for174 _ines b electricity storage for renewables ninth meeting of the council – thematic events 1...

11
FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES COMMISSION

Upload: barry-goodman

Post on 24-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

FOR174 _INES B

ELECTRICITY STORAGE FOR

RENEWABLES

NINTH MEETING OF THE COUNCIL –

THEMATIC EVENTS

1

FRANCK AL SHAKARCHI

ATOMIC ENERGY AND ALTERNATIVE ENERGIES COMMISSION

Page 2: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

| PAGE 2

ISLAND CASE: MARTINIQUEFUEL BASED ELECTRICITY MIX

Production 2012:471 MW installed capacity60 MWp PV1591 GWh produced electricity

Consumption 2012:254 MW peak load~1422 GWh Capacity (MW) Production (GWh)

0

200

400

600

800

1000

1200

1400

1600

1800

Wind powerPVWaste incinerationLFOHFO

2015

2017

2019

2021

2023

2023

0

50

100

150

200

250

300

Comparaison of PV power generation cost according to ins-talled year with average production cost (with 2012 Marti-

nique mix structure)

Average production cost with 50€/bbl

Average production cost with 100€/bbl

Average production cost with 150€/bbl

6 kWp PV system production cost in La Martinique

1 MWp PV system power generation cost in La Mar-tinique

€/M

Wh

High power generation costsin La Martinique:

From 160 to 280 €/MWhDepending on oil pricesRequiring subsidiesLittle local jobs~700 gCO2/kWh

Page 3: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

ISLAND CASE: MARTINIQUEBENEFITS AND LIMITS OF VARIABLE RE INTEGRATION

Source: EDF SEI

Benefits from increasing share of PV generationStable pricesLocal jobsLittle global CO2 emissions (no local emissions) and little local pollution

Limits to a higher integration of PV: 30% limitFrench law (23 april 2008): TSO can disconnect variable RE generation in case of instantaneous power exceeding 30% of total loadCurrently around 24% (some French islands > 35%)

Page 4: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

WHAT ARE THE ISSUES RELATED TO THE INTEGRATION OF VARIABLE RENEWABLES ?

Grid needs

Planning and scheduling

Power balancing and regulation

Power production 24h a day

Variable RE

Cannot be guaranteed and fluctuates

Is limited by instantaneous ressource availability

Depends on daytime and wheather conditions

Requirements for integration of RE

Production forecasting

Capacity firming and production smoothing

Energy time-shifting

Additional supply capacity for regulation

00:00 06:00 12:00 18:00 00:000

500

1000

1500

2000

2500

3000

3500

4000

4500

Pu

issa

nce

AC

(kW

)

Time

MedianDaily prod

06/03/13 06/04 06/050

20

40

60

Pow

er (k

W)

D-1 planPV with down-regPV max availablePV+StorageD-1 plan tolerance

06/03/13 06/04 06/050

0.05

Elec

trici

ty p

rice

(€/k

Wh)

06/03/13 06/04 06/05-50

0

50

Pow

er k

W

Storage delivered powerStorage SolicitationPower limits

06/03/13 06/04 06/050

50

100

SOE

%

Realizedtarget run: 03-Jun-2013

Little issues for integration up to around 30-40% of instantaneous RE power in a gridÞ Total grid including interconnections

Voltage regulationIs currently required to produce max and min reactive

Controls of active/reactive power according to voltage

Page 5: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

ISLANDS AND REMOTE AREASSOME EXAMPLES OF RE-STORAGE PROJECTS

| PAGE 5

% of intermittent RE in total grid

160%40-80%

100W

100MW

Unitary size of system

0%0%

Power/peakEnergy

80%20-40%

40%10-20%

120%30-60%

El Hierro 100% RES 11MW Wind - 6MW

pumped-hydro storage

French overseas MILLENER

1000 domestic PV-storage systems

100kW

10kW

MW

10MWFrench overseasPV-storage RFP

Trapezoidal control, forecast and ancillary services

Puerto RicoPV-storage-dieselRamp rate controlAncillary services

French overseasWind-storage FIT

½h constant power, forecast and ancillary services

Kiribati2000 off-grid solar

homes and community buildings

kW

Australia Weipa mine6,7 MW solar and

batteries27 MW remote grid

Australia King islandSmart renewable grid

Wind, batteries, flywheel, resistor frequency control

Remote areas

Islands

Page 6: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

HOW TO ASSESS THE NEED FOR STORAGE OF VARIABLE RENEWABLE ELECTRICITY ?

Grid needs Variable RERequirements for integration of RE

00:00 06:00 12:00 18:00 00:000

500

1000

1500

2000

2500

3000

3500

4000

4500

Pu

issa

nce

AC

(kW

)

Time

MedianDaily prod

06/03/13 06/04 06/050

20

40

60

Pow

er (k

W)

D-1 planPV with down-regPV max availablePV+StorageD-1 plan tolerance

06/03/13 06/04 06/050

0.05

Elec

trici

ty p

rice

(€/k

Wh)

06/03/13 06/04 06/05-50

0

50Po

wer

kW

Storage delivered powerStorage SolicitationPower limits

06/03/13 06/04 06/050

50

100

SOE

%

Realizedtarget run: 03-Jun-2013

What amount of variable renewable electricity ?Instantaneous RE power > 30% instantaneous load ? Total RE energy > 10% total consumption ?

How stable is my grid ?Little other flexibility option ? No interconnection with a large stable grid ? Island or remote area ?

What are the total integrated costs of other options ?flexibility and power generation

Page 7: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

KEEP IN MIND ALL THE SERVICES CAN STORAGE PROVIDE !!! NOT ONLY FOR VARIABLE RE

| PAGE 7(based on (EPRI & DOE, DOE/EPRI 2013 Electricity Storage Handbook in Collaboration with NRECA, 2013))

Page 8: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

STORAGE ADDED-VALUE INCREASES BY COMBINING SERVICES

| PAGE 8

Page 9: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

AND STORAGE CAN FITS INTO MULTIPLE PLACES OF THE GRID !!!

| PAGE 9

EV charging station

Distribution grid

With some CEA demonstrators

Community storage

Residential

CEA R&D grid operation

Commercial building

GeneratorTransmission grid

Page 10: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

A STORAGE SYSTEM IS COMPOSED OF MORE THAN A STORAGE DEVICE: TECHNOLOGY ISSUES

| PAGE 10

Storage performances and ageing

Storage ManagementSystem

Selection of storage technologyAnd optimal sizing

Electrical architecture

Smart Energy Management Systems with optimal control algorithms – application specific

EMS

Page 11: FOR174 _INES B ELECTRICITY STORAGE FOR RENEWABLES NINTH MEETING OF THE COUNCIL – THEMATIC EVENTS 1 FRANCK AL SHAKARCHI ATOMIC ENERGY AND ALTERNATIVE ENERGIES

CEA: ATOMIC ENERGY & ALTERNATIVE ENERGIES COMMISSIONCONTACT DETAILS

| PAGE 11

16 000 employees in 10 research centers4 B€ annual budget580 priority patents filed / year120 new high tech companies created

Defence Applications

Division

NuclearEnergyDivision Research &

Technology DivisionMaterial

Science Division

Life ScienceDivision

Smart Electrical Systems LaboratoryScope:• Electricity Storage Systems• Electric vehicles• Integration of solar generation• Demand-side management• Smart grids & micro-gridsServices:• Modelling and simulations• Smart management and SCADA• Demonstrators and experimental grids

4 500 employees550 M€ budget500 priority patents / year50 spin-off companies

NEW ENERGYTECHNOLOGIES1 400 employees

1 052 patent portfolio170 M€ budget 2013

NanomaterialsThermal, Biomass & H2

Electric vehiclesSolar energy

Contact details

Franck AL SHAKARCHI

[email protected]

+33 4 79 79 21 43