FORM 1 APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE For Expansion of Coal Mine from 0.30 MTPA to 0.333 MTPA (Normative Capacity) / 0.42 MTPA (Peak Capacity) Marki Mangli - I Coal Mine Area -731.42 Ha. Topworth Urja & Metals Limited Office No. 126-128, 1 st Floor Shriram Tower, Kingsway Near NIT Office, Sadar Nagpur - 440 001. Prepared By ENVIRO TECHNO CONSULT PRIVATE LIMITED 68, MAHAKALI NAGAR 2, NEAR MANEWADA SQUARE NAGPUR - 440 024 Accredited by NABET/QCI and Listed at Sr. No. 50 February,2019 February - 2019

Upload: others

Post on 15-Feb-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

  • FORM 1

    APPLICATION FOR

    PRIOR ENVIRONMENTAL CLEARANCE

    For

    Expansion of Coal Mine from 0.30 MTPA to 0.333 MTPA (Normative Capacity) /

    0.42 MTPA (Peak Capacity)

    Marki Mangli - I Coal Mine Area -731.42 Ha.

    Topworth Urja & Metals Limited

    Office No. 126-128, 1st Floor

    Shriram Tower, Kingsway

    Near NIT Office, Sadar

    Nagpur - 440 001.

    Prepared By

    ENVIRO TECHNO CONSULT PRIVATE LIMITED 68, MAHAKALI NAGAR 2,

    NEAR MANEWADA SQUARE

    NAGPUR - 440 024

    Accredited by NABET/QCI and Listed at Sr. No. 50 February,2019

    February - 2019

  • Page | 1

    APPENDIX - I

    (See Paragraph – 6) FORM - 1

    Sl.

    No. Item Details

    I. Basic Information

    1 Name of the Project

    Expansion of Marki Mangli-I Coal Mine

    from 0.30 MTPA to 0.333 MTPA

    (Normative)/0.42 MTPA (Peak Capacity)

    without change in Lease hold area, Mining

    Method

    2 S. No. in the schedule 1 (a)

    3

    Proposed capacity/area/ length /tonnage

    To handled /command area/lease

    area/number of wells to be drilled

    Area-731.42 Ha.

    Proposed Mining -@ 0.333 MTPA

    (Normative) / 0.42 (Peak) Capacity

    4 New/expansion/modernization

    Expansion from 0.30 MTPA to 0.333 MTPA

    (Normative) / 0.42 MTPA (Peak Capacity)

    without change in Leasehold area and

    Mining Method

    5 Existing Capacity, area, etc 0.30 MTPA / 0.42 (Peak) Capacity

    Area- 731.42 Ha.

    6 Category of the Project i.e. A or B A

    7 Does it attract the general condition? if

    yes, please specify Yes, as per MOEF&CC Circular

    8 Does it attract the specific condition? if

    yes, please specify Yes, as per MOEF&CC Circular

    9

    Location Marki Mangli - I Coal Mine

    Plot/survey/Khasra No. As per Annexure -1

    Village Pardi, Pandharkawda (Lahan), Marki (Bu),

    Marki (Kh) & Ganeshpur (Kh)

    Tehsil Jhari Jamni

    District Yavatmal

    State Maharashtra

    10 Nearest railway station/ airport along with

    distance in kms.

    Railway Station: Kayar - 24 km. to SE

    Airport-: Nagpur, 190 km. to N

    11 Nearest town, city, district headquarters

    along with distance in kms.

    Town – Mukutban 5.4 KM SE City - Wani

  • Page | 2

    Sl.

    No. Item Details

    12

    Village Panchayats, Zilla Parishad,

    Municipal Corporation, Local body

    (Complete postal address with telephone

    numbers to be given)

    Panchayat - Pandharkawda(Lahan), Marki

    (Bu),

    Panchayat Samiti, Jhari Jamni

    Tahsil - Jhari Jamni,

    Zilla Parishad, Yavatmal

    13 Name of the applicant Topworth Urja & Metals Ltd.

    14 Registered Office Address

    Topworh Urja & Metals Ltd,

    308, 3rd Floor, Ceejay House,

    Dr. Annie Bascent Road, Worli,

    Mumbai – 400 018.

    15 Address for Correspondence

    Topworth Urja & Metals Ltd.

    Office No. 126-128, 1st Floor,

    Shriram Tower, Kingsway, Near NIT Office,

    Sadar, Nagpur - 440 001

    Name Shri. H. S. Khare

    Designation (Owner/ Partner/ CEO) Authorized Signatory / Chief Mining

    Address

    Office No. 126-128, 1st Floor, Shriram

    Tower, Kingsway, Near NIT Office,

    Sadar, Nagpur.

    Pin Code 440 001

    E-mail

    [email protected],

    [email protected]

    Telephone Number 0712-2527120/121/122

    Fax number 0712-2527120/121/122

    16

    Details of alternative sites examined, if

    any. Location of these sites should be

    shown on a topo –sheet

    Alternative sites cannot be examined as it

    is a working coal mine based on lease

    granted for specific mineral explored by

    Govt. of India and Vested by Ministry of

    Coal.

    Location- Please see Annexure 2

    17 Interlinked Projects

    Yes, coal mined from Marki Mangli - I Coal

    Mine will be used at TUML’s End Use Plants consisting “Sponge Iron Plant & Captive Power Plant” at Mouza- Ukkarwahi Tah-Umred, District- Nagpur.

    mailto:[email protected]:[email protected]

  • Page | 3

    Sl.

    No. Item Details

    18 Whether separate application of

    interlinked project has been submitted?

    Both the interlinked units referred at Sl. No.

    17 are running since 2006 onwards with

    valid Environmental Clearances and other

    requisite permissions and licenses.

    19 If yes, date of submission N. A.

    20 If no, reason N. A.

    21

    Whether the proposal involves

    approval/clearance under : If yes,

    details of the same and their status to

    be given.

    No, E.C. has been granted for production

    @ 0.30 MTPA vide MOEF Letter No.J -

    11015/256/2006 - IA. II(M) dtd 17.05. 2007

    which has been transferred to TUML on

    09.02.2016 copy of above letters are

    enclosed as Annexure 3

    a) The Forest (Conservation) Act, 1980? N.A.

    b) The Wildlife (Protection) Act, 1972? N.A.

    c) The C.R.Z. notification, 1991? N.A.

    22 Whether there is any Gowvvernment

    order/Policy relevant/relating to the sites?

    Topworth Urja & Metals Ltd. has been

    vested Marki Mangli - I Coal Mine vide

    Vesting Order dated 30.09.2015 by

    Ministry of Coal, Government of India.

    Annexure 4

    23 Forest Land involved (Ha.) No

    24

    Whether there is any litigation pending

    against the project and/or land in which

    the project is propose to be set up?

    There is no litigation

    (a) Name of the court N.A.

    (b) Case No. N.A.

    (c) Orders/directions of the court, if any

    and its relevance with the proposed

    project.

    N.A.

    25 Expected Project Cost Rs. 10,000 Lakhs

  • Page | 4

    II. Activity

    Sr.

    No. Information/Checklist confirmation Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data

    1.

    Construction, operation or decommissioning of the Project involving

    actions, which will cause physical changes in the locality (topography, land

    use, changes in water bodies, etc.)

    1.1

    Permanent or temporary change in

    land use, land cover or topography

    including increase in intensity of land

    use (with respect to local land use

    plan)

    Yes

    Total area of OC & UG Mining is

    731.42 Ha. out of which 119.16 Ha.

    area is proposed for excavation,

    safety zone, embankment, 40 Ha. is

    for OB and Soil Dump dumps,

    33.12 Ha for Mining infrastructure

    etc. Remaining area will be

    undisturbed.

    1.2 Clearance of existing land, vegetation

    and buildings? Yes

    As above, land will be cleared from

    vegetation and used for

    excavation. Out of which 46.20 Ha

    land is already cleared for existing

    excavation, infrastructure purposes.

    1.3 Creation of new land uses? Yes Existing & Proposed Mining will

    create new land use.

    1.4 Pre-construction investigations e.g.

    bore houses, soil testing? No N.A.

    1.5 Construction works? No N.A.

    1.6 Demolition works? No N.A.

    1.7

    Temporary sites used for construction

    works or housing of construction

    workers?

    No N.A.

    1.8

    Above ground buildings, structures or

    earthworks including linear structures,

    cut and fill or excavations

    No N.A. Since mine is already in

    operation.

    1.9 Underground works including mining

    or tunneling? Yes As per approved Mining Plan

    1.10 Reclamation works? Yes As per approved Mining Plan

    1.11 Dredging? No N.A.

    1.12 Offshore structures? No N.A.

  • Page | 5

    Sr.

    No. Information/Checklist confirmation Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data

    1.13 Production and manufacturing

    processes? Yes

    It is proposed to achieve

    production @0.333 MTPA

    (Normative) / 0.42 MTPA (Peak) by

    both OC & UG mining.

    UG will commence after 9th year of

    grant of E.C.

    This proposal is as per Approved

    Mining Plan.

    1.14 Facilities for storage of goods or

    materials? No

    Existing facility will be utilized as

    per Approved Mining Plan.

    1.15 Facilities for treatment or disposal of

    solid waste or liquid effluents? No

    Out of 23.21 Mm3 of Soil & OB

    dump, 3.09 Mm3 of soil will be

    dumped at one external and three

    internal dumps whereas 20.12 Mm3

    of OB will be dumped externally at

    one site each. And externally at

    three sites each. These dumps will

    be properly stabilized and a

    garland drain of 1x1x1 m3 will be

    made. Out of proposed dumps,

    one Soil dump of 1.79 ha is created

    where as one dump of 7.80 ha &

    other of 0.84 Ha for OB are created

    of sizes 195.35m x 235.58m x

    29.70m and 262.0m x 133.93m x

    27m.

    ETP of treatment capacity 30

    m3/day is proposed to treat

    domestic and proposed workshop

    (vehicle washing) discharge.

    1.16 Facilities for long term housing of

    operational workers? No Not required

    1.17 New road, rail or sea traffic during

    construction or operation? No Not required

    1.18

    New road, rail, air waterborne or other

    transport infrastructure including new

    or altered routes and stations, ports,

    airports etc?

    No Not required

  • Page | 6

    Sr.

    No. Information/Checklist confirmation Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data

    1.19

    Closure or diversion of existing

    transport routes or infrastructure

    leading to changes in traffic

    movements?

    No Not required

    1.20 New or diverted transmission lines or

    pipelines? No Not required

    1.21

    Impoundment, damming, culverting,

    realignment or other changes to the

    hydrology of water courses or

    aquifers?

    No Not required

    1.22 Stream crossings? No Not required

    1.23 Abstraction or transfers of water form

    ground or surface waters?

    CGWA approval for 827 m3/day for

    different mining operations like

    recharge, green belt development,

    dust suppression, agricultural

    purposes from seepage during OC

    & UG operations and potable

    water requirement of 12 m3/day

    from two nos. of tube wells is

    obtained.

    1.24 Changes in water bodies or the land

    surface affecting drainage or run-off? No

    Present day operation has not

    affected drainage within lease.

    1.25

    Transport of personnel or materials for

    construction, operation or

    decommissioning?

    No

    No construction activity is involved

    being working coal mine. However,

    there is a transport system for

    transportation of Mine Workers &

    Coal Evacuation.

    1.26

    Long-term dismantling or

    decommissioning

    or restoration works?

    No

    Total of 158.62 Ha. area will be

    green belt and a decoaled void of

    15.24 ha. will be converted into

    water reservoir at the end of mine

    life.

    1.27

    Ongoing activity during

    decommissioning which could have an

    impact on the environment?

    No Not envisaged

  • Page | 7

    Sr.

    No. Information/Checklist confirmation Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data

    1.28 Influx of people to an area in either

    temporarily or permanently? No

    Influx of people has taken place

    due to direct and indirect

    employment opportunities. This

    will continue throughout the life of

    the mine.

    1.29 Introduction of alien species? No Not envisaged

    1.30 Loss of native species or genetic

    diversity? No Not envisaged

    1.31 Any other actions? No -

    2.

    Use of Natural resources for construction or operation of the Project (such

    as land, water, materials or energy, especially any resources which are non-

    renewable or in short supply)

    2.1 Land especially undeveloped or

    agricultural land (ha) No

    About 260.27 Ha. of Non Forest

    agricultural land will be required

    for mining operations. Out of

    which 46.20 Ha. land is already in

    possession of project and mining

    is under operation.

    2.2 Water (expected source & competing

    users) unit: KLD No

    CGWA approval for 827 m3/day

    for different mining operations

    like recharge, green belt

    development, dust suppression,

    agricultural purposes from

    seepage during OC & UG

    operations and potable water

    requirement of 12 m3/day from

    two nos. of tube wells is obtained.

    2.3 Minerals (MT) Nil Not required

    2.4

    Construction material – stone, aggregates, sand / soil (expected

    source – MT) Yes

    Material required for U.G. entry is

    available at site

    2.5 Forests and timber (source – MT) No Not required

    2.6

    Energy including electricity and fuels

    (source, competing users) Unit: fuel

    (MT), energy (MW)

    Yes

    Connected load is 11 KvA from

    MSEB.

    Standby D.G. Set Capacity of 500

    kVA will meet requirement.

    2.7 Any other natural resources (use

    appropriate standard units) No Not required

  • Page | 8

    Sr.

    No. Information/Checklist confirmation Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data

    3.

    Use, storage, transport, handling or production of substances or materials, which

    could be harmful to human health or the environment or raise concerns about

    actual or perceived risks to human health.

    3.1

    Use of substances or materials, which

    are hazardous (as per MSIHC rules) to

    human health or the environment

    (flora, fauna, and water supplies)

    No Not required

    3.2

    Changes in occurrence of disease or

    affect disease vectors (e.g. insect or

    water borne diseases)

    No Not applicable

    3.3 Affect the welfare of people e.g. by

    changing living conditions? No Not envisaged

    3.4

    Vulnerable groups of people who could

    be affected by the project e.g. hospital

    patients, children, the elderly etc.,

    No Not envisaged

    3.5 Any other causes - -

    4. Production of solid wastes during construction or operation or decommissioning

    (MT/month)

    4.1 Spoil, overburden or mine wastes Yes

    Out of 20.96 Mm3 of OB dump,

    13.18 Mm3 of OB will be

    accommodated in externally and

    6.78 Mm3 is to be accommodated

    internally in the void Quarry itself.

    4.2 Municipal waste (domestic and or

    commercial wastes) No No.

    4.3 Hazardous wastes (as per Hazardous

    Waste Management Rules) Nil Not envisaged

    4.4 Other industrial process wastes No Not envisaged

    4.5 Surplus product No Not envisaged

    4.6 Sewage sludge or other sludge from

    effluent treatment No

    Not Applicable, being no colony

    is proposed.

    4.7 Construction or demolition wastes No Not envisaged

    4.8 Redundant machinery or equipment No

    Old equipment & machinery will

    become redundant after the end

    of useful life and will be surveyed

    off & sold as scrap.

    4.9 Contaminated soils or other materials No

    Not applicable. Existing O.B.

    dump will be used. Top soil will

    be used for reclamation of

    backfilled area.

    4.10 Agricultural wastes No Not applicable

    4.11 Other solid wastes No Not applicable

  • Page | 9

    Sr.

    No. Information/Checklist confirmation

    Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data.

    5. Release of pollutants or any hazardous, toxic or noxious substances to air

    (Kg/hr)

    5.1

    Emissions from combustion of fossil

    fuels from stationary or mobile

    sources

    Yes

    Only during power failure, D.G.

    set is operated. The SO2 and NOx

    are generated from fossil fuel

    (mainly Diesel) burning. It is

    within permissible limits from the

    coal mine.

    5.2 Emissions from production processes No

    Dust emissions will take place

    from drilling / blasting in OB

    benches, surface mining

    operation in coal benches,

    loading, unloading and

    transportation of coal and OB.

    Three nos. of mobile water

    sprinklers and dust suppression

    system has been provided.

    5.3 Emissions from materials handling

    including storage or transport Yes

    Particulate Matter during coal &

    O.B. handling

    5.4 Emissions from construction activities

    including plant and equipment No N.A. as it’s an operating coal mine

    5.5

    Dust or odours from handling of

    materials including construction

    materials, sewage and waste

    No N.A. as it’s an operating coal mine

    5.6 Emissions from incineration of waste No N.A.

    5.7

    Emissions from burning of waste in

    open air (e.g. slash materials,

    construction debris)

    No N.A.

    5.8 Emissions from any other sources No -

    6. Generation of Noise and Vibration, and Emissions of Light and Heat

    6.1 From operation of equipment e.g.

    engines, ventilation plant, crushers Yes

    Noise will be generated during

    drilling & blasting, operation of

    HEMM, CHP, transportation,

    ventilation fan. Suitable

    measures of noise control will be

    adopted. Ambient Noise level

    outside the lease area is not

    likely to exceed the permissible

    limit of 55 dBA during day-time

    and 45 dBA during night-time.

    6.2 From industrial or similar processes No Not applicable

  • Page | 10

    Sr.

    No. Information/Checklist confirmation

    Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data.

    6.3 From construction or demolition No No

    6.4 From blasting or piling Yes Blasting for O.C. mining will

    continue.

    6.5 From construction or operational traffic No

    Present traffic activities will

    continue which has noise levels

    well within limits. No extra traffic

    load will be added due to

    expansion.

    6.6 From lighting or cooling systems Yes

    During D.G. operation. DG will

    be operated during power

    failure only.

    6.7 From any other sources No -

    7.

    Risks of contamination of land or water from releases of pollutants into the

    ground or into sewers, surface waters, groundwater, coastal waters or the

    sea.

    7.1 From handling, storage, use or spillage

    of hazardous materials No

    Hazardous material except LDO /

    Diesel will not be used. Burnt oil

    generated from workshop

    maintenance activity of HEMM

    will be collected and stored

    safely for further disposal.

    7.2

    From discharge of sewage or other

    effluents to water or the land (expected

    mode and place of discharge)

    No Sewage will be used for

    plantation after treatment.

    7.3 By deposition of pollutants emitted to

    air into the land or into water. No

    Control measures and

    implementation of approved

    Environmental Management

    Plan activities like water

    spraying, plantation will help in

    reducing the fugitive dust

    emission.

    7.4 From any other sources No Existing O.B. has garland drain to

    collect run offs.

    7.5

    Is there a risk of long term build up of

    pollutants in the environment from

    these sources?

    No

    Semi-arid conditions are not

    favorable for built up of

    pollutants.

  • Page | 11

    Sr.

    No. Information/Checklist confirmation

    Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data.

    8. Risk of accidents during construction or operation of the Project, which

    could affect human health or the environment

    8.1

    From explosions, spillages, fires etc

    from storage, handling, use or

    production of hazardous substances

    No

    The magazine house for storage

    of explosives will be maintained

    as per the condition of explosive

    license.

    8.2 From any other causes No

    (i) Slope failure in OB dump

    and mine pit,

    (ii) mine inundation,

    (iii) blasting,

    (iv) fire in coal / shale /

    workshop area. These are

    managed as per Safety

    Management Plan based on

    DGMS guidelines.

    8.3

    Could the project be affected by natural

    disasters causing environmental

    damage (e.g. floods, earthquakes,

    landslides, cloudburst etc)?

    No

    None reported till date.

    However, project does not fall

    under seismically active zone or

    landslide prone area. Apart from

    above, the mine is equipped to

    deal with any eventuality like

    mine inundation and slope

    failure in OB dump and mine pit.

  • Page | 12

    Sr.

    No. Information/Checklist confirmation

    Yes/No?

    Details thereof (with

    approximate quantities / rates,

    wherever possible) with source

    of information data.

    9

    Factors which should be considered (such as consequential development)

    which could lead to environmental effects or the potential for cumulative

    impacts with other existing or planned activities in the locality.

    9.1

    Lead to development of supporting

    utilities, ancillary development or

    development stimulated by the project

    which could have impact on the

    environment e.g.

    • Supporting infrastructure (roads, power supply, waste or waste water

    treatment, etc.)

    • housing development • extractive industries • supply industries • other

    Yes

    Infrastructure hitherto created

    will continue to be useful after

    commencement of U.G. mining.

    The region is already semi

    urbanized as coal mining, power

    houses and other industrial

    activities are operating for

    decades. Additional

    infrastructure facilities of the

    mine will support development

    of ancillaries and other related

    activities.

    9.2

    Lead to after-use of the site, which

    could have an impact on the

    environment

    Yes

    The Coal Mine will continue to

    be used for mining for next 30

    years. The mined out area will be

    partly backfilled and converted

    to forestry & water body in post

    mine closure phase.

    9.3 Set a precedent for later developments Yes

    Properly reclaimed area will be

    converted into forest land which

    will help the society after

    cessation of mining. Activities at

    9.1 & 9.2 above will lead to over

    all socio economic growth of the

    area. Socio-economic benefits of

    the project will accrue to local

    population largely.

    9.4

    Have cumulative effects due to

    proximity to other existing or planned

    projects with similar effects

    No Not envisaged

  • Page | 13

    Environmental Sensitivity

    Sr.

    No. Areas

    Name /

    Identity

    Aerial Distance (within 15 km.)

    Proposed project location

    boundary

    1.

    Areas protected under international

    conventions, national or local legislation

    for their ecological, landscape, cultural

    or other related value

    No -

    2.

    Areas which are important or sensitive

    for ecological reasons - Wetlands,

    watercourses or other water bodies,

    coastal zone, biospheres, mountains,

    forests

    No

    Do not exist within Mining Lease

    Area. Nearest Forest is at 2.00

    Km.: Paunar Reserve Forest.

    However, Ardvan R.F., Sekapur

    R.F., Matharjun R.F. Junoni R.F.,

    Dongargaon R.F. are within 10

    km of project area.

    3.

    Areas used by protected, important or

    sensitive species of flora or fauna for

    breeding, nesting, foraging, resting,

    over wintering, migration

    No Not Reported.

    4. Inland, coastal, marine or underground

    waters No N.A.

    5. State, National boundaries No N.A.

    6.

    Routes or facilities used by the public

    for access to recreation or other tourist,

    pilgrim areas

    No N.A.

    7. Defense installations No N.A.

    8. Densely populated or built-up area No Mukutban is at 10 Km SE

    9.

    Areas occupied by sensitive man-made

    land uses (hospitals, schools, places of

    worship, community facilities)

    No

    Mukutban is at 5.4 Km SE.

    School is at Village-

    Pandharkawada (Lahan) at 1.09

    KM and Marki Bu at 2.52 Km

    10.

    Areas containing important, high quality

    or scarce resources (ground water

    resources, surface resources, forestry,

    agriculture, fisheries, tourism, minerals)

    No N.A.

    11.

    Areas already subjected to pollution or

    environmental damage. (those where

    existing legal environmental standards

    are exceeded)

    No N.A.

  • Page | 14

    Sr.

    No. Areas

    Name /

    Identity

    Aerial Distance (within 15 km.)

    Proposed project location

    boundary

    12.

    Areas susceptible to natural hazard

    which could cause the project to

    present environmental problems

    (earthquakes, subsidence, landslides,

    erosion, flooding or extreme or adverse

    climatic conditions)

    No N.A.

    IV. Proposed Terms of Reference for EIA Study

    This proposal is submitted for one time expansion of Coal Mine for production of coal

    from 0.30 MTPA to 0.333 MTPA (Normative) and 0.42 MTPA (Peak) i.e. 11% vide OM

    Dated J-11015-30-2004-IA.II (M) Dated 28.07.2014 & Dated 11.08.2014.

    I hereby give an undertaking that the data and information given in the application and

    enclosures are true to the best of my knowledge and belief and I am aware that if any

    part of the data and information submitted is found to be false or misleading at any

    stage, the project will be rejected and clearance give, if any to the project will be

    revoked at our risk and cost.

    Date : 18.02.2019

    Shri. H.S. Khare

    Chief Mining

    Topworth Urja & Metals Ltd.

    Marki Mangli - I Coal Mine

    126-128, 2nd Floor,

    Shriram Tower, Kingsway,

    Nr. NIT Building, Sadar

    Nagpur - 440 001 (Maharashtra) Place : Nagpur

  • 1

    PART I

    THE AREA OF THIS LEASE

    LOCATION AND AREA OF THE LEASE:-

    All that tract of lands situated at,

    District Tahsil Village Sur./Gat No. Area (Ha.)

    YAVATMAL

    JHARI

    JAMNI

    PARDI

    As per

    description

    given below :

    87.28

    PANDHARKAWADA 225.75

    MARKI (BK) 235.32

    MARKI (KHU) 21.48

    GANESHPUR 112.95

    TOTAL 682.78

    Lease area of 682.78 Ha., breakup of which is mentioned below :-

    VILLAGE - PARDI, TAHSIL - JHARI JAMNI, DIST. YAVATMAL

    Sr.

    No. Kh. No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    1 3/1 3.04 3.04 Bapuji Rama Gonde

    2 3/2-A 2.11 2.11 TOPWORTH URJA & METALS LTD. Mutated

    3 3/2-B 1.21 1.21 Gajanan Latari Vichu

    4 3/3 2.86 2.86 Ramkrishna Maroti Gedekar

    5 3/4 1.60 1.60 Gopal Sakharam Choudhari & 2 Others

    6 3/4-A 1.62 1.62 TOPWORTH URJA & METALS LTD. Mutated

    7 4/1 1.21 1.21 TOPWORTH URJA & METALS LTD. Mutated

    8 4/1 Paiki 1.22 1.22 TOPWORTH URJA & METALS LTD. Mutated

    9 4/1-A 3.20 3.20 TOPWORTH URJA & METALS LTD. Mutated

    10 4/1-B 1.41 1.41 TOPWORTH URJA & METALS LTD. Mutated

    11 4/2 2.49 2.49 TOPWORTH URJA & METALS LTD. Mutated

    12 4/2-A 1.62 1.62 TOPWORTH URJA & METALS LTD. Mutated

    13 5/1 1.21 1.06 Dilip Devanand Valke & 5 Others

    14 5/1-A 2.02 2.02 Anandrao Yadav Valke & 1 Other

    Annexure-1

    Page | 15

  • 2

    Sr.

    No. Kh. No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    15 5/1-B 1.23 1.23 Ashok Punaji Sonarkhan & 2 Others

    16 5/1-C 1.21 1.21 Valmik Janardhan Sonarkhan

    17 5/2 1.88 0.13 Ambadas Govinda Khadse

    18 5/3 1.96 1.36 Damodhar Shankar Khadse & 1 Other

    19 5/4 1.89 1.89 Ganpat Krishna Khadse

    20 6/2 2.43 0.28 Chaban Sadashiv Shedame & 1 Other

    21 6/3 2.03 0.89 Kanhoba Vothoba Dohe & 1 Other

    z22 6/3-A 1.24 0.37 Mandabai Gajanan Kadukar & 3 Others

    23 8/2 4.86 0.20 Anuradha Kailash Milmile & 2 Others

    24 8/3 4.85 0.77 Narayan Maroti Bodhe & 1 Other

    25 9/1 3.55 1.09 Dattu Krishna Hingane & 7 Others

    26 9/1-A 3.44 1.51 Vitthal Maroti Vichu & 3 Others

    27 9/2 3.61 0.93 Mahadeo Muknda Pimpalkar & 3 Others

    28 22/1 4.79 4.34 Anil Baliram Pote

    29 22/2 4.80 1.29 Satish Baliram Pote

    30 23/1 3.71 3.71 Ramkrishna Maroti Gedekar

    31 23/2 2.02 2.02 Ramkrishna Maroti Gedekar

    32 23/3 2.02

    10.30

    Bhimrao Govinda Chunarkar & 7 Others

    33 23/4 2.42 Parmeshwar J. Sonarkhan & 3 Others

    34 23/5 3.29 Ramchandra Narayan Warke

    35 23/6 4.21 Ramkrishna Maroti Gedekar

    36 24/1 1.34 1.34 Kusum Namdeo Khade & 6 Others

    37 24/1-A 2.02 2.02 TOPWORTH URJA & METALS LTD. Mutated

    38 24/2 1.94 1.94 Baban Sadashiv Shedame & 2 Others

    39 24/3 1.94 1.94 TOPWORTH URJA & METALS LTD. Mutated

    40 25 10.13 8.92 TOPWORTH URJA & METALS LTD. Mutated

    41 26/1 6.56 6.56 Samba Arjuna Pote & 1 Other

    42 26/2 4.57 4.57 Sindhu Shivram Chunarkhan & 1 Other

    T O T A L 87.28

    Page | 16

  • 3

    VILL. - PANDHARKAWADA, TAHSIL - JHARI JAMNI, DIST. YAVATMAL

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    1 1 2.97 2.97 Gajanan Ambadar Gode

    2 2/1 2.11 2.11 Dasaru Ramchandra Ghugul

    3 2/2 1.47 1.47 Ramesh Dattu Hingane

    4 2/2-A 1.31 1.31 Dilip Waman Bhongale & 1 Other

    5 2/2-B 1.22 1.22 Raju Bhaurao Vinchu

    6 3 0.81 0.81 Mangesh Bhaurao Vinchu

    7 4 1.21 1.21 Parvatabai Vishvanath Vaidya

    8 5/1 5.20 5.20 Bhaurao Dhuma Vinchu

    9 5/2 1.23 1.23 Mangesh Bhaurao Vinchu

    10 6 1.25 1.25 Anil Shrihari Nibrad

    11 7 1.21 1.21 Madhukar Lodu Rajurkar

    12 8 1.21 1.21 Lodu Govinda Rajurkar

    13 9 2.02 2.02 Santosh Devrao Vaidya

    14 10 0.77 0.00 Government Gaothan F- Class (0.40)

    15 11 1.62 0.00 Government Gaothan F- Class

    16 12/1 2.00

    3.50

    Rajeshwar Dattu Gore

    17 12/2 1.35 Ramchandra Dattu Gore & 1 Other

    18 12/3 1.67 Gajanan Dattu Gore

    19 16 4.16 4.16 Minabai Sukhdeo Pote & 1 Other

    20 17 4.59 4.59 Girjashankar Shivramji Tiple & 1 Other

    21 18/1 1.62 1.62 Ashok Punaji Sonarkhan & 2 Others

    22 18/2 2.35 2.35 Ishwar Mahavev Davare & 1 Other

    23 18/3 2.35 2.35 Subhash Sambha Davare & 1 Other

    24 19/1 1.62 1.62 Manohar Ganpat Hingane

    25 19/2 1.36 1.36 Prakash Manohar Hingane

    26 19/3 1.37 1.37 Chatrapati Manohar Hingane

    27 20/1 1.22 1.22 Ramkrishna Tukaram chandurkar

    28 20/2 1.22 1.22 Indrakala Ramkrishna chandurkar

    29 20/3 3.50 3.50 Ashish Ramkrishna chandurkar

    30 21/1 7.52 7.52 Gajanan Ambadas Gode & 4 Others

    31 21/2 2.02 2.02 Malubai Murlidhar Thakare

    Page | 17

  • 4

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    32 22/1 2.44

    12.22

    Ramesh Gajanan Ghugul & 1 Other

    33 22/2 2.44 Ganpat Sambashiv Ghugul

    34 22/3 2.45 Shila Manohar Pote

    35 22/5 2.44 Ahilya Bhaskar Ghugul & 1 Other

    36 22/6 2.45 Divakar Sambashiv Ghugul

    37 23/1 2.65 2.65 Baban Krishnaji Ghugul

    38 23/2 2.42 2.42 Surendra Bapurao Khadse & 1 Other

    39 24 1.21 1.21 Vaman Latari Pote & 4 Others

    40 25/1 1.21 1.21 Jitendra Dashrath Bhoyar

    41 25/2 1.70 1.70 Rajendrakumar Dashrath Bhoyar

    42 26 7.70 7.70 Vaman Latari Pote & 1 Other

    43 27/1 2.00 2.00 Kalpana Shravan Pote

    44 27/2 2.00

    6.89

    Kalpana Shravan Pote & 4 Others

    45 27/2-A 1.22 Mukesh Shravan Pote

    46 27/2-B 1.22 Prashant Shravan Pote

    47 27/2-K 1.23 Santosh Shravan Pote

    48 27/2-D 1.22 Sulbha Vinod Khandalkar

    49 28/1 1.70

    3.94

    Manda Chandrakant Bhoyar & 3 Others

    50 28/2 3.00 Durgesh Mahadeo Pote

    51 28/3 3.00 Prajwal Arun Pote

    52 46/1 1.73 1.73 Vaman Jagannath Pawade

    53 46/1-A 1.62 1.62 Nitin Vamanrao Pawade

    54 46/1-B 1.62 1.62 Jaiprakash Vamanrao Pawade

    55 46/2 1.41 1.41 Ushatai Vaman Pawade

    56 47 7.24 7.24 Vaman Jagannath Pawade & 9 Others

    57 48 1.72 1.72 Bhaurao Karnu Jhagjhap

    58 49 1.72 1.72 Anandrao Karnu Jhagjhap

    59 50 2.52 2.52 Bapurao Karnu Jhagjhap & others

    60 51 3.50 3.50 Laxman Karnu Jhagjhap

    61 52/1 1.40 1.40 Gajanan Manohar Jivtode

    62 52/2 1.60 1.60 Mahesh Manohar Jivtode

    63 53 2.02 2.02 Lilabai Manoharrao Jivtode

    Page | 18

  • 5

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    64 54 1.43 1.43 Vitthal Dadaji Vinchu

    65 55 1.44 1.44 Vitthal Dadaji Vinchu

    66 56 1.89 1.89 Ashok Ghularam Wankhede

    67 57 2.30 2.30 Sunita Arun Pote & 3 Others

    68 58 3.27 3.27 Anil Baliram Pote & 6 Others

    69 59 1.21 1.21 Vaman Latari Pote

    70 60 2.43 2.43 Sambu Sakharam Kadukar

    71 61 1.24 1.24 Gajanan Manohar Jivtode

    72 62/1 1.51 1.51 Dinesh Tatyaji Sidame

    73 62/2 1.24 1.24 Manohar Dadaji Jivtode

    74 63/1 1.52 1.52 Tarabai Ramkrishna Gohokar & 2 Others

    75 63/2 1.22 1.22 Nirmala Tatyaji Sidame

    76 64/1 1.41 1.41 Bapurao Govinda Tikle

    77 64/2 1.41 1.41 Kusum Bapurao Tikle

    78 65/1 1.62 1.62 Mangesh Ganpatrao Ghugul

    79 65/2 1.29 1.29 Yagnik Ramesh Ghugul

    80 65/3 1.21 1.21 Rohit Girjashankar Tiple

    81 65/4 1.21 1.21 Ashok Ganpatrao Ghugul

    82 65/5 1.21 1.21 Mangesh Ganpat Derkar

    83 66 2.81 2.81 Jhibla Sadashiv Gohokar

    84 67/1 1.21 1.21 Doulat Dasaru Ghugul

    85 67/1-A 1.21 1.21 Mangesh Tatyaji Shedame

    86 67/1-B 1.22 1.22 Smita Doulat Ghugul

    87 67/2 3.20 3.20 Chandrakant Dashrath Ghugul & 1 Other

    88 68 1.74 1.74 Jairam Gujoba Nakhate & 4 Others

    89 69 1.67 1.67 M. P. Bhudan Yagya Mandal & 1 Other

    90 70 3.54 3.54 Sanjay Parshram Chikankar & 5 Other

    91 71 4.86 4.86 Devrao Malhari Bhongale & 2 others

    92 72 1.68 1.68 Ankit Dilip Asutkar

    93 73/1 2.23

    5.03

    Eknath Arjuna Nakhate

    94 73/2 1.40 Kalinda Anandrao Nakhate

    95 73/3 1.40 Gajanan Anandrao Nakhate

    Page | 19

  • 6

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    96 74/1 1.62 1.62 Sudhakar Namdev Tonge & others

    97 74/2 1.62 1.62 Bhaskar Namdev Tonge & Others

    98 74/3 1.85 1.85 Namdev Madhav Tonge

    99 75 2.08 2.08 Urkuda Sitaram Tonge

    100 76/1 2.00 2.00 Malatai Vasudev Tonge

    101 76/1-A 5.60 5.60 Vasudev Urkuda Tonge

    102 76/2 2.00 2.00 Yugal Vasudeo Tonge & 3 Others

    103 77 2.45 2.45 Pandurang Govinda Rajurkar

    104 78/1 5.05 5.05 Parag Bhalchandra Thakare

    105 78/2 4.05 4.05 Pawan Bhalchandra Thakare

    106 79/1 1.84 1.84 Parag Bhalchandra Thakare

    107 79/2 1.41 1.41 Shamlata Bhalchandra Thakare

    108 79/3 4.29 4.29 Gita Bhalchandra Thakare

    T O T A L 225.75

    VILL. – MARKI (BK.), TAHSIL - JHARI JAMNI, DIST. YAVATMAL

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    1 1/1 2.11 2.11 Anil Ramchandra Ringole & 1 Others

    2 1/2 2.00 2.00 Krishna Ramchandra Rengole

    3 2/1 2.39 2.39 Satish Maroti Yedme

    4 2/2 2.00 2.00 Baby Maroti Yedme

    5 3-A/1 2.00 2.00 Magala Ashok Vidhate & 2 Others

    6 3-A/2 1.41 1.41 Anandrao Ganpatrao Vidhate

    7 3-B/1 1.46 1.46 Prakash Anandrao Vidhate

    8 3-B/2 1.46 1.46 Chandrashekar Ramesh Vidhate

    9 3-B/3 1.46 1.46 Suresh Anandrao Vidhate

    10 4/1 1.85 1.85 Gajanan Narayan Gazalwar

    11 4/2 1.85 1.85 Savita Charandas Vasekar & 1 Other

    12 4/3 1.42 1.42 Sushila Nararayan Gazalwar

    13 5/1 5.89

    9.00

    Laxmibai M. Shekbandiwar & 7 Others

    14 5/1-A 2.02 Tai Madhukar Kelzalkar

    15 5/1-B 1.61 Shrihari Uddhav Balki

    16 5/2 2.02 Natthu Mahadeo Gohokar

    Page | 20

  • 7

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    17 6 2.56 2.56 Ragnath Ashanna Polshettiwar

    18 7 2.57 2.57 Vittal Ashanna Polshettiwar

    19 8 2.39 2.39 Vilas Shamrao Polshettiwar & 4 Others

    20 9 3.36 3.36 Gajanan Estari polcheettiwar & 5 Other

    21 10 1.41 1.41 Amar Tulshiram Balki

    22 11 1.96 1.96 Suman Vitthal Raout

    23 12 1.62 1.62 Hanumantu Shakaram Ulmale

    24 13 2.02 2.02 Namdeo Devaji Yemjelwar

    25 14/1 1.28 3.53

    Raju Hanumantu Ulmale

    26 14/2 2.25 Vijay Hanumantu Ulmale

    27 15 2.40 2.40 Vilas Shamrao Polshettiwar

    28 16/1 1.51

    4.55

    Laxmibai Estari Polchettiwar

    29 16/2 1.52 Pandurang Estari Poshettiwar

    30 16/3 1.52 Gajanan Estari polcheettiwar

    31 17/1 2.21

    5.05

    Jamuwant Namdeo Kurmelwar

    32 17/2 1.41 Chandralekha Jamuwant Kurmelwar

    33 17/3 1.43 Jamuwant Namdeo Kurmelwar

    34 18 3.08 3.08 Gajanan Bapurao Barshetiwar & 3 Others

    35 19 3.18 3.18 Shantabai Maroti Gazalwar & 2 Others

    36 20 2.83 2.83 Laxman Somanna Tatewar

    37 21/1-B 2.03 2.03 Anil Namdeo Zatte

    38 21/1-A 1.21 1.21 Namdeo Damaji Zatte

    39 21/2 1.21 1.21 Ramesh Namdeo Zatte

    40 22 5.08 5.08 Bhonanath Laxman Tatewar

    41 23 2.48 2.48 Sunil Vittal Payghan & 6 Others

    42 24 1.21 1.21 Ranjana Ganpat Payghan 1 Others

    43 25 1.28 1.28 Lilabai Hanumantu Ulmale

    44 26/1 1.62 1.62 Gokul Ghularam Navde

    45 26/2-A 1.21 1.21 Sangita Chetan Payghan

    46 26/2-B 2.15 2.15 Chetan Janardhan Payghan

    47 27 2.22 2.22 Bapurao Ganpat Rakude

    48 28/1 1.21 1.21 Ziblabai Ramdas Lande

    49 28/2 3.15 3.15 Sudham Ganpat Rakhunde

    Page | 21

  • 8

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    50 29 1.62 1.62 Vijay Mahado There

    51 30/1 1.73 4.84

    Suresh Anandrao Vidhate

    52 30/2 3.11 Ramesh Anandrao Vidhate

    53 31 4.34 4.34 Gaourav Suresh Vidhate

    54 32 3.85 3.85 Gajanan Istari Pangantiwar & 4 Others

    55 33 1.82 1.82 Laxman Krishna Kelzalkar

    56 34 1.65 1.65 Janardhan Ramchandra Madavkar

    57 35 1.66 1.66 Shobha Tai Uttam Madavkar

    58 36 1.76 1.76 Bhaskar Vasudo Madavkar

    59 37/1 1.73

    8.19

    Baby Mohan Turankar

    60 37/2 1.28 Gajanan Shivram Raout

    61 37/3 1.28 Namdeo Shivram Raout

    62 37/4 1.28 Vitthal Shivram Raout

    63 37/5 1.40 Waman Shivram Raout

    64 37/6 1.22 Ganpat Shivram Raout

    65 38/1 4.90 4.90 Shuhas Jivan Vidhate

    66 38/2 2.06 2.06 Gajanan Laxman Vidhate

    67 39 0.81 0.81 Mukhayadhyapak Adiwasi Ashram Shala Marki B

    68 40/1 1.99 3.40

    Vijay Krishanarao Vidhate

    69 40/2 1.41 Shalikrao Tukaram Nandurkar

    70 45 3.84 3.84 Vittal Lachmanna Barlawar

    71 46/1 2.21 3.83

    Krishta Laxman Barlawar

    71-A 46/2 1.62 Sharwan Krishta Barlawar

    72 47/1 3.04 3.04 Panchfula Purshotam Madavi

    73 47/2 3.03 3.03 Shankar Kishan Muke

    74 49 1.51 1.51 Bhavna Uddhav Muke

    75 50 2.43 2.43 Suresh Vithu Balki

    76 51/1 1.22 1.22 Subhash Vithu Balki

    77 51/2 1.21 1.21 Sachin Subhash Balki

    78 52/1 1.58 3.16

    Panchfula Maroti Balki & 2 Others

    79 52/2 1.58 Harichandra Maroti Balki

    80 54 1.62 1.62 Trivna Narayan Musale & 6 Others

    Page | 22

  • 9

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    81 55/1 2.59

    8.25

    Santosh Vyankati Rasamwar

    82 55/2 2.00 Krishnarao Ganpatrao Vidhate

    83 55/3 1.22 Jyoti Chandrashekhar Nagpure

    84 55/4 1.22 Pravin Ganpatrao Vidhate

    85 55/5 1.22 Gitabai Pravin Vidhate

    86 86/1 1.62 1.62 Bayabai Raghunath Vidhate

    87 86/2 1.62 1.62 Gajanan Shamrao Tonge

    88 87 3.24 3.24 Anil Raghunath Vidhate & 1 Other

    89 120 2.83 2.83 Nitesh Bandu Ulmale & 1 Other

    90 121 3.50 3.50 Aadku Vishvanath Dahaki & 1 Other

    91 122/1 1.22 1.22 Dadaji Ramu Ulmale & 5 Others

    92 123/1 1.82 1.82 Kavdu Balaji Mohitkar

    93 123/2 2.40 2.40 Vijay Kisan Roge & 1 Other

    94 124/1 3.02 3.02 Kejaji Vishvanath Dahaki

    95 124/2 1.21 1.21 Atul Madhav Ulmale

    96 125 2.83 2.83 Bandu Ganpat Ulmale & 2 Other

    97 154 2.21 0.25 Purushottam Mukinda Deulkar

    98 157/1 4.22

    10.34

    Sindhu Janardan Badkhal & 4 Others

    99 157/2 4.04 Madhukar Madhav Badkhal & 4 Others

    100 157/3 3.20 Ravindra Yadav Badkhal & 3 Others

    101 158 4.95 0.80 Santosh Kavdu Ulmale & 3 Other

    102 169/1 1.21 1.21 Shankar Ravindra Badkhal

    103 169/2 1.46 1.46 Haridas Uddhav Mohitkar

    104 169/3 1.45 1.45 Shobhabai Ramdas Mohitkar

    105 170 3.55 3.55 Sindhu Bandu Ulmale

    106 171 3.53 2.70 Hariram Bandu Ulmale & 1 Other

    107 172/1 2.23 2.23 Bandu Ganpat Ulmale

    108 172/2 1.82 1.82 Sandeep Maroti Yedame

    109 173 1.62 1.62 Rajeshwar Vithu Payghan & 2 Others

    110 174 1.76 1.76 Anil Kavdu Bobate

    Page | 23

  • 10

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    111 175 1.07 1.07 Bahurao Malhari Bhongale

    112 176/1 1.62 1.62 Surekha Kavdu Mohitkar

    113 176/2 1.82 1.82 Kavdu Balaji Mohitkar & 3 Others

    114 177 2.36 2.36 Badu Namdev Gohokar

    115 178 2.44 2.44 Anandrao Karnu Hajari & 1 Others

    T O T A L 235.32

    VILL. – MARKI (KH.), TAHSIL - JHARI JAMNI, DIST. YAVATMAL

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    1 25 2.02 2.02 Jagdish Natthuji Kapse & 1 Other

    2 26 1.41 1.41 Jagdish Natthuji Kapse

    3 27 2.02 2.02 Janrao Ramaji Thokne

    4 28 1.82 1.82 Trivenibai Yadav Badkhal & 1 Other

    5 29 1.42 1.42 Sindhu Janardhan Badkhal & 4 Others

    6 30 2.46 2.46 Sombai Punaji Madavi & 2 Others

    7 31/1 1.31 1.31 Vaibhav Vinod Burhan

    8 31/2 1.31 1.31 Ravindra Pundlik Shekbandiwar

    9 31/3 1.30 1.30 Valmik Jairam Jhade

    10 32 2.31 2.17 Laxman Karnuji Aatram

    11 36 1.72 0.14 Pramod Pandurang Shekbandiwar & 2

    Others

    12 41/1 1.92

    3.31

    Devrao Anandrao Devalkar

    13 41/2 1.41 Subhash Anandrao Devalkar

    14 41/3 1.41 Vinod Anandrao Devalkar

    15 42/1 1.36 0.79

    Anil Tanba Bodhe

    16 42/2 1.36 Gajanan Nagoba Balki

    T O T A L 21.48

    Page | 24

  • 11

    VILL. – GANESHPUR (KH.), TAHSIL - JHARI JAMNI, DIST. YAVATMAL

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    1 1/1 2.25

    7.00

    Maroti Kanhoba Devalkar

    2 1/2 1.98 Vasanta Laxman Devalkar

    3 1/3 2.70 Kamalbai Ramdas Devalkar & 2 Others

    4 1/4 1.24 Ramrao Kanhoba Devalkar

    5 1/5 1.21 Maroti Kanhoba Devalkar & 1 Other

    6 3 4.99 1.50 Manjula Pandurang Jumnake & 2 Others

    7 18/1 7.67

    5.96

    Kavadu Krishnaji Ghugul

    8 18/2 1.52 Pranita Chandrakant Ghugul

    9 18/3 2.02 Chandrakant Dashrath Ghugul

    10 28 1.16 1.00 Gosai Vithoba Tonge, Bhudan Yagya

    Mandal

    11 39-1-A 1.28

    11.25

    Ramchandra Mahadev Pawade

    12 39-1-B 1.27 Taibai Ramchandra Pawade

    13 39-1-C 1.27 Ganesh Kanchan Pawade

    14 39-1-D 1.27 Kanchan Ramchandra Pawade

    15 39-1-E 1.27 Rajat Anil Pawade

    16 39-1-F 1.27 Anil Ramchandra Pawade

    17 39/2 6.61

    18 40 3.81 2.25 Devidas Keshavrao Balki & 1 Other

    19 41 1.04 1.04 Lodba Mahadev Devalkar

    20 42 2.96 2.70 Devrao Shankar Devalkar

    21 43 7.24 7.24 Jhibla Bhaduji Devalkar & 5 Others

    22 44 1.75 1.75 Sambu Dasaru Maraskolhe

    23 45 1.41 1.13 Lodba Mahadev Devalkar

    24 46 1.62 1.62 Shankar Lingu Maraskolhe & 2 Others

    25 47 1.45 1.45 Manohar Soma Maraskolhe

    26 48 2.04 2.04 Ashok Malku Maraskolhe & 6 Others

    27 49 1.14 1.14 Vaman Baliram Bhogale

    28 50 1.14 1.14 Vasudev Sadu Jhungare & 1 Other

    29 51 1.38 1.38 Aatmaram Sakharam Petkar

    Page | 25

  • 12

    Sr.

    No.

    Kh.

    No.

    Area as

    per 7/12

    Applied

    Area Name of Land Owners Remakrs

    30 52/1 2.00

    5.20

    Arun Latari Phuse

    31 52/2 1.99 Mohandas Latari Phuse

    32 52/3 1.21 Jijabai Latari Phuse

    33 53 1.14 1.14 Atul Vaman Bhogale & 1 Other

    34 54 2.02 2.02 Vishvanath Ganpat Vaidya

    35 55 1.62 1.62 Purushottam Ramchandra Kale & 5

    others

    36 56 1.23 1.23 Keshav Punjaraj Nibrad & 1 Other

    37 57 3.21 3.21 Latari Sadu Dhurve & 6 Others

    38 58/1 1.61 3.22

    Anil Ramrao Devalkar

    39 58/2 1.61 Kamlakar Ramrao Devalkar

    40 59/1 1.42 1.42 Janabai Shankar Matte

    41 59/1-1 1.40 1.40 Madan Shankar Matte

    42 59/1-2 1.23 1.23 Shankar Hiram Matte

    43 59/1-A 1.42 1.42 Rajendra Shrihari Balki

    44 59/2 1.62 1.62 Uttam Ramchandra Mandavkar

    45 60/1 1.53 1.53 Mahadev Dada Vinchu

    46 60/2 2.23 2.23 Pandurang Jhigu Pimpalkar

    47 60/3 2.22 2.22 Vaman Gajanan Junagari

    48 61 2.01 4.02

    Rajendra Ramdas Devalkar

    49 61/1 2.01 Ramesh Ramdas Devalkar

    50 62/1 1.23 1.23 Radho Shivaji Dhengale

    51 62/1-1 2.23 2.23 Gajanan Radho Dhengale

    52 62/1-2 2.23 2.23 Pandit Radho Dhengale

    53 62/2 4.88 4.88 Sindhubai Balaji Dhengale & 2 Others

    54 63 2.44 2.44 Pandhari Sakharam Upare & 2 Others

    55 64 2.12 2.12 Santosh Govinda Uike

    56 65 2.13 2.13 Nanaji Keshav Uike

    57 66 4.48 4.48 Purshottam Ramchandra Kale & 2 others

    58 67/1 1.54 1.54 Vaman Dadarao Balki

    59 67/2 1.54 1.54 Bhauji Dadarao Balki

    60 67/3 1.81 1.81 Rohit Madan Matte

    T O T A L 112.95

    Page | 26

  • MARKI MANGLI-I

    COAL MINE

    MARKI MANGLI-I COAL MINE, DIST-YAVATMAL, MAHARASTRA

    P. P. TOPWORTH URJA & METALS LTD.

    Page | 27

  • Page | 28

    Sanjay DakTypewritten Text

    Sanjay DakTypewritten Text"ANNEXURE - 3"

  • Page | 29

  • Page | 30

  • Page | 31

    Sanjay DakTypewritten Text"ANNEXURE - 3-A"

  • Page | 32

  • Page | 33

  • Page | 34

  • Page | 35

  • Page | 36

  • Page | 3

    7

    Sanjay DakTypewritten Text"ANNEXURE - 3"

    Sanjay DakTypewritten Text

  • Page | 3

    8

  • Page | 3

    9

  • Page | 4

    0

  • Page | 4

    1

  • Page | 4

    2

  • Page | 4

    3

  • Page | 4

    4

  • Page | 4

    5

  • Page | 4

    6

  • Page | 4

    7

  • Page | 4

    8

  • Page | 4

    9

  • Page | 50

  • Page | 51

  • Page | 52

  • Page | 53

  • Page | 54

    Page 1Page 2Page 3Page 1 (1)Page 2 (1)Page 1 (2)Page 2 (2)Page 3 (1)