fluor presentation on managing mega projects

Upload: zubair

Post on 07-Jul-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    1/21

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    2/21

    Managing Mega projects

    Content

    Mega projects Definition

    Mega projects Challenges Driving and executing mega projects to success

    Mega projects execution - Risks & Opportunities

    Fluor tools and processes

    Mega projects Opportunities

    Information from: FLUOR guidelines, procedures and database.

    2012 AACE INTERNATIONAL TRANSACTIONS RISK.823.4

    Industrial Megaprojects: Concepts, Strategies and Practices for Success. (Edward W Merrow. 2011)

    MegaProjects and Risk, An Anatomy of Ambition, (Bent Flyvbjerg, Nils Bruzelius, Werner Rothengatter. 2003)

    1

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    3/21

    Mega project definition

    A mega project is an extremely large-scale investment project,typically defined as costing more than US$1 billion

    Mega projects attract a lot of public attention because of substantialimpacts on communities, environment, and budgets

    Mega projects include oil and gas, petrochemical, mining,aerospace, airports, canals, environmental, information technology,stadium and sporting venues, rail and rapid transportation, bridgeand highway, science, space flight, planned cities, dam andhydroelectric and water infrastructure projects

    Governments invest in mega projects to stimulate the general

    economy (i.e. Chinese economic stimulus program (2008-2009);the European Union stimulus plan (2008) and the AmericanRecovery and Reinvestment Act (2009)

    2

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    4/21

    Mega project elements

    3

    PROCESS

    ENGIN.COMPLEXITY MAYOR STIR.

    LABOR

    MARKETS

    COMPLEX

    EXECUTIONINTERFACE

    COST ANDSCHEDULES

      OWNERORGANIZATION

    COMPLEX

    ENVIRON.REGULATION

    PART OFA PROGRAM

    FINANCIALPROFILE

    MEGAPROJECTS

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    5/21

    4

    Political, security and financial instability

    Economic uncertainty (i.e. recession / devaluation)

    Government licensing and permitting constraints

    Transportation and logistical difficulties

    Extreme climatic conditions / Communications

    Manpower staffing, retention and labor unrest

    Camp and catering facilities

    Emergency preparedness and evacuation

    Healthcare services / medevac capabilities

    Environmental protection and preservation

    Mega project Challenges

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    6/21

    5

    Mega project Challenges

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    7/21

    Driving and executing Mega projects to success

    Business priorities (finance, investment, economic model, time tomarket, commercial opportunities, business objectives)

    Design Definition (Licensing process, engineering, contractingstrategy, procurement, construction, key engineering deliverablescompleteness)

    Organization Capability (Owner organization, dedicated owner´s

    team for core engineering and construction disciplines andmanaging interfaces)

    Project Controls (Level of controls needed, change management,risk management, physical progress attained before moving into

    next phase) Mega project / Program Execution

    6

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    8/21

    Mega project Execution (cont.)

    Program Execution - Risks and Opportunities

     – Integrated Stage-Gate Process (approval of internal and

    external stakeholders, partners)

     – Engineering/Construction Interface (engineering maturebefore construction starts – evaluate overlap in phases, effectiveinterface management)

    • Execution approach (concurrent or phased execution)• Greenfield and Brownfield units/projects

     – Construction Costs

    • Productivity (scope, construction management, contract and

    material management, logistic, weather, site congested, shutdownenvironment, geographical, local regulations)

    • Incentives (safety, schedule)

     – Cash Flow Constraints (reworking the execution plan, resourcingrequirements, schedule logic, priorities, completion date)

    7

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    9/21

    Mega project Execution (cont.)

    Program Execution - Risks and Opportunities (cont.)

     – Procurement

    • Start ahead of sanction for long lead items

    • Cancellation terms

    • Bulk quantities (buy down /discounts)

     – Contracting Strategy (LNTP, LS, LSTK, reimbursable, unit

    price, OBE convertible to LS)• Level of project definition

    • Schedule constraints

    • Market conditions

    • Resources – Division of Responsibility

    • Break down the scope between engineering, construction, suppliers,licensor and owner’s team

    • In alignment with estimate and schedule basis8

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    10/21

    Mega project Execution (cont.)

    Gatekeeping is a process, not a single person. It encompassesvarious steps. Key steps include:

     – Assurance  —checking that project deliverables are accurate andof high quality

     – Endorsement  —a recommendation that the project meets thebusiness need and is ready for execution

     – Financial sign-off  —agreement that the project is aligned with thecompany’s financial goals and can be authorized for execution

    Financial entities requirements ECAs (Export Credit Agencies)

    IPA – Independent Project Analysis – VIP (Value Improving practices)

    PDRI – Project development rate index

    Surveillance Analysis

    9

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    11/21

    Fluor’s Tools and Processes

    Project Phase

    FEL-1 FEL-2 FEL-3

    MarketAssessment

    and

    BusinessCase

    BusinessPlanning

    FacilityPlanning

    ProjectPlanning

    Engineering,Procurement

    and

    Construction

    Turn-overand Start-up

    Operations &Maintenance

    • Define project objectives

    • Identify and defineprocess options

    • Test options forconsistency with projectobjectives

    • Select project processscheme

    • Define scope for market,product, capacity, sitelocation

    • Class 5 estimate(Capacity factored)

    To provide "what hasto be done" 

    Gate AReview

    To provide correctand completeBaseline Data

    To provide correct andcomplete

    Basis for ProjectExecution

    • Further developselected processoption

    • ConceptualEngineering, Definebasis of design (BOD)

    • Preparedocumentation forauthority approval (e.g.

    EIA)

    • Licensor selection

    • Class 4 estimate(Equipment factored)

    • Finalize scope of theproject

    • PreliminaryEngineering, DefineBasic Design Package

    • Class 3 estimate(during FEL 3) (Semidetailed)

    • Class 2 estimate and(at the End of FEL 3)(Forced Detailed)

    • Identify resourcesrequired

    • Tendering of long leaditems

    • Set up of executionplan

    • Detailed Design andEngineering

    • Material & EquipmentPOs

    • VendorDocumentation

    • Installation DesignDrawings (IFC)

    • Final ConstructionSchedule

    • I,O&M Manuals

    • Turn-over, Testingand Start-UpProcedures

    To provide correct andcomplete Design for

    Construction

    Objectives andDeliverables

    Gate BReview

    Gate CReview

    Gates D,EReview

    10

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    12/21

    Fluor’s Tools and Processes

    Agreed Baseline

    Project Manager

    Lead

    Engineering / Design

    Baseline:Project Level

    Baseline:Discipline Level

    Baseline:Activity Level

    Analysis andReport

    Status andExceptions

    Analysis andReport

    Status andExceptions

    Analysis andReportStatus andExceptions

    Progress Report and ReviewFluor (PSR) - Client

    Facilitationby ProjectControls

    • Contract• Scope• Schedule

    • Cost• Risk• Execution Plan

    • Changes• Updates• Preventative Actions

    11

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    13/21

    Fluor’s Tools and Processes

    Baseline:Project Level

    Baseline:Activity Level

    Progress Report and ReviewFluor (PSR) - Client

    Facilitationby ProjectControls

    12

    6 Basic Elements

     – Scope of Work (Facilities and Services)

     – Cost Estimate – Schedule

     – Execution Plan and Change Management

     – Risk Management

     – Prime Contract

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    14/21

    Fluor’s Tools and Processes

    13

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    15/21

    Fluor’s Tools and Processes

    CONCEPTUAL ENGINEERING

    ProjectControls

    Baseline CentricExecution

    RiskManagement Document

    ControlMaterials Control

    SiteManagement

    ContractManagement

    ProjectManagement

    ENGINEERING

    PROCUREMENT

    CONSTRUCTION

    START UP

    14

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    16/21

    Fluor’s Tools and Processes

    OperationalSupport

    Maintenance

    Training

    Start-up

    Construction

    Procurement

    Design/ Engineering

    Basic / Design

    Feasibility

    ConceptDevelopment

    15

    Phase 5Operate &

    Evaluate

    Phase 4Execute

    EPC

    Phase 3Define Project(FEL 2 and 3)

    Phase 2

    Generate andSelect Alternatives

    (FEL 1)

    Phase 1Identify & Assess

    Opportunity

    BusinessPlanning

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    17/21

    16

    Fluor’s Tools and Processes

    PMC/Owner

    Project 1

    Project 2 

    Project 3 

    Project 4 

    Program Management in MegaProjects must extend across severalEPCs in addition to integrating allsuch EPC into a single Project 

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    18/21

    Mega project Opportunities

    Uplift employees in developing markets

    Develop skilled local workforces Support community outreach programs

    Build and sustain ‘world class’ HSE practices

    Establish strong business relationships

    Leave a positive impression on the societies in which we work Improve Owner competitive advantage

    Leave a legacy

    17

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    19/21

    Success or Failure?

    There are underlying causes of over budgeted, delayed, andunsafe megaprojects.

    We need to ensure a safe and profitable future formegaprojects 

    There are project best concepts, strategies and practices

    that, when delivered in a disciplined manner deliverpredictably good results 

    “Good” results:  – World class safety results

     – Completion in accordance with the contract schedule

     – Costs in accordance with the budget – Flawless Project startup

     – High project quality reflected in plant operation

    18

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    20/21

    Energy & Chemicals in Latin America

    19

  • 8/18/2019 FLUOR Presentation on Managing Mega Projects

    21/21

    20

    Thanks