focus on the process: bim project execution planning · focus on the process: bim project execution...
TRANSCRIPT
![Page 1: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/1.jpg)
FOCUS ON THE PROCESS:
BIM PROJECT EXECUTION PLANNING
JOHN MESSNERCHARLES & ELINOR MATTS PROFESSOR
![Page 2: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/2.jpg)
BIMExperienced-based Design
Visualization
Collaboration
High Performance BuildingsSustainability
Modularization Process Design
Integrated Delivery
Information Standards
Virtual Reality
Automation
Simulation
Team Selection
Decision Making
Virtual Mock-ups
Lean Construction
Cloud Computing
Innovation
Integrated Systems
Serious Games
Design PedagogyInternet of Things
Geographic Information Systems
![Page 3: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/3.jpg)
BUILDING INFORMATION MODELING
(BIM)
… a product or intelligent digital representation of data about a
capital facility.…
… a collaborative process which covers business drivers, automated
process capabilities, and open information standards.…
… a facilities lifecycle management tool….
Source: National BIM Standard - US, Ver. 1
![Page 4: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/4.jpg)
COPYRIGHT 2017COPYRIGHT 2017
BIM Project Execution Planning
4
![Page 5: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/5.jpg)
COPYRIGHT 2017COPYRIGHT 2017
BIM Goals and Uses
Process
Information Exchanges
Infrastructure
5
![Page 6: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/6.jpg)
COPYRIGHT 2017COPYRIGHT 2017
6
BIM Goals and Uses
Process
Information Exchanges
Infrastructure
“Begin with the end in mind.”
Identify BIM Goals and Uses
![Page 7: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/7.jpg)
COPYRIGHT 2017COPYRIGHT 2017
7
Primary and Secondary Purposes for BIM
![Page 8: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/8.jpg)
COPYRIGHT 2017COPYRIGHT 2017
BIM Goals and Uses
Process
Information Exchanges
Infrastructure
Design the BIM Process
8
![Page 9: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/9.jpg)
COPYRIGHT 2017COPYRIGHT 2017
BIM Goals and Uses
Process
Information Exchanges
Infrastructure
Define Information Exchanges
9
![Page 10: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/10.jpg)
COPYRIGHT 2017COPYRIGHT 2017
BIM Goals and Uses
Process
Information Exchanges
Infrastructure
Develop Supporting Infrastructure
10
![Page 11: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/11.jpg)
COPYRIGHT 2017COPYRIGHT 2017
11
Begin with the End in Mind.
![Page 12: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/12.jpg)
COPYRIGHT 2017COPYRIGHT 2017
12
![Page 13: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/13.jpg)
COPYRIGHT 2017COPYRIGHT 2017
13
Contents
Process for Implementation• Defining BIM Requirements
• Team Roles & Responsibilities
• BIM Planning
• Managing Requirements & Deliverables
Infrastructure & Standards
BIM Execution• BIM Planning requirement
• Identifying Essential BIM Uses
• Existing Condition Modeling
• Design Authoring
• Design Review
• Coordination
• Record Modeling
![Page 14: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/14.jpg)
COPYRIGHT 2017COPYRIGHT 2017
14
What is Important?
Simple
Standard
Practices
Advanced
Research
Initiatives
Pilot
Implementation
Projects
Education
and
Training
![Page 15: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/15.jpg)
COPYRIGHT 2017
Implement easy to adopt standard approaches for high value BIM uses,
with well trained experts,
while continuing to research, develop and test new approaches in the lab and on pilot projects.
COPYRIGHT 2017
Focus on the Goal
15
![Page 16: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/16.jpg)
Danke!
John Messner
Charles & Elinor Matts Professor
BIM.PSU.EDUWWW.NIBS.ORG/?N
BGO
![Page 17: Focus on the Process: BIM Project Execution Planning · FOCUS ON THE PROCESS: BIM PROJECT EXECUTION PLANNING ... CHARLES & ELINOR MATTS PROFESSOR. BIM Experienced-based Design Visualization](https://reader036.vdocuments.net/reader036/viewer/2022062311/5f0238fc7e708231d4032f22/html5/thumbnails/17.jpg)
FOCUS ON THE PROCESS:
BIM PROJECT EXECUTION PLANNING
JOHN MESSNERCHARLES & ELINOR MATTS PROFESSOR