flowgate allocation method examples of proportional curtailment of firm ptp and gtl
TRANSCRIPT
![Page 1: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/1.jpg)
Flowgate Allocation Method
Examples of Proportional Curtailment of FIRM PTP and GTL
![Page 2: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/2.jpg)
Proportional Curtailment of Firm PTP and Firm GTL – Problem Statement
• Provide equal treatment of FIRM Point-to-Point (PTP) Transaction impacts and FIRM Generation-to-Load (GTL) Impacts during a TLR event– Flowgate allocation does not “downgrade” FIRM PTP and GTL transactions to NON-FIRM– TLR curtailment of FIRM contributions requires the issuance of a TLR-5 or higher– FIRM contributions are NOT curtailed in TLR-3a, TLR-3b and TLR-4
• Allocations are based on forecasted/reserved (Expected) FIRM usage of flowgates up to but not exceeding the flowgate limit– Expected FIRM usage is determined in the Day-Ahead and Hour-Ahead– All Expected FIRM contributions to the flow on the flowgate are included– The total Expected FIRM contributions does not exceed the flowgate limit:
• BAs and TSPs are allocated FIRM limits to their contribution on the flowgate that equals its total Expected FIRM contributions
– The total Expected FIRM contributions exceeds the flowgate limit:• BAs and TSPs are allocated FIRM limits to their contribution on the flowgate proportional to their
contribution• FIRM contributions are placed in two curtailment buckets – LAST TO CUT (LTC) and FIRST TO CUT
(FTC)– Nomenclature:
• PTP transactions: FTC = 7-F LTC = 7-FC• GTL: FTC = 7-FN LTC = 7-FCN
– FIRM contributions in FTC and LTC are determined in real-time based on current system conditions
– LTC: FIRM contributions in the LTC bucket are those that do NOT exceed the Expected FIRM usage of the flowgate for FIRM PTP and GTL impacts
– FTC: FIRM contributions in the FTC bucket are those that exceed the Expected FIRM usage of the flowgate for FIRM PTP and GTL impacts
![Page 3: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/3.jpg)
Proportional Curtailment of Firm PTP and Firm GTL - Example
• Flowgate limit: 500 MW
Entity DA/HA Firm GTL Impact
DA/HA Firm PTP Impact
GTL Firm Limit
PTP Firm Limit
A 150 75
B 160 120 80 60
C 160 80
D 120 200 60 100
E 40 50 20 25
Total 480 520 240 260
1,000 500
![Page 4: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/4.jpg)
Proportional Curtailment of Firm PTP and Firm GTL - Example
• Flowgate limit: 500 MW
Entity GTL Firm Limit
PTP Firm Limit
RT Firm GTL
Impact
RT Firm PTP
Impact
Over (Under)
Allocation
A 75 80 5
B 80 120 40
B 60 50 (10)
C 80 80 0
D 60 100 40
D 100 80 (20)
E 20 10 (10)
E 25 30 5
Total 240 260 310 240 50
500 550
![Page 5: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/5.jpg)
FTC and LTC Calculations• TLR 5-a requires curtailment of 65 MW of FIRM transactions after exhausting all
NON-FIRM curtailments– 65 MW of relief will be provided pro-rata from 90 MW of FTC (7-FC and 7-FCN), using
the same TLR pro-rata formulas– 460 MW of LTC (7-F and 7-FN) are not curtailed
Entity GTL Firm Limit
PTP Firm Limit
RT Firm GTL
Impact
RT Firm PTP
Impact
Over (Under)
Allocation
FTC LTC
A 75 80 5 5 75
B 80 120 40 40 80
B 60 50 (10) 0 50
C 80 80 0 0 80
D 60 100 40 40 60
D 100 80 (20) 0 80
E 20 10 (10) 0 10
E 25 30 5 5 25
Total 240 260 310 240 50 90 460
500 550 550
![Page 6: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/6.jpg)
Proportional Distribution of Under-Allocated Amounts to Over-Allocated GTL/PTP – Issues To Be Resolved
• Sum of all LTC (7-F and 7-FN) in Real-Time can be smaller than the flowgate limit– Only the over-allocated entities/transactions are “penalized” for over-
allocating• Remaining of flowgate limit can be reassigned to over-
allocated entities/transactions so that LTC equals the flowgate limit– Reduces the FTC bucket size– Distribution Proportion Options:
• FIRM limits of over-allocated entities/transactions• Real-Time over-allocation impact• Real-Time impacts• Other
– If TLR-5 cannot be resolved with curtailments from FTC bucket, may need to curtail pro-rata the LTC bucket• Entities/Transaction that do not over-allocate may be curtailed (see next
examples)
![Page 7: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/7.jpg)
Option 2: Proportional Distribution of Under-Allocated Amounts to Over-Allocated GTL/PTP – Proportional to Firm Limit
• Under-allocation from:– Entity B PTP: 10 MW– Entity D PTP: 20 MW– Entity E GTL: 10 MW– Total: 40 MW
• Distribute under-allocation among over-allocating entities:– Entity A PTP: 75 MW– Entity B GTL: 80 MW– Entity D GTL: 60 MW– Entity E PTP: 25 MW– Total: 240 MW
• Allocation Adjustment Ratio: (240+40)/240 = 1.17• Adjusted Firm Limit:
– Entity A PTP: 75 * 1.17 =87.8 MW– Entity B GTL: 80 * 1.17 =93.6 MW– Entity D GTL: 60 * 1.17 =70.2 MW– Entity E PTP: 25 * 1.17 =29.3 MW– Total: 240 MW
![Page 8: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/8.jpg)
Option 2: Proportional Distribution of Under-Allocated Amounts to Over-Allocated GTL/PTP – Proportional to Firm Limit
• Adjustment factor of 1.17 applied to firm limits of over-allocated PTP/GTL (needs iterative process to use all under allocation amounts)
• TLR 5-a requires curtailment of 65MW of FIRM transactions after exhausting all NON-FIRM curtailments– All 56.9 MW of FTC (7-FC and 7-FCN) will be curtailed– 8.1 MW of the 493.1 MW of LTC (7-F and 7-FN) will be curtailed pro-rata
• Total LTC is adjusted to equal total limit of the flowgateEntity GTL
Firm Limit
PTP Firm Limit
RT Firm GTL Impact
RT Firm PTP Impact
Over (Under) Allocation
Adj. GTL F-Limit
Adj. PTP F-Limit
FTC LTC
A 75 80 5 87.8 0 80
B 80 120 40 93.6 26.4 93.6
B 60 50 (10) 50 0 50
C 80 80 0 80 0 80
D 60 100 40 70.2 29.8 70.2
D 100 80 (20) 80 0 80
E 20 10 (10) 10 0 10
E 25 30 5 29.3 0.7 29.3
Total 240 260 310 240 50 253.8 247.1 56.9 493.1
500 550 500.9 550
![Page 9: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/9.jpg)
Option 3: Proportional Distribution of Under-Allocated Amounts to Over-Allocated GTL/PTP – Proportional to Real-Time Over-Allocation
• Under-allocation from:– Entity B PTP: 10 MW– Entity D PTP: 20 MW– Entity E GTL: 10 MW– Total: 40 MW
• Distribute under-allocation among over-allocating entities:– Entity A PTP: 5 MW– Entity B GTL: 40 MW– Entity D GTL: 40 MW– Entity E PTP: 5 MW– Total: 90 MW
• Allocation Adjustment Ratio: 40/90 = 0.44• Adjusted Firm Limit:
– Entity A PTP: 75 + 5*0.44 = 77.2 MW– Entity B GTL: 80 + 40*0.44 = 97.6 MW– Entity D GTL: 60 + 40*0.44 = 77.6 MW– Entity E PTP: 25 + 5*0.44 = 27.2 MW– Total: 279.6 MW
![Page 10: Flowgate Allocation Method Examples of Proportional Curtailment of FIRM PTP and GTL](https://reader036.vdocuments.net/reader036/viewer/2022082805/5514cc6655034693478b4d34/html5/thumbnails/10.jpg)
Option 3: Proportional Distribution of Under-Allocated Amounts to Over-Allocated GTL/PTP – Proportional to Real-Time Over Allocation
• Adjustment factor of 0.44 applied to over-allocated firm limits (no iterative process needed)
• TLR 5-a requires curtailment of 65MW of FIRM transactions after exhausting all NON-FIRM curtailments– All 50.4 MW of FTC (7-FC and 7-FCN) will be curtailed– 14.6 MW of the 499.6 MW of LTC (7-F and 7-FN) will be curtailed pro-rata
• Total LTC is adjusted to equal total limit of the flowgateEntity GTL
Firm Limit
PTP Firm Limit
RT Firm GTL Impact
RT Firm PTP Impact
Over (Under) Allocation
Adj. GTL F-Limit
Adj. PTP F-Limit
FTC LTC
A 75 80 5 77.2 2.8 77.2
B 80 120 40 97.6 22.4 97.6
B 60 50 (10) 50 0 50
C 80 80 0 80 0 80
D 60 100 40 77.6 22.4 77.6
D 100 80 (20) 80 0 80
E 20 10 (10) 10 0 10
E 25 30 5 27.2 2.8 27.2
Total 240 260 310 240 50 265.2 234.4 50.4 499.6
500 550 499.6 550