fleet strategy - hvdc

Upload: ebene2

Post on 03-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Fleet Strategy - HVDC

    1/57

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved.

    HIGH VOLTAGE DIRECT CURRENT(HVDC)

    Fleet Strategy

    Document TP.FS 46.01

    16/10/2013

  • 8/12/2019 Fleet Strategy - HVDC

    2/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved.

    C O P Y R I G H T 2 0 1 3 T R A N S P O W E R N E W Z E A L A N D L I M I T E D . A L L R I G H T SR E S E R V E D

    This document is protected by copyright vested in Transpower NewZealand Limited (Transpower). No part of the document may bereproduced or transmitted in any form by any means including, without limitation, electronic, photocopying, recording or otherwise,

    without the prior written permission of Transpower. No information embodied in the documents which is not already in the public

    domain shall be communicated in any manner whatsoever to any third party without the prior written consent of Transpower.Any breach of the above obligations may be restrained by legal proceedings seeking remedies including injunctions, damages and costs.

  • 8/12/2019 Fleet Strategy - HVDC

    3/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved.

    Table of Contents

    EXECUTIVE SUMMARY ...................................................................................................................... 1

    SUMMARY OF STRATEGIES .............................................................................................................. 4

    1 INTRODUCTION ....................................................................................................................... 5

    1.1 Purpose ................................................................................................................................. 5

    1.2 Scope .................................................................................................................................... 5

    1.3 Stakeholders ......................................................................................................................... 7

    1.4 Strategic Alignment ............................................................................................................... 7

    1.5 Document Structure .............................................................................................................. 8

    2 ASSET FLEET .......................................................................................................................... 9

    2.1 Asset Statistics ...................................................................................................................... 9

    2.2 Asset Characteristics .......................................................................................................... 13

    2.3 Asset Performance .............................................................................................................. 20

    3 OBJECTIVES .......................................................................................................................... 25

    3.1 Safety Objectives ................................................................................................................ 25

    3.2 Service Performance ........................................................................................................... 25

    3.3 Cost Performance ............................................................................................................... 26

    3.4 New Zealand Communities ................................................................................................. 26

    3.5 Asset Management Capability ............................................................................................ 27

    4 STRATEGIES.......................................................................................................................... 29

    4.1 Planning .............................................................................................................................. 29

    4.2 Delivery ............................................................................................................................... 38

    4.3 Operations ........................................................................................................................... 40

    4.4 Maintenance ........................................................................................................................ 43

    4.5 Disposal ............................................................................................................................... 50

    4.6 Asset Management Capability ............................................................................................ 50

    4.7 Summary of RCP2 Fleet Strategies .................................................................................... 53

  • 8/12/2019 Fleet Strategy - HVDC

    4/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 1 of 54

    EXECUTIVE SUMMARY

    Introduction

    The High Voltage Direct Current (HVDC) link provides a high-capacity connection between

    the North Island and South Island electricity systems, enabling the operation of an efficient

    national electricity market. We have recently completed a major upgrade of the HVDC link,

    with the commissioning of the Pole 3 converter stations at Benmore and Haywards.

    The HVDC inter-island link has achieved world-class levels of performance over the years

    since the original scheme was commissioned in 1965. Our asset management approach for

    the HVDC link seeks to achieve continued high levels of availability and reliability on a

    sustainable basis, and to achieve least whole-of-life cost.

    Asset fleet and condition assessment

    The HVDC converter stations include a diverse range of equipment, some of which is highly

    specialised. There are particular challenges in asset management of HVDC equipment,

    because of the small population of similar equipment in service (even including similar HVDC

    schemes worldwide). There is only a limited experience base on which to build a detailed

    understanding of potential failure modes and develop appropriate condition assessment and

    risk management strategies.

    Further, our customers for the HVDC transmission service require high levels of annual

    availability. We typically aim to limit scheduled outages for routine maintenance and

    condition assessment to 23 days each year for each pole of the HVDC link.

    The HVDC Pole 2 converter stations were commissioned in 1991 and use electrically

    triggered thyristor technology. The main circuit equipment in Pole 2 is generally in goodcondition and has considerable remaining life.

    However, some subsystems within the Pole 2 converter systems have reached the end of

    their expected lives, and replacements or other interventions are now required. One

    example is the original control and protection systems in Pole 2 that have recently been

    almost completely replaced, as part of the new Pole 3 project.

    Some assets within the Pole 2 converter stations undergo frequent mechanical switching as

    HVDC transfer varies. Asset management attention is focused on this frequently operated

    equipment, to minimise the risk of failure. A programme of special inspections and condition

    assessments is used to determine the need for major overhauls and replacements.

    The HVDC Pole 3 converter stations were commissioned in May 2013, to fully replace the

    mercury-arc valve converters of the original 1965 inter-island transmission scheme. The

    Pole 3 converter stations use light-triggered thyristor technology. Asset management

    approaches for the Pole 3 equipment will follow the manufacturersrecommendations, and

    will be adapted with further operational experience.

    The HVDC connection between the North Island and the South Island relies on three HVDC

    submarine power cables across Cook Strait. The submarine cables were installed in 1991,

    together with new cable terminal stations where the cables connect to the overhead HVDC

    transmission line. The underwater environment in Cook Strait is harsh, and the cables are

    now more than 20 years old. Yet underwater surveys indicate that the cables are still in good

    condition and likely to remain usable beyond their original design life. The most significant

  • 8/12/2019 Fleet Strategy - HVDC

    5/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 2 of 54

    risk to the submarine cables is damage caused by illegal fishing and anchoring in the Cook

    Strait Cable Protection Zone (CPZ).

    Strategies

    The level of capital expenditure (capex) required during RCP2 for the HVDC fleet is expectedto be relatively low because of the good condition of the submarine cables and Pole 2 assets

    and the new condition of the Pole 3 assets. This fleet strategy aims to ensure that we

    maximise the remaining life of the assets, which is now likely to be greater than the original

    design life of the submarine cables and the Pole 2 equipment.

    The forecast capex is for some individual assets that require replacement or refurbishment

    because they have a shorter life expectancy than the rest of the Pole 2 system, based on

    their current condition, age and operation frequency. We will also make some investments

    to bring the older Pole 2 assets up to the same standard as the new Pole 3 equipment where

    practical and cost efficient, so that we can maximise the benefits of the Pole 3 project.

    We will complete Stage 2 of the Pole 3 project as part of the originally approved Pole 3Major Capex Proposal (MCP). The remaining work involves improving voltage stability

    through the addition of filter banks and a static synchronous compensator (STATCOM). This

    will increase the HVDC capacity to 1,200 MW. Stage 2 is due to be commissioned by 2014.

    The Pole 2 valve base electronics (VBE) and thyristor control units (TCUs) are critical

    components of the Pole 2 control system. The main control and protection systems in Pole 2

    have been replaced as part of the Pole 3 project, but the replacement of VBE and TCUs was

    not part of the scope of work. We have very limited spares for this equipment and there is a

    risk that failure rates will start to increase due to age-related deterioration. We plan to

    replace this equipment during the RCP2 period to ensure continued high levels of reliability.

    The Pole 2 filter bank circuit breakers operate frequently, as a result of changes in HVDCpower transfer. Several of the Pole 2 filter bank circuit breakers are expected to reach their

    recommended maximum number of operations during RCP2. We plan to replace and

    refurbish filter bank circuit breakers before the risk of failure escalates.

    The Oteranga Bay Cable Station is located in an extremely harsh coastal environment. The

    roof and wall cladding of the building is significantly corroded, and the building is no longer

    weather-tight. We plan to re-clad the roof and walls of the cable station to protect the cable

    station equipment and ensure reliability.

    We will continue to monitor the Cook Strait submarine cables with a variety of approaches,

    including a marine patrol of the Cook Strait CPZ to deter and detect illegal fishing and

    anchoring. To ensure that we have reliable information about the condition of thesubmarine cables, we will continue with programmes of surveys by Remote Operated

    Vehicles (ROVs) and by divers. We are currently investigating alternative approaches to the

    maintenance of the submarine cables, to reduce the operating expenditure (opex) required.

    Failure of the Cook Strait submarine power cables is a low probability but high-impact risk.

    We will maintain contingency plans for undertaking repairs to submarine power cables, and

    ensure preparedness to respond promptly and effectively to any cable fault.

    Improvements

    We have recently made a number of improvements to the asset management of the HVDC

    assets.

  • 8/12/2019 Fleet Strategy - HVDC

    6/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 3 of 54

    We have installed a Real Time Digital Simulator (RTDS) that will be used forsupporting operations, and for post-event analysis. It will also be used as a risk

    management tool, for testing the effects of proposed changes to HVDC control

    system software or settings, before any such changes are implemented at site.

    We have established an in-house team of HVDC field engineers to help manage thelong-term risks of retaining an appropriate level of highly specialised skills required

    for maintenance and support of the HVDC and power electronics assets.

    We have appointed an HVDC Manager, who has responsibility for overview of theasset management of the HVDC asset fleet.

  • 8/12/2019 Fleet Strategy - HVDC

    7/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 4 of 54

    SUMMARY OF STRATEGIES

    This section provides a high-level summary of the main asset management strategies andtheir costs during the RCP2 period (20152020) for the HVDC fleet. The three main

    strategies summarised below relate to capex.

    Capital Expend iture

    Replace Pole 2 Valve Base Electronics and Thyristor

    Control UnitsRCP2 Cost $7.6m

    The VBE and TCUs are critical parts of the control system and are nearing the end of their

    useful lives. We have very limited spares for this equipment and failure rates are starting to

    increase due to age-related condition deterioration.

    Our strategy is to replace the Pole 2 VBE and TCU over RCP2, to improve long-term

    reliability.

    Over the RCP2 period, we plan to replace the VBE and TCU, together with the connecting

    fibre optic links, at an estimated cost of $7.6m.

    Replace and Refurbish Pole 2 Filter Bank Circuit

    BreakersRCP2 Cost $3.2m

    Several frequently operated Pole 2 filter bank circuit breakers are expected to surpass theirrecommended number of operations during RCP2.

    Our strategy is to replace and refurbish filter bank circuit breakers before the risk of failure

    escalates.

    The plan will involve replacing 5 filter bank circuit breakers and refurbishing 1 filter bank

    circuit breaker over RCP2 at an estimated cost of $3.2m.

    Re-clad Oteranga Bay Cable Station RCP2 Cost $2.2m

    The Oteranga Bay Cable Station is located in an extremely challenging coastal environment.The roof and wall cladding of the building is significantly corroded, allowing water to enter.

    Our strategy is to re-clad the roof and walls of the cable station with a design that is better

    suited to the environment. This will result in enhanced protection of cable station assets.

    Over the RCP2 period, we plan to re-clad the cable station roof at a cost of $1.2m and the

    exterior walls at a cost of $800,000.

    Chapter 4 has further details on these strategies and a discussion of the remaining

    strategies.

  • 8/12/2019 Fleet Strategy - HVDC

    8/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 5 of 54

    1 INTRODUCTION

    Chapter 1 introduces the purpose, scope, stakeholders, and strategic alignment of the High

    Voltage Direct Current (HVDC) fleet strategy.

    1.1 Purpose

    We plan, build, maintain and operate New Zealands high-voltage electricity transmission

    network (Grid). This includes the HVDC assets, which provide a high-efficiency, high-

    capacity connection between the North Island and South Island electricity grids.

    The purpose of this fleet strategy document is to describe our approach to lifecycle

    management of the HVDC asset fleet. This includes a description of the asset fleet,

    objectives for future performance and strategies being adopted to achieve these objectives.

    The strategy sets the high-level direction for fleet asset management activities across the

    lifecycle of the asset fleet. These activities include Planning, Delivery, Operations,

    Maintenance, and Disposal.

    This document has been developed based on good practice guidance from internationally

    recognised sources, including BSI PAS 55:2008.

    1.2 Scope

    The New Zealand HVDC systems assets have key asset management differences to the AC

    system, which is why the assets in the HVDC system have their own fleet strategy. The scope

    of the fleet strategy includes the following HVDC asset categories:

    Converter Stations:converters, DC yard equipment, and AC switchyard equipment

    Electrode Stations:earthing electrodes, isolating switches, roof bushings andbuildings

    Submarine Cables and Cable Stations:submarine cables, cable terminations, andbuildings.

    The HVDC system is a sophisticated system that requires complex controls to ensure it

    operates optimally and safely. This includes two reactive power control (RPC) systems, one

    at Benmore and one at Haywards. We also have a Real Time Digital Simulator (RTDS) and a

    valve base simulator for the HVDC system. This is located at Transpower House andsimulates the real-time response of the power system to various scenarios to support

    maintenance and testing of HVDC controls.

    Given the extensive nature of the HVDC system with its large number of asset types, further

    information on the assets within each category is provided below.

    Converter Stations

    The valve halls at each converter station contain the primary equipment that enables the

    conversion between DC and AC. The two main types of equipment in the valve halls are:

    thyristors

    bushings.

  • 8/12/2019 Fleet Strategy - HVDC

    9/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 6 of 54

    The converter stations include a diverse range of complex and special purpose secondary

    equipment, such as protection systems, control systems, water cooling systems, and

    auxiliary power supplies. The scope of this strategy document includes the converter valve

    hall buildings themselves and their building services.1

    The converter stations also include DC and AC switchyards, which include a number of

    assets. The most important of these assets are:

    converter transformers

    circuit breakers

    harmonic filters

    buses

    disconnectors and earth switches

    instrument transformers

    smoothing reactors.

    Much of the equipment in the HVDC converter stations are specialised unique designs that

    vary significantly from those used on the AC system, which is the reason they are considered

    under this strategy and asset portfolio and not under the relevant AC asset fleet strategy.

    The converter transformers are particularly unique assets, with designs that are much more

    complex and fundamentally different from our AC power transformers.

    Electrode Stations

    There are two electrode stations, with one set of electrodes being inland and the other set

    underwater. The electrode stations include:

    roof bushings

    electrode arms

    isolating switches

    cabling.

    Submarine Cables and Cable Stations

    Three HVDC submarine cables cross Cook Strait to connect the North Island with the South

    Island. There are two cable terminal stations, where the HVDC submarine cables are

    connected to overhead lines.

    Exclusions

    The HVDC overhead transmission lines are excluded from this strategy as they are covered

    within the Conductors and Insulators fleet strategy. Similarly, the management of the HVDC

    towers is described in the Towers and Poles fleet strategy. The Haywards synchronous

    condensers, which support the operation of the HVDC link, are included in the Reactive

    Power Fleet Strategy.

    1 At the time of writing, we are considering a transfer of responsibility for several aspects of HVDC buildings and

    grounds management from the HVDC maintenance service providers to the Buildings and Grounds FacilitiesManagement service provider.

  • 8/12/2019 Fleet Strategy - HVDC

    10/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 7 of 54

    1.3 Stakeholders

    The HVDC system provides a high-efficiency and high-capacity connection between the

    North Island and South Island electricity grids, enabling a national electricity market. Correct

    operation and maintenance of the HVDC asset fleet is essential for transporting electricityfrom areas of high supply to areas of high demand, thus reducing disparity between the

    electricity prices in different regions of New Zealand.

    Key stakeholders include:

    Transpower Groups: Grid Development, Performance and Projects

    regulatory bodies: Commerce Commission and Electricity Authority

    generators

    service providers

    landowners customers: including distribution network businesses

    fishing and shipping industry.

    1.4 Strategic Alignment

    A good asset management system shows clear hierarchical connectivity or line of sight

    between the high-level organisation policy and strategic plan, and the daily activities of

    managing the assets. This document forms part of that connectivity by setting out the

    strategy for managing the HVDC asset fleet to deliver our overall Asset Management

    Strategy.

    This fleet strategy directly informs the HVDC Asset Management Plan, which is provided

    separately. The hierarchical connectivity is represented graphically inFigure 1.It indicates

    where the fleet strategy and plan fit within our asset management system.

  • 8/12/2019 Fleet Strategy - HVDC

    11/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 8 of 54

    Figure 1: The HVDC Fleet Strategy within the Asset Management Hierarchy

    1.5 Document Structure

    The rest of this document is structured as follows.

    Chapter 2provides an overview of the HVDC asset fleet including fleet statistics,characteristics and their performance.

    Chapter 3sets out asset management related objectives for the HVDC asset fleet. These

    objectives have been aligned with the corporate and asset management policies, and with

    high-lever asset management objectives and targets.

    Chapter 4sets out the fleet specific strategies for the management of the HVDC fleet. These

    strategies provide medium-term to long-term guidance and direction for asset management

    decisions and will support the achievement of the objectives in chapter 3.

    HVDC Plan

    HVDC Strategy

    Corporate Objectives & Strategy

    Asset Management Policy

    Asset Management Strategy

    Lifecycle Strategies

    DeliveryPlanning Operations DisposalMaintenance

  • 8/12/2019 Fleet Strategy - HVDC

    12/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 9 of 54

    2 ASSET FLEET

    Chapter 2 provides a high-level description of the HVDC asset fleet, including:

    Asset statistics:including population, diversity, age profile and spares

    Asset characteristics:including safety and environmental considerations, assetcriticality, asset condition, maintenance requirements and interaction with other

    assets.

    Asset performance:including reliability, safety and environmental

    Risks and issues.

    2.1 Asset Statistics

    This section outlines the HVDC asset fleet population, along with their diversity and age

    profiles.

    2.1.1 Overview of Asset Fleet

    The HVDC system is an important part of New Zealands electricity transmission system.It

    connects the North Island with the South Island via submarine cables. The HVDC system has

    a high capacity and low losses due to its high voltage and DC configuration (HVDC is only

    cost effective for long distance point-to-point transmission).

    The HVDC system runs from Benmore Station in the Waitaki Valley (South Island) to the

    Haywards station in the Hutt Valley (North Island). The system includes the HVDC Cook Strait

    submarine power cables connecting the North Island with the South Island, overhead HVDC

    transmission lines in both islands, and the Benmore and Haywards converter stations, where

    power is converted between AC and DC. There are also two electrode stations which provide

    an earth return system. Cable stations are located at Fighting Bay and Oteranga Bay where

    the HVDC overhead line conductors are connected to the Cook Strait submarine cables.

    The original Pole 1 converter station equipment, first commissioned in 1965, was replaced in

    2013 with the new Pole 3 equipment (although the use of Pole 1 equipment was restricted

    from 2007, and it was fully decommissioned in 2012). The Pole 3 project has brought the

    fleet up to a modern standard.

    2.1.2 Asset PopulationTable 1 shows the population of the current asset fleet as of June 2013.

    Station Population Comment

    Converter Stations 4 2 at Benmore and 2 at Haywards

    Electrode Stations 2 1 at Bog Roy and 1 at Te Hikowhenua

    Cable Stations 2 1 at Fighting Bay and 1 at Oteranga Bay

    Submarine Cables 3 38 km per submarine cable

    Table 1: HVDC Asset Fleet

  • 8/12/2019 Fleet Strategy - HVDC

    13/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 10 of 54

    2.1.3 Fleet Diversity

    Fleet diversity is a significant issue for the management of the HVDC fleet given the small

    number of each asset type within the fleet. The small numbers of individual types of

    equipment mean that there is limited operational experience on which to base assessments

    of condition and risk. Further, the unusual characteristics of many of these items of

    equipment require us to consider a diverse range of asset management risks and issues in

    managing the system as a whole. In some cases, the worldwide population of identical

    equipment is very small. This makes the retention of skills important as well as maintaining

    relationships with suppliers and service providers, including specialised overseas service

    providers.

    Converter stations

    The four converter stations are of the same basic type, that is, Line Commutated Converter

    (LCC). However, there are significant differences in the technology used in Pole 2 and Pole 3.

    For example, they have different thyristor technology, which are also from differentmanufacturers. The differences in technology have some benefits and some disadvantages.

    One benefit is that the technology reduces the likelihood of simultaneous pole failure on

    both poles from a common cause.

    The maintenance tasks for the converter stations are the same in a general sense, but the

    specific procedures for the tasks differ between the two poles, and different spares are

    required. For example, Pole 3 uses light triggered thyristors, whereas Pole 2 uses electrically

    triggered thyristors, so separate spares must be kept. There is only one HVDC equipment

    supplier worldwide that supplies light triggered thyristors.

    As part of the Pole 3 project, the Pole 2 control system was replaced with a system identical

    to that of Pole 3 so the control systems would be fully compatible.

    The majority of assets in the HVDC system require a unique design with different

    specifications to the assets on the AC system. For example, HVDC transformers and filter

    bank circuit breakers are very different to those in the AC system.

    Electrode and cable stations

    Diversity is not a significant issue for the majority of the assets at the electrode and cable

    stations. However, diversity is relevant to the cable station roof bushings. Roof bushings can

    be damaged by extreme weather, so maintenance and emergency replacement may be

    required. Using standard designs for all four roof bushings has made such activities easier.

    Submarine cables and cable stations

    Historically, submarine cables were impacted by diversity given that the cable fleet was

    procured in tranches over time and used differing technology. However the three cables that

    are now in service are identical in design and practice, even though they were produced by

    two different manufacturers. Table 2 shows the types of submarine cable in the fleet.

    Cables Type Comment

    HVDC Cables 46 Oil impregnated paperIdentical designs; two differentmanufacturers.

    Table 2: Diversity of the Submarine Cable Fleet

    We only need to carry one type of spare cable because the three cables in service have thesame design.

  • 8/12/2019 Fleet Strategy - HVDC

    14/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 11 of 54

    2.1.4 Age Profile

    The original HVDC link was commissioned in 1965 and there was a substantial HVDC upgrade

    project in 1991, when the Pole 2 converter stations were commissioned and the three

    currently operating HVDC submarine power cables were installed. This upgrade process has

    continued with the recent replacement and refurbishment of some Pole 2 HVDC assets.

    As discussed in subsection 2.1.1, new converter stations, called Pole 3, replaced the

    decommissioned Pole 1 converter stations in 2012/13.

    Converter stations

    It is worth noting that life expectancy as shown in Table 3 is the nominal life established for

    fixed asset accounting purposes. It represents the typical average life expected from a type

    of equipment before it is no longer fit to remain in service. For example, the original life

    given to the Pole 2 primary equipment was 30 years for accounting purposes, but with

    further experience with the assets we now anticipate the Pole 2 primary equipment to last

    much longer. The nominal life expectancy is a generalisation across the primary equipment,but the life expectancies of different components within the converter stations differ

    markedly.

    Station InstalledNominal LifeExpectancy

    Pole 2 converter station (Haywards) 1991 30 years

    Pole 2 converter station (Benmore) 1991 30 years

    Pole 3 converter station (Haywards) 2012 40 years

    Pole 3 converter station (Benmore) 2012 40 years

    Table 3: HVDC Stations Age

    Within each HVDC station, the component assets will have varying ages as components have

    been refurbished, replaced or enhanced over time.

    Electrode stations

    The electrode stations at Te Hikowhenua and Bog Roy were installed in 1965 when the HVDC

    system was originally installed. Both stations were extended between 1989 and 1993 to

    significantly increase their current rating. The various components of the electrode stations

    continue to be maintained, refurbished or replaced as required to maintain the required

    condition and function of the stations. In particular, there has been an ongoing programme

    of total replacement of the buried electrode arms of the Bog Roy land electrode station.

    Cables and cable stations

    The three HVDC submarine cables were installed between 1990 and 1991.

    The two cable stations (at Oteranga Bay and Fighting Bay) were initially built in 1965, and

    new cable terminal buildings added in 1991. Their nominal life expectancy is 30 years, from

    1991.

    Life expectancy is the nominal life established for fixed asset accounting purposes. It

    represents the typical average life that is expected from a type of equipment before it is no

    longer fit to remain in service. Yet some assets may be useful for much longer. The average

    age of the in-service fleet is approximately 22 years as of June 2013, with details of eachcable shown in Table 4.

  • 8/12/2019 Fleet Strategy - HVDC

    15/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 12 of 54

    Cable Installation Nominal Life Expectancy

    Cable 4 1991 35 years

    Cable 5 1991 35 years

    Cable 6 1991 35 years

    Table 4: Age Profile of Submarine Cables

    2.1.5 Spares

    We have ample spares for the Pole 2 primary equipment, and a large amount of spares for

    Pole 3. The spares are predominantly stored at Bunnythorpe and Addington warehouses

    along with storage at the Haywards and Benmore sites. The total number of spares stored

    for the HVDC systems is much too large to include in this document and cannot be easily

    summarised because of the different types of assets required. Subsection 4.1.2 provides

    information on new spares required to be purchased during RCP2.

    Converter stations

    A very small amount of the HVDC station equipment is compatible with assets on the AC

    system, so specialised spares are mostly required. Table 5 shows some of the most

    important spares currently kept for the converter stations.

    Asset Number Status

    Smoothing reactor 2New as of 1991, can be used as spare for Pole 2 orPole 3, although one of the spares has beendamaged.

    Circuit breakers Multiple sparesSpares are held for filter bank circuit breakers,transformer circuit breakers, DC circuit breakers, andAC circuit breakers (for Pole 2 and Pole 3).

    Capacitor cans Multiple sparesCapacitor cans are specialised and not available offthe shelf, so we have a number of spares for thevarious types used in the HVDC system.

    Table 5: Examples of converter station spares

    One of the spare smoothing reactors has been damaged and it is likely that it is uneconomic

    to repair. We intend to replace the damaged reactor within RCP1.

    Electrode stations

    We hold approximately 25m3of coking coal in the event that the coking coal surrounding the

    electrodes is eroded away due to electrochemical reaction. The electrochemical erosion

    mainly occurs during mono-pole operation of the HVDC link at Bog Roy electrode station.Specialised low sulphur coal is required to minimise the corrosion of the electrodes, and this

    is difficult to procure at short notice. In addition, as the suppliers mostly supply large

    amounts to the steel-making industry, their distribution systems are not set up for small

    customers like Transpower.

    We recycle the electrode arm materials where possible, and retain one spare electrode arm

    at all times.

    As other electrode station equipment such as cables, roof bushings, switches, resistors and

    capacitors are readily available from suppliers, spares holdings are not required.

  • 8/12/2019 Fleet Strategy - HVDC

    16/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 13 of 54

    Submarine cables and cable stations

    We hold a total of 3.6 km of HVDC submarine cable as spares at the Miramar cable store

    (one 2.4 km length and one 1.2 km length). The usefulness of these spares for repair of a

    cable fault in deep water is dependent on the ability to quickly cap a damaged cable. To limit

    the requirement for spare cable, it is essential to act promptly and prevent water ingress

    further than 1.2 km in both directions from the fault.

    For details of the contingency planning for submarine cable repairs, see subsection4.3.4.

    There are two spares available for the critically important roof bushings at each Cable

    Station. There are four roof bushings in service (two at each cable station). They are all the

    same sulphur hexafluoride (SF6) pressurised design. They are all interchangeable, and three

    of the four current spares can be used to replace any of the four roof bushings, while the

    other spare can only be used for Pole 2. We believe that only three spares are necessary, so

    one of these spares will be used to replace an Oteranga Bay roof bushing during RCP2 when

    it reaches the end of its useful life.

    2.2 Asset Characteristics

    The HVDC asset fleet can be characterised according to:

    safety and environmental considerations

    asset criticality

    asset condition

    maintenance requirements

    emerging technologies interaction with other assets.

    These characteristics and the associated risks are discussed in the following subsections.

    2.2.1 Safety and Environmental Considerations

    Safety and environmental considerations are important for asset management as they can

    require costly mitigation if not considered early in asset management planning. The most

    significant safety and environmental considerations for the HVDC asset fleet are:

    Converter valve hallswork at heights:maintenance and inspection of the thyristorvalves and other equipment in the valve halls requires work at considerable heights.

    Each valve hall is equipped with an elevating work platform to enable safe access for

    work at height.

    Converter station fire risk:Converter station explosions/fires have occurredoverseas and are theoretically possible in the valve halls. One of the risk mitigations

    is to provide a water deluge system. It is proposed that the fire water supply systems

    at Haywards and Benmore substations will be upgraded during RCP2 (see

    subsection 4.1.2).

    High land and marine voltage gradients at shore electrode station: Marine voltagegradients, caused by erosion of land electrodes and material build-up on sea

    electrodes, can potentially affect marine life in the vicinity of the shore electrode

    station. However, the design of the Te Hikowhenua shore electrode is such that the

    voltage gradient is very low (less than 7 V/m).

  • 8/12/2019 Fleet Strategy - HVDC

    17/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 14 of 54

    Generation of chlorine gas at shore electrode station: During periods of HVDCoperation when the electrodes at Te Hikowhenua act as an anode, chlorine gas is

    generated in the electrode pits. Service providers working in the pits wear gas

    monitors and allow time for any chlorine gas to dissipate after opening the lids.

    Metal corrosion at land electrode station: A particular problem that one landownernear the Bog Roy electrode station experiences is accelerated corrosion of metal

    earthed assets, such as fences and sheds. We actively work with that landowner to

    mitigate the effects.

    2.2.2 Asset Criticality

    Asset management is adapted to recognise the differing levels of criticality to mitigate the

    risk of failures at critical sites and corridors and to potentially reduce expenditure on assets

    that are less critical. We have established a framework for assigning Asset Criticality for

    transmission assets, which classifies the assets as high, medium, or low criticality.

    The asset criticality framework is at an early stage of development. At this stage we haveassigned all assets within the HVDC fleet as low criticality because a failure of the HVDC

    system will not usually result in interruptions for customers. Yet we recognise that the HVDC

    system is a special case where very rare failures can lead to widespread under-frequency

    load shedding, and less severe failures can result in a substantial change in electricity prices.

    A failure of any part of the HVDC system is generally equally important as it will result in the

    failure of a pole and a steep reduction in the capacity of the link. Yet some assets have

    redundancy built in, such as the control systems and the multiple filter banks. Other

    essential assets have unit spares, such as the converter transformers, available. The neutral

    earth circuit is particularly critical to HVDC reliability, because it is common to both poles,

    and its failure could result in an outage of both HVDC poles. We take these factors intoconsideration in the planning phase of the asset management lifecycle for the HVDC fleet.

    There are scenarios in which the relative criticality of the HVDC link could rise. For example,

    if a large amount of generating capacity in the North Island failed (such as the Huntly power

    station), the HVDC link could become essential for maintaining electricity supply in the North

    Island.2

    2.2.3 Asset Condition

    The following discussion outlines the condition of the HVDC asset fleet as at 30 June 2013.

    Converter stations

    The Pole 3 Converter Stations were constructed between 2011 and 2013 and are therefore

    in excellent condition. The outages and site access required by the Pole 3 project provided

    an opportunity to replace Pole 2 equipment that was nearing the end of its life. So the

    individual assets at the Pole 2 converter stations are generally in good condition and the

    majority of the main equipment items should achieve their expected design life of 30 years.

    Further life-extending refurbishments are possible on some of these items.

    2 There is currently sufficient generating capacity for the North Island within the North Island, but the HVDC link is

    employed to utilise generation from the South Island with a much lower marginal cost. This generally involves hydroand wind generation compared with thermal generation in the North Island.

  • 8/12/2019 Fleet Strategy - HVDC

    18/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 15 of 54

    Pole 2 Thyr istor valve water cool ing sy stem

    At the time of original commissioning in 1991, it was recognised that the design of the Pole 2

    thyristor valves creates a flow of a small electrolytic current in the cooling water pipes of the

    valve cooling system. This electrolytic current causes corrosion of the stainless steel

    couplings in the valve cooling system. These couplings are critically important componentsthat distribute cooling water to the thyristor valve layers. In the early 1990s, corrosion in

    similar components in another HVDC thyristor valve was identified as the probable cause of

    cooling water leakage, flashover and failure of the complete thyristor valve. Since

    commissioning Pole 2 in 1991, we have monitored corrosion rates annually by sampling 6

    out of 194 couplings at each converter station. The water treatment plant is critical to the

    thyristor valve cooling systems and the number of instrumentation faults has increased.

    There are also other aspects of the water cooling system that are degrading to a condition

    that will require replacement and/or refurbishment over RCP2 (see subsection 4.1.2 for our

    strategy to respond to these issues).

    Pole 2conv er ter transformers

    The converter transformers are in a good condition, as expected for their age. Yet the

    condition of some components, such as the diverter switches, is deteriorating. The condition

    of the tap changers may also be deteriorating, although reliable assessment will require the

    detailed evaluation that we have planned for the RCP2 period (see subsection 4.4.3).

    The demands of the electricity market require frequent changes in HVDC power transfer.

    These changes require frequent diverter switches of the converter transformers. There are

    approximately 17,000 diverter switch operations annually on each of the six in-service

    converter transformers. The diverter switches operate in oil and the oil quality deteriorates

    slightly with each operation. Major diverter switch refurbishments are required at

    approximately every 450,000 operations. The Pole 2 converter transformer diverter switcheshave approximately 350,000 operations and are due for refurbishment during the RCP2

    period.

    The condition of the transformer oil is very important to the performance of the

    transformers and for maximising their useful lives. It is also an important consideration

    because of the scaleeach converter transformer bank contains 240,000 litres of oil. The

    condition of the transformer oil was recently assessed, showing that it is in very good

    condition. It is clear, of a normal colour, has low moisture levels, is not acidic, and shows no

    signs of sludge. Even so, the dielectric breakdown voltage is becoming lower than ideal. We

    expect that the condition of the oil will remain reasonable through RCP2, although we will

    continue to monitor it to identify if any filtering of the oil is required.

    Pole 2 f i l ter bank circu i t breakers

    Frequent changes of HVDC power transfer also require frequent switching of the Pole 2 filter

    bank circuit breakers. There are 10 circuit breakers and they operate between 150 and 750

    times each year. The original circuit breakers had design lives of 2,000 operations or 35 years

    in service.

    Four of the original circuit breakers were replaced (two in 2005 and two in 2012) with

    10,000 operation breakers. Other circuit breakers were refurbished to extend their lives to

    cover the next 2,000 operations. As of March 2013, of the 10 circuit breakers four have less

    than half of their life expectancy operations remaining while the other six have most of their

    maximum operations remaining. A number of the circuit breakers are expected to reach

  • 8/12/2019 Fleet Strategy - HVDC

    19/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 16 of 54

    their maximum number of operations during RCP2, and their replacement and

    refurbishment is discussed in subsection 4.1.2.

    Pole 2 Reactors

    The reactors in the HVDC Pole 2 system are all air-cored. They were commissioned in 1991and are in good condition.

    Electrode stations

    The condition deterioration of the electrodes depends on the cumulative amount of

    electrode current passed through them over time. When the HVDC link is in balanced

    current operation, the electrode current is very small and there is only very slow

    degradation of the electrodes. During unbalanced operation, and particularly during mono-

    pole operations, there can be significant currents and rapid degradation.

    Bog Roy electrode stat ion

    The Bog Roy electrode generally operates as an anode during current flow because theHVDC flow is usually northwards. During anode operation, electrolytic action erodes the

    steel rods buried in the ground that make up its electrode arms. There has been significant

    erosion and breakage of the electrode arms. The eroded arms have to be replaced and it is

    essential to monitor the electrode condition to determine their priority for replacement. The

    land electrode erosion rate at Bog Roy during mono-pole operation is 15 to 18 times higher

    than during balanced operation.

    After Pole 1 was decommissioned, and prior to the commissioning of Pole 3, the HVDC link

    was operating in mono-pole operation for an extended period. This led to significantly

    increased rate of deterioration of the electrodes, involving more frequent maintenance and

    progressive replacement of the buried electrode arms.The strategy for further refurbishment of the Bog Roy electrode arms is set out in

    subsection4.1.2.

    Te Hikow henua electrode stat ion

    The Te Hikowhenua land electrode provides a return path to earth for DC current when only

    one HVDC pole is operating or when current flow between the two poles is unbalanced.

    The electrode operated as a cathode for an extended period following the decommissioning

    of Pole 1, when the HVDC system was in a mono-pole configuration and only Pole 2 was

    operating. The long periods of operation as a cathode led to the build-up of a thick layer of

    magnesium and calcium hydroxide on the 42 four metre-long high silicon chromium iron

    electrodes that are buried in the beach. This build-up of deposits degraded the electrode

    performance, and required regular maintenance.

    All the sea electrodes were replaced in 2007, so they are (as of 30 June 2013) in good

    condition aside from the continued accumulation of magnesium and calcium hydroxide

    during any periods of operation as a cathode. Following the commissioning of Pole 3 this will

    no longer be such a significant issue.

    Cables and cable stations

    Oteranga Bay cable stat ion

    The HVDC cable station at Oteranga Bay faces severe environmental conditions, with regulargale-force and storm-force winds. In storm conditions, heavy salt deposition occurs. This

  • 8/12/2019 Fleet Strategy - HVDC

    20/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 17 of 54

    location rates as one of the most demanding operational HVDC sites worldwide in terms of

    environmental conditions, and cannot be directly simulated by any HVDC electrical

    equipment tests. The high wind speed and constant wind-borne salt pollution significantly

    reduces the life of the roof and cladding of the cable station buildings, and places high

    stresses on the HVDC roof bushings.

    The extreme environmental conditions have led to severe corrosion of the exterior walls and

    roof cladding of the cable station building, particularly around the edge of the building, and

    the building is no longer weather-tight. This is a particular issue during high winds. Water is

    also entering the building due to the failure of corroded flashing, which consists of thinner

    material than the main roofing material.

    The strategy for the roof and cladding of the Oteranga Bay building is set out in

    subsection4.1.2.

    The Oteranga Bay Pole 2 350 kV roof bushings have previously been replaced at

    approximately 4-year intervals because of the harsh environment. The replacements have

    included several different types of bushing as we have attempted to find a design that suitsthe environment. The latest roof bushing is a composite bushing designed to withstand wind

    speed up to 300 km/h and has improved material properties. It has been in service since

    February 2006. The roof bushings require regular extensive cleaning (annually and after

    large storms) to maintain their hydrophobicity, as there have been several incidents of

    arcing due to salt deposition in the past.

    Fight ing Bay cable stat ion

    The Fighting Bay cable terminal station has a much less severe climate than the Oteranga

    Bay site, and consequently there are less stresses on the insulation of the roof bushings.

    Both of the roof bushings have recently been replaced with polymer bushings so are in good

    condition. The building cladding is currently in good condition and does not require anyrefurbishment or replacement in the foreseeable future.

    Submar ine cables

    Surveys using an ROV show that the three power cables are in good condition and generally

    well supported by the seabed. Due to the nature of the marine environment, corrosion of

    areas of exposed armouring on the cables is expected, with cathodic protection needed on

    the cables.

    Yet the ROV surveys and diving inspections have shown virtually no corrosion of the

    armouring to date. No further natural cathodic protection investigations are planned, and

    neither is any further prevention action planned at this stage because the evidence showsthat, at present, corrosion does not appear to be a significant issue. Currently, cables 4 and 5

    are undamaged and in good condition while cable 6 has had one fault repair undertaken.

    2.2.4 Maintenance Requirements

    This subsection describes the maintenance requirements of the HVDC asset fleet, including

    the underlying drivers and rationale. These requirements have informed the maintenance

    strategies discussed in section 4.4. This subsection also sets out a high-level overview of

    historic maintenance expenditure for these activities.

    The most common types of maintenance carried out on these assets are:

    preventive maintenance, including:- line patrols and condition assessments

  • 8/12/2019 Fleet Strategy - HVDC

    21/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 18 of 54

    - servicing

    corrective maintenance, including:

    - fault response

    - repairs

    maintenance projects.

    Maintenance projects are programmes of works (essentially made up of small projects) used

    to address repetitive issues identified through preventive and corrective maintenance.

    The Maintenance Lifecycle Strategy provides further details on our approach to the above

    maintenance works, and the specific maintenance requirements are included in the relevant

    service specification documents.

    Preventive maintenance

    The following sections discuss the preventive maintenance works on each major asset type.

    Converter stat ions

    Preventive maintenance of the converter station assets is planned on a regular basis, with

    the frequency dependent on the type and known condition of the asset. We schedule an

    annual maintenance outage in summer when demand for inter-island HVDC transfer is

    relatively low. The majority of maintenance works are carried out then. Regular condition

    assessments undertaken for the converter station assets may include:

    periodic visual inspections

    thermographic checks

    out-of-service diagnostic inspections

    transformer dissolved gas analysis (DGA)

    continuous monitoring of the performance of the HVDC cooling systems via thevalve cooling control systems

    thyristor diagnostic inspection in line with manufacturer requirements

    frequent inspections of filter bank circuit breakers because of the high frequency ofswitching required.

    Electrode stat ions

    The Te Hikowhenua electrode station has undergone 3-monthly lifting inspections of the

    2 pilot electrodes and 6-monthly lifting and cleaning of salt deposits on all electrodes while

    the system has been operated as mono-pole. With the operation of Pole 3 and return to

    bipolar operation, cleaning will only be carried out as required.

    Cable stat ion s

    Preventive maintenance of the cable terminal stations is usually planned around annual

    shutdowns.

    Regular condition assessments undertaken on the roof bushings include:

    visual and UV camera inspection

    monitoring of corrosion in the sealing and central flange area

  • 8/12/2019 Fleet Strategy - HVDC

    22/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 19 of 54

    hydrophobicity testing

    monitoring of internal bushing gas pressure and top-up intervals

    bushing gas analysis.

    Roof bushings are also regularly cleaned to maintain hydrophobicity at a required level.

    Submar ine cables

    Maintenance of submarine cables is complicated by the marine environment, requiring

    specialised equipment and techniques such as the ROV and divers.

    The submarine cables can be severely damaged by contact with fishing trawling devices or

    ship anchors. So preventive maintenance of the submarine cables includes regular patrolling

    of the area by vessel and helicopter to identify and deter ships (particularly trawlers) from

    operating illegally in the vicinity of the submarine cables. The marine patrol enforces the law

    prohibiting fishing and anchoring within the CPZ and educates ship operators in the area on

    CPZ law. The Ministry of Transport undertakes prosecutions for illegal fishing activity in theCPZ, based on evidence provided by the patrol vessel. One third of each cable is condition

    assessed each year using an ROV and diver (so every cable is assessed in any 3-year period).

    This has been dependent on the weather and the availability of resources. At times,

    condition assessments have been delayed when resources have been diverted to repairs to

    the HVDC or fibre optic cables.

    Also, there is a need to move sandbags and other protective equipment every 2 to3 years

    because the seabed conditions change over time. An electrical cable test is undertaken every

    10 years, with the last one being carried out in 2011.

    Corrective maintenance

    We carry out a wide range of corrective maintenance due to the diverse types of assets

    included in the HVDC fleet. Corrective work ranges from the relatively simple replacement of

    failed assets, such as capacitor cans, through to major repairs and replacement of complex

    assets, such as the converter transformers and submarine cables.

    In some cases, corrective work requires the involvement of overseas technicians and

    experts, particularly those from the original equipment manufacturers.

    One of the largest and most complex cases of corrective maintenance is submarine cable

    repair. In 2005 we repaired a submarine cable fault in shallow water in Oteranga Bay. This

    was a large and complicated procedure supported by overseas expertise, and required

    maintenance support equipment to be custom-built for the procedure, including the retrofit

    of a barge.

    The repair of a cable fault in deep water would be more difficult and complicated, requiring

    specialist vessels and equipment from overseas. It is important to quickly cut and cap the

    cable in the event of a cable fault, to prevent excessive water ingress. In deep water, the

    water ingress could be relatively rapid, reaching a length beyond the length of spare cable.

    This would necessitate purchasing replacement cable. Procurement of submarine cable can

    take 2 to 3 years. Repairs will generally need to be made in relatively calm weather, and may

    not be possible in winter. Depending on the time of the year and the complexity of the

    repair, it could take between 3 and 9 months to repair a cable.

  • 8/12/2019 Fleet Strategy - HVDC

    23/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 20 of 54

    Maintenance projects

    Maintenance projects typically consist of relatively high value planned repairs or

    replacements of components of larger assets. Maintenance projects would not be expected

    to increase the original design life of the larger assets. Maintenance jobs are typically run as

    a project where there are operational and financial efficiencies from doing so. The drivers

    for maintenance projects include asset condition, mitigating safety and environmental risks,

    and to improve performance.

    A number of maintenance projects have been undertaken for the HVDC fleet, including:

    Haywards maintenance projects:

    - reactor painting

    - busbar corrosion

    Benmore maintenance projects:

    - Supervisory Control and Data Acquisition (SCADA) cards repairs

    - valve busbar corrosion.

    The maintenance projects planned for the RCP2 period are described in subsection 4.4.3.

    2.2.5 Interaction with Other Assets

    The HVDC system is mostly physically separate from the rest of the transmission system

    assets. However, a number of assets in or associated with the converter stations (including

    synchronous condensers, AC power transformers, AC switchyard equipment and

    Transmission Lines) are covered by other asset strategies. These assets need to be managed,

    taking into account any interactions with the HVDC system and any additional performance

    or spares holding requirements.

    The HVDC system is reliant on reactive power assets, particularly the Haywards synchronous

    condensers and STATCOM and the transmission circuits around them.

    2.3 Asset Performance

    This section describes the historic performance of the HVDC fleet together with any risks and

    issues.

    2.3.1 Reliability Performance

    Achieving an appropriate level of reliability for our asset fleets is a key objective, as itdirectly affects the services received by our customers.

    Failure of the assets within the HVDC asset fleet can lead to an outage of the inter-island

    connection or a portion of the connections capacity.In many cases this would lead to a

    large price discrepancy in the electricity market, between the North Island and the South

    Island.

  • 8/12/2019 Fleet Strategy - HVDC

    24/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 21 of 54

    Major failures

    Converter stat ions

    There have been no major failures at HVDC stations between 1990 and 2012. We define

    major failures as those that have caused a long-term (greater than one week) outage of atleast one pole.

    Electrode stat ions

    There have been no failures of the electrode stations significant enough to cause an outage

    of the HVDC link.

    Submar ine cables and cable stat ions

    HVDC submarine cable performance has been very reliable, with only one failure due to an

    internal electrical faultin Cable 6 in October 2004. There have been no failures

    attributable to mechanical damage. The 2004 cable failure reduced the capacity of the HVDC

    link from 1,040 MW to 886 MW. The failure occurred in shallow water in Oteranga Bay, andthis meant it was feasible to undertake repairs by converting a locally available barge. The

    repairs to Cable 6 took almost six months.

    The greatest risk to the cables is damage caused by boats illegally fishing or anchoring in the

    area. While the current cables have not failed due to boat activity, it is suspected that the

    failure of one of the old decommissioned cables in 1991 (Cable 2) was caused by a fishing

    operation. The Maintenance section (section 4.4) describes the activities that will be

    undertaken to reduce the risk of this occurring.

    The original Pole 2 350 kV porcelain roof bushing at the Oteranga Bay Cable Station failed in

    service in 1996 after only four years of service, damaging the building and causing a lengthy

    forced outage. Replacement roof bushings using composite technology have been installedand, although there have been problems with deteriorating condition, there have been no

    further major failures.

    Availability

    The availability of the HVDC link varies from year to year, depending on the number and

    length of planned and forced outages. The availability from 2003/04 to 2011/12 is shown in

    Figure 2.

    Figure 2: HVDC Annual Availability

    75%

    80%

    85%

    90%

    95%

    100%

    2003/04 2005/06 2007/08 2009/10 2011/12

    HVDC AVAILABILITY

  • 8/12/2019 Fleet Strategy - HVDC

    25/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 22 of 54

    Pole 1 was generally less reliable than Pole 2 towards the end of its operation. Pole 1 was

    decommissioned in September 2007, which is why the availability is higher after 2007 when

    the data only relates to Pole 2. In 2010/11 and 2011/12 the availability was lower than

    previous years because a relatively large number of planned outages were required for the

    construction of Pole 3.

    2.3.2 Safety and Environmental Performance

    Subsection 2.2.1 described the characteristics of the HVDC assets that impact safety and

    environmental performance. This subsection reports on the actual safety and environmental

    performance of the fleets.

    There have been no major safety incidents involving the HVDC fleet in recent years.

    The number and nature of environmental incidents involving the HVDC assets have not been

    clearly recorded in the past, although recording and management of this information has

    begun recently so future versions of the fleet strategy will be able to provide improved

    environmental performance data.

    2.3.3 Risks and Issues

    This subsection briefly discusses the most significant risks and issues facing the asset

    management of the HVDC asset fleet.

    Strategies to manage these risks and issues are set out in chapter4.

    Submar ine cables r isk posed by m ar ine vessels

    The main risk to the submarine cables is damage caused by fishing activity where heavy

    trawl nets and associated equipment makes contact with the cables. There is also potential

    for anchor damage from large and small vessels to place the cables at risk.

    The Submarine Cables and Pipelines Protection Act 1996 provides legal protection for a CPZ

    across Cook Strait. In 1995 we started marine patrols of the Cook Strait CPZ, initially focusing

    on the hoki fishing season from June to September. Incidents of damage to the submarine

    fibre optic cables, and efforts by fishermen to circumvent the part-time patrol led to full-

    time patrolling, which has now been in place for some years.

    There are about 4,000 vessel movements in the vicinity of the cables every year. Roughly

    300 of these are of interest for gathering of evidence of possible infringements, and around

    20 require follow-up. Information about alleged infringements is passed to the Ministry of

    Transport. There is a prosecution every 1 to 2 years. The marine patrol service includes

    continuing efforts to communicate with the fishing industry to help mitigate risk.The cables are laid separately to minimise the likelihood of all three cables being damaged in

    one incident.

    Consequences of subm ar ine cable fai lure

    There is no backup for the submarine power cables and restoration times range from at least

    6 months for a repair to 24 months for total replacement. Failure of any one power cable

    can result in a reduction in HVDC cable capacity to 1000 MW (there are 3 cables, each rated

    to carry 500 MW). The current total capacity of the link is 1,000 MW due to other

    constraints, but this is due to increase to 1,200 MW by the end of 2013 when the new

    Haywards STATCOM is commissioned. So a cable failure in the immediate future would

    reduce redundancy but not reduce the capacity of the link. It should also be noted that 84%of the time the transfer on the HVDC link is less than 500 MW.

  • 8/12/2019 Fleet Strategy - HVDC

    26/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 23 of 54

    Severe environment at Oteranga Bay cable stat ion

    The HVDC cable station at Oteranga Bay faces severe environmental conditions, with regular

    gale-force and storm-force winds from north and south. The high wind speed and constant

    windborne salt pollution significantly reduces the life of the outdoor roof bushings.

    The harsh environment also affects the speed of deterioration of the station building

    cladding. As outlined in subsection 2.2.3, the building cladding at Oteranga Bay is currently

    in poor condition and needs to be replaced in the next five years.

    In response to the extreme environmental conditions, maintenance activities for the

    Oteranga Bay cable station are more regular to identify any rapidly accelerating corrosion. In

    addition, the design of new assets for the site must carefully consider the environmental

    factors. For example, we are planning to replace the current corroded roof cladding with

    aluminium cladding, which has superior corrosion resistance compared to most cladding

    options.

    The strategy for the Oteranga Bay cable station building is set out in subsection4.1.2.

    Cable stat ion s roof bush ings

    HVDC transfer depends heavily on the performance of the roof bushings at the cable

    stations. The cable stations are located in remote areas and have difficult access for the

    heavy lifting equipment that is required for bushing replacement. If there is an emergency

    that requires a bushing replacement at short notice, a forced outage will be required for at

    least three days.

    Pole 2 VBE and TCUs

    Once stage 2 of the Pole 3 project is complete, the Pole 2 VBE and TCUs will be the only 1990

    vintage controls left in the HVDC system because the other parts of the control system are

    being replaced as part of the Pole 3 project. The VBE and TCUs are critical parts of the

    control system and are nearing the end of their useful lives as they have a design life of

    approximately 20 years. We have very limited spares for this equipment and there is a risk

    that failure rates will start to increase due to age-related condition deterioration. It is

    becoming increasingly difficult to procure spares because of the age of the equipment.

    The strategy for the Pole 2 VBE and TCUs is set out in subsection4.1.2.

    Pole 3 seism ic resil ience

    The new Pole 3 equipment has been designed to withstand higher-intensity earthquakes

    than Pole 2 (1 in 2,500 compared to 1 in 1,000 year event). In addition, the seismic resilience

    of Pole 2 equipment was estimated by analysis alone, while Pole 3 equipment had its seismicresilience estimated with the use of shake table testing.

    In the event of a relatively large earthquake, it is expected that Pole 3 could continue to

    operate while Pole 2 may not. Yet Pole 3 is dependent on several parts of the Pole 2 system

    (that lack readily available spares). In particular, the Haywards switchyard B insulators and

    disconnectors are a seismic risk for Pole 2 and Pole 3.

    The strategy for improving the seismic performance of Pole 2 equipment is set out in

    subsection4.1.2.

    Pole 2 Thyr istor valve water cool ing sy stem

    The Pole 2 thyristor valve uses stainless steel couplings in its cooling water distributionsystem. In the early 1990s, corrosion in similar components in another HVDC thyristor valve

  • 8/12/2019 Fleet Strategy - HVDC

    27/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 24 of 54

    was identified as the probable cause of cooling water leakage, leading to flashover and

    catastrophic failure of the complete thyristor valve. Condition assessment of the stainless

    steel couplings in the Pole 2 valves has identified increased corrosion and accumulation of

    aluminium hydroxide.

    Since the time of Pole 2 commissioning in 1991, there has been annual monitoring of

    corrosion rates by sampling of 6 out of 194 couplings at each converter station. Programmes

    of complete replacement of these couplings have been undertaken, and annual condition

    monitoring continues, to ensure that this risk is managed.

    HVDC capaci ty c onstra ints

    The commissioning of the Pole 3 converter stations has substantially increased the capacity

    of the inter-island HVDC link to 1,000 MW. Yet the capacity of the link is still constrained by

    several factors, including voltage stability, capacity of existing submarine cables, and the

    overload capability of Pole 2.

    The capacity will be extended to 1,200 MW by 2014, on completion of Stage 2 of the Pole 3project.

    Long-term future studies, as outlined in subsection4.1.1,will assess the economic case for

    further investment to relieve other constraints so as to provide additional inter-island HVDC

    capacity.

  • 8/12/2019 Fleet Strategy - HVDC

    28/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 25 of 54

    3 OBJECTIVES

    Chapter 3 sets out asset management related objectives for the HVDC fleets. As described in

    section 1.4, these objectives have been aligned with our corporate management objectives,

    and higher-level asset management objectives and targets as set out in the Asset

    Management Strategy.

    Our overarching vision for the HVDC fleet is to provide an energy balancing system that

    matches generation and demand in the North Island and the South Island. In addition, the

    HVDC link facilitates the transfer of renewable energy from the South Island generation

    centres to the North Island load centres. Further objectives have been defined in the

    following five areas:

    Safety

    Service performance Cost performance

    New Zealand communities

    Asset management capability.

    These objectives are set out below, while the strategies to achieve them are discussed in

    chapter 4.

    3.1 Safety ObjectivesWe are committed to becoming a leader in safety by achieving injury-free workplaces for our

    employees and to mitigate risks to the general public. Safety is a fundamental organisational

    value and we consider that all incidents are preventable.

    Safety Objectives for HVDC Fleets

    - Zero medical treatment injuries arising from the maintenance or operation of theHVDC assets.

    - Ensure that risks to the public from the operation of HVDC ground electrodes are aslow as reasonably practical.

    3.2 Service PerformanceEnsuring appropriate levels of service performance is a key underlying objective. The overall

    service performance objectives for the Grid in terms of Grid Performance (reliability) andAsset Performance (availability) are set out in the Asset Management Strategy.

    Grid performance objectives state that a set of measures are to be met for Grid Exit Points

    (GXPs) based on the criticality of the connected load. In addition, asset performance

    objectives linked to system availability have been defined, including a target of 97.5% HVDC

    system availability during RCP2.

  • 8/12/2019 Fleet Strategy - HVDC

    29/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 26 of 54

    Service Performance Objectives for HVDC Fleets3

    Availability

    - Pole 3 forced energy unavailability: 0.5% or less.

    - Pole 2 forced energy unavailability: 0.5% or less.

    - Pole 3 scheduled energy unavailability: 1.0% or less.

    - Pole 2 scheduled energy unavailability: 1.0% or less.

    Outage rates

    - Pole 3 forced outage rate: 5 outages or less each year.

    - Pole 2 forced outage rate: 5 outages or less each year.

    - Bi-pole forced outage rate: 0.1 outages or less each year.

    Grid effects

    - Minimal harmonic distortion.

    - Minimal interference to customer ripple control systems.

    3.3 Cost PerformanceEffective asset management requires optimising lifecycle asset costs while managing risks

    and maintaining performance. We are committed to implementing systems and decision-

    making processes that allow us to effectively manage the lifecycle costs of our assets.

    Cost Performance Objectives for HVDC Fleets

    - Minimise whole-of-life cost in asset management decision making (such as evaluationof replacement versus refurbishment, and capital versus maintenance expenditure).

    - Minimise cost of major submarine cable repairs by maintaining necessary resourcesto undertake a prompt cut and capoperation in the event of a fault.

    3.4 New Zealand CommunitiesAsset management activities associated with the HVDC fleets have the potential to impact

    on both the environment and on the day-to-day lives of various stakeholders. Relationships

    with landowners and communities are of great importance to us and we are committed to

    using asset management approaches that protect the natural environment.

    New Zealand Community Objectives for the HVDC Fleets

    - No noise complaints from the public regarding the converter stations.

    - No significant release of oil to the environment.

    - SF6emissions as low as reasonably practical.

    - Reduced corrosion impacts of the Bog Roy electrode on the neighbouring farm.

    3

    These targets only cover the performance of the converter stations, and exclude outages of the HVDCassets caused by faults in other fleets, such as faults in the transmission line conductors.

  • 8/12/2019 Fleet Strategy - HVDC

    30/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 27 of 54

    - Effective relationships with landowners of the access routes to cable terminal andelectrode stations.

    - Effective relationships with the fishing industry in relation to the CPZ.

    3.5 Asset Management CapabilityWe aim to be recognised as a leading asset management company. To achieve this, we have

    set out a number of maturity and capability related objectives. These objectives have been

    grouped under a number of processes and disciplines that include:

    Risk Management

    Training and Competency

    Asset Knowledge

    Continual Improvement and Innovation.

    The rest of this section discusses objectives in these areas relevant to the HVDC fleets.

    3.5.1 Risk Management

    Understanding and managing asset-related risk is essential to successful asset management.

    We currently use asset criticality and asset health as proxies for a fully modelled asset risk

    approach.

    Asset criticality is a key element of many asset management systems. We are currently at an

    early stage of developing and implementing the approach as we work towards formal and

    consistent integration of asset criticality into the asset management framework.

    Asset health has not yet been implemented for the HVDC fleets.

    Risk Management Objectives for HVDC Fleets

    - Up-to-date assessment of spares requirements and current availability.

    - Reduced likelihood of a bi-pole fault.

    - Development of criticality framework to differentiate HVDC assets.

    3.5.2 Asset Knowledge

    We are committed to ensuring that our asset knowledge standards are well defined to

    ensure good asset management decisions. Relevant asset knowledge comes from a varietyof sources including experience from assets on the Grid and information from the

    manufacturers. This asset knowledge must be captured and recorded in such a way that it

    can be conveniently accessed.

    Asset Knowledge Objectives for HVDC Fleets

    - Comprehensive understanding and experience of Pole 3 assets recorded.

    3.5.3 Training and Competency

    We are committed to developing and retaining the right mix of talented, competent and

    motivated staff to improve our asset management capability. This is particularly importantfor the HVDC fleet because of the specialised nature of the knowledge and work required.

  • 8/12/2019 Fleet Strategy - HVDC

    31/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 28 of 54

    Training and Competency Objectives for HVDC Fleets

    - Service providers suitably qualified for work on specialised HVDC assets.

    3.5.4 Continual Improvement and Innovation

    Continual improvement and innovation are important aspects of asset management. A large

    source of continual improvement initiatives will be ongoing learning from our asset

    management experience.

    Continual Improvement and Innovation Objectives for the HVDC Fleets

    - Development of understanding in regards to HVDC and dynamic and variable linerating.

    - Improved long-term strategic planning approach to capital investment, such as thetiming for the fourth submarine cable.

  • 8/12/2019 Fleet Strategy - HVDC

    32/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 29 of 54

    4 STRATEGIES

    Chapter 4 sets out the specific strategies for the management of the HVDC fleet. These

    strategies are designed to support the achievement of the objectives in chapter 3 and reflect

    the characteristics, issues and risks identified in chapter 2.

    The strategies are aligned with our lifecycle strategies below and the chapter has been

    drafted to be read in conjunction with them.

    Planning Lifecycle Strategy

    Delivery Lifecycle Strategy

    Operations Lifecycle Strategy

    Maintenance Lifecycle Strategy

    Disposal Lifecycle Strategy

    This chapter also discusses personnel and service provider capability related strategies which

    cover asset knowledge, training and competence.

    Scope of Strategies

    The strategies focus on expenditure that is planned to occur over the RCP2 period (2015

    2020), but also include expenditure from 1 July 2013 to the start of the RCP2 period and

    some expenditure after the RCP2 period (where relevant). Capex planned for the RCP2

    period is covered by the strategies in sections 4.1 and 4.2, and opex is covered by the

    strategies in sections 4.3 to 4.6. The majority of the capex consists of asset replacements,

    which is described in subsection 4.1.2.

    4.1 Planning

    This section describes our strategies for the Planning lifecycle.

    Planning activities

    Planning activities are primarily concerned with identifying the need to make capital

    investments in the asset fleet. The main types of investment considered for this fleet are

    enhancement, development, replacement, and refurbishment works.

    We support the planning activities through a number of processes, including:

    Integrated Works Planning (IWP)

    cost estimation.

    The planning lifecycle strategies for the HVDC fleet are described in the subsections below.

    Capital investment drivers

    Categories of capital investment generally have specific drivers or triggers that are derived

    from the state of the overall system or of individual assets. These drivers include demand

    growth, compliance with Grid reliability standards and failure risk (indicated by asset

    criticality and condition). Specific examples that drive capital investment in the HVDC asset

    fleet include:

  • 8/12/2019 Fleet Strategy - HVDC

    33/57

    HVDC Fleet StrategyTP.FS 46.01

    Issue 1October 2013

    HVDC FLEET STRATEGY

    Transpower New Zealand Limited 2013. All rights reserved. Page 30 of 54

    asset replacement, driven by condition

    increased capacity requirements, driven by demand for HVDC energy transfer

    enhancement of existing assets, driven by safety and performance.

    4.1.1 Enhancement and Development

    This subsection describes enhancement and development investments for the HVDC fleet.

    Enhancement and development investments in HVDC assets have been undertaken in

    response to a number of drivers including supply and demand forecasts, and the need to

    maintain appropriate levels of availability.

    Supply and demand forecasts determine the required capacity and associatedinvestments for the inter-island link.

    The need to maintain appropriate levels of availability sometimes involves newimproved equipment, while in other cases it involves auxiliary and maintenance

    equipment to help support the reliability of the HVDC equipment.

    The strategies below consider the long-term implications for these drivers as we extend our

    planning horizon as part of our programme of asset management improvement.

    Pole 3 Project

    Continue the Pole 3 project, including stage 2 in 2013/14 and the investigation

    of stage 3.

    With the addition of Pole 3 in 2013, we have substantially increased the capacity of the

    inter-island HVDC link to 1,000 W, although the link is still constrained by several factors,including voltage stability, capacity of existing submarine cables, and the overload capability

    of Pole 2. Stage 2a major capex proposal (MCP)of the Pole 3 project involves replacing

    existing Pole 2 control system (task completed), and improving voltage stability by adding

    filter banks and a STATCOM, which will increase the HVDC capacity to 1,200 MW. Stage 2 is

    due to be commissioned by 2014.

    Stage 3 of the Pole 3 project is currently being considered as a potential MCP. This would

    include at least one more submarine cable, a second STATCOM, and additional filter banks,

    which would allow the HVDC link to operate at 1400 MW. Stage 3 is unlikely to begin before

    the end of RCP3 as supply and demand forecasting suggest that current capacity is expected

    to be sufficient until 2030. This is dependent on a number of factors, such as overall South

    Island demand. Currently, the majority of generation projects being planned until 2020 arebased in the North Island, where the majority of demand growth is expected.4

    One aspect outside the MCP is the upgrade of the RTDS with new processor cards during

    RCP2, which is forecast to cost approximately $100,000.

    4.1.2 Replacement and Refurbishment

    Replacement is expenditure to replace substantially all of an asset. Refurbishment is

    expenditure on an asset that creates a material extension to the end of life of the asset. It

    does not improve its attributes. This is distinct from maintenance work, which is carried out

    4

    A list of all publicly known generation projects is maintained and provided by the Electricity Authority, available fromwww.ea.govt.nz/industry/monitoring/forecasting/long-term-generation-development/list-of-generation-projects/

    http://c/Users/Public/Documents/Write%20client%20work/Transpower/00%20WORKED%20ON%20DOCUMENTS%20AND%20STYLE%20SHEETS/Fleet%20Strategies/www.ea.govt.nz/industry/monitoring/forecasting/long-term-generation-development/list-of-generation-projects/http://c/Users/Publi