foothill college site improvementsfhdafiles.fhda.edu/downloads/aboutfhda/fhsite... · 7.05.2012...
TRANSCRIPT
![Page 1: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/1.jpg)
Foothill College Site ImprovementsFoothill – De Anza Community College District
Board of Trustees Presentation
May 7, 2012
1 of 17
![Page 2: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/2.jpg)
- Campus Outreach Efforts
- Project Timeline & Construction Phasing
- #162 Parking & Circulation- Phase 1 Summer 2012- Phase 2 Summer 2013
- #144 Central Campus Site Improvements
- Summer & Fall 2012
- Mitigation of Construction Impactswith emphasis maintaining enrollment
2 of 17
PRESENTATION OVERVIEW
![Page 3: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/3.jpg)
PROJECT TEAM & OUTREACH EFFORTS
Steering CommitteeFrank Nunez (FHDA)
Art Heinrich (FHDA)
Shirley Treanor (Foothill)
Brenda Visas (Foothill)
Annette Stenger (Foothill)
Chief Ron Levine (Police)
Todd Leicht (Gilbane / Maas)
Campus OutreachSustainability Committee
Building & Grounds
Academic Senate
Administration Council
Classified Senate
Planning & Resource Committee (PaRC)
President’s Cabinet
Associated Student Body (soon)
Central Services (soon)
Project Design TeamWRNS Studio (Wright Sherman)
Meyer Silberberg Land Architects
SANDIS, Civil Engineers
Fehr & Peers, Traffic Engineers
Silverman & Light
Crosby Group , Structural Engineers
Technical OutreachTraffic Studies
VTA
District Police
3 of 17
![Page 4: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/4.jpg)
GUIDING PRINCIPLES• Maintain student enrollment • Limit impact on educational offerings• Student safety• Maintain accessibility and circulation• Convenience• Sustainability• Apply engineering best practices
GOALS• Safety Improvements: Vehicle, pedestrian, bicycle • Enhance and improve accessibility• Limit impact on parking • Aesthetics – maintain beauty of campus• Lighting improvements and signage• Reduce traffic congestion & improve efficiency• Protect, renew, and enhance the integrity of the
campus• Improve storm-water management
CONSTRUCTION PROCESS
4 of 17
![Page 5: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/5.jpg)
SUMMER 2012:
• Extensive Construction Throughout Central and Outer Campus
• PSEC Bus Stop Closed
FALL 2012:
• Irrigation and Planting will continue
• Northern Threshold and Stairs under Construction
• New Pathways will be Accessible, Safe, Barrier Free
• Improved Pathway Lighting
• Fountains Restored
EXPECTATIONS FOR SUMMER & FALL 2012
5 of 17
![Page 6: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/6.jpg)
De Anza Combined Site Improvements Phase IFoothill Utilities Infrastructure Project Phase I
• Minimize impact on enrollments
• Minimize impact on parking
• Clearly defined paths for travel (signage)
• Utilize proven Campus Notification Protocols- Steering Committee- Foothill Fusion Newsletter- Measure C Construction Web Page
- Collaborative Scheduling with Contractor and College
6 of 17
LESSONS LEARNED & BEST PRACTICES
![Page 7: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/7.jpg)
• Coordinate Construction with Academic Calendar
• Maintain Accessible Routes
• Emergency Vehicle Access
• Comprehensive Signage Plan
MITIGATION OF CONSTRUCTION IMPACTS
7 of 17
![Page 8: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/8.jpg)
Parking & Circulation Projects 8 of 17
Project #162 – Parking & Circulation
IMPROVEMENTS:• New lighting• Accessibility routes• Bus Stop & Crossings• Landscaping• Storm water Management
Phase 12012
Lot 4b
![Page 9: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/9.jpg)
Parking & Circulation Projects 9 of 17
IMPROVEMENTS:• New lighting• Accessibility routes• Bus Stop & Crossings• Landscaping• Stormwater Management
Phase 2Summer 2013
Phase 1Summer 2012
Project #162 – Parking & Circulation
Lot 4b
![Page 10: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/10.jpg)
Parking Lot 2/3 Plan
IMPROVEMENTS:• Widen PE Access Road• Upgrade stairs to meet Code • Lighting upgrades• Landscape buffer• Pedestrian & Vehicle Circulation• Stormwater Management
10 of 17
Project #162 – Parking & Circulation
![Page 11: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/11.jpg)
Parking Lot 2/3 Plan
IMPROVEMENTS:• Widen PE Access Road• Upgrade stairs to meet Code • Lighting upgrades• Landscape buffer• Pedestrian & Vehicle Circulation• Stormwater Management
11 of 17
Enhanced pedestrian crossing safety measures
Emergency Access Only
PE Access Road closed for summer
Pathway closed for summer
Project #162 – Parking & Circulation
Access to PE
![Page 12: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/12.jpg)
PSEC Threshold Plan
IMPROVEMENTS:• Enhanced pedestrian plaza• Larger, safer bus stop• Safe waiting area @ bus stop• Improved sight lines for safety• New Traffic signal
5700
5800
4300
PSEC
12 of 17
5600
Bus stop closed for summer
Project #162 – Parking & Circulation
![Page 13: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/13.jpg)
Project #144 – Central Campus Site Improvements
13 of 17Central Campus Master Plan
IMPROVEMENTS:• Renovate Courtyards• Improve Pathways• Pathway Lighting upgrades• Accessibility• Landscape Renewal• Tree Replacement
![Page 14: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/14.jpg)
Project #144 – Central Campus Construction Timeline
14 of 17
PROJECT #144 CENTRAL CAMPUSCONSTRUCTION TIMELINE 2012Area 1 JULY – SEPTArea 2 AUG – SEPTArea 3 JULY – SEPTArea 4 OCT – DEC
![Page 15: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/15.jpg)
Project #144 – Central Campus Construction Mitigation & Accessibility
15 of 17
2012 CONSTRUCTION
Area 1 JULY – SEPTArea 2 AUG – SEPTArea 3 JULY – SEPTArea 4 OCT – DEC
![Page 16: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/16.jpg)
Project #144 - Central Campus Tree Replacement
16 of 17
![Page 17: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/17.jpg)
Project #144 - Central Campus Tree Replacement
16 of 17
Chinese Elm White Ash “Autumn Purple”Ginko biloba “Princeton Sentry”London Plane “Columbia” (existing)
![Page 18: Foothill College Site Improvementsfhdafiles.fhda.edu/downloads/aboutfhda/FHSite... · 7.05.2012 · -Campus Outreach Efforts -Project Timeline & Construction Phasing-#162 Parking](https://reader033.vdocuments.net/reader033/viewer/2022052000/6012e5069a5ad2168863b491/html5/thumbnails/18.jpg)
Foothill College Site ImprovementsFoothill – De Anza Community College District
Board of Trustees Presentation
May 7, 2012
17 of 17