FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE MEETING
KENYA WILLIAMS
CAPITAL PROJECTS
![Page 2: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/2.jpg)
2
PLEASE HOLD ALL QUESTIONS
until the end of the presentation
that is when the Q&A session will begin
(Answers may be in the presentation)
![Page 3: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/3.jpg)
3
SERVICE LINES
![Page 4: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/4.jpg)
MARTHA CASTEX-TATUM
VICE MAYOR PRO-TEM
DISTRICT K
![Page 5: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/5.jpg)
JUAN CHAVIRA, PE
ASSISTANT DIRECTOR
CAPITAL PROJECTS
![Page 6: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/6.jpg)
6
THE PROJECT TEAM
MOHAMMAD SABZEVARI CITY OF HOUSTONSTEPHEN CAMPAGNA CITY OF HOUSTONMOHAMMAD WARRAD CITY OF HOUSTONIAN HLAVACEK CITY OF HOUSTON
ARAVIND NIMMA GUNDA CORPORATION LLCRAGHU VETURI GUNDA CORPORATION LLC
MARCEL STRACHAN CP&Y INC
![Page 7: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/7.jpg)
7
LET’S TALK ABOUT
what is this project
design updates
mobility features
next steps
![Page 8: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/8.jpg)
8
TYPE PAVING & DRAINAGE
STATUS DESIGN PHASE
BUDGET $32 MILLION
FONDREN ROAD
CONTACT STEPHEN CAMPAGNA
CITY OF HOUSTON PROJECT MANAGER832.395.2225
INSERT AERIAL MAP
![Page 9: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/9.jpg)
15,800LINEAR FT. OF STORM SEWER
PROJECT BY THE NUMBERS
24,000LINEAR FT. OF NEW SIDEWALK
2.2MILES OF NEW PAVEMENT
Figures are estimates and are subject to change
LINEAR FT. OF SANITARY SEWER
2,200
7
LINEAR FT. OF WATER LINES
14,600
TRAFFIC SIGNALS
![Page 10: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/10.jpg)
10
IMPROVEMENTS TO YOUR NEIGHBORHOOD
➢ Storm drainage system improvements for flooding relief
➢ New street paving
➢ New ADA compliance sidewalks
➢ New street lighting for vehicle and pedestrian safety
➢ New signal improvements with ADA compliance features
![Page 11: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/11.jpg)
MOHAMMAD SABZEVARI, PE
MANAGING ENGINEER
CAPITAL PROJECTS
![Page 12: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/12.jpg)
12
STORM DRAINAGE SYSTEM IMPROVEMENTS
➢ Improve capacity and Level of Service
➢ Increase drainage flow
➢ Better manhole placement and inlet improvements
➢ Enhanced safety for travel lanes during stormwater event
➢ In-line detention w/no adverse impact to Braes Bayou
![Page 13: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/13.jpg)
13
![Page 14: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/14.jpg)
14
![Page 15: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/15.jpg)
15
![Page 16: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/16.jpg)
16
![Page 17: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/17.jpg)
17
NEW DRAINAGE BOXES
![Page 18: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/18.jpg)
18
EXISTING ROADWAY CONDITIONS
![Page 19: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/19.jpg)
19
NEW INLET DESIGN
![Page 20: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/20.jpg)
20
NEW ROADWAY CROSS SECTION – TYPICAL
• 12-ft wide shared
bus lanes
• New 6-ft sidewalks
• Increased
pedestrian safety
![Page 21: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/21.jpg)
Fondren Road Schematics
21
![Page 22: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/22.jpg)
Fondren Road Schematics
22
![Page 23: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/23.jpg)
23
7 NEW SIGNAL ENHANCEMENTSINTERSECTIONS:
W. AIRPORT BLVD.
LUDINGTON DR.
W. BELLFORT AVE.
PORTAL DR.
CREEKBEND DR.
WILLOBEND DR.
S. BRAESWOOD BLVD.
![Page 24: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/24.jpg)
24
![Page 25: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/25.jpg)
25
![Page 26: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/26.jpg)
26
![Page 27: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/27.jpg)
IAN HLAVACEK, PE
MANAGING ENGINEER
TRANSPORTATION & DRAINAGE OPERATIONS
![Page 28: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/28.jpg)
28
EXISTING CRASH HEAT MAP
![Page 29: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/29.jpg)
29
SAFETY FEATURE: ACCESS MANAGEMENT
• Driveways and median openings create conflict points (x’s on the figure)
• Minimizing conflict points improves safety for people walking, bicycling, and driving
![Page 30: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/30.jpg)
30
ALTERNATIVES
We are currently looking at opportunities for left-turn designs.
![Page 31: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/31.jpg)
31
ECONOMIC IMPACTS – ACCESS MANAGEMENT
Federal Highway Administration:
“Installing raised medians often raises seriousconcerns by the business community that localbusinesses that depend upon pass-by traffic. . .willbe adversely affected by medians. Though thereare few studies of the actual impacts of medianson business sales, there are several surveys ofbusiness owner opinions. Surveys conducted inmultiple corridors in Texas, Iowa, and Floridademonstrate that the vast majority of businessowners believe there have been no declinesin sales, with some believing there are actuallyimprovements in business sales. . .One study inTexas indicated that corridors with access controlimprovements experienced an 18 percent increasein property values after construction.”
Source: https://safety.fhwa.dot.gov/geometric/pubs/accessmgmtbrochure/median.htm
![Page 32: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/32.jpg)
32
SAFETY FEATURE: LEFT-TURN LANES
• Left-turn lanes improve
traffic flow by removing
turning vehicles from through
lanes
• Left-turn lanes improve
safety by decreasing rear-
end collisions
• IDM requires left-turn
lanes at all median openings
However. . .
• New left-turn lanes do
impact trees and
landscaping
![Page 33: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/33.jpg)
33
MEDIAN OPENING REQUIRE LEFT-TURN LANES
![Page 34: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/34.jpg)
34
• Houston Public Works
is a leading Vision
Zero partner
• Houston Public Works
will be systematically
reviewing all projects
to find opportunities to
align with Vision Zero
• Some projects
(including Fondren)
have federal funding,
and any design
changes will need
approval of funding
partners
•Commitment to end
traffic deaths and
serious injuries by 2030.
•Traffic deaths and serious
injuries are an
unacceptable
and preventable public
health issue.
•Prioritizes street safety
and accessibility for all
modes and for people of
all ages and abilities.
![Page 35: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/35.jpg)
35
NEXT STEPS
Design Phase
2020
Construction Phase
2021
Construction Complete
2023
Timeline subject to change
![Page 36: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/36.jpg)
36
publicworks.houstontx.gov/engage
![Page 37: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/37.jpg)
37
WHO TO CONTACT
Send concerns or comments to
Questions? call 3.1.1 (713.837.0311)
visit houstontx.gov/311 (provide project #)
![Page 38: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/38.jpg)
38
THANK YOU!
![Page 39: FONDREN ROAD PAVING AND DRAINAGE DESIGN UPDATE …](https://reader030.vdocuments.net/reader030/viewer/2022012217/61dfc0b8fae5e025e01d5aea/html5/thumbnails/39.jpg)
39
QUESTIONS & ANSWERS
✓ Select Q&A on the right side of the screen.
✓ Type your question in the compose box and
then select Send. If you want to ask your
question anonymously, select Ask
anonymously.