fixed electrical wiring inspection and test report · pdf filefixed electrical wiring...
TRANSCRIPT
FIXED ELECTRICAL WIRINGINSPECTION AND TEST REPORT
Brunswick Park Health Centre
London
F.A.O. Mr R Pegrum
Bureau Veritas Inspection Ltd
1 Summary & Conclusions.
2 Extent of the Electrical Installation Covered by This Report.
3 NICEIC Certificate.
4 DB Summary.
5 Test Results.
6 Defects and Comments.
7. Rectification List.
CONTENTS
Brunswick Park Health Centre - London Page 2 of 24
Bureau Veritas Inspection Ltd
Company Tested : Brunswick Park Health Centre
Town : London
Site Code :
Date of inspection : 23rd February 2008
Next inspection due : 23rd February 2013
Quantity of distribution boards inspected : 7
Status of report : Unsatisfactory P
TRectify all priority 1 faults T
Type of Test Instrument Instrument IDEarth Loop Impedance Set 202Insulation Continuity Tester 1/394
RECOMMENDATIONS
confirms that the remedial work has been correctly completed.Therefore once necessary remedial work has been completed we will be pleased to provide a quotation to re-test the relevant parts, and subject to the results of those tests, we can issue a satisfactory certificate.Provided these retests are completed with 6 months of the Inspection date.
SUMMARY
Test Instrument Details
CONCLUSIONS
Due to the extended period between Periodic inspections, it is recommended that you carry out interim inspections
Detailed electrical testing and inspection has been performed on your electrical installation as required by the 'Electricity at Work Regulations 1989'. The Specification of the work is detailed at the beginning of this report.
The purpose of the testing is to identify faults and non-compliance within the installation and to notify you of such so that potential danger can be removed.
The faults found have all been categorised either 1, 2, 3 or 4 as required by the NICEIC (National Inspection Council for Electrical Installation Contracting), with priority 1 faults being the most urgent.
To achieve satisfactory status for this installation you are required toOn completion of the necessary remedial works the certificate can be considered as satisfactory and does notneed to be replaced. However, it is often desirable to see a certificate marked 'satisfactory' as it clearly
The NICEIC also require that any installation where one or more priority 1 faults are identified, must be classified as unsatisfactory. In addition, where there are a significant number of priority 2 faults, this too can constitute an unsatisfactory installation.
which are included in the BS7671 Guidance Note Number 3. These interim inspections vary in their content and we would be more than happy to discuss your individual requirements with you.We would be pleased to discuss your requirements at any time by calling us on 01279 634000.
Brunswick Park Health Centre - London Page 3 of 24
Bureau Veritas Inspection Ltd
Priority Test Ref Site Ref Risk
1 DB01 N/A 19
2 DB02 Storage Heating 6
3 DB03 Storage Heating 6
4 DB04 Storage Heating 6
5 DB05 Storage Heating 4
6 DB06 Storage Heating 4
7 DB07 Storage Heating 4
8
9
10
Distribution Board Top Ten Risk Rating
Location
Main Intake Cupboard
Main Intake Cupboard
Main Intake Cupboard
Main Intake Cupboard
Please refer to the Defects and Comments section in this report for full details of all Priority 1 faults.
The above graph indicates the top ten fuse boards, in terms of level of risk at the specific board, However it is important to note that there may be boards that have low risk factors but contain priority 1 faults (which indicate immidiate danger exists).
It is important to ensure all Priority 1 faults are rectifed before using this risk assesment as a means to allocate resources and actions.
Main Intake Cupboard
Main Intake Cupboard
Main Intake Cupboard
19
6
6
6
4
4
4
0 10 20 30 40 50
DB01DB02DB03DB04DB05DB06DB07
Brunswick Park Health Centre - London Page 4 of 24
Bureau Veritas Inspection Ltd
Qty %Bonding 1 2.6Control Panel 0 0.0Distribution Board 24 61.5Fixed 4 10.3General 6 15.4Lighting 0 0.0RCD 0 0.0Sockets 4 10.3Sub Mains 0 0.0Total 39 100
Qty %Test Results 3 7.7Visual 36 92.3Earth 0 0.0Total 39 100.0
Description
The chart above shows how the faults were found, it is normal for most faults to be identified visually. This is due to the extensive knowledge and experience of the inspecting engineers who can identify faults in this non intrusive nature. The level of faults found within “Earthing” is always a key indictor to the safety of the installation, as all fuses and protective devises in your installation rely upon the presence of a good earth path.
Percentage of Faults by Type
Percentage of Faults by Category
The chart above shows the breakdown of the faults into the various sections of your installation. This highlights if any particular areas of your installation are in a poor condition and may need special attention.
Description
2.6
61.510.3
15.4
10.3BondingControl PanelDistribution BoardFixedGeneralLightingRCDSocketsSub Mains
7.7
92.3
Test ResultsVisualEarth
Brunswick Park Health Centre - London Page 5 of 24
Bureau Veritas Inspection Ltd
1
(a)(b)(c)(d)(e)(f)(g)(h)
1.1
(a)(b)(c)(d)
2
(a)
(b)
Random sample inspection to verify integrity of same, e.g. signs of overheating etc.A random 10% in total internal inspection of socket outlets, switching devices and luminaries.
Wear and tear.Corrosion.
Conductors (Including Protective Conductors)
Electric burn.Fires of electrical origin.
External influences.Suitability.
To supplement the visual inspection with such electrical testing as considered necessary for protection against:
Electric shock from direct or indirect contact.
Verify suitability, condition and means of identification etc.A random 10% in total internal inspection of socket outlets, switching devices and luminaries.
EXTENT OF THE ELECTRICAL INSTALLATION COVERED BY THIS REPORT
A 100% visual inspection of the fixed electrical installation, including an internal inspection of distribution boards has been carried out where practicable to include the following:
VISUAL INSPECTION
Joints and Connections
Electrical arcing or explosions initiated or caused by electricity.
Damage.Excessive loading (overloading).Age.
A thorough visual inspection of the electrical installation has been carried out where practicable with regard to the following:
Safety.
Brunswick Park Health Centre - London Page 6 of 24
Bureau Veritas Inspection Ltd
(c)
(d)
(e)
(f)
(g)
(h)
3
3.1
(a)(b)(c)(d)(e)
Verify suitability and integrity of enclosures for mechanical protection of electrical apparatus and equipment.
Installed machinery/fixed equipment
Exposed conductive parts on installed machinery/fixed equipment.
Verify suitability and condition.
Switching Devices
Continuity testing of protective conductors includes: -
Earthing conductors.
Verify presence, accessibility, labelling and condition of devices for electrical protection, isolation and switching.
Protection Devices
Enclosures and Mechanical Protection
Carry out a random 10% internal inspection.
Fuses, circuit breakers etc., to be checked for correct type and rating, if reasonably practicable.
Main Equipotential Bonding Conductors.Supplementary Bonding Conductors.All circuit protective conductors (sample lighting circuits).
TESTING SCHEDULE
Verify suitability and condition.
Verify presence of fire barriers etc., if reasonably practicable.
Flexible Cables and Cords
Protection against Thermal Effects
An external visual inspection for electrical safety, excluding all control and operational functions.
Brunswick Park Health Centre - London Page 7 of 24
Bureau Veritas Inspection Ltd
3.2
(a)(b)(c)
(d)
(e)
(f)
3.3
(a)(b)(c)
(d)
3.4
3.5
3.6
Earth loop impedance tests have been carried out at the locations indicated below: -
Earth loop impedance
At the origin and at each distribution board.
Operation of Residual Current Devices (RCD’s)
All socket outlets.Any location which is exposed to exceptional damage or deterioration or represents a special hazard.Whilst 100% of fixed equipment are tested for Earth Continuity, a further 10% sample will be checked for Earth Loop Impedance.
Operating devices for isolation and switching
100% of socket outlets will be checked to ensure conductors are correctly connected and a 10% random sample of other accessories/equipment.
Single pole control and protective devices are connected in the phase conductors only. (10% random sample to be taken).Centre contacts of Edison screw type lamp holders have correct connections (10% random sample to be taken).Multi-pole devices are correctly installed (10% random sample to by taken).
Polarity Testing
The Polarity has been checked at the meter position.100% distribution boards where practicable.
These have been checked for effectiveness and to ensure adequate and correct labelling.
100% of RCD’s have been tested for tripping time at half rated, full rated and five times rated tripping current across positive and negative cycles, where practicable.
Prospective fault current
Tests have been carried out at the origin and at each distribution board.
Brunswick Park Health Centre - London Page 8 of 24
Bureau Veritas Inspection Ltd
3.7
4
4.1
4.2
4.3
5
(a)(b)(c)(d)
(e)(f)(g)(h)(i)
Fire, security and door entry systems.Data/telecommunication systems.Heating and ventilation equipment and controls.
Lift installations.Potentially explosive atmosphere installations, which are subject to local licensing authority requirements.High level parts of the fixed installation, as detailed in GN3 table 3.3 note H.V. Power Systems i.e. in excess of 1000 volts ac.
Unless otherwise requested, the following specialist areas will be subject to separate contracts and will not therefore form part of the inspection and test.
Emergency lighting systems.Lightning protection systems.
Cables concealed within trunking and conduits, or cables and conduits concealed under floors, in inaccessible roof spaces and generally within the fabric of the building or underground, have not been visually inspected.
Insulation resistance tests have not be carried out on circuits and/or sections of the installation, which contain electronic or similar sensitive circuitry.
LIMITATIONS
The inspection and testing has been carried out where practicable at the discretion of the Inspecting Engineer, taking into account availability and accessibility.
Insulation Resistance tests have been carried out at the discretion of the inspecting engineer with due regards to age, condition and visual inspection, up to 10% of the circuits.
From the results of the sample insulation resistance testing, if an unacceptable high failure rate is found further testing will be recommended.
Insulation Resistance Testing
Brunswick Park Health Centre - London Page 9 of 24
Client
Domestic Industrial
Occupier
Address
Postcode
N/A
This inspection has been carried out in accordance with BS 7671:
INSPECTED AND TESTED BY:
Name Name
Position Position
Date Date
Work was carried out as far as was reasonably practical as laid out under regulation 731-01-02. Supply fuses(s) and their characteristics have not been verified. Unable to obtain Ze, Zs measured from nearest point of intake. DB01 - unable to verify all fuse sizes. Staff Toilet. Sockets for Comms equipment.
A. DETAILS OF CLIENT
2001 (IEE Wiring Regulations), amended to
N/A E.I.C or previous P.I.R Number:
D. EXTENT OF THE INSTALLATION AND LIMITATIONS OF THE INSPECTION
D TOMPKINS
ELECTRICAL INSPECTOR QUALIFYING MANAGER
18th March 2008 18th March 2008
Signature Signature
D BROWN
The schedules of circuit details and associated test results (see H), and my/our observations (see F), are accurate assessments of the condition of the
electrical installation (see C), within the stated extent of the installation and limitations of the inspection (see D).
I further confirm that in my/our judgement the installation is overall in an unsatisfactory condition (see I).
Cable concealed within trunking or conduits, or cables and conduits concealed under floors, in roof spaces and generally within the fabric of the building
or underground have not been inspected.
E. DECLARATION To the best of my/our knowledge and belief I/we confirm that the details recorded in this report, including the attached schedules of inspection and testing,
No. 2 : 2004
HA1164151
Extent of the installation covered by this report:See section two of this report for details of the extent of the test and inspection.
Limitations:
Installation records available: Records held by: N/A
Date of last inspection: N/A
N11 1EY If yes, estimated age Misc years
Evidence of alterations or additions
London Estimated age of installation 30 years
Brunswick Park Other Please State
London Road
C. DETAILS OF THE INSTALLATIONCommercial
Brunswick Park Health CentreDescription of Premises
B. PURPOSE OF REPORT
Purpose for which the report is required Periodic Inspection of the Installation
Edgware HA8 OAD
This form is based on the recommendations of Appendix 6 of BS 7671: 2001
CERTIFICATE REFERENCE:
PERIODIC INSPECTION REPORT FOR AN ELECTRICAL INSTALLATION(REQUIREMENTS FOR ELECTRICAL INSTALLATIONS - BS 7671 [IEE WIRING REGULATIONS])
Barnet Primary Care Edgware HospitalAddress Burnt Oak Broadway
Page 10 of 24
Item No Code #
This form is based on the recommendations of Appendix 6 of BS 7671: 2001
HA1164151
General condition of the installation:See Report,
Date(s) of inspection: 23rd February 2008 Overall assessment of the
installation: Unsatisfactory
Urgent remedial work recommended for items: Corrective action recommended for items:
G. SUMMARY OF THE INSPECTION
amended to No 2: 2004 (This does not imply that the electrical installation
inspected is unsafe).
1. 'requires urgent attention'2. 'requires improvement'3. 'requires further investigation'4. 'does not comply with BS 7671: 2001
# Where observations are made, one of the following codes is to be entered against each one to indicate the action (if any) recommended:-
FOR MORE DETAILED RECOMMENDATIONS SEE ENCLOSED
REPORT
orThe following observations and recommendations are made.
CERTIFICATE REFERENCE:
F. OBSERVATIONS AND RECOMMENDATIONS Referring to the attached schedule(s) of the inspection and test results, and subject to the limitations specified at D.
There are no items adversely affecting electrical safety.
Page 11 of 24
TN-S a.c. d.c. 400 V Uo (1) 230 V
TN-C-S
1-phase (2 wire)
1-phase (3 wire)
2 Pole 50 Hz
TN-C
2-phase (3 wire) 3 Pole 2.84 kA N/A A
TT 3-phase (3 wire)
3-phase (4 wire) Other 0.14 Ω N/A kA
IT Other 1
(Ω)
Amps per phase
500 V
60 AConductor material
Gas services N/A
N/A mA 16 mm² C.S.A Structural steel
N/A
mm² N/A msContinuity check N/A
Other incoming services
N/A
CM19 5QAPostcode:
Conductor material
Copper
Maximum Demand
Earthing conductor
Main Protective Conductors
N/A
Equipotential bonding conductors
Water services
130 Sandringham AvenueHarlow Business ParkHarlow Essex
N/A
Extraneous conductive parts bonded
mm²
K. SUPPLY CHARACTERISTICS AND EARTHING ARRANGEMENTS
C.S.A
Continuity check
N/A
Lightning protection
X
N/ACopper
Method of protection against indirect contact
EEBADS
Oil Services
Supply conductor CSA 35
Voltage rating
Current rating, In
RCD operating current, I ∆n
RCD operating time (at I ∆n)
No of Poles
Supply conductor material
3
Type: BS(EN)
60947-2
Main Switch or Circuit-Breaker(applicable only where an RCD is suitable and is used as a main
circuit-breaker)
J. CONTRACTOR DETAILS
H. SCHEDULES
I. NEXT INSPECTION
L. PARTICULARS OF INSTALLATION AT THE ORIGIN
I/We recommend that this installation is further inspected and tested after an interval of not more than
Nature of Supply Parameters
Notes:(1) by enquiry.
Nominal voltage(s) U(1)
Nominal frequency f (1)
Installation earth electrode:
Means of Earthing
Type of earth (e.g. rod(s), tape etc):
Electrode resistance, RA:
Suppliers facility:
Details of Installation Earth Electrode (where applicable)
Method of measurement:
Location:
Tick boxes and enter details, as appropriate
Tick boxes and enter details, as appropriate
System
(3) where more than one supply, record the higher or highest records.
(4) by measurement.
Characteristics of Primary Supply Overcurrent Protection Device(s)
BS(EN) N/A
Type N/A
Nominal current rating
Short-circuit capacity
Number of sources
(2) by enquiry or by measurement.
Prospective fault current Ipf (2)(3)
External earth fault loop impedance Ze (3)(4)
Type of Live Conductors
Page No 4
Section 5
Branch No (If applicable) 000
Schedule of circuit details for the installation: Page(s) Schedule of test results for the installation: (Page(s)
(Enter interval in terms of weeks, months or weeks as appropriate)
Provided that any observation shown at F with a recommended code of 1 (requires urgent attention) are remedied without delay.
Items which have been attributed a recommendation code 2 or 3 should be actioned as soon as possible.
Years5
NIC-EIC Enrolment N0 23577
Fax number: 01279 634001
Trading Title: Bureau Veritas Inspection Limited
Address: Telephone number: 01279 634100Langlands House
Section 5
The schedules identified here form an essential part of this report, and this document is valid only if accompanied by the relevant schedules.
CERTIFICATE REFERENCE:
Schedule of items inspected and items tested: Additional pages including additional sources: N/A
HA1164151
Page 12 of 24
(i)
(ii)
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(i)
(ii)
(iii)
(iv)
(v)
N/A
Protection by separation of circuits.
Protection against direct contact, by barrier or enclosure provided during erection.
Insulation of non-conducting floors or walls.
Polarity.
Earth fault loop impedance.
Operation of residual current devices.
Functional testing of assemblies.
Continuity of ring final circuit conductors.
N/A
N/A
N/A
This form is based on the recommendations of Appendix 6 of BS 7671: 2001
CERTIFICATE REFERENCEHA1164151
N/A
Insulation resistance between live conductors.
Insulation resistance between live conductors and earth.
Site applied insulation.
Lim
N/A
Presence of RCD device(s).
SCHEDULE OF ITEMS TESTED (See Section 713 of BS 7671)
Earth-free equipotential bonding: Presence of earth-free equipotential bonding conductors.
Electrical separation.
Use of class II equipment or equivalent insulation.
Non-conducting location: Absence of protective conductors. bonding conductors.
External earth fault loop impedance, (Ze).
Installation earth electrode resistance, (Ra).N/A
Continuity of protective conductors.
N/A
N/A
Presence of main equipotential bonding conductor.
Presence of supplementary equipotential bonding conductors.
Presence of earthing arrangements for combined protective and functional purposes.Presence of adequate arrangements for alternative source(s), where applicable.
General
Presence of undervoltage protective devices.
Connection of single-pole devices for protection or switching in phase conductors only.
Correct connection of accessories and equipment.
Presence and correct location of appropriate devices for isolation and switching.
Selection of appropriate functional switching devices.
Choice of settings of protective and monitoring devices (for protection against indirect contact and/or overcurrent).Selection of equipment and protective measures appropriate to external influences.
N/A
Adequacy of access to switchgear and other equipment.
Particular measures for special installations and locations.
N/A
N/A
N/A
N/A
X
N/A
N/A
Selection of conductors for current carrying capacity and voltage drop.Presence of earthing conductor.
Presence of circuit protective conductor. Presence of fire barriers, suitable seals and protection against thermal effects.N/A
c. Protection against indirect contact:
Erection methods.EEBAD including:
Connection of conductors.
Routing of cables in prescribed zones or within mechanical protection.
Presence of diagrams, instructions, circuit charts and similar information.
Presence of danger notices and other warning notices.
Labelling of protective devices, switches and terminals.
Identification of conductors.
Identification
Cables and Conductors
Placing out of reach.
PELV
X
X
X
X
Presence of RCD for supplementary protection.
N/A
N/A
N/A
N/A
a. Proximity of non-electrical services and other influences.
b. Segregation of Band I and Band II cables or Band II insulation used.
c. Segregation of safety circuits.
Insulation of live parts.
b. Protection against direct contact:
X Barriers or enclosures.
N/A Obstacles.
N/A Limitation of discharge of energy.
M. SCHEDULE OF ITEMS INSPECTED (See Section 712 of BS 7671)
N/A
Method of protection against electric shock
a. Protection against both direct and indirect contact:
Prevention of detrimental influence
N/A
SELV.N/A
Page 13 of 24
CERTIFICATE REFERENCE
V
Overcurrent protective device at supply to this Distribution Board
A I ∆n mA
HA1164151
Max
imum
pe
rmi tt
ed Z
s
DISTRIBUTION BOARD DETAILS
Location:
Associated RCD
Overcurrent Protective Devices RCD
Max
imum
pe
rmitt
ed
disc
onne
ctio
n tim
e
CIRCUIT DETAILS
RCD No of poles:
Type: (BS EN)
DB Number Rating:
Num
ber o
f poi
nts
serv
ed
Circ
uit n
umbe
r and
ph
ase
Circuit designation
Type
of w
iring
(see
co
de b
elow
)
Circuit conductors
Ref
eren
ce M
etho
d
Voltage:
SCHEDULE OF CIRCUIT DETAILS FOR THE INSTALLATION
No of phases:
Supplied from:
O (other please state)CODES FOR TYPE OF WIRING
A B C D G H
XLPE/SWA cables
Mineral insulated cables
This form is based on the recommendations of Appendix 6 of BS 7671: 2001
PVC/PVC cables
PVC cables in metallic
conduit
PVC cables in non-metallic conduit
PVC cables in metal trunking
PVC cables in non-metallic trunking
PVC/SWA cabs
E F
ALL FINAL CIRCUIT TEST RESULTS ARE DETAILED IN THE CIRCUIT TEST RESULT
SECTION
Max
imum
pe
rmi tt
ed Z
s
(Ω)
Sho
rt ci
rcui
t ca
paci
ty
(kA)
Overcurrent Protective Devices RCD
Max
imum
pe
rmitt
ed
disc
onne
ctio
n tim
e
Ope
ratin
g cu
rren
t I∆n
(mA)
BS(EN) & Type No
Type
No
Rat
ing
(A)(S)Num
ber o
f poi
nts
serv
ed
Live (mm²)
opc (mm²)
Circ
uit n
umbe
r and
ph
ase
Circuit designation
Type
of w
iring
(see
co
de b
elow
)
Circuit conductors
Ref
eren
ce M
etho
d
Page 14 of 24
Zs Ω ms
Ipf kA msat 5I∆n
SOURCE DETAILS
Operating times of associated RCD (if any)
at I ∆n
Only record if not connected directly at the origin of the installation.
SCHEDULE OF CIRCUIT DETAILS FOR THE INSTALLATION
CERTIFICATE REFERENCEHA1164151
Circuit impedances
Phase / Phase
(MΩ)
Insulation resistance (record lowest or lowest value
r2
(cpc)
Ring final circuits only (Ω)
r1 + r2
Phase(s) / Neutral
Circ
uit n
umbe
r and
ph
ase Phase(s) /
EarthNeutral /
Earth
(MΩ) (MΩ) (MΩ)r1
(Phase)rn
(Neutral)r2
All circuits (Ω)Polarity
(√)
TEST RESULTSMaximum measured earth fault
loop impedance
(Ω)
at I ∆n at 5I∆n
(ms) (ms)
RCD operating times
This form is based on the recommendations of Appendix 6 of BS 7671: 2001
PVC/PVC cables
PVC cables in metallic conduit
PVC cables in non-metallic
conduit
PVC cables in metal trunking
PVC cables in non-metallic trunking
PVC/SWA cab
E FCODES FOR TYPE OF WIRING
G H
XLPE/SWA
cables
Mineral insulated cables
O (other please state)A B C D
TEST INSTRUMENTS (Serial Numbers) USED
ALL FINAL CIRCUIT TEST RESULTS ARE DETAILED IN THE CIRCUIT TEST RESULT
SECTION
Earth fault loop impedance RCD
Insulation resistance
Continuity
Other
Other
Page 15 of 24
Bureau Veritas Inspection Ltd DB SUMMARY
Test Ref Site Ref Location Zs PSCC/IF No of Ways
No of Ways in
use
Circuit Protection
TypeType of DB
DB01 N/A Main Intake Cupboard 0.14 2840 21 20 BS88 MEM
DB02 Storage Heating Main Intake Cupboard N/A N/A 4 3 BS1361 Wylex
DB03 Storage Heating Main Intake Cupboard N/A N/A 4 3 BS1361 Wylex
DB04 Storage Heating Main Intake Cupboard N/A N/A 4 3 BS1361 Wylex
DB05 Storage Heating Main Intake Cupboard 0.16 1330 4 3 BS1361 Wylex
DB06 Storage Heating Main Intake Cupboard 0.18 1200 4 3 BS1361 Wylex
DB07 Storage Heating Main Intake Cupboard 0.16 1380 4 3 BS1361 Wylex
Brunswick Park Health Centre - London Page 16 of 24
Bureau Veritas Inspection Ltd TEST RESULTS
No Type P/N CPC
Type Ref
Rating (in)
Phase
Neutral
CPC
P-E
P-N
P-P
E-N
DB01 Main Intake Cupboard B2 Rad 4.0 Sheath N/A H Sockets Doctor Sarah Cowley 80 0.4 BS88 30 999 999 0.31 1.09 1
DB01 Main Intake Cupboard B4 Rad 1.5 1.5 N/A B Lights Doctor Sarah Cowley 80 5 BS88 6 999 1.05 14.1 3
DB04 Main Intake Cupboard 2 Rad 2.5 1.5 N/A A Storage Heater Waiting Room 40 5 BS1361 15 999 999 0.39 4.36 3
DB04 Main Intake Cupboard 3 Rad 2.5 1.5 N/A A Storage Heater Doctor Sarah Cowley Room 40 5 BS1361 15 999 999 0.42 4.36 3
DB05 Main Intake Cupboard 3 Rad 2.5 1.5 N/A A Storage Heater Waiting Room 40 5 BS1361 15 999 999 0.40 4.36 3
DB07 Main Intake Cupboard 1 Rad 2.5 1.5 N/A A Storage Heater Waiting Room 40 5 BS1361 15 999 999 0.35 4.36 3
DB Num
Circuit Cable Size (mm2)MCB TypeLocation Cable
Type Destination of Circuit
K Factor M
R
ating
Design
Disconnection
Time (S)
Overcurrent Device Type Continuity of Conductors Ω Insulation Resistance (MΩ )
Zs Ω
R1 R
eading
Ref M
ethod
Polarity
Test Ref
Ring Circuit R2 R
eading
Max Zs Ω
Brunswick Park Health Centre - London Page 17 of 24
Bureau Veritas Inspection Ltd
1
2
3
4
BCPDB
FGL
RCDS
SMSW
Every fault listed in this section has a test reference to enable easy location and rectification on site by electrical personnel. The first part is alpha and the key below indicates what type of equipment the fault has been found on, the second part is numeric and indicates the Bureau
Veritas unique fault reference that is on the Bureau Veritas label attached to the asset. e.g. DB8 indicates a fault found on Distribution Board labelled as Number 8.
DEFECTS & COMMENTS
Further investigation.
Does not comply with current IEE Wiring Regulations. (This does not necessarily imply that the electrical installation inspected is unsafe.)
The following fault reports detail all defects and non compliances that were identified during the inspection and test.
Each defect has been identified with a priority from 1 to 4.
Requires urgent attention.
Requires improvement.
Key
BondingControl PanelDistribution BoardFixed Appliances
Sub MainsSwitching Devices
GeneralLightingResidual Current DevicesSockets
Brunswick Park Health Centre - London Page 18 of 24
Bureau Veritas Inspection Ltd DEFECTS COMMENTS
Test Ref Location Fault Recommended Action Regulation Priority
S04 CMO Socket poorly mounted to wall. Refit with suitable fixings. 133-01-01 2
S02 Corridor by Doctor Stella Okonkwo Room Socket poorly mounted to wall. Refit with suitable fixings. 133-01-01 2
F04 Disabled Toilet Water Heater No strain relief for cable from isolator to machine. Provide adequate support for cable. 522-08-05 2
F03 Doctor G Duru Room Water Heater No means of local isolation.Install local isolator or ensure that remote point of isolation is
fitted with a lock off device. 460-01-01 2
F02 Doctor Stella Okonkwo Room Water Heater Excessive cable with no support to machine. Reterminate cable and provide support. 522-08-04 2
S01 Eye Clinic Waiting Room Damaged faceplate. Replace faceplate. 412-03-03 2
B01 Front Lobby No Main equipotential bonding at water. Provide equipotential bonding. 413-02-02 1
DB01 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
DB01 Main Intake Cupboard Phase conductors not identified. Identify in relevant colour coding sleeving. 514-06-01 4
DB01 Main Intake Cupboard CPC conductors not identified. Sleeve green / yellow. 514-03-01 4
DB01 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
DB01 Main Intake Cupboard Blanks missing. Provide blanks. 412-03-01 2
DB01 Main Intake Cupboard Phase barriers missing. Replace barriers. 412-03-04 2
DB01 Main Intake Cupboard Insulation from fuse carriers missing. Replace insulation. 533-01-03 2
DB01 Main Intake CupboardProtective devices protecting multiple circuits in ways R7 &
Y2. Provide separate protection for each circuit. 314-01-04 4
Brunswick Park Health Centre - London Page 19 of 24
Bureau Veritas Inspection Ltd DEFECTS COMMENTS
Test Ref Location Fault Recommended Action Regulation Priority
DB01 Main Intake Cupboard Poor / insufficient lighting at distribution board. Provide adequate lighting. EAWR 1989 Reg 15 2
DB02 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
DB02 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
DB02 Main Intake Cupboard No power at time of test. Further investigation required. Good Practice 3
DB03 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
DB03 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
DB03 Main Intake Cupboard No power at time of test. Further investigation required. Good Practice 3
DB04 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
DB04 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
DB04 Main Intake Cupboard No power at time of test. Further investigation required. Good Practice 3
DB05 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
DB05 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
DB06 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
DB06 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
DB07 Main Intake Cupboard Schedule is incorrect. Provide complete schedule. 514-09-01 2
Brunswick Park Health Centre - London Page 20 of 24
Bureau Veritas Inspection Ltd DEFECTS COMMENTS
Test Ref Location Fault Recommended Action Regulation Priority
DB07 Main Intake Cupboard Neutrals not circuit identified in distribution board. Provide correct identification. 514-01-02 4
G01 Main Intake Cupboard Redundant equipment. Remove and make safe. Guidance Note 4 Sect 4.2 2
G02 Main Intake Cupboard Redundant cables. Remove and make safe. Guidance Note 4 Sect 4.2 2
G03 Main Intake Cupboard Trunking lids poorly fitted or missing. Refit and replace trunking lids. 521-05-01 2
G04 Main Intake Cupboard Riser cupboards / switch room used for general storage.Remove debris and provide access to switch gear at all
times. 131-12-01 2
G05 Main Intake Cupboard No 400V warning signs on 3-phase equipment. Provide warning labels. 514-10-01 4
G06 Main Intake Cupboard Poor support for cables. Provide adequate support. 522-08-04/5 2
F01 Practice Manager Water Heater No means of local isolation.Install local isolator or ensure that remote point of isolation is
fitted with a lock off device. 460-01-01 2
S03 Practice Nurse Doctor Damaged faceplate. Replace faceplate. 412-03-03 2
Brunswick Park Health Centre - London Page 21 of 24
Bureau Veritas Inspection Ltd Rectification List
Test Ref Location Fault Priority Remedial Work Carried out Date Initials
S04 CMO Socket poorly mounted to wall. 2
S02 Corridor by Doctor Stella Okonkwo Room Socket poorly mounted to wall. 2
F04 Disabled Toilet Water Heater No strain relief for cable from isolator to machine. 2
F03 Doctor G Duru Room Water Heater No means of local isolation. 2
F02 Doctor Stella Okonkwo Room Water Heater Excessive cable with no support to machine. 2
S01 Eye Clinic Waiting Room Damaged faceplate. 2
B01 Front Lobby No Main equipotential bonding at water. 1
DB01 Main Intake Cupboard Schedule is incorrect. 2
DB01 Main Intake Cupboard Phase conductors not identified. 4
DB01 Main Intake Cupboard CPC conductors not identified. 4
DB01 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
DB01 Main Intake Cupboard Blanks missing. 2
DB01 Main Intake Cupboard Phase barriers missing. 2
DB01 Main Intake Cupboard Insulation from fuse carriers missing. 2
DB01 Main Intake CupboardProtective devices protecting multiple circuits in ways R7 &
Y2. 4
Brunswick Park Health Centre - London Page 22 of 24
Bureau Veritas Inspection Ltd Rectification List
Test Ref Location Fault Priority Remedial Work Carried out Date Initials
DB01 Main Intake Cupboard Poor / insufficient lighting at distribution board. 2
DB02 Main Intake Cupboard Schedule is incorrect. 2
DB02 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
DB02 Main Intake Cupboard No power at time of test. 3
DB03 Main Intake Cupboard Schedule is incorrect. 2
DB03 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
DB03 Main Intake Cupboard No power at time of test. 3
DB04 Main Intake Cupboard Schedule is incorrect. 2
DB04 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
DB04 Main Intake Cupboard No power at time of test. 3
DB05 Main Intake Cupboard Schedule is incorrect. 2
DB05 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
DB06 Main Intake Cupboard Schedule is incorrect. 2
DB06 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
DB07 Main Intake Cupboard Schedule is incorrect. 2
Brunswick Park Health Centre - London Page 23 of 24
Bureau Veritas Inspection Ltd Rectification List
Test Ref Location Fault Priority Remedial Work Carried out Date Initials
DB07 Main Intake Cupboard Neutrals not circuit identified in distribution board. 4
G01 Main Intake Cupboard Redundant equipment. 2
G02 Main Intake Cupboard Redundant cables. 2
G03 Main Intake Cupboard Trunking lids poorly fitted or missing. 2
G04 Main Intake Cupboard Riser cupboards / switch room used for general storage. 2
G05 Main Intake Cupboard No 400V warning signs on 3-phase equipment. 4
G06 Main Intake Cupboard Poor support for cables. 2
F01 Practice Manager Water Heater No means of local isolation. 2
S03 Practice Nurse Doctor Damaged faceplate. 2
Brunswick Park Health Centre - London Page 24 of 24