Financing Essentials for Public-Private Partnerships Financing Essentials for Public-Private Partnerships United Nations SU/SSC Training Course United Nations SU/SSC Training Course
September 19, 2006September 19, 2006
2
Financing of Private Public Projects
Role of Financial Counterparty
Funding Resource Professional ExpertiseProject Oversight and Monitoring
Objectives of the Financial Counterparty
Policy Goals and Objectives Proper Risk- Reward Relationship Market Rates of Return
Financial Social
3
Financing of Private Public ProjectsUniverse of Financial Counterparties
Commercial BanksInvestment Banks Multilateral OrganizationsDevelopment Banks Non-Profit OrganizationsLocal, Provincial and National GovernmentsMultinational Development Companies Pension and Investment Funds Infrastructure Equity Funds
Sources of Funding DebtEquity Quasi - Equity
4
Financing of Private Public ProjectsDebt
Bank Loans Bond Offerings Domestic or International Public Markets Local or Foreign Currency Denomination Senior/Mezzanine/Subordinated Debt
EquityInitial Funding Long Term Investment Change of Control Provisions/Replacement StandardsReturn Expectations Ongoing Financial Support
5
Financing of Private Public Projects
Quasi-Equity Cash ContributionsGrants SubsidiesSupport AgreementsGuarantees Certain Forms of Debt
6
Application of Funds
Direct Project CostsDevelopment Costs DesignSite Acquisition Construction Equipment/Rolling Stock
7
Application of Funds
Finance Costs Capitalized Interest Reserve Funds
Debt Service ReserveMaintenance ReserveWorking Capital Reserve
Transaction Costs Structuring Fees Commitment Fees Legal Fees Credit Enhancement FeesFinancial Advisory Fees
8
Project Risk AssessmentType of Project
Greenfield v. Brownfield SectorService AreaMature or Developing Market
Project Evaluation and Economics Project Need Sources and Uses of FundsMarket Analysis
Project Rationale Competition Pricing StructureMarket Competitiveness
9
Project Risk Assessment
Project Financial Forecasts and Sensitivity AnalysesDevelopment of Key AssumptionsIdentification of Sensitivities Analysis of Sensitized Cashflows
Revenue ShortfallsConstruction CostsInterest RatesInflationCurrency Fluctuation
10
Legal and Environmental Requirements
Legislation/Regulation/Tax PolicyContract Law Public Private PartnershipsEnvironmental Land Use Other
Project Documentation Concession Agreement Construction Contract Operations and Maintenance Contract Supply or Off-take Contracts
11
Legal and Environmental Requirements
Concession Agreement Term of the Concession Revenue Tail Allocation of Risk Termination ProvisionsPayment Mechanism Deduction Regime Lenders’ RightsInsurance Provisions
12
Legal and Environmental Requirements
Construction Contract Fixed Price/Date CertainTypes of Technology/Track RecordWarranties and Guarantees Construction Performance SupportLiability CapLiquidated Damages Lenders’ RightsRole of Technical Advisor/Scope of ServicesContingency Levels
13
Legal and Environmental Requirements
Operations and Maintenance Contract Scope of Services/ComplexityDurationPrice/Payment Pass Through of DeductionsBenchmarking and Market Testing ProvisionsOperations Performance Support
14
Legal and Environmental Requirements
Supply and Off-take Arrangements DurationTerms Price Price Adjustment Mechanisms
Financial Documentation Bond Indenture/Loan AgreementIntercreditor AgreementLenders’ Direct Agreements
15
Evaluation of Main Project Parties
BorrowerShareholders Construction Contractor and SubcontractorsService Operator(s)Multilateral AgenciesLocal Authorities Other Public Sector Counterparties Suppliers Off-takers Co-LendersAdvisors
16
Project Security
Forms of Security Revenue Pledges MortgagesLiens on or Assignment of Various Assets GuaranteesLetters of CreditImplicit/Explicit Public Sector Support
17
Project Security
Reserve FundsTypes of Reserves
Maintenance ReserveOperating Reserves Dividend Reserves Others
Funding Requirements Amounts/Sizing TimingReplenishmentSource of Funding Release Tests/Dates
18
Risk Evaluation
Design and Construction Risk
Operating Risk
Commercial Risk Sufficient Demand Pricing Levels AffordabilityCollection
Regulatory Risk
19
Risk Evaluation
Macroeconomic and Sovereign Risk
Legal Risks
Financing RiskDebt StructureTermination/PrepaymentsForeign Exchange/Currency
Market Risks Interest Rate Inflation Sensitivities Currency Volatility
20
The Decision
Evaluation of the Risks and Mitigants
Identification of the Strengths and Weaknesses of the Transaction
Risk v. Reward Analysis
Decision ProcessesGovernmental Investment Banks Commercial Banks Multinational OrganizationsEquity Investors
21
Business Terms
Security Package Construction Support Package Operator Support Package
Gearing Requirements Drawdown ScheduleTerm of the FinancingFlow of FundsRepresentations and WarrantiesConditions Precedent
22
Business Terms
Financial Covenants Interest Coverage RatiosDebt Service Coverage Ratios (historical and
projected) Loan Loss Coverage Ratio
Dividend Payout RestrictionsEvents of Default/RemediesCredit Ratings Derivative Products
23
After Financial Close
Drawdown Process and Procedures Interest Rate Resets and RolloversRepayments and PrepaymentsPortfolio Review and Monitoring
Construction Monitor Monthly/Quarterly/Annual Financial Reporting Lifecycle CostsCovenant ComplianceInsurance Advisor
Waivers/Consents/Amendments