flexible ramp product provision from grid - connected ... · 1 sumanth yamujala, anjali jain 1,...
TRANSCRIPT
Flexible Ramp Product Provision from Grid-Connected Energy Storage Systems
Sumanth Yamujala1, Anjali Jain1, Partha Das3, Rohit Bhakar1, Jyotirmay Mathur1, Priyanka Kushwaha2
1 Centre for Energy and Environment, 2 Department of Electrical Engineering
Malaviya National Institute of Technology Jaipur, India 3 Center for Study of Science, Technology and Policy, Noida, Uttar Pradesh, India
Email: [email protected], [email protected]
Submission ID #84
Background
Power System Flexibility
Contribution
Scheduling Problem
Data
Case Studies
Conclusions
Key References
2
Presentation Outline
Global power generation - A 62% increase between 2017 and 2040 [1]
Coal fired & Natural gas plants - key role in supplying the demand (~60%)
Dwindling fossil fuels, environmental concerns and policy implications Clean and sustainable sources of energy
Many nations are setting ambitious targets to increase the share of RES in the generation mix.
Intermittency of RE Challenges in power system operations
Background
Traditional System - Variability of load and inevitable contingencies
RE integrated systems - Variability of both demand and generation along with inevitable contingencies
Steeper net load ramps
Undesirable outcomes The system must rely on regulation services, market efficiency (penalties), leaning towards interconnections/curtailments
Necessitates flexibility requirements
Background (Cont…)
Controllable units with insufficient ramping capability
Flexibility - Generation, Transmission, Distribution, Market Operations and long term planning
Ability of system to vary energy production in a certain ramp rate to cope up with variations and uncertainties in net-load at minimum cost [1]
PS Flexibility
For Flexibility Enhancement
Physical Measures
Institutional Measures
Improved Grid Infrastructure Fast Start Resources Energy Storage
Improved Operations Market Structures Demand Response
PS Flexibility (Cont…)
Improved Operations
Demand Response
Improved Grid
Infrastructure Fast Start Resources
Energy Storage
Investment Cost
• Improved Forecasting
• Time resolution of scheduling
• BESS • PHES • CAES
• Gas Power plants
• Peaking units
• Distribution and Transmission corridors
• Retrofitting
• Time shifting
• Curtailable loads
Improved operations helps in effective NL handling
India
DA:15 min- 5 min
CAISO
DA: 1hr-15 mins
PS Flexibility (Cont…)
0
1000
2000
3000
4000
5000
6000
7000
t1 t3 t5 t7 t9 t11 t13 t15 t17 t19 t21 t23
Net
load
(M
W)
Time blocks (1 hour)
0
1000
2000
3000
4000
5000
6000
t1 t4 t7 t10
t13
t16
t19
t22
t25
t28
t31
t34
t37
t40
t43
t46
t49
t52
t55
t58
t61
t64
t67
t70
t73
t76
t79
t82
t85
t88
t91
t94
Net
-Loa
d
(
MW
)
Time blocks (15 minutes)
Fig.2: Hourly Net-load
Fig.3: Intra- hour Net-load
Market operators like CAISO, MISO etc., are implementing market-based FRP to address the RR in RT dispatch
Unlike AS, FRP is the capacity deployed to meet RR of consecutive real-time dispatch intervals [3]
FRP - FRU/FRD
Energy Storage - quick start and ramping ability, ESS have become an increased interest [9]
RR- Ramp Rate, FRP- Flexible Ramp Products
PS Flexibility (Cont…)
Ability of PHES in FRP provision and its impact on system operations
Mature technology
High power density and energy density
96% of total installed storage capacity
A detailed modelling of PHES is incorporated in a 15-minute temporal DA SCUC and 5-minute RT re-dispatch
Effectiveness of the proposed model is analysed on IEEE RTS 24 bus test system.
Performance parameters like load and RE curtailment, operating cost and cycling of units are studied.
Contribution
Objective Function:
Subject to- operational and network constraints of
Generator minimum and maximum generation
Generator up/down ramp
Generator minimum Up/Down Time
Transmission line limit
Scheduling Problem
D D D RT RToper ener res frpMin C C C C Lc Rc= + + + + …(1)
PHES Modelling
Scheduling Problem (cont...)
, ,( ).turb UR turbph t g ph tP gH Qη ρ=
, ,( ). /pump pumpLRmph t ph tP gH Qρ η=
, , 1 ,,( )pumpUR UR turbph t ph t ph tph tL L Q Q t−= + −
, , 1 , ,( )pumpLR LR turbph t ph t ph t ph tL L Q Q t−= + −
_, ,,
g stor stor turbph t ph tph tP RU P+ ≤
_,, ,
m stor pumpstorph tph t ph tP RD P− ≤
…(3)
…(2)
…(4)
…(5)
…(6)
…(7)
max, ,, pumpturb
ph t phph tQ Q Q≤
_ min _ max,, ,
LR LRLRph tph t ph tL L L≤ ≤
_ min _ max,, ,
UR URURph tph t ph tL L L≤ ≤ …(10)
…(9)
…(8)
RT ramp requirement:
Scheduling Problem (cont…)
_1max(0, )RT up RT RT
m m mNLR NL NL −= −
_1max(0, )RT dn RT RT
m m mNLR NL NL−= −
_ _ _, ,RT gen RT stor RT up
mi m i mi ph
RU RU NLR+ =∑ ∑
_ _ _, ,RT gen RT stor RT dn
mi m i mi ph
RD RD NLR+ =∑ ∑
…(11)
…(12)
…(13)
…(14)
The proposed model is implemented on IEEE RTS 24 bus test system with a peak load of 2650 MW
Solar and wind generation - buses 3,5,20 and 23
Solar radiation and wind speed - CAISO for July 2018 [12]
Load Profile – normalized CAISO hourly load profile wrt peak demand of test case
Costs:
Opportunity cost for the reserve : $3.34/MW
FRP procurement: 20% higher than the average market clearing price of energy.
Case Study
Data (Cont…)
0100200300400500600700800
0
500
1000
1500
2000
2500
3000t1 t4 t7 t10
t13
t16
t19
t22
t25
t28
t31
t34
t37
t40
t43
t46
t49
t52
t55
t58
t61
t64
t67
t70
t73
t76
t79
t82
t85
t88
t91
t94
Sola
r an
d W
ind
Gen
erat
ion
(MW
)
Tota
l Loa
d (M
W)
Time (15 minutes block) Load Solar Wind
Figure 2. Day-ahead load and renewable profile at 30% RE integration
Case-1: FRP Provision from conventional units Case-2: FRP Provision from conventional units and PHES
FRP in DA is estimated from the standard deviation of historical data
Result Analysis
0
100
200
300
400
500
600
700
800
0
500
1000
1500
2000
2500
3000
t1 t5 t9 t13
t17
t21
t25
t29
t33
t37
t41
t45
t49
t53
t57
t61
t65
t69
t73
t77
t81
t85
t89
t93
RE
_ge
n/R
am_
req
(MW
)
Tota
l Loa
d/C
onv_
gen
(MW
)
Time (15 minutes block)
Conv_gen Total Load Ramp_req RE_gen
Figure 3. Day-ahead scheduling at 30% RE integration
Case-1:
Commitment status and scheduling of committed units is considered
Changes in net-load is supplied by up and down FRPs
Ramping incapability between dispatch intervals resulted in load curtailment with a max. value of 285 MW at block m190
Result Analysis (Cont…)
0
50
100
150
200
250
300
0
500
1000
1500
2000
2500
3000
m1
m8
m15
m22
m29
m36
m43
m50
m57
m64
m71
m78
m85
m92
m99
m10
6m
113
m12
0m
127
m13
4m
141
m14
8m
155
m16
2m
169
m17
6m
183
m19
0m
197
m20
4m
211
m21
8m
225
m23
2m
239
m24
6m
253
m26
0m
267
m27
4m
281
m28
8
FRU
/FR
D/L
oad_
curt
(MW
)
Con
v_di
spat
ch/N
et_
load
(MW
)
Time (5 minutes block)
P_Dispatch Net_load FRU FRD Load_Curt
Figure 4. Real-Time Power balance at 30% RE integration
PHES participation in energy, reserve and FRP markets resulted in low operating costs
Result Analysis (Cont…) Case- II
0
50
100
150
200
250
0
500
1000
1500
2000
2500
3000
t1 t4 t7 t10
t13
t16
t19
t22
t25
t28
t31
t34
t37
t40
t43
t46
t49
t52
t55
t58
t61
t64
t67
t70
t73
t76
t79
t82
t85
t88
t91
t94
PHE
S_ge
n/PH
ES_
mot
/Ram
p_re
q (M
W)
Con
v_ge
n/N
et_
load
(MW
)
Time (15 minutes block)
Conv_gen Net_load PHES_gen PHES_mot Ramp_req
Figure 5. Day-ahead scheduling of conventional units and PHES at 30% RE integration
Maximum Value of load curtailment in the case has decreased to 136 MW
Deviation of PHES pumping in real time is observed compared to its day-ahead schedule
Result Analysis (Cont…)
0
10
20
30
40
50
60
020406080
100120140160
m1
m9
m17
m25
m33
m41
m49
m57
m65
m73
m81
m89
m97
m10
5m
113
m12
1m
129
m13
7m
145
m15
3m
161
m16
9m
177
m18
5m
193
m20
1m
209
m21
7m
225
m23
3m
241
m24
9m
257
m26
5m
273
m28
1 PHE
S_FR
U/P
HE
S_FR
D (M
W)
Load
_cu
rt/C
onv_
FRU
/Con
v_FR
D
(MW
)
Time (5 Minutes block) Load_curt Conv_FRU Conv_FRD PHES_FRU PHES_FRD
Figure 7. FRP provision from conventional units and PHES in real-time at 30% RE integration
Result Analysis (Cont…)
Parameter 30% RE Integration
40% RE Integration
Case-I Operating Cost
($) 4596032 4165769
Load Curtailment
(MWh) 515 358
FRU deployed (MWh) 716.25 740
FRD deployed (MWh) 10 22.5
Case-II Operating Cost
($) 4170586 3904470
Load Curtailment
(MWh) 307 250
FRU deployed (MWh) 799.16 861
FRD deployed (MWh) 18 13
Table 1: Comparison of cases at different RE Integration
Variability and uncertainty associated with RES necessitates flexible resources in the system.
Improved operations+ Energy Storage
Flexibility product from the coordinated operation of conventional units and PHES is proposed along with improved operations
Integration of fast start units like PHES resulted in reduction in cycling of conventional units.
Use of peaking units decreased with FRP from PHES
Load curtailment and operating costs decrement with PHES participation at different RE penetrations is observed.
Conclusion
References 1. https://www.globalenergyinstitute.org/look-ieas-new-global-energy-forecast 2. H. Nosair and F. Bouffard, "Flexibility Envelopes for Power System Operational Planning," in
IEEE Transactions on Sustainable Energy, vol. 6, no. 3, pp. 800-809, July 2015. 3. B. Zhang and M. Kezunovic, "Impact on Power System Flexibility by Electric Vehicle Participation
in Ramp Market," in IEEE Transactions on Smart Grid, vol. 7, no. 3, pp. 1285-1294, May 2016. 4. Kyle Westendorf, " Flexible Ramping Product UncertaintyCalculation and Implementation Issues,"
CAISO, Apr. 18, 2018. Accessed on: Jun. 30, 2019. [Online]. Available: Available: https://www.caiso.com/Documents/FlexibleRampingProductUncertaintyCalculationImplementationIssues.pdf
5. E. Heydarian-Forushani, M. E. H. Golshan and P. Siano, "Evaluating the Operational Flexibility of Generation Mixture with an Innovative Techno-Economic Measure," in IEEE Transactions on Power Systems, vol. PP, no. 99, pp. 1-1.
6. E. Ibanez, I. Krad and E. Ela, "A systematic comparison of operating reserve methodologies," 2014 IEEE PES General Meeting,Conference & Exposition, National Harbor, MD, 2014, pp. 1-5.
7. Y. Dvorkin, D. S. Kirschen and M. A. Ortega-Vazquez, "Assessing flexibility requirements in power systems," in IET Generation, Transmission & Distribution, vol. 8, no. 11, pp. 1820-1830, 11 2014.
8. J. Devlin, K. Li, P. Higgins and A. Foley, "System flexibility provision using short term grid scale storage," in IET Generation, Transmission & Distribution, vol. 10, no. 3, pp. 697-703, 2 18 2016.
9. M. B. Anwar, H. W. Qazi, D. J. Burke and M. J. O’Malley, "Harnessing the Flexibility of Demand-Side Resources," in IEEE Transactions on Smart Grid, vol. 10, no. 4, pp. 4151-4163, July 2019.
10. P. Kushwaha, V. Prakash, R. Bhakar, U. R. Yaragatti, A. Jain and Y. Sumanth, "Assessment of Energy Storage Potential for Primary Frequency Response Adequacy in Future Grids," 2018 8th IEEE India International Conference on Power Electronics (IICPE), JAIPUR, India, 2018, pp. 1-6.
11. A. Jain, S. Yamujala, P. Das, R. Bhakar, J. Mathur and P. Kushwaha, "Stacked Benefits of Energy Storage in Microgrid Scheduling," 2018 8th IEEE India International Conference on Power Electronics (IICPE), JAIPUR, India, 2018, pp. 1-5.
12. Y. Sumanth, A. Jain, P. Das, R. Bhakar, J. Mathur and P. Kushwaha, "Operational Strategy of Energy Storage to Address Day-Ahead Scheduling Errors in High RE Scenario," 2018 8th IEEE India International Conference on Power Electronics (IICPE), JAIPUR, India, 2018, pp. 1-6.
13. “Hourly and 15 minute wind and solar data sets”. Accessed on: Apr. 15, 2019. [Online]. Available: http://www.soda-pro.com/web-services
14. Technical Report, “Pinnapuram Integrated Renewable Energy With Storage Project (IRESP)”, Greenko Energies Pvt. Ltd., Accessed on: Jul. 05, 2019. [Online]. Available: http://environmentclearance.nic.in/writereaddata/Online/TOR/16_Apr_2018_13182853391O82IHRPinnapuramPFRFinalToR.pdf
15. Juan M. Morales, Antonio J. Conejo, Henrik Madsen, Pierre Pinson and Marco Zugno, “Integrating Renewables in Electricity Markets”, 2014.
References (Cont…)
Thank You !!