financial analysis
DESCRIPTION
costingTRANSCRIPT
Technological Institute of the Philippines
FINANCIAL ANALYSIS
This is an outline of the economic considerations, which are necessary when preparing an estimate of the capital investment or total product cost for a new venture or project.
Methods for obtaining predesign cost estimates has purposely been emphasized because the latter are extremely important for determining the feasibility of proposed investment and to compare alternative designs. The predesign estimates are based partially on
approximate percentages or factor that are applicable to a particular plant or process under consideration.
USE OF COST INDEXES
A cost index is merely an index value for a given period point in time showing the cost at
that time relative to a certain base time. If the cost at some time in the past is known, the equivalent cost at the present time can be determined by multiplying the original cost by the ratio of the present index value to the index value applicable when the original cost
was obtained.
For the Manufacture of Ammonium Nitrate by Prilling Process from Ammonia and Nitric acid, we used the Marshall and Swift Equipment Cost Indexes projected to 2013. We used the projections cost index
Marshall and Swift Installed Equipment Indexes (Reference: Chemical Engineering
Plant Cost Index)
YEAR X is the number of years since 2005
Y is the CEPCI
2005 0 468.2
2006 1 499.6
2007 2 525.4
2008 3 575.4
2009 4 521.9
2010 5 550.8
2011 6 585.7
2012 7 584.6
2013 8 567.6
Technological Institute of the Philippines
By plotting the data above, we could get the cost index for the year 2015,
Using the Equation above
๐ฆ = โ0.1211๐ฅ 6 + 2.051๐ฅ 5 โ 11.509๐ฅ 4 + 22.461๐ฅ 3 โ 6.5617๐ฅ 2 + 20.605๐ฅ+ 468.76
Where:
X=3
๐ฆ = โ0.1211(3)6 + 2.051(3)5 โ 11.509(3)4 + 22.461(3)3 โ 6.5617(3)2
+ 20.605(3) + 468.76
๐ = ๐๐๐.๐๐ (๐ช๐๐๐ ๐๐๐ ๐๐ ๐๐๐ ๐๐๐๐ ๐๐๐๐)
๐ช๐๐๐ ๐ฐ๐๐ ๐๐ ๐๐ ๐๐๐๐ = ๐๐๐.๐
Exchange Rate (Source: www.bsp.gov.ph)
Unite States Dollar (USD) Philippine Peso (Php)
$1 Php 46.831
As of October 1, 2015
Technological Institute of the Philippines
Cost Estimation
Estimation of Capital Investment
Plant Capacity:10000 kg/day
Plant Operation: 300 days/year at 8 hours/day
TOTAL COST OF PURCHASED EQUIPMENT
Equipment No. of
Equipment Total Cost Unit
Silo 1 374,648.00 PhP
Neutralizer 1 1,986,439.89 PhP
Vibrating Screen 1 448,547.32 PhP
Prill Tower 1 46,350,500.00 PhP
Dryer 1 2,056,872.78 PhP
Mixer 1 140,498.00 PhP
Flash Drum Evaporator 1 1,030,282.00 PhP
Evaporator 1 38,624,589.38 PhP
Shell and Tube Heat Exchanger (V-001) 1 573,283.56 PhP
Shell and Tube Heat Exchanger (HEX-001) 1 103,480.39 PhP
Shell and Tube Heat Exchanger (HEX-002) 1 628,634.99 PhP
Shell and Tube Heat Exchanger (HEX-006) 1 137,636.31 PhP
Double Pipe Heat Exchanger (HEX-003) 1 535,319.07 PhP
Double Pipe Heat Exchanger (HEX-004) 1 257,991.98 PhP
Double Pipe Heat Exchanger (HEX-005) 1 257,991.98 PhP
Rotary Cooler 1 468,310.00 PhP
Screw Conveyor 4 515,141.00 PhP
Total Purchase Equipment Cost w/ Delivery Cost 94,490,166.65 PhP
Technological Institute of the Philippines
Cost of Equipment
* Using the McGraw Hill Online Cost Estimator
1. SILO
Heat transfer area: m2 Materials of Construction: Cost2002: PhP 374,648.00
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 374,648.00 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐
2. NEUTRALIZER
Heat transfer area: m2 Materials of Construction: Carbon Steel Cost2002: PhP 1,986,439.89
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 1,986,439.89 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐,๐๐๐,๐๐๐.๐๐ 3. VIBRATING SCREEN
Heat transfer area: m2 Materials of Construction: Cost2002: PhP 448,547.32
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 448,547.32 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐
4. PRILL TOWER Heat transfer area: m2
Materials of Construction: Cost2002: PhP 46,350,500.00 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 46,350,500.00 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐,๐๐๐,๐๐๐.๐๐
Technological Institute of the Philippines
5. DRYER Heat transfer area: m2 Materials of Construction:
Cost2002: PhP 2,056,872.78 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 2,056,872.78 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐,๐๐๐,๐๐๐.๐๐ 6. MIXER
Heat transfer area: m2 Materials of Construction: Cost2002: PhP 140,498.00
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 140,498.00 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐ 7. FLASH DRUM EVAPORATOR
Heat transfer area: m2 Materials of Construction:
Cost2002: PhP 1,030,282.00 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 1,030,282.00 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐,๐๐๐,๐๐๐.๐๐ 8. EVAPORATOR
Heat transfer area: 40.93 m2 Materials of Construction: Carbon Steel & Stainless Steel Cost2002: PhP 38,624,589.38
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 38,624,589.38 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐๐๐๐๐๐.๐๐
Technological Institute of the Philippines
9. SHELL AND TUBE HEAT EXCHANGER (V-001) Heat transfer area: m2 Materials of Construction:
Cost2002: PhP 573,283.56 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 573,283.56 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐ 10. SHELL AND TUBE HEAT EXCHANGER (HEX-001)
Heat transfer area: m2 Materials of Construction: Cost2002: PhP 103,480.39
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 103,480.39 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐
11. SHELL AND TUBE HEAT EXCHANGER (HEX-002) Heat transfer area: 3.8704 m2 Materials of Construction: 304 Stainless Steel
Cost2002: PhP 628,634.99 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 628,634.99 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐ 12. SHELL AND TUBE HEAT EXCHANGER (HEX-006)
Heat transfer area: m2 Materials of Construction: Cost2002: PhP 137,636.31
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 137,636.31 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐
Technological Institute of the Philippines
13. DOUBLE PIPE HEAT EXCHANGER (HEX-003) Heat transfer area: m2 Materials of Construction:
Cost2002: PhP 535,319.07 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 535,319.07 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐ 14. DOUBLE PIPE HEAT EXCHANGER (HEX-004)
Heat transfer area: m2 Materials of Construction: Cost2002: PhP 257,991.98
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 257,991.98 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐ 15. DOUBLE PIPE HEAT EXCHANGER (HEX-005)
Heat transfer area: m2 Materials of Construction:
Cost2002: PhP 257,991.98 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 257,991.98 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐ 16. ROTARY COOLER
Heat transfer area: 2.66 m2 Materials of Construction: Cost2002: PhP 468,319.00
Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 468,319.00 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐
Technological Institute of the Philippines
17. SCREW CONVEYOR (4 UNITS) Heat transfer area: m2 Materials of Construction:
Cost2002: PhP 515,141.00 Solving for Cost2015
Cost2015 = Cost 2002 (cost index at 2015
cost index at 2002)
Cost2015 = 515,141.00 (555.85
395.6)
๐ช๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐๐,๐๐๐.๐๐
It is assumed that delivery charges are 5% of the purchased price.
๐๐๐ก๐๐ ๐๐ข๐๐โ๐๐ ๐๐ ๐ถ๐๐ ๐ก = ๐โ๐ 132,766,338.7
๐๐๐ก๐๐ ๐๐ข๐๐โ๐๐ ๐๐ ๐ถ๐๐ ๐ก ๐ค๐๐กโ ๐๐๐๐๐ฃ๐๐๐ฆ ๐ถ๐๐ ๐ก
= ๐โ๐ 132,766,338.7 + (0.05 ๐ฅ ๐โ๐ 132,766,338.7)
๐ป๐๐๐๐ ๐ท๐๐๐๐๐๐๐๐ ๐ช๐๐๐ ๐๐๐๐ ๐ซ๐๐๐๐๐๐๐ ๐ช๐๐๐ (๐ท๐น๐ถ๐ช๐ฌ๐บ๐บ๐ฐ๐ต๐ฎ ๐ฌ๐ธ๐ผ๐ฐ๐ท๐ด๐ฌ๐ต๐ป)
= ๐ท๐๐ท ๐๐๐,๐๐๐,๐๐๐.๐๐
Technological Institute of the Philippines
Instrumentation and Control Cost
The scope of the instrumentation and control cost comprises the purchase and installation labor cost of auxillary machines, such as pressure and temperature gauges or flow controller, used to control equipment.
Total Instrumentation Cost (Alibaba.com)
Name of Instrumentation No. of Units
Price per unit, Php
Total Price, Php
Ball Valve 10
Check Valve 3
Conveyor Speeder 15
Flow Controller 3
Flow Transmitter 3
Level Transmitter 10
Orifice 3
Pump 3
Speed Controller 15
Summation controller 3
Temperature transmitter 2
Transducer 16
Weight Controller 10
Weight Transmitter 14
Total 6,024,000.00
Technological Institute of the Philippines
I.DIRECT COSTS
Installation Cost
The scope of the installation cost of the equipment comprises the cost of foundation
support platforms, labor cost, construction related expense, and other factors related to the erection of the purchased equipment.
Basis: for a solid processing plant, 45% of the delivered equipment cost is the amount of the purchased equipment installed.
๐๐ข๐๐โ๐๐ ๐๐ ๐ธ๐๐ข๐๐๐๐๐๐ก ๐ผ๐๐ ๐ก๐๐๐๐๐ก๐๐๐= 0.45 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐ข๐๐โ๐๐ ๐๐ ๐ธ๐๐ข๐๐๐๐๐๐ก ๐ผ๐๐ ๐ก๐๐๐๐๐ก๐๐๐ = 0.45 ๐ฅ ๐โ๐ 139,404,655.60
๐ท๐๐๐๐๐๐๐๐ ๐ฌ๐๐๐๐๐๐๐๐ ๐ฐ๐๐๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐,๐๐๐,๐๐๐.๐๐
Piping and Conveyor Installation
The scope of the piping and conveyor installation comprises the labor cost of installation, cost of pipes, valves, fittings and all other piping and conveyor requirements.
Basis: 31% of the cost of purchased equipment delivered is the piping and conveyor cost installation.
๐๐๐๐๐๐ ๐๐๐ ๐๐๐๐ฃ๐๐ฆ๐๐ ๐๐๐ ๐ก๐๐๐๐๐ก๐๐๐= 0.16 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐๐๐๐๐ ๐๐๐ ๐๐๐๐ฃ๐๐ฆ๐๐ ๐๐๐ ๐ก๐๐๐๐๐ก๐๐๐ = 0.31 ๐ฅ ๐โ๐ 139,404,655.60
๐ท๐๐๐๐๐ ๐๐๐ ๐๐๐๐๐๐๐๐ ๐๐๐๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐,๐๐๐,๐๐๐.๐๐
Electrical Systems
The scope of the electrical system cost comprises the power, wiring, lightning,
transformation, service and instrumentation and control wiring.
Basis: 10% of the delivered equipment cost is the installed electrical system cost.
๐๐๐๐๐ก๐๐๐๐๐ ๐ ๐ฆ๐ ๐ก๐๐ ๐๐๐ ๐ก๐๐๐๐๐ก๐๐๐
= 0.10 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐๐๐๐ก๐๐๐๐๐ ๐ ๐ฆ๐ ๐ก๐๐ ๐๐๐ ๐ก๐๐๐๐๐ก๐๐๐ = 0.10 ๐ฅ ๐โ๐ 139,404,655.60
๐๐๐๐๐๐๐๐๐๐ ๐๐๐๐๐๐ ๐๐๐๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐,๐๐๐,๐๐๐.๐๐
Technological Institute of the Philippines
Yard Improvement
The scope of the yard improvement comprises the roads, grading,fencing, sidewalks, railroads, sidings, landscaping, and any other similar items related to yard improvements.
Basis: for a solid processing plant, 15% of the delivered equipment cost is the yard improvement cost.
๐ฆ๐๐๐ ๐๐๐๐๐๐ฃ๐๐๐ก = 0.15 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐ฆ๐๐๐ ๐๐๐๐๐๐ฃ๐๐๐ก = 0.15 ๐ฅ ๐โ๐ 139,404,655.60
๐๐๐๐ ๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ท ๐๐,๐๐๐,๐๐๐.๐๐
Service Facilities
The scope of service facilities comprises the utilities for supplying steam, water, power, and fuel for the chemical processes and operations. Fire protection, waste disposal and
miscellaneous service items such as shops, clinics or first aid quarters, and cafeterias require capital investment that are included under general heading of service facilities.
Basis: For a solid processing plant, the 40% of the delivered equipment cost is the service facility cost.
๐ ๐๐๐ฃ๐๐๐ ๐๐๐๐๐๐๐ก๐ฆ ๐๐๐ ๐ก๐๐๐๐๐ก๐๐๐= 0.40 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐ ๐๐๐ฃ๐๐๐ ๐๐๐๐๐๐๐ก๐ฆ ๐๐๐ ๐ก๐๐๐๐๐ก๐๐๐ = 0.40 ๐ฅ ๐โ๐ 139,404,655.60
๐๐๐๐๐๐๐ ๐๐๐๐๐๐๐๐ ๐๐๐๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐๐๐๐๐๐๐.๐๐
Total Direct Plant Cost:
๐ท๐๐ = ๐๐๐๐๐๐๐๐๐.๐
INDIRECT COSTS
Engineering and Supervision
Technological Institute of the Philippines
The scope of the engineering and supervision comprises the internal or licensed software, computer-aided drafts, purchasing, accounting, travel, and the plant
supervisory services.
Basis: for a solid processing plant, 33% of the delivered equipment cost is the
engineering and supervision cost.
๐๐๐๐๐๐๐๐๐๐๐ ๐๐๐ ๐ ๐ข๐๐๐๐ฃ๐๐ ๐๐๐
= 0.33 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐๐๐๐๐๐๐๐๐๐ ๐๐๐ ๐ ๐ข๐๐๐๐ฃ๐๐ ๐๐๐ = 0.33 ๐ฅ ๐โ๐ 119,452,840.3
๐๐๐๐๐๐๐๐๐๐๐ ๐๐๐ ๐๐๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐๐๐๐๐๐๐.๐๐
Construction Expenses The scope of the construction expenses comprises the cost construction labor and other construction related expenses such as the construction tools and rentals,
construction payroll, construction tariffs, insurance and permits, miscellaneous equipment installation and other fees related to the construction process. Basis: for solid processing plant, 39% of the delivered equipment cost is the
construction expenses
๐๐๐๐ ๐ก๐๐ข๐๐ก๐๐๐ ๐๐ฅ๐๐๐๐ ๐๐ = 0.39 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐๐๐ ๐ก๐๐ข๐๐ก๐๐๐ ๐๐ฅ๐๐๐๐ ๐๐ = 0.39 ๐ฅ ๐โ๐ 119,452,840.3
๐๐๐๐๐๐๐๐๐๐๐๐ ๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐๐๐๐๐๐๐.๐๐
Legal Expenses
The scope of legal expenses comprises the costs related to the processing of land purchase, equipment purchase, and contracts of construction. Understanding and
proving compliance to government requirements, such as environmental and safety measures requirements constitute major sources of legal cost.
Basis: for solid processing equipment, 4% of the delivered equipment cost is the legal expenses.
๐๐๐๐๐ ๐๐ฅ๐๐๐๐ ๐๐ = 0.04 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐๐๐๐ ๐๐ฅ๐๐๐๐ ๐๐ = 0.04 ๐ฅ ๐โ๐ 119,452,840.3
๐๐๐๐๐ ๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐๐๐๐๐๐.๐๐๐
Contractorโs Fee
Technological Institute of the Philippines
The scope of the contractorโs fee includes the payment given to the construction company hired for the construction of the plant.
Basis: for solid processing equipment, 17% of the delivered equipment cost is the contractorโs fee.
๐๐๐๐ก๐๐๐๐ก๐๐โฒ๐ ๐๐๐ = 0.17 ๐ฅ (๐๐๐ก๐๐ ๐๐๐๐๐ฃ๐๐๐๐ โ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐ ๐ก)
๐๐๐๐ก๐๐๐๐ก๐๐โฒ๐ ๐๐๐ = 0.17 ๐ฅ ๐โ๐ 119,452,840.3
๐๐๐๐๐๐๐๐๐๐โฒ๐๐๐๐ = ๐ท๐๐ ๐๐๐๐๐๐๐๐.๐๐ Contingency
The scope of the contingency comprises the estimation of the project cost in recognition of the fact that unexpected events and expenses that inevitably increase the cost of the project might arise during the erection of the plant. Inevitable events
such as storm, flood, transportation accidents, strikes, price changes, errors of the estimation, and unforeseen expenses may occur.
Basis: 37% of the purchase equipment delivered is the contingency.
๐๐๐๐ก๐๐๐๐๐๐๐ฆ = 0.37(๐๐ข๐๐โ๐๐ ๐ ๐๐๐ข๐๐๐๐๐๐ก ๐๐๐๐๐ฃ๐๐๐๐)
๐๐๐๐ก๐๐๐๐๐๐๐ฆ = 0.37 ๐ฅ ๐โ๐ 119,452,840.3
๐๐๐๐๐๐๐๐๐๐๐ = ๐ท๐๐ ๐๐๐๐๐๐๐๐.๐๐
Total Indirect Plant Cost:
๐ท๐๐ = ๐๐๐๐๐๐๐๐๐
RAW MATERIALS
Anyhdrous Liquid Ammonia
๐ถ = (2528.45 ๐๐
๐๐๐ฆ๐ฅ
1 ๐๐๐ฆ
24 โ๐๐ ) ๐ฅ 2400 โ๐๐ ๐ฅ
โฑ 43.51
๐๐= โฑ ๐๐,๐๐๐,๐๐๐.๐๐
Nitric Acid (55 % solution)
๐ถ = (13629.32 ๐๐
๐๐๐ฆ๐ฅ
1 ๐๐๐ฆ
24 โ๐๐ ) ๐ฅ 2400 โ๐๐ ๐ฅ
โฑ 5.50
๐๐= โฑ ๐,๐๐๐,๐๐๐
Dolomite
Technological Institute of the Philippines
๐ถ = (431.1092 ๐๐
๐๐๐ฆ๐ฅ
1 ๐๐๐ฆ
24 โ๐๐ ) ๐ฅ 2400 โ๐๐ ๐ฅ
โฑ2.07
๐๐= โฑ ๐๐,๐๐๐.๐๐
Total Raw Materials Cost = 18,586,651.55
๐น๐๐ฅ๐๐ ๐ถ๐๐๐๐ก๐๐ ๐ถ๐๐ ๐ก๐ = ๐ท๐๐๐๐๐ก ๐ถ๐๐ ๐ก + ๐ผ๐๐๐๐๐๐๐ก ๐ถ๐๐ ๐ก ๐โ๐ = 174452504.8 + 155288784
๐ญ๐ช๐ช = โฑ๐๐๐๐๐๐๐๐๐.๐
๐๐๐ก๐๐ ๐ถ๐๐๐๐ก๐๐ ๐ถ๐๐ ๐ก = ๐น๐๐ฅ๐๐ ๐ถ๐๐๐๐ก๐๐ + ๐๐๐๐๐๐๐ ๐ถ๐๐๐๐ก๐๐
= 329741288.8 +18,586,651.55
๐ป๐ช๐ช = โฑ ๐๐๐๐๐๐๐๐๐.๐