fleet strategy - hvdc
TRANSCRIPT
-
8/12/2019 Fleet Strategy - HVDC
1/57
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved.
HIGH VOLTAGE DIRECT CURRENT(HVDC)
Fleet Strategy
Document TP.FS 46.01
16/10/2013
-
8/12/2019 Fleet Strategy - HVDC
2/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved.
C O P Y R I G H T 2 0 1 3 T R A N S P O W E R N E W Z E A L A N D L I M I T E D . A L L R I G H T SR E S E R V E D
This document is protected by copyright vested in Transpower NewZealand Limited (Transpower). No part of the document may bereproduced or transmitted in any form by any means including, without limitation, electronic, photocopying, recording or otherwise,
without the prior written permission of Transpower. No information embodied in the documents which is not already in the public
domain shall be communicated in any manner whatsoever to any third party without the prior written consent of Transpower.Any breach of the above obligations may be restrained by legal proceedings seeking remedies including injunctions, damages and costs.
-
8/12/2019 Fleet Strategy - HVDC
3/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved.
Table of Contents
EXECUTIVE SUMMARY ...................................................................................................................... 1
SUMMARY OF STRATEGIES .............................................................................................................. 4
1 INTRODUCTION ....................................................................................................................... 5
1.1 Purpose ................................................................................................................................. 5
1.2 Scope .................................................................................................................................... 5
1.3 Stakeholders ......................................................................................................................... 7
1.4 Strategic Alignment ............................................................................................................... 7
1.5 Document Structure .............................................................................................................. 8
2 ASSET FLEET .......................................................................................................................... 9
2.1 Asset Statistics ...................................................................................................................... 9
2.2 Asset Characteristics .......................................................................................................... 13
2.3 Asset Performance .............................................................................................................. 20
3 OBJECTIVES .......................................................................................................................... 25
3.1 Safety Objectives ................................................................................................................ 25
3.2 Service Performance ........................................................................................................... 25
3.3 Cost Performance ............................................................................................................... 26
3.4 New Zealand Communities ................................................................................................. 26
3.5 Asset Management Capability ............................................................................................ 27
4 STRATEGIES.......................................................................................................................... 29
4.1 Planning .............................................................................................................................. 29
4.2 Delivery ............................................................................................................................... 38
4.3 Operations ........................................................................................................................... 40
4.4 Maintenance ........................................................................................................................ 43
4.5 Disposal ............................................................................................................................... 50
4.6 Asset Management Capability ............................................................................................ 50
4.7 Summary of RCP2 Fleet Strategies .................................................................................... 53
-
8/12/2019 Fleet Strategy - HVDC
4/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 1 of 54
EXECUTIVE SUMMARY
Introduction
The High Voltage Direct Current (HVDC) link provides a high-capacity connection between
the North Island and South Island electricity systems, enabling the operation of an efficient
national electricity market. We have recently completed a major upgrade of the HVDC link,
with the commissioning of the Pole 3 converter stations at Benmore and Haywards.
The HVDC inter-island link has achieved world-class levels of performance over the years
since the original scheme was commissioned in 1965. Our asset management approach for
the HVDC link seeks to achieve continued high levels of availability and reliability on a
sustainable basis, and to achieve least whole-of-life cost.
Asset fleet and condition assessment
The HVDC converter stations include a diverse range of equipment, some of which is highly
specialised. There are particular challenges in asset management of HVDC equipment,
because of the small population of similar equipment in service (even including similar HVDC
schemes worldwide). There is only a limited experience base on which to build a detailed
understanding of potential failure modes and develop appropriate condition assessment and
risk management strategies.
Further, our customers for the HVDC transmission service require high levels of annual
availability. We typically aim to limit scheduled outages for routine maintenance and
condition assessment to 23 days each year for each pole of the HVDC link.
The HVDC Pole 2 converter stations were commissioned in 1991 and use electrically
triggered thyristor technology. The main circuit equipment in Pole 2 is generally in goodcondition and has considerable remaining life.
However, some subsystems within the Pole 2 converter systems have reached the end of
their expected lives, and replacements or other interventions are now required. One
example is the original control and protection systems in Pole 2 that have recently been
almost completely replaced, as part of the new Pole 3 project.
Some assets within the Pole 2 converter stations undergo frequent mechanical switching as
HVDC transfer varies. Asset management attention is focused on this frequently operated
equipment, to minimise the risk of failure. A programme of special inspections and condition
assessments is used to determine the need for major overhauls and replacements.
The HVDC Pole 3 converter stations were commissioned in May 2013, to fully replace the
mercury-arc valve converters of the original 1965 inter-island transmission scheme. The
Pole 3 converter stations use light-triggered thyristor technology. Asset management
approaches for the Pole 3 equipment will follow the manufacturersrecommendations, and
will be adapted with further operational experience.
The HVDC connection between the North Island and the South Island relies on three HVDC
submarine power cables across Cook Strait. The submarine cables were installed in 1991,
together with new cable terminal stations where the cables connect to the overhead HVDC
transmission line. The underwater environment in Cook Strait is harsh, and the cables are
now more than 20 years old. Yet underwater surveys indicate that the cables are still in good
condition and likely to remain usable beyond their original design life. The most significant
-
8/12/2019 Fleet Strategy - HVDC
5/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 2 of 54
risk to the submarine cables is damage caused by illegal fishing and anchoring in the Cook
Strait Cable Protection Zone (CPZ).
Strategies
The level of capital expenditure (capex) required during RCP2 for the HVDC fleet is expectedto be relatively low because of the good condition of the submarine cables and Pole 2 assets
and the new condition of the Pole 3 assets. This fleet strategy aims to ensure that we
maximise the remaining life of the assets, which is now likely to be greater than the original
design life of the submarine cables and the Pole 2 equipment.
The forecast capex is for some individual assets that require replacement or refurbishment
because they have a shorter life expectancy than the rest of the Pole 2 system, based on
their current condition, age and operation frequency. We will also make some investments
to bring the older Pole 2 assets up to the same standard as the new Pole 3 equipment where
practical and cost efficient, so that we can maximise the benefits of the Pole 3 project.
We will complete Stage 2 of the Pole 3 project as part of the originally approved Pole 3Major Capex Proposal (MCP). The remaining work involves improving voltage stability
through the addition of filter banks and a static synchronous compensator (STATCOM). This
will increase the HVDC capacity to 1,200 MW. Stage 2 is due to be commissioned by 2014.
The Pole 2 valve base electronics (VBE) and thyristor control units (TCUs) are critical
components of the Pole 2 control system. The main control and protection systems in Pole 2
have been replaced as part of the Pole 3 project, but the replacement of VBE and TCUs was
not part of the scope of work. We have very limited spares for this equipment and there is a
risk that failure rates will start to increase due to age-related deterioration. We plan to
replace this equipment during the RCP2 period to ensure continued high levels of reliability.
The Pole 2 filter bank circuit breakers operate frequently, as a result of changes in HVDCpower transfer. Several of the Pole 2 filter bank circuit breakers are expected to reach their
recommended maximum number of operations during RCP2. We plan to replace and
refurbish filter bank circuit breakers before the risk of failure escalates.
The Oteranga Bay Cable Station is located in an extremely harsh coastal environment. The
roof and wall cladding of the building is significantly corroded, and the building is no longer
weather-tight. We plan to re-clad the roof and walls of the cable station to protect the cable
station equipment and ensure reliability.
We will continue to monitor the Cook Strait submarine cables with a variety of approaches,
including a marine patrol of the Cook Strait CPZ to deter and detect illegal fishing and
anchoring. To ensure that we have reliable information about the condition of thesubmarine cables, we will continue with programmes of surveys by Remote Operated
Vehicles (ROVs) and by divers. We are currently investigating alternative approaches to the
maintenance of the submarine cables, to reduce the operating expenditure (opex) required.
Failure of the Cook Strait submarine power cables is a low probability but high-impact risk.
We will maintain contingency plans for undertaking repairs to submarine power cables, and
ensure preparedness to respond promptly and effectively to any cable fault.
Improvements
We have recently made a number of improvements to the asset management of the HVDC
assets.
-
8/12/2019 Fleet Strategy - HVDC
6/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 3 of 54
We have installed a Real Time Digital Simulator (RTDS) that will be used forsupporting operations, and for post-event analysis. It will also be used as a risk
management tool, for testing the effects of proposed changes to HVDC control
system software or settings, before any such changes are implemented at site.
We have established an in-house team of HVDC field engineers to help manage thelong-term risks of retaining an appropriate level of highly specialised skills required
for maintenance and support of the HVDC and power electronics assets.
We have appointed an HVDC Manager, who has responsibility for overview of theasset management of the HVDC asset fleet.
-
8/12/2019 Fleet Strategy - HVDC
7/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 4 of 54
SUMMARY OF STRATEGIES
This section provides a high-level summary of the main asset management strategies andtheir costs during the RCP2 period (20152020) for the HVDC fleet. The three main
strategies summarised below relate to capex.
Capital Expend iture
Replace Pole 2 Valve Base Electronics and Thyristor
Control UnitsRCP2 Cost $7.6m
The VBE and TCUs are critical parts of the control system and are nearing the end of their
useful lives. We have very limited spares for this equipment and failure rates are starting to
increase due to age-related condition deterioration.
Our strategy is to replace the Pole 2 VBE and TCU over RCP2, to improve long-term
reliability.
Over the RCP2 period, we plan to replace the VBE and TCU, together with the connecting
fibre optic links, at an estimated cost of $7.6m.
Replace and Refurbish Pole 2 Filter Bank Circuit
BreakersRCP2 Cost $3.2m
Several frequently operated Pole 2 filter bank circuit breakers are expected to surpass theirrecommended number of operations during RCP2.
Our strategy is to replace and refurbish filter bank circuit breakers before the risk of failure
escalates.
The plan will involve replacing 5 filter bank circuit breakers and refurbishing 1 filter bank
circuit breaker over RCP2 at an estimated cost of $3.2m.
Re-clad Oteranga Bay Cable Station RCP2 Cost $2.2m
The Oteranga Bay Cable Station is located in an extremely challenging coastal environment.The roof and wall cladding of the building is significantly corroded, allowing water to enter.
Our strategy is to re-clad the roof and walls of the cable station with a design that is better
suited to the environment. This will result in enhanced protection of cable station assets.
Over the RCP2 period, we plan to re-clad the cable station roof at a cost of $1.2m and the
exterior walls at a cost of $800,000.
Chapter 4 has further details on these strategies and a discussion of the remaining
strategies.
-
8/12/2019 Fleet Strategy - HVDC
8/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 5 of 54
1 INTRODUCTION
Chapter 1 introduces the purpose, scope, stakeholders, and strategic alignment of the High
Voltage Direct Current (HVDC) fleet strategy.
1.1 Purpose
We plan, build, maintain and operate New Zealands high-voltage electricity transmission
network (Grid). This includes the HVDC assets, which provide a high-efficiency, high-
capacity connection between the North Island and South Island electricity grids.
The purpose of this fleet strategy document is to describe our approach to lifecycle
management of the HVDC asset fleet. This includes a description of the asset fleet,
objectives for future performance and strategies being adopted to achieve these objectives.
The strategy sets the high-level direction for fleet asset management activities across the
lifecycle of the asset fleet. These activities include Planning, Delivery, Operations,
Maintenance, and Disposal.
This document has been developed based on good practice guidance from internationally
recognised sources, including BSI PAS 55:2008.
1.2 Scope
The New Zealand HVDC systems assets have key asset management differences to the AC
system, which is why the assets in the HVDC system have their own fleet strategy. The scope
of the fleet strategy includes the following HVDC asset categories:
Converter Stations:converters, DC yard equipment, and AC switchyard equipment
Electrode Stations:earthing electrodes, isolating switches, roof bushings andbuildings
Submarine Cables and Cable Stations:submarine cables, cable terminations, andbuildings.
The HVDC system is a sophisticated system that requires complex controls to ensure it
operates optimally and safely. This includes two reactive power control (RPC) systems, one
at Benmore and one at Haywards. We also have a Real Time Digital Simulator (RTDS) and a
valve base simulator for the HVDC system. This is located at Transpower House andsimulates the real-time response of the power system to various scenarios to support
maintenance and testing of HVDC controls.
Given the extensive nature of the HVDC system with its large number of asset types, further
information on the assets within each category is provided below.
Converter Stations
The valve halls at each converter station contain the primary equipment that enables the
conversion between DC and AC. The two main types of equipment in the valve halls are:
thyristors
bushings.
-
8/12/2019 Fleet Strategy - HVDC
9/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 6 of 54
The converter stations include a diverse range of complex and special purpose secondary
equipment, such as protection systems, control systems, water cooling systems, and
auxiliary power supplies. The scope of this strategy document includes the converter valve
hall buildings themselves and their building services.1
The converter stations also include DC and AC switchyards, which include a number of
assets. The most important of these assets are:
converter transformers
circuit breakers
harmonic filters
buses
disconnectors and earth switches
instrument transformers
smoothing reactors.
Much of the equipment in the HVDC converter stations are specialised unique designs that
vary significantly from those used on the AC system, which is the reason they are considered
under this strategy and asset portfolio and not under the relevant AC asset fleet strategy.
The converter transformers are particularly unique assets, with designs that are much more
complex and fundamentally different from our AC power transformers.
Electrode Stations
There are two electrode stations, with one set of electrodes being inland and the other set
underwater. The electrode stations include:
roof bushings
electrode arms
isolating switches
cabling.
Submarine Cables and Cable Stations
Three HVDC submarine cables cross Cook Strait to connect the North Island with the South
Island. There are two cable terminal stations, where the HVDC submarine cables are
connected to overhead lines.
Exclusions
The HVDC overhead transmission lines are excluded from this strategy as they are covered
within the Conductors and Insulators fleet strategy. Similarly, the management of the HVDC
towers is described in the Towers and Poles fleet strategy. The Haywards synchronous
condensers, which support the operation of the HVDC link, are included in the Reactive
Power Fleet Strategy.
1 At the time of writing, we are considering a transfer of responsibility for several aspects of HVDC buildings and
grounds management from the HVDC maintenance service providers to the Buildings and Grounds FacilitiesManagement service provider.
-
8/12/2019 Fleet Strategy - HVDC
10/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 7 of 54
1.3 Stakeholders
The HVDC system provides a high-efficiency and high-capacity connection between the
North Island and South Island electricity grids, enabling a national electricity market. Correct
operation and maintenance of the HVDC asset fleet is essential for transporting electricityfrom areas of high supply to areas of high demand, thus reducing disparity between the
electricity prices in different regions of New Zealand.
Key stakeholders include:
Transpower Groups: Grid Development, Performance and Projects
regulatory bodies: Commerce Commission and Electricity Authority
generators
service providers
landowners customers: including distribution network businesses
fishing and shipping industry.
1.4 Strategic Alignment
A good asset management system shows clear hierarchical connectivity or line of sight
between the high-level organisation policy and strategic plan, and the daily activities of
managing the assets. This document forms part of that connectivity by setting out the
strategy for managing the HVDC asset fleet to deliver our overall Asset Management
Strategy.
This fleet strategy directly informs the HVDC Asset Management Plan, which is provided
separately. The hierarchical connectivity is represented graphically inFigure 1.It indicates
where the fleet strategy and plan fit within our asset management system.
-
8/12/2019 Fleet Strategy - HVDC
11/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 8 of 54
Figure 1: The HVDC Fleet Strategy within the Asset Management Hierarchy
1.5 Document Structure
The rest of this document is structured as follows.
Chapter 2provides an overview of the HVDC asset fleet including fleet statistics,characteristics and their performance.
Chapter 3sets out asset management related objectives for the HVDC asset fleet. These
objectives have been aligned with the corporate and asset management policies, and with
high-lever asset management objectives and targets.
Chapter 4sets out the fleet specific strategies for the management of the HVDC fleet. These
strategies provide medium-term to long-term guidance and direction for asset management
decisions and will support the achievement of the objectives in chapter 3.
HVDC Plan
HVDC Strategy
Corporate Objectives & Strategy
Asset Management Policy
Asset Management Strategy
Lifecycle Strategies
DeliveryPlanning Operations DisposalMaintenance
-
8/12/2019 Fleet Strategy - HVDC
12/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 9 of 54
2 ASSET FLEET
Chapter 2 provides a high-level description of the HVDC asset fleet, including:
Asset statistics:including population, diversity, age profile and spares
Asset characteristics:including safety and environmental considerations, assetcriticality, asset condition, maintenance requirements and interaction with other
assets.
Asset performance:including reliability, safety and environmental
Risks and issues.
2.1 Asset Statistics
This section outlines the HVDC asset fleet population, along with their diversity and age
profiles.
2.1.1 Overview of Asset Fleet
The HVDC system is an important part of New Zealands electricity transmission system.It
connects the North Island with the South Island via submarine cables. The HVDC system has
a high capacity and low losses due to its high voltage and DC configuration (HVDC is only
cost effective for long distance point-to-point transmission).
The HVDC system runs from Benmore Station in the Waitaki Valley (South Island) to the
Haywards station in the Hutt Valley (North Island). The system includes the HVDC Cook Strait
submarine power cables connecting the North Island with the South Island, overhead HVDC
transmission lines in both islands, and the Benmore and Haywards converter stations, where
power is converted between AC and DC. There are also two electrode stations which provide
an earth return system. Cable stations are located at Fighting Bay and Oteranga Bay where
the HVDC overhead line conductors are connected to the Cook Strait submarine cables.
The original Pole 1 converter station equipment, first commissioned in 1965, was replaced in
2013 with the new Pole 3 equipment (although the use of Pole 1 equipment was restricted
from 2007, and it was fully decommissioned in 2012). The Pole 3 project has brought the
fleet up to a modern standard.
2.1.2 Asset PopulationTable 1 shows the population of the current asset fleet as of June 2013.
Station Population Comment
Converter Stations 4 2 at Benmore and 2 at Haywards
Electrode Stations 2 1 at Bog Roy and 1 at Te Hikowhenua
Cable Stations 2 1 at Fighting Bay and 1 at Oteranga Bay
Submarine Cables 3 38 km per submarine cable
Table 1: HVDC Asset Fleet
-
8/12/2019 Fleet Strategy - HVDC
13/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 10 of 54
2.1.3 Fleet Diversity
Fleet diversity is a significant issue for the management of the HVDC fleet given the small
number of each asset type within the fleet. The small numbers of individual types of
equipment mean that there is limited operational experience on which to base assessments
of condition and risk. Further, the unusual characteristics of many of these items of
equipment require us to consider a diverse range of asset management risks and issues in
managing the system as a whole. In some cases, the worldwide population of identical
equipment is very small. This makes the retention of skills important as well as maintaining
relationships with suppliers and service providers, including specialised overseas service
providers.
Converter stations
The four converter stations are of the same basic type, that is, Line Commutated Converter
(LCC). However, there are significant differences in the technology used in Pole 2 and Pole 3.
For example, they have different thyristor technology, which are also from differentmanufacturers. The differences in technology have some benefits and some disadvantages.
One benefit is that the technology reduces the likelihood of simultaneous pole failure on
both poles from a common cause.
The maintenance tasks for the converter stations are the same in a general sense, but the
specific procedures for the tasks differ between the two poles, and different spares are
required. For example, Pole 3 uses light triggered thyristors, whereas Pole 2 uses electrically
triggered thyristors, so separate spares must be kept. There is only one HVDC equipment
supplier worldwide that supplies light triggered thyristors.
As part of the Pole 3 project, the Pole 2 control system was replaced with a system identical
to that of Pole 3 so the control systems would be fully compatible.
The majority of assets in the HVDC system require a unique design with different
specifications to the assets on the AC system. For example, HVDC transformers and filter
bank circuit breakers are very different to those in the AC system.
Electrode and cable stations
Diversity is not a significant issue for the majority of the assets at the electrode and cable
stations. However, diversity is relevant to the cable station roof bushings. Roof bushings can
be damaged by extreme weather, so maintenance and emergency replacement may be
required. Using standard designs for all four roof bushings has made such activities easier.
Submarine cables and cable stations
Historically, submarine cables were impacted by diversity given that the cable fleet was
procured in tranches over time and used differing technology. However the three cables that
are now in service are identical in design and practice, even though they were produced by
two different manufacturers. Table 2 shows the types of submarine cable in the fleet.
Cables Type Comment
HVDC Cables 46 Oil impregnated paperIdentical designs; two differentmanufacturers.
Table 2: Diversity of the Submarine Cable Fleet
We only need to carry one type of spare cable because the three cables in service have thesame design.
-
8/12/2019 Fleet Strategy - HVDC
14/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 11 of 54
2.1.4 Age Profile
The original HVDC link was commissioned in 1965 and there was a substantial HVDC upgrade
project in 1991, when the Pole 2 converter stations were commissioned and the three
currently operating HVDC submarine power cables were installed. This upgrade process has
continued with the recent replacement and refurbishment of some Pole 2 HVDC assets.
As discussed in subsection 2.1.1, new converter stations, called Pole 3, replaced the
decommissioned Pole 1 converter stations in 2012/13.
Converter stations
It is worth noting that life expectancy as shown in Table 3 is the nominal life established for
fixed asset accounting purposes. It represents the typical average life expected from a type
of equipment before it is no longer fit to remain in service. For example, the original life
given to the Pole 2 primary equipment was 30 years for accounting purposes, but with
further experience with the assets we now anticipate the Pole 2 primary equipment to last
much longer. The nominal life expectancy is a generalisation across the primary equipment,but the life expectancies of different components within the converter stations differ
markedly.
Station InstalledNominal LifeExpectancy
Pole 2 converter station (Haywards) 1991 30 years
Pole 2 converter station (Benmore) 1991 30 years
Pole 3 converter station (Haywards) 2012 40 years
Pole 3 converter station (Benmore) 2012 40 years
Table 3: HVDC Stations Age
Within each HVDC station, the component assets will have varying ages as components have
been refurbished, replaced or enhanced over time.
Electrode stations
The electrode stations at Te Hikowhenua and Bog Roy were installed in 1965 when the HVDC
system was originally installed. Both stations were extended between 1989 and 1993 to
significantly increase their current rating. The various components of the electrode stations
continue to be maintained, refurbished or replaced as required to maintain the required
condition and function of the stations. In particular, there has been an ongoing programme
of total replacement of the buried electrode arms of the Bog Roy land electrode station.
Cables and cable stations
The three HVDC submarine cables were installed between 1990 and 1991.
The two cable stations (at Oteranga Bay and Fighting Bay) were initially built in 1965, and
new cable terminal buildings added in 1991. Their nominal life expectancy is 30 years, from
1991.
Life expectancy is the nominal life established for fixed asset accounting purposes. It
represents the typical average life that is expected from a type of equipment before it is no
longer fit to remain in service. Yet some assets may be useful for much longer. The average
age of the in-service fleet is approximately 22 years as of June 2013, with details of eachcable shown in Table 4.
-
8/12/2019 Fleet Strategy - HVDC
15/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 12 of 54
Cable Installation Nominal Life Expectancy
Cable 4 1991 35 years
Cable 5 1991 35 years
Cable 6 1991 35 years
Table 4: Age Profile of Submarine Cables
2.1.5 Spares
We have ample spares for the Pole 2 primary equipment, and a large amount of spares for
Pole 3. The spares are predominantly stored at Bunnythorpe and Addington warehouses
along with storage at the Haywards and Benmore sites. The total number of spares stored
for the HVDC systems is much too large to include in this document and cannot be easily
summarised because of the different types of assets required. Subsection 4.1.2 provides
information on new spares required to be purchased during RCP2.
Converter stations
A very small amount of the HVDC station equipment is compatible with assets on the AC
system, so specialised spares are mostly required. Table 5 shows some of the most
important spares currently kept for the converter stations.
Asset Number Status
Smoothing reactor 2New as of 1991, can be used as spare for Pole 2 orPole 3, although one of the spares has beendamaged.
Circuit breakers Multiple sparesSpares are held for filter bank circuit breakers,transformer circuit breakers, DC circuit breakers, andAC circuit breakers (for Pole 2 and Pole 3).
Capacitor cans Multiple sparesCapacitor cans are specialised and not available offthe shelf, so we have a number of spares for thevarious types used in the HVDC system.
Table 5: Examples of converter station spares
One of the spare smoothing reactors has been damaged and it is likely that it is uneconomic
to repair. We intend to replace the damaged reactor within RCP1.
Electrode stations
We hold approximately 25m3of coking coal in the event that the coking coal surrounding the
electrodes is eroded away due to electrochemical reaction. The electrochemical erosion
mainly occurs during mono-pole operation of the HVDC link at Bog Roy electrode station.Specialised low sulphur coal is required to minimise the corrosion of the electrodes, and this
is difficult to procure at short notice. In addition, as the suppliers mostly supply large
amounts to the steel-making industry, their distribution systems are not set up for small
customers like Transpower.
We recycle the electrode arm materials where possible, and retain one spare electrode arm
at all times.
As other electrode station equipment such as cables, roof bushings, switches, resistors and
capacitors are readily available from suppliers, spares holdings are not required.
-
8/12/2019 Fleet Strategy - HVDC
16/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 13 of 54
Submarine cables and cable stations
We hold a total of 3.6 km of HVDC submarine cable as spares at the Miramar cable store
(one 2.4 km length and one 1.2 km length). The usefulness of these spares for repair of a
cable fault in deep water is dependent on the ability to quickly cap a damaged cable. To limit
the requirement for spare cable, it is essential to act promptly and prevent water ingress
further than 1.2 km in both directions from the fault.
For details of the contingency planning for submarine cable repairs, see subsection4.3.4.
There are two spares available for the critically important roof bushings at each Cable
Station. There are four roof bushings in service (two at each cable station). They are all the
same sulphur hexafluoride (SF6) pressurised design. They are all interchangeable, and three
of the four current spares can be used to replace any of the four roof bushings, while the
other spare can only be used for Pole 2. We believe that only three spares are necessary, so
one of these spares will be used to replace an Oteranga Bay roof bushing during RCP2 when
it reaches the end of its useful life.
2.2 Asset Characteristics
The HVDC asset fleet can be characterised according to:
safety and environmental considerations
asset criticality
asset condition
maintenance requirements
emerging technologies interaction with other assets.
These characteristics and the associated risks are discussed in the following subsections.
2.2.1 Safety and Environmental Considerations
Safety and environmental considerations are important for asset management as they can
require costly mitigation if not considered early in asset management planning. The most
significant safety and environmental considerations for the HVDC asset fleet are:
Converter valve hallswork at heights:maintenance and inspection of the thyristorvalves and other equipment in the valve halls requires work at considerable heights.
Each valve hall is equipped with an elevating work platform to enable safe access for
work at height.
Converter station fire risk:Converter station explosions/fires have occurredoverseas and are theoretically possible in the valve halls. One of the risk mitigations
is to provide a water deluge system. It is proposed that the fire water supply systems
at Haywards and Benmore substations will be upgraded during RCP2 (see
subsection 4.1.2).
High land and marine voltage gradients at shore electrode station: Marine voltagegradients, caused by erosion of land electrodes and material build-up on sea
electrodes, can potentially affect marine life in the vicinity of the shore electrode
station. However, the design of the Te Hikowhenua shore electrode is such that the
voltage gradient is very low (less than 7 V/m).
-
8/12/2019 Fleet Strategy - HVDC
17/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 14 of 54
Generation of chlorine gas at shore electrode station: During periods of HVDCoperation when the electrodes at Te Hikowhenua act as an anode, chlorine gas is
generated in the electrode pits. Service providers working in the pits wear gas
monitors and allow time for any chlorine gas to dissipate after opening the lids.
Metal corrosion at land electrode station: A particular problem that one landownernear the Bog Roy electrode station experiences is accelerated corrosion of metal
earthed assets, such as fences and sheds. We actively work with that landowner to
mitigate the effects.
2.2.2 Asset Criticality
Asset management is adapted to recognise the differing levels of criticality to mitigate the
risk of failures at critical sites and corridors and to potentially reduce expenditure on assets
that are less critical. We have established a framework for assigning Asset Criticality for
transmission assets, which classifies the assets as high, medium, or low criticality.
The asset criticality framework is at an early stage of development. At this stage we haveassigned all assets within the HVDC fleet as low criticality because a failure of the HVDC
system will not usually result in interruptions for customers. Yet we recognise that the HVDC
system is a special case where very rare failures can lead to widespread under-frequency
load shedding, and less severe failures can result in a substantial change in electricity prices.
A failure of any part of the HVDC system is generally equally important as it will result in the
failure of a pole and a steep reduction in the capacity of the link. Yet some assets have
redundancy built in, such as the control systems and the multiple filter banks. Other
essential assets have unit spares, such as the converter transformers, available. The neutral
earth circuit is particularly critical to HVDC reliability, because it is common to both poles,
and its failure could result in an outage of both HVDC poles. We take these factors intoconsideration in the planning phase of the asset management lifecycle for the HVDC fleet.
There are scenarios in which the relative criticality of the HVDC link could rise. For example,
if a large amount of generating capacity in the North Island failed (such as the Huntly power
station), the HVDC link could become essential for maintaining electricity supply in the North
Island.2
2.2.3 Asset Condition
The following discussion outlines the condition of the HVDC asset fleet as at 30 June 2013.
Converter stations
The Pole 3 Converter Stations were constructed between 2011 and 2013 and are therefore
in excellent condition. The outages and site access required by the Pole 3 project provided
an opportunity to replace Pole 2 equipment that was nearing the end of its life. So the
individual assets at the Pole 2 converter stations are generally in good condition and the
majority of the main equipment items should achieve their expected design life of 30 years.
Further life-extending refurbishments are possible on some of these items.
2 There is currently sufficient generating capacity for the North Island within the North Island, but the HVDC link is
employed to utilise generation from the South Island with a much lower marginal cost. This generally involves hydroand wind generation compared with thermal generation in the North Island.
-
8/12/2019 Fleet Strategy - HVDC
18/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 15 of 54
Pole 2 Thyr istor valve water cool ing sy stem
At the time of original commissioning in 1991, it was recognised that the design of the Pole 2
thyristor valves creates a flow of a small electrolytic current in the cooling water pipes of the
valve cooling system. This electrolytic current causes corrosion of the stainless steel
couplings in the valve cooling system. These couplings are critically important componentsthat distribute cooling water to the thyristor valve layers. In the early 1990s, corrosion in
similar components in another HVDC thyristor valve was identified as the probable cause of
cooling water leakage, flashover and failure of the complete thyristor valve. Since
commissioning Pole 2 in 1991, we have monitored corrosion rates annually by sampling 6
out of 194 couplings at each converter station. The water treatment plant is critical to the
thyristor valve cooling systems and the number of instrumentation faults has increased.
There are also other aspects of the water cooling system that are degrading to a condition
that will require replacement and/or refurbishment over RCP2 (see subsection 4.1.2 for our
strategy to respond to these issues).
Pole 2conv er ter transformers
The converter transformers are in a good condition, as expected for their age. Yet the
condition of some components, such as the diverter switches, is deteriorating. The condition
of the tap changers may also be deteriorating, although reliable assessment will require the
detailed evaluation that we have planned for the RCP2 period (see subsection 4.4.3).
The demands of the electricity market require frequent changes in HVDC power transfer.
These changes require frequent diverter switches of the converter transformers. There are
approximately 17,000 diverter switch operations annually on each of the six in-service
converter transformers. The diverter switches operate in oil and the oil quality deteriorates
slightly with each operation. Major diverter switch refurbishments are required at
approximately every 450,000 operations. The Pole 2 converter transformer diverter switcheshave approximately 350,000 operations and are due for refurbishment during the RCP2
period.
The condition of the transformer oil is very important to the performance of the
transformers and for maximising their useful lives. It is also an important consideration
because of the scaleeach converter transformer bank contains 240,000 litres of oil. The
condition of the transformer oil was recently assessed, showing that it is in very good
condition. It is clear, of a normal colour, has low moisture levels, is not acidic, and shows no
signs of sludge. Even so, the dielectric breakdown voltage is becoming lower than ideal. We
expect that the condition of the oil will remain reasonable through RCP2, although we will
continue to monitor it to identify if any filtering of the oil is required.
Pole 2 f i l ter bank circu i t breakers
Frequent changes of HVDC power transfer also require frequent switching of the Pole 2 filter
bank circuit breakers. There are 10 circuit breakers and they operate between 150 and 750
times each year. The original circuit breakers had design lives of 2,000 operations or 35 years
in service.
Four of the original circuit breakers were replaced (two in 2005 and two in 2012) with
10,000 operation breakers. Other circuit breakers were refurbished to extend their lives to
cover the next 2,000 operations. As of March 2013, of the 10 circuit breakers four have less
than half of their life expectancy operations remaining while the other six have most of their
maximum operations remaining. A number of the circuit breakers are expected to reach
-
8/12/2019 Fleet Strategy - HVDC
19/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 16 of 54
their maximum number of operations during RCP2, and their replacement and
refurbishment is discussed in subsection 4.1.2.
Pole 2 Reactors
The reactors in the HVDC Pole 2 system are all air-cored. They were commissioned in 1991and are in good condition.
Electrode stations
The condition deterioration of the electrodes depends on the cumulative amount of
electrode current passed through them over time. When the HVDC link is in balanced
current operation, the electrode current is very small and there is only very slow
degradation of the electrodes. During unbalanced operation, and particularly during mono-
pole operations, there can be significant currents and rapid degradation.
Bog Roy electrode stat ion
The Bog Roy electrode generally operates as an anode during current flow because theHVDC flow is usually northwards. During anode operation, electrolytic action erodes the
steel rods buried in the ground that make up its electrode arms. There has been significant
erosion and breakage of the electrode arms. The eroded arms have to be replaced and it is
essential to monitor the electrode condition to determine their priority for replacement. The
land electrode erosion rate at Bog Roy during mono-pole operation is 15 to 18 times higher
than during balanced operation.
After Pole 1 was decommissioned, and prior to the commissioning of Pole 3, the HVDC link
was operating in mono-pole operation for an extended period. This led to significantly
increased rate of deterioration of the electrodes, involving more frequent maintenance and
progressive replacement of the buried electrode arms.The strategy for further refurbishment of the Bog Roy electrode arms is set out in
subsection4.1.2.
Te Hikow henua electrode stat ion
The Te Hikowhenua land electrode provides a return path to earth for DC current when only
one HVDC pole is operating or when current flow between the two poles is unbalanced.
The electrode operated as a cathode for an extended period following the decommissioning
of Pole 1, when the HVDC system was in a mono-pole configuration and only Pole 2 was
operating. The long periods of operation as a cathode led to the build-up of a thick layer of
magnesium and calcium hydroxide on the 42 four metre-long high silicon chromium iron
electrodes that are buried in the beach. This build-up of deposits degraded the electrode
performance, and required regular maintenance.
All the sea electrodes were replaced in 2007, so they are (as of 30 June 2013) in good
condition aside from the continued accumulation of magnesium and calcium hydroxide
during any periods of operation as a cathode. Following the commissioning of Pole 3 this will
no longer be such a significant issue.
Cables and cable stations
Oteranga Bay cable stat ion
The HVDC cable station at Oteranga Bay faces severe environmental conditions, with regulargale-force and storm-force winds. In storm conditions, heavy salt deposition occurs. This
-
8/12/2019 Fleet Strategy - HVDC
20/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 17 of 54
location rates as one of the most demanding operational HVDC sites worldwide in terms of
environmental conditions, and cannot be directly simulated by any HVDC electrical
equipment tests. The high wind speed and constant wind-borne salt pollution significantly
reduces the life of the roof and cladding of the cable station buildings, and places high
stresses on the HVDC roof bushings.
The extreme environmental conditions have led to severe corrosion of the exterior walls and
roof cladding of the cable station building, particularly around the edge of the building, and
the building is no longer weather-tight. This is a particular issue during high winds. Water is
also entering the building due to the failure of corroded flashing, which consists of thinner
material than the main roofing material.
The strategy for the roof and cladding of the Oteranga Bay building is set out in
subsection4.1.2.
The Oteranga Bay Pole 2 350 kV roof bushings have previously been replaced at
approximately 4-year intervals because of the harsh environment. The replacements have
included several different types of bushing as we have attempted to find a design that suitsthe environment. The latest roof bushing is a composite bushing designed to withstand wind
speed up to 300 km/h and has improved material properties. It has been in service since
February 2006. The roof bushings require regular extensive cleaning (annually and after
large storms) to maintain their hydrophobicity, as there have been several incidents of
arcing due to salt deposition in the past.
Fight ing Bay cable stat ion
The Fighting Bay cable terminal station has a much less severe climate than the Oteranga
Bay site, and consequently there are less stresses on the insulation of the roof bushings.
Both of the roof bushings have recently been replaced with polymer bushings so are in good
condition. The building cladding is currently in good condition and does not require anyrefurbishment or replacement in the foreseeable future.
Submar ine cables
Surveys using an ROV show that the three power cables are in good condition and generally
well supported by the seabed. Due to the nature of the marine environment, corrosion of
areas of exposed armouring on the cables is expected, with cathodic protection needed on
the cables.
Yet the ROV surveys and diving inspections have shown virtually no corrosion of the
armouring to date. No further natural cathodic protection investigations are planned, and
neither is any further prevention action planned at this stage because the evidence showsthat, at present, corrosion does not appear to be a significant issue. Currently, cables 4 and 5
are undamaged and in good condition while cable 6 has had one fault repair undertaken.
2.2.4 Maintenance Requirements
This subsection describes the maintenance requirements of the HVDC asset fleet, including
the underlying drivers and rationale. These requirements have informed the maintenance
strategies discussed in section 4.4. This subsection also sets out a high-level overview of
historic maintenance expenditure for these activities.
The most common types of maintenance carried out on these assets are:
preventive maintenance, including:- line patrols and condition assessments
-
8/12/2019 Fleet Strategy - HVDC
21/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 18 of 54
- servicing
corrective maintenance, including:
- fault response
- repairs
maintenance projects.
Maintenance projects are programmes of works (essentially made up of small projects) used
to address repetitive issues identified through preventive and corrective maintenance.
The Maintenance Lifecycle Strategy provides further details on our approach to the above
maintenance works, and the specific maintenance requirements are included in the relevant
service specification documents.
Preventive maintenance
The following sections discuss the preventive maintenance works on each major asset type.
Converter stat ions
Preventive maintenance of the converter station assets is planned on a regular basis, with
the frequency dependent on the type and known condition of the asset. We schedule an
annual maintenance outage in summer when demand for inter-island HVDC transfer is
relatively low. The majority of maintenance works are carried out then. Regular condition
assessments undertaken for the converter station assets may include:
periodic visual inspections
thermographic checks
out-of-service diagnostic inspections
transformer dissolved gas analysis (DGA)
continuous monitoring of the performance of the HVDC cooling systems via thevalve cooling control systems
thyristor diagnostic inspection in line with manufacturer requirements
frequent inspections of filter bank circuit breakers because of the high frequency ofswitching required.
Electrode stat ions
The Te Hikowhenua electrode station has undergone 3-monthly lifting inspections of the
2 pilot electrodes and 6-monthly lifting and cleaning of salt deposits on all electrodes while
the system has been operated as mono-pole. With the operation of Pole 3 and return to
bipolar operation, cleaning will only be carried out as required.
Cable stat ion s
Preventive maintenance of the cable terminal stations is usually planned around annual
shutdowns.
Regular condition assessments undertaken on the roof bushings include:
visual and UV camera inspection
monitoring of corrosion in the sealing and central flange area
-
8/12/2019 Fleet Strategy - HVDC
22/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 19 of 54
hydrophobicity testing
monitoring of internal bushing gas pressure and top-up intervals
bushing gas analysis.
Roof bushings are also regularly cleaned to maintain hydrophobicity at a required level.
Submar ine cables
Maintenance of submarine cables is complicated by the marine environment, requiring
specialised equipment and techniques such as the ROV and divers.
The submarine cables can be severely damaged by contact with fishing trawling devices or
ship anchors. So preventive maintenance of the submarine cables includes regular patrolling
of the area by vessel and helicopter to identify and deter ships (particularly trawlers) from
operating illegally in the vicinity of the submarine cables. The marine patrol enforces the law
prohibiting fishing and anchoring within the CPZ and educates ship operators in the area on
CPZ law. The Ministry of Transport undertakes prosecutions for illegal fishing activity in theCPZ, based on evidence provided by the patrol vessel. One third of each cable is condition
assessed each year using an ROV and diver (so every cable is assessed in any 3-year period).
This has been dependent on the weather and the availability of resources. At times,
condition assessments have been delayed when resources have been diverted to repairs to
the HVDC or fibre optic cables.
Also, there is a need to move sandbags and other protective equipment every 2 to3 years
because the seabed conditions change over time. An electrical cable test is undertaken every
10 years, with the last one being carried out in 2011.
Corrective maintenance
We carry out a wide range of corrective maintenance due to the diverse types of assets
included in the HVDC fleet. Corrective work ranges from the relatively simple replacement of
failed assets, such as capacitor cans, through to major repairs and replacement of complex
assets, such as the converter transformers and submarine cables.
In some cases, corrective work requires the involvement of overseas technicians and
experts, particularly those from the original equipment manufacturers.
One of the largest and most complex cases of corrective maintenance is submarine cable
repair. In 2005 we repaired a submarine cable fault in shallow water in Oteranga Bay. This
was a large and complicated procedure supported by overseas expertise, and required
maintenance support equipment to be custom-built for the procedure, including the retrofit
of a barge.
The repair of a cable fault in deep water would be more difficult and complicated, requiring
specialist vessels and equipment from overseas. It is important to quickly cut and cap the
cable in the event of a cable fault, to prevent excessive water ingress. In deep water, the
water ingress could be relatively rapid, reaching a length beyond the length of spare cable.
This would necessitate purchasing replacement cable. Procurement of submarine cable can
take 2 to 3 years. Repairs will generally need to be made in relatively calm weather, and may
not be possible in winter. Depending on the time of the year and the complexity of the
repair, it could take between 3 and 9 months to repair a cable.
-
8/12/2019 Fleet Strategy - HVDC
23/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 20 of 54
Maintenance projects
Maintenance projects typically consist of relatively high value planned repairs or
replacements of components of larger assets. Maintenance projects would not be expected
to increase the original design life of the larger assets. Maintenance jobs are typically run as
a project where there are operational and financial efficiencies from doing so. The drivers
for maintenance projects include asset condition, mitigating safety and environmental risks,
and to improve performance.
A number of maintenance projects have been undertaken for the HVDC fleet, including:
Haywards maintenance projects:
- reactor painting
- busbar corrosion
Benmore maintenance projects:
- Supervisory Control and Data Acquisition (SCADA) cards repairs
- valve busbar corrosion.
The maintenance projects planned for the RCP2 period are described in subsection 4.4.3.
2.2.5 Interaction with Other Assets
The HVDC system is mostly physically separate from the rest of the transmission system
assets. However, a number of assets in or associated with the converter stations (including
synchronous condensers, AC power transformers, AC switchyard equipment and
Transmission Lines) are covered by other asset strategies. These assets need to be managed,
taking into account any interactions with the HVDC system and any additional performance
or spares holding requirements.
The HVDC system is reliant on reactive power assets, particularly the Haywards synchronous
condensers and STATCOM and the transmission circuits around them.
2.3 Asset Performance
This section describes the historic performance of the HVDC fleet together with any risks and
issues.
2.3.1 Reliability Performance
Achieving an appropriate level of reliability for our asset fleets is a key objective, as itdirectly affects the services received by our customers.
Failure of the assets within the HVDC asset fleet can lead to an outage of the inter-island
connection or a portion of the connections capacity.In many cases this would lead to a
large price discrepancy in the electricity market, between the North Island and the South
Island.
-
8/12/2019 Fleet Strategy - HVDC
24/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 21 of 54
Major failures
Converter stat ions
There have been no major failures at HVDC stations between 1990 and 2012. We define
major failures as those that have caused a long-term (greater than one week) outage of atleast one pole.
Electrode stat ions
There have been no failures of the electrode stations significant enough to cause an outage
of the HVDC link.
Submar ine cables and cable stat ions
HVDC submarine cable performance has been very reliable, with only one failure due to an
internal electrical faultin Cable 6 in October 2004. There have been no failures
attributable to mechanical damage. The 2004 cable failure reduced the capacity of the HVDC
link from 1,040 MW to 886 MW. The failure occurred in shallow water in Oteranga Bay, andthis meant it was feasible to undertake repairs by converting a locally available barge. The
repairs to Cable 6 took almost six months.
The greatest risk to the cables is damage caused by boats illegally fishing or anchoring in the
area. While the current cables have not failed due to boat activity, it is suspected that the
failure of one of the old decommissioned cables in 1991 (Cable 2) was caused by a fishing
operation. The Maintenance section (section 4.4) describes the activities that will be
undertaken to reduce the risk of this occurring.
The original Pole 2 350 kV porcelain roof bushing at the Oteranga Bay Cable Station failed in
service in 1996 after only four years of service, damaging the building and causing a lengthy
forced outage. Replacement roof bushings using composite technology have been installedand, although there have been problems with deteriorating condition, there have been no
further major failures.
Availability
The availability of the HVDC link varies from year to year, depending on the number and
length of planned and forced outages. The availability from 2003/04 to 2011/12 is shown in
Figure 2.
Figure 2: HVDC Annual Availability
75%
80%
85%
90%
95%
100%
2003/04 2005/06 2007/08 2009/10 2011/12
HVDC AVAILABILITY
-
8/12/2019 Fleet Strategy - HVDC
25/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 22 of 54
Pole 1 was generally less reliable than Pole 2 towards the end of its operation. Pole 1 was
decommissioned in September 2007, which is why the availability is higher after 2007 when
the data only relates to Pole 2. In 2010/11 and 2011/12 the availability was lower than
previous years because a relatively large number of planned outages were required for the
construction of Pole 3.
2.3.2 Safety and Environmental Performance
Subsection 2.2.1 described the characteristics of the HVDC assets that impact safety and
environmental performance. This subsection reports on the actual safety and environmental
performance of the fleets.
There have been no major safety incidents involving the HVDC fleet in recent years.
The number and nature of environmental incidents involving the HVDC assets have not been
clearly recorded in the past, although recording and management of this information has
begun recently so future versions of the fleet strategy will be able to provide improved
environmental performance data.
2.3.3 Risks and Issues
This subsection briefly discusses the most significant risks and issues facing the asset
management of the HVDC asset fleet.
Strategies to manage these risks and issues are set out in chapter4.
Submar ine cables r isk posed by m ar ine vessels
The main risk to the submarine cables is damage caused by fishing activity where heavy
trawl nets and associated equipment makes contact with the cables. There is also potential
for anchor damage from large and small vessels to place the cables at risk.
The Submarine Cables and Pipelines Protection Act 1996 provides legal protection for a CPZ
across Cook Strait. In 1995 we started marine patrols of the Cook Strait CPZ, initially focusing
on the hoki fishing season from June to September. Incidents of damage to the submarine
fibre optic cables, and efforts by fishermen to circumvent the part-time patrol led to full-
time patrolling, which has now been in place for some years.
There are about 4,000 vessel movements in the vicinity of the cables every year. Roughly
300 of these are of interest for gathering of evidence of possible infringements, and around
20 require follow-up. Information about alleged infringements is passed to the Ministry of
Transport. There is a prosecution every 1 to 2 years. The marine patrol service includes
continuing efforts to communicate with the fishing industry to help mitigate risk.The cables are laid separately to minimise the likelihood of all three cables being damaged in
one incident.
Consequences of subm ar ine cable fai lure
There is no backup for the submarine power cables and restoration times range from at least
6 months for a repair to 24 months for total replacement. Failure of any one power cable
can result in a reduction in HVDC cable capacity to 1000 MW (there are 3 cables, each rated
to carry 500 MW). The current total capacity of the link is 1,000 MW due to other
constraints, but this is due to increase to 1,200 MW by the end of 2013 when the new
Haywards STATCOM is commissioned. So a cable failure in the immediate future would
reduce redundancy but not reduce the capacity of the link. It should also be noted that 84%of the time the transfer on the HVDC link is less than 500 MW.
-
8/12/2019 Fleet Strategy - HVDC
26/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 23 of 54
Severe environment at Oteranga Bay cable stat ion
The HVDC cable station at Oteranga Bay faces severe environmental conditions, with regular
gale-force and storm-force winds from north and south. The high wind speed and constant
windborne salt pollution significantly reduces the life of the outdoor roof bushings.
The harsh environment also affects the speed of deterioration of the station building
cladding. As outlined in subsection 2.2.3, the building cladding at Oteranga Bay is currently
in poor condition and needs to be replaced in the next five years.
In response to the extreme environmental conditions, maintenance activities for the
Oteranga Bay cable station are more regular to identify any rapidly accelerating corrosion. In
addition, the design of new assets for the site must carefully consider the environmental
factors. For example, we are planning to replace the current corroded roof cladding with
aluminium cladding, which has superior corrosion resistance compared to most cladding
options.
The strategy for the Oteranga Bay cable station building is set out in subsection4.1.2.
Cable stat ion s roof bush ings
HVDC transfer depends heavily on the performance of the roof bushings at the cable
stations. The cable stations are located in remote areas and have difficult access for the
heavy lifting equipment that is required for bushing replacement. If there is an emergency
that requires a bushing replacement at short notice, a forced outage will be required for at
least three days.
Pole 2 VBE and TCUs
Once stage 2 of the Pole 3 project is complete, the Pole 2 VBE and TCUs will be the only 1990
vintage controls left in the HVDC system because the other parts of the control system are
being replaced as part of the Pole 3 project. The VBE and TCUs are critical parts of the
control system and are nearing the end of their useful lives as they have a design life of
approximately 20 years. We have very limited spares for this equipment and there is a risk
that failure rates will start to increase due to age-related condition deterioration. It is
becoming increasingly difficult to procure spares because of the age of the equipment.
The strategy for the Pole 2 VBE and TCUs is set out in subsection4.1.2.
Pole 3 seism ic resil ience
The new Pole 3 equipment has been designed to withstand higher-intensity earthquakes
than Pole 2 (1 in 2,500 compared to 1 in 1,000 year event). In addition, the seismic resilience
of Pole 2 equipment was estimated by analysis alone, while Pole 3 equipment had its seismicresilience estimated with the use of shake table testing.
In the event of a relatively large earthquake, it is expected that Pole 3 could continue to
operate while Pole 2 may not. Yet Pole 3 is dependent on several parts of the Pole 2 system
(that lack readily available spares). In particular, the Haywards switchyard B insulators and
disconnectors are a seismic risk for Pole 2 and Pole 3.
The strategy for improving the seismic performance of Pole 2 equipment is set out in
subsection4.1.2.
Pole 2 Thyr istor valve water cool ing sy stem
The Pole 2 thyristor valve uses stainless steel couplings in its cooling water distributionsystem. In the early 1990s, corrosion in similar components in another HVDC thyristor valve
-
8/12/2019 Fleet Strategy - HVDC
27/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 24 of 54
was identified as the probable cause of cooling water leakage, leading to flashover and
catastrophic failure of the complete thyristor valve. Condition assessment of the stainless
steel couplings in the Pole 2 valves has identified increased corrosion and accumulation of
aluminium hydroxide.
Since the time of Pole 2 commissioning in 1991, there has been annual monitoring of
corrosion rates by sampling of 6 out of 194 couplings at each converter station. Programmes
of complete replacement of these couplings have been undertaken, and annual condition
monitoring continues, to ensure that this risk is managed.
HVDC capaci ty c onstra ints
The commissioning of the Pole 3 converter stations has substantially increased the capacity
of the inter-island HVDC link to 1,000 MW. Yet the capacity of the link is still constrained by
several factors, including voltage stability, capacity of existing submarine cables, and the
overload capability of Pole 2.
The capacity will be extended to 1,200 MW by 2014, on completion of Stage 2 of the Pole 3project.
Long-term future studies, as outlined in subsection4.1.1,will assess the economic case for
further investment to relieve other constraints so as to provide additional inter-island HVDC
capacity.
-
8/12/2019 Fleet Strategy - HVDC
28/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 25 of 54
3 OBJECTIVES
Chapter 3 sets out asset management related objectives for the HVDC fleets. As described in
section 1.4, these objectives have been aligned with our corporate management objectives,
and higher-level asset management objectives and targets as set out in the Asset
Management Strategy.
Our overarching vision for the HVDC fleet is to provide an energy balancing system that
matches generation and demand in the North Island and the South Island. In addition, the
HVDC link facilitates the transfer of renewable energy from the South Island generation
centres to the North Island load centres. Further objectives have been defined in the
following five areas:
Safety
Service performance Cost performance
New Zealand communities
Asset management capability.
These objectives are set out below, while the strategies to achieve them are discussed in
chapter 4.
3.1 Safety ObjectivesWe are committed to becoming a leader in safety by achieving injury-free workplaces for our
employees and to mitigate risks to the general public. Safety is a fundamental organisational
value and we consider that all incidents are preventable.
Safety Objectives for HVDC Fleets
- Zero medical treatment injuries arising from the maintenance or operation of theHVDC assets.
- Ensure that risks to the public from the operation of HVDC ground electrodes are aslow as reasonably practical.
3.2 Service PerformanceEnsuring appropriate levels of service performance is a key underlying objective. The overall
service performance objectives for the Grid in terms of Grid Performance (reliability) andAsset Performance (availability) are set out in the Asset Management Strategy.
Grid performance objectives state that a set of measures are to be met for Grid Exit Points
(GXPs) based on the criticality of the connected load. In addition, asset performance
objectives linked to system availability have been defined, including a target of 97.5% HVDC
system availability during RCP2.
-
8/12/2019 Fleet Strategy - HVDC
29/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 26 of 54
Service Performance Objectives for HVDC Fleets3
Availability
- Pole 3 forced energy unavailability: 0.5% or less.
- Pole 2 forced energy unavailability: 0.5% or less.
- Pole 3 scheduled energy unavailability: 1.0% or less.
- Pole 2 scheduled energy unavailability: 1.0% or less.
Outage rates
- Pole 3 forced outage rate: 5 outages or less each year.
- Pole 2 forced outage rate: 5 outages or less each year.
- Bi-pole forced outage rate: 0.1 outages or less each year.
Grid effects
- Minimal harmonic distortion.
- Minimal interference to customer ripple control systems.
3.3 Cost PerformanceEffective asset management requires optimising lifecycle asset costs while managing risks
and maintaining performance. We are committed to implementing systems and decision-
making processes that allow us to effectively manage the lifecycle costs of our assets.
Cost Performance Objectives for HVDC Fleets
- Minimise whole-of-life cost in asset management decision making (such as evaluationof replacement versus refurbishment, and capital versus maintenance expenditure).
- Minimise cost of major submarine cable repairs by maintaining necessary resourcesto undertake a prompt cut and capoperation in the event of a fault.
3.4 New Zealand CommunitiesAsset management activities associated with the HVDC fleets have the potential to impact
on both the environment and on the day-to-day lives of various stakeholders. Relationships
with landowners and communities are of great importance to us and we are committed to
using asset management approaches that protect the natural environment.
New Zealand Community Objectives for the HVDC Fleets
- No noise complaints from the public regarding the converter stations.
- No significant release of oil to the environment.
- SF6emissions as low as reasonably practical.
- Reduced corrosion impacts of the Bog Roy electrode on the neighbouring farm.
3
These targets only cover the performance of the converter stations, and exclude outages of the HVDCassets caused by faults in other fleets, such as faults in the transmission line conductors.
-
8/12/2019 Fleet Strategy - HVDC
30/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 27 of 54
- Effective relationships with landowners of the access routes to cable terminal andelectrode stations.
- Effective relationships with the fishing industry in relation to the CPZ.
3.5 Asset Management CapabilityWe aim to be recognised as a leading asset management company. To achieve this, we have
set out a number of maturity and capability related objectives. These objectives have been
grouped under a number of processes and disciplines that include:
Risk Management
Training and Competency
Asset Knowledge
Continual Improvement and Innovation.
The rest of this section discusses objectives in these areas relevant to the HVDC fleets.
3.5.1 Risk Management
Understanding and managing asset-related risk is essential to successful asset management.
We currently use asset criticality and asset health as proxies for a fully modelled asset risk
approach.
Asset criticality is a key element of many asset management systems. We are currently at an
early stage of developing and implementing the approach as we work towards formal and
consistent integration of asset criticality into the asset management framework.
Asset health has not yet been implemented for the HVDC fleets.
Risk Management Objectives for HVDC Fleets
- Up-to-date assessment of spares requirements and current availability.
- Reduced likelihood of a bi-pole fault.
- Development of criticality framework to differentiate HVDC assets.
3.5.2 Asset Knowledge
We are committed to ensuring that our asset knowledge standards are well defined to
ensure good asset management decisions. Relevant asset knowledge comes from a varietyof sources including experience from assets on the Grid and information from the
manufacturers. This asset knowledge must be captured and recorded in such a way that it
can be conveniently accessed.
Asset Knowledge Objectives for HVDC Fleets
- Comprehensive understanding and experience of Pole 3 assets recorded.
3.5.3 Training and Competency
We are committed to developing and retaining the right mix of talented, competent and
motivated staff to improve our asset management capability. This is particularly importantfor the HVDC fleet because of the specialised nature of the knowledge and work required.
-
8/12/2019 Fleet Strategy - HVDC
31/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 28 of 54
Training and Competency Objectives for HVDC Fleets
- Service providers suitably qualified for work on specialised HVDC assets.
3.5.4 Continual Improvement and Innovation
Continual improvement and innovation are important aspects of asset management. A large
source of continual improvement initiatives will be ongoing learning from our asset
management experience.
Continual Improvement and Innovation Objectives for the HVDC Fleets
- Development of understanding in regards to HVDC and dynamic and variable linerating.
- Improved long-term strategic planning approach to capital investment, such as thetiming for the fourth submarine cable.
-
8/12/2019 Fleet Strategy - HVDC
32/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 29 of 54
4 STRATEGIES
Chapter 4 sets out the specific strategies for the management of the HVDC fleet. These
strategies are designed to support the achievement of the objectives in chapter 3 and reflect
the characteristics, issues and risks identified in chapter 2.
The strategies are aligned with our lifecycle strategies below and the chapter has been
drafted to be read in conjunction with them.
Planning Lifecycle Strategy
Delivery Lifecycle Strategy
Operations Lifecycle Strategy
Maintenance Lifecycle Strategy
Disposal Lifecycle Strategy
This chapter also discusses personnel and service provider capability related strategies which
cover asset knowledge, training and competence.
Scope of Strategies
The strategies focus on expenditure that is planned to occur over the RCP2 period (2015
2020), but also include expenditure from 1 July 2013 to the start of the RCP2 period and
some expenditure after the RCP2 period (where relevant). Capex planned for the RCP2
period is covered by the strategies in sections 4.1 and 4.2, and opex is covered by the
strategies in sections 4.3 to 4.6. The majority of the capex consists of asset replacements,
which is described in subsection 4.1.2.
4.1 Planning
This section describes our strategies for the Planning lifecycle.
Planning activities
Planning activities are primarily concerned with identifying the need to make capital
investments in the asset fleet. The main types of investment considered for this fleet are
enhancement, development, replacement, and refurbishment works.
We support the planning activities through a number of processes, including:
Integrated Works Planning (IWP)
cost estimation.
The planning lifecycle strategies for the HVDC fleet are described in the subsections below.
Capital investment drivers
Categories of capital investment generally have specific drivers or triggers that are derived
from the state of the overall system or of individual assets. These drivers include demand
growth, compliance with Grid reliability standards and failure risk (indicated by asset
criticality and condition). Specific examples that drive capital investment in the HVDC asset
fleet include:
-
8/12/2019 Fleet Strategy - HVDC
33/57
HVDC Fleet StrategyTP.FS 46.01
Issue 1October 2013
HVDC FLEET STRATEGY
Transpower New Zealand Limited 2013. All rights reserved. Page 30 of 54
asset replacement, driven by condition
increased capacity requirements, driven by demand for HVDC energy transfer
enhancement of existing assets, driven by safety and performance.
4.1.1 Enhancement and Development
This subsection describes enhancement and development investments for the HVDC fleet.
Enhancement and development investments in HVDC assets have been undertaken in
response to a number of drivers including supply and demand forecasts, and the need to
maintain appropriate levels of availability.
Supply and demand forecasts determine the required capacity and associatedinvestments for the inter-island link.
The need to maintain appropriate levels of availability sometimes involves newimproved equipment, while in other cases it involves auxiliary and maintenance
equipment to help support the reliability of the HVDC equipment.
The strategies below consider the long-term implications for these drivers as we extend our
planning horizon as part of our programme of asset management improvement.
Pole 3 Project
Continue the Pole 3 project, including stage 2 in 2013/14 and the investigation
of stage 3.
With the addition of Pole 3 in 2013, we have substantially increased the capacity of the
inter-island HVDC link to 1,000 W, although the link is still constrained by several factors,including voltage stability, capacity of existing submarine cables, and the overload capability
of Pole 2. Stage 2a major capex proposal (MCP)of the Pole 3 project involves replacing
existing Pole 2 control system (task completed), and improving voltage stability by adding
filter banks and a STATCOM, which will increase the HVDC capacity to 1,200 MW. Stage 2 is
due to be commissioned by 2014.
Stage 3 of the Pole 3 project is currently being considered as a potential MCP. This would
include at least one more submarine cable, a second STATCOM, and additional filter banks,
which would allow the HVDC link to operate at 1400 MW. Stage 3 is unlikely to begin before
the end of RCP3 as supply and demand forecasting suggest that current capacity is expected
to be sufficient until 2030. This is dependent on a number of factors, such as overall South
Island demand. Currently, the majority of generation projects being planned until 2020 arebased in the North Island, where the majority of demand growth is expected.4
One aspect outside the MCP is the upgrade of the RTDS with new processor cards during
RCP2, which is forecast to cost approximately $100,000.
4.1.2 Replacement and Refurbishment
Replacement is expenditure to replace substantially all of an asset. Refurbishment is
expenditure on an asset that creates a material extension to the end of life of the asset. It
does not improve its attributes. This is distinct from maintenance work, which is carried out
4
A list of all publicly known generation projects is maintained and provided by the Electricity Authority, available fromwww.ea.govt.nz/industry/monitoring/forecasting/long-term-generation-development/list-of-generation-projects/
http://c/Users/Public/Documents/Write%20client%20work/Transpower/00%20WORKED%20ON%20DOCUMENTS%20AND%20STYLE%20SHEETS/Fleet%20Strategies/www.ea.govt.nz/industry/monitoring/forecasting/long-term-generation-development/list-of-generation-projects/http://c/Users/Publi