force majeure - presentation
TRANSCRIPT
-
8/12/2019 Force Majeure - Presentation
1/15
FORCE MAJEUREHiding Behind
Non PerformanceJonathan Moss
Partner
DWF Fishburns
-
8/12/2019 Force Majeure - Presentation
2/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
SUMMARY OF TOPICS TO BE COVERED
What is Force Majeure?
Force Majeure versus Frustration
A review of recent catastrophes and their impact on performance
of contracts (effect, operation, reality)
Drafting tips, sample clauses
What to include in a Force Majeure notice
What to include in a response to a Force Majeure notice
-
8/12/2019 Force Majeure - Presentation
3/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
INTRODUCTION TO FORCE
MAJEURE
Force Majeure - The means by which contracting parties can avoid being tiedinto the obligations created by a contract
Force Majeure is an event which
(i) is beyond the control of the parties and
(ii) prevents, impedes, or delays the performance of a contract
The event must be unforeseeable, unpreventable (by the parties) and external
Operates to suspend or terminate the contract on terms agreed between theparties
A carefully drafted force majeure clause will always be clearer, more certainand more satisfactory than relying on general principles of law
-
8/12/2019 Force Majeure - Presentation
4/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
FORCE MAJEURE V FRUSTRATION
Force Majeure Advantages Frustration - Disadvantages
Certainty English Courts reluctant to find that aninternational trade contract has beenfrustrated
Does not always need to bring a contract toan end
Requirement for impossibility to perform thecontract; complete destruction of the objectof the contract
Temporary suspension or permanentsuspension subject to agreement or seekan extension of time for performance
Only applies in extremis
Negotiated terms of operation agreed by allparties
Will bring a contract to an end
Event does not have to be unforeseen ifagreed (unlike frustration)
Includes cessation of all future obligations
-
8/12/2019 Force Majeure - Presentation
5/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
DRAFTING CONSIDERATIONS
Description of the events that will trigger the operation of theclause
Terms that define the duration of the condition
Notice provision describing how a declaration of Force Majeureis to be communicated
The consequences of a Force Majeure occurrence i.e.defences/remedies available to the parties
-
8/12/2019 Force Majeure - Presentation
6/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
DEFINING FORCE MAJEURE EVENTS
Acts of God, earthquake, flood, fire, storm, epidemic
War
Revolution, rebellion, civil commotion, riot
Strike
Depletion, reduction or insufficiency of reserves
Rupture or explosion
Laws, regulations and any acts of any state
-
8/12/2019 Force Majeure - Presentation
7/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
PRACTICAL EXAMPLES COUNTRY TO
COUNTRY HIDING BEHIND NON-
PERFORMANCE
Annus Horribilis
During the course of 2011, natural disasters areestimated to have claimed the lives of over 30,000people across the globe and cost the worldwide
economy a record of $350 billion
-
8/12/2019 Force Majeure - Presentation
8/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
JAPAN
Tsunami in March 2011: 16,000 lives lost and costs inthe region of $210 billion making it the most costlynatural disaster ever recorded
Proliferation of disputes regarding Force Majeure
Consider the nature of the transaction in issue
-
8/12/2019 Force Majeure - Presentation
9/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
VIOLENCE, RIOTS AND CIVIL
COMMOTION - EGYPT
Egypt bore witness to violence, riots and civil commotionfrom January to June 2011
Contracting parties were unable to present documents
under letters of credit involving banks based in Egypt andused this as an excuse for non-performance
When the banks are still open for business there is no
difficulty
-
8/12/2019 Force Majeure - Presentation
10/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
FLOODS - THAILAND 2011/2012
Thailand suffered its worst floods in 50 years in 2011. 800 liveslost, 660,000 workers, 10,000 factories and 7 large industrialestates affected
Thailand issues:
Were the floods truly unforeseeable and unpreventable naturaldisasters or were they foreseeable (or even foreseen) andcapable of being prevented or at least mitigated in advance?
Were the floods caused or aggravated by official actions?
-
8/12/2019 Force Majeure - Presentation
11/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
CHECK LIST IN THE EVENT OF
POTENTIAL FORCE MAJEURE
Follow events as closely as possible on the ground andliaise with counter-parties
Check sales contracts for Force Majeure provisions,
notices, payments, procedural obligations
Talk to your counter-party (consider diverting vessels toalternative ports)
Notices sent to the broker or agent may be valid notice
-
8/12/2019 Force Majeure - Presentation
12/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
POINTS TO INCLUDE IN A FORCE
MAJEURE DECLARATION
The parties should specify in the notice what their rights andobligations are on the happening of a Force Majeure event.These could be:
Right to terminate without liability on either side
Suspension of performance until the Force Majeure eventceases without liability
-
8/12/2019 Force Majeure - Presentation
13/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
RESPONDING TO A SIMPLE FORCE
MAJEURE DECLARATION
The non-claiming party should respond with a requestfor reasonable details of the force majeure event(Request for Further Information):
Actual details of the FM eventIts impact on contractual performanceThe expected duration of the FM events
Efforts being undertaken by the claiming party toremedy the FM event or avoid its effects
-
8/12/2019 Force Majeure - Presentation
14/15
Private & Confidential. Not for distribution.
DWF LLP 2012 www.dwf.co.uk
CONCLUSION
Force Majeure event is unforeseeable, unpreventable (by theparties) and external
The ability to declare a Force Majeure Notice depends on thedefinition of the goods/products and the specific description ofthe Force Majeure events in the contract
The Force Majeure clause must define
i. The events which will trigger the operation of the clause
ii. The impact those events will have on the party whoinvokes the clause
iii. And the effect invocation will have on the contractualobligations
-
8/12/2019 Force Majeure - Presentation
15/15
FORCE MAJEUREHiding Behind
Non PerformanceJonathan Moss
Partner
DWF Fishburns