Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013 FLAGSTAFF UNIFIED SCHOOL DISTRICT EDUCATIONAL TECHNOLOGY PLAN JULY 1, 2010 JUNE 30, 2013

Upload: others

Post on 13-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

FLAGSTAFF

UNIFIED SCHOOL DISTRICT

EDUCATIONAL TECHNOLOGY PLAN

JULY 1, 2010 – JUNE 30, 2013

Page 2: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

LEA PROFILE

LEA Profile

LEA NAME: Flagstaff Unified School District

CTDS: 03-02-01-000

NUMBER OF SCHOOLS IN LEA

19

E-RATE BILLED ENTITY NUMBER (if not applicable, indicate N/A)

143151 TECHNOLOGY PLAN CONTACT INFORMATION

Primary Technology Plan Contact Information Name: Mary Knight

Telephone #: 928-527-6120

Title: Director of Technology

Fax #: 928-527-6125

Address: 3285 E. Sparrow Ave.

Flagstaff, AZ 86004

E-mail: [email protected]

Secondary Technology Plan Contact Information Name: Ted Grudniewski

Telephone #: 928-527-2323

Title: Assistant Director of Technology

Fax #: 928-527-4202

Address: 3285 E. Sparrow Ave. Flagstaff, Az 86004

E-mail: [email protected]

Page 3: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

TECHNOLOGY COMMITTEE

The FUSD District Technology Committee meets monthly on the first Tuesday of each month. Minutes are recorded and posted at: www.tinyurl.com/fusddtcminutes

FUSD District Technology Committee

Member Title

(if applicable) Constituency Represented

Beth Sanborn Inclusion Specialist Mt Elden Middle

Claire Wendt LMS (Library Media Specialist) Cromer Elem.

Connie Chensky LMS DeMiguel Elem.

Cynthia Conn Title I Technology Teacher Thomas Elem.

Emily Knox LMS Christensen Elem.

Heather Zeigler Peer Coach Facilitator Technology Dept.

Jane Reukema LMS Kinsey Elem.

Jean Dunham LMS Flagstaff High

Jennifer Parker LMS Sinagua High

Jillian Worssam Teacher Project New Start

Joan Hughes LMS Puente de Hozho

Laurie Jeffers Teacher S Beaver Elem.

Mary Knight Director of Technology Technology Dept.

Mary Lara LMS Knoles Elem.

Maureen McCauley LMS Sechrist Elem.

Ted Grudniewski Asst. Director of Technology Technical Services

Patricia Roach Peer Coach Facilitator Technology Dept.

Virginia Brown LMS Flagstaff Middle

Linda Sutera LMS Coconino High

Russell Kasch Teacher Marshall Elem.

Sussie Macias LMS Killip Elem.

Brad Kamradt Instructional Tech. Coordinator Technology Dept.

Page 4: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

TECHNOLOGY VISION & MISSION Vision Statement “Members of the FUSD Community will have equitable access to technology within the school setting. Technology will be integrated into administrative and curricular areas in order to improve management, student achievement and professional development opportunities. Effective and appropriate use of technology will result in significant improvements in the quality of our educational system and community.” Mission Statement “Teachers, administrators, library media specialists and support personnel will work in concert to develop learning experiences that are infused with technology and incorporate the Arizona State Standard.” ISTE (International Society for Tech. in Education) Conditions for Successful Technology Learning Environments The FUSD District Technology Committee will utilize the ISTE Essential Conditions for Successful Technology Learning Environments to guide district technology initiatives. 1. Vision with support and proactive leadership from the educational system 2. Educators skilled in the use of technology for learning 3. Content standards and curriculum resources 4. Student centered approaches to learning 5. Assessment of the effectiveness of technology for learning 6. Access to contemporary technologies, software and telecommunications networks 7. Technical assistance for maintaining and using technology resources 8. Community partners who provide expertise, support, and real-life interactions 9. Ongoing financial support for sustained technology use 10. Policies and standards supporting new learning environments

Page 5: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

TECHNOLOGY PLAN TERM LEA Name: Begins: JULY 1, 2010 End: JUNE 30, 2013 CIPA CERTIFICATION (Schools or Districts who apply for E-Rate should check the first option below.) _X__ The LEA applies for E-Rate funds and are therefore not required to submit CIPA compliance under the ESEA to the Arizona Department of Education, but instead submit CIPA compliance certification directly through the E-Rate application. ____ Every “applicable school”1 has complied with the CIPA requirements in subpart 4 of Part D of Title II of the ESEA. ____ Not all “applicable schools”1 have yet complied with the requirements in subpart 4 of Part D of Title II of the ESEA. However, the LEA has received a one-year waiver from the U.S. Secretary of Education under section 2441(b) (2) (C) of the ESEA for those applicable schools not yet in compliance. ____ The CIPA requirements in the ESEA do not apply because no funds made available under the program are being used to purchase computers to access the Internet, or to pay for direct costs associated with accessing the Internet, for elementary and secondary schools that do not receive e-rate services under the Communications Act of 1934, as amended. 1(An “applicable school” is an elementary or secondary school that does not receive e-rate discounts and for which Ed Tech funds are used to purchase computers used to access the Internet, or to pay the direct costs associated with accessing the Internet) Technology plans will be submitted online through a web based application in the Common Logon, https://www.ade.az.gov/CommonLogon/logon.aspx, "ALEAT” (Arizona Local Education Agency Tracker.) The Arizona Department of Education (ADE) will review the technology plan for accuracy and compliance. Detailed records of all submissions (and accompanying documents) must be retained by the school district or charter school and made available for review or audit upon request.

LEA APPROVAL & SIGNATURE Date the plan was approved by the LEA governing board: 06/22/2010

OR

Date the plan will be submitted for board approval: xx/xx/xxxx Your signature below certifies that detailed records will be retained and made available for audit upon request. I certify that:

The information in the technology plan is true to the best of my knowledge, and has been created and written in accordance with Enhancing Education Through Technology Act of 2001, 20 U.S.C. and the Federal Communications Commission’s (FCC) Fifth Report and Order (FCC 04-190, released August 13, 2004) for those applying for E-rate. _______Flagstaff Unified School District____________________ ____03-02-01-000_________ School District/Charter School District/Charter CTDS Number _____________________ _______________________________ ________________________ School District Superintendent/Charter School Principal (signature in blue ink) Date An original copy of this form must be sent to ADE by certified mail.

Page 6: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

NEEDS ASSESSMENT In support of student learning, Flagstaff Unified School District has been fortunate to make great strides in providing instructional technology devices in the past two years. The Capital Override passed by the Flagstaff community in 2006 has resulted in funds being available to build a refresh cycle for infrastructure and classroom technologies including workstations, laptops, computer labs, projectors and document cameras. The 2009-10 school year has been focused on implementing projectors and document cameras for every classroom and laptops for all certified instructional positions. This has included nine hours of professional development conducted by a cadre of district teacher trainers as well as activities through our districtwide technology peer coaching program. The overall goal is to have the infrastructure, support, devices and professional development to allow for seamless integration of technology in all curricular areas. Student Learning The challenge for our education system is to leverage the learning sciences and modern technology to create engaging, relevant, and personalized learning experiences for all learners that mirror students’ daily lives and the reality of their futures. In contrast to traditional classroom instruction, this requires that we put students at the center and empower them to take control of their own learning by providing flexibility on several dimensions. A core set of standards-based concepts and competencies should form the basis of what all students should learn, but beyond that students and educators should have options for engaging in learning: large groups, small groups, and work tailored to individual goals, needs, interests, and prior experience of each learner. By supporting student learning in areas that are of real concern or particular interest to them, personalized learning adds to its relevance, inspiring higher levels of motivation and achievement.

Transforming American Education: Learning Powered by Technology National Educational Technology Plan (Draft), 2010

All learners will: • have access to authentic learning activities appropriate to their development whenever and wherever they need. • use appropriate strategies and technology to collaborate, construct knowledge and develop solutions to real-world problems. • communicate effectively with global audiences.

Long Range Strategic Goals Transforming Education: Enabling Learning for All Arizona Students

The Arizona Long-Range Strategic Educational Technology Plan, 2009

Current Reality Current level of technology integration and technology integration method Technology is currently being integrated throughout all subject areas on a variety of levels. Some examples are technology peer coaches and collaborating teachers developing interactive lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept; lessons in which the coach's students and the collaborating teacher's students work as a team on a tech-integrated lesson. In addition to peer coaching documentation, results are available through observations, as well as projects that are developed and implemented through professional development courses. Beginning in May 2010, technology walkthroughs will be completed for each school to ascertain the level of technology integration and types of technology readily available in classrooms. Fall 2010

Page 7: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

walkthroughs will be continued but will also include how those technologies are being used for instruction.

Technology Literacy FUSD 5th and 8th grade students are assessed with the 21st Century Skills Assessment twice yearly in fall and spring. Fall pre-assessment scores:

Number of Students Assessed

Number of Students scoring

Proficient

District Average Exam Score

5th grade 282 76 253 (27%) 8th grade 367 67 265 (22%)

Spring post-assessments will be completed in May following submission of the district tech plan. Delivering curriculum through the use of technology At this time, FUSD utilizes onlines courses available through Mesa Distance Learning. 61 students took part in online course during the 2009-2010 school year. Currently, over 80 7-12 grade courses online - courses range from basic core classes like Algebra and 9th grade Science and English to Mandarin Chinese, Service Learning, Multicultural Literature and Mythology. This particular student population consists of students with social issues that make attending the traditional school environment challenging, preferred home school students (often religious reasons), expecting teens or teen parents, students on probation or in Teen Challenge (New Horizons Academy), and students with various health issues. Mesa is always adding courses online the most recent editions being Drivers Education, Service Learning, Multicultural Literature and Mythology. Parental involvement HomeLogic is a module available through our student information system that allows parents to access student attendance and grades. In addition, Schoolwires, a content management system (CMS), was selected to replace the existing Dreamweaver-based district website. Through the CMS, district and classroom level information is contributed and shared. Finally, the VoIP phone system project will be completed in summer 2010 and enables improved communcations between parents and teachers/administrators. Technology for increased authentic learning, increased collaboration and communication skills, and problem-solving by students Instructional technology resources currently in place have contributed to a 21st learning environment in FUSD. Computer labs, mobile labs, teacher laptops, interactive whiteboards, projectors, document cameras, student response systems, iPods and sufficient bandwidth for access to online resources are available to teachers, students and administrators at this time. The combination of infusing these tools into core content, basic and 21st century skills for students enables authentic experiences that are relevant to their lives and allows them to be connected to communities and the world beyond the classroom. FUSD Student Learning Needs

• Increase opportunities for individual learning devices by purchasing iPods touches, iPads, student response devices, etc.

• Provide continued professional development on effective technology integration methods

Page 8: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

• Establish consistent method of assessing levels and methods of technology integration • Find a way to disseminate ways to use technology • Establish assessment methods for all our students on their knowledge and use of

technology • Cultivate authentic 21st century learning experiences • Create and deliver internet safety curriculum, grades K-12

Leadership All leaders will: • model, implement, and assess appropriate technology use at all levels of the teaching and learning process. • have access to the appropriate tools and resources to guide instructional and administrative practice. • implement a dynamic technology planning process that expands curricular and instructional opportunities to students. • provide opportunities for sustained, relevant, timely and effective professional development

Long Range Strategic Goals Transforming Education: Enabling Learning for All Arizona Students

The Arizona Long-Range Strategic Educational Technology Plan, 2009

Current Reality Current uses of technology to support LEA administrators and their responsibilities (district, school-based, student achievement and teacher effectiveness)

Technology Resource Activity

Student Information System Student enrollment, attendance, grades, classes, schedules, AIMS data, etc.

AzSAFE Student discipline

Communication tools (e-mail, phone, ConnectEd notification system, instant messenger, district/school website, wikis, Google docs

Communicate with staff, students, parents, community, teacher effectiveness monitoring

Assessment tools (mClass, AIMS data, 4Sight, RTI, 21st CSA)

Student achievement data monitoring and analysis, teacher effectiveness monitoring

Internet Instructional resources, collaboration

Workstations, laptops, projectors, document cameras, digital cameras

Productivity, collaboration, staff development, administrator professional development, PLCs

Curriculum tools—Curriculum maps, EasyTech

Curriculm maps and materials, Technology Curriculum, Internet Safety

Ways administrators promote and evaluate the effective use of technology by teachers

Page 9: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

• Classroom observations, evaluation discussions, monitoring of teacher professional development selections, support of site-based technology peer coaches

• Technology usage is promoted by supporting teacher technology needs and by arranging for technology professional development

o Electronic lesson planning tools o Content Management System o Document cameras o Interactive whiteboards o VoIP phone system (voicemail, etc.) o Technology integration o Laptop care and feeding

• Clear expectations for technology integration • Hiring site-based technology specialists • Promoting the use of Easy Tech • Viewing the multi media and technology projects done by the students • Purchasing and promoting technology resources for teachers and classrooms • Reviewing the district technology assessment results given to 5th graders.

Roles site-based LEA administrators play in the types and quantity of technology that are available to their staff and students FUSD administrators participate in site-based technology teams as well as the district level technology committee and the district level Technology Capital Override Planning Team. Technology planning and purchase activities are conducted in all three levels. Additional current realities for FUSD--

• Generally speaking, there is a strong administrative focus on using technology for data anaylsis versus technology integration.

• Evaluations do not include technology integration and effective use of technology. • Teacher leaders do exist within schools and administrators often rely on them for

modeling and providing professional development and guidance

FUSD Leadership Needs • Administrators’ use of technology

o Administrators should be evaluated on their own use of technology o Provide professional development for administrators so they can accurately

evaluate teachers in the area of technology integration o Modeling of relevant use and integration of technology by administrators o Regular, active administrator participation in technology professional

development and technology initiatives • Technology Integration

o Administrators need a stronger sense of what tech integration is and how to evaluate it

o Administrators need to be open to new technology development and encourage professional development and sharing of technology integration

• Evaluation of Technology Integration

Page 10: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

o Develop a realistic/appropriate tool for evaluating teachers (in technology integration) that would be used by all administrators consistently across the district

• Technology Planning o Administrators should participate in tech planning for their school

Preparation and Development Of Educators Just as leveraging technology can help us improve learning and assessment, the model of 21st century learning calls for using technology to help build the capacity of educators by enabling a shift to a model of connected teaching. In such a teaching model, teams of connected educators replace solo practitioners and classrooms are fully connected to provide educators with 24/7 access to data and analytic tools as well as to resources that help them act on the insights the data provide.

Transforming American Education: Learning Powered by Technology National Educational Technology Plan (Draft), 2010

All educators will: • complete their initial preparation with the pedagogy, practical knowledge and skills to use technology to enhance every student’s learning. • have access to research-based professional development opportunities whenever and wherever they need.

Long Range Strategic Goals Transforming Education: Enabling Learning for All Arizona Students

The Arizona Long-Range Strategic Educational Technology Plan, 2009 Current Reality Methods for identifying tech PD In recent years, including this one, technology PD needs have been identified primarily through volunteer participation in surveys and skills assessments. District technology rollouts -- such as this year's Web content-management system, document cameras, projectors, teacher laptops, and VOIP phones -- as well as non-tech-related district initiatives have also helped drive tech PD offerings in terms of both content and frequency. Similarly, tech PD is also informed by the need to provide training and support for district goals and initiatives that are not directly tech related, such as Curriculum Mapping, parental involvement via the Logic attendance and gradebook system, and assessments such as DIBELS. Student achievement data in programs such as EasyTech is also utilized to develop professional development offerings to assist teachers in effective use of the curriculum. Tech PD availablilty to faculty, staff, and administrators Most professional development offerings take the form of 3-hour workshops and 15-hour Professional Growth Academy (PGA) courses. Shorter trainings and workshops are also delivered on an as-needed basis at the district office and individual school sites. In addition, tech PD is delivered during shorter prep-hour, early-release, and after-school sessions. We also have an established technology peer-coaching program that trains coaches to assist collaborating teachers with lesson improvement and the rigorous and relevant integration of technology. Finally, tech-related (and non-tech-related) PD is available through Web-based IDEAL courses and resources. This year, in particular, our efforts have also focused on delivering 9 hours of training to every certified faculty and staff member who received a laptop as part of this year’s technology roll-out. The 9 hours comprises three 3-hour workshops: “Teacher Website Section Editor Training,” “Care and Feeding of Your Laptop,” and “Technology Integration, Quadrant D, and You.”

Page 11: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

Tech PD incentives All tech PD, from prep-period trainings to PGA courses, is typically offered for recertification seat hours. 3-hour workshops are also worth 1/4 undergraduate credit on the FUSD salary scale upon approval by the Professional Growth Committee (PGC). Approved PGA courses are worth 1 graduate salary-scale credit in additional to seat hours. Tech peer coaches are typically rewarded for their time and effort with stipends, equipment, and Career Ladder ICP points. Frequency of tech PD offerings The frequency of tech PD ranges from several offerings a month to several offerings a semester depending on the topic(s) and other ongoing activity and commitments throughout FUSD. Summer offerings, varying from 3 hours to one week in length, are also common. In general, trainings are made available to everyone, from classified staff to certified faculty to administrators and others. Some opportunities are limited to specific groups, such as Webmasters (several work days per year), technology trainers (3-5 hours of train-the-trainer PD), technology peer coaches (5 full days during the summer and 3 full days during the school year), and tech peer coaches’ collaborating teachers (a half-hour or more per week with their coaches). Tech PD providers Tech PD is most commonly delivered by FUSD’s Technology Integration Coordinator, our grant-funded Northern Arizona Technology Integration Coaching Consortium (N.A.T.I.C.C.) Technology Peer Coaching Facilitators, and our region's state-funded Technology Integration Specialist. This year, we have also leveraged a cadre of twenty-four technology trainers who have assisted in our efforts to deliver 9 hours of designated tech PD to almost every certified faculty and staff member in the district. Additionally, N.A.T.I.C.C.'s active Technology Peer Coaches each work with one or more collaborating teachers, and other individuals throughout the district occasionally put on tech-related workshops and PGA courses of their own design. Measuring the effectiveness of tech PD The effectiveness of tech PD is typically measured with a mix of periodic volunteer surveys and more frequent, required evaluations that every participant in an official training must complete to receive seat hours and/or credit. (These required evaluations are part of district PD policy that governs non-tech-related PD offerings as well.) FUSD Professional Development Needs Leadership & Administration

• Modeling of relevant use and integration of technology by administrators • Regular, active administrator participation in tech PD and tech initiatives • More consistent communication of expectations related to the integration of technology • Increased participation in voluntary, embedded, tech-related PD to ensure that tech

integration expectations can be met • Inclusion of technology integration concepts in new-hire qualifications and ongoing

faculty and staff evaluations Evaluation & Data Collection

• Walk-throughs to assess the quality and quantity of tech integration and to compare first-hand observation with self-reporting data

• A/V recording and subsequent, widespread dissemination of tech-inclusive model lessons and best practices

Page 12: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

Curriculum

• Increased awareness and inclusion of Arizona and (inter)national technology standards in teachers' planning and practice

• PD that continues to focus not just on skills and confidence, but also on meaningful technology integration through lesson planning and improvement

• Systematic inclusion of technology "common assessments" (electronic portfolios, student-driven projects, etc.) throughout the K-12 curriculum via integration with approved curriculum maps

• Increased teacher and student use of Easytech, with a PD emphasis on EasyTech as a customizable, holistic curriculum solution

• Promoting awareness of 21st Century Skills, with a particular emphasis on digital citizenship (legal, ethical, and online safety concerns)

• Emphasis on Web-based IDEAL resources as viable, desirable sources for tech-related and non-tech-related curriculum enhancement

Programmatic Professional Development

• Remedial and "next steps" PD related to 209-2010 technology rollouts, especially the Website CMS and teacher document cameras

• Alternative modes of PD -- including incentives like seat hours and salary-scale credit -- such as webinars, independent study, and "just-in-time" online trainings

• Regular inclusion of technology in professional-learning community conversations • Emphasis on Web-based IDEAL courses and resources as viable, desirable alternatives

for tech-related and non-tech-related continuing education • Coordinated PD planning that leverages the reach and work of existing non-tech groups

(Career Ladder PFEs, Instructional Coaches, etc.) to increase tech integration awareness and literacy

• Continued development of and support to ensure the sustainability of tech peer coaching and technology trainer programs

Infrastructure An essential component of the 21st century learning model is a comprehensive infrastructure for learning that provides every student, educator, and level of our education system with the resources they need when and where they are needed. The underlying principle is that infrastructure includes people, processes, learning resources, policies, and sustainable models for continuous improvement in addition to broadband connectivity, servers, software, management systems, and administration tools. Building this infrastructure is a far-reaching project that will demand concerted and coordinated effort.

Transforming American Education: Learning Powered by Technology National Educational Technology Plan (Draft), 2010

The goals above will be achieved through an infrastructure that provides: • secure and reliable anytime/anywhere access to a variety of current and emerging technologies. • just-in-time assistance to support the use of technology for administration, teaching and learning. • policies and procedures that ensure equitable access to all users.

Long Range Strategic Goals Transforming Education: Enabling Learning for All Arizona Students

The Arizona Long-Range Strategic Educational Technology Plan, 2009

Page 13: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

Current Reality Network configuration and utilization The District office is connected to Qwest Metro Optical Ethernet (QMOE) with a 1000Mbs fiber connection. Each of the secondary and elementary schools have a 100Mbs fiber connection to QMOE. A 100 Mbs connection to the internet originates at the District office and is shared by all of the sites. One or more 100 Mbs CAT 5e network connections are available in every classroom throughout the district. Access to the internet and local network resources is also available in each elementary and secondary via a district wide wireless network (802.11 b/g/n capable) allowing for greater mobility and access to network resources for both students and staff. Internet connection utilization runs anywhere from 25% to 50% on average with peaks of 80% to 90% during heavy usage. Exceptions to this scenario are Leupp School with a dedicated 3mbs microwave connection and Project New Start with a dedicated T1 connection. Access to technology/technology replacement cycle Students have access to one or more computer labs comprised of 30 or more computers in each of the schools. In addition, one or more computers are available in each classroom or library. 75% of schools have one or more mobile carts comprised of 20 or more laptops available for student use. FUSD is investigating the potential use of other mobile devices such as iPods and iPads for student use. Each teacher in the district has a district issued laptop assigned to them. Every classroom has been provided with a projector and document camera during the 2009-10 school year. Approximately 30% of classrooms have interactive whiteboards and all schools have at least one set of individual student response systems. Voice amplification systems are primiarily installed in elementary classrooms with a limited number of systems available in middle school classrooms. Digital still and video cameras are available throughout FUSD schools. Administrators have a district issued laptop assigned to them. Cell/smartphones are currently in use on a limited basis by some administrative personnel. Equipment purchased in 2008/09 and 2009/10 with Capital Override and Bond funds, marks the beginning of a five year replacement cycle for desktops, three year replacement cycle for laptops, and five year replacement cycle for network and server components. E-Rate & Infrastructure Currently, FUSD relies on E-rate discounted services for internet access (microwave) to Leupp School, a K-8 school residing on the Navajo reservation. Yearly discount requests assist in the maintenance of this 3 mb connection. FUSD’s 2010-11 E-rate requests included an increase to 10 mb for this school. Given the low districtwide percentage, E-rate services have been requested in past years for individual schools in the 90% discount range for a very limited amount of internal connection devices (routers). FUSD will continue to investigate E-rate infrastructure services that can be leveraged for our higher discount percentage schools.

Page 14: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

Technology infrastructure for department procedures

Dept/Service Technology Infrastructure

Business/Inventory/Purchasing/HR/ Depts

IFAS (Integrated Financial Accounting System)

District Communication VoIP phone system ConnectEd mass notification system IPSwitch Instant Messenger SIRS (Student Information System) Exchange E-mail (outsourced to ETC)

Student Information System (required for state reporting)

SIRS (Student Information Record System)

Transportation Transfinder routing software

Staffing levels vs. devices/infrastructure needing support

Device/Infrastructure Component

Number of devices Number of Support Positions

Workstations/Users/Software 4000 desktops/laptops 4

Printers /AV—projectors/document cameras

500 printers 500 projectors

570 document cameras Variety of addtl electronic devices

1

Network/WAN/LAN/VoIP 21 sites 1 Servers/network storage 48 1 Internet security/filtering/antivirus/Email account management

Internet security/filtering/antivirus for all desktops/laptops

1200 email accounts

1

Student Information System/SAIS reporting

19 site databases 2

Finance System 1800 accounts 1 FUSD Infrastructure Needs

• Hardware o One to one student devices to provide individual access to instructional resources o Wireless access points to expand existing wireless network o Network switches to provide for expansion of VoIP and wireless network o Additional network data storage for student and staff needs o Servers capable of virtualization to centralizing processing and reduce our carbon

footprint o Additional interactive whiteboards to provide equitable access to all classrooms o Additional voice amplification systems to provide equitable access to all

classrooms

Page 15: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Flagstaff Unified School District Technology Plan July 1, 2010 – June 30, 2013

• Software o Update existing Student Information System to meet district data needs o Helpdesk and knowledge base software package o Additional network monitoring and bandwidth management tools to ensure

equitable and reliable internet access • Staffing

o Dedicated help desk position for remote hardware/software/VoIP support o Additional workstation support personnel to reduce the workstation to tech ratio o Site-based technology support positions o Dedicated network /lab administrator position to support school labs districtwide

Page 16: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

2010-2011 Budget Summary

Arizona Department of Education Revised 12/7/2009

M&O Capital Title II-D Title IOverrides &

Bonds E-Rate Other TotalsHardware/Network 1,790.00$ 1,571,067.00$ 1,572,857.00$ Software Purchases/Licenses 225,612.00$ 171,994.00$ 1,790.00$ 399,396.00$ Professional Dev. 7,160.00$ 7,160.00$ Phone Services 134,300.50$ 240,967.22$ 375,267.72$ Internet Access/WAN 25,388.40$ 87,435.60$ 112,824.00$ Support/Maintenance/Repair 36,000.00$ 36,000.00$ Other (utilities, construction, retrofitting, etc) 19,641.56$ 36,477.19$ 56,118.75$ Totals per funding source 440,942.46$ 171,994.00$ 10,740.00$ -$ 1,571,067.00$ 364,880.01$ -$ 2,559,623.47$

Estimated E-Rate Discount Percentage 65%

Please see http://www.usac.org/sl/applicants/step05/discount-matrix.aspx for more information on calculating E-Rate discounts

*If any figures in the E-Rate column are highlighted in red, that indicates you have calculated a higher E-Rate discount for that row than you indicated in the Estimated E-Rate Discount box. Please reduce the amount budgeted for E-Rate or double-check you have input the correct E-Rate discount percentage in cell B11.

Comments: E-rate discounts vary--64% telephones, 65% internet access for majority of district, 90% for internet access @ Leupp school, "Other" category includes web hosting and e-mail. Support/Maint does not include personnel costs. Most figures estimated based on 09-10 year spending.

Page 17: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

2011-2012 Budget Summary

Arizona Department of Education Revised 12/7/2009

M&O Capital Title II-D Title IOverrides &

Bonds E-Rate Other TotalsHardware/Network 1,790.00$ $946,090.00 947,880.00$ Software Purchases/Licenses 225,612.00$ 171,994.00$ 1,790.00$ 399,396.00$ Professional Development 7,160.00$ 7,160.00$ Phone Services 134,300.50$ 240,967.22$ 375,267.72$ Internet Access/WAN 25,388.40$ 87,435.60$ 112,824.00$ Support/Maintenance/Repair 36,000.00$ 36,000.00$ Other (utilities, construction, retrofitting, etc) 19,641.56$ 36,477.19$ 56,118.75$ Totals per funding source 440,942.46$ 171,994.00$ 10,740.00$ -$ 946,090.00$ 364,880.01$ -$ 1,934,646.47$

Estimated E-Rate Discount Percentage 65%

Please see http://www.usac.org/sl/applicants/step05/discount-matrix.aspx for more information on calculating E-Rate discounts

*If any figures in the E-Rate column are highlighted in red, that indicates you have calculated a higher E-Rate discount for that row than you indicated in the Estimated E-Rate Discount box. Please reduce the amount budgeted for E-Rate or double-check you have input the correct E-Rate discount percentage in cell B11.

Comments: E-rate discounts vary--64% telephones, 65% internet access for majority of district, 90% for internet access @ Leupp school, "Other" category includes web hosting and e-mail. Support/Maint does not include personnel costs. Most figures estimated based on 09-10 year spending.

Page 18: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

2012-2013 Budget Summary

Arizona Department of Education Revised 12/7/2009

M&O Capital Title II-D Title IOverrides &

Bonds E-Rate Other TotalsHardware/Network 1,790.00$ 451,500.00$ 453,290.00$ Software Purchases/Licenses 225,612.00$ 171,994.00$ 1,790.00$ 399,396.00$ Professional Development 7,160.00$ 7,160.00$ Phone Services 134,300.50$ 240,967.22$ 375,267.72$ Internet Access/WAN 25,388.40$ 87,435.60$ 112,824.00$ Support/Maintenance/Repair 36,000.00$ 36,000.00$ Other (utilities, construction, retrofitting, etc) 19,641.56$ 36,477.19$ 56,118.75$ Totals per funding source 440,942.46$ 171,994.00$ 10,740.00$ -$ 451,500.00$ 364,880.01$ -$ 1,440,056.47$

Estimated E-Rate Discount Percentage 65%

Please see http://www.usac.org/sl/applicants/step05/discount-matrix.aspx for more information on calculating E-Rate discounts

*If any figures in the E-Rate column are highlighted in red, that indicates you have calculated a higher E-Rate discount for that row than you indicated in the Estimated E-Rate Discount box. Please reduce the amount budgeted for E-Rate or double-check you have input the correct E-Rate discount percentage in cell B11.

Comments: E-rate discounts vary--64% telephones, 65% internet access for majority of district, 90% for internet access @ Leupp school, "Other" category includes web hosting and e-mail. Support/Maint does not include personnel costs. Most figures estimated based on 09-10 year spending.

Page 19: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 1

Consolidated Plan for Flagstaff Unified District - 030201000

LEA Consolidated Plan

Date of Report: 4/29/2010

Progress 20 %

(17 of 83) Action Steps Complete

Goal: 1A Reading/Language Arts Proficiency

Flagstaff Unified School District (FUSD) will meet the Annual Measurable Achievement Objective

(AMAO) of attaining proficiency or better in reading/language arts by meeting or exceeding the

goal of 17% of our English language learner (ELL) and Special Education populations

demonstrating Adequate Yearly Progress (AYP) as measured by meeting or exceeding the

standard in Reading on the Spring 2010 AIMS. For this objective, FUSD will target all grade

spans at all schools in the district.

ADE Resources Available: 4

Estimated Cost: $2,532,397.00

Budgeted: $872,994.00

Actual: $872,994.00

Strategy: Collaborative Literacy Intervention Project (CLIP)

CLIP provides one-on-one and small group tutoring to emergent readers

(grades 1-2), utilizing an intensive year-long job-embedded training model

for primary grade teachers.

Status: Not Reviewed : 10/5/2009

Action Step: CLIP Training

Tags: PD

Identify 10-14 teachers annually to participate in the CLIP training model

provided on-site by FUSD trained facilitators.

Persons Responsible: Sylvia A. Johnson

Start Date: 08/01/2009 End Date: 06/30/2010

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Curriculum Mapping

FUSD supports a procedure for consistent, districtwide implementation of

Page 20: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 2

curriculum (i.e., curriculum mapping, ongoing professional development,

etc.) to facilitate curriculum collaboration between grade levels and at

transition grades to ensure continuous progress toward meeting the

standards.

Status: Not Reviewed : 10/5/2009

Action Step: Alignment of Maps to Standards Reports

Tags: PD

By August 15, 2009, FUSD will finalize revisions to the K-6 Standards Reports

to show alignment to the adopted curriculum maps.

Persons Responsible: Barbara Hickman, Sylvia A. Johnson, Gretchen

Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2010

Status: Completed 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Infrastructure & Connectivity

Tags: Tech

FUSD will ensure that the infrastructure for broadband connectivity delivered

to district classrooms enables reliable access to curriculum mapping tools.

Network monitoring (utilizing monitoring software) is conducted on a regular

basis by the FUSD network administrator.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Instructional Coaches

Title I ARRA funds will be used to provide two full-time instructional

coaches--one for each of two schoolwide projects--Coconino High School

and Mount Elden Middle School.

Status: Not Reviewed : 10/5/2009

Page 21: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 3

Action Step: Coaching Collaboration

Tags: Tech

Technology Peer Coaches will train on and model effective technology

integration strategies for Instructional Coaches. Instructional Coaches will, in

turn, incorporate technology into activities with staff to improve instruction.

The FUSD Technology Director, Instructional Coach Coordinator, and

Technology Integration Coordinator will meet monthly to monitor coach

activities and collaborate on strategies to enhance coaching throughout the

district.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Instructional Coach Tasks

Tags: PD

Title I, Special Education and the Bilingual Department collaborated to develop

a coaching/mentoring model to support these secondary schools. Coaches

will work one-on-one and in small groups with staff to improve instruction,

share SIOP strategies, evaluate student progress, develop intervention plans,

and work with schools on implementation of their school improvement plans.

Persons Responsible: Michael Fillerup, Sylvia A. Johnson, Diana Shaum

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: KinderCamp

A four-week pre-kindergarten program will be provided each summer to

incoming kindergarten students identified for services based on primary

home language, educational level of the parent, lack of preschool

experience, health or developmental delay issues, etc.

Status: Not Reviewed : 10/5/2009

Page 22: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 4

Action Step: KinderCamp

Tags:

KinderCamp provides a four week, five-hour per day summer experience for

entering kindergarten students. The curriculum focuses on early literacy skills,

while helping students learn the routine and expectations of school. Family

engagement (with home visits and school-based activities) are a major

emphasis of the program.

Persons Responsible: Sylvia A. Johnson

Timeline Notes: KinderCamp crosses fiscal years with a program in June-July

2009 and June-July 2010.

Start Date: 06/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Out-of-School-Time Tutoring & Enrichment

Tutoring and academic enrichment will be provided to identified students

before and after-school, during summer break, and (at the secondary level)

on Saturdays.

Status: Not Reviewed : 10/5/2009

Action Step: Tutoring

Tags:

Tutoring and other academic enrichment will be provided at a variety of

locations and times, using several funding sources, and provided by highly

qualified staff.

Persons Responsible: Sylvia A. Johnson

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Read Right

FUSD will provide supplemental intervention classes in the Read Right

Page 23: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 5

model to identified ELL, Special Education and Title I students in Title I

middle and high schools. This research-based model is intended to

dramatically improve reading ability among students who are one or more

years below age-level in reading.

Status: Not Reviewed : 10/5/2009

Action Step: Read Right Classes

Tags:

Identified high-risk readers will be selected for participation in Read Right

intervention classes for a minimum of 45 minutes daily until proficiency is

attained.

Persons Responsible: Sylvia A. Johnson

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Read Right Training

Tags: PD

Intensive seven-week training will be provided for instructional staff new to the

model, with annual improvement reviews and "program recertification" for

continuing staff.

Persons Responsible: Sylvia A. Johnson

Start Date: 08/15/2009 End Date: 06/30/2010

Status: Suspended 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Response to Intervention

All elementary schools will utilize the RTI Framework to identify specific

students needs within Tiers 1, 2 and 3 and to provide approrpaite

supplemental interventions.

Status: Not Reviewed : 10/5/2009

Action Step: Elementary Intervention Specialists

Page 24: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 6

Tags: PD

Title I ARRA and IDEA ARRA funds will be used to provide Elementary

Intervention Specialists (EIS) to oversee quality implementation of the RTI

framework and to provide direct student intervention at Tiers 2 and 3.

Persons Responsible: Sylvia A. Johnson, Diana Shaum

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Web-Based Assessment

Tags: Tech

FUSD will ensure that the infrastructure for broadband connectivity delivered

to district classrooms enables reliable access to web-based assessment tools.

Network monitoring (utilizing monitoring software) is conducted on a regular

basis by the FUSD network administrator.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Technology Integration

FUSD has placed a major emphasis on providing 21st century learning for

all students. This involves substantial output in technology and in ongoing

staff development to support integration of technology across all content

areas and in all classrooms.

Status: Not Reviewed : 10/5/2009

Action Step: IDEAL Courses

Tags: Tech

FUSD teachers will enroll in instructional technology professional development

courses available through IDEAL. Technology Integration Coordinator will

coordinate IDEAL course announcements and communications with the

Professional Development Coordinator and will monitor levels of participation

in IDEAL courses by FUSD teachers on a monthly basis.

Page 25: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 7

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Intel® Courses

Tags: Tech

FUSD teachers will engage in Intel® professional development courses

facilitated by our county Technology Integration Specialist. Technology

Integration Coordinator will coordinate Intel coursework planning and

communications with the Coconino County TIS and will monitor levels of

participation in Intel courses by FUSD teachers on a monthly basis.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Integration

Tags: PD, Tech

Ongoing professional development focuses on strategies for teachers to

extend learning by seamlessly integrating technology into the classroom in a

rigorous and relavant manner. The Technology Integration Coordinator will

work with district technology peer coaches and technology trainers to provide

technology integration professional development opportunities. Ongoing

evaluation of course offerings and semi-yearly technology walkthroughs will

result in meaningful data to assess the effectiveness of these strategies.

Persons Responsible: Sylvia A. Johnson, Mary Knight

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Peer Coaching

Tags: Tech

Page 26: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 8

FUSD technology peer coaches will receive training in the PeerEd peer

coaching model and will integrate technology into the lesson improvement

process in the own classrooms as well as in their work with collaborating

teachers.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Peer Coaching

Tags: Tech

FUSD technology peer coaches will receive training in the PeerEd peer

coaching model and will integrate technology into the lesson improvement

process in their own classrooms as well as in their work with collaborating

teachers. The district Technology Peer Coach Facilitators will provide training

and sustained support for coaches throughout the year. Semi-annual data

collection on student achievement and collaboration time will provide

benchmarks for gauging progress.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Trainers

Tags: Tech

Teachers and administrators will engage in instructional technology

professional development courses provided by FUSD Technology Trainers.

IDEAL resources such as Recipes4Success and Discovery Education

streaming will be utilized as well as district created courses such as

Technology, Quadrant D and you. The Technology Integration Coordinator

will assemble, coordinate and support this cadre of trainers. Data on number

and types of courses, course evaluations and teacher technology proficiency

scores will be assembled and analyzed.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Page 27: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 9

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Technology Support

Expand the use of technology for instruction, professional development,

data collection, and parent/community/school communication.

Status: Not Reviewed : 4/27/2010

Action Step: Technology Resources

Tags: Tech

FUSD will provide adequate technology resources to support administrative

data gathering and reporting, technology tools for student instruction and

assessment data gathering, community and staff communication, and

technology integration professional development activities. The Director of

Technology will work with the District Technology Committee to coordinate,

monitor and support technology resources districtwide. The DTC meets on a

monthly basis.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Staffing

Tags: Tech

FUSD will employ staff for the following activities: technology planning and

project management, network management, website design, technology

integration professional development and technical support to all staff. The

Director of Technology will work with district administration to monitor the

effectiveness of existing positions, explore additional staff positions if needed

and compare district staffing to state and national staffing data.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Page 28: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 10

Actual: $0.00

Tasks: None

Strategy: Arizona Task Force SEI Program Models

FUSD will effectively implement the Arizona ELL Task Force SEI Program

models with 100% of the ELL population.

Status: Not Reviewed : 10/5/2009

Action Step: ELD Training for Teachers and Administrators

Tags: PD, ELL

FUSD will provide or make provisions for ELD (Round II) training for

designated SEI/ILLP classroom teachers and school administrators.

Persons Responsible: Michael Fillerup

Timeline Notes: Round IIA ELD training completed by 8/15/2008

Rounds IIB and IIC will be completed by 05/15/2009.

Start Date: 05/01/2008 End Date: 05/15/2009

Status: Completed 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: AZ Task Force SEI Program Model Selection

Tags: ELL

FUSD will determine the SEI Program Models for the schools, submit the

Model Adoption Forms to the Governing Board for approval, and enter the

required information for SEI Program Model Adoptions online in Common

Logon under the SEI Budget Application 2.0 menu item.

Persons Responsible: Michael Fillerup

Timeline Notes: The SEI Program Model Adoptions were submitted to and

approved by the Arizona Department of Education on 01/16/2009.

Start Date: 10/01/2008 End Date: 02/01/2009

Status: Completed 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: SEI Program Model Implementation

Page 29: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 11

Tags: PD, ELL

FUSD will ensure that the four-hour SEI program models are being effectively

implemented at each site by conducting classroom observations, classroom

walk-throughs, and teacher conferences. Language Acquisition Plans (LAPs)

will be developed and implemented for each ELL. ELL Coaches will provide

on-going training and coaching to SEI teachers.

Persons Responsible: Michael Fillerup

Timeline Notes: LAPs were developed by 10/01/2008.

Principals and administrators will complete formal observations by 04/15/2009.

ELL Coaches have been providing on-site training and coaching throughout

the school year.

Start Date: 08/15/2008 End Date: 04/30/2009

Status: Completed 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Individual Language Learner Plan (ILLP)

In schools with smaller ELL populations, FUSD will effectively implement

the Arizona ELL Task Force approved Individual Language Learner Plan

(ILLP) for all (100%) of the ELLs who are not served via the four-hour SEI

program.

Status: Not Reviewed : 10/5/2009

Action Step: Training for ILLP Teachers

Tags: PD, ELL

FUSD will provide training and on-site assistance for teachers who are

implementing the ILLP.

Persons Responsible: Michael Fillerup

Timeline Notes: All ILLP teachers completed training for the full or provisional

SEI endorsement by 12/01/2008

ELL Coaches provided all ILLP teachers with training on how to develop and

implement ILLPs by 10/31/2008

Start Date: 08/15/2008 End Date: 05/15/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Page 30: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 12

Tasks: None

Action Step: AZ Task Force SEI Program Model Selection

Tags: ELL

FUSD will determine which sites will utilize the ILLP, submit the Model

Adoption Forms to the Governing Board for approval, and enter the required

information for SEI Program Model Adoptions online in Common Logon under

the SEI Budget Application 2.0 menu item.

Persons Responsible: Michael Fillerup

Timeline Notes: SEI Program Model Adoption was submitted to and approved

by the Arizona Department of Education on 01/16/2009.

Start Date: 12/01/2008 End Date: 02/01/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: ILLP Implementation

Tags: PD, ELL

FUSD will ensure that the ILLP is effectively implemented by conducting

regular classroom observations, classroom walk-throughs, and teacher

conferences, and by providing on-going coaching and training from the ELL

Coaches.

Persons Responsible: Michael Fillerup

Timeline Notes: ELL Coaches are providing on-going training and coahcing

support.

Principals and administrators will complete formal observations by 04/15/2009.

Start Date: 08/15/2008 End Date: 06/01/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Sheltered Instruction Observation Protocol (SIOP)

To ensure that reclassified ELLs receive on-going linguistic and academic

development, FUSD will implement the Sheltered Instruction Observation

Protocol (SIOP)in all mainstream classes during the 2008-09 school year.

Page 31: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 13

Status: Not Reviewed : 10/5/2009

Action Step: SIOP Training for Teachers and Administrators

Tags: PD

The FUSD will provide training in the eight components of the SIOP to all

teachers and administrators.

Persons Responsible: Michael Fillerup

Timeline Notes: Teachers and administrators recevie training in 6 of the 8

components of SIOP by 12/01/2008.

Teachers and administrators will receive training in the other two compoenents

of SIOP by 04/15/2009.

Start Date: 08/15/2008 End Date: 05/15/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: SIOP Implementation

Tags: PD

The FUSD will ensure that the SIOP model is effectively implemented by

conducting regular classroom observations, classroom walk-throughs, and

teacher conferences and by providing on-site coaching and training support

from the ELL Coaches.

Persons Responsible: Michael Fillerup

Timeline Notes: ELL Coaches are providing coaching and training support on

a daily basis.

Principals will complete formal observations of all teachers by 04/15/2009.

Start Date: 08/15/2008 End Date: 06/01/2009

Status: Completed 04/16/2010

Budgeted: $872,994.00

Actual: $872,994.00

Tasks: None

Strategy: Compensatory Education

Page 32: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 14

FUSD will provide supplementary English Language Development

instruction to ELLs and reclassified ELLs in an extended day and a summer

school program.

Status: Not Reviewed : 10/5/2009

Action Step: Training CIP Teachers

Tags: PD, ELL

The FUSD will provide training in the development and implementation of

Written Compensatory Instruction Plans (WICPs) to all CIP teachers.

Persons Responsible: Michael Fillerup

Timeline Notes: Teachers will be trained, students identified, and parents

notified for extedned day program by 01/15/2009.

For the summer CIP program, teachers will be trained, students identified, and

parents notified by 06/15/2009

Start Date: 12/01/2008 End Date: 05/15/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: COMPENSATORY INSTRUCTION

Tags: PD, ELL

A Written Individual Compensatory Plan (WICP) will be developed and

implemented for each student in the program

Timeline Notes: WICPs will be developed and implemnted for students in the

spring after-school program by 02/01/2009. For students in the summer

program WICPs will be developed by 06/15/2009.

Start Date: 01/20/2009 End Date: 06/15/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Goal: 1B Mathematics Proficiency

FUSD will show an overall improvement in math achievement from the Spring 2009 AIMS to

Spring 2010, by attaining a 10% improvement for Special Education and ELL students and a 4%

Page 33: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 15

improvement for Hispanic and Native American students.

ADE Resources Available: 1

Estimated Cost: $1,370,700.00

Budgeted: $0.00

Actual: $0.00

Strategy: Curriculum Mapping

FUSD supports a procedure for consistent, districtwide implementation of

curriculum (i.e., curriculum mapping, ongoing professional development,

etc.) to facilitate curriculum collaboration between grade levels and at

transition grades to ensure continuous progress toward meeting the

standards.

Status: Not Reviewed : 10/5/2009

Action Step: DW Math Maps

Tags: PD

By August 15, 2009, FUSD will finalize and adopt revision of math maps K-12

for required implementation throughout FY10.

Persons Responsible: Barbara Hickman, Sylvia A. Johnson, Gretchen

Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2010

Status: Completed 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Infrastructure & Connectivity

Tags: Tech

FUSD will ensure that the infrastructure for broadband connectivity delivered

to district classrooms enables reliable access to curriculum mapping tools.

Network monitoring (utilizing monitoring software) is conducted on a regular

basis by the FUSD network administrator.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Page 34: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 16

Strategy: Out-of-School-Time Tutoring & Enrichment

Tutoring and academic enrichment will be provided to identified students

before and after-school, during summer break, and (at the secondary level)

on Saturdays.

Status: Not Reviewed : 10/5/2009

Action Step: Tutoring

Tags:

Tutoring and other academic enrichment will be provided at a variety of

locations and times, using several funding sources, and provided by highly

qualified staff.

Persons Responsible: Sylvia A. Johnson

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Response to Intervention

All elementary schools will utilize the RIT Framework to identify specific

student needs within Tiers 1, 2 and 3 and to provide appropriate

supplemental interventions.

Status: Not Reviewed : 10/5/2009

Action Step: Elementary Intervention Specialists

Tags: PD

Title I ARRA and IDEA ARRA funds will be used to provide Elementary

Intervention Specialists (EIS) to oversee quality implementation of the RTI

framework and to provide direct student intervention at Tiers 2 and 3.

Persons Responsible: Sylvia A. Johnson, Diana Shaum

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Page 35: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 17

Action Step: Web-based Assessment

Tags: Tech

FUSD will ensure that the infrastructure for broadband connectivity delivered

to district classrooms enables reliable access to curriculum mapping tools.

Network monitoring (utilizing monitoring software) is conducted on a regular

basis by the FUSD network administrator.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: STEM Initiative

FUSD will collaborate with businesses and foundations to implement

varying components of a districtwide STEM initiative--Science, Technology,

Engineering and Math. This includes supplemental enrichment such as

robotics competitions, science camps, chess tournaments, etc. to an

increased emphasis on science and technology instruction in every

classroom.

Status: Not Reviewed : 10/5/2009

Action Step: STEM Partnerships

Tags: PD

FUSD will work with local, state and national entities to identify high-interest,

higher-order thinking programs and processes to increase student participation

and achievement in science, math and technology.

Persons Responsible: Kevin Brown, Barbara Hickman, Gretchen Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Technology Integration

FUSD has placed a major emphasis on providing 21st century learning for

Page 36: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 18

all students. This involves substantial output in technology and in ongoing

staff development to support integration of technology across all content

areas and in all classrooms.

Status: Not Reviewed : 10/5/2009

Action Step: IDEAL Courses

Tags: PD, Tech

FUSD teachers will enroll in instructional technology professional development

courses available through IDEAL. Technology Integration Coordinator will

coordinate IDEAL course announcements and communications with the

Professional Development Coordinator and will monitor levels of participation

in IDEAL courses by FUSD teachers on a monthly basis.

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Intel Courses

Tags: PD, Tech

FUSD teachers will engage in Intel® professional development courses

facilitated by our county Technology Integration Specialist. Technology

Integration Coordinator will coordinate Intel coursework planning and

communications with the Coconino County TIS and will monitor levels of

participation in Intel courses by FUSD teachers on a monthly basis.

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Integration

Tags: PD, Tech

Ongoing professional development focuses on strategies for teachers to

extend learning by seamlessly integrating technology into the classroom in a

rigorous and relavant manner. The Technology Integration Coordinator will

Page 37: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 19

work with district technology peer coaches and technology trainers to provide

technology integration professional development opportunities. Ongoing

evaluation of course offerings and semi-annual technology walkthroughs will

result in meaningful data to assess the effectiveness of these strategies.

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2011

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Peer Coaching

Tags: Tech

FUSD technology peer coaches will receive training in the PeerEd peer

coaching model and will integrate technology into the lesson improvement

process in their own classrooms as well as in their work with collaborating

teachers. The district Technology Peer Coach Facilitators will provide training

and sustained support for coaches throughout the year. Semi-annual data

collection on student achievement and collaboration time will provide

benchmarks for gauging progress.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Trainers

Tags: PD, Tech

Teachers and administrators will engage in instructional technology

professional development courses provided by FUSD Technology Trainers.

IDEAL resources such as Recipes4Success and Discovery Education

streaming will be utilized as well as district created courses such as

Technology, Quadrant D and you. The Technology Integration Coordinator

will assemble, coordinate and support this cadre of trainers. Data on number

and types of courses, course evaluations and teacher technology proficiency

scores will be assembled and analyzed.

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2010 End Date: 06/30/2011

Page 38: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 20

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Technology Support

Expand the use of technology for instruction, professional development,

data collection, and parent/community/school communication.

Status: Not Reviewed : 4/27/2010

Action Step: Technology Resources

Tags:

FUSD will provide adequate technology resources to support administrative

data gathering and reporting, technology tools for student instruction and

assessment data gathering, community and staff communication, and

technology integration professional development activities. The Director of

Technology will work with the District Technology Committee to coordinate,

monitor and support technology resources districtwide. The DTC meets on a

monthly basis.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Staffing

Tags: Tech

FUSD will employ staff for the following activities: technology planning and

project management, network management, website design, technology

integration professional development and technical support to all staff. The

Director of Technology will work with district administration to monitor the

effectiveness of existing positions, explore additional staff positions if needed

and compare district staffing to state and national staffing data.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Page 39: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 21

Actual: $0.00

Tasks: None

Goal: 2 HQ Teachers and Para-Professionals

All core academic content teachers serving in Title I schools for the 2009-2010 school year will be

highly qualified as evidenced by Teacher Attestations and the ADE HQ Teacher Input Position

Report.

Filing Cabinet Count: 1

ADE Resources Available: 2

Estimated Cost: $24,000.00

Budgeted: $0.00

Actual: $0.00

Strategy: Disallow Emergency Certifications

Effective with the 2009-2010 school year, Emergency Certifications will not

be requested for any certificated staff member serving in a Title I school.

Status: Not Reviewed : 10/5/2009

Action Step: Emergency Certificates

Tags:

Notification of current staff on ETC regarding job status for upcoming school

year.

Persons Responsible: Sylvia A. Johnson

Start Date: 04/01/2009 End Date: 04/15/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Obtain Provisional Certification

Tags:

Staff on Emergency Certification in FY09 will work on ITP with Professional

Development Coordinator and Principal to obtain a Provisional Certification

prior to opening day of the 2009-2010 school year. This will be a condition of

re-hire.

Persons Responsible: Sylvia A. Johnson

Start Date: 09/01/2008 End Date: 08/13/2009

Page 40: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 22

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Screening Applicants for HQ Status

The FUSD Human Resources Department will screen applicants for HQ

status prior to processing the "Recommendation for Hire."

Status: Not Reviewed : 10/5/2009

Action Step: Job Applicant Screening

Tags:

The Human Resources Department, in conjunction with building principals, will

screen all applicants for HQ status in the content area prior to submission of

recommendation for hire.

Persons Responsible: Barbara West

Start Date: 06/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: SEI Endorsements

All FUSD teachers will meet Arizona requirements for the Sheltered English

Instruction Endorsement.

Status: Not Reviewed : 4/27/2010

Action Step: SEI Completion Course

Tags: ELL, Tech

Teachers not yet meeting the SEI requirements will complete the online 45-

Hour SEI Completion course through IDEAL. Technology Department

personnel will market and support IDEAL opportunities on a monthly and as

needed basis. Course evaluations will reflect the effectiveness of strategies to

engage and enroll personnel in IDEAL coursework and resources.

Persons Responsible: Michael Fillerup, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Page 41: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 23

Budgeted: $0.00

Actual: $0.00

Tasks: None

Goal: 3 Proficiency in English for ELLs

Flagstaff Unified School District (FUSD) will demonstrate meeting the Annual Measurable

Achievement Objective (AMAO) of Reclassification" for English language learners to the

"proficient" level, as measured by AZELLA, by meeting or exceeding 17% reclassification rate for

the English language learner population during 2009-10 school year. FUSD will demonstrate the

AMAO of "Making Progress" towards English language proficiency, as measured by AZELLA, by

meeting or exceeding 17% growth for the English language learner population during the 2009-10

school year.

ADE Resources Available: 3

Estimated Cost: $0.00

Budgeted: $0.00

Actual: $0.00

Strategy: ELL Task Force SEI Program Models

The FUSD will effectively implement the Arizona ELL Task Force SEI

Program Models for 100% of the LEA's ELL population. The LEA will

ensure that all ELL students receive a minimum of four hours of English

language development (ELD) daily as required by the State-mandated SEI

Task Force Models.

Status: Not Reviewed : 10/5/2009

Action Step: ELD Class Schedules

Tags: ELL

The LEA administration/staff will create ELD class schedules which

incorporate the mandated time allocations of four hours of ELD.

Persons Responsible: Michael Fillerup

Start Date: 08/01/2008 End Date: 09/01/2008

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: ELD/SEI Training for ELD Teachers

Page 42: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 24

Tags: PD, ELL

The LEA will ensure that teachers designated for the ELD classrooms recevie

appropriate training, which includes the SEI training and ELD trainings (Round

IIA, IIB, and IIC).

Persons Responsible: Michael Fillerup

Start Date: 05/01/2008 End Date: 06/01/2009

Status: Completed 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Prof. Development for ELL Specialists

ELL Specialists will receive technology integration professional

development and methodologies appropriate for working with ELL students.

Status: Not Reviewed : 4/27/2010

Action Step: Technology Integration PD

Tags: ELL, Tech

FUSD's Technology and ELL departments will work with the county

Technology Integration Specialist (TIS) to provide technology integration

professional development for ELL Specialists. Coursework will be focused on

technology integration lesson design targeted for ELL students (ex.--

podcasting, digital storytelling). PD participation and evaluations will provide

data for analysis of professional development opportunities. Student

achievement data will also be utilized to determine effectiveness of these

strategies.

Persons Responsible: Michael Fillerup, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Goal: 4 Safe, Drug-free Schools Conducive to Learning

FUSD's secondary schools (grades 7-12) will show a 1% decrease in both alcohol and drug abuse

referrals from the 2008-2009 school year to the 2009-2010 school year.

Page 43: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 25

ADE Resources Available: 1

Estimated Cost: $55,994.00

Budgeted: $0.00

Actual: $0.00

Strategy: Internet Safety

Provide internet safety information and training for all students.

Status: Not Reviewed : 3/17/2010

Action Step: CIPA Requirements

Tags: Tech

The district will provide safe and appropriate internet access through the

district firewall that is compliant with CIPA procedures. The Assistant Director

of Technology will monitor firewall effectiveness on a continual basis.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 03/17/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: eSafety Task Force

Tags: Tech

The school district will establish an eSafety Task Force to work with students,

teachers and parents in establishing an Internet Safety Curriculum, hosting

internet and cell phone safety workshops and update district policies to ensure

the safety of students using electronic devices. Meetings will be held on a

quarterly basis. Data on participation and resulting products will be analyzed

by the Prevention Coordintor and Technology Director to determine the

effectiveness of the group’s activities in support of internet and cell phone

safety.

Persons Responsible: Sally Ake, David Dirksen, Barbara Hickman, Mary

Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Page 44: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 26

Action Step: Policies for Electronic Devices

Tags: Tech

The district will require all staff, students, and parents to read, accept, and sign

an Acceptable Use Policy for technology and the internet prior to using such

tools.

Persons Responsible: David Dirksen, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Student Release

Tags: Tech

The district will require all students and parents to read, accept and sign a

Student Release form before any student information in made available to the

public via the district website.

Persons Responsible: David Dirksen, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Prevention Programs

FUSD's prevention program includes a mentoring and peer leadership

model with components of peer mediation, communication, conflict

resolution, group dynamics, peer tutoring, one-to-one check-ins, academic

and social presentations.

Status: Not Reviewed : 10/5/2009

Action Step: DITEP Training

Tags: PD

Most secondary teachers, nurses and administrators have been trained in

DITEP (Drug Impairment Training for Educational Professionals) and through

this program more students are being identified, referred and helped. This

training will continue for new staff.

Page 45: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 27

Persons Responsible: Sally Ake

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Prevention Coordinator & Mentors

Tags: PD

The Title IV Safe and Drug Free Basic Grant supports school-based peer

mentor program teachers to sponsor peer leadership activities and a .5 fte

districtwide prevention coordinator.

Persons Responsible: Sally Ake

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Goal: 5 High School Graduation

FUSD will increase its percentage of high school graduates by 1% annually over each preceding

year.

ADE Resources Available: 9

Estimated Cost: $1,013,400.00

Budgeted: $0.00

Actual: $0.00

Strategy: Credit Recovery

Students will utilize online coursework to recover credits necessary for

graduation.

Status: Not Reviewed : 4/27/2010

Action Step: Infrastructure

Tags: Tech

FUSD will ensure that the infrastructure for broadband connectivity delivered

to district classrooms enables reliable access to online coursework. Network

monitoring (utilizing monitoring software) is conducted on a regular basis by

Page 46: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 28

the FUSD network administrator.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Dropout Prevention

Each high school develops and implements site-specific dropout prevention

programs to meet the needs of their at-risk population. This includes

activities or programs such as (1) Read Right, (2) WINGS Academy, (3)

online credit retrieval coursework supported by HQ staff after-school and

evenings, (4) Responsible Thinking Centers, and (5) grant-funded programs

such as Title I N&D, Indian Education, and McKinney-Vento Homeless

Assistance.

Status: Not Reviewed : 10/5/2009

Action Step: Project New Start

Tags:

Project New Start is an alternative educational setting for identified high-risk

students in a smaller setting and in separate off-campus facilities.

Persons Responsible: David Dirksen

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Read Right

Tags:

This intensive reading tutoring program supports many struggling readers

most at risk of dropout (i.e., high school students reading at a primary grade

level).

Persons Responsible: Sylvia A. Johnson

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Page 47: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 29

Actual: $0.00

Tasks: None

Action Step: Responsible Thinking Centers

Tags:

Pull-out classrooms staffed by behavior coaches provide a support system for

struggling students to set goals and practice skills to experience greater

success in the regular classroom.

Persons Responsible: Barbara Hickman

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Support Programs

Tags:

Various programs support specific student populations at high-risk of dropping

out. These include the homeless assistance program, the neglected and

delinquent program, out-of-school-time support for academic assistance and

credit retrieval, etc.

Persons Responsible: David Dirksen, Sylvia A. Johnson, Cara Slaughter

Start Date: 08/15/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Goal: 6 Parent Involvement

FUSD will increase parent satisfaction levels by 3% from Spring 2009 to Spring 2010, as

evidenced by the following items on the annual family survey: (1) involvement in school-based

decision making, 2) active partnerships between home and school, and (3) understanding of

student academic expectations.

ADE Resources Available: 1

Estimated Cost: $125,000.00

Budgeted: $0.00

Actual: $0.00

Page 48: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 30

Strategy: Annual Satisfaction Survey

Families and students will participate in an annual satisfaction survey.

Status: Not Reviewed : 4/16/2010

Action Step: Annual Survey

Tags:

Parents and students grades 7-12 will participate in an annual satisfaction

survey available in both English and Spanish, with completion online or in

hard-copy format.

Persons Responsible: Sylvia A. Johnson, Cara Slaughter

Start Date: 04/01/2010 End Date: 05/31/2010

Status: Retired 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Survey Administration

Tags:

An annual survey, available in both English and Spanish, will be opened in

April/May of each school year for completion online and in hard-copy format.

Persons Responsible: Sylvia A. Johnson, Cara Slaughter

Start Date: 04/01/2010 End Date: 05/31/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Family Resource Center

FUSD will sponsor a "one-stop" family resource center which is centrally

located and easily accessible to all Title I eligible families. The FRC will

provide K-12 academic support, preschool activities, family support and

referral services, educational information and advocacy, parenting

workshops, adult education, Navajo and Spanish translation services, etc.

Status: Not Reviewed : 10/5/2009

Action Step: Expanded Family Services

Page 49: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 31

Tags:

FRC staff will work with teachers and parents at Title I schools to expand

usage of the center by typically "disenfranchised" parents/families.

Persons Responsible: Sylvia A. Johnson, Cara Slaughter

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Integration

Tags:

Technology classes for adults help parents and other caregivers to become

more technologically literate in order to support their own student's learning.

Persons Responsible: Sylvia A. Johnson, Cara Slaughter

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Home/School Communication

Online resources will link students, families, and schools, providing ongoing

communication and information.

Status: Not Reviewed : 4/27/2010

Action Step: Communication Tools

Tags: Tech

The district will retain an infrastructure that enables email, phone system

communication and notifications through technology in order to communicate

with parents and families. The Director and Assistant Directors of Technology

will monitor availability and effectiveness of communication systems on a daily

basis.

Persons Responsible: David Dirksen, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Page 50: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 32

Tasks: None

Action Step: District Website

Tags: Tech

FUSD will maintain an up-to-date internet web page communicating

information about the district and school to families, the community, and the

world. Effective, ongoing monitoring and support will result from a

collaboration of district department and site administrators as well as district

and school webmasters.

Persons Responsible: Barbara Hickman, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Parent Access

Tags: Tech

The district will maintain an online student management sytem that allows

parents access to their grades and attendance. Student Information System

personnel will maintain and support the SIS. School based personnel will

assist with communition and support of parents utilizing the system. Parent

and family feedback will be used in determining the effectiveness of the

system.

Persons Responsible: David Dirksen, Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: SDSU Partnership

FUSD will partner during the 2009-2010 school year with

consultants/trainers from the California Parent Center at San Diego

University's Research Foundation in a coaching model to build school-

family-community partnerships focused on supporting schools' academic

goals for students.

Status: Not Reviewed : 10/5/2009

Page 51: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 33

Action Step: FIAT

Tags: PD

Family Involvement Action Teams will be developed at each of the four ARRA

schools and will serve as the core of the new districtwide initiative to expand

and improve the quality of family engagement. These teams will participate in

a two-day SDSU training to be provided locally.

Persons Responsible: Sylvia A. Johnson, Cara Slaughter

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Needs Assessment & Planning

Tags: PD

The primary focus for the SDSU partnership will be on four schools which are

eligible for the ARRA Title I Family Engagement Grant. Teams from each of

the four schools will work with SDSU trainers to complete a needs

assessment, develop and implement an improvement plan, and provide

training in effective engagement strategies. Other schools will be included as

time and other funding sources allow.

Persons Responsible: Sylvia A. Johnson, Cara Slaughter

Start Date: 07/01/2009 End Date: 06/30/2010

Status: Not Begun 06/25/2009

Budgeted: $0.00

Actual: $0.00

Tasks: None

Goal: Technology Literacy

By the end of the 2010-2011 school year, there will be a 5% increase of 8th grade students and

5% increase of 5th grade students who will be technology literate as measured by the Student

Technology Literacy Assessment.

Estimated Cost: $0.00

Budgeted: $0.00

Actual: $0.00

Page 52: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 34

Strategy: Student Proficiency

FUSD students will utilize the district online technology curriculum to master

technology standards and will complete a technology literacy assessment to

determine proficiency.

Status: Not Reviewed : 4/27/2010

Action Step: Technology Assessment

Tags: Tech

FUSD will administer the 21st Century Skills Assessment pre- and post-

assessments with the 5th and 8th grades. The Technology Integration

Coordinator will coordinate and support site based personnel in the

preparation for and administration of the 21st Century Skills Assessment.

Student achievement data will be analyzed and results will be communicated

to the appropriate district, site and classroom level personnel. This data will

also be used for professional development course offerings and support

activities at school level.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Curriculum

Tags: Tech

FUSD students will utilize our online technology curriculum to master Arizona

technology standards. The Technology Integration Coordinator will monitor

monthly usage and variety of activties being utilized to determine the level of

usage at schools. These results will be communicated to district and site

administators. A comparison of curriculum usage and completion results will

be compared to student technology proficiency assessment data to determine

effectiveness of the online technology curriculum.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Page 53: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 35

Goal: Innovation for Continuous Growth

FUSD will research and utilize best practices to provide 21st century learning environments to

meet the needs of all students. Progress will be measured by evaluation of success of specific

models implemented and continuous improvement in the overall academic achievement of

students as measured annually by AIMS Reading, Math and Science.

Estimated Cost: $260,000.00

Budgeted: $0.00

Actual: $0.00

Strategy: Exploration and Innovation

FUSD will seek opportunities for improvement through research-based,

innovative programs or models for continuous growth.

Status: Not Reviewed : 10/5/2009

Action Step: Common Assessments

Tags: PD

FUSD will utilize best practices research (i.e., Stiggins, Marzano) to develop

rigorous, high-quality common assessments based on aligned curriulum

maps.

Persons Responsible: Barbara Hickman, Gretchen Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2011

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: P-3 Initiative

Tags:

FUSD will collaborate with Northern Arizona University's College of Education

to develop a communitywide strategic plan for innovative P-3 programming.

Persons Responsible: Barbara Hickman, Sylvia A. Johnson

Start Date: 07/01/2009 End Date: 06/30/2011

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Page 54: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 36

Action Step: Reinventing Schools

Tags: PD

FUSD will explore the research and options for adopting the model espoused

by the Reinventing Schools Coalition for a non-graded, continuous

improvement model.

Persons Responsible: David Dirksen, Barbara Hickman

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: STEM Initiative

Tags: Tech

FUSD will collaborate with businesses and foundations to implement varying

components of a districtwide STEM initiative--Science, Technology,

Engineering and Math. This includes supplemental enrichment such as

robotics competitions, science camps, chess tournaments, etc. to an increased

emphasis on science and technology instruction in every classroom.

Persons Responsible: David Dirksen, Barbara Hickman, Mary Knight,

Gretchen Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2011

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Highly Effective Teachers

FUSD will provide sustained, high-quality professional development to

ensure that all learning environments are supported by teachers and

administrators who are not only highly-qualified as defined by NCLB, but are

highly effective (Marzano, et al).

Status: Not Reviewed : 10/5/2009

Action Step: Coaching/Mentoring

Tags: PD, Tech

FUSD teachers will be supported in improvement efforts through the utilization

Page 55: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 37

of coaching and mentoring programs.

Persons Responsible: Michael Fillerup, Barbara Hickman, Sylvia A. Johnson,

Mary Knight, Gretchen Markiewicz, Diana Shaum

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: SIOP

Tags: PD

All staff will receive ongoing professional development and support for

implementation of SIOP strategies to support differentiated instruction for all

students.

Persons Responsible: Michael Fillerup

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Sustained Professional Development

Tags: Tech

Teachers will utilize professional development resources and a districtwide

electronic registration system to facilitate participation in online courses

through IDEAL, and Intel Teach Thinking with Technology and/or Intel Teach

Essentials professional development course facilitated by the county

Technology Integration Specialist (TIS).

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Integration

Tags: PD, Tech

Teachers and administrators will become proficient in the use of technology

and effective methods for integrating technology throughout the curriculum.

Page 56: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 38

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2010

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Technology Integration

FUSD's learning environments will be enhanced with 21st century

technology integrated throughout the curriculum, both to support student

engagement and to better prepare students for the rapidly changing global

environment.

Status: Not Reviewed : 10/5/2009

Action Step: Technology Training

Tags: PD, Tech

Teachers and administrators will become proficient in the use of technology

and effective methods for integrating technology throughout the curriculum.

Persons Responsible: Mary Knight, Gretchen Markiewicz

Start Date: 07/01/2009 End Date: 06/30/2011

Status: In Progress 04/16/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Strategy: Technology Support

Expand the use of technology for instruction, professional development,

data collection, and parent/community/school communication.

Status: Not Reviewed : 4/27/2010

Action Step: Technology Resources

Tags: Tech

FUSD will provide adequate technology resources to support administrative

data gathering and reporting, technology tools for student instruction and

assessment data gathering, community and staff communication, and

technology integration professional development activities. The Director of

Technology will work with the District Technology Committee to coordinate,

Page 57: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 39

monitor and support technology resources districtwide. The DTC meets on a

monthly basis.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Resources

Tags: Tech

The District will provide adequate technology resources to support

administrative data gathering and reporting, technology tools for student

instruction and assessment data gathering, community and staff

communication, and technology integration professional development

activities.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Action Step: Technology Staffing

Tags: Tech

FUSD will employ staff for the following activities: technology planning and

project management, network management, website design, technology

integration professional development and technical support to all staff. The

Director of Technology will work with district administration to monitor the

effectiveness of existing positions, explore additional staff positions if needed

and compare district staffing to state and national staffing data.

Persons Responsible: Mary Knight

Start Date: 07/01/2010 End Date: 06/30/2011

Status: Not Begun 04/27/2010

Budgeted: $0.00

Actual: $0.00

Tasks: None

Page 58: FLAGSTAFF UNIFIED SCHOOL DISTRICT · lessons for the Smart Board or Promethean together; digital storytelling ideas in which students demonstrate their understanding of a concept;

Consolidated Plan for Flagstaff Unified District - 030201000 Page: 40

TOTAL PLAN FUNDS:

Estimated Cost: $5,381,491.00

Actual Cost: $872,994.00

Budgeted Cost: $872,994.00

Available Funds: $0.00