Page 1: Financing energy projects in Serbia

karanovic/nikolic

Financing of Renewable

Energy Projects in Serbia

September 2013 / Petar Mitrović

Page 2: Financing energy projects in Serbia

karanovic/nikolic

2

The Firm

Financing of Renewable Energy Projects in Serbia

Key facts— Staff over 100 and 80 lawyers— Integrated service over 12 practice

areas— 6 Offices, 5 Countries

Page 3: Financing energy projects in Serbia

karanovic/nikolic

3

Serbia: Financing of RES Projects

Financing of Renewable Energy Projects in Serbia

Page 4: Financing energy projects in Serbia

karanovic/nikolic

4

Serbia – Potential

64%

16%

12%

4% 4%

BiomassHydropotentialSolar energyWind energy Geothermal energy

Potential: 6 Mtoe annuallyUsed: 33%

Financing of Renewable Energy Projects in Serbia

Page 5: Financing energy projects in Serbia

karanovic/nikolic

5

Financing of RES Projects – Factors to consider

Government Support

Market Economics

Project Economics

Security

Reliability of a Sponsor

Government Support

Financing of Renewable Energy Projects in Serbia

Page 6: Financing energy projects in Serbia

karanovic/nikolic

6

Financing of RES Projects – Government support

▬ PPA for 12 years with Public Supplier / fixed prices

▬ Guaranteed take-off after 12 years / market prices▬ Priority in access to the grid▬ Exemption from balancing costs▬ Guarantees of origin

Financing of Renewable Energy Projects in Serbia

Page 7: Financing energy projects in Serbia

karanovic/nikolic

7

Financing of RES Projects – Obstacles

▬ Overall cap for wind (500 MW) and sun (10MW) power plants

▬ Lack of bankable PPA model

▬ Underdeveloped grid

Financing of Renewable Energy Projects in Serbia

Page 8: Financing energy projects in Serbia

karanovic/nikolic

8

Financing of RES Projects – PPA

▬ Key asset and collateral — With state owned entity – Public Supplier— Preliminary (for wind/solar projects) and final (far all)— Preliminary – construction permit / Final – finalization of

the project

New PPA models adopted in July 2013

Financing of Renewable Energy Projects in Serbia

Page 9: Financing energy projects in Serbia

karanovic/nikolic

9

Financing of RES Projects – PPA Main Concerns of Financiers

▬ Deadlines (construction and commencement of operations)

▬ Transition between preliminary and final PPA

▬ Grid connection and curtailment

▬ Rights and obligations in the commissioning period

Financing of Renewable Energy Projects in Serbia

▬ Assignment and step-in rights 444444444444444444

▬ No cure periods before termination

▬ No adequate protection against change in law

▬ Dispute resolution mechanism

Page 10: Financing energy projects in Serbia

karanovic/nikolic

10

Financing of RES Projects –Necessary steps

▬ Amendments to the Energy Law and separate law on renewables

▬ New PPA Model▬ Simplification of the permitting procedure /

Ministry of Energy “one-stop shop”

Financing of Renewable Energy Projects in Serbia

Page 11: Financing energy projects in Serbia

karanovic/nikolic

11

Our Team

Miloš VučkovićSENIOR PARTNER

Stevan DimitrijevićPARTNER

Petar MitrovićASSOCIATE

[email protected]

Resavska 2311000 BelgradeSerbiaT + 381 11 3094 200F + 381 11 3094 223

[email protected]

Gundulićeva 478000 Banja LukaRepublic of SrpskaBosnia and HerzegovinaT + 387 51 250 001F + 387 51 250 005

[email protected]

Resavska 2311000 BelgradeSerbiaT + 381 11 3094 266F + 381 11 3094 223

Financing of Renewable Energy Projects in Serbia

Page 12: Financing energy projects in Serbia

karanovic/nikolic

Thank you