flow shop production
DESCRIPTION
Flow Shop Production. http://business.mrwood.com.au/unit3/opstrat/opstrat1.asp. Flow shop layout. cf. Heizer, J., Render, B., Operations Management, Prentice Hall, 2006, Chapter 9 - PowerPoint PPT PresentationTRANSCRIPT
Flow Shop Production
http://business.mrwood.com.au/unit3/opstrat/opstrat1.asp
Flow shop layout
cf. Heizer, J., Render, B., Operations Management, Prentice Hall, 2006, Chapter 9cf. Francis, R., McGinnis, L., White, J., Facility Layout and Location: An Analytical Approach, Prentice Hall, 1992
(c) Prof. Richard F. Hartl
Flow shop production
Object-oriented
Assignment is derived from the item´s work plans. Uniform material flow:
Linear assignment (in most cases) Useful if (and only if) only one kind of product or a limited
amount of different kinds of products is manufactured (i.e. low variety – high volume)
(c) Prof. Richard F. Hartl
Flow shop production
According to time-dependencies we distinguish between
Flow shop production without fixed time restriction for each workstation („Reihenfertigung“)
Flow shop production with fixed time restriction for each workstation (Assembly line balancing, „Fließbandabgleich“)
(c) Prof. Richard F. Hartl
Flow shop production
No fixed time restriction for the workload of each workstation: Intermediate inventories are needed Material flow should be similiar for all products Some workstations may be skipped, but going back to a previous department is
not possible Processing times may differ between products
Inventory Station 1 Int. inventory Station 2 ... Station m Inventory
(c) Prof. Richard F. Hartl
Flow shop production
Fixed time restricition (for each workstation): Balancing problems Cycle time („Taktzeit“): upper bound for the workload of each workstation. Idle time: if the workload of a station is smaller than the cycle time.
Production lines, assembly lines automated system (simultaneous shifting)
Station 1 Station 2 Station 3 ...
(c) Prof. Richard F. Hartl
Assembly line balancing
Production rate = Reciprocal of cycle time The line proceeds continuously. Workers proceed within their station parallel with their workpiece
until it reaches the end of the station; afterwards they return to the beginning of the station.
Further possibilites: Line stops during processing time Intermittent transport: workpieces are transported between the stations.
(c) Prof. Richard F. Hartl
Assembly line balancing
„Fließbandabstimmung“, „Fließbandaustaktung“, „Leistungsabstimmung“, „Bandabgleich“
The mulit-level production process is decomomposed into n operations/tasks for each product.
Processing time tj for each operation j Restrictions due to production sequence of precedences may occur
and are displayed using a precedence graph:
Directed graph witout cyles G = (V, E, t) No parallel arcs or loops Relation i < j is true for all (i, j)
(c) Prof. Richard F. Hartl
Example
Operation j Predecessor tj
1 - 6
2 - 9
3 1 4
4 1 5
5 2 4
6 3 2
7 3, 4 3
8 6 7
9 7 3
10 5, 9 1
11 8,1 10
12 11 1
t1=61 1
12 1011 3
9 37
78
26
43
54
..110
t2=92
45
Precedence graph
(c) Prof. Richard F. Hartl
Flow shop production
Machines (workstations) are assigned in a row, each station contains 1 or more operations/tasks.
Each operation is assigned to exactly 1 station i before j , (i, j) E:
i and j in same station or i in an earlier station than j
Assignment of operations to stations: Time- or cost oriented objective function Precedence conditions Optimize cycle time Simultaneous determination of number of stations and cycle time
(c) Prof. Richard F. Hartl
Single product problems
Simple assembly line balancing problem Basic model with alternative objectives
(c) Prof. Richard F. Hartl
Single product problems
Assumptions: 1 homogenuous product is produced by performing n operations given processing times ti for operations j = 1,...,n Precedence graph Same cycle time for all stations fixed starting rate („Anstoßrate“) all stations are equally equipped (workers and utilities) no parallel stations closed stations workpieces are attached to the line
(c) Prof. Richard F. Hartl
Alternative1
Minimization of number of stations m (cycle time is given):
Cycle time c: lower bound for number of stations
upper bound for number of stations
ctm j
n
j 1min :
11: max1
max
tctm j
n
j
(c) Prof. Richard F. Hartl
Alternative 1Derivation of upper bound:
t(Sk) … workload of station k Sk, k = 1, ..., m
Integer property
Sum of inequalities
and integer property of m
max1
111 tcmSt k
m
k
k
m
kj
n
jStt
1
11
upper bound
tmax + t(Sk) > c i.e. t(Sk) c + 1 - tmax k =1,...,m-1
(c) Prof. Richard F. Hartl
Alternative 2
Minimization of cycle time (i.e. maximization of prodcution rate)
lower bound for cycle time c: tmax = max {tj j = 1, ... , n} … processing time of longest operation
c tmax Maximum production amount qmax in time horizon T is given
Given number of stations m
maxqTc
mtc jn
j 1
(c) Prof. Richard F. Hartl
Alternative 2
lower bound for cycle time:
upper bound for cycle time
mtqTtcc jn
j 1maxmaxmin ,,max:
min/qTc
(c) Prof. Richard F. Hartl
Alternative 3
Maximization of efficiency („Bandwirkungsgrad“)
Determination of: Cycle time c Number of stations m Efficiency („BG“)
BG = 1 100% efficiency (no idle time)
j
n
jt
cmBG
1
1
(c) Prof. Richard F. Hartl
Alternative 3
Lower bound for cycle time: see Alternative 2 Upper bound for cycle time cmax is given
Lower bound for number of stations
Upper bound for number of stations
max
1min : ctm j
n
j
11: maxmin1
max
tctm j
n
j
(c) Prof. Richard F. Hartl
ExampIe
T = 7,5 hours Minimum production amount qmin = 600 units seconds/unit 45600/3600*5,7: minmax qTc
t1=6 1
1 12
10 11 3
9 3 7
7 8
2 6
4 3
5 4
..1 10
t2=9 2
4 5
(c) Prof. Richard F. Hartl
ExampIe
Arbeitsgang j Vorgänger tj
1 - 6
2 - 9
3 1 4
4 1 5
5 2 4
6 3 2
7 3, 4 3
8 6 7
9 7 3
10 5, 9 1
11 8,1 10
12 11 1
Summe 55
tj = 55
No maximum production amount
Minimum cycle timecmin = tmax = 10 seconds/unit
m t cj
n
jmin max:
155 45 2
(c) Prof. Richard F. Hartl
ExampIe
0
1
2
3
4
5
6
7
10 20 30 40 50 60
m BG = 1 BG = 0.982
c Combinations of m and c leading to feasible solutions.
(c) Prof. Richard F. Hartl
ExampIe
maximum BG = 1(is reached only with invalid values m = 1 and c = 55)
Optimal BG = 0,982(feasible values for m and c: 10 c 45 und m 2)
m = 2 stations c = 28 seconds/unit
(c) Prof. Richard F. Hartl
# Stationen m
theoretisch min Taktzeit
minimale realisierbare Taktzeit c
Bandwirkungsgrad 55/cm
1 55 nicht möglich da c 45 -
2 28 28 0,982
3 19 19 0.965
4 14 15 0,917
5 11 12 0.917
6 10 10 0,917
Example
Possible cycle times c for varying number of stations m
m55
Increasing cycle time Reduction of BG (increasing idle time) until 1 station can be omitted. BG has a local maximum for each number of stations m with the minimum cycle time c where a feasible solution for m exists.
(c) Prof. Richard F. Hartl
Further objectives
Maximization of BG is equivalent to Minimization of total processing time („Durchlaufzeit“):
D = m c
Minimization of sum of idle times:
Minimization of ratio of idle time: LA = = 1 – BG
Minimization of total waiting time:
j
n
jtcmL
1
mcL
LtDW j
n
j
1
(c) Prof. Richard F. Hartl
LP formulation
We distinguish between:
LP-Formulation for given cycle time
LP-Formulation for given number of stations
Mathematical formulation for maximization of efficiency
(c) Prof. Richard F. Hartl
LP formulation for given cycle time
Binary variables:
= number of station, where operation j is assigned to
Assumption: Graph G has only 1 sink, which is node n
otherwise0
station toassigned is operation if1 k jx jk
j = 1, ..., n
k = 1, ..., mmax
max
1
m
kjkxk
(c) Prof. Richard F. Hartl
LP formulation for given cycle time
Objective function:
Constraints:
nk
m
kxkxZMinimize
max
1
1max
1
m
kjkx
ctx jn
j=jk
1
maxmax
11
m
kjk
m
khk xkxk
10,x jk
j = 1, ... , n ... j on exactly 1 station
k = 1, ... , mmax ... Cycle time
… Precedence cond.
... Binary variables
Eh,j
j and k
(c) Prof. Richard F. Hartl
Notes
Possible extensions: Assignment restrictions (for utilities or positions)
elimination of variables or fix them to 0
Restrictions according to operations Operations h and j with (h, j) are not allowed to be assigned
to the same station.
E(h,j)xkxkm
k
m
kjkhk with 1
1 1
(c) Prof. Richard F. Hartl
LP formulation for given number of stations
Replace mmax by the given number of stations m
c becomes an additional variable
(c) Prof. Richard F. Hartl
LP formulation for given number of stations
Objective function: Minimize Z(x, c) = c … cycle time
Constraints:
j = 1, ... , n ... j on exactly 1 station
k = 1, ... , m ... cycle time
... precedence cond.
j und k ... binary variables
Eh,j
11
m
kjkx
ctx jn
j=jk
1
m
kjk
m
khk xkxk
11
10,x jk
c 0 and integer
(c) Prof. Richard F. Hartl
LP formulation for maximization of BG
If neither cycle time c nor number of stations m is given take the formulation for given cycle time.
Objective function (nonlinear):
Additional constraints:c cmax
c cmin
nk
m
kxkccxZ
max
1, Minimize
(c) Prof. Richard F. Hartl
LP formulation for maximization of BG
Derive a LP again Weight cycle time and number of stations with factors w1 and w2
Objective function (linear):
Minimize Z(x,c) = w1(kxnk) + w2c
Large Lp-models! Many binary variables!
(c) Prof. Richard F. Hartl
Heuristic methods in case of given cycle time
Many heuristic methods(mostly priorityrule methods)
Shortened exact methods
Enumerative methods
(c) Prof. Richard F. Hartl
Priorityrule methods
Determine a priortity value PVj for each operation j
Prioritiy list
A non-assigned operation j can be assigned to station k if all his precedessors are already assigned to a station 1,..k and the remaining idle time in station k is equal or larger than the
processing time of operation j
(c) Prof. Richard F. Hartl
Priorityrule methods
Requirements: Cycle time c Operations j=1,...,n with processing times tj c Precedence graph, defined by a set of precedessors
Variables k number of current station idle time of current station Lp set of already assigned operations Ls sorted list of n operations in respect to priority value
c
(c) Prof. Richard F. Hartl
Priorityrule methods
Operation j Lp can be assigned, if tj and h Lp is true for all h V(j)
Start with station 1 and fill one station after the other
From the list of operations ready to be assigned to the current station the highest prioritized is taken
Open a new station if the current station is filled to the maximum
c
(c) Prof. Richard F. Hartl
Priorityrule methods
Start: determine list Ls by applying a prioritiy rule; k := 0; LP := <]; ... No operations assigned so far
Iteration:repeat
k := k+1; := c;while there is an operation in list Ls that can be assigned to station k do
beginselect and delete the first operation j (that can be assigned to) from list Ls;Lp:= < Lp,j]; :=- tjend;
until Ls = <];Result: Lp contains a valid sorted list of operations with m = k stations.
Single-pass- vs. multi-pass-heuristics (procedure is performed once or several times)
c
c
(c) Prof. Richard F. Hartl
Priorityrule methods
Rule 1: Random choice of operations
Rule 2: Choose operations due to monotonuously decreasing (or increasing) processing time: PVj: = tj
Rule 3: Choose operations due to monotonuously decreasing (or increasing) number of direct followers:
PVj : = (j)
Rule 4: Choose operations due to monotonuously increasing depths of operations in G:PVj : = number of arcs in the longest way from a source of the graph to j
(c) Prof. Richard F. Hartl
Priorityrule methods
Rule 5 Choose operations due to monotonuously decreasing positional weight („Positionswert“):
Rule 6: Choose operations due to monotonuously increasing upper bound for the minimum number of stations needed for j and all it´s predecessors:
Rule 7: Choose operations due to monotonuously increasing upper bound for the latest possible station of j:
mjNh
hj tt:PVj
cttmjVh
hjjj E:PV
cttmLmjNh
hjj 1:PVj
(c) Prof. Richard F. Hartl
Example – Rule 5
t1=6 1
1 12
10 11 3
9 3 7
7 8
2 6
4 3
5 4
..1 10
t2=9 2
4 5
j 1 2 3 4 5 6 7 8 9 10 11 12tj 6 9 4 5 4 2 3 7 3 1 10 1
PVj(5) 42 25 31 23 16 20 18 118 111215
Cycle time c = 28 -> m = 3 stationsBG = tj / (3*28) = 0,655
S1 = {1,3,2,4,6}
S2 = {7,8,5,9,10,11}
S3 = {12}
(c) Prof. Richard F. Hartl
Example– Regel 7, 6 und 2
= 3 mj 1 2 3 4 5 6 7 8 9 10 11 12
PVj(7)
PVj(6)
PVj(2)
1 21
11 1 11 1 1 1 1
1 1103
2 2 2 2 2 2 2 2 22 22
26 9 4 5 4 3 7
Apply rule 7 (latest possible station) at firstIf this leads to equally prioritized operatios -> apply rule 6 (minimum number of stations for j and all predecessors)If this leads to equally prioritized operatios -> apply rule 2 (decreasing processing times tj)Solution: c = 28 m = 2; BG = 0,982
S1 = {1,3,2,4,5} ; S2 = {7,9,6,8,10,11,12}
(c) Prof. Richard F. Hartl
More heuristic methods
Stochastic elements for rules 2 to 7: Random selection of the next operation (out of the set of
operations ready to be applied) Selection probabilities: proportional or reciprocally proportional
to the priority value Randomly chosen priority rule
Enumerative heuristics: Determination of the set of all feasible assignments for the first
station Choose the assignment leading to the minimum idle time Proceed the same way with the next station, and so on (greedy)
(c) Prof. Richard F. Hartl
Further heuristic methods
Heuristics for cutting&packing problems Precedence conditions have to be considered as well E.g.: generalization of first-fit-decreasing heuristic for the bin
packing problem.
Shortest-path-problem with exponential number of nodes
Exchange methods: Exchange of operations between stations Objective: improvement in terms of the subordinate objective of
equally utilized stations
(c) Prof. Richard F. Hartl
Worst-Case analysis of heuristics
Solution characteristics for integer c and tj
(j = 1,...,n) for Alternative 2:
Total workload of 2 neigboured stations has to exceed the cycle time
Worst-Case bounds for the deviation of a solution with mStations from a solution with m* stations:
11 allfor 1
11 allfor 1
max
1
,...,m-k=ctSt,...,m-k=cStSt
k
kk
m/m* 2 - 2/m* for even m and m/m* 2 - 1/m* for odd mm < cm*/(c - tmax + 1) + 1
(c) Prof. Richard F. Hartl
Determination of cyle time c
Given number of stations
Cycle time unknown Minimize cycle time (alternative 1) or Optimize cycle time together with the number of stations trying to
maximize the system´s efficiency (alternative 3).
(c) Prof. Richard F. Hartl
Iterative approach for determination of minimal cycle time
1. Calculate the theoretical minimal cycle time:
(or cmin = tmax if this is larger) and c = cmin
2. Find an optimal solution for c with minimum m(c) by applying methods presented for alternative 1
3. If m(c) is larger than the given number of stations: increase c by (integer value) and repeat step 2.
stations ofnumber minjt
c
(c) Prof. Richard F. Hartl
Iterative approach for determination of minimal cycle time
Repeat until feasible solution with cycle time c and number of stations m is found
If > 1, an interval reduction can be applied: if for c a solution with number of stations m has been found and for c- not, one can try to find a solution for c-/2 and so on…
(c) Prof. Richard F. Hartl
Example – rule 5
m = 5 stationsFind: maximum production rate, i.e. minimum cycle time
j 1 2 3 4 5 6 7 8 9 10 11 12tj 6 9 4 5 4 2 3 7 3 1 10 1
PVj(5) 42 25 31 23 16 20 18 18 15 12 11 1
cmin = tj/m = 55/5 = 11 (11 > tmax = 10)
(c) Prof. Richard F. Hartl
Example – rule 5
Solution c = 11:{1,3}, {2,6}, {4,7,9}, {8,5}, {10,11}, {12} Needed: 6 > m = 5 stations
c = 12, assign operation 12 to station 5
S5 = {10,11,12}
For larger problems: usually, c leading to an assignment for the given number of stations, is much larger than cmin. Thus, stepwise increase of c by 1 would be too time consuming -> increase by > 1 is recommended.
t1=6 1
1 12
10 11 3
9 3 7
7 8
2 6
4 3
5 4
.1 10
t2=9 2
4 5
(c) Prof. Richard F. Hartl
Classification of complex line balancing problems
Parameters: Number of products Assignment restrictions Parallel stations Equipment of stations Station boundaries Starting rate Connection between items and transportation system Different technologies Objectives
(c) Prof. Richard F. Hartl
Number of products
Single-product-models: 1 homogenuous product on 1 assembly line Mass production, serial production
Multi-product models: Combined manufacturing of several products on 1 (or more) lines.
Mixed-model-assembly: Products are variations (models) of a basic product they are processed in mixed sequence
Lot-wise multiple-model-production: Set-up between production of different products is necessary Production lots (the line is balanced for each product separately) Lotsizing and scheduling of products TSP
(c) Prof. Richard F. Hartl
Assignment restrictions
Restricted utilities: Stations have to be equipped with an adequate quantity of utilities Given environmental conditions
Positions: Given positions of items within a station
some operation may not be performed then (e.g.: underfloor operations)
Operations: Minimum or maximum distances between 2 operations (concerning time
or space) 2 operations may not be assigned to the same station
Qualifications: Combination of operations with similiar complexity
(c) Prof. Richard F. Hartl
Parallel stations
Models without parallel stations: Heterogenuous stations with different operations serial line
Models with parallel stations: At least 2 stations performing the same operation Alternating processing of 2 subsequent operations in parallel stations
Hybridization: Parallelization of operations: Assignment of an operation to 2 different stations of a serial line
(c) Prof. Richard F. Hartl
Equipment of stations
1-worker per station
Multiple workers per station: Different workloads between stations are possible Short-term capacity adaptions by using „jumpers“
Fully automated stations: Workers are used for inspection of processes Workers are usually assigned to several stations
(c) Prof. Richard F. Hartl
Station boundaries
Closed stations: Expansion of station is limited Workers are not allowed to leave the station during processing
Open stations: Workers my leave their station in („rechtsoffen“) or in reversed
(„linksoffen“) flow direction of the line Short-term capacity adaption by under- and over-usage of cycle time. E.g.: Manufacturing of variations of products
(c) Prof. Richard F. Hartl
Starting rate
Models with fixed starting rate: Subsequent items enter the line after a fixed time span.
Models with variable starting rate: An item enters the line once the first station of the line is idle Distances between items on the line may vary (in case of multiple-
product-production)
(c) Prof. Richard F. Hartl
Connection between items and transportation systems
Unmoveable items: Items are attached to the transportation system and may not be
removed Maybe turning moves are possible
Moveable items: Removing items from the transportation system during processing is
allowed Post-production Intermediate inventories
Flow shop production without fixed time constraints for each station
(c) Prof. Richard F. Hartl
Different technologies
Given production technologies Schedules are given
Different technologies Production technology is to be chosen Different alternative schedules are given (precedence graph)
and/or
different processing times for 1 operation
(c) Prof. Richard F. Hartl
Objectives
Time-oriented objectives Minimization of total cycle time, total idle time, ratio of idle time, total
waiting time Maximization of capacity utilization (system`s efficieny) – most relevant
for (single-product) problems Equally utilized stations
Further objectives Minimization of number of stations in case of given cycle time Minimization of cycle time in case of given number of stations Minimization of sum of weighted cycle time and weighted number of
stations
(c) Prof. Richard F. Hartl
Objectives
Profit-oriented approaches: Maximization of total marginal return Minimization of total costs
Machines- and utility costs (hourly wage rate of machines depends on the number of stations)
Labour costs: often identical rates of labour costs for all workers in all stations
Material costs: defined by output quantity and cycle time Idle time costs: Opportunity costs – depend on cycle time and number of
stations
(c) Prof. Richard F. Hartl
Multiple-product-problems
Mixed model assembly:Several variants of a basic product are processed in mixed sequence on a production line.
Processing times of operations may vary between the models Some operations may not be necessary for all of the variants Determination of an optimal line balancing and of an optimal
sequence of models.
(c) Prof. Richard F. Hartl
multi-model Lot-wise
mixed-model production
With machine set-up Set-up from type „X“ to type „Y“ after 2
weeks
(c) Prof. Richard F. Hartl
mixed-model Without set-up Balancing for a
„theoretical average model“
(c) Prof. Richard F. Hartl
Balancing mixed-model assembly lines
Similiar models: Avoid set-ups and lot sizing Consider all models simultaneously
Generalization of the basic model Production of p models of 1 basic model with up to n operations;
production method is given Given precedence conditions for operations in each model j = 1,...,n
aggregated precendence graph for all models Each operation is assigned to exactly 1 station Given processing times tjv for each operation j in each model v Given demand bv for each model v Given total time T of the working shifts in the planning horizon
(c) Prof. Richard F. Hartl
Balancing mixed-model assembly lines
Total demand for all models in planning horizon
Cumulated processing time of operation j over all models in planning horizon:
p
vvbb
1
jvp
vvj tbt
1
(c) Prof. Richard F. Hartl
LP-Model
Aggregated model: Line is balanced according to total time T of working shifts in the
planning horizon.
Same LP as for the 1-product problem, but cycle time c is replaced by total time T
m,...,k= ,...,n j= S j
x kjk 1and1allfor
otherwise0operation if1
(c) Prof. Richard F. Hartl
LP-Model
Objective function:
nk
m
kxkxZMinimize
1 … number of the last station (job n)
Constraints:
for all j = 1, ... , n ... Each job in 1 station
for all k = 1, ... , n ... Total workload in station k
for all ... Precedence conditions
for all j and k
x jkk
m
11
x tjkj=
n
j1
T
k x k xhkk
m
jkk
m
1 1
x ,jk 0 1
h,j E
(c) Prof. Richard F. Hartl
Example
v = 1, b1 = 4 v = 2, b2 = 2
v = 3, b3 = 1 aggregated model
t12=51 0
12 1111 4
9 17
48
16
63
54
110
112
35
t13=81 3
12 811 1
9 37
138
46
03
54
110
132
25
t11=6 1
1 12
10 11 3
9 4 7
7 8
2 6
4 3
5 4
1 10
7 2
5 5
t1=42 1
7 12
70 11 21
9 21 7
49 8
14 6
28 3
35 4
7 10
63 2
28 5
(c) Prof. Richard F. Hartl
Example
Applying exact method:
given: T = 70
Assignment of jobs to stations with m = 7 stations:S1 = {1,3}S2 = {2} S3 = {4,6,7} S4 = {8,9} S5 = {5,10} S6 = {11} S7 = {12}
(c) Prof. Richard F. Hartl
Parameters
... Workload of station k for model v in T
... Average workload of m stations for model v in T
Per unit:
... Workload of station k for 1 unit of model v
... Avg. workload of m stations for 1 unit of model v
Aggregated over all models:
... Total workload of station k in T
kv v jv jkj
nb t x
1
v v jvj
nb t m
/
1
kv jv jkj
nt x
1
v jvj
nt m/
1
t S tk kvv
p( )
1
(c) Prof. Richard F. Hartl
Example – parameters per unit
’kv
Station k Avg.
Model v 1 2 3 4 5 6 7 `v
1 10 7 11 10 6 10 1 7,86
2
3
11 11 7 8 4 0
8
7,4311
13 12 14 3 8 3 8,71
x 4
x 2
x 1
(c) Prof. Richard F. Hartl
Example - Parameters
kv
Station k Avg.
Model v 1 2 3 4 5 6 7 v
1 40 28 44 40 24 40 4 31,43
2
3
t(Sk) 70 63 70 70 35 70 7 55
22 14 16 8 22 0 14,86
8 1213 14 383
22
8,71
(c) Prof. Richard F. Hartl
Conclusion
Station 5 and 7 are not efficiently utilized
Variation of workload kv of stations k is higher for the models v as for the aggregated model t(Sk)
Parameters per unit show a high degree of variation for the models. Model 3, for example, leads to an high utilization of stations 2, 3, and 4.
If we want to produce several units of model 3 subsequently, the average cycle time will be exceeded -> the line has to be stopped
(c) Prof. Richard F. Hartl
Avoiding unequally utilized stations
Consider the following objectives Out of a set of solutions leading to the same (minimal) number of
stations m (1st objective), choose the one minimizing the following 2nd objective:
...Sum of absolute deviation in utilization
Minimization by, e.g., applying the following greedy heuristic
p
vvkv
m
k 11
(c) Prof. Richard F. Hartl
Thomopoulos heuristic
Start: Deviation = 0, k = 0
Iteration: until non-assigned jobs are available:
increase k by 1
determine all feasible assignments Sk for the next station k
choose Sk with the minimum sum of deviation
= + (Sk)
p
vvkvkS
1)(
(c) Prof. Richard F. Hartl
Thomopoulos example
T = 70 m = 7
Solution: 9 stations (min. number of stations = 7):
S1 = {1}, S2 = {3,6}, S3 = {4,7}, S4 = {8}, S5 = {2}, S6 = {5,9}, S7 = {10}, S8 = {11}, S9 = {12}
Sum of deviation: = 183,14
(c) Prof. Richard F. Hartl
Thomopoulos heuristic
Consider only assignments Sk where workload t(Sk) exceeds a value (i.e. avoid high idle times).
Choose a value for : small:
well balanced workloads concerning the models Maybe too much stations
large: Stations are not so well balanced Rather minimum number of stations [very large maybe no
feasible assignment with t(Sk) ]
(c) Prof. Richard F. Hartl
Thomopoulos heuristic – Example
= 49
Solution:7 stations:
S1 = {2}, S2 = {1,5}, S3 = {3,4}, S4 = {7,9,10}, S5 = {6,8}, S6 = {11}, S7 = {12}
Sum of deviation: = 134,57
(c) Prof. Richard F. Hartl
Exact solution
7 stations:S1 = {1,3}, S2 = {2}, S3 = {4,5}, S4 = {6,7,9 }, S5 = {8,10}, S6 = {11}, S7 = {12}
Sum of deviation: = 126
kv
Station k Avg.
Modelv 1 2 3 4 5 6 7 v
1 40 28 40 36 32 40 4 31,43
2 22 22 16 12 10 22 0 14,86
3 8 13 7 8 14 8 3 8,71
t(Sk) 70 63 63 56 56 70 7 55
(c) Prof. Richard F. Hartl
Further objectives
Line balancing depends on demand values bj Changes in demand Balancing has to be reivsed and
further machine set-ups have to be considered
Workaround: Objectives not depending on demand
… sum of absolute deviations in utilization per unit
kv vv
p
k
m
11
(c) Prof. Richard F. Hartl
Further objectives
Disadvantages of this objective:
Large deviations for a station (may lead to interruptions in production). They may be compensated by lower deviations in other stations
... Maximum deviation in utilization per unitmax
,max k v
kv v