methods

    that are under adoption are improved continuously. Improvement has to be one part

    of sustain because the environment should be improved with the help of results from

    follow-up. Internal audition lists should be created in the phase five, and auditions

    should be made at regular intervals. The results from the auditions should begathered and put on to bulletin boards so that everyone can see and follow up the

    development of 5S-actions. Evaluation should include, happened changes andcomparison to earlier months. Audition is essential tool in progress of pushing

    cleanliness and sustaining a creditable level of order.

  • 8/11/2019 finalreport (Autosaved)

    17/23

    17 | P a g e

    Figure 14 - 5S Audit for Hardy Machine and Design

  • 8/11/2019 finalreport (Autosaved)

    18/23

    18 | P a g e

    Proposal 2 - S.M.E.D

    Single Minute Exchange of Die is one of the many Lean production methods for

    reducing waste in manufacturing process. It provides a rapid and efficient way of

    converting a manufacturing process from running current product to running the nextproduct. This rapid changeover is helpful in reducing production lot sizes andthereby improving flow. It is also often referred to as Quick Changeover (QCO).

    Performing faster changeovers is important in manufacturing, or any process,because they make low cost flexible operations possible.

    The concept of SMED is created by shigeo shingo, one of the main contributors toToyota Production system. According to Shingo, if the change over time can be

    reduced, then the economic lot size could be reduced, directly reducing expenses.

    Shingo also stated that large lot sizes requires higher stock levels to be kept in restof the process and these hidden costs, are also reduced by smaller lot sizes through

    implementing SMED [2].

    The following eight techniques [3] should be considered during the implementation

    of SMED:

    1. Separate internal from external setup operations

    2. Convert internal to external setup.

    3. Standardize function, not shape.

    4. Use functional clamps or eliminate fasteners altogether.5. Use intermediate jigs.

    6. Adopt parallel operations.

    7. Eliminate adjustments.

    8. Mechanization.

    In general, the idea behind the SMED methodology is to convert internal setup

    operations to external operations. This method is highly recommended to reducechangeover time, thereby allowing extra production time to increase output [4].

  • 8/11/2019 finalreport (Autosaved)

    19/23

    19 | P a g e

    2.1 Data collected at Hardy:

    Further analysis has been made, to identify the percentage Non value added

    internal activities performed during setup operation and results are shown in table

    3 and table 4.Table 3 - Internal and External activities during CNC Lathe machine 406 setup

  • 8/11/2019 finalreport (Autosaved)

    20/23

    20 | P a g e

    Figure 15Percentage of internal and external activities during Machine 406 Setup

    Results:

    Total Time required for setup60 mins

    Time for Internal setup34 Mins

    Time for External Setup26 mins

    External40%

    Internal60%

    Machine 406 SetuExternal Internal

    Table 4 - I nternal and External activiti es dur ing CNC Lathe machine 408 setup

  • 8/11/2019 finalreport (Autosaved)

    21/23

    21 | P a g e

    Figure 16Percentage of internal and external activities during Machine 406 Setup

    Results:

    Total Time required for setup31 mins

    Time for internal setup16 Mins

    Time for External Setup15 mins

    2.2 Need for SMED:

    As seen in figure 1 and figure 2, Non-Value Added can be reduce to 40% by

    implementing 5S, the activities like discussion with the supervisor, and fixing drill

    and holder cannot be eliminated.

    From table 2 and table 3, it can be noted that the more than 50 % of activities

    performed during the setup are external operation. This activities are performed

    as internal operation. By implementing the concept of S.M.E.D, Non Value Added

    time can be further reduced.

    External48%Internal

    52%

    Machine 408 Setu

    External Internal

  • 8/11/2019 finalreport (Autosaved)

    22/23

    22 | P a g e

    2.3 Steps in implementation of SMED:

    The SMED methodology consists of two phases. In the first phase, a distinction is

    made between internal and external setup tasks. Internal setup operations are

    those that must be performed when the machine is stopped. These operations

    occur on-line to the machine. External operations are those that can be performed

    while the machine is in operation. It is more efficient to perform these tasks off-

    line from the machine. Once the operations are classified as either external or

    internal, the external operations can be moved off-line to reduce machine

    downtime.

    In the second phase of SMED, all aspects of the setup, both internal and external,

    are streamlined to make them more efficient. Internal setup efficiency results in

    labor savings and less downtime machine capacity. External efficiency does notdirectly improve downtime, but gives better utilization of labor. Since at the factory

    or line level labor can be a constraint on doing setups, it can also indirectly reduce

    downtime.

    Conclusion:

    By implementing 5S and S.M.E.D the setup time can be reduced by 70%.This

    projects can also help Hardy to minimize tooling issues and reduce inventory.

  • 8/11/2019 finalreport (Autosaved)

    23/23

    23 | P a g e

    References:

    [1] 5S for Operators: 5 Pillars of the Visual Workplace (For Your

    Organization!) PaperbackMarch 1, 1996 byHiroyuki Hirano

    [2] Eliyahu Goldratt, 1990, Theory of Constraints, North River Press, Massachusetts,

    pp. 40

    [3] Shigeo Shingo, 1989, A study of Toyota Production System, Productivity Press,

    New York, pp. 47

    [4] Greg Lane, 2007, MadeToOrder Lean, Productivity Press, New York, pp. 66

    http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1